JP4145738B2 - Tunnel support method - Google Patents

Tunnel support method Download PDF

Info

Publication number
JP4145738B2
JP4145738B2 JP2003188285A JP2003188285A JP4145738B2 JP 4145738 B2 JP4145738 B2 JP 4145738B2 JP 2003188285 A JP2003188285 A JP 2003188285A JP 2003188285 A JP2003188285 A JP 2003188285A JP 4145738 B2 JP4145738 B2 JP 4145738B2
Authority
JP
Japan
Prior art keywords
drilling
bit
upper half
tunnel
inner tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003188285A
Other languages
Japanese (ja)
Other versions
JP2005023582A (en
Inventor
幸男 矢部
宏之 木全
重行 河野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2003188285A priority Critical patent/JP4145738B2/en
Publication of JP2005023582A publication Critical patent/JP2005023582A/en
Application granted granted Critical
Publication of JP4145738B2 publication Critical patent/JP4145738B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、トンネル支保工法に関し、特に、上半支保工脚部の補強工法に関する。
【0002】
【従来の技術】
山岳トンネル工法において、通常の支保工では対処できないか対処することが得策ではない場合、トンネルの安全性確保または周辺環境の保全のために様々な補助工法が採用される。このうち、上半支保工脚部の支持力が不足するために生じる前記脚部の沈下を抑制する補助工法では、レッグパイル工法などが用いられている。特許文献1では、トンネルの切羽から前方斜め下向きに曲線状の補強工を設ける脚部補強工法が開示されている。
【0003】
【特許文献1】
特開2002−147164号公報(第3頁、第1図)
【0004】
【発明が解決しようとする課題】
しかしながら、上記の脚部補強工法はいずれも、各切羽における作業になるため、工期が長くなるうえ、工事費も嵩む問題がある。また、脚部補強部と上半支保工とを一体化するのが難しく、確実な脚部支持力が得られないことがある。
本発明は、上述する問題点に鑑みてなされたもので、上半支保工脚部の支持力が確実に得られるとともに、掘削効率の改善が図れるトンネル支保構造およびトンネル支保工法を提供することを目的とする。
【0005】
【課題を解決するための手段】
上記目的を達成するため、本発明に係るトンネル支保工法では、上半を掘削する前に、上半支保工脚部の下方位置でトンネル軸方向に沿って、長尺先受工による地山改良部を施工し、前記上半を掘削して前記上半支保工を設置する際に、前記上半支保工脚部を前記地山改良部に支持させるトンネル支保工法であって、前記長尺先受工は、前記上半支保工脚部から下方の地山部分について所定の離間間隔をおいて、トンネル坑口から前方に向けて削孔軌道を修正しつつ削孔を行い、管体を挿入してなり、前記削孔を行うに当たり、削孔時に削孔方向を第一の方向に偏向させる力が生じる形状からなる外管ビットを先端に有する外管と、削孔時に削孔方向を第二の方向に偏向させる力が生じる形状からなる内管ビットを先端に有する内管とを備え、直線削孔時には、削孔方向を第一の方向に偏向させる力と削孔方向を第二の方向に偏向させる力とが相殺されるように、前記外管ビットと前記内管ビットの周方向相対位置を設定して打撃力による削孔を行い、削孔方向修正時には、削孔方向を第一の方向に偏向させる力と削孔方向を第二の方向に偏向させる力との合力方向に削孔できるように、前記外管ビットと前記内管ビットの周方向相対位置を設定して打撃力による削孔を行うことを特徴とする。
この際、前記外管ビットおよび前記内管ビットの先端面が、前記外管ビットおよび前記内管ビットの軸方向と直交する面に対して、それぞれ傾斜角を有するように形成されていることが好適である。
【0006】
本発明では、上半支保工脚部から下方部を先受工によって予め地山改良しておくことにより、上半支保工脚部の沈下を抑制し、確実な支持力を得るものである。また、長尺先受工では、トンネル掘削前に地山改良を行うため、切羽到達前の先行変位を低減でき、地表面沈下の抑制効果も大きい。
従来の長尺先受工は、長さ10〜15m程度の鋼管を削孔・打設した後、鋼管内部およびその周囲に注入材を充填することにより、地山を補強するものであるが、本発明における長尺先受工では、略100m単位の超長尺先受工とする。そのため、本発明における長尺先受工では、削孔軌道を修正しつつ削孔を行う必要が生じるが、略100m単位の地山改良を一度に行うため、従来工法に比べて工期の短縮および工費の削減を図ることができる。
そして、外管ビットおよび内管ビットの先端面が傾斜角を有する場合、地山の削孔反力に対して、外管ビットおよび内管ビットは、抵抗の小さな傾斜面の先端に向かう方向に逃げるようになる。本発明は、この原理を応用したものであり、直進時には、外管ビットを偏向させる力と内管ビットを偏向させる力が相殺するように削孔し、削孔方向修正時には、外管ビットを偏向させる力と内管ビットを偏向させる力の合力を利用して削孔することにより、長尺の削孔が可能となる。
【0009】
あるいは、本発明に係るトンネル支保工法では、上半を掘削する前に、上半支保工脚部の下方位置でトンネル軸方向に沿って、長尺先受工による地山改良部を施工し、前記上半を掘削して前記上半支保工を設置する際に、前記上半支保工脚部を前記地山改良部に支持させるトンネル支保工法であって、前記長尺先受工は、前記上半支保工脚部から下方の地山部分について所定の離間間隔をおいて、トンネル坑口から前方に向けて削孔軌道を修正しつつ削孔を行い、管体を挿入してなり、前記削孔を行うに当たり、外管ビットを先端に有する外管と、内管ビットシューを先端に有する内管とを備え、前記内管ビットシューは、前記内管ビットシューの軸心より放射方向に伸長可能なリーマー片を有し、直線削孔時には、前記リーマー片を前記内管ビットシュー内に格納した状態として打撃力による削孔を行い、削孔方向修正時には、前記リーマー片を前記内管ビットシューから伸長させた状態として打撃力による削孔を行うことを特徴としている。
本発明では、リーマー片を内管ビットシューから伸長させることにより、削孔面の中心が内管ビットシューの軸心から偏心するため、削孔方向を修正することができるものである。
【0010】
【発明の実施の形態】
以下、本発明の実施形態を図面を参照して説明する。
図1は、本発明に係るトンネル支保構造の実施形態の一例を示すものである。
この図に示すように、本実施形態によるトンネル支保構造では、従来のトンネル支保構造と同様に、トンネル上半6内周に鋼製支保工と吹付けコンクリートからなる上半支保工3が設置されている。上半支保工3の外周部には長尺先受工2がトンネル周方向に所定の離間間隔をおいてトンネル軸方向と略平行に配設されるとともに、ロックボルト5がトンネル軸直交方向に放射状に配設されている。また、上半支保工3の内側には覆工コンクリート4が設置されている。
本実施形態によるトンネル支保構造では、従来のトンネル支保構造に加えて、上半支保工3脚部から下方の略トンネル壁面に沿った地山G部分について、トンネル軸方向に施工された長尺先受工による地山改良が施されている。そして、本発明においては、この長尺先受工は略100m単位の超長尺先受工1となっている。
超長尺先受工1は、芯材としての鋼管を削孔・打設し、その内外周に地山改良材を注入充填して地山改良部9を形成する工法であるが、地山改良部9が互いに重複するような離間間隔で超長尺先受工1を配設する。また、地山改良部9は、上部は上半支保工3脚部が含まれるようにし、下部はインバート8付近まで施工される。
なお、上半支保工3脚部の地山G支持力を確保するために、超長尺先受工1を上半支保工3脚部下方の地山G部分に縦一列ではなく、複数列配置する場合もある。
本実施形態によるトンネル支保構造では、上半支保工3脚部から下方部を超長尺先受工1によって予め地山改良しておくことにより、上半支保工3脚部の沈下を抑制し、確実な支持力を得ることができる。また、超長尺先受工1では、トンネル掘削前に地山改良を行うため、切羽到達前の先行変位を低減でき、地表面沈下も抑制することができる。
また、本実施形態によるトンネル支保構造では、略100m単位の超長尺先受工1とするため、従来工法に比べて工期の短縮および工費の削減を図ることができるうえ、トンネル軸方向に均一な改良が行えるため、不等沈下の抑制効果も大きい。
【0011】
本実施形態によるトンネル支保工では、トンネル掘削断面の上半6を先行して掘削し、上半支保工3を設置するが、その上半6の掘削前に、予め上半支保工3脚部からトンネル下半7に亘る部分に、超長尺先受工1をトンネル軸方向に施工するものである。この長尺先受工1の施工は、地山Gの状態によって決められるが、最初から施工する場合は、トンネル坑口からトンネル前方に向けて施工し、トンネル途中の一部区間を施工する場合は、トンネルの側部を部分的に拡幅して施工スペースとし、そこから施工することになる。いずれにしても、超長尺先受工1の施工長は100m程度なので、トンネルがそれよりも長く且つ全延長施工する場合は、トンネル途中で側部を一部拡幅して施工することになる。
【0012】
次に、超長尺先受工の具体的実施形態であるが、図2は、超長尺先受工における削孔方法の第一の実施形態を示したものである。また、図3は、削孔方法の第一実施形態における外管ビットおよび内管ビットの斜視図である。ただし、図3ではビット刃15は省略している。以下、図1と同一の構成要素には同一の符号を用いて説明を省略する。
本実施形態による削孔方法は、外管(鋼管)10と内管(鋼管)11とからなる二重管の基端を、図示していない削孔駆動装置に連結し、前記二重管に打撃力を加えて地山Gの削孔を行う。外管10の先端には外管ビット12が設けられ、外管ビット12の先端面は、外管ビット12の軸方向と直交する面に対して傾斜角を有している。一方、内管11の先端には内管ビット13が設けられ、内管ビット12の先端面は、内管ビット13の軸方向と直交する面に対して傾斜角を有している。また、外管ビット12および内管ビット13の先端面には、多数のビット刃15が配設されている。さらに、内管ビット13の後方の内管11内には、削孔方向を確認するための計測装置14が備えられている。
直線削孔時には、図2(a)および図3(a)に示すように、外管ビット12先端面と内管ビット13先端面の相対位置を、外管ビット12および内管ビット13の軸心を回転軸として周方向に180度の位置に設定し、計測装置14で削孔方向を確認しつつ直線方向L1に削孔を行う。
削孔方向修正時には、図2(b)および図3(b)に示すように、外管ビット12先端面と内管ビット13先端面の相対位置を、外管ビット12および内管ビット13軸心を回転軸として周方向に0度の位置に設定し、計測装置14で削孔方向を確認しつつ偏向方向B1に削孔を行う。この際、外管ビット12先端面と内管ビット13先端面の相対位置は、外管ビット12および内管ビット13の軸心を回転軸として周方向に180度の位置でなければよく、45度あるいは90度などの位置に設定して偏向方向B1に削孔を行ってもよい。
【0013】
図4は、超長尺先受工における削孔方法の第二の実施形態を示したものである。
本実施形態による削孔方法では、外管ビット22を先端に備えた外管(鋼管)20と、内管ビットシュー(鋼管)23を先端に備えた内管21とからなる二重管を使用する。内管ビットシュー23側面には、内管ビットシュー23の軸心より放射方向に伸長可能なリーマー片25が設けられている。リーマー片25を内管ビットシュー23側面に格納した状態における削孔面の中心は実質的に内管ビットシュー23の軸心に一致し、リーマー片25を内管ビットシュー23から伸長させた状態における削孔面の中心は内管ビットシュー23の軸心から偏心する。また、内管ビットシュー23後方の内管21内には、削孔方向を確認するための計測装置24が備えられている。
直線削孔時には、図4(a)に示すように、リーマー片25を内管ビットシュー23側面に格納した状態とし、計測装置24で削孔方向を確認しつつ直線方向L2に削孔を行う。
削孔方向修正時には、図4(b)に示すように、リーマー片25を内管ビットシュー23から伸長させた状態とし、計測装置24で削孔方向を確認しつつ偏向方向B2に削孔を行う。
なお、リーマー片25は内管ビットシュー23に複数設けてもよい。
【0014】
このように、第一あるいは第二の実施形態による削孔方法によって削孔した後、内管11、21を引抜き、改良材を外管10、20内方と外管10、20外方に注入することで、外管10、20よりも大径の地山改良部9を形成する。この地山改良部9は、互いに重複(ラップ)するように施工することによって支持機能を有するようになる。本実施形態では、この超長尺先受工1を上半支保工3脚部から下方に形成して上半支保工3を支持することになる。なお、施工長が長いことから、改良材の注入充填に当たっては、外管10、20を有孔管とし、パッカー等を使用して区間を区切って注入することが好適である。
この超長尺先受工1による地山改良部9の施工が完了したら、上半6の掘削をし、上半支保工3を前記地山改良部9に支持させて設置する。その後、下半7の掘削をするが、並列する超長尺先受工1の鋼管(外管10、20)の隙間からロックボルト5を打設して、下半7のトンネル壁面(地山改良部9となっている。)の補強をすることも可能である。
【0015】
【発明の効果】
以上説明したように、本発明に係るトンネル支保工法によれば、上半支保工脚部の支持力が確実に得られるとともに、掘削効率の改善を図ることができる。
【図面の簡単な説明】
【図1】 本発明に係るトンネル支保構造の実施形態の一例を示す図である。
【図2】 超長尺先受工における削孔方法の第一の実施形態を示す図である。
【図3】 超長尺先受工における削孔方法の第一の実施形態における外管ビットおよび内管ビットの斜視図である。
【図4】 超長尺先受工における削孔方法の第二の実施形態を示す図である。
【符号の説明】
1……超長尺先受工
2……長尺先受工
3……上半支保工
4……覆工コンクリート
5……ロックボルト
6……上半
7……下半
8……インバート
9……地山改良部
10、20……外管
11、21……内管
12、22……外管ビット
13……内管ビット
14、24……計測装置
15……ビット刃
23……内管ビットシュー
25……リーマー片
G……地山
L1、L2……直線方向
B1、B2……偏向方向
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a tunnel support method , and more particularly, to a reinforcement method for an upper half support leg.
[0002]
[Prior art]
In the mountain tunnel construction method, when it is not possible or impossible to deal with by ordinary support works, various auxiliary construction methods are adopted for securing the safety of the tunnel or preserving the surrounding environment. Among these, a leg pile construction method or the like is used as an auxiliary construction method for suppressing the settlement of the leg portion due to insufficient support force of the upper half support leg portion. Patent Document 1 discloses a leg reinforcement method in which a curved reinforcement is provided obliquely downward and forward from the face of a tunnel.
[0003]
[Patent Document 1]
Japanese Patent Laid-Open No. 2002-147164 (page 3, FIG. 1)
[0004]
[Problems to be solved by the invention]
However, each of the above-mentioned leg reinforcement methods involves work on each face, so that there is a problem that the construction period becomes long and the construction cost increases. Moreover, it is difficult to integrate the leg portion reinforcing portion and the upper half support work, and a certain leg portion supporting force may not be obtained.
The present invention has been made in view of the above-described problems, and provides a tunnel support structure and a tunnel support method capable of reliably obtaining the support force of the upper half support legs and improving the excavation efficiency. Objective.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, in the tunnel support method according to the present invention, before excavating the upper half, along the tunnel axis direction at a position below the upper half support leg, the ground improvement by a long tip receiving work is performed. A tunnel support method in which the upper half support leg is supported by the ground improvement part when the upper half is excavated and the upper half support is installed. The receiving work is drilled while correcting the drilling trajectory from the tunnel wellhead to the front, with a predetermined separation interval in the ground part below the upper half support leg, and inserting the pipe body When performing the above-described drilling, an outer tube having an outer tube bit having a shape that generates a force that deflects the drilling direction in the first direction at the time of drilling, and a second drilling direction at the time of drilling. An inner tube having an inner tube bit having a shape that generates a force deflecting in the direction of During linear drilling, the circumferential direction of the outer tube bit and the inner tube bit is such that the force that deflects the drilling direction in the first direction and the force that deflects the drilling direction in the second direction cancel each other. Set the relative position and perform drilling with the striking force.When correcting the drilling direction, in the resultant direction of the force that deflects the drilling direction in the first direction and the force that deflects the drilling direction in the second direction In order to enable drilling, the outer tube bit and the inner tube bit are set in a circumferential relative position to perform drilling with a striking force.
At this time, the distal end surfaces of the outer tube bit and the inner tube bit are formed so as to have an inclination angle with respect to a surface orthogonal to the axial direction of the outer tube bit and the inner tube bit, respectively. Is preferred.
[0006]
In the present invention, the lower part from the upper half support leg is improved in advance by receiving work in advance, thereby suppressing the settlement of the upper half support leg and obtaining a reliable support force. In addition, in the long tip receiving work, since the ground is improved before tunnel excavation, the preceding displacement before reaching the face can be reduced, and the effect of suppressing the ground surface settlement is great.
The conventional long tip receiving work is to reinforce the natural ground by filling an injection material in and around the steel pipe after drilling and placing a steel pipe having a length of about 10 to 15 m. In the long tip receiving work in the present invention, it is an ultra long tip receiving work of about 100 m. Therefore, it is necessary to perform drilling while correcting the drilling track in the long tip receiving work in the present invention. However, since the ground is improved by about 100 m at a time, the construction period is shortened compared with the conventional method. Construction cost can be reduced.
When the outer tube bit and the inner tube bit have a tip end surface having an inclination angle, the outer tube bit and the inner tube bit are directed in a direction toward the tip of the inclined surface having a small resistance against the drilling reaction force of the ground. I will escape. The present invention is an application of this principle. When straight running, drilling is performed so that the force that deflects the outer tube bit and the force that deflects the inner tube bit cancel each other. By drilling using the resultant force of the deflecting force and the force deflecting the inner tube bit, a long drilling is possible.
[0009]
Alternatively, in the tunnel support method according to the present invention, before excavating the upper half, along the tunnel axis direction at the lower position of the upper half support legs, construct a natural ground improvement part by a long tip receiving work, When excavating the upper half and installing the upper half support work, it is a tunnel support method that supports the upper half support leg to the natural ground improvement part, the long tip receiving work, Drilling a hole while correcting the drilling track from the tunnel wellhead to the front, with a predetermined separation interval in the ground part below the upper half support leg, inserting the pipe, When the hole is formed, an outer tube having an outer tube bit at the distal end and an inner tube having an inner tube bit shoe at the distal end are provided, and the inner tube bit shoe extends radially from the axis of the inner tube bit shoe. Possible reamer pieces, and during straight drilling, the reamer pieces Performs drilling by impact force in a state stored in the bit shoe, at the time of drilling direction correcting, it is characterized by performing the drilling by striking force the reamer piece as a state of being extended from the inner tube bits shoe.
In the present invention, by extending the reamer piece from the inner pipe bit shoe, the center of the drilling surface is decentered from the axis of the inner pipe bit shoe, so that the drilling direction can be corrected.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 shows an example of an embodiment of a tunnel support structure according to the present invention.
As shown in this figure, in the tunnel support structure according to the present embodiment, as in the conventional tunnel support structure, the upper half support work 3 made of steel support work and shotcrete is installed on the inner periphery of the upper half 6 of the tunnel. ing. On the outer peripheral portion of the upper half support 3, a long tip receiving work 2 is disposed substantially parallel to the tunnel axis direction at a predetermined spacing in the tunnel circumferential direction, and the lock bolt 5 is arranged in a direction perpendicular to the tunnel axis. They are arranged radially. Moreover, the lining concrete 4 is installed inside the upper half support 3.
In the tunnel support structure according to the present embodiment, in addition to the conventional tunnel support structure, a long tip constructed in the tunnel axis direction on the ground mountain G portion along the substantially tunnel wall surface below the upper half support work tripod. The ground has been improved by receiving work. And in this invention, this elongate tip receiving work is the ultra-long elongate receiving work 1 of a unit of about 100 m.
The ultra-long tip receiving construction 1 is a construction method in which a steel pipe as a core material is drilled and placed, and a natural ground improvement material is injected and filled into the inner and outer circumferences to form the natural ground improvement portion 9. The super-long leading edge receivers 1 are arranged at a separation interval such that the improved portions 9 overlap each other. Moreover, the natural ground improvement part 9 is constructed so that an upper half supporting work 3 leg part is included in the upper part, and the lower part is constructed to the vicinity of the invert 8.
In addition, in order to secure the support ground G support force of the upper half support work 3 legs, the super long tip receiving work 1 is not arranged in a single row but in a vertical row in the natural ground G portion below the upper support work 3 legs. Sometimes it is arranged.
In the tunnel support structure according to the present embodiment, the lower part from the upper half support work 3 leg part is improved in advance by the ultra-long tip receiving work 1 to suppress the settlement of the upper half support work 3 leg part. A reliable supporting force can be obtained. In addition, since the super long tip receiving work 1 improves the natural ground before tunnel excavation, it is possible to reduce the preceding displacement before reaching the face and to suppress the ground surface settlement.
Further, in the tunnel support structure according to the present embodiment, since it is a very long tip receiving work 1 in units of about 100 m, it is possible to shorten the construction period and reduce the construction cost compared with the conventional construction method, and it is uniform in the tunnel axis direction. Since it can be improved, the effect of suppressing uneven settlement is great.
[0011]
In the tunnel support work according to the present embodiment, the upper half 6 of the tunnel excavation section is excavated in advance and the upper half support work 3 is installed. The super long tip receiving work 1 is constructed in the tunnel axial direction in the part extending from the tunnel to the lower half 7 of the tunnel. The construction of this long tip receiving construction 1 is determined by the state of the natural ground G, but when constructing from the beginning, when constructing from the tunnel entrance to the front of the tunnel and constructing a section in the middle of the tunnel The side of the tunnel is partially widened to form a construction space, and construction is performed from there. In any case, since the construction length of the ultra-long length receiving work 1 is about 100 m, when the tunnel is longer than that and fully extended, the side portion is partially expanded in the middle of the tunnel. .
[0012]
Next, although it is a concrete embodiment of the super-long tip receiving, FIG. 2 shows a first embodiment of a drilling method in the super-long tip receiving. FIG. 3 is a perspective view of the outer tube bit and the inner tube bit in the first embodiment of the hole drilling method. However, the bit blade 15 is omitted in FIG. Hereinafter, the same components as those in FIG.
In the drilling method according to the present embodiment, the base end of a double pipe composed of an outer pipe (steel pipe) 10 and an inner pipe (steel pipe) 11 is connected to a drilling driving device (not shown), and the double pipe is connected to the double pipe. carry out the drilling of natural ground G in addition a striking force. An outer tube bit 12 is provided at the distal end of the outer tube 10, and the distal end surface of the outer tube bit 12 has an inclination angle with respect to a plane orthogonal to the axial direction of the outer tube bit 12. On the other hand, an inner tube bit 13 is provided at the distal end of the inner tube 11, and the distal end surface of the inner tube bit 12 has an inclination angle with respect to a plane orthogonal to the axial direction of the inner tube bit 13. In addition, a large number of bit blades 15 are disposed on the distal end surfaces of the outer tube bit 12 and the inner tube bit 13. Furthermore, a measuring device 14 for confirming the drilling direction is provided in the inner tube 11 behind the inner tube bit 13.
At the time of straight hole drilling, as shown in FIGS. 2 (a) and 3 (a), the relative positions of the distal end surface of the outer tube bit 12 and the distal end surface of the inner tube bit 13 are set to the axes of the outer tube bit 12 and the inner tube bit 13. The center is set as a rotation axis at a position of 180 degrees in the circumferential direction, and drilling is performed in the linear direction L1 while confirming the drilling direction with the measuring device 14.
When the drilling direction is corrected, as shown in FIGS. 2B and 3B, the relative positions of the distal end surface of the outer tube bit 12 and the distal end surface of the inner tube bit 13 are set to the axis of the outer tube bit 12 and the inner tube bit 13. The center is set as a rotation axis at a position of 0 degrees in the circumferential direction, and drilling is performed in the deflection direction B1 while confirming the drilling direction with the measuring device 14. At this time, the relative position of the distal end surface of the outer tube bit 12 and the distal end surface of the inner tube bit 13 may not be a position of 180 degrees in the circumferential direction about the axis of the outer tube bit 12 and the inner tube bit 13 as a rotation axis. Drilling may be performed in the deflection direction B1 by setting the position at a degree or 90 degrees.
[0013]
FIG. 4 shows a second embodiment of the hole drilling method in the ultra-long tip receiving work.
In the hole drilling method according to the present embodiment, a double pipe comprising an outer pipe (steel pipe) 20 having an outer pipe bit 22 at the tip and an inner pipe 21 having an inner pipe bit shoe (steel pipe) 23 at the tip is used. To do. On the side surface of the inner tube bit shoe 23, a reamer piece 25 is provided that can extend radially from the axis of the inner tube bit shoe 23. When the reamer piece 25 is stored on the side surface of the inner tube bit shoe 23, the center of the drilling surface substantially coincides with the axis of the inner tube bit shoe 23, and the reamer piece 25 is extended from the inner tube bit shoe 23. The center of the drilling surface is eccentric from the axis of the inner tube bit shoe 23. A measuring device 24 for confirming the drilling direction is provided in the inner tube 21 behind the inner tube bit shoe 23.
At the time of straight hole drilling, as shown in FIG. 4A, the reamer piece 25 is stored in the side surface of the inner pipe bit shoe 23, and the hole is drilled in the linear direction L2 while checking the hole drilling direction with the measuring device 24. .
When the drilling direction is corrected, as shown in FIG. 4B, the reamer piece 25 is extended from the inner pipe bit shoe 23, and the drilling direction is confirmed in the deflection direction B2 while checking the drilling direction with the measuring device 24. Do.
A plurality of reamer pieces 25 may be provided on the inner tube bit shoe 23.
[0014]
As described above, after drilling by the drilling method according to the first or second embodiment, the inner pipes 11 and 21 are pulled out, and the improved material is injected into the outer pipes 10 and 20 and the outer pipes 10 and 20 outside. By doing so, the natural ground improvement part 9 larger diameter than the outer tubes 10 and 20 is formed. This natural ground improvement part 9 comes to have a support function by constructing so that it may overlap (wrap) mutually. In the present embodiment, the super-long tip receiving work 1 is formed downward from the upper half supporting work 3 leg portion to support the upper half supporting work 3. In addition, since the construction length is long, it is preferable that the outer pipes 10 and 20 are perforated pipes and the sections are divided and injected using a packer or the like when the improved material is injected and filled.
When the construction of the natural ground improvement portion 9 by the super long tip receiving work 1 is completed, the upper half 6 is excavated, and the upper half support work 3 is supported by the natural ground improvement portion 9 and installed. After that, the lower half 7 is excavated, but the lock bolt 5 is driven from the gap between the steel pipes (outer pipes 10 and 20) of the super-long-length receiver 1 in parallel, and the tunnel wall of the lower half 7 (natural ground) It is also possible to reinforce the improved portion 9).
[0015]
【The invention's effect】
As described above, according to the tunnel support method according to the present invention, the support force of the upper half support legs can be obtained reliably, and the excavation efficiency can be improved.
[Brief description of the drawings]
FIG. 1 is a diagram showing an example of an embodiment of a tunnel support structure according to the present invention.
FIG. 2 is a diagram showing a first embodiment of a drilling method in an ultra-long tip receiving work.
FIG. 3 is a perspective view of an outer tube bit and an inner tube bit in a first embodiment of a drilling method in an ultra-long tip receiving work.
FIG. 4 is a diagram showing a second embodiment of a drilling method in an ultra-long tip receiving work.
[Explanation of symbols]
1 …… Super-long edge receiving 2 …… Long edge receiving 3 …… Upper half support 4 …… Liding concrete 5 …… Lock bolt 6 …… Upper half 7 …… Lower half 8 …… Invert 9 ...... Machiyama improvement part 10, 20 ... Outer pipe 11, 21 ... Inner pipe 12, 22 ... Outer pipe bit 13 ... Inner pipe bit 14, 24 ... Measuring device 15 ... Bit blade 23 ... Inner Tube bit shoe 25 ... Reamer piece G ... Natural ground L1, L2 ... Linear direction B1, B2 ... Deflection direction

Claims (3)

上半を掘削する前に、上半支保工脚部の下方位置でトンネル軸方向に沿って、長尺先受工による地山改良部を施工し、前記上半を掘削して前記上半支保工を設置する際に、前記上半支保工脚部を前記地山改良部に支持させるトンネル支保工法であって、Before excavating the upper half, construct a ground improvement part by a long tip construction along the tunnel axis direction at a position below the upper half support leg, and excavate the upper half to support the upper half When installing a work, it is a tunnel support method for supporting the upper half support leg to the natural ground improvement part,
前記長尺先受工は、前記上半支保工脚部から下方の地山部分について所定の離間間隔をおいて、トンネル坑口から前方に向けて削孔軌道を修正しつつ削孔を行い、管体を挿入してなり、The long tip receiving work performs drilling while correcting the drilling track from the tunnel wellhead to the front side at a predetermined separation interval with respect to the natural ground part below the upper half support leg, and Insert the body,
前記削孔を行うに当たり、削孔時に削孔方向を第一の方向に偏向させる力が生じる形状からなる外管ビットを先端に有する外管と、削孔時に削孔方向を第二の方向に偏向させる力が生じる形状からなる内管ビットを先端に有する内管とを備え、In performing the drilling, an outer tube having an outer tube bit having a shape that generates a force that deflects the drilling direction in the first direction during drilling, and the drilling direction in the second direction during drilling. An inner tube having an inner tube bit having a shape that generates a deflecting force at the tip;
直線削孔時には、削孔方向を第一の方向に偏向させる力と削孔方向を第二の方向に偏向させる力とが相殺されるように、前記外管ビットと前記内管ビットの周方向相対位置を設定して打撃力による削孔を行い、During linear drilling, the circumferential direction of the outer tube bit and the inner tube bit is such that the force that deflects the drilling direction in the first direction and the force that deflects the drilling direction in the second direction cancel each other. Set the relative position and drill with the impact force,
削孔方向修正時には、削孔方向を第一の方向に偏向させる力と削孔方向を第二の方向に偏向させる力との合力方向に削孔できるように、前記外管ビットと前記内管ビットの周方向相対位置を設定して打撃力による削孔を行うことを特徴とするトンネル支保工法。When correcting the drilling direction, the outer pipe bit and the inner pipe can be drilled in the resultant direction of the force that deflects the drilling direction in the first direction and the force that deflects the drilling direction in the second direction. A tunnel support method characterized by setting the relative position in the circumferential direction of the bit and drilling with impact force.
前記外管ビットおよび前記内管ビットの先端面が、前記外管ビットおよび前記内管ビットの軸方向と直交する面に対して、それぞれ傾斜角を有するように形成されていることを特徴とする請求項1に記載のトンネル支保工法。 The distal end surfaces of the outer tube bit and the inner tube bit are formed so as to have an inclination angle with respect to a surface perpendicular to the axial direction of the outer tube bit and the inner tube bit, respectively. The tunnel support method according to claim 1 . 上半を掘削する前に、上半支保工脚部の下方位置でトンネル軸方向に沿って、長尺先受工による地山改良部を施工し、前記上半を掘削して前記上半支保工を設置する際に、前記上半支保工脚部を前記地山改良部に支持させるトンネル支保工法であって、
前記長尺先受工は、前記上半支保工脚部から下方の地山部分について所定の離間間隔をおいて、トンネル坑口から前方に向けて削孔軌道を修正しつつ削孔を行い、管体を挿入してなり、
前記削孔を行うに当たり、外管ビットを先端に有する外管と、内管ビットシューを先端に有する内管とを備え、前記内管ビットシューは、前記内管ビットシューの軸心より放射方向に伸長可能なリーマー片を有し、
直線削孔時には、前記リーマー片を前記内管ビットシュー内に格納した状態として打撃力による削孔を行い、
削孔方向修正時には、前記リーマー片を前記内管ビットシューから伸長させた状態として打撃力による削孔を行うことを特徴とするトンネル支保工法。
Before excavating the upper half, construct a ground improvement part by a long tip construction along the tunnel axis direction at a position below the upper half support leg, and excavate the upper half to support the upper half A tunnel support method for supporting the upper half support leg to the natural ground improvement part when installing a work,
The long tip receiving work performs drilling while correcting the drilling track from the tunnel wellhead to the front side at a predetermined separation interval with respect to the natural ground part below the upper half support leg, and Insert the body,
In performing the drilling, an outer tube having an outer tube bit at the distal end and an inner tube having an inner tube bit shoe at the distal end are provided, and the inner tube bit shoe is radial from the axis of the inner tube bit shoe. Has an extendable reamer piece,
At the time of straight hole drilling, drilling by striking force is performed with the reamer piece stored in the inner pipe bit shoe,
A tunnel support method characterized by drilling by striking force with the reamer piece extended from the inner pipe bit shoe when correcting the drilling direction .
JP2003188285A 2003-06-30 2003-06-30 Tunnel support method Expired - Fee Related JP4145738B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003188285A JP4145738B2 (en) 2003-06-30 2003-06-30 Tunnel support method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003188285A JP4145738B2 (en) 2003-06-30 2003-06-30 Tunnel support method

Publications (2)

Publication Number Publication Date
JP2005023582A JP2005023582A (en) 2005-01-27
JP4145738B2 true JP4145738B2 (en) 2008-09-03

Family

ID=34186873

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003188285A Expired - Fee Related JP4145738B2 (en) 2003-06-30 2003-06-30 Tunnel support method

Country Status (1)

Country Link
JP (1) JP4145738B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110005444A (en) * 2019-05-05 2019-07-12 西南交通大学 Highly seismic region method for tunnel construction and tunnel support structure

Also Published As

Publication number Publication date
JP2005023582A (en) 2005-01-27

Similar Documents

Publication Publication Date Title
JP4668874B2 (en) Steel pipe tip receiving method
JP3833403B2 (en) Large-section tunnel sushi bone method
KR101233794B1 (en) Tunnel reinforcing method by multi-forepoling
JP6232743B2 (en) Tunnel construction method and tunnel
KR20160042584A (en) CIP retaining wall with steel tube
JP2788953B2 (en) Structure of tunnel structure
JP2874561B2 (en) Fore piling method with stiffening of the leading leg using a shaft
JP4145738B2 (en) Tunnel support method
KR0171394B1 (en) Drill bit
JP2010116739A (en) Tunnel supporting method and tunnel supporting structure
JP2008248528A (en) All-ground-fasten tunneling method
JP3863320B2 (en) Tunnel receiving method
JP2009074309A (en) Vertical shaft and its construction method
JP3134898U (en) Concrete pile
JP2000314291A (en) Flexible pipe and reinforcing method of tunnel natural ground
JP3839461B1 (en) Steel pipe pole foundation and its foundation method
JP3621880B2 (en) Tunnel construction method and tunnel
JP7316184B2 (en) Auxiliary method
JP4405043B2 (en) Drilling tools
JP7010312B2 (en) Ground reinforcement method
JP3100347B2 (en) Construction method of ground reinforcement bolt
JP2849605B2 (en) Large section tunnel and its construction method
JP4262303B2 (en) Ground receiving reinforcement material and method for receiving ground reinforcement
JPH0823261B2 (en) Parallel tunnel construction method
JP7075265B2 (en) Auxiliary construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060301

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071018

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071030

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071226

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080520

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080618

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110627

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110627

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120627

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120627

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130627

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140627

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees