JP4136762B2 - Method for transporting long hollow pipe into side tunnel and method for laying piping in side tunnel using the method - Google Patents

Method for transporting long hollow pipe into side tunnel and method for laying piping in side tunnel using the method Download PDF

Info

Publication number
JP4136762B2
JP4136762B2 JP2003106434A JP2003106434A JP4136762B2 JP 4136762 B2 JP4136762 B2 JP 4136762B2 JP 2003106434 A JP2003106434 A JP 2003106434A JP 2003106434 A JP2003106434 A JP 2003106434A JP 4136762 B2 JP4136762 B2 JP 4136762B2
Authority
JP
Japan
Prior art keywords
pipe
tunnel
shaft
long hollow
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2003106434A
Other languages
Japanese (ja)
Other versions
JP2004308360A (en
Inventor
直行 濱田
Original Assignee
中谷石油株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中谷石油株式会社 filed Critical 中谷石油株式会社
Priority to JP2003106434A priority Critical patent/JP4136762B2/en
Publication of JP2004308360A publication Critical patent/JP2004308360A/en
Application granted granted Critical
Publication of JP4136762B2 publication Critical patent/JP4136762B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、竪坑下部に連続する横坑トンネル内に気体や液体物を搬送するためのパイプラインや電線ケーブルの保護管等(以下「中空管」という。)を配管敷設するための工法に関するもので、とくに竪坑の長さが深く横坑トンネルが長大である場合に、長尺中空管を横坑トンネル内へ安全に搬入する方法と、該搬入方法を用いた効率がよく低コストなトンネル内配管敷設方法に関するものである。
【0002】
【従来の技術】
従来、例えば共同溝のように、略垂直な竪坑の下部(底部付近)から略水平方向に連続する横坑トンネル内に中空管を配管敷設する場合には、竪坑の直径より短い中空管を竪坑底部に水平に降下させ、次いで各中空管を横坑トンネル内所定位置にまで搬送し、順次溶接連結していく方法が一般的であった。ところが、このように敷設した完成配管の最先端へ常に新しい中空管を搬送し逐次溶接連結して延長していく方法では、溶接作業現場も横坑トンネル奥部へと順次移動しなければならないので、横坑トンネルが長大になった場合には配管敷設作業の効率が低下するという問題があった。
【0003】
そこで、特許第2754281号(特許文献1)では、発進竪坑から続く横坑トンネルの一部に長尺管製作スペースを設けて、該長尺管製作スペース内に設置した芯出し仮組み装置や溶接装置、検査装置、排煙設備を用いることにより、発進竪坑から降下搬入された中空管を複数本溶接連結して長尺の中空管(未完成配管)とした後、搬送装置により横坑トンネル内を移動させ、先行配管した長尺管(完成配管)に接続することを反復して行うトンネル内配管工法が提案されている。
【0004】
【特許文献1】
特許第2754281号公報(第1−2頁、第1−2図)
【0005】
【発明が解決しようとする課題】
前記トンネル内配管工法によれば、発進竪坑に接続された横坑トンネルの基端部分を長尺管の製作を行う作業スペースとし、発進竪坑から降下搬入される中空管を順次長尺化して配管敷設するので、長尺管製作スペース部分に集約して溶接ヒュームの排除を効率よく行うことができ、作業環境を悪化させることがなく高能率に溶接配管作業を行うことができる利点があるが、竪坑から搬入される中空管は従来と同様に竪坑の最大直径(水平断面最大長さ)以下の長さのものであり、これを水平状態で降下搬入していたので、必然的に溶接作業回数を減らすことはできなかった。
【0006】
溶接作業回数を削減するためには、可能なかぎり長尺な中空管を用いればよいということになるが、竪坑の最大直径を大きくすることはかえって工事全体のコスト高を招来してしまう欠点があったし、長尺な中空管を竪坑内に落とし込むように垂直状態で降下搬入させるとすれば、竪坑底部において中空管を水平状態にして横坑トンネル内に送入するために再度玉掛け作業が必要となり、煩雑である。
【0007】
また、前記トンネル内配管工法では、溶接連結された中空管(完成配管)は、発進竪坑側に位置する後端部をバッテリー駆動による搬送装置で押すか、又は到達竪坑側に位置する前端部を牽引することが提案されているが、後端部側には順次新たな中空管が降下搬入されてくるので作業スペースが不足しがちであるし、前端部側を牽引するとなると搬送装置と中空管搬入作業や溶接連結作業など他の作業との連携が困難となり、ひいては作業の安全性を損なう欠点がある。
【0008】
本発明は、こうした従来の中空管搬入作業や配管敷設作業の困難性に鑑み、より一層の作業工数の削減と効率化を図りながら、安全性を高めた長尺中空管の横坑トンネル内搬入方法や横坑トンネル内における配管敷設方法の提供を課題とするものである。
【0009】
【課題を解決するための手段】
前記所期の課題解決を図るため、本発明に係る長尺中空管の横坑トンネル内搬入方法では、横坑トンネル開口部と対向する発進竪坑側壁面にガイドワイヤを垂直方向に張設する一方、該ガイドワイヤ下端付近から横坑トンネル内へ移動可能な引込台車を配設しておき、長尺中空管の両端に上部配管吊具と下部配管吊具をそれぞれ仮固定し、これら配管吊具に吊下ワイヤを連結した状態で長尺中空管を発進竪坑内へと垂直降下させ、上部配管吊具をガイドワイヤに連結した後さらに長尺中空管を降下させて、下部配管吊具を前記引込台車に連結した状態で横坑トンネル内へと移動させることにより長尺中空管を水平に載置することとした。発進竪坑内へ垂直に立てらせた状態で吊下搬入することで、発進竪坑の最大直径に拘束されない、より長尺な中空管の採用を可能としつつ、ガイドワイヤに沿って降下させた後に引込台車によって水平方向への方向転換の容易化を実現したのである。
【0010】
引込台車は、竪坑底部から横坑トンネル内に至るよう敷設した仮設軌道上に配設するのが望ましく、該仮設軌道上を手動または電動等により移動させるよう構成される。長尺中空管を安定した状態で降下させて落下事故の防止を図るために、長尺中空管にはその両端に上部配管吊具と下部配管吊具をそれぞれ仮固定しておき、吊り下げワイヤを長尺中空管の外側に沿わせるか、あるいは長尺中空管の内側に挿通させるようにして、上部配管吊具と下部配管吊具に連結する。一方、ガイドワイヤと上部配管吊具との連結は、スナップフック等により遊嵌させるとよい。
【0011】
以上のようにして横坑トンネル入口付近に降下搬入された長尺中空管を横坑トンネル内に順次効率的に配管敷設するために、本発明に係る横坑トンネル内配管敷設方法では、横坑トンネル内において所定間隔で複数箇所に設けた架構にガイドローラを仮設し、横坑トンネル内の途中に設置した仮設配管送出固定架台を折り返し点として発進竪坑寄りに設けた仮設ウインチよりウインチワイヤを張設しておき、発進竪坑より搬入された長尺中空管を複数本溶接連結した後に溶接作業場より到達竪坑側に移動させて仮置きする第1工程と、仮置きされた未完成配管を架構の所定位置にあるガイドローラ上に設置して既に溶接連結作業が完了している完成配管の最後端に当接させ溶接連結した後、前記ウインチワイヤを用いて完成配管を到達竪坑に向けて送出する第2工程とを並行して行うこととした。
【0012】
横坑トンネル内に設けられる架構は、複数本の配管を振り分けて棚状に保持するものであり、敷設配管に撓み等が生じないように、所定間隔で複数箇所に配設される。この架構における各中空管配設位置にガイドローラを仮設しておくことで、既に溶接連結作業が完了している完成配管や該完成配管の最後端に溶接連結される新たな未完成配管を到達竪坑方向へ送出する作業が容易となる。送出される各完成配管の最先端部には、次に到達する架構のガイドローラ上に対して円滑に載置されるように、円錐形等の先鋭なキャップを仮被着しておくとよい。
【0013】
前記ウインチワイヤは、横坑トンネル内の途中に配設された仮設配管送出固定架台を折り返し点として、狭い横坑トンネル内を避けて幾分スペース的余裕のある発進竪坑寄りに配設された仮設ウインチにより巻き取り操作が行われる。仮設配管送出固定架台の配設位置は、横坑トンネル入口より到達竪坑に向かって順に設けられた、複数本の長尺中空管を予め連結する溶接作業場と、溶接連結された未完成配管の仮置き場と、完成配管の最後尾に新たな未完成配管を溶接する連結作業場を越えて、さらに横坑トンネル内を到達竪坑方向に奥に入った完成配管部分に設定される。例えば、仮置き場から移送された未完成配管の前端に対してウインチワイヤを連結し、当該未完成配管の最前端を既に架構の所定位置に配設された完成配管の最後尾に対して当接させ、完成配管のより前方側(到達竪坑寄り)に配設した仮設配管送出固定架台を折り返し点として発進竪坑底部に設けた仮設ウインチまで張設したウインチワイヤを巻き取ることにより、次に溶接連結作業を行う未完成配管とともに完成配管を順次送出していくことができる。
【0014】
【発明の実施の形態】
以下、図面に基づいて本発明を詳細に説明する。図1は竪坑から横坑トンネルに至る部分の概略断面図であり、竪坑内に長尺中空管を降下搬入している状態を示している。図2及び図3は、図1における竪坑底部に配設された引込台車付近を拡大した概略斜視図である。これらの図は、地表面から垂直に掘削形成された発進竪坑Aの下部に対して横坑トンネルBが水平方向に接続された海底トンネル工事を概観するものであり、発進竪坑Aは深さ約35mで直径約12m程度であり、長さ数百mの横坑トンネルBを抜けると発進竪坑と同様な到達竪坑(図示されていない)が構築されている例を想定したものである。本発明に係る長尺中空管の横坑トンネル内搬入方法は、こうした例に代表される横坑トンネルB内に複数ラインの配管敷設工事を行うに際して、横坑トンネルB内にできるだけ長尺な中空管5を安全に搬入することを可能とするものであって、2本の竪坑の双方から同時並行的に敷設工事を行う場合には、両方の竪坑が発進竪坑となるわけである。
【0015】
図1に示されるように、発進竪坑Aの地表面開口部A2には上部仮設ステージ1が延設されている一方、横坑トンネルBの開口部より一段低く構築された発進竪坑Aの底部A1には下部仮設ステージ3が設置されており、これら上下仮設ステージ間1,3において、横坑トンネルBの開口部と対向する発進竪坑側壁面A3に沿うように、一定間隔で離隔した状態で垂直方向平行にガイドワイヤ2が張設されている。なお、上部仮設ステージ1は、発進竪坑Aの中心寄りの位置に地表面より高い柵が形成され、転落防止柵として機能するよう工夫されており、この上部仮設ステージ1が設けられない発進竪坑A開口部A2の周囲には別途転落防止柵A22が配設されている。
【0016】
前記ガイドワイヤ2の下端付近には、横坑トンネルB内へと移動可能な引込台車4が配設されている。本例の引込台車4は、図2及び図3に示されるように、ガイドワイヤ2の下端付近から横坑トンネルB内へと敷設された2本の平行な仮設軌道41に沿って手動でスライド移動するものであるが、バッテリー等の動力源を備えた駆動台車としてもよい。引込台車の上面には2本の支持柱42, 42が立設されており、これら支持柱42, 42間に掛け渡された回動軸43に対して連結部材44が軸支されている。
【0017】
図1に戻って、発進竪坑A内へは、クレーンCRによって長尺中空管5を吊り下げ降下させることになる。吊り下げ降下に際しては、長尺中空管5の一端側に下部配管吊具51が被着される一方、同長尺中空管5の他端側に上部配管吊具52が被着される。これら下部配管吊具51と上部配管吊具52は、固定ボルト521等を用いて長尺中空管5に仮固定されるのであるが、本例ではクレーンCRからの吊下ワイヤCR1が上部配管吊具52に穿設された透孔522から長尺中空管5内に挿通され、かつ、当該吊下ワイヤCR1の先端が下部配管吊具51に連結固定されているので、クレーンCRにより吊り下げた際にも長尺中空管5は垂直状態を維持することになる。吊下ワイヤCR1の先端と下部配管吊具51との連結固定は、後の取り外しの便宜等のため、吊下ワイヤCR1先端の環状部に対してピンを挿通する方法が好適である。
【0018】
さらに長尺中空管5の吊り下げ降下作業を安定的に行うため、上部配管吊具52とガイドワイヤ2は、スナップフック523等を用いて連結される。スナップフック523がガイドワイヤ2に遊嵌されているために、上部配管吊具52、つまり長尺中空管5の上端部がガイドワイヤ2から離隔することなく、ガイドワイヤ2に沿って長尺中空管5が安定的に垂直降下することになるわけである。
【0019】
クレーンCRによって1本づつ吊り下げ降下された長尺中空管5が発進竪坑Aの底部A1(本例では下部仮設ステージ3)に到達すると、下部配管吊具51より延設された連結部511を引込台車4における連結部材44と連結する(図2参照)。両者の連結後は引き続き長尺中空管5を降下させ、必要により作業員が補助しながら、引込台車4を横坑トンネルB方向へと移動させる。
【0020】
図3は、図2に示される下部配管吊具51と引込台車4を連結した状態から、引込台車4を横坑トンネルB方向へと移動させていく状態を示したもので、図中破線で示したように、引込台車4が移動するにつれて長尺中空管5が5a−5b−5cと次第に倒れていく。この間も上部配管吊具52がガイドワイヤ2と連結されているので、長尺中空管5は、最終的に引込台車4の仮設軌道41, 41と平行に、すなわち水平状態に載置されることになる。引込台車4と下部配管吊具51との連結を解除し、下部配管吊具51と上部配管吊具52の双方を長尺中空管5から取り外し、長尺中空管5内から吊下ワイヤCR1を抜き去ると、長尺中空管5の降下搬入作業は完了する。
【0021】
以上の作業によって水平状態に載置された長尺中空管5は、引込台車4の仮設軌道41, 41の両脇に平行に配置されたローラコンベア(図示されていない)や、横坑トンネルB内上面に配設されたハンガートロリによって横坑トンネルB内へと移送されることになる。ローラコンベアへ載置する転動作業やハンガートロリによる吊下作業等の便宜を図るため、長尺中空管5が水平載置される前に、図3に示されるように、引込台車4が通過した後、仮設軌道41, 41を跨ぐように適宜本数の配管受台45を掛け渡しておくとよい。この配管受台45の上面が先のローラコンベアの上面部分と同じ高さになるよう設定することで、配管受台45上に載置された長尺中空管5を極めて容易にローラコンベア上に移動させることが可能となる。
【0022】
以上のようにして横坑トンネルB内へと搬入された長尺中空管5は、横坑トンネルBの入口付近に設けられた溶接作業場において予め複数本毎に溶接連結される。図4は、横坑トンネルBの入口から溶接作業場を経て未完成配管の仮置き場に至る部分の縦断面図であり、左端の引込台車4が見られる方向が発進竪坑A側である。横坑トンネルB内には所定間隔で複数箇所に架構L1〜L9が断面方向に設けられている。図5は、各架構L1〜L9の一例を横坑トンネルB長さ方向に見た状態を示した正面図であり、円形をした横坑トンネルB断面において中央部分の通路B1を介して左右両側に多段棚状に立設されており、各棚部分に配管が敷設されることになる。
【0023】
なお、図5では各配管と棚部分との間にガイドローラGが仮設されている状態が示されている。ガイドローラGは、ローラ部分に配管の幅に合わせて左右2枚の鍔が立設された糸巻き状のものが好適に用いられ、略C字形をしたクリップによって架構L1〜L9の各棚部に締結固定する等して用いられる。
【0024】
さて、図4に戻って、本例の横坑トンネルBでは、各作業場所確保のために発進竪坑A側を起点として第1架構L1から第5架構L5までの5つの架構は一時的にその一部を取り外した状態になっており、第3架構L3から第5架構L5までの横坑トンネルB内天井面にハンガートロリHが仮設されている。ハンガートロリHの下方は適宜位置にターニングローラTRが配設された効率的な溶接作業場として確保されており、この溶接作業場において、発進竪坑Aから降下搬入された長尺中空管5が2本ずつ溶接連結されている状態が示されている。このように予め溶接連結される長尺中空管5の本数は、本例のように2本に限定されるものではなく、溶接作業場として確保できる長さや作業員数等によって決定すればよい。
【0025】
2本ずつ溶接連結された長尺中空管5は、未完成配管50としてハンガートロリHによって吊り下げられ、第6架構L6より到達竪坑側に位置する架構L9までを仮置き場として、各々の未完成配管50の配管敷設が予定されている棚位置に仮置きされる。このとき、各棚位置に仮置きされる未完成配管50の送出を容易にするために、各棚には先の図5に示されるようにガイドローラが仮設されることになる。
【0026】
仮置きされた未完成配管50は、順次到達竪坑方向へと送出され、溶接連結されることにより完成配管500となる。図6も横坑トンネルBの縦断面図であり、先の図5に続いて第9架構L9より後の連結作業場付近までを図示している。図6中左側の到達竪坑側には完成配管500が上下方向三段に配管敷設されており、これら完成配管500が載置された第15架構L15と第16架構L16との間に仮設配管送出固定架台7が設置されている。この仮設配管送出固定架台7を折り返し点として、発進竪坑Aにおけるガイドワイヤ2の下端付近に設けられた仮設ウインチ6(図1参照)までの間にウインチワイヤ61が張設されており、ウインチワイヤ61の先端側は前記仮設配管送出固定架台7における複数個の滑車K2, K4等を介して再び発進竪坑A側に折り返して、完成配管500の最後端付近(溶接連結直前まで未完成配管50であり、新たに完成配管500となった部分)と連結される。ウインチワイヤ61の先端と完成配管500の連結点を図6中にY点として示す。なお、図6中のX点は、完成配管500の最後端と未完成配管50との溶接箇所である(ただし、この溶接連結により未完成配管50は完成配管500の一部となっている)。
【0027】
図7は、仮設ウインチ6から仮設配管送出固定架台7を経て未完成配管50に連結されるウインチワイヤ61の配設状態を示した概略斜視図である。図示された例では、仮設ウインチ6と仮設配管送出固定架台7間のウインチワイヤ61に荷重計62が設けられているほか、計4個の滑車K1〜K4を介してウインチワイヤ61の先端が未完成配管50に対してY点で連結されている状態が示されている。未完成配管50と完成配管500はいずれも架構L14, L15, L16の棚上に仮設されたガイドローラG上に載置されており、未完成配管50の先端は完成配管500の最後端に当接した状態でX点において溶接連結されることになる。溶接連結後、仮設ウインチ6によりウインチワイヤ61を巻き取ると、未完成配管50とともに完成配管500が到達竪坑側に送出されることになる。
【0028】
以上説明した、発進竪坑Aより搬入された長尺中空管5を複数本溶接連結した未完成配管50を溶接作業場より到達竪坑側に移動させて仮置きする第1工程と、仮置きされた未完成配管50を架構Lの所定位置にあるガイドローラG上に設置して完成配管500の最後端と当接させて溶接連結した後にウインチワイヤ61を用いて到達竪坑に向けて送出する第2工程とは、並行して行うことが可能であるから、これら第1工程と第2工程の並行処理を1日の作業とすれば、作業箇所を横坑トンネル内の発進竪坑A寄りに限定して効率的に作業を進行させることができるのである。
【0029】
【発明の効果】
本発明に係る長尺中空管の横坑トンネル内搬入方法では、発進竪坑内を垂直状態に立てらせて吊り下げ降下することによって、竪坑の最大直径に拘束されることなく長尺な中空管を搬入することが可能になるため、後に横坑トンネル内で行われる溶接連結作業工数の削減ひいては工事費用の軽減を図ることができる。また、長尺中空管は、ガイドワイヤに沿って降下されるので、発進竪坑等の構造物に接触することがないし、引込台車を用いることによって吊下降下作業から連続して水平状態に方向転換することができるので、垂直状態にある長尺中空管に再度玉掛けする作業が不要となり、極めて効率的かつ安全に横坑トンネル内に移送することができる。
【0030】
そして、本発明に係る横坑トンネル内配管敷設方法では、横坑トンネル内の入口付近に溶接作業場、仮置き場、連結作業場を集中配置したので、作業能率の向上と、ユーティリティ・安全・環境設備の簡素化を図ることができる。また、溶接作業場に仮設したウインチから伸びるウインチワイヤの引っ張り方向を横坑トンネル内途中に設けた仮設配管送出固定架台で方向変換したうえで未完成配管等に連結したので、ウインチ操作による完成配管の送出作業の連絡・調整を確実かつ迅速に行うことができ、安全作業に寄与することができるほか、ウインチワイヤの全長を短く抑えることができるので、経済的である。
【0031】
さらに、架構の棚上に対してガイドローラを配設したので、完成配管等の送出時における摩擦係数が低減し、ウインチの小型化、ウインチワイヤの小径化、配管の座屈防止が図られる。
【図面の簡単な説明】
【図1】竪坑から横坑トンネルに至る部分の概略断面図である。
【図2】図1における竪坑底部に配設された引込台車付近を拡大した概略斜視図である。
【図3】図2において引込台車を横坑トンネル方向に移動させている状態を示す概略斜視図である。
【図4】横坑トンネルの入口から溶接作業場を経て未完成配管の仮置き場に至る部分の縦断面図である。
【図5】各架構の一例を横坑トンネルの長さ方向に見た状態を示した正面図である。
【図6】図5に続く第9架構より後の連結作業場付近までを図示した横坑トンネルBの縦断面図である。
【図7】仮設ウインチから仮設配管送出固定架台を経て新たに完成配管となった部分に連結されるウインチワイヤの配設状態を示した概略斜視図である。
【符号の説明】
A 発進竪坑
B 横坑トンネル
CR1 吊下ワイヤ
1 上部仮設ステージ
2 ガイドワイヤ
3 下部仮設ステージ
4 引込台車
5 長尺中空管
6 仮設ウインチ
7 仮設配管送出固定架台
51 下部配管吊具
52 上部配管吊具
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method for laying a pipeline for protecting gas or liquid in a horizontal pit tunnel continuous to the lower part of a shaft, a protective tube for electric cable, etc. (hereinafter referred to as “hollow tube”). In particular, when the shaft is deep and the horizontal tunnel is long, the method of safely transporting the long hollow tube into the horizontal tunnel and the efficiency and low cost of using the transport method are low. The present invention relates to a tunnel laying method.
[0002]
[Prior art]
Conventionally, when a hollow pipe is laid in a horizontal tunnel that extends in a substantially horizontal direction from the bottom (near the bottom) of a substantially vertical shaft, such as a common groove, a hollow tube shorter than the diameter of the shaft Is generally lowered to the bottom of the shaft and then each hollow tube is transported to a predetermined position in the side tunnel and sequentially welded. However, in the method in which a new hollow pipe is always transported to the forefront of the completed pipe laid in this way, and it is sequentially welded and extended, the welding work site must also move sequentially to the back of the side tunnel. Therefore, when the horizontal tunnel becomes long, there is a problem that the efficiency of pipe laying work is lowered.
[0003]
Therefore, in Japanese Patent No. 2754281 (Patent Document 1), a long pipe manufacturing space is provided in a part of a horizontal tunnel that extends from the starting shaft, and a centering temporary assembly device or welding installed in the long pipe manufacturing space is provided. By using the equipment, inspection equipment, and smoke exhausting equipment, a plurality of hollow pipes lowered from the starting shaft are welded together to form a long hollow pipe (unfinished pipe), and then the horizontal pipe is transported by the transport device. An in-tunnel piping method has been proposed in which the inside of a tunnel is moved and connected to a long pipe (completed pipe) that has been previously piped.
[0004]
[Patent Document 1]
Japanese Patent No. 2754281 (page 1-2, Fig. 1-2)
[0005]
[Problems to be solved by the invention]
According to the tunnel piping method, the base end portion of the horizontal tunnel connected to the starting shaft is used as a work space for manufacturing a long tube, and the hollow tubes lowered from the starting shaft are sequentially elongated. Since piping is laid, it is possible to efficiently eliminate welding fumes by concentrating on the long pipe manufacturing space, and there is an advantage that welding piping work can be performed efficiently without deteriorating the work environment. The hollow tube carried in from the shaft is the same as the conventional shaft with the maximum diameter (horizontal section maximum length) or less, and since it was carried down in a horizontal state, it was inevitably welded. The number of work could not be reduced.
[0006]
In order to reduce the number of welding operations, it is sufficient to use the longest hollow tube possible. However, increasing the maximum diameter of the shaft is rather expensive. If a long hollow tube is lowered and carried in a vertical state so as to drop into the shaft, the hollow tube is placed in the horizontal state at the bottom of the shaft and is again fed into the horizontal tunnel. A slinging work is required and is complicated.
[0007]
Further, in the tunnel piping method, the welded and connected hollow pipe (completed pipe) pushes the rear end portion located on the starting shaft side with a battery-driven transfer device or the front end portion located on the reaching shaft side However, work space tends to be short because new hollow tubes are sequentially lowered and carried on the rear end side, and when the front end side is pulled, There is a drawback in that it is difficult to cooperate with other operations such as a hollow tube carrying-in operation and a welding connection operation, and as a result, the safety of the operation is impaired.
[0008]
In view of the difficulty of such conventional hollow tube carrying-in work and piping laying work, the present invention is a long hollow tube horizontal tunnel with improved safety while further reducing the work man-hours and increasing efficiency. It is an object to provide an inward carrying method and a pipe laying method in a horizontal tunnel.
[0009]
[Means for Solving the Problems]
In order to solve the desired problem, in the method for carrying in the long hollow tube according to the present invention in the horizontal tunnel, a guide wire is stretched in the vertical direction on the side wall surface of the starting shaft opposite to the opening of the horizontal tunnel. On the other hand, a retractable carriage that is movable from near the lower end of the guide wire into the side tunnel is disposed, and an upper pipe hanger and a lower pipe hanger are temporarily fixed to both ends of the long hollow pipe, respectively. With the hanging wire connected to the hanging tool, the long hollow tube is lowered vertically into the starting shaft, and after the upper pipe hanging device is connected to the guide wire, the long hollow tube is further lowered to the lower piping. The long hollow tube was placed horizontally by moving the hoisting tool into the side tunnel while being connected to the pulling carriage. It was lowered along the guide wire while allowing the adoption of a longer hollow tube that is not restricted by the maximum diameter of the starting shaft by hanging and carrying it in a state of standing vertically into the starting shaft. Later, a pull-in cart facilitated the change of direction in the horizontal direction.
[0010]
The lead-in cart is preferably arranged on a temporary track laid from the bottom of the shaft to the inside of the horizontal tunnel, and is configured to be moved manually or electrically on the temporary track. In order to prevent the fall accident by dropping the long hollow tube in a stable state, the upper and lower pipe suspensions are temporarily fixed to both ends of the long hollow tube. The lower wire is connected to the upper pipe hanger and the lower pipe hanger so as to extend along the outer side of the long hollow pipe or to be inserted inside the long hollow pipe. On the other hand, the guide wire and the upper pipe hanger may be connected loosely by a snap hook or the like.
[0011]
In order to efficiently lay down the long hollow pipe that has been carried down near the entrance of the side pit tunnel as described above, the pipe laying method in the side pit tunnel according to the present invention is Guide rollers are temporarily installed on the frames provided at multiple locations at predetermined intervals in the tunnel, and a winch wire is installed from a temporary winch provided near the starting dredging pit with the temporary pipe feed fixed installation installed in the middle of the horizontal tunnel as a turning point. A first step in which a plurality of long hollow tubes carried from the starting shaft are connected by welding and then moved from the welding work site to the ultimate shaft and temporarily placed, and the temporarily placed unfinished pipe Installed on the guide roller at a predetermined position of the frame and contacted with the last end of the finished pipe that has already been welded and connected by welding, and then using the winch wire to move the finished pipe to the final shaft Only the second step of delivered was be performed in parallel.
[0012]
The frame provided in the horizontal tunnel is for distributing a plurality of pipes and holding them in a shelf shape, and is arranged at a plurality of locations at predetermined intervals so that the laid pipes do not bend. By temporarily installing a guide roller at each hollow tube placement position in this frame, a completed pipe that has already been welded and connected, or a new incomplete pipe that is welded and connected to the end of the finished pipe The work of sending in the direction of the reaching shaft becomes easy. It is advisable to temporarily attach a sharp cap such as a conical shape at the most advanced portion of each finished pipe to be sent out so that it can be smoothly placed on the guide roller of the next reaching structure. .
[0013]
The winch wire is a temporary installation that is located near the starting dredging shaft with some space to avoid the inside of the narrow horizontal tunnel, with the temporary pipe delivery fixed stand installed in the middle of the horizontal tunnel as a turning point. The winding operation is performed by the winch. The temporary pipe delivery fixed stand is arranged in order from the entrance of the horizontal tunnel toward the arrival shaft, a welding work place for connecting a plurality of long hollow tubes in advance, and the welded unfinished pipe It is set in the completed pipe part that goes beyond the temporary work place and the connection work place where a new unfinished pipe is welded to the end of the finished pipe, and further enters the inner side of the horizontal tunnel. For example, a winch wire is connected to the front end of the unfinished pipe transferred from the temporary storage site, and the foremost end of the unfinished pipe is brought into contact with the rear end of the finished pipe already arranged at a predetermined position of the frame. Next, welded connection is made by winding up the winch wire stretched up to the temporary winch provided at the bottom of the starting dredging pit with the temporary piping delivery fixing stand arranged on the more forward side (near the reaching dredging pit) of the completed pipe as the turning point Completed pipes can be sent out together with unfinished pipes that perform work.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described in detail with reference to the drawings. FIG. 1 is a schematic cross-sectional view of a portion from a shaft to a horizontal shaft tunnel, and shows a state in which a long hollow tube is lowered into the shaft. 2 and 3 are enlarged schematic perspective views of the vicinity of the pull-in carriage disposed at the bottom of the shaft in FIG. These figures give an overview of the submarine tunnel construction in which the horizontal tunnel B is connected horizontally to the lower part of the start shaft A excavated vertically from the ground surface. It is assumed that an arrival shaft (not shown) similar to the starting shaft is constructed after passing through a horizontal shaft tunnel B having a diameter of about 12 meters at 35 m and a length of several hundred meters. The method of carrying a long hollow pipe into a horizontal tunnel according to the present invention is as long as possible in the horizontal tunnel B when a plurality of lines of pipes are laid in the horizontal tunnel B represented by such an example. The hollow tube 5 can be safely carried in, and when laying work is performed in parallel from both of the two shafts, both shafts become starting shafts.
[0015]
As shown in FIG. 1, an upper temporary stage 1 is extended to the ground surface opening A2 of the starting shaft A, while a bottom A1 of the starting shaft A constructed one step lower than the opening of the horizontal tunnel B. The lower temporary stage 3 is installed in the upper and lower temporary stages 1, 3 so that the vertical shaft is spaced apart at regular intervals along the starting shaft side wall surface A3 facing the opening of the horizontal tunnel B. A guide wire 2 is stretched parallel to the direction. In addition, the upper temporary stage 1 is devised so that a fence higher than the ground surface is formed near the center of the starting shaft A and functions as a fall-preventing fence, and the starting shaft A where the upper temporary stage 1 is not provided. A fall prevention fence A22 is separately provided around the opening A2.
[0016]
In the vicinity of the lower end of the guide wire 2, a retractable carriage 4 that can move into the horizontal tunnel B is disposed. As shown in FIGS. 2 and 3, the pull-in cart 4 of this example is manually slid along two parallel temporary tracks 41 laid from the vicinity of the lower end of the guide wire 2 into the horizontal tunnel B. Although it moves, it is good also as a drive trolley | bogie provided with power sources, such as a battery. Two support columns 42 and 42 are erected on the upper surface of the pull-in carriage, and a connecting member 44 is pivotally supported on a rotating shaft 43 spanned between the support columns 42 and 42.
[0017]
Returning to FIG. 1, the long hollow tube 5 is suspended and lowered into the start shaft A by the crane CR. When the suspension is lowered, the lower pipe suspension 51 is attached to one end side of the long hollow tube 5, while the upper pipe suspension 52 is attached to the other end side of the long hollow tube 5. . The lower pipe hanger 51 and the upper pipe hanger 52 are temporarily fixed to the long hollow pipe 5 using fixing bolts 521 or the like. In this example, the hanger wire CR1 from the crane CR is used as the upper pipe. Since the through hole 522 formed in the hanging tool 52 is inserted into the long hollow tube 5 and the tip of the hanging wire CR1 is connected and fixed to the lower pipe hanging tool 51, it is suspended by the crane CR. Even when lowered, the long hollow tube 5 maintains the vertical state. For the connection and fixation between the tip of the suspension wire CR1 and the lower pipe suspension 51, a method of inserting a pin into the annular portion at the tip of the suspension wire CR1 is suitable for the convenience of subsequent removal.
[0018]
Further, in order to stably perform the hanging down operation of the long hollow tube 5, the upper pipe suspension 52 and the guide wire 2 are connected using a snap hook 523 or the like. Since the snap hook 523 is loosely fitted to the guide wire 2, the upper pipe suspension 52, that is, the upper end portion of the long hollow tube 5 is not separated from the guide wire 2, and is long along the guide wire 2. That is, the hollow tube 5 descends vertically stably.
[0019]
When the long hollow tube 5 suspended and lowered by the crane CR one by one reaches the bottom A1 of the starting shaft A (the lower temporary stage 3 in this example), the connecting portion 511 extending from the lower pipe suspension 51 is provided. Is connected to the connecting member 44 in the pull-in cart 4 (see FIG. 2). After the connection between the two, the long hollow tube 5 is continuously lowered, and the pull-in cart 4 is moved in the direction of the side tunnel B with assistance from an operator as necessary.
[0020]
FIG. 3 shows a state in which the pulling carriage 4 is moved in the direction of the horizontal tunnel B from the state where the lower pipe suspension 51 and the pulling carriage 4 shown in FIG. 2 are connected. As shown, the long hollow tube 5 gradually falls down to 5a-5b-5c as the retracting carriage 4 moves. During this time, the upper pipe suspension 52 is connected to the guide wire 2, so that the long hollow tube 5 is finally placed in parallel with the temporary tracks 41, 41 of the retracting carriage 4, that is, in a horizontal state. It will be. The connection between the pull-in carriage 4 and the lower pipe hanger 51 is released, and both the lower pipe hanger 51 and the upper pipe hanger 52 are detached from the long hollow tube 5, and the suspended wire is drawn from the long hollow tube 5. When CR1 is removed, the work of moving down the long hollow tube 5 is completed.
[0021]
The long hollow tube 5 placed in a horizontal state by the above-described work is composed of a roller conveyor (not shown) arranged in parallel on both sides of the temporary tracks 41 and 41 of the pull-in carriage 4 and a horizontal tunnel. It will be transferred into the horizontal tunnel B by the hanger trolley disposed on the upper surface of B. Before the long hollow tube 5 is placed horizontally, for the convenience of rolling work placed on a roller conveyor or hanging work by a hanger trolley, as shown in FIG. After passing, a suitable number of pipe cradles 45 may be bridged over the temporary tracks 41, 41 as appropriate. By setting the upper surface of the pipe cradle 45 to be the same height as the upper surface of the roller conveyor, the long hollow tube 5 placed on the pipe cradle 45 can be very easily placed on the roller conveyor. It is possible to move to.
[0022]
The long hollow tube 5 carried into the side tunnel B as described above is welded in advance at a plurality of positions in a welding work place provided near the entrance of the side tunnel B. FIG. 4 is a vertical cross-sectional view of a portion from the entrance of the horizontal tunnel B to the temporary storage place for the unfinished pipe through the welding work place, and the direction in which the pull-in carriage 4 at the left end is seen is the start shaft A side. Within the horizontal tunnel B, frames L1 to L9 are provided in a cross-sectional direction at a plurality of locations at predetermined intervals. FIG. 5 is a front view showing an example of each of the frames L1 to L9 as seen in the length direction of the horizontal tunnel B. Both the right and left sides of the circular horizontal tunnel B cross section through the passage B1 in the center portion In this case, the pipes are laid on each shelf portion.
[0023]
FIG. 5 shows a state in which a guide roller G is temporarily installed between each pipe and the shelf portion. The guide roller G is preferably a bobbin-shaped one in which two left and right ridges are erected in accordance with the width of the pipe on the roller portion, and each of the racks L1 to L9 is provided with a substantially C-shaped clip. Used by fastening and fixing.
[0024]
Now, referring back to FIG. 4, in the horizontal pit tunnel B of this example, the five frames from the first frame L1 to the fifth frame L5 are temporarily set from the start shaft A side to secure each work place. The hanger trolley H is temporarily installed on the ceiling surface in the horizontal tunnel B from the third frame L3 to the fifth frame L5. Below the hanger trolley H is secured as an efficient welding work place in which a turning roller TR is disposed at an appropriate position. In this welding work place, two long hollow tubes 5 lowered and carried from the starting shaft A are provided. The state where it is weld-connected one by one is shown. Thus, the number of the long hollow tubes 5 to be welded in advance is not limited to two as in this example, but may be determined by the length that can be secured as a welding work place, the number of workers, and the like.
[0025]
The two long hollow pipes 5 welded to each other are suspended by the hanger trolley H as unfinished pipes 50, and each unfinished pipe is set as a temporary storage area from the sixth frame L6 to the frame L9 located on the arrival shaft side. The completed piping 50 is temporarily placed on the shelf position where the piping is scheduled to be laid. At this time, in order to facilitate the delivery of the unfinished pipe 50 temporarily placed at each shelf position, a guide roller is temporarily installed on each shelf as shown in FIG.
[0026]
The temporarily placed unfinished pipe 50 is sequentially sent in the direction of the reaching shaft and welded to form a finished pipe 500. FIG. 6 is also a vertical cross-sectional view of the horizontal tunnel B, and shows the area up to the connection work site after the ninth frame L9 following FIG. In FIG. 6, the completed pipe 500 is laid in three stages in the vertical direction on the left shaft side of the shaft in FIG. 6, and the temporary pipe is sent between the 15th frame L15 and the 16th frame L16 on which the completed pipe 500 is placed. A fixed base 7 is installed. A winch wire 61 is stretched between the temporary pipe sending fixed base 7 and a temporary winch 6 (see FIG. 1) provided near the lower end of the guide wire 2 in the starting shaft A. The front end of 61 is turned back to the starting shaft A side again via a plurality of pulleys K2, K4, etc. in the temporary pipe delivery fixed stand 7, and the vicinity of the final end of the completed pipe 500 (until the unfinished pipe 50 until just before welding connection). Yes, it is connected to the newly completed pipe 500). A connection point between the tip of the winch wire 61 and the completed pipe 500 is shown as a Y point in FIG. Note that the point X in FIG. 6 is a welded portion between the rearmost end of the completed pipe 500 and the incomplete pipe 50 (however, the incomplete pipe 50 becomes a part of the completed pipe 500 by this welding connection). .
[0027]
FIG. 7 is a schematic perspective view showing an arrangement state of the winch wire 61 connected from the temporary winch 6 to the unfinished pipe 50 through the temporary pipe sending and fixing base 7. In the illustrated example, a load meter 62 is provided on the winch wire 61 between the temporary winch 6 and the temporary pipe delivery fixing stand 7, and the tip of the winch wire 61 is not yet connected via a total of four pulleys K1 to K4. The state where it is connected to the completed pipe 50 at the point Y is shown. The unfinished pipe 50 and the finished pipe 500 are both placed on the guide rollers G temporarily installed on the shelves of the frames L14, L15, and L16, and the tip of the unfinished pipe 50 hits the end of the finished pipe 500. It will be welded at point X in contact. When the winch wire 61 is wound up by the temporary winch 6 after the welding connection, the completed pipe 500 together with the unfinished pipe 50 is sent to the reaching shaft side.
[0028]
As described above, the first step of temporarily placing the unfinished pipe 50 in which a plurality of long hollow tubes 5 carried from the starting shaft A are welded and connected to the arrival shaft side from the welding work place is temporarily placed. A second pipe 50 is installed on a guide roller G at a predetermined position of the frame L, brought into contact with the rearmost end of the finished pipe 500 and welded, and then sent to the final shaft using the winch wire 61. Since the process can be performed in parallel, if the parallel processing of the first process and the second process is a day work, the work location is limited to the start shaft A in the horizontal tunnel. Work efficiently.
[0029]
【The invention's effect】
In the method for carrying a long hollow tube into a horizontal shaft tunnel according to the present invention, the inside of the starting shaft is set in a vertical state and suspended and lowered, so that it is not restricted by the maximum diameter of the shaft. Since it becomes possible to carry in the empty pipe, it is possible to reduce the number of welding connection work steps to be performed later in the horizontal tunnel and to reduce the construction cost. In addition, since the long hollow tube is lowered along the guide wire, it does not come into contact with structures such as starting shafts, and the horizontal direction can be continuously extended from the suspended lowering work by using the retracting carriage. Since it can be converted, it is not necessary to hang again on the long hollow tube in the vertical state, and it can be transferred into the side tunnel very efficiently and safely.
[0030]
In the horizontal tunnel tunnel laying method according to the present invention, the welding work site, temporary storage site, and connection work site are concentrated in the vicinity of the entrance in the horizontal shaft tunnel, which improves work efficiency and improves utility, safety and environmental equipment. Simplification can be achieved. In addition, the direction of the pulling of the winch wire extending from the winch temporarily installed in the welding workshop was changed by a temporary pipe delivery fixed stand provided in the middle of the horizontal tunnel, and then connected to the unfinished pipe. Since it is possible to contact and adjust the delivery work reliably and quickly, it can contribute to safety work, and the overall length of the winch wire can be kept short, which is economical.
[0031]
Further, since the guide roller is disposed on the shelf of the frame, the friction coefficient at the time of sending out the finished pipe or the like is reduced, so that the winch can be downsized, the winch wire can be reduced in diameter, and the pipe can be prevented from buckling.
[Brief description of the drawings]
FIG. 1 is a schematic cross-sectional view of a portion from a shaft to a horizontal tunnel.
2 is an enlarged schematic perspective view of the vicinity of a pull-in carriage disposed at the bottom of the shaft in FIG. 1. FIG.
FIG. 3 is a schematic perspective view showing a state in which the retracting carriage is moved in the direction of the side tunnel in FIG. 2;
FIG. 4 is a longitudinal sectional view of a portion from an entrance of a horizontal tunnel through a welding work site to a temporary storage place for unfinished piping.
FIG. 5 is a front view showing a state in which an example of each frame is viewed in the length direction of the horizontal tunnel.
FIG. 6 is a longitudinal sectional view of a horizontal tunnel B illustrating the area up to the connection work site after the ninth frame following FIG. 5;
FIG. 7 is a schematic perspective view showing an arrangement state of a winch wire connected from a temporary winch through a temporary pipe sending and fixing base to a newly completed pipe.
[Explanation of symbols]
A Starting shaft B Horizontal shaft tunnel CR1 Suspension wire 1 Upper temporary stage 2 Guide wire 3 Lower temporary stage 4 Pull-in carriage 5 Long hollow pipe 6 Temporary winch 7 Temporary pipe delivery fixed stand 51 Lower pipe suspension 52 Upper pipe suspension

Claims (2)

発進竪坑下部に接続された横坑トンネル内に長尺中空管を降下搬入する方法であって、横坑トンネル開口部と対向する発進竪坑側壁面にガイドワイヤを垂直方向に張設する一方、該ガイドワイヤ下端付近から横坑トンネル内へ移動可能な引込台車を配設しておき、長尺中空管の両端に上部配管吊具と下部配管吊具をそれぞれ仮固定し、これら配管吊具に吊下ワイヤを連結した状態で長尺中空管を発進竪坑内へと垂直降下させ、上部配管吊具をガイドワイヤに連結した後さらに長尺中空管を降下させて、下部配管吊具を前記引込台車に連結した状態で横坑トンネル内へと移動させることにより長尺中空管を水平に載置することを特徴とする長尺中空管の横坑トンネル内搬入方法。In this method, the long hollow tube is lowered into the horizontal tunnel connected to the lower part of the starting shaft, and a guide wire is vertically stretched on the side surface of the starting shaft opposite to the opening of the horizontal shaft tunnel, A retractable carriage that is movable from the vicinity of the lower end of the guide wire into the horizontal tunnel is disposed, and an upper pipe hanger and a lower pipe hanger are temporarily fixed to both ends of the long hollow pipe, respectively. With the suspension wire connected to the vertical hollow pipe, the long hollow pipe is vertically lowered into the starting shaft, the upper pipe suspension is connected to the guide wire, and then the long hollow pipe is further lowered to lower the pipe suspension. The long hollow tube is horizontally placed by moving the tube into the horizontal shaft tunnel while being connected to the pull-in carriage, and the method for carrying the long hollow tube into the horizontal shaft tunnel. 横坑トンネル内において所定間隔で複数箇所に設けた架構にガイドローラを仮設し、横坑トンネル内の途中に設置した仮設配管送出固定架台を折り返し点として発進竪坑寄りに設けた仮設ウインチよりウインチワイヤを張設しておき、発進竪坑より搬入された長尺中空管を複数本溶接連結した後に溶接作業場より到達竪坑側に移動させて仮置きする第1工程と、仮置きされた未完成配管を架構の所定位置にあるガイドローラ上に設置して完成配管の最後端と当接させて溶接連結した後、前記ウインチワイヤを用いて完成配管を到達竪坑に向けて送出する第2工程とを並行して行うことを特徴とする請求項1記載の長尺中空管の横坑トンネル内搬入方法を用いた横坑トンネル内配管敷設方法。A guide roller is temporarily installed on a frame provided at a plurality of locations at a predetermined interval in the horizontal tunnel, and a winch wire is provided from a temporary winch provided near the starting dredging shaft with a temporary pipe feed fixed installation installed in the middle of the horizontal tunnel as a turning point. A first step in which a plurality of long hollow pipes carried from the starting shaft are welded together and then moved from the welding work site to the ultimate shaft and temporarily placed, and temporarily placed unfinished piping Is installed on a guide roller at a predetermined position of the frame, brought into contact with the rearmost end of the finished pipe and welded, and then the second step of sending the finished pipe toward the reaching shaft using the winch wire; The method for laying piping in a horizontal shaft tunnel using the method for carrying in a horizontal tunnel of a long hollow tube according to claim 1, wherein the method is carried out in parallel.
JP2003106434A 2003-04-10 2003-04-10 Method for transporting long hollow pipe into side tunnel and method for laying piping in side tunnel using the method Expired - Lifetime JP4136762B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003106434A JP4136762B2 (en) 2003-04-10 2003-04-10 Method for transporting long hollow pipe into side tunnel and method for laying piping in side tunnel using the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003106434A JP4136762B2 (en) 2003-04-10 2003-04-10 Method for transporting long hollow pipe into side tunnel and method for laying piping in side tunnel using the method

Publications (2)

Publication Number Publication Date
JP2004308360A JP2004308360A (en) 2004-11-04
JP4136762B2 true JP4136762B2 (en) 2008-08-20

Family

ID=33468623

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003106434A Expired - Lifetime JP4136762B2 (en) 2003-04-10 2003-04-10 Method for transporting long hollow pipe into side tunnel and method for laying piping in side tunnel using the method

Country Status (1)

Country Link
JP (1) JP4136762B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105984730B (en) * 2015-02-16 2019-11-08 中国二十冶集团有限公司 A kind of pipeline transport method of pipe trench discharge port
CN109854273A (en) * 2019-02-19 2019-06-07 中铁第一勘察设计院集团有限公司 The shield duct piece method for dismounting and its equipment of service channel in tunnel

Also Published As

Publication number Publication date
JP2004308360A (en) 2004-11-04

Similar Documents

Publication Publication Date Title
CN111502714A (en) Shield machine and tunnel tunneling material transportation system thereof
CN102653360A (en) Multifunctional soft bundled cable take-up and pay-off device
CN104295077A (en) Annular hanging platform for mounting stove shell of hot-blast stove, and mounting and dismounting method thereof
CN112758593B (en) Inserting frame device
JP4136762B2 (en) Method for transporting long hollow pipe into side tunnel and method for laying piping in side tunnel using the method
CN109441457A (en) The construction method of the synchronous transfer of shield separate launching pipeline
CN206305732U (en) Suspension type motor -cycle frame assembly assembles device
JP4933881B2 (en) Tube transport carriage and tube laying method
CN114933231A (en) Row pipe bundle hoisting tool and construction method thereof
CN108868098B (en) Support frame used outside hoistway and mounting method thereof
CN112813777A (en) Material distribution device for municipal road engineering kerbstone and kerbstone construction method
JP4804676B2 (en) Piping installation method and apparatus in tunnel
CN111472783A (en) Shield tunneling machine split initial lengthened pipeline extending device and application method
CN112660988B (en) A conveyer that is used for heavy steel pipe of heavy bore in piping lane
CN216471910U (en) Large-diameter pipeline installation structure in narrow space
CN212406759U (en) Shield machine and tunnel tunneling material transportation system thereof
CN109339801B (en) Pipeline extension device of shield tunneling machine
CN112456358B (en) Pipeline translation lifting device suitable for membrane bag method barrage and operation method
JPS5830963B2 (en) Method and device for transferring parallel cable strands to saddle
CN220765624U (en) Photovoltaic module conveyer
CN214337366U (en) Cable traction device for buried ground wire pipe of household distribution box
JP2018159407A (en) Pipe lift device
CN210111483U (en) Auxiliary laying device for bridge pipeline
CN210418680U (en) Cable paying-off support
CN117090436B (en) Telegraph pole fixing traction device for power supply equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060303

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080430

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080513

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080603

R150 Certificate of patent or registration of utility model

Ref document number: 4136762

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140613

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140613

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term