JP4127933B2 - Construction method of prestressed concrete floor slab with closed section box girder. - Google Patents
Construction method of prestressed concrete floor slab with closed section box girder. Download PDFInfo
- Publication number
- JP4127933B2 JP4127933B2 JP20877599A JP20877599A JP4127933B2 JP 4127933 B2 JP4127933 B2 JP 4127933B2 JP 20877599 A JP20877599 A JP 20877599A JP 20877599 A JP20877599 A JP 20877599A JP 4127933 B2 JP4127933 B2 JP 4127933B2
- Authority
- JP
- Japan
- Prior art keywords
- box girder
- floor slab
- section box
- concrete
- stud
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法に関する。
【0002】
【従来の技術】
閉断面箱桁のプレストレストコンクリート床版の施工は、予め工場で製造したプレストレストコンクリート床版を現場に搬送して閉断面箱桁に設置し固定する方法がとられる。したがって、閉断面箱桁の現場打ちプレストレストコンクリート床版の施工例は無い。これは、現場打ちの場合は、図6に示すように、閉断面箱桁11上に従来構造の床版12のための型枠を設置し、コンクリートを打設し、コンクリート硬化後、PC鋼線13を緊張してプレストレスを導入することになるので、プレストレスの導入がポストテンションとなり、以下の問題を生じるからである。
【0003】
【発明が解決しようとする課題】
閉断面箱桁に現場打ちプレストレストコンクリート床版を施工すると、つぎの問題が生じる。
(i)プレストレス導入時に箱桁の拘束が大きく、導入プレストレスの損失が発生する。
( ii )プレストレス導入時に箱桁本体に常時外力が作用するため、箱桁の補強が必要となる。
(iii) プレストレス導入時の箱桁の変形が少ないため、PCプレストレスの緊張により、床版コンクリートに割れが発生する虞がある。
本発明の目的は、プレストレス導入時に箱桁の拘束が大きくなくかつ箱桁の補強も必要でなく、プレストレス導入時に床版コンクリートに割れが発生する虞がない、閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法を提供することにある。
【0004】
【課題を解決するための手段】
上記目的を達成する本発明はつぎの通りである。
(1) 閉断面箱桁上にスタッド部には箱抜き用型枠を設置しスタッド部以外には硬質ウレタンの板材またはすべり性のよい樹脂を少なくとも表面に貼付した樹脂製または金属製の硬質部材からなる滑り用部材を設置し、
前記滑り用部材の外側側面に型枠端部を合わせて前記閉断面箱桁から横方向に外側に張り出し、コンクリート打設時には床版コンクリートの下面と側面の形状を出し、打設コンクリート硬化後には撤去される型枠(以下、「打設コンクリート硬化後には撤去される型枠」、または、「従来構造の型枠」、「床版型枠」ともいう)を設置し、
床版コンクリートを打設し、
コンクリート硬化後前記型枠を撤去し、
滑り用部材部位での滑りにより床版コンクリートと箱桁との間の相対変位を許容しつつPC鋼線を緊張し、
箱抜き部にモルタルを充填する、
工程からなる、閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法。
(2) 閉断面箱桁上に、スタッド付き鋼板を該鋼板または閉断面箱桁に形成したPC鋼線緊張方向に拡大された拡大孔に高力ボルトを挿通して仮締めし、
前記スタッド付き鋼板の外側側面に型枠端部を合わせて前記閉断面箱桁から横方向に外側に張り出し、コンクリート打設時には床版コンクリートの下面と側面の形状を出し、打設コンクリート硬化後には撤去される型枠(以下、「打設コンクリート硬化後には撤去される型枠」、または、「従来型枠」、「床版型枠」ともいう)を設置し、
床版コンクリートを打設し、
コンクリート硬化後前記型枠を撤去し、
拡大孔内での高力ボルトの移動によりスタッド付き鋼板と箱桁との間の相対変位を許容しつつ橋軸直角方向にPC鋼線を緊張し、
スタッド付き鋼板の高力ボルトを本締めする、
工程からなる、閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法。
【0005】
上記(1)の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法では、スタッド部には箱抜き用型枠を設置してコンクリートを打つので、PC緊張時に床版コンクリートがスタッドに対して相対移動しても、スタッド部はコンクリートと干渉せず、また、閉断面箱桁上に滑り用部材(たとえば、硬質ウレタン)を設置した上に床版型枠を設置するので、PC緊張時に床版コンクリートが閉断面箱桁に対して相対移動しても、滑り用部材部位で滑ることができる。その結果、PC緊張時に、床版コンクリートと閉断面箱桁とは、互いに拘束し合わず、プレストレス導入時における、床版コンクリートと箱桁の互いの拘束は大きくなく、したがって、箱桁の補強も必要でなく、プレストレス導入時に床版コンクリートに割れが発生する虞もない。
上記(2)の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法では、閉断面箱桁上に、スタッド付き鋼板を該鋼板に形成した拡大孔に高力ボルトを挿通して仮締めするので、PC緊張時に床版コンクリートとスタッド付き鋼板が一体になって閉断面箱桁に対して相対移動しても、高力ボルトが拡大孔内を移動できるため、スタッド付き鋼板の下面が閉断面箱桁に対して滑ることができる。その結果、PC緊張時に、床版コンクリートと閉断面箱桁とは、互いに拘束し合わず、プレストレス導入時における、床版コンクリートと箱桁の互いの拘束は大きくなく、したがって、箱桁の補強も必要でなく、プレストレス導入時に床版コンクリートに割れが発生する虞もない。
【0006】
【発明の実施の形態】
図1、図2は本発明の第1実施例の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法を示しており、図3〜図5は本発明の第2実施例の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法を示している。
【0007】
まず、本発明の第1実施例を、図1、図2を参照して説明する。
図1、図2に示すように、本発明の第1実施例の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法は、閉断面箱桁11上にスタッド部14には箱抜き用型枠15を設置しスタッド部14以外には滑り用部材16を設置する工程と、ついで滑り用部材16上に従来構造の型枠17を設置する工程と、ついで床版コンクリート18を打設する工程と、コンクリート硬化後従来構造の型枠17を撤去する工程と、ついでPC鋼線13を緊張する工程と、ついで箱抜き部19にモルタルを充填する工程と、からなる。滑り用部材16は、たとえば、硬質ウレタンからなる。滑り用部材16は、硬質ウレタン16の代わりに、すべり性のよい樹脂を少なくとも表面に貼付した樹脂製または金属製の硬質部材であってもよい。以下の説明では、滑り用部材16が硬質ウレタンの板材である場合を例にとる。
【0008】
スタッド部14にはスタッドジベルが閉断面箱桁11に固定され、その周囲が箱抜き用型枠15で箱抜きされる。滑り用部材16である硬質ウレタン16は箱抜き部19には設置されない。スタッド部14および硬質ウレタン16は、閉断面箱桁11の断面の左右両側部上面に設けられる。
【0009】
型枠17を設置後、鉄筋を配筋する時にPC鋼線の鞘を設置した後、コンクリートを打設する。PC鋼線13を緊張する工程では、PC鋼線13を鞘に通しているので、PC鋼線13はコンクリートとは独立である。PC鋼線13は、現場で緊張され、コンクリート硬化後のポストテンションとなる。PC鋼線13緊張時には床版12にPC鋼線13緊張方向に圧縮力がかかるが(この時PC鋼線13には引張り力がかかる)、床版12と硬質ウレタン16または硬質ウレタン16と閉断面箱桁11との間にすべりが生じて、床版12は閉断面箱桁11とほとんど拘束しあうことなく縮み、また箱抜き部19にモルタルを充填する前であるので、スタッドジベルと拘束しあうことなく縮むことができる。
【0010】
床版12と閉断面箱桁との間の空間には、床版コンクリートの型枠17と同時施行される埋め殺し型枠23が設置される。埋め殺し型枠23は、通常、発泡スチロールや硬質ウレタンからなり、型枠下部と箱桁上面との間に空間が生じないように施行される。埋め殺し型枠23は、完成後も撤去されず残される。
【0011】
本発明の第1実施例の作用を説明する。
スタッド部14には箱抜き用型枠15を設置して箱抜き部19とし、箱抜き部19以外の部位にコンクリートを打つので、PC緊張時に床版12がスタッド部14に対して相対移動しても、スタッド部14は床版コンクリートと干渉しない。また、閉断面箱桁上に滑り用部材16である硬質ウレタンの板材を設置した上に床版型枠17を設置するので、PC緊張時に床版12が閉断面箱桁11に対して相対移動しても、硬質ウレタン16部位で滑ることができる。その結果、PC緊張時に、床版12と閉断面箱桁11とは、互いにほとんど拘束し合わない。プレストレス導入時における、床版12と箱桁11の互いの拘束は大きくないため、箱桁11の補強も必要でなく、プレストレス導入時に床版コンクリート18に割れが発生する虞もない。PC鋼線13の緊張によって床版12を縮ませた後に、硬質ウレタン16を撤去し、箱抜き部19及び硬質ウレタン部16にモルタルを充填する。
【0012】
つぎに、本発明の第2実施例を、図3〜図5を参照して説明する。
図3〜図5に示すように、本発明の第2実施例の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法は、閉断面箱桁11上に、スタッド14付き鋼板20を全長に敷きわたした後、該鋼板20または閉断面箱桁11に形成した拡大孔21に高力ボルト22を挿通して仮締めする工程と、ついで鋼板20上に従来構造の型枠17を設置する工程と、ついで床版コンクリート18を打設する工程と、コンクリート硬化後従来構造の型枠17を撤去する工程と、ついでPC鋼線13を緊張する工程と、ついでスタッド付き鋼板20の高力ボルト22を本締めする工程と、からなる。PC緊張時には、鋼板20の下面と閉断面箱桁11の上面との間で滑りを生じさせる。
【0013】
鋼板20にはスタッドジベル14が固定される。床版コンクリート18の打設時、コンクリートはスタッドジベル14のまわりを埋める。スタッド14付き鋼板20は、閉断面箱桁11の断面の左右両側部上面に設けられる。
【0014】
型枠17を設置後、コンクリートを打設する前に、鉄筋を配筋する時にPC鋼線の鞘を設置する。PC鋼線13を緊張する工程では、PC鋼線13を鞘に通しているので、PC鋼線13はコンクリートとは独立である。PC鋼線13は、現場で緊張され、コンクリート硬化後のポストテンションとなる。PC鋼線13緊張時には床版12にPC鋼線13緊張方向に圧縮力がかかるが(この時PC鋼線13には引張り力がかかる)、鋼板20の下面と閉断面箱桁11の上面との間で滑りが生じて、床版12は閉断面箱桁11とほとんど拘束しあうことなく縮むことができる。
【0015】
床版12と閉断面箱桁11との間の空間には、床版コンクリートの型枠17と同時施工される埋め殺し型枠23が設置される。埋め殺し型枠23は、通常、発泡スチロールや硬質ウレタンからなり、型枠下部と箱桁上部との間に空間が生じないように施工される。埋め殺し型枠23は、完成後も撤去されず残される。
【0016】
本発明の第2実施例の作用を説明する。
閉断面箱桁11上に、スタッド14付き鋼板20を該鋼板20または閉断面箱桁11に形成した拡大孔21に高力ボルト22を挿通して仮締めするので、PC緊張時に床版12とスタッド付き鋼板20が一体になって閉断面箱桁11に対して相対移動しても、高力ボルト22が拡大孔21内を移動できるため、スタッド付き鋼板20の下面が閉断面箱桁11に対して滑ることができる。その結果、PC緊張時に、床版12と閉断面箱桁11とは、互いにほとんど拘束し合わない。プレストレス導入時における、床版コンクリート18と箱桁11の互いの拘束は大きくないため、箱桁11の補強も必要でなく、プレストレス導入時に床版コンクリート18に割れが発生する虞もない。PC鋼線13の緊張によって床版12を縮ませた後に、高力ボルト22を本締めする。
【0017】
【発明の効果】
請求項1の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法によれば、スタッド部に箱抜き用型枠を設置してコンクリートを打つので、PC緊張時に床版コンクリートがスタッドに対して相対移動しても、スタッド部はコンクリートと干渉せず、また、閉断面箱桁上に滑り用部材を設置した上に床版型枠を設置するので、PC緊張時に床版コンクリートが閉断面箱桁に対して相対移動しても、滑り用部材部位で滑ることができる。その結果、PC緊張時に、床版コンクリートと閉断面箱桁とは、互いに拘束し合わない。プレストレス導入時における、床版コンクリートと箱桁の互いの拘束は大きくないため、箱桁の補強も必要でなく、プレストレス導入時に床版コンクリートに割れが発生する虞もない。
請求項2の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法によれば、閉断面箱桁上に、スタッド付き鋼板を該鋼板に形成した拡大孔に高力ボルトを挿通して仮締めするので、PC緊張時に床版コンクリートとスタッド付き鋼板が一体になって閉断面箱桁に対して相対移動しても、高力ボルトが拡大孔内を移動でき、スタッド付き鋼板の下面が閉断面箱桁に対して滑ることができる。その結果、PC緊張時に、床版コンクリートと閉断面箱桁とは、互いに拘束し合わない。プレストレス導入時における、床版コンクリートと箱桁の互いの拘束は大きくないため、箱桁の補強も必要でなく、プレストレス導入時に床版コンクリートに割れが発生する虞もない。
【図面の簡単な説明】
【図1】 本発明の第1実施例の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法の実施途中の断面図である。
【図2】 図1の平面図である。
【図3】 本発明の第2実施例の閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法の実施途中の断面図である。
【図4】 図3のa部の拡大断面図である。
【図5】 図4の拡大孔の平面図である。
【図6】 閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法の問題を示す断面図である。
【符号の説明】
11 閉断面箱桁
12 床版
13 PC鋼線
14 スタッド部(スタッドジベル)
15 箱抜き用型枠
16 滑り用部材
17 従来構造の型枠
18 床版コンクリート
19 箱抜き部
20 スタッド14付き鋼板
21 拡大孔
22 高力ボルト
23 埋め殺し型枠[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method of a prestressed concrete floor slab with a closed section box girder.
[0002]
[Prior art]
The construction of the prestressed concrete floor slab of the closed section box girder is carried out by transporting the prestressed concrete floor slab manufactured in the factory in advance to the site, and installing and fixing it on the closed section box girder. Therefore, there is no construction example of on-site prestressed concrete slabs with closed section box girders. In the case of on-site casting, as shown in FIG. 6, a formwork for a
[0003]
[Problems to be solved by the invention]
The following problems occur when a prestressed concrete floor slab is installed on a closed section box girder.
(I) When prestress is introduced, the box girder is largely restrained, and a loss of introduction prestress occurs.
( Ii ) Since external force always acts on the box girder body when prestress is introduced, the box girder needs to be reinforced.
(iii) Since there is little deformation of the box girder when prestress is introduced, there is a possibility that cracks may occur in the floor slab concrete due to the tension of PC prestress.
The object of the present invention is that the box girder is not constrained when pre-stress is introduced and does not require reinforcement of the box girder, and there is no risk of cracking in the floor slab concrete when pre-stress is introduced. The purpose is to provide a method for constructing prestressed concrete slabs.
[0004]
[Means for Solving the Problems]
The present invention for achieving the above object is as follows.
(1) A rigid member made of resin or metal in which a box form is placed on the stud on the closed cross-section box girder and a hard urethane plate or a slippery resin is stuck on at least the surface other than the stud A sliding member consisting of
Align the edge of the formwork with the outer side surface of the sliding member and project it laterally outward from the closed cross-section box girder. Install the formwork to be removed (hereinafter referred to as “ formwork removed after setting concrete is hardened”, or “former formwork of conventional structure”, “floor formwork”) ,
Placing floor slab concrete,
And removing the after concrete curing before Symbol type frame,
Nervous the PC steel wire by sliding in sliding member site while allowing relative displacement between the slab concrete and box girder,
Fill the box opening with mortar,
Construction method of on-site prestressed concrete floor slab with closed section box girder consisting of processes.
(2) On the closed section box girder, a steel plate with a stud is temporarily tightened by inserting a high-strength bolt into an enlarged hole expanded in the direction of tension in the PC steel wire formed in the steel plate or the closed section box girder,
Align the edge of the formwork with the outer side surface of the steel plate with studs and project it laterally outward from the closed cross-section box girder. Install the formwork to be removed (hereinafter referred to as “ formwork to be removed after the cast concrete is hardened”, or “conventional formwork”, “floor formwork”) ,
Placing floor slab concrete,
And removing the after concrete curing before Symbol type frame,
Nervous the PC steel wire Hashijiku perpendicular direction while allowing relative displacement between the-out with stud steel plate and box girder by the movement of the high-strength bolts in the expansion hole,
Fully tighten high-strength bolts of steel plates with studs,
Construction method of on-site prestressed concrete floor slab with closed section box girder consisting of processes.
[0005]
In the construction method of on-site prestressed concrete floor slabs for closed section box girders (1) above, the box slabs are placed on the studs and the concrete is cast, so that the floor slab concrete is against the studs during PC tension. Even if it moves relatively, the stud part does not interfere with the concrete, and because the floor slab formwork is installed on the closed cross-section box girder with the sliding member (for example, hard urethane) installed, Even if the plate concrete moves relative to the closed cross-section box girder, it can slide at the sliding member portion. As a result, the floor slab concrete and the closed cross-section box girder are not constrained to each other when the PC is tensioned, and the mutual restraint between the floor slab concrete and the box girder when pre-stress is introduced is not large. There is no need to crack the floor slab concrete when prestress is introduced.
In the construction method of the prestressed concrete floor slab of the closed section box girder of (2) above, a high strength bolt is inserted into the enlarged hole formed in the steel plate on the closed section box girder and temporarily tightened. Therefore, even if the floor slab concrete and the steel plate with studs move together relative to the closed section box girder when the PC is strained, the high strength bolt can move in the enlarged hole, so the bottom surface of the steel plate with studs is closed cross section You can slide against the box girder. As a result, the floor slab concrete and the closed cross-section box girder are not constrained to each other when the PC is tensioned, and the mutual restraint between the floor slab concrete and the box girder when pre-stress is introduced is not large. There is no need to crack the floor slab concrete when prestress is introduced.
[0006]
DETAILED DESCRIPTION OF THE INVENTION
1 and 2 show a construction method of a prestressed concrete floor slab of a closed section box girder according to a first embodiment of the present invention. FIGS. 3 to 5 show a closed section box according to a second embodiment of the present invention. It shows the construction method of prestressed concrete slabs for on-site girders.
[0007]
First, a first embodiment of the present invention will be described with reference to FIGS.
As shown in FIGS. 1 and 2, the construction method of the prestressed concrete floor slab of the closed section box girder according to the first embodiment of the present invention is such that the
[0008]
The
[0009]
After installing the
[0010]
In the space between the
[0011]
The operation of the first embodiment of the present invention will be described.
Since the
[0012]
Next, a second embodiment of the present invention will be described with reference to FIGS.
As shown in FIG. 3 to FIG. 5, the construction method of the in-situ prestressed concrete floor slab of the closed section box girder of the second embodiment of the present invention is that the
[0013]
A
[0014]
After placing the
[0015]
In the space between the
[0016]
The operation of the second embodiment of the present invention will be described.
Since the
[0017]
【The invention's effect】
According to the construction method of the prestressed concrete floor slab of the closed cross-section box girder of claim 1, the box slab is placed on the stud and the concrete is cast. Even if it moves relatively, the stud part does not interfere with the concrete, and the floor slab form is installed on the closed section box girder and the floor slab form is installed. Even if it moves relative to the girder, it can slide at the sliding member portion. As a result, the floor slab concrete and the closed cross-section box girder are not constrained to each other during PC tension. Since the restraint between the floor slab concrete and the box girder is not large when pre-stress is introduced, there is no need to reinforce the box girder, and there is no possibility of cracking in the floor slab concrete when pre-stress is introduced.
According to the construction method of the prestressed concrete floor slab of the closed section box girder of claim 2, a high strength bolt is inserted into the enlarged hole formed in the steel plate with the stud on the closed section box girder and temporarily tightened. Therefore, even if the floor slab concrete and the steel plate with studs move together relative to the closed section box girder when the PC is strained, the high strength bolt can move in the enlarged hole, and the bottom surface of the steel plate with studs is closed cross section You can slide against the box girder. As a result, the floor slab concrete and the closed cross-section box girder are not constrained to each other during PC tension. Since the restraint between the floor slab concrete and the box girder is not large when pre-stress is introduced, there is no need to reinforce the box girder, and there is no possibility of cracking in the floor slab concrete when pre-stress is introduced.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a cross-sectional view of a first embodiment of the present invention in the middle of a construction method for a spot-cast prestressed concrete floor slab of a closed cross-section box girder.
FIG. 2 is a plan view of FIG.
FIG. 3 is a cross-sectional view of the second embodiment of the present invention in the middle of the construction method for a prestressed concrete floor slab of a closed cross-section box girder.
4 is an enlarged cross-sectional view of a part a in FIG. 3;
FIG. 5 is a plan view of the enlarged hole of FIG. 4;
FIG. 6 is a cross-sectional view showing a problem of a construction method of a spot-cast prestressed concrete floor slab with a closed cross-section box girder.
[Explanation of symbols]
11 Closed
15 Forming box for
Claims (2)
前記滑り用部材の外側側面に型枠端部を合わせて前記閉断面箱桁から横方向に外側に張り出し、コンクリート打設時には床版コンクリートの下面と側面の形状を出し、打設コンクリート硬化後には撤去される型枠を設置し、
床版コンクリートを打設し、
コンクリート硬化後前記型枠を撤去し、
滑り用部材部位での滑りにより床版コンクリートと箱桁との間の相対変位を許容しつつPC鋼線を緊張し、
箱抜き部にモルタルを充填する、
工程からなる、閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法。A slip made of a resin or metal hard member with a box made of boxing on the stud on the closed section box girder and a hard urethane plate or non-slip resin affixed to the surface of the stud other than the stud. Install the parts for
Align the edge of the formwork with the outer side surface of the sliding member and project it laterally outward from the closed cross-section box girder. Set up the formwork to be removed ,
Placing floor slab concrete,
And removing the after concrete curing before Symbol type frame,
Nervous the PC steel wire by sliding in sliding member site while allowing relative displacement between the slab concrete and box girder,
Fill the box opening with mortar,
Construction method of on-site prestressed concrete floor slab with closed section box girder consisting of processes.
前記スタッド付き鋼板の外側側面に型枠端部を合わせて前記閉断面箱桁から横方向に外側に張り出し、コンクリート打設時には床版コンクリートの下面と側面の形状を出し、打設コンクリート硬化後には撤去される型枠を設置し、
床版コンクリートを打設し、
コンクリート硬化後前記型枠を撤去し、
拡大孔内での高力ボルトの移動によりスタッド付き鋼板と箱桁との間の相対変位を許容しつつ橋軸直角方向にPC鋼線を緊張し、
スタッド付き鋼板の高力ボルトを本締めする、
工程からなる、閉断面箱桁の現場打ちプレストレストコンクリート床版の施工法。On the closed cross-section box girder, a steel plate with a stud is temporarily tightened by inserting a high-strength bolt into an enlarged hole expanded in the direction of tension of the PC steel wire formed on the steel plate or the closed cross-section box girder,
Align the edge of the formwork with the outer side surface of the steel plate with studs and project it laterally outward from the closed cross-section box girder. Set up the formwork to be removed ,
Placing floor slab concrete,
And removing the after concrete curing before Symbol type frame,
Nervous the PC steel wire Hashijiku perpendicular direction while allowing relative displacement between the-out with stud steel plate and box girder by the movement of the high-strength bolts in the expansion hole,
Fully tighten high-strength bolts of steel plates with studs,
Construction method of on-site prestressed concrete floor slab with closed section box girder consisting of processes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20877599A JP4127933B2 (en) | 1999-07-23 | 1999-07-23 | Construction method of prestressed concrete floor slab with closed section box girder. |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20877599A JP4127933B2 (en) | 1999-07-23 | 1999-07-23 | Construction method of prestressed concrete floor slab with closed section box girder. |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001032216A JP2001032216A (en) | 2001-02-06 |
JP4127933B2 true JP4127933B2 (en) | 2008-07-30 |
Family
ID=16561900
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP20877599A Expired - Fee Related JP4127933B2 (en) | 1999-07-23 | 1999-07-23 | Construction method of prestressed concrete floor slab with closed section box girder. |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4127933B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103233425A (en) * | 2013-04-20 | 2013-08-07 | 中铁十六局集团第四工程有限公司 | Method for observing support cast-in-place beam preloading by utilizing reflector |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20030094767A (en) * | 2002-06-07 | 2003-12-18 | 심창수 | Composite Bridge having Easy Replacing Shear Connection Structure and Constructing Method thereof |
KR100519234B1 (en) * | 2002-11-22 | 2005-10-06 | 한국건설기술연구원 | joint structure of precast bridge slab and girder and bridge construction method using the same |
KR100601100B1 (en) | 2004-12-21 | 2006-07-19 | 재단법인 포항산업과학연구원 | Personal rapid transit bridge with steel tubes |
JP2007032212A (en) * | 2005-07-29 | 2007-02-08 | Taisei Corp | Ribbed floor slab and on-water structure |
JP4845039B2 (en) * | 2007-03-07 | 2011-12-28 | 三井造船株式会社 | RC slab minority main girder bridge |
JP4977110B2 (en) * | 2008-10-24 | 2012-07-18 | 大成建設株式会社 | Composite digit structure and composite digit construction method |
CN106808564B (en) * | 2017-04-07 | 2023-05-26 | 中铁十七局集团第三工程有限公司 | Three-word buckle type box girder end sealing template and box girder end sealing method |
CN108004904B (en) * | 2017-12-12 | 2019-04-12 | 石伟东 | A kind of highway prefabricated T-shaped beam of the road traffic convenient for draining |
CN112853985B (en) * | 2021-01-13 | 2022-05-20 | 中建五局土木工程有限公司 | Translation and traction construction method for PC narrow and high track beam on cast-in-place beam |
CN115075114B (en) * | 2022-07-20 | 2024-05-24 | 东南大学 | Transverse widening connection structure of longitudinal deformable concrete continuous box girder and construction method |
-
1999
- 1999-07-23 JP JP20877599A patent/JP4127933B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103233425A (en) * | 2013-04-20 | 2013-08-07 | 中铁十六局集团第四工程有限公司 | Method for observing support cast-in-place beam preloading by utilizing reflector |
CN103233425B (en) * | 2013-04-20 | 2015-07-22 | 中铁十六局集团第四工程有限公司 | Method for observing support cast-in-place beam preloading by utilizing reflector |
Also Published As
Publication number | Publication date |
---|---|
JP2001032216A (en) | 2001-02-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100696441B1 (en) | Precast Prestressed reinforced concrete bottom plate, bridge having the same, and construction method for the bridge | |
JP4127933B2 (en) | Construction method of prestressed concrete floor slab with closed section box girder. | |
KR101170922B1 (en) | The rahmen bridge construction technique for which tendon and the connection support stand was used | |
KR20010045640A (en) | Precast Reinforced Concrete Slab, Composite Continuous Bridge Having Such Slab, and Constructing Method thereof | |
JP2008266910A (en) | Projection structure of anchorage or deviator of tendon, and construction method therefor | |
KR100570231B1 (en) | Structure section extension equipment and an extension method of construction using ps steel materials and a steel plate | |
KR102059435B1 (en) | Precast slab beam and rahmen structure construction method therewith | |
JP5536988B2 (en) | Construction method of steel plate concrete structure | |
KR100555046B1 (en) | A tunnel structure and method for constructing of it | |
JP7186670B2 (en) | Concrete floor slab repair method | |
JP2528435B2 (en) | Prestressing reinforcement structure for structures with girders installed in parallel | |
JP2003129676A (en) | Method of reinforcing concrete frame | |
KR100694763B1 (en) | Construction methods of underground structure adopting concrete-composite crossbeam | |
JP3713192B2 (en) | Foundation structure with anchor bolt and its construction method | |
KR100403505B1 (en) | The Method of Reinforcing A Steel Girder Beam type Bridge and The Structure thereof | |
JPH11181809A (en) | Construction of large scale prestressed concrete culvert | |
JP2020133260A (en) | Concrete slab joint structure and concrete slab joining method | |
KR101208088B1 (en) | rifling beam for prestressing bridge and device for manufacturing thereof | |
KR20130103970A (en) | Concrete deck slab assembly, method for making the same and temporary bridge using the same | |
KR101278151B1 (en) | Prestressed precast segment rahmen-bridge | |
JP3275017B2 (en) | Method of manufacturing caisson using precast member | |
JP7455931B1 (en) | Precast board manufacturing method and precast board | |
JP7372506B2 (en) | Concrete slab and concrete slab connection structure | |
JPH10184028A (en) | Earthquake-resisting reinforcing structure of building | |
JP2719991B2 (en) | Construction method of slope protection structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050428 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070402 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070522 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070719 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071204 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080201 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080513 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080513 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110523 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
LAPS | Cancellation because of no payment of annual fees |