JP4072826B2 - Rail suspension girder and its erection method - Google Patents

Rail suspension girder and its erection method Download PDF

Info

Publication number
JP4072826B2
JP4072826B2 JP2003126957A JP2003126957A JP4072826B2 JP 4072826 B2 JP4072826 B2 JP 4072826B2 JP 2003126957 A JP2003126957 A JP 2003126957A JP 2003126957 A JP2003126957 A JP 2003126957A JP 4072826 B2 JP4072826 B2 JP 4072826B2
Authority
JP
Japan
Prior art keywords
girder
track
rail
rails
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003126957A
Other languages
Japanese (ja)
Other versions
JP2004332285A (en
Inventor
俊博 飯田
昭宏 村松
文雄 佐藤
一民 畑
登 中谷
忠 上部
守 遠藤
Original Assignee
大日本土木株式会社
株式会社交通建設
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 大日本土木株式会社, 株式会社交通建設 filed Critical 大日本土木株式会社
Priority to JP2003126957A priority Critical patent/JP4072826B2/en
Publication of JP2004332285A publication Critical patent/JP2004332285A/en
Application granted granted Critical
Publication of JP4072826B2 publication Critical patent/JP4072826B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、線路下構造物の構築など軌道の下で掘削等の工事を行う場合に、軌道を支持する鉄道工事桁とその架設方法に関する。
【0002】
【従来の技術】
列車を走行させつつ軌道の下方に線路下構造物を構築する場合、掘削により線路下が空洞となっても線路を強固に支持し、列車が当該区間を安全に走行できるようにする鉄道工事桁が用いられる。この工事桁は、軌道の両側に配置した2本の主桁に、既設軌道の枕木の下にU形断面の鋼製横桁を配置し、この横桁の凹部底面で枕木を支持した受桁を接続固定することで構成される。一般に、軌道枕木にはPC枕木が用いられているが、重量が重く、横桁(枕木受け桁)の挿入作業が大変になることから、PC枕木を木製枕木に置き換えるのが通例である。
【0003】
この工事桁では、これら主桁、および受け桁が各々鋼板を溶接して製作する構造であり、溶接ひずみによる製作精度のバラツキや製作コストが高価になるといった問題があった。これらを解決するために、主桁や受け桁に形鋼を用いることで溶接不要とし、コストを削減できる方法がある。(例えば、特許文献1参照)。
【0004】
【特許文献1】
特開2001−214405号公報
【0005】
【発明が解決しようとする課題】
しかし、この架設方法は、主桁を収納する溝状凹部を軌道の側方に掘削して道床土留め工とともに形成し、主桁を配して予め用意した工事桁用受け台に据え付け固定する。次に、枕木の下方および側方のバラスト砕石を除去して鋼製の受け桁を枕木の下方に挿入して軌道を支持し、主桁に接続固定するものであるが、バラスト砕石の除去範囲が主桁間にわたるとともに重い受け桁の設置が人力に頼らざるを得ないため、限られた列車間合いの時間内での作業は極めて煩雑であり、この工事桁の架設に日数が長くかかるといった不具合があった。
【0006】
本発明は、上述のような問題を解決するためになされたもので、架設期間を短縮し、ひいては建設コストを低減できる工事桁およびその架設方法を提供することを目的とする。
【0007】
【課題を解決するための手段】
上記目的を達成するために、本発明による鉄道工事桁は、軌道の下を開削する場合に前記軌道を支持する鉄道工事桁において、左右のレールの下で前記レールと交差するようにそれぞれ配置され、前記各レールをそれぞれ支持する受桁と、前記各レールの両側に前記レールに沿ってそれぞれ配置され、前記受桁を吊り支承する各一対の縦桁と、前記縦桁の下を前記縦桁と交差するように前記左右のレールを横切って配置され、前記縦桁を支持する横桁と、前記軌道の両側に配置され、前記横桁の両端を支持する一対の主桁と、を備える。
【0008】
また、本発明による鉄道工事桁の架設方法は、軌道の下を開削する場合に前記軌道を支持する鉄道工事桁を架設する方法において、枕木間のレール下を開削し、受桁を設置する工程と、所定の間隔をもって、枕木間のレール下を前記軌道を渡って開削し、横桁を設置する工程と、縦桁を前記レールの両側に前記レールに沿って配置し、前記縦桁を前記受桁および前記横桁に締結固定する工程と、前記軌道の両側に前記軌道に沿って主桁を配置する工程と、前記横桁を前記主桁に載せて接続固定する工程と、を備える。
【0009】
【発明の効果】
第1の発明によれば、受桁の設置は、受桁が左右それぞれのレールを支持すべく短尺としているのでバラスト砕石の除去範囲は短くてよく、また重量も軽いので極めて短時間の内に作業を終えることができる。また、枕木2〜3本程度の軌道下の掘削をする小規模工事では、縦桁が軌道を支持するので主桁が不要となる。さらに、既存の枕木はそのまま存置できるので、軌道下掘削工事の終了後の復旧が容易となる。
【0010】
第2の発明によれば、横桁は数丁おきの枕木間に配置すればよいので、すべての枕木間を左右のレール下を横切って開削する必要がなくなり、作業を短縮化できる。
【0011】
第3の発明によれば、主桁設置に伴う道床土留め工が不要となり、架設工期の短縮および架設費の削減に寄与する。この場合、前記受桁および前記横桁の設置が、列車間合いに応じて工事桁架設範囲の任意の箇所で行われることが好ましいが、それにより、限られた列車間合いを有効に活用でき、作業の効率化を図ることができる。
【0012】
【発明の実施の形態】
図1を参照し、本発明による鉄道工事桁の構造を説明する。
【0013】
本工事桁は、レール1の下に、かつPC枕木8とPC枕木8との間にレール1と交差するように配置された受桁3と、レール1に沿って配置され、受桁3の上部に固定されて受桁3を吊り支承する縦桁5と、レール1の下に、かつPC枕木8とPC枕木8との間にPC枕木8に沿って配置され、縦桁5を下から支持する横桁2と、レール1の外側にレール1に沿って配置され、横桁2を支持する主桁4と、から構成される。
【0014】
鋼材からなる主桁4は架台11を有し、軌道下構造物開削部の両側に軌道に沿って設置される。両側の主桁4との間には鋼材からなる横桁2が渡され、両方の主桁4の架台11上で支持される。この実施形態では、PC枕木8の4丁分の間隔で横桁2が1つ設置されるが、その他の間隔で横桁2を設置してもよい。
【0015】
各横桁2は、その上に、2本のレール1と、各レール1に沿って挟むように延びる一対の縦桁5の2組の縦桁5を支持する。縦桁5は鋼材からなり、絶縁材7を介して横桁2に締結ボルト6で固定される。同様に、レール1も絶縁材10を介して横桁2に固定具9で固定される。
【0016】
横桁2が配されないPC枕木8の間には、各レール1の下に、かつ、レール1と交差するように短尺の受桁3が配置される。受桁3は一本のレール1と2本の縦桁5とを固定するのに必要な幅を有する鋼材からなり、その両端部の上面が各縦桁5と当接するように縦桁5に締結ボルト6により固定される。受桁3は絶縁材10を介して固定具9によりレール1と固定される。
【0017】
この構成により、主桁4は横桁2を支持し、横桁2は各レール1の両側に配置した各一対の縦桁5を介して各レール1の下側に配置した受桁3を支持し、左右の受桁3はそれぞれ左右のレール1を下から支承する。これにより、レール1のたわみを防止し、レール1を十分な強度をもって支持する。したがって、軌道を破線することなく、軌道下を開削することができる。
【0018】
次に、図2から図4を参照して、本工事桁の架設方法を説明する。各図中には横断図および側面図を示す。
【0019】
▲1▼は本工事桁架設工事前のPC枕木8とレール1を示す。
【0020】
先ず、▲2▼に示すように、横桁2を配置する箇所の軌道下を左右のレール1の下面を横切って開削し、開削部に横桁2を設置し、横桁2とレール1を固定具9で固定する。
【0021】
次に、▲3▼に示すように、受桁3を配置する箇所のそれぞれのレール1の下を部分的に開削し、開削部に一対の受桁3を軌道の両側よりそれぞれ挿入し、受桁3とレール1を固定具9で固定する。受桁3は短尺なため、左右のレール1の間を横切って開削する必要はなく左右のレール1の間のバラスト砕石を残したまま工事ができる。本実施形態では、受桁3にレール外側の縦桁5を締結固定した後にレール1下の開削部に受桁3を設置するが、受桁3を設置後に外側の縦桁5を取り付けてもよい。
【0022】
次に、▲4▼に示すように、レール内側の縦桁5をレール1に沿って配置し、これを受桁3に締結固定する。すなわち、レール1と平行な2本の縦桁5によって短い受桁3を吊り下げ支持する。
【0023】
最後に、▲5▼に示すように、主桁4を軌道両側に設置し、横桁2を主桁4の架台11の上に載せて固定する。
【0024】
このようにして主桁4によって軌道を支持したならば、列車の走行は全く支障なく行われるので、軌道下の掘削工事は列車の走行と無関係に自由に実施可能となる。
【0025】
以下に、本工事桁による効果を列挙する。
【0026】
本工事桁によりPC枕木を十分な強度で支えることができ、工事桁架設中でも列車の無徐行運転が可能である。
【0027】
従来技術のPC枕木抱き込み工事桁の架設時に必要であった道床土留め工および既存PC枕木と横桁の設置替え作業が不要となり、PC枕木はレール1に取り付けたままでよく、架設工期の短縮および架設費の削減に寄与する。
【0028】
受桁3および横桁2の設置を、列車間合いに応じて工事桁架設範囲の任意の箇所で行われる場合、限られた列車間合いを有効に活用でき、作業の効率化を図ることができる。
【0029】
作業の分割化が容易であり、短時間の間合い作業においても施工可能となる。
【0030】
受桁3の設置は、受桁3が左右それぞれのレール1を支持すべく短尺としているのでバラスト砕石の除去範囲は短くてよく、また重量も軽いので極めて短時間の内に作業を終えることができる。
【0031】
枕木2〜3本程度の軌道下の掘削をする小規模工事では、縦桁5が軌道を支持するので主桁4が不要となり、簡易な施工が可能となる。
【0032】
既存の枕木はそのまま存置できるので、軌道下掘削工事の終了後の復旧が容易となる。
【0033】
したがって、工事桁架設・撤去に伴う作業が縮減され、線閉時間の制約が厳しい条件下でも工事桁が施工可能となる。
【0034】
本発明を、構造的と方法的特徴に関してある程度特定的な言葉で説明したが、本明細書に開示した手段は本発明を実施する好ましい形態を含むものであり、本発明はこれら図示し記載された特定の特徴に制限されない。したがって、本発明は、均等の原則に従って適切に解釈される特許請求の範囲に記載された範囲内におけるいかなる形態または変更についても含むものである。
【図面の簡単な説明】
【図1】本発明による鉄道工事桁の概略構成図である。Aは線路方向から見た工事桁の断面図であり、Bは上から見た工事桁の断面図であり、Cは横方向から見た工事桁の断面図である。
【図2】本発明による工事桁架設方法を説明する図である。
【図3】本発明による工事桁架設方法を説明する図である。
【図4】本発明による工事桁架設方法を説明する図である。
【符号の説明】
1 レール
2 横桁
3 受桁
4 主桁
5 縦桁
8 枕木
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a railway work girder that supports a track and a method of erection thereof when performing construction such as excavation under the track, such as construction of a structure under a track.
[0002]
[Prior art]
When constructing the structure under the track under the track while running the train, the railway construction girder that firmly supports the track even if the underside of the track becomes hollow due to excavation and allows the train to travel safely in the section Is used. This construction girder has two main girders arranged on both sides of the track, U steel cross beams placed under the sleepers of the existing track, and a support beam that supports the sleepers at the bottom of the recesses of the cross beams. Consists of fixed connection. Generally, a PC sleeper is used as the track sleeper. However, the weight of the track sleeper is heavy, and it is difficult to insert a horizontal girder (sleeper receiving girder). Therefore, it is usual to replace the PC sleeper with a wooden sleeper.
[0003]
This construction girder has a structure in which the main girder and the receiving girder are each manufactured by welding steel plates, and there is a problem that manufacturing accuracy varies due to welding distortion and manufacturing cost becomes expensive. In order to solve these problems, there is a method that eliminates the need for welding by using shaped steel for the main girder and the receiving girder, thereby reducing the cost. (For example, refer to Patent Document 1).
[0004]
[Patent Document 1]
JP-A-2001-214405 gazette
[Problems to be solved by the invention]
However, in this construction method, a groove-like recess for storing the main girder is excavated to the side of the track and formed together with the earth retaining work, and the main girder is arranged and fixed on a work girder cradle prepared in advance. . Next, the ballast crushed stone at the bottom and side of the sleeper is removed, and a steel receiving girder is inserted below the sleeper to support the track and to be fixedly connected to the main girder. However, the work within the limited train interval is extremely complicated and the construction of the construction girder takes a long time. was there.
[0006]
The present invention has been made to solve the above-described problems, and an object of the present invention is to provide a construction girder that can shorten the erection period and thus reduce the construction cost, and a erection method therefor.
[0007]
[Means for Solving the Problems]
In order to achieve the above object, the railway construction girder according to the present invention is arranged so as to cross the rail under the left and right rails in the railway construction girder that supports the track when excavating under the track. A receiving girder for supporting each of the rails, a pair of vertical beams arranged on both sides of the rails along the rails for supporting the receiving girder, and the vertical beams under the vertical girder And a transverse girder that crosses the left and right rails to support the stringer and a pair of main girders that are arranged on both sides of the track and that support both ends of the stringer.
[0008]
Further, the construction method of the railway construction girder according to the present invention is a method of constructing the railway construction girder that supports the track when the undercut of the track is opened. And a step of excavating under the rail between the sleepers across the track with a predetermined interval, installing a cross beam, and placing the vertical beam along the rail on both sides of the rail, the vertical beam A step of fastening and fixing to the receiving beam and the cross beam, a step of arranging a main beam along the track on both sides of the track, and a step of connecting and fixing the cross beam on the main beam.
[0009]
【The invention's effect】
According to the first invention, since the girder is set to be short so as to support the left and right rails, the removal range of the ballast crushed stone may be short, and the weight is light so that it is very short. You can finish the work. Moreover, in the small-scale construction which excavates under the track of about 2 to 3 sleepers, the main beam becomes unnecessary because the vertical beam supports the track. Furthermore, since existing sleepers can be left as they are, it is easy to recover after completion of under-orbit excavation work.
[0010]
According to the second invention, it is only necessary to arrange the cross beams between every few sleepers, so that it is not necessary to cut all the sleepers across the left and right rails, and the work can be shortened.
[0011]
According to the third aspect of the invention, the roadbed earth retaining work associated with the installation of the main girder is unnecessary, which contributes to shortening the construction period and reducing the construction cost. In this case, it is preferable that the receiving girder and the horizontal girder are installed at an arbitrary place in the construction girder erection range according to the space between trains. Can be made more efficient.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
With reference to FIG. 1, the structure of a railway construction girder according to the present invention will be described.
[0013]
This construction girder is arranged below the rail 1 and between the PC sleepers 8 and 8 so as to intersect the rail 1, and along the rail 1, A vertical girder 5 that is fixed to the upper part and suspends and supports the receiving girder 3, and is arranged under the rail 1 and between the PC sleeper 8 and the PC sleeper 8 along the PC sleeper 8. The cross beam 2 is supported, and the main beam 4 is arranged outside the rail 1 along the rail 1 and supports the cross beam 2.
[0014]
The main girder 4 made of steel has a gantry 11 and is installed along the track on both sides of the structure under the track. Between the main girders 4 on both sides, a cross beam 2 made of steel is passed and supported on the gantry 11 of both main girders 4. In this embodiment, one cross beam 2 is installed at intervals of four of the PC sleepers 8, but the cross beams 2 may be installed at other intervals.
[0015]
Each cross beam 2 supports two sets of vertical beams 5 including two rails 1 and a pair of vertical beams 5 extending so as to be sandwiched along each rail 1. The vertical girder 5 is made of steel and is fixed to the horizontal girder 2 with fastening bolts 6 via an insulating material 7. Similarly, the rail 1 is also fixed to the cross beam 2 by the fixing tool 9 through the insulating material 10.
[0016]
Between the PC sleepers 8 where the horizontal beam 2 is not arranged, the short receiving beam 3 is arranged under each rail 1 and so as to intersect with the rail 1. The receiving girder 3 is made of a steel material having a width necessary for fixing one rail 1 and two stringers 5, and the stringers 5 are arranged so that the upper surfaces of both ends abut each stringer 5. It is fixed by the fastening bolt 6. The receiving girder 3 is fixed to the rail 1 by a fixing tool 9 through an insulating material 10.
[0017]
With this configuration, the main beam 4 supports the horizontal beam 2, and the horizontal beam 2 supports the receiving beam 3 disposed below each rail 1 via each pair of vertical beams 5 disposed on both sides of each rail 1. The left and right receiving girders 3 support the left and right rails 1 from below. Thereby, the deflection of the rail 1 is prevented and the rail 1 is supported with sufficient strength. Therefore, without a line fracture trajectories can be digging the track under.
[0018]
Next, the construction method of the construction girder will be described with reference to FIGS. Each figure shows a cross-sectional view and a side view.
[0019]
(1) shows PC sleepers 8 and rails 1 before the construction of the girder.
[0020]
First, as shown in (2), under the track where the cross beam 2 is to be placed, the lower beam of the left and right rails 1 is cut open, the cross beam 2 is installed in the cut portion, and the cross beam 2 and the rail 1 are connected. Fix with the fixture 9.
[0021]
Next, as shown in (3), the lower part of each rail 1 where the receiving girder 3 is arranged is partially excavated, and a pair of receiving girders 3 are inserted into the excavated part from both sides of the track, respectively. The girder 3 and the rail 1 are fixed with a fixing tool 9. Since the girder 3 is short, it is not necessary to cut across between the left and right rails 1, and construction can be performed while leaving the ballast crushed stone between the left and right rails 1. In this embodiment, after the stringer 5 outside the rail is fastened and fixed to the beam 3, the beam 3 is installed in the cut-out portion below the rail 1. Good.
[0022]
Next, as shown in (4), the vertical girder 5 on the inner side of the rail is disposed along the rail 1, and this is fastened and fixed to the receiving girder 3. That is, the short receiving beam 3 is suspended and supported by two vertical beams 5 parallel to the rail 1.
[0023]
Finally, as shown in (5), the main girder 4 is installed on both sides of the track, and the horizontal girder 2 is placed on the frame 11 of the main girder 4 and fixed.
[0024]
If the track is supported by the main girder 4 in this way, the train travels without any trouble, so excavation work under the track can be performed freely regardless of the train travel.
[0025]
The effects of this construction girder are listed below.
[0026]
This construction girder can support PC sleepers with sufficient strength, and trains can be operated at low speed even while the construction girder is installed.
[0027]
It is not necessary to carry out the earth retaining work and the installation work of the existing PC sleepers and horizontal girders, which was necessary when laying the PC sleeper embedding girders of the prior art. And contributes to the reduction of construction costs.
[0028]
When the installation of the receiving girder 3 and the horizontal girder 2 is performed at an arbitrary position in the construction girder erection range according to the space between trains, the limited space between trains can be used effectively, and work efficiency can be improved.
[0029]
It is easy to divide the work, and the work can be performed even for a short time.
[0030]
Installation of the girder 3 is short so that the girder 3 can support the left and right rails 1, so the removal range of the ballast crushed stone may be short and the weight is light, so the work can be completed within a very short time. it can.
[0031]
In the small-scale construction work for the excavation under the orbit of two or three about sleepers, because the girders 5 to support the orbit main girder 4 is not required, it is possible to simple facilities Engineering.
[0032]
Since existing sleepers can be kept as they are, it is easy to recover after completion of under-orbit excavation work.
[0033]
Therefore, the work accompanying the construction girder construction / removal is reduced, and the construction girder can be constructed even under severe conditions of line closing time.
[0034]
Although the present invention has been described in certain terms with regard to structural and methodological features, the means disclosed herein include preferred forms of practicing the invention, and the invention is illustrated and described. It is not limited to specific features. Accordingly, the present invention includes any forms or modifications within the scope of the claims as appropriately interpreted in accordance with the principle of equality.
[Brief description of the drawings]
FIG. 1 is a schematic configuration diagram of a railway construction girder according to the present invention. A is a cross-sectional view of the work girder as viewed from the track direction, B is a cross-sectional view of the work girder as viewed from above, and C is a cross-sectional view of the work girder as viewed from the lateral direction.
FIG. 2 is a diagram for explaining a construction girder construction method according to the present invention.
FIG. 3 is a diagram for explaining a construction girder construction method according to the present invention.
FIG. 4 is a diagram for explaining a construction beam erection method according to the present invention.
[Explanation of symbols]
1 rail 2 horizontal girder 3 receiving girder 4 main girder 5 vertical girder 8 sleepers

Claims (3)

軌道の下を開削する場合に前記軌道を支持する鉄道工事桁において、
左右のレールの下で前記レールと交差するようにそれぞれ配置され、前記各レールをそれぞれ支持する受桁と、
前記各レールの両側に前記レールに沿ってそれぞれ配置され、前記受桁を吊り支承する各一対の縦桁と、
前記縦桁の下を前記縦桁と交差するように前記左右のレールを横切って配置され、前記縦桁を支持する横桁と、
前記軌道の両側に配置され、前記横桁の両端を支持する一対の主桁と、
を備えることを特徴とする鉄道工事桁。
In the railway girder that supports the track when excavating under the track,
Receiving girders that are respectively arranged to cross the rails under the left and right rails and support the rails;
A pair of vertical beams arranged on both sides of the rails along the rails and supporting the receiving beams;
A transverse beam arranged across the left and right rails so as to cross the longitudinal beam under the longitudinal beam, and supporting the longitudinal beam,
A pair of main beams arranged on both sides of the track and supporting both ends of the cross beam;
Railway construction girder characterized by comprising.
前記受桁は前記左右のレールを支持する各枕木の間にそれぞれ配置され、前記横桁は複数の枕木の間に配置されることを特徴とする請求項1に記載の鉄道工事桁。2. The railway construction girder according to claim 1, wherein the receiving girder is disposed between sleepers that support the left and right rails, and the horizontal girder is disposed between a plurality of sleepers. 軌道の下を開削する場合に前記軌道を支持する鉄道工事桁を架設する方法において、
枕木間のレール下を開削し、受桁を設置する工程と、
所定の間隔をもって、枕木間のレール下を前記軌道を渡って開削し、横桁を設置する工程と、
縦桁を前記レールの両側に前記レールに沿って配置し、前記縦桁を前記受桁および前記横桁に締結固定する工程と、
前記軌道の両側に前記軌道に沿って主桁を配置する工程と、
前記横桁を前記主桁に載せて接続固定する工程と、
を備えることを特徴とする鉄道工事桁の架設方法。
In the method of constructing a railroad work girder that supports the track when excavating under the track,
Excavating under the rails between the sleepers and installing a receiving girder;
A step of cutting under the rail between the sleepers across the track with a predetermined interval, and installing a cross beam;
Arranging a stringer along the rail on both sides of the rail, and fastening the stringer to the receiving beam and the cross beam;
Placing main girders along the track on both sides of the track;
Mounting and fixing the horizontal beam on the main beam;
A construction method of a railway construction girder characterized by comprising:
JP2003126957A 2003-05-02 2003-05-02 Rail suspension girder and its erection method Expired - Fee Related JP4072826B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003126957A JP4072826B2 (en) 2003-05-02 2003-05-02 Rail suspension girder and its erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003126957A JP4072826B2 (en) 2003-05-02 2003-05-02 Rail suspension girder and its erection method

Publications (2)

Publication Number Publication Date
JP2004332285A JP2004332285A (en) 2004-11-25
JP4072826B2 true JP4072826B2 (en) 2008-04-09

Family

ID=33503689

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003126957A Expired - Fee Related JP4072826B2 (en) 2003-05-02 2003-05-02 Rail suspension girder and its erection method

Country Status (1)

Country Link
JP (1) JP4072826B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113897822A (en) * 2021-11-13 2022-01-07 大同市陆宏铁路建设有限公司 Transverse and longitudinal moving device for construction based on D-shaped temporary beam and construction method thereof

Also Published As

Publication number Publication date
JP2004332285A (en) 2004-11-25

Similar Documents

Publication Publication Date Title
CN106049209B (en) A kind of interim rail support meanss changed for railway ballastless track supporting layer
CN203546524U (en) Medium-and-low-speed magnetically-suspended traffic integral-type road-bed track structure
JP3728657B2 (en) Railway bridge replacement method
CN106192620B (en) A kind of railway ballastless track supporting layer and substructure change method
CN103485244A (en) Moderate-low speed magnetic levitation traffic integration type track bed track structure
CN108149577B (en) A kind of steel bracket system and its installation method
CN113931091A (en) Construction method for dismantling wide-width continuous beam of business line of overpass railway
JP4540632B2 (en) Erection girder
KR101399839B1 (en) Transition track structure of railway bridge deck end and Construction method
JP4072826B2 (en) Rail suspension girder and its erection method
KR101669437B1 (en) Girder having Embedded Sleeper, and Constructing Method thereof
JP4136959B2 (en) "How to build underground structures and installation girder"
KR100881598B1 (en) Method for construction of track for linear induction motor panel in linear induction motor
KR100759923B1 (en) Low height and longspan girder for a railway
JP4858850B2 (en) Installation method for vibration-proof track of existing track
CN110219250A (en) The continuous combined overhead beam of multilayer
CN205893837U (en) A interim rail strutting arrangement that is used for railway ballastless track supporting layer to tear open trading
JP3746479B2 (en) Railway construction girder and its installation method
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
KR101211693B1 (en) Substructure construction method for existing railway using auger and moving apparatus
JP3788774B2 (en) Railroad track structure and railroad track construction method
KR101653559B1 (en) Method of repairing railway
CN217052888U (en) Railway temporary beam structure for box culvert to pass existing railway downwards
JP3791719B2 (en) Directly connected track construction method and track structure using construction girders
JP2001081726A (en) Method and structure for re-laying steel floor slab of concrete floor slab bridge

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050727

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20050727

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20050727

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050906

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060310

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071127

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080108

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110201

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4072826

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140201

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees