JP4039978B2 - Construction method of concrete lining of shaft wall - Google Patents
Construction method of concrete lining of shaft wall Download PDFInfo
- Publication number
- JP4039978B2 JP4039978B2 JP2003136811A JP2003136811A JP4039978B2 JP 4039978 B2 JP4039978 B2 JP 4039978B2 JP 2003136811 A JP2003136811 A JP 2003136811A JP 2003136811 A JP2003136811 A JP 2003136811A JP 4039978 B2 JP4039978 B2 JP 4039978B2
- Authority
- JP
- Japan
- Prior art keywords
- excavation
- concrete
- shaft
- concrete lining
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は立坑掘削機によって地表側から地下の深層部にまで立坑を掘削する際に、その立坑掘削壁面に施工されるコンクリート覆工の築造方法に関するものである
【0002】
【従来の技術】
地下深層部に例えば、石油貯蔵所や放射性廃棄物の貯留所などの地下構造物を築造するには、まず、この計画地下構造物の築造位置まで地表側から立坑を掘削する必要がある。このような立坑を掘削する手段としては、従来から、発破によって掘り下げていくことが一般に行われているが、この方法では所定径の立坑を能率よく掘削することが困難である。
【0003】
そのため、地表側からロープによって上下移動可能に懸吊される足場台の下端にホールハンマー等の掘削手段を備えていると共に、上記足場台の上方部側に先に掘削壁面に施工したコンクリート覆工の下端に移動型枠を掘削壁面に沿ってスライド可能に吊支させ、さらに、掘削土砂を上方に排出する排出管を備えた立坑掘削装置が開発されている(例えば、特許文献1参照)。
【0004】
【特許文献1】
特開昭62−276192号公報(第2〜3頁、第1図)。
【0005】
【発明が解決しようとする課題】
この装置によれば、掘削手段によって所定径の立坑を垂直下方に能率よく掘り下げていくことができると共に一定長の立坑が掘削される毎に、その掘削壁面に沿って移動型枠を配設して該移動型枠と掘削壁面との間にコンクリートを打設することにより、容易にコンクリート覆工を築造することができるが、このコンクリート覆工の下端は地盤上に支持されておらず、立坑の垂直な掘削壁面に対する付着力と摩擦力とによって支持させているものであるから、該コンリート覆工はその大きな自重によって掘削壁面に沿って下方に滑動し、大きな事故が発生する虞れがあった。
【0006】
さらに、掘削装置によって掘削された壁面には、地下水の浸入を防止するために通常防水シートが張設され、この防水シートと移動型枠との間にコンクートを打設して上記コンクリート覆工を築造するものであるから、防水シートの内面が滑り面となってコンクリート覆工が一層下方に滑動しやすくなるといった問題点がある。
【0007】
また、移動型枠は、先に築造されたコンクリート覆工の下端にねじ機構等を介して上下スライド自在に吊支させるものであるから、一定長の立坑が掘削される毎に移動型枠を下方のコンクリート覆工側に盛り替えなければならず、その上、足場台は地表側からロープを操作しない限り単独では立坑内で昇降することができないために、掘削壁面の点検や型枠内への配筋作業、防水シートの張設作業等に手間取り、能率よく作業が行えないという問題点があった。
【0008】
本発明はこのような問題点に鑑みてなされたもので、その目的とするところは、垂直な立坑掘削壁面に対するコンクリート覆工の支持を確実且つ強固に行えるようにすると共に、該コンクリート覆工の施工が能率よく行うことができる立坑掘削壁面のコンクリート覆工の築造方法を提供するにある。
【0009】
【課題を解決するための手段】
上記目的を達成するために本発明の立坑掘削壁面のコンクリート覆工の築造方法は、請求項1に記載したように、立坑掘削機によって地盤を直下方向に掘削していく毎にその掘削壁面に、該掘削壁面の一部を拡径する方向に掘削することによって掘削凹部を形成したのちこの掘削壁面に沿って型枠を組立て、しかるのち、型枠と掘削壁面との間にコンクリートを打設してコンクリート覆工を築造すると共に上記掘削凹部に充満したコンクリートの硬化によって上記掘削凹部に嵌合、係止した凸部を形成することを特徴とするものである。
【0010】
上記コンクリート覆工の築造方法において、請求項2に係る発明は、立坑掘削機の下端に配設しているカッタ板を回転させることによって立坑を掘削すると共に、このカッタ板の外周部に径方向に出没自在に設けているディスクカッタ等の掘削刃を突出させることにより掘削凹部を形成することを特徴とする。
【0011】
また、請求項3に係る発明は、上記立坑掘削機の上端中央部に上方に向かって一定高さの支柱を立設し、この支柱の上半部外周方に径方向に拡縮可能な複数枚の型枠片を配設する一方、下半部に足場台を上下移動自在に配設して、上記型枠片の拡げることにより立坑掘削壁面に沿って型枠を組立てると共に足場台を使用して型枠内に対する配筋作業等を行うことを特徴とする。
【0012】
【作用】
立坑掘削機によって地盤の直下方向に立坑を掘削していく時に、その掘削壁面の一部を拡径する方向に掘削することによって凹部が形成され、さらに、この凹部を有する一定長さの掘削壁面を掘削する毎に、該掘削壁面に沿って型枠を組立て、この型枠と掘削壁面との間にコンクリートを打設することによって外周面に上記凹部に嵌合、係止した凸部を有するコンクリート覆工が築造される。
【0013】
さらに、上記立坑掘削機の下端に配設しているカッタ板を回転させながら掘り下げていくことによって一定径を有する立坑を能率よく掘削することができると共に、上記カッタ板の外周部に径方向に出没自在に設けているゲージカッタ等からなる掘削刃を突出させることにより、掘削中の立坑における所望部分に所望長さ、所望深さの凹部を連続的に或いは断続的に形成することができる。なお、この凹部は上記ディスクカッタ等の掘削刃の突出によることなく、グリッパジャッキの操作によりグリッパに対し、掘削機本体を首振り自在にすることによっても形成することができる。
【0014】
また、立坑掘削機の上端中央部に上方に向かって一定高さの支柱を立設し、この支柱の上半部外周方に径方向に拡縮可能な複数枚の型枠片を配設しておくことによって、立坑掘削機が次のコンクリート覆工が可能な深さまで一定長、掘進すると、型枠片は自動的にそのコンクリート覆工位置まで降下した状態となり、この位置で型枠片を拡げて型枠を組み立てることによりコンクリート覆工の築造が正確に且つ能率よく行うことができる。その上、上記支柱に足場台を上下移動自在に配設しておくことによって、コンクリート覆工時にこの足場台を上昇させて掘削壁面の点検や防水シートの張設作業、さらには型枠内への配筋や型枠の下端開口部への妻型枠の装着作業が容易に行える。
【0015】
【発明の実施の形態】
次に、本発明の具体的な実施の形態を図面について説明すると、図1は立坑Aの掘削壁面1に施工しているコンクリート覆工2の一部の縦断正面図であって、立坑掘削壁面1にはその長さ方向、即ち、立坑Aの深さ方向に所定間隔毎に周溝からなる凹部3が掘削によって形成されている一方、上記コンクリート覆工2は一定厚みを有する円筒形状に形成されてあり、さらに、このコンクリート覆工2における上記凹部3と対向した部分に、該凹部3と断面形状が同一の凸部4を全周に亘て連続した状態で一体に突設している。そして、この凸部4を上記凹部3に嵌合、係止させていることによってコンクリート覆工2を立坑掘削壁面1に支持させた覆工構造を構成している。
【0016】
また、立坑A内に地下水が浸入するのを防止するために、立坑掘削壁面1に防水シート5が全面的に張設されてあり、この防水シート5を介してコンクリート覆工2が掘削壁面1に築造されている。なお、防水シート5を張設する前に、立坑掘削壁面1に吹付けコンクリートによる一次覆工コンクリート層2Aが設けられてあり、この一次覆工コンクリート層2A上に上記防水シート5を張設している。従って、この防水シート5上に施工されている上記コンクリート覆工2によって二次覆工コンクリート層を形成しているが、地下水が浸入する虞れのない地盤中に立坑Aを掘削する場合には、上記防水シート5を設けることなく、掘削壁面1に直接、このコンクリート覆工2を築造すればよい。
【0017】
掘削壁面1の拡径方向に掘削形成される上記凹部3の深さや上下幅等は、コンクリート覆工2における上下に隣接する凸部4、4間のコンクリート覆工部分の重量を支持することができる深さや上下幅に設定される。即ち、コンクリート覆工2の重量はその凸部4を介して凹部3の下面に支持されるが、その支持反力が凸部4に対する剪断力として作用し、凹部3と同一断面形状に形成されている凸部4の突出幅や上下幅が狭いと、上記剪断力によって凸部4が剪断されてコンクリート覆工2が掘削壁面1に沿って滑落する虞れが生じる。
【0018】
そのため、上下に隣接する凸部4、4間のコンクリート覆工部分の重量を該凸部4と上記凹部3との係止力によって支持することができるように、これらの凹部3と凸部4との断面形状の大きさや立坑Aに対する周方向の長さ等を設定するものである。
【0019】
また、上記実施の形態においては、掘削壁面1に拡径方向に掘削形成された凹部3は周溝からなるものであるが、螺旋溝からなるものであってもよく、或いは、掘削壁面1の長さ方向と周方向とに所定間隔毎に掘削形成された不連続な溝からなるものであってもよい。
【0020】
図2は上記コンクリート覆工2を築造しながら立坑Aを掘り下げていく立坑掘削機の簡略縦断正面図であって、掘削機本体Bはその中心部に設けている小径垂直筒部11の下端側にカッタ板12を回転自在に配設している。このカッタ板12は、その板面に地盤を掘削する多数のディスクカッタ等の掘削刃12a を突設していると共に上下面に連通する掘削土砂取込み開口部12b を設けてあり、さらに、外周部の数カ所には、同じくディスクカッタ等からなる掘削刃12a'を径方向に出没自在に設けてなるものである。この掘削刃12a'の出没機構としては、例えば、カッタ板12の外周部の背面側(図においては上面側)に油圧ジャッキ12c を装着し、この油圧ジャッキ12c のロッド先端に掘削刃12a'を固定してなる構造を採用している。
【0021】
また、上記小径垂直筒部11の上端に固定足場台を兼用した水平固定支持台13の下面中央部を一体に固着してあり、この水平固定支持台13の上面中央部に上方に向かって一定高さの支柱14を垂直に立設、固定し、該支柱14に足場台15を上下移動自在に配設している。
【0022】
なお、支柱14は上記水平固定支持台13の上面にその下端を直接固定して立設してもよいが、図においては、支柱14の下端を平面矩形状支持枠13a 上に固定し、この支持枠13a を水平固定支持台13上に4個のレベル調整装置16を介して連結、支持させた構造としている。このように構成することにより、掘削中に掘削機本体Bが傾いた場合でも支柱14を鉛直に維持することができ、従って、足場台15を水平に保つことができ且つ足場台15が掘削壁面1に当接することがない。
【0023】
この支柱14は、上記支持枠13a の四隅部から互いに平行に且つ前後左右に等間隔を存して立設している4本の縦柱材14a と、これらの縦柱材間を連結、固定しているトラス状に組み合わせた多数本の斜桁14b と水平桁14c とからなり、4本の縦柱材14a によって囲まれた中空内には上記水平固定台13から上端間に亘って昇降用階段17をジグザグ状に設けていると共にこの昇降用階段17の昇降途中には長さ方向に一定間隔毎に踊り場17a を形成している。
【0024】
支柱14に上下移動自在に配設した上記足場台15は、掘削機本体Bによって掘削された立坑Aよりも小径の水平円板形状に形成されてあり、その中央部に、図3に示すように、支柱14を挿通させている矩形状孔15a を設けていると共に外周端縁部に上方に向かって一定高さの手摺り15b を立設している。
【0025】
この足場台15を上記支柱14をガイドとして上下移動させる昇降駆動機構18としては、支柱14の縦柱材14a に固定垂直ラック18a を一体に設ける一方、足場台15の上記矩形状孔15a の隅角部に昇降駆動用モータ18b を装着し、この昇降用駆動モータ18b の回転軸に固着しているピニオン18c を上記固定垂直ラック18a に噛合させた構造を採用している。
【0026】
支柱14に対する足場台15の上下移動範囲は、支柱14の下端から長さ方向の中央部、即ち、支柱14の下半部において行われ、従って、上記垂直ラック18a は支柱14の下端から長さ方向の中間部に達する部分に設けられている。そして、この支柱14の上半部側には移動型枠19が配設されている。
【0027】
この移動型枠19は、立坑Tの掘削壁面1に沿って凸円弧状に湾曲している一定長さの型枠片19a を複数個、互いに径方向に伸縮自在に連結してなり、各型枠片19a の上端を、支柱14の上端部に固着している円板形状の固定台枠20の外周部下面に吊支された複数個のチェーンブロック21によってそれぞれ吊支されている。固定台枠20は、その中央部に設けている矩形状の孔20a (図4に示す)に支柱14を挿通させた状態で該支柱14の上端から下方に所定距離を存した部分に固着されてあり、その外周端面を立坑Aの掘削壁面1に近接させていると共に外周部下面に上記複数個のチェーンブロック21を該固定台枠20の径方向に移動可能に支持している。なお、型枠片19a の内周面には足場板を張設した足場枠22を取付けている。
【0028】
さらに、支柱14の上端には上記固定台枠20と略同大、同形の天板23が固定されていてこの天板23上にコンクリートホッパ24が設置されてあり、該コンクリートホッパ24に連結、連通しているコンクリート供給管25の下端を立坑Aの掘削壁面1に先に施工した覆工コンクリート2の下端から下方に臨ませるように形成している。
【0029】
一方、上記カッタ板12はその外周端に内径方向に向かってアーム部材12d を突設してこれらのアーム部材12d の内端をリング部材12e に一体に固着し、該リング部材12e を掘削機本体Bの中心胴部を形成している上記小径垂直筒部11の下端部外周面に一体に固着した円形固定枠26の下端外周部に回転自在に支持させてあり、このリング部材12e の内周面に設けている円形ラック12f に、円形固定枠26上に設置しているカッタ板駆動用モータ27の回転軸に固着した小歯車28を噛合させてモータ27の駆動によりカッタ板12を回転させるように構成している。
【0030】
さらに、上記円形固定枠26の外周面に、周方向に所定間隔毎に下向きに傾斜した傾斜ジャッキ30と上向きに傾斜した傾斜ジャッキ31との内端部を上下方向に回動可能に連結、支持してあり、これらの傾斜ジャッキ30、31の外端部を周方向に複数分割しているグリッパ32に連結し、該傾斜ジャッキ30、31を伸長させることによってグリッパ32を掘削壁面1に圧着させて掘削機本体Bを支持させながら下方に推進させるように構成している。
【0031】
29は排土手段であって排土管29a と給水管29b とからなり、排口管29a の下端開口部を上記カッタ板12の回転中心部の上面に集合する掘削土砂Cに臨ませていると共に、この排土管29a の下端部に上記給水管29b のV字状に屈折した下端部における上端開口部を連結、連通させてこの給水管29b から排土管29a 内に下端から上方に向かう圧力水を噴出させ、エゼクタ作用によって排土管29a に吸引力を発生させて掘削土砂Cを吸入し、上方の適所に設置している貯留タンク(図示せず)に土砂を排出し、水を分離させて再び圧力水として使用するように構成している。
【0032】
貯留タンク内に一旦貯留された土砂は、適宜な搬出手段によって地上側に搬出される。なお、上記支柱14に上下移動自在に配設している足場台15や、固定している固定台枠20、天板23には搬出手段を貫通させるための貫通孔40や立坑T内への換気を行うための送気管や排気管の挿通孔41が設けられている。
【0033】
このように構成した立坑掘削機によって立坑Aを掘進すると共にその掘削壁面1にコンクリート覆工2を築造する方法について説明すると、立坑掘削機は傾斜ジャッキ30、31によってグリッパ32を掘削壁面1に圧着させることにより、該掘削壁面1に推進反力をとると共に掘削機本体Bの支持を行わせ、円形固定枠26から斜め上方に傾斜している傾斜ジャッキ31を伸長させることにより、掘削機本体Bを垂直下方に推進させながらカッタ板12によって切羽の岩盤を切り下げ掘削していく。なお、円形固定枠26から斜め下方に傾斜している傾斜ジャッキ30は掘削壁面1に対するグリッパ32の下端部の圧着力を調整して掘削機本体10が必要以上に下動するのを阻止する突張り作用を奏するものである。
【0034】
掘削された土砂は、ズリ取込み開口部12b を通じてカッタ板12の裏面側、即ち、上面側に掻き上げられると共にカッタ板12の回転中心部上に寄せ集められて排土手段29や搬出手段によって地上に排出される。
【0035】
こうして掘削機本体Bによって立坑Aを掘進するに従って、掘削機本体Bから上方に立設している支柱14も立坑A内を一体に下動し、この支柱14の下端外周方に掘削された壁面1が露出する。この立坑掘削壁面1が、型枠19によってコンクリート覆工が可能な一定深さ(長さ)だけ掘削される間に、カッタ板12の外周部に出没自在に配設している掘削刃12a'をカッタ板12の外周から径方向に突出させた状態にしてカッタ板12を回転させることにより、カッタ板12によって掘削された掘削壁面1の一部を該掘削刃12a'で拡径する方向に掘削して掘削壁面1の周方向に連続した周溝からなる凹部3を形成する。
【0036】
この凹部3の深さや上下方向の幅は、カッタ板12の外周から外径方向に突出する掘削刃12a'の突出長と掘削刃12a'の厚み及び該掘削刃12a'を突出させた状態で掘進するカッタ板12の掘進長さによって設定することができる。なお、この凹部3としては、掘削壁面1の全周に亘って円環状に連続した周溝形状に形成することなく、断続的に、即ち、不連続な溝を掘削壁面1の長さ方向及び周方向に所定間隔毎に設けることによって形成してもよく、或いは、連続螺旋状の溝に形成してもよい。また、上記カタ板12の外周から径方向に出没する掘削刃12a'によって凹部3を形成することなく、カッタ板12によって立坑Aを掘削中に、上記グリッパ32のジャッキ30、31の操作により、グリッパ32に対して掘削機本体Bを首振りさせることによってカッタ板12に突設している掘削刃により凹部3を掘削形成してもよい。
【0037】
カッタ板12によって掘削された壁面には、該壁面の崩落等を防止するために、足場台15上を利用して直ちに吹付けコンクリートによる一次覆工コンクリート層2Aが施工され、さらに、一定長の立坑A(掘削壁面1)が掘削されると、支柱14の下半部に上下移動自在に配設している足場台15上に作業員が乗って足場台15を支柱14に沿って上下昇降させなることにより掘削壁面1の点検を行うと共に、該掘削壁面1に施工した上記一次覆工コンクリート層2A上に防水シート5を張設し、且つ鉄筋(図示せず)を配筋する。
【0038】
さらに、掘削機本体Bが支柱14の上半部側に設けている移動型枠19の長さに相当した長さの立坑Aを掘削すると、固定台枠20から吊支している該移動型枠19が先に防水シート5上に施工している覆工コンクリート2の下端にその上端を対向させた位置に達し、この型枠片19a を吊支しているチェーンブロック21を固定台枠20の外周端側に向かって移動させることにより型枠片19a を拡径させて円筒形状に組み立てる。
【0039】
チェーンブロック21を適宜作動させて移動型枠19を上下移動させることにより、その上端面を先に施工した上記覆工コンクリート2の下端に合わせておくと共に外径方向に拡大させて移動型枠19の上端部と掘削壁面1との間の隙間にコンクリート供給管25の下端を臨ませておく。
【0040】
一方、支柱14の下半部側において、上記足場台15を移動型枠19の下端部近傍にまで上昇させ、この足場台上で移動型枠19と掘削壁面1との間の隙間に配筋後の妻型枠19b の装着、固定作業を行い、しかるのち、支柱14の上端に固着している天板23上に設置したコンクリートホッパ24にコンクリートを投入して、上記供給管25を通じて移動型枠19と掘削壁面1との間の隙間にコンクリートを打設して二次覆工コンクリート層となる一定厚みのコンクリート覆工2を施工する。そうすると、打設したコンクリートの一部が掘削壁面1に形成している上記凹部3内にも充満して該コンクリート覆工2の外周面に上記凹部3と同一断面形状を有し且つ該凹部3に嵌合、係止した状態の凸部4が一体に形成される。なお、掘削壁面1に防水シート5が張設されている場合には掘削壁面1とコンクリート覆工2との間にこの防水シート5が介在している覆工構造となる。
【0041】
このように、先に施工した覆工コンクリート2の下端にその上端部を連設するようにして覆工コンクリート2を施工した後、チェーンブロック21を固定台枠20の内側に移動させることにより移動型枠19を内径方向に縮小させて折り畳み、次の覆工作業に備える。
【0042】
以下、同様にして立坑掘削機Bによって、凹部3を有する一定長さの立坑部分を掘削する毎に、支柱14の下半部側においては足場台15を利用したコンクリートの吹付け作業や掘削壁面1の点検、該掘削壁面1に対する防水シート5の張設作業等を行うと共に、支柱14の上半部側においては移動型枠19による覆工コンクリート2の施工作業を並行して行うものである。なお、覆工コンクリート2としては打設コンクリートによることなく外面に上記凹部3に嵌合する凸部を設けた既成のコンクリートパネルによって形成してもよい。
【0043】
【発明の効果】
本発明の立坑掘削壁面のコンクリート覆工の築造方法によれば、請求項1に記載したように、立坑掘削機によって地盤を直下方向に掘削していく毎にその掘削壁面に、該掘削壁面の一部を拡径する方向に掘削することによって掘削凹部を形成したのちこの掘削壁面に沿って型枠を組立て、しかるのち、型枠と掘削壁面との間にコンクリートを打設してコンクリート覆工を築造すると共に上記掘削凹部に充満したコンクリートの硬化によって上記掘削凹部に嵌合、係止した凸部を形成することを特徴とするものであるから、立坑掘削機による立坑の掘削と並行してその立坑掘削壁面に所望の断面形状を有する凹部を形成することができると共に、この凹部の掘削に後続して該掘削壁面に沿って組立てた型枠内にコンクリートを打設するので、コンクリート覆工の築造と同時に該コンクリート覆工の外周面に上記凹部に係合支持した凸部を確実に形成することができる。
【0044】
従って、立坑の掘削中においては、築造されたコンクリート覆工の下端は何ら支持されておらず、下方の立坑掘削機側に臨んでいる状態となっているが、このコンクリート覆工は立坑掘削壁面に形成された凹部にその外周面に形成された凸部を支持させた構造となっているから、立坑掘削機側に滑落する虞れはなく、作業の安全性を高めることができる。
【0045】
さらに、請求項2に係る発明によれば、上記立坑掘削機のカッタ板の外周部に径方向に出没自在に設けているディスクカッタ等の掘削刃を突出させることにより上記掘削凹部を形成するものであるから、掘削中の立坑における所望部分に所望長さ、所望深さの凹部を連続的に或いは断続的に形成することができる。
【0046】
また、上記コンクリート覆工の築造方法において、請求項3に係る発明は、立坑掘削機の上端中央部に上方に向かって一定高さの支柱を立設し、この支柱の上半部外周方に径方向に拡縮可能な複数枚の型枠片を配設している一方、下半部に足場台を上下移動自在に配設してあり、上記型枠片の拡げることにより立坑掘削壁面に沿って型枠を組立てると共に足場台を使用して型枠内に対する配筋作業等を行うことを特徴とするものであるから、立坑掘削機が次のコンクリート覆工が可能な深さまで一定長、掘進すると、型枠片は自動的にそのコンクリート覆工位置まで降下した状態となり、この位置で型枠片を拡げて型枠を組み立てることによりコンクリート覆工の築造が正確に且つ能率よく行うことができる。その上、上記支柱に足場台を上下移動自在に配設しているので、コンクリート覆工時にこの足場台を上昇させて掘削壁面の点検や防水シートの張設作業、さらには型枠内への配筋や型枠の下端開口部への妻型枠の装着作業が円滑に且つ能率良く行うことができる。
【図面の簡単な説明】
【図1】 コンクリート覆工の縦断正面図、
【図2】 コンクリート覆工を築造中の立坑掘削機の簡略縦断側面図、
【図3】 その足場台部分の簡略平面図、
【図4】 固定台枠部分の簡略平面図。
【符号の説明】
1 掘削壁面
2 コンクリート覆工
3 凹部
4 凸部
10 掘削機本体
12 カッタ板
12a' 掘削刃
14 支柱
15 足場台
19 移動型枠
A 立坑
B 掘削機本体[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a concrete lining to be constructed on a wall of a shaft excavated when a shaft is excavated from a ground surface side to an underground deep layer by a shaft excavator.
[Prior art]
In order to construct an underground structure such as an oil reservoir or a radioactive waste storage in the deep underground, for example, it is necessary to first excavate a shaft from the surface side to the construction position of the planned underground structure. Conventionally, as a means for excavating such a vertical shaft, it is generally carried out by digging down by blasting. However, it is difficult to efficiently excavate a vertical shaft having a predetermined diameter by this method.
[0003]
For this reason, a concrete lining that is provided with excavation means such as a hole hammer at the lower end of a scaffolding base suspended from a ground surface so as to be movable up and down by a rope, and that has been constructed on the excavation wall first above the scaffolding base. A shaft excavation device has been developed that has a movable form frame slidably supported along the excavation wall surface at the lower end of the excavator and further has a discharge pipe for discharging excavated earth and sand upward (see, for example, Patent Document 1).
[0004]
[Patent Document 1]
JP-A-62-276192 (
[0005]
[Problems to be solved by the invention]
According to this apparatus, a shaft having a predetermined diameter can be efficiently dug down vertically by the excavating means, and a movable frame is arranged along the excavation wall every time a shaft having a certain length is excavated. By placing concrete between the movable formwork and the excavation wall, it is possible to easily construct a concrete lining, but the lower end of the concrete lining is not supported on the ground, and Therefore, the concrete lining slides downward along the excavation wall surface due to its large weight, and there is a possibility that a large accident will occur. It was.
[0006]
In addition, a waterproof sheet is usually stretched on the wall excavated by the excavator to prevent intrusion of groundwater, and a concrete is placed between the waterproof sheet and the movable formwork to cover the concrete lining. Since it is constructed, there is a problem that the inner surface of the waterproof sheet becomes a sliding surface and the concrete lining becomes easier to slide downward.
[0007]
In addition, since the movable form is suspended from the lower end of the concrete lining that has been built in advance through a screw mechanism or the like, it can be slid up and down. In addition, the scaffold must be replaced with the concrete lining side below, and the scaffolding can not be lifted up and down in the shaft alone unless the rope is operated from the surface side. However, there is a problem in that it is difficult to perform the work efficiently because it takes time for the bar arrangement work and the tension sheet installation work.
[0008]
The present invention has been made in view of such problems, and the object of the present invention is to make it possible to reliably and firmly support the concrete lining against the vertical shaft wall of the vertical shaft, and to The object of the present invention is to provide a method for constructing a concrete lining of a shaft wall for excavation that can be efficiently constructed.
[0009]
[Means for Solving the Problems]
In order to achieve the above object, the concrete lining method for a shaft wall of the shaft according to the present invention, as described in
[0010]
In the concrete lining construction method, the invention according to claim 2 excavates the shaft by rotating the cutter plate disposed at the lower end of the shaft excavator, and the outer periphery of the cutter plate is radially arranged. An excavation recess is formed by projecting an excavation blade such as a disk cutter provided so as to freely move in and out.
[0011]
Moreover, the invention which concerns on
[0012]
[Action]
When a shaft is excavated in a direction directly below the ground by a shaft excavator , a recess is formed by excavating a part of the excavation wall in the direction of expanding the diameter, and a certain length of the excavation wall having the recess Each time a dig is excavated, a mold is assembled along the excavation wall, and concrete is placed between the mold and the excavation wall so that the outer surface has a convex portion that fits and locks into the concave portion. Concrete lining is built.
[0013]
Furthermore, the shaft having a constant diameter can be efficiently excavated by rotating the cutter plate disposed at the lower end of the shaft excavator while rotating, and the outer periphery of the cutter plate can be radially expanded. By projecting an excavating blade made of a gauge cutter or the like provided so as to be able to appear and retract, a concave portion having a desired length and a desired depth can be formed continuously or intermittently in a desired portion of the shaft being excavated. In addition, this recessed part can be formed not only by protrusion of excavation blades, such as the said disk cutter, but also by making an excavator main body swing freely with respect to a gripper by operation of a gripper jack.
[0014]
In addition, a column having a fixed height is erected upward at the center of the upper end of the shaft excavator, and a plurality of mold pieces that can be expanded and contracted in the radial direction are disposed on the outer periphery of the upper half of the column. As a result, the formwork piece automatically descends to the concrete lining position when the shaft excavator is excavated for a certain length to the depth where the next concrete lining is possible, and the formwork piece is expanded at this position. By assembling the formwork, the construction of the concrete lining can be performed accurately and efficiently. In addition, by placing the scaffolding platform on the above-mentioned column so as to be movable up and down, the scaffolding platform can be raised during concrete lining to check the excavation wall, stretch the waterproof sheet, and even into the formwork. It is possible to easily attach the wife formwork to the lower bar opening of the formwork or the formwork.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
Next, a specific embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a longitudinal front view of a part of a
[0016]
Further, in order to prevent the underground water from entering the shaft A, a
[0017]
The depth, vertical width, etc. of the
[0018]
Therefore, the
[0019]
Moreover, in the said embodiment, although the recessed
[0020]
FIG. 2 is a simplified longitudinal front view of a shaft excavator that digs down the shaft A while building the
[0021]
In addition, a central portion of the lower surface of the horizontal fixed
[0022]
The
[0023]
The
[0024]
The above-mentioned
[0025]
As an elevating
[0026]
The vertical movement range of the
[0027]
This
[0028]
Further, a
[0029]
On the other hand, the
[0030]
Further, on the outer peripheral surface of the circular fixed
[0031]
29 is a soil discharging means, which is composed of a
[0032]
The earth and sand once stored in the storage tank is carried out to the ground side by an appropriate carrying-out means. It should be noted that the
[0033]
The method of excavating the shaft A with the shaft excavator thus configured and constructing the
[0034]
The excavated earth and sand is scraped up to the back side of the
[0035]
As the shaft A is excavated by the excavator main body B, the
[0036]
The depth and the vertical width of the
[0037]
On the wall surface excavated by the
[0038]
Further, when the excavator body B excavates a vertical shaft A having a length corresponding to the length of the
[0039]
By appropriately operating the
[0040]
On the other hand, on the lower half side of the
[0041]
In this way, after the lining
[0042]
In the same manner, each time the shaft portion having a certain length having the
[0043]
【The invention's effect】
According to the concrete lining construction method for a shaft excavation wall according to the present invention, as described in
[0044]
Therefore, during the excavation of the shaft, the lower end of the built concrete lining is not supported at all and is facing the lower shaft excavator side. Since the convex portion formed on the outer peripheral surface is supported by the concave portion formed on the inner surface, there is no fear of sliding down to the shaft excavator side, and the safety of the work can be improved.
[0045]
Furthermore, according to the invention which concerns on
[0046]
In the concrete lining construction method described above, the invention according to
[Brief description of the drawings]
[FIG. 1] A longitudinal front view of a concrete lining,
[Fig.2] Simplified vertical side view of shaft excavator under construction of concrete lining,
FIG. 3 is a simplified plan view of the scaffolding part,
FIG. 4 is a simplified plan view of a fixed base frame portion.
[Explanation of symbols]
10 Excavator body
12 Cutter plate
12a 'drilling blade
14 Prop
15 Scaffolding stand
19 Mobile formwork A Vertical shaft B Excavator body
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003136811A JP4039978B2 (en) | 2003-05-15 | 2003-05-15 | Construction method of concrete lining of shaft wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003136811A JP4039978B2 (en) | 2003-05-15 | 2003-05-15 | Construction method of concrete lining of shaft wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004339768A JP2004339768A (en) | 2004-12-02 |
JP4039978B2 true JP4039978B2 (en) | 2008-01-30 |
Family
ID=33526628
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003136811A Expired - Lifetime JP4039978B2 (en) | 2003-05-15 | 2003-05-15 | Construction method of concrete lining of shaft wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4039978B2 (en) |
-
2003
- 2003-05-15 JP JP2003136811A patent/JP4039978B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2004339768A (en) | 2004-12-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6010070B2 (en) | Temporary closing method for existing underwater structures | |
WO2018133746A1 (en) | Underground building formed of piles and walls, and method for constructing same | |
JP6595825B2 (en) | Underground building construction method | |
JP4040003B2 (en) | Formwork device for concrete lining of shaft wall of shaft excavation and concrete lining method | |
JP4039978B2 (en) | Construction method of concrete lining of shaft wall | |
JP2797244B2 (en) | Shaft excavation device and shaft construction method | |
JP3418343B2 (en) | Earth retaining wall formation method in root cutting method | |
JP5378066B2 (en) | Mountain fastening method | |
KR102171437B1 (en) | Construction method of panel for pedestrian block | |
JP3898562B2 (en) | Mobile formwork device in shaft excavator | |
KR102059051B1 (en) | Method for excavating vertical shaft | |
JP3898561B2 (en) | Mobile scaffolding device for shaft excavator | |
JP3303115B2 (en) | Underground shaft construction equipment | |
JP2004003229A (en) | Method for constructing vertical shaft | |
JPH0534475B2 (en) | ||
JP4196273B2 (en) | How to form a retaining wall at the bottom of an existing building | |
JP2854838B2 (en) | Method and apparatus for excavating a vertical hole and excavator | |
JPH0960311A (en) | Lift-up demolition method | |
JP7061526B2 (en) | Excavation method and excavation equipment | |
JPH10102966A (en) | Excavating equipment of cast-in-place concrete pile hole | |
CN116378034A (en) | Demolition process and auxiliary demolition equipment for subway connecting channel | |
KR20130003341A (en) | Apparatus for executing underground outer wall | |
DE3716750A1 (en) | Method of constructing and sinking foundation structures | |
JP2553986B2 (en) | Deep foundation foundation construction machine | |
JPH07113394A (en) | Shield excavator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050802 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070608 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070626 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070824 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20071009 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20071106 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101116 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4039978 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131116 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |