JP4029058B2 - Construction method of approach part of multilevel intersection road - Google Patents

Construction method of approach part of multilevel intersection road Download PDF

Info

Publication number
JP4029058B2
JP4029058B2 JP2003077262A JP2003077262A JP4029058B2 JP 4029058 B2 JP4029058 B2 JP 4029058B2 JP 2003077262 A JP2003077262 A JP 2003077262A JP 2003077262 A JP2003077262 A JP 2003077262A JP 4029058 B2 JP4029058 B2 JP 4029058B2
Authority
JP
Japan
Prior art keywords
road
approach
intersection road
width
dimensional intersection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2003077262A
Other languages
Japanese (ja)
Other versions
JP2004285627A (en
Inventor
龍一 皆田
研一 西山
良弘 楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Engineering and Shipbuilding Co Ltd
Mitsui E&S Holdings Co Ltd
Original Assignee
Mitsui Engineering and Shipbuilding Co Ltd
Mitsui E&S Holdings Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Engineering and Shipbuilding Co Ltd, Mitsui E&S Holdings Co Ltd filed Critical Mitsui Engineering and Shipbuilding Co Ltd
Priority to JP2003077262A priority Critical patent/JP4029058B2/en
Publication of JP2004285627A publication Critical patent/JP2004285627A/en
Application granted granted Critical
Publication of JP4029058B2 publication Critical patent/JP4029058B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、複数の道路が平面的に交差している既設の交差点を跨ぐ橋梁部と、この橋梁部の両側に設けられ前記橋梁部と路面とを連結するアプローチ部とからなる立体交差道路のアプローチ部建設方法に関するものである。
【0002】
【従来の技術】
近年の車社会においては、複数の道路が平面的に交差している既設の交差点において交通渋滞が生じている。この傾向は、特に、都市部において激しくなっている。そのため、既設の道路の一方を立体化することが実施されている。
【0003】
例えば、図11に示すように、第一の道路A(例えば4車線)と第二の道路B(4車線)とが平面的に交差している交差点Cにおいて、第二の道路Bを立体化する場合は、第二の道路Bの中央部の2車線が第一の道路Aを跨ぐように構成するが、この場合は第二の道路Bの立体化部分、即ち、立体交差道路Dは、図12に示されるように第一の道路Aを跨ぐ橋梁部D1と、この橋梁部D1の両側に配置され、かつ橋梁部D1と第二の道路Bの路面B1とを連結するアプローチ部D2とより構成される。
【0004】
ところで、このアプローチ部D2は、通常その断面を図13に示すように立体交差道路幅W1と同じ間隔を有するようにL型擁壁1a、1bを設け、このL型擁壁1a、1b間に盛土2を施し、この盛土2上に路床3を敷設して構成されている。
【0005】
そして、このようなアプローチ部D2は、図14に示すように予めフェンス4を立体交差道路幅W1より大なる幅W2を有する作業帯5を設置し、その後、この作業帯5内の上面の土を除去してL型擁壁1a、1bを配置する(図15)。
【0006】
そして、このL型擁壁1a、1bの間に盛土2を施した(図16)後、この盛土2上に路床3を配置する(図17)。しかる後、この路床3上に舗装の橋面工事を行うことで完成させるという建設方法が採られている。
【0007】
【発明が解決しようとする課題】
ところで、前記したような立体交差道路のアプローチ部構造によれば、L型擁壁1a、1bの間に盛土2を行うため、このための土砂が必要となるばかりでなく、この盛土2が定成するまで路床3を配置することができないため工期が長くなるという問題がある。そして、かかる構造のアプローチ部D2を建設する場合、予め立体交差道路幅W1より大な幅W2を有する作業帯5を設置する必要があり、そのため、長期にわたって交通渋滞が生じている。
【0008】
具体的には、立体交差道路Dは第二の道路Bの内側の車線a1、b1(図11参照)を立体化させることとなるが、この場合、作業帯5は、外側の車線a2、b2の一部を利用せざるを得ないので、この外側の車線a2、b2の車の走行が制限され、その結果、交通渋滞が生じるのであるが、この交通渋滞はアプローチ部D2(図12)が完成するまでの長期(例えば4ヶ月以上)にわたって生じることとなる。
【0009】
【課題を解決するための手段】
本発明は、前記したような従来の問題点を解決するためになされたものであって次のように構成されている。
【0010】
請求項1記載の発明は、複数の道路が平面的に交差している既設の交差点を跨ぐ橋梁部と該橋梁部の両側に設けられ且つ前記橋梁部と路面とを連結するアプローチ部とからなる立体交差道路のアプローチ部の建設方法において、前記アプローチ部が配置される路面上に内側車線の一部を利用して作業帯を形成する工程と、該作業帯の地上に立体交差道路の幅より小なる幅を有する底版を敷設する工程と、前記底版の両側上面に側壁を配置する工程と、立体交差道路幅を有するプレキャスト床版を前記両側壁の間を走行するフォークリフトを用いて前記側壁上に設置する工程とよりなることを特徴とする立体交差道路のアプローチ部建設方法である。
【0015】
かかる立体交差道路のアプローチ部建設方法によれば、路面上に形成される作業帯の幅は、立体交差道路の幅より小なる幅とすることができ、その結果、建設中の交通渋滞を少なくすることができる。
【0017】
かかる立体交差道路の建設方法によれば、底版とその両側上面に配置された側壁間の作業帯を移動する揚重機によりプレキャスト床版を移送し、そして側板上に配置するため交通渋滞が生じることはない。
【0019】
かかる立体交差道路のアプローチ部建設方法によれば、フォークリフトによりプレキャスト床版を持ち上げて側壁上に配置することとなるため交通渋滞の防止と作業性の向上による工期の短縮を図ることができる。
【0020】
【発明の実施の形態】
以下、図1乃至図10を参照して本発明による立体交差道路のアプローチ部構造及び建設方法の実施例を説明する。これらの図において、図11乃至図17と同一符号は同一名称を示す。
【0021】
図1は、立体交差道路Dを構成するアプローチ部D2(図12)の断面図であって、このアプローチ部D2は、立体交差道路Dの幅W1と同じ幅を有するプレキャスト床版6と、このプレキャスト床版6の幅W1より小なる幅W3を有し、かつ第二の道路Bの中央部に配置された底板7と、この底版7の上面に配置された側壁8a、8bにより構成されている。そして、このプレキャスト床版6は、好ましくは図2に示されるように複数の短尺状の単位プレキャスト床版6a〜6nを連続して配置して構成される。
【0022】
このような立体交差道路Dのアプローチ部D2を建設する場合は、まず図3及び図4に示すように、フェンス等4の表示器具を用いて第二の道路Bの内側の車線a1、b1の一部を利用して、アプローチ部D2が建設される箇所に作業帯9を設置する。そして、底版7を配置し(図5)、しかる後、この底版7の両側上面に側壁8a、8bを設置する(図6)。
【0023】
この底版7及び側壁8a、8bを設置する間に、短尺上の単位プレキャスト床版6a〜6nを工場で製作しておく。そして、このようにして底版7と側壁8a、8bがアプローチ部D2の建設部分に設置されると、フェンス等4を移動させて作業帯9の幅W4が立体交差道路Dの幅W1より僅かに大となるように修正しておく。
【0024】
その後、単位プレキャスト床版6a〜6n(図2)をフォークリフトの如き第二の揚重機13(図9)を用いて作業帯9である側壁8a、8bの間から搬入して側壁8a、8b上に設置する(図7、図10)。
【0025】
このプレキャスト床版6a〜6nの搬入設置についてより具体的に説明すれば、図9及び図10に示すように工場で製作されたプレキャスト床版6a〜6nは、トラック11により現地まで輸送され、ここで、例えば油圧式クレーン等の第一の揚重機12により第二の揚重機13に積み替えられる。この第二の揚重機13は、好ましくは、フォークリフトが用いられる。
【0026】
即ち、第二の揚重機13としてフォークリフトを用いることにより、2枚の側壁8a、8bの間の作業帯を走行して所定の位置にこのプレキャスト床版6a〜6nを設置することが出来るので作業の効率が向上する。
【0027】
このような、立体交差道路Dのアプローチ部D2の建設方法において、第二の道路Bの外側に歩道が存在する場合は、その一部、即ち、作業帯9を設置するために利用された内側の車線a1、b1の一部の幅と同程度の幅を車線とするようにすれば、両側2車線とすることができ、かかる工事による交通渋滞は殆ど生じない。
【0028】
そして、側壁8a、8b上にプレキャスト床版6を設置するとき(図7,8)、第一の作業帯9及び第二の作業帯10を立体交差道路Dの幅W1まで広げることにより車線a1、b1は一時的に狭められるがその期間は全体工期(例えば4ヶ月)の約1/4程度であるため大きな交通渋滞を来たすことはない。
【0029】
【発明の効果】
以上の説明から明らかなように、本発明による立体交差道路のアプローチ部構造及びその建設方法によれば、アプローチ部を立体交差道路の幅と同じプレキャスト床版と,この立体交差道路幅より小なる幅を有する底版とこの底版の両側上面に配置された側壁とにより構成したため、その建設工期を短縮することができるばかりでなく、その建設時に必要となる作業帯の範囲を縮小、とくにその幅を小さくすることができ、その結果、交通渋滞を防止することができるという効果を奏する。
【図面の簡単な説明】
【図1】本発明による立体交差道路のアプローチ部構造の断面図である。
【図2】本発明による立体交差道路のアプローチ部構造の一部破断した斜視図である。
【図3】本発明による立体交差道路のアプローチ部建設方法を説明するための道路交差部の平面図である。
【図4】本発明による立体交差道路のアプローチ部建設方法を実施する場合の作業帯形成方法の説明図である。
【図5】本発明による立体交差道路のアプローチ部建設方法を実施する場合の底板の設置状態の説明図である。
【図6】本発明による立体交差道路のアプローチ部建設方法を実施する場合の側板の設置状態説明図である。
【図7】本発明による立体交差道路のアプローチ部建設方法を実施する場合のプレキャスト床版の設置状態説明図である。
【図8】本発明による立体交差道路のアプローチ部建設方法を実施する場合のプレキャスト床版の設置完了説明図である。
【図9】本発明による立体交差道路のアプローチ部建設方法を実施する場合のプレキャスト床版の設置状況を示す側面図である。
【図10】図9の平面図である。
【図11】道路交差部の斜視図である。
【図12】立体交差道路の側面図である。
【図13】従来の立体交差道路のアプローチ部の断面図である。
【図14】従来の立体交差道路のアプローチ部建設方法における作業帯設置の説明図である。
【図15】従来の立体交差道路のアプローチ部建設方法におけるL型擁壁設置の説明図である。
【図16】従来の立体交差道路のアプローチ部建設方法における盛土の説明図である。
【図17】従来の立体交差道路のアプローチ部建設方法における路床の設置説明図である。
【符号の説明】
1a、1b L型擁壁 2 盛土
3 路床 4 フェンス等 5 作業帯
6 プレキャスト床版 7 底版 8a、8b 側壁
9 作業帯 11 トラック 12 第一の揚重機
13 第二の揚重機
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a three-dimensional intersection road comprising a bridge portion straddling an existing intersection where a plurality of roads intersect in plan, and an approach portion provided on both sides of the bridge portion and connecting the bridge portion and a road surface. it relates to approach Buken設方method.
[0002]
[Prior art]
In the recent automobile society, traffic congestion occurs at an existing intersection where a plurality of roads intersect in a plane. This trend is particularly acute in urban areas. Therefore, three-dimensionalization of one of the existing roads has been implemented.
[0003]
For example, as shown in FIG. 11, the second road B is three-dimensionalized at an intersection C where the first road A (for example, four lanes) and the second road B (four lanes) intersect in a plane. In this case, it is configured so that the two lanes in the center of the second road B straddle the first road A. In this case, the three-dimensional portion of the second road B, that is, the three-dimensional intersection road D, As shown in FIG. 12, a bridge part D1 straddling the first road A, an approach part D2 arranged on both sides of the bridge part D1 and connecting the bridge part D1 and the road surface B1 of the second road B, Consists of.
[0004]
By the way, this approach part D2 is provided with L-shaped retaining walls 1a and 1b so that the section thereof has the same interval as the three-dimensional intersection road width W1 as shown in FIG. 13, and between these L-shaped retaining walls 1a and 1b. A bank 2 is applied, and a road bed 3 is laid on the bank 2.
[0005]
Then, as shown in FIG. 14, such an approach portion D <b> 2 previously installs a work band 5 having a width W <b> 2 larger than the three-dimensional intersection road width W <b> 1 on the fence 4, and then soils on the upper surface in the work band 5. And the L-shaped retaining walls 1a and 1b are arranged (FIG. 15).
[0006]
And after embankment 2 is given between these L-shaped retaining walls 1a and 1b (FIG. 16), the road bed 3 is arrange | positioned on this embankment 2 (FIG. 17). After that, a construction method has been adopted in which the road surface 3 is completed by pavement bridge construction.
[0007]
[Problems to be solved by the invention]
By the way, according to the approach part structure of a three-dimensional intersection road as described above, since the embankment 2 is performed between the L-shaped retaining walls 1a and 1b, not only the earth and sand for this purpose but also the embankment 2 is fixed. Since the road bed 3 cannot be arranged until it is completed, there is a problem that the construction period becomes long. And when constructing approach part D2 of such structure, it is necessary to install work zone 5 which has width W2 larger than level crossing road width W1 beforehand, and, therefore, traffic congestion has arisen over a long period of time.
[0008]
More specifically, the three-dimensional intersection road D is a three-dimensional lane a1, b1 (see FIG. 11) on the inner side of the second road B. In this case, the work zone 5 is located on the outer lanes a2, b2. As a result, traffic on the outside lanes a2 and b2 is restricted, and as a result, traffic congestion occurs. This traffic congestion is caused by the approach unit D2 (FIG. 12). It occurs over a long period of time until completion (for example, 4 months or more).
[0009]
[Means for Solving the Problems]
The present invention has been made to solve the conventional problems as described above, and is configured as follows.
[0010]
First aspect of the present invention, from a bridge portion straddling the existing intersections where a plurality of roads intersect in a plan view, and approach portion which connects the and the bridge portion and the road surface provided on both sides of該橋beam portion In the method of constructing the approach portion of the three-dimensional intersection road , a step of forming a work zone using a part of the inner lane on the road surface on which the approach portion is arranged, and the width of the three-dimensional intersection road on the ground of the work zone A step of laying a bottom plate having a smaller width; a step of arranging side walls on both upper surfaces of the bottom plate; and a side wall using a forklift that travels between the side walls of a precast floor slab having a three-dimensional intersection road width. It is the approach part construction method of the multilevel intersection road characterized by comprising the process of installing on top.
[0015]
According to the approach construction method for a three-dimensional intersection road, the width of the work zone formed on the road surface can be made smaller than the width of the three-dimensional intersection road, resulting in less traffic congestion during construction. can do.
[0017]
According to such a construction method of a three-dimensional intersection road, the precast floor slab is transferred by a lifting machine that moves a work zone between the bottom slab and the side walls arranged on both upper surfaces thereof, and is placed on the side plate, resulting in traffic congestion. There is no.
[0019]
According to the approach construction method of such a three-dimensional intersection road, the precast floor slab is lifted and disposed on the side wall by a forklift, so that it is possible to prevent traffic congestion and shorten the work period by improving workability.
[0020]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the approach structure and construction method of a multilevel intersection road according to the present invention will be described with reference to FIGS. 1 to 10. In these drawings, the same reference numerals as those in FIGS. 11 to 17 denote the same names.
[0021]
FIG. 1 is a cross-sectional view of an approach portion D2 (FIG. 12) constituting a three-dimensional intersection road D. The approach portion D2 includes a precast floor slab 6 having the same width as the width W1 of the three-dimensional intersection road D, The bottom plate 7 has a width W3 smaller than the width W1 of the precast floor slab 6 and is disposed at the center of the second road B, and side walls 8a and 8b disposed on the upper surface of the bottom slab 7. Yes. The precast floor slab 6 is preferably configured by continuously arranging a plurality of short unit precast floor slabs 6a to 6n as shown in FIG.
[0022]
When constructing the approach part D2 of such a three-dimensional intersection road D, first, as shown in FIG. 3 and FIG. 4, the lanes a1 and b1 on the inner side of the second road B are displayed using a display device such as a fence 4. Using a part, the work zone 9 is installed at a place where the approach portion D2 is constructed. And the bottom plate 7 is arrange | positioned (FIG. 5), and side wall 8a, 8b is installed in the both-sides upper surface of this bottom plate 7 after that (FIG. 6).
[0023]
While the bottom plate 7 and the side walls 8a and 8b are installed, the short unit precast floor plates 6a to 6n are manufactured at the factory. Then, when the bottom plate 7 and the side walls 8a, 8b are installed in the construction part of the approach part D2, the fence 4 is moved so that the width W4 of the work zone 9 is slightly smaller than the width W1 of the three-dimensional intersection road D. Modify it to be large.
[0024]
Thereafter, the unit precast slabs 6a to 6n (FIG. 2) are carried in between the side walls 8a and 8b, which are the work belt 9, using the second lifting machine 13 (FIG. 9) such as a forklift, and are placed on the side walls 8a and 8b. (FIGS. 7 and 10).
[0025]
More specifically, the installation of the precast floor slabs 6a to 6n will be described. The precast floor slabs 6a to 6n manufactured at the factory as shown in FIGS. Thus, the first lifting machine 12 such as a hydraulic crane is transferred to the second lifting machine 13. The second lifting machine 13 is preferably a forklift.
[0026]
That is, by using a forklift as the second lifting machine 13, the precast floor slabs 6a to 6n can be installed at predetermined positions by running on a work zone between the two side walls 8a and 8b. Increases efficiency.
[0027]
In such a construction method of the approach portion D2 of the three-dimensional intersection road D, when there is a sidewalk outside the second road B, a part thereof, that is, the inside used for installing the work zone 9 is used. If the width of the lanes a1 and b1 is approximately the same as the width of a part of the lanes, two lanes on both sides can be obtained, and traffic congestion due to such construction hardly occurs.
[0028]
Then, when the precast floor slab 6 is installed on the side walls 8a and 8b (FIGS. 7 and 8), the first work zone 9 and the second work zone 10 are expanded to the width W1 of the three-dimensional intersection road D, thereby lane a1. , B1 is temporarily narrowed, but the period is about ¼ of the entire construction period (for example, 4 months), so there is no heavy traffic congestion.
[0029]
【The invention's effect】
As is apparent from the above description, according to the approach structure of the multilevel intersection road and the construction method thereof according to the present invention, the approach section has the same precast floor slab as the width of the multilevel intersection road and the width of the multilevel intersection road is smaller. Since it is composed of a bottom plate with a width and side walls arranged on both upper surfaces of the bottom plate, not only can the construction work period be shortened, but the range of work zones required for the construction is reduced, especially the width. As a result, the traffic congestion can be prevented.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view of an approach portion structure of a three-dimensional intersection road according to the present invention.
FIG. 2 is a partially cutaway perspective view of an approach structure of a three-dimensional intersection road according to the present invention.
FIG. 3 is a plan view of a road intersection for explaining a method for constructing an approach portion of a three-dimensional intersection road according to the present invention.
FIG. 4 is an explanatory diagram of a work band forming method in the case where the approach construction method for a multilevel intersection road according to the present invention is carried out.
FIG. 5 is an explanatory diagram of an installed state of a bottom plate when the method for constructing an approach portion of a multilevel intersection road according to the present invention is carried out.
FIG. 6 is an explanatory diagram of the installation state of the side plates in the case where the approach construction method for the multilevel intersection road according to the present invention is performed.
FIG. 7 is an explanatory diagram of a precast floor slab installation state when the method for constructing an approach portion of a three-dimensional intersection road according to the present invention is carried out.
FIG. 8 is an explanatory diagram illustrating the completion of installation of a precast floor slab when the method for constructing an approach portion of a multilevel intersection road according to the present invention is performed.
FIG. 9 is a side view showing an installation state of a precast floor slab when the method for constructing an approach portion of a multilevel intersection road according to the present invention is carried out.
FIG. 10 is a plan view of FIG. 9;
FIG. 11 is a perspective view of a road intersection.
FIG. 12 is a side view of a three-dimensional intersection road.
FIG. 13 is a cross-sectional view of a conventional approach portion of a three-dimensional intersection road.
FIG. 14 is an explanatory diagram of work zone installation in a conventional method for constructing an approach portion of a three-dimensional intersection road.
FIG. 15 is an explanatory diagram of L-type retaining wall installation in a conventional method for constructing an approach portion of a three-dimensional intersection road.
FIG. 16 is an explanatory diagram of embankment in a conventional method for constructing an approach portion of a three-dimensional intersection road.
FIG. 17 is an explanatory diagram of roadbed installation in the conventional method of constructing an approach portion of a three-dimensional intersection road.
[Explanation of symbols]
1a, 1b L-type retaining wall 2 Embankment 3 Road floor 4 Fence etc. 5 Work zone 6 Precast floor slab 7 Bottom plate 8a, 8b Side wall 9 Work zone 11 Truck 12 First lifting machine 13 Second lifting machine

Claims (1)

複数の道路が平面的に交差している既設の交差点を跨ぐ橋梁部と、該橋梁部の両側に設けられ且つ前記橋梁部と路面とを連結するアプローチ部とからなる立体交差道路のアプローチ部の建設方法において、前記アプローチ部が配置される路面上に内側車線の一部を利用して作業帯を形成する工程と、該作業帯の地上に立体交差道路の幅より小なる幅を有する底版を敷設する工程と、前記底版の両側上面に側壁を配置する工程と、立体交差道路幅を有するプレキャスト床版を前記両側壁の間を走行するフォークリフトを用いて前記側壁上に設置する工程とよりなることを特徴とする立体交差道路のアプローチ部建設方法。 A bridge portion spanning the intersection of the existing multiple roads intersect in a plane, the approach of the three-dimensional cross road consisting of approach portion which connects the and the bridge portion and the road surface provided on both sides of該橋beam portion In the construction method , a step of forming a work zone using a part of the inner lane on the road surface on which the approach portion is disposed, and a bottom plate having a width smaller than the width of the three-dimensional intersection road on the ground of the work zone. Laying step, placing a side wall on the upper surface on both sides of the bottom slab, and installing a precast floor slab having a three-dimensional intersection road width on the side wall using a forklift that travels between the side walls. A method for constructing an approach section of a three-dimensional intersection road characterized by the above .
JP2003077262A 2003-03-20 2003-03-20 Construction method of approach part of multilevel intersection road Expired - Lifetime JP4029058B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003077262A JP4029058B2 (en) 2003-03-20 2003-03-20 Construction method of approach part of multilevel intersection road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003077262A JP4029058B2 (en) 2003-03-20 2003-03-20 Construction method of approach part of multilevel intersection road

Publications (2)

Publication Number Publication Date
JP2004285627A JP2004285627A (en) 2004-10-14
JP4029058B2 true JP4029058B2 (en) 2008-01-09

Family

ID=33292063

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003077262A Expired - Lifetime JP4029058B2 (en) 2003-03-20 2003-03-20 Construction method of approach part of multilevel intersection road

Country Status (1)

Country Link
JP (1) JP4029058B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4695953B2 (en) * 2005-09-30 2011-06-08 株式会社大林組 Construction method of approach part of viaduct, structure based on construction method of approach part, and structure provided with said structure
JP4969895B2 (en) * 2006-04-10 2012-07-04 三菱重工鉄構エンジニアリング株式会社 Three-dimensional viaduct approach section construction method and three-dimensional viaduct approach section structure
JP7421466B2 (en) 2020-11-05 2024-01-24 株式会社ピーエス三菱 Concrete slab replacement method

Also Published As

Publication number Publication date
JP2004285627A (en) 2004-10-14

Similar Documents

Publication Publication Date Title
JP4029058B2 (en) Construction method of approach part of multilevel intersection road
JP2003213708A (en) Construction method for underground structure and elevated traffic roadway
KR101187369B1 (en) Cip use of underground motorways construction work method
US20100272509A1 (en) Traffic barrier section
JP2005290889A (en) Structure of depressed road and its execution method
JP3857124B2 (en) Road surface lining construction method and lining board used therefor
CN114562129A (en) Trinity reinforcing method for basement roof on crawler crane
JPH0711691A (en) Underground water storage tank
RU2256747C2 (en) Method for forming interface between bridge roadway and embankment
JP2002106054A (en) Inclinable side-ditch block unit body and inclinable side- ditch structure body using the same
JP3343598B2 (en) Hanging wall type retaining wall method for lightweight embankment method
JP2004285799A (en) Construction method of bridge section side span of multi-level crossover road
JP4233025B2 (en) How to construct a three-dimensional intersection
JP4047093B2 (en) Construction method of multilevel intersection road
KR20050089576A (en) Precast concrete block for retaining wall and construction method using the same
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP2003064614A (en) Execution method of expansion joint for road bridge
JP3854545B2 (en) Box-type transportation
JP3824242B2 (en) Viaduct-free support construction method
KR200354133Y1 (en) Precast concrete block for retaining wall
JP2573159B2 (en) How to install a tire washer
JP3619515B2 (en) Split-bridge type traffic road and method for constructing split-bridge type traffic road
JP2005060959A (en) Grade separation construction method
JPH11280008A (en) Precast paving floor board and manufacture thereof
JP2023160289A (en) Temporary lining structure and temporary lining method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050606

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070604

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070612

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070808

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071002

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071015

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101019

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4029058

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101019

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111019

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131019

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141019

Year of fee payment: 7

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term