JP3981308B2 - Exterior wall panel seal structure - Google Patents

Exterior wall panel seal structure Download PDF

Info

Publication number
JP3981308B2
JP3981308B2 JP2002222032A JP2002222032A JP3981308B2 JP 3981308 B2 JP3981308 B2 JP 3981308B2 JP 2002222032 A JP2002222032 A JP 2002222032A JP 2002222032 A JP2002222032 A JP 2002222032A JP 3981308 B2 JP3981308 B2 JP 3981308B2
Authority
JP
Japan
Prior art keywords
joint
packing
hole
wall panel
fixture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002222032A
Other languages
Japanese (ja)
Other versions
JP2004060347A (en
Inventor
禮吉 大辻
良浩 牛原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Coated Sheet Corp
Original Assignee
Nippon Steel Coated Sheet Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Coated Sheet Corp filed Critical Nippon Steel Coated Sheet Corp
Priority to JP2002222032A priority Critical patent/JP3981308B2/en
Publication of JP2004060347A publication Critical patent/JP2004060347A/en
Application granted granted Critical
Publication of JP3981308B2 publication Critical patent/JP3981308B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Building Environments (AREA)
  • Finishing Walls (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、外壁を形成するために壁下地に並べて取り付けられた複数枚の外壁パネルシール構造に関するものである。
【0002】
【従来の技術】
従来より、複数枚の外壁パネルを壁下地の屋外側に略水平あるいは略鉛直に並設することによって、建物の外壁を形成することが行なわれている。このような外壁の隣接する外壁パネル間には屋外側に開口する目地(隙間)が形成されており、この目地には外壁の防水性を高めるために目地パッキンが充填されている。この目地パッキンは二枚の外壁パネルを隣接させて配設した後、外壁パネルの屋外側から目地に目地パッキンを挿入することにより充填されるものである。
【0003】
【発明が解決しようとする課題】
しかし、上記のように外壁パネルの屋外側から目地に目地パッキンを挿入する場合、外壁パネルの屋外側に作業者が入って作業できるスペースが必要であり、また、高所の目地に目地パッキンを挿入しようとする場合にはさらに足場を組むためのスペースも必要であるが、建物が密集している施工現場では外壁パネルの屋外側に上記のようなスペースを確保できないかあるいは非常に狭いスペースしか確保できないことがあり、目地パッキンの施工が行えないあるいは行ないにくいという問題があった。
【0004】
本発明は上記の点に鑑みてなされたものであり、目地パッキンの施工を容易に行うことができる外壁パネルシール構造を提供することを目的とするものであり、特に、外壁パネルの屋外側に充分な作業スペースが確保できない場合に好適に用いることができる外壁パネルシール構造を提供することを目的とするものである。
【0005】
【課題を解決するための手段】
本発明の請求項1に係る外壁パネルシール構造は、壁下地5に取り付けた隣接する外壁パネル1、2間に目地パッキン3を配設してなる外壁パネルシール構造において、ボルト等の固定具4の基端部に支持材6を介して目地パッキン3を取り付け、隣接する外壁パネル1、2間の目地28に固定具4を挿入して係止して目地パッキン3を目地28に配設して成り、
前記支持材6は一対の支持材半体33,33を組み合わせて構成され、前記支持材半体33は、本体部34と、本体部34から屋外側に向かって突出する係止部36とを有し、本体部34の屋内側の背部34aを貫通すると共にこの背部34aの先端に開口する半孔37が形成されており、
固定具4の頭部4aを本体部34に収納するようにして一対の支持材半体33,33を結合して支持材6が形成されると共に固定具4の基端部と支持材6とが連結され、支持材6の係止部36を目地パッキン3の係止溝32に差し込むことで固定具4の基端部に支持材6を介して目地パッキン3が取り付けられていることを特徴とするものであり、外壁パネル1、2より屋内側の作業で目地パッキン3を隣接する外壁パネル1、2間の目地28に配設することができ、外壁パネル1、2の屋外側に充分な作業スペースが確保できない場合でも、目地パッキン3の施工を容易に行うことができるものである。
【0006】
また、本発明の請求項2に係る外壁パネルシール構造は、請求項1に加えて、長尺の支持材6に複数本の固定具4を設け、支持材6の全長に亘って目地パッキン3を取り付けることによって、支持材6を介して固定具4の基端部に目地パッキン3を取り付けて成ることを特徴するものであり、長尺で柔軟性のある目地パッキン3を支持材6で支持しながら隣接する外壁パネル1、2間の目地28に配設することができ、目地パッキン3の施工をさらに容易に行うことができるものである。
【0007】
また、本発明の請求項3に係る外壁パネルシール構造は、請求項1又は2に加えて、目地パッキン3の屋内側に排水樋材7を設けて成ることを特徴とするものであり、目地パッキン3の屋内側に浸入した雨水等の水を排水樋材7で排水することができ、外壁の防水性を高めることができるものである。
【0008】
また、本発明の請求項4に係る外壁パネルシール構造は、請求項3に加えて、排水樋材7に貫通孔8を形成し、貫通孔8を通して固定具4を配設し、貫通孔8と固定具4との隙間を閉塞する貫通孔パッキン9を固定具4の外周に装着して成ることを特徴とするものであり、貫通孔8を通して固定具4を操作することによって目地28に目地パッキン3を配設することができ、目地パッキン3の屋内側に排水樋材7を設けても目地パッキン3の施工性を損なわないようにすることができるものであり、しかも、貫通孔パッキン9で貫通孔8と固定具4との隙間を閉塞することによって、貫通孔8と固定具4との隙間を通じて雨水等の水が排水樋材7の屋内側に浸入するのを防止することができ、排水樋材7に貫通孔8を設けても外壁の防水性を損なわないようにすることができるものである。
【0009】
【発明の実施の形態】
以下、本発明の実施の形態を説明する。
【0010】
図1に略水平方向に隣接する外壁パネル1、2間のシール構造を示す。外壁パネル1、2は表面板20と裏面板21との間に芯材22を充填して形成されるものである。表面板20と裏面板21としては耐食性に優れる金属板を用いることができ、例えば、ステンレス鋼板、亜鉛めっき鋼板、塗装鋼板等の公知のものを用いることができる。また、芯材22としては断熱性及び耐火性に優れるものを用いることができ、例えば、グラスウール、ロックウール、フェノールフォーム、ウレタンフォーム等の公知のものを用いることができる。
【0011】
外壁パネル1、2の側端部には突出片23が略全長に亘って突設されている。突出片23は表面板20の側端部に略水平に延設された延設部24と、延設部24の先端から屋内側に向かって略直角に屈曲形成された密着部25と、密着部25の先端から外側(芯材3と反対側)に向かって略直角に屈曲形成された支え部26とで構成されている。また、突出片23の屋内側の空間、すなわち、芯材22の側端面と延設部24と密着部25で囲まれた空間にはパネルパッキン27が外壁パネル1、2の鉛直方向の略全長に亘って充填されている。
【0012】
そして、突出片23の密着部25を対向させるようにして二枚の外壁パネル1、2を略水平に隣接させることによって、対向する密着部25の間の空間を目地28として形成するものである。また、目地28の屋内側において、隣接する外壁パネル1、2の芯材22、22間の空間は樋収納部30として形成するものである。また、隣接する突出片23の支え部26の先端間には目地28と樋収納部30とを連通させるための間隙29を設けるようにするものである。
【0013】
目地パッキン3はEPDMなどの柔軟性及び弾性のあるゴム材料等で形成されるものである。また、目地パッキン3は鉛直方向に長尺な角材状に形成されていると共に目地パッキン3の両側面には複数個の防水片31が全長に亘って突設されている。さらに、目地パッキン3にはその背面(屋内側面)に開口する係止溝32が全長に亘って形成されている。
【0014】
そして、上記の目地パッキン3は目地28の鉛直方向の全長に亘って充填されている。この時、目地パッキン3の防水片31は屋外側に向かって倒れた状態で両側の密着部25の表面に当接している。また、目地パッキン3の係止溝32の開口の位置は間隙29の位置と合致しており、係止溝32の開口以外において目地パッキン3の背面は両側の支え部26の表面に密着している。
【0015】
上記の目地パッキン3は支持材6に取り付けられて支持されている。支持材6は鉛直方向に長尺に形成されるものであって、支え部26の屋内側において樋収納部30の鉛直方向の略全長に亘って配置されている。支持材6は一対の支持材半体33を組み合わせることにより形成されている。図2(a)に示すように支持材半体33は、断面略コ字状の本体部34と、本体部34から前側(屋外側)に向かって突出する挿入部35と、挿入部35の先端から後側斜め(屋内側斜め)に向かって突出する係止部36とを備えて形成されている。また、図2(b)に示すように、本体部34の背部(屋内側の部分)34aを貫通する半孔37が形成されている。この半孔37は本体部34の背部34aの先端にも開口されている。支持材半体33にはその長手方向に沿って複数個の半孔37が設けられており、隣り合う半孔37の間隔は例えば300mmにすることができる。
【0016】
そして、一対の支持材半体33を係止部36同士が向かい合わないようにして線対称に配置すると共に一対の支持材半体33の挿入部35同士を両面テープ等で接着することによって支持材6を形成することができる。この時、一方の支持材半体33の背部34aと他方の支持材半体33の背部34aとは前後方向(屋内外方向)に重ねられると共に一方の支持材半体33の半孔37と他方の支持材半体33の半孔37とが合致した状態となっている。
【0017】
このようにして形成した支持材6の両方の係止部36を目地パッキン3の係止溝32に背面の開口から差し込んで係止溝32内の開口縁部に係止することによって、支持材6と目地パッキン3を結合することができる。この時、支持材6の本体部34は目地28の背面側(屋内側)に配置されており、支持材6の挿入部35が間隙29を通って目地28内に挿入されており、目地28内において目地パッキン3と支持材6とは上記のように結合されている。
【0018】
支持材6にはボルト等で形成される複数本の固定具4が設けられている。固定具4はその頭部4aを支持材6の本体部34の間の空間に収納されており、固定具4のネジ部4bは支持材6の半孔37から屋内側に突出されている。また、固定具4の頭部4aは半孔37の開口縁部に係止されている。また、固定具4のネジ部4bは排水樋材7と樋下地材38と座金39とを貫通して外壁パネル1、2の屋内側に突出しており、ネジ部4bにナット40を螺合することにより固定具4は座金39に係止されて取り付けられている。
【0019】
排水樋材7は屋外側に開口する断面略コ字状で長尺に形成されるものであって、樋収納部30内に鉛直方向に長く配設されている。また、排水樋材7の端部は外壁パネル1、2のパネルパッキン27の屋内側面に食い込ませている。
【0020】
樋下地材38は、屋内側に開口する断面略ハット状に形成される下地本体41と、下地本体41の開口を閉塞する塞ぎ板42と、下地本体41と塞ぎ板42の間に充填された珪酸カルシウムなどの耐火材43とで長尺に形成されており、排水樋材7の屋内側において樋収納部30内に鉛直方向に長く配設されている。また、樋下地材38の側端部は取付片44として形成されており、取付片44は壁下地5の添え胴縁45と外壁パネル1、2との間に差し込まれて添え胴縁45に固定されている。この樋下地材38は排水樋材7の背面に当接あるいは接着して排水樋材7を支持するものである。
【0021】
また、排水樋材7の背部7a及び樋下地材38には屋内外方向に貫通する複数個の貫通孔8が形成されており、各貫通孔8には固定具4のネジ部4bが挿通されている。また、排水樋材7の背部7aと支持材6の本体部34との間において固定具4のネジ部4bには貫通孔パッキン9が装着されており、この貫通孔パッキン9を排水樋材7の背部7aの屋外側面に密着させることによって、排水樋材7の背部7aに形成された貫通孔8の開口縁部と固定具4のネジ部4bとの間の隙間が閉塞されている。
【0022】
座金39は隣接する壁下地5の添え胴縁45の間に架設されている。
【0023】
次に、上記のような外壁パネルのシール構造の施工方法の一例を説明する。
【0024】
壁下地5は胴縁46及び添え胴縁45とで構成されている。胴縁46はリップ溝型鋼等で形成されるものであって、鉛直方向に長く配設されている。添え胴縁45はL型鋼等で形成されるものであって、鉛直方向に長く配設されると共に胴縁46の側面に固着されている。このような複数本の壁下地5は所定の間隔を介して水平方向に並べて配設されている。
【0025】
また、目地パッキン3、支持体6、固定具4、貫通孔パッキン9は施工する前に予め組み立てておく。この組み立ては次のようにして行なう。まず、一対の支持材半体33の本体部34内に固定具4の頭部4aを収納するようにして一対の支持材半体33を結合して支持材6を形成すると共に複数個の固定具4の基端部と支持材6とを連結する。次に、各固定具4のネジ部4bに貫通孔パッキン9を差し込んで挿着する。また、支持材6の係止部36を目地パッキン3の係止溝32に差し込んで係止溝32内の開口縁部に係止することによって、固定具4の基端部に支持材6を介して目地パッキン3を取り付ける。このようにして目地パッキン3、支持体6、固定具4、貫通孔パッキン9からなる組み合わせ体55を形成する。
【0026】
また、排水樋材7と樋下地材38は施工する前に予め組み立てておく。この組み立ては、樋下地材38の下地本体41の屋外側面に排水樋材7の屋内側面(背面)を接着等することによって行うことができる。
【0027】
そして、まず、排水樋材7と樋下地材38を組み立てたものを隣り合う添え胴縁45、45の屋外側に配置し、樋下地材38の取付片44を添え胴縁45にビス等の固定具で固定することによって、排水樋材7と樋下地材38を隣り合う添え胴縁45、45に亘るように取り付けられるものであり、排水樋材7及び樋下地材38は隣り合う添え胴縁45、45の先端間の間隙56の屋外側に位置するものである。次に、排水樋材7の背部7aと樋下地材38とを貫通する貫通孔8を屋内側より形成する。この貫通孔8の屋内側の開口は隣り合う添え胴縁45、45の先端間の間隙56に露出するように形成されている。尚、この貫通孔8は排水樋材7と樋下地材38を添え胴縁45に取り付ける前に形成しておいてもよい。
【0028】
次に、一方の外壁パネル1に固定ボルト50を設ける。固定ボルト50は外壁パネル1の側端部を厚み方向に貫通するように挿着されるものであり、固定ボルト50の頭部51は外壁パネル1の屋外側面に設けた水平方向の凹溝52内に収納されている。次に、固定ボルト50を設けた外壁パネル1を壁下地5の屋外側に配置する。外壁パネル1の配置は壁下地5の屋外側から行なうようにする。次に、外壁パネル1の屋内側面に突出した固定ボルト50の先端を添え胴縁45のボルト孔53に屋外側から挿入すると共に添え胴縁45の屋内側に突出した固定ボルト50の先端に固定ナット54を螺合する。このようにして外壁パネル1を壁下地5に取り付けて固定する。この時、樋下地材38の一方の取付片44は外壁パネル1と壁下地5の添え胴縁45の間に介在すると共に排水樋材7の一方の先端は外壁パネル1のパネルパッキン27に弾接するものである。
【0029】
上記のようにして一方の外壁パネル1を壁下地5に取り付けた後、組み合わせ体55の配置を壁下地5の屋外側から行なう。つまり、図3に示すように、組み合わせ体55の固定具4のネジ部4bを貫通孔8に屋外側の開口から挿入し、貫通孔8の屋内側の開口及び間隙56を通して固定具4のネジ部4bを添え胴縁45よりも屋内側に突出させる。次に、固定具4のネジ部4bを添え胴縁45よりも屋内側から引張ることにより、貫通孔パッキン9と支持材6及び目地パッキン3を屋内側方向に向かって移動させる。このようにして貫通孔パッキン9を排水樋材7の背部7aの屋外側面に当接させると共に目地パッキン3を外壁パネル1の密着部25の外面と支え部26の屋外側面に当接させるものであり、これにより、目地28となる箇所に目地パッキン3が配置される。また、支持具6及び貫通孔パッキン9は壁下地5に取り付けた外壁パネル1の支え部26と排水樋材7の背部7aとの間に配置される。
【0030】
次に、上記外壁パネル1とは別の外壁パネル2を取り付ける。この外壁パネル2は上記外壁パネル1を取り付けた壁下地5と隣接する他の壁下地5に取り付けられるものである。また、外壁パネル2にも上記外壁パネル1と同様に固定ボルト50が設けられている。そして、固定ボルト50を設けた外壁パネル2を壁下地5の屋外側に配置する。外壁パネル2の配置も壁下地5の屋外側から行なうようにする。次に、外壁パネル2の屋内側面に突出した固定ボルト50の先端を上記添え胴縁45と隣接する他の添え胴縁45のボルト孔53に屋外側から挿入すると共に添え胴縁45の屋内側に突出した固定ボルト50の先端に固定ナット54を螺合する。このようにして外壁パネル2を壁下地5に取り付けて固定する。この時、外壁パネル1と外壁パネル2は側端部同士が対向するように配設される。また、樋下地材38のもう一方の取付片44は外壁パネル2と壁下地5の添え胴縁45の間に挿入されると共に排水樋材7のもう一方の先端は外壁パネル2のパネルパッキン27に弾接させるようにする。さらに、外壁パネル2の支え部26を上記のように配置した目地パッキン3と支持体6の間に差し込んで、目地パッキン3を外壁パネル2の密着部25の外面と支え部26の屋外側面に当接させる。
【0031】
次に、添え胴縁45よりも屋内側に突出する固定具4のネジ部4bに座金39を装着すると共に座金39よりも屋内側に突出する固定具4のネジ部4bにナット40を螺合して締め付けることによって、固定具4を座金39に係止して固定する。また、このナット40の締め付けにより、固定具4が屋内側から引張られて貫通孔パッキン9と支持材6及び目地パッキン3を屋内側方向に向かって移動することになり、これにより、貫通孔パッキン9を排水樋材7の背部7aの屋外側面に密着させることができ、貫通孔8の屋外側の開口と固定具4のネジ部4bとの間の隙間を閉塞することができると共に、目地パッキン3を外壁パネル1、2の密着部25の外面と支え部26の屋外側面に密着させることができるものである。
【0032】
そして、上記の外壁パネル1、2の施工を順次繰り返していくことにより、複数枚の外壁パネル1、2で建物の外壁を形成することができるものである。
【0033】
図4に他の実施の形態を示す。この実施の形態は目地パッキン3の形状及び支持材6の形状が上記実施の形態と異なり、その他の構成は上記実施の形態と同様である。目地パッキン3の係止溝32は断面略T字状に形成されており、従って、支持材6の挿入部35及び係止部36も断面略T字状に形成されている。また、目地パッキン3の厚み寸法(屋内外方向の寸法)は目地28の深さ寸法(屋内外方向の寸法)とほぼ同じに形成されており、従って、目地28に目地パッキン3を充填すると、外壁パネル1、2の屋外側面と目地パッキン3の屋外側面とがほぼ面一となるものである。また、目地パッキン3の屋内側面にはシーリングテープ58が貼り付けてあって、シーリングテープ58が支え部26に密着することになってさらに防水性を高めることができるものである。
【0034】
尚、上記では鉛直方向に長い目地28について説明したが、本発明は水平方向に長い目地に適用することも可能である。
【0035】
【発明の効果】
上記のように本発明の請求項1の発明は、壁下地に取り付けた隣接する外壁パネル間に目地パッキンを配設してなる外壁パネルシール構造において、ボルト等の固定具の基端部に支持材を介して目地パッキンを取り付け、隣接する外壁パネル間の目地に固定具を挿入して係止して目地パッキンを目地に配設して成り、前記支持材は一対の支持材半体を組み合わせて構成され、前記支持材半体は、本体部と、本体部から屋外側に向かって突出する係止部とを有し、本体部の屋内側の背部を貫通すると共にこの背部の先端に開口する半孔が形成されており、固定具の頭部を本体部に収納するようにして一対の支持材半体を結合して支持材が形成されると共に固定具の基端部と支持材とが連結され、支持材の係止部を目地パッキンの係止溝に差し込むことで固定具の基端部に支持材を介して目地パッキンが取り付けられていることを特徴とするものであり、目地への目地パッキンの施工を容易に行うことができるものであり、特に、外壁パネルの屋内側の作業で目地パッキンを隣接する外壁パネル間に配設することができ、外壁パネルの屋外側に充分な作業スペースが確保できない場合でも、目地パッキンの施工を容易に行うことができるものである。
【0036】
また、本発明の請求項2の発明は、長尺の支持材に複数本の固定具を設け、支持材の全長に亘って目地パッキンを取り付けることによって、支持材を介して固定具の基端部に目地パッキンを取り付けて成ることを特徴するものであり、長尺で柔軟性のある目地パッキンを支持材で支持しながら隣接する外壁パネル間の目地に配設することができ、目地パッキンの施工をさらに容易に行うことができるものである。
【0037】
また、本発明の請求項3の発明は、目地パッキンの屋内側に排水樋材を設けて成ることを特徴とするものであり、目地パッキンの屋内側に浸入した雨水等の水を排水樋材で排水することができ、外壁の防水性を高めることができるものである。
【0038】
また、本発明の請求項4の発明は、排水樋材に貫通孔を形成し、貫通孔を通して固定具を配設し、貫通孔と固定具との隙間を閉塞する貫通孔パッキンを固定具の外周に装着して成ることを特徴とするものであり、貫通孔を通して固定具を操作することによって目地に目地パッキンを配設することができ、目地パッキンの屋内側に排水樋材を設けても目地パッキンの施工性を損なわないようにすることができるものであり、しかも、貫通孔パッキンで貫通孔と固定具との隙間を閉塞することによって、貫通孔と固定具との隙間を通じて雨水等の水が排水樋材の屋内側に浸入するのを防止することができ、排水樋材に貫通孔を設けても外壁の防水性を損なわないようにすることができるものである。
【図面の簡単な説明】
【図1】本発明の実施の形態の一例を示す断面図である。
【図2】同上の支持材を示し、(a)は断面図、(b)は一部の正面図である。
【図3】同上の施工途中を示す断面図である。
【図4】同上の他の実施の形態の施工途中を示す断面図である。
【符号の説明】
1 外壁パネル
2 外壁パネル
3 目地パッキン
4 固定具
5 壁下地
6 支持材
7 排水樋材
8 貫通孔
9 貫通孔パッキン
28 目地
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a plurality of outer wall panel seal structures mounted side by side on a wall base to form an outer wall.
[0002]
[Prior art]
Conventionally, an outer wall of a building has been formed by arranging a plurality of outer wall panels substantially horizontally or substantially vertically on the outdoor side of the wall base. A joint (gap) that opens to the outdoor side is formed between adjacent outer wall panels of such an outer wall, and the joint is filled with joint packing to enhance the waterproofness of the outer wall. The joint packing is provided by placing two outer wall panels adjacent to each other and then inserting the joint packing into the joint from the outside side of the outer wall panel.
[0003]
[Problems to be solved by the invention]
However, when the joint packing is inserted from the outdoor side of the outer wall panel to the joint as described above, there is a need for a space where an operator can enter and work on the outdoor side of the outer wall panel, and the joint packing is attached to the joint at a high place. When trying to insert, a space for assembling the scaffold is also necessary, but at the construction site where the building is densely packed, the above space cannot be secured on the outdoor side of the outer wall panel or only a very narrow space There was a problem that joint packing could not be performed or it was difficult to perform.
[0004]
The present invention has been made in view of the above points, and an object of the present invention is to provide an outer wall panel seal structure capable of easily performing joint packing, and particularly on the outdoor side of the outer wall panel. An object of the present invention is to provide an outer wall panel seal structure that can be suitably used when a sufficient working space cannot be secured.
[0005]
[Means for Solving the Problems]
The outer wall panel seal structure according to claim 1 of the present invention is an outer wall panel seal structure in which a joint packing 3 is disposed between adjacent outer wall panels 1 and 2 attached to a wall base 5, and a fixture 4 such as a bolt. The joint packing 3 is attached to the base end portion of the base plate through the support member 6, and the fixture 4 is inserted into the joint 28 between the adjacent outer wall panels 1 and 2 to be locked to dispose the joint packing 3 on the joint 28. adult Te is,
The support member 6 is configured by combining a pair of support member halves 33, 33. The support member half member 33 includes a main body part 34 and a locking part 36 that protrudes from the main body part 34 toward the outdoor side. A half hole 37 is formed which penetrates the indoor side back 34a of the main body 34 and opens at the tip of the back 34a.
A pair of support material halves 33 and 33 are coupled so that the head portion 4a of the fixture 4 is housed in the main body portion 34 to form a support material 6, and the base end portion of the fixture 4 and the support material 6 features There are connected, the Rukoto have an engagement portion 36 of the support 6 is joint packing 3 is mounted via a support member 6 to the base end portion of the fixture 4 by inserting the locking groove 32 of the joint packing 3 The joint packing 3 can be disposed in the joint 28 between the adjacent outer wall panels 1 and 2 by work on the indoor side from the outer wall panels 1 and 2, and is sufficient for the outdoor side of the outer wall panels 1 and 2. Even when a simple work space cannot be secured, the joint packing 3 can be easily constructed.
[0006]
In addition to the first aspect, the outer wall panel seal structure according to the second aspect of the present invention is provided with a plurality of fixtures 4 on the long support member 6, and the joint packing 3 over the entire length of the support member 6. It is characterized in that the joint packing 3 is attached to the base end portion of the fixture 4 through the support member 6, and the long and flexible joint packing 3 is supported by the support member 6. However, it can arrange | position in the joint 28 between the outer wall panels 1 and 2 which adjoin, and construction of the joint packing 3 can be performed still more easily.
[0007]
Further, the outer wall panel seal structure according to claim 3 of the present invention is characterized in that, in addition to claim 1 or 2, a drainage dredge material 7 is provided on the indoor side of the joint packing 3, Water such as rain water that has entered the indoor side of the packing 3 can be drained by the drainage trough 7 and the waterproofness of the outer wall can be improved.
[0008]
In addition to the third aspect, the outer wall panel seal structure according to the fourth aspect of the present invention has a through hole 8 formed in the drainage dredger material 7 and the fixture 4 is disposed through the through hole 8. A through-hole packing 9 that closes the gap between the fixing tool 4 and the fixing tool 4 is mounted on the outer periphery of the fixing tool 4. By operating the fixing tool 4 through the through-hole 8, the joint 28 is connected to the joint 28. The packing 3 can be disposed, and even if the drainage dredging material 7 is provided on the indoor side of the joint packing 3, the workability of the joint packing 3 can be maintained, and the through-hole packing 9 is provided. By closing the gap between the through hole 8 and the fixture 4, it is possible to prevent water such as rainwater from entering the indoor side of the drainage dredger 7 through the gap between the through hole 8 and the fixture 4. Even if the through hole 8 is provided in the drainage dredging material 7, the waterproofness of the outer wall is maintained. It is capable to prevent rope.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below.
[0010]
FIG. 1 shows a seal structure between outer wall panels 1 and 2 adjacent to each other in a substantially horizontal direction. The outer wall panels 1 and 2 are formed by filling a core material 22 between the front plate 20 and the back plate 21. As the front plate 20 and the back plate 21, a metal plate having excellent corrosion resistance can be used. For example, a known plate such as a stainless steel plate, a galvanized steel plate, or a coated steel plate can be used. Moreover, as the core material 22, a material having excellent heat insulation and fire resistance can be used. For example, known materials such as glass wool, rock wool, phenol foam, urethane foam, and the like can be used.
[0011]
Protruding pieces 23 project from the side end portions of the outer wall panels 1 and 2 over substantially the entire length. The projecting piece 23 includes an extended portion 24 that extends substantially horizontally at a side end portion of the surface plate 20, a close contact portion 25 that is bent at a substantially right angle from the tip of the extended portion 24 toward the indoor side, and a close contact It is comprised by the support part 26 bent and formed in the substantially right angle toward the outer side (opposite side to the core material 3) from the front-end | tip of the part 25. FIG. In addition, the panel packing 27 is provided in the space on the indoor side of the projecting piece 23, that is, the space surrounded by the side end surface of the core member 22, the extended portion 24, and the contact portion 25. Is filled.
[0012]
Then, the two outer wall panels 1 and 2 are adjoined substantially horizontally so that the close contact portion 25 of the projecting piece 23 is opposed to each other, thereby forming a space between the facing close contact portions 25 as a joint 28. . Further, on the indoor side of the joint 28, the space between the core members 22, 22 of the adjacent outer wall panels 1, 2 is formed as the bag storage unit 30. Further, a gap 29 is provided between the tips of the support portions 26 of the adjacent projecting pieces 23 to allow the joint 28 and the heel storage portion 30 to communicate with each other.
[0013]
The joint packing 3 is formed of a flexible and elastic rubber material such as EPDM. Further, the joint packing 3 is formed in a rectangular shape that is long in the vertical direction, and a plurality of waterproof pieces 31 are provided on both side surfaces of the joint packing 3 so as to protrude over the entire length. Further, the joint packing 3 is formed with a locking groove 32 that opens on the back surface (inside side surface) of the joint packing 3 over the entire length.
[0014]
The joint packing 3 is filled over the entire length of the joint 28 in the vertical direction. At this time, the waterproof piece 31 of the joint packing 3 is in contact with the surfaces of the contact portions 25 on both sides in a state of being inclined toward the outdoor side. Further, the position of the opening of the locking groove 32 of the joint packing 3 coincides with the position of the gap 29, and the back surface of the joint packing 3 is in close contact with the surfaces of the support portions 26 on both sides except for the opening of the locking groove 32. Yes.
[0015]
The joint packing 3 is attached to and supported by a support material 6. The support member 6 is formed to be long in the vertical direction, and is disposed over substantially the entire length in the vertical direction of the bag storage portion 30 on the indoor side of the support portion 26. The support member 6 is formed by combining a pair of support member halves 33. As shown in FIG. 2A, the support member half 33 includes a main body part 34 having a substantially U-shaped cross section, an insertion part 35 projecting from the main body part 34 toward the front side (outdoor side), and the insertion part 35. It is formed with a locking portion 36 protruding from the front end toward the rear diagonal (indoor diagonal). Moreover, as shown in FIG.2 (b), the half hole 37 which penetrates the back part (part on the indoor side) 34a of the main-body part 34 is formed. The half hole 37 is also opened at the tip of the back part 34 a of the main body part 34. The support half member 33 is provided with a plurality of half holes 37 along the longitudinal direction thereof, and the interval between the adjacent half holes 37 can be set to, for example, 300 mm.
[0016]
The pair of support member halves 33 are arranged in line symmetry so that the locking portions 36 do not face each other, and the insertion portions 35 of the pair of support member halves 33 are bonded to each other with a double-sided tape or the like. 6 can be formed. At this time, the back portion 34a of one support member half 33 and the back portion 34a of the other support member half 33 are overlapped in the front-rear direction (indoor / outdoor direction) and the half hole 37 of one support member half 33 and the other This is in a state where the half hole 37 of the support material half 33 matches.
[0017]
By inserting both locking portions 36 of the support member 6 formed in this way into the locking groove 32 of the joint packing 3 from the opening on the back surface and locking it to the opening edge in the locking groove 32, the supporting material 6 and the joint packing 3 can be combined. At this time, the main body 34 of the support member 6 is disposed on the back side (indoor side) of the joint 28, and the insertion portion 35 of the support member 6 is inserted into the joint 28 through the gap 29. Inside, the joint packing 3 and the support material 6 are combined as described above.
[0018]
The support member 6 is provided with a plurality of fixtures 4 formed of bolts or the like. The fixture 4 has its head portion 4 a housed in a space between the main body portions 34 of the support member 6, and the screw portion 4 b of the fixture 4 projects from the half hole 37 of the support member 6 to the indoor side. Further, the head 4 a of the fixture 4 is locked to the opening edge of the half hole 37. Further, the screw portion 4b of the fixture 4 penetrates the drainage dredging material 7, the dredging base material 38, and the washer 39 and protrudes to the indoor side of the outer wall panels 1 and 2, and the nut 40 is screwed into the screw portion 4b. Thus, the fixture 4 is locked and attached to the washer 39.
[0019]
The drainage dredging material 7 is formed in a long shape with a substantially U-shaped cross section that opens to the outdoor side, and is disposed long in the vertical direction in the dredge storage portion 30. Further, the end portion of the drainage dredger 7 bites into the indoor side surface of the panel packing 27 of the outer wall panels 1 and 2.
[0020]
The base material 38 is filled between the base body 41 and the closing plate 42, the base body 41 having a substantially hat-shaped cross section that opens to the indoor side, the closing plate 42 that closes the opening of the base body 41, and It is formed long with a refractory material 43 such as calcium silicate, and is long in the vertical direction in the tub storage portion 30 on the indoor side of the drainage ridge material 7. Further, the side edge portion of the eaves base material 38 is formed as an attachment piece 44, and the attachment piece 44 is inserted between the accessory drum edge 45 of the wall foundation 5 and the outer wall panels 1, 2 to the accessory drum edge 45. It is fixed. This dredging base material 38 supports the drainage dredging material 7 by contacting or bonding to the back surface of the drainage dredging material 7.
[0021]
In addition, a plurality of through holes 8 are formed in the back portion 7a of the drainage dredger material 7 and the dredging base material 38 so as to penetrate in the indoor and outdoor directions, and the screw portion 4b of the fixture 4 is inserted into each through hole 8. ing. A through-hole packing 9 is attached to the screw portion 4 b of the fixture 4 between the back portion 7 a of the drainage dredger 7 and the main body 34 of the support member 6. By closely adhering to the outdoor side surface of the back portion 7a, the gap between the opening edge portion of the through hole 8 formed in the back portion 7a of the drainage dredger material 7 and the screw portion 4b of the fixture 4 is closed.
[0022]
The washer 39 is constructed between the accessory drum edges 45 of the adjacent wall base 5.
[0023]
Next, an example of the construction method of the sealing structure of the above outer wall panel is demonstrated.
[0024]
The wall base 5 is composed of a body edge 46 and an attached body edge 45. The trunk edge 46 is formed of lip groove steel or the like and is long in the vertical direction. The accessory cylinder edge 45 is formed of L-shaped steel or the like, and is provided long in the vertical direction and fixed to the side surface of the cylinder edge 46. Such a plurality of wall bases 5 are arranged in a horizontal direction at a predetermined interval.
[0025]
Further, the joint packing 3, the support 6, the fixture 4, and the through hole packing 9 are assembled in advance before construction. This assembly is performed as follows. First, the support member 6 is formed by combining the pair of support member halves 33 so that the head part 4a of the fixture 4 is housed in the main body part 34 of the pair of support member halves 33, and a plurality of fixed members are fixed. The base end part of the tool 4 and the support material 6 are connected. Next, the through-hole packing 9 is inserted into the screw portion 4b of each fixture 4 and attached. Further, by inserting the locking portion 36 of the support material 6 into the locking groove 32 of the joint packing 3 and locking it to the opening edge in the locking groove 32, the support material 6 is attached to the base end portion of the fixture 4. The joint packing 3 is attached via In this way, a combined body 55 including the joint packing 3, the support 6, the fixture 4, and the through-hole packing 9 is formed.
[0026]
Further, the drainage dredging material 7 and the dredging base material 38 are assembled in advance before construction. This assembly can be performed by bonding the indoor side surface (rear surface) of the drainage dredger material 7 to the outdoor side surface of the base body 41 of the dredger base material 38.
[0027]
First, an assembly of the drainage dredging material 7 and the dredging base material 38 is disposed on the outdoor side of the adjacent accessory drum edges 45, 45, and the attachment piece 44 of the dredging foundation material 38 is attached to the accessory drum edge 45 with screws or the like. By fixing with the fixing tool, the drainage dredging material 7 and the dredging base material 38 are attached so as to extend over the adjacent accessory cylinder edges 45, 45. It is located on the outdoor side of the gap 56 between the tips of the edges 45, 45. Next, the through-hole 8 that penetrates the back portion 7a of the drainage dredging material 7 and the dredging base material 38 is formed from the indoor side. The opening on the indoor side of the through hole 8 is formed so as to be exposed in the gap 56 between the tips of the adjacent accessory drum edges 45, 45. The through-hole 8 may be formed before the drainage dredging material 7 and the dredging base material 38 are attached to the accessory cylinder edge 45.
[0028]
Next, the fixing bolt 50 is provided on one outer wall panel 1. The fixing bolt 50 is inserted so as to penetrate the side end of the outer wall panel 1 in the thickness direction, and the head 51 of the fixing bolt 50 is a horizontal groove 52 provided on the outdoor side surface of the outer wall panel 1. It is stored inside. Next, the outer wall panel 1 provided with the fixing bolt 50 is disposed on the outdoor side of the wall base 5. The outer wall panel 1 is arranged from the outdoor side of the wall base 5. Next, the front end of the fixing bolt 50 protruding to the indoor side surface of the outer wall panel 1 is inserted from the outdoor side into the bolt hole 53 of the accessory drum edge 45 and fixed to the tip of the fixing bolt 50 protruding to the indoor side of the accessory drum edge 45. The nut 54 is screwed. In this way, the outer wall panel 1 is attached and fixed to the wall base 5. At this time, one attachment piece 44 of the dredging base material 38 is interposed between the outer wall panel 1 and the attachment drum edge 45 of the wall base 5 and one end of the drainage dredging material 7 is elastically applied to the panel packing 27 of the outer wall panel 1. It touches.
[0029]
After the one outer wall panel 1 is attached to the wall base 5 as described above, the combination body 55 is arranged from the outdoor side of the wall base 5. That is, as shown in FIG. 3, the screw portion 4 b of the fixture 4 of the combination body 55 is inserted into the through hole 8 from the outdoor side opening, and the screw of the fixture 4 is passed through the indoor side opening and the gap 56 of the through hole 8. The portion 4b is projected to the indoor side with respect to the attached drum edge 45. Next, the through-hole packing 9, the support member 6, and the joint packing 3 are moved toward the indoor side by pulling the screw portion 4 b of the fixture 4 from the indoor side with respect to the accessory cylinder edge 45. In this way, the through-hole packing 9 is brought into contact with the outdoor side surface of the back part 7a of the drainage dredging material 7, and the joint packing 3 is brought into contact with the outer surface of the close contact portion 25 of the outer wall panel 1 and the outdoor side surface of the support portion 26. With this, the joint packing 3 is disposed at a place to be the joint 28. Further, the support 6 and the through-hole packing 9 are disposed between the support portion 26 of the outer wall panel 1 attached to the wall base 5 and the back portion 7 a of the drainage dredger material 7.
[0030]
Next, the outer wall panel 2 different from the outer wall panel 1 is attached. The outer wall panel 2 is attached to a wall base 5 to which the outer wall panel 1 is attached and another wall base 5 adjacent thereto. The outer wall panel 2 is also provided with a fixing bolt 50 as in the outer wall panel 1. Then, the outer wall panel 2 provided with the fixing bolt 50 is disposed on the outdoor side of the wall base 5. The outer wall panel 2 is also arranged from the outdoor side of the wall base 5. Next, the front end of the fixing bolt 50 protruding to the indoor side surface of the outer wall panel 2 is inserted from the outdoor side into the bolt hole 53 of the other accessory drum edge 45 adjacent to the accessory drum edge 45 and the indoor side of the accessory drum edge 45. A fixing nut 54 is screwed onto the tip of the fixing bolt 50 protruding to the front. In this way, the outer wall panel 2 is attached to the wall base 5 and fixed. At this time, the outer wall panel 1 and the outer wall panel 2 are disposed so that the side ends face each other. Further, the other attachment piece 44 of the dredging base material 38 is inserted between the outer wall panel 2 and the attachment drum edge 45 of the wall base 5 and the other end of the drainage dredging material 7 is the panel packing 27 of the outer wall panel 2. To make it elastic. Further, the support portion 26 of the outer wall panel 2 is inserted between the joint packing 3 and the support body 6 arranged as described above, and the joint packing 3 is placed between the outer surface of the contact portion 25 of the outer wall panel 2 and the outdoor side surface of the support portion 26. Make contact.
[0031]
Next, the washer 39 is attached to the screw portion 4b of the fixture 4 protruding to the indoor side from the accessory drum edge 45, and the nut 40 is screwed to the screw portion 4b of the fixture 4 protruding to the indoor side of the washer 39. Then, the fixing tool 4 is locked and fixed to the washer 39 by tightening. Further, by tightening the nut 40, the fixture 4 is pulled from the indoor side, and the through-hole packing 9, the support material 6, and the joint packing 3 are moved toward the indoor side, whereby the through-hole packing is obtained. 9 can be brought into close contact with the outdoor side surface of the back portion 7a of the drainage dredging material 7, and the gap between the outdoor side opening of the through hole 8 and the screw portion 4b of the fixture 4 can be closed, and the joint packing 3 can be brought into close contact with the outer surface of the contact portion 25 of the outer wall panels 1 and 2 and the outdoor side surface of the support portion 26.
[0032]
And the outer wall of a building can be formed with a plurality of outer wall panels 1 and 2 by repeating the construction of the outer wall panels 1 and 2 sequentially.
[0033]
FIG. 4 shows another embodiment. In this embodiment, the shape of the joint packing 3 and the shape of the support member 6 are different from those of the above embodiment, and other configurations are the same as those of the above embodiment. The locking groove 32 of the joint packing 3 is formed in a substantially T-shaped cross section, and therefore the insertion portion 35 and the locking portion 36 of the support member 6 are also formed in a substantially T-shaped cross section. Further, the thickness dimension (dimension in the indoor / outdoor direction) of the joint packing 3 is formed to be substantially the same as the depth dimension (dimension in the indoor / outdoor direction) of the joint 28. Therefore, when the joint packing 3 is filled in the joint 28, The outdoor side surfaces of the outer wall panels 1 and 2 and the outdoor side surface of the joint packing 3 are substantially flush with each other. Moreover, the sealing tape 58 is affixed on the indoor side surface of the joint packing 3, and the sealing tape 58 comes into close contact with the support portion 26, so that the waterproof property can be further improved.
[0034]
In the above description, the joint 28 that is long in the vertical direction has been described. However, the present invention can also be applied to joints that are long in the horizontal direction.
[0035]
【The invention's effect】
As described above, the invention according to claim 1 of the present invention supports an outer wall panel seal structure in which joint packing is disposed between adjacent outer wall panels attached to a wall base, and is supported on a base end portion of a fixture such as a bolt. Attach the joint packing through the wood, Ri formed by arranging the joint packing joints engaged by inserting a fixture in the joints between adjacent exterior wall panel, said support material a pair of support halves The supporting material half has a main body part and a locking part that protrudes from the main body part toward the outdoor side, and penetrates the back part on the indoor side of the main body part and at the tip of the back part. An opening half hole is formed, a support member is formed by combining a pair of support member halves so that the head of the fixture is housed in the main body, and the base end portion of the fixture and the support member Are inserted into the locking groove of the joint packing. Joint packing through the support member to the base end portion of the fastener by are those that characterized that you have installed, which can perform application of joint packing into joints easily, in particular, The joint packing can be installed between adjacent outer wall panels in the work on the indoor side of the outer wall panel, and even if a sufficient work space cannot be secured on the outdoor side of the outer wall panel, the joint packing can be easily installed. It can be done.
[0036]
Moreover, the invention of claim 2 of the present invention provides a base end of the fixture through the support material by providing a plurality of fixtures on the long support material and attaching joint packing over the entire length of the support material. It is characterized in that the joint packing is attached to the part, and the long and flexible joint packing can be disposed in the joint between the adjacent outer wall panels while being supported by the support material. Construction can be performed more easily.
[0037]
The invention of claim 3 of the present invention is characterized in that a drainage dredge material is provided on the indoor side of the joint packing, and water such as rainwater that has entered the indoor side of the joint packing is used as a drainage dredge material. It is possible to drain the water and improve the waterproofness of the outer wall.
[0038]
According to a fourth aspect of the present invention, a through hole is formed in the drainage dredger material, a fixing tool is disposed through the through hole, and a through hole packing that closes a gap between the through hole and the fixing tool is provided on the fixing tool. It is characterized by being mounted on the outer periphery, and the joint packing can be disposed on the joint by operating the fixing tool through the through hole, and the drainage dredging material can be provided on the indoor side of the joint packing. It is possible to prevent the workability of the joint packing from being impaired, and by closing the gap between the through hole and the fixture with the through hole packing, the rainwater and the like can be passed through the gap between the through hole and the fixture. Water can be prevented from entering the indoor side of the drainage dredger, and even if the drainage dredger is provided with a through hole, the waterproof property of the outer wall can be prevented.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing an example of an embodiment of the present invention.
FIGS. 2A and 2B show the same support material, wherein FIG. 2A is a cross-sectional view and FIG. 2B is a partial front view.
FIG. 3 is a cross-sectional view showing the construction in progress.
FIG. 4 is a cross-sectional view showing the middle of construction of another embodiment of the above.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Exterior wall panel 2 Exterior wall panel 3 Joint packing 4 Fixture 5 Wall base 6 Support material 7 Drainage material 8 Through-hole 9 Through-hole packing 28 Joint

Claims (4)

壁下地に取り付けた隣接する外壁パネル間に目地パッキンを配設してなる外壁パネルシール構造において、ボルト等の固定具の基端部に支持材を介して目地パッキンを取り付け、隣接する外壁パネル間の目地に固定具を挿入して係止して目地パッキンを目地に配設して成り、
前記支持材は一対の支持材半体を組み合わせて構成され、前記支持材半体は、本体部と、本体部から屋外側に向かって突出する係止部とを有し、本体部の屋内側の背部を貫通すると共にこの背部の先端に開口する半孔が形成されており、
固定具の頭部を本体部に収納するようにして一対の支持材半体を結合して支持材が形成されると共に固定具の基端部と支持材とが連結され、支持材の係止部を目地パッキンの係止溝に差し込むことで固定具の基端部に支持材を介して目地パッキンが取り付けられていることを特徴とする外壁パネルシール構造。
In an outer wall panel seal structure in which joint gaskets are arranged between adjacent outer wall panels attached to the wall base, joint gaskets are attached to the base end of a fixture such as a bolt via a support material, and between adjacent outer wall panels. to the joint by inserting a fixture Ri formed by arranging the joint packing joints engaged,
The support member is configured by combining a pair of support member halves, and the support member half member includes a main body part and a locking part protruding from the main body part toward the outdoor side, and the indoor side of the main body part. A half hole is formed that penetrates the back of the back and opens at the tip of the back.
A pair of supporting material halves are joined together so that the head of the fixing device is housed in the main body, and the supporting material is formed, and the base end portion of the fixing device and the supporting material are connected, and the supporting material is locked. external wall panels seal structure characterized that you have the joint packing attached to part through the support member to the base end portion of the fixture by inserting the engaging groove of the joint packing.
長尺の支持材に複数本の固定具を設け、支持材の全長に亘って目地パッキンを取り付けることによって、支持材を介して固定具の基端部に目地パッキンを取り付けて成ることを特徴する請求項1に記載の外壁パネルシール構造。A plurality of fixtures are provided on a long support material, and the joint packing is attached to the base end portion of the fixture via the support material by attaching the joint packing over the entire length of the support material. The outer wall panel seal structure according to claim 1. 目地パッキンの屋内側に排水樋材を設けて成ることを特徴とする請求項1又は2に記載の外壁パネルシール構造。The outer wall panel seal structure according to claim 1 or 2, wherein a drainage dredge material is provided on the indoor side of the joint packing. 排水樋材に貫通孔を形成し、貫通孔を通して固定具を配設し、貫通孔と固定具との隙間を閉塞する貫通孔パッキンを固定具の外周に装着して成ることを特徴とする請求項3に記載の外壁パネルシール構造。A through hole is formed in the drainage dredger material, a fixing tool is disposed through the through hole, and a through hole packing for closing a gap between the through hole and the fixing tool is attached to the outer periphery of the fixing tool. Item 4. The outer wall panel seal structure according to Item 3.
JP2002222032A 2002-07-30 2002-07-30 Exterior wall panel seal structure Expired - Fee Related JP3981308B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002222032A JP3981308B2 (en) 2002-07-30 2002-07-30 Exterior wall panel seal structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002222032A JP3981308B2 (en) 2002-07-30 2002-07-30 Exterior wall panel seal structure

Publications (2)

Publication Number Publication Date
JP2004060347A JP2004060347A (en) 2004-02-26
JP3981308B2 true JP3981308B2 (en) 2007-09-26

Family

ID=31942182

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002222032A Expired - Fee Related JP3981308B2 (en) 2002-07-30 2002-07-30 Exterior wall panel seal structure

Country Status (1)

Country Link
JP (1) JP3981308B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6457691B1 (en) * 2018-08-24 2019-01-23 小栗 優香 Wall panel connection structure

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6312286B2 (en) * 2012-11-20 2018-04-18 日鉄住金鋼板株式会社 Joint structure
JP6286346B2 (en) * 2014-12-16 2018-02-28 大和ハウス工業株式会社 Joint structure of outer wall panel
JP6952451B2 (en) * 2016-09-26 2021-10-20 大和ハウス工業株式会社 Dry joint structure of outer wall
JP6672349B2 (en) * 2018-02-08 2020-03-25 大和ハウス工業株式会社 Joint structure of outer wall panel and joint construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6457691B1 (en) * 2018-08-24 2019-01-23 小栗 優香 Wall panel connection structure
WO2020040235A1 (en) * 2018-08-24 2020-02-27 小島 正也 Wall panel connection structure

Also Published As

Publication number Publication date
JP2004060347A (en) 2004-02-26

Similar Documents

Publication Publication Date Title
EP1279776B1 (en) Building using external facing material for construction
JP3981308B2 (en) Exterior wall panel seal structure
JP2003074163A (en) External facing member
JP2994984B2 (en) Fire wall structure
JP7538686B2 (en) Building board mounting fixture and renovation structure using same
JP3528034B2 (en) Joint structure of solar cell holding tile
JP2005299345A (en) Sealing structure of extrusion molding cement plate joint, water drip material for extrusion molding cement plate and outer wall non-scaffold construction method using extrusion molding cement plate
JP3807693B2 (en) Joint drainage fitting for vertical outer wall plate and its connection structure
JPH0419341B2 (en)
JP3860447B2 (en) Panel device
JPS6355299A (en) Method of concrete wall-surface heat-insulating waterproof panel construction
JPH0347361A (en) Fire resisting joint construction of wall
JP6777128B2 (en) Waterproof structure of handrail
JP2000110286A (en) Connection structure of wall panel, and wall panel execution method
JPS6340037A (en) Seal structure of outer wall panel
JP2001090236A (en) External wall alc panel and method for installing the same
JPH0227075Y2 (en)
JP3399628B2 (en) Outer wall trunk waterproof structure
JPH0735984Y2 (en) Building wall equipment
JP2021092136A (en) Fixture of architectural material and reconstruction structure using the same
JP2024092353A (en) Exterior wall structure and construction method
JPS5837470B2 (en) Mounting structure for plate-shaped building materials
JP2002088955A (en) Exterior wall panel and exterior wall structure
JP2595206Y2 (en) Water leakage repair finishing panel
JP2714082B2 (en) Panel joint structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050620

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070207

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070213

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070416

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070619

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070629

R150 Certificate of patent or registration of utility model

Ref document number: 3981308

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100706

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100706

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130706

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees