JP3968750B2 - Brick residue accumulation program, computer-readable recording medium recording the program, and tile residue accumulation system - Google Patents
Brick residue accumulation program, computer-readable recording medium recording the program, and tile residue accumulation system Download PDFInfo
- Publication number
- JP3968750B2 JP3968750B2 JP2002209792A JP2002209792A JP3968750B2 JP 3968750 B2 JP3968750 B2 JP 3968750B2 JP 2002209792 A JP2002209792 A JP 2002209792A JP 2002209792 A JP2002209792 A JP 2002209792A JP 3968750 B2 JP3968750 B2 JP 3968750B2
- Authority
- JP
- Japan
- Prior art keywords
- tile
- procedure
- roof
- data
- cad data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Description
【0001】
【発明の属する技術分野】
この発明は、建物の屋根に施工される瓦のうち、所定範囲を切断して屋根の隅棟部等に沿って施工される切断瓦の実寸(実際の寸法)を算出し、切断瓦から切除される残材の量等を算出するための瓦残材積算プログラム、該プログラムを記録したコンピュータ読み取り可能な記録媒体、及び瓦残材積算システムに関する。
【0002】
【従来の技術】
周知のように、建物の寄棟屋根等の屋根に瓦を施工する場合、屋根の隅棟部等に施工する瓦(切断瓦)に対しては、あらかじめ所定範囲を斜め方向等に切断しておく必要がある。この切断瓦の施工部位における採寸作業や瓦の切断作業は、施工現場でその都度行われている。また、切断瓦から切除される残材は、産業廃棄物として処理されている。
【0003】
【発明が解決しようとする課題】
しかしながら、瓦の切断作業が終了しなければ残材の総量を把握できないので、残材の処理コスト管理を行いにくいという問題点がある。
【0004】
この発明は、以上のような問題点に鑑みてなされたものであり、瓦を施工する前にあらかじめ残材の総量を見積もることができる瓦残材積算プログラム、該プログラムを記録したコンピュータ読み取り可能な記録媒体、及び瓦残材積算システムを提供することを目的とする。
【0005】
【課題を解決するための手段】
上記目的を達成するための請求項1の瓦残材積算プログラムは、建物の屋根に施工される瓦のうち、所定範囲を切断して施工される切断瓦の切断後の実寸を算出し、切断瓦から切除される残材の量を算出するために、コンピュータに、所定の記憶手段から屋根伏せCADデータを読み込む手順と、入力装置から入力された屋根伏せCADデータの縮尺に基づいて屋根伏せCADデータを実寸スケールに補正し、屋根伏せ補正CADデータを作成する手順と、屋根伏せ補正CADデータを表示装置の画面上に表示する手順と、ファイル装置にあらかじめ記録された瓦施工面補正ルールファイルから、入力装置により屋根伏せ補正CADデータにそれぞれ指定された要素線の組合せ及び入力装置から入力された瓦の種類に応じた瓦施工面補正ルールを読み出す手順と、瓦施工面補正ルール及び入力装置から入力された屋根勾配に基づいて屋根伏せ補正CADデータを補正し、瓦施工面CADデータを作成する手順と、ファイル装置にあらかじめ記録された割り付けルールファイルから、瓦の種類及び入力装置から入力された割り付け型に応じた割り付けルールを読み出す手順と、ファイル装置にあらかじめ記録された瓦CADデータファイルから瓦の種類及び割り付け型に応じた瓦CADデータを読み出す手順と、瓦CADデータを割り付けルールに基づいて瓦施工面CADデータに割り付ける手順と、瓦施工面CADデータの要素線と交差する切断瓦としての瓦CADデータに割り付けルールに基づいて切断瓦番号を付与する手順と、ファイル装置にあらかじめ記録された実寸算出ルールファイルから瓦の種類に応じた実寸算出ルールを読み出す手順と、実寸算出ルールに基づいて各切断瓦ごとに実寸データを算出する手順と、ファイル装置にあらかじめ記録された実寸補正ルールファイルから、瓦の種類に応じた実寸補正ルールを読み出す手順と、実寸補正ルールに基づいて各実寸データをそれぞれ補正し、各切断瓦ごとに実寸補正データを算出する手順と、実寸補正データに基づいて基礎データを各切断瓦ごとに算出する手順と、ファイル装置にあらかじめ記録された瓦データファイルから切断瓦に応じた瓦データを各切断瓦ごとに読み出す手順と、基礎データ及び瓦データに基づいて残材の量を各切断瓦ごとに算出して集計し、この集計値を残材の総量として出力する手順と、を実行させるためのものである。
【0006】
請求項2の瓦残材積算プログラムは、建物の屋根に施工される瓦のうち、所定範囲を切断して施工される切断瓦の切断後の実寸を算出し、切断瓦から切除される残材の量を算出するために、コンピュータに、所定の記憶手段から屋根伏せCADデータを読み込む手順と、入力装置から入力された屋根伏せCADデータの縮尺に基づいて屋根伏せCADデータを実寸スケールに補正し、屋根伏せ補正CADデータを作成する手順と、屋根伏せ補正CADデータを表示装置の画面上に表示する手順と、ファイル装置にあらかじめ記録された瓦施工面補正ルールファイルから、入力装置により屋根伏せ補正CADデータにそれぞれ指定された要素線の組合せ及び入力装置から入力された瓦の種類に応じた瓦施工面補正ルールを読み出す手順と、瓦施工面補正ルール及び入力装置から入力された屋根勾配に基づいて屋根伏せ補正CADデータを補正し、瓦施工面CADデータを作成する手順と、ファイル装置にあらかじめ記録された割り付けルールファイルから、瓦の種類及び入力装置から入力された割り付け型に応じた割り付けルールを読み出す手順と、ファイル装置にあらかじめ記録された瓦CADデータファイルから瓦の種類及び割り付け型に応じた瓦CADデータを読み出す手順と、瓦CADデータを割り付けルールに基づいて瓦施工面CADデータに割り付ける手順と、瓦施工面CADデータの要素線と交差する切断瓦としての瓦CADデータに割り付けルールに基づいて切断瓦番号を付与する手順と、ファイル装置にあらかじめ記録された実寸算出ルールファイルから瓦の種類に応じた実寸算出ルールを読み出す手順と、実寸算出ルールに基づいて各切断瓦ごとに実寸データを算出する手順と、ファイル装置にあらかじめ記録された実寸補正ルールファイルから瓦の種類に応じた実寸補正ルールを読み出す手順と、実寸補正ルールに基づいて各実寸データをそれぞれ補正し、各切断瓦ごとに実寸補正データを算出する手順と、実寸補正データに基づいて基礎データを各切断瓦ごとに算出する手順と、ファイル装置にあらかじめ記録された瓦データファイルから、切断瓦及び基礎データに応じた瓦データを各切断瓦ごとに読み出す手順と、瓦データ及び実寸補正データに基づいて残材の量を各切断瓦ごとに算出して集計し、この集計値を残材の総量として出力する手順と、を実行させるためのものである。
【0007】
請求項3の瓦残材積算プログラムは、建物の屋根に施工される瓦のうち、所定範囲を切断して施工される切断瓦の切断後の実寸を算出し、切断瓦から切除される残材の量を算出するために、コンピュータに、所定の記憶手段から屋根伏せCADデータを読み込む手順と、入力装置から入力された屋根伏せCADデータの縮尺に基づいて屋根伏せCADデータを実寸スケールに補正し、屋根伏せ補正CADデータを作成する手順と、屋根伏せ補正CADデータを表示装置の画面上に表示する手順と、ファイル装置にあらかじめ記録された瓦施工面補正ルールファイルから、入力装置により屋根伏せ補正CADデータにそれぞれ指定された要素線の組合せ及び入力装置から入力された瓦の種類に応じた瓦施工面補正ルールを読み出す手順と、瓦施工面補正ルール及び入力装置から入力された屋根勾配に基づいて屋根伏せ補正CADデータを補正し、瓦施工面CADデータを作成する手順と、ファイル装置にあらかじめ記録された割り付けルールファイルから、瓦の種類及び入力装置から入力された割り付け型に応じた割り付けルールを読み出す手順と、ファイル装置にあらかじめ記録された瓦CADデータファイルから瓦の種類及び割り付け型に応じた瓦CADデータを読み出す手順と、瓦CADデータを割り付けルールに基づいて瓦施工面CADデータに割り付ける手順と、瓦施工面CADデータの要素線と交差する切断瓦としての瓦CADデータに割り付けルールに基づいて切断瓦番号を付与する手順と、ファイル装置にあらかじめ記録された実寸算出ルールファイルから瓦の種類に応じた実寸算出ルールを読み出す手順と、実寸算出ルールに基づいて各切断瓦ごとに実寸データを算出する手順と、ファイル装置にあらかじめ記録された実寸補正ルールファイルから、瓦の種類に応じた実寸補正ルールを読み出す手順と、実寸補正ルールに基づいて各実寸データをそれぞれ補正し、各切断瓦ごとに実寸補正データを算出する手順と、ファイル装置にあらかじめ記録された3次元瓦CADデータファイルから切断瓦に応じた3次元瓦CADデータを各切断瓦ごとに読み出す手順と、3次元瓦CADデータに基づいて各実寸補正データをそれぞれ補正し、各切断瓦ごとに3次元実寸補正データを算出する手順と、ファイル装置にあらかじめ記録された瓦データファイルから切断瓦に応じた瓦データを各切断瓦ごとに読み出す手順と、3次元瓦CADデータ、3次元実寸補正データ、及び瓦データに基づいて残材の量を各切断瓦ごとに算出して集計し、この集計値を残材の総量として出力する手順と、を実行させるためのものである。
【0008】
請求項4の瓦残材積算プログラムにおいては、コンピュータに、切断瓦を加工するための瓦切断機を制御する制御装置へ3次元実寸補正データをCAMデータとして転送する手順を実行させることもできる。
【0009】
請求項5の瓦残材積算プログラムにおいては、コンピュータに、残材の全量を粉砕してなる粉砕物を粒径により複数種に分別した分別粉砕物の量を残材の総量に基づいて各分別粉砕物ごとに算出する手順と、各分別粉砕物の量をそれぞれ出力する手順とを実行させることもできる。
【0010】
請求項6の瓦残材積算プログラムにおいては、コンピュータに、入力装置により施工の種類として葺き替えが選択されたときに、瓦施工面CADデータに含まれている複数の瓦施工面の面積をそれぞれ算出して集計する手順と、ファイル装置にあらかじめ記録された元葺きデータファイルから、入力装置から入力された元葺き瓦の種類に応じた元葺きデータを読み出す手順と、元葺きデータ及び瓦施工面の総面積に基づいて元葺き量を算出する手順と、元葺き量を出力する手順とを実行させることもできる。
【0011】
請求項7の瓦残材積算プログラムにおいては、コンピュータに、残材の総量と元葺き量を加算する手順と、この加算値を残材混合物の総量として出力する手順とを実行させることもできる。
【0012】
請求項8の瓦残材積算プログラムにおいては、コンピュータに、残材混合物の全量を粉砕してなる粉砕物を粒径により複数種に分別した分別粉砕物の量を残材混合物の総量に基づいて各分別粉砕物ごとに算出する手順と、各分別粉砕物の量をそれぞれ出力する手順とを実行させることもできる。
【0013】
請求項9の瓦残材積算プログラムにおいては、コンピュータに、分別粉砕物から製造されるリサイクル品の量を分別粉砕物の量に基づいて各分別粉砕物ごとに算出する手順と、各リサイクル品の量をそれぞれ出力する手順とを実行させることもできる。
【0014】
また、請求項10のコンピュータ読み取り可能な記録媒体は、請求項1乃至9のいずれか記載の瓦残材積算プログラムを記録したものである。
【0015】
更に、瓦残材積算システムは、請求項1乃至9のいずれか記載の瓦残材積算プログラムをコンピュータのファイル装置に記録したものである。
【0016】
【発明の実施の形態】
以下、この発明の実施形態を図面に基づいて説明する。
図1に示すように、この実施形態に係る瓦残材積算システムは、瓦残材積算プログラム1をコンピュータのファイル装置2に記録(インストール)したものである。
【0017】
コンピュータは、ハードディスクドライブ等のファイル装置2の他、CPU(Central Processing Unit,中央処理装置)3、メインメモリ4、キーボードやマウス等の入力装置5、及びディスプレイ等の表示装置6等を備えており、これらCPU3等はコンピュータのシステムバス7にそれぞれ接続されている。また、システムバス7には、必要に応じて、レーザープリンタやインクジェットプリンタ等の印刷装置8や、切断瓦を加工するための瓦切断機を制御する制御装置(図示せず)も接続されている。なお、制御装置は、RS−232Cケーブル等の通信ケーブル及びインターフェイスを介してシステムバス7と接続することができる。
【0018】
瓦残材積算プログラム(ソフトウェア)1は、制御プログラム9、瓦施工面補正ルールファイル10、割り付けルールファイル11、瓦CADデータファイル12、実寸算出ルールファイル13、実寸補正ルールファイル14、瓦データファイル15D等を備えており、ファイル装置2にあらかじめ記録されている。この瓦残材積算プログラム1をコンピュータ上で起動させれば、制御プログラム9がメインメモリ4上に読み込まれ、この制御プログラム9の指令によってCPU3が各ファイル10,11,12,13,14,15D等から適用すべきルールやデータを検索し、メインメモリ4上に読み出す等して各種の処理を実行するようになっている。
【0019】
瓦残材積算プログラム1による処理を詳細に説明する前に、まず、図2及び図3のようなF形瓦(瓦)15を例にとり、瓦を実際に建物の屋根16に施工する場合の施工例について説明する。
【0020】
F形瓦15は、平面視が四角形の本体部17と、この本体部17の左側の側端に突設された平面視が長方形のアンダーラップ部18とから構成されている。このようなF形瓦15は、図4乃至図6に示すように、屋根16の下方側かつ右側から順に千鳥状(一文字葺)に施工されるのが一般的である。横方向においては、本体部17が互いに隣接するように配置される。上下方向においては、下段のF形瓦15の上端にその上段のF形瓦15の下端が数十mmの重ね代をとって重ねるように載置される。最下段のF形瓦15の下端は、野地板19上にアスファルトルーフィング20を介して長手方向が水平となるように固定された瓦座(図示せず)等の上に載置される。
【0021】
図3及び図5に示すように、F形瓦15の上端には下方へ突出する例えば2つのフック部21が突設されているが、このF形瓦15は、野地板19上にアスファルトルーフィング20を介して長手方向が水平となるように固定された瓦桟22にフック部21を引掛けるようにして配置され、緊結用釘23等により瓦桟22に固着される。F形瓦15の野地板19の面方向に対する葺き勾配θは、5°程度が一般的である。また、図6に示すように、屋根16の隅棟部16a等においては、F形瓦15のうち、所定範囲を斜め方向等に切断して残材を切除した後の切断瓦15bが施工される。隅棟部16a等には、取付け桟木24を介して隅棟瓦25等が施工される。なお、J形瓦やS形瓦等においては、下段と上段の瓦の配置が左右にずれない桟瓦葺等となるのが一般的である。また、瓦桟22を長手方向が水平となるように固定する上記のような一般の工法(いわゆる横桟工法)による場合に加え、瓦桟22を長手方向が屋根勾配の向きに沿うように固定するいわゆる縦桟工法や、あるいは瓦桟22を使用しない直葺により瓦を施工する場合もある。
【0022】
瓦残材積算プログラム1は、上記のような瓦の施工に際しての割り付けをあらかじめコンピュータ上で仮想的に実行し、切断瓦の切断後の実寸を算出し、切断瓦から切除される残材の量を算出するものである。なお、割り付ける瓦の種類としては、例えばF形瓦15、J形瓦、S形瓦等の粘土瓦の他、各種の厚形スレート、金属板瓦等が挙げられる。また、割り付ける瓦の形状による種類としては、桟瓦の他、例えば軒瓦、袖瓦、角瓦、掛瓦等が挙げられる。
【0023】
次に、瓦残材積算プログラム1による処理の手順例を図7乃至図9のフローチャートに基づいてより詳細に説明する。
【0024】
まず、所定の記憶手段(図示せず)から、DXF(Drawing Interchange File)形式等のCADソフト用のファイル形式でこの記憶手段に記録されていた屋根伏せCADデータがメインメモリ4上に読み込まれる(ステップS1)。
【0025】
屋根伏せCADデータが記録された記憶手段としては、例えば、FD(Flexible Disk)、CD−ROM(Compact Disc Read Only Memory)、CD−R(Compact Disc Recordable)、CD−RW(Compact Disc Rewritable)、MO(Magneto Optical Disk)等のコンピュータ読み取り可能な記録媒体の他、瓦残材積算システムのコンピュータがLAN(Local Area Network)やインターネット等のネットワークを介してアクセス可能な他のコンピュータのハードディスクドライブ(ネットワークドライブ)等が挙げられる。
【0026】
屋根伏せCADデータは、瓦を施工しようとする建物の屋根16の平面図に相当する屋根伏せ図を表すものであり、所定の縮尺で描画された複数の要素線(線分データ)を含んでいる。
【0027】
次いで、キーボード又はマウス等の入力装置5から、屋根伏せCADデータの縮尺が入力される(ステップS2)。
【0028】
入力は、キーボード等から例えば「1:100」又は「1/100」、「1:30」又は「1/30」、「1:1」又は「1/1」等と打ち込むことにより実行してもよいが、GUI(Graphical User Interface)環境における表示装置6の画面6a上のメニューバー(ツールバー)やマウスの右ボタン(右クリック)等のプルダウンメニュー等に割り当てられた縮尺の上記のような種類をマウス等により選択できるようにしておけば、簡単に実行できる。
【0029】
その後、制御プログラム9の指令を受けたCPU3により、メインメモリ4上で屋根伏せCADデータの縮尺に基づいて屋根伏せCADデータが実寸スケール(1:1の実物大スケール)に補正され、図10のような屋根伏せ補正CADデータ31が作成されて(ステップS3)、表面装置6の画面6a上に表示される(ステップS4)。
【0030】
例えば、図10のような寄棟屋根の場合、屋根伏せ補正CADデータ31には、要素線として、1つの陸棟線32と4つの隅棟線33と4つの軒瓦線34とが含まれる。なお、屋根16の形状としては、寄棟の他、例えば切妻、方形、入母屋等が挙げられる。要素線の種類は特に限定されるものではなく、その他に谷線、右袖瓦線、左袖瓦線、掛瓦線、降棟線、水平壁際線、流れ壁際線、渡根丸線(利根丸線)、風切り丸線等が挙げられる。また、要素線は、直線状の他、曲線状であってもよい。
【0031】
次いで、マウス等の入力装置5から、各要素線ごとにその種類が指定される(ステップS5)。
【0032】
図10の例においては、陸棟線(要素線)32は陸棟線として、隅棟線(要素線)33は隅棟線として、軒瓦線(要素線)34は軒瓦線として、それぞれ要素線の種類が指定される。指定は、例えば、マウス等により画面6a上の適宜の要素線を選択した後又は選択する前に、GUI環境における画面6a上のメニューバー(ツールバー)やマウスの右ボタン(右クリック)等のプルダウンメニュー等に割り当てられた要素線の種類をマウス等により選択できるようにしておけば、簡単に実行できる。この場合、プルダウンメニュー等には、例えば「陸棟線」、「隅棟線」、「軒瓦線」等の各種の要素線の種類を割り当てることができる。また、屋根面が凸面となった照り(てり)や凹面となった起り(むくり)である場合に対応するために、例えば「隅棟線(照り)」や「隅棟線(起り)」等の種類も指定できるようにしておくのが望ましい。この場合、照りや起りの曲率半径(R)を加味した例えば「隅棟線(照り:R=XXXXX)」や「隅棟線(起り:R=XXXXX)」等の種類を曲率半径の値に応じて選択できるようにすることもできる。
【0033】
その後、キーボード又はマウス等の入力装置5から、瓦の種類、屋根勾配、割り付け型が入力される(ステップS6〜S8)。なお、瓦の種類等の入力の順序は特に限定されるものではなく、また、これら瓦の種類等の入力を各要素線ごとの種類の指定(ステップS5)の前に実行することもできる。
【0034】
この場合も、GUI環境におけるプルダウンメニュー等に割り当てられた瓦の種類等をマウス等により選択できるようにしておけば、簡単に入力できる。プルダウンメニュー等に割り当てる瓦の種類としては、例えば「F形瓦」、「J形瓦」、「S形瓦」等が挙げられる。同様に、屋根勾配としては、例えば「4/10」、「3.5/10」、「3/10」、「2.5/10」、「1/10」等が挙げられる。割り付け型としては、例えば、軒瓦線34の中点34aから最下段の瓦を左右に配置していくいわゆる「対称型」や、軒瓦線34の中点34aに最下段の瓦の中心線等が重なるように配置するいわゆる「中央型」、袖瓦線(図示せず)から最下段の瓦を配置していくいわゆる「切妻型」等が挙げられる。
【0035】
次いで、制御プログラム9の指令を受けたCPU3により瓦施工面補正ルールファイル10が検索され、この瓦施工面補正ルールファイル10から、要素線の組合せ及び瓦の種類に応じた瓦施工面補正ルールがメインメモリ4上に読み出される(ステップS9)。
【0036】
瓦施工面補正ルールファイル10は、各種の瓦施工面補正ルールが要素線の組合せ及び瓦の種類に対応付けて記録されている。例えば、図10の例において、瓦の種類として「F形瓦」を入力すれば、要素線の組合せが「1つの陸棟線32,4つの隅棟線33,4つの軒瓦線34」でありかつ瓦の種類が「F形瓦」である場合、即ち、寄棟屋根にF形瓦15を施工する場合に対応付けられた瓦施工面補正ルールが読み出される。
【0037】
その後、制御プログラム9の指令を受けたCPU3により瓦施工面補正ルール及び屋根勾配に基づいて屋根伏せ補正CADデータ31が補正され、メインメモリ4上に図11のような瓦施工面CADデータ35が作成される(ステップS10)。
【0038】
瓦施工面CADデータ35は、瓦施工面補正ルールに基づいて屋根伏せ補正CADデータ31から補正された複数の野地板面19a,19bを含む屋根16の展開図を、更に瓦施工面補正ルールに基づいて瓦の施工後の投影面である複数の瓦施工面36a,36bを含む展開図に補正したものである。例えば、図10の例においては、まず、屋根伏せ補正CADデータ31が瓦施工面補正ルールに基づいて図11のような台形の2つの野地板面19aと三角形の2つの野地板面19bを含むように補正される。適用される瓦施工面補正ルールには、屋根勾配に基づいて展開図が作成されるように補正を行う計算式等が含まれている。次いで、瓦施工面補正ルールに基づいて各野地板面19a,19bの高さに「F形瓦」の軒の出寸法Eを加算するように補正され、台形の2つの瓦施工面36aと三角形の2つの瓦施工面36bを含む瓦施工面CADデータ35が作成される。台形の瓦施工面36aは、1つの陸棟線32と2つの隅棟線33と1つの軒瓦線34とを含んでいる。三角形の瓦施工面36bは、2つの隅棟線33と1つの軒瓦線34とを含んでいる。
【0039】
既述したように、瓦施工面補正ルールは要素線の組合せ及び瓦の種類に応じて適用されるので、屋根伏せ補正CADデータ31が例えば右袖瓦線や左袖瓦線を含んでいる場合においては、瓦の袖の出寸法(右袖瓦線等の元の位置からの突出長さ)を横幅に加算等するように補正される。同様に、谷線を含んでいる場合においては、瓦の谷の入り寸法(谷線の元の位置からの横方向への引き込み長さ)を横幅から減算等するように補正される。陸棟線32を含んでおり、他の瓦の種類を入力した場合等においては、瓦の陸棟の入り寸法(陸棟線32の元の位置からの縦方向への引き込み長さ)を高さから減算等するように補正される。隅棟線33を含んでおり、他の瓦の種類を入力した場合等においては、瓦の隅棟の入り寸法(隅棟線33の元の位置からの横方向への引き込み長さ)を横幅から減算等するように補正される。水平壁際線を含んでおり、他の瓦の種類を入力した場合等においては、瓦の水平壁際の入り寸法(水平壁際線の元の位置からの縦方向への引き込み長さ)を高さから減算等するように補正される。流れ壁際線を含んでおり、他の瓦の種類を入力した場合等においては、瓦の流れ壁際の入り寸法(流れ壁際線の元の位置からの横方向への引き込み長さ)を横幅から減算等するように補正される。渡根丸線を含んでおり、他の瓦の種類を入力した場合等においては、瓦の渡根丸の入り寸法(渡根丸線の元の位置からの横方向への引き込み長さ)を横幅から減算等するように補正される。
【0040】
なお、軒の出寸法E等は瓦の種類によっても相違するが、瓦の種類にも応じた瓦施工面補正ルールが適用されるので、適正に瓦施工面CADデータ35に補正される。また、瓦施工面CADデータ35への補正は、実寸スケールのまま実行される。
【0041】
要素線の種類として既述の「隅棟線(照り:R=XXXXX)」又は「隅棟線(起り:R=XXXXX)」等を指定した場合、即ち、屋根面が照り又は起りである場合は、照り又は起りの曲率半径(R)に基づいても補正される。
【0042】
また、作成された瓦施工面CADデータ35は、制御プログラム9の指令を受けたCPU3により、この段階で表示装置6や印刷装置8に出力することもできる。この場合、図11のような2次元の展開面に加え、屋根16の立体形状を容易に把握できるように、3次元の立体図として出力することもできる。
【0043】
次いで、制御プログラム9の指令を受けたCPU3により割り付けルールファイル11が検索され、この割り付けルールファイル11から、瓦の種類及び割り付け型に応じた割り付けルールがメインメモリ4上に読み出される(ステップS11)。
【0044】
割り付けルールファイル11は、各種の割り付けルールが瓦の種類及び割り付け型に対応付けて記録されている。例えば、瓦の種類が「F形瓦」でありかつ割り付け型が既述の「対称型」である場合、即ち、軒瓦線34の中点34aから最下段のF形瓦15を左右に配置していく場合に対応付けられた割り付けルールが読み出される。割り付けルールには、瓦の種類及び割り付け型に応じ、所定の形状の瓦(桟瓦、軒瓦、袖瓦、角瓦、掛瓦等)を所定の部位に所定の重ね代をとって所定の葺き方で配置するように実行させる指令や計算式等が含まれている。例えば、袖瓦線に沿って袖瓦を配置したり、軒瓦線に沿って軒瓦を配置したり、その他の部位に桟瓦を配置したりするように実行させる。
【0045】
また、制御プログラム9の指令を受けたCPU3により瓦CADデータファイル12が検索され、この瓦CADデータファイル12から、瓦の種類及び割り付け型に応じた瓦CADデータがメインメモリ4上に読み出される(ステップS12)。
【0046】
瓦CADデータファイル12は、実寸スケールで描画された各種の瓦CADデータが瓦の種類及び割り付け型に対応付けて記録されている。例えば、瓦の種類が「F形瓦」でありかつ割り付け型が「対称型」である場合は、図12のような瓦CADデータ37が読み出される。この瓦CADデータ37は、既述の本体部17とアンダーラップ部18とを含むF形瓦15の平面図を表すものであり、実寸スケールで作成されている。なお、瓦CADデータ37のうち、本体部18の所定範囲は、表面に露出する働き面37aとなる。また、「F形瓦」でも他の割り付け型である場合や、瓦の種類が「F形瓦」以外である場合等においては、桟瓦としての瓦CADデータ37に加え、軒瓦、袖瓦、角瓦、又は掛瓦等としての瓦CADデータが読み出されることもある。
【0047】
その後、制御プログラム9の指令を受けたCPU3により、図13及び図14に示すように、瓦CADデータ37(図13及び図14では働き面37aのみを示している。)が割り付けルールに基づいてメインメモリ4上の瓦施工面CADデータ35に割り付けられる(ステップS13)。
【0048】
例えば、図13及び図14の例においては、瓦の種類が「F形瓦」でありかつ割り付け型が「対称型」である場合に応じて読み出された割り付けルールに基づいて瓦CADデータ37が割り付けられている。この例においては、瓦の形状による種類として、全て「F形瓦」の「桟瓦」に対応した瓦CADデータ37が割り付けられている。割り付けルールには、既述した実際の施工例と同様の配置状態となるような指令や計算式等が含まれている。
【0049】
なお、上記と同様、制御プログラム9の指令を受けたCPU3により、割り付けた状態の瓦施工面CADデータ35及び瓦CADデータ37をこの段階で表示装置6や印刷装置8に出力することもできる。
【0050】
次いで、制御プログラム9の指令を受けたCPU3により、図15乃至図17に示すように、要素線と交差する、切断前の切断瓦15aとしての瓦CADデータ37(図15乃至図17では働き面37aのみを示している。)にメインメモリ4上で切断瓦番号Nが付与される(ステップS14)。
【0051】
例えば、図15乃至図17の例においては、瓦の種類が「F形瓦」でありかつ割り付け型が「対称型」である場合に応じて読み出された割り付けルールに基づいて、例えば隅棟線33や陸棟線32と交差する瓦CADデータ37に「1」、「2」、「3」等の切断瓦番号Nが付与される。割り付けルールには、切断瓦番号Nを所定の順序で付与するための指令や計算式等が含まれている。
【0052】
なお、上記と同様、制御プログラム9の指令を受けたCPU3により、切断瓦番号Nを付与した状態の瓦施工面CADデータ35及び瓦CADデータ37を切断瓦番号Nと共にこの段階で表示装置6や印刷装置8に出力することもできる。この場合、各切断瓦番号Nは、円38により包囲したいわゆるバルーンナンバーとして出力してもよいし、あるいは、切断瓦番号N又はバルーンナンバーを各瓦CADデータ37から引出線によりそれぞれ引き出した状態で出力してもよい。
【0053】
その後、制御プログラム9の指令を受けたCPU3により実寸算出ルールファイル13が検索され、この実寸算出ルールファイル13から、瓦の種類に応じた実寸算出ルールがメインメモリ4上に読み出される(ステップS15)。
【0054】
次いで、制御プログラム9の指令を受けたCPU3により、図18乃至図23に示すように、切断瓦15aの切断後の実寸データ(必要材15bの実寸データ)が各切断瓦15aごとに算出される(ステップS16)。なお、屋根16には、切断瓦15aから残材15cを切除した必要材15bが施工される。
【0055】
実寸算出ルールファイル13は、各種の実寸算出ルールが瓦の種類に対応付けて記録されている。例えば、瓦の種類が「F形瓦」である場合、実寸算出ルールには、本体部17における隅棟線33や陸棟線32の下側の部分の「上辺寸法」A、「下辺寸法」B、「左辺寸法」C、「右辺寸法」D、隅棟線33が瓦CADデータ37のうちのアンダーラップ部18のみと交差する場合のアンダーラップ部18における隅棟線33や陸棟線32の下側の部分の上辺寸法(「U上辺寸法」)、下辺寸法(「U下辺寸法」)UB、左辺寸法(「U左辺寸法」)UC等を採寸するように実行させる指令や計算式等が含まれている。
【0056】
ここで、CPU3に、制御プログラム9の指令を受けて、下辺寸法B等の切断瓦15aの切断後の実寸データ(必要材15bの実寸データ)があらかじめ設定(相対値又は絶対値による設定)していた設定値以下の場合はその切断瓦15aの切断瓦番号Nを削除する手順と、各切断瓦15aの切断瓦番号Nをリナンバする手順とを実行させるように構成すれば、実際の施工時には使用しない切断瓦15aについての実寸データの算出を防止できるという利点がある。
【0057】
その後、制御プログラム9の指令を受けたCPU3により実寸補正ルールファイル14が検索され、この実寸補正ルールファイル14から、瓦の種類に応じた実寸補正ルールがメインメモリ4上に読み出される(ステップS17)。
【0058】
実寸補正ルールファイル14は、各種の実寸補正ルールが瓦の種類に対応付けて記録されている。例えば、瓦の種類が「F形瓦」である場合、実寸補正ルールには、既述のF形瓦15の葺き勾配θに基づいて実寸データの補正を行う計算式等が含まれている。
【0059】
次いで、制御プログラム9の指令を受けたCPU3により、実寸補正ルールに基づいて各実寸データがそれぞれ補正され、各切断瓦15aごとに実寸補正データが算出される(ステップS18)。
【0060】
ここで、図8に示すように、必要に応じて、制御プログラム9の指令を受けたCPU3に、実寸補正データを切断瓦15aに対応付けて図24のような瓦屋根積算データテーブルを作成する手順(ステップS19)と、瓦屋根積算データテーブルを表示装置6や印刷装置8に出力する手順(ステップS20)とを実行させるように構成すれば、切断瓦15aの切断後の実寸(必要材15bの実寸)を把握し易いという利点がある。
【0061】
また、制御プログラム9の指令を受けたCPU3に、切断瓦番号Nが付与された瓦CADデータ37の瓦施工面CADデータ35上の位置を計測する手順と、この位置を切断瓦15aの施工部位として切断瓦15aに対応付けて瓦屋根積算データテーブルに格納する手順とを実行させるように構成すれば、瓦屋根積算データテーブルの出力により切断瓦15aの施工部位を簡単に把握することもできる。
【0062】
切断瓦15aの施工部位としては、図24に示すように、例えば「台形1段左」、「台形2段左」、「台形21段左」、「台形21段中」、「台形1段右」等が挙げられる。これらは既述の例に対応したものであり、それぞれ切断瓦番号Nが「1」、「2」、「4」、「39」、「40」、「86」の切断瓦15aに対応している。
【0063】
この場合、CPU3に、制御プログラム9の指令を受けて、切断瓦番号Nが付与された瓦CADデータ37の形状による種類を切断瓦15aに対応付けて瓦屋根積算データテーブルに格納する手順を実行させるように構成すれば、瓦屋根積算データテーブルの出力により切断瓦15aの形状による種類を簡単に把握できる。
【0064】
切断瓦15aの形状による種類としては、図24に示す「桟瓦」の他、例えば「軒瓦」、「袖瓦」、「角瓦」、「掛瓦」等が挙げられる。
【0065】
その後、図9に示すように、制御プログラム9の指令を受けたCPU3により、実寸補正データに基づいて基礎データが算出される(ステップS21)。
【0066】
基礎データとしては、例えば切断瓦15aの切断後の投影面積(必要材15bの投影面積)等が挙げられる。制御プログラムには、実寸補正データに基づいて切断瓦15aの切断後の投影面積等を算出する計算式等が含まれている。
【0067】
次いで、制御プログラム9の指令を受けたCPU3により瓦データファイルが検索され、この瓦データファイルから、切断瓦15aに応じた瓦データが各切断瓦15aごとにメインメモリ上に読み出される(ステップS22)。
【0068】
瓦データには、例えば切断前の切断瓦15aの初期投影面積の他、初期重量又は初期体積等が含まれている。瓦データファイルは、瓦データが切断瓦15aに対応付けてファイル装置に記録されている。
【0069】
その後、制御プログラム9の指令を受けたCPU3により、基礎データ及び瓦データに基づいて残材15cの量が各切断瓦15aごとに算出されて集計されると共に、この集計値が残材15cの総量として出力され(ステップS23)、処理が終了する。
【0070】
制御プログラム9には、基礎データ及び瓦データに基づいて残材15cの量(重量又は体積)を算出する計算式等が含まれている。この場合、図25のような瓦残材積算データテーブルに、残材15cの総量(総重量又は総体積)を例えば「合計XXXkg」又は「合計XXXm3」等として格納するようにしてもよい。また、上記の処理のいずれかの段階でキーボード等の入力装置5から例えば「YYYYYYYYYY」等の物件名を入力しておき、この物件名を例えば「F形瓦」等の瓦の種類や例えば「対称型」等の割り付け型と共に、瓦残材積算データテーブルに格納するようにしてもよい。
【0071】
上記のように構成された瓦残材積算システム及び瓦残材積算プログラム1によれば、瓦を施工する前にあらかじめ切断瓦15aの切断後の実寸を算出できると共に、残材15cの総量を見積もることができるので、残材15cを産業廃棄物として処理する場合でも、処理コスト管理を行い易いという利点がある。また、残材15cを適宜の粒径に粉砕して粉砕物とし、この粉砕物を例えば埋め立て材等としてリサイクルする場合は、残材15cの総量を埋め立て材等の製品出荷量として見積もることができる。
【0072】
ここで、図26に示すように、残材15cの総量を出力(ステップS23)した後、必要に応じて、制御プログラム9の指令を受けたCPU3により、残材15cの全量を粉砕してなる粉砕物を粒径により複数種に分別した分別粉砕物の量を残材15cの総量に基づいて各分別粉砕物ごとに算出する手順(ステップS24)と、各分別粉砕物の量をそれぞれ出力する手順(ステップS25)とを実行させるように構成すれば、各分別粉砕物をリサイクルする場合におけるそれぞれの製品出荷量を見積もることができるという利点がある。
【0073】
粉砕物は、粒径により例えば、1mm未満、1mm以上3mm未満、3mm以上の3種の分別粉砕物に分別できる。制御プログラム9には、複数種の分別粉砕物の量比(重量比又は体積比)及び残材15c(粉砕物)の総量に基づいて分別粉砕物の量(重量又は体積)を算出する計算式等が含まれている。この場合、図25のような瓦残材積算データテーブルに、分別粉砕物の粒径を例えば「φ<1mm」、「1≦φ<3mm」、「φ≧3mm」等とし、各分別粉砕物の量を例えば「XXXkg」又は「XXXm3」等としてそれぞれ格納するようにしてもよい。なお、分別粉砕物への分別は3種に限定されるものではなく、適当な粒径により2種や4種以上に分別することもできる。
【0074】
また、図26に示すように、各分別粉砕物の量をそれぞれ出力(ステップS25)した後、必要に応じて、制御プログラム9の指令を受けたCPU3により、分別粉砕物から製造されるリサイクル品の量を分別粉砕物の量に基づいて各分別粉砕物ごとに算出する手順(ステップS26)と、各リサイクル品の量をそれぞれ出力する手順(ステップS27)とを実行させるように構成すれば、分別粉砕物から適宜のリサイクル品を製造する場合における各リサイクル品の製品出荷量をそれぞれ見積もることができるという利点がある。
【0075】
リサイクル品としては、分別粉砕物の粒径が例えば1mm未満の場合は、南蛮漆喰用原料、U字溝・路側帯用L字ブロック・植木鉢・プランター・インターロッキングブロック等のセメントブロック又はセメント製品等が挙げられる。南蛮漆喰用原料は、粒径が1mm未満の分別粉砕物に、消石灰、すさ等を適宜の割合で添加、混合すれば製造できる。セメントブロック又はセメント製品は、粒径が1mm未満の分別粉砕物に、セメント、水分、添加剤等を適宜の割合で添加、混練して注型成形、プレス成形、遠心成形、又は押出成形、及び養生等を行えば製造できる。
【0076】
分別粉砕物の粒径が例えば1mm以上3mm未満の場合、リサイクル品としては、例えば苗床土等の育苗資材等が挙げられる。育苗資材は、粒径が1mm以上3mm未満の分別粉砕物に、化成肥料、有機肥料、腐葉土、造粒剤、水分等を適宜の割合で添加、混合して粒状等に成形、乾燥等すれば製造できる。
【0077】
分別粉砕物の粒径が例えば3mm以上の場合、リサイクル品としては、例えば、建物の基礎用の捨石、道路用骨材等の土木建築資材等が挙げられる。土木建築資材は、粒径が3mm以上の分別粉砕物に、セメント、リグニン酸塩、ステアリン酸塩等の固形化材、水分等を適宜の割合で添加、混合して粒状等に成形、養生等すれば製造できる。
【0078】
制御プログラム9には、分別粉砕物の単位量当たりのリサイクル品の量(重量、体積、又は数量)及び分別粉砕物の量(重量又は体積)に基づいてリサイクル品の量を各分別粉砕物ごとに算出する計算式等が含まれている。この場合、図25のような瓦残材積算データテーブルに、各リサイクル品の量を例えば「XXXkg」、「XXXm3」、又は「XXX個」等としてそれぞれ格納するようにしてもよい。また、各分別粉砕物につき、2種以上のリサイクル品の量をそれぞれ出力し、瓦残材積算データテーブルに格納するようにしてもよい。
【0079】
ここで、図27に示すように、既述のステップS24〜S27の代わりに、残材15cの総量を出力(ステップS23)した後、必要に応じて、制御プログラム9の指令を受けたCPU3により、入力装置5により施工の種類として葺き替えが選択されたときに(ステップS28でYES)、瓦施工面CADデータ35に含まれている複数の瓦施工面36a,36bの面積をそれぞれ算出して集計する手順(ステップS29)と、ファイル装置2にあらかじめ記録された元葺きデータファイルから、入力装置5から入力(ステップS30)された元葺き瓦の種類に応じた元葺きデータを読み出す手順(ステップS31)と、元葺きデータ及び瓦施工面36a,36bの総面積に基づいて元葺き量を算出する手順(ステップS32)と、元葺き量を出力する手順(ステップS33)とを実行させるように構成すれば、瓦を葺き替える場合における元葺き量を見積もることができるという利点がある。
【0080】
入力装置5により施工の種類として新築が選択(ステップS28でNO)された場合は、ステップS24に進み、既述の処理が実行される。
【0081】
なお、元葺き量とは、瓦の葺き替え前に既に施工されていた元葺き瓦(古瓦)及びそれを施工するために使用されていた元葺き土(古土)の総量(総重量又は総体積)をいう。この場合も、GUI環境におけるプルダウンメニュー等に割り当てられた施工の種類や元葺き瓦の種類をマウス等により選択できるようにしておけば、簡単に入力できる。プルダウンメニュー等に割り当てる施工の種類としては、例えば「葺き替え」、「新築」等が挙げられる。同様に、元葺き瓦の種類としては、例えば「F形瓦」、「J形瓦」、「S形瓦」等が挙げられる。
【0082】
元葺きデータファイルは、瓦施工面36a,36bの単位面積当たりの元葺き量が元葺き瓦の種類に対応付けてファイル装置に記録されている。制御プログラム9には、読み出された元葺きデータ及び瓦施工面36a,36bの総面積に基づいて元葺き量を算出する計算式等が含まれている。この場合、図28のような瓦残材積算データテーブルに、元葺き量を例えば「XXXkg」又は「XXXm3」等として格納するようにしてもよい。
【0083】
また、図27に示すように、元葺き量を出力(ステップS33)した後、必要に応じて、制御プログラム9の指令を受けたCPU3により、残材15cの総量と元葺き量を加算する手順(ステップS34)と、この加算値を残材混合物の総量(総重量又は総体積)として出力する手順(ステップS35)とを実行させるように構成すれば、葺き替えの場合における残材混合物の総量を見積もることができるという利点がある。
【0084】
制御プログラム9には、残材15cの総量と元葺き量を加算して加算値を算出する計算式等が含まれている。この場合、図28のような瓦残材積算データテーブルに、残材混合物の総量を例えば「総合計XXXkg」又は「総合計XXXm3」等として格納するようにしてもよい。
【0085】
更に、図27に示すように、残材混合物の総量を出力(ステップS35)した後、必要に応じて、制御プログラム9の指令を受けたCPU3により、残材混合物の全量を粉砕してなる粉砕物を粒径により複数種に分別した分別粉砕物の量を残材混合物の総量に基づいて各分別粉砕物ごとに算出する手順(ステップS36)と、各分別粉砕物の量をそれぞれ出力する手順(ステップS37)とを実行させるように構成すれば、残材混合物からの各分別粉砕物の量をそれぞれ見積もることができるという利点がある。
【0086】
残材混合物の粉砕物からの各分別粉砕物への分別の仕方、各分別粉砕物の量の見積もり、及びリサイクル品の量の見積もりは、既述と同様の手法及び構成により実行させることができる。即ち、制御プログラム9の指令を受けたCPU3により、分別粉砕物から製造されるリサイクル品の量を分別粉砕物の量に基づいて各分別粉砕物ごとに算出する手順(ステップS38)と、各リサイクル品の量をそれぞれ出力する手順(ステップS39)とを実行させるように構成することができる。
【0087】
なお、図29に示すように、既述のステップS21〜S23の代わりに、制御プログラム9の指令を受けたCPU3により、実寸補正データに基づいて基礎データを各切断瓦15aごとに算出する手順(ステップS40)と、ファイル装置2にあらかじめ記録された瓦データファイルから、切断瓦15a及び基礎データに応じた瓦データを各切断瓦15aごとに読み出す手順(ステップS41)と、瓦データ及び実寸補正データに基づいて残材15cの量を各切断瓦15aごとに算出して集計し、この集計値を残材15cの総量として出力する手順(ステップS42)とを実行させるように構成しても、既述と同様の利点がある。
【0088】
基礎データとしては、例えば瓦CADデータ37の下辺bに対する隅棟線33等の要素線の傾き等が挙げられる。制御プログラム9には、実寸補正データに基づいて要素線の傾き等を算出する計算式等が含まれている。
【0089】
瓦データには、例えば所定の傾きにおける要素線の瓦CADデータ37内の上下位置に対する残材15cの量を算出する計算式(検量線を示す数式)等が含まれている。瓦データファイルは、上記の計算式等が要素線の傾き等の基礎データ及び切断瓦15aに対応付けてファイル装置2に記録されている。制御プログラム9には、読み出された瓦データ及び実寸補正データに基づいて残材15cの量を算出する計算式等が含まれている。
【0090】
また、図30に示すように、既述のステップS21〜S23の代わりに、制御プログラム9の指令を受けたCPU3により、ファイル装置2にあらかじめ記録された3次元瓦CADデータファイルから切断瓦15aに応じた3次元瓦CADデータを各切断瓦15aごとに読み出す手順(ステップS43)と、3次元瓦CADデータに基づいて各実寸補正データをそれぞれ補正し、各切断瓦15aごとに3次元実寸補正データを算出する手順(ステップS44)と、ファイル装置2にあらかじめ記録された瓦データファイルから切断瓦15aに応じた瓦データを各切断瓦15aごとに読み出す手順(ステップS45)と、3次元瓦CADデータ、3次元実寸補正データ、及び瓦データに基づいて残材15cの量を各切断瓦15aごとに算出して集計し、この集計値を残材15cの総量として出力する手順(ステップS47)とを実行させるように構成しても、既述と同様の利点がある。
【0091】
3次元瓦CADデータファイルは、実寸スケールで3次元的に描画された各種の3次元瓦CADデータが切断瓦15aに対応付けてファイル装置に記録されている。制御プログラム9には、読み出された3次元瓦CADデータに基づいて各実寸補正データをそれぞれ補正し、各切断瓦15aごとに3次元実寸補正データを算出する計算式等が含まれている。
【0092】
瓦データには、例えば切断前の切断瓦15aの初期重量又は初期体積等が含まれている。瓦データファイルは、瓦データが切断瓦15aに対応付けてファイル装置2に記録されている。制御プログラム9には、読み出された瓦データ、3次元瓦CADデータ、及び3次元実寸補正データに基づいて残材15cの量を各切断瓦15aごとに算出して集計する計算式等が含まれている。
【0093】
ここで、瓦データを各切断瓦15aごとに読み出した(ステップS45)後、制御プログラム9の指令を受けたCPU3により、既述の瓦切断機を制御する制御装置へ3次元実寸補正データをCAMデータとして転送する手順(ステップS46)を実行させるように構成すれば、3次元CAD/CAMシステムを利用して切断瓦15aの切断作業を自動的に実行させることができるという利点がある。
【0094】
また、瓦残材積算プログラム1を記録したコンピュータ読み取り可能な記録媒体としておけば、瓦残材積算プログラム1を適宜のコンピュータのファイル装置に記録(インストール)して簡単に瓦残材積算システムを構築できるという利点がある。なお、記録媒体には、瓦残材積算プログラム1と共に、この瓦残材積算プログラム1をコンピュータのファイル装置に簡単に記録(インストール)するためのインストールプログラム等を記録しておくことができる。このような記録媒体としては、既述と同様、FD、CD−ROM、CD−RW、CD−R、MO等の各種のものが挙げられる。
【0095】
以上、この実施形態においては、実寸補正データや残材15cの総量等を瓦残材積算プログラム1により算出する場合について説明したが、その他、メインメモリ4上から抽出した実寸データ等を上記と同様にして実寸補正データ等に補正等するための計算式等を含む表計算ソフト用のフォームを例えば瓦の種類や割り付け型等ごとにファイル装置2に記録しておき、瓦残材積算プログラム1により実寸データ等を算出した後はこのフォームを利用して表計算ソフト上で実寸補正データや残材15cの総量等を算出するようにしてもよい。また、瓦残材積算プログラム1により作成された図24のような瓦屋根積算データテーブルや図25及び図28のような瓦残材積算データテーブルを、CSV(Comma Separated Value)形式やXLS形式等の表計算ソフト用又はデータベースソフト用のファイル形式で保存できるようにしてもよい。
【0096】
【発明の効果】
以上のように、請求項1、請求項2、請求項3、及び請求項11の発明によれば、瓦を施工する前にあらかじめ切断瓦の切断後の実寸を算出できると共に、残材の総量を見積もることができるので、残材を産業廃棄物として処理する場合でも、処理コスト管理を行い易い。また、残材を適宜の粒径に粉砕して粉砕物とし、この粉砕物を例えば埋め立て材等としてリサイクルする場合は、残材の総量を埋め立て材等の製品出荷量として見積もることができる。
【0097】
請求項4及び請求項11の発明によれば、コンピュータに、瓦切断機を制御する制御装置へ3次元実寸補正データをCAMデータとして転送する手順を実行させることもできるので、3次元CAD/CAMシステムを利用して切断瓦の切断作業を自動的に実行させることができる。
【0098】
請求項5及び請求項11の発明によれば、コンピュータに、分別粉砕物の量を残材の総量に基づいて各分別粉砕物ごとに算出する手順と、各分別粉砕物の量をそれぞれ出力する手順とを実行させることもできるので、各分別粉砕物をリサイクルする場合におけるそれぞれの製品出荷量を見積もることができる。
【0099】
請求項6及び請求項11の発明によれば、コンピュータに、入力装置により施工の種類として葺き替えが選択されたときに、瓦施工面CADデータに含まれている複数の瓦施工面の面積をそれぞれ算出して集計する手順と、元葺きデータファイルから元葺き瓦の種類に応じた元葺きデータを読み出す手順と、元葺きデータ及び瓦施工面の総面積に基づいて元葺き量を算出する手順と、元葺き量を出力する手順とを実行させることもできるので、瓦を葺き替える場合における元葺き量を見積もることができる。
【0100】
請求項7及び請求項11の発明によれば、コンピュータに、残材の総量と元葺き量を加算する手順と、この加算値を残材混合物の総量として出力する手順とを実行させることもできるので、葺き替えの場合における残材混合物の総量を見積もることができる。
【0101】
請求項8及び請求項11の発明によれば、コンピュータに、分別粉砕物の量を残材混合物の総量に基づいて各分別粉砕物ごとに算出する手順と、各分別粉砕物の量をそれぞれ出力する手順とを実行させることもできるので、残材混合物からの各分別粉砕物の量をそれぞれ見積もることができる。
【0102】
請求項9及び請求項11の発明によれば、コンピュータに、分別粉砕物から製造されるリサイクル品の量を分別粉砕物の量に基づいて各分別粉砕物ごとに算出する手順と、各リサイクル品の量をそれぞれ出力する手順とを実行させることもできるので、分別粉砕物から適宜のリサイクル品を製造する場合における各リサイクル品の製品出荷量をそれぞれ見積もることができる。
【0103】
請求項10の発明によれば、瓦残材積算プログラムを記録したコンピュータ読み取り可能な記録媒体であるので、上記の効果に加え、瓦残材積算プログラムを適宜のコンピュータのファイル装置に記録(インストール)して簡単に瓦残材積算システムを構築できる。
【図面の簡単な説明】
【図1】実施形態に係る瓦残材積算システムのシステム構成図。
【図2】F形瓦の表側を示す斜視図。
【図3】F形瓦の裏側を示す斜視図。
【図4】F形瓦の施工例を示す斜視図。
【図5】F形瓦を施工した状態を示す要部拡大縦断面図。
【図6】屋根の隅棟部付近を示す斜視図。
【図7】瓦残材積算プログラムによる処理の手順の一例を示すフローチャート。
【図8】瓦残材積算プログラムによる処理の手順の一例を示すフローチャート。
【図9】瓦残材積算プログラムによる処理の手順の一例を示すフローチャート。
【図10】屋根伏せ補正CADデータを表示装置の画面上に表示した状態を示す説明図。
【図11】瓦施工面CADデータを示す説明図。
【図12】瓦CADデータを示す説明図。
【図13】台形の瓦施工面に瓦CADデータを割り付けた状態を示す説明図。
【図14】三角形の瓦施工面に瓦CADデータを割り付けた状態を示す説明図。
【図15】台形の瓦施工面における隅棟線の左下側付近の要部拡大説明図。
【図16】台形の瓦施工面における隅棟線の左上側付近の要部拡大説明図。
【図17】台形の瓦施工面における隅棟線の右下側付近の要部拡大説明図。
【図18】切断瓦番号が「1」である瓦CADデータの説明図。
【図19】切断瓦番号が「2」である瓦CADデータの説明図。
【図20】切断瓦番号が「4」である瓦CADデータの説明図。
【図21】切断瓦番号が「39」である瓦CADデータの説明図。
【図22】切断瓦番号が「40」である瓦CADデータの説明図。
【図23】切断瓦番号が「86」である瓦CADデータの説明図。
【図24】瓦屋根積算データテーブルの一例を示す説明図。
【図25】瓦残材積算データテーブルの一例を示す説明図。
【図26】瓦残材積算プログラムによる処理の手順の他例を示すフローチャート。
【図27】瓦残材積算プログラムによる処理の手順の他例を示すフローチャート。
【図28】瓦残材積算データテーブルの他例を示す説明図。
【図29】瓦残材積算プログラムによる処理の手順の他例を示すフローチャート。
【図30】瓦残材積算プログラムによる処理の手順の他例を示すフローチャート。
【符号の説明】
1 瓦残材積算プログラム
2 ファイル装置
5 入力装置
6 表示装置
6a 画面
10 瓦施工面補正ルールファイル
11 割り付けルールファイル
12 瓦CADデータファイル
13 実寸算出ルールファイル
14 実寸補正ルールファイル
15D 瓦データファイル
15 F形瓦(瓦)
15a 切断瓦
15c 残材
16 屋根
16a 隅棟部
31 屋根伏せ補正CADデータ
32 陸棟線(要素線)
33 隅棟線(要素線)
34 軒瓦線(要素線)
35 瓦施工面CADデータ
36a,36b 瓦施工面
37 瓦CADデータ
N 切断瓦番号[0001]
BACKGROUND OF THE INVENTION
This invention calculates the actual size (actual dimension) of the cut tiles constructed along the corner ridges of the roof by cutting a predetermined range among the tiles constructed on the roof of the building, and excised from the cut tiles The present invention relates to a tile remaining material accumulation program for calculating the amount of remaining material, etc., a computer-readable recording medium recording the program, and a tile remaining material accumulation system.
[0002]
[Prior art]
As is well known, when tiles are constructed on the roof of a building such as a dormitory roof, the tiles (cut tiles) constructed on the corner ridges, etc. of the roof are preliminarily cut in a diagonal direction. It is necessary to keep. The measuring work and the cutting work of the roof tile at the construction site are performed each time at the construction site. Moreover, the remaining material cut out from the cut roof tile is treated as industrial waste.
[0003]
[Problems to be solved by the invention]
However, there is a problem that it is difficult to manage the processing cost of the remaining material because the total amount of the remaining material cannot be grasped unless the roof cutting operation is completed.
[0004]
The present invention has been made in view of the above problems, and a tile remaining material accumulation program capable of estimating the total amount of remaining material in advance before constructing a roof tile, and a computer-readable recording of the program. It is an object of the present invention to provide a recording medium and a roof tile accumulation system.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, the remaining tile accumulation program according to
[0006]
The tile remaining material accumulation program according to
[0007]
The tile residual material accumulation program according to
[0008]
In the roof tile accumulation program according to the fourth aspect, it is possible to cause the computer to execute a procedure of transferring the three-dimensional actual size correction data as CAM data to a control device that controls a roof tile cutting machine for processing the roof tile.
[0009]
In the tile remaining material accumulation program according to
[0010]
In the tile remaining material accumulation program according to claim 6, when the replacement is selected as the construction type by the input device, the computer calculates the areas of the plurality of tile construction surfaces included in the tile construction surface CAD data, respectively. And the procedure for reading the original roofing data according to the type of the roofing tile input from the input device, the source roofing data and the roof construction surface It is also possible to execute a procedure for calculating the original amount of fire based on the total area and a procedure for outputting the original amount of fire.
[0011]
In the roof tile accumulation program according to the seventh aspect, it is possible to cause the computer to execute a procedure of adding the total amount of the remaining material and the amount of the original material and a procedure of outputting the added value as the total amount of the remaining material mixture.
[0012]
In the tile remaining material integration program according to
[0013]
In the tile remaining material accumulation program according to
[0014]
A computer-readable recording medium according to a tenth aspect is a recording medium for recording the roof tile accumulation material accumulation program according to any one of the first to ninth aspects.
[0015]
Further, the tile remaining material accumulation system records the tile remaining material accumulation program according to any one of
[0016]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings.
As shown in FIG. 1, the remaining
[0017]
The computer includes a
[0018]
The tile remaining material integration program (software) 1 includes a
[0019]
Before explaining in detail the processing by the tile remaining
[0020]
The F-shaped
[0021]
As shown in FIGS. 3 and 5, for example, two
[0022]
The amount of remaining material to be cut from the cut tile is calculated by virtually executing the allocation of the tile as described above on a computer in advance and calculating the actual size after cutting the cut tile. Is calculated. In addition, as a kind of tile to allocate, various thick slate, a metal plate roof tile, etc. other than clay roof tiles, such as F-shaped
[0023]
Next, a procedure example of the processing by the roof
[0024]
First, the roof-cover CAD data recorded in the storage means in a file format for CAD software such as DXF (Drawing Interchange File) format is read into the
[0025]
Examples of the storage means in which the roofing CAD data is recorded include FD (Flexible Disk), CD-ROM (Compact Disc Read Only Memory), CD-R (Compact Disc Recordable), CD-RW (Compact Disc Rewritable), In addition to computer-readable recording media such as MO (Magneto Optical Disk), hard disk drives (networks) of other computers that can be accessed via a network such as a LAN (Local Area Network) or the Internet. Drive).
[0026]
The roof covering CAD data represents a roof covering diagram corresponding to a plan view of the
[0027]
Next, the scale of the roof-cover CAD data is input from the
[0028]
Input is performed by typing "1: 100" or "1/100", "1:30" or "1/30", "1: 1" or "1/1" etc. from a keyboard or the like. However, the above-described types of scales assigned to pull-down menus such as a menu bar (toolbar) on the screen 6a of the display device 6 in the GUI (Graphical User Interface) environment and the right button (right click) of the mouse. If it can be selected with a mouse or the like, it can be easily executed.
[0029]
After that, the
[0030]
For example, in the case of a dormitory roof as shown in FIG. 10, the roofing
[0031]
Next, the type is designated for each element line from the
[0032]
In the example of FIG. 10, the land building line (element line) 32 is the land building line, the corner building line (element line) 33 is the corner building line, and the eaves tile line (element line) 34 is the eaves roof line. The element line type is specified. For example, after selecting or selecting an appropriate element line on the screen 6a with a mouse or the like, pull-down such as a menu bar (toolbar) on the screen 6a or a right button (right click) of the mouse in the GUI environment. If the type of element line assigned to a menu or the like can be selected with a mouse or the like, it can be easily executed. In this case, various types of element lines such as “land building line”, “corner building line”, and “eave tile line” can be assigned to the pull-down menu or the like. In addition, in order to cope with the case where the roof surface is a convex shin (tele) or a concave ridge (turn), for example, "Sumi-Kon Line (shine)" or "Sumi-Kon Line (rise) It is desirable to be able to specify a type such as “”. In this case, for example, “corner ridge line (shine: R = XXXX)” or “corner ridge line (raise: R = XXXX)” or the like that takes account of the radius of curvature (R) of shine or rise is used as the radius of curvature It can also be made to be selectable accordingly.
[0033]
Thereafter, the tile type, the roof gradient, and the layout type are input from the
[0034]
Also in this case, if the tile type assigned to the pull-down menu or the like in the GUI environment can be selected with a mouse or the like, it can be easily input. Examples of the tile type assigned to the pull-down menu include “F-shaped roof tile”, “J-shaped roof tile”, “S-shaped roof tile”, and the like. Similarly, examples of the roof slope include “4/10”, “3.5 / 10”, “3/10”, “2.5 / 10”, “1/10”, and the like. As the allocation type, for example, a so-called “symmetric type” in which the lowermost tile is arranged from the
[0035]
Next, the tile construction surface
[0036]
In the tile construction surface
[0037]
Thereafter, the
[0038]
The tile construction
[0039]
As described above, the tile construction surface correction rule is applied according to the combination of the element lines and the type of the tile, so that the roof-up
[0040]
The eaves protruding dimension E and the like vary depending on the type of tile, but since the tile construction surface correction rule corresponding to the type of tile is applied, the tile construction
[0041]
When the above-mentioned “Sumishin Line (light: R = XXXX)” or “Sumishin Line (rise: R = XXXX)” or the like is specified as the type of element line, that is, the roof surface is lighted or raised. Is also corrected based on the radius of curvature (R) of the shimmer or rise.
[0042]
Further, the created roof construction
[0043]
Next, the
[0044]
In the
[0045]
Further, the tile CAD data file 12 is retrieved by the
[0046]
In the roof tile CAD data file 12, various roof tile CAD data drawn on an actual scale are recorded in association with roof tile types and layout types. For example, when the type of roof tile is “F roof tile” and the allocation type is “symmetric” roof
[0047]
Thereafter, as shown in FIGS. 13 and 14, the tile CAD data 37 (only the working
[0048]
For example, in the example of FIGS. 13 and 14, the roof
[0049]
Similarly to the above, the
[0050]
Next, the tile CAD data 37 (the work surface in FIGS. 15 to 17) as the
[0051]
For example, in the examples of FIGS. 15 to 17, for example, the corner building is based on the allocation rule read according to the case where the type of roof tile is “F-shaped roof tile” and the layout type is “symmetric”. Cut tile numbers N such as “1”, “2”, “3”, etc. are assigned to the
[0052]
In the same manner as described above, the
[0053]
Thereafter, the actual size
[0054]
Next, as shown in FIGS. 18 to 23, the
[0055]
In the actual size
[0056]
Here, upon receiving a command from the
[0057]
Thereafter, the
[0058]
In the actual size
[0059]
Next, the
[0060]
Here, as shown in FIG. 8, the tile roof integrated data table as shown in FIG. 24 is created by associating the actual size correction data with the
[0061]
Further, the
[0062]
24. As shown in FIG. 24, for example, “trapezoid one step left”, “trapezoid two steps left”, “
[0063]
In this case, the
[0064]
Examples of the type depending on the shape of the
[0065]
After that, as shown in FIG. 9, the basic data is calculated based on the actual size correction data by the
[0066]
Examples of the basic data include a projected area after cutting the
[0067]
Next, the roof tile data file is retrieved by the
[0068]
The tile data includes, for example, an initial weight or an initial volume in addition to the initial projected area of the
[0069]
Thereafter, the
[0070]
The
[0071]
According to the tile remaining material accumulation system and the tile remaining
[0072]
Here, as shown in FIG. 26, after the total amount of the remaining
[0073]
The pulverized product can be classified into, for example, three types of separately pulverized products having a particle size of less than 1 mm, less than 1 mm, less than 3 mm, and 3 mm. In the
[0074]
In addition, as shown in FIG. 26, after outputting the amount of each pulverized product (step S25), the recycled product manufactured from the pulverized product by the
[0075]
As recycled products, if the particle size of the pulverized product is less than 1 mm, for example, raw materials for Nanto plaster, cement blocks such as U-shaped grooves, L-shaped blocks for roadside belts, flowerpots, planters, interlocking blocks, etc. Is mentioned. The raw material for Nanban plaster can be produced by adding and mixing slaked lime, soot, etc. in an appropriate ratio to a fractionally pulverized product having a particle size of less than 1 mm. Cement block or cement product is added to kneaded pulverized material having a particle size of less than 1 mm in an appropriate ratio, kneaded and cast, press, centrifugal, or extrusion, and Can be manufactured by curing.
[0076]
When the particle size of the pulverized product is, for example, 1 mm or more and less than 3 mm, examples of the recycled product include seedling raising materials such as a seedbed soil. If the seedling material is a pulverized product having a particle size of 1 mm or more and less than 3 mm, a chemical fertilizer, organic fertilizer, humus, granulating agent, moisture, etc. are added at an appropriate ratio, mixed, shaped into granules, dried, etc. Can be manufactured.
[0077]
When the particle size of the separated and pulverized product is, for example, 3 mm or more, examples of the recycled products include rubble for building foundations, civil engineering and building materials such as road aggregates, and the like. Civil engineering and construction materials are added to and mixed with solidified materials such as cement, lignate, and stearate, and water, etc., in appropriate proportions, and then shaped into granules, cured, etc. Can be manufactured.
[0078]
In the
[0079]
Here, as shown in FIG. 27, instead of the above-described steps S24 to S27, after outputting the total amount of the remaining
[0080]
When new construction is selected as the construction type by the input device 5 (NO in step S28), the process proceeds to step S24, and the above-described processing is executed.
[0081]
In addition, the original amount of firewood refers to the total amount (total weight or total weight) of the former thatched tiles (old tiles) that had already been constructed before the replacement of the tiles and the former thatched soils (old soil) that were used to construct them. Volume). Also in this case, if the type of construction assigned to the pull-down menu or the like in the GUI environment or the type of the former roof tile can be selected with a mouse or the like, it can be easily input. Examples of the construction type assigned to the pull-down menu include “replacement” and “new construction”. Similarly, examples of the original roof tile include “F-shaped roof tile”, “J-shaped roof tile”, and “S-shaped roof tile”.
[0082]
In the original roofing data file, the amount of original roofing per unit area of the tile construction surfaces 36a and 36b is recorded in the file device in association with the type of roofing tile. The
[0083]
In addition, as shown in FIG. 27, after outputting the original amount (step S33), the
[0084]
The
[0085]
Further, as shown in FIG. 27, after the total amount of the remaining material mixture is output (step S35), the
[0086]
The method of separating the remaining material mixture from the pulverized product into each pulverized product, the estimation of the amount of each pulverized product, and the estimation of the amount of the recycled product can be executed by the same method and configuration as described above. . That is, the
[0087]
In addition, as shown in FIG. 29, instead of the above-described steps S21 to S23, the
[0088]
As the basic data, for example, the inclination of an element line such as the
[0089]
The roof tile data includes, for example, a calculation formula (formula indicating a calibration curve) for calculating the amount of the remaining
[0090]
Further, as shown in FIG. 30, instead of the above-described steps S21 to S23, the
[0091]
In the three-dimensional roof CAD data file, various three-dimensional roof CAD data drawn three-dimensionally on an actual scale are recorded in the file device in association with the
[0092]
The tile data includes, for example, the initial weight or initial volume of the
[0093]
Here, after the roof tile data is read for each cutting
[0094]
In addition, if a computer-readable recording medium that records the roof
[0095]
As described above, in this embodiment, the case where the actual size correction data, the total amount of the remaining
[0096]
【The invention's effect】
As described above, according to the first, second, third, and eleventh inventions, the actual size after cutting of the roof tile can be calculated in advance before the roof tile is constructed, and the total amount of the remaining material. Therefore, even when the remaining material is processed as industrial waste, it is easy to manage the processing cost. Further, when the remaining material is pulverized into an appropriate particle size to obtain a pulverized product, and the pulverized product is recycled as, for example, a landfill material, the total amount of the remaining material can be estimated as a product shipment amount of the landfill material.
[0097]
According to the fourth and eleventh aspects of the invention, it is possible to cause the computer to execute a procedure for transferring the three-dimensional actual size correction data as CAM data to the control device for controlling the roof tile cutting machine. The system can be used to automatically execute the cutting work of the roof tile.
[0098]
According to the fifth and eleventh aspects of the present invention, a procedure for calculating the amount of the separately pulverized product for each of the pulverized products based on the total amount of the remaining material and the amount of each of the pulverized products are output to the computer. Therefore, it is possible to estimate each product shipment amount in the case of recycling each sorted pulverized product.
[0099]
According to the sixth and eleventh aspects of the present invention, when switching is selected as the type of construction by the input device, the areas of the plurality of tile construction surfaces included in the tile construction surface CAD data are respectively determined. A procedure for calculating and summing up, a procedure for reading the original roofing data corresponding to the type of the original roof tile from the original roofing data file, a procedure for calculating the amount of the roofing based on the original roofing data and the total area of the roof tile construction surface, and In addition, since it is possible to execute the procedure of outputting the original amount of fire, it is possible to estimate the amount of original fire when the roof tile is replaced.
[0100]
According to the seventh and eleventh aspects of the invention, it is possible to cause the computer to execute a procedure for adding the total amount of the remaining material and the amount of the original material and a procedure for outputting the added value as the total amount of the remaining material mixture. Therefore, it is possible to estimate the total amount of the remaining material mixture in the case of replacement.
[0101]
According to the eighth and eleventh aspects of the invention, a procedure for calculating the amount of the separately pulverized product for each of the pulverized products based on the total amount of the remaining material mixture and the amount of each of the pulverized products are output to the computer. Therefore, it is possible to estimate the amount of each pulverized product from the remaining material mixture.
[0102]
According to the ninth and eleventh aspects of the invention, the computer calculates the amount of the recycled product produced from the fractionated pulverized product for each fractionated pulverized product based on the amount of the fractionated pulverized product, and each recycled product. Therefore, it is possible to estimate the product shipment amount of each recycled product when an appropriate recycled product is manufactured from the separately pulverized product.
[0103]
According to the invention of
[Brief description of the drawings]
FIG. 1 is a system configuration diagram of a tile remaining material integrating system according to an embodiment.
FIG. 2 is a perspective view showing the front side of an F-shaped roof tile.
FIG. 3 is a perspective view showing the back side of an F-shaped roof tile.
FIG. 4 is a perspective view showing a construction example of F-shaped roof tiles.
FIG. 5 is an enlarged vertical cross-sectional view of a main part showing a state in which an F-shaped roof tile is constructed.
FIG. 6 is a perspective view showing the vicinity of a corner ridge portion of a roof.
FIG. 7 is a flowchart showing an example of a processing procedure by a roof tile accumulation program.
FIG. 8 is a flowchart showing an example of a processing procedure performed by a roof tile accumulation program.
FIG. 9 is a flowchart showing an example of a procedure of processing by a roof tile accumulation program.
FIG. 10 is an explanatory diagram illustrating a state in which roof-up correction CAD data is displayed on a screen of a display device.
FIG. 11 is an explanatory diagram showing tile construction surface CAD data.
FIG. 12 is an explanatory diagram showing roof tile CAD data.
FIG. 13 is an explanatory view showing a state in which tile CAD data is assigned to a trapezoidal tile construction surface.
FIG. 14 is an explanatory diagram showing a state in which tile CAD data is assigned to a triangular roof tile construction surface.
FIG. 15 is an enlarged explanatory view of the main part near the lower left side of the corner building line on the trapezoidal tile construction surface.
FIG. 16 is an enlarged explanatory view of the main part near the upper left side of the corner building line on the trapezoidal tile construction surface.
FIG. 17 is an enlarged explanatory view of the main part near the lower right side of the corner building line on the trapezoidal tile construction surface.
FIG. 18 is an explanatory diagram of roof tile CAD data whose cut roof tile number is “1”.
FIG. 19 is an explanatory diagram of roof tile CAD data whose cut roof tile number is “2”.
FIG. 20 is an explanatory diagram of roof tile CAD data whose cut roof tile number is “4”.
FIG. 21 is an explanatory diagram of roof tile CAD data whose cut roof tile number is “39”.
FIG. 22 is an explanatory diagram of roof tile CAD data whose cut roof tile number is “40”.
FIG. 23 is an explanatory diagram of roof tile CAD data whose cut roof tile number is “86”.
FIG. 24 is an explanatory diagram showing an example of a tiled roof integration data table.
FIG. 25 is an explanatory diagram showing an example of a tile remaining material integration data table.
FIG. 26 is a flowchart showing another example of the processing procedure by the roof tile accumulation program.
FIG. 27 is a flowchart showing another example of the processing procedure by the tile remaining material integration program.
FIG. 28 is an explanatory view showing another example of the tile remaining material integration data table.
FIG. 29 is a flowchart showing another example of the processing procedure by the roof tile accumulation program.
FIG. 30 is a flowchart showing another example of the processing procedure by the tile remaining material integration program.
[Explanation of symbols]
1 Tile residue accumulation program
2 File device
5 input devices
6 Display device
6a screen
10 Tile construction surface correction rule file
11 Allocation rule file
12 Tile CAD data file
13 Actual size calculation rule file
14 Actual size correction rule file
15D roof tile data file
15 F-shaped roof tile (tile)
15a Cut tile
15c Remaining material
16 Roof
16a Corner building
31 Roof-up correction CAD data
32 Land building line (element line)
33 Corner building line (element line)
34 tile lines (element lines)
35 Roof construction surface CAD data
36a, 36b Tile construction surface
37 Tile CAD data
N Cut tile number
Claims (11)
所定の記憶手段から屋根伏せCADデータを読み込む手順と、
入力装置から入力された屋根伏せCADデータの縮尺に基づいて屋根伏せCADデータを実寸スケールに補正し、屋根伏せ補正CADデータを作成する手順と、
屋根伏せ補正CADデータを表示装置の画面上に表示する手順と、
ファイル装置にあらかじめ記録された瓦施工面補正ルールファイルから、入力装置により屋根伏せ補正CADデータにそれぞれ指定された要素線の組合せ及び入力装置から入力された瓦の種類に応じた瓦施工面補正ルールを読み出す手順と、
瓦施工面補正ルール及び入力装置から入力された屋根勾配に基づいて屋根伏せ補正CADデータを補正し、瓦施工面CADデータを作成する手順と、
ファイル装置にあらかじめ記録された割り付けルールファイルから、瓦の種類及び入力装置から入力された割り付け型に応じた割り付けルールを読み出す手順と、
ファイル装置にあらかじめ記録された瓦CADデータファイルから瓦の種類及び割り付け型に応じた瓦CADデータを読み出す手順と、
瓦CADデータを割り付けルールに基づいて瓦施工面CADデータに割り付ける手順と、
瓦施工面CADデータの要素線と交差する切断瓦としての瓦CADデータに割り付けルールに基づいて切断瓦番号を付与する手順と、
ファイル装置にあらかじめ記録された実寸算出ルールファイルから瓦の種類に応じた実寸算出ルールを読み出す手順と、
実寸算出ルールに基づいて各切断瓦ごとに実寸データを算出する手順と、
ファイル装置にあらかじめ記録された実寸補正ルールファイルから、瓦の種類に応じた実寸補正ルールを読み出す手順と、
実寸補正ルールに基づいて各実寸データをそれぞれ補正し、各切断瓦ごとに実寸補正データを算出する手順と、
実寸補正データに基づいて基礎データを各切断瓦ごとに算出する手順と、
ファイル装置にあらかじめ記録された瓦データファイルから切断瓦に応じた瓦データを各切断瓦ごとに読み出す手順と、
基礎データ及び瓦データに基づいて残材の量を各切断瓦ごとに算出して集計し、この集計値を残材の総量として出力する手順と、
を実行させるための瓦残材積算プログラム。In order to calculate the actual size after cutting of the cut tiles constructed by cutting a predetermined range among the tiles constructed on the roof of the building, and to calculate the amount of remaining material cut from the cut tiles,
A procedure for reading roof covering CAD data from a predetermined storage means;
A procedure for correcting the roofing CAD data to an actual scale based on the scale of the roofing CAD data input from the input device, and creating roofing correction CAD data;
A procedure for displaying the roofing correction CAD data on the screen of the display device;
The tile construction surface correction rule according to the combination of the element lines specified in the roofing correction CAD data by the input device and the type of the tile input from the input device from the tile construction surface correction rule file recorded in advance in the file device The procedure of reading
A procedure for correcting the roofing correction CAD data based on the tile construction surface correction rule and the roof slope input from the input device, and creating the tile construction surface CAD data;
A procedure for reading out an allocation rule corresponding to the type of roof tile and the allocation type input from the input device from the allocation rule file recorded in advance on the file device;
A procedure for reading roof tile CAD data corresponding to the type and layout type of roof tiles from a roof tile CAD data file recorded in advance in the file device;
A procedure for allocating tile CAD data to the tile construction surface CAD data based on the allocation rules;
A procedure for assigning a cut tile number to the tile CAD data as a cut tile intersecting with the element line of the tile construction surface CAD data based on the allocation rule;
A procedure for reading an actual size calculation rule corresponding to the type of roof tile from an actual size calculation rule file recorded in advance on the file device,
A procedure for calculating the actual size data for each cutting tile based on the actual size calculation rule,
A procedure for reading out an actual size correction rule corresponding to the type of roof tile from an actual size correction rule file recorded in advance on the file device,
Correcting each actual size data individually based on the actual size correction rule, calculating the actual size correction data for each cutting roof,
A procedure for calculating basic data for each cutting tile based on the actual size correction data,
A procedure for reading roof tile data corresponding to each cut roof tile from a roof tile data file recorded in advance on the file device,
Calculating and totaling the amount of remaining material for each cut tile based on the basic data and roof tile data, and outputting this total value as the total amount of remaining material;
Tile residual material accumulation program for running.
所定の記憶手段から屋根伏せCADデータを読み込む手順と、
入力装置から入力された屋根伏せCADデータの縮尺に基づいて屋根伏せCADデータを実寸スケールに補正し、屋根伏せ補正CADデータを作成する手順と、
屋根伏せ補正CADデータを表示装置の画面上に表示する手順と、
ファイル装置にあらかじめ記録された瓦施工面補正ルールファイルから、入力装置により屋根伏せ補正CADデータにそれぞれ指定された要素線の組合せ及び入力装置から入力された瓦の種類に応じた瓦施工面補正ルールを読み出す手順と、
瓦施工面補正ルール及び入力装置から入力された屋根勾配に基づいて屋根伏せ補正CADデータを補正し、瓦施工面CADデータを作成する手順と、
ファイル装置にあらかじめ記録された割り付けルールファイルから、瓦の種類及び入力装置から入力された割り付け型に応じた割り付けルールを読み出す手順と、
ファイル装置にあらかじめ記録された瓦CADデータファイルから瓦の種類及び割り付け型に応じた瓦CADデータを読み出す手順と、
瓦CADデータを割り付けルールに基づいて瓦施工面CADデータに割り付ける手順と、
瓦施工面CADデータの要素線と交差する切断瓦としての瓦CADデータに割り付けルールに基づいて切断瓦番号を付与する手順と、
ファイル装置にあらかじめ記録された実寸算出ルールファイルから瓦の種類に応じた実寸算出ルールを読み出す手順と、
実寸算出ルールに基づいて各切断瓦ごとに実寸データを算出する手順と、
ファイル装置にあらかじめ記録された実寸補正ルールファイルから瓦の種類に応じた実寸補正ルールを読み出す手順と、
実寸補正ルールに基づいて各実寸データをそれぞれ補正し、各切断瓦ごとに実寸補正データを算出する手順と、
実寸補正データに基づいて基礎データを各切断瓦ごとに算出する手順と、
ファイル装置にあらかじめ記録された瓦データファイルから、切断瓦及び基礎データに応じた瓦データを各切断瓦ごとに読み出す手順と、
瓦データ及び実寸補正データに基づいて残材の量を各切断瓦ごとに算出して集計し、この集計値を残材の総量として出力する手順と、
を実行させるための瓦残材積算プログラム。In order to calculate the actual size after cutting of the cut tiles constructed by cutting a predetermined range among the tiles constructed on the roof of the building, and to calculate the amount of remaining material cut from the cut tiles,
A procedure for reading roof covering CAD data from a predetermined storage means;
A procedure for correcting the roofing CAD data to an actual scale based on the scale of the roofing CAD data input from the input device, and creating roofing correction CAD data;
A procedure for displaying the roofing correction CAD data on the screen of the display device;
The tile construction surface correction rule according to the combination of the element lines specified in the roofing correction CAD data by the input device and the type of the tile input from the input device from the tile construction surface correction rule file recorded in advance in the file device The procedure of reading
A procedure for correcting the roofing correction CAD data based on the tile construction surface correction rule and the roof slope input from the input device, and creating the tile construction surface CAD data;
A procedure for reading out an allocation rule corresponding to the type of roof tile and the allocation type input from the input device from the allocation rule file recorded in advance on the file device;
A procedure for reading roof tile CAD data corresponding to the type and layout type of roof tiles from a roof tile CAD data file recorded in advance in the file device;
A procedure for allocating tile CAD data to the tile construction surface CAD data based on the allocation rules;
A procedure for assigning a cut tile number to the tile CAD data as a cut tile intersecting with the element line of the tile construction surface CAD data based on the allocation rule;
A procedure for reading an actual size calculation rule corresponding to the type of roof tile from an actual size calculation rule file recorded in advance on the file device,
A procedure for calculating the actual size data for each cutting tile based on the actual size calculation rule,
The procedure for reading out the actual size correction rule corresponding to the type of roof tile from the actual size correction rule file recorded in advance on the file device,
Correcting each actual size data individually based on the actual size correction rule, calculating the actual size correction data for each cutting roof,
A procedure for calculating basic data for each cutting tile based on the actual size correction data,
A procedure for reading the roof tile data corresponding to the cut roof tile and the basic data from the roof tile data file recorded in advance in the file device for each roof tile,
A procedure for calculating and totaling the amount of remaining material for each cut roof tile based on the roof tile data and actual size correction data, and outputting this total value as the total amount of remaining material,
Tile residual material accumulation program for running.
所定の記憶手段から屋根伏せCADデータを読み込む手順と、
入力装置から入力された屋根伏せCADデータの縮尺に基づいて屋根伏せCADデータを実寸スケールに補正し、屋根伏せ補正CADデータを作成する手順と、
屋根伏せ補正CADデータを表示装置の画面上に表示する手順と、
ファイル装置にあらかじめ記録された瓦施工面補正ルールファイルから、入力装置により屋根伏せ補正CADデータにそれぞれ指定された要素線の組合せ及び入力装置から入力された瓦の種類に応じた瓦施工面補正ルールを読み出す手順と、
瓦施工面補正ルール及び入力装置から入力された屋根勾配に基づいて屋根伏せ補正CADデータを補正し、瓦施工面CADデータを作成する手順と、
ファイル装置にあらかじめ記録された割り付けルールファイルから、瓦の種類及び入力装置から入力された割り付け型に応じた割り付けルールを読み出す手順と、
ファイル装置にあらかじめ記録された瓦CADデータファイルから瓦の種類及び割り付け型に応じた瓦CADデータを読み出す手順と、
瓦CADデータを割り付けルールに基づいて瓦施工面CADデータに割り付ける手順と、
瓦施工面CADデータの要素線と交差する切断瓦としての瓦CADデータに割り付けルールに基づいて切断瓦番号を付与する手順と、
ファイル装置にあらかじめ記録された実寸算出ルールファイルから瓦の種類に応じた実寸算出ルールを読み出す手順と、
実寸算出ルールに基づいて各切断瓦ごとに実寸データを算出する手順と、
ファイル装置にあらかじめ記録された実寸補正ルールファイルから、瓦の種類に応じた実寸補正ルールを読み出す手順と、
実寸補正ルールに基づいて各実寸データをそれぞれ補正し、各切断瓦ごとに実寸補正データを算出する手順と、
ファイル装置にあらかじめ記録された3次元瓦CADデータファイルから切断瓦に応じた3次元瓦CADデータを各切断瓦ごとに読み出す手順と、
3次元瓦CADデータに基づいて各実寸補正データをそれぞれ補正し、各切断瓦ごとに3次元実寸補正データを算出する手順と、
ファイル装置にあらかじめ記録された瓦データファイルから切断瓦に応じた瓦データを各切断瓦ごとに読み出す手順と、
3次元瓦CADデータ、3次元実寸補正データ、及び瓦データに基づいて残材の量を各切断瓦ごとに算出して集計し、この集計値を残材の総量として出力する手順と、
を実行させるための瓦残材積算プログラム。In order to calculate the actual size after cutting of the cut tiles constructed by cutting a predetermined range among the tiles constructed on the roof of the building, and to calculate the amount of remaining material cut from the cut tiles,
A procedure for reading roof covering CAD data from a predetermined storage means;
A procedure for correcting the roofing CAD data to an actual scale based on the scale of the roofing CAD data input from the input device, and creating roofing correction CAD data;
A procedure for displaying the roofing correction CAD data on the screen of the display device;
The tile construction surface correction rule according to the combination of the element lines specified in the roofing correction CAD data by the input device and the type of the tile input from the input device from the tile construction surface correction rule file recorded in advance in the file device The procedure of reading
A procedure for correcting the roofing correction CAD data based on the tile construction surface correction rule and the roof slope input from the input device, and creating the tile construction surface CAD data;
A procedure for reading out an allocation rule corresponding to the type of roof tile and the allocation type input from the input device from the allocation rule file recorded in advance on the file device;
A procedure for reading roof tile CAD data corresponding to the type and layout type of roof tiles from a roof tile CAD data file recorded in advance in the file device;
A procedure for allocating tile CAD data to the tile construction surface CAD data based on the allocation rules;
A procedure for assigning a cut tile number to the tile CAD data as a cut tile intersecting with the element line of the tile construction surface CAD data based on the allocation rule;
A procedure for reading an actual size calculation rule corresponding to the type of roof tile from an actual size calculation rule file recorded in advance on the file device,
A procedure for calculating the actual size data for each cutting tile based on the actual size calculation rule,
A procedure for reading out an actual size correction rule corresponding to the type of roof tile from an actual size correction rule file recorded in advance on the file device,
Correcting each actual size data individually based on the actual size correction rule, calculating the actual size correction data for each cutting roof,
A procedure for reading out the 3D roof tile CAD data corresponding to the cut roof tile from the 3D roof tile CAD data file recorded in advance in the file device for each cut roof tile,
A procedure for correcting each actual size correction data based on the three-dimensional roof tile CAD data and calculating the three-dimensional actual size correction data for each cut roof tile,
A procedure for reading roof tile data corresponding to each cut roof tile from a roof tile data file recorded in advance on the file device,
A procedure for calculating and totaling the amount of remaining material for each cut roof tile based on the three-dimensional roof tile CAD data, the three-dimensional actual size correction data, and the roof tile data, and outputting the total value as the total amount of the remaining material;
Tile residual material accumulation program for running.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002209792A JP3968750B2 (en) | 2002-07-18 | 2002-07-18 | Brick residue accumulation program, computer-readable recording medium recording the program, and tile residue accumulation system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002209792A JP3968750B2 (en) | 2002-07-18 | 2002-07-18 | Brick residue accumulation program, computer-readable recording medium recording the program, and tile residue accumulation system |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004054506A JP2004054506A (en) | 2004-02-19 |
JP3968750B2 true JP3968750B2 (en) | 2007-08-29 |
Family
ID=31933548
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002209792A Expired - Lifetime JP3968750B2 (en) | 2002-07-18 | 2002-07-18 | Brick residue accumulation program, computer-readable recording medium recording the program, and tile residue accumulation system |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3968750B2 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10909482B2 (en) * | 2013-03-15 | 2021-02-02 | Pictometry International Corp. | Building materials estimation |
JP6395091B2 (en) * | 2014-09-12 | 2018-09-26 | パナソニックIpマネジメント株式会社 | Allocation device, program |
CN111274642B (en) * | 2020-01-23 | 2023-11-21 | 久瓴(江苏)数字智能科技有限公司 | Method and device for generating pottery tile sloping roof, computer equipment and storage medium |
JP7167289B1 (en) * | 2021-10-19 | 2022-11-08 | サンユー販売株式会社 | ROOFING MATERIAL ALLOCATION DEVICE, METHOD AND PROGRAM THEREOF |
JP7264356B1 (en) | 2022-01-26 | 2023-04-25 | ケイミュー株式会社 | Roof material allocation device |
-
2002
- 2002-07-18 JP JP2002209792A patent/JP3968750B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2004054506A (en) | 2004-02-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8260585B2 (en) | Computer-implemented land planning system and method designed to generate at least one conceptual fit solution to a user-defined land development problem | |
CN108475399B (en) | Simulation system and simulation method | |
US8718941B2 (en) | Monitoring and displaying deflection of layers of landfill material | |
JP3968750B2 (en) | Brick residue accumulation program, computer-readable recording medium recording the program, and tile residue accumulation system | |
Seeley et al. | Building quantities explained | |
Cajzek et al. | Cost optimization of project schedules under constrained resources and alternative production processes by mixed-integer nonlinear programming | |
Hassanein et al. | Planning and scheduling highway construction | |
Cairo | Environmental and sustainable guidelines for integrated municipal solid waste management in Egypt | |
JP3962833B2 (en) | Tile roof accumulation program, computer-readable recording medium recording the program, and tile roof accumulation system | |
Horner et al. | Characteristic items-a new approach to pricing and controlling construction projects | |
CN105064163A (en) | Cement stabilization macadam base layer ultrahigh reverse slope section one-time molding construction method | |
KR102112747B1 (en) | Method for planning of construction management using vertical relation and horizontal relation and program and computer readable media thereof | |
Bannister | Building construction inspection: A guide for architects | |
JP2000250975A (en) | Progress schedule generation system | |
Jackson et al. | Using existing pavement in place and achieving long life | |
CN204676387U (en) | A kind of cement concrete pavement becomes base layer structure | |
AECOM | Spon's External Works and Landscape Price Book 2019 | |
Khalik et al. | Simulation analysis for schedule and performance evaluation of slip forming operations | |
Dietrich | Kerr's Cost Data for Landscape Construction: 1994 Unit Prices for Site Development | |
JP2004118686A (en) | Civil engineering construction cost management program and recording medium | |
Ding et al. | Stadium Neighborhood Underground Parkades and Water Storage | |
Sabahi | Speeding up the process of modeling temporary structures in a building information model using predefined families | |
McCormack | Driveways, Paths and Patios | |
Donatello et al. | Revision of EU Ecolabel criteria for Hard Coverings | |
Andersen et al. | Team Squared |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050506 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070426 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070525 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3968750 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130615 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |