JP3942152B2 - Road surface lining construction method - Google Patents
Road surface lining construction method Download PDFInfo
- Publication number
- JP3942152B2 JP3942152B2 JP2001350014A JP2001350014A JP3942152B2 JP 3942152 B2 JP3942152 B2 JP 3942152B2 JP 2001350014 A JP2001350014 A JP 2001350014A JP 2001350014 A JP2001350014 A JP 2001350014A JP 3942152 B2 JP3942152 B2 JP 3942152B2
- Authority
- JP
- Japan
- Prior art keywords
- support
- lining
- earth retaining
- height
- road surface
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【産業上の利用分野】
本発明は、道路等の地盤(路盤)に溝を開削して下水管等の埋設や補修等を行う際に、工事の途中における安全を確保できるようにした路面覆工施工法に関するものである。
【0002】
【従来の技術】
道路等の地盤に下水管等を埋設したり、埋設されている下水管等の補修を行う工事においては、路盤を掘削して開削溝を形成することが行われているが、この工事は1日では完了せず数日にわたって継続されることが多い。このような場合、夜間等工事休止中の安全を確保するため、開削溝の上部開口を覆工板で覆い、歩行者等の転落防止や車等が交通できるようにしている。
【0003】
この種の工事では、従来一般に、図5、図6に示すような方法が採られている。図5に示す方法は、開削する開削溝Aの両側に土留杭1,1を打込み、腹起し材3と切梁4を設けて地山の崩壊を防止し、土留杭1,1の上部に取り付けた受ピース5,5に受桁6を架設し、その上に複数に分割形成された覆工板7,7を路面aと面一となるようにして載設するものである。
【0004】
また、図6の方法は、開削溝Aの両側に地山支持部20を設けて、その上に桁受基礎9,9を造成し、これに受桁6を架設し、開削溝Aの両側に土留矢板2,2を打込みあるいは建て込み、腹起し材3と切梁4を設けて地山の崩壊を防止するとともに、受桁6上に覆工板7,7を路面aと面一となるように載設するものである。
【0005】
【発明が解決しようとする課題】
ところで、この種の工事においては、工事の途中で、周囲の地盤が沈下したり、反対に土留杭1や地山支持部20が沈下することがしばしば起こるものである。そうした場合、覆工板7の上面と路面aとに段差(高低差)が生じ、歩行者や車等の通行や安全上問題が生じることにもなる。
【0006】
そうした場合、例えば、土留杭1に覆工板7を支持する前者においては、図7(イ)に示すように、周囲の地盤が沈下して、路面aが覆工板7の上面bより低くなったときは、覆工板7と段差の生じた路面aの上に補正アスファルト等の舗装材9をすり付け(盛り付け)て、路面aと覆工板7の上面bとがゆるく傾斜して接続するようにしている。また、図7(ロ)に示すように、土留杭1の方が沈下して、路面aより覆工板7の上面bが低くなったときは、高さを調整するためのかいものを、受桁6と覆工板7との間、あるいは受桁6と受ピース5との間に介装して、図7(ロ)の鎖線で示すように、覆工板7の上面bが路面aと面一となる高さとなるように覆工板7の高さを調整するようにしている。また、覆工板7を地山支持部20に支持する後者においてもほぼ同様の調整を行っている。
【0007】
このように、従来の路面覆工においては、夜間等覆工板の敷設の都度、上記のような補正用舗装材9のすり付けやかいものの介装を行わなければならず、施工が面倒で多くの労力を要しており、それだけ施工コストも高価になる、といった問題を有している。
【0008】
本発明は、上記従来の問題点を解決するためになされたもので、覆工板を、これを支持する土留杭または土留矢板の外側(地山側)の地盤に高さ調節自在なジャッキ等の支持手段を介して敷設できるようにして、覆工板の敷設にあたっての路面と覆工板の上面との段差が、簡単な作業で解消することができるようにした、路面覆工の施工法を提供しようとするものである。
【0009】
【課題を解決するための手段】
上記の目的を達成するため、請求項1の施工法は路面覆工施工法であって、路盤の開削溝の両側部に打設された土留杭の上端部に高さ調節自在としかつ上部に受杆を架設した支持体を設置し、開削溝両側の対向する土留杭の支持体間に、それぞれ土留杭の上端と受桁の下面とが間隔を保つようにして前記受杆上に受桁を架設し、それら受桁上に覆工板を載設して、支持体の高さを調節することにより、覆工板の高さを調節することを特徴とするものである。
【0010】
また、請求項2の施工法は路面覆工施工法であって、路盤の開削溝の両側部に打設または建込まれる土留矢板の地山側に、路盤より低い地山支持部を形成し、この地山支持部に、高さ調節自在としかつ上部に受杆を架設した支持体を、開削溝の長手方向に沿って間隔をおいて配設し、開削溝を挟んで対向する各支持体間に、土留矢板の上端と受桁の下面とが間隔を保つようにして受桁を架設し、それら受桁上に覆工板を載設して、支持体の高さを調節することにより、覆工板の高さを調節することを特徴とするものである。
【0011】
【発明の実施の形態】
以下、本発明の実施の態様について図面を参照して説明する。図1、図2は、覆工板を土留杭に支持するようにした施工の実施の態様(第1の実施態様)を示し、図3、図4は、覆工板を路盤に支持するようにした施工の実施態様(第2の実施態様)を示したものである。
【0012】
まず、第1の実施態様について説明する。図1、図2において、Aは、道路等の地盤(路盤)Bを掘削して管路等の埋設や補修のために形成された開削溝で、開削溝Aの両側には、開削溝Aの長手方向に沿って土留杭1,1が打設される。そして、各側の土留杭1,1どうしは腹起し材3によって結合するとともに、それら両側の腹起し材3,3間に切梁4を架設し、地山の崩壊を防止する。
【0013】
土留杭1の上部内側(開削溝Aに面する側)には、受けピース(ブラケット)5を固着し、この受ピース5の上には、高さ調節自在とした支持体10を設置する。この支持体10は、受けピース5の上面にボルト・ナット12等で着脱自在に取り付けられるようにした台板11に、ネジ杆13を螺着、立設し、ネジ杆13の上端にはネジ杆13をスパナ等で回転させるための角ナット14を固着した構造となっており、ネジ杆13を回動させることにより、ネジ杆13の高さが調節できるようになっている。
【0014】
支持体10を設置したら、各側に設置した支持体10,10の上にチャンネル材等による受杆15を架設して、両側の受杆15,15にわたって覆工板7の受桁6を、開削溝Aの長さ方向に所定の間隔をおいて並列、架設する。そして、受桁6には、その下面に、受杆15の内側に近接して、ずれ止め材16を取り付けて、受杆15が開削溝Aの巾方向(横断方向)に移動するのを防止する。
【0015】
次に、架設した受桁6,6にわたしかけて覆工板7,7を配設する。この場合、配設した覆工板7の上面bが、路面aとほぼ面一となるように、あらかじめ受けピース5の取り付け位置を設定しておくが、土留杭の上端と受桁6の下面とは、少し間隔を保つようにしておくのがよい。
【0016】
工事の当初あるいは途中で周囲の路盤Bが沈下し、覆工板7の上面が路面aより高くなったときは、支持体10を短縮させて覆工板7を降下させ、その上面bが路盤Bの上面(路面)aと面一となるように調節する。また、打設した土留杭1が全体的に沈下し、覆工板7の上面が路面aより低くなったときは、支持体10を伸長させて覆工板7を上昇させ、その上面bが路面aと面一となるように調節する。また、打設した土留杭1の一部のものが沈下したようなときは、その沈下した土留杭1に設置された支持体10を伸長させて、各支持体10がほぼ均等な荷重配分となるように調整する。
【0017】
なお、支持体10は、上記のようにネジ式のジャッキに限定されるものではなく、油圧式ジャッキ等従来公知の高さ調節可能なものを広く採用することができる。
【0018】
次に、第2の実施態様について説明する。図3、図4において、Aは、道路の地盤(路盤)Bを掘削して管路等の埋設、補修のために形成された開削溝で、開削溝Aの両側には、開削溝Aの長手方向に沿って土留矢板2が対向して打設または建込まれる。各土留矢板2の外側(路盤B側)には、土留矢板2に沿って、路面より所定の深さ掘り下げた、所定の巾を有する地山支持部20を形成する。そして、各側の土留矢板2,2には腹起し材3が取り付けられ、それら両側の腹起し材3,3間に切梁4を架設し、地山の崩壊を防止する。
【0019】
地山支持部20には、栗石層21を介してコンクリートや鋼板等よりなる基盤22が設けられ、この基盤22上に、地山支持部20の長手方向(開削溝Aの長手方向)に所定の間隔をおいてさきに説明した高さ調節自在の支持体10を設置する。この支持体10はさきの実施態様におけると同様で、その台板11をボルト・ナットあるいは所要のアンカー等を用いて基盤22に固定する。この場合、支持体10の上端が土留矢板2の上端より、所要距離高い位置となるように設置する。また、地山支持部20には、その路盤側の側壁面23の崩壊を防止する、断面L形の土砂抑え板24を設置する。
【0020】
支持体10を設置したら、さきの実施態様におけると同様に、各側に設置した支持体10,10の上にチャンネル材等による受杆15を架設して、両側の受杆5,5にわたって覆工板7の受桁6を、開削溝Aの長さ方向に所定の間隔をおいて並列、架設する。そして、受桁6には、その下面に、受杆15の内側に近接して、ずれ止め材16を取り付けて、受杆15が開削溝Aの巾方向(横断方向)に移動するのを防止する。
【0021】
次に、架設した受桁6,6にわたしかけて覆工板7,7を配設する。この場合、配設した覆工板7の上面bが、路面aとほぼ面一となるように、あらかじめ受けピース5の取り付け位置を設定しておくが、土留矢板2の上端と受桁6の下面とは、少し間隔を保つようにしておくのがよい。
【0022】
工事の途中で周囲の路盤Bが沈下し、覆工板7の上面が路面aより高くなったときは、支持体10を短縮させて覆工板7を降下させ、その上面bが路盤Bの上面(路面)aと面一となるように調節する。また、地山支持部20が全体的に沈下し、覆工板7の上面が路面aより低くなったときは、支持台10を伸長させて覆工板7を上昇させ、その上面bが路面aと面一となるように調節する。また、地山支持部20の一部が沈下したようなときは、その沈下した地山支持部20に設置された支持台10を伸長させて、各支持台10がほぼ均等な荷重配分となるように調整する。
【0023】
【発明の効果】
以上説明したように、本発明によれば、管路等の地中埋設あるいは補修を行うための路盤開削工事における、路面覆工が、土留杭に装着した高さ調節自在の支持体を介して覆工板を昇降調節可能に支持し、あるいは、土留矢板の地山側に形成した地山支持部に設置した高さ調節自在の支持体を介して覆工板を昇降調節可能に支持したので、路盤と覆工板とに段差が生じた場合に、従来のように、段差部分に舗装材を摺り付けて段差をゆるやかりしたり、あるいは、覆工板の支持部材にかいものを介装して覆工板の高さを調節するというような面倒な作業を行うことなく、支持体の高さを調節するだけの極めて簡単な作業で路盤と覆工板との段差を除くことができる。
【0024】
したがって、路盤の開削工事における覆工施工が簡便化し、工事工程が円滑となって工事期間の減縮と経費の節減が図れることになる。
【図面の簡単な説明】
【図1】本発明の第1の実施態様を示す縦断面図である。
【図2】同要部の拡大縦断面図である。
【図3】本発明の第2の実施態様を示す縦断面図である。
【図4】同要部の拡大縦断面図である。
【図5】従来施工法の一実施態様を示す縦断面図である。
【図6】同他の実施態様を示す縦断面図である。
【図7】(イ)、(ロ)は従来法による覆工調整の説明図である。
【符号の説明】
A 開削溝
B 路盤
1 土留杭
2 土留矢板
3 腹起し材
4 切梁
5 受ピース
6 受桁
7 覆工板
支持体
11 台板
13 ネジ杆
14 角ナット
15 受杆
20 地山支持部
22 基盤
24 土砂抑え板[0001]
[Industrial application fields]
The present invention relates to a road surface lining construction method that can ensure safety during construction when excavating a groove in the ground (roadbed) of a road or the like to bury or repair a sewer pipe or the like. .
[0002]
[Prior art]
In construction that embeds sewer pipes in the ground such as roads and repairs the sewer pipes that are buried, excavation of the roadbed to form an open groove is performed. Often the day does not complete and continues for several days. In such a case, in order to ensure safety during construction stoppages such as at night, the upper opening of the cut groove is covered with a lining plate so that a pedestrian or the like can fall and a vehicle or the like can be transported.
[0003]
In this type of construction, a method as shown in FIGS. 5 and 6 is generally used. In the method shown in FIG. 5, the
[0004]
Further, in the method of FIG. 6, the
[0005]
[Problems to be solved by the invention]
By the way, in this type of construction, it is often the case that the surrounding ground sinks in the middle of the construction, and on the contrary, the
[0006]
In such a case, for example, in the former case in which the
[0007]
In this way, in the conventional road surface lining, every time a lining plate such as nighttime is laid, the correction paving
[0008]
The present invention was made in order to solve the above-mentioned conventional problems, such as a jack whose height can be adjusted to the ground on the outer side (the ground side) of the earth retaining pile or the earth retaining pile, which supports the lining board. A road surface lining construction method that can be laid via a support means, and the step between the road surface and the top surface of the lining plate when laying the lining plate can be eliminated with a simple operation. It is something to be offered.
[0009]
[Means for Solving the Problems]
To achieve the above object, construction methods of
[0010]
In addition, the construction method of
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings. 1 and 2 show an embodiment of the construction in which the lining board is supported by the retaining pile (first embodiment), and FIGS. 3 and 4 show that the lining board is supported by the roadbed. The embodiment (2nd embodiment) of the construction which was made is shown.
[0012]
First, the first embodiment will be described. 1 and 2, A is an excavation groove formed for excavating a ground (roadbed) B such as a road to embed or repair a pipe or the like. The soil retaining
[0013]
A receiving piece (bracket) 5 is fixed to the upper inner side (side facing the cut groove A) of the
[0014]
After installing the
[0015]
Next, the
[0016]
When the surrounding roadbed B sinks at the beginning or midway of the construction and the upper surface of the
[0017]
The
[0018]
Next, a second embodiment will be described. 3 and 4, A is an excavation groove formed for excavating the ground (roadbed) B of the road to embed or repair a pipe or the like. The earth retaining
[0019]
The
[0020]
When the
[0021]
Next, the
[0022]
When the surrounding roadbed B sinks in the middle of the construction and the upper surface of the
[0023]
【The invention's effect】
As described above, according to the present invention, road surface lining in roadbed excavation work for underground burial or repair of pipes and the like is performed via a height-adjustable support attached to the earth retaining pile. Since the lining board is supported so that it can be raised or lowered, or the lining board is supported so that it can be raised or lowered via a height-adjustable support body installed on the ground support part formed on the ground side of the earth retaining sheet pile, When there is a difference in level between the roadbed and the lining plate, the pavement material is slid on the stepped portion to loosen the leveling as before, or a support member for the lining plate is inserted. Therefore, the step between the roadbed and the lining plate can be removed by an extremely simple operation of adjusting the height of the support body without performing the troublesome work of adjusting the height of the lining plate.
[0024]
Therefore, the lining work in the excavation work of the roadbed is simplified, the construction process becomes smooth, and the construction period can be reduced and the cost can be reduced.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view showing a first embodiment of the present invention.
FIG. 2 is an enlarged longitudinal sectional view of the main part.
FIG. 3 is a longitudinal sectional view showing a second embodiment of the present invention.
FIG. 4 is an enlarged longitudinal sectional view of the main part.
FIG. 5 is a longitudinal sectional view showing an embodiment of a conventional construction method.
FIG. 6 is a longitudinal sectional view showing another embodiment.
7A and 7B are explanatory diagrams of lining adjustment by a conventional method.
[Explanation of symbols]
A Open
11 base plate
13 Screw 杆
14 square nut
15 Receiving
20 Chiyama Support Department
22 Foundation
24 Sedimentation board
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001350014A JP3942152B2 (en) | 2001-11-15 | 2001-11-15 | Road surface lining construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001350014A JP3942152B2 (en) | 2001-11-15 | 2001-11-15 | Road surface lining construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003147712A JP2003147712A (en) | 2003-05-21 |
JP3942152B2 true JP3942152B2 (en) | 2007-07-11 |
Family
ID=19162602
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001350014A Expired - Fee Related JP3942152B2 (en) | 2001-11-15 | 2001-11-15 | Road surface lining construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3942152B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5109939B2 (en) * | 2007-12-03 | 2012-12-26 | Jfeエンジニアリング株式会社 | Lining method |
JP5843413B1 (en) * | 2015-04-20 | 2016-01-13 | 株式会社建設技術センター | Lowering method of existing tunnel |
KR102068441B1 (en) * | 2019-07-01 | 2020-01-20 | 박상원 | Temporary Strcuture of Underpass Traverse Construction for Traffic Facilities and Tunnel Construction Method Using by This |
JP7413158B2 (en) | 2020-06-22 | 2024-01-15 | 鹿島建設株式会社 | shoring structure |
-
2001
- 2001-11-15 JP JP2001350014A patent/JP3942152B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2003147712A (en) | 2003-05-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8920068B1 (en) | Process for slip forming reinforced bridge coping with exposed rebars | |
KR101206860B1 (en) | Excavation tunnel constructing method using vertical side wall and arch ceiling | |
JP6340044B2 (en) | Overhang trail construction body and construction method of overhang trail using these | |
JP3942152B2 (en) | Road surface lining construction method | |
US20100272509A1 (en) | Traffic barrier section | |
KR100592416B1 (en) | How to secure the sidewalk and widen the roadway using concrete retaining wall blocks and truss-shaped pedestals on narrow roads | |
KR100509707B1 (en) | None open cut tunnelling of arch type with hume pipe and con'c rib | |
JP3856791B2 (en) | How to lay an overhanging sidewalk | |
JP3857124B2 (en) | Road surface lining construction method and lining board used therefor | |
CN113106801A (en) | Pavement widening method for highway engineering | |
JP3403345B2 (en) | Invert formation method and block in existing mountain tunnel | |
CN112663431A (en) | Concrete pavement fracture subsidence section treatment structure and construction method | |
CN111691255A (en) | Construction method for municipal road along river and enclosure used by construction method | |
KR100436896B1 (en) | Construction method for back-fill area of abutment | |
JP4700987B2 (en) | Overhangway block and method for constructing overhangway using the block | |
JPH09256450A (en) | Concrete structure | |
JP2008231756A (en) | Subsidence prevention device for strut for supporting guard rail and method of constructing the strut | |
JP3450294B2 (en) | Supporting structure of lining plate and lining method | |
JP2000345502A (en) | Boundary jointing structure for road with enlarged width and method for jointing boundary | |
KR100488130B1 (en) | Precast concrete counterforts retaining wall | |
KR101455202B1 (en) | Construction method of an underground structure using lower member installed temporary system | |
KR20110006423A (en) | A constructing gutter of a road | |
KR100593195B1 (en) | Structure for preventing slide slope and method for construcing it | |
JP2007297807A (en) | Construction method for underground structure, and underground structure | |
JP2000297403A (en) | Passage and construction method therefor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040401 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060119 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060127 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060324 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060821 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061019 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070329 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070402 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100413 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110413 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110413 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120413 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120413 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130413 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140413 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |