JP3942152B2 - Road surface lining construction method - Google Patents

Road surface lining construction method Download PDF

Info

Publication number
JP3942152B2
JP3942152B2 JP2001350014A JP2001350014A JP3942152B2 JP 3942152 B2 JP3942152 B2 JP 3942152B2 JP 2001350014 A JP2001350014 A JP 2001350014A JP 2001350014 A JP2001350014 A JP 2001350014A JP 3942152 B2 JP3942152 B2 JP 3942152B2
Authority
JP
Japan
Prior art keywords
support
lining
earth retaining
height
road surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001350014A
Other languages
Japanese (ja)
Other versions
JP2003147712A (en
Inventor
哲太 布戸
Original Assignee
東起業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 東起業株式会社 filed Critical 東起業株式会社
Priority to JP2001350014A priority Critical patent/JP3942152B2/en
Publication of JP2003147712A publication Critical patent/JP2003147712A/en
Application granted granted Critical
Publication of JP3942152B2 publication Critical patent/JP3942152B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【産業上の利用分野】
本発明は、道路等の地盤(路盤)に溝を開削して下水管等の埋設や補修等を行う際に、工事の途中における安全を確保できるようにした路面覆工施工法に関するものである。
【0002】
【従来の技術】
道路等の地盤に下水管等を埋設したり、埋設されている下水管等の補修を行う工事においては、路盤を掘削して開削溝を形成することが行われているが、この工事は1日では完了せず数日にわたって継続されることが多い。このような場合、夜間等工事休止中の安全を確保するため、開削溝の上部開口を覆工板で覆い、歩行者等の転落防止や車等が交通できるようにしている。
【0003】
この種の工事では、従来一般に、図5、図6に示すような方法が採られている。図5に示す方法は、開削する開削溝Aの両側に土留杭1,1を打込み、腹起し材3と切梁4を設けて地山の崩壊を防止し、土留杭1,1の上部に取り付けた受ピース5,5に受桁6を架設し、その上に複数に分割形成された覆工板7,7を路面aと面一となるようにして載設するものである。
【0004】
また、図6の方法は、開削溝Aの両側に地山支持部20を設けて、その上に桁受基礎9,9を造成し、これに受桁6を架設し、開削溝Aの両側に土留矢板2,2を打込みあるいは建て込み、腹起し材3と切梁4を設けて地山の崩壊を防止するとともに、受桁6上に覆工板7,7を路面aと面一となるように載設するものである。
【0005】
【発明が解決しようとする課題】
ところで、この種の工事においては、工事の途中で、周囲の地盤が沈下したり、反対に土留杭1や地山支持部20が沈下することがしばしば起こるものである。そうした場合、覆工板7の上面と路面aとに段差(高低差)が生じ、歩行者や車等の通行や安全上問題が生じることにもなる。
【0006】
そうした場合、例えば、土留杭1に覆工板7を支持する前者においては、図7(イ)に示すように、周囲の地盤が沈下して、路面aが覆工板7の上面bより低くなったときは、覆工板7と段差の生じた路面aの上に補正アスファルト等の舗装材9をすり付け(盛り付け)て、路面aと覆工板7の上面bとがゆるく傾斜して接続するようにしている。また、図7(ロ)に示すように、土留杭1の方が沈下して、路面aより覆工板7の上面bが低くなったときは、高さを調整するためのかいものを、受桁6と覆工板7との間、あるいは受桁6と受ピース5との間に介装して、図7(ロ)の鎖線で示すように、覆工板7の上面bが路面aと面一となる高さとなるように覆工板7の高さを調整するようにしている。また、覆工板7を地山支持部20に支持する後者においてもほぼ同様の調整を行っている。
【0007】
このように、従来の路面覆工においては、夜間等覆工板の敷設の都度、上記のような補正用舗装材9のすり付けやかいものの介装を行わなければならず、施工が面倒で多くの労力を要しており、それだけ施工コストも高価になる、といった問題を有している。
【0008】
本発明は、上記従来の問題点を解決するためになされたもので、覆工板を、これを支持する土留杭または土留矢板の外側(地山側)の地盤に高さ調節自在なジャッキ等の支持手段を介して敷設できるようにして、覆工板の敷設にあたっての路面と覆工板の上面との段差が、簡単な作業で解消することができるようにした、路面覆工の施工法を提供しようとするものである。
【0009】
【課題を解決するための手段】
上記の目的を達成するため、請求項1の施工法は路面覆工施工法であって、路盤の開削溝の両側部に打設された土留杭の上端部に高さ調節自在としかつ上部に受杆を架設した支持体を設置し、開削溝両側の対向する土留杭の支持体間にそれぞれ土留杭の上端と受桁の下面とが間隔を保つようにして前記受杆上に受桁を架設し、それら受桁上に覆工板を載設して、支持体の高さを調節することにより、覆工板の高さを調節することを特徴とするものである。
【0010】
また、請求項2の施工法は路面覆工施工法であって、路盤の開削溝の両側部に打設または建込まれる土留矢板の地山側に、路盤より低い地山支持部を形成し、この地山支持部に、高さ調節自在としかつ上部に受杆を架設した支持体を、開削溝の長手方向に沿って間隔をおいて配設し、開削溝を挟んで対向する各支持体間に、土留矢板の上端と受桁の下面とが間隔を保つようにして受桁を架設し、それら受桁上に覆工板を載設して、支持体の高さを調節することにより、覆工板の高さを調節することを特徴とするものである。
【0011】
【発明の実施の形態】
以下、本発明の実施の態様について図面を参照して説明する。図1、図2は、覆工板を土留杭に支持するようにした施工の実施の態様(第1の実施態様)を示し、図3、図4は、覆工板を路盤に支持するようにした施工の実施態様(第2の実施態様)を示したものである。
【0012】
まず、第1の実施態様について説明する。図1、図2において、Aは、道路等の地盤(路盤)Bを掘削して管路等の埋設や補修のために形成された開削溝で、開削溝Aの両側には、開削溝Aの長手方向に沿って土留杭1,1が打設される。そして、各側の土留杭1,1どうしは腹起し材3によって結合するとともに、それら両側の腹起し材3,3間に切梁4を架設し、地山の崩壊を防止する。
【0013】
土留杭1の上部内側(開削溝Aに面する側)には、受けピース(ブラケット)5を固着し、この受ピース5の上には、高さ調節自在とした支持体10を設置する。この支持体10は、受けピース5の上面にボルト・ナット12等で着脱自在に取り付けられるようにした台板11に、ネジ杆13を螺着、立設し、ネジ杆13の上端にはネジ杆13をスパナ等で回転させるための角ナット14を固着した構造となっており、ネジ杆13を回動させることにより、ネジ杆13の高さが調節できるようになっている。
【0014】
支持体10を設置したら、各側に設置した支持体10,10の上にチャンネル材等による受杆15を架設して、両側の受杆15,15にわたって覆工板7の受桁6を、開削溝Aの長さ方向に所定の間隔をおいて並列、架設する。そして、受桁6には、その下面に、受杆15の内側に近接して、ずれ止め材16を取り付けて、受杆15が開削溝Aの巾方向(横断方向)に移動するのを防止する。
【0015】
次に、架設した受桁6,6にわたしかけて覆工板7,7を配設する。この場合、配設した覆工板7の上面bが、路面aとほぼ面一となるように、あらかじめ受けピース5の取り付け位置を設定しておくが、土留杭の上端と受桁6の下面とは、少し間隔を保つようにしておくのがよい。
【0016】
工事の当初あるいは途中で周囲の路盤Bが沈下し、覆工板7の上面が路面aより高くなったときは、支持体10を短縮させて覆工板7を降下させ、その上面bが路盤Bの上面(路面)aと面一となるように調節する。また、打設した土留杭1が全体的に沈下し、覆工板7の上面が路面aより低くなったときは、支持体10を伸長させて覆工板7を上昇させ、その上面bが路面aと面一となるように調節する。また、打設した土留杭1の一部のものが沈下したようなときは、その沈下した土留杭1に設置された支持体10を伸長させて、各支持体10がほぼ均等な荷重配分となるように調整する。
【0017】
なお、支持体10は、上記のようにネジ式のジャッキに限定されるものではなく、油圧式ジャッキ等従来公知の高さ調節可能なものを広く採用することができる。
【0018】
次に、第2の実施態様について説明する。図3、図4において、Aは、道路の地盤(路盤)Bを掘削して管路等の埋設、補修のために形成された開削溝で、開削溝Aの両側には、開削溝Aの長手方向に沿って土留矢板2が対向して打設または建込まれる。各土留矢板2の外側(路盤B側)には、土留矢板2に沿って、路面より所定の深さ掘り下げた、所定の巾を有する地山支持部20を形成する。そして、各側の土留矢板2,2には腹起し材3が取り付けられ、それら両側の腹起し材3,3間に切梁4を架設し、地山の崩壊を防止する。
【0019】
地山支持部20には、栗石層21を介してコンクリートや鋼板等よりなる基盤22が設けられ、この基盤22上に、地山支持部20の長手方向(開削溝Aの長手方向)に所定の間隔をおいてさきに説明した高さ調節自在の支持体10を設置する。この支持体10はさきの実施態様におけると同様で、その台板11をボルト・ナットあるいは所要のアンカー等を用いて基盤22に固定する。この場合、支持体10の上端が土留矢板2の上端より、所要距離高い位置となるように設置する。また、地山支持部20には、その路盤側の側壁面23の崩壊を防止する、断面L形の土砂抑え板24を設置する。
【0020】
支持体10を設置したら、さきの実施態様におけると同様に、各側に設置した支持10,10の上にチャンネル材等による受杆15を架設して、両側の受杆5,5にわたって覆工板7の受桁6を、開削溝Aの長さ方向に所定の間隔をおいて並列、架設する。そして、受桁6には、その下面に、受杆15の内側に近接して、ずれ止め材16を取り付けて、受杆15が開削溝Aの巾方向(横断方向)に移動するのを防止する。
【0021】
次に、架設した受桁6,6にわたしかけて覆工板7,7を配設する。この場合、配設した覆工板7の上面bが、路面aとほぼ面一となるように、あらかじめ受けピース5の取り付け位置を設定しておくが、土留矢板2の上端と受桁6の下面とは、少し間隔を保つようにしておくのがよい。
【0022】
工事の途中で周囲の路盤Bが沈下し、覆工板7の上面が路面aより高くなったときは、支持体10を短縮させて覆工板7を降下させ、その上面bが路盤Bの上面(路面)aと面一となるように調節する。また、地山支持部20が全体的に沈下し、覆工板7の上面が路面aより低くなったときは、支持台10を伸長させて覆工板7を上昇させ、その上面bが路面aと面一となるように調節する。また、地山支持部20の一部が沈下したようなときは、その沈下した地山支持部20に設置された支持台10を伸長させて、各支持台10がほぼ均等な荷重配分となるように調整する。
【0023】
【発明の効果】
以上説明したように、本発明によれば、管路等の地中埋設あるいは補修を行うための路盤開削工事における、路面覆工が、土留杭に装着した高さ調節自在の支持体を介して覆工板を昇降調節可能に支持し、あるいは、土留矢板の地山側に形成した地山支持部に設置した高さ調節自在の支持体を介して覆工板を昇降調節可能に支持したので、路盤と覆工板とに段差が生じた場合に、従来のように、段差部分に舗装材を摺り付けて段差をゆるやかりしたり、あるいは、覆工板の支持部材にかいものを介装して覆工板の高さを調節するというような面倒な作業を行うことなく、支持体の高さを調節するだけの極めて簡単な作業で路盤と覆工板との段差を除くことができる。
【0024】
したがって、路盤の開削工事における覆工施工が簡便化し、工事工程が円滑となって工事期間の減縮と経費の節減が図れることになる。
【図面の簡単な説明】
【図1】本発明の第1の実施態様を示す縦断面図である。
【図2】同要部の拡大縦断面図である。
【図3】本発明の第2の実施態様を示す縦断面図である。
【図4】同要部の拡大縦断面図である。
【図5】従来施工法の一実施態様を示す縦断面図である。
【図6】同他の実施態様を示す縦断面図である。
【図7】(イ)、(ロ)は従来法による覆工調整の説明図である。
【符号の説明】
A 開削溝
B 路盤
1 土留杭
2 土留矢板
3 腹起し材
4 切梁
5 受ピース
6 受桁
7 覆工板
支持体
11 台板
13 ネジ杆
14 角ナット
15 受杆
20 地山支持部
22 基盤
24 土砂抑え板
[0001]
[Industrial application fields]
The present invention relates to a road surface lining construction method that can ensure safety during construction when excavating a groove in the ground (roadbed) of a road or the like to bury or repair a sewer pipe or the like. .
[0002]
[Prior art]
In construction that embeds sewer pipes in the ground such as roads and repairs the sewer pipes that are buried, excavation of the roadbed to form an open groove is performed. Often the day does not complete and continues for several days. In such a case, in order to ensure safety during construction stoppages such as at night, the upper opening of the cut groove is covered with a lining plate so that a pedestrian or the like can fall and a vehicle or the like can be transported.
[0003]
In this type of construction, a method as shown in FIGS. 5 and 6 is generally used. In the method shown in FIG. 5, the retaining piles 1 and 1 are driven on both sides of the cut groove A to be cut, and the uplifting material 3 and the cut beam 4 are provided to prevent the collapse of the natural ground. The receiving girder 6 is installed on the receiving pieces 5 and 5 attached to the upper and lower sides, and the covering plates 7 and 7 divided into a plurality of pieces are mounted thereon so as to be flush with the road surface a.
[0004]
Further, in the method of FIG. 6, the ground support portions 20 are provided on both sides of the cut groove A, and the girder receiving bases 9 and 9 are formed thereon, and the receiving girder 6 is erected thereon, and both sides of the cut groove A are formed. The earth retaining sheet piles 2 and 2 are driven in or built in, and the uplifting material 3 and the cut beam 4 are provided to prevent the collapse of the natural ground, and the lining plates 7 and 7 are flush with the road surface a on the receiving girder 6. It will be placed so that
[0005]
[Problems to be solved by the invention]
By the way, in this type of construction, it is often the case that the surrounding ground sinks in the middle of the construction, and on the contrary, the retaining pile 1 and the natural ground support 20 sink. In such a case, a level difference (level difference) occurs between the upper surface of the lining board 7 and the road surface a, and this may cause a problem in traffic and safety of pedestrians and cars.
[0006]
In such a case, for example, in the former case in which the lining plate 7 is supported by the retaining pile 1, the surrounding ground sinks and the road surface a is lower than the upper surface b of the lining plate 7 as shown in FIG. When it becomes, pavement material 9 such as correction asphalt is rubbed (laid) on the lining plate 7 and the road surface a where the level difference occurs, and the road surface a and the upper surface b of the lining plate 7 are gently inclined. I try to connect. In addition, as shown in FIG. 7 (b), when the earth retaining pile 1 sinks and the upper surface b of the lining board 7 is lower than the road surface a, a paddle for adjusting the height is used. The upper surface b of the lining plate 7 is disposed between the receiving beam 6 and the lining plate 7 or between the receiving beam 6 and the receiving piece 5 as shown by the chain line in FIG. The height of the lining plate 7 is adjusted so as to be flush with a. Further, substantially the same adjustment is performed in the latter case in which the lining plate 7 is supported by the natural ground support portion 20.
[0007]
In this way, in the conventional road surface lining, every time a lining plate such as nighttime is laid, the correction paving material 9 must be rubbed and the intermediary of the stuffed material must be carried out, and the construction is troublesome. A lot of labor is required, and the construction cost is increased accordingly.
[0008]
The present invention was made in order to solve the above-mentioned conventional problems, such as a jack whose height can be adjusted to the ground on the outer side (the ground side) of the earth retaining pile or the earth retaining pile, which supports the lining board. A road surface lining construction method that can be laid via a support means, and the step between the road surface and the top surface of the lining plate when laying the lining plate can be eliminated with a simple operation. It is something to be offered.
[0009]
[Means for Solving the Problems]
To achieve the above object, construction methods of claim 1 is a road lining construction methods, height adjustment and freely to the upper end of the earth retaining stakes are Da設on both sides of the cutting grooves of the base course and the top established a support having laid the受杆,受桁between support earth retaining piles facing the cutting grooves on both sides, to on the受杆so that the lower surface of the upper end and受桁of earth retaining pile respectively keep a proper distance The height of the lining plate is adjusted by installing a lining plate on these receiving girders and adjusting the height of the support.
[0010]
In addition, the construction method of claim 2 is a road surface lining construction method, and a ground support portion lower than the roadbed is formed on the ground pile side of the earth retaining sheet pile placed or built on both sides of the cut groove of the roadbed, this natural ground support, each support height adjustable and with and support with bridged the受杆the top, arranged at intervals along the longitudinal direction of the cutting grooves, facing each other across the cutting grooves By installing the girder in such a way that the upper end of the earth retaining sheet pile and the lower surface of the girder are kept apart, and placing the lining plate on the girder and adjusting the height of the support The height of the lining plate is adjusted.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings. 1 and 2 show an embodiment of the construction in which the lining board is supported by the retaining pile (first embodiment), and FIGS. 3 and 4 show that the lining board is supported by the roadbed. The embodiment (2nd embodiment) of the construction which was made is shown.
[0012]
First, the first embodiment will be described. 1 and 2, A is an excavation groove formed for excavating a ground (roadbed) B such as a road to embed or repair a pipe or the like. The soil retaining piles 1 and 1 are driven along the longitudinal direction of the. Then, the earth retaining piles 1 and 1 on each side are joined together by the erection material 3, and a cut beam 4 is installed between the erection materials 3 and 3 on both sides to prevent the collapse of the natural ground.
[0013]
A receiving piece (bracket) 5 is fixed to the upper inner side (side facing the cut groove A) of the earth retaining pile 1, and a support body 10 whose height is adjustable is installed on the receiving piece 5. The support body 10 has a screw plate 13 screwed and erected on a base plate 11 which is detachably attached to the upper surface of the receiving piece 5 with bolts and nuts 12 and the like, and a screw plate 13 is provided at the upper end of the screw rod 13. It has a structure in which a square nut 14 for rotating the flange 13 with a spanner or the like is fixed, and the height of the screw flange 13 can be adjusted by rotating the screw flange 13.
[0014]
After installing the support 10, a receiving bar 15 made of channel material or the like is installed on the support 10, 10 installed on each side, and the receiving girder 6 of the lining plate 7 is stretched across the receiving bars 15, 15 on both sides. The cut grooves A are installed in parallel in the length direction at a predetermined interval. And, on the underside of the receiving girder 6, an anti-slip material 16 is attached to the lower surface of the receiving girder 16 in the vicinity of the inner side of the receiving rod 15 to prevent the receiving rod 15 from moving in the width direction (cross direction) of the cut groove A To do.
[0015]
Next, the lining plates 7 and 7 are disposed over the installed receiving girders 6 and 6. In this case, the mounting position of the receiving piece 5 is set in advance so that the upper surface b of the arranged lining plate 7 is substantially flush with the road surface a. It is better to keep a little interval.
[0016]
When the surrounding roadbed B sinks at the beginning or midway of the construction and the upper surface of the lining plate 7 becomes higher than the road surface a, the support 10 is shortened to lower the lining plate 7, and the upper surface b is the roadbed. Adjust so that it is flush with the upper surface (road surface) a of B. In addition, when the earth retaining pile 1 that has been laid down sinks as a whole and the upper surface of the lining plate 7 becomes lower than the road surface a, the supporting body 10 is extended to raise the lining plate 7, and the upper surface b is Adjust so that it is flush with the road surface a. In addition, when a part of the placed pile 1 sinks, the support 10 installed on the settled pile 1 is extended so that each support 10 has a substantially equal load distribution. Adjust so that
[0017]
The support 10 is not limited to the screw-type jack as described above, and a conventionally known height-adjustable one such as a hydraulic jack can be widely used.
[0018]
Next, a second embodiment will be described. 3 and 4, A is an excavation groove formed for excavating the ground (roadbed) B of the road to embed or repair a pipe or the like. The earth retaining sheet pile 2 is placed or built oppositely along the longitudinal direction. On the outer side of each earth retaining sheet pile 2 (on the road bed B side), a ground support portion 20 having a predetermined width is formed along the earth retaining sheet pile 2 by digging a predetermined depth from the road surface. And the erection material 3 is attached to the earth retaining sheet piles 2 and 2 of each side, and the cut beam 4 is constructed between the erection materials 3 and 3 of those both sides, and the collapse of a natural ground is prevented.
[0019]
The ground support 20 is provided with a base 22 made of concrete, a steel plate or the like via a chestnut layer 21, and a predetermined length in the longitudinal direction of the ground support 20 (longitudinal direction of the cut groove A) is provided on the base 22. The height-adjustable support 10 described above is installed with the interval of. The support 10 is the same as in the previous embodiment, and the base plate 11 is fixed to the base 22 using bolts / nuts or required anchors. In this case, it installs so that the upper end of the support body 10 may become a position higher required distance than the upper end of the earth retaining sheet pile 2. The ground support 20 is provided with an earth and sand control plate 24 having an L-shaped cross section that prevents the side wall surface 23 on the roadbed side from collapsing.
[0020]
When the support member 10 is placed, as in the previous embodiment, by bridging the受杆15 by channel member or the like on a support 10, 10 installed in each side, covered over opposite sides of受杆5,5 The receiving beam 6 of the work plate 7 is installed in parallel in the length direction of the cut groove A with a predetermined interval. And, on the underside of the receiving girder 6, an anti-slip material 16 is attached to the lower surface of the receiving girder 16 in the vicinity of the inner side of the receiving rod 15 to prevent the receiving rod 15 from moving in the width direction (cross direction) of the cut groove A To do.
[0021]
Next, the lining plates 7 and 7 are disposed over the installed receiving girders 6 and 6. In this case, the mounting position of the receiving piece 5 is set in advance so that the upper surface b of the arranged lining plate 7 is substantially flush with the road surface a, but the upper end of the earth retaining sheet pile 2 and the receiving beam 6 It is preferable to keep a little distance from the lower surface.
[0022]
When the surrounding roadbed B sinks in the middle of the construction and the upper surface of the lining board 7 becomes higher than the road surface a, the support 10 is shortened to lower the lining board 7, and the upper surface b is Adjust so that it is flush with the upper surface (road surface) a. In addition, when the natural ground support part 20 sinks as a whole and the upper surface of the lining board 7 becomes lower than the road surface a, the support base 10 is extended to raise the lining board 7, and the upper surface b becomes the road surface. Adjust so that it is flush with a. In addition, when a part of the natural ground support part 20 sinks, the support bases 10 installed in the subsidized natural ground support part 20 are extended, and each support base 10 has a substantially equal load distribution. Adjust as follows.
[0023]
【The invention's effect】
As described above, according to the present invention, road surface lining in roadbed excavation work for underground burial or repair of pipes and the like is performed via a height-adjustable support attached to the earth retaining pile. Since the lining board is supported so that it can be raised or lowered, or the lining board is supported so that it can be raised or lowered via a height-adjustable support body installed on the ground support part formed on the ground side of the earth retaining sheet pile, When there is a difference in level between the roadbed and the lining plate, the pavement material is slid on the stepped portion to loosen the leveling as before, or a support member for the lining plate is inserted. Therefore, the step between the roadbed and the lining plate can be removed by an extremely simple operation of adjusting the height of the support body without performing the troublesome work of adjusting the height of the lining plate.
[0024]
Therefore, the lining work in the excavation work of the roadbed is simplified, the construction process becomes smooth, and the construction period can be reduced and the cost can be reduced.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view showing a first embodiment of the present invention.
FIG. 2 is an enlarged longitudinal sectional view of the main part.
FIG. 3 is a longitudinal sectional view showing a second embodiment of the present invention.
FIG. 4 is an enlarged longitudinal sectional view of the main part.
FIG. 5 is a longitudinal sectional view showing an embodiment of a conventional construction method.
FIG. 6 is a longitudinal sectional view showing another embodiment.
7A and 7B are explanatory diagrams of lining adjustment by a conventional method.
[Explanation of symbols]
A Open groove B Roadbed 1 Earth retaining pile 2 Earth retaining sheet pile 3 Raised material 4 Cut beam 5 Receiving piece 6 Receiving girder 7 Backing plate support
11 base plate
13 Screw 杆
14 square nut
15 Receiving
20 Chiyama Support Department
22 Foundation
24 Sedimentation board

Claims (2)

路盤の開削溝の両側部に打設された土留杭の上端部に高さ調節自在としかつ上部に受杆を架設した支持体を設置し、開削溝両側の対向する土留杭の支持体間にそれぞれ土留杭の上端と受桁の下面とが間隔を保つようにして前記受杆上に受桁を架設し、それら受桁上に覆工板を載設して、支持体の高さを調節することにより、覆工板の高さを調節することを特徴とする、路面覆工施工法。It established a support having erection height adjustable and to and受杆the top to the upper end of the earth retaining stakes are Da設on both sides of the cutting grooves of the roadbed, between support earth retaining piles facing the cutting grooves on both sides The support girders are erected on the receiving girder so that the upper end of the earth retaining pile and the lower surface of the girder are kept apart, and the lining plate is placed on the girder to increase the height of the support. A road surface lining construction method characterized by adjusting the height of the lining board by adjusting. 路盤の開削溝の両側部に打設または建込まれる土留矢板の地山側に、路盤より低い地山支持部を形成し、この地山支持部に、高さ調節自在としかつ上部に受杆を架設した支持体を、開削溝の長手方向に沿って間隔をおいて配設し、開削溝を挟んで対向する各支持体間に、土留矢板の上端と受桁の下面とが間隔を保つようにして受桁を架設し、それら受桁上に覆工板を載設して、支持体の高さを調節することにより、覆工板の高さを調節することを特徴とする、路面覆工施工法。The land mountain side of earth retaining sheet pile to be written Da設or denominated on both sides of the cutting grooves of the roadbed, to form a low natural ground support unit than roadbed, to the natural ground support, height adjustable and to and受杆the top The installed supports are arranged at intervals along the longitudinal direction of the excavation groove, and the upper end of the earth retaining sheet pile and the lower surface of the receiving girder are kept at an interval between the respective supports facing each other across the excavation groove. A road surface covering characterized in that the height of the lining plate is adjusted by installing the supporting girders and placing the lining plates on the receiving girders and adjusting the height of the support. Construction method.
JP2001350014A 2001-11-15 2001-11-15 Road surface lining construction method Expired - Fee Related JP3942152B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001350014A JP3942152B2 (en) 2001-11-15 2001-11-15 Road surface lining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001350014A JP3942152B2 (en) 2001-11-15 2001-11-15 Road surface lining construction method

Publications (2)

Publication Number Publication Date
JP2003147712A JP2003147712A (en) 2003-05-21
JP3942152B2 true JP3942152B2 (en) 2007-07-11

Family

ID=19162602

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001350014A Expired - Fee Related JP3942152B2 (en) 2001-11-15 2001-11-15 Road surface lining construction method

Country Status (1)

Country Link
JP (1) JP3942152B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5109939B2 (en) * 2007-12-03 2012-12-26 Jfeエンジニアリング株式会社 Lining method
JP5843413B1 (en) * 2015-04-20 2016-01-13 株式会社建設技術センター Lowering method of existing tunnel
KR102068441B1 (en) * 2019-07-01 2020-01-20 박상원 Temporary Strcuture of Underpass Traverse Construction for Traffic Facilities and Tunnel Construction Method Using by This
JP7413158B2 (en) 2020-06-22 2024-01-15 鹿島建設株式会社 shoring structure

Also Published As

Publication number Publication date
JP2003147712A (en) 2003-05-21

Similar Documents

Publication Publication Date Title
US8920068B1 (en) Process for slip forming reinforced bridge coping with exposed rebars
KR101206860B1 (en) Excavation tunnel constructing method using vertical side wall and arch ceiling
JP6340044B2 (en) Overhang trail construction body and construction method of overhang trail using these
JP3942152B2 (en) Road surface lining construction method
US20100272509A1 (en) Traffic barrier section
KR100592416B1 (en) How to secure the sidewalk and widen the roadway using concrete retaining wall blocks and truss-shaped pedestals on narrow roads
KR100509707B1 (en) None open cut tunnelling of arch type with hume pipe and con'c rib
JP3856791B2 (en) How to lay an overhanging sidewalk
JP3857124B2 (en) Road surface lining construction method and lining board used therefor
CN113106801A (en) Pavement widening method for highway engineering
JP3403345B2 (en) Invert formation method and block in existing mountain tunnel
CN112663431A (en) Concrete pavement fracture subsidence section treatment structure and construction method
CN111691255A (en) Construction method for municipal road along river and enclosure used by construction method
KR100436896B1 (en) Construction method for back-fill area of abutment
JP4700987B2 (en) Overhangway block and method for constructing overhangway using the block
JPH09256450A (en) Concrete structure
JP2008231756A (en) Subsidence prevention device for strut for supporting guard rail and method of constructing the strut
JP3450294B2 (en) Supporting structure of lining plate and lining method
JP2000345502A (en) Boundary jointing structure for road with enlarged width and method for jointing boundary
KR100488130B1 (en) Precast concrete counterforts retaining wall
KR101455202B1 (en) Construction method of an underground structure using lower member installed temporary system
KR20110006423A (en) A constructing gutter of a road
KR100593195B1 (en) Structure for preventing slide slope and method for construcing it
JP2007297807A (en) Construction method for underground structure, and underground structure
JP2000297403A (en) Passage and construction method therefor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040401

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060127

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060324

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060821

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061019

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070329

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070402

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100413

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110413

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110413

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120413

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120413

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130413

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140413

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees