JP3861100B1 - Bridge girder dismantling method - Google Patents

Bridge girder dismantling method Download PDF

Info

Publication number
JP3861100B1
JP3861100B1 JP2005332159A JP2005332159A JP3861100B1 JP 3861100 B1 JP3861100 B1 JP 3861100B1 JP 2005332159 A JP2005332159 A JP 2005332159A JP 2005332159 A JP2005332159 A JP 2005332159A JP 3861100 B1 JP3861100 B1 JP 3861100B1
Authority
JP
Japan
Prior art keywords
bridge girder
girder
cut
bridge
divided
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005332159A
Other languages
Japanese (ja)
Other versions
JP2007113376A (en
Inventor
義明 目黒
正裕 松岡
Original Assignee
有限会社 松岡知的所有権事務所
株式会社国土
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 有限会社 松岡知的所有権事務所, 株式会社国土 filed Critical 有限会社 松岡知的所有権事務所
Priority to JP2005332159A priority Critical patent/JP3861100B1/en
Application granted granted Critical
Publication of JP3861100B1 publication Critical patent/JP3861100B1/en
Publication of JP2007113376A publication Critical patent/JP2007113376A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

【課題】桁橋の撤去に当って特に桁下空間の利用が不可能な場合は、工法が限定され工事費用も大きく、工事期間も長くかかるのが一般的であった。さらに河川橋の場合は渇水期間の施工条件つけられるなどの制約があり通年施工が出来ないなどの問題があった。
【解決手段】橋桁両端の橋台または橋脚付近に門型鉄塔を建て、橋桁本体を切断分割する区分を決定し、前記門型鉄塔の頭部と橋桁本体の切断分割する位置付近とを数条のケーブルで固定し、切断分割する区分のうちの中央部を解体する橋桁の背面に設置したトラッククレーンにてあらかじめ仮吊りし、その状態のままで中央部を切断し、前記切断した中央部を前記トラッククレーンで撤去し、その後、橋桁の残りの部分について、順次端部へと、切断分割する区分ごとに仮吊り、切断、撤去の操作を繰り返すことを特徴とする橋桁の解体工法を提供する。
【選択図】図1
[PROBLEMS] When a girder bridge cannot be used, especially when it is impossible to use the space under the girder, the construction method is limited, the construction cost is high, and the construction period is generally long. Furthermore, in the case of river bridges, there was a problem that construction was not possible throughout the year due to restrictions such as the construction conditions for drought periods.
[MEANS FOR SOLVING PROBLEMS] A portal tower is built near the abutments or piers at both ends of a bridge girder, a section for cutting and dividing the bridge girder body is determined, and the head of the portal tower and the vicinity of the position where the bridge girder body is divided are divided into several sections. Fixed with a cable, suspended in advance with a truck crane installed on the back of the bridge girder that disassembles the central part of the section to be cut and divided, cut the central part in that state, and cut the central part A bridge girder dismantling method is provided, in which the bridge girder is removed by a truck crane, and then the remaining part of the bridge girder is repeatedly subjected to temporary suspension, cutting, and removal operations for each section to be cut and divided into the ends.
[Selection] Figure 1

Description

本発明は、橋桁の撤去に関するものである。  The present invention relates to the removal of a bridge girder.

従来桁橋の撤去は、その立地条件から桁下空間を利用できるか否かによって撤去工法は大きく異なってくる。一般的には▲1▼桁下空間に支保工を組み立てて解体する方法や、▲2▼大型トラッククレーンによる撤去方法などが採用されている。都市の高架橋や海上橋あるいは桁下空間利用の制約が無いが地上からの高さが20mを超える桁橋には、▲1▼や▲2▼の解体工法は安全面、工期、費用面などから採用は困難な場合が多い。
桁下空間を利用しないで解体する従来工法として、▲3▼隣径間の桁上や取付道路上に配置した大型トラッククレーンによる撤去工法、海上橋では▲4▼大型クレーン船による撤去工法、▲5▼既存橋桁に平行して作成した桟橋を利用したトラッククレーンによる撤去方法がある。(例えば、非特許文献1参照、特許文献1 )
The removal method of the conventional girder bridge differs greatly depending on whether the space under the girder can be used due to the location conditions. In general, (1) a method of assembling and dismantling a support work in the space under the girder, and (2) a removal method using a large truck crane are adopted. There are no restrictions on urban viaducts, maritime bridges or under-girder space use, but for girder bridges with heights above 20m above ground, the dismantling methods (1) and (2) are based on safety, construction period, and cost. Hiring is often difficult.
As a conventional method of dismantling without using the under-girder space, (3) removal method using a large truck crane placed on the girder between adjacent diameters and on the attachment road, (4) removal method using a large crane ship at the offshore bridge, ▲ 5 ▼ There is a removal method with a truck crane using a jetty created in parallel with the existing bridge girder. (For example, refer nonpatent literature 1, patent literature 1)

以下、従来の撤去工法を図3、図4、図5、図6、図7、図8により説明する。図において、図3は▲1▼の方法、図4は▲2▼の方法、図5は▲3▼の方法、図6は▲4▼の方法、図7は▲5▼の方法の説明図である。
「橋梁撤去技術マニュアル」北陸橋撤去技術協会 2000年 p.46 特開H10−280328 特願2003−357029
Hereinafter, the conventional removal method will be described with reference to FIGS. 3, 4, 5, 6, 7, and 8. 3 is a method of (1), FIG. 4 is a method of (2), FIG. 5 is a method of (3), FIG. 6 is a method of (4), and FIG. It is.
“Bridge Removal Technology Manual” Hokuriku Bridge Removal Technology Association 2000 p. 46 JP H10-280328 Japanese Patent Application No. 2003-357029

従来の桁橋の撤去工法▲1▼では支保工用の組立に必要な大量の仮設材と組立に必要な多くの職人、さらには支保工組み立て解体の期間が必要となり高所作業の為の様々な安全設備が必要である。従って工事費用も大きく、工事期間も長くかかるのが一般的である、特に河川橋では渇水期間だけの施工条件が付き通年施工が難しい。
撤去工法▲2▼は比較的短経間の橋桁を短期間で撤去する場合に用いられる工法であるが、撤去する橋桁の直近まで大型クレーンの進入路が確保されていることが条件となる。
撤去工法▲3▼はクレーンを載荷する桁橋の耐力などの問題もあり比較的小規模径間桁橋に限定される。撤去工法▲4▼の場合は主として大規模海上橋で採用される方法であるが、大型クレーン船が回送可能な水深が必要条件となる。
撤去工法▲5▼の場合は河川橋梁や水深が確保されない海上橋などに採用される方法であるが、トラッククレーン等の重機作業に耐える強度の仮桟橋を作成して橋桁を撤去する方法である。河川橋では桟橋の設置期間が渇水期に制限される欠点がある。
このように従来工法の欠点は、現場の条件に大きく左右されるために工事日数、工事費用、施工時期などの変動が大きいことが欠点であった。
The conventional girder bridge removal method (1) requires a large amount of temporary materials necessary for assembling for supporting works, many craftsmen necessary for assembling, and a period for disassembling the supporting works. Safe equipment is necessary. Therefore, the construction cost is high and the construction period is generally long. Especially, river bridges have construction conditions only for the drought period, and it is difficult to construct them throughout the year.
The removal method {circle around (2)} is a method used for removing bridges between relatively short meridians in a short period of time. However, it is a condition that an access path for a large crane is secured as close as possible to the bridge girder to be removed.
The removal method (3) is limited to relatively small span girder bridges due to problems such as the strength of the girder bridge carrying the crane. The removal method (4) is mainly used for large-scale offshore bridges, but requires a water depth that can be transported by a large crane ship.
In the case of removal method (5), this method is used for river bridges and offshore bridges where the water depth is not secured, but it is a method to create a temporary pier that can withstand heavy machinery work such as truck cranes and remove the bridge girder. . River bridges have the disadvantage that the pier installation period is limited to the dry season.
As described above, the disadvantage of the conventional construction method is that it largely depends on the conditions at the site, so that the variation in construction days, construction costs, construction time, etc. is large.

本発明は、従来の工法が有していた問題を解決しようとするものであり、短期間に、工事費用を安く、安全に桁橋の撤去作業を実施することを目的としたものである。  The present invention is intended to solve the problems of the conventional construction method, and aims to carry out the girder bridge removal operation safely in a short period of time at a low construction cost.

そして、本発明は上記目的を達成するために架橋地点のいかなる条件にも適合する工法として、特にこれから更新時期を迎える都市連続高架橋の撤去の有力な工法としても提供する。
本工法は解体撤去する径間の橋脚や橋台上に門型鉄塔を設け、隣径間の橋脚などに固定したアンカーと門型鉄塔頭部を控索で固定し、橋桁の切断分割する位置付近と門型鉄塔頭部を斜ケーブルで固定し段取りを終わる。この状態で隣径間の橋桁上に配置したトラッククレーンで切断する区分を仮吊りした状態のまま,橋桁を所定位置で切断しクレーンで吊り上げ撤去する工法を提供する。
切断ヶ所は自走式トラッククレーンで吊り上げ可能な重量となるように配分し、部材切断撤去作業は橋梁中央部から開始し、順次端部側へと作業を進め、橋桁切断部材は待機したトラックに直接積み込み搬出する。
In order to achieve the above object, the present invention is provided as a construction method suitable for any conditions at the bridge point, particularly as an effective construction method for removing a continuous urban viaduct that is about to be renewed.
In this construction method, the bridge piers to be dismantled and the gate towers are installed on the abutments, and the anchors fixed to the bridge piers between adjacent diameters and the heads of the portal towers are fixed with a lanyard, and the bridge girder is near the position where it is cut and divided Fix the head of the tower tower with a diagonal cable and finish the setup. In this state, a method is provided in which the bridge girder is cut at a predetermined position and lifted and removed by a crane while the section to be cut by the truck crane arranged on the bridge girder between adjacent diameters is temporarily suspended.
The cutting points are allocated so that the weight can be lifted by a self-propelled truck crane, and the member cutting / removing work starts from the center of the bridge, proceeding to the end side sequentially, and the bridge girder cutting member is placed on the waiting truck. Direct loading and unloading.

トラッククレーンを載荷する橋桁の耐力が不足する場合は、当該径間の桁にPCケーブルを配置し応力補強を行う.  If the strength of the bridge girder on which the truck crane is loaded is insufficient, a PC cable is placed in the girder between the spans to reinforce the stress.

上述したように本発明の橋桁撤去工法は、従来の工法に比較し橋桁の架橋条件に左右されることが少ない。  As described above, the bridge girder removal method of the present invention is less affected by the bridge girder bridge conditions than the conventional method.

搬入する仮設材の部材は少量で比較的軽量であり、短期間の作業で、高所作業が極端に少なく、従って安全性が高く工事費用も従来工法に比べて大幅に低減できることを特徴としている。  The temporary material to be carried in is small and relatively light, and it is characterized by extremely short work and extremely little work at high places. Therefore, safety is high and construction costs can be significantly reduced compared to conventional methods. .

以下、本発明の実施の形態を図1〜図2に基づいて説明する。  Hereinafter, embodiments of the present invention will be described with reference to FIGS.

門型鉄塔設備3を組立て、3の頭部から後控索4を張り、隣径間の橋脚や取り付け道路に設けたアンカー6に固定する。The tower-type tower equipment 3 is assembled, and the rear cable 4 is stretched from the head of 3 and fixed to an anchor 6 provided on a bridge pier between adjacent diameters or an attachment road.

門型鉄塔設備3の頭部から切断部分7に向けて、複数の斜吊り材5で橋桁本体1を固定し、1の分割撤去にそなえる。The bridge girder body 1 is fixed with a plurality of slanting members 5 from the head of the portal tower 3 to the cut portion 7 to prepare for the division and removal of one.

次に自走クレーン8で撤去する橋桁1の部分を仮吊りした状態で7部分を切断し8にて吊り上げ撤去する。8の能力は1の区分重量を踏まえた作業半径により決定される。Next, in a state where the portion of the bridge girder 1 to be removed by the self-propelled crane 8 is temporarily suspended, 7 portions are cut and lifted and removed at 8. The capacity of 8 is determined by the working radius based on the weight of 1 division.

分割撤去された桁1は背面で二次切断を行うか又は、順次運搬トラック9に積みこみ搬出する事を繰り返し1の撤去作業が終了する。The divided and removed girders 1 are subjected to secondary cutting on the back surface or sequentially loaded and unloaded on the transport truck 9 to complete the removal operation 1.

以下、橋桁の残りの部分について、順次端部側へと切断分割する区分ごとに仮吊り、切断、撤去の操作を繰り返す。Hereinafter, for the remaining part of the bridge girder, the operation of temporarily suspending, cutting, and removing is repeated for each section that is sequentially cut and divided toward the end side.

クレーンを載荷する径間の橋桁の耐力が不足する場合は当該径間にPCケーブルによる補強を行なう。When the strength of the bridge girder between the spans on which the crane is loaded is insufficient, the span is reinforced with a PC cable.

本発明の実施形態を示す橋桁撤去の段取り説明図Setup explanatory drawing of bridge girder removal showing an embodiment of the present invention 本発明の実施形態を示す橋桁橋撤去状況の説明図Explanatory drawing of the bridge girder bridge removal situation showing the embodiment of the present invention 従来の撤去工法▲1▼で支保工上での分割撤去作業説明図Explanatory drawing of split removal work on support with conventional removal method (1) 従来の撤去工法▲2▼でトラッククレーンにて橋桁を撤去する一般的方法General method of removing bridge girder with truck crane using conventional removal method (2) 従来の撤去工法▲3▼でトラッククレーンを隣径間に配置し橋桁を撤去する方法Method of removing the bridge girder by placing the truck crane between adjacent diameters with the conventional removal method (3) 従来の撤去工法▲4▼でクレーン船にて橋桁を撤去する方法How to remove bridge girder with crane ship by conventional removal method (4) 従来の撤去工法▲5▼で仮桟橋を設けトラッククレーンにて橋桁を撤去する方法A method of removing a bridge girder with a truck crane by installing a temporary pier in the conventional removal method (5) 橋桁のPCケーブルによる補強概念図Conceptual diagram of reinforcement using PC cables for bridge girders

符号の説明Explanation of symbols

1 橋桁本体
2 橋脚、橋台
3 門型鉄塔設備
4 後控索
5 斜吊り材
6 後控索固定用アンカー
7 切断位置
8 自走式トラッククレーン
9 運搬トラック
10 支保工
11 仮桟橋
12 クレーン船
13 補強PCケーブル
DESCRIPTION OF SYMBOLS 1 Bridge girder body 2 Pier, abutment 3 Gate type steel tower equipment 4 Rear cable 5 Slant hanging material 6 Anchor for anchoring rear cable 7 Cutting position 8 Self-propelled truck crane 9 Transport truck 10 Supporting work 11 Temporary pier 12 Crane ship 13 Reinforcement PC cable

Claims (1)

都市連続高架橋における解体しようとする橋桁両端の橋台または橋脚付近にそれぞれ門型鉄塔を建て、前記橋桁の両隣の径間のもう一方の橋脚または取り付け道路にそれぞれ設けたアンカーと前記各門型鉄塔の頭部との間にそれぞれ控索を張り、前記門型鉄塔の頭部と前記橋桁の切断分割する区分の端部付近とをそれぞれ数条のケーブルで固定し、前記解体する橋桁の軸方向手前側の径間の橋桁にPCケーブルを配置し、前記切断分割する区分のうちの中央部を前記軸方向手前側の橋桁上に配置した自走式トラッククレーンにてあらかじめ仮吊りし、その状態のままで中央部を切断し、前記切断した中央部を前記自走式トラッククレーンで撤去し、その後、橋桁の残りの部分について、順次端部へと、切断分割する区分ごとに仮吊り、切断、撤去の操作を繰り返す作業を1セットとし、前記1セットの作業終了後、前記自走式トラッククレーンを隣接する橋桁上に移動させて、前記1セットの作業を順次繰り返すことにより、都市連続高架橋における橋桁を解体することを特徴とする橋桁の解体工法。 Each built portal tower in abutment or near abutment at both ends of the girder to be dismantled in urban continuous viaduct, anchor and each portal tower provided respectively on the other pier or installing road span on both sides of the bridge girder axial tension to Hikaesaku respectively between the head, the fixed by the end cable and the number Article respective near segment for cutting division of the head and the bridge girder of the gantry tower, bridge girder to the dismantling PC cable is placed on the bridge girder between the front side of the direction, and the central part of the section to be cut and divided is temporarily suspended by a self-propelled truck crane arranged on the front side girder of the axial direction. The central part is cut in the state, the cut central part is removed by the self-propelled truck crane, and then the remaining part of the bridge girder is temporarily suspended for each of the sections to be cut and divided sequentially. Cut off , The task of repeating the operations of removal and set, after the work end of the set, is moved on the bridge deck adjacent the self-propelled truck crane, by sequentially repeating the operations of the set, urban continuous viaduct Bridge girder dismantling method, characterized by dismantling the bridge girder in
JP2005332159A 2005-10-19 2005-10-19 Bridge girder dismantling method Active JP3861100B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005332159A JP3861100B1 (en) 2005-10-19 2005-10-19 Bridge girder dismantling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005332159A JP3861100B1 (en) 2005-10-19 2005-10-19 Bridge girder dismantling method

Publications (2)

Publication Number Publication Date
JP3861100B1 true JP3861100B1 (en) 2006-12-20
JP2007113376A JP2007113376A (en) 2007-05-10

Family

ID=37648339

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005332159A Active JP3861100B1 (en) 2005-10-19 2005-10-19 Bridge girder dismantling method

Country Status (1)

Country Link
JP (1) JP3861100B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900027A (en) * 2012-10-22 2013-01-30 中铁十局集团有限公司 Dismounting method of bailey beam with upwardly strode existing lines and underneath penetrated existing bridge
CN103343512A (en) * 2013-07-03 2013-10-09 上海市机械施工集团有限公司 Method for dismantling large-section concrete box girders and hoisting device
CN106812073A (en) * 2017-01-12 2017-06-09 浙江交工金筑交通建设有限公司 It is quick to remove bridge pier column construction method
CN110273385A (en) * 2019-04-03 2019-09-24 中铁大桥局武汉桥梁特种技术有限公司 A kind of across concrete box girder method for dismounting in cross-line hole
CN111560864A (en) * 2020-01-17 2020-08-21 广东冠粤路桥有限公司 Method for dismantling old bridge
CN112921839A (en) * 2021-01-22 2021-06-08 广东冠粤路桥有限公司 Dismantling method of inclined leg rigid frame bridge
CN113774822A (en) * 2021-09-15 2021-12-10 中交二航局第三工程有限公司 Dismantling method of old reinforced concrete bridge
CN113863171A (en) * 2021-09-02 2021-12-31 武汉二航路桥特种工程有限责任公司 Method for dismantling horizontal thrust overpass

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6434885B2 (en) * 2015-10-07 2018-12-05 大日本コンサルタント株式会社 How to build a cable-stayed bridge
CN106996083B (en) * 2017-05-25 2018-11-09 中铁二局集团有限公司 A method of Bridge Erector is reinforced
JP7172916B2 (en) * 2019-08-20 2022-11-16 Jfeエンジニアリング株式会社 Bridge superstructure removal method
CN110552296B (en) * 2019-09-20 2020-12-25 上海浦东新区公路建设发展有限公司 Cable-stayed bridge dismantling construction method
CN112276248B (en) * 2020-11-02 2022-12-20 唐山开滦建设(集团)有限责任公司 Method for dismantling box type derrick
CN114134829B (en) * 2021-12-29 2023-08-08 杭州萧山交通建设管理有限公司 Prestressed hollow slab girder bridge dismantling system and construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900027A (en) * 2012-10-22 2013-01-30 中铁十局集团有限公司 Dismounting method of bailey beam with upwardly strode existing lines and underneath penetrated existing bridge
CN103343512A (en) * 2013-07-03 2013-10-09 上海市机械施工集团有限公司 Method for dismantling large-section concrete box girders and hoisting device
CN103343512B (en) * 2013-07-03 2015-10-28 上海市机械施工集团有限公司 The method for dismounting of big cross section concrete box girder and hanging apparatus
CN106812073A (en) * 2017-01-12 2017-06-09 浙江交工金筑交通建设有限公司 It is quick to remove bridge pier column construction method
CN110273385A (en) * 2019-04-03 2019-09-24 中铁大桥局武汉桥梁特种技术有限公司 A kind of across concrete box girder method for dismounting in cross-line hole
CN111560864A (en) * 2020-01-17 2020-08-21 广东冠粤路桥有限公司 Method for dismantling old bridge
CN112921839A (en) * 2021-01-22 2021-06-08 广东冠粤路桥有限公司 Dismantling method of inclined leg rigid frame bridge
CN113863171A (en) * 2021-09-02 2021-12-31 武汉二航路桥特种工程有限责任公司 Method for dismantling horizontal thrust overpass
CN113774822A (en) * 2021-09-15 2021-12-10 中交二航局第三工程有限公司 Dismantling method of old reinforced concrete bridge

Also Published As

Publication number Publication date
JP2007113376A (en) 2007-05-10

Similar Documents

Publication Publication Date Title
JP3861100B1 (en) Bridge girder dismantling method
JP3716316B2 (en) Demolition and removal method of arch bridge
CN107905116B (en) Construction method of large-span through type rigid tied steel arch bridge
CN106049293B (en) Stiffening girder of suspension bridge installation method and used shifting system is swung on navigable river
CN111560864B (en) Method for dismantling old bridge
CN113235467A (en) Construction method for dismantling large-span prestressed cast-in-place box girder
CN110374008A (en) A method of the erection of cable-stayed bridge steel truss is carried out in marine environment
CN101487234B (en) Construction method for transverse beam hoisting in-position of arch first and beam late tied-arch bridge
CN112252212A (en) Method for dismantling prestressed concrete variable cross-section continuous beam bridge
JP5075392B2 (en) Rope type repair scaffold
CN111960245B (en) Hoisting and rope hanging method for viaduct dismantling
JP5693869B2 (en) Bridge girder construction method
CN203682931U (en) Wharf building crane
CN102493367A (en) Non-blasting construction method for dismantling pier to land bridge
KR20130036578A (en) Cantilever of ship for external turret mooring system is applied truss structure
Naqvi et al. Transportation considerations in module design
CN218621839U (en) Steel-concrete joint section construction support system of hybrid beam cable-stayed bridge
Homsi et al. Management of specialized erection equipment: selection and organization
RU2737748C1 (en) Installation of underwater road demountable bridge in design position of superstructure with one intermediate pile-shoe support
CN210659363U (en) Steel structure for oil storage tank
CN214530258U (en) Bridge deck hanging bracket for dismantling variable cross-section prestressed continuous box girder bridge deck
CN111764313B (en) Construction method for dismantling multi-layer steel structure overbridge
JP6889743B2 (en) Manufacturing method of erected concrete structure in water area
Ascaso Til et al. 1915Çanakkale Bridge, Turkey: challenges and achievements of deck erection over the Dardanelles
CN116289669A (en) Cable-stayed bridge dismantling method with few brackets in complex environment

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060912

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060925

R150 Certificate of patent or registration of utility model

Ref document number: 3861100

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120929

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130929

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250