JP3773678B2 - Concrete compaction method and apparatus - Google Patents

Concrete compaction method and apparatus Download PDF

Info

Publication number
JP3773678B2
JP3773678B2 JP32769198A JP32769198A JP3773678B2 JP 3773678 B2 JP3773678 B2 JP 3773678B2 JP 32769198 A JP32769198 A JP 32769198A JP 32769198 A JP32769198 A JP 32769198A JP 3773678 B2 JP3773678 B2 JP 3773678B2
Authority
JP
Japan
Prior art keywords
concrete
cord
tool
float
vibration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP32769198A
Other languages
Japanese (ja)
Other versions
JP2000145149A (en
Inventor
秀利 原
勉 北川
雪久 稲川
毅 相崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP32769198A priority Critical patent/JP3773678B2/en
Publication of JP2000145149A publication Critical patent/JP2000145149A/en
Application granted granted Critical
Publication of JP3773678B2 publication Critical patent/JP3773678B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、トンネル内に二次覆工用のコンクリートを打設する際、型枠とトンネル内壁面との間に打設されたコンクリートに振動を与え、周辺のコンクリートを締固める方法および装置に関するものである。
なお、本明細書中、「打設」とは、養生硬化させていない泥状のコンクリートを型枠とトンネル内壁面との間に充填させることをいう。
【0002】
【従来の技術】
元来、トンネル内への二次覆工用のコンクリートの打設は、コンクリートを打設するための移動式型枠を、コンクリート打設終了後、前方に折畳んで搬送し、展開させて設置し、その個所でコンクリートを打設する形式の二次覆工用移動式型枠により行われていた。
【0003】
この移動式型枠をトンネル内の所定位置に設置した後、移動式型枠に多数設けられた所定位置の開閉自在の検査窓からコンクリート搬送管を介して移動式型枠とトンネル内壁面との間にコンクリートを打設する際、養生硬化後のコンクリートの強度、耐久性を向上させるため、コンクリートを打設する検査窓より上方の検査窓から作業員が振動具を突出させると共に、打設したコンクリート内に挿入させ、この振動具の振動により、打設したコンクリートの締固め、およびコンクリート内に混在する気泡の除去を行っていた。
【0004】
また、移動式型枠とトンネル内壁面との間へのコンクリートの打設は、トンネルの掘削側と反対(既コンクリート打設)側の下部、トンネルの掘削側の下部、トンネルの掘削側と反対側の上部、トンネルの掘削側の上部へと順次打設するのが常である。
【0005】
また、振動具は、耐久性を考慮した大径の接続コードの先端に振動部を備えたものが主流であり、作業員はコードを把持し、検査窓から振動部を打設したコンクリート内に挿入させ、振動部の振動により、打設したコンクリートに振動を与えていた。
【0006】
このため、図11に示すように、まず所定位置の検査窓を開放させることによりコンクリート搬送口とし、コンクリート供給管に連結されたコンクリート搬送管の先端をこの検査窓から突出させ、このコンクリート搬送管からコンクリートを、移動式型枠とトンネル内壁面との間へ投入し、
コンクリートの打設位置より上方の検査窓から、作業員が移動式型枠とトンネル内壁面との間へのコンクリートの打設量を目視し、所定量のコンクリートを打設した後、検査窓内にコンクリート搬送管を収納し、
作業員が上方の検査窓から振動具を突出させ、打設したコンクリート内に挿入させ、振動具を振動させると共に、昇降させることにより、打設したコンクリートの締固め、およびコンクリート内に混在する気泡の除去を行い、
所定のコンクリートの打設が終了した後、別の個所へコンクリートを打設するため、別の位置の検査窓をコンクリート搬出口として使用し、再び前記同様作業により打設したコンクリートに振動を与えていた。
【0007】
また、振動具を突出させた検査窓部分にコンクリートを打設する際、振動具を検査窓内に収納してこの検査窓を窓用蓋により閉鎖して行うため、この間は振動具を介して振動させることが不可能であり、また移動式型枠とトンネル内壁面との間の間隔が狭い場合、作業員により振動具をその狭い空間内に挿入させることが非常に困難であるため、効果は少なくなるが移動式型枠に直接振動モーターを取付け、この振動モーターにより移動式型枠を介して打設したコンクリートに振動を与えていた。
【0008】
なお、図11中、62は移動式型枠、64は検査窓、66は窓用蓋、68はコンクリート搬送管、70は振動具、72はコンクリート、74はトンネル内壁面、76は作業員を示す。
【0009】
【発明が解決しようとする課題】
従来、作業員により振動具を操作する場合、コンクリートを打設する毎に、検査窓からの振動具の突出、打設したコンクリート内への挿入、振動具の振動、振動具の昇降、を全て人手により行うため、作業能率が良くないことが問題となっていた。
【0010】
また、振動具を長時間、連続振動させた場合、泥状のコンクリートが水分とコンクリートに分離し、硬化後コンクリートとしての効果が全く得られないことが問題となっていた。
【0011】
また、振動モーターにより移動式型枠を振動させる場合、その振動が局部的であるため、打設したコンクリートに振動を十分に与えることが不可能であり、養生硬化後のコンクリートの強度、耐久性が低下することが問題となっていた。
【0012】
本発明は、このような欠点に鑑み、移動式型枠とトンネル内壁面との間に打設したコンクリートを締固める際、作業員の負担を激減させ、作業能率を向上させることができると共に、養生硬化後のコンクリートの強度、耐久性を格段に向上させることができるコンクリート締固め方法および装置を提供することを目的とするものである。
【0013】
【課題を解決するための手段】
本発明は、トンネル内に移動式型枠を使用して二次覆工用のコンクリートを打設する装置において、前記移動式型枠の検査窓から外側に巻揚機構をもって昇降自在となる振動具を吊下し、該振動具には挿脱自在に浮子が装着されるとともに、該振動具にはコード本体を空間部を介在させて被覆コードにより被覆することで中空構造となる接続コードが接続されているコンクリート締固め装置を特徴とする。また、その装置は、前記浮子のコード挿通孔を、振動具の外径より大きく形成し、浮子は、振動具側から挿入可能であって固定具を介して接続コードに固定されるとともに、固定具の固定を解除して振動具側から取外し可能であることを特徴とする。それら特徴を有する装置によってトンネル内に二次覆工用のコンクリートを打設する工程において、移動式型枠とトンネル内壁面との間に、予め挿脱自在に浮子を装着してなる振動具を、振動具に接続された接続コードを巻揚機構を介して延出させることにより、所定の検査窓から突出させて移動式型枠外側に昇降自在に吊下させ、移動式型枠とトンネル内壁面との間にコンクリートを打設した後、振動具の昇降と連動して振動具を間欠振動させ、コンクリートを締固めた後、浮子の浮力により続いて打設されるコンクリート上面を浮遊させ、振動具を上昇させながら周辺のコンクリートを締固めるコンクリート締固め方法を特徴とするものである。
【0014】
【発明の実施の形態】
本発明に係るトンネル用打設コンクリートの締固め装置は、トンネル12内に二次覆工用のコンクリート14を打設するための移動式型枠16に装着されるものである。
【0015】
本発明で使用する移動式型枠16は、上円部分18および下円部分20がそれぞれ折畳み搬送可能なものである。
【0016】
本発明に係るトンネル用打設コンクリートの振動装置は、図1〜図10に示すように、以下の構成からなるものである。
【0017】
移動式型枠16に外部と貫通した検査窓22が複数個設けられている。
【0018】
移動式型枠16の最上段の各検査窓22内に巻揚機構24を設置し、この巻揚機構24を介して、浮子26を挿脱自在に装着した振動具28が、移動式型枠16外側に昇降自在に吊下されている。
【0019】
本例において、振動具28は電磁式振動体を収容した振動部30が、接続コード32を介して電源34と接続され、この接続コード32を長尺とし、巻揚構24に巻回させてある。
【0020】
また、図5に示すように、接続コード32は、コード本体36の外周を空間部37を介在させて被覆コード38により被覆させ、中空構造としてあり、この構造を採用することにより、接続コードを軽量化し、取扱易くなり、このため巻揚機構24を小型化することができる。
【0021】
また、浮子26はポリ塩化ビニール製の中空の球体であり、振動具28への挿脱手段は、浮子26の中央に設けられたコード挿通孔40を、振動具28(振動部30)の外径より大きく形成し、振動具28の先端側(図4において下側)から浮子26を挿入させ、抜止め体、止め金具およびナットからなる固定具42を介して接続コード32に固定してある。
【0022】
振動具28を突出させる検査窓を含む各検査窓22の外側に突出させて振動具28のコード用ガイドローラー44を、移動式型枠12内に収納自在に設置してある。
【0023】
本例において、コード用ガイドローラー44の外周面は、幅方向の中心部に向けて内側に湾曲させてあり、振動具28の昇降移動により、接続コード32に対する負荷を激減させ、接続コード32の耐久性を向上させることができる。
【0024】
また、巻揚機構24はリールであり、電動により巻揚げる機構を備えたものが望ましく、手動により巻揚げる機構のものでもよい。
【0025】
各振動具28は、振動具28を間欠振動させる制御機構46により制御され、この制御機構46は振動具28を昇降させるための巻揚機構24も同時に制御する。
【0026】
図8および図9に、振動具28を突出させる検査窓22の外側を、被覆する被覆板48が示してある。
【0027】
本被覆板48は、検査窓22を被覆可能な大きさの平板であり、中央部に蝶番50を配して2個に折り畳み可能とし、この被覆板48により振動具28を突出させる検査窓22を被覆させることにより、振動具28を突出させた検査窓22上方からのコンクリート投入時に、振動具28を突出させた検査窓22からの投入コンクリートの移動式型枠16内への浸入を防止することができる。
【0028】
なお、図中52は移動式型枠16上部に設置されたコンクリート搬出管、53は検査窓22を開閉するための窓用蓋を止着するための止着孔、54はガントリー、56はレール、58は駆動ローラー、60はトンネル内壁面を示す。
【0029】
本装置を介して移動式型枠16とトンネル内壁面60との間に打設した二次覆工用のコンクリート14を締固める方法を以下に詳述する。
【0030】
まず、移動式型枠16をトンネル12の所定位置まで移動させる。
【0031】
次に、コンクリート打設個所の最上段の検査窓22から浮子26を装着してなる振動具28を、振動具28に接続された接続コード32を巻揚機構24を介して延出させることにより、移動式型枠16外側に昇降自在に吊下させる。
【0032】
この際、振動具28を突出させる検査窓を含む各検査窓22内に収納自在に設置してある各コード用ガイドローラー44を外側に突出させて、振動具28の接続コード32を各コード用ガイドローラー44に掛装させる。
【0033】
このコード用ガイドローラー44の外周面は幅方向の中心部に向けて内側に湾曲させてあるため、振動具28の操作性、接続コード32の耐久性、を向上させることができる。
【0034】
次に、コンクリート搬出管52からコンクリート14を、移動式型枠16とトンネル内壁面60との間に打設する。
【0035】
次に、コンクリート14の打設量の作業員の目視により、所定個所(1個所または複数個所)の振動具28を制御機構46を介して間欠振動させる。
【0036】
この際、コンクリート14の打設量は、図2の破線で示すように、コンクリート投入側(図2において左側)から順次流動し、均一状態とならないため、コンクリート14の打設量が多いコンクリート投入側(図2において左側)部分をより多く振動させる必要があり、このため振動具28を個別に間欠振動させるように制御させてある。
【0037】
振動具28を間欠振動させることにより、打設コンクリート14を長時間、連続振動させることがないため、コンクリートが水分とコンクリートとに分離することがなくなり、コンクリートの強度、耐久性を向上させることができる。
【0038】
また、振動具28に装着された浮子26は打設された泥状コンクリート14上面に浮上するため、振動具28はコンクリート打設に伴い浮子26と共に上昇し、このため振動具28は続いて打設されるコンクリート14の打設速度に応じて自動的に浮遊、上昇しながら、適宜間隔でコンクリート14を間欠振動させ、周辺のコンクリート14を確実に締固めることができる。
【0039】
この際、振動具28の浮上に伴う接続コード32の弛みは、巻揚機構24により自動的に巻揚げて解消させ、また投入コンクリート内に振動具28が埋没した際には、この巻揚機構24により強制的に巻揚げることができる。
【0040】
次に、所定量のコンクリート14の打設終了後、検査窓22を順次閉鎖する。
【0041】
次に、別のコンクリート搬出管52から別個所へコンクリート14を打設し、前記同様各振動具28を間欠振動させることにより、トンネル12の掘削側と反対側の下部、トンネル12の掘削側の下部、トンネル12の掘削側と反対側の上部、トンネル12の掘削側の上部へと順次コンクリート14を打設すると共に、打設したコンクリート14を締固める。
【0042】
また、振動具28を突出させた検査窓22の外側を、被覆板48により被覆させ、振動具28を突出させた検査窓22上方からのコンクリート投入時に、振動具28を突出させた検査窓22からの投入コンクリートの移動式型枠16内への浸入を防止することができる。
【0043】
この際、被覆板48は検査窓22の内側から2個に折り畳んで検査窓22外側へ突出させた後、展開させて止着孔53を利用して止着させる。
【0044】
また、移動式型枠16とトンネル内壁面60との間に、鉄筋等の補強具が多数配設されている場合、あるいは移動式型枠16とトンネル内壁面60との間隔が狭い場合、には振動具28の浮子26が邪魔になるため、浮子26を取外して振動具28を使用することをしいられるが、本発明の振動具28の浮子26は固定具42の固定を解除して、浮子26を振動具28(振動部30)の先端側から容易に取外すことができる。
【0045】
なお、本例において、移動式型枠16とトンネル内壁面60との間へのコンクリート打設量は作業員の目視によるものであるが、コンクリート打設量を感知するコンクリートセンサーを設置し、コンクリートセンサーのコンクリート打設量の感知により、振動具28の間欠振動、昇降、コンクリート搬出管52からのコンクリート打設、等を連動させることにより、作業員の削減を図り、作業性をより一層向上させることができる。
【0046】
また、浮子26の形状、接続コード32の内部構造、等の振動具28の構造は本例と同様である必要性はなく、他の構造を採用することは自由である。
【0047】
また、移動式型枠16とトンネル内壁面60との間へのコンクリート投入は移動式型枠16上部のコンクリート搬出管52によるものであるが、移動式型枠16内に配設された移動自在のコンクリート搬出管を各検査窓から突出させてコンクリート投入することは自明のことである。
【0048】
また、本例は略半円径のトンネルにおけるコンクリート打設におけるものであるが、円形のトンネル、例えば海中トンネル、下水道等にも利用できる。
【0049】
また、移動式型枠16は折畳み自在のものであるが、必ずしも折畳み自在のものに限定されることはない。
【0050】
【発明の効果】
本発明に係るコンクリート締固め方法および装置によれば、移動式型枠とトンネル内壁面との間へのコンクリートの打設量に応じて、浮子の浮力により続いて打設されるコンクリート上面を浮遊させ、振動具を上昇させながら間欠振動させることにより周辺のコンクリートを効率良く自動的に締固めることができる。
【0051】
また、浮子のコード挿通孔を、振動具の外径より大きく形成することにより、浮子を固定具を介して接続コードに固定すると共に、浮子を接続コードから取外す際、固定具の固定を解除し、浮子を振動具側から容易に取外すことができる。
【0052】
また、各検査窓の外側に突出させて振動具のコード用ガイドローラーを、移動式型枠内に収納自在に設置し、振動具の接続コードを各コード用ガイドローラーに掛装させることにより、型枠外周面から離隔させ、操作性を向上させると共に、接続コードの耐久性を向上させることができる。
【0053】
また、振動具を突出させる検査窓の外側を、検査窓を被覆可能な被覆板により被覆させることにより、振動具を突出させた検査窓上方からのコンクリート投入時に、振動具を突出させた検査窓からの投入コンクリートの移動式型枠内への浸入を防止することかできる。
【図面の簡単な説明】
【図1】本発明に係るコンクリート締固め装置が装着された移動式型枠の正面図。
【図2】同、側面図。
【図3】同、制御機構を示す配線図。
【図4】振動具の一部破断正面図。
【図5】振動具の接続コードの断面図。
【図6】コード用ガイドローラーの正面図。
【図7】同、平面図。
【図8】被覆板の使用状態を示す正面図。
【図9】同、側面図。
【図10】振動具の使用状態を示す正面図。
【図11】従来のコンクリート打設および締固め作業を示す正面図。
【符号の説明】
12 トンネル
14 コンクリート
16 移動式型枠
22 検査窓
24 巻揚機構
26 浮子
28 振動具
32 接続コード
40 コード挿通孔
42 固定具
44 コード用ガイドローラー
48 被覆板
52 コンクリート搬出管
60 トンネル内壁面
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method and an apparatus for applying vibration to concrete placed between a formwork and a tunnel inner wall surface and compacting the surrounding concrete when placing concrete for secondary lining in the tunnel. Is.
In the present specification, “laying” means filling mud concrete that has not been cured and cured between the mold and the inner wall surface of the tunnel.
[0002]
[Prior art]
Originally, concrete placement for secondary lining in tunnels was carried out by moving a movable formwork for placing concrete into the tunnel, folding it forward, and then unfolding it. However, it was carried out by a mobile formwork for secondary lining in which concrete was cast at that location.
[0003]
After this mobile formwork is installed at a predetermined position in the tunnel, the mobile formwork and the inner wall surface of the tunnel are connected through concrete transport pipes from a plurality of openable inspection windows at predetermined positions provided on the mobile formwork. In order to improve the strength and durability of the cured concrete when placing concrete in between, an operator made the vibration tool protrude from the inspection window above the inspection window where the concrete was placed and cast it. It was inserted into the concrete, and the vibration of the vibrating tool was used to compact the placed concrete and to remove bubbles mixed in the concrete.
[0004]
In addition, concrete placement between the mobile formwork and the inner wall of the tunnel is the opposite of the tunnel excavation side (existing concrete placement) side, tunnel excavation side lower part, tunnel excavation side opposite It is usual to place them one after the other at the upper part of the tunnel and the upper part of the excavation side of the tunnel.
[0005]
In addition, vibration tools are mainly equipped with a vibration part at the end of a large-diameter connection cord in consideration of durability, and an operator grips the cord and puts it in the concrete where the vibration part is placed from the inspection window. The inserted concrete was vibrated by the vibration of the vibration part.
[0006]
For this reason, as shown in FIG. 11, first, the inspection window at a predetermined position is opened to form a concrete conveyance port, and the end of the concrete conveyance pipe connected to the concrete supply pipe is protruded from the inspection window. The concrete from between the mobile formwork and the inner wall of the tunnel,
From the inspection window above the concrete placement position, the operator visually inspected the amount of concrete placed between the mobile formwork and the tunnel inner wall, and after placing a predetermined amount of concrete, the inside of the inspection window To store the concrete transport pipe,
The operator projects the vibration tool from the upper inspection window, inserts it into the placed concrete, vibrates the vibration tool, and raises and lowers it to compact the placed concrete and bubbles mixed in the concrete. Removing
After placing the specified concrete, the concrete placed in another location is used as a concrete exit to place the concrete in another location. It was.
[0007]
In addition, when placing concrete in the inspection window part where the vibration tool is projected, the vibration tool is housed in the inspection window and this inspection window is closed with a window lid. If it is impossible to vibrate and the distance between the movable formwork and the inner wall surface of the tunnel is narrow, it is very difficult for an operator to insert the vibration tool into the narrow space. However, the vibration motor was directly attached to the mobile formwork, and this vibration motor vibrated the concrete placed through the mobile formwork.
[0008]
In FIG. 11, 62 is a movable formwork, 64 is an inspection window, 66 is a window lid, 68 is a concrete transport pipe, 70 is a vibration tool, 72 is concrete, 74 is a tunnel inner wall surface, and 76 is an operator. Show.
[0009]
[Problems to be solved by the invention]
Conventionally, when a vibration tool is operated by an operator, every time concrete is placed, the protrusion of the vibration tool from the inspection window, the insertion into the placed concrete, the vibration of the vibration tool, and the lifting and lowering of the vibration tool are all performed. Since it is performed manually, the problem is that work efficiency is not good.
[0010]
In addition, when the vibration tool is continuously vibrated for a long time, the mud concrete is separated into moisture and concrete, and there is a problem that the effect as concrete after curing cannot be obtained at all.
[0011]
In addition, when the mobile formwork is vibrated by a vibration motor, the vibration is local, so it is impossible to give sufficient vibration to the placed concrete, and the strength and durability of the concrete after curing and curing. Has been a problem.
[0012]
In view of such drawbacks, the present invention can drastically reduce the burden on the worker when compacting the concrete placed between the mobile formwork and the inner wall surface of the tunnel, and can improve the work efficiency. An object of the present invention is to provide a concrete compaction method and apparatus that can remarkably improve the strength and durability of concrete after curing.
[0013]
[Means for Solving the Problems]
The present invention relates to an apparatus for placing concrete for secondary lining using a movable formwork in a tunnel, and a vibrating tool that can be moved up and down with a hoisting mechanism outside the inspection window of the movable formwork. A floating cord is attached to the vibrator so that it can be inserted and removed, and a connecting cord that has a hollow structure is connected to the vibrator by covering the cord body with a covering cord with a space in between. Features a compacted concrete compaction device. Further, the device forms the cord insertion hole of the float larger than the outer diameter of the vibration tool, and the float can be inserted from the vibration tool side and is fixed to the connection cord via the fixing tool. It is characterized in that the tool can be released and removed from the vibrating tool side. In the process of placing concrete for secondary lining in the tunnel by the device having these characteristics, a vibrating tool in which a float is mounted in a removable manner in advance between the movable formwork and the inner wall surface of the tunnel. By extending the connecting cord connected to the vibration tool through a hoisting mechanism, the cord is projected from a predetermined inspection window and hung up and down freely outside the movable formwork. After placing concrete between the walls, the vibrating tool is intermittently vibrated in conjunction with the raising and lowering of the vibrating tool, and after the concrete is compacted, the concrete upper surface to be subsequently placed is floated by the buoyancy of the float, The concrete compaction method is characterized by compacting surrounding concrete while raising the vibration tool.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
The tunnel placing concrete compaction apparatus according to the present invention is mounted on a movable mold 16 for placing secondary lining concrete 14 in a tunnel 12.
[0015]
In the movable mold 16 used in the present invention, the upper circle portion 18 and the lower circle portion 20 can be folded and conveyed.
[0016]
As shown in FIGS. 1 to 10, the vibration device for tunnel casting concrete according to the present invention has the following configuration.
[0017]
A plurality of inspection windows 22 penetrating the outside are provided in the movable mold 16.
[0018]
A hoisting mechanism 24 is installed in each inspection window 22 at the uppermost stage of the movable mold 16, and a vibrating tool 28 in which a float 26 is detachably mounted is provided via the hoisting mechanism 24. 16 is suspended from the outside so as to be movable up and down.
[0019]
In this example, the vibrating device 28 includes a vibrating unit 30 that houses an electromagnetic vibrating body, and is connected to a power source 34 via a connection cord 32. The connection cord 32 is elongated and wound around a winding mechanism 24. is there.
[0020]
Further, as shown in FIG. 5, the connection cord 32 has a hollow structure in which the outer periphery of the cord main body 36 is covered with a covering cord 38 with a space portion 37 interposed therebetween. It is lighter and easier to handle, and therefore the hoisting mechanism 24 can be made smaller.
[0021]
Moreover, the float 26 is a hollow sphere made of polyvinyl chloride, and the means for inserting into and removing from the vibrating tool 28 is configured such that the cord insertion hole 40 provided in the center of the float 26 is connected to the outside of the vibrating tool 28 (vibrating unit 30). The float 26 is inserted from the front end side (lower side in FIG. 4) of the vibration tool 28 and is fixed to the connection cord 32 via a fixing tool 42 including a retaining member, a stopper and a nut. .
[0022]
The cord guide roller 44 of the vibrating tool 28 is installed in the movable mold 12 so as to be freely housed by protruding outside the inspection windows 22 including the inspection window for projecting the vibrating tool 28.
[0023]
In this example, the outer peripheral surface of the cord guide roller 44 is curved inward toward the center in the width direction, and the load on the connection cord 32 is drastically reduced by the up-and-down movement of the vibration tool 28. Durability can be improved.
[0024]
The hoisting mechanism 24 is a reel, and is preferably provided with a mechanism for electrically hoisting, or may be a mechanism for manually hoisting.
[0025]
Each vibration tool 28 is controlled by a control mechanism 46 that causes the vibration tool 28 to vibrate intermittently, and the control mechanism 46 also controls the hoisting mechanism 24 for raising and lowering the vibration tool 28 at the same time.
[0026]
8 and 9 show a cover plate 48 that covers the outside of the inspection window 22 through which the vibration tool 28 protrudes.
[0027]
The cover plate 48 is a flat plate having a size that can cover the inspection window 22. The hinge plate 50 is arranged at the center so that the cover plate 48 can be folded into two. The inspection window 22 projects the vibration tool 28 by the cover plate 48. When the concrete is poured from above the inspection window 22 from which the vibration tool 28 is projected, the intrusion concrete from the inspection window 22 from which the vibration tool 28 is projected is prevented from entering the movable mold 16. be able to.
[0028]
In the figure, 52 is a concrete carry-out pipe installed on the upper part of the movable mold 16, 53 is a fastening hole for fastening a window lid for opening and closing the inspection window 22, 54 is a gantry, and 56 is a rail. , 58 is a driving roller, and 60 is a tunnel inner wall surface.
[0029]
A method for compacting the concrete 14 for secondary lining placed between the movable mold 16 and the tunnel inner wall surface 60 through this apparatus will be described in detail below.
[0030]
First, the movable mold 16 is moved to a predetermined position in the tunnel 12.
[0031]
Next, by extending the connecting cord 32 connected to the vibrating tool 28 via the hoisting mechanism 24, the vibrating tool 28 to which the float 26 is mounted from the inspection window 22 at the uppermost stage of the concrete placement site is extended. Then, it is suspended from the movable mold 16 so as to be movable up and down.
[0032]
At this time, each cord guide roller 44 slidably installed in each inspection window 22 including the inspection window for projecting the vibration tool 28 is projected outward, and the connection cord 32 of the vibration tool 28 is used for each cord. The guide roller 44 is hung.
[0033]
Since the outer circumferential surface of the cord guide roller 44 is curved inward toward the center in the width direction, the operability of the vibration tool 28 and the durability of the connection cord 32 can be improved.
[0034]
Next, the concrete 14 is placed between the movable formwork 16 and the tunnel inner wall surface 60 from the concrete carry-out pipe 52.
[0035]
Next, the vibration tool 28 at a predetermined place (one place or a plurality of places) is intermittently vibrated through the control mechanism 46 by visual observation of an operator of the placement amount of the concrete 14.
[0036]
At this time, as shown by the broken line in FIG. 2, the amount of concrete 14 that is poured flows from the concrete loading side (left side in FIG. 2) in order and does not become uniform. It is necessary to vibrate more of the side (left side in FIG. 2) portion. For this reason, the vibrator 28 is controlled to be intermittently vibrated individually.
[0037]
By intermittently vibrating the vibrating tool 28, the cast concrete 14 is not continuously vibrated for a long time, so that the concrete is not separated into moisture and concrete, and the strength and durability of the concrete can be improved. it can.
[0038]
Further, since the float 26 attached to the vibration tool 28 floats on the upper surface of the placed mud concrete 14, the vibration tool 28 rises together with the float 26 as the concrete is placed, so that the vibration tool 28 continues to strike. The concrete 14 is intermittently vibrated at appropriate intervals while automatically floating and rising according to the placement speed of the concrete 14 to be provided, and the surrounding concrete 14 can be reliably compacted.
[0039]
At this time, the looseness of the connection cord 32 due to the floating of the vibration tool 28 is automatically lifted by the winding mechanism 24 to be eliminated, and when the vibration tool 28 is buried in the input concrete, the winding mechanism 24 can be forcibly wound.
[0040]
Next, after the placement of a predetermined amount of concrete 14 is completed, the inspection windows 22 are sequentially closed.
[0041]
Next, the concrete 14 is placed from another concrete discharge pipe 52 to a separate place, and each vibration tool 28 is intermittently vibrated in the same manner as described above. The concrete 14 is sequentially cast in the lower part, the upper part of the tunnel 12 opposite to the excavation side, and the upper part of the tunnel 12 on the excavation side, and the cast concrete 14 is compacted.
[0042]
Further, the outside of the inspection window 22 from which the vibration tool 28 protrudes is covered with a covering plate 48, and the inspection window 22 from which the vibration tool 28 protrudes when the concrete is poured from above the inspection window 22 from which the vibration tool 28 protrudes. It is possible to prevent the input concrete from entering the movable mold 16.
[0043]
At this time, the cover plate 48 is folded into two pieces from the inside of the inspection window 22, protrudes to the outside of the inspection window 22, and then spreads and is fixed using the fixing holes 53.
[0044]
Further, when a large number of reinforcing tools such as reinforcing bars are arranged between the movable mold 16 and the tunnel inner wall surface 60, or when the distance between the movable mold 16 and the tunnel inner wall surface 60 is narrow, Since the float 26 of the vibration tool 28 is in the way, it is recommended to use the vibration tool 28 by removing the float 26. However, the float 26 of the vibration tool 28 of the present invention releases the fixation of the fixing tool 42, The float 26 can be easily removed from the distal end side of the vibrating tool 28 (vibrating unit 30).
[0045]
In this example, the amount of concrete placed between the mobile formwork 16 and the tunnel inner wall surface 60 is visually observed by an operator. However, a concrete sensor for detecting the amount of concrete placed is installed and the concrete is placed. By detecting the amount of concrete placed by the sensor, the intermittent vibration of the vibration tool 28, raising and lowering, and concrete placing from the concrete carry-out pipe 52 are interlocked, thereby reducing the number of workers and further improving workability. be able to.
[0046]
Further, the structure of the vibrating tool 28 such as the shape of the float 26 and the internal structure of the connection cord 32 is not necessarily the same as in this example, and other structures can be freely adopted.
[0047]
In addition, the concrete input between the movable mold 16 and the inner wall surface 60 of the tunnel is due to the concrete carry-out pipe 52 on the upper part of the movable mold 16, but it is movable within the movable mold 16. It is self-evident that the concrete carrying pipe is projected from each inspection window and poured into the concrete.
[0048]
Moreover, although this example is about the concrete placement in the tunnel of a substantially semicircle diameter, it can utilize also for a circular tunnel, for example, an underwater tunnel, a sewer.
[0049]
Moreover, although the movable formwork 16 is a foldable thing, it is not necessarily limited to a foldable thing.
[0050]
【The invention's effect】
According to the concrete compaction method and apparatus of the present invention, the upper surface of the concrete to be subsequently placed is floated by the buoyancy of the float according to the amount of concrete placed between the mobile formwork and the inner wall surface of the tunnel. The surrounding concrete can be efficiently and automatically compacted by intermittent vibration while raising the vibration tool.
[0051]
In addition, by forming the cord insertion hole of the float larger than the outer diameter of the vibration tool, the float is fixed to the connection cord via the fixture, and the fixture is released when the float is removed from the connection cord. The float can be easily removed from the vibrating tool side.
[0052]
In addition, the cord guide roller for the vibration tool is protruded outside each inspection window so that it can be stored in the movable mold, and the connection cord of the vibration tool is hung on the guide roller for each cord. While being separated from the outer peripheral surface of the formwork, the operability can be improved and the durability of the connection cord can be improved.
[0053]
In addition, by covering the outside of the inspection window through which the vibration tool protrudes with a covering plate that can cover the inspection window, the inspection window through which the vibration tool protrudes when concrete is introduced from above the inspection window from which the vibration tool protrudes It is possible to prevent the input concrete from entering the mobile formwork.
[Brief description of the drawings]
FIG. 1 is a front view of a mobile formwork equipped with a concrete compaction apparatus according to the present invention.
FIG. 2 is a side view of the same.
FIG. 3 is a wiring diagram showing the control mechanism.
FIG. 4 is a partially broken front view of the vibration tool.
FIG. 5 is a cross-sectional view of a connecting cord of a vibration tool.
FIG. 6 is a front view of a cord guide roller.
FIG. 7 is a plan view of the same.
FIG. 8 is a front view showing a use state of the cover plate.
FIG. 9 is a side view of the same.
FIG. 10 is a front view showing a usage state of the vibration tool.
FIG. 11 is a front view showing a conventional concrete placing and compacting operation.
[Explanation of symbols]
12 Tunnel 14 Concrete 16 Mobile Form 22 Inspection Window 24 Lifting Mechanism 26 Float 28 Vibrating Tool 32 Connection Cord 40 Cord Insertion Hole 42 Fixing Tool 44 Guide Roller for Cord 48 Cover Plate 52 Concrete Unloading Pipe 60 Tunnel Inner Wall Surface

Claims (4)

トンネル(12)内に移動式型枠(16)を使用して二次覆工用のコンクリート(14)を打設する工程において、移動式型枠(16)とトンネル内壁面(60)との間に、予め挿脱自在に浮子(26)を装着してなる振動具(28)が、該振動具(28)に接続されたコード本体(36)を空間部(37)を介在させて被覆コード(38)により被覆することで中空構造となる接続コード(32)によって巻揚機構(24)を介して延出されることにより、所定の検査窓(22)から突出させて移動式型枠(16)外側に昇降自在に吊下させ、移動式型枠(16)とトンネル内壁面(60)との間にコンクリート(14)を打設した後、振動具(28)の昇降と連動して振動具(28)を間欠振動させ、コンクリート(14)を締固めた後、浮子(26)の浮力により続いて打設されるコンクリート上面を浮遊させ、振動具(28)を上昇させながら周辺のコンクリート(14)を締固めることを特徴とし、浮子 (26) のコード挿通孔 (40) を、振動具 (28) の外径より大きく形成し、浮子 (26) を振動具側から挿入させ、固定具 (42) を介して接続コード (32) に固定すると共に、固定具 (42) の固定を解除し、浮子 (26) を振動具側から取外すことを特徴とするコンクリート締固め方法。In the process of placing concrete for secondary lining (14) using the mobile formwork (16) in the tunnel (12), the mobile formwork (16) and the tunnel inner wall surface (60) A vibrating tool (28) in which a float (26) is mounted in a removable manner in advance, covers the cord body (36) connected to the vibrating tool (28) with a space (37) interposed therebetween. By extending through the hoisting mechanism (24) by the connection cord (32) which becomes a hollow structure by covering with the cord (38), the movable formwork is projected from the predetermined inspection window (22) ( 16) After hanging up and down freely, placing concrete (14) between the movable formwork (16) and the tunnel inner wall surface (60), interlocking with the raising and lowering of the vibration tool (28) After the vibrating tool (28) is intermittently vibrated and the concrete (14) is compacted, the upper surface of the concrete to be subsequently placed is floated by the buoyancy of the float (26), and the vibrating tool (28) is raised while Concrete (14) Characterized by compacting, float the cord insertion hole (40) in (26), formed larger than the outer diameter of the vibrating member (28), is inserted float (26) from the vibration member side, the fixture (42) is fixed to via a connection cord (32), to release the fastener (42), concrete compaction method characterized by removing the float (26) from the vibration member side. 振動具 (28) を突出させた検査窓 (22) の外側を、検査窓 (22) を被覆可能な被覆板 (48) により被覆させ、振動具 (28) を突出させた検査窓 (22) 上方からのコンクリート投入時に、振動具 (28) を突出させた検査窓 (22) からの投入コンクリートの移動式型枠 (16) 内への浸入を防止したことを特徴とする請求項1記載のコンクリート締固め方法。 Outward, inspection window (22) is coated with a coating capable cover plate (48) and inspection window is protruded vibration device (28) of the inspection window that is projected vibration device (28) (22) (22) when the concrete poured from above, according to claim 1, characterized in that to prevent the intrusion of the vibration member (28) movable formwork turned concrete from the inspection window is protruded (22) (16) in Concrete compaction method. トンネル (12) 内に移動式型枠 (16) を使用して二次覆工用のコンクリート (14) を打設する装置において、前記移動式型枠 (16) の検査窓 (22) から外側に巻揚機構 (24) をもって昇降自在となる振動具 (28) を吊下し、該振動具 (28) には挿脱自在に浮子 (26) が装着されるとともに、該振動具 (28) にはコード本体 (36) を空間部 (37) を介在させて被覆コード (38) により被覆することで中空構造となる接続コード (32) が接続されていることを特徴とし、前記浮子 (26) のコード挿通孔 (40) を、振動具 (28) の外径より大きく形成し、浮子 (26) は、振動具 (28) 側から挿入可能であって固定具 (42) を介して接続コード (32) に固定されるとともに、固定具 (42) の固定を解除して振動具 (28) 側から取外し可能であることを特徴とするコンクリート締固め装置 In an apparatus for placing concrete (14) for secondary lining using a mobile formwork (16 ) in a tunnel (12) , outside the inspection window (22) of the mobile formwork (16) wound fried mechanism (24) with a vertically movable and comprising vibrating equipment (28) suspended beat, with removably float (26) is mounted to the vibrating equipment (28), the vibrating equipment (28) Is connected to the cord body (36) with the covering cord (38 ) with the space portion (37) interposed therebetween to connect the connecting cord (32) having a hollow structure, and the float (26 ) Cord insertion hole (40) is made larger than the outer diameter of the vibration tool (28) , and the float (26) can be inserted from the vibration tool (28) side and connected via the fixing tool (42). it is fixed to the cord (32), characterized and to Turkey Nkurito compaction device that releases the fixation of the fixture (42) is removable from the vibrating equipment (28) side. 前記検査窓 (22) は、その外側を被覆板 (48) によって被覆可能としたことを特徴とする請求項3に記載のコンクリート締固め装置。 The inspection window (22), the concrete compaction device according to claim 3, characterized in that to enable covering the outward by the cover plate (48).
JP32769198A 1998-11-18 1998-11-18 Concrete compaction method and apparatus Expired - Lifetime JP3773678B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32769198A JP3773678B2 (en) 1998-11-18 1998-11-18 Concrete compaction method and apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32769198A JP3773678B2 (en) 1998-11-18 1998-11-18 Concrete compaction method and apparatus

Publications (2)

Publication Number Publication Date
JP2000145149A JP2000145149A (en) 2000-05-26
JP3773678B2 true JP3773678B2 (en) 2006-05-10

Family

ID=18201907

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32769198A Expired - Lifetime JP3773678B2 (en) 1998-11-18 1998-11-18 Concrete compaction method and apparatus

Country Status (1)

Country Link
JP (1) JP3773678B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106640135B (en) * 2016-12-08 2018-11-09 中铁十四局集团第二工程有限公司 A kind of automatic vibrating system and vibrating method performing concrete for tunnel double-lining
JP7030310B2 (en) * 2018-12-25 2022-03-07 戸田建設株式会社 Vibration device and vibration method for cast concrete
JP7026841B1 (en) * 2021-12-09 2022-02-28 大栄工機株式会社 Inspection window opening / closing mechanism and tunnel lining formwork

Also Published As

Publication number Publication date
JP2000145149A (en) 2000-05-26

Similar Documents

Publication Publication Date Title
JP3773678B2 (en) Concrete compaction method and apparatus
JP3278355B2 (en) Vibration method of cast concrete for tunnel and vibrating device of cast concrete for tunnel
JP2001262986A (en) Concrete compacting method and device therefor
JP4812666B2 (en) Tunnel lining concrete placement method
JP4044827B2 (en) Concrete compaction method and apparatus
JP4799453B2 (en) Tunnel lining concrete placement method
JP4566891B2 (en) Tunnel lining concrete placement method
JP2001082087A (en) Concrete compacting method and its device
JP2002235496A (en) Concrete compacting method by vibrator
JPH08260896A (en) Compaction method of tunnel lining concrete
JP3981585B2 (en) Method and apparatus for placing concrete for tunnel
JPH07198558A (en) Concrete sampling device of cast-in-situ pile
JP2007309014A (en) Construction method for pile core body
JP2000356098A (en) Method for compacting concrete and compacting vibrator device
JPH04222772A (en) Placing device of steel pipe concrete column and placing method thereof
JP3093020U (en) Form with inspection window
JP2003064996A (en) Vibration method for placing concrete for tunnel and its device
JP2003184321A (en) Device and method for demolishing tower-like structure
JPH04222773A (en) Placing device of steel pipe concrete column and placing method thereof
JP2003129662A (en) Method and apparatus for vibrating concrete placed
JPS6140920A (en) Method and apparatus for placing in-place pile concrete
JPH10231517A (en) Pile head concrete elimination method and device for concrete-charged steel pipe pile
JP2002227597A (en) Concrete placing method for tunnel and device thereof
JP2794166B2 (en) Underground excavator
JPS6092511A (en) Formation work of partly covered sand drain pile

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050128

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050215

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050418

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050524

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050725

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060131

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060215

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090224

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120224

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150224

Year of fee payment: 9

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term