JP3764668B2 - Water path estimation method and water path estimation device - Google Patents

Water path estimation method and water path estimation device Download PDF

Info

Publication number
JP3764668B2
JP3764668B2 JP2001327270A JP2001327270A JP3764668B2 JP 3764668 B2 JP3764668 B2 JP 3764668B2 JP 2001327270 A JP2001327270 A JP 2001327270A JP 2001327270 A JP2001327270 A JP 2001327270A JP 3764668 B2 JP3764668 B2 JP 3764668B2
Authority
JP
Japan
Prior art keywords
water
drilling
pressure
boring
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001327270A
Other languages
Japanese (ja)
Other versions
JP2003129782A (en
Inventor
泰典 阿部
一彦 升元
克 戸井田
泰宏 須山
幸弘 塩釜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2001327270A priority Critical patent/JP3764668B2/en
Publication of JP2003129782A publication Critical patent/JP2003129782A/en
Application granted granted Critical
Publication of JP3764668B2 publication Critical patent/JP3764668B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Geophysics And Detection Of Objects (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、水みち推定方法および水みち推定装置に関するものである。
【0002】
【従来の技術】
従来、地質調査や水理特性等を把握するために実施するボーリングの孔を利用して、その周辺の岩盤や地盤を調査するために透水試験やトモグラフィ計測等の原位置試験が実施される。これらの結果を利用し、土木構造物の建設に必要な情報を取得する。
【0003】
図8は、従来の孔間透水試験装置の概略図である。地盤101には、事前に、2本のボーリング孔103、ボーリング孔105が掘削される。送水装置として使用されるボーリング孔103では、パッカ107の間に発信区間109が設けられる。受信装置として使用されるボーリング孔105では、パッカ111の間に複数の受信区間113が設けられる。ボーリング孔103の発信区間109から注水を行い、ボーリング孔105の受信区間113で圧力応答を観測し、孔間内の水みちを推定する。
【0004】
【発明が解決しようとする課題】
しかしながら、従来の方法では、事前に掘削したボーリング孔に、発信側と受信側の試験装置を設置して計測を実施するため、時間・コストの面において効率的でない。
【0005】
本発明は、このような問題に鑑みてなされたもので、その目的とするところは、短時間で経済的に、簡便な透水試験と同等の結果を得ることができる水みち推定方法および水みち推定装置を提供することにある。
【0006】
【課題を解決するための手段】
前述した目的を達成するための第1の発明は、地盤に第1のボーリング孔を削孔し、前記第1のボーリング孔内の所定の部分をパッカで閉塞して、圧力計が設けられた受信区間を形成し、ボーリング機械で第2のボーリング孔を削孔して掘進状況を記録しつつ、前記圧力計を用いて前記受信区間での水圧を取得することを特徴とする水みち推定方法である。
【0007】
地盤に削孔された第1のボーリング孔は、受信装置として使用される。第1のボーリング孔には、1箇所以上の受信区間が形成され、各受信区間には圧力計が設けられる。削孔途中の第2のボーリング孔は、送水装置として使用される。第2のボーリング孔は、少なくとも1箇所に削孔され、任意の個所に配置できる。第2のボーリング孔の掘進状況のうち、例えばボーリング機械の削孔水圧力と、受信区間で取得した水圧とを比較し、第1のボーリング孔と第2のボーリング孔との間の水みちの位置を推定する。
【0008】
第1の発明では、地盤に削孔した第1のボーリング孔内の所定の部分をパッカで閉塞して受信区間を形成する。受信区間には、圧力計が設けられる。次に、ボーリング機械で第2のボーリング孔を削孔して掘進状況を記録しつつ、受信区間に設けた圧力計を用いて受信区間での水圧を取得する。
【0009】
第2の発明は、地盤内に削孔された第1のボーリング孔をパッカで閉塞して形成された受信区間に設けられた圧力計と、前記地盤内に第2のボーリング孔を削孔するボーリング機械と、前記圧力計を用いて測定された水圧および前記ボーリング機械の掘進状況を取得するデータ取得手段とを具備し、前記水圧と前記掘進状況とを比較して、前記第1のボーリング孔と前記第2のボーリング孔との間の水みちの位置を推定することを特徴とする水みち推定装置である。
【0010】
第2の発明では、地盤内に削孔済みの第1のボーリング孔をパッカで閉塞して形成された受信区間に設けられた圧力計で水圧が測定される。また、第2のボーリング孔が、ボーリング機械を使用して削孔される。第2のボーリング孔の掘削時には、圧力計で測定された水圧、および、ボーリング機械の掘削状況がデータ取得手段で取得される。水圧と、掘削状況を比較して、第1のボーリング孔と第2のボーリング孔との間の水みちの位置が推定される。なお、データ取得手段は、水圧と掘削状況のそれぞれについて設けてもよい。
【0011】
【発明の実施の形態】
以下、図面に基づいて、本発明の実施の形態について詳細に説明する。図1は、水みち推定装置Aの概略図である。図1に示すように、水みち推定装置Aは、地盤1に掘削されたNo.2ボーリング孔7に設けられた圧力計33a、33b、33c、33d、33e、コンピュータ39、No.1ボーリング孔4とNo.3ボーリング孔5とを削孔しつつあるボーリング機械19のポンプ15、給圧装置17等で構成される。No.2ボーリング孔7は、水みち推定装置Aの受信装置として使用され、No.1ボーリング孔4、No.3ボーリング孔5は、送水装置として使用される。
【0012】
2台のボーリング機械19は、No.1ボーリング孔4、No.3ボーリング孔5にそれぞれ挿入されたロッド11、ロッド11の先端に取り付けられたビット9、地盤1上に設置された給圧装置17、ポンプ15等で構成される。ボーリング機械19は、ホース13を介してポンプ15から送水しつつ、給圧装置17でビット9に適切な圧力を与えて、No.1ボーリング孔4、No.3ボーリング孔5を削孔する。
【0013】
No.1ボーリング孔4、No.3ボーリング孔5の削孔中には、掘削状況を管理し、記録する。掘削状況とは、削孔深度と時間、ボーリング機械19の削孔水圧力、回転数、送水量、排水量、給圧、掘進速度等の情報である。
【0014】
図2は、No.2ボーリング孔7へのパッカおよび圧力計の設置工程を示す断面図である。No.2ボーリング孔7は、ボーリング機械19と同様の機械を使用して、あらかじめ地盤1に掘削されている。パッカ21a、21b、21c…、21fは、例えば、ゴム製等の収縮・膨張が可能な材質である。パッカ21a、21b、21c…の内部にはケーブル35が通され、ケーブル35には圧力計33a、33b、33c…が接続されている。図2に示すように、収縮した状態のパッカ21a、21b、21c…、21fをNo.2ボーリング孔7に挿入し、それぞれ所定の位置に配置する。
【0015】
図1に示すように、所定の位置に配置したパッカ21a、21b、21c、21d、21e、21fを膨張させ、No.2ボーリング孔7を閉塞する。パッカ21aとパッカ21bの間には受信区間2−aが、パッカ21bとパッカ21cの間には受信区間2−bが、パッカ21cとパッカ21dの間には受信区間2−cが、パッカ21dとパッカ21eの間には受信区間2−dが、パッカ21eとパッカ21fの間には受信区間2−eが、それぞれ形成される。
【0016】
受信区間2−a、受信区間2−b、受信区間2−c、受信区間2−d、受信区間2−eには、それぞれ、圧力計33a、33b、33c、33d、33eが設置される。圧力計33a、33b、33c、33d、33eは、ケーブル35を介して、地盤1上のアンプ37、コンピュータ39に接続される。コンピュータ39は、圧力計33a、33b、33c、33d、33eで計測した受信区間2−a、受信区間2−b、受信区間2−c、受信区間2−d、受信区間2−eでの水圧を、アンプ37を介して取得する。
【0017】
次に、水みち推定装置の動作について説明する。
ボーリング機械19のホース13を介してポンプ15から送水し、給圧装置17でビット9に適切な圧力を与えて、No.1ボーリング孔4、No.3ボーリング孔5を掘削する。掘削中には、掘削状況を管理し、記録する。掘削状況とは、削孔深度と時間、ボーリング機械19の削孔水圧力、回転数、送水量、排水量、給圧、掘進速度等の情報である。
【0018】
同時に、No.2ボーリング孔7側では、受信区間2−a、受信区間2−b、受信区間2−c、受信区間2−d、受信区間2−eでの水圧を圧力計33a、33b、33c、33d、33eで計測する。コンピュータ39は、アンプ37を介して水圧の経時変化のデータを取得する。
【0019】
図3は、経過時間を横軸に、水圧を縦軸に表した場合の圧力モニタリングの結果を示す図である。2−b区間41、2−c区間43、2−d区間45、2−e区間47に示す曲線は、それぞれ受信区間2−b、受信区間2−c、受信区間2−d、受信区間2−eで観測された水圧の経時変化を示す。No.1ボーリング孔削孔時49(楕円形の印)は、No.1ボーリング孔4を削孔した時間を、No.3ボーリング孔削孔時51(長方形の印)は、No.3ボーリング孔5を削孔した時間を示す。
【0020】
No.1ボーリング孔4およびNo.3ボーリング孔5と、No.2ボーリング孔7との間の地盤101の透水性が大きい場合、No.1ボーリング孔4、No.3ボーリング孔5の削孔中にポンプ15からビット9へ送水された削孔水が地盤101へ流入してNo.2ボーリング孔7へ到達し、受信区間2−b、受信区間2−c、受信区間2−d、受信区間2−eで観測される水圧に応答が見られる。
【0021】
例えば、No.3ボーリング孔削孔時51aには、2−b区間41、2−c区間43、2−d区間45に示す曲線に応答が見られる。よって、No.3ボーリング孔削孔時51aに相当する深度において、No.3ボーリング孔5と、受信区間2−b、受信区間2−c、受信区間2−dとは、連続性が高いと推定できる。
【0022】
また、2−e区間47に示す曲線は、他の2−b区間41、2−c区間43、2−d区間45に示す曲線と比較して応答が極めて小さい。よって、一番深い位置にある受信区間2−eにおいては、No.1ボーリング孔4やNo.3ボーリング孔5との連続性が小さいと判断できる。
【0023】
図4は、No.3ボーリング孔5削孔深度を横軸に、水圧と削孔水注入圧を縦軸に表した場合の圧力応答モニタリング結果を示す。2−b区間53、2−c区間55、2−d区間57、2−e区間59に示す曲線は、それぞれ受信区間2−b、受信区間2−c、受信区間2−d、受信区間2−eで観測された水圧の応答値の変化を示す。削孔水注入圧61(三角形の印)は、各削孔深度でのボーリング機械19の削孔水注入圧を示す。
【0024】
図4では、No.3ボーリング孔5削孔深度により、水圧の応答値に差が見られる。圧力応答が大きいほど、その削孔深度でのNo.3ボーリング孔5と受信区間2−b、受信区間2−c、受信区間2−d、受信区間2−eの間の透水性が大きいと推定できる。
【0025】
送水装置側のボーリング孔の掘削状況と、受信装置側のボーリング孔での圧力応答を比較することにより水みちの位置を推定できることを検証するため、ルジオン試験を行った。すなわち、削孔済みのNo.3ボーリング孔5から注水して、No.2ボーリング孔7での圧力応答を観測した。
【0026】
図5は、No.3ボーリング孔5で注水を行った試験区間を示す図である。No.3ボーリング孔5は、パッカ等(図示せず)で閉塞され、試験区間3−a、試験区間3−b、試験区間3−c、試験区間3−d、試験区間3−eが形成される。なお、これらの試験区間は、図4では試験区間3−b63、試験区間3−c65、試験区間3−d67、試験区間3−e69に示す深度に位置する。
【0027】
図6は、No.2ボーリング孔7の受信区間2−c、受信区間2−dにおいて、No.3ボーリング孔5削孔時およびルジオン試験時に観測した圧力応答結果を示す図である。横軸は加圧側の位置、縦軸はNo.2ボーリング孔7での応答圧である。横軸に示す加圧側の位置は、No.3ボーリング孔5側の試験区間3−b、試験区間3−c、試験区間3−d、試験区間3−eである。
【0028】
No.3ボーリング孔5の各試験区間でルジオン試験を行った時の、No.2ボーリング孔7の受信区間2−c、受信区間2−dでの応答圧を、それぞれ、応答圧87c、87d(折れ線)に示す。また、No.3ボーリング孔5の各試験区間の深度を削孔した時の、受信区間2−c、受信区間2−dでの応答圧を、それぞれ、応答圧89c、89d(折れ線)に示す。なお、図6の応答圧は、全て加圧側を100kPaに換算した場合の値を示している。
【0029】
図6に示すように、ルジオン試験時の応答圧87c、87d、削孔時の応答圧89c、89dとも、試験区間3−bでの加圧に対して、最大の応答値を示している。よって、ルジオン試験、本実施の形態の水みち推定方法のいずれの方法でも、試験区間3−bと受信区間2−c、試験区間3−bと受信区間2−dとの間に水みちがあることが推定できる。
【0030】
なお、試験区間3−d、試験区間3−eでの加圧に対して、ルジオン試験時の応答圧87c、87dは減少しているが、削孔時の応答圧89c、89dは増加しており、結果が一致していない。この原因として、ルジオン試験時の注入水は、パッカで閉塞された試験区間からのみ注入されるのに対し、ボーリング中の削孔水は地上へ戻る流れがあることにより、削孔深度より浅い区間からも岩盤内へ削孔水が流入することが考えられる。今回の場合では、図4に示すように、試験区間3−d67の上方の深度24m付近に圧力応答の大きい区間、すなわち透水性が大きいと推定できる区間があり、この区間からの削孔水の流入の影響を受けたと推定できる。
【0031】
このように、水みち推定装置Aでは、送水装置としてボーリング機械19で削孔しつつあるNo.1ボーリング孔4、No.3ボーリング孔5を使用し、削孔水に対する圧力応答を観測するため、短時間で従来の透水試験を行ったのと同等の結果を得ることができる。また、送水装置を簡便化できるので、経済的である。
【0032】
なお、本実施の形態では、水みち推定装置Aとして、3本のボーリング孔を直線上に配置し、送水装置である2本のボーリング孔をほぼ同時に削孔したが、ボーリング孔の本数や位置関係、送水装置の削孔時間はこの限りでない。1個所の受信装置に対して、送水装置は1個所以上とする。複数の送水装置を使用する場合、孔配置や削孔の順番を適切に計画することにより、効率的に精度良く水みち推定を行うことができる。また、受信装置として使用するボーリング孔に形成する受信区間は、任意の数量や位置に設定できる。
【0033】
さらに、ボーリング機械19の削孔水圧と受信区間での応答圧を比較して水みちの位置を推定する方法の他に、ボーリング機械19の送水量、排水量、給圧、回転数、掘進速度等のデータを使用する方法が考えられる。
【0034】
なお、図3から図6に結果を示した試験において、図5に示すように、No.1ボーリング孔4は泥岩優勢層81に、No.2ボーリング孔7は泥岩優勢層81と礫岩83の層に、No.3ボーリング孔5は礫岩83の層と砂岩優勢層85に位置する。裸孔での孔壁維持が困難な場合は、ボーリング孔内に塩ビケーシングを設置した。
【0035】
図7は、塩ビ管97を設置したボーリング孔内の受信区間または試験区間付近の拡大断面図である。ボーリング孔内には塩ビ管97が挿入され、受信区間または試験区間に相当する位置にはストレーナ93が配置される。塩ビ管97と周辺岩盤99の間はベントナイトペレット91で、ストレーナ93およびその上下部分の塩ビ管97と周辺岩盤99の間は珪砂95で埋め戻される。
【0036】
【発明の効果】
以上、詳細に説明したように、本発明によれば、短時間で経済的に、簡便な透水試験と同等の結果を得ることができる水みち推定方法および水みち推定装置を提供できる。
【図面の簡単な説明】
【図1】水みち推定装置Aの概略図
【図2】ボーリング孔3へのパッカおよび圧力計の設置工程を示す断面図
【図3】圧力モニタリングの結果を示す図
【図4】圧力応答モニタリング結果を示す図
【図5】No.3ボーリング孔5で注水を行った試験区間を示す図
【図6】No.2ボーリング孔7の受信区間2−c、受信区間2−dにおいて、No.3ボーリング孔5削孔時およびルジオン試験時に観測した圧力応答結果を示す図
【図7】塩ビ管97を設置したボーリング孔内の受信区間または試験区間付近の拡大断面図
【図8】従来の孔間透水試験装置の概略図
【符号の説明】
1………地盤
4………No.1ボーリング孔
5………No.3ボーリング孔
7………No.2ボーリング孔
9………ビット
15………ポンプ
19………ボーリング機械
21a、21b、21c、21d、21e、21f………パッカ
33a、33b、33c、33d、33e………圧力計
87c、87d、89c、89d………応答圧
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a water channel estimation method and a water channel estimation device.
[0002]
[Prior art]
Conventionally, in-situ tests such as permeability tests and tomography measurements have been carried out in order to investigate the surrounding rock mass and ground using boreholes that are carried out to grasp geological surveys and hydraulic characteristics. . Using these results, information necessary for construction of civil engineering structures is obtained.
[0003]
FIG. 8 is a schematic view of a conventional interpore permeability test apparatus. In the ground 101, two boring holes 103 and a boring hole 105 are excavated in advance. In the boring hole 103 used as a water feeding device, a transmission section 109 is provided between the packers 107. In the boring hole 105 used as a receiving device, a plurality of receiving sections 113 are provided between the packers 111. Water is injected from the transmission section 109 of the boring hole 103, the pressure response is observed in the receiving section 113 of the boring hole 105, and the water channel between the holes is estimated.
[0004]
[Problems to be solved by the invention]
However, the conventional method is not efficient in terms of time and cost because the transmitter and receiver test devices are installed in the drilled holes that have been excavated in advance.
[0005]
The present invention has been made in view of such a problem, and the object of the present invention is to provide a water path estimation method and a water path capable of obtaining results equivalent to a simple water permeability test in a short time and economically. It is to provide an estimation device.
[0006]
[Means for Solving the Problems]
According to a first invention for achieving the above-mentioned object, a pressure gauge is provided by cutting a first boring hole in the ground, closing a predetermined portion in the first boring hole with a packer. A water channel estimation method characterized in that a receiving section is formed, a second boring hole is drilled by a boring machine and a drilling situation is recorded, and a water pressure in the receiving section is acquired using the pressure gauge. It is.
[0007]
The first bore hole drilled in the ground is used as a receiving device. One or more receiving sections are formed in the first boring hole, and a pressure gauge is provided in each receiving section. The second boring hole in the middle of drilling is used as a water supply device. The second boring hole is drilled at at least one place and can be arranged at an arbitrary place. Of the drilling status of the second boring hole, for example, the drilling water pressure of the boring machine is compared with the water pressure acquired in the receiving section, and the water path between the first boring hole and the second boring hole is compared. Estimate the position.
[0008]
In the first invention, a predetermined section in the first boring hole drilled in the ground is closed with a packer to form a receiving section. A pressure gauge is provided in the reception section. Next, the second boring hole is drilled with a boring machine to record the state of digging, and the water pressure in the receiving section is acquired using a pressure gauge provided in the receiving section.
[0009]
According to a second aspect of the present invention, a pressure gauge provided in a receiving section formed by closing a first boring hole drilled in the ground with a packer, and a second boring hole drilled in the ground A boring machine, and a data acquisition means for acquiring the water pressure measured using the pressure gauge and the drilling status of the boring machine, and comparing the water pressure with the drilling status to determine the first boring hole And a second water-hole estimating device for estimating a water-hole position between the second boring hole.
[0010]
In the second aspect of the invention, the water pressure is measured with a pressure gauge provided in a receiving section formed by closing the first bored hole in the ground with a packer. Also, the second boring hole is drilled using a boring machine. At the time of excavation of the second boring hole, the water pressure measured by the pressure gauge and the excavation status of the boring machine are acquired by the data acquisition means. By comparing the water pressure and the excavation status, the position of the water channel between the first bore hole and the second bore hole is estimated. Data acquisition means may be provided for each of the water pressure and the excavation status.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a schematic view of a water channel estimation apparatus A. As shown in FIG. 1, the water channel estimation apparatus A is a No. 1 excavated in the ground 1. 2 Pressure gauges 33a, 33b, 33c, 33d, 33e provided in the borehole 7, computer 39, No. 2 1 boring hole 4 and no. 3 is constituted by a pump 15 of a boring machine 19 that is drilling the boring hole 5, a pressure supply device 17, and the like. No. The 2 boring hole 7 is used as a receiving device of the water channel estimating device A. 1 boring hole 4, no. The 3 boring hole 5 is used as a water supply device.
[0012]
The two boring machines 19 are no. 1 boring hole 4, no. The rod 11 is inserted into the three boring holes 5, the bit 9 is attached to the tip of the rod 11, the pressure supply device 17 is installed on the ground 1, the pump 15 and the like. The boring machine 19 applies appropriate pressure to the bit 9 with the pressure supply device 17 while feeding water from the pump 15 through the hose 13. 1 boring hole 4, no. 3 Drill the bore 5.
[0013]
No. 1 boring hole 4, no. During the drilling of the three boring holes 5, the excavation status is managed and recorded. The excavation status is information such as the drilling depth and time, the drilling water pressure of the boring machine 19, the number of revolutions, the water supply amount, the drainage amount, the supply pressure, the excavation speed, and the like.
[0014]
FIG. It is sectional drawing which shows the installation process of the packer in the 2 boring hole 7, and a pressure gauge. No. The 2 boring hole 7 is excavated in the ground 1 in advance using a machine similar to the boring machine 19. The packers 21a, 21b, 21c,..., 21f are made of a material that can be contracted and expanded, such as rubber. The cables 35 are passed through the packers 21a, 21b, 21c..., And pressure gauges 33a, 33b, 33c. As shown in FIG. 2, the packers 21a, 21b, 21c,. 2 are inserted into the boring holes 7 and arranged at predetermined positions.
[0015]
As shown in FIG. 1, the packers 21a, 21b, 21c, 21d, 21e, and 21f arranged at predetermined positions are inflated. 2 The boring hole 7 is closed. The receiving section 2-a is between the packer 21a and the packer 21b, the receiving section 2-b is between the packer 21b and the packer 21c, and the receiving section 2-c is between the packer 21c and the packer 21d. The receiving section 2-d is formed between the packer 21e and the receiving section 2-e, and the receiving section 2-e is formed between the packer 21e and the packer 21f.
[0016]
Pressure gauges 33a, 33b, 33c, 33d, and 33e are installed in the reception section 2-a, the reception section 2-b, the reception section 2-c, the reception section 2-d, and the reception section 2-e, respectively. The pressure gauges 33a, 33b, 33c, 33d, and 33e are connected to the amplifier 37 and the computer 39 on the ground 1 via the cable 35. The computer 39 measures the water pressure in the receiving section 2-a, the receiving section 2-b, the receiving section 2-c, the receiving section 2-d, and the receiving section 2-e measured by the pressure gauges 33a, 33b, 33c, 33d, and 33e. Is obtained via the amplifier 37.
[0017]
Next, operation | movement of a water path estimation apparatus is demonstrated.
Water is fed from the pump 15 through the hose 13 of the boring machine 19 and an appropriate pressure is applied to the bit 9 by the pressure supply device 17. 1 boring hole 4, no. 3 Drill a bore 5. During excavation, the excavation status is managed and recorded. The excavation status is information such as the drilling depth and time, the drilling water pressure of the boring machine 19, the number of revolutions, the water supply amount, the drainage amount, the supply pressure, the excavation speed, and the like.
[0018]
At the same time, no. 2 On the borehole 7 side, the water pressure in the receiving section 2-a, the receiving section 2-b, the receiving section 2-c, the receiving section 2-d, and the receiving section 2-e is changed to the pressure gauges 33a, 33b, 33c, 33d, Measure at 33e. The computer 39 acquires water pressure change data via the amplifier 37.
[0019]
FIG. 3 is a diagram showing the result of pressure monitoring when the elapsed time is represented on the horizontal axis and the water pressure is represented on the vertical axis. Curves shown in 2-b section 41, 2-c section 43, 2-d section 45, and 2-e section 47 are reception section 2-b, reception section 2-c, reception section 2-d, and reception section 2 respectively. -E shows the time course of the water pressure observed at -e. No. For No. 1 boring drilling 49 (oval mark), no. The time for drilling 1 boring hole 4 is At the time of 3 boring drilling 51 (rectangular mark), no. 3 shows the time for drilling the bore 5.
[0020]
No. 1 boring hole 4 and no. 3 boring holes 5, No. 2 when the water permeability of the ground 101 between the two boring holes 7 is large. 1 boring hole 4, no. No. 3 drilling water fed from the pump 15 to the bit 9 during the drilling of the 3 boring hole 5 flows into the ground 101 and No. 3 A response is seen in the water pressure observed in the receiving section 2-b, the receiving section 2-c, the receiving section 2-d, and the receiving section 2-e.
[0021]
For example, no. At the time of 3 boring drilling 51a, responses are seen in the curves shown in the 2-b section 41, the 2-c section 43, and the 2-d section 45. Therefore, no. In the depth corresponding to 51a at the time of 3 boring drilling, No. It can be estimated that the 3 boring holes 5, the receiving section 2-b, the receiving section 2-c, and the receiving section 2-d have high continuity.
[0022]
Further, the curve shown in the 2-e section 47 has a very small response compared to the curves shown in the other 2-b section 41, 2-c section 43, and 2-d section 45. Therefore, in the receiving section 2-e at the deepest position, No. 1 boring hole 4 and no. It can be determined that the continuity with the 3 boring holes 5 is small.
[0023]
FIG. 3 shows the results of pressure response monitoring when the borehole depth is expressed on the horizontal axis and the water pressure and the water injection pressure are expressed on the vertical axis. Curves shown in 2-b section 53, 2-c section 55, 2-d section 57, and 2-e section 59 are reception section 2-b, reception section 2-c, reception section 2-d, and reception section 2, respectively. The change in the response value of the water pressure observed at −e is shown. The drilling water injection pressure 61 (triangular mark) indicates the drilling water injection pressure of the boring machine 19 at each drilling depth.
[0024]
In FIG. There is a difference in the response value of the water pressure depending on the depth of the 3 boring holes and 5 holes. The greater the pressure response, the No. at that drilling depth. It can be estimated that the water permeability between the 3 boring holes 5 and the receiving section 2-b, the receiving section 2-c, the receiving section 2-d, and the receiving section 2-e is large.
[0025]
In order to verify that the location of the water channel can be estimated by comparing the excavation status of the borehole on the water supply device side and the pressure response at the borehole on the receiver side, a Lugion test was conducted. That is, no. 3 Water is poured from the bore 5 and The pressure response at the two bore holes 7 was observed.
[0026]
FIG. It is a figure which shows the test area which poured water by 3 boring hole. No. 3 The boring hole 5 is closed by a packer or the like (not shown) to form a test section 3-a, a test section 3-b, a test section 3-c, a test section 3-d, and a test section 3-e. . In FIG. 4, these test sections are located at the depths indicated by test section 3-b63, test section 3-c65, test section 3-d67, and test section 3-e69.
[0027]
FIG. No. 2 in the receiving section 2-c and the receiving section 2-d of the boring hole 7. It is a figure which shows the pressure response result observed at the time of 3 boring hole 5 drilling, and a lugion test. The horizontal axis is the pressure side position, and the vertical axis is No. 2 is the response pressure at the borehole 7. The position on the pressure side shown on the horizontal axis is No. 3 is a test section 3-b, a test section 3-c, a test section 3-d, and a test section 3-e on the boring hole 5 side.
[0028]
No. No. 3 when the Lugion test was conducted in each test section of the 3 boring hole 5. Response pressures in the receiving section 2-c and the receiving section 2-d of the two boring holes 7 are shown as response pressures 87c and 87d (broken lines), respectively. No. The response pressures in the receiving section 2-c and the receiving section 2-d when the depth of each test section of the 3 boring hole 5 is cut are shown as response pressures 89c and 89d (broken lines), respectively. In addition, the response pressure of FIG. 6 has shown the value at the time of converting all the pressurization sides into 100 kPa.
[0029]
As shown in FIG. 6, the response pressures 87c and 87d at the time of the lugion test and the response pressures 89c and 89d at the time of drilling show the maximum response values with respect to the pressurization in the test section 3-b. Therefore, in any of the Lujion test and the water channel estimation method of the present embodiment, there is a water channel between the test section 3-b and the reception section 2-c, and between the test section 3-b and the reception section 2-d. It can be estimated that there is.
[0030]
In addition, although the response pressures 87c and 87d at the time of the lugion test decrease with respect to the pressurization in the test section 3-d and the test section 3-e, the response pressures 89c and 89d at the time of drilling increase. And the results do not match. The reason for this is that the injection water during the Lujion test is injected only from the test section blocked by the packer, whereas the drilling water during boring has a flow that returns to the ground, so the section is shallower than the drilling depth. It is considered that drilling water flows into the bedrock. In this case, as shown in FIG. 4, there is a section with a large pressure response near the depth of 24 m above the test section 3-d67, that is, a section where water permeability can be estimated to be large. It can be estimated that it was affected by the inflow.
[0031]
As described above, in the water channel estimation device A, No. 1 is drilling with the boring machine 19 as a water feeding device. 1 boring hole 4, no. Since the 3-boring hole 5 is used and the pressure response to the drilling water is observed, a result equivalent to the conventional water permeability test can be obtained in a short time. Moreover, since the water supply device can be simplified, it is economical.
[0032]
In this embodiment, as the water channel estimation device A, three boring holes are arranged on a straight line, and the two boring holes that are water feeding devices are drilled almost simultaneously, but the number and positions of the boring holes This does not apply to the drilling time of water supply equipment. There shall be at least one water supply device for one receiving device. In the case of using a plurality of water feeding devices, it is possible to estimate the water channel efficiently and accurately by appropriately planning the hole arrangement and the drilling order. Moreover, the receiving section formed in the boring hole used as a receiving device can be set to an arbitrary quantity or position.
[0033]
Furthermore, in addition to the method of estimating the position of the water path by comparing the drilling water pressure of the boring machine 19 and the response pressure in the receiving section, the water supply amount, drainage amount, supply pressure, rotation speed, excavation speed, etc. of the boring machine 19 The method of using the data of can be considered.
[0034]
In the tests whose results are shown in FIGS. 3 to 6, as shown in FIG. 1 borehole 4 is in the mudstone dominant layer 81, Two boreholes 7 are formed in the mudstone dominating layer 81 and conglomerate 83, The three boreholes 5 are located in the conglomerate 83 layer and the sandstone dominant layer 85. When it was difficult to maintain the hole wall in the bare hole, a PVC casing was installed in the borehole.
[0035]
FIG. 7 is an enlarged cross-sectional view in the vicinity of the receiving section or test section in the borehole where the PVC pipe 97 is installed. A PVC pipe 97 is inserted into the borehole, and a strainer 93 is disposed at a position corresponding to the reception section or the test section. Between the PVC pipe 97 and the surrounding rock mass 99 is bentonite pellet 91, and between the strainer 93 and the upper and lower portions of the PVC pipe 97 and the surrounding rock mass 99 is filled with silica sand 95.
[0036]
【The invention's effect】
As described above in detail, according to the present invention, it is possible to provide a water channel estimation method and a water channel estimation device capable of obtaining results equivalent to a simple permeability test economically in a short time.
[Brief description of the drawings]
FIG. 1 is a schematic diagram of a water channel estimation device A. FIG. 2 is a cross-sectional view showing a process of installing a packer and a pressure gauge in a borehole 3. FIG. 3 is a diagram showing the results of pressure monitoring. FIG. 5 shows the results. 3 is a diagram showing a test section in which water is injected through the bore 5; No. 2 in the receiving section 2-c and the receiving section 2-d of the boring hole 7. Fig. 7 shows the pressure response results observed during drilling of 5 bore holes and during the Lugion test. Fig. 7 is an enlarged cross-sectional view of the receiving section or the vicinity of the test section in the bore hole where the PVC pipe 97 is installed. Schematic diagram of inter-permeability test equipment 【Explanation of symbols】
1 ……… Ground 4 ……… No. 1 boring hole 5 3 boring hole 7 2 boring hole 9 ... bit 15 ... pump 19 ... boring machine 21a, 21b, 21c, 21d, 21e, 21f ... packer 33a, 33b, 33c, 33d, 33e ... pressure gauge 87c, 87d, 89c, 89d ... …… Response pressure

Claims (9)

地盤に第1のボーリング孔を削孔し、
前記第1のボーリング孔内の所定の部分をパッカで閉塞して、圧力計が設けられた受信区間を形成し、
ボーリング機械で第2のボーリング孔を削孔して掘進状況を記録しつつ、前記圧力計を用いて前記受信区間での水圧を取得することを特徴とする水みち推定方法。
Drill the first boring hole in the ground,
A predetermined portion in the first boring hole is closed with a packer to form a receiving section provided with a pressure gauge,
A water channel estimation method, wherein a water pressure in the receiving section is acquired using the pressure gauge while recording a state of excavation by drilling a second boring hole with a boring machine.
前記掘進状況は、前記ボーリング機械の削孔深度と時間、削孔水圧力、回転数、送水量、排水量、給圧、掘進速度のうち少なくともいずれかを含むことを特徴とする請求項1記載の水みち推定方法。The drilling condition includes at least one of a drilling depth and time, a drilling water pressure, a rotation speed, a water supply amount, a drainage amount, a supply pressure, and a drilling speed of the boring machine. Water path estimation method. 前記掘進状況のうち、前記削孔水圧力と、前記水圧とを比較して水みちの位置を推定することを特徴とする請求項2記載の水みち推定方法。The water channel estimation method according to claim 2, wherein the position of the water channel is estimated by comparing the drilling water pressure and the water pressure in the excavation state. 前記受信区間が、前記第1のボーリング孔内の複数箇所に形成されることを特徴とする請求項1記載の水みち推定方法。The method according to claim 1, wherein the receiving section is formed at a plurality of locations in the first boring hole. 少なくとも1本の前記第2のボーリング孔を削孔することを特徴とする請求項1記載の水みち推定方法。2. The water channel estimation method according to claim 1, wherein at least one second boring hole is drilled. 地盤内に削孔された第1のボーリング孔をパッカで閉塞して形成された受信区間に設けられた圧力計と、
前記地盤内に第2のボーリング孔を削孔するボーリング機械と、
前記圧力計を用いて測定された水圧および前記ボーリング機械の掘進状況を取得するデータ取得手段と、
を具備し、
前記水圧と前記掘進状況とを比較して、前記第1のボーリング孔と前記第2のボーリング孔との間の水みちの位置を推定することを特徴とする水みち推定装置。
A pressure gauge provided in the receiving section formed by closing the first boring hole drilled in the ground with a packer;
A boring machine for drilling a second boring hole in the ground;
Data acquisition means for acquiring the water pressure measured using the pressure gauge and the drilling status of the boring machine;
Comprising
A water channel estimation apparatus that compares the water pressure with the excavation status and estimates a position of a water channel between the first bore hole and the second bore hole.
前記掘進状況は、前記ボーリング機械の削孔深度と時間、削孔水圧力、回転数、送水量、排水量、給圧、掘進速度のうち少なくともいずれかを含むことを特徴とする請求項6記載の水みち推定装置。The drilling status includes at least one of a drilling depth and time, a drilling water pressure, a rotation speed, a water supply amount, a drainage amount, a supply pressure, and a drilling speed of the boring machine. Water path estimation device. 前記受信区間が、前記第1のボーリング孔内の複数箇所に形成されたことを特徴とする請求項6記載の水みち推定装置。The water channel estimation device according to claim 6, wherein the reception section is formed at a plurality of locations in the first boring hole. 少なくとも1本の前記第2のボーリング孔が削孔されることを特徴とする請求項6記載の水みち推定装置。The water channel estimation apparatus according to claim 6, wherein at least one of the second bore holes is drilled.
JP2001327270A 2001-10-25 2001-10-25 Water path estimation method and water path estimation device Expired - Fee Related JP3764668B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001327270A JP3764668B2 (en) 2001-10-25 2001-10-25 Water path estimation method and water path estimation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001327270A JP3764668B2 (en) 2001-10-25 2001-10-25 Water path estimation method and water path estimation device

Publications (2)

Publication Number Publication Date
JP2003129782A JP2003129782A (en) 2003-05-08
JP3764668B2 true JP3764668B2 (en) 2006-04-12

Family

ID=19143522

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001327270A Expired - Fee Related JP3764668B2 (en) 2001-10-25 2001-10-25 Water path estimation method and water path estimation device

Country Status (1)

Country Link
JP (1) JP3764668B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5565751B2 (en) * 2010-06-03 2014-08-06 株式会社大林組 Water channel detection system and method in bedrock
JP6961525B2 (en) * 2018-03-29 2021-11-05 鹿島建設株式会社 How to evaluate the permeability of the ground
CN109448532B (en) * 2018-11-06 2021-01-08 宁波大学 Starting tunneling model test platform of mechanical method connection channel tunneling machine and test method thereof
CN109668747B (en) * 2018-11-06 2021-01-08 宁波大学 Mechanical method connection channel heading machine receiving model test platform and test method thereof

Also Published As

Publication number Publication date
JP2003129782A (en) 2003-05-08

Similar Documents

Publication Publication Date Title
US10465471B2 (en) Treatment methods for water or gas reduction in hydrocarbon production wells
US10612306B2 (en) Optimized production via geological mapping
CA2488783C (en) Method for in-situ analysis of formation parameters
US8286476B2 (en) Downhole 4D pressure measurement apparatus and method for permeability characterization
US9063250B2 (en) Interference testing while drilling
KR101773868B1 (en) Trace test system and method in an unsaturated zone aquifer
JP6929179B2 (en) Hydraulic characterization method
US7765862B2 (en) Determination of formation pressure during a drilling operation
JP4006884B2 (en) Groundwater status logging method and device
JP3764668B2 (en) Water path estimation method and water path estimation device
CA2977216C (en) Surface excitation ranging methods and systems employing a ground well and a supplemental grounding arrangement
CA2976352C (en) Surface excitation ranging methods and systems employing a customized grounding arrangement
US20210381363A1 (en) Relative permeability estimation methods and systems employing downhole pressure transient analysis, saturation analysis, and porosity analysis
CN108930534B (en) Method and device for correcting temperature influence of nuclear magnetic resonance formation while drilling
JP2626456B2 (en) Rock permeability test equipment
GB2391944A (en) Determination of relative permeability from saturation level measurements in a borehole
Deady et al. Applications For Formation Testing While Drilling In the Middle East

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040617

TRDD Decision of grant or rejection written
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060111

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060117

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060120

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120127

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150127

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees