JP3749374B2 - Building construction method using existing piles - Google Patents

Building construction method using existing piles Download PDF

Info

Publication number
JP3749374B2
JP3749374B2 JP07003098A JP7003098A JP3749374B2 JP 3749374 B2 JP3749374 B2 JP 3749374B2 JP 07003098 A JP07003098 A JP 07003098A JP 7003098 A JP7003098 A JP 7003098A JP 3749374 B2 JP3749374 B2 JP 3749374B2
Authority
JP
Japan
Prior art keywords
existing
pile
building
piles
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP07003098A
Other languages
Japanese (ja)
Other versions
JPH11264247A (en
Inventor
昇昭 伊勢本
高志 光成
治 金子
美敏 保井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP07003098A priority Critical patent/JP3749374B2/en
Publication of JPH11264247A publication Critical patent/JPH11264247A/en
Application granted granted Critical
Publication of JP3749374B2 publication Critical patent/JP3749374B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は既設杭を利用した建物の構築方法に関するものである。
【0002】
【従来の技術】
場所打ち杭は低騒音、低振動の施工が可能なことから市街地において非常に多く使用されている。このような建物を建て替える場合は、既設杭の通り芯を避けて新設杭を打設したり、既設杭を図3に示すような方法で解体したりしている。今後、このような場所打ち杭10を使用した建物の建て替え需要は益々増えることが確実視されている。
【0003】
【発明が解決しようとする課題】
しかし、上記のように建物を建て替える場合に、既設杭の通り芯を避けて新設杭を打設したり、既設杭を図3に示すような方法で解体したりすると、コスト高になるばかりでなく、解体に伴う騒音、振動、廃棄物などの環境問題が生じていた。
【0004】
本発明は、このような問題に鑑みてなされたものであり、その目的は、建物を建て替える場合に、既設杭の通り芯を避けて新設杭を打設したり、既設杭を解体したりせずに建物を構築することである。
【0005】
【課題を解決するための手段】
以上の課題を解決するための手段は、請求項1の発明が、既存建物における所定の既設杭の頭部を所定長さ切断して基礎スラブと縁切りし、該縁切りした基礎スラブと既設杭の間にジャッキを設置して前記基礎スラブを反力として載荷試験を行って既設杭の支持力を確認した後、前記基礎スラブを含む上部躯体を撤去するとともに地盤を所定の深さ掘削して既設杭の杭頭処理を行い、これらの既設杭上に所定厚さのマットスラブを構築して新たな建物を構築することを特徴とする。
【0006】
請求項1の発明によれば、既存杭が有効利用できるので、資源の有効利用が図れるとともに、既存杭の解体によるコストやエネルギーの低減、および既存杭の解体に伴う振動、騒音、廃棄物等の環境悪化の防止を図ることができる。また既設杭上に所定厚さのマットスラブを構築して新たな建物を構築することにより、柱と杭の位置関係が自由になる。
【0007】
また請求項2の発明が、請求項1において、前記既設杭の近傍に新設杭を打設することを特徴とする。
【0008】
請求項2の発明によれば、支持力が不足する場合に、新設杭の増打ちをすることにより、経費を低く押さえかつ簡単な方法で必要な支持力を得ることができる。
【0009】
また請求項3の発明が、請求項1において、前記既設杭の頭部は一部を切断して撤去するごとにジャッキを設置し、該ジャッキによって仮り受けすることを特徴とする。
【0010】
請求項3の発明によれば、杭頭部を一度に切断することなく、一部づつ切断してジャッキを据え付けることにより、ジャッキが容易に据え付けられる。
【0011】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて説明する。図1は既存建物の基礎の断面図、図2の(1)は既存杭の杭頭部の高さを揃えた断面図、同図の(2)は杭頭部にマットスラブを形成した断面図、同図の(3)はマットスラブ上に新たな建物を構築した断面図である。
【0012】
図1に示す建物は、場所打ちコンクリート杭(以下既存杭)で支持された既存建物であり、この上部の躯体は解体するが、既存杭は解体せずにそのまま利用して新たな建物を構築するものである。
【0013】
はじめに、図1に示すように、基礎スラブ1から約2mまで地盤2を掘削して所定の既存杭(数カ所)3の杭頭部3aを露出させる。そして杭頭部3aの一部をワイヤーソーで切断して基礎スラブ1と縁切りし、該縁切りした部分にジャッキ4を設置する。このジャッキ4は、杭頭部3aの一部、すなわち平面視において約半分を削り取って一基を設置するとともに、残り半分を削り取って他の一基を設置して上部躯体5を仮り受けする。このとき既設杭3と基礎スラブ1は縁切りされ、ジャッキ4の上部が基礎スラブ1に接した状態になっている。
【0014】
このように杭頭部3aにジャッキ4を設置したら、基礎スラブ1に反力をとって載荷試験を行って既設杭3の支持力を確認する。既設杭3は地中に埋設されているため施工後長期間、例えば30年以上経過した杭であっても圧縮強度は新設杭とほとんど変わらず、中性化深さも1mm単位のわずかなものであり、ひび割れもほとんど見られないため十分な支持力を保持していることが確認できる。このような載荷試験を適当な本数の既設杭3で行って全ての既設杭3が十分な支持力を備えているとみなすことにより、全体として十分な支持力を保持していることを推認する。
【0015】
そして、既設杭3が十分な支持力を保持していることを確認したら、図2の(1)に示すように、上部躯体5を解体撤去する。このとき、所定の既設杭3の支持力が不足していたら、同図に示すように、既設杭3の近傍に増杭6を打設して不足分の支持力を補う。
【0016】
次に、同図の(2)に示すように、地盤2を所定の深さ掘削するとともに、既設杭3の杭頭処理を行って高さを揃える。そして、これらの杭頭部3aの上に所定の厚さのマットスラブ7を構築して剛性を強める。また高さが揃わない場合は、ワイヤーソー等を用いて揃えることができるので、設計上の対応が簡単にできる。
【0017】
そして、同図の(3)に示すように、マットスラブ7上に新たな建物8を構築するが、マットスラブ7を介して既設杭3で支持されているため、柱9と既設杭3の位置関係が自由、すなわち、ずれた状態になっても剛性と耐力を有するマットスラブ7を介して既設杭3に力が伝わる。
【0018】
このように本発明は、従来なら既設杭3を全て撤去するか、あるいはそのままにして既設杭3の通り芯をよけて新設杭を打設していたのに比べて、非常に簡単な方法で建て替えをすることができる。
【0019】
【発明の効果】
既存杭が有効利用できるので、資源の有効利用が図れるとともに、既存杭の解体によるコストやエネルギーの低減、および既存杭の解体に伴う振動、騒音、廃棄物等の環境悪化の防止を図ることができる。
【0020】
既設杭上に所定厚さのマットスラブを構築して新たな建物を構築することにより、柱と杭の位置関係が自由になる。
【0021】
支持力が不足する場合に、新設杭の増打ちをすることにより、経費を低く押さえかつ簡単な方法で必要な支持力を得ることができる。
【0022】
杭の支持力試験を行うときに、杭頭部を一度に切断することなく、一部づつ切断してジャッキを据え付けることにより、ジャッキが容易に据え付けられる。また地下深さに応じて杭頭の高さを自由に設定できるので、設計上の対応が簡単である。
【図面の簡単な説明】
【図1】杭頭部と基礎スラブの間にジャッキを据え付けた状態の断面図である。
【図2】(1)は新設杭を増打ちした断面図、(2)は杭頭部にマットスラブを構築した断面図、(3)はマットスラブに新たな建物を構築した断面図である。
【図3】(1)〜(3)は従来の建物の建て替え方法を示す断面図である。
【符号の説明】
1 基礎スラブ
2 地盤
3 既設杭
4 ジャッキ
5 上部躯体
6 増杭
7 マットスラブ
8 建物
9 柱
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a building construction method using existing piles.
[0002]
[Prior art]
Cast-in-place piles are widely used in urban areas because they can be constructed with low noise and vibration. When rebuilding such a building, avoiding the core of the existing pile, placing a new pile, or dismantling the existing pile by the method shown in FIG. In the future, it is expected that the demand for rebuilding buildings using such cast-in-place piles 10 will increase more and more.
[0003]
[Problems to be solved by the invention]
However, when rebuilding a building as described above, avoiding the core of the existing pile and placing a new pile, or dismantling the existing pile using the method shown in FIG. However, environmental problems such as noise, vibration and waste associated with dismantling occurred.
[0004]
The present invention has been made in view of such problems, and the purpose of the present invention is to, when rebuilding a building, avoid the core of existing piles, place new piles, or dismantle existing piles. Without building a building.
[0005]
[Means for Solving the Problems]
Means for solving the above problems is that the invention according to claim 1 is that the head of a predetermined existing pile in an existing building is cut to a predetermined length to be edge-cut from the foundation slab, and the edge-cut foundation slab and the existing pile are After installing a jack between the foundation slabs and performing a loading test to confirm the supporting force of the existing piles, the upper frame including the foundation slabs was removed and the ground was excavated to a predetermined depth. Pile head processing of piles is performed, and a mat slab having a predetermined thickness is constructed on these existing piles to construct a new building.
[0006]
According to the invention of claim 1, since existing piles can be used effectively, resources can be used effectively, cost and energy can be reduced by dismantling existing piles, and vibration, noise, waste, etc. associated with dismantling existing piles Can prevent environmental degradation. In addition, by constructing a new building by constructing a mat slab of a predetermined thickness on an existing pile, the positional relationship between the pillar and the pile becomes free.
[0007]
The invention of claim 2 is characterized in that, in claim 1, a new pile is driven in the vicinity of the existing pile.
[0008]
According to the second aspect of the present invention, when the supporting force is insufficient, the necessary supporting force can be obtained by a simple method while keeping the cost low by increasing the number of new piles.
[0009]
The invention of claim 3 is characterized in that, in claim 1, the head of the existing pile is installed with a jack each time a part is cut and removed, and the head is temporarily received by the jack.
[0010]
According to invention of Claim 3, a jack is easily installed by cut | disconnecting a pile head part by cutting one by one, and cutting a pile head part at a time.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings. 1 is a cross-sectional view of the foundation of an existing building, (1) in FIG. 2 is a cross-sectional view in which the heights of the pile heads of existing piles are aligned, and (2) in the same figure is a cross-section in which a mat slab is formed on the pile head. The figure (3) is a sectional view in which a new building is constructed on the mat slab.
[0012]
The building shown in Fig. 1 is an existing building supported by cast-in-place concrete piles (hereinafter referred to as existing piles). The upper frame is dismantled, but the existing piles are used without being dismantled to construct a new building. To do.
[0013]
First, as shown in FIG. 1, the ground 2 is excavated from the foundation slab 1 to about 2 m, and the pile heads 3a of predetermined existing piles (several places) 3 are exposed. Then, a portion of the pile head 3a is cut with a wire saw and cut off with the foundation slab 1, and the jack 4 is installed at the cut edge. The jack 4 scrapes a part of the pile head 3a, that is, about half in plan view and installs one, and scrapes the other half and installs another to temporarily receive the upper casing 5. At this time, the existing pile 3 and the foundation slab 1 are cut off, and the upper part of the jack 4 is in contact with the foundation slab 1.
[0014]
When the jack 4 is thus installed on the pile head 3a, a reaction test is performed on the foundation slab 1 to check the supporting force of the existing pile 3. Since the existing pile 3 is buried in the ground, the compressive strength is almost the same as that of the new pile even if it is a long-term pile after construction, for example, 30 years or more, and the neutralization depth is only 1mm. There are almost no cracks, so it can be confirmed that sufficient support force is maintained. By carrying out such a loading test with an appropriate number of existing piles 3 and assuming that all the existing piles 3 have sufficient supporting force, it is estimated that the entire supporting force is maintained as a whole. .
[0015]
And if it confirms that the existing pile 3 has hold | maintained sufficient support force, as shown to (1) of FIG. 2, the upper frame 5 will be dismantled and removed. At this time, if the supporting force of the predetermined existing pile 3 is insufficient, as shown in the figure, the additional pile 6 is driven in the vicinity of the existing pile 3 to supplement the insufficient supporting force.
[0016]
Next, as shown to (2) of the figure, while excavating the ground 2 to predetermined depth, the pile head process of the existing pile 3 is performed and the height is arrange | equalized. And the mat | matte slab 7 of predetermined thickness is built on these pile heads 3a, and rigidity is strengthened. In addition, when the heights are not aligned, it can be aligned using a wire saw or the like, so that the design can be easily handled.
[0017]
And as shown to (3) of the figure, although the new building 8 is constructed | assembled on the mat slab 7, since it is supported by the existing pile 3 via the mat slab 7, the pillar 9 and the existing pile 3 of The force is transmitted to the existing pile 3 through the mat slab 7 having rigidity and proof strength even if the positional relationship is free, that is, shifted.
[0018]
As described above, the present invention is a much simpler method compared to the case where the existing piles 3 are all removed or the new piles are driven away from the cores of the existing piles 3 as they are. Can be rebuilt.
[0019]
【The invention's effect】
Since existing piles can be used effectively, resources can be used effectively, costs and energy can be reduced by dismantling existing piles, and environmental degradation such as vibration, noise, and waste associated with dismantling existing piles can be prevented. it can.
[0020]
By building a mat slab of a predetermined thickness on an existing pile and building a new building, the positional relationship between the pillar and the pile becomes free.
[0021]
When the supporting force is insufficient, by increasing the number of new piles, the necessary supporting force can be obtained in a simple manner while keeping costs low.
[0022]
When the pile bearing force test is performed, the jack can be easily installed by cutting the pile heads one by one and installing the jacks without cutting the pile head at a time. Moreover, the height of the pile head can be set freely according to the underground depth, so the design is easy to handle.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view of a state where a jack is installed between a pile head and a foundation slab.
FIGS. 2A and 2B are cross-sectional views in which a newly built pile is added, FIG. 2B is a cross-sectional view in which a mat slab is built on the pile head, and FIG. 3C is a cross-sectional view in which a new building is built on the mat slab. .
FIGS. 3A to 3C are cross-sectional views showing a conventional method of rebuilding a building.
[Explanation of symbols]
1 Foundation slab 2 Ground 3 Existing pile 4 Jack 5 Upper frame 6 Additional pile 7 Mat slab 8 Building 9 Column

Claims (3)

既存建物における所定の既設杭の頭部を所定長さ切断して基礎スラブと縁切りし、該縁切りした基礎スラブと既設杭の間にジャッキを設置して前記基礎スラブを反力として載荷試験を行って既設杭の支持力を確認した後、前記基礎スラブを含む上部躯体を撤去するとともに地盤を所定の深さ掘削して既設杭の杭頭処理を行い、これらの既設杭上に所定厚さのマットスラブを構築して新たな建物を構築することを特徴とする既設杭を利用した建物の構築方法。The head of a pre-existing pile in an existing building is cut to a predetermined length and edged with the foundation slab, and a jack is installed between the foundation slab and the existing pile, and the loading test is performed using the foundation slab as a reaction force. After confirming the bearing capacity of the existing piles, the upper frame including the foundation slab is removed and the ground is excavated to a predetermined depth to perform pile head treatment of the existing piles. A building construction method using existing piles, characterized by building a mat slab and building a new building. 前記既設杭の近傍に新設杭を打設することを特徴とする請求項1に記載の既設杭を利用した建物の構築方法。The building construction method using the existing pile according to claim 1, wherein a new pile is driven in the vicinity of the existing pile. 前記既設杭の頭部は一部を切断して撤去するごとにジャッキを設置し、該ジャッキによって仮り受けすることを特徴とする請求項1に記載の既設杭を利用した建物の構築方法。2. The building construction method using an existing pile according to claim 1, wherein a head is installed every time the head of the existing pile is cut and removed, and the jack is temporarily received by the jack.
JP07003098A 1998-03-19 1998-03-19 Building construction method using existing piles Expired - Fee Related JP3749374B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07003098A JP3749374B2 (en) 1998-03-19 1998-03-19 Building construction method using existing piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07003098A JP3749374B2 (en) 1998-03-19 1998-03-19 Building construction method using existing piles

Publications (2)

Publication Number Publication Date
JPH11264247A JPH11264247A (en) 1999-09-28
JP3749374B2 true JP3749374B2 (en) 2006-02-22

Family

ID=13419799

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07003098A Expired - Fee Related JP3749374B2 (en) 1998-03-19 1998-03-19 Building construction method using existing piles

Country Status (1)

Country Link
JP (1) JP3749374B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146809A (en) * 2000-11-07 2002-05-22 Taisei Corp Construction method for structure
JP2006037633A (en) * 2004-07-29 2006-02-09 Taisei Corp Foundation structure and construction method thereof
JP4502797B2 (en) * 2004-12-20 2010-07-14 株式会社竹中工務店 Vertical loading test method for existing piles
JP2013245450A (en) * 2012-05-24 2013-12-09 Mase Kensetsu Kk Existing pile bearing force regenerating and sinking correction method
CN103147469B (en) * 2013-03-28 2015-04-29 中国建筑第八工程局有限公司 Vertical compression-resistance static load test method for foundation pile of high-rise building
JP6166574B2 (en) * 2013-04-04 2017-07-19 株式会社竹中工務店 Building design method
CN104314316B (en) * 2014-11-20 2016-05-11 中建六局土木工程有限公司 A kind of special-shaped leg post supports construction method of installation

Also Published As

Publication number Publication date
JPH11264247A (en) 1999-09-28

Similar Documents

Publication Publication Date Title
JP3749374B2 (en) Building construction method using existing piles
JP4624867B2 (en) Seismic isolation repair method for existing buildings
JP5485085B2 (en) Axial force replacement method for existing piles
JP3692805B2 (en) Seismic isolation method for existing buildings
JP3706997B2 (en) Base seismic isolation method for existing buildings
JPH09184144A (en) Construction method for base isolation pit for existing building
JP4067688B2 (en) Construction method of seismic isolation structure
JP2989539B2 (en) Existing building seismic isolation method
JP2001271497A (en) Temporary bearing construction method for existing building
JPH11310928A (en) Vibration isolation reinforcing method for existing structure
JP4789549B2 (en) Reconstruction method for existing buildings
JP2002309593A (en) Method of base-isolating existing building
JP4313871B2 (en) Method for sunk body and sunk body
JP3407168B2 (en) Foundation of new building using existing pile foundation
JPH09170338A (en) Base isolation method for existing building
JP3648670B2 (en) Seismic isolation device installation method for existing foundation deep piles
JPH09170339A (en) Base isolation method for existing building
JPH09317208A (en) Base isolation construction method for existing wooden house
JP2011017187A (en) Base-isolating method for existing building
JP4195406B2 (en) Seismic isolation method for existing building and seismic isolation building
JP3740607B2 (en) Building provisional receiving method and structure
JP5123967B2 (en) Seismic isolation method
JP2019157508A (en) Under-ground piled column and seismic base-isolated buildings
KR20060108122A (en) Structure and construction method thereof of foundation
JPH11166242A (en) Underground space constructing method and supporting structure in underground space construction

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20051108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051124

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051201

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081209

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091209

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091209

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101209

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121209

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121209

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151209

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees