JP3745027B2 - Deep foundation and its forming method, eccentric prevention metal fittings and inner mold fixing metal fittings used for them - Google Patents
Deep foundation and its forming method, eccentric prevention metal fittings and inner mold fixing metal fittings used for them Download PDFInfo
- Publication number
- JP3745027B2 JP3745027B2 JP15601296A JP15601296A JP3745027B2 JP 3745027 B2 JP3745027 B2 JP 3745027B2 JP 15601296 A JP15601296 A JP 15601296A JP 15601296 A JP15601296 A JP 15601296A JP 3745027 B2 JP3745027 B2 JP 3745027B2
- Authority
- JP
- Japan
- Prior art keywords
- inner mold
- shaft
- forming
- deep foundation
- metal fitting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
この発明は、山間地における送電鉄塔、橋等の脚部を支持するのに好適な深礎基礎とその形成方法及びこれらに使用する偏心防止金具と内型枠固定金具に関するものである。
【0002】
【従来の技術】
図22は送電鉄塔の脚部を支持する深礎基礎の従来例を示す縦断面図である。同図において、10は立坑であり、立坑10は地面から下方に垂直に掘削形成された円筒状の上部立坑12と、上部立坑12の底部から更に下方に垂直に掘削形成された円筒状の下部立坑14とからなる。
【0003】
下部立坑14は上部立坑12の直径より径が小さく、その中心は上部立坑12の直下から水平方向(同図では左側)に若干ずれた位置に形成されている。上部立坑12の上縁部の周囲にはリング状の上部支え16が設けられ、上部立坑12の底部で下部立坑14の上縁部の周囲にはリング状の中間支え18が設けられている。上部支え16及び中間支え18はいずれもコンクリートによって形成されている。
【0004】
上部立坑12の内壁及び下部立坑14の内壁は筒状に連結されたライナープレート(薄鋼板を波付け加工し、周囲にフランジを形成させた鋼材)からなる型枠20,22によって各々被覆されている。上部立坑12の内壁を被覆している型枠20は上部支え16によって側方から吊り下げられるようにして支えられている。下部立坑14の内壁を被覆している型枠22は中間支え18によって吊り下げられるようにして支えられている。
【0005】
下部立坑14の内部には円柱状の鉄筋コンクリート構造体からなる基礎本体24が下部立坑14を満たすように形成されており、その上部には例えば電力鉄塔の脚部(図示せず)の下端部を接続するための脚材26がその接続端を上部に露出させた状態で埋設・設置されている。
【0006】
この深礎基礎は例えば次のようにして形成される。すなわち、形成すべき上部立坑12の径より若干大き目の穴を、ライナープレート1〜3リング分程度の深さまで掘り、この穴の中で型枠20を筒状に組み立てる。型枠20を組み立てた後、型枠20の水平度、真円度を確認し、型枠20と地山28との間にコンクリートを打設する。打設されたコンクリートは硬化して上部支え16となり、型枠20の上方は周囲の地山28に固定される。
【0007】
コンクリートが硬化して、型枠20の上方が周囲の地山28に固定された後、穴を更に下方に掘削し、型枠20を更に下方に継ぎ足していく。ここで、地山28の崩壊を防ぐために穴をあまり大きく掘削せず、継ぎ足し可能な範囲で穴を掘削し、型枠20を継ぎ足す。また、型枠20は軸継目が縦方向に通らないように、交互(千鳥状)に組み立て、全体の強度を低下させないようにする。以上の作業によって上部立坑12が形成される。
【0008】
次に、上部立坑12より径の小さい穴を、その中心が上部立坑12の中心から水平方向(同図では左側)に若干ずれるように、ライナープレート1〜3リング分程度の深さまで掘り、この穴の中で型枠22を筒状に組み立てる。型枠22を組み立てた後、型枠22の水平度、真円度を確認し、型枠22と地山28との間にコンクリートを打設する。ここで、打設されたコンクリートは硬化して中間支え18となり、型枠22の上縁部は周囲の地山28に固定される。
【0009】
コンクリートが硬化して、型枠22の上縁部が周囲の地山28に固定された後、穴を更に下方に掘削し、型枠22を更に下方に継ぎ足していく。ここでも、地山28の崩壊を防ぐために穴をあまり大きく掘削せず、継ぎ足し可能な範囲で穴を掘削し、型枠22を上部立坑12の場合と同様に継ぎ足す。以上の作業を繰り返すことにより下部立坑14が形成される。
【0010】
次に、下部立坑14の床盤(底部)に配筋するとともに、床盤近くの下部立坑14の内壁に配筋し、生コンクリートを打設する。そして、下部立坑14の内壁に下方から上方に向けて配筋しながら、生コンクリートを上方に向けて順次打設していく。下部立坑14の上部空間が少し残った段階で、電力鉄塔の脚部の下端部を接続するための脚材26を斜めに設置し、下部立坑14の上部空間を生コンクリートで完全に満たして脚材26の基部を基礎本体24に埋設する。
【0011】
なお、上述した例では、立坑を上部立坑12と下部立坑14の2つに分け、下部立坑14の径を上部立坑12の径より若干小さくしているが、これは、1つの立坑で斜めの脚材26が埋設されるように立坑を形成すると、立坑の底の方では斜めの脚材26が埋設されるために必要とされる以上に立坑を広く形成することになるので、立坑の掘削作業の軽減化を図るためにこのようにしたのである。
【0012】
【発明が解決しようとする課題】
ところで、深礎基礎を形成するために立坑を掘削すると、立坑の空間を占めていた大量の土砂や岩石が残土として排出される。送電鉄塔用の深礎基礎を形成するような山間僻地は急傾斜地が多いので、この残土をそのまま立坑の周囲に放置しておくと、残土が雨水によって流出して河川を汚染したり、崩壊して危険なので、どこか安全な場所へ運んで残土処理をしなければならない。
【0013】
残土処理のできる場所が立坑の近くに確保できれば好都合であるが、多くの場合は立坑から離れた場所になってしまう。そして、送電鉄塔用の深礎基礎を形成するような場所は上述したように山間僻地が多いので、残土を輸送するための道路が無い場合が多く、ヘリコプターで残土を運ばなければならない。このため、残土の輸送のために多大な費用がかかるという問題があった。
【0014】
また、残土処理のできる場所でも、残土をそのまま投棄すると、残土が雨水によって流出して河川を汚したり、残土が崩壊して危険なので、雨水による残土の流出を防止したり、残土の崩壊を防止するために、水抜き、表面緑化、土留等の保全工事をしておかなければならない。このため、この残土の保全対策のためにも多大な費用がかかるという問題があった。
【0015】
この発明は、処理しなければならない残土の量をできるだけ減らして、上述したような諸費用を減らすようにした深礎基礎とその形成方法及びこれらに使用する偏心防止金具と内型枠固定金具を提供することを目的とする。
【0016】
【課題を解決するための手段】
本発明に係る深礎基礎は、立坑の内部を満たしている柱状の鉄筋コンクリート構造体からなる基礎本体と、該基礎本体の内部に該基礎本体と略同軸に形成されている柱状の中空部と、該中空部内に充填されている土砂とを有しているものである。
【0017】
ここで、前記基礎本体は、前記立坑の床盤から前記中空部の下端部の高さまで該立坑内を満たしている下部ベース部と、該下部ベース部から上方へ延設されて前記中空部を側方から囲んでいる側壁部と、該側壁部から上方へ延設されて所定の高さまで該立坑内を満たしている上部ベース部とから構成されている。そして、該上部ベース部には、固定すべき脚部の下端部を接続するための脚材がその接続端を露出させた状態で埋設・設置されている。
【0018】
また、前記立坑と前記コンクリート構造体との間には外型枠が設けられ、前記中空部と前記土砂との間には内型枠が設けられている。前記外型枠としてはライナープレート又はコルゲートパイプを使用することができ、前記内型枠としてはコルゲートパイプ又はライナープレートを使用することができるが、内型枠としては高張力シート又はエアーバックを使用することも可能である。なお、前記土砂としては前記立坑を掘削した際に出た残土が好ましいことは勿論である。
【0019】
また、本発明に係る深礎基礎の形成方法は、立坑を掘削しながら該立坑の内側に外型枠を組立てる工程と、該立坑の床盤上に生コンクリートを所定高さまで打設して下部ベース部を形成する工程と、該下部ベース部の上に内型枠を該外型枠と略同軸に組立てる工程と、該内型枠内へ土砂を充填する工程と、該外型枠と該内型枠との間に生コンクリートを打設して側壁部を形成する工程と、該側壁部の上に生コンクリートを所定高さまで打設して上部ベース部を形成する工程とを有しているものである。
【0020】
ここで、前記内型枠内へ土砂を充填する工程と、前記外型枠と前記内型枠との間に生コンクリートを打設して前記側壁部を形成する工程は、どちらが先になっても良い。すなわち、前記内型枠内へ土砂を充填した後、前記外型枠と前記内型枠との間に生コンクリートを打設して前記側壁部を形成してもよいし、前記外型枠と前記内型枠との間に生コンクリートを打設して前記側壁部を形成した後に、前記内型枠内へ土砂を充填してもよい。
【0021】
また、前記下部ベース部を形成する工程が前記立坑の床盤上の空間に配筋する工程を、前記側壁部を形成する工程が前記外型枠の内側に沿って配筋する工程を、前記上部ベース部を形成する工程が前記内型枠の上方空間に配筋する工程を各々有している。前記上部ベース部を形成する際に、固定すべき脚部の下端部を接続するための脚材をその接続端を露出させた状態で前記上部ベース部に埋設・設置する。
【0022】
また、前記立坑の外において前記内型枠を所定高さの小ブロックに組み立て、この小ブロックの内型枠を該立坑内で組み立ててもよい。また、先に組み立てられた内型枠の小ブロックの上端部の波と、後から継ぎ足して行く内型枠の小ブロックの下端部の波が平行に重なるようにしてもよい。
【0023】
また、前記外型枠としてはライナープレート又はコルゲートパイプを使用することができ、前記内型枠としてはコルゲートパイプ又はライナープレートを使用することができるが、内型枠としては高張力シート又はエアーバックを使用することも可能である。なお、前記土砂としては前記立坑を掘削した際に出た残土が好ましいことは勿論である。
【0024】
また、本発明に係る偏心防止金具は、内型枠の下端部を案内するガイド金具と、該ガイド金具を前記下部ベース部上の前記外型枠と同軸の位置に沿った位置に固定する固定金具とを有し、該ガイド金具の前記内型枠を案内する側の全部または一部は上方が該内型枠から離れるように傾斜しているものである。
【0025】
ここで、前記固定金具は、前記外型枠から内側に所定間隔をおいた位置に前記ガイド金具を保持させる保持金具と、該保持金具を該外型枠に支持させる支持金具とを備えている。前記ガイド金具にピンが下方に向けて設けられ、該ピンは前記下部ベース中の鉄筋に固定される。前記保持金具は前記支持金具に上下スライド可能に取り付けられている。
【0026】
また、本発明に係る内型枠固定金具は、内型枠を支持する支持金具と、該支持金具の一方の端部を該外型枠に取り付ける第1の取付金具と、該支持金具の他方の端部を該内型枠に取り付ける第2の取付金具とを備えているものである。
【0027】
ここで、前記支持金具は前記第1の取付金具に上下スライド可能に取り付けられている。前記支持金具は長さ調整可能に形成されている。また、先に組み立てられた内型枠の上端部に後から継ぎ足して行く内型枠の下端部を重ねるように案内する案内金具が前記第2の取付金具に設けられている。更に前記案内金具の全部又は一部は上方が前記内型枠から離れるように傾斜している。
【0028】
【発明の実施の形態】
図1はこの発明の一実施態様に係る深礎基礎の縦断面図である。同図において、10は立坑であり、立坑10は地面から下方に垂直に掘削形成された円筒状の上部立坑12と、上部立坑12の底部から更に下方に垂直に掘削形成された円筒状の下部立坑14とからなる。
【0029】
下部立坑14は上部立坑12の直径より径が小さく、その中心は上部立坑12の直下から水平方向(同図では左側)に若干ずれた位置に形成されている。上部立坑12の上縁部の周囲にはリング状の上部支え16が設けられ、上部立坑12の底部で下部立坑14の上縁部の周囲にはリング状の中間支え18が設けられている。上部支え16及び中間支え18はいずれもコンクリートによって形成されている。
【0030】
上部立坑12の内壁及び下部立坑14の内壁は筒状に連結されたライナープレート(薄鋼板を波付け加工し、周囲にフランジを形成させた鋼材)からなる外型枠21,23によって各々被覆されている。上部立坑12の内壁を被覆している外型枠21は上部支え16によって側方から吊り下げられるようにして支えられている。下部立坑14の内壁を被覆している外型枠23は中間支え18によって吊り下げられるようにして支えられている。
【0031】
下部立坑14の内部には円柱状の鉄筋コンクリート構造体からなる基礎本体24が下部立坑14を満たすように形成されている。基礎本体24の内部には円柱状の中空部30が基礎本体24と同軸に形成されている。
【0032】
基礎本体24は、下部立坑14の床盤(底部)から中空部30の下端部の高さまで下部立坑14内を満たしている下部ベース部32と、下部ベース部32から上方へ延設されて中空部30を側方から囲んでいる側壁部34と、側壁部34から上方へ延設されて所定の高さまで下部立坑14内を満たしている上部ベース部36とからなる。
【0033】
中空部30の内部には立坑を掘削した際に排出された残土38が充填され、中空部30の内壁と残土38とはコルゲートパイプからなる内型枠40によって区画されている。上部ベース部36には例えば電力鉄塔の脚部(図示せず)の下端部を接続するための脚材26がその接続端を上部に露出させた状態で斜めに埋設・設置されている。
【0034】
次に、この深礎基礎の形成方法の一例について図2〜図18を参照しながら説明する。まず、形成すべき上部立坑12の径より若干大き目の穴を、ライナープレート1〜3リング分程度の深さまで掘り、この穴の中にライナープレートからなる外型枠21を筒状に組み立てる。外型枠21を組み立てた後、外型枠21の水平度、真円度を確認し、外型枠21と地山28との間にコンクリートを打設する。打設されたコンクリートは硬化して上部支え16となり、外型枠21の上方は周囲の地山28に固定される。
【0035】
コンクリートが硬化して、外型枠21の上方が周囲の地山28に固定された後、穴を更に下方に掘削しながら、外型枠21を更に下方に所定の深さだけ継ぎ足していく。ここで、地山28の崩壊を防ぐために穴をあまり大きく掘削せず、継ぎ足し可能な範囲で穴を掘削し、外型枠21を継ぎ足す。また、外型枠21は軸継目が縦方向に通らないように、交互(千鳥状)に組み立て、全体の強度を低下させないようにする。以上の作業によって、図2に示すような上部立坑12が形成される。
【0036】
次に、上部立坑12より径の小さい穴を、その中心が上部立坑12の中心から水平方向(同図では左側)に若干ずれるように、ライナープレート1〜3リング分程度の深さまで掘り、この穴の中で外型枠23を筒状に組み立てる。外型枠23を組み立てた後、外型枠23の水平度、真円度を確認し、外型枠23と地山28との間にコンクリートを打設する。ここで、打設されたコンクリートは硬化して中間支え18となり、外型枠23の上縁部は周囲の地山28に固定される。
【0037】
コンクリートが硬化して、外型枠23の上縁部が周囲の地山28に固定された後、穴を更に下方に掘削し、外型枠23を更に下方に所定の深さ分だけ継ぎ足していく。ここでも、地山28の崩壊を防ぐために穴をあまり大きく掘削せず、継ぎ足し可能な範囲で穴を掘削し、外型枠23を上部立坑12の場合と同様にして下方へ継ぎ足す。以上の作業を繰り返すことにより、図2に示すような下部立坑14が形成される。
【0038】
次に、図3に示すように、下部立坑14の床盤上の空間に所定の厚さで配筋42を施すとともに、下部立坑14の下方の型枠に沿って配筋44の一部を施す。そして、図4に示すように、床盤上の配筋42に偏心防止金具46を放射状に取り付け、下部立坑14内に生コンクリートをちょうちんシュート47等を用いて床盤上の配筋42が埋れ、内型枠ガイド具46が残る高さまで打設する。
【0039】
ここで、偏心防止金具46は、図5及び図6に示すように、内型枠40の下端部を下部立坑14の同軸位置に案内するガイド金具48と、ガイド金具48を固定する固定金具50とから構成されている。
【0040】
ガイド金具48の内型枠を案内する側の全部または一部は上方が内型枠から離れるように傾斜している。ガイド金具48にはピン52が下方に向けて設けられ、ピン52は番線によって配筋42に固定されている。固定金具50は、外型枠23から内側に所定間隔をおいた位置にガイド金具48を保持させる保持金具54と、保持金具54を外型枠23に支持させる支持金具56とからなる。保持金具54は支持金具56に上下スライド可能に取り付けられている。図5では、ガイド金具48の下部に保持金具54が取り付けられているが、ガイド金具48の上部に保持金具54を取り付けてもよい。
【0041】
次に、図7に示すように、下部立坑14の半ば付近まで外型枠23に沿って配筋44を施す。そして、立坑の外においてコルゲートパイプ(薄鋼板を波付け加工し、弧状に湾曲形成させた鋼材を筒状に組み立てたパイプ)からなる小ブロックの内型枠ブロック40aを予め組み立て、この内型枠ブロック40aをクレーンで下部立坑14内に降ろし、図8に示すように、内型枠ブロック40aの下縁部をガイド金具48でガイドさせながら、偏心防止金具46の内側に置き、内型枠ブロック40aの上縁部と下部立坑14の外型枠23とを内型枠固定金具58で連結する。
【0042】
内型枠固定金具58は、図9及び図10に示すように、内型枠ブロック40aを支持する支持金具60と、支持金具60の一方の端部を外型枠23に取り付ける第1の取付金具62と、支持金具60の他方の端部を内型枠ブロック40aに取り付ける第2の取付金具64とからなる。
【0043】
支持金具60は長さ調整可能に形成され、第1の取付金具62に上下スライド可能に取り付けられている。また、先に組み立てられた内型枠ブロック40aの上端部に後から継ぎ足して行く内型枠ブロック40aの下端部を重ねるように案内する案内金具66が第2の取付金具64に設けられている。案内金具66の全部又は一部は上方が内型枠ブロック40aから離れるように傾斜している。
【0044】
次に、図11に示すように、バケット68等を用い、リモートコントロールで内型枠ブロック40a内へ残土38を充填する。残土38を内型枠ブロック40aの上縁部近くまで充填した後、下部立坑14の上部の外型枠23の内側に沿って配筋44を施す。そして、図12に示すように、別に組み立てた内型枠ブロック40aを下部立坑14内に降下させ、先に設置された内型枠ブロック40aの上端部の上に置く。
【0045】
後から継ぎ足して行く内型枠ブロック40aの下端部の波は、図13(a)に切除部41として示す半山分だけ切除して平行にしてあるので、後から継ぎ足して行く内型枠ブロック40aの下端部は、図13(b)に示すように、先に組み立てられた内型枠ブロック40aの上端部上に重なるように載る。
【0046】
次に、後から継ぎ足した内型枠ブロック40aの上縁部に内型枠固定金具58を取り付けて内型枠ブロック40aの上縁部を固定し、図14に示すように、バケット68等を用い、リモートコントロールで後から継ぎ足した内型枠ブロック40aの内部に残土38を充填する。そして、図15に示すように、外型枠23と内型枠40との間にちょうちんシュート47等を用いて生コンクリートを打設する。これによって、側壁部34が形成される。
【0047】
次に、図16に示すように、側壁部34及び内型枠40の上に所定の厚さで配筋70を施し、生コンクリートを打設する。そして、図17に示すように、その上に脚材26を斜めに据え付け、下部立坑14内の上部空間に生コンクリートを打設して、脚材26の基部を埋設した上部ベース部36を形成する。そして、図18に示すように、脚材26の周囲に型枠を組み、内部に生コンクリートを打設して脚材26を完成する。
【0048】
なお、上述した実施態様では、内型枠40内へ残土38を充填した後に、内型枠40と外型枠23の間に生コンクリートを打設したが、内型枠40と外型枠23の間に生コンクリートを打設した後に、内型枠40内に残土38を充填してもよい。
【0049】
次に、内型枠40と外型枠23の間に生コンクリートを打設した後に、内型枠内40に残土38を充填する場合について説明する。
【0050】
まず、この場合、上部立坑12及び下部立坑14の形成、偏心防止金具46の取り付け、下部ベース部32の形成、最下段の内型枠ブロック40aの設置、内型枠固定金具58の取り付けまでを上述した実施態様の場合と同様に行なう(図2〜図8参照)。なお、この段階迄に配筋44は、全て施す。
【0051】
そして、最下段の内型枠ブロック40aの上端部に内型枠固定金具58を取り付けた後、図19に示すように、最下段の内型枠ブロック40aの上端部に足場43を取り付け、足場43の周囲に手摺45を取り付ける。そして、図20に示すように、外型枠23と内型枠ブロック40aとの間に生コンクリートを打設する。
【0052】
次に、足場43及び手摺45を撤去し、図21に示すように、立坑の外で組み立てた他の内型枠ブロック40aを最下段の内型枠ブロック40aの上に継ぎ足し、内型枠ブロック40aの上縁部を内型枠固定金具58で固定する。そして、外型枠23と内型枠ブロック40aとの間に生コンクリートを打設する。なお、内型枠ブロック40aは継ぎ足されて内型枠40になる。
【0053】
次に、内型枠40内に残土38をバケット68等を用いて充填する。そして、その後、上述した実施態様と同様に上部ベース部36を形成し、上部ベース部36に脚材26を埋設・設置する。
【0054】
【発明の効果】
本発明によれば、立坑を掘削する際に排出される残土の量を減らし、残土の輸送費用及び処理費用を軽減させることができるという効果がある。
【0055】
また、本発明によれば、残土を充填する中空部の分だけ生コンクリートの量を減らすことができるので、この分だけ深礎基礎の建設コストを下げることができるという効果がある。
【0056】
また、本発明によれば、深礎基礎の中空部に残土が充填されているので、送電鉄塔等の脚部を支えるための十分な重量を深礎基礎に持たせることができるという効果がある。
【0057】
外型枠及び/又は内型枠が、コルゲートパイプ及び/又はライナープレートからなる本発明によれば、鋼製であるから強度が高い割には、重量が軽いので山間僻地の現場にヘリコプター等で輸送するのに大変有利である。又、小さく分割して運搬することもできるので、都合により現地でリング状に小ブロックを組立てられ、融通性に富んでいる。さらに、分割したライナープレート、コルゲートパイプは、多数積み重ねて保管もできるので便利である。
【図面の簡単な説明】
【図1】図1はこの発明の一実施態様に係る深礎基礎の縦断面図である。
【図2】図2はこの発明の一実施態様に係る深礎基礎の形成方法における立坑の形成工程を示す説明図である。
【図3】図3はこの発明の一実施態様に係る深礎基礎の形成方法における下部ベース部の配筋工程を示す説明図である。
【図4】図4はこの発明の一実施態様に係る深礎基礎の形成方法における下部ベース部への生コン打設工程を示す説明図である。
【図5】図5はこの発明の一実施態様に係る偏心防止金具の説明図である。
【図6】図6は図5のA−A断面図である。
【図7】図7はこの発明の一実施態様に係る深礎基礎の形成方法における側壁部の配筋工程を示す説明図である。
【図8】図8はこの発明の一実施態様に係る深礎基礎の形成方法における内型枠の設置工程を示す説明図である。
【図9】図9はこの発明の一実施態様に係る内型枠固定金具の説明図である。
【図10】図10は図9のB−B断面図である。
【図11】図11はこの発明の一実施態様に係る深礎基礎の形成方法における内型枠への残土投入工程を示す説明図である。
【図12】図12はこの発明の一実施態様に係る深礎基礎の形成方法における内型枠の接続工程を示す説明図である。
【図13】図13はこの発明の一実施態様に係る深礎基礎の形成方法における内型枠の接続状態を説明する説明図である。
【図14】図14はこの発明の一実施態様に係る深礎基礎の形成方法における内型枠への残土投入工程を示す説明図である。
【図15】図15はこの発明の一実施態様に係る深礎基礎の形成方法における側壁部への生コン打設工程を示す説明図である。
【図16】図16はこの発明の一実施態様に係る深礎基礎の形成方法における上部ベース部への生コン打設工程を示す説明図である。
【図17】図17はこの発明の一実施態様に係る深礎基礎の形成方法における脚材の設置工程を示す説明図である。
【図18】図18はこの発明の一実施態様に係る深礎基礎の形成方法における脚材の形成工程を示す説明図である。
【図19】図19はこの発明の他の実施態様に係る深礎基礎の形成方法における内型枠ブロックの上端部への足場及び手摺の取付工程を示す説明図である。
【図20】図20はこの発明の他の実施態様に係る深礎基礎の形成方法における内型枠ブロックと外型枠との間への生コンクリートの打設工程を示す説明図である。
【図21】図21はこの発明の他の実施態様に係る深礎基礎の形成方法における内型枠ブロックの継足工程を示す説明図である。
【図22】図22は従来の深礎基礎の一例の縦断面図である。
【符号の説明】
10 立坑
12 上部立坑
14 下部立坑
16 上部支え
18 中間支え
21 外型枠
23 外型枠
24 基礎本体
26 脚材
28 地山
30 中空部
32 下部ベース部
34 側壁部
36 上部ベース部
38 残土
40 内型枠
40a 内型枠ブロック
41 切除部
42 配筋
43 足場
44 配筋
45 手摺
46 偏心防止金具
47 ちょうちんシュート
48 ガイド金具
50 固定金具
52 ピン
54 保持金具
56 支持金具
58 内型枠固定金具
60 支持金具
62 第1の取付金具
64 第2の取付金具
66 案内金具
68 バケット
70 配筋[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a deep foundation suitable for supporting legs such as power transmission towers and bridges in mountainous areas, a method for forming the foundation, and an eccentric preventing metal fitting and an inner mold fixing metal fitting used for these foundations.
[0002]
[Prior art]
FIG. 22 is a longitudinal sectional view showing a conventional example of a deep foundation that supports the legs of the power transmission tower. In the figure, 10 is a shaft, and the
[0003]
The
[0004]
The inner wall of the
[0005]
A base
[0006]
For example, this foundation is formed as follows. That is, a hole slightly larger than the diameter of the
[0007]
After the concrete is hardened and the upper part of the
[0008]
Next, a hole having a diameter smaller than that of the
[0009]
After the concrete is hardened and the upper edge of the
[0010]
Next, the bar is placed on the floor (bottom) of the
[0011]
In the above-described example, the shaft is divided into the
[0012]
[Problems to be solved by the invention]
By the way, when a shaft is excavated to form a deep foundation, a large amount of earth and sand that have occupied the space of the shaft is discharged as residual soil. There are many steep slopes in mountainous remote areas that form the foundation for transmission towers. If this leftover soil is left as it is around the shaft, it will flow out of the rainwater and pollute the river or collapse. Because it is dangerous, it must be transported somewhere safe to dispose of the remaining soil.
[0013]
It would be convenient if a place where the remaining soil could be treated could be secured near the shaft, but in many cases it would be a location away from the shaft. And as described above, there are many mountainous areas where the foundation for the power transmission tower is formed, so there are often no roads for transporting the remaining soil, and the helicopter must carry the remaining soil. For this reason, there was a problem that it took a great deal of cost for transporting the remaining soil.
[0014]
In addition, even if the remaining soil can be disposed of, if the remaining soil is dumped as it is, the remaining soil will be washed away by rainwater and the river will be polluted. In order to do this, it is necessary to perform maintenance work such as draining water, surface greening, and earth retaining. For this reason, there has been a problem that a great amount of cost is required for the conservation measures of the remaining soil.
[0015]
The present invention provides a deep foundation and its forming method that reduces the amount of residual soil that must be processed as much as possible to reduce various costs as described above, and an eccentricity prevention metal fitting and an inner mold fixing metal fitting used for these. The purpose is to provide.
[0016]
[Means for Solving the Problems]
A deep foundation according to the present invention is a foundation main body made of a columnar reinforced concrete structure that fills the inside of the shaft, and a columnar hollow portion formed substantially coaxially with the foundation main body inside the foundation main body, It has earth and sand filled in the hollow portion.
[0017]
Here, the base body includes a lower base portion filling the shaft from the floor of the shaft to a height of a lower end portion of the hollow portion, and the hollow portion extending upward from the lower base portion. A side wall portion that is surrounded from the side and an upper base portion that extends upward from the side wall portion and fills the shaft up to a predetermined height. And the leg material for connecting the lower end part of the leg part which should be fixed is embed | buried and installed in this upper base part in the state which exposed the connection end.
[0018]
Further, an outer mold is provided between the shaft and the concrete structure, and an inner mold is provided between the hollow portion and the earth and sand. A liner plate or corrugated pipe can be used as the outer mold, and a corrugated pipe or liner plate can be used as the inner mold, but a high-tensile sheet or air bag is used as the inner mold. It is also possible to do. Of course, as the earth and sand, the residual earth which comes out when excavating the shaft is preferable.
[0019]
In addition, the method for forming a deep foundation according to the present invention includes a step of assembling an outer frame inside the shaft while excavating the shaft, and placing a ready-mixed concrete on the floor of the shaft to a predetermined height. A step of forming a base portion, a step of assembling an inner mold frame substantially coaxially with the outer mold frame on the lower base portion, a step of filling earth and sand into the inner mold frame, the outer mold frame and the Placing a ready-mixed concrete between the inner mold and forming a side wall; and placing a ready-mixed concrete on the side wall to a predetermined height to form an upper base. It is what.
[0020]
Here, the step of filling the inner mold with earth and sand and the step of placing the ready-mixed concrete between the outer mold and the inner mold to form the side wall part is first. Also good. That is, after filling the inner mold with earth and sand, the side wall portion may be formed by placing ready-mixed concrete between the outer mold and the inner mold, and the outer mold and After the ready-mixed concrete is placed between the inner mold and the side wall portion is formed, earth and sand may be filled into the inner mold.
[0021]
Further, the step of forming the lower base portion arranges the step of arranging the space in the space on the floor of the shaft, the step of forming the side wall portion arranges the step along the inside of the outer mold frame, The step of forming the upper base portion includes the step of arranging the bars in the space above the inner mold. When the upper base portion is formed, a leg material for connecting the lower end portion of the leg portion to be fixed is embedded and installed in the upper base portion with the connection end exposed.
[0022]
Further, the inner mold frame may be assembled into a small block having a predetermined height outside the shaft, and the inner mold frame of the small block may be assembled inside the shaft. Further, the wave at the upper end portion of the small block of the inner mold frame assembled earlier and the wave at the lower end portion of the small block of the inner mold frame to be added later may overlap in parallel.
[0023]
Further, a liner plate or a corrugated pipe can be used as the outer mold, and a corrugated pipe or a liner plate can be used as the inner mold, but a high tension sheet or an air bag can be used as the inner mold. Can also be used. Of course, as the earth and sand, the residual earth which comes out when excavating the shaft is preferable.
[0024]
Further, the eccentric preventing metal fitting according to the present invention includes a guide metal fitting for guiding a lower end portion of the inner mold frame, and a fixing for fixing the guide metal fitting at a position along the same axis as the outer mold frame on the lower base portion. And all or part of the guide metal fitting on the side for guiding the inner mold frame is inclined so that the upper part is separated from the inner mold frame.
[0025]
Here, the fixing metal fitting includes a holding metal fitting that holds the guide metal fitting at a position spaced inward from the outer mold frame, and a support metal fitting that supports the holding metal fitting on the outer mold frame. . A pin is provided on the guide metal fitting downward, and the pin is fixed to a reinforcing bar in the lower base. The holding bracket is slidably attached to the support bracket.
[0026]
The inner mold fixing bracket according to the present invention includes a support bracket that supports the inner mold, a first mounting bracket that attaches one end of the support bracket to the outer mold, and the other of the support bracket. And a second mounting bracket for mounting the end of the second mounting bracket to the inner mold.
[0027]
Here, the support fitting is attached to the first attachment fitting so as to be vertically slidable. The support fitting is formed to be adjustable in length. In addition, a guide fitting for guiding the lower end portion of the inner mold frame, which is added later, to the upper end portion of the previously assembled inner mold frame, is provided on the second mounting bracket. Further, all or a part of the guide fitting is inclined so that the upper part is separated from the inner mold.
[0028]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 is a longitudinal sectional view of a deep foundation according to an embodiment of the present invention. In the figure, 10 is a shaft, and the
[0029]
The
[0030]
The inner wall of the
[0031]
Inside the
[0032]
The
[0033]
The inside of the
[0034]
Next, an example of a method for forming this foundation will be described with reference to FIGS. First, a hole slightly larger than the diameter of the
[0035]
After the concrete is hardened and the upper part of the
[0036]
Next, a hole having a diameter smaller than that of the
[0037]
After the concrete is hardened and the upper edge of the
[0038]
Next, as shown in FIG. 3, a
[0039]
Here, as shown in FIGS. 5 and 6, the eccentric prevention metal fitting 46 includes a guide metal fitting 48 that guides the lower end portion of the
[0040]
All or part of the
[0041]
Next, as shown in FIG. 7, reinforcing
[0042]
As shown in FIGS. 9 and 10, the inner mold fixing metal fitting 58 includes a support metal fitting 60 that supports the inner
[0043]
The support fitting 60 is formed to be adjustable in length, and is attached to the first attachment fitting 62 so as to be slidable up and down. In addition, a guide fitting 66 for guiding the lower end portion of the
[0044]
Next, as shown in FIG. 11, the remaining
[0045]
The wave at the lower end of the
[0046]
Next, the inner
[0047]
Next, as shown in FIG. 16, reinforcing
[0048]
In the embodiment described above, after filling the
[0049]
Next, a case where the remaining
[0050]
First, in this case, the formation of the
[0051]
Then, after attaching the inner
[0052]
Next, the
[0053]
Next, the remaining
[0054]
【The invention's effect】
ADVANTAGE OF THE INVENTION According to this invention, there exists an effect that the quantity of the residual soil discharged | emitted when excavating a shaft can be reduced, and the transportation cost and processing cost of residual soil can be reduced.
[0055]
Further, according to the present invention, the amount of ready-mixed concrete can be reduced by the amount of the hollow portion filled with the remaining soil, so that the construction cost of the deep foundation can be reduced by this amount.
[0056]
Further, according to the present invention, since the remaining soil is filled in the hollow portion of the deep foundation foundation, there is an effect that the deep foundation foundation can have a sufficient weight for supporting the legs of the power transmission tower and the like. .
[0057]
According to the present invention, in which the outer formwork and / or the inner formwork are made of corrugated pipes and / or liner plates, they are made of steel. It is very advantageous for transportation. In addition, since it can be transported in small parts, a small block can be assembled in the form of a ring on site for convenience and high flexibility. Furthermore, a large number of divided liner plates and corrugated pipes can be stacked and stored, which is convenient.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view of a deep foundation according to an embodiment of the present invention.
FIG. 2 is an explanatory view showing a shaft forming process in a method for forming a deep foundation according to an embodiment of the present invention.
FIG. 3 is an explanatory view showing a bar arrangement process of a lower base portion in a method for forming a deep foundation according to an embodiment of the present invention.
FIG. 4 is an explanatory view showing a raw concrete placing step on the lower base portion in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 5 is an explanatory view of an eccentricity preventing metal fitting according to one embodiment of the present invention.
6 is a cross-sectional view taken along the line AA in FIG. 5. FIG.
FIG. 7 is an explanatory view showing a side bar arrangement process in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 8 is an explanatory diagram showing an installation process of an inner mold in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 9 is an explanatory view of an inner mold fixing bracket according to one embodiment of the present invention.
10 is a cross-sectional view taken along the line BB in FIG. 9. FIG.
FIG. 11 is an explanatory view showing a remaining soil charging step into the inner mold in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 12 is an explanatory view showing an inner mold frame connecting step in the deep foundation forming method according to one embodiment of the present invention.
FIG. 13 is an explanatory view for explaining a connection state of inner mold frames in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 14 is an explanatory view showing a remaining soil charging step into the inner mold in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 15 is an explanatory view showing a raw concrete placing step on the side wall in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 16 is an explanatory view showing a raw concrete placing step on the upper base portion in the deep foundation foundation forming method according to one embodiment of the present invention.
FIG. 17 is an explanatory view showing a leg installation step in the method for forming a deep foundation according to one embodiment of the present invention.
FIG. 18 is an explanatory view showing a leg forming step in the deep foundation forming method according to one embodiment of the present invention.
FIG. 19 is an explanatory view showing a step of attaching a scaffold and a handrail to the upper end portion of the inner mold block in the method for forming a deep foundation according to another embodiment of the present invention.
FIG. 20 is an explanatory view showing a process for placing ready-mixed concrete between an inner mold frame block and an outer mold frame in a method for forming a deep foundation according to another embodiment of the present invention.
FIG. 21 is an explanatory view showing a step of joining the inner form block in the method for forming a deep foundation according to another embodiment of the present invention.
FIG. 22 is a longitudinal sectional view of an example of a conventional deep foundation.
[Explanation of symbols]
10 shaft
12 Upper shaft
14 Lower shaft
16 Upper support
18 Intermediate support
21 Outer formwork
23 Outer formwork
24 Basic body
26 Legs
28
30 hollow part
32 Lower base
34 Side wall
36 Upper base
38 Remaining soil
40 Inside formwork
40a Inner formwork block
41 excision
42 Reinforcement
43 Scaffolding
44 Reinforcement
45 Handrail
46 Eccentricity prevention bracket
47 Lantern Shoot
48 Guide bracket
50 Fixing bracket
52 pins
54 Holding bracket
56 Supporting bracket
58 Inner mold fixing bracket
60 Support bracket
62 First mounting bracket
64 Second mounting bracket
66 Guide bracket
68 buckets
70 Reinforcement
Claims (24)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15601296A JP3745027B2 (en) | 1996-04-18 | 1996-05-28 | Deep foundation and its forming method, eccentric prevention metal fittings and inner mold fixing metal fittings used for them |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8-121128 | 1996-04-18 | ||
JP12112896 | 1996-04-18 | ||
JP15601296A JP3745027B2 (en) | 1996-04-18 | 1996-05-28 | Deep foundation and its forming method, eccentric prevention metal fittings and inner mold fixing metal fittings used for them |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH101944A JPH101944A (en) | 1998-01-06 |
JP3745027B2 true JP3745027B2 (en) | 2006-02-15 |
Family
ID=26458565
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP15601296A Expired - Lifetime JP3745027B2 (en) | 1996-04-18 | 1996-05-28 | Deep foundation and its forming method, eccentric prevention metal fittings and inner mold fixing metal fittings used for them |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3745027B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4890217B2 (en) * | 2006-12-05 | 2012-03-07 | 東急建設株式会社 | Construction method of underground structure and underground structure |
ATE434113T1 (en) * | 2007-04-05 | 2009-07-15 | Bauer Maschinen Gmbh | EARTH DRILLING EQUIPMENT |
JP6177577B2 (en) * | 2013-04-26 | 2017-08-09 | Jfe建材株式会社 | Deep foundation pile construction method and deep foundation pile |
JP6300983B2 (en) * | 2017-04-17 | 2018-03-28 | Jfe建材株式会社 | Deep foundation pile construction method and deep foundation pile |
-
1996
- 1996-05-28 JP JP15601296A patent/JP3745027B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH101944A (en) | 1998-01-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107542108B (en) | A kind of reverse construction method of building basement structure | |
CN101691751B (en) | Construction method for making ultra-long artificial excavating pile penetrate cave and ultra-long pile penetrating cave | |
CN111733828A (en) | Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology | |
US20080019779A1 (en) | Steel-Cased Concrete Piers | |
CN108505805A (en) | Large-scale cast-in-place pond and its construction method are split in expansion reinforcing band control | |
CN107964976A (en) | Steel pipe-conversion steel platform tower crane top-down construction method | |
JP4013182B2 (en) | Self-supporting mountain retaining wall method and self-supporting mountain retaining wall | |
CN208455793U (en) | Heavy Traffic road inspection well walling crib | |
JP3745027B2 (en) | Deep foundation and its forming method, eccentric prevention metal fittings and inner mold fixing metal fittings used for them | |
JPH1060817A (en) | Constructing method of annexing structure | |
KR910001393B1 (en) | Method of constructing a rigid structure upon the bottom of a body of water as well as lost casing fbottom of a body of mater as well as lost casting or performing said method for preforming baid method | |
CN109763507B (en) | Double-wall corrugated pipe foundation and construction process thereof | |
KR20040039271A (en) | Shoe coffering method for new construction and repair, reinforcement of bridge open caisson foundation | |
JP3453664B2 (en) | Shaft construction method | |
CN218322863U (en) | Well body reinforcing system for inspection well | |
CN113266019B (en) | Construction method of foundation pit steel pipe support system | |
JP2001241287A (en) | Construction method of shaft, assembly method of structural body used for construction method, and assembly device used for assembly method | |
JP4475116B2 (en) | Vertical shaft structure and its construction method | |
JP4964032B2 (en) | Side wall and method for constructing side wall | |
JP2996113B2 (en) | How to build a shaft | |
RU2807350C1 (en) | Constructive and technological solution for foundation of intermediate support of high pile work type constructed in temporary enclosing structure | |
KR102656370B1 (en) | Underground structure capable of forming a supporting point of a molded beam and its construction method | |
CN112942312B (en) | T-shaped underground diaphragm wall construction process | |
CN107938700A (en) | A kind of installation method of assembled underground pipe gallery | |
JP2635934B2 (en) | Shaft construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050531 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050726 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20051115 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20051116 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091202 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101202 Year of fee payment: 5 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101202 Year of fee payment: 5 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101202 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111202 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121202 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131202 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |