JP3721257B2 - Seedling planting method by log - Google Patents

Seedling planting method by log Download PDF

Info

Publication number
JP3721257B2
JP3721257B2 JP10873598A JP10873598A JP3721257B2 JP 3721257 B2 JP3721257 B2 JP 3721257B2 JP 10873598 A JP10873598 A JP 10873598A JP 10873598 A JP10873598 A JP 10873598A JP 3721257 B2 JP3721257 B2 JP 3721257B2
Authority
JP
Japan
Prior art keywords
planting
log
slope
hole
base material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP10873598A
Other languages
Japanese (ja)
Other versions
JPH11286939A (en
Inventor
範行 高橋
Original Assignee
上毛緑産工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 上毛緑産工業株式会社 filed Critical 上毛緑産工業株式会社
Priority to JP10873598A priority Critical patent/JP3721257B2/en
Publication of JPH11286939A publication Critical patent/JPH11286939A/en
Application granted granted Critical
Publication of JP3721257B2 publication Critical patent/JP3721257B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【産業上の利用分野】
本発明は丸太による苗木植栽工法に関するもので、急勾配の法面であっても植栽しようとする個所に丸太を設置することによって勾配が緩やかになるようにすると共に、植栽に必要な保水性を確保し、且つ法面の地盤の安定強化を図ることを目的とする。
【0002】
【従来の技術】
法面の所定個所に植栽用穴を掘削し、これに苗木や草本類の植栽を行うことは、法面緑化工事として一般的に行われている。
【0003】
【発明が解決しようとする課題】
ところが、法面に直接植栽穴を掘削して苗木等を植栽する工法は、急勾配の法面にあっては、雨水を一時的でも貯留することができないため、保水性が確保されず、且つ斜面の安定化にも課題があった。
【0004】
【課題を解決するための手段】
そこで、本発明は上記従来の課題を解決し、発明の目的を達成するため提供するものである。本発明の第1は、丸太による苗木植栽工法において、丸太を植栽穴径より長く切断し、且つ丸太の直径を長さの10分の1から5分の1程度に設定し、その端部から中央に略直径の長さで寄った位置の丸太に貫通孔をあけ、その丸太を法面の植栽をしようとする個所における横方向に配置すると共に、竹串を可とする頭部に鈎部がある木質アンカーピンを丸太の貫通孔に挿通して法面に打ち込んで固定し、且つ固定した丸太の直上位置に植栽穴を掘削した後、植生基盤材を法面に吹付けて厚層基材吹付層を形成し、且つ植栽穴部の厚層基材吹付層を掘り取った後、苗木類を植え込むと共に、掘り取った植生基盤材を埋め戻すようにしたものである。
【0005】
本発明の第2は、第1の発明に係る丸太による苗木植栽工法において、間伐材を使用した丸太の長さを50〜60cmにすると共に、丸太の直径を6〜12cm程度に設定すると共に、丸太の端部から長さ方向の中央に寄った孔の位置を5〜15cm程度に設定し、且つアンカ−ピンを竹串を可とする木質材料で製作したものである。
【0006】
【実施例】
次に本発明の実施例を図面を以て説明する。図において、1は法面、2は厚層基材吹付層、3は間伐材を可とする丸太であり、長さL=50〜60cm、端部の直径R=6〜12cm程度のものを用い、且つ丸太の両端から長さL1=10cm程度長さ方向の中央に寄った位置において直径方向に挿通するアンカーピン用孔4をあけてある。前記の孔径は15〜20cm程度を可とする。そして、この丸太を法面1の植栽をしようとする所定の個所に配置する。5は丸太の孔4に挿通するアンカーピンであり、当該丸太を法面1に打ち込んで固定する。当該アンカーピンは竹串を可とする木質材で作ると共に、竹の節部を利用して頭部に鈎部を成形し、且つ丸太の孔4に挿通する太さとし、且つその長さは400cm程度に設定する。6は法面1に固定した丸太3の直上位置に掘削する埴栽穴、7は埴栽穴に植え込むための苗木類である。8は厚層基材吹付層2の中間に張設したラス、9はラス8を法面1に沿って張設するためのアンカーピン、10は厚層基材吹付層2の表面に張設したネット、11はネット張設用のアンカーピンを示す。
【0007】
【具体的な使用例】
上記の実施例に基づく具体的な使用例を説明する。
(1)「厚層基材吹付工例」
▲1▼ 丸太筋工設置=法面1の植栽を使用とする個所に、丸太3を水平横方向に配置してアンカ−ピン5を孔4に挿通すると共に法面1に打ち込んで固定する。
▲2▼ 植栽穴掘削(その1)=法面1に固定した丸太3の直上位置に植栽穴6を掘削する
▲3▼ 厚層基材吹付工=法面1の全体に植生基盤材を吹付けて厚層基材吹付層2を形成する。
▲4▼ 植栽穴掘削(その2)=掘削した植栽穴6の部分に吹付けた植生基盤材を堀り取って除去する。
▲5▼ 苗木植栽=掘削した植栽穴6に苗木7を植え込み、植え込んだ後に堀り取った植生基盤材を客土として埋め戻す。
【0008】
(2)「ラス張り工を施した厚層基材吹付工例」
▲1▼ 丸太筋工設置=法面1の植栽をしようとする個所に、丸太3を水平横方向に配置してアンカ−ピン5を孔4に挿通すると共に法面1に打ち込んで固定する。
▲2▼ 植栽穴掘削(その1)=法面1に固定した丸太3の直上位置に植栽穴6を掘削する
▲3▼ ラス張工=ラス8を法面1から少し浮かして配設し、アンカ−ピン9で張設する。その浮かす高さhは基材吹付厚さTの略中間になるように設定する。
▲4▼ 厚層基材吹付工=法面1の全体に植生基盤材を吹付けて厚層基材吹付層2を形成する。
▲5▼ 植栽穴掘削(その2)=掘削した植栽穴6の部分に吹付けた植生基盤材を堀り取って除去する。
▲6▼ 苗木植栽=掘削した植栽穴6に苗木7を植え込み、植え込んだ後に堀り取った植生基盤材を客土として埋め戻す。
ただし、前記▲5▼の掘削穴掘削(その2)の際に苗木植栽の妨げになるラス8を切除する。
【0009】
(3)「ネット張工を施した厚層基材吹付工例」
▲1▼ 丸太筋工設置=法面1の植栽を使用とする個所に、丸太3を水平横方向に配置してアンカ−ピン5を孔4に挿通すると共に法面に打ち込んで固定する。
▲2▼ 植栽穴掘削(その1)=法面1に固定した丸太3の直上位置に植栽穴6を掘削する
▲3▼ 厚層基材吹付工=法面1の全体に植生基盤材を吹付けて厚層基材吹付層2を形成する。
▲4▼ ネット張工=厚層基材吹付層2の表面にネット10を張り巡らしてアンカ−ピン11で当該吹付層の表面に固定する。
▲5▼ 植栽穴掘削(その2)=掘削した植栽穴6の部分に吹付けた植生基盤材を堀り取って除去する。
ただし、前記▲5▼の掘削穴掘削(その2)の際に苗木植栽の妨げになるネット10を切除する。
▲6▼ 苗木植栽=掘削した植栽穴6に苗木7を植え込み、植え込んだ後に堀り取った植生基盤材を客土として埋め戻す。
▲7▼ ネット補修=前記▲5▼の掘削穴掘削(その2)の際に切り取った個所のネットを厚層基材吹付層2の表面に張り付ける。
【0010】
(4)「ラス張り工とネット張り工を施した厚層基材吹付工例」
▲1▼ 丸太筋工設置=法面1の植栽を使用とする個所に、丸太3を水平横方向に配置してアンカ−ピン5を孔4に挿通すると共に法面に打ち込んで固定する。
▲2▼ 植栽穴掘削(その1)=法面1に固定した丸太3の直上位置に植栽穴6を掘削する
▲3▼ ラス張工=ラス8を法面1から少し浮かして配設し、アンカ−ピン9で張設する。その浮かす高さhは厚層基材吹付層厚さTの略中間になるように設定する。
▲4▼ 厚層基材吹付工=法面1の全体に植生基盤材を吹付けて厚層基材吹付層2を形成する。
▲5▼ ネット張工=厚層基材吹付工による厚層基材吹付層2の表面にネット10を張り巡らしてアンカ−ピン11を打ち込んで当該厚層基材吹付層の表面に張設する。
▲6▼ 植栽穴掘削(その2)=掘削した植栽穴6の部分に吹付けた植生基盤材を堀り取って除去する。
ただし、この掘削穴掘削(その2)の際に苗木植栽の妨げになるネット10を切除する。
▲7▼ 苗木植栽=掘削した植栽穴6に苗木7を植え込み、植え込んだ後に堀り取った植生基盤材を客土として埋め戻す。
▲8▼ ネット補修=前記▲6▼の掘削穴掘削(その2)の際に切り取った個所のネットを厚層基材吹付層2の表面に張り付ける。
【0011】
【発明の効果】
本発明は上記の構成であるから、苗木等を植栽しようとする個所に当該植栽に必要な長さの丸太を設置するだけで植栽が確実に行えると共に、従来の丸太伏せ工のように法面の横方向全体に渡って設置する必要がない。また、その丸太に孔をあけてこれにアンカ−ピンを挿通して打ち込むことによって、法面に対して丸太の固定が確実となり、しかも法面の勾配が緩やかになって植物の生育に適すると共に、法面を流れる雨水が一時的に丸太上部で停滞し植栽穴の中に浸透して植栽穴の水分が増す。さらに法面に吹付けた植生基盤材の滑落の防止に役立つ。
そして、土壌硬度の硬質な法面に対しても植栽前に植栽穴を苗木に応じて適当な形に掘削しておき、植物の生育に適した植生基盤材を植栽穴の客土として利用できるので、土壌硬度及び保水性にすぐれた苗床となる。
さらに、丸太使用のため、期間の経過によって丸太は腐り土に還元する。また、土質によってアンカ−を竹串等の木質材料を用いることができるのですべて土に還元される。
また、間伐材の使用によって低コストで且つ有効利用にも役立つものである。しかも、法面の植栽穴部に吹付けられた厚層基材吹付材を客土として植栽した苗木に埋め戻すことによって客土として利用できる。そして、苗木の植栽によって根系の緊迫力によって法面の地盤強化が図れる。以上の結果、本発明によれば廃材がでないので最終的には環境面に優れ、且つ地球に優しい緑化が得られる。
【図面の簡単な説明】
【図1】 本発明工法を厚層基材吹付工に適用した縦断面図である。
【図2】 本発明工法をラス張工を施した厚層基材吹付工に適用した縦断面図である。
【図3】 本発明工法をでネット張工を施した厚層基材吹付工に適用した縦断面図である。
【図4】 本発明工法をでラス張工及びネット張工を施した厚層基材吹付工に適用した縦断面図である。
【図5】 本発明工法に用いる丸太の斜視図である。
【符号の説明】
1……法面
2……厚層基材吹付層
3……間伐材使用の丸太
4……丸太にあけた貫通孔
5……竹串を可とする木質系のアンカ−ピン
6……植栽穴
7……苗木
8……張設用ラス
9……アンカ−ピン
10……張設用ネット
11……アンカ−ピン
[Industrial application fields]
The present invention relates to a method for planting seedlings with logs, and even if the slope is steep, the slope is made gentle by installing logs at the place to be planted and is necessary for planting. The purpose is to secure water retention and to strengthen the stability of the slope ground.
[0002]
[Prior art]
Drilling a planting hole at a predetermined location on the slope and planting seedlings and herbs is a common practice for slope planting.
[0003]
[Problems to be solved by the invention]
However, the method of drilling a planting hole directly on the slope and planting seedlings, etc., does not secure water retention because rainwater cannot be stored temporarily even on steep slopes. There was also a problem in stabilizing the slope.
[0004]
[Means for Solving the Problems]
Therefore, the present invention is provided to solve the above conventional problems and achieve the object of the invention. In the first aspect of the present invention, in the seedling planting method using logs, the logs are cut longer than the diameter of the planting hole, and the diameter of the logs is set to about one-tenth to one-fifth of the length. Part opened logs into the through hole of the position near the length of substantially a diameter in the center from, as well as arranged laterally at the location to be planting slopes the log, head and allowed a toothpick A wood anchor pin with a buttock is inserted into the through hole of the log and driven into the slope to fix it. After drilling a planting hole directly above the fixed log, the vegetation base material is sprayed onto the slope. After forming the thick base material spray layer and digging up the thick base material spray layer of the planting hole, the seedlings are planted and the vegetation base material dug up is backfilled. .
[0005]
In the second aspect of the present invention, in the seedling planting method using logs according to the first invention, the length of logs using thinned wood is set to 50 to 60 cm, and the diameter of the logs is set to about 6 to 12 cm. The position of the hole from the end of the log to the center in the length direction is set to about 5 to 15 cm, and the anchor pin is made of a wood material allowing a bamboo skewer.
[0006]
【Example】
Next, embodiments of the present invention will be described with reference to the drawings. In the figure, 1 is a slope, 2 is a thick substrate spray layer, 3 is a log that allows thinned wood, and has a length L = 50-60 cm and an end diameter R = 6-12 cm. An anchor pin hole 4 that is used and is inserted in the diameter direction at a position near the center in the length direction by a length L1 = 10 cm from both ends of the log is formed. The hole diameter is about 15 to 20 cm. And this log is arrange | positioned in the predetermined | prescribed location which is going to plant the slope 1. FIG. An anchor pin 5 is inserted through the hole 4 of the log, and the log is driven into the slope 1 and fixed. The anchor pin is made of a wood material that allows a bamboo skewer, and a brim is formed on the head using a bamboo joint , and the length is 400 cm. The length of the anchor pin is 400 cm. Set to degree. 6 is a potting hole to be excavated at a position directly above the log 3 fixed to the slope 1, and 7 is a seedling for planting in the potting hole. 8 is a lath stretched in the middle of the thick substrate spray layer 2, 9 is an anchor pin for stretching the lath 8 along the slope 1, and 10 is stretched on the surface of the thick substrate spray layer 2 Reference numeral 11 denotes an anchor pin for extending the net.
[0007]
[Specific use examples]
A specific use example based on the above embodiment will be described.
(1) “Thick layer base material spraying example”
▲ 1 ▼ Installation of log reinforcement = Place where slope 1 planting is used, place log 3 horizontally and insert anchor pin 5 into hole 4 and drive into slope 1 to fix .
(2) Planting hole excavation (Part 1) = Drilling a planting hole 6 directly above the log 3 fixed on the slope 1 (3) Thick layer base material spraying = Vegetation base material on the whole slope 1 To form the thick base material spray layer 2.
(4) Planting hole excavation (part 2) = The vegetation base material sprayed on the excavated planting hole 6 is dug and removed.
(5) Planting seedlings = planting seedlings 7 in the excavated planting holes 6, and filling the ground with the vegetation base material dug after planting.
[0008]
(2) “Thick layer base material spraying process with lath tension”
▲ 1 ▼ Installation of log bars = Place log 3 in the horizontal direction at the place where you want to plant slope 1 and insert anchor pin 5 into hole 4 and drive it into slope 1 and fix it. .
(2) Planting hole excavation (Part 1) = Drilling a planting hole 6 directly above the log 3 fixed on the slope 1 (3) Lath tension = Lath 8 is slightly lifted from the slope 1 Then, it is tensioned with the anchor pin 9. The floating height h is set to be approximately in the middle of the base material spraying thickness T.
{Circle around (4)} Thick layer base material spraying method = Thick layer base material spraying layer 2 is formed by spraying a vegetation base material on the entire slope 1.
(5) Planting hole excavation (part 2) = The vegetation base material sprayed on the excavated planting hole 6 is dug and removed.
(6) Seedling planting = planting seedlings 7 in the excavated planting hole 6, and filling the ground with the vegetation base material dug after planting.
However, the lath 8 that hinders seedling planting is excised during the excavation hole excavation (2).
[0009]
(3) “Thick layer base material spraying with net tension”
{Circle around (1)} A log 3 is placed in a place where the planting of the slope 1 is used, the log 3 is arranged in the horizontal direction and the anchor pin 5 is inserted into the hole 4 and driven into the slope to be fixed.
(2) Planting hole excavation (Part 1) = Drilling a planting hole 6 directly above the log 3 fixed on the slope 1 (3) Thick layer base material spraying = Vegetation base material on the whole slope 1 To form the thick base material spray layer 2.
{Circle around (4)} Net stretcher = A net 10 is stretched around the surface of the thick base material spray layer 2 and fixed to the surface of the spray layer with anchor pins 11.
(5) Planting hole excavation (part 2) = The vegetation base material sprayed on the excavated planting hole 6 is dug and removed.
However, the net 10 that hinders seedling planting is excised during the excavation hole excavation (part 2) of (5).
(6) Seedling planting = planting seedlings 7 in the excavated planting hole 6, and filling the ground with the vegetation base material dug after planting.
(7) Net repair = The net of the portion cut out during the excavation hole excavation (part 2) of the above (5) is attached to the surface of the thick base material spray layer 2.
[0010]
(4) "Thick layer base material spraying work with lath and net work"
{Circle around (1)} A log 3 is placed in a place where the planting of the slope 1 is used, the log 3 is arranged in the horizontal direction and the anchor pin 5 is inserted into the hole 4 and driven into the slope to be fixed.
(2) Planting hole excavation (Part 1) = Drilling a planting hole 6 directly above the log 3 fixed on the slope 1 (3) Lath tension = Lath 8 is slightly lifted from the slope 1 Then, it is tensioned with the anchor pin 9. The floating height h is set so as to be approximately in the middle of the thick base material spray layer thickness T.
{Circle around (4)} Thick layer base material spraying method = Thick layer base material spraying layer 2 is formed by spraying a vegetation base material on the entire slope 1.
(5) Net tensioning = Thick layer base spraying by thick base spraying layer 2 The net 10 is stretched around the surface of the thick base spraying layer 2 and anchor pins 11 are driven to stretch the surface of the thick layer base spraying layer. .
(6) Planting hole excavation (Part 2) = The vegetation base material sprayed on the excavated planting hole 6 is dug and removed.
However, in this excavation hole excavation (part 2), the net 10 that hinders seedling planting is excised.
(7) Seedling planting = planting seedlings 7 in the excavated planting hole 6 and filling the ground with the vegetation base material dug after planting.
(8) Net repair = A net cut at the time of excavation hole excavation (part 2) of (6) is pasted on the surface of the thick base material spray layer 2.
[0011]
【The invention's effect】
Since the present invention has the above-described configuration, it is possible to reliably plant trees by installing a log having a length necessary for planting in a place where a seedling or the like is to be planted. It is not necessary to install it across the entire lateral direction of the slope. In addition, by making a hole in the log and driving an anchor pin through it, the log can be securely fixed to the slope, and the slope of the slope becomes gentle and suitable for plant growth. The rainwater flowing on the slope temporarily stagnates in the upper part of the log and penetrates into the planting hole, increasing the moisture in the planting hole. Furthermore, it helps prevent the vegetation base material sprayed on the slope.
And before planting, planting holes are excavated in an appropriate shape according to the seedlings even on the slope with a hard soil hardness, and a vegetation base material suitable for the growth of plants is used as the soil for planting holes. Therefore, it becomes a nursery bed with excellent soil hardness and water retention.
In addition, due to the use of logs, logs are reduced to decayed soil over time. In addition, the anchor can be made of wood material such as bamboo skewers depending on the soil, so that everything is reduced to soil.
In addition, the use of thinned wood is low cost and useful for effective use. In addition, the thick layer base material sprayed on the planting hole on the slope can be used as the soil by refilling the seedlings planted as the soil. And, by planting the seedlings, the slope can be strengthened by the tension of the root system. As a result of the above, according to the present invention, since there is no waste material, finally, greening that is environmentally friendly and friendly to the earth can be obtained.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view in which the method of the present invention is applied to a thick layer base material spraying method.
FIG. 2 is a longitudinal sectional view in which the construction method of the present invention is applied to a thick layer base material sprayed with a lath tension work.
FIG. 3 is a longitudinal cross-sectional view in which the method of the present invention is applied to a thick layer base material sprayer that has been netted.
FIG. 4 is a longitudinal sectional view in which the construction method of the present invention is applied to a thick layer base material spraying method that has been subjected to lath stretching and net stretching.
FIG. 5 is a perspective view of a log used in the method of the present invention.
[Explanation of symbols]
1 ... Slope 2 ... Thick base material spray layer 3 ... Log using thinned wood 4 ... Through hole 5 in the log ... Wood anchor pin 6 allowing bamboo skewer ... Planting Tree hole 7 ... Seedling 8 ... Tension lath 9 ... Anchor pin
10 …… Net for installation
11 …… Anchor pin

Claims (1)

丸太を植栽穴径より長く切断し、且つ丸太の直径を長さの10分の1から5分の1程度に設定し、その端部から中央に略直径の長さで寄った位置の丸太に貫通孔(4)をあけ、その丸太を法面(1)の植栽をしようとする個所における横方向に配置すると共に、竹串を可とする頭部に鈎部がある木質アンカーピン(5)を丸太の貫通孔(4)に挿通して法面(1)に打ち込んで固定し、且つ固定した丸太の直上位置に植栽穴(6)を掘削した後、植生基盤材を法面(1)に吹付けて厚層基材吹付層(2)を形成し、且つ植栽穴部の厚層基材吹付層(2)を掘り取った後、苗木類(7)を植え込むと共に、掘り取った植生基盤材を埋め戻すようにしたことを特徴とする丸太による苗木植栽工法。The log is cut longer than the diameter of the planting hole, and the log diameter is set to about one-tenth to one-fifth of the length. A through hole (4) is drilled in the wood, and the log is placed in the horizontal direction at the location where the slope (1) is to be planted, and a wooden anchor pin with a buttock on the head allowing a bamboo skewer ( 5) is inserted into the log through hole (4) , driven into the slope ( 1) and fixed, and the planting hole (6) is excavated directly above the fixed log, and then the vegetation base material is by blowing in (1) to form a thick layer substrate sprayed layer (2), and after taking digging thickness layer substrate sprayed layer of planting栽穴portion (2), together with the implanted seedlings such a (7), A seedling planting method using logs, characterized in that the dug vegetation base material is backfilled.
JP10873598A 1998-04-02 1998-04-02 Seedling planting method by log Expired - Lifetime JP3721257B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10873598A JP3721257B2 (en) 1998-04-02 1998-04-02 Seedling planting method by log

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10873598A JP3721257B2 (en) 1998-04-02 1998-04-02 Seedling planting method by log

Publications (2)

Publication Number Publication Date
JPH11286939A JPH11286939A (en) 1999-10-19
JP3721257B2 true JP3721257B2 (en) 2005-11-30

Family

ID=14492205

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10873598A Expired - Lifetime JP3721257B2 (en) 1998-04-02 1998-04-02 Seedling planting method by log

Country Status (1)

Country Link
JP (1) JP3721257B2 (en)

Also Published As

Publication number Publication date
JPH11286939A (en) 1999-10-19

Similar Documents

Publication Publication Date Title
JP4223081B2 (en) Tree planting on the slope
US4809460A (en) Bank planter
JP3721257B2 (en) Seedling planting method by log
JP2789460B2 (en) Vegetation bag body and slope planting method using it
US4890417A (en) Bank planter
JPH06294132A (en) Slope protection greening work and vegitation member
JPH048236A (en) Planting method for ground cover plant or shrub using artificial turf
JP2004076389A (en) Vegetation net having greening foundation function
JP2003116357A (en) Stake for fixing plate material for planting
JP2717368B2 (en) Slope planting method
JPH10150862A (en) Vegetation protective cylinder and its method of use
JP3941195B2 (en) Revegetation method such as slope
JPH10140573A (en) Young plant planting method on slope face and slope face plating pot employed for the same system
JP2850021B2 (en) Slope greening method using anchor pins
JPS5930061Y2 (en) Equipment for installing soil bags on montal or concrete sprayed slopes
JP3030115U (en) Round pot for planting
RU2120729C1 (en) Method of growing trees on pavements for street landscaping
JPH07189260A (en) Garden planting method
JPH0351371Y2 (en)
JP2884225B2 (en) Planting soil protection frame
JP2660315B2 (en) Revegetation method such as slope using soil retaining stopper
JP3163329B2 (en) Sandbag for vegetation and method of constructing the sandbag
JP2003313873A (en) Slope covering implantable mat and method of covering slope with the mat
JPS63206519A (en) Slope vegetating work
JPS60338Y2 (en) Flowerpot for seawall planting

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20040722

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040820

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040825

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041007

A911 Transfer of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20041014

A912 Removal of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A912

Effective date: 20050114

R155 Notification before disposition of declining of application

Free format text: JAPANESE INTERMEDIATE CODE: R155

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050912

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090916

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090916

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100916

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100916

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110916

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120916

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130916

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term