JP3713556B2 - Tunnel widening equipment - Google Patents

Tunnel widening equipment Download PDF

Info

Publication number
JP3713556B2
JP3713556B2 JP2002083415A JP2002083415A JP3713556B2 JP 3713556 B2 JP3713556 B2 JP 3713556B2 JP 2002083415 A JP2002083415 A JP 2002083415A JP 2002083415 A JP2002083415 A JP 2002083415A JP 3713556 B2 JP3713556 B2 JP 3713556B2
Authority
JP
Japan
Prior art keywords
protector
gantry
extending
tunnel
protrusion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002083415A
Other languages
Japanese (ja)
Other versions
JP2003278478A (en
Inventor
英人 真下
浩久 蒲田
純一郎 中森
良夫 御手洗
光雄 益田
幸雄 垣内
英雄 神山
良博 安川
彦三 今岡
孝則 星野
敏晴 桜井
光生 渡辺
宏実 佐伯
義信 藤城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Furukawa Co Ltd
Tobishima Corp
Kumagai Gumi Co Ltd
Sato Kogyo Co Ltd
National Research and Development Agency Public Works Research Institute
Original Assignee
Furukawa Co Ltd
Public Works Research Institute
Tobishima Corp
Kumagai Gumi Co Ltd
Sato Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Furukawa Co Ltd, Public Works Research Institute, Tobishima Corp, Kumagai Gumi Co Ltd, Sato Kogyo Co Ltd filed Critical Furukawa Co Ltd
Priority to JP2002083415A priority Critical patent/JP3713556B2/en
Publication of JP2003278478A publication Critical patent/JP2003278478A/en
Application granted granted Critical
Publication of JP3713556B2 publication Critical patent/JP3713556B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、山脈や丘を貫通する既設の山岳トンネルの拡幅工事に用いられる、前記トンネル内に通路を確保するためのプロテクタと、前記トンネルの覆工の破砕およびその周囲地盤の掘削に用いられる装置を据え付けるための、前記プロテクタ上に載置される架台とを含むトンネル拡幅工事用設備に関する。
【0002】
【従来の技術】
狭小な既設山岳トンネルの拡幅を図るべく、機械装置や発破を用いて既設トンネルの覆工の破砕およびその周囲地盤の掘削を行った後、その破砕、掘削跡に既設トンネルより大きい断面を有する新たなトンネルを構築し、これにより既設トンネルを新たなトンネルに置き換えることが行われている。
【0003】
従来、既設トンネルの覆工の破砕およびその周囲地盤の掘削に際し、既設トンネル内に歩行者、車両等の通行を確保するための通行路を確保するためのプロテクタと、ブレーカ、切断機、穿孔機等からなる破砕・掘削装置および必要に応じて掘削後のトンネル壁面処理のための吹付けマニュピュレータのような吹付用装置が据え付けられる架台であってプロテクタ上にその伸長方向へ走行可能に載置された架台とを備えるトンネル拡幅工事用設備が提案されている(特開2000−328871)。
【0004】
これによれば、プロテクタ上で架台をその伸長方向へ移動させることにより、既設トンネルの破砕、掘削、吹き付け等の作業箇所をトンネルの軸線方向へ順次移動させることができる。
【0005】
トンネルの破砕、掘削、吹き付け等の作業は、架台をプロテクタ上に静止させる間に行われる。前記従来の設備にあっては、さらに、架台に設けられプロテクタの側方を下方へ伸びる複数の脚部と、各脚の下端部に取り付けられたアウトリガーとを備え、架台はアウトリガーの伸長動作によりトンネルの路面上に支持され、プロテクタに対する静止状態を維持される。
【0006】
ところで、前記従来の設備にあっては、架台から伸びる脚部がトンネル空間内における作業スペース、特にプロテクタの側方の作業スペースを狭めるという問題があり、また、プロテクタの側方の作業スペースに置かれる資材、ずり運搬用のベルトコンベヤ、ずり運搬車両等が前記脚部の進行の障害となり、プロテクタ上における架台の円滑な進行が妨げられる場合があった。
【0007】
【発明が解決しようとする課題】
したがって、本発明の目的は、拡幅対象である既設山岳トンネル内空間をより有効に活用し得るトンネル拡幅工事用設備を提供することにある。
【0008】
【課題を解決するための手段】
本発明に係るトンネル拡幅工事用設備は、拡幅される既設山岳トンネル内に配置され通行路を規定する頂部および両側部を有するプロテクタと、該プロテクタ上にその伸長方向へ走行可能に載置された、前記トンネルの覆工の破砕およびその周囲地盤の掘削に用いられる装置が据え付けられる架台と、前記プロテクタに前記架台を解除可能に固定する固定手段とを備える。
【0009】
前記固定手段は、前記プロテクタの各側部に設けられその伸長方向へ伸びる1又は複数の突起と、前記架台に設けられ前記突起を抱き込むように伸びる伸長部と、前記プロテクタの突起及び前記架台の伸長部間に配置されかつ前記突起及び前記架台のいずれか一方に支持された、上下方向へ伸びる複数のジャッキとからなるものとすることができる。
【0010】
好ましくは、前記プロテクタがその頂部とその各側部とに連なる斜め下方へ伸びる肩部を有し、また前記架台の伸長部が前記プロテクタの肩部に沿って伸びる傾斜部分を備える。また、前記架台がその各伸長部から水平に伸びる張出部を備えるものとすることができる。
【0011】
本発明に係る設備は、さらに、前記架台に支持され該架台に沿って伸びるベルトコンベヤを含むものとすることができる。前記ベルトコンベヤは、好ましくは、前記トンネルの覆工の破砕及びその周囲地盤の掘削によって生じたずりを運搬するために使用されるトラックの全長より長い長さ寸法を有する。さらに好ましくは、前記ベルトコンベヤの一部が残りの一部に対して揺動可能である。
【0012】
【発明の作用および効果】
本発明によれば、拡幅される山岳トンネル内に設置されるプロテクタに対し、該プロテクタ上を走行可能である架台を解除可能に固定する固定手段を設けたことから、前記トンネルの破砕、掘削等の作業の際、前記架台が移動、傾斜等しないようにこれを前記プロテクタに静止状態に保持することができる。このため、前記従来の設備におけるプロテクタ側方の脚及びアウトリガーの存在とこれに伴うプロテクタ側方の作業スペースの狭小化、作業スペースに置かれる資材、ずり運搬車両等による架台の進行障害等とを解消し、また前記作業スペースにおけるずり運搬車両の円滑な進行を確保することができる。
【0013】
前記固定手段は、前記プロテクタの各側部に設けられた突起と、前記架台に設けられ前記突起を抱き込むように伸びる伸長部と、前記突起及び前記伸長部間に配置されかつ前記突起及び前記架台のいずれか一方に支持された、上下方向へ伸びる複数のジャッキとからなるものとするときは、前記ジャッキの伸長動作による該ジャッキの両端部の前記突起及び前記伸長部に対する圧接、及びその収縮動作による前記圧接の解除により、前記プロテクタに対する前記架台の固定及びその解除を容易かつ確実に行うことができる。
【0014】
また、前記ジャッキの収縮動作により移動可能状態におかれた前記架台は、その移動の間に傾きが生じたとき、前記突起又は伸長部と前記ジャッキとの相互接触により、その傾きが矯正され、また過剰な傾斜の発生が防止される。前記架台下の作業スペースは、前記突起および前記伸長部の高さ位置をより上位におくことにより、より広いものとすることができる。
【0015】
前記プロテクタにその頂部からその側部に連なる、斜め下方に伸びる肩部を設け、また、前記架台の伸長部に、前記プロテクタの肩部に沿って伸びる傾斜部分を設けるときは、前記架台の上方により大きい作業スペースを確保することができる。
【0016】
前記架台の伸長部から水平に伸びる張出部を設けるときは、前記トンネル覆工の破砕及びその周囲地盤の掘削の作業のための作業床の面積を増大することができる。
【0017】
前記架台にベルトコンベヤを支持するときは、前記プロテクタの側方の作業スペースを規定するトンネル内路面上へのベルトコンベヤの設置を不要とし、これにより前記作業スペースをより有効に活用することができる。
【0018】
前記トンネルの拡幅工事により生じたずりは、前記プロテクタ上の架台に支持された前記ベルトコンベヤを介して、前記プロテクタの側方の作業スペースで待機するずり搬送車両であるトラックに搬送することができる。前記ベルトコンベヤは、トラックの上方位置に配置されかつその長さ寸法がトラックの全長より長いことから、ずりの一時的な集積又は堆積場所から、少なくとも1台のトラックの長さを越えた場所にずりを搬送することができる。このため、トラックの待機台数を複数として、ずりの堆積場所から遠いトラックから近い方のトラックに順にずりを搬送し、積み込むことができる。
【0019】
これにより、1台のトラックの積込み量を超える多量のずりが発生した場合にあってもずりの搬出処理を遅滞なく円滑に行うことができる。また、前記作業スペースを出入りするトラックと前記プロテクタ内の通行車両との交通整理については、一時に出入りするトラックの台数を複数に設定することにより、その回数を減らし、トラックの入れ替えに要する時間を節減することができる。その結果、既設山岳トンネルの拡幅工事により生じるずりの搬出能率を高めることができる。
【0020】
前記ベルトコンベヤの一部を残りの一部に対して揺動可能とするときは、前記一部が残りの一部と共に一直線に伸びる状態と、残りの一部に対して折れ曲がり下方に傾斜する状態とすることができる。一直線に伸びる状態下ではその下方を作業スペースとして利用することができる。また、前記傾斜状態下におくときは、前記ベルトコンベヤ上へのずりの載置作業を容易にすることができる。
【0021】
【発明の実施の形態】
図1を参照すると、馬蹄形の既設の山岳トンネル10と、該トンネルの拡幅のために新たに構築される、既設トンネル10より大きい断面を有する馬蹄形の新たなトンネル12とが、それぞれ、想像線と実線とで示されている。
【0022】
新たなトンネル12は、既設トンネル10の覆工(図示せず)を破砕し、さらにその周囲地盤14を掘削した後、その掘削壁面に沿って構築される。既設トンネル10の覆工の破砕およびその周囲地盤14の掘削(発破による掘削を含む)並びに新トンネル12の構築は、既設トンネル10の一端(後方端)からその他端(前方端)に向けて段階的に行われる。なお、図示の周囲地盤14は、トンネル10の他端側に残る未掘削のものを示す。
【0023】
既設トンネル10の覆工の破砕およびその周囲地盤14の掘削の箇所並びにその近傍における通行人や一般車両の通行及びその安全を確保するため、既設トンネル10内に通行路を規定するプロテクタ16が配置されている。また、プロテクタ16上には、前記破砕および掘削に使用される後記破砕・掘削装置を設置するための架台18が載置されている。プロテクタ16及び架台18、並びに後記固定手段30,34,40は、トンネル拡幅工事用設備を構成する。
【0024】
図示のプロテクタ16は全体に逆U字形の横断面形状を有し、その頂部20および両側部22が、既設トンネル10の軸線方向に関して、前記破砕・掘削箇所およびその前後に亘って伸びている(図2で見て左方が前方)。
【0025】
図示のプロテクタ16は、さらに、その頂部20とその各側部22とに連なりかつ斜め下方へ伸びる肩部24を有する。このような肩部24を有しない、互いに直交する頂部および両側部とからなるプロテクタとすることも可能であるが、肩部24を設けるときは、これを設けないときに現れる角部が存しないため、プロテクタ16の上方により広い作業空間を得ることができる。
【0026】
プロテクタ16は既設トンネル10内の路面26上に配置され、トンネル10の壁面(覆工壁面)との間に作業スペースとしての側方空間28が存する。図示の例では、プロテクタ16はトンネル10の横断方向におけるほぼ中央部に位置するが、必要に応じて、前記中央部以外の位置におかれる。
【0027】
プロテクタ16は、その各側部(より詳細には各側部の内外両側面のうちの外側の面)22に、その伸長方向へ連続して伸びる突条からなる1の突起30を有する。
【0028】
突起30は、プロテクタの側部22のより上位の位置に配置することが望ましい。これにより、突起30とほぼ同じ高さ位置を占めることとなる、架台18に設けられた後記伸長部34の下方に、より広い側方空間28を得ることができ、ここに工事資材や機器、後記トラック50,52、シャフローダ54等を配置することができ、また、これらは架台18の移動の障害とならない。図示の例では、突起30は肩部24の直下に位置する。
【0029】
突起30は、連続して伸びる1の突条からなるものに代えて、例えば、断続して伸びる複数の突条からなるものとすることができる。また、前記突条の横断面形状は任意に定めることができる。図示の例では、矩形の横断面形状を有する。
【0030】
プロテクタ16は、前記破砕および掘削の進行(前進)に合わせて、路面26上をトンネルの軸線方向へ移動される。この移動のため、図示の例では、路面26上に1対のレール(図示せず)が敷かれ、プロテクタの両側部22下に両レール上を走行可能の複数対の車輪(図示せず)が設けられる。
【0031】
架台18は、プロテクタ16の頂部20上にあってこれと相対する板状の本体32と、本体32に連なる一対の伸長部34とを有する。両伸長部34は、それぞれ、プロテクタの両側部22に位置する突起30を抱き込むように、本体32から下方へ伸びている。
【0032】
好ましくは、さらに、両伸長部34からそれぞれ水平に張り出す一対の張出部36を有する。これによれば、側方空間28の上方に、架台18上における前記装置の設置スペースおよびその操作スペースの増大を図ることができる。
【0033】
架台18は、プロテクタ16上をその長手方向へ走行可能である。このため、図示の例では、プロテクタの頂部20に設けられその伸長方向へ伸びる2条のレール35上を転動可能である複数の車輪37が、架台の本体32に回転可能に支承されている。
【0034】
架台の伸長部34は、プロテクタの突起30を抱き込み、これを受け入れる凹所38を有する。凹所38は、架台18の伸長方向へ伸びかつプロテクタの側部22に向けて開放している。
【0035】
伸長部34とプロテクタの突起30との間、すなわち伸長部の凹所38にはその伸長方向へ互いに間隔をおいて複数のジャッキ40が配置されている。より詳細には、各ジャッキ40は、伸長部34の下部と突起30との間に上下に向けて配置されかつ伸長部34に支持されている。ジャッキ40は、油圧ジャッキのような液圧ジャッキ、スクリュージャッキ等からなる。ジャッキ40は、プロテクタの突起30及び架台の伸長部34と共に、架台18をプロテクタ16に解除固定するための固定手段をなす。
【0036】
収縮状態にある図示のジャッキ40を突起30に当接するまで伸長動作させると、ジャッキ40の上下両端が伸長部34と突起30とに圧接し、実質的に、架台18をプロテクタ16に固定することができる。この固定により、架台18をプロテクタ16上に傾斜、移動等しない静止状態に保持することができ、この間に後記破砕・掘削装置を用いての既設トンネル10の破壊、周囲地盤の掘削作業、あるいはさらにその後の吹き付け作業を安定的に行うことができる。
【0037】
他方、収縮状態におかれたジャッキ40の下で、すなわち前記固定を解除した状態において、プロテクタ16上における架台18の移動を可能とすることができる。ジャッキ40は、架台16の移動時にこれが傾くときにプロテクタの突起30に当たり、架台16の傾斜を制限する作用をなす。
【0038】
ジャッキ40は、図示の例に代えて、プロテクタの突起30に取り付け、該突起から垂下するようにしてもよい。
【0039】
図示の架台18にあっては、伸長部34が、プロテクタの両肩部24の上方をこれに沿って伸びる傾斜部分42を有する。
【0040】
架台18の各伸長部に傾斜部分42を設けた結果、プロテクタに肩部24を設けることによって得られた前記プロテクタ上方の広い作業空間の狭小化を回避することができる。ただし、傾斜部分42を有しない架台、すなわち本体32と伸長部34とが互いに直交する架台を使用することは任意である。
【0041】
架台の本体22および各張出部36上には、既設トンネル10の覆工の破砕、その周囲地盤14の掘削、周囲地盤14中への装薬等を行うために用いられるブレーカ、切断機、穿孔機等からなる破砕・掘削装置、あるいはこれらに加えて吹付けマニュピュレータのような吹付用装置(図示せず)が据え付けられる。前記破砕・掘削装置は架台18上での作業員による操作により、その前方に位置する前記覆工および地盤14に対して破砕・掘削作用を及ぼす。
【0042】
この破砕・掘削作用により生じた破砕片および掘削片(以下、これらを総称して「ずり」という。)は、その一部が架台18上に落下し、また、他の一部が、プロテクタ16の両側方、すなわちプロテクタ16と前記破砕・掘削作用により現れた新設トンネル12の壁面との間の側方空間28を落下する。架台18上のずりは、人為的に、各側方空間28に落とされ、各側方空間28を規定する新旧両トンネル10,12の底面上に堆積する。
【0043】
架台18の各張出部36の下部には前記ずりを搬送するためのベルトコンベヤ48が吊持、支持されている。
【0044】
各側方空間28は、また、ベルトコンベヤ48で搬送されたずりを受け取り、これを満載してトンネル12外に搬出するためのダンプカーのようなトラック50,52のための走行用スペースを提供する。張出部36に支持されたベルトコンベヤ48は、前記トラックの全高すなわちその天井面より高い上方位置にあり、この上方位置から前記トラックの荷台上にずりを放出、落下させることができる。
【0045】
各側方空間28の底面に落下し、堆積した前記ずりは、側方空間28に導入することができる例えばシャフローダ54を用いて、ベルトコンベヤ48上に載置することができる。シャフローダ54は前記ずりを掬い集め、さらにベルトコンベヤ48上に移送する機能を有する。
【0046】
図示のベルトコンベヤ48は、架台の張出部36に固定され該張出部に沿って伸びる第1のコンベヤ部56と、該第1のコンベヤ部に連結された第2のコンベヤ部58とからなる。前記ずりは、第2のコンベヤ部58から第1のコンベヤ部56へ搬送される。
【0047】
第2のコンベヤ部58は、その後端部において、第1のコンベヤ部56の前端部に枢着され、架台18を横断する方向へ伸びる軸60の周りに揺動可能である。第2のコンベヤ部56は、また、その前端部において、チェーンブロック62を介して、架台の張出部36に吊持されている。
【0048】
第2のコンベヤ部58は、チェーンブロック62を作動させてそのチェーンを巻き上げることにより、これが張出部36下において水平状態となるまで、図2に示す傾斜状態から時計方向へ揺動させることができる。水平状態下においては、その下方領域を作業空間として利用することができる。
【0049】
また、チェーンブロック62のチェーンを繰り出すことにより、第2のコンベヤ部58を前記水平状態から反時計方向へ揺動させ、前記傾斜状態にすることができる。シャフローダ54からの前記ずりの受け取りは、この傾斜状態において行う。
【0050】
なお、第2のコンベヤ部58を揺動可能としないで、第1のコンベヤ部56と同様に、架台の張出部36にこれに沿って伸びるように固定することもできる。第2のコンベヤ部58を非揺動のものとした場合、および第2のコンベヤ部58を前記水平状態に維持した場合のいずれにおいても、第2のコンベヤへ部58のずりの載置は可能である。ずりの載置は、適当な機械的手段を使用して行うことができる。
【0051】
第2のコンベヤ部58は、シャフローダ54から受け取ったずりを第1のコンベヤ部56の前端部上まで運び、第1のコンベヤ部56は受け取ったずりをその後端部から側方空間28に放出する。
【0052】
放出されたずりは、第1のコンベヤ部56下に予め待機しているトラック52の荷台上に落下する。このトラック52の後方には他のトラック50が同様に待機している。
【0053】
ベルトコンベヤ48はその全長、すなわち第1および第2の両コンベヤ部56,58の合計長さが、前方位置のトラック52の全長より長いものに設定されている。このため、トラック52の前方位置から、該トラックを越えて、その後方位置で待機するトラック50までのずりの移送が可能である。他のトラック52へのずりの載置は、ずりで満載のトラック50を後方へ移動した跡に他のトラック52を移動させて行う。
【0054】
空荷状態の複数台のトラックを待機させておけば、1台のトラックの積込み量を超える多量のずりが発生した場合であっても、余裕を持ってずりを受け取りかつ円滑に搬出することができる。
【0055】
満載後のトラック50は、他のトラック52が満載になるのを待って、トラック52と共に一時にプロテクタの側方空間28外に移動させることができる。これにより、側方空間28外へのトラックの移動を1台ずづ行う場合と比べて、側方空間28外における一般車両に対する交通整理の回数を少なくすることができる。
【0056】
ベルトコンベヤ48の全長はより長いものに設定することができる。これによれば、さらに多くの台数のトラックを側方空間28に待機させ、より多くの台数を越える距離にわたるずりの移送が可能である。例えば、ベルトコンベヤの全長を2台分のトラックの長さより長いものに設定すれば、2台の待機トラックの後方で待機する1台のトラックにずりを移送し、満載後、その前方のトラックに対し順次ずりを移送することができる。なお、ベルトコンベヤ48の全長を増大するときは、これに応じて、ベルトコンベヤ48を支持する架台18の長さ寸法をより大きいものに設定する必要がある。
【0057】
図示の例では、トラックが走行可能である側方空間28がプロテクタ16の両側に設けられ、これに合わせて、ベルトコンベヤ48が架台の両側の張出部36に支持されているが、いずれか一方の側方空間28が比較的狭いときは、他方の側方空間28に関してのみ、ベルトコンベヤ48を配置することができる。
【図面の簡単な説明】
【図1】本発明に係るトンネル拡幅工事用設備の正面図である。
【図2】本発明に係るトンネル拡幅工事用設備の側面図である。
【符号の説明】
10 既設の山岳トンネル
12 新たなトンネル
14 周囲地盤
16,18 プロテクタ及び架台(トンネル拡幅工事用設備)
24,42 プロテクタの肩部及び架台の傾斜部分
28 トンネル内プロテクタの側方空間
30,34,40 突起、伸長部及びジャッキ(固定手段)
36 架台の張出部
48,56,58 ベルトコンベヤ、その第1のベルトコンベヤ部及びその第2のベルトコンベヤ部
[0001]
BACKGROUND OF THE INVENTION
The present invention is used for widening an existing mountain tunnel that penetrates a mountain range or a hill, and is used for crushing the tunnel lining and excavating the surrounding ground, and a protector for securing a passage in the tunnel. The present invention relates to a facility for widening a tunnel including a gantry placed on the protector for installing the device.
[0002]
[Prior art]
In order to widen a narrow existing mountain tunnel, after crushing the lining of the existing tunnel and excavating the surrounding ground using machinery and blasting, the crushing and excavation site has a new cross section that is larger than the existing tunnel. A new tunnel is constructed, and the existing tunnel is replaced with a new tunnel.
[0003]
Conventionally, a protector, breaker, cutting machine, drilling machine for securing a passage for securing pedestrians, vehicles, etc. in the existing tunnel when crushing the lining of the existing tunnel and excavating the surrounding ground It is a mount on which a spraying device such as a spraying manipulator for processing the tunnel wall surface after excavation is installed, and is mounted on a protector so as to be able to travel in its extending direction. There has been proposed a tunnel widening facility equipped with a mounted base (Japanese Patent Laid-Open No. 2000-328871).
[0004]
According to this, by moving the gantry in the extending direction on the protector, it is possible to sequentially move work points such as crushing, excavation, and blowing of the existing tunnel in the axial direction of the tunnel.
[0005]
Operations such as tunnel crushing, excavation, and spraying are performed while the gantry rests on the protector. The conventional equipment further includes a plurality of legs provided on the pedestal and extending downward on the side of the protector, and an outrigger attached to the lower end of each leg. It is supported on the road surface of the tunnel and is kept stationary with respect to the protector.
[0006]
By the way, the conventional equipment has a problem that the leg portion extending from the gantry narrows the work space in the tunnel space, particularly the work space on the side of the protector, and is placed in the work space on the side of the protector. Materials to be scraped, belt conveyors for shear transport, shear transport vehicles, and the like become obstacles to the progress of the legs, and the smooth progress of the mount on the protector may be hindered.
[0007]
[Problems to be solved by the invention]
Accordingly, an object of the present invention is to provide a tunnel widening facility that can more effectively utilize the space in an existing mountain tunnel that is to be widened.
[0008]
[Means for Solving the Problems]
A tunnel widening construction facility according to the present invention is placed in an existing mountain tunnel to be widened, and is mounted on a protector having a top portion and both side portions that define a passageway, and can travel in the extending direction on the protector. A gantry on which a device used for crushing the tunnel lining and excavating the surrounding ground is installed, and a fixing means for releasably fixing the gantry to the protector.
[0009]
The fixing means includes one or a plurality of protrusions provided on each side portion of the protector and extending in the extending direction; an extension portion provided on the mount and extending so as to embrace the protrusion; the protrusion of the protector and the mount And a plurality of jacks that are arranged between the extending portions and are supported by one of the protrusion and the gantry and extend in the vertical direction.
[0010]
Preferably, the protector has a shoulder portion extending obliquely downward from the top portion and each side portion thereof, and the extension portion of the gantry includes an inclined portion extending along the shoulder portion of the protector. Moreover, the said mount frame shall be equipped with the overhang | projection part extended horizontally from each extension part.
[0011]
The facility according to the present invention may further include a belt conveyor supported by the frame and extending along the frame. The belt conveyor preferably has a length dimension that is longer than the total length of the truck used to carry the shear generated by crushing the tunnel lining and excavating the surrounding ground. More preferably, a part of the belt conveyor is swingable with respect to the remaining part.
[0012]
Operation and effect of the invention
According to the present invention, the protector installed in the mountain tunnel to be widened is provided with the fixing means for releasably fixing the cradle that can run on the protector, so that the tunnel is crushed, excavated, etc. During the operation, the frame can be held stationary by the protector so that the pedestal does not move or tilt. For this reason, the presence of the legs and outriggers on the side of the protector in the conventional equipment and the accompanying reduction in the work space on the side of the protector, the materials placed in the work space, the progress of the pedestal due to the shear transport vehicle, etc. It is possible to eliminate this problem and to ensure the smooth progress of the shear transport vehicle in the work space.
[0013]
The fixing means includes a protrusion provided on each side of the protector, an extension provided on the pedestal and extending to embrace the protrusion, and disposed between the protrusion and the extension, and the protrusion and the When it is composed of a plurality of jacks that are supported by any one of the pedestals and extend in the vertical direction, the jacks are pressed against the protrusions and the extension parts at both ends by the extension operation of the jacks, and the contraction thereof. By releasing the pressure contact by operation, the frame can be fixed to the protector and released easily and reliably.
[0014]
In addition, when the pedestal placed in a movable state by the contraction operation of the jack is tilted during the movement, the tilt is corrected by mutual contact between the protrusion or the extension and the jack, In addition, excessive inclination is prevented from occurring. The work space under the gantry can be made wider by placing the height positions of the protrusions and the extension part higher.
[0015]
When the protector is provided with a shoulder extending from the top to the side thereof and extending obliquely downward, and when an inclined portion extending along the shoulder of the protector is provided at the extension of the mount, the top of the mount A larger working space can be secured.
[0016]
When an overhanging portion that extends horizontally from the extending portion of the gantry is provided, the area of the work floor for the operation of crushing the tunnel lining and excavating the surrounding ground can be increased.
[0017]
When the belt conveyor is supported on the gantry, it is not necessary to install a belt conveyor on the road surface in the tunnel that defines the working space on the side of the protector, thereby making it possible to use the working space more effectively. .
[0018]
The shear generated by the widening work of the tunnel can be transported to a truck which is a shear transport vehicle waiting in a work space on the side of the protector via the belt conveyor supported by a mount on the protector. . The belt conveyor is located above the track and has a length dimension that is longer than the total length of the track, so that the belt conveyor is located at a location beyond the length of at least one track from the temporary accumulation or deposition location of the shear. The shear can be conveyed. For this reason, it is possible to transport and load the slurries in order from a truck far from the position where the sludge is accumulated, to a truck closer to the truck, where a plurality of trucks are waiting.
[0019]
As a result, even when a large amount of slip exceeding the loading amount of one truck occurs, the carry-out processing of the slip can be smoothly performed without delay. In addition, regarding the traffic control between the trucks entering and exiting the work space and the passing vehicles in the protector, the number of trucks entering and exiting at a time can be set to a plurality, thereby reducing the number of times and the time required for the replacement of the trucks. You can save. As a result, it is possible to increase the efficiency of carrying out the shear generated by the widening work of the existing mountain tunnel.
[0020]
When a part of the belt conveyor is swingable with respect to the remaining part, the part extends in a straight line with the remaining part, and the part is bent and inclined downward with respect to the remaining part. It can be. Under a straight line, the lower part can be used as a work space. Further, when placed in the inclined state, it is possible to facilitate the work of placing the shear on the belt conveyor.
[0021]
DETAILED DESCRIPTION OF THE INVENTION
Referring to FIG. 1, a horseshoe-shaped existing mountain tunnel 10 and a new horseshoe-shaped tunnel 12 that is newly constructed for widening the tunnel and has a cross section larger than that of the existing tunnel 10, respectively, It is shown with a solid line.
[0022]
The new tunnel 12 is constructed along the excavation wall surface after crushing the lining (not shown) of the existing tunnel 10 and excavating the surrounding ground 14. The crushing of the lining of the existing tunnel 10 and the excavation of the surrounding ground 14 (including excavation by blasting) and the construction of the new tunnel 12 are staged from one end (rear end) to the other end (front end) of the existing tunnel 10 Done. In addition, the surrounding ground 14 shown in the figure indicates an unexcavated one that remains on the other end side of the tunnel 10.
[0023]
In order to ensure the passage of the lining of the existing tunnel 10 and the excavation of the surrounding ground 14 as well as the passage of passersby and general vehicles in the vicinity and the safety thereof, a protector 16 that defines the passage is arranged in the existing tunnel 10. Has been. Further, on the protector 16, a gantry 18 for placing a crushing and excavating device described later used for the crushing and excavation is placed. The protector 16 and the gantry 18, and fixing means 30, 34, and 40 described later constitute a tunnel widening facility.
[0024]
The illustrated protector 16 has an inverted U-shaped cross-sectional shape as a whole, and its top portion 20 and both side portions 22 extend over the crushing / excavation site and its front and rear in the axial direction of the existing tunnel 10 ( The left side in FIG.
[0025]
The illustrated protector 16 further includes a shoulder portion 24 that extends from the top portion 20 and the side portions 22 thereof and extends obliquely downward. Although it is possible to provide a protector having a top part and two side parts orthogonal to each other without the shoulder part 24, when the shoulder part 24 is provided, there is no corner that appears when the shoulder part 24 is not provided. Therefore, a wider working space can be obtained above the protector 16.
[0026]
The protector 16 is disposed on a road surface 26 in the existing tunnel 10, and a side space 28 as a work space exists between the tunnel 10 and a wall surface (lining wall surface). In the illustrated example, the protector 16 is located at a substantially central portion in the transverse direction of the tunnel 10, but may be placed at a position other than the central portion as necessary.
[0027]
The protector 16 has one projection 30 formed of a ridge that continuously extends in the extending direction on each side portion (more specifically, the outer surface of both inner and outer side surfaces of each side portion) 22.
[0028]
It is desirable to arrange the protrusion 30 at a position higher than the side part 22 of the protector. As a result, a wider side space 28 can be obtained below the extended portion 34 provided on the gantry 18 that occupies substantially the same height as the protrusion 30, where construction materials and equipment, Tracks 50 and 52, a shaflower 54, and the like which will be described later can be disposed, and these do not hinder the movement of the gantry 18. In the illustrated example, the protrusion 30 is located immediately below the shoulder 24.
[0029]
The protrusion 30 may be composed of, for example, a plurality of protrusions extending intermittently instead of one protrusion extending continuously. Moreover, the cross-sectional shape of the said protrusion can be defined arbitrarily. In the illustrated example, it has a rectangular cross-sectional shape.
[0030]
The protector 16 is moved on the road surface 26 in the axial direction of the tunnel in accordance with the progress (advance) of the crushing and excavation. For this movement, in the illustrated example, a pair of rails (not shown) are laid on the road surface 26, and a plurality of pairs of wheels (not shown) that can travel on both rails under the side portions 22 of the protector. Is provided.
[0031]
The gantry 18 has a plate-like main body 32 on the top portion 20 of the protector 16 and opposed thereto, and a pair of extending portions 34 connected to the main body 32. Both extending portions 34 extend downward from the main body 32 so as to embrace the protrusions 30 located on both side portions 22 of the protector.
[0032]
Preferably, it further has a pair of overhang | projection parts 36 which each project horizontally from both the extending parts 34. According to this, it is possible to increase the installation space for the apparatus and the operation space on the gantry 18 above the side space 28.
[0033]
The gantry 18 can travel in the longitudinal direction on the protector 16. For this reason, in the illustrated example, a plurality of wheels 37 provided on the top 20 of the protector and capable of rolling on the two rails 35 extending in the extending direction are rotatably supported by the main body 32 of the gantry. .
[0034]
The gantry extension 34 has a recess 38 that embraces and receives the protector protrusion 30. The recess 38 extends in the extending direction of the gantry 18 and opens toward the side 22 of the protector.
[0035]
A plurality of jacks 40 are arranged between the extension portion 34 and the protrusion 30 of the protector, that is, in the recess 38 of the extension portion, spaced from each other in the extension direction. More specifically, each jack 40 is arranged vertically between the lower part of the extension part 34 and the protrusion 30 and supported by the extension part 34. The jack 40 includes a hydraulic jack such as a hydraulic jack, a screw jack, or the like. The jack 40 together with the projection 30 of the protector and the extension part 34 of the mount constitute a fixing means for releasing and fixing the mount 18 to the protector 16.
[0036]
When the illustrated jack 40 in a contracted state is extended until it comes into contact with the protrusion 30, the upper and lower ends of the jack 40 are pressed against the extended portion 34 and the protrusion 30, and the gantry 18 is substantially fixed to the protector 16. Can do. By this fixing, the gantry 18 can be held stationary on the protector 16 without being tilted, moved, etc. During this time, the existing tunnel 10 is destroyed using the crushing / excavating device described later, the excavation work of the surrounding ground, or further Subsequent spraying operations can be performed stably.
[0037]
On the other hand, the gantry 18 can be moved on the protector 16 under the jack 40 placed in the contracted state, that is, in the state where the fixing is released. The jack 40 abuts against the protrusion 30 of the protector when the gantry 16 is tilted when the gantry 16 is moved, and acts to limit the tilt of the gantry 16.
[0038]
Instead of the illustrated example, the jack 40 may be attached to the protrusion 30 of the protector and suspended from the protrusion.
[0039]
In the illustrated gantry 18, the extending portion 34 has an inclined portion 42 that extends along and above the shoulder portions 24 of the protector.
[0040]
As a result of providing the inclined portion 42 in each extending part of the gantry 18, it is possible to avoid the narrowing of the wide working space above the protector obtained by providing the shoulder 24 on the protector. However, it is optional to use a gantry that does not have the inclined portion 42, that is, a gantry in which the main body 32 and the extending portion 34 are orthogonal to each other.
[0041]
On the main body 22 of the gantry and each overhang portion 36, a breaker, a cutting machine, etc. used for crushing the lining of the existing tunnel 10, excavating the surrounding ground 14, charging the surrounding ground 14, etc. A crushing / excavating device such as a drilling machine, or a spraying device (not shown) such as a spraying manipulator is installed. The crushing / excavating device exerts a crushing / excavating action on the lining and the ground 14 located in front of the crushing / excavating device by an operation by a worker on the gantry 18.
[0042]
Part of the crushed pieces and excavated pieces (hereinafter collectively referred to as “slip”) generated by the crushing and excavating action fall on the mount 18, and the other part is the protector 16. , That is, a side space 28 between the protector 16 and the wall surface of the new tunnel 12 that appears due to the crushing and excavating action. The shear on the gantry 18 is artificially dropped into the side spaces 28 and is deposited on the bottom surfaces of the old and new tunnels 10 and 12 that define the side spaces 28.
[0043]
A belt conveyor 48 for conveying the shear is suspended and supported at the lower part of each overhang portion 36 of the gantry 18.
[0044]
Each side space 28 also provides a traveling space for trucks 50 and 52 such as dump trucks for receiving the shear conveyed by the belt conveyor 48 and loading it out of the tunnel 12. . The belt conveyor 48 supported by the overhanging portion 36 is at an upper position higher than the total height of the truck, that is, higher than the ceiling surface, and the shear can be discharged and dropped from the upper position onto the truck bed.
[0045]
The above-mentioned shear that falls and accumulates on the bottom surface of each side space 28 can be placed on the belt conveyor 48 by using, for example, a shrouder 54 that can be introduced into the side space 28. The shuffler 54 has a function of scooping and collecting the above-mentioned shear and further transferring it onto the belt conveyor 48.
[0046]
The illustrated belt conveyor 48 includes a first conveyor unit 56 that is fixed to and extends along the overhang 36 of the gantry, and a second conveyor unit 58 that is coupled to the first conveyor unit. Become. The shear is conveyed from the second conveyor unit 58 to the first conveyor unit 56.
[0047]
The second conveyor portion 58 is pivotally attached to the front end portion of the first conveyor portion 56 at the rear end portion thereof, and can swing around an axis 60 extending in a direction transverse to the gantry 18. The second conveyor portion 56 is also suspended at the front end portion of the gantry overhanging portion 36 via the chain block 62.
[0048]
The second conveyor section 58 can be swung clockwise from the tilted state shown in FIG. 2 until the chain block 62 is actuated to wind up the chain until it becomes horizontal under the overhanging section 36. it can. Under the horizontal state, the lower area can be used as a work space.
[0049]
Further, by feeding out the chain of the chain block 62, the second conveyor portion 58 can be swung counterclockwise from the horizontal state to be in the inclined state. The shear is received from the shroud 54 in this inclined state.
[0050]
It should be noted that the second conveyor portion 58 can be fixed so as to extend along the extension portion 36 of the gantry in the same manner as the first conveyor portion 56 without making the second conveyor portion 58 swingable. Whether the second conveyor unit 58 is non-oscillating or the second conveyor unit 58 is maintained in the horizontal state, the section 58 can be placed on the second conveyor. It is. The placement of the shear can be performed using suitable mechanical means.
[0051]
The second conveyor part 58 carries the shear received from the shafluder 54 onto the front end of the first conveyor part 56, and the first conveyor part 56 discharges the received shear from the rear end to the side space 28. .
[0052]
The released shear falls on the loading platform of the truck 52 waiting in advance under the first conveyor unit 56. Other trucks 50 are also waiting behind the truck 52 in the same manner.
[0053]
The belt conveyor 48 is set to have a total length, that is, a total length of both the first and second conveyor portions 56 and 58 longer than the total length of the track 52 at the front position. For this reason, it is possible to transfer the shear from the front position of the truck 52 to the truck 50 that waits at the rear position beyond the truck. The placement of the slip on the other track 52 is performed by moving the other track 52 to the trace where the track 50 full of the slip is moved backward.
[0054]
If multiple trucks that are in an unloaded state are placed on standby, even if a large amount of slip occurs that exceeds the loading amount of a single truck, it is possible to receive the slip with sufficient margin and carry it out smoothly. it can.
[0055]
The fully loaded track 50 can be moved out of the side space 28 of the protector together with the track 52 after waiting for the other tracks 52 to be fully loaded. Thereby, compared with the case where one truck is moved outside the side space 28, the number of times of traffic control with respect to the general vehicle outside the side space 28 can be reduced.
[0056]
The overall length of the belt conveyor 48 can be set longer. According to this, it is possible to make a larger number of trucks stand by in the side space 28 and transfer the shear over a distance exceeding the larger number of trucks. For example, if the total length of the belt conveyor is set to be longer than the length of two trucks, the shear is transferred to one truck waiting behind two standby trucks, and then loaded to the truck ahead of it Sequential shears can be transferred. When the overall length of the belt conveyor 48 is increased, the length of the gantry 18 that supports the belt conveyor 48 needs to be set larger.
[0057]
In the illustrated example, the side spaces 28 in which the truck can run are provided on both sides of the protector 16, and the belt conveyors 48 are supported by the overhang portions 36 on both sides of the gantry. When one side space 28 is relatively narrow, the belt conveyor 48 can be disposed only with respect to the other side space 28.
[Brief description of the drawings]
FIG. 1 is a front view of a tunnel widening facility according to the present invention.
FIG. 2 is a side view of the tunnel widening facility according to the present invention.
[Explanation of symbols]
10 Existing mountain tunnel 12 New tunnel 14 Surrounding ground 16, 18 Protector and mount (equipment for tunnel widening work)
24, 42 Shoulder part of the protector and inclined part 28 of the frame 28 Side space 30, 34, 40 of the protector in the tunnel Projection, extension part and jack (fixing means)
36 Overhang portions 48, 56, and 58 of belt frame, its first belt conveyor portion and its second belt conveyor portion

Claims (7)

拡幅される既設山岳トンネル内に配置され通行路を規定する頂部および両側部を有するプロテクタと、該プロテクタ上にその伸長方向へ走行可能に載置された、前記トンネルの覆工の破砕およびその周囲地盤の掘削に用いられる装置が据え付けられる架台と、前記プロテクタに前記架台を解除可能に固定する固定手段とを含む、トンネル拡幅工事用設備。A protector having a top portion and both side portions that are arranged in an existing mountain tunnel to be widened and that defines a passage, and a shroud of the tunnel lining and its surroundings placed on the protector so as to be able to travel in the extending direction A facility for tunnel widening work, comprising a gantry on which a device used for excavating the ground is installed, and a fixing means for releasably fixing the gantry to the protector. 前記固定手段は、前記プロテクタの各側部に設けられその伸長方向へ伸びる1又は複数の突起と、前記架台に設けられ前記突起を抱き込むように伸びる伸長部と、前記プロテクタの突起及び前記架台の伸長部間に配置されかつ前記突起及び前記架台のいずれか一方に支持された、上下方向へ伸びる複数のジャッキとからなる、請求項1に記載の設備。The fixing means includes one or a plurality of protrusions provided on each side portion of the protector and extending in an extending direction thereof, an extension portion provided on the mount and extending so as to embrace the protrusion, the protrusion of the protector, and the mount The equipment according to claim 1, comprising a plurality of jacks extending in the vertical direction and disposed between the extending portions of the two and supported by one of the protrusion and the gantry. 前記プロテクタはその頂部とその各側部とに連なる斜め下方へ伸びる肩部を有し、また前記架台の伸長部が前記プロテクタの肩部に沿って伸びる傾斜部分を備える、請求項2に記載の設備。3. The protector according to claim 2, wherein the protector has a shoulder extending obliquely downward from the top and each side thereof, and the extension of the pedestal includes an inclined portion extending along the shoulder of the protector. Facility. 前記架台はその各伸長部から水平に伸びる張出部を備える、請求項2に記載の設備。The facility according to claim 2, wherein the gantry includes an overhanging portion extending horizontally from each of the extending portions. 前記架台に支持され該架台に沿って伸びるベルトコンベヤを含む、請求項1に記載の設備。The facility according to claim 1, comprising a belt conveyor supported by the gantry and extending along the gantry. 前記ベルトコンベヤは、前記トンネルの覆工の破砕及びその周囲地盤の掘削によって生じたずりを運搬するために使用されるトラックの全高より高い位置にありかつ前記トラックの全長より長い長さ寸法を有する、請求項5に記載の設備。The belt conveyor has a length dimension higher than the total height of the truck used to carry the shear generated by crushing the tunnel lining and excavating the surrounding ground and longer than the total length of the truck. The facility according to claim 5. 前記ベルトコンベヤの一部はその残りの一部に対して揺動可能である、請求項6に記載の設備。7. The installation of claim 6, wherein a portion of the belt conveyor is swingable relative to the remaining portion.
JP2002083415A 2002-03-25 2002-03-25 Tunnel widening equipment Expired - Lifetime JP3713556B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002083415A JP3713556B2 (en) 2002-03-25 2002-03-25 Tunnel widening equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002083415A JP3713556B2 (en) 2002-03-25 2002-03-25 Tunnel widening equipment

Publications (2)

Publication Number Publication Date
JP2003278478A JP2003278478A (en) 2003-10-02
JP3713556B2 true JP3713556B2 (en) 2005-11-09

Family

ID=29231206

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002083415A Expired - Lifetime JP3713556B2 (en) 2002-03-25 2002-03-25 Tunnel widening equipment

Country Status (1)

Country Link
JP (1) JP3713556B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104847393A (en) * 2015-06-02 2015-08-19 北京首尔工程技术有限公司 Mobile tunnel supporting structure and tunnel construction method implemented under protection effect of mobile tunnel supporting structure

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661685B (en) * 2018-05-14 2020-02-14 贵州大学 Temporary tunnel supporting device convenient to deploy and detach
JP7266774B2 (en) * 2020-04-28 2023-05-01 国立研究開発法人土木研究所 Reconstruction method of existing road tunnel lining and equipment used therefor
CN117449864B (en) * 2023-12-22 2024-03-05 洛阳高飞桥隧机械股份有限公司 Tunnel widening driving protection construction device and tunnel widening construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104847393A (en) * 2015-06-02 2015-08-19 北京首尔工程技术有限公司 Mobile tunnel supporting structure and tunnel construction method implemented under protection effect of mobile tunnel supporting structure
CN104847393B (en) * 2015-06-02 2016-09-28 北京首尔工程技术有限公司 A kind of tunnel moves the method for tunnel construction under supporting construction and protection thereof

Also Published As

Publication number Publication date
JP2003278478A (en) 2003-10-02

Similar Documents

Publication Publication Date Title
CN104564050B (en) Equipment for heading and anchoring parallel operation construction
US6729464B2 (en) Mine conveying system
JP7036311B2 (en) Slip transport and ventilation equipment in the tunnel
US4150853A (en) Method of strip mining
CA2653449A1 (en) Mobile crusher unit
JP3713556B2 (en) Tunnel widening equipment
JP6537397B2 (en) Method of carrying out shear in tunnel excavation work and mobile stage used therefor
WO1999054049A1 (en) A mineral breaker apparatus
JP3706878B2 (en) Expansion method for existing tunnels
JPH08170486A (en) Tunnel excavated muck carry-out gantry
KR102254532B1 (en) Vertical soil transfer device of urban NATM method
US4396313A (en) Method of forming flooring in tunnels
JP6549411B2 (en) Floor construction method of shield tunnel
EP0989285A1 (en) Tunneling device
JP2967535B2 (en) Backup deck
JP3856301B2 (en) Expansion method of existing tunnel using mobile work platform
JP3803036B2 (en) Rail for construction in tunnel excavation
KR102175331B1 (en) Earthwork treatment device for excavation of road header in NATM TUNNEL
WO1995022481A1 (en) Crawler type slope travelling machine and track thereof
JP3151116B2 (en) Tunnel excavation method and gantry used for this method
JPH11210382A (en) Continuous belt conveyor supporting mechanism in tunnel excavation
KR102163299B1 (en) Bogie conveyor sediment handling device in NATM method tunnel
CN210622850U (en) Mine transportation system
JP6917113B2 (en) Belt conveyor line lifting device
CN210686052U (en) Underground roadway interchange transportation structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041228

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050510

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050802

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050804

R150 Certificate of patent or registration of utility model

Ref document number: 3713556

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080902

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090902

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090902

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090902

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100902

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110902

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110902

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110902

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110902

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120902

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120902

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130902

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term