JP3691400B2 - Building process management system - Google Patents

Building process management system Download PDF

Info

Publication number
JP3691400B2
JP3691400B2 JP2001042381A JP2001042381A JP3691400B2 JP 3691400 B2 JP3691400 B2 JP 3691400B2 JP 2001042381 A JP2001042381 A JP 2001042381A JP 2001042381 A JP2001042381 A JP 2001042381A JP 3691400 B2 JP3691400 B2 JP 3691400B2
Authority
JP
Japan
Prior art keywords
work
unit
data
group
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001042381A
Other languages
Japanese (ja)
Other versions
JP2002242432A (en
Inventor
谷 誠 菅
谷 英 紀 染
Original Assignee
株式会社アイフルホームテクノロジー
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社アイフルホームテクノロジー filed Critical 株式会社アイフルホームテクノロジー
Priority to JP2001042381A priority Critical patent/JP3691400B2/en
Publication of JP2002242432A publication Critical patent/JP2002242432A/en
Application granted granted Critical
Publication of JP3691400B2 publication Critical patent/JP3691400B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、建築工程管理システムに係り、特に、住宅建築の工程管理に必要な工程管理表を自動生成する建築工程管理システムに関する。
【0002】
【従来の技術】
住宅の建築では、あらかじめ工程管理表を作成しておき、この工程管理表にしたがって着工から竣工までの一連の諸工事を進めている。この工程管理表は、工事費用の見積、資材の手配、管理、作業員の手配、工事の進行などの管理になくてはならないもので、工程管理表を適正に作成することは、工期の短縮や建築コストの削減に直結する。
【0003】
従来から、建築業をはじめとして、広く製造業では、生産管理技術として工程管理の手法が研究されている。その代表的なものとしては、例えば、CPM工程管理法((critical pass method)限界工程管理法)を挙げることができる。
【0004】
また、ビル建築などでの作業計画や工程管理を合理的に行うコンピュータシステムの開発が進められており、この種の従来技術としては、特開平9−21231号公報や、特開平11−193631号公報等、様々なものが提案され、さらにはパソコンで利用できる工程管理用のソフトウェアも実際に使用されている。
【0005】
【発明が解決しようとする課題】
戸建て住宅のように、小規模の建築物の場合はビル建築の場合と違って、工程表の作成はあらかじめ用意された基準の工程表に工事種目を割り振り、施工図面や積算資料を参照しながら、作業を拾い出し、その基準工程表を改変して手作業あるいはパソコンで作成している。
【0006】
例えば、基準として代表的なモデル住宅の工程表を基準工程表として選び、個々の住宅の工程表を作成する際には、その住宅の床面積や間取りをモデル住宅と比較し、同一の作業項目を基準工程表に当てはめるとともにその時間を床面積や間取りに応じて調整しながら作成しており、その場合の工程表作成の基本となる基準は建坪であるのが一般的である。
【0007】
このため、同一作業が数日かかるような作業、例えば、サッシの取付工程などは、1階でのサッシ取付工程、2階でのサッシ取付工程というように大まかに分類して時間を割り振っており、個々の住宅の間取りの具体的な違いや作業のし易さなどは捨象され、工程表に反映されないため、実際の作業量と工程表上の作業量との間にずれが出てくる。また、一日で終了する作業の目標が明確とならないという問題があった。
【0008】
そこで、本発明の目的は、前記従来技術の有する問題点を解消し、間取りなどの個々の住宅の条件が工程表に正確に反映されるとともに、作業に必要な実際作業量と、一日で終了する作業目標を明確に把握することができる工程表を自動生成できるようにした建築工程管理システムを提供することにある。
【0009】
【課題を解決するための手段】
前記の目的を達成するために、本発明は、建築物の施工工事の一連の作業工程を管理するための建築工程管理システムであって、建築物のCAD図面データと資材データが蓄積されたCADデータベースと、作業時間算定の基礎となるデータとして、単位工程の要素をなし作業量と作業時間とが関連付けられている単位作業のデータが格納された作業時間算定マスタファイルを記憶する記憶手段と、各々が独立した単位工程を構成要素とする作業グループと、複数の部屋間にまたがって資材または階床を共通する単位作業を部屋単位に集約した単位工程を構成要素とする作業グループと、からなる複数の作業グループを設定する工程マスタファイルと、施工予定の建築物のCAD図面データと資材データから資材および資材の使われる場所、数量を読み取り、単位作業の作業項目と作業量を拾い出し、前記作業時間算定マスタファイルと突き合わせて、各単位工程ごとに作業時間を集計する単位作業拾い出し手段と、前記工程マスタファイルのデータと突き合わせて、各単位工程を前記作業グループ別にまとめるとともに、作業グループ別に作業時間を集計する集計手段と、各作業グループを予め定められた標準工程表に従って割り当て、特に、複数の部屋間にまたがって資材または階床を共通する単位作業を部屋単位に集約した単位工程を構成要素とする作業グループに属する作業グループついては、隣接する部屋順に各単位工程が配列されて工程表に割り当てて工程表を生成する手段と、を具備することを特徴とするものである。
【0010】
【発明の実施形態】
以下、本発明による建築工程管理システムの一実施形態について、添付の図面を参照しながら説明する。
図1は、本発明の一実施形態による建築工程管理システムのシステム構成を示すブロック図である。この図1において、参照符号10は、CADシステムを示し、参照符号12は、建築工程管理装置を構成するコンピュータである。CADシステムは、CAD用のコンピュータ14を備えるとともに、その記憶装置には建物のCAD図面を作成するために必要な資材に関する積算データが登録されているCAD積算マスタ15と、CAD用コンピュータ14で作成した建物の設計図面の画像データであるCADデータや、建物の基本情報、資材情報などがデータベースとして蓄積されたCADデータベース16を備えている。
【0011】
建築工程管理装置12は、コンピュータ本体17を備え、このコンピュータ本体17には、周辺装置として、キーボード、マウス等の入力装置18、新規工程作成や工程実績管理等のメニュー画面や、生成した工程表や図面の画像等を表示するためのCRTモニタなどの表示装置19、作成した工程表などを印刷するプリンターなどの出力装置20、生成した工程表などのデータを保存しておくための外部記憶装置21が接続されている。コンピュータ本体17は、入力装置18、表示装置19、出力装置20、外部記憶装置21との間のインターフェースをつかさどる入出力部22aと、表示装置19に情報を表示する表示機能22b、CADデータベース16と接続しデータを参照するデータベース接続機能22c、工程生成等の各種処理に必要な演算を行う演算処理部22dを有している。
【0012】
参照符号23は、工程管理に必要な各種データを登録しているマスタファイルが記憶された記憶装置である。マスタファイルには、作業時間の集計の基礎となるデータが格納された作業時間算定マスタファイル24、工程生成の標準となる工程が登録された工程マスタファイル25、各工程で必要とされる工具、資材が登録されている工具・資材マスタファイル26などがある。これらのマスタファイルについては、さらに後述する。
【0013】
図2は、戸建て住宅の建築に関連するすべての工程を示す工程図である。住宅建築の施工には、様々な工程がある。建物そのものの建築に関連して大工により作業が行われる工事の種類としては、工事順で土台敷、上棟、木工事(造作工事)がある。建物に関連する工事には、そのほかに仮設工事、基礎工事、屋根工事、外壁工事、クロス工事、タイル工事、畳工事などがあるが、これらの工事は専門の職人が行う。また、その他の専門の職人が行う工事としては、電気工事、ガス工事、給排水工事、防蟻工事などがある。
【0014】
一般の住宅建築の場合、着工から、架設工事、基礎工事と進んで、大工工事では上棟のみが複数人の大工が協同作業を行うが、上棟が終了して木工事になると、1名の大工が最終工程まで工事を担当することが多い。しかも木工事は、その工事種目も多岐にわたる上に工程も長くかかることから、適正な工程表を作成することが他の工事に比べて一層重要となる。
【0015】
そこで、工程日数の最も長い木工事についての工程生成を本発明の実施形態として挙げ、以下詳細に説明する。
【0016】
図3は、木工事の一連の工程を構成する作業グループを表す図である。この作業グループは、所定の基準で定められたいくつかの単位工程がいくつか集まって一つの作業グループを形成するようになっている。例えば、最初の工程の作業グループSG1は、建物の土台敷きを構成する複数の単位工程である墨付け、土台換気部材取付、土台間配り、アンカーボルト穴明け、土台据え付け、アンカーボルト締め付け、大引き取付、床下収納庫下地といった単位工程からなる。これらの単位工程は、一つ一つが独立して資材が共通するというような性質はもっていない工程である。
【0017】
これに対して、例えば、作業グループSG6が窓台まぐさの取り付けの作業グループであるとすると、このような作業は、建物の1階、2階で共通して行なわれ、また、同じ階床でも和室、洋室、居間というように部屋にまたがる作業であり、しかも、窓台、まぐさという資材が共通する作業である。このような作業グループを構成する単位工程は、部屋単位の工程となっている。サッシ取付という作業も部屋単位の単位工程からなる作業グループである。このような作業グループは、あらかじめ工程マスタファイル25に図4に示すようなデータとして登録されている。各作業グループの属する単位工程には、工程コードで識別されるようになっている。図4に図示しないすべての作業グループについても、同じようにその単位工程が登録され、工程コードが付けられている。
【0018】
次に、図5は、作業時間の集計の基礎となるデータが格納された作業時間算定マスタファイル24に登録されているデータを示す図である。
【0019】
図5に示すように、分類とあるのは、その工事が基礎工事などはその他、一階での工事あるいは2階での工事かを区別するためのものである。工程コードは、図4の単位工程のコードと対応するものである。単位作業の項目には、工程の生成に必要なすべての単位作業項目が登録されており、例えば、窓台マグサやサッシの取付であれば、その窓台マグサのすべての仕様が登録されており、それぞれ取付作業に必要な単位時間が分単位であらかじめ設定されている。これらの単位作業のデータは、すべての作業について登録されている。
【0020】
ここで、図6は、工程生成の対象建物のCAD図面の例を示している。演算処理部22dは、CADデータベース16からこのCADデータとこれに対応する資材データを読み込むと、CAD図面に表されているすべての単位作業を拾い出す。
【0021】
例えば、図6は、一階の平面図であるが、例えば、居間、和室、キッチン、浴室、トイレといった各部屋の床面積、壁の面積を算出するともに、各部屋の床の工事に必要な資材、壁に必要な資材を拾うことで単位作業を拾い出す。また、各部屋の窓台、マグサ、間柱の数、サッシの数並びにその仕様などすべての資材、建具を拾うことで必要な単位作業を拾い出す。このような単位作業の拾い出しは、2階の平面図、建物の正面図、土台の平面図などその建物のすべてのCAD図面を対象に実行される。
【0022】
次いで、演算処理部22dは、拾い出した資材を図5に示した作業時間算定マスタファイル24のデータと突き合わせることで、単位作業を拾い出す。図7は、一階のCADデータについて拾い出した単位作業の例を示している。この場合、拾い出された単位作業は、工程コードごとに集計されることで、単位工程として作業時間が集計することができるようになっている。
【0023】
こうして、すべての単位作業が工程コード別に集計されることで、単位作業は単位工程ごとにまとめられる。そして、演算処理部22dは、すべての単位工程を図4の工程マスタファイル25を参照しながら作業グループ別に集計する。例えば、サッシ取付の作業グループSG12であれは、図8に示すように、部屋別のサッシ取付の単位工程が作業グループSG12にまとめられ、各単位工程ことに作業時間が集計される。
【0024】
次いで、集計された各作業グループは、工程マスタファイル25に登録されている標準工程表に割り当てられて工程表が生成される。図9は、生成される工程表の一部を示している。この工程表の生成に際しては、工具・資材マスタファイル26が参照されて必要な資材、および必要な工具が拾い出されて作業グループごとに集計され、工程表に割り当てられる。作業グループ内では、部屋別の単位工程は、CADデータに基づいて隣接する部屋の順序で配列することが好ましい。また、一日についての稼働率が算出される。なお、ここでの稼働率は、1日の労働時間を8時間を基準となる管理時間として、作業グループで集計した単位工程の作業時間の総計の管理時間に対する割合をいう。
【0025】
このように作業グループという概念を導入して単位工程をまとめることで、一日の作業の目標値が明確にすることができる。しかも、資材等を共通とする作業については、部屋単位の工程として生成されるので、間取りなどの個々の住宅の条件が工程表に正確に反映させることができる。
【0026】
以上、木工事の工程生成を例に挙げて本発明を説明したが、本発明の工程管理システムでは、生成した工程に作業実績を書き込む機能や、生成した工程を更新する機能などを組み込むようにしてもよい。また、工程生成も木工事に限らず、他の工事に適用することも可能である。
【0027】
【発明の効果】
以上の説明から明らかなように、本発明によれば、各々が独立した単位工程を構成要素とする作業グループと、複数の部屋間にまたがって資材または階床を共通する単位作業を部屋単位に集約した単位工程を構成要素とする作業グループと、からなる複数の作業グループを設定し、その作業グループ別に単位工程をまとめるので、間取りなどの個々の住宅の条件が工程表に正確に反映されるとともに、作業に必要な実際作業量と、一日で終了する作業目標を明確に把握することができる工程表を自動生成することができる。
【図面の簡単な説明】
【図1】本発明の一実施形態による建築工程管理システムのシステム構成を示すブロック図。
【図2】建築工程を構成する各種工事の工程説明図。
【図3】本発明の建築構成管理システムが利用する作業グループの概念の説明図。
【図4】工程マスタファイルに登録された作業グループとその単位工程のデータの例を示す図。
【図5】作業時間の集計の基礎となるデータが格納された作業時間算定マスタファイル24に登録されているデータを示す図。
【図6】CADデータとして読み込むCAD図面の一例を示す図。
【図7】単位作業を拾い出した例を示す図。
【図8】サッシ取付の作業グループの例を示す図。
【図9】生成した工程表の一部分を示す図。
【符号の説明】
10 CADシステム
12 工程管理装置
14 CAD用コンピュータ
16 CADデータベース
17 コンピュータ本体
24 工程マスタファイル
25 作業時間算定マスタファイル
26 資材・工具マスタファィル
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a building process management system, and more particularly to a building process management system that automatically generates a process management table necessary for house building process management.
[0002]
[Prior art]
In the construction of houses, a process control table is prepared in advance, and a series of various work from the start to the completion is carried out according to this process control table. This process management table is indispensable for management of construction cost estimation, material arrangement, management, worker arrangement, construction progress, etc. Producing a process management table properly shortens the construction period. And directly reduce the construction cost.
[0003]
Conventionally, a process management method has been studied as a production management technique in the manufacturing industry widely including the construction industry. A typical example is a CPM process management method (critical process method).
[0004]
In addition, development of computer systems that rationally perform work planning and process management in building construction and the like is underway. As this type of prior art, Japanese Patent Application Laid-Open No. 9-21231 and Japanese Patent Application Laid-Open No. 11-193431. Various things such as a gazette have been proposed, and further, process management software that can be used on a personal computer is actually used.
[0005]
[Problems to be solved by the invention]
Unlike small buildings, such as single-family houses, schedules are created by assigning work items to standard schedules prepared in advance, while referring to construction drawings and accumulated materials. The work is picked up, and the standard process chart is modified and created manually or by a personal computer.
[0006]
For example, when selecting a process schedule for a typical model house as a standard process schedule and creating a process schedule for an individual house, compare the floor area and floor plan of that house with that of the model house, and use the same work items. Is applied to the standard process chart and the time is adjusted according to the floor area and the floor plan. In this case, the basic standard for creating the process chart is the floor area.
[0007]
For this reason, work that takes several days for the same work, for example, the sash installation process, etc., is roughly classified as a sash installation process on the first floor and a sash installation process on the second floor. Since specific differences in the layout of individual houses and ease of work are discarded and are not reflected in the process chart, a deviation appears between the actual work volume and the work volume on the process chart. In addition, there is a problem that the goal of work to be completed in one day is not clear.
[0008]
Therefore, an object of the present invention is to solve the problems of the prior art, accurately reflect the conditions of each house such as a floor plan in the process chart, and the actual work amount required for the work in one day. An object of the present invention is to provide a building process management system capable of automatically generating a process chart capable of clearly grasping a work target to be finished.
[0009]
[Means for Solving the Problems]
In order to achieve the above object, the present invention is a building process management system for managing a series of work processes of construction work of a building, in which CAD drawing data and material data of the building are accumulated. A storage means for storing a work time calculation master file in which data of unit work in which a work amount and work time are associated with each other as a data base for work time calculation is stored as a database , A work group consisting of independent unit processes as constituent elements, and a work group consisting of unit processes that consolidate unit works that share materials or floors across multiple rooms into room units. more of a step master file to set the working group, CAD drawing data and location to be used of materials and material from the material data of the building of the construction schedule, Reads the amount, picked up work items and work of the unit work, against said working time calculation master file, and means picking unit operation counts the operation time for each unit process, the data of the step master file In addition, each unit process is grouped by work group, and a totaling means for totaling work time by work group, and assigning each work group in accordance with a predetermined standard process table, in particular, materials across multiple rooms. Or, for a work group belonging to a work group whose unit element is a unit process in which unit works common to floors are aggregated into room units, each unit process is arranged in the order of adjacent rooms and assigned to the process chart to generate a process chart. And means.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of a construction process management system according to the present invention will be described with reference to the accompanying drawings.
FIG. 1 is a block diagram showing a system configuration of a building process management system according to an embodiment of the present invention. In FIG. 1, reference numeral 10 indicates a CAD system, and reference numeral 12 indicates a computer constituting the building process management apparatus. The CAD system includes a CAD computer 14 and is created by a CAD integration master 15 in which integration data related to materials necessary for creating a CAD drawing of a building is registered in the storage device, and the CAD computer 14. A CAD database 16 in which CAD data, which is image data of a design drawing of a building, basic information of a building, material information, and the like are stored as a database is provided.
[0011]
The building process management device 12 includes a computer main body 17. The computer main body 17 includes peripheral devices such as an input device 18 such as a keyboard and a mouse, a menu screen for creating a new process and managing process results, and a generated process chart. A display device 19 such as a CRT monitor for displaying images and drawings, etc., an output device 20 such as a printer for printing the created process table, and an external storage device for storing data such as the generated process table 21 is connected. The computer main body 17 includes an input / output unit 22a that controls an interface between the input device 18, display device 19, output device 20, and external storage device 21, a display function 22b that displays information on the display device 19, and a CAD database 16. It has a database connection function 22c for connecting and referring to data, and an arithmetic processing unit 22d for performing calculations necessary for various processes such as process generation.
[0012]
Reference numeral 23 denotes a storage device that stores a master file in which various data necessary for process management are registered. The master file includes a work time calculation master file 24 in which data serving as a basis for totaling work time is stored, a process master file 25 in which processes that are standard for process generation are registered, tools required in each process, There is a tool / material master file 26 in which materials are registered. These master files will be further described later.
[0013]
FIG. 2 is a process diagram showing all processes related to the construction of a detached house. There are various processes in the construction of a residential building. The types of work performed by carpenters in connection with the construction of the building itself include the basement, the upper building, and the woodwork (manufacturing) in the order of construction. Other construction related to the building includes temporary work, foundation work, roof work, exterior wall work, cloth work, tile work, tatami work, etc., but these work is performed by specialized craftsmen. Other specialized craftsman works include electrical work, gas work, water supply / drainage work, and ant work.
[0014]
In the case of ordinary residential buildings, the construction progresses from construction to foundation work and foundation work. In carpentry work, only the upper wing works together by multiple carpenters. Are often in charge of construction until the final process. Moreover, since woodwork has a wide range of work types and takes a long time, it is more important to create an appropriate work schedule than other works.
[0015]
Therefore, the process generation for the woodwork with the longest process days will be described as an embodiment of the present invention and will be described in detail below.
[0016]
FIG. 3 is a diagram showing a work group constituting a series of steps of the woodwork. In this work group, some unit processes defined by a predetermined standard are gathered to form one work group. For example, the work group SG1 of the first process is a plurality of unit processes that constitute the foundation of the building, marking, foundation ventilation member installation, distribution between foundations, drilling anchor bolts, foundation installation, anchor bolt tightening, large pulling It consists of unit processes such as mounting and under floor storage. These unit processes are processes that do not have such a property that each of the unit processes is independently common.
[0017]
On the other hand, for example, if the work group SG6 is a work group for attaching window lintels, such work is commonly performed on the first and second floors of the building, and the same floor is used. However, it is a work that spans rooms such as a Japanese-style room, a Western-style room, and a living room. Unit processes constituting such a work group are room-unit processes. The work of attaching the sash is also a work group composed of unit processes in units of rooms. Such work groups are registered in advance in the process master file 25 as data as shown in FIG. The unit process to which each work group belongs is identified by a process code. For all work groups not shown in FIG. 4, the unit processes are registered in the same manner and assigned process codes.
[0018]
Next, FIG. 5 is a diagram showing data registered in the work time calculation master file 24 in which data serving as a basis for work time aggregation is stored.
[0019]
As shown in FIG. 5, the classification is for distinguishing whether the construction is foundation work or the like, and construction on the first floor or construction on the second floor. The process code corresponds to the unit process code shown in FIG. In the unit work item, all unit work items necessary for process generation are registered.For example, when installing a window sill or sash, all specifications of the window sill are registered. Each unit time required for the mounting operation is preset in minutes. These unit work data are registered for all work.
[0020]
Here, FIG. 6 shows an example of a CAD drawing of a target building for process generation. When the arithmetic processing unit 22 d reads the CAD data and the corresponding material data from the CAD database 16, the arithmetic processing unit 22 d picks up all unit operations shown in the CAD drawing.
[0021]
For example, FIG. 6 is a plan view of the first floor. For example, the floor area and wall area of each room such as a living room, a Japanese-style room, a kitchen, a bathroom, and a toilet are calculated and necessary for the construction of the floor of each room. Pick up unit work by picking up materials and materials necessary for walls. In addition, the necessary unit work is picked up by picking up all materials and fittings such as the window sill, magsa, number of studs, number of sashes and specifications of each room. Such unit work is picked up on all CAD drawings of the building such as the second floor plan, the front view of the building, and the base plan view.
[0022]
Next, the arithmetic processing unit 22d picks up the unit work by matching the picked-up material with the data of the work time calculation master file 24 shown in FIG. FIG. 7 shows an example of unit work picked up from CAD data on the first floor. In this case, the unit work picked up is totaled for each process code, so that the work time can be totaled as a unit process.
[0023]
In this way, all unit operations are tabulated by process code, so that unit operations are grouped for each unit process. Then, the arithmetic processing unit 22d aggregates all unit processes by work group while referring to the process master file 25 of FIG. For example, in the sash-attached work group SG12, as shown in FIG. 8, the unit processes of sash attachment for each room are grouped into the work group SG12, and the work time is totaled for each unit process.
[0024]
Next, each tabulated work group is assigned to a standard process chart registered in the process master file 25 to generate a process chart. FIG. 9 shows a part of the generated process chart. When generating the process table, the tool / material master file 26 is referred to, and necessary materials and necessary tools are picked up, aggregated for each work group, and assigned to the process table. Within the work group, the unit processes for each room are preferably arranged in the order of adjacent rooms based on CAD data. Also, the operating rate for one day is calculated. Here, the operating rate refers to the ratio of the total working time of the unit process calculated by the work group to the management time, where the working time per day is 8 hours as a reference management time.
[0025]
In this way, by introducing the concept of a work group and summarizing unit processes, the target value of the daily work can be clarified. In addition, since work with common materials and the like is generated as a process in units of rooms, the conditions of individual houses such as floor plans can be accurately reflected in the process chart.
[0026]
As described above, the present invention has been described by taking the process generation of the woodwork as an example. However, the process management system of the present invention incorporates a function of writing a work record in the generated process and a function of updating the generated process. May be. Further, the process generation is not limited to the wood work but can be applied to other works.
[0027]
【The invention's effect】
As is apparent from the above description, according to the present invention, a work group having independent unit processes as constituent elements, and a unit work that shares materials or floors across a plurality of rooms are made room units. By setting up multiple work groups consisting of work units that have aggregated unit processes as components, and uniting the unit processes for each work group, the conditions of individual housing such as floor plans are accurately reflected in the process table. In addition, it is possible to automatically generate a process chart that can clearly grasp the actual work amount necessary for work and the work target to be completed in one day.
[Brief description of the drawings]
FIG. 1 is a block diagram showing a system configuration of a building process management system according to an embodiment of the present invention.
FIG. 2 is a process explanatory diagram of various constructions constituting the building process.
FIG. 3 is an explanatory diagram of the concept of a work group used by the building configuration management system of the present invention.
FIG. 4 is a diagram showing an example of work groups registered in a process master file and data of unit processes thereof.
FIG. 5 is a diagram showing data registered in a work time calculation master file 24 in which data serving as a basis for work time aggregation is stored.
FIG. 6 is a diagram showing an example of a CAD drawing read as CAD data.
FIG. 7 is a diagram showing an example of picking up a unit work.
FIG. 8 is a diagram showing an example of a sash-attached work group.
FIG. 9 is a diagram showing a part of a generated process chart.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 10 CAD system 12 Process management apparatus 14 CAD computer 16 CAD database 17 Computer main body 24 Process master file 25 Work time calculation master file 26 Material / tool master file

Claims (1)

建築物の施工工事の一連の作業工程を管理するための建築工程管理システムであって、
建築物のCAD図面データと資材データが蓄積されたCADデータベースと、
作業時間算定の基礎となるデータとして、単位工程の要素をなし作業量と作業時間とが関連付けられている単位作業のデータが格納された作業時間算定マスタファイルを記憶する記憶手段と、
各々が独立した単位工程を構成要素とする作業グループと、複数の部屋間にまたがって資材または階床を共通する単位作業を部屋単位に集約した単位工程を構成要素とする作業グループと、からなる複数の作業グループを設定する工程マスタファイルと、
施工予定の建築物のCAD図面データと資材データから資材および資材の使われる場所、数量を読み取り、単位作業の作業項目と作業量を拾い出し、前記作業時間算定マスタファイルと突き合わせて、各単位工程ごとに作業時間を集計する単位作業拾い出し手段と、
前記工程マスタファイルのデータと突き合わせて、各単位工程を前記作業グループ別にまとめるとともに、作業グループ別に作業時間を集計する集計手段と、
各作業グループを予め定められた標準工程表に従って割り当て、特に、複数の部屋間にまたがって資材または階床を共通する単位作業を部屋単位に集約した単位工程を構成要素とする作業グループに属する作業グループついては、隣接する部屋順に各単位工程が配列されて工程表に割り当てて工程表を生成する手段と、
を具備することを特徴とする建築工程管理システム。
A building process management system for managing a series of work processes of building construction work,
A CAD database in which building CAD drawing data and material data are stored;
Storage means for storing a work time calculation master file in which unit work data in which the amount of work and the work time are associated is stored as data serving as a basis for the work time calculation;
A work group consisting of independent unit processes as constituent elements, and a work group consisting of unit processes that consolidate unit works that share materials or floors across multiple rooms into room units. Process master file that sets multiple work groups,
Read the location and quantity of materials and materials used from the CAD drawing data and material data of the building to be constructed, pick up the work items and work amount of the unit work, and match each work process with the work time calculation master file. Unit work pick-up means for summing up work time every time,
Along with the data of the process master file, each unit process is grouped by the work group, and totaling means for totaling work time by work group ;
Each work group is assigned according to a predetermined standard process chart, and in particular, work belonging to a work group whose unit is a unit process in which unit works that share materials or floors across multiple rooms are aggregated into units of rooms. For the group, each unit process is arranged in the order of adjacent rooms and assigned to the process table to generate a process table;
A construction process management system comprising:
JP2001042381A 2001-02-19 2001-02-19 Building process management system Expired - Fee Related JP3691400B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001042381A JP3691400B2 (en) 2001-02-19 2001-02-19 Building process management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001042381A JP3691400B2 (en) 2001-02-19 2001-02-19 Building process management system

Publications (2)

Publication Number Publication Date
JP2002242432A JP2002242432A (en) 2002-08-28
JP3691400B2 true JP3691400B2 (en) 2005-09-07

Family

ID=18904682

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001042381A Expired - Fee Related JP3691400B2 (en) 2001-02-19 2001-02-19 Building process management system

Country Status (1)

Country Link
JP (1) JP3691400B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006309610A (en) * 2005-04-28 2006-11-09 Asahi Kasei Homes Kk Construction work planning system for building
JP5413653B2 (en) * 2009-05-19 2014-02-12 清水建設株式会社 Construction management system and construction management program
CN112182733A (en) * 2020-10-30 2021-01-05 湖南宝家云建筑工程管理有限公司 Visual building process management method, management system and storage medium

Also Published As

Publication number Publication date
JP2002242432A (en) 2002-08-28

Similar Documents

Publication Publication Date Title
Weygant BIM content development: standards, strategies, and best practices
JP4173135B2 (en) Construction planning method for brick wall
US7752020B2 (en) System and method for modeling construction risk using location-based construction planning models
EP1643335A2 (en) System and method for designing building structures with associated estimates and schedules
US20060074609A1 (en) System and method for determining variance in building structures
CA2345182A1 (en) System and method for take-off of materials using two-dimensional cad interface
Shaked et al. CONSCHED: expert system for scheduling of modular construction projects
US20040205014A1 (en) System for preparing construction project bids
JP3691400B2 (en) Building process management system
Sacks et al. A project model for an automated building system: design and planning phases
Zhang et al. Lean-based diagnosis and improvement for offsite construction factory manufacturing facilities
JP7221717B2 (en) Building progress control method and progress control system
JP2006309610A (en) Construction work planning system for building
WO2007109030A2 (en) Location-based construction planning and scheduling system
JP2002245121A (en) System for managing building process
JP2008134797A (en) Support system for forming remodeling construction schedule
Yi et al. Network creation and development for repetitive-unit projects
Senghore et al. Production process for manufactured housing
Ritter et al. Production monitoring and process improvement for floor panel manufacturing
JP2003064873A (en) Construction automatic analysis system
JP7421323B2 (en) Building construction management method and construction management system
Adedeji et al. Construction Procedure of a Straw Bale Walled Building–a review
JP5330068B2 (en) Building repair information providing device, building repair information providing method, and computer program
JP2607201B2 (en) Comprehensive production method by linking design and production of framed wall method
KR20100121846A (en) System and method for calculating construction expenses of building project

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041118

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050125

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050222

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050418

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050520

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050615

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3691400

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080624

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080624

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090624

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090624

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100624

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100624

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110624

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110624

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120624

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130624

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130624

Year of fee payment: 8

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130624

Year of fee payment: 8

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130624

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140624

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees