JP3672055B2 - Construction method of piping member assemblies - Google Patents
Construction method of piping member assemblies Download PDFInfo
- Publication number
- JP3672055B2 JP3672055B2 JP09217696A JP9217696A JP3672055B2 JP 3672055 B2 JP3672055 B2 JP 3672055B2 JP 09217696 A JP09217696 A JP 09217696A JP 9217696 A JP9217696 A JP 9217696A JP 3672055 B2 JP3672055 B2 JP 3672055B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- construction method
- header
- liquid feeding
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Domestic Plumbing Installations (AREA)
Description
【0001】
【産業条の利用分野】
本発明は、配管用部材組立品の施工方法に関する。さらに詳しくは、一般の住宅、集合住宅または商業ビルなどのプレハブ住宅に主に用いられる給水・給湯配管に関し、現場における施工の簡便化を図った配管用部材組立品の施工方法に関する。
【0002】
【従来の技術】
従来、一般の住宅、集合住宅、ホテルおよび商業ビルは、建築作業の合理化を目的としてプレハブ建築法が普及してきた。プレハブ住宅においては各ユニット、たとえば洗面所、風呂および便所が1ユニット、台所および洗濯機置場は1ユニットなどというように、1ユニットごとに工場で製作し、さらに床、壁、天井なども工場で製作し、これらの一部は工場のベルトコンベア上で組立て、残りを建築現場に運んで組立る方法、総てのユニット部品を建築現場に運びそこで組立て目的の建築物とする方法、などを採用する。
【0003】
このようなプレハブ住宅においては、水周りユニット内の機器はほぼ同じであるので、配管の形、大きさがほぼ同じ物となる。しかし、これらの配管は各ユニットの組立時に行われるので、極めて短時間に完了することが要求される。また、集合住宅、ホテルなどの場合も各戸、各室ごとに規格化された内部構造とされているので、水周り配管も統一されたものにされている。しかし、配管工事が一時期に集中し、その後の工程までを極めて短期間内に施工する必要がある。特に、集合住宅のように、小スペースにコンパクトにまとめて設置される水周りの設備を多数施工する建築現場では、他の業種の工程との兼ね合い上、工程短縮の要請が強く、施工後の検査時間の短縮も必要であった。
【0004】
この様な配管施工の時間を短縮するために、従来から、ヘッダー工法、サヤ管ヘッダー工法が提案され、実用化されている。「ヘッダー工法」とは、主給水配管に接続されるヘッダーに設けられた複数個の分岐口の1個1個に可撓性を有する送液管等を接続し、この送液管を建築物のスラブ面上等に敷設して、所望の場所の各水栓器具(行き先)まで導く工法である。この工法によれば配管施工の時間短縮は可能であるが、さらに短縮化を求められ、ヘッダーの複数個の分岐口に、予め所定長さの可撓性のある送液管を接続した配管用部材の組立品が提案された(特開平7−158128号公報参照)。
【0005】
また、「サヤ管ヘッダー工法」とは、給水配管に接続されるヘッダーから所望の場所まで、建築物の床壁上に送液管を敷設するに当たり、スラブ面上に予め管状部材(サヤ管)を敷設し、次いでこの管状部材(さや管)内に可撓性を有する送液管を挿通して敷設する工法である。この工法によると、可撓性を有する送液管が作業員に踏まれたり、スラブ面上に直接に接したりしないので、傷が付くことがなく、配管作業に技量を要さず、熟練者でなくても容易に施工ができるという利点があるが、長尺の場合の搬入・運搬の問題、施工現場での作業スペース確保の問題などがある。このような問題を解消するために、予め所定長さとした可撓性を有する送液管を予め所定長さとしたサヤ管に挿通し、これらの一端をヘッダーの複数個の分岐口に予め接続した配管用部材をコイル状に巻回したさや管ヘッダープレハブユニットとして施工する方法が提案された(特開平7−197495号公報参照)。
【0006】
これら提案されている改良法のうち、特開平7−158128号公報に記載の組立品の場合は、送液管の一端がヘッダーの複数個の分岐口に予め固定されており、送液管の長さは予め所定の長さに調整されているとは言うものの、送液管は固定具でスラブ面、壁面、桟木などに固定されるので、送液管の余分な長さを吸収させることができず、長さを施工現場において微調整(切断)する必要がある。予め所定の長さに調整されている送液管が短い場合は、全体を長いものに置き換えなければならず、この危険をさけるために理論値より若干長めにされているのが普通である。送液管の長さの微調整は、各水栓器具は一戸の建物の中で分散しており、これら分散した各水栓器具の継手のある場所で個々に行う必要があり、作業者にとっては極めて煩わしいという欠点がある。
【0007】
また、特開平7−197495号公報に記載の施工方法によるときは、特開平7−158128号公報に記載の場合と同様に、送液管の一端がヘッダーの複数個の分岐口に予め固定されており送液管の長さは予め所定の長さに調整されているとは言うものの、余分な長さを施工現場において微調整(切断)する必要がある。この公報に記載のサヤ管ヘッダープレハブユニットは、送液管がサヤ管に挿通されているので、送液管の余分な長さを他の部分に吸収させることは極めて困難で、送液管の長さの微調整をしなければならず、上の場合と同様の欠点がある。また、サヤ管ヘッダープレハブユニットは、送液管を挿通したサヤ管を複数本予めヘッダー固定しているので、全体として重量が重く、保管、輸送、取扱いが不便であるという欠点がある。
【0008】
【発明が解決しようとする課題】
本発明者らは、かかる現状に鑑み、一般の住宅、高層住宅、ホテルおよび商業ビルなどのプレハブ建築物に主に用いられる給水・給湯配管に関し、現場における施工の簡便化を図った配管用部材組立品、およびこの配管用部材を使用した施工方法を提供することを目的として、鋭意検討した結果、本発明を完成した。 すなわち、本発明は、次のことを目的とする。
1.配管施工時間を大幅に短縮できる配管用部材組立品の施工方法を提供すること。
2.全体として重量が重くなく、保管、輸送、取扱いに便利な配管用部材組立品の施工方法を提供すること。
3.送液管のロス(廃棄物)の発生の少ない配管用部材組立品の施工方法を提供すること。
【0009】
【課題を解決するための手段】
上記課題を解決するため、本発明は、所定の長さに切断された可撓性を有する送液管の一端に、事前に継手が接続されてなる複数組の配管用部材組立品を、まず、施工場所において継手を水栓器具設置場所に固定し、次いで、送液管を配管ルートに沿って配管し、最後に、各送液管の他端をそれぞれ複数の分岐口を有する給水・給湯ヘッダーの各一個の分岐口に接続することを特徴とする配管用部材組立品の施工方法を提供する。
【0010】
【発明の実施の形態】
以下、本発明を詳細に説明する。
本発明において、可撓性を有する送液管としては、架橋ポリエチレン管、架橋ポリブテン管のように機械的に、または融着で接続できる管、ステンレス・スチール・コルゲイテッド・チューブ(SSCT)、銅管、アルミニウム管の内外面に中密度ポリエチレンや架橋ポリエチレンを被覆した金属強化ポリエチレン管、またはJIS G3448に規定されている一般配管用ステンレス鋼鋼管よりも薄肉にされたステンレス鋼コイルド・チューブ(SCT)、などが挙げられる。中でも好ましいのは、架橋ポリエチレン管、架橋ポリブテン管である。
【0011】
本発明に係る施工方法で使用される配管用部材組立品は、上記の送液管の一端に、事前に、継手が接続されている必要がある。ここで「事前に」とは、配管用部材組立品の施工現場で接続するものでないことを意味する。一般には、送液管を所定の長さに切断する工場、施工現場以外の他の作業場などで接続される。また「所定の長さ」とは、各水栓器具の継手から複数の分岐口を有する給水・給湯ヘッダーの各一個の分岐口までの距離を言い、図面上の長さ(理論値)より数ミリメートルまたは数センチメートル長めの長さをいう。送液管の長さ不足がおこると、これに継ぎ足すことは困難であるので全体を長いものに置き換えるが必要となり、送液管のロス(廃棄物)が発生する。図面上の長さより若干長くしておくことにより、長さ不足が起こらなくなり、全体を長いものに置き換えることが不要になり、送液管のロスの発生を少なくすることができる。
【0012】
送液管の一端に接続される継手は、送液管の端部と水栓器具との間に配置されて両者を接続するもので、水栓アダプタ、水栓エルボなどを兼ねる構造のものであってもよい。水栓器具は用途(行き先)によって設置場所が異なるので、複数の分岐口を有するヘッダーの各分岐口から各水栓器具までの距離は、水栓器具は用途によって個々に異なることになる。水栓器具の用途としては、台所の給水・給湯栓、風呂の給水・給湯栓、洗面化粧台の給水・給湯栓、便所の給水栓などが挙げられる。
【0013】
本発明に係る施工方法で使用される配管用部材組立品は、その送液管が裸管のままであってもよい。ただし、裸管の場合には、施工中に送液管が作業員に踏まれたり、その上に工具が落下したりした場合に傷が付き、漏水の原因になることがある。このような不都合を防ぐために、上記送液管をサヤ管内に挿通しておくのが好適である。サヤ管の長さは、その中に挿通する送液管の長さに合せて調節する。一般には、サヤ管は送液管の長さより若干短くされる。送液管をサヤ管に挿通する作業は、「事前に」行うものとする。送液管をサヤ管に挿通する作業を事前に行うので、施工現場での作業スペースが必要ない。
【0014】
サヤ管を構成するものとしては、可撓性を有する合成樹脂管、特に波付き管、蛇腹管などのコイル巻きが可能な管が使用される。波付き管、蛇腹管の素材としては、ポリ塩化ビニル、ポリエチレン、ポリプロピレン、ポリ塩化ビニリデン、ポリカーボネート、ポリアミド類などの熱可塑性樹脂が挙げられる。
【0015】
なお、サヤ管と送液管との間には緩衝層を設けるのが好ましい。この緩衝層は、ウォターハンマー現象による打撃音の消音対策に役立つ。緩衝層は、発泡ポリエチレンなどの発泡体のシート材によって構成し、これを送液管の外側に巻き付けて、サヤ管に挿通することによって形成することができる。
【0016】
本発明に係る施工方法で使用される配管用部材組立品は、工場でまたは施工現場以外の作業場などで、複数組の組立品の用途別にコイル状に巻回して継手部分に行き先表示札(用途名表示札)を取り付け、さらにこのコイル状に巻回した複数組の組立品を一組ごとに段ボール箱に収納し、箱には各組立品の行き先を明記するのが好ましい。段ボール箱には一組の組立品しか収納しないので、保管スペースも少なくでき、段ボール箱の重量はそれ程重くならず、輸送、取扱いに極めて便利である。段ボール箱に行き先を明記しておくと、輸送、配管施工の際に便利である。
【0017】
本発明に係る施工方法で施工するには、まず、一施工ユニット(一戸、一室用などとして纏めたもの)に要する組立品の種類、数を、個別に段ボール箱に収納されている段階で確認して準備する。次に、これら複数の段ボール箱を施工現場に運搬し、水栓器具の用途に合った組立品を段ボール箱の表示で確認して取り出し、組立品の行き先表示札で再確認してから、各組立品の継手側を水栓器具の設置場所に固定し、コイル状に巻回されている組立品を所定の配管ルートに沿って解きつつ配管し、コーナーベント、サヤ管サドルなどによって定位置で固定し、各送液管の他端をそれぞれ複数の分岐口を有する給水・給湯ヘッダーの各一個の分岐口に導く。
【0018】
水栓器具の用途ごとに上と同様の手順で配管し、複数本の送液管をそれぞれ複数の分岐口を有する給水・給湯ヘッダーの各一個の分岐口に導く。複数本の送液管長さの微調整は、給水・給湯ヘッダーを設置した一箇所で集中して行い、給水・給湯ヘッダーの複数の分岐口に接続することができる。従来のヘッダープレハブユニット、サヤ管ヘッダープレハブユニットなどを使用する場合には、送液管の一端をヘッダー側で固定されているが、他端は水栓器ごとに固定する必要があったので、作業員が複数の水栓器具の設置場所を移動する必要があったが、本発明に係る配管用部材組立品を用いた施工方法による場合は、作業員は一箇所で作業ができるので移動の必要がない。
【0019】
本発明に係る施工方法による施工は、一般の住宅、マンションなどの集合住宅、高層商業ビル、高層ビジネスホテルなどのプレハブ建築物の水周りユニットを施工する際に、適用することができる。水周りとしては、台所、洗面所、風呂、便所、洗濯機置場などが挙げられるが、これら例示したものに限定されるものではない。
【0020】
【実施例】
以下、本発明を図面に基いて詳細に説明する。
図1は、本発明に係る施工方法により施工する際に使用される、配管用部材組立品の一例の斜視図であり、図2は、本発明に係る施工方法によって、一般の住宅の水周りユニットを施工した一例を示す斜視図である。
【0021】
図1において、10は送液管、11はサヤ管、12は送液管の一端に接続された継手、13は表示板、14は送液管の他端、15は配管用部材組立品を示す。図2において、給湯器20からの温水が導かれる給水配管21には、給湯側のヘッダー22が接続され、水道水が導かれる給水配管23には、給水側のヘッダー24が接続されている。給湯側のヘッダー22に接続された複数の湯配管25、給水側のヘッダー24に接続された複数の水配管26は、住戸内の複数箇所に設けられた水栓器具のそれぞれから導かれている。図示した例では、継手31によって水栓器具27に固定されている。水栓器具27は、浴槽、シャワー、流し台、洗濯機、洗面台、トイレなどの水栓器具のものである。水配管26の他端は、継手32を介してヘッダー22、24に接続された例を示している。
【0022】
図2に示した例では、湯配管25および水配管26のそれぞれは、サヤ管11に挿通して構成した例を示したが、裸管であってもよい。送液管10の一端に取付けられた継手12を、まず、接続具を介して水栓器具設置場所ごとに固定し、コイル状に巻回されている組立品を所定の配管ルートに沿って解きつつ配管し、コーナーベント、サヤ管サドルなどによって定位置で固定し、湯配管25および水配管26の他端をヘッダー22、24の分岐口に導く。ヘッダーの分岐口に導かれた送液管の他端は、ヘッダー22、24付近に導かれた湯配管25および水配管26は、ヘッダー分岐口の部分で長さを微調整して、それぞれ継手31によって分岐口に接続され、施工が完成する。
【0023】
【発明の効果】
本発明は、次のような特別に有利な効果を奏し、その産業上の利用価値は極めて大である。
1.発明に係る施工方法によって施工するときは、送液管の継手を水栓器具設置場所に固定し、送液管を配置・固定し、送液管の他端を給水・給湯ヘッダーの分岐口に接続すればよいので、配管施工時間を大幅に短縮することができる。
2.本発明に係る施工方法において使用する配管用部材組立品は、水栓器具の用途によって個々にコイル状に巻回されており、従来のヘッダープレハブユニットのように複数の用途に使用される配管が同時に巻回されてはいないので、組立品の重量が軽く、保管、輸送、取扱いに極めて便利である。
3.本発明に係る施工方法によれば、コイル状に巻回されている組立品を所定の配管ルートに沿って解きつつ配管するので、施工作業を能率的に行うことができる。
4.本発明に係る施工方法によれば、送液管の長さの微調整は、給水・給湯ヘッダーを設置した一箇所で集中して行うことができ、しかも送液管のロス(廃棄物)の発生の少なくすることができる。
5.本発明に係る施工方法によれば、送液管とヘッダーとの接続作業を一箇所ででき作業員の移動がないので、他の業種との作業工程が重なっても、他業種の作業員の作業を邪魔することがない。
【図面の簡単な説明】
【図1】 本発明に係る施工方法により施工する際に使用される配管用部材組立品の一例の斜視図である。
【図2】 本発明に係る施工方法によって、一般の住宅の水周りユニットを施工した一例を示す斜視図である。 [0001]
[Industrial fields]
The present invention relates to a method for constructing a piping member assembly . More specifically, the present invention relates to a water supply / hot water supply piping mainly used in prefabricated houses such as ordinary houses, apartment houses, or commercial buildings, and a construction method of a member assembly for piping that simplifies construction on site.
[0002]
[Prior art]
Conventionally, prefabricated construction methods have been widely used in general houses, apartment houses, hotels and commercial buildings for the purpose of rationalizing construction work. Each unit in prefabricated houses, for example, toilet, bath and toilet are one unit, Kitchen and Laundry Area, as referred to, such as one unit, manufactured at the factory for each unit, further floors, walls, ceiling, etc. also at the factory A part of these parts is assembled on the belt conveyor of the factory, the rest is transported to the construction site, and all unit parts are transported to the construction site, where they are assembled for the purpose of assembly. To do.
[0003]
In such a prefabricated house, the equipment in the water unit is almost the same, so the shape and size of the pipes are almost the same. However, since these piping are performed at the time of assembling each unit, it is required to complete in a very short time. In addition, in the case of apartment houses, hotels, etc., because the internal structure is standardized for each house and room, the plumbing around the water is unified. However, plumbing work is concentrated at one time, and it is necessary to construct the subsequent processes within an extremely short period of time. In particular, at construction sites where many facilities around the water are installed in a compact space in a compact space, such as apartment buildings, there is a strong demand for process shortening due to the balance with other industries. It was also necessary to shorten the inspection time.
[0004]
In order to shorten the time for such pipe construction, a header method and a Saya pipe header method have been proposed and put into practical use. “Header construction method” means that a flexible liquid feed pipe is connected to each of a plurality of branch ports provided in a header connected to a main water supply pipe, and this liquid feed pipe is connected to a building. This is a construction method that leads to each faucet device (destination) at a desired location by laying it on the slab surface. Although it is possible to shorten the pipe construction time according to this construction method, further shortening is required, and for pipes in which a flexible liquid feed pipe having a predetermined length is connected in advance to a plurality of branch ports of the header. An assembly of members has been proposed (see JP-A-7-158128).
[0005]
In addition, the “saya pipe header construction method” means that a pipe member (saya pipe) is preliminarily placed on the slab surface when laying a liquid feed pipe on the floor wall of the building from the header connected to the water supply pipe to a desired location. Then, a flexible liquid feeding pipe is inserted into the tubular member (sheath pipe) and then laid. According to this method, the flexible liquid supply pipe is not stepped on by the worker or directly touches the slab surface, so that it is not damaged and does not require skill in the piping work. Although there is an advantage that it can be easily constructed even if it is not, there are problems of carrying in and carrying in the case of a long length, problems of securing a work space at the construction site, and the like. In order to solve such a problem, a flexible liquid feeding pipe having a predetermined length is inserted into a sheath pipe having a predetermined length, and one end thereof is connected in advance to a plurality of branch ports of the header. There has been proposed a method of constructing a pipe header prefabricated unit in which a pipe member is wound in a coil shape (see JP-A-7-197495).
[0006]
Among these proposed improvements, in the case of the assembly described in Japanese Patent Application Laid-Open No. 7-158128, one end of the liquid feeding pipe is fixed in advance to a plurality of branch ports of the header. Although the length is adjusted to a predetermined length in advance, the liquid feeding pipe is fixed to the slab surface, wall surface, pier, etc. with a fixture, so that the extra length of the liquid feeding pipe is absorbed. It is necessary to finely adjust (cut) the length at the construction site. When the liquid feeding pipe that has been adjusted to a predetermined length in advance is short, the whole must be replaced with a long one, and is usually slightly longer than the theoretical value to avoid this danger. Fine adjustment of the length of the liquid supply pipe is carried out in a building where each faucet device is dispersed, and it is necessary to perform it individually at the place where the joints of these dispersed faucet devices are located. Has the disadvantage of being extremely annoying.
[0007]
When the construction method described in JP-A-7-197495 is used, as in the case described in JP-A-7-158128, one end of the liquid feeding pipe is fixed in advance to a plurality of branch ports of the header. Although the length of the liquid feeding pipe is adjusted to a predetermined length in advance, it is necessary to finely adjust (cut) the extra length at the construction site. In the Saya pipe header prefab unit described in this publication, since the liquid feeding pipe is inserted through the Saya pipe, it is extremely difficult to absorb the extra length of the liquid feeding pipe in other parts. The length has to be finely adjusted and has the same drawbacks as above. In addition, the Saya tube header prefab unit has a disadvantage that a plurality of Saya tubes through which the liquid feeding tube is inserted is fixed to the header in advance, so that the weight is heavy as a whole and storage, transportation and handling are inconvenient.
[0008]
[Problems to be solved by the invention]
In view of the present situation, the present inventors relate to water supply / hot water supply pipes mainly used for prefabricated buildings such as ordinary houses, high-rise houses, hotels, and commercial buildings, and piping members for simplifying construction on site. As a result of intensive studies aimed at providing an assembly and a construction method using the piping member, the present invention was completed. That is, the present invention aims at the following.
1. To provide a method for constructing a pipe member assembly that can greatly shorten the pipe construction time.
2. To provide a construction method for piping member assemblies that is not heavy overall and is convenient for storage, transportation, and handling.
3. To provide a method for constructing a pipe member assembly that generates less liquid pipe loss (waste).
[0009]
[Means for Solving the Problems]
In order to solve the above-mentioned problems, the present invention provides a plurality of sets of piping member assemblies in which a joint is connected in advance to one end of a flexible liquid feeding pipe cut to a predetermined length. the joint is fixed to the faucet fixture location in construction site, then the pipe along the liquid feed pipe to the piping route, finally, water supply and hot water supply to which the other end of the liquid feed pipe each having a plurality of branch ports Provided is a pipe member assembly construction method characterized by connecting to each one branch port of a header.
[00 10 ]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described in detail.
In the present invention, the flexible liquid feeding pipe includes a cross-linked polyethylene pipe, a pipe that can be connected mechanically or by fusion, such as a cross-linked polybutene pipe, a stainless steel corrugated tube (SSCT), and a copper pipe. A stainless steel coiled tube (SCT) made thinner than a metal reinforced polyethylene pipe coated with medium density polyethylene or cross-linked polyethylene on the inner and outer surfaces of an aluminum pipe, or a stainless steel pipe for general piping defined in JIS G3448, Etc. Among these, a cross-linked polyethylene pipe and a cross-linked polybutene pipe are preferable.
[0011]
In the member assembly for piping used in the construction method according to the present invention, a joint needs to be connected in advance to one end of the liquid feeding pipe. Here, “in advance” means that the pipe member assembly is not connected at the construction site. Generally, it is connected in a factory that cuts the liquid feeding pipe into a predetermined length, a work place other than the construction site, and the like. “Predetermined length” refers to the distance from the joint of each faucet device to each one of the water / hot water headers having a plurality of branch ports, which is a number from the length (theoretical value) on the drawing. A length of millimeter or several centimeters. If the length of the liquid feeding pipe is short, it is difficult to add to this, so it is necessary to replace the whole with a long one, and the liquid feeding pipe loses (waste). By making the length slightly longer than the length on the drawing, there is no shortage of length, it becomes unnecessary to replace the whole with a long one, and the occurrence of loss of the liquid feeding pipe can be reduced.
[0012]
The joint connected to one end of the liquid supply pipe is arranged between the end of the liquid supply pipe and the faucet device to connect both, and has a structure that also serves as a faucet adapter, faucet elbow, etc. There may be. Since the installation location of the faucet device differs depending on the application (destination), the distance from each branch port of the header having a plurality of branch ports to each faucet device varies depending on the application. Applications of the faucet include kitchen water / hot water tap, bath water / hot water tap, toilet vanity water / hot water tap, toilet hydrant, etc.
[0013]
The piping member assembly used in the construction method according to the present invention may be a bare pipe as its liquid feeding pipe. However, in the case of a bare pipe, if a liquid feeding pipe is stepped on by an operator during construction or a tool falls on the pipe, it may be damaged and cause water leakage. In order to prevent such inconvenience, it is preferable to insert the liquid feeding pipe into the sheath pipe. The length of the Saya tube is adjusted according to the length of the liquid feeding tube inserted through it. In general, the sheath pipe is slightly shorter than the length of the liquid feeding pipe. The operation of inserting the liquid feeding pipe into the sheath pipe is performed “in advance”. Since the work of inserting the liquid feeding pipe into the sheath pipe is performed in advance, there is no need for a work space at the construction site.
[00 14 ]
As the material constituting the sheath tube, a flexible synthetic resin tube, in particular, a tube capable of coil winding such as a corrugated tube and a bellows tube is used. Examples of the material for the corrugated tube and the bellows tube include thermoplastic resins such as polyvinyl chloride, polyethylene, polypropylene, polyvinylidene chloride, polycarbonate, and polyamides.
[00 15 ]
A buffer layer is preferably provided between the sheath tube and the liquid feeding tube. This buffer layer is useful for countermeasures to mute the impact sound caused by the water hammer phenomenon. The buffer layer can be formed of a foam sheet material such as foamed polyethylene, wound around the outside of the liquid feeding pipe, and inserted into the sheath pipe.
[0016]
The piping member assembly used in the construction method according to the present invention is wound at the factory or at a workplace other than the construction site, etc., wound in a coil shape according to the use of the multiple sets of assemblies, It is preferable that a plurality of sets of assemblies wound in a coil shape are stored in a corrugated cardboard box, and the destination of each assembly is specified in the box. Since only one set of assemblies is stored in the cardboard box, the storage space can be reduced, and the weight of the cardboard box does not increase so much, which is very convenient for transportation and handling. It is convenient for transportation and piping construction to specify the destination on the cardboard box.
[0017]
To construct with the construction method according to the present invention, first, at the stage where the types and number of assemblies required for one construction unit (one house, one room, etc.) are individually stored in a cardboard box. Check and prepare. Then, carrying a plurality of cardboard boxes in a construction site, taken out to check the assembly that matches the use of faucet fixtures in the display of cardboard boxes, re-check the destination indication tag of the assembly, each Fix the joint side of the assembly to the installation location of the faucet device, pipe the assembly wound in a coil shape along the predetermined piping route, and fix it in place by corner vents, saddle pipe saddles, etc. fixed, leads the other end of each liquid feed pipe to each one of the branch port of the water supply and hot water supply header, each having a plurality of branch ports.
[0018]
The pipes are piped in the same procedure as above for each use of the faucet device, and a plurality of liquid feeding pipes are led to one branch port of each of the water supply and hot water supply headers having a plurality of branch ports . Fine adjustment of the length of a plurality of liquid feeding pipes can be performed at a single location where a water / hot water header is installed, and can be connected to a plurality of branch ports of the water / hot water header . When using a conventional header prefab unit, Saya pipe header prefab unit, etc., one end of the liquid feed pipe is fixed on the header side, but the other end must be fixed for each faucet, Although it was necessary for the worker to move between the installation locations of a plurality of faucet appliances, in the case of the construction method using the pipe member assembly according to the present invention, the worker can work at one place, so There is no need.
[0019]
Construction by the construction method according to the present invention can be applied when constructing a water-based unit of a prefabricated building such as a general house, a housing complex such as a condominium, a high-rise commercial building, a high-rise business hotel or the like. Examples of the area around the water include a kitchen, a washroom, a bath, a toilet, and a washing machine place, but are not limited to those illustrated.
[0020]
【Example】
Hereinafter, the present invention will be described in detail with reference to the drawings.
FIG. 1 is a perspective view of an example of a pipe member assembly used when performing construction according to the construction method according to the present invention , and FIG. It is a perspective view which shows an example which constructed the unit.
[00 21 ]
In FIG. 1, 10 is a liquid feed pipe, 11 is a sheath pipe, 12 is a joint connected to one end of the liquid feed pipe, 13 is a display board, 14 is the other end of the liquid feed pipe, and 15 is a member assembly for piping. Show. In FIG. 2, a hot water supply side header 22 is connected to a water supply pipe 21 through which hot water from a
[00 22 ]
In the example illustrated in FIG. 2, each of the hot water pipe 25 and the
[0023]
【The invention's effect】
The present invention has the following particularly advantageous effects, and its industrial utility value is extremely great.
1. When installing by the construction method according to the invention, fix the joint of the liquid feeding pipe to the faucet installation location, place and fix the liquid feeding pipe, and connect the other end of the liquid feeding pipe to the branch port of the water supply / hot water header Since it only has to be connected, piping construction time can be greatly shortened.
2. The piping member assembly used in the construction method according to the present invention is individually wound in a coil shape depending on the use of the faucet device, and piping used for a plurality of uses like a conventional header prefab unit. Since they are not wound at the same time, the weight of the assembly is light and it is very convenient for storage, transportation and handling.
3. According to the construction method according to the present invention, since the assembly wound in the coil shape is piped while being unwound along a predetermined pipe route, the construction work can be performed efficiently.
4). According to the construction method of the present invention, the fine adjustment of the length of the liquid supply pipe can be performed in one place where the water supply / hot water supply header is installed, and the loss of the liquid supply pipe (waste) Occurrence can be reduced.
5. According to the construction method according to the present invention, since the connection work between the liquid feeding pipe and the header can be performed in one place, and there is no movement of the worker, even if the work process with other industry overlaps, There is no obstacle to work.
[Brief description of the drawings]
FIG. 1 is a perspective view of an example of a piping member assembly used when performing construction by the construction method according to the present invention.
FIG. 2 is a perspective view showing an example of constructing a general house water unit by the construction method according to the present invention.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09217696A JP3672055B2 (en) | 1996-04-15 | 1996-04-15 | Construction method of piping member assemblies |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09217696A JP3672055B2 (en) | 1996-04-15 | 1996-04-15 | Construction method of piping member assemblies |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09279647A JPH09279647A (en) | 1997-10-28 |
JP3672055B2 true JP3672055B2 (en) | 2005-07-13 |
Family
ID=14047131
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP09217696A Expired - Lifetime JP3672055B2 (en) | 1996-04-15 | 1996-04-15 | Construction method of piping member assemblies |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3672055B2 (en) |
-
1996
- 1996-04-15 JP JP09217696A patent/JP3672055B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH09279647A (en) | 1997-10-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5076310A (en) | Framed wall with a prefabricated underfloor drain line and method of manufacture | |
US4919164A (en) | Method of installing piping, ducts and conduits in a prefabricated framed wall for a building structure and partition made thereby | |
US20080196161A1 (en) | Flexible Bathtub Waste Pipe Assembly for Bathtubs and the Like | |
JP3672055B2 (en) | Construction method of piping member assemblies | |
KR101867766B1 (en) | Connector for duct to reduce the floor height and improve the workability ,and duct constructing method using thereof | |
US6241024B1 (en) | Parallel-fed nonstagnant integrated water distribution network for domestic water and fire sprinkler application | |
JP2001065008A (en) | Water supply/hot water supply piping of house | |
JP4095868B2 (en) | Water supply / hot water supply piping unit and its construction method | |
JP2001214485A (en) | Installation structure for drainage header for drainage facility to be required in apartment house | |
JPH07197495A (en) | Method for execution of work for liquid feed piping with sheath pipe | |
EP1132528B1 (en) | Parallel-fed nonstagnant integrated water distribution network for domestic water and fire sprinkler application | |
WO1990002850A1 (en) | A method and device for laying waste pipes in hollow flooring blocks | |
JPH07158128A (en) | Built-up product of piping member and piping method thereof | |
JP2539019Y2 (en) | Piping structure in buildings | |
JP3052000B2 (en) | Underfloor piping structure of building | |
KR200496747Y1 (en) | Fixing device for riser pipe | |
JPH09165804A (en) | Water supply piping and water supply piping method of plural storied building | |
JP3249454B2 (en) | Equipment plumbing for apartment houses | |
JP2021154122A (en) | Sprinkler piping structure and installation method thereof | |
JPH07268912A (en) | Water supply-hot water supply piping system device and water supply vertical pipe therefor | |
JP3660365B2 (en) | Piping device and piping method | |
JP3190201B2 (en) | Underfloor piping structure of building unit | |
JP2002070093A (en) | Method for installing integral pipe line for supplying water, draining, and supplying hot water | |
JP2001090202A (en) | Building unit | |
JP2000205465A (en) | Piping member and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20031217 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040113 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040308 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050104 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050225 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050412 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050413 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090428 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090428 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100428 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110428 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120428 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130428 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140428 Year of fee payment: 9 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |