JP3619998B2 - Maintenance management system, method and program - Google Patents

Maintenance management system, method and program Download PDF

Info

Publication number
JP3619998B2
JP3619998B2 JP2002000070A JP2002000070A JP3619998B2 JP 3619998 B2 JP3619998 B2 JP 3619998B2 JP 2002000070 A JP2002000070 A JP 2002000070A JP 2002000070 A JP2002000070 A JP 2002000070A JP 3619998 B2 JP3619998 B2 JP 3619998B2
Authority
JP
Japan
Prior art keywords
isolation
plan
state
maintenance management
operation state
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002000070A
Other languages
Japanese (ja)
Other versions
JP2003202920A (en
Inventor
利彰 小松
真 三澤
潤一 蓮沼
和利 磯村
篤志 菅谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2002000070A priority Critical patent/JP3619998B2/en
Publication of JP2003202920A publication Critical patent/JP2003202920A/en
Application granted granted Critical
Publication of JP3619998B2 publication Critical patent/JP3619998B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Testing And Monitoring For Control Systems (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、プラントの修理点検時等に特定の機器を隔離する操作のために使用するアイソレーション計画を作成する保守管理システム、方法及びプログラムに関し、特に、アイソレーション計画図面の機器操作状態を確認しやすいように表示させる保守管理システム、方法及びプログラムに関する。
【0002】
【従来技術】
従来、原子力施設などのプラント内において故障が発生した場合、まず故障した機器の周りの弁を閉めるなどの操作により故障機器を隔離するアイソレーション操作を実施し、アイソレーション操作後に故障機器の交換等の作業を実施する。
【0003】
またプラントによっては法的に定期的な点検が義務付けられている場合があり、この定期点検の際にも点検対象機器を隔離するアイソレーション操作を実施し、アイソレーション操作後に機器の交換等の作業を実施する。
【0004】
このようなアイソレーション操作にあっては、従来、保守要員が保守管理図面を管理しているサーバにアクセスして故障個所のCAD図面を検索してプリントアウトし、CAD図面上で故障機器の周りの弁などの機器を表すシンボルに、アイソレーション操作のために必要な弁の開閉状態などを示す状態図形を手作業で書込んでアイソレーション計画図面を準備し、アイソレーション状況が一見して確認できるようにすることで、業務上の安全性向上を図っている。
【0005】
【発明が解決しようとする課題】
しかしながら、従来のアイソレーション計画図面の作成作業にあっては、保守要員がプリントアウトしたCAD図面見て、対象機器に対するアイソレーション範囲の判断、アイソレーション範囲に含まれる弁の開閉状態などを手作業で書込んでおり、計画図面の作成に手間と時間がかかる問題がある。
【0006】
また故障機器の交換を行った場合には、交換機器をインデックスに、アイソレーション操作を行った機器のリストを保守記録として作成して保存しているが、後に同じ機器が故障した場合には、保存している対象リストを検索し、このリストを見ながら保守要員がプリントアウトしたCAD図面にアイソレーションのための弁の開閉状態などを手作業で書込んでアイソレーション計画図面を再度作成しており、依然として手間と時間がかかり、過去の保守履歴が充分に活用できない問題もある。
【0007】
本発明は、機器交換等に際しアイソレーション操作のための計画図面を効率良く作成可能とする保守管理システム、方法及びプログラムを提供することを目的とする。
【0008】
また本発明の他の目的は、機器シンボルに操作状態を示す状態表示図形を強調表示させてアイソレーション状況を一見して確認可能とする保守管理システム、方法及びプログラムを提供することを目的とする。
【0009】
【課題を解決するための手段】
図1は本発明の原理説明図である。本発明は、プラントの修理点検時等に特定の機器を隔離する操作のために使用するアイソレーション計画を作成する保守管理方法を提供する。
【0010】
この保守管理方法は、
隔離対象機器を含む図面を検索して表示する図面検索ステップと、
図面上で隔離範囲を決定し、隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定ステップと、
操作対象機器の操作状態に対応して手書き風の状態表示図形を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する計画図面作成ステップと、
確定操作によりアイソレーション計画図面を含む計画情報を保存する保存ステップと、
を備えたことを特徴とする。
【0011】
このため交換しようとする隔離対象機器を特定することによって、対応するCAD図面が自動的に検索して表示され、表示されたCAD図面上で隔離対象機器の周りのアイソレーション操作を必要とする隔離範囲を試行錯誤的に決定し、決定した隔離範囲の操作対象機器の操作状態を決めると、操作状態を示す手書き風の状態表示図形が聞きシンボルに重ねて表示され、アイソレーション状況が一見して確認可能となる。
【0012】
特に、通常、規則正しい図形が並ぶCAD図面において、手書き風図形の歪さは非常に強調された存在となり、機器シンボル図形と操作の状態表示図形との区別が、凝視せずとも感覚で識別可能となり、アイソレーション業務の安全性をさらに向上させることができる。
【0013】
本発明の保守管理方法は、アイソレーション計画図面を含む計画情報が保存されている場合、
隔離対象機器に対応した保存済みアイソレーション計画図面を検索して表示させる保存図面検索ステップと、
アイソレーション計画図面上で必要に応じて操作対象機器の操作状態を設定変更する操作状態変更ステップと、
操作対象機器の操作状態の設定変更に対応して手書き風の状態表示図形を変更させる計画図面変更ステップと、
確定操作により変更済みのアイソレーション計画図面を含む計画情報を保存する保存ステップと、
を備えたことを特徴とする。
【0014】
このため、一度、特定の隔離対象機器についてアイソレーション計画図面を含む計画情報が作成保存されると、それ以降については、保存しているアイソレーション計画図面を検索表示し、必要に応じて操作対象機器の操作状態を変更するだけでよく、保存されている過去の保守管理の資産を活用して迅速且つ確実なアイソレーション操作を可能とする。
【0015】
ここで、図面検索ステップは、機器番号、機器名称又は図面名称の入力により図面管理サーバから前記隔離対象機器を含むCAD図面を取得して表示する。
【0016】
操作状態設定ステップは、図面上の操作対象機器をクリックした際に、クリックした操作対象機器に配管接続されている次の操作対象機器を終端機器として隔離範囲を決定する。
【0017】
具体的には、操作状態設定ステップは、図面上の操作機器をクリックした際に、操作対象機器に配管接続されている次の操作対象機器を終端機器として予め登録した終端機器テーブルを参照して、クリックした操作対象機器に対応する終端機器を認識して隔離範囲を決定する。
【0018】
このため画面表示されているCAD図面上で隔離対象機器の周り操作対象機器をクリックすると、これに配管接続されている他の機器が自動的に選択されて例えば色を変えて表示され、この繰り返しにより試行錯誤的に隔離範囲を効率良く決定できる。
【0019】
操作状態設定ステップは、決定された隔離範囲に含まれる操作対象機器のリストを表示し、このリストに操作状態を入力設定する。
【0020】
計画図面作成ステップは、人が手書きした図形をCADシステムのプリミティブ図形に登録し、手書き風の状態表示図形として読出し表示させる。また計画図面作成ステップは、基本となる図形に所定のゆらぎをランダムに与えて手書き風の状態表示図形を作成表示させても良い。
【0021】
計画図面作成ステップは、操作機器の状態名称と状態表示図形の識別フラグを予め登録したアイソレーション状態定義テーブルを参照して、手書き風の状態表示図形を作成表示させる。
【0022】
計画図面作成ステップは、操作機器が弁の場合、弁の全開、中間開放及び全閉に対応して丸、三角及びバツの手書き風の状態表示図形を作成表示させる。
【0023】
保存ステップは、確定操作時に、操作対象機器に配管接続されている次の操作機器を終端機器として予め登録した終端機器テーブルを参照して隔離範囲を検証し、隔離範囲の過不足を表示させる。この自動検証機能により隔離範囲の決定をより確実なものとする。
【0024】
本発明は、プラントの修理点検時に特定の機器を隔離する操作のために使用するアイソレーション計画を作成する保守管理のためのプログラムを提供する。このプログラムは、
コンピュータに、
プラントの特定の隔離対象機器を含む図面を検索して表示する図面検索ステップと、
図面上で隔離範囲を決定し、前記隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定ステップと、
操作対象機器の操作状態に対応して手書き風の状態表示図形を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する計画図面作成ステップと、
確定操作によりアイソレーション計画図面を含む計画情報を保存する保存ステップと、
を実行させることを特徴とする。
【0025】
本発明のプログラムは、アイソレーション計画図面を含む計画情報が保存されている場合、コンピュータに、
隔離対象機器に対応した保存済みアイソレーション計画図面を検索して表示させる保存図面検索ステップと、
アイソレーション計画図面上で必要に応じて前記操作対象機器の操作状態を設定変更する操作状態変更ステップと、
操作対象機器の操作状態の設定変更に対応して手書き風の状態表示図形を変更させる計画図面変更ステップと、
確定操作により変更済みのアイソレーション計画図面を含む計画情報を保存する保存ステップと、
を実行させることを特徴とする。
【0026】
本発明は、プラントの修理点検時に特定の機器を隔離する操作のために使用するアイソレーション計画を作成する保守管理システムを提供する。
【0027】
この保守管理システムは、図1(B)のように、
隔離対象機器を含む図面を検索して表示する図面検索部40と、
図面上で隔離範囲を決定し、隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定部42と、
操作対象機器の操作状態に対応して手書き風の状態表示図形を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する計画図面作成部44と、
確定操作によりアイソレーション計画図面を含む計画情報を保存する保存部46と、
を備えたことを特徴とする。
【0028】
更に、本発明の保守管理システムは、
隔離対象機器に対応した保存済みアイソレーション計画図面を検索して表示させる保存図面検索部48と、
アイソレーション計画図面上で必要に応じて操作対象機器の操作状態を設定変更する操作状態変更部50と、
操作対象機器の操作状態の設定変更に対応して手書き風の状態表示図形を変更させる計画図面変更部52と、
を備えたことを特徴とする。尚、本発明のプログラム及び保守管理システムの詳細は、保守管理方法と同じになる。
【0029】
【発明の実施の形態】
図2は、本発明によるシステム構成の説明図である。図2において、原子力施設などのプラントに対し本発明の保守管理システムが設置されており、システム構成としては、保守管理クライアント10に対しLANなどのネットワークを介して図面管理サーバ12と保守管理データベースサーバ14を接続し、更にプラントを対象に設けられているデータ収集システムサーバ16が設けられている。
【0030】
保守管理クライアント10は、本発明による保守管理システムとしての機能を実現しており、プラントの機器が故障した場合の修理点検や定期点検の際に、特定の機器を隔離するための操作に使用するアイソレーション計画を作成する。このアイソレーション計画は、CAD図面を利用したアイソレーション計画図面とアイソレーション票で構成されている。
【0031】
図面管理サーバ12には、保守管理の対象となるプラントのCAD図面及び各種機器の情報が保存管理されている。このため保守管理クライアント10は、図面管理サーバ12にアクセスすることで、故障または点検時に交換対象とする機器を含むCAD図面を検索して表示することができる。
【0032】
保守管理データベースサーバ14は、本発明の保守管理システムを構築する保守管理クライアント10で作成されたアイソレーション計画を含む各種の保守管理データを、データベースとして蓄積管理している。
【0033】
更にデータ収集システムサーバ16は、保守管理対象となるプラントに設けられている各種センサによるデータ収集の記録管理を行っている。このデータ収集システムサーバ16で収集されたデータは、プラントの集中管理を行うクライアントもしくは監視パネルなどの表示制御に用いられる。
【0034】
図3は、本発明による保守管理システムの機能構成のブロック図であり、ネットワーク18を介して接続された図面管理サーバ12及び保守管理データベースサーバ14側と共に示している。
【0035】
図3において、本発明の保守管理システム11は、保守管理クライアント10と保守管理に必要な各種のテーブルで構成される。保守管理クライアント10には本発明によるアイソレーション計画の作成処理のため、機器テーブル20、機器/図面変換テーブル22、図番/図面名変換テーブル24、終端機器テーブル26、アイソレーション状態定義テーブル28、状態表示図形テーブル30、実施計画テーブル32及び実施計画詳細テーブル34が設けられている。これらのテーブルの詳細は後の説明で明らかにする。
【0036】
保守管理クライアント10の機能は、新規作成部36と実績参照作成部38で構成される。新規作成部36は、特定の隔離対象機器につきアイソレーション計画を最初に作成するときに動作する。実績参照作成部38は、特定の隔離対象機器につきアイソレーション計画が既に作成保存されている場合に動作する。
【0037】
新規作成部36は、図面検索部40、操作状態設定部42、計画図面作成部44及び保存部46を備える。図面検索部40は、故障または保守点検の対象となった隔離対象機器を含むCAD図面を検索して表示する。
【0038】
操作状態設定部42は、図面検索により表示されたCAD図面上でアイソレーションを行う隔離範囲を決定し、この隔離範囲に存在する操作対象機器の各々に隔離のための操作状態、例えば弁であれば弁の開または閉状態を設定する。
【0039】
計画図面作成部44は、操作状態設定部42で設定された操作対象機器の操作状態に対応して、手書き風の状態表示図形を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する。保存部46は確定操作によりアイソレーション計画図面を含む計画情報を、保守管理データベースサーバ14に設けているアイソレーション票ファイル58及びアイソレーション計画図面ファイル60に保存する。
【0040】
実績参照作成部38は、保存図面検索部48、操作状態変更部50及び計画図面変更部52を備える。保存図面検索部48は、故障または保守点検を行う隔離対象機器に対応した保存済みアイソレーション計画図面を検索して表示させる。
【0041】
この検索は、保守管理データベースサーバ14にアクセスし、アイソレーション票ファイル58から対応するアイソレーション票を読み出し、同時にアイソレーション計画図面ファイル60から対象とするアイソレーション計画図面を読み出す。
【0042】
操作状態変更部50は、検索表示された保存済みアイソレーション計画図面上で、必要に応じて操作対象機器の操作状態を設定変更する。もちろん、保存しているアイソレーション計画図面と今回の操作対象機器の操作状態に変化がなければ、この操作状態の変更は行わず、そのまま保存済みのアイソレーション計画図面を使用することになる。
【0043】
計画図面変更部52は、操作対象機器の操作状態の設定変更に対応して手書き風の状態表示図形を変更させる。もちろん実績参照作成部38においても、確定操作が行われると新規作成部36の保存部46を動作し、修正変更したアイソレーション計画図面及びこれに対応したアイソレーション票を保守管理データベースサーバ14のアイソレーション計画図面ファイル60及びアイソレーション票ファイル58に保存する。
【0044】
図4は、図3の保守管理システム11として機能する本発明の保守管理方法によるアイソレーション計画図面作成処理のフローチャートである。
【0045】
図4において、ステップS1〜S3、S5〜S7の処理が、図3の保守管理クライアント10に設けている新規作成部36の処理となる。またステップS1,S4,S5〜S7の処理が、図3の保守管理クライアント10における実績参照作成部38の処理となる。
【0046】
まずステップS1で新規作成が判別された場合には、ステップS2に進み、修理または保守点検の対象となっている隔離対象機器を含む図面を検索して表示する。続いてステップS2で、表示図面上でアイソレーション操作を行う隔離範囲を試行錯誤的に決定する。
【0047】
隔離範囲が決定したならば、ステップS5で隔離範囲に存在する操作対象機器についてアイソレーションのための操作状態を設定する。続いてステップS6で、操作対象機器の操作状態に対応して手書き風の状態表示図形、例えば手書き風の「○」「△」「×」を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する。ステップS7にあっては確定操作に基づき、作成されたアイソレーション計画図面を対応するアイソレーション票と共に保存する。
【0048】
一方、ステップS1で実績参照作成が判別された場合には、ステップS4に進み、修理または保守対象となっている隔離対象危機に対応した保存済みアイソレーション計画図面及びそのアイソレーション票を検索して保存図面を表示する。この保存図面には、前回作成された隔離範囲の操作対象機器について手書き風の状態表示図形が機器シンボルに重ねて表示されており、もし操作対象機器の操作状態を変更する必要があれば、ステップS5で操作状態の設定変更を行う。
【0049】
操作状態の設定変更が行われると、ステップS6で、変更した操作状態に対応して手書き風の状態表示図形を変更させて計画図面を作成する。最終的にステップS7で、確定操作に基づき、保存されているアイソレーション計画図面の修正変更により作成された新たなアイソレーション計画図面を、対応するアイソレーション票と共に保存する。
【0050】
図5は、図3の保守管理システム11及び図4のフローチャートに従って作成されたアイソレーション計画図面として使用される状態表示図面62の具体例である。
【0051】
図5において、この状態表示図面62は保守点検のためのアイソレーション計画図面の例であり、破線で示す部分が色分けされた隔離範囲を表わしており、この隔離範囲に存在する弁などの操作対象機器に対し、アイソレーションのための操作状態を表わす図形として手書き風の「○」「△」及び「×」が機器シンボルに重ね合わせて表示される。
【0052】
この手書き風状態表示図形による強調表示により操作対象機器のアイソレーション状態がCAD図面の機器シンボルから明確に区別でき、一見して確認することができる。
【0053】
図6は、図3の機器テーブル20の具体例であり、図5の状態表示図面62を作成する場合を例にとっている。この機器テーブル20は、機器番号、機器名称、定常状態コードの3つの情報で構成されている。また、この例ではテスト弁、テスト計測器、テストポンプの3種が示されており、テスト弁及びテスト計測器の定常状態コードは全開を示す「OP」、またテストポンプについては運転状態を示す定常状態コード「ON」となっている。
【0054】
図7は、図3の機器/図面変換テーブル22の具体例である。この機器/図面変換テーブル22は機器番号と図面番号で構成されている。このため、機器番号を指定することによって、指定した機器が含まれる図面番号を認識し、指定した機器を含むCAD図面を検索して表示させることができる。
【0055】
図8は、図3の図番/図面名変換テーブル24であり、図面番号に対応して図面名を登録している。このため、図7の機器/図面変換テーブル22により機器番号から図面番号が検索された後に、検索された図面番号により図番/図面名変換テーブル24を参照し、対応する図面名を取得し、これによって図面管理サーバ12側のCAD図面ファイル56から対象図面を読み出すことができる。
【0056】
図9は、図3の終端機器テーブル26の説明図である。この終端機器テーブル26は、CAD図面上でアイソレーションのための隔離範囲を自動的に決定する際に利用される。即ち終端機器テーブル26には、特定の操作対象機器をクリックした際に、配管により接続されているどの機器まで隔離範囲を拡大するかを定義している。
【0057】
この例では機種コードとして弁を意味する機種コード「TST1」が定義されている。したがって、CAD図面上で特定の機器をクリックすると、この終端機器テーブル26の定義に従って配管で接続された次の弁まで隔離範囲を自動的に拡張する処理が実行される。
【0058】
終端機器テーブル26は、CAD図面上で隔離範囲を決定する際に使用されるのみならず、アイソレーション計画図面を作成して確定操作を行って保存する際の検証にも使用される。
【0059】
即ち、CAD図面上における隔離範囲は保守要員が画面上で図面を見ながら試行錯誤的に範囲を決定しており、人為的な処理であることから必ずしも終端機器テーブルの定義に従った範囲の決定が行われていない可能性がある。
【0060】
そのため、アイソレーション計画図面について確定操作により保存する前に、CAD図面上に決定されている隔離範囲について終端機器テーブル26の定義を適用して検証し、隔離範囲の過不足があれば、これを図面上に例えば正規化表示などさせて、保守要員による確認を促すことになる。
【0061】
図10は、図3のアイソレーション状態定義テーブル28の説明図である。アイソレーション状態定義テーブル28は、状態コード、状態名及び状態表示図形フラグで構成されている。状態コードは、弁の場合についてはOPが開、MDが中間開、CLが閉となる。またポンプについてはONがオン(運転)、OFがオフ(停止)となる。
【0062】
状態表示図形フラグは、0で手書き風「○」、1で手書き風「△」、更に2で手書き風「×」としている。このアイソレーション状態定義テーブル28の内容に従って、例えば図6の機器テーブル20における定常状態コード、図13の実施計画詳細テーブル34におけるIL状態コード、復旧状態コードが設定されていることが分かる。
【0063】
図11は、図3の状態表示図形テーブル30の説明図である。この状態表示図形テーブル30には、図10のアイソレーション状態定義テーブル28の状態表示図形フラグ0、1、2に対応した手書き風の基本状態図形30−1,30−2,30−3が、CADのプリミティブ図形として登録されている。
【0064】
このプリミティブ図形は基本状態図形30−1〜30−3は、「1.0×1.0」に正規化された図形情報として、状態を「開」「中間開」「閉」に分けて登録されている。
【0065】
手書き風の基本状態図形30−1〜30−3は、図5の状態表示図面62のように、操作状態が設定された機器シンボルのサイズに合わせた拡大、縮小を受けて、機器シンボルに重ね合わせて表示される。
【0066】
図11の手書き風の基本状態図形30−1〜30−3は、次の2通りの手法で実現できる。
(1)実際に人が手書きした図形をCADシステムのプリミティブ図形として登録する。
(2)基本となる図形に、ある程度の揺らぎをランダムに与えて、手書き風図形をリアルタイムで生成して表示させる。
【0067】
このうち、(1)の人が手描きした図形を利用した場合には全て同じ手書き風図形となるが、(2)のランダムに揺らぎを与えてリアルタイムで生成する場合については、同じCAD図面の同じ図形であっても、シンボルごとにランダムに揺らぎが生じて異なった図形となり、手書き風図形としての強調性をより一層高めることができる。この(2)の、基本図形にある程度の揺らぎをランダムに与えて手書き風図形を生成する処理は、後の説明で明らかにする。
【0068】
図12は、図3の実施計画テーブル32の説明図である。この実施計画テーブル32はアイソレーション票のヘッダに当たるテーブルであり、実績参照作成時に検索されるデータであり、新規作成時には参照されない。実施計画テーブル32には、IL管理番号(アイソレーション管理番号)、件名、計画者名、計画日、計画開始日、計画終了日が設けられている。
【0069】
図13は図3の実施計画詳細テーブル34の説明図である。この実施計画詳細テーブル34は、アイソレーション票のデータ部に当たるテーブルであり、実績参照時に検索され、新規作成時には参照されない。
【0070】
実施計画詳細テーブル34は、IL管理番号、機器通番、IL機器番号、IL状態コード及び復旧状態コードで構成され、この例では図5に示した状態表示図面62に対応している。
【0071】
図14は、図5に状態表示図面62として示されたアイソレーション計画図面を作成する本発明による具体的な処理手順のフローチャートであり、このフローチャートが図3の保守管理クライアント10の新規作成部36、及び実績参照作成部38の機能を実現するプログラムを構成する。
【0072】
図14において、まずステップS1で図15のメニュー画面64を開き、その中の「アイソレーション管理」における新規計画66を選択してクリックする。このクリックにより、図16の新規作成画面68が開く。
【0073】
続いて保守要員は、ステップS2で新規作成か否かチェックし、新規作成であればステップS3に進み、図16の新規作成画面68の右下の対象図面一覧70をクリックし、図17の図面検索画面74を表示させる。
【0074】
この図面検索画面74には、図面名称76、対象機器番号78及び対象機器名称80の入力枠が設けられており、ステップS4でいずれかに必要な事項を入力して検索ボタンを押すと、図18の対象図面一覧画面82が開く。この場合には、図17の図面検索画面74の図面名称76に「テスト図面」を入力して検索ボタン80をクリックしている。
【0075】
続いてステップS5で、図18の対象図面一覧画面82から例えば「テスト図面2」を選択して図面確認ボタン84をクリックすると、図19のような元図面86が呼び出されて表示される。
【0076】
そこでステップS6において、図19の元図面86を対象に保守要員は試行錯誤的にアイソレーションのための隔離範囲を決定する。この隔離範囲の決定により、例えば図20のような範囲表示図面88が表示される。
【0077】
このアイソレーション範囲の決定にあっては、図面に表示されている機器の機器番号をクリックすると、クリックした機器の両側に配管接続されている弁までが自動的にアイソレーション範囲として広がる。
【0078】
例えば機器番号「TST3−999−2」をクリックすると、これに配管接続されている弁を示す機器番号「TST1−999−4」「TST1−999−5」「TST1−999−5V」「TST1−999−6」及び「TST1−999−7」まで、アイソレーション範囲が自動的に拡大する。このアイソレーション範囲の自動拡大は、図9に示した終端機器テーブル26の内容に基づいて行われている。
【0079】
ステップS6でアイソレーション範囲が決定したならば、ステップS11に進み、アイソレーション範囲の中の隔離操作したい機器を選択してクリックすることにより、図21のような機器情報操作画面90が開かれる。そこでステップS12に進み、この機器情報操作画面90にリスト表示されている機器に対し、アイソレーション状態を必要に応じて指定する。
【0080】
機器情報操作画面90におけるアイソレーション状態の設定が済んだならば、OKボタン91をクリックすると、このアイソレーション状態の指定に応じ、ステップS13で手書き風の状態表示図形を表示した図5の状態表示図面62が表示される。
【0081】
このようにして手書き風状態表示図形が機器シンボルに重ね合わせて表示されたアイソレーション計画図面が作成できたならば、ステップS14でダイアログを開いてリスト作成ボタンをクリックすると、図22に示すように、図5の状態表示図面62におけるアイソレーション範囲の機器とその操作状態に対応したアイソレーション票としてのアイソレーション票作成画面94が開かれる。
【0082】
最終的に、ステップS15でアイソレーション票作成画面94の左上のアイソレ票発行ボタン96をクリックするとデータが確定し、図5の状態表示図面92及び図22のアイソレーション票が保守管理データべ―スサーバ14に転送されて、アイソレーション票ファイル58及びアイソレーション計画図面ファイル60のそれぞれに保存される。
【0083】
一方、ステップS1で図15のメニュー画面64から図16の新規作成画面68を開いた状態で実績参照作成処理を行う場合には、新規作成画面68に設けているアイソレーションデータ抽出一覧72をステップS7で選択してクリックすることで、図23の実績参照画面98が開かれる。
【0084】
この実績参照画面98は、この例にあっては新規作成により保存した実績が1件登録されていることから、これを参照情報として選択した後にコピーボタン102を操作する処理をステップS8で行うと、図24のアイソレーション票修正画面102が作成中画面として表示される。
【0085】
そこでステップS9において、この作成中画面であるアイソレーション票修正画面102の中の対象図面一覧ボタン106をステップS9で選択して操作すると、図18と同じ対象図面一覧画面82が表示される。
【0086】
次にステップS10で対象画面一覧の中から図面例えば「テスト図面2」を選択して図面確認ボタン84を操作すると、新規作成により保存されている図5と同じアイソレーション範囲が広げられ、且つ手書き風操作状態図形が機器シンボルに重ねて表示された状態表示図面62が開く。
【0087】
ここで図5の状態表示図面62においてアイソレーション範囲の中に状態を変更したい機器があった場合には、その機器を選択してステップS11でクリックすると、ステップS12で図21のような機器情報操作画面90が開き、ここに表示された機器について必要に応じてアイソレーション状態を変更し、OKボタン91を操作すると、状態の変更に対応した機器シンボルについて変更後の手書き風状態表示図形に切り替わった状態表示図面62が表示される。
【0088】
そしてステップS14でダイアログを開いてリスト作成ボタンを押すと、変更後の操作状態に対応した図24のアイソレーション票修正画面102が表示され、左上の修正終了ボタン104をクリックすることで、ステップS15の新規作成時のアイソレーション票発行と同様にデータの確定が行われ、修正された状態表示図面62及びアイソレーション票を図3の保守管理データベースサーバ14側に転送して保存する。
【0089】
またステップS15で確定操作を行った場合には、図5のような状態表示図面62の中のアイソレーション範囲について、図3の終端機器テーブル26に定義しているアイソレーション範囲を拡大する条件との照合を行い、もし終端機器テーブル26の条件に適合しないアイソレーション範囲の過不足があった場合には、その部分を例えばフリッカ表示などし、操作員に確認を促す。
【0090】
次に図5のように、状態表示図面62の中に機器シンボルに応じてアイソレーションの操作状態を示す手書き風の状態表示図形として、基本状態図形に、ある程度の揺らぎをランダムに与えて手書き風図形を表示する処理を説明する。
【0091】
図25は、手書き風図形作成処理のフローチャートであり、揺らぎ状態図形の生成には、この実施形態にあってはベジェ曲線の特性を利用している。ベジェ曲線は、曲線を制御するコントロールポイントを決定すれば、コントロールポイントを通る滑らかな曲線を描画することができるアルゴリズムである。
【0092】
本発明にあっては、このベジェ曲線の生成に使用するコントロールポイントに、ある程度の揺らぎを与え、そのコントロールポイントを通るベジェ曲線を描画することにより、描画するごとに微妙に形の異なる手書き風の状態表示図形を生成する。更に、状態表示図形を描画する際に状態表示図形の重心座標にある程度のずれを与えることにより、描画ごとに微妙に位置のずれた状態図形を描く。
【0093】
なお、ここでは揺らぎ状態図形の生成にベジェ曲線を利用しているが、コントロールポイントによって制御することができ、滑らかな曲線を描けるものであれば、どのような曲線であってもよい。
【0094】
図25において、まずステップS1で、取得された機器番号及び開閉状態からシンボル図形及び基本状態図形を決定する。即ち、機器番号により弁のシンボル図形と開状態に対応した基本状態図形「○」を決定する。次に図25のステップS2で、シンボル図形を構成する基本図形の座標から図26のステップS2に示すように重心csとサイズ「size」を算出する。
【0095】
ここでサイズ「size」とはシンボル図形の重心から最も遠いシンボル位置までの長さであり、この例ではsize=3.6となっている。
【0096】
続いて図25のステップS3で、重心座標(cj)を
【0097】
【数1】

Figure 0003619998
【0098】
(但し、rudは│rud│≦1となる乱数関数により表記のたびに生成される揺らぎベクトル)
により決定する。この式における右辺第2項を重心csに加えることにより、ランダムに重心座標(cj)がずれ、これが状態図形の描画位置のずれを引き起こす。続いてステップS4で、次式により状態図形のコントロールポイントを決定する。
【0099】
【数2】
Figure 0003619998
【0100】
この場合にも右辺第3項によるランダムな成分の加算でコントロールポイントに揺らぎを与え、結果として状態図形に揺らぎが与えられる。
【0101】
このようにして状態図形のコントロールポイントが決定されてならば、ステップS5で、各コントロールポイントを通過するベジェ曲線を描画し、図5の状態表示図面62のように表示してユーザに示す。
【0102】
この図25のステップS3〜S5の処理は、図26のステップS3〜S5にまとめて示す処理となる。
【0103】
図27は、図25,図26に示した手書き風図形作成処理で使用される基本状態図形の登録データである。この基本状態図形は、開を示す「○」、中間開を示す「△」、閉を示す「×」のそれぞれにおいて、基本状態図形30−1,30−2,30−3を準備している。コントロールポイント座標は、基本状態図形30−1については6ポイント、基本状態図形30−2についても6ポイント、基本状態図形30−3については5ポイントを決めている。
【0104】
更に、これは基本状態図形を作成するベジェ曲線の数として、基本状態図形32−1については1本、基本状態図形32−2については3本、基本状態図形32−3については2本を、それぞれコントロールポイントに対応して定義している。
【0105】
したがって、図27のような基本状態図形のデータから基本コントロールポイントの座標を取得し、図25のステップS4のようにシンボル図形の重心座標とサイズを用いてコントロールポイントに揺らぎを与えることで、描画ごとに揺らぎを持った状態表示図形を生成することができる。
【0106】
このような本発明における機器シンボルに重ねて表示する状態表示図形に揺らぎを与える方法としては、これ以外に次のような方法をとることもできる。
(1)ユーザ別基本状態図形の登録
通常、人が描いた図形は描く人によって異なり、同じ人が描けばよく似た図形になるという特徴も考えられる。この特徴を表現するために、ユーザごとに異なった基本状態図形、即ち実際に手描きした図形もしくは基本コントロールポイントを登録する。そして図面を開く際に保守管理データベースサーバ14からアイソレーション票を読み出す際に、作成者を抽出し、作成者に対応した基本状態図形を選択して使用することで、作成者の癖に応じた状態表示図形を機器シンボルに重ねて表示することができる。
(2)重要度別基本状態図形の登録
機器番号ごとに重要度のパラメータを持たせ、重要度に応じ基本状態図形を登録することによって、重要な機器については通常より目立つ状態表示図形を描画する。
(3)重要度によるサイズ(size)への重み付け
機器番号ごとに重要度のパラメータを持たせ、重要度に応じてsizeパラメータを調整することによって、重要な機器の状態表示図形は少し大きめに強調描画する。
【0107】
なお、本発明は上記の実施形態に限定されず、その目的と利点を損なわない適宜の変形を含む。また、本発明は上記の実施形態に示した数値による限定は受けない。
【0108】
(付記)
(付記1)
プラントの修理点検時等に特定の機器を隔離する操作のために使用するアイソレーション計画を作成する保守管理方法に於いて、
隔離対象機器を含む図面を検索して表示する図面検索ステップと、
前記図面上で隔離範囲を決定し、前記隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定ステップと、
前記操作対象機器の操作状態に対応して手書き風の状態表示図形を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する計画図面作成ステップと、
確定操作により前記アイソレーション計画図面を含む計画情報を保存する保存ステップと、
を備えたことを特徴とする保守管理方法。(1)
【0109】
(付記2)
付記1記載の保守管理方法に於いて、アイソレーション計画図面を含む計画情報が保存されている場合、
隔離対象機器に対応した保存済みアイソレーション計画図面を検索して表示させる保存図面検索ステップと、
前記アイソレーション計画図面上で必要に応じて前記操作対象機器の操作状態を設定変更する操作状態変更ステップと、
前記操作対象機器の操作状態の設定変更に対応して手書き風の状態表示図形を変更させる計画図面変更ステップと、
確定操作により変更済みの前記アイソレーション計画図面を含む計画情報を保存する保存ステップと、
を備えたことを特徴とする保守管理方法。(2)
【0110】
(付記3)
付記1記載の保守管理方法に於いて、前記図面検索ステップは、機器番号、機器名称又は図面名称の入力により図面管理サーバから前記隔離対象機器を含むCAD図面を取得して表示することを特徴とする保守管理方法。
【0111】
(付記4)
付記1記載の保守管理方法に於いて、前記操作状態設定ステップは、前記図面上の操作機器をクリックした際に、クリックした前記操作機器に配管接続されている次の操作機器を終端機器として隔離範囲を決定することを特徴とする保守管理方法。
【0112】
(付記5)
付記1記載の保守管理方法に於いて、前記操作状態設定ステップは、前記図面上の操作対象機器をクリックした際に、該操作対象機器に配管接続されている次の操作対象機器を終端機器として予め登録した終端機器テーブルを参照して、クリックした前記操作機器に対応する終端機器を認識して隔離範囲を決定することを特徴とする保守管理方法。
【0113】
(付記6)
付記1記載の保守管理方法に於いて、前記操作状態設定ステップは、決定された隔離範囲に含まれる操作対象機器のリストを表示し、前記リストに操作状態を入力設定することを特徴とする保守管理方法。
【0114】
(付記7)
付記1記載の保守管理方法に於いて、前記計画図面作成ステップは、人が手書きした図形をCADシステムのプリミティブ図形に登録し、前記手書き風の状態表示図形として読出し表示させることを特徴とする保守管理方法。
【0115】
(付記8)
付記1記載の保守管理方法に於いて、前記計画図面作成ステップは、基本となる図形に所定のゆらぎをランダムに与えて前記手書き風の状態表示図形を作成表示させることを特徴とする保守管理方法。
【0116】
(付記9)
付記1記載の保守管理方法に於いて、前記計画図面作成ステップは、操作対象機器の状態名称と状態表示図形の識別フラグを予め登録したアイソレーション状態定義テーブルを参照して、前記手書き風の状態表示図形を作成表示させることを特徴とする保守管理方法。
【0117】
(付記10)
付記1記載の保守管理方法に於いて、前記計画図面作成ステップは、操作対象機器が弁の場合、弁の全開、中間開放及び全閉に対応して丸、三角及びバツの手書き風の状態表示図形を作成表示させることを特徴とする保守管理方法。
【0118】
(付記11)
付記1記載の保守管理方法に於いて、前記保存ステップは、確定操作時に、操作対象機器に配管接続されている次の操作対象機器を終端機器として予め登録した終端機器テーブルを参照して前記隔離範囲を検証し、隔離範囲の過不足を表示させることを特徴とする保守管理方法。
【0119】
(付記12)
コンピュータに、
プラントの特定の隔離対象機器を含む図面を検索して表示する図面検索ステップと、
前記図面上で隔離範囲を決定し、前記隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定ステップと、
前記操作対象機器の操作状態に対応して手書き風の状態表示図形を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する計画図面作成ステップと、
確定操作により前記アイソレーション計画図面を含む計画情報を保存する保存ステップと、
を実行させることを特徴とするプログラム。(3)
【0120】
(付記13)
付記12記載のプログラムに於いて、アイソレーション計画図面を含む計画情報が保存されている場合、前記コンピュータに、
隔離対象機器に対応した保存済みアイソレーション計画図面を検索して表示させる保存図面検索ステップと、
前記アイソレーション計画図面上で必要に応じて前記操作対象機器の操作状態を設定変更する操作状態変更ステップと、
前記操作対象機器の操作状態の設定変更に対応して手書き風の状態表示図形を変更させる計画図面変更ステップと、
確定操作により変更済みの前記アイソレーション計画図面を含む計画情報を保存する保存ステップと、
を実行させることを特徴とするプログラム。(4)
【0121】
(付記14)
プラントの修理点検時等に特定の機器を隔離する操作のために使用するアイソレーション計画を作成する保守管理システムに於いて、
隔離対象機器を含む図面を検索して表示する図面検索部と、
前記図面上で隔離範囲を決定し、前記隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定部と、
前記操作対象機器の操作状態に対応して手書き風の状態表示図形を機器のシンボルに重ねて表示させたアイソレーション計画図面を作成する計画図面作成部と、
確定操作により前記アイソレーション計画図面を含む計画情報を保存する保存部と、
を備えたことを特徴とする保守管理システム。(5)
【0122】
(付記15)
付記14記載の保守管理システムに於いて、更に、
隔離対象機器に対応した保存済みアイソレーション計画図面を検索して表示させる保存図面検索部と、
前記アイソレーション計画図面上で必要に応じて前記操作対象機器の操作状態を設定変更する操作状態変更部と、
前記操作対象機器の操作状態の設定変更に対応して手書き風の状態表示図形を変更させる計画図面変更部と、
を備えたことを特徴とする保守管理システム。
【0123】
【発明の効果】
以上説明してきたように本発明によれば、修理または保守のために隔離対象となる機器を特定することで、CAD図面が自動的に検索されて表示され、CAD図面上で隔離対象機器の周りのアイソレーション操作を必要とする隔離範囲を試行錯誤的に決定して操作対象機器の操作状態を決めると、操作状態を示す手書き風の状態表示図形が機器シンボルに重ねて表示され、アイソレーション状態を一見して確認可能なアイソレーション計画図面を迅速且つ適切に作成することができる。
【0124】
特に、規則正しい図形が並ぶCAD図面において手書き風の操作状態図形の描画は非常に強調された存在となり、機器シンボル図形と操作状態図形との区別が凝視しなくとも感覚的に識別可能となり、アイソレーションのための機器の操作状態を見誤ることなく、確実にアイソレーション計画図面に従った操作を現場で行うことができ、アイソレーション業務の安全性を更に向上することができる。
【図面の簡単な説明】
【図1】本発明の原理説明図
【図2】本発明のシステム構成のブロック図
【図3】本発明の機能構成のブロック図
【図4】本発明によるアイソレーション計画図面作成処理のフローチャート
【図5】本発明により作成表示されるアイソレーション計画図面の説明図
【図6】図3の機器テーブルの説明図
【図7】図3の機器/図面変換テーブルの説明図
【図8】図3の図番/図面名変換テーブルの説明図
【図9】図3の終端機器テーブルの説明図
【図10】図3のアイソレーション定義テーブルの説明図
【図11】図3の状態表示図形テーブルの説明図
【図12】図3の計画図面テーブルの説明図
【図13】図3の実施計画詳細テーブルの説明図
【図14】図5のアイソレーション計画図面を作成する具体的処理手順のフローチャート
【図15】メニュー画面の説明図
【図16】メニュー画面から開いた新規作成画面の説明図
【図17】新規作成画面から開いた図面検索画面の説明図
【図18】図面検索画面の検索実行で得られた対象図面一覧画面の説明図
【図19】対象図面一覧画面から開かれた元図面の画面説明図
【図20】隔離範囲の決定による範囲表示図面の画面説明図
【図21】隔離範囲の機器のクリックで開かれた機器情報操作画面の説明図
【図22】確定操作で作成された図5の計画図面に対応したアイソレーションリスト作成画面の説明図
【図23】保存している計画図面を検索する実績参照画面の説明図
【図24】実績参照画面から計画図面の修正に使用するアイソレーション修正画面の説明図
【図25】本発明で使用する手書き風図形作成処理のフローチャート
【図26】図25の処理内容の説明図
【図27】図25の処理に使用される手書き風の基本状態図形、コントロールポイント及びベジェ曲線の数の説明図
【符号の説明】
10:保守管理クライアント
11:保守管理システム
12:図面管理サーバ
14:保守管理データベースサーバ
16:データ収集システムサーバ
18:ネットワーク
20:機器テーブル
22:機器/図面変換テーブル
24:図番/図面名変換テーブル
26:終端機器テーブル
28:アイソレーション状態定義テーブル
30:状態表示図形テーブル
32:実施計画テーブル(ヘッダ部)
34:実施計画詳細テーブル(データ部)
36:新規作成部
38:実績参照作成部
40:図面検索部
42:操作状態設定部
44:計画図面作成部
46:保存部
48:保存図面検索部
50:操作状態変更部
52:計画図面変更部
54:図面機器ファイル
56:CAD図面ファイル
58:アイソレーション票ファイル
60:アイソレーション計画図面ファイル
62:状態表示図面
64:メニュー画面
68:新規作成画面
74:図面検索画面
82:対象図面一覧画面
86:元図面
88:範囲表示図面
90:機器情報操作画面
92:アイソレーション票作成画面
98:実績参照画面[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a maintenance management system, method, and program for creating an isolation plan used for an operation of isolating a specific device at the time of repair and inspection of a plant, and in particular, confirming a device operation state in an isolation plan drawing. The present invention relates to a maintenance management system, a method, and a program that are displayed so as to be easily performed.
[0002]
[Prior art]
Conventionally, when a failure occurs in a plant such as a nuclear facility, an isolation operation that isolates the failed device by first closing a valve around the failed device is performed, and then the failed device is replaced after the isolation operation. Perform the work.
[0003]
Also, depending on the plant, there may be legally required periodic inspections. During this periodic inspection, an isolation operation is performed to isolate the inspection target equipment, and the work such as replacement of the equipment is performed after the isolation operation. To implement.
[0004]
In such an isolation operation, conventionally, a maintenance staff accesses a server that manages maintenance management drawings, searches for a CAD drawing of a failure location, prints it out, and around the failed device on the CAD drawing. Prepare the isolation plan drawing by manually writing the state figure indicating the open / closed state of the valve necessary for the isolation operation on the symbol representing the device such as the valve, and check the isolation status at a glance By making it possible, we are working to improve operational safety.
[0005]
[Problems to be solved by the invention]
However, in the conventional process of creating an isolation plan drawing, it is necessary to manually determine the isolation range for the target device, open / close state of the valves included in the isolation range, etc. by looking at the CAD drawing printed out by maintenance personnel. There is a problem that it takes time and labor to create a plan drawing.
[0006]
In addition, when a failed device is replaced, the replacement device is used as an index, and a list of devices that have performed isolation operations is created and saved as a maintenance record.If the same device fails later, Search the saved target list, write the isolation plan drawing again by manually writing the open / closed state of the valve for isolation on the CAD drawing printed by maintenance personnel while viewing this list. However, it still takes time and effort, and the past maintenance history cannot be fully utilized.
[0007]
It is an object of the present invention to provide a maintenance management system, method, and program that can efficiently create a plan drawing for an isolation operation when equipment is replaced.
[0008]
Another object of the present invention is to provide a maintenance management system, method, and program that make it possible to confirm an isolation status at a glance by highlighting a status display graphic indicating an operation status on a device symbol. .
[0009]
[Means for Solving the Problems]
FIG. 1 is a diagram illustrating the principle of the present invention. The present invention provides a maintenance management method for creating an isolation plan used for an operation of isolating a specific device at the time of repair and inspection of a plant.
[0010]
This maintenance management method
A drawing search step for searching and displaying a drawing including a device to be quarantined;
An operation state setting step for determining an isolation range on the drawing and setting an operation state for isolation for each operation target device existing in the isolation range;
A plan drawing creation step for creating an isolation plan drawing in which a hand-drawn state display figure is displayed on a device symbol in correspondence with the operation state of the operation target device;
A saving step for saving the plan information including the isolation plan drawing by a confirmation operation;
It is provided with.
[0011]
For this reason, by identifying the isolation target device to be replaced, the corresponding CAD drawing is automatically searched and displayed, and the isolation that requires an isolation operation around the isolation target device on the displayed CAD drawing. When the range is determined on a trial and error basis, and the operation status of the device to be operated in the determined isolation range is determined, a hand-drawn status display figure indicating the operation status is displayed over the listening symbol, and the isolation status can be seen at a glance. It becomes possible to confirm.
[0012]
In particular, in a CAD drawing in which regular graphics are usually arranged, the distortion of handwritten-style graphics is highly emphasized, and the distinction between device symbol graphics and operation status display graphics can be identified with a sense without staring. The safety of isolation work can be further improved.
[0013]
In the maintenance management method of the present invention, when plan information including an isolation plan drawing is stored,
A saved drawing search step for searching and displaying a saved isolation plan drawing corresponding to the device to be quarantined;
An operation state change step for changing the operation state of the operation target device as necessary on the isolation plan drawing,
A plan drawing change step for changing a handwritten-like state display figure in response to a change in the operation state of the operation target device;
A save step for saving plan information including an isolation plan drawing that has been changed by a confirm operation;
It is provided with.
[0014]
For this reason, once the plan information including the isolation plan drawing is created and saved for a specific device to be isolated, the saved isolation plan drawing is searched and displayed for the subsequent items, and the operation target is operated as necessary. It is only necessary to change the operation state of the device, and quick and reliable isolation operation can be performed by utilizing the stored maintenance management assets.
[0015]
Here, the drawing retrieval step acquires and displays a CAD drawing including the device to be isolated from the drawing management server by inputting a device number, a device name, or a drawing name.
[0016]
In the operation state setting step, when the operation target device on the drawing is clicked, the isolation range is determined with the next operation target device connected to the clicked operation target device as a terminal device.
[0017]
Specifically, in the operation state setting step, when the operation device on the drawing is clicked, the next operation target device connected by piping to the operation target device is referred to as a termination device table registered in advance as a termination device. The terminal device corresponding to the clicked operation target device is recognized to determine the isolation range.
[0018]
For this reason, when an operation target device is clicked around the device to be isolated on the CAD drawing displayed on the screen, another device connected to the pipe is automatically selected and displayed, for example, in a different color. Thus, the isolation range can be efficiently determined by trial and error.
[0019]
The operation state setting step displays a list of operation target devices included in the determined isolation range, and inputs and sets the operation state in this list.
[0020]
In the plan drawing creation step, a figure handwritten by a person is registered in a primitive figure of the CAD system, and is read and displayed as a handwritten-like state display figure. In the planned drawing creation step, a predetermined fluctuation may be randomly given to the basic figure to create and display a handwritten state display figure.
[0021]
The planned drawing creation step creates and displays a handwritten-like state display graphic with reference to the isolation state definition table in which the state name of the operating device and the identification flag of the state display graphic are registered in advance.
[0022]
In the plan drawing creation step, when the operation device is a valve, a handwritten-like state display figure of circle, triangle and cross is created and displayed corresponding to full open, intermediate open and full close of the valve.
[0023]
The saving step verifies the isolation range with reference to a terminal device table in which the next operation device connected to the operation target device by pipe connection is registered in advance as a terminal device, and displays whether the isolation range is excessive or insufficient. This automatic verification function makes the isolation range more reliable.
[0024]
The present invention provides a maintenance management program for creating an isolation plan to be used for an operation of isolating a specific device during a repair inspection of a plant. This program
On the computer,
A drawing search step for searching and displaying a drawing including a specific device to be isolated in the plant;
An operation state setting step for determining an isolation range on the drawing, and setting an operation state for isolation for each operation target device existing in the isolation range;
A plan drawing creation step for creating an isolation plan drawing in which a hand-drawn state display figure is displayed on a device symbol in correspondence with the operation state of the operation target device;
A saving step for saving the plan information including the isolation plan drawing by a confirmation operation;
Is executed.
[0025]
The program of the present invention, when plan information including an isolation plan drawing is stored,
A saved drawing search step for searching and displaying a saved isolation plan drawing corresponding to the device to be quarantined;
An operation state change step for changing the operation state of the operation target device as necessary on the isolation plan drawing; and
A plan drawing change step for changing a handwritten-like state display figure in response to a change in the operation state of the operation target device;
A save step for saving plan information including an isolation plan drawing that has been changed by a confirm operation;
Is executed.
[0026]
The present invention provides a maintenance management system for creating an isolation plan to be used for an operation of isolating a specific device during a repair inspection of a plant.
[0027]
This maintenance management system is as shown in FIG.
A drawing search unit 40 for searching and displaying a drawing including a device to be isolated;
An operation state setting unit 42 for determining an isolation range on the drawing, and setting an operation state for isolation for each operation target device existing in the isolation range;
A plan drawing creation unit 44 for creating an isolation plan drawing in which a handwritten-like state display graphic is displayed on a symbol of the device in correspondence with the operation state of the operation target device;
A storage unit 46 for storing plan information including an isolation plan drawing by a confirmation operation;
It is provided with.
[0028]
Furthermore, the maintenance management system of the present invention provides:
A saved drawing search unit 48 for searching and displaying a saved isolation plan drawing corresponding to the isolation target device;
An operation state changing unit 50 for changing the setting of the operation state of the operation target device as necessary on the isolation plan drawing;
A plan drawing changing unit 52 for changing a state display figure in a handwritten style in response to a change in setting of an operation state of the operation target device;
It is provided with. The details of the program and the maintenance management system of the present invention are the same as the maintenance management method.
[0029]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 2 is an explanatory diagram of a system configuration according to the present invention. In FIG. 2, the maintenance management system of the present invention is installed in a plant such as a nuclear facility. As a system configuration, the drawing management server 12 and the maintenance management database server are connected to the maintenance management client 10 via a network such as a LAN. 14 and a data collection system server 16 provided for the plant.
[0030]
The maintenance management client 10 realizes a function as a maintenance management system according to the present invention, and is used for an operation for isolating a specific device at the time of repair inspection and periodic inspection when a plant device fails. Create an isolation plan. This isolation plan is composed of an isolation plan drawing using a CAD drawing and an isolation vote.
[0031]
The drawing management server 12 stores and manages the CAD drawings of the plant to be maintained and information on various devices. For this reason, the maintenance management client 10 can search and display a CAD drawing including a device to be replaced at the time of failure or inspection by accessing the drawing management server 12.
[0032]
The maintenance management database server 14 stores and manages various maintenance management data including an isolation plan created by the maintenance management client 10 that constructs the maintenance management system of the present invention as a database.
[0033]
Further, the data collection system server 16 performs record management of data collection by various sensors provided in the plant to be maintained and managed. Data collected by the data collection system server 16 is used for display control of a client or a monitoring panel that performs centralized management of the plant.
[0034]
FIG. 3 is a block diagram of the functional configuration of the maintenance management system according to the present invention, which is shown together with the drawing management server 12 and the maintenance management database server 14 connected via the network 18.
[0035]
In FIG. 3, the maintenance management system 11 of the present invention comprises a maintenance management client 10 and various tables necessary for maintenance management. The maintenance management client 10 includes a device table 20, a device / drawing conversion table 22, a drawing number / drawing name conversion table 24, a terminal device table 26, an isolation state definition table 28, for creating an isolation plan according to the present invention. A status display graphic table 30, an execution plan table 32, and an execution plan detail table 34 are provided. Details of these tables will be made clear later.
[0036]
The function of the maintenance management client 10 includes a new creation unit 36 and a result reference creation unit 38. The new creation unit 36 operates when an isolation plan is first created for a specific device to be isolated. The result reference creation unit 38 operates when an isolation plan has already been created and stored for a specific device to be isolated.
[0037]
The new creation unit 36 includes a drawing search unit 40, an operation state setting unit 42, a plan drawing creation unit 44, and a storage unit 46. The drawing retrieval unit 40 retrieves and displays a CAD drawing including an isolation target device that is a target of failure or maintenance inspection.
[0038]
The operation state setting unit 42 determines an isolation range to be isolated on the CAD drawing displayed by drawing search, and each operation target device existing in the isolation range has an operation state for isolation, for example, a valve. Set the valve open or closed.
[0039]
The plan drawing creation unit 44 creates an isolation plan drawing in which a hand-drawn state display graphic is displayed superimposed on a device symbol in accordance with the operation state of the operation target device set by the operation state setting unit 42. . The storage unit 46 stores the plan information including the isolation plan drawing by the confirmation operation in the isolation form file 58 and the isolation plan drawing file 60 provided in the maintenance management database server 14.
[0040]
The record reference creation unit 38 includes a saved drawing search unit 48, an operation state change unit 50, and a plan drawing change unit 52. The saved drawing retrieval unit 48 retrieves and displays a saved isolation plan drawing corresponding to the isolation target device to be subjected to failure or maintenance inspection.
[0041]
In this search, the maintenance management database server 14 is accessed, the corresponding isolation vote is read from the isolation vote file 58, and the target isolation plan drawing is simultaneously read from the isolation plan drawing file 60.
[0042]
The operation state changing unit 50 changes the setting of the operation state of the operation target device as needed on the stored isolation plan drawing displayed by search. Of course, if there is no change in the stored isolation plan drawing and the operation state of the current operation target device, the operation state is not changed and the stored isolation plan drawing is used as it is.
[0043]
The plan drawing change unit 52 changes the handwritten-style state display graphic in response to the change in setting of the operation state of the operation target device. Of course, in the result reference creation unit 38, when a confirmation operation is performed, the storage unit 46 of the new creation unit 36 is operated, and the modified isolation plan drawing and the isolation form corresponding thereto are stored in the maintenance management database server 14. The configuration plan drawing file 60 and the isolation form file 58 are stored.
[0044]
FIG. 4 is a flowchart of an isolation plan drawing creation process according to the maintenance management method of the present invention that functions as the maintenance management system 11 of FIG.
[0045]
In FIG. 4, the processing of steps S1 to S3 and S5 to S7 is the processing of the new creation unit 36 provided in the maintenance management client 10 of FIG. Further, the processing of steps S1, S4, S5 to S7 is the processing of the result reference creation unit 38 in the maintenance management client 10 of FIG.
[0046]
First, if it is determined in step S1 that a new product has been created, the process proceeds to step S2, and a drawing including a device to be isolated that is a target of repair or maintenance inspection is retrieved and displayed. Subsequently, in step S2, the isolation range for performing the isolation operation on the display drawing is determined by trial and error.
[0047]
If the isolation range is determined, an operation state for isolation is set for the operation target device existing in the isolation range in step S5. Subsequently, in step S6, an isolation plan drawing in which handwritten style display graphics, for example, “O”, “△”, and “X” in a handwritten style are displayed on the equipment symbol in correspondence with the operating state of the operation target device. Create In step S7, based on the confirmation operation, the created isolation plan drawing is stored together with the corresponding isolation form.
[0048]
On the other hand, if the result reference creation is determined in step S1, the process proceeds to step S4, and the stored isolation plan drawing corresponding to the isolation target crisis that is the object of repair or maintenance and its isolation form are searched. Display the saved drawing. In this saved drawing, a handwritten-like status display figure is displayed over the device symbol for the operation target device in the isolation range created last time, and if it is necessary to change the operation state of the operation target device, In S5, the setting of the operation state is changed.
[0049]
When the operation state setting is changed, in step S6, a plan drawing is created by changing the handwritten-style state display graphic corresponding to the changed operation state. Finally, in step S7, a new isolation plan drawing created by correcting and changing the stored isolation plan drawing based on the confirmation operation is saved together with the corresponding isolation form.
[0050]
FIG. 5 is a specific example of the state display drawing 62 used as the isolation plan drawing created according to the maintenance management system 11 of FIG. 3 and the flowchart of FIG.
[0051]
In FIG. 5, this state display drawing 62 is an example of an isolation plan drawing for maintenance and inspection, and a portion indicated by a broken line represents a color-isolated isolation range, and an operation target such as a valve existing in this isolation range. For the device, handwritten-style “◯”, “Δ”, and “×” are superimposed on the device symbol as graphics representing the operation state for isolation.
[0052]
The highlighted state by the handwritten-like state display graphic can clearly distinguish the operation target device from the device symbol of the CAD drawing and can be confirmed at a glance.
[0053]
FIG. 6 is a specific example of the device table 20 of FIG. 3, and takes the case of creating the state display drawing 62 of FIG. The device table 20 is composed of three pieces of information: a device number, a device name, and a steady state code. In this example, three types of test valves, test measuring instruments, and test pumps are shown. The steady state codes of the test valves and test measuring instruments are “OP” indicating full open, and the test pumps indicate operating conditions. The steady state code is “ON”.
[0054]
FIG. 7 is a specific example of the device / drawing conversion table 22 of FIG. The device / drawing conversion table 22 includes a device number and a drawing number. For this reason, by designating the device number, it is possible to recognize the drawing number including the designated device and to search and display the CAD drawing including the designated device.
[0055]
FIG. 8 is a diagram number / drawing name conversion table 24 of FIG. 3, in which drawing names are registered corresponding to the drawing numbers. For this reason, after the drawing number is searched from the device number by the device / drawing conversion table 22 in FIG. 7, the drawing number / drawing name conversion table 24 is referred to by the searched drawing number, and the corresponding drawing name is acquired. As a result, the target drawing can be read from the CAD drawing file 56 on the drawing management server 12 side.
[0056]
FIG. 9 is an explanatory diagram of the terminal device table 26 of FIG. This terminal device table 26 is used when automatically determining an isolation range for isolation on a CAD drawing. In other words, in the terminal device table 26, when a specific operation target device is clicked, it is defined to which device connected by piping the range of isolation is expanded.
[0057]
In this example, a model code “TST1” meaning a valve is defined as a model code. Therefore, when a specific device is clicked on the CAD drawing, a process of automatically extending the isolation range to the next valve connected by piping according to the definition of the terminal device table 26 is executed.
[0058]
The terminal device table 26 is used not only for determining the isolation range on the CAD drawing but also for verification when the isolation plan drawing is created and confirmed and saved.
[0059]
That is, the isolation range on the CAD drawing is determined by trial and error while maintenance personnel look at the drawing on the screen, and since it is an artificial process, the range is always determined according to the definition of the terminal device table. May not have been done.
[0060]
Therefore, before saving the isolation plan drawing by the confirmation operation, the definition of the termination device table 26 is applied to the isolation range determined on the CAD drawing and verified. For example, normalization is displayed on the drawing to prompt confirmation by maintenance personnel.
[0061]
FIG. 10 is an explanatory diagram of the isolation state definition table 28 of FIG. The isolation state definition table 28 includes a state code, a state name, and a state display graphic flag. In the case of a valve, the status code is OP open, MD intermediate open, and CL closed. As for the pump, ON is on (operation) and OF is off (stop).
[0062]
The state display graphic flag is 0 for handwritten style “◯”, 1 for handwritten style “Δ”, and 2 for handwritten style “X”. It can be seen that, for example, a steady state code in the device table 20 of FIG. 6 and an IL state code and a recovery state code in the implementation plan detail table 34 of FIG. 13 are set according to the contents of the isolation state definition table 28.
[0063]
FIG. 11 is an explanatory diagram of the state display graphic table 30 of FIG. In this state display graphic table 30, handwritten-like basic state figures 30-1, 30-2, 30-3 corresponding to the state display graphic flags 0, 1, 2 of the isolation state definition table 28 of FIG. It is registered as a primitive figure of CAD.
[0064]
As for this primitive figure, basic state figures 30-1 to 30-3 are registered as figure information normalized to “1.0 × 1.0” by dividing the state into “open”, “intermediate open”, and “closed”. Has been.
[0065]
As shown in the state display drawing 62 of FIG. 5, the handwritten-like basic state figures 30-1 to 30-3 are enlarged and reduced in accordance with the size of the device symbol for which the operation state is set, and are superimposed on the device symbol. Displayed together.
[0066]
The handwritten style basic state figures 30-1 to 30-3 in FIG. 11 can be realized by the following two methods.
(1) A figure actually handwritten by hand is registered as a primitive figure of a CAD system.
(2) A certain amount of fluctuation is randomly given to a basic figure, and a handwritten-like figure is generated and displayed in real time.
[0067]
Of these, when the hand-drawn figure by the person of (1) is used, all the same hand-drawn-like figures are obtained. However, in the case of generating in real time with random fluctuations of (2), the same CAD drawing is the same. Even in the case of a graphic, a random fluctuation occurs for each symbol, resulting in a different graphic, and the emphasis as a handwritten graphic can be further enhanced. The process of generating a handwritten style figure by randomly giving a certain amount of fluctuation to the basic figure in (2) will be clarified in later explanation.
[0068]
FIG. 12 is an explanatory diagram of the execution plan table 32 of FIG. The implementation plan table 32 is a table corresponding to the header of the isolation vote, and is data that is searched for when creating a result reference, and is not referenced when creating a new record. The execution plan table 32 includes an IL management number (isolation management number), a subject, a planner name, a planning date, a planning start date, and a planning end date.
[0069]
FIG. 13 is an implementation plan detail table of FIG. 34 It is explanatory drawing of. This execution plan detail table 34 Is a table corresponding to the data part of the isolation vote, which is searched when referring to the results and is not referred to when newly creating.
[0070]
Implementation plan details table 34 Consists of an IL management number, an equipment serial number, an IL equipment number, an IL status code, and a recovery status code, and corresponds to the status display drawing 62 shown in FIG. 5 in this example.
[0071]
FIG. 14 is a flowchart of a specific processing procedure according to the present invention for creating the isolation plan drawing shown as the state display drawing 62 in FIG. 5. This flowchart is a new creation unit 36 of the maintenance management client 10 in FIG. And the program which implement | achieves the function of the results reference preparation part 38 is comprised.
[0072]
In FIG. 14, first, in step S1, the menu screen 64 of FIG. 15 is opened, and a new plan 66 in “isolation management” is selected and clicked. This click opens the new creation screen 68 of FIG.
[0073]
Subsequently, the maintenance staff checks whether or not it is a new creation in step S2, and if it is a new creation, proceeds to step S3, clicks the target drawing list 70 in the lower right of the new creation screen 68 in FIG. A search screen 74 is displayed.
[0074]
The drawing search screen 74 is provided with input boxes for drawing name 76, target device number 78, and target device name 80. When a necessary item is input in step S4 and the search button is pressed, 18 target drawing list screen 82 opens. In this case, “test drawing” is entered as the drawing name 76 on the drawing search screen 74 in FIG. 17 and the search button 80 is clicked.
[0075]
Subsequently, in step S5, for example, when “test drawing 2” is selected from the target drawing list screen 82 of FIG. 18 and the drawing confirmation button 84 is clicked, the original drawing 86 as shown in FIG. 19 is called and displayed.
[0076]
Therefore, in step S6, the maintenance staff determines the isolation range for isolation by trial and error with the original drawing 86 of FIG. By determining the isolation range, for example, a range display drawing 88 as shown in FIG. 20 is displayed.
[0077]
In the determination of the isolation range, when the device number of the device displayed in the drawing is clicked, the valves connected to both sides of the clicked device are automatically expanded as the isolation range.
[0078]
For example, when the device number “TST3-999-2” is clicked, the device numbers “TST1-999-4”, “TST1-999-5”, “TST1-999-5V”, and “TST1-” indicating the valves connected to the pipes are clicked. The isolation range automatically expands to “999-6” and “TST1-999-7”. This automatic expansion of the isolation range is performed based on the contents of the terminal device table 26 shown in FIG.
[0079]
If the isolation range is determined in step S6, the process proceeds to step S11, and the device information operation screen 90 as shown in FIG. 21 is opened by selecting and clicking a device to be isolated in the isolation range. Therefore, the process proceeds to step S12, and the isolation state is designated as necessary for the devices listed on the device information operation screen 90.
[0080]
After the setting of the isolation state on the device information operation screen 90 is completed, when the OK button 91 is clicked, according to the designation of the isolation state, the state display in FIG. A drawing 62 is displayed.
[0081]
When the isolation plan drawing in which the handwritten-like state display figure is superimposed on the device symbol can be created in this way, the dialog is opened in step S14 and the list creation button is clicked, as shown in FIG. Then, an isolation form creation screen 94 is opened as an isolation form corresponding to the device in the isolation range in the state display drawing 62 of FIG. 5 and its operation state.
[0082]
Finally, in step S15, when the isot form issuing button 96 on the upper left of the isolation form creation screen 94 is clicked, the data is confirmed, and the status display drawing 92 of FIG. 5 and the isolation form of FIG. 22 are the maintenance management database server. 14 and stored in the isolation form file 58 and the isolation plan drawing file 60, respectively.
[0083]
On the other hand, when the performance reference creation process is performed in the state where the new creation screen 68 of FIG. 16 is opened from the menu screen 64 of FIG. 15 in step S1, the isolation data extraction list 72 provided in the new creation screen 68 is stepped. By selecting and clicking in S7, the result reference screen 98 of FIG. 23 is opened.
[0084]
In this example, the result reference screen 98 is registered with one record that has been newly created, and when this is selected as reference information, the process of operating the copy button 102 is performed in step S8. 24, the isolation form correction screen 102 shown in FIG. 24 is displayed as a creating screen.
[0085]
Therefore, in step S9, when the target drawing list button 106 in the isolation form correction screen 102, which is the creation screen, is selected and operated in step S9, the same target drawing list screen 82 as in FIG. 18 is displayed.
[0086]
Next, in step S10, when a drawing such as “test drawing 2” is selected from the target screen list and the drawing confirmation button 84 is operated, the same isolation range as that in FIG. The state display drawing 62 in which the wind operation state figure is displayed in an overlapping manner with the device symbol is opened.
[0087]
Here, in the state display drawing 62 of FIG. 5, when there is a device whose state is to be changed in the isolation range, when that device is selected and clicked in step S11, device information as shown in FIG. 21 is displayed in step S12. When the operation screen 90 is opened, the isolation state of the device displayed here is changed as necessary, and the OK button 91 is operated, the device symbol corresponding to the change of state is switched to the changed handwritten state display figure. The state display drawing 62 is displayed.
[0088]
When the dialog is opened in step S14 and the list creation button is pressed, the isolation form correction screen 102 shown in FIG. 24 corresponding to the changed operation state is displayed. By clicking the correction end button 104 in the upper left, step S15 The data is confirmed in the same manner as the issuance of the isolation form at the time of new creation, and the corrected state display drawing 62 and the isolation form are transferred to the maintenance management database server 14 side of FIG. 3 and stored.
[0089]
When the confirmation operation is performed in step S15, conditions for expanding the isolation range defined in the terminal device table 26 of FIG. 3 for the isolation range in the state display drawing 62 as shown in FIG. If there is an excess or deficiency in the isolation range that does not conform to the conditions of the terminal device table 26, the part is displayed, for example, as a flicker, and the operator is prompted to confirm.
[0090]
Next, as shown in FIG. 5, in the state display drawing 62, as a handwritten-like state display figure indicating the operation state of isolation according to the device symbol, a certain amount of fluctuation is randomly given to the basic state figure and the handwritten style is displayed. A process for displaying a graphic will be described.
[0091]
FIG. 25 is a flowchart of a handwritten-style graphic creation process. In this embodiment, the characteristics of the Bezier curve are used to generate the fluctuation state graphic. The Bezier curve is an algorithm that can draw a smooth curve passing through a control point if a control point for controlling the curve is determined.
[0092]
In the present invention, a certain amount of fluctuation is given to the control point used to generate the Bezier curve, and a Bezier curve passing through the control point is drawn, so that a handwriting style with a slightly different shape every time it is drawn. A status display figure is generated. Further, when the state display graphic is drawn, a certain amount of deviation is given to the barycentric coordinates of the state display graphic, thereby drawing the state graphic slightly shifted in position for each drawing.
[0093]
Here, a Bezier curve is used to generate the fluctuation state figure, but any curve may be used as long as it can be controlled by control points and can draw a smooth curve.
[0094]
In FIG. 25, first, in step S1, a symbol graphic and a basic state graphic are determined from the acquired device number and open / closed state. That is, the basic symbol “◯” corresponding to the valve symbol and the open state is determined based on the device number. Next, in step S2 of FIG. 25, the center of gravity cs and the size “size” are calculated from the coordinates of the basic figure constituting the symbol figure as shown in step S2 of FIG.
[0095]
Here, the size “size” is the length from the barycenter of the symbol figure to the furthest symbol position, and in this example, size = 3.6.
[0096]
Subsequently, in step S3 of FIG.
[0097]
[Expression 1]
Figure 0003619998
[0098]
(Where rud is a fluctuation vector generated each time by a random number function satisfying | rud | ≦ 1)
Determined by By adding the second term on the right side of this equation to the center of gravity cs, the center of gravity coordinates (cj) are randomly shifted, which causes a shift in the drawing position of the state figure. Subsequently, in step S4, a control point of the state figure is determined by the following equation.
[0099]
[Expression 2]
Figure 0003619998
[0100]
Also in this case, the control point is fluctuated by addition of a random component according to the third term on the right side, and as a result, the state figure is fluctuated.
[0101]
If the control points of the state figure are determined in this way, in step S5, a Bezier curve passing through each control point is drawn and displayed as shown in the state display drawing 62 of FIG. 5 to the user.
[0102]
The processes in steps S3 to S5 in FIG. 25 are processes collectively shown in steps S3 to S5 in FIG.
[0103]
FIG. 27 shows basic state graphic registration data used in the handwritten-style graphic creation processing shown in FIGS. The basic state figures 30-1, 30-2, and 30-3 are prepared for each of the basic state figures “◯” indicating open, “Δ” indicating intermediate open, and “×” indicating close. . The control point coordinates are determined to be 6 points for the basic state graphic 30-1, 6 points for the basic state graphic 30-2, and 5 points for the basic state graphic 30-3.
[0104]
Furthermore, this is the number of Bezier curves for creating the basic state figure: one for the basic state figure 32-1, three for the basic state figure 32-2, and two for the basic state figure 32-3. Each is defined corresponding to a control point.
[0105]
Accordingly, the coordinates of the basic control point are acquired from the data of the basic state figure as shown in FIG. 27, and the control point is fluctuated using the barycentric coordinates and size of the symbol figure as shown in step S4 of FIG. It is possible to generate a state display figure with fluctuation for each.
[0106]
In addition to this, the following method can also be used as a method for giving fluctuation to the state display graphic displayed in such a manner as to be superimposed on the device symbol in the present invention.
(1) Registration of basic state figures by user
Usually, the figure drawn by a person differs depending on the person who draws it, and if the same person draws it, it may be a similar figure. In order to express this feature, a different basic state figure for each user, that is, an actually hand-drawn figure or a basic control point is registered. Then, when reading the isolation form from the maintenance management database server 14 when opening the drawing, the creator is extracted, and the basic state figure corresponding to the creator is selected and used. The status display figure can be displayed over the device symbol.
(2) Registration of basic state figures by importance
By assigning an importance parameter to each device number and registering a basic state figure according to the importance, a state display figure that is more noticeable than usual is drawn for important equipment.
(3) Weighting the size according to importance
By assigning an importance parameter to each device number and adjusting the size parameter according to the importance, the state display graphic of the important device is drawn with a slightly larger size.
[0107]
In addition, this invention is not limited to said embodiment, The appropriate deformation | transformation which does not impair the objective and advantage is included. The present invention is not limited by the numerical values shown in the above embodiments.
[0108]
(Appendix)
(Appendix 1)
In the maintenance management method of creating an isolation plan used for the operation of isolating specific equipment at the time of plant repair inspection, etc.
A drawing search step for searching and displaying a drawing including a device to be quarantined;
An operation state setting step for determining an isolation range on the drawing, and setting an operation state for isolation for each operation target device existing in the isolation range;
A plan drawing creation step for creating an isolation plan drawing in which a handwritten-like state display graphic is displayed on a device symbol in correspondence with the operation state of the operation target device;
A storing step of storing plan information including the isolation plan drawing by a confirming operation;
A maintenance management method characterized by comprising: (1)
[0109]
(Appendix 2)
In the maintenance management method described in Appendix 1, when plan information including an isolation plan drawing is stored,
A saved drawing search step for searching and displaying a saved isolation plan drawing corresponding to the device to be quarantined;
An operation state change step for changing the operation state of the operation target device as necessary on the isolation plan drawing; and
A plan drawing change step for changing a handwriting-like state display figure in response to a change in setting of the operation state of the operation target device;
A saving step for saving the plan information including the isolation plan drawing changed by the confirmation operation;
A maintenance management method characterized by comprising: (2)
[0110]
(Appendix 3)
The maintenance management method according to attachment 1, wherein the drawing search step acquires and displays a CAD drawing including the device to be isolated from the drawing management server by inputting a device number, a device name, or a drawing name. Maintenance management method.
[0111]
(Appendix 4)
In the maintenance management method according to attachment 1, in the operation state setting step, when the operation device on the drawing is clicked, the next operation device connected to the clicked operation device is isolated as a terminal device. A maintenance management method characterized by determining a range.
[0112]
(Appendix 5)
In the maintenance management method according to attachment 1, in the operation state setting step, when the operation target device on the drawing is clicked, the next operation target device piped to the operation target device is set as a termination device. A maintenance management method characterized by referring to a pre-registered terminal device table and recognizing a terminal device corresponding to the clicked operation device to determine an isolation range.
[0113]
(Appendix 6)
The maintenance management method according to attachment 1, wherein the operation state setting step displays a list of operation target devices included in the determined isolation range, and inputs and sets the operation state in the list. Management method.
[0114]
(Appendix 7)
The maintenance management method according to attachment 1, wherein the planned drawing creation step registers a figure handwritten by a person in a primitive figure of a CAD system, and reads and displays the figure as a handwritten state display figure. Management method.
[0115]
(Appendix 8)
The maintenance management method according to appendix 1, wherein the planned drawing creation step creates and displays the handwritten-like state display graphic by randomly giving a predetermined fluctuation to a basic graphic. .
[0116]
(Appendix 9)
In the maintenance management method according to attachment 1, the plan drawing creation step refers to an isolation state definition table in which a state name of an operation target device and an identification flag of a state display figure are registered in advance, and the handwritten state A maintenance management method characterized by creating and displaying a display figure.
[0117]
(Appendix 10)
In the maintenance management method according to attachment 1, in the planned drawing creation step, when the operation target device is a valve, a circle, a triangle and a cross-shaped handwriting-like state display corresponding to full open, intermediate open and full close of the valve A maintenance management method characterized by creating and displaying a figure.
[0118]
(Appendix 11)
In the maintenance management method according to attachment 1, the storage step refers to the end device table in which the next operation target device connected to the operation target device by piping is preliminarily registered as the end device during the confirmation operation. A maintenance management method characterized by verifying the range and displaying the excess or deficiency of the isolation range.
[0119]
(Appendix 12)
On the computer,
A drawing search step for searching and displaying a drawing including a specific device to be isolated in the plant;
An operation state setting step for determining an isolation range on the drawing, and setting an operation state for isolation for each operation target device existing in the isolation range;
A plan drawing creation step for creating an isolation plan drawing in which a handwritten-like state display graphic is displayed on a device symbol in correspondence with the operation state of the operation target device;
A storing step of storing plan information including the isolation plan drawing by a confirming operation;
A program characterized in that is executed. (3)
[0120]
(Appendix 13)
In the program according to attachment 12, when plan information including an isolation plan drawing is stored, the computer stores:
A saved drawing search step for searching and displaying a saved isolation plan drawing corresponding to the device to be quarantined;
An operation state change step for changing the operation state of the operation target device as necessary on the isolation plan drawing; and
A plan drawing change step for changing a handwriting-like state display figure in response to a change in setting of the operation state of the operation target device;
A saving step for saving the plan information including the isolation plan drawing changed by the confirmation operation;
A program characterized in that is executed. (4)
[0121]
(Appendix 14)
In a maintenance management system that creates an isolation plan to be used for the operation of isolating specific equipment at the time of plant repair inspection, etc.
A drawing search unit for searching and displaying a drawing including a device to be quarantined;
An operation state setting unit that determines an isolation range on the drawing, and sets an operation state for isolation for each operation target device existing in the isolation range;
A plan drawing creation unit for creating an isolation plan drawing in which a handwritten-like state display graphic is displayed on the symbol of the device in correspondence with the operation state of the operation target device;
A storage unit for storing plan information including the isolation plan drawing by a confirmation operation;
A maintenance management system characterized by comprising: (5)
[0122]
(Appendix 15)
In the maintenance management system described in appendix 14,
A saved drawing search unit for searching and displaying a saved isolation plan drawing corresponding to the device to be quarantined;
An operation state change unit that changes the operation state of the operation target device as necessary on the isolation plan drawing;
A plan drawing change unit for changing a handwritten-like state display graphic corresponding to a change in setting of an operation state of the operation target device;
A maintenance management system characterized by comprising:
[0123]
【The invention's effect】
As described above, according to the present invention, by specifying a device to be isolated for repair or maintenance, a CAD drawing is automatically retrieved and displayed, and around the device to be isolated on the CAD drawing. When the operation range of the target device is determined by trial and error by determining the isolation range that requires the isolation operation, a hand-drawn status display figure indicating the operation status is displayed over the device symbol, and the isolation status It is possible to quickly and appropriately create an isolation plan drawing that can be confirmed at a glance.
[0124]
In particular, the drawing of the operation state figure in the handwritten style in the CAD drawing in which the regular figure is arranged becomes very emphasized, and the distinction between the device symbol figure and the operation state figure can be identified sensuously without staring, and the isolation. Therefore, it is possible to reliably perform the operation according to the isolation plan drawing in the field without mistakenly checking the operation state of the equipment for the purpose, and the safety of the isolation work can be further improved.
[Brief description of the drawings]
FIG. 1 illustrates the principle of the present invention
FIG. 2 is a block diagram of the system configuration of the present invention.
FIG. 3 is a block diagram of the functional configuration of the present invention.
FIG. 4 is a flowchart of an isolation plan drawing creation process according to the present invention.
FIG. 5 is an explanatory diagram of an isolation plan drawing created and displayed according to the present invention.
6 is an explanatory diagram of the device table in FIG. 3. FIG.
7 is an explanatory diagram of the device / drawing conversion table of FIG. 3;
FIG. 8 is an explanatory diagram of the figure number / drawing name conversion table of FIG. 3;
FIG. 9 is an explanatory diagram of the terminal device table in FIG. 3;
10 is an explanatory diagram of the isolation definition table in FIG. 3;
11 is an explanatory diagram of the state display graphic table of FIG. 3;
12 is an explanatory diagram of the plan drawing table of FIG. 3;
FIG. 13 is an explanatory diagram of the implementation plan detail table of FIG.
14 is a flowchart of a specific processing procedure for creating the isolation plan drawing of FIG. 5;
FIG. 15 is an explanatory diagram of a menu screen.
FIG. 16 is an explanatory diagram of a new creation screen opened from the menu screen.
FIG. 17 is an explanatory diagram of a drawing search screen opened from a new creation screen.
FIG. 18 is an explanatory diagram of a target drawing list screen obtained by performing a search on the drawing search screen.
FIG. 19 is a screen explanatory diagram of the original drawing opened from the target drawing list screen.
FIG. 20 is a screen explanatory diagram of a range display drawing by determining the isolation range.
FIG. 21 is an explanatory diagram of a device information operation screen opened by clicking a device in the isolation range.
22 is an explanatory diagram of an isolation list creation screen corresponding to the plan drawing of FIG. 5 created by the confirmation operation.
FIG. 23 is an explanatory diagram of a result reference screen for searching a stored plan drawing.
FIG. 24 is an explanatory diagram of an isolation correction screen used for correcting the plan drawing from the result reference screen.
FIG. 25 is a flowchart of a handwritten-style figure creation process used in the present invention.
FIG. 26 is an explanatory diagram of the processing contents of FIG.
27 is an explanatory diagram of the number of handwritten-like basic state figures, control points, and Bezier curves used in the processing of FIG. 25;
[Explanation of symbols]
10: Maintenance management client
11: Maintenance management system
12: Drawing management server
14: Maintenance management database server
16: Data collection system server
18: Network
20: Equipment table
22: Device / drawing conversion table
24: Drawing number / drawing name conversion table
26: Terminal device table
28: Isolation state definition table
30: Status display graphic table
32: Implementation plan table (header part)
34: Detailed execution plan table (data part)
36: New creation department
38: Achievement reference creation section
40: Drawing search section
42: Operation state setting section
44: Planning drawing creation department
46: Storage
48: Saved drawing search section
50: Operation state change unit
52: Planning drawing change part
54: Drawing equipment file
56: CAD drawing file
58: Isolation vote file
60: Isolation plan drawing file
62: State display drawing
64: Menu screen
68: New creation screen
74: Drawing search screen
82: Target drawing list screen
86: Original drawing
88: Range display drawing
90: Device information operation screen
92: Isolation vote creation screen
98: Results reference screen

Claims (5)

コンピューが、
図面を記憶した図面管理手段から隔離対象機器を含む図面を検索する図面検索ステップと、
前記図面検索ステップで検索した図面上の機器が指定されると、該機器に接続されている次の操作機器を終端機器として隔離範囲を決定し、隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定ステップと、
前記操作対象機器の各々のシンボルに重ねて前記操作状態設定ステップで設定した操作状態に対応する手書き風の状態表示図形を表示するアイソレーション計画図面を作成する計画図面作成ステップと、
を実行することを特徴とする保守管理方法。
Computer is,
A drawing search step of searching for a drawing including a device to be isolated from a drawing management means storing the drawing;
When a device on the drawing searched in the drawing search step is specified, an isolation range is determined with the next operation device connected to the device as a termination device, and each operation target device existing in the isolation range is assigned to each operation target device. An operation state setting step for setting an operation state for isolation,
A plan drawing creating step for creating an isolation plan drawing for displaying a handwritten-like state display graphic corresponding to the operation state set in the operation state setting step overlaid on each symbol of the operation target device;
The maintenance management method characterized by performing.
コンピュータが、
イソレーション計画図面を含む計画情報を記憶した保守管理テーブル手段から、隔離対象機器に対応するアイソレーション計画図面を検索する保存図面検索ステップと、
前記保存図面検索ステップで検索したアイソレーション計画図面上の操作対象機器の操作状態を設定変更する操作状態変更ステップと、
前記操作状態変更ステップで設定変更した操作状態に対応して前記操作対象機器のシンボルに重ねて表示する手書き風の状態表示図形を変更する計画図面変更ステップと、
確定操作により前記計画図面変更ステップで変更したアイソレーション計画図面を含む計画情報を前記保守管理テーブル手段に保存する保存ステップと、
を実行することを特徴とする保守管理方法。
Computer
From the maintenance management table means for storing plan information including the A iso configuration plan drawings, and save drawing retrieving step of search for A iso configuration plan diagram corresponding to the quarantine target device,
An operation state change step for setting and changing the operation state of the operation target device on the isolation plan drawing searched in the saved drawing search step ;
A plan drawing changing step that varying puff status display figure of handwriting style to be displayed superimposed on the symbol of the operation target apparatus in response to the operation status set change in the operation state changing step,
A storage step of storing plan information including the isolation plan drawing changed in the plan drawing change step by a confirmation operation in the maintenance management table means ;
The maintenance management method characterized by performing.
コンピュータに、
図面を記憶した図面管理手段からプラントの特定の隔離対象機器を含む図面を検索する図面検索ステップと、
前記図面索ステップで検索した図面上の機器が指定されると、該機器に接続されている次の操作機器を終端器として隔離範囲を決定し、隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定ステップと、
前記操作対象機器の各々のシンボルに重ねて前記操作状態設定ステップで設定した操作状態に対応する手書き風の状態表示図形を表示するアイソレーション計画図面を作成する計画図面作成ステップと、
実行させることを特徴とする保守管理プロクラム。
On the computer,
A drawing retrieval step you find a drawing that contains specific isolation target device of the plant from the drawing management means for storing drawings,
When a device on the drawing searched in the drawing search step is specified, an isolation range is determined using the next operation device connected to the device as a terminator , and each operation target device existing in the isolation range is assigned to each of the operation target devices. An operation state setting step for setting an operation state for isolation,
A plan drawing creation step of creating an isolation plan drawing state display graphic handwriting style corresponding to the operation status set by the operation condition setting step superimposed on each symbol of the operation target apparatus,
Maintenance management program characterized by running
コンピュータに、
アイソレーション計画図面を含む計画情報を記憶した保守管理テーブル手段から、隔離対象機器に対応するアイソレーション計画図面を検索する保存図面検索ステップと、
前記保存図面検索ステップで検索したアイソレーション計画図面上の操作対象機器の操作状態を設定変更する操作状態変更ステップと、
前記操作対象機器のシンボルに重ねて操作状態変更ステップで設定変更した操作状態に対応する手書き風の状態表示図形を表示するように前記保存図面検索ステップで検索したアイソレーション計画図面を変更る計画図面変更ステップと、
確定操作により前記計画図面変更ステップで変更したアイソレーション計画図面を含む計画情報を保守管理テーブル手段に保存する保存ステッブと、
を実行させることを特徴とする保守管理プロクラム。
On the computer,
A stored drawing search step for searching for an isolation plan drawing corresponding to a device to be isolated from a maintenance management table means storing plan information including an isolation plan drawing;
An operation state change step for setting and changing the operation state of the operation target device on the isolation plan drawing searched in the saved drawing search step ;
The storing drawing retrieval step to change the isolation plan drawings retrieved in plan so as to display the status display figure of handwriting style corresponding to the operation status set change in Cascade operation state change step to the symbol of the operation target apparatus A drawing change step;
A storage Sutebbu that the confirmation operation is stored in the maintenance management table means planning information including isolation plan drawings has been changed in the plan drawings changing step,
Maintenance management program characterized by running
図面を記憶した図面管理手段から隔離対象機器を含む図面を検索する図面検索手段と、
前記図面索手段で検索した図面上の機器が指定されると、該機器に接続されている次の操作機器を終端機器として隔離範囲を決定し、隔離範囲に存在する操作対象機器の各々に隔離のための操作状態を設定する操作状態設定手段と、
前記操作対象機器の各々のシンボルに重ねて前記操作状態設定手段で設定した操作状態に対応する手書き風の状態表示図形を表示するアイソレーション計画図面を作成する計画図面作成手段と、
備えたことを特徴とする保守管理システム。
A drawing search means for searching for a drawing including a device to be isolated from a drawing management means storing the drawing ;
When a device on the drawing searched by the drawing search means is specified, an isolation range is determined with the next operation device connected to the device as a termination device , and each of the operation target devices existing in the isolation range is determined. An operation state setting means for setting an operation state for isolation,
A plan drawing creation means for creating isolation plan drawing state display graphic handwriting style corresponding to the operation status set by the operation condition setting means superimposed on each of the symbols of the operation target apparatus,
Maintenance management system comprising the.
JP2002000070A 2002-01-04 2002-01-04 Maintenance management system, method and program Expired - Fee Related JP3619998B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002000070A JP3619998B2 (en) 2002-01-04 2002-01-04 Maintenance management system, method and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002000070A JP3619998B2 (en) 2002-01-04 2002-01-04 Maintenance management system, method and program

Publications (2)

Publication Number Publication Date
JP2003202920A JP2003202920A (en) 2003-07-18
JP3619998B2 true JP3619998B2 (en) 2005-02-16

Family

ID=27640581

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002000070A Expired - Fee Related JP3619998B2 (en) 2002-01-04 2002-01-04 Maintenance management system, method and program

Country Status (1)

Country Link
JP (1) JP3619998B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4671616B2 (en) * 2004-03-30 2011-04-20 中国電力株式会社 Drawing registration method, drawing registration program, recording medium recording the program, and information processing apparatus
JP4773083B2 (en) * 2004-12-21 2011-09-14 富士通株式会社 Isolation list creation program, method and apparatus
US8555206B2 (en) * 2007-12-21 2013-10-08 Fisher-Rosemount Systems, Inc. Methods and apparatus to present recipe progress status information
JP2011107890A (en) * 2009-11-16 2011-06-02 Ihi Corp Design support program and design support device
JP5916647B2 (en) * 2013-02-25 2016-05-11 三菱電機株式会社 Maintenance device
JP6516419B2 (en) * 2014-07-24 2019-05-22 三菱電機株式会社 Plant control system
JP6789848B2 (en) * 2017-02-27 2020-11-25 株式会社東芝 Isolation management system and isolation management method
CN113111967A (en) * 2021-04-30 2021-07-13 中核武汉核电运行技术股份有限公司 Isolation deduction method and device for nuclear power station problem equipment

Also Published As

Publication number Publication date
JP2003202920A (en) 2003-07-18

Similar Documents

Publication Publication Date Title
US5161211A (en) Method and system of specification processing
EP2755096A1 (en) Work management system, work management terminal, program and work management method
CN102385323B (en) For showing the method and device of localization process control object
CN103678109B (en) A kind of dump file analysis method, device and system
JPH08190587A (en) Simulation system for application process
CN104106066A (en) System to view and manipulate artifacts at temporal reference point
WO2008105611A1 (en) Database auto-building method for link of search data in gis system using cad drawings
JP3619998B2 (en) Maintenance management system, method and program
WO2001088703A1 (en) System for developing data collection software applications
EP1494150A2 (en) Engineering drawing data extraction
US20050119852A1 (en) Semiconductor test data analysis system
KR970004105B1 (en) Simulation system for measured economic model
JP5308991B2 (en) Maintenance work plan support method and system
JP6606450B2 (en) Checklist creation device, work performance management system, and checklist creation method
JP2006285647A (en) Plant inspection system, plant inspection method and plant inspection program
JP2002149980A (en) Investment trust information displaying method
CN115328442B (en) Hazardous chemical substance enterprise safety risk management and control platform constructed based on low code platform
CN110457705A (en) A kind of interest point data processing method, device, equipment and storage medium
JP2000237937A (en) Design support method of production system
CN110390170A (en) A kind of gas ductwork connection inspection method and pipe network online editing system
US8151242B1 (en) Description support apparatus and method for requisition sheet, and recording medium
JP4614568B2 (en) Code search processing system
JP4113652B2 (en) Housing development design system
JPH11338903A (en) Equipment data extraction method, and device and recording medium therefor
JP5180809B2 (en) Information control system and method for creating control software

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040421

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040427

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040624

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040831

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040906

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20041012

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20041104

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081126

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081126

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081126

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081126

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091126

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101126

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101126

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111126

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111126

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121126

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121126

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131126

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees