JP3586500B2 - Excavation method for large section arched tunnel - Google Patents
Excavation method for large section arched tunnel Download PDFInfo
- Publication number
- JP3586500B2 JP3586500B2 JP18217195A JP18217195A JP3586500B2 JP 3586500 B2 JP3586500 B2 JP 3586500B2 JP 18217195 A JP18217195 A JP 18217195A JP 18217195 A JP18217195 A JP 18217195A JP 3586500 B2 JP3586500 B2 JP 3586500B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- shaped
- section
- tunnel
- arch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【産業上の利用分野】
本発明は、特に土破りの比較的薄い未固結地山等にあっても、大断面トンネル(大断面(掘削断面積100〜150m2 )ないし超大断面(掘削断面積150m2 より大)を、安全かつ短期に掘進できるようにした大断面アーチ形トンネルの掘進工法に関する。
【0002】
【従来の技術】
上記の大断面アーチ形トンネルの掘進工法としては、既に特公平4−63198号公報による提案が開示されているが、これによるときは図5乃至図7により明示の如く、所要の地山1に掘進すべき大断面トンネル2を、下盤部3上のレール4を走行するアーチ形トンネル掘進機5の稼動により、その透し溝掘削用チェーンカッタ6を駆動させながら、これをアーチ状ガイド枠7に沿って回動させることにより、軟弱地盤1a等にアーチ形透し溝8を穿設し、これに別途設けられている硬化性材料注入管9より、図6に示す如く硬化性材料9aを注入することで、アーチ形支保版としてのプレライニングコンクリート10を囲成して行き、これに囲まれた大断面の切羽1bを、全断面工法により一度に掘削して行くものである。
【0003】
【発明が解決しようとする課題】
上記従来の大断面アーチ形トンネルの掘進工法によるときは、機械化施工を効率化するため、全断面工法を採っているが、中断面トンネル(掘削断面積100m2 以下)の場合には、当該全断面工法によることが、一般的工法となっているものの、大断面トンネルである場合は、鏡吹付けや鏡ボルトなどの通常の補強工では切羽1bの自立性を確保することが困難となり、鏡パイルなどで大規模な補強工を必要とすることになってしまう。しかも、大きなトンネル断面であることから一回の掘進で搬出すべき土砂の量が多くなることから、切羽1bの進行速度も遅延してしまうことになる。
【0004】
さらに、当該従来工法にあって重大な問題は、大断面となるほどプレライニングコンクリート10における両側下部の脚基部により当該地盤に対して与える応力集中が激しくなると考えられるから、この脚部地盤に対する補強を回避できないことが多発するだけでなく、補強工の実施時期が遅きに失すれば、プレライニングコンクリート10の全体が沈下してしまうといった事態の発生も予測される。
【0005】
そこで、当該補強工として切羽1bの近傍における地盤上にインバートコンクリートを打設し、これによってプレライニングコンクリート10の両脚基部を連設するようにし、このことで、大断面をインバートコンクリートとプレライニングコンクリート10とにより早期に閉合することも考えられるのであるがこのような工程によるときは、切羽1bの掘削による進捗を、一層妨げる結果となり、大断面トンネルの施工期間が長期化してしまうことになる。
【0006】
本発明は、上記従来工法の難点に鑑み、その請求項1にあっては全断面工法
によることなく、予め、掘進スピードの早い先進中央導坑を掘進しておき、その下盤部上に先行インバートコンクリートを打設してしまうのであり、しかも、後続の大断面トンネルに領域を画成するプレライニングコンクリートを立設したならば、これと先進中央導坑との間に形成されたアーチ形の本坑切羽を、これまた一度に掘削してしまうことなく、一側半部を掘削したところで、プレライニングコンクリートの一側脚基部と前記先行インバートコンクリートとを、一側インバートコンクリートで連設してしまい、同様にして他側半部を掘削した後、プレライニングコンクリートと他側脚基部と先行インバートコンクリートとを、他側インバートコンクリートにより連設するのである。
【0007】
上記の如き掘進工程によって、当該請求項1では、先進中央導坑と、その先行インバートコンクリートの施工によって、後続のプレライニングコンクリート形成工程における本坑切羽の自立性を確保すると共に、アーチ形である本坑切羽の掘削土量を減少することにより掘進効率を向上しようとするのが、第1の目的である。
【0008】
さらに、当該請求項1では、本坑切羽を全断面工法により一度に掘削してしまうのではなく、左右の側半部毎に掘進し、その都度一側インバートコンクリートと他側インバートコンクリートを打設することで、可及的早期の大断面閉合を可能として、大断面アーチ形トンネルを軟弱地盤にあっても支障なく、かつ短期に完成させようとするのが、第2の目的である。
【0009】
次に請求項2にあっては、上記請求項1における工程に加えて、先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、当該先進中央導坑からの注入作業等によって、次工程である大断面トンネル領域を画成するプレライニングコンクリートの形成に際し、その両脚基部が載置される脚部地盤周辺に対して、モルタル等による先行補強処理を施すのであり、このことにより、プレライニングコンクリートの両脚基部を、上記による補強脚部地盤上に立設することで、当該プレライニングコンクリートの不本意な沈下を、より効果的に防止しようとしている。
【0010】
【課題を解決するための手段】
本発明は上記の目的を達成するため請求項1にあっては、所要の地山に掘進すべき大断面トンネル領域の中央底部に、所望長だけ先進中央導坑を掘進して、必要に応じ当該先進中央導坑に対する導坑支保工または導坑支保工と先受け補助工とを施し、この先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、当該先行インバートコンクリート上にレールを敷設して、これに上記大断面トンネル領域である本坑切羽用のアーチ形トンネル掘進機を走行案内して、このアーチ形トンネル掘進機の稼動により、その円弧状の透し溝掘削用チェーンカッタにて、円弧状断面のアーチ形透し溝を掘削して、これに硬化性材料を充填硬化することで、円弧状断面のアーチ形支保版であるプレライニングコンクリートを、アーチ形に立設した後、このプレライニングコンクリートと前記先進中央導坑との間におけるアーチ形の本坑切羽につき、その一側半部を掘削除去した後、前記の先行インバートコンクリートとプレライニングコンクリートの一脚基部間を、一側インバートコンクリートによって連設し、次に本坑切羽の他側半部を掘削除去して、前記の先行インバートコンクリートとプレライニングコンクリートの他脚基部間を、他側インバートコンクリートにより連設し、前記のプレライニングコンクリートの立設から、上記他側インバートコンクリートの連設に至る工程を繰り返すと共に、プレライニングコンクリートの内面に、適時二次覆工アーチコンクリートの打設が施されるようにしたことを特徴とする大断面アーチ形トンネルの掘進工法を提供しようとするものである。
【0011】
さらに、請求項2の大断面アーチ形トンネルの掘進工法にあっては、上記の請求項1における構成に加えて、前記した先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、当該先進中央導坑から大断面トンネル領域の両脚部地盤周辺に対する注入操作により先行補強処理を施して、予め、プレライニングコンクリートを立設すべき地盤箇所を硬化しておくようにしたことを、その内容としている。
【0012】
【作用】
先ず、請求項1に係る大断面アーチ形トンネルの掘進工法によるときは、先行する先進中央導坑が、自由断面掘削機によって、比較的短期に掘進でき、これには先行インバートコンクリートを打設されることで、大断面トンネルの断面中、その一部が早期に補強されることになる。前記の先行インバートコンクリート上にはレールが敷設され、これにより、アーチ形トンネル掘進機を走行案内して、その稼動により効率的にアーチ形透し溝に対して、硬化性材料を充填硬化することができ、円弧状断面のアーチ形支保版である上記のプレライニングコンクリートを、アーチ形となるよう立設することができる。
【0013】
次に実施される掘削作業は、アーチ形の本坑切羽について実施されるので、先進中央導坑分の掘削土量を差し引いた掘削土量ですむこととなり、このため、その掘削速度は可成り迅速化され、しかも本坑切羽は、左右半側分毎にわけて実施されるので、効率のよい作業を行うことができる。さらに、その都度一側インバートコンクリート、他側インバートコンクリートが打設されて、早期の大断面閉合が実施されるので、プレライニングコンクリートの沈下とか、本坑切羽の崩壊などを防止し得て、安全かつ、能率的に大断面のアーチ形トンネルを掘進することが可能となる。
【0014】
請求項2にあっては、さらに、先進中央導坑に先行インバートコンクリートが打設された後にあって、安全に先進中央導坑から、プレライニングコンクリートの脚部周辺地盤に対して、モルタルやウレタンの注入処理により、当該地盤につき、工程の遅延なしに先行補強処理が施されるから、より一層プレライニングコンクリートの沈下を、高い信頼性をもって阻止することができる。
【0015】
【実施例】
本発明に係る大断面アーチ形トンネルの掘進工法を、その一実施例により図面を参照して以下詳記すると、図1(A)に示した通り、先ず土被りの薄い未固結等である所要の地山1に、大断面トンネル2を掘進して行くのであるが、その本坑切羽2aに対し、100m程度先行させて、山岳トンネル標準掘削方式(NATM)により、図示しない自由断面掘削機を用いて、2車線道路トンネル断面程度の先進中央導坑11を掘進する。この先進中央導坑11は、構築しようとする大断面トンネル2にあって、図1(B)、図2、図3により理解される通り、その中央低部となる位置に掘削することになる。
【0016】
ここで、上記の先進中央導坑11については、必要に応じその導坑支保を形成しなければならないが、このための手段としては、その内面に鋼製支保工12を建て込むとか、吹付けコンクリートを形成するとか、ロックボルトの打ち込みをすればよく、この際、後述の本坑切羽2aを掘削する場合を考えて、ロックボルトにはファイバーボルトを使用するのが望ましい。
【0017】
さらに、上記の支保工だけでなく、当該先進中央導坑11の掘削によって生じたゆるみ領域13が、図2に示したように大断面トンネル2の領域外まで広がって行く虞れがある場合には、先受け補助工法を施工することになり、このため既存の簡易な手段、すなわちファイバーボルト14を用いたモルタル充填式フォアポーリング(Fore Poling)、ウレタン注入式フォアポーリングなどにより地盤改良を行うことになる。この地盤改良はプレライニングコンクリート10の内側領域内に打設するのが原則であるが、当該領域外まで打設することもあり得る。
【0018】
次に、上記のようにして予め掘進した先進中央導坑11には、その下盤部11aにあって、図1、図3に明示の如く、その後方にあって先行インバートコンクリート15を打設するのである。次に、請求項2にあっては、ここで後述する本坑切羽2aが接近してくるまでの数十日程度となるタイムラグを利用して、当該先進中央導坑11からの作業により、図3に明示する如く、大断面トンネル2における左右両側下部の脚部地盤周辺16a、16bに対する先行補強処理を施すのである。
【0019】
この先行補強処理としては、先進中央導坑11の内壁面11bから差し込んだ図3に示す注入管17a、17bを用いるモルタル注入工とかウレタン注入工によって補強脚部地盤18a、18bを形成するのである。これ以降は、請求項1と請求項2の何れにあっても、同じ工程によるのであり、先ず、当該先行インバートコンクリート15の上面に、本坑切羽2aに対してプレライニングコンクリート10を形成するための前掲アーチ形トンネル掘進機5につき、これが走行案内されることになるレール4を敷設するのである。
【0020】
さて、次に、上記のアーチ形トンネル掘進機5を稼動して、図5乃至図8により、前記の如く、プレライニングコンクリート10を形成するのであるが、ここで同上図を借りて、当該工程につき詳記する。特に図8に明示しているように、円弧状の透し溝掘削用チェーンカッタ6を支持している移動フレーム19につき、これを円弧状ガイド部材20に沿って、カッタ進退用駆動装置21により前進移動させた後、当該円弧状ガイド部材20を支持している可動ブーム22が、アーチ状ガイド枠7に沿って移動し、このことで、前記透し溝掘削用チェーンカッタ6により、長手方向中間部が大断面トンネルの外側に向け凸曲するように弯曲している円弧状断面のアーチ形透し溝8を掘削する。
【0021】
次いで、上記のアーチ形透し溝8内に硬化性材料9aを、硬化性材料注入管9を介して充填硬化させることで、円弧状断面のアーチ形支保版であるプレライニングコンクリート10を図7に明示の如くアーチ形に形成するのであり、図5乃至図7にあって、23は透し溝掘削用チェーンカッタ6の駆動装置、24は注入管移動用注入装置、25は可動フレーム22の移動用駆動装置、20aは円弧状ガイド部材20の円弧状ラック、7aはアーチ状ガイド枠7の円弧状ラック、そして26はレール4を走行する車輪で、27は、当該車輪26を駆動する走行用駆動装置で、図8の28、29、30、31a、31bは、円弧状透し溝掘削用チェーンカッタ6における夫々スプロケット、掘削刃、リンク、一対の連結用リンクを示している。
【0022】
そして、次に再び円弧状の透し溝掘削用チェーンカッタ6により、円弧状断面のアーチ形支保版であるプレライニングコンクリート10を形成する工程とを反復して行い、相互に近接または接合されている多数のプレライニングコンクリート10を長手方向に順次施工していくのである。
【0023】
ここで、もちろん、上記のレール4は従来例では下盤部3に敷設されているのに対し、本発明では先行インバートコンクリート15上に設置されている。そして、図9は、上記した特公平4−63198号との関連において、その前記円弧状の透し溝掘削用チェーンカッタ6に関し、これを一個だけ設けるのではなしに、一対を併設するようにした従前例を示している(特開平2−167994号)。
すなわち、図9にあっては、上記のプレライニングコンクリート10の形成をより効率的に実施し得るようにした二重チェーンカッタ機構を提案しており、これによるときは、溝形カバー32がアーチ形透し溝8における溝切進方向Dに向けて開口していると共に、大断面トンネル2の長手方向へ二重チェーンカッタと共に移動自在となっている。
【0024】
さらに、この溝形カバー32内には、環境駆動自在なる一対の透し溝掘削用チェーンカッタ6a、6bが、大断面トンネル2の径方向に重縦配置されているだけでなく、溝切進方向Dの前部から後部に向けて、アーチ形透し溝8の幅中心に接近するよう傾斜した配装となっており、かつ、これら透し溝掘削用チェーンカッタ6a、6bの前部だけが溝形カバー32から露呈し、その他の部分は当該溝形カバー32内に収納保護された状態となっている。
【0025】
従って、上記の二重チェーンカッタ機構により、本坑切羽2aにアーチ形透し溝8を、前記の如く切削するようにすれば、当該切削時に崩落した土砂類が、透し溝掘削用チェーンカッタ6a、6bの戻り移動部分に落入して、過大な負荷
をかけたりすることなく、しかも、前記のように透し溝掘削用チェーンカッタ6a、6bが、傾斜して配設されていることから、掘進に際し、溝形カバー32が、これを阻害することもないので、能率的なアーチ形透し溝8の掘削を行うことができる。
尚、図9にあって、29a、29bは透し溝掘削用チェーンカッタ6a、6bの掘削刃を示している。
【0026】
ここで、実際上、アーチ形トンネル掘進機5の中央底部は、図7により理解され、図1(B)に示されている如く、アーチ状ガイド枠7の内側にあって適当な落下防護覆いの下でアプローチ空間Sが形成されるようにするのがよく、このことで、当該アーチ形トンネル掘進機5が稼動中でも休止中の場合にも、先進中央導坑11の切羽に対する対応が可能となり、休みなく当該切羽の掘削土砂を搬出したり、資材の搬入ができ、作業能率を向上し得ることになる。
【0027】
上記プレライニングコンクリート10の施工後、図1(B)に示すように、本坑切羽2aを大断面用の自由断面掘削機により掘削することになるが、この掘削は、先進中央導坑11における前記の導坑支保とプレライニングコンクリート10との間につき実施されることになるから、本坑切羽2aの高さは、大断面トンネル2の高さより可成り小さくなっていることから、切羽が安定すると共に掘削土量も少なくなる。
【0028】
本発明では、上記の本坑切羽2aにつき全断面を掘削してしまうのでなく、その右または左である一側半部2a1 を先行して掘削するのであり、この状態にあってはプレライニングコンクリート10の一脚基部10aが、請求項1では脚部地盤周辺16a上にあり、請求項2では前記の補強脚部地盤18a上に立設されているので、何れの場合もプレライニングコンクリート10の沈下は抑制されており、この状態下にあって、前記の先行インバートコンクリート15と一脚基部10aとの間を、一側インバートコンクリート15aによって連設してしまうのである。
【0029】
次に、本坑切羽2aにおける他側半部2a2 につき、掘削を行い、これが終われば前同様にして先行インバートコンクリート15とプレライニングコンクリート10の他脚基部10bとの間を、他側インバートコンクリート15bによって連設し、これにより、掘削すべき大断面トンネル2の全内周面をプレライニングコンクリート10と先行インバートコンクリート15および一側インバートコンクリート15aそして他側インバートコンクリート15bとによって、トンネル覆工断面の早期閉合を行うことになる。
【0030】
ここで、上記本坑切羽2aに対する掘進サイクルの最終段階にあっては、前記のアーチ形トンネル掘進機5が、次のプレライニングコンクリート10を形成するため前進することとなるから、前掲導坑支保の取外しを行うが、鋼製支保工12については、再使用が可能である。このようにしてプレライニングコンクリート10の内面が露呈されるから、これに対し、適時図1(B)に示す如く二次覆工アーチコンクリート33が施工されることになる。
【0031】
【発明の効果】
本発明は以上のようにして実施し得るものであるから、請求項1によるときは、予め先進中央導坑を掘進し、これに打設した先行インバートコンクリートにレールを敷設してしまった後、当該レールを走行するアーチ形トンネル掘進機により大断面トンネル領域にプレライニングコンクリートを構築するようにしたから、プレライニングコンクリートを施す本坑切羽の自立性が確保されて安全な作業を保証できると共に、アーチ形である本坑切羽の掘削に際する掘削土量を削減できて、当該掘進能率を向上することができる。
【0032】
さらに、本坑切羽の左右2回に分けて掘削するようにし、1回の掘削が終わった階段で、夫々前記の先行インバートコンクリートとプレライニングコンクリートの各脚基部とも、夫々一側インバートコンクリートと他側インバートコンクリートにより連設してしまうようにしたから、プレライニングコンクリートの沈下を遅滞なく早期に阻止することができる。
【0033】
さらに、請求項2にあっては、請求項1の工程に加えて先進中央導坑から、先行インバートコンクリート敷設後にあって、プレライニングコンクリートの脚部地盤周辺に対する先行補強処理を行うようにしたので、プレライニングコンクリートの不本意な沈下を、より高い確率で抑制することができる。
【図面の簡単な説明】
【図1】(A)は本発明に係る大断面アーチ形トンネルの掘進工法にあって、プレライニングコンクリートの形成工程を示した地山の縦断側面略示図で、(B)は一側インバートコンクリートと他側インバートコンクリートを打設した状態における地山の横断正面略示図である。
【図2】本発明の同上掘進工法にあって、必要に応じ実施される本坑切羽におけるゆるみ領域に施された先受け補助工法を示した地山の横断正面説明図である。
【図3】請求項2における同上掘進工法にあって、プレライニングコンクリートの脚部地盤周辺に対して施される先行補強処理を示した地山の横断説明図である。
【図4】請求項2に係る同上掘進工法の工程順を示したフローチャートである。
【図5】本発明に係るプレライニングコンクリートの形成に用いられるアーチ形トンネル掘進機の一使用態様を示した地山の縦断側面略示図である。
【図6】図5におけるアーチ形トンネル掘進機を示す平面説明図である。
【図7】図5のアーチ形トンネル掘進機を示す横断正面図である。
【図8】図5のアーチ形トンネル掘進機における透し溝掘削用チェーンカッタの部分斜視図である。
【図9】図5とは異色のアーチ形トンネル掘進機にあって、その透し溝掘削用チェーンカッタを示す部分横断正面図である。
【符号の説明】
1 地山
2 大断面トンネル
2a 本坑切羽
2a1 一側半部
2a2 他側半部
4 レール
5 アーチ形トンネル掘進機
6 透し溝掘削用チェーンカッタ
8 アーチ形透し溝
9a 硬化性材料
10 プレライニングコンクリート
10a 一脚基部
10b 他脚基部
11 先進中央導坑
11a 下盤部
15 先行インバートコンクリート
15a 一側インバートコンクリート
15b 他側インバートコンクリート
16a 脚部地盤周辺
16b 脚部地盤周辺
18a 補強脚部地盤
18b 補強脚部地盤[0001]
[Industrial applications]
The present invention is particularly even in relatively thin unconsolidated Yuichi mountain like soil breaking, a large cross-section tunnel (large section (drilling sectional area 100-150 2) to very large cross-section (larger than the excavation
[0002]
[Prior art]
As a method for excavating the large-section arch-shaped tunnel, a proposal by Japanese Patent Publication No. 4-63198 has already been disclosed. In this case, as clearly shown in FIGS. The large-
[0003]
[Problems to be solved by the invention]
When due to excavation method of the conventional large cross section arcuate tunnels for efficient mechanized construction, but takes the entire cross-section method, in the case of interruption plane tunnel (drilling sectional area 100 m 2 or less), the total Although the cross section method is a general method, in the case of a tunnel with a large cross section, it is difficult to secure the independence of the face 1b by ordinary reinforcing works such as mirror spraying and mirror bolts, and the mirror Large-scale reinforcement work will be required for piles and the like. Moreover, since the tunnel cross section is large, the amount of earth and sand to be carried out by one excavation increases, so that the traveling speed of the face 1b is also delayed.
[0004]
Further, a serious problem in the conventional method is that it is considered that the larger the cross-section, the more the stress concentration given to the ground by the lower leg portions on both sides of the prelining concrete 10 is increased. In addition to frequent occurrences of unavoidable situations, it is also anticipated that a situation in which the entire prelining concrete 10 sinks if the implementation time of the reinforcement work is lost late.
[0005]
Therefore, as the reinforcement, invert concrete is cast on the ground near the face 1b, whereby the bases of the two legs of the prelining concrete 10 are continuously provided, whereby a large section is formed between the invert concrete and the prelining concrete. Although it is conceivable that the closing operation is performed earlier by using the
[0006]
The present invention is the light of the difficulties of the prior art method, the In the
[0007]
According to the above-described excavation process, in
[0008]
Furthermore, in the said
[0009]
Next, in
[0010]
[Means for Solving the Problems]
In order to achieve the above object, according to the present invention, an advanced central shaft is dug by a desired length at a central bottom of a large-section tunnel region to be dug into a required ground. After performing the shaft support or shaft support and pre-assembly auxiliary work for the advanced central shaft, placing the pre-inverted concrete on the lower part of the advanced central shaft, and then on the pre-inverted concrete A rail is laid, and the arched tunnel excavator for the main tunnel face, which is the large section tunnel area, is guided on the rail, and the operation of the arched tunnel excavator causes the arc-shaped through groove excavation to be performed. Using a chain cutter, an arch-shaped see-through groove with an arc-shaped cross section is excavated and filled with hardening material to harden, so that the pre-lining concrete, which is an arch-shaped support plate with an arc-shaped cross section, is formed into an arch shape. Set up Later, after excavating and removing one half of one side of the arched main shaft face between the prelining concrete and the advanced central shaft, the space between the preceding invert concrete and the monopod base of the prelining concrete was removed. Then, one side of the invert concrete is connected continuously, then the other half of the face of the main shaft is excavated and removed, and the preceding invert concrete and the other base of the prelining concrete are connected by the other side invert concrete. In addition, the process from the erecting of the pre-lining concrete to the continuous installation of the other-side invert concrete was repeated, and the inner lining of the pre-lining concrete was appropriately cast with a secondary lining arch concrete. To provide an excavation method for a large arched tunnel characterized by the following features: A.
[0011]
Furthermore, in the method for excavating a large-section arched tunnel according to
[0012]
[Action]
First, when the excavation method of the large section arch type tunnel according to
[0013]
The next excavation work will be carried out on the arched main shaft face, so the excavated soil volume will be less than the excavated soil volume of the advanced central shaft, and the excavation speed will be quite high. Since the speed of the operation is increased and the pit face is performed for each of the right and left halves, efficient work can be performed. In addition, the invert concrete on one side and the invert concrete on the other side are cast each time, and the large-scale closing of the section is carried out at an early stage. In addition, it becomes possible to efficiently excavate an arched tunnel having a large cross section.
[0014]
According to
[0015]
【Example】
An excavation method for an arched tunnel with a large cross section according to the present invention will be described in detail below with reference to the drawings according to an embodiment. First, as shown in FIG. The
[0016]
Here, as for the above-mentioned advanced central shaft 11, a shaft support must be formed as necessary, and as a means for this, a
[0017]
Furthermore, in addition to the above-mentioned support, there is a possibility that the loosened
[0018]
Next, in the advanced central shaft 11 excavated in advance as described above, the preceding
[0019]
As the pre-reinforcement process, the reinforcing foot grounds 18a, 18b are formed by mortar injection or urethane injection using the injection pipes 17a, 17b shown in FIG. 3 inserted from the inner wall surface 11b of the advanced central shaft 11. . After this, the same process is performed in any of
[0020]
Next, the above-described
[0021]
Next, the curable material 9a is filled and cured in the arched see-through
[0022]
Then, again, the step of forming the pre-lining concrete 10 which is the arch-shaped support plate having an arc-shaped cross section by the
[0023]
Here, of course, the
That is, FIG. 9 proposes a double chain cutter mechanism that enables the formation of the prelining concrete 10 to be performed more efficiently. It is open in the groove cutting direction D in the through-shaped
[0024]
Further, in this groove-shaped
[0025]
Therefore, if the above-described double chain cutter mechanism is used to cut the arched see-through
In FIG. 9,
[0026]
Here, in practice, the central bottom of the
[0027]
After the construction of the prelining concrete 10, as shown in FIG. 1 (B), the
[0028]
In the present invention, rather than resulting in excavating entire cross-section per the above
[0029]
Then, per the other side
[0030]
Here, in the final stage of the excavation cycle for the
[0031]
【The invention's effect】
Since the present invention can be carried out as described above, according to
[0032]
In addition, the excavation is divided into two parts on the left and right sides of the main shaft, and on the stairs after one excavation, each of the above-mentioned preceding invert concrete and prelining concrete leg bases is also connected to one side invert concrete and the other. Since the continuous inverting concrete is used, settlement of the prelining concrete can be prevented early without delay.
[0033]
Furthermore, in
[Brief description of the drawings]
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 (A) is a schematic view of a vertical cross-section of a ground showing a process of forming prelining concrete in a method of excavating a large-section arched tunnel according to the present invention, and FIG. FIG. 3 is a schematic cross-sectional front view of a ground in a state where concrete and other-side invert concrete are cast.
FIG. 2 is a cross-sectional front view of the ground showing an auxiliary receiving method applied to a loosened area in the main shaft face as required in the excavation method according to the present invention.
FIG. 3 is an explanatory cross-sectional view of the ground showing the pre-reinforcement processing performed on the periphery of the foot ground of pre-lining concrete in the above-described excavation method according to
FIG. 4 is a flowchart showing a process order of the above excavation method according to
FIG. 5 is a schematic vertical sectional side view of a ground showing one mode of use of an arched tunnel excavator used for forming prelining concrete according to the present invention.
FIG. 6 is an explanatory plan view showing the arched tunnel excavator in FIG. 5;
FIG. 7 is a cross-sectional front view showing the arched tunnel machine shown in FIG. 5;
FIG. 8 is a partial perspective view of a chain cutter for drilling a seepage groove in the arched tunnel machine shown in FIG. 5;
FIG. 9 is a partial cross-sectional front view of the arched tunnel machine having a different color from that of FIG.
[Explanation of symbols]
DESCRIPTION OF
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18217195A JP3586500B2 (en) | 1995-06-26 | 1995-06-26 | Excavation method for large section arched tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18217195A JP3586500B2 (en) | 1995-06-26 | 1995-06-26 | Excavation method for large section arched tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0913872A JPH0913872A (en) | 1997-01-14 |
JP3586500B2 true JP3586500B2 (en) | 2004-11-10 |
Family
ID=16113593
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18217195A Expired - Lifetime JP3586500B2 (en) | 1995-06-26 | 1995-06-26 | Excavation method for large section arched tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3586500B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105507908A (en) * | 2016-02-02 | 2016-04-20 | 中铁十九局集团轨道交通工程有限公司 | Three-arch construction process for connecting tunnel of large cross-section tunnel |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103104265B (en) * | 2013-02-05 | 2015-02-04 | 北京首尔工程技术有限公司 | Advanced lining method and lining equipment used in construction of weak surrounding rock tunnel |
CN103147770B (en) * | 2013-03-24 | 2016-09-21 | 中铁二院工程集团有限责任公司 | Large-span heavy-load stress induced backfill open cut tunnel liner structure |
CN105683374A (en) | 2013-10-25 | 2016-06-15 | 龟甲万株式会社 | HEMOGLOBIN A1c MEASUREMENT METHOD AND MEASUREMENT KIT |
WO2015060431A1 (en) | 2013-10-25 | 2015-04-30 | キッコーマン株式会社 | HbA1c MEASUREMENT METHOD USING AMADORIASE ACTING ON GLYCATED PEPTIDES |
CN105626084A (en) * | 2016-02-26 | 2016-06-01 | 中铁隧道集团有限公司 | Method for cutting large-section loess tunnel to form advance pre-supporting stable layer |
CN109312312B (en) | 2016-04-22 | 2023-06-02 | 龟甲万株式会社 | HbA1c dehydrogenase |
CN112129183A (en) * | 2020-09-23 | 2020-12-25 | 中铁四局集团有限公司 | Hyperboloid cave depot dome accurate and rapid forming blasting excavation method |
-
1995
- 1995-06-26 JP JP18217195A patent/JP3586500B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105507908A (en) * | 2016-02-02 | 2016-04-20 | 中铁十九局集团轨道交通工程有限公司 | Three-arch construction process for connecting tunnel of large cross-section tunnel |
CN105507908B (en) * | 2016-02-02 | 2017-08-29 | 中铁十九局集团轨道交通工程有限公司 | A kind of large cross-section tunnel branch-cut bridge Duan Sanlian encircles construction technology |
Also Published As
Publication number | Publication date |
---|---|
JPH0913872A (en) | 1997-01-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100209103B1 (en) | Excavator for forming underground continuous wall | |
JP3824114B2 (en) | Whale bone method for large section tunnel | |
CN110306593A (en) | A kind of station construction method | |
JP3586500B2 (en) | Excavation method for large section arched tunnel | |
JP2020084474A (en) | Widening construction method of existing tunnel | |
US6375390B1 (en) | Method for widening road, superhighway or railway tunnels, without interrupting the traffic | |
CN207047833U (en) | A kind of groover for subterranean wall construction | |
JP2833482B2 (en) | Steel lining structure of tunnel | |
JPH07173835A (en) | Excavator for underground continuous wall | |
JP2979044B2 (en) | Large-scale underground structures and their construction methods | |
JP3931123B2 (en) | Non-open-cutting construction method for underground structures | |
JPH04213695A (en) | Segment for shield tunnel | |
JP3831900B2 (en) | Tunnel construction method | |
JP2001003677A (en) | Workstation type tunnel widening device and method | |
JP2594864B2 (en) | Widening method of underground tunnel | |
JP2004060266A5 (en) | ||
JP3996597B2 (en) | Open shield machine and open shield method using it | |
JP2697762B2 (en) | Tunnel structure and construction method | |
JP4705467B2 (en) | Construction method of underground structure | |
KR102621084B1 (en) | Movable excavation temporary shelter and underground structure construction method using the same | |
JP2656892B2 (en) | Underground structure construction method and continuous underground wall construction method | |
JP2762140B2 (en) | Construction method of underground continuous wall based on underground tunnel | |
JP2668648B2 (en) | Construction method of underground structure and starting pit used for it | |
JP7504841B2 (en) | Tunnel box group unit and its construction method | |
CN211648162U (en) | A open shield structure machine system of impulse type for executing and do underground box culvert |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040709 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040720 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040809 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080813 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080813 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090813 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090813 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100813 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100813 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110813 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120813 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130813 Year of fee payment: 9 |
|
EXPY | Cancellation because of completion of term |