JP3586500B2 - Excavation method for large section arched tunnel - Google Patents

Excavation method for large section arched tunnel Download PDF

Info

Publication number
JP3586500B2
JP3586500B2 JP18217195A JP18217195A JP3586500B2 JP 3586500 B2 JP3586500 B2 JP 3586500B2 JP 18217195 A JP18217195 A JP 18217195A JP 18217195 A JP18217195 A JP 18217195A JP 3586500 B2 JP3586500 B2 JP 3586500B2
Authority
JP
Japan
Prior art keywords
concrete
shaped
section
tunnel
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP18217195A
Other languages
Japanese (ja)
Other versions
JPH0913872A (en
Inventor
健次 指田
秀樹 米山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JDC Corp
Original Assignee
JDC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JDC Corp filed Critical JDC Corp
Priority to JP18217195A priority Critical patent/JP3586500B2/en
Publication of JPH0913872A publication Critical patent/JPH0913872A/en
Application granted granted Critical
Publication of JP3586500B2 publication Critical patent/JP3586500B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【産業上の利用分野】
本発明は、特に土破りの比較的薄い未固結地山等にあっても、大断面トンネル(大断面(掘削断面積100〜150m )ないし超大断面(掘削断面積150m より大)を、安全かつ短期に掘進できるようにした大断面アーチ形トンネルの掘進工法に関する。
【0002】
【従来の技術】
上記の大断面アーチ形トンネルの掘進工法としては、既に特公平4−63198号公報による提案が開示されているが、これによるときは図5乃至図7により明示の如く、所要の地山1に掘進すべき大断面トンネル2を、下盤部3上のレール4を走行するアーチ形トンネル掘進機5の稼動により、その透し溝掘削用チェーンカッタ6を駆動させながら、これをアーチ状ガイド枠7に沿って回動させることにより、軟弱地盤1a等にアーチ形透し溝8を穿設し、これに別途設けられている硬化性材料注入管9より、図6に示す如く硬化性材料9aを注入することで、アーチ形支保版としてのプレライニングコンクリート10を囲成して行き、これに囲まれた大断面の切羽1bを、全断面工法により一度に掘削して行くものである。
【0003】
【発明が解決しようとする課題】
上記従来の大断面アーチ形トンネルの掘進工法によるときは、機械化施工を効率化するため、全断面工法を採っているが、中断面トンネル(掘削断面積100m 以下)の場合には、当該全断面工法によることが、一般的工法となっているものの、大断面トンネルである場合は、鏡吹付けや鏡ボルトなどの通常の補強工では切羽1bの自立性を確保することが困難となり、鏡パイルなどで大規模な補強工を必要とすることになってしまう。しかも、大きなトンネル断面であることから一回の掘進で搬出すべき土砂の量が多くなることから、切羽1bの進行速度も遅延してしまうことになる。
【0004】
さらに、当該従来工法にあって重大な問題は、大断面となるほどプレライニングコンクリート10における両側下部の脚基部により当該地盤に対して与える応力集中が激しくなると考えられるから、この脚部地盤に対する補強を回避できないことが多発するだけでなく、補強工の実施時期が遅きに失すれば、プレライニングコンクリート10の全体が沈下してしまうといった事態の発生も予測される。
【0005】
そこで、当該補強工として切羽1bの近傍における地盤上にインバートコンクリートを打設し、これによってプレライニングコンクリート10の両脚基部を連設するようにし、このことで、大断面をインバートコンクリートとプレライニングコンクリート10とにより早期に閉合することも考えられるのであるがこのような工程によるときは、切羽1bの掘削による進捗を、一層妨げる結果となり、大断面トンネルの施工期間が長期化してしまうことになる。
【0006】
本発明は、上記従来工法の難点に鑑みその請求項1にあっては全断面工法
によることなく、予め、掘進スピードの早い先進中央導坑を掘進しておき、その下盤部上に先行インバートコンクリートを打設してしまうのであり、しかも、後続の大断面トンネルに領域を画成するプレライニングコンクリートを立設したならば、これと先進中央導坑との間に形成されたアーチ形の本坑切羽を、これまた一度に掘削してしまうことなく、一側半部を掘削したところで、プレライニングコンクリートの一側脚基部と前記先行インバートコンクリートとを、一側インバートコンクリートで連設してしまい、同様にして他側半部を掘削した後、プレライニングコンクリートと他側脚基部と先行インバートコンクリートとを、他側インバートコンクリートにより連設するのである。
【0007】
上記の如き掘進工程によって、当該請求項1では、先進中央導坑と、その先行インバートコンクリートの施工によって、後続のプレライニングコンクリート形成工程における本坑切羽の自立性を確保すると共に、アーチ形である本坑切羽の掘削土量を減少することにより掘進効率を向上しようとするのが、第1の目的である。
【0008】
さらに、当該請求項1では、本坑切羽を全断面工法により一度に掘削してしまうのではなく、左右の側半部毎に掘進し、その都度一側インバートコンクリートと他側インバートコンクリートを打設することで、可及的早期の大断面閉合を可能として、大断面アーチ形トンネルを軟弱地盤にあっても支障なく、かつ短期に完成させようとするのが、第2の目的である。
【0009】
次に請求項2にあっては、上記請求項1における工程に加えて、先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、当該先進中央導坑からの注入作業等によって、次工程である大断面トンネル領域を画成するプレライニングコンクリートの形成に際し、その両脚基部が載置される脚部地盤周辺に対して、モルタル等による先行補強処理を施すのであり、このことにより、プレライニングコンクリートの両脚基部を、上記による補強脚部地盤上に立設することで、当該プレライニングコンクリートの不本意な沈下を、より効果的に防止しようとしている。
【0010】
【課題を解決するための手段】
本発明は上記の目的を達成するため請求項1にあっては、所要の地山に掘進すべき大断面トンネル領域の中央底部に、所望長だけ先進中央導坑を掘進して、必要に応じ当該先進中央導坑に対する導坑支保工または導坑支保工と先受け補助工とを施し、この先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、当該先行インバートコンクリート上にレールを敷設して、これに上記大断面トンネル領域である本坑切羽用のアーチ形トンネル掘進機を走行案内して、このアーチ形トンネル掘進機の稼動により、その円弧状の透し溝掘削用チェーンカッタにて、円弧状断面のアーチ形透し溝を掘削して、これに硬化性材料を充填硬化することで、円弧状断面のアーチ形支保版であるプレライニングコンクリートを、アーチ形に立設した後、このプレライニングコンクリートと前記先進中央導坑との間におけるアーチ形の本坑切羽につき、その一側半部を掘削除去した後、前記の先行インバートコンクリートとプレライニングコンクリートの一脚基部間を、一側インバートコンクリートによって連設し、次に本坑切羽の他側半部を掘削除去して、前記の先行インバートコンクリートとプレライニングコンクリートの他脚基部間を、他側インバートコンクリートにより連設し、前記のプレライニングコンクリートの立設から、上記他側インバートコンクリートの連設に至る工程を繰り返すと共に、プレライニングコンクリートの内面に、適時二次覆工アーチコンクリートの打設が施されるようにしたことを特徴とする大断面アーチ形トンネルの掘進工法を提供しようとするものである。
【0011】
さらに、請求項2の大断面アーチ形トンネルの掘進工法にあっては、上記の請求項1における構成に加えて、前記した先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、当該先進中央導坑から大断面トンネル領域の両脚部地盤周辺に対する注入操作により先行補強処理を施して、予め、プレライニングコンクリートを立設すべき地盤箇所を硬化しておくようにしたことを、その内容としている。
【0012】
【作用】
先ず、請求項1に係る大断面アーチ形トンネルの掘進工法によるときは、先行する先進中央導坑が、自由断面掘削機によって、比較的短期に掘進でき、これには先行インバートコンクリートを打設されることで、大断面トンネルの断面中、その一部が早期に補強されることになる。前記の先行インバートコンクリート上にはレールが敷設され、これにより、アーチ形トンネル掘進機を走行案内して、その稼動により効率的にアーチ形透し溝に対して、硬化性材料を充填硬化することができ、円弧状断面のアーチ形支保版である上記のプレライニングコンクリートを、アーチ形となるよう立設することができる。
【0013】
次に実施される掘削作業は、アーチ形の本坑切羽について実施されるので、先進中央導坑分の掘削土量を差し引いた掘削土量ですむこととなり、このため、その掘削速度は可成り迅速化され、しかも本坑切羽は、左右半側分毎にわけて実施されるので、効率のよい作業を行うことができる。さらに、その都度一側インバートコンクリート、他側インバートコンクリートが打設されて、早期の大断面閉合が実施されるので、プレライニングコンクリートの沈下とか、本坑切羽の崩壊などを防止し得て、安全かつ、能率的に大断面のアーチ形トンネルを掘進することが可能となる。
【0014】
請求項2にあっては、さらに、先進中央導坑に先行インバートコンクリートが打設された後にあって、安全に先進中央導坑から、プレライニングコンクリートの脚部周辺地盤に対して、モルタルやウレタンの注入処理により、当該地盤につき、工程の遅延なしに先行補強処理が施されるから、より一層プレライニングコンクリートの沈下を、高い信頼性をもって阻止することができる。
【0015】
【実施例】
本発明に係る大断面アーチ形トンネルの掘進工法を、その一実施例により図面を参照して以下詳記すると、図1(A)に示した通り、先ず土被りの薄い未固結等である所要の地山1に、大断面トンネル2を掘進して行くのであるが、その本坑切羽2aに対し、100m程度先行させて、山岳トンネル標準掘削方式(NATM)により、図示しない自由断面掘削機を用いて、2車線道路トンネル断面程度の先進中央導坑11を掘進する。この先進中央導坑11は、構築しようとする大断面トンネル2にあって、図1(B)、図2、図3により理解される通り、その中央低部となる位置に掘削することになる。
【0016】
ここで、上記の先進中央導坑11については、必要に応じその導坑支保を形成しなければならないが、このための手段としては、その内面に鋼製支保工12を建て込むとか、吹付けコンクリートを形成するとか、ロックボルトの打ち込みをすればよく、この際、後述の本坑切羽2aを掘削する場合を考えて、ロックボルトにはファイバーボルトを使用するのが望ましい。
【0017】
さらに、上記の支保工だけでなく、当該先進中央導坑11の掘削によって生じたゆるみ領域13が、図2に示したように大断面トンネル2の領域外まで広がって行く虞れがある場合には、先受け補助工法を施工することになり、このため既存の簡易な手段、すなわちファイバーボルト14を用いたモルタル充填式フォアポーリング(Fore Poling)、ウレタン注入式フォアポーリングなどにより地盤改良を行うことになる。この地盤改良はプレライニングコンクリート10の内側領域内に打設するのが原則であるが、当該領域外まで打設することもあり得る。
【0018】
次に、上記のようにして予め掘進した先進中央導坑11には、その下盤部11aにあって、図1、図3に明示の如く、その後方にあって先行インバートコンクリート15を打設するのである。次に、請求項2にあっては、ここで後述する本坑切羽2aが接近してくるまでの数十日程度となるタイムラグを利用して、当該先進中央導坑11からの作業により、図3に明示する如く、大断面トンネル2における左右両側下部の脚部地盤周辺16a、16bに対する先行補強処理を施すのである。
【0019】
この先行補強処理としては、先進中央導坑11の内壁面11bから差し込んだ図3に示す注入管17a、17bを用いるモルタル注入工とかウレタン注入工によって補強脚部地盤18a、18bを形成するのである。これ以降は、請求項1と請求項2の何れにあっても、同じ工程によるのであり、先ず、当該先行インバートコンクリート15の上面に、本坑切羽2aに対してプレライニングコンクリート10を形成するための前掲アーチ形トンネル掘進機5につき、これが走行案内されることになるレール4を敷設するのである。
【0020】
さて、次に、上記のアーチ形トンネル掘進機5を稼動して、図5乃至図8により、前記の如く、プレライニングコンクリート10を形成するのであるが、ここで同上図を借りて、当該工程につき詳記する。特に図8に明示しているように、円弧状の透し溝掘削用チェーンカッタ6を支持している移動フレーム19につき、これを円弧状ガイド部材20に沿って、カッタ進退用駆動装置21により前進移動させた後、当該円弧状ガイド部材20を支持している可動ブーム22が、アーチ状ガイド枠7に沿って移動し、このことで、前記透し溝掘削用チェーンカッタ6により、長手方向中間部が大断面トンネルの外側に向け凸曲するように弯曲している円弧状断面のアーチ形透し溝8を掘削する。
【0021】
次いで、上記のアーチ形透し溝8内に硬化性材料9aを、硬化性材料注入管9を介して充填硬化させることで、円弧状断面のアーチ形支保版であるプレライニングコンクリート10を図7に明示の如くアーチ形に形成するのであり、図5乃至図7にあって、23は透し溝掘削用チェーンカッタ6の駆動装置、24は注入管移動用注入装置、25は可動フレーム22の移動用駆動装置、20aは円弧状ガイド部材20の円弧状ラック、7aはアーチ状ガイド枠7の円弧状ラック、そして26はレール4を走行する車輪で、27は、当該車輪26を駆動する走行用駆動装置で、図8の28、29、30、31a、31bは、円弧状透し溝掘削用チェーンカッタ6における夫々スプロケット、掘削刃、リンク、一対の連結用リンクを示している。
【0022】
そして、次に再び円弧状の透し溝掘削用チェーンカッタ6により、円弧状断面のアーチ形支保版であるプレライニングコンクリート10を形成する工程とを反復して行い、相互に近接または接合されている多数のプレライニングコンクリート10を長手方向に順次施工していくのである。
【0023】
ここで、もちろん、上記のレール4は従来例では下盤部3に敷設されているのに対し、本発明では先行インバートコンクリート15上に設置されている。そして、図9は、上記した特公平4−63198号との関連において、その前記円弧状の透し溝掘削用チェーンカッタ6に関し、これを一個だけ設けるのではなしに、一対を併設するようにした従前例を示している(特開平2−167994号)。
すなわち、図9にあっては、上記のプレライニングコンクリート10の形成をより効率的に実施し得るようにした二重チェーンカッタ機構を提案しており、これによるときは、溝形カバー32がアーチ形透し溝8における溝切進方向Dに向けて開口していると共に、大断面トンネル2の長手方向へ二重チェーンカッタと共に移動自在となっている。
【0024】
さらに、この溝形カバー32内には、環境駆動自在なる一対の透し溝掘削用チェーンカッタ6a、6bが、大断面トンネル2の径方向に重縦配置されているだけでなく、溝切進方向Dの前部から後部に向けて、アーチ形透し溝8の幅中心に接近するよう傾斜した配装となっており、かつ、これら透し溝掘削用チェーンカッタ6a、6bの前部だけが溝形カバー32から露呈し、その他の部分は当該溝形カバー32内に収納保護された状態となっている。
【0025】
従って、上記の二重チェーンカッタ機構により、本坑切羽2aにアーチ形透し溝8を、前記の如く切削するようにすれば、当該切削時に崩落した土砂類が、透し溝掘削用チェーンカッタ6a、6bの戻り移動部分に落入して過大な負荷
をかけたりすることなく、しかも、前記のように透し溝掘削用チェーンカッタ6a、6bが、傾斜して配設されていることから、掘進に際し、溝形カバー32が、これを阻害することもないので、能率的なアーチ形透し溝8の掘削を行うことができる。
尚、図9にあって、29a、29bは透し溝掘削用チェーンカッタ6a、6bの掘削刃を示している。
【0026】
ここで、実際上、アーチ形トンネル掘進機5の中央底部は、図7により理解され、図1(B)に示されている如く、アーチ状ガイド枠7の内側にあって適当な落下防護覆いの下でアプローチ空間Sが形成されるようにするのがよく、このことで、当該アーチ形トンネル掘進機5が稼動中でも休止中の場合にも、先進中央導坑11の切羽に対する対応が可能となり、休みなく当該切羽の掘削土砂を搬出したり、資材の搬入ができ、作業能率を向上し得ることになる。
【0027】
上記プレライニングコンクリート10の施工後、図1(B)に示すように、本坑切羽2aを大断面用の自由断面掘削機により掘削することになるが、この掘削は、先進中央導坑11における前記の導坑支保とプレライニングコンクリート10との間につき実施されることになるから、本坑切羽2aの高さは、大断面トンネル2の高さより可成り小さくなっていることから、切羽が安定すると共に掘削土量も少なくなる。
【0028】
本発明では、上記の本坑切羽2aにつき全断面を掘削してしまうのでなく、その右または左である一側半部2a を先行して掘削するのであり、この状態にあってはプレライニングコンクリート10の一脚基部10aが、請求項1では脚部地盤周辺16a上にあり、請求項2では前記の補強脚部地盤18a上に立設されているので、何れの場合もプレライニングコンクリート10の沈下は抑制されており、この状態下にあって、前記の先行インバートコンクリート15と一脚基部10aとの間を、一側インバートコンクリート15aによって連設してしまうのである。
【0029】
次に、本坑切羽2aにおける他側半部2a につき、掘削を行い、これが終われば前同様にして先行インバートコンクリート15とプレライニングコンクリート10の他脚基部10bとの間を、他側インバートコンクリート15bによって連設し、これにより、掘削すべき大断面トンネル2の全内周面をプレライニングコンクリート10と先行インバートコンクリート15および一側インバートコンクリート15aそして他側インバートコンクリート15bとによって、トンネル覆工断面の早期閉合を行うことになる。
【0030】
ここで、上記本坑切羽2aに対する掘進サイクルの最終段階にあっては、前記のアーチ形トンネル掘進機5が、次のプレライニングコンクリート10を形成するため前進することとなるから、前掲導坑支保の取外しを行うが、鋼製支保工12については、再使用が可能である。このようにしてプレライニングコンクリート10の内面が露呈されるから、これに対し、適時図1(B)に示す如く二次覆工アーチコンクリート33が施工されることになる。
【0031】
【発明の効果】
本発明は以上のようにして実施し得るものであるから、請求項1によるときは、予め先進中央導坑を掘進し、これに打設した先行インバートコンクリートにレールを敷設してしまった後、当該レールを走行するアーチ形トンネル掘進機により大断面トンネル領域にプレライニングコンクリートを構築するようにしたから、プレライニングコンクリートを施す本坑切羽の自立性が確保されて安全な作業を保証できると共に、アーチ形である本坑切羽の掘削に際する掘削土量を削減できて、当該掘進能率を向上することができる。
【0032】
さらに、本坑切羽の左右2回に分けて掘削するようにし、1回の掘削が終わった階段で、夫々前記の先行インバートコンクリートとプレライニングコンクリートの各脚基部とも、夫々一側インバートコンクリートと他側インバートコンクリートにより連設してしまうようにしたから、プレライニングコンクリートの沈下を遅滞なく早期に阻止することができる。
【0033】
さらに、請求項2にあっては、請求項1の工程に加えて先進中央導坑から、先行インバートコンクリート敷設後にあって、プレライニングコンクリートの脚部地盤周辺に対する先行補強処理を行うようにしたので、プレライニングコンクリートの不本意な沈下を、より高い確率で抑制することができる。
【図面の簡単な説明】
【図1】(A)は本発明に係る大断面アーチ形トンネルの掘進工法にあって、プレライニングコンクリートの形成工程を示した地山の縦断側面略示図で、(B)は一側インバートコンクリートと他側インバートコンクリートを打設した状態における地山の横断正面略示図である。
【図2】本発明の同上掘進工法にあって、必要に応じ実施される本坑切羽におけるゆるみ領域に施された先受け補助工法を示した地山の横断正面説明図である。
【図3】請求項2における同上掘進工法にあって、プレライニングコンクリートの脚部地盤周辺に対して施される先行補強処理を示した地山の横断説明図である。
【図4】請求項2に係る同上掘進工法の工程順を示したフローチャートである。
【図5】本発明に係るプレライニングコンクリートの形成に用いられるアーチ形トンネル掘進機の一使用態様を示した地山の縦断側面略示図である。
【図6】図5におけるアーチ形トンネル掘進機を示す平面説明図である。
【図7】図5のアーチ形トンネル掘進機を示す横断正面図である。
【図8】図5のアーチ形トンネル掘進機における透し溝掘削用チェーンカッタの部分斜視図である。
【図9】図5とは異色のアーチ形トンネル掘進機にあって、その透し溝掘削用チェーンカッタを示す部分横断正面図である。
【符号の説明】
1 地山
2 大断面トンネル
2a 本坑切羽
2a 一側半部
2a 他側半部
4 レール
5 アーチ形トンネル掘進機
6 透し溝掘削用チェーンカッタ
8 アーチ形透し溝
9a 硬化性材料
10 プレライニングコンクリート
10a 一脚基部
10b 他脚基部
11 先進中央導坑
11a 下盤部
15 先行インバートコンクリート
15a 一側インバートコンクリート
15b 他側インバートコンクリート
16a 脚部地盤周辺
16b 脚部地盤周辺
18a 補強脚部地盤
18b 補強脚部地盤
[0001]
[Industrial applications]
The present invention is particularly even in relatively thin unconsolidated Yuichi mountain like soil breaking, a large cross-section tunnel (large section (drilling sectional area 100-150 2) to very large cross-section (larger than the excavation cross-sectional area 150 meters 2) The present invention relates to a method for excavating a large-section arched tunnel that enables safe and short-term excavation.
[0002]
[Prior art]
As a method for excavating the large-section arch-shaped tunnel, a proposal by Japanese Patent Publication No. 4-63198 has already been disclosed. In this case, as clearly shown in FIGS. The large-section tunnel 2 to be excavated is driven by the arch-shaped tunnel excavator 5 running on the rail 4 on the lower part 3 to drive the through-groove-excavating chain cutter 6 to form an arch-shaped guide frame. 7, an arched see-through groove 8 is formed in the soft ground 1 a or the like, and a curable material injection pipe 9 separately provided therein is used to form a curable material 9 a as shown in FIG. Is injected, the prelining concrete 10 as an arched support plate is surrounded, and a large-section face 1b surrounded by the prelining is excavated at a time by the full-section method.
[0003]
[Problems to be solved by the invention]
When due to excavation method of the conventional large cross section arcuate tunnels for efficient mechanized construction, but takes the entire cross-section method, in the case of interruption plane tunnel (drilling sectional area 100 m 2 or less), the total Although the cross section method is a general method, in the case of a tunnel with a large cross section, it is difficult to secure the independence of the face 1b by ordinary reinforcing works such as mirror spraying and mirror bolts, and the mirror Large-scale reinforcement work will be required for piles and the like. Moreover, since the tunnel cross section is large, the amount of earth and sand to be carried out by one excavation increases, so that the traveling speed of the face 1b is also delayed.
[0004]
Further, a serious problem in the conventional method is that it is considered that the larger the cross-section, the more the stress concentration given to the ground by the lower leg portions on both sides of the prelining concrete 10 is increased. In addition to frequent occurrences of unavoidable situations, it is also anticipated that a situation in which the entire prelining concrete 10 sinks if the implementation time of the reinforcement work is lost late.
[0005]
Therefore, as the reinforcement, invert concrete is cast on the ground near the face 1b, whereby the bases of the two legs of the prelining concrete 10 are continuously provided, whereby a large section is formed between the invert concrete and the prelining concrete. Although it is conceivable that the closing operation is performed earlier by using the step 10, the progress of excavation of the face 1b is further impeded by such a process, and the construction period of the large-section tunnel is prolonged.
[0006]
The present invention is the light of the difficulties of the prior art method, the In the claim 1 without by total cross-sectional method, preliminarily to excavation early advanced central pilot tunnel of tunneling speed, prior on its lower plate portion Invert concrete is cast and if the pre-lining concrete that defines the area in the subsequent large section tunnel is erected, the arch-shaped concrete formed between this and the advanced central shaft Without excavating this pit face once again, once one half was excavated, one base leg of pre-lining concrete and the preceding invert concrete were continuously connected with one side invert concrete. In the same way, after excavating the other half in the same way, the pre-lining concrete, the base of the other side and the preceding inverted concrete were converted to the other side inverted concrete. Ri is to continuously provided.
[0007]
According to the above-described excavation process, in claim 1, by applying the advanced central shaft and the preceding invert concrete, the self-sustainability of the main shaft face in the subsequent prelining concrete forming process is ensured, and the arch is shaped. The first object is to improve the excavation efficiency by reducing the amount of excavated soil of the main shaft face.
[0008]
Furthermore, in the said claim 1, this digging face is not excavated at once by the full-section method, but is excavated in each of the right and left side halves, and the one side invert concrete and the other side invert concrete are cast each time. A second object of the present invention is to make it possible to close the large section as soon as possible, and to complete the large section arched tunnel in a short time without any trouble even in soft ground.
[0009]
Next, in claim 2, in addition to the step of claim 1, after the preceding invert concrete is cast on the lower part of the advanced central shaft, the work is performed by pouring from the advanced central shaft. In forming the pre-lining concrete that defines the large-section tunnel area in the next step, the pre-reinforcement processing with mortar or the like is performed around the foot ground on which both bases of the legs are placed. By laying the bases of the two legs of the prelining concrete on the ground of the reinforcing legs as described above, it is attempted to more effectively prevent the undesired subsidence of the prelining concrete.
[0010]
[Means for Solving the Problems]
In order to achieve the above object, according to the present invention, an advanced central shaft is dug by a desired length at a central bottom of a large-section tunnel region to be dug into a required ground. After performing the shaft support or shaft support and pre-assembly auxiliary work for the advanced central shaft, placing the pre-inverted concrete on the lower part of the advanced central shaft, and then on the pre-inverted concrete A rail is laid, and the arched tunnel excavator for the main tunnel face, which is the large section tunnel area, is guided on the rail, and the operation of the arched tunnel excavator causes the arc-shaped through groove excavation to be performed. Using a chain cutter, an arch-shaped see-through groove with an arc-shaped cross section is excavated and filled with hardening material to harden, so that the pre-lining concrete, which is an arch-shaped support plate with an arc-shaped cross section, is formed into an arch shape. Set up Later, after excavating and removing one half of one side of the arched main shaft face between the prelining concrete and the advanced central shaft, the space between the preceding invert concrete and the monopod base of the prelining concrete was removed. Then, one side of the invert concrete is connected continuously, then the other half of the face of the main shaft is excavated and removed, and the preceding invert concrete and the other base of the prelining concrete are connected by the other side invert concrete. In addition, the process from the erecting of the pre-lining concrete to the continuous installation of the other-side invert concrete was repeated, and the inner lining of the pre-lining concrete was appropriately cast with a secondary lining arch concrete. To provide an excavation method for a large arched tunnel characterized by the following features: A.
[0011]
Furthermore, in the method for excavating a large-section arched tunnel according to claim 2, in addition to the configuration according to claim 1, after the preceding invert concrete is cast on the lower part of the advanced central shaft. The advanced central shaft was subjected to a pre-reinforcement process by an injection operation from the advanced central shaft to the periphery of both legs in the large-section tunnel area, and in advance, the ground portion where the prelining concrete should be erected was hardened, Its contents.
[0012]
[Action]
First, when the excavation method of the large section arch type tunnel according to claim 1 is used, the leading advanced central shaft can be excavated in a relatively short time by the free section excavator, and the leading invert concrete is cast therein. By doing so, part of the large-section tunnel is reinforced early in the section. Rails are laid on the preceding invert concrete, thereby guiding the arched tunnel excavator to travel, and by its operation, efficiently filling and curing the curable material in the arched see-through groove. The above-mentioned pre-lining concrete, which is an arch-shaped support plate having an arc-shaped cross section, can be erected so as to be arch-shaped.
[0013]
The next excavation work will be carried out on the arched main shaft face, so the excavated soil volume will be less than the excavated soil volume of the advanced central shaft, and the excavation speed will be quite high. Since the speed of the operation is increased and the pit face is performed for each of the right and left halves, efficient work can be performed. In addition, the invert concrete on one side and the invert concrete on the other side are cast each time, and the large-scale closing of the section is carried out at an early stage. In addition, it becomes possible to efficiently excavate an arched tunnel having a large cross section.
[0014]
According to claim 2, furthermore, after the leading invert concrete is poured into the advanced central shaft, the mortar or urethane can be safely transferred from the advanced central shaft to the ground around the legs of the prelining concrete. , The pre-reinforcement processing is performed on the ground without delay of the process, so that the settlement of the prelining concrete can be more reliably prevented.
[0015]
【Example】
An excavation method for an arched tunnel with a large cross section according to the present invention will be described in detail below with reference to the drawings according to an embodiment. First, as shown in FIG. The large section tunnel 2 is excavated to the required ground 1. The free section excavator (not shown) is advanced by 100 m ahead of the main tunnel face 2 a by the standard method of mountain tunnel excavation (NATM). The advanced central shaft 11 having a cross section of a two-lane road tunnel is excavated by using. This advanced central shaft 11 is to be excavated in the large-section tunnel 2 to be constructed, and at a position which is the central lower part thereof as understood from FIGS. 1 (B), 2 and 3. .
[0016]
Here, as for the above-mentioned advanced central shaft 11, a shaft support must be formed as necessary, and as a means for this, a steel support 12 is built on the inner surface or spraying is performed. It is sufficient to form concrete or drive in a rock bolt. In this case, it is preferable to use a fiber bolt for the lock bolt in consideration of excavation of the main shaft 2a described later.
[0017]
Furthermore, in addition to the above-mentioned support, there is a possibility that the loosened area 13 caused by the excavation of the advanced central shaft 11 may spread out of the area of the large-section tunnel 2 as shown in FIG. Means that the pre-assembly method is to be applied. For this reason, ground improvement is to be performed by existing simple means, for example, mortar filling type fore polling (Fore Poling) using a fiber bolt 14, urethane injection type fore polling, or the like. become. In principle, this ground improvement is cast in the inside area of the prelining concrete 10, but it may be cast out of the area.
[0018]
Next, in the advanced central shaft 11 excavated in advance as described above, the preceding invert concrete 15 is cast behind the lower shaft portion 11a, as shown in FIGS. You do it. Next, in claim 2, by using a time lag of about several tens of days until the main shaft cutting face 2a described below approaches, the work from the advanced central shaft 11 is used. As shown in FIG. 3, the precedent reinforcement processing is performed on the periphery 16a, 16b of the leg ground at the lower left and right sides of the large-section tunnel 2.
[0019]
As the pre-reinforcement process, the reinforcing foot grounds 18a, 18b are formed by mortar injection or urethane injection using the injection pipes 17a, 17b shown in FIG. 3 inserted from the inner wall surface 11b of the advanced central shaft 11. . After this, the same process is performed in any of claims 1 and 2. First, the pre-lining concrete 10 is formed on the upper surface of the preceding inverted concrete 15 with respect to the main shaft 2a. For the above-mentioned arched tunnel excavator 5, the rail 4 to which the traveling is guided is laid.
[0020]
Next, the above-described arched tunnel excavator 5 is operated to form the prelining concrete 10 as described above with reference to FIGS. 5 to 8. Here, referring to FIG. Will be described in detail. In particular, as clearly shown in FIG. 8, the moving frame 19 supporting the arc-shaped see-through groove excavating chain cutter 6 is moved along the arc-shaped guide member 20 by the cutter advance / retreat driving device 21. After the forward movement, the movable boom 22 supporting the arc-shaped guide member 20 moves along the arch-shaped guide frame 7, whereby the chain cutter 6 for excavating the see-through groove moves the movable boom 22 in the longitudinal direction. The arched see-through groove 8 having an arc-shaped cross section whose middle portion is curved so as to protrude toward the outside of the large-section tunnel is excavated.
[0021]
Next, the curable material 9a is filled and cured in the arched see-through groove 8 through the curable material injection pipe 9, whereby the pre-lining concrete 10 which is an arc-shaped support plate having an arc-shaped cross section is obtained. 5 to 7, reference numeral 23 denotes a drive device of the chain cutter 6 for drilling a through-groove, 24 denotes an injection device for moving an injection pipe, and 25 denotes a movable frame 22. A driving device for movement, 20a is an arc-shaped rack of the arc-shaped guide member 20, 7a is an arc-shaped rack of the arch-shaped guide frame 7, 26 is a wheel running on the rail 4, and 27 is a running driving the wheel 26 8, 28, 29, 30, 31a, and 31b in FIG. 8 indicate a sprocket, a digging blade, a link, and a pair of connecting links in the arc-shaped see-through groove excavating chain cutter 6, respectively.
[0022]
Then, again, the step of forming the pre-lining concrete 10 which is the arch-shaped support plate having an arc-shaped cross section by the chain cutter 6 for excavating an arc-shaped see-through groove is repeatedly performed, and the steps are brought close to or joined to each other. Many pre-lining concretes 10 are sequentially constructed in the longitudinal direction.
[0023]
Here, of course, the rail 4 is laid on the lower base 3 in the conventional example, but is installed on the preceding inverted concrete 15 in the present invention. FIG. 9 relates to the above-described chain cutter 6 for excavating the circular see-through groove in relation to the above-mentioned Japanese Patent Publication No. 4-63198. Instead of providing only one of them, a pair of them is provided. A conventional example is shown (JP-A-2-167994).
That is, FIG. 9 proposes a double chain cutter mechanism that enables the formation of the prelining concrete 10 to be performed more efficiently. It is open in the groove cutting direction D in the through-shaped groove 8 and is movable with the double chain cutter in the longitudinal direction of the large-section tunnel 2.
[0024]
Further, in this groove-shaped cover 32, not only are a pair of chain cutters 6a and 6b for digging the see-through groove which can be driven in the environment arranged not only vertically but also vertically in the radial direction of the large-section tunnel 2, and groove cutting is performed. From the front part to the rear part in the direction D, the arrangement is inclined so as to approach the center of the width of the arched see-through groove 8, and only the front parts of these see-through groove excavating chain cutters 6a and 6b are provided. Are exposed from the channel-shaped cover 32, and the other portions are housed and protected in the channel-shaped cover 32.
[0025]
Therefore, if the above-described double chain cutter mechanism is used to cut the arched see-through groove 8 in the main shaft cutting face 2a as described above, the sediment collapsed at the time of the cutting will cause the see-through groove excavating chain cutter. The chain cutters 6a and 6b for excavating the see-through grooves are provided without being inclined without dropping into the return movement portions of the 6a and 6b and applying an excessive load, and as described above. Therefore, when excavating, the groove-shaped cover 32 does not hinder the excavation, so that it is possible to efficiently excavate the arched see-through groove 8.
In FIG. 9, reference numerals 29a and 29b denote excavating blades of the chain cutters 6a and 6b for excavating the see-through groove.
[0026]
Here, in practice, the central bottom of the arched tunnel excavator 5 can be understood from FIG. 7 and, as shown in FIG. It is preferable that the approach space S be formed under the above-mentioned condition. This makes it possible to cope with the face of the advanced central shaft 11 even when the arched tunnel machine 5 is in operation or at rest. In addition, the excavated earth and sand of the face can be carried out without interruption, and materials can be carried in, so that work efficiency can be improved.
[0027]
After the construction of the prelining concrete 10, as shown in FIG. 1 (B), the main pit face 2 a is excavated by a large-section free-section excavator. The height of the main shaft face 2a is considerably smaller than the height of the large-section tunnel 2 because the height of the main shaft face 2a is set between the shaft support and the prelining concrete 10, so that the face is stable. And the amount of excavated soil decreases.
[0028]
In the present invention, rather than resulting in excavating entire cross-section per the above Honko working face 2a, and of being drilled in advance one half portion 2a 1 which is the right or left, the pre-lining In this state Since the monopod base 10a of the concrete 10 is located on the periphery 16a of the foot ground in claim 1, and is erected on the reinforcing foot ground 18a in claim 2, the prelining concrete 10 Is suppressed, and under this condition, the preceding invert concrete 15 and the monopod base 10a are continuously connected by the one-side invert concrete 15a.
[0029]
Then, per the other side half portion 2a 2 in Honko working face 2a, performs the drilling, which between the other leg base 10b before preceding similarly invert concrete 15 and the pre-lining concrete 10 After completion, the other side invert concrete 15b, the entire inner peripheral surface of the large-section tunnel 2 to be excavated is covered with the prelining concrete 10, the preceding invert concrete 15, the one-side invert concrete 15a, and the other-side invert concrete 15b. Will be closed early.
[0030]
Here, in the final stage of the excavation cycle for the main shaft face 2a, since the above-mentioned arched tunnel excavator 5 moves forward to form the next prelining concrete 10, the above-mentioned guide shaft support is provided. The steel support 12 can be reused. Since the inner surface of the pre-lining concrete 10 is exposed in this manner, the secondary lining arch concrete 33 is applied thereto as appropriate, as shown in FIG. 1B.
[0031]
【The invention's effect】
Since the present invention can be carried out as described above, according to claim 1, after digging in advance an advanced central shaft and laying a rail on the preceding invert concrete poured into this, Since the pre-lining concrete is constructed in the large section tunnel area by the arched tunnel excavator running on the rail, the self-sufficiency of the main pit face for applying the pre-lining concrete can be secured and the safe work can be guaranteed, The amount of excavated soil at the time of excavation of the arch-shaped main face can be reduced, and the excavation efficiency can be improved.
[0032]
In addition, the excavation is divided into two parts on the left and right sides of the main shaft, and on the stairs after one excavation, each of the above-mentioned preceding invert concrete and prelining concrete leg bases is also connected to one side invert concrete and the other. Since the continuous inverting concrete is used, settlement of the prelining concrete can be prevented early without delay.
[0033]
Furthermore, in claim 2, in addition to the step of claim 1, since the advanced central shaft has been laid after the preceding invert concrete, the pre-reinforcement concrete for the periphery of the foot ground of the pre-lining concrete is performed. In addition, undesired settlement of the prelining concrete can be suppressed with a higher probability.
[Brief description of the drawings]
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 (A) is a schematic view of a vertical cross-section of a ground showing a process of forming prelining concrete in a method of excavating a large-section arched tunnel according to the present invention, and FIG. FIG. 3 is a schematic cross-sectional front view of a ground in a state where concrete and other-side invert concrete are cast.
FIG. 2 is a cross-sectional front view of the ground showing an auxiliary receiving method applied to a loosened area in the main shaft face as required in the excavation method according to the present invention.
FIG. 3 is an explanatory cross-sectional view of the ground showing the pre-reinforcement processing performed on the periphery of the foot ground of pre-lining concrete in the above-described excavation method according to claim 2;
FIG. 4 is a flowchart showing a process order of the above excavation method according to claim 2;
FIG. 5 is a schematic vertical sectional side view of a ground showing one mode of use of an arched tunnel excavator used for forming prelining concrete according to the present invention.
FIG. 6 is an explanatory plan view showing the arched tunnel excavator in FIG. 5;
FIG. 7 is a cross-sectional front view showing the arched tunnel machine shown in FIG. 5;
FIG. 8 is a partial perspective view of a chain cutter for drilling a seepage groove in the arched tunnel machine shown in FIG. 5;
FIG. 9 is a partial cross-sectional front view of the arched tunnel machine having a different color from that of FIG.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Ground 2 Large section tunnel 2a Main pit face 2a 1 One half 2a 2 The other half 4 Rail 5 Arch type tunnel excavator 6 Chain cutter for drilling a through groove 8 Arch through groove 9a Hardening material 10 Prelining concrete 10a Monopod base 10b Other leg base 11 Advanced central shaft 11a Lower base 15 Leading invert concrete 15a One side invert concrete 15b Other side invert concrete 16a Leg base periphery 16b Leg base periphery 18a Reinforcement leg ground 18b Reinforcement foot ground

Claims (2)

所要の地山に掘進すべき大断面トンネル領域の中央底部に、所望長だけ先進中央導坑を掘進して、必要に応じ当該先進中央導坑に対する導坑支保工または導坑支保工と先受け補助工とを施し、この先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、当該先行インバートコンクリート上にレールを敷設して、これに上記大断面トンネル領域である本坑切羽用のアーチ形トンネル掘進機を走行案内して、このアーチ形トンネル掘進機の稼動により、その円弧状の透し溝掘削用チェーンカッタにて、円弧状断面のアーチ形透し溝を掘削して、これに硬化性材料を充填硬化することで、円弧状断面のアーチ形支保版であるプレライニングコンクリートを、アーチ形に立設した後、このプレライニングコンクリートと前記先進中央導坑との間におけるアーチ形の本坑切羽につき、その一側半部を掘削除去した後、前記の先行インバートコンクリートとプレライニングコンクリートの一脚基部間を、一側インバートコンクリートによって連設し、次に本坑切羽の他側半部を掘削除去して、前記の先行インバートコンクリートとプレライニングコンクリートの他脚基部間を、他側インバートコンクリートにより連設し、前記のプレライニングコンクリートの立設から、上記他側インバートコンクリートの連設に至る工程を繰り返すと共に、プレライニングコンクリートの内面に、適時二次覆工アーチコンクリートの打設が施されるようにしたことを特徴とする大断面アーチ形トンネルの掘進工法。At the center of the large section tunnel area to be excavated to the required ground, an advanced central shaft is dug by a desired length, and if necessary, a shaft support or a shaft support for the advanced central shaft is required. After carrying out auxiliary work, placing the leading invert concrete on the lower part of this advanced central shaft, laying a rail on the leading invert concrete, and placing it on the main shaft The arch-shaped tunnel excavator for traveling is guided, and by the operation of this arch-shaped tunnel excavator, the arc-shaped through-groove having an arc-shaped cross-section is excavated by the arc-shaped through-groove excavating chain cutter. The pre-lining concrete, which is an arch-shaped support plate having an arc-shaped cross section, is erected by filling and hardening a curable material, and then the pre-lining concrete and the advanced central conductor are erected. After excavating and removing one half of one side of the arch-shaped pit face between the above, between the preceding invert concrete and the monopod base of the pre-lining concrete, one side invert concrete is connected, and then Excavating and removing the other half of the shaft face of the main shaft, connecting the base of the preceding invert concrete and the other leg base of the prelining concrete with the other side invert concrete, and starting from the erecting of the prelining concrete, The excavation of a large-section arched tunnel characterized by repeating the process of connecting the inverting concrete on the other side and placing the secondary lining arch concrete on the inner surface of the pre-lining concrete in a timely manner. Construction method. 所要の地山に掘進すべき大断面トンネル領域の中央底部に、所望長だけ先進中央導坑を掘進して、必要に応じ当該先進中央導坑に対する導坑支保工または導坑支保工と先受け補助工とを施し、この先進中央導坑の下盤部上に先行インバートコンクリートを打設した後、上記先進中央導坑から前記大断面トンネル領域の両脚部地盤周辺に対する注入操作による先行補強処理を施し、次に当該先行インバートコンクリート上にレールを敷設して、これに上記大断面トンネル領域である本坑切羽用のアーチ形トンネル掘進機を走行案内して、このアーチ形トンネル掘進機の稼動により、その円弧状の透し溝掘削用チェーンカッタにて、円弧状断面のアーチ形透し溝を掘削して、これに硬化性材料を充填硬化することで、円弧状断面のアーチ形支保版であるプレライニングコンクリートを、前記の先行補強処理により形成した補強脚部地盤上に立設した後、このプレライニングコンクリートと前記先進中央導坑との間におけるアーチ形の本坑切羽につき、その一側半部を掘削除去した後、前記の先行インバートコンクリートとプレライニングコンクリートの一脚基部間を、一側インバートコンクリートによって連設し、次に本坑切羽の他側半部を掘削除去して、前記の先行インバートコンクリートとプレライニングコンクリートの他脚基部間を、他側インバートコンクリートにより連設し、前記のプレライニングコンクリートの立設から、上記他側インバートコンクリートの連設に至る工程を繰り返すと共に、プレライニングコンクリートの内面に、適時二次覆工アーチコンクリートの打設が施されるようにしたことを特徴とする大断面アーチ形トンネルの掘進工法。At the center of the large section tunnel area to be excavated to the required ground, an advanced central shaft is dug by a desired length, and if necessary, a shaft support or a shaft support for the advanced central shaft is required. After carrying out auxiliary work and placing inverting concrete on the lower part of this advanced central shaft, advance reinforcement processing by injection operation from the advanced central shaft to the periphery of both legs of the large section tunnel area is performed. Then, a rail is laid on the preceding invert concrete, and an arched tunnel excavator for the main tunnel face, which is the large section tunnel area, is guided on the rail, and the operation of the arched tunnel excavator is performed by operating the arched tunnel excavator. By using the chain cutter for excavating the arc-shaped see-through groove, an arch-shaped see-through groove having an arc-shaped cross section is excavated, and a hardening material is filled and hardened into the arch-shaped see-through groove, thereby forming an arch-shaped support plate having an arc-shaped cross section. After a certain prelining concrete is erected on the ground of the reinforcing leg formed by the preceding reinforcing treatment, one side of the arched main shaft face between the prelining concrete and the advanced central shaft is provided. After excavating and removing one half, the preceding invert concrete and the monopod base of the pre-lining concrete are continuously connected by one-side invert concrete, and then the other half of the main shaft is excavated and removed. The other side of the preinverted concrete and the base of the prelining concrete are continuously connected by the other side of the inverting concrete, and the steps from the erecting of the prelining concrete to the connecting of the other side of the inverting concrete are repeated. Timely placing secondary lining arch concrete on the inner surface of lining concrete Excavation method of large cross-section arcuate tunnel, characterized in that it has to be subjected.
JP18217195A 1995-06-26 1995-06-26 Excavation method for large section arched tunnel Expired - Lifetime JP3586500B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18217195A JP3586500B2 (en) 1995-06-26 1995-06-26 Excavation method for large section arched tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18217195A JP3586500B2 (en) 1995-06-26 1995-06-26 Excavation method for large section arched tunnel

Publications (2)

Publication Number Publication Date
JPH0913872A JPH0913872A (en) 1997-01-14
JP3586500B2 true JP3586500B2 (en) 2004-11-10

Family

ID=16113593

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18217195A Expired - Lifetime JP3586500B2 (en) 1995-06-26 1995-06-26 Excavation method for large section arched tunnel

Country Status (1)

Country Link
JP (1) JP3586500B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507908A (en) * 2016-02-02 2016-04-20 中铁十九局集团轨道交通工程有限公司 Three-arch construction process for connecting tunnel of large cross-section tunnel

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103104265B (en) * 2013-02-05 2015-02-04 北京首尔工程技术有限公司 Advanced lining method and lining equipment used in construction of weak surrounding rock tunnel
CN103147770B (en) * 2013-03-24 2016-09-21 中铁二院工程集团有限责任公司 Large-span heavy-load stress induced backfill open cut tunnel liner structure
CN105683374A (en) 2013-10-25 2016-06-15 龟甲万株式会社 HEMOGLOBIN A1c MEASUREMENT METHOD AND MEASUREMENT KIT
WO2015060431A1 (en) 2013-10-25 2015-04-30 キッコーマン株式会社 HbA1c MEASUREMENT METHOD USING AMADORIASE ACTING ON GLYCATED PEPTIDES
CN105626084A (en) * 2016-02-26 2016-06-01 中铁隧道集团有限公司 Method for cutting large-section loess tunnel to form advance pre-supporting stable layer
CN109312312B (en) 2016-04-22 2023-06-02 龟甲万株式会社 HbA1c dehydrogenase
CN112129183A (en) * 2020-09-23 2020-12-25 中铁四局集团有限公司 Hyperboloid cave depot dome accurate and rapid forming blasting excavation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507908A (en) * 2016-02-02 2016-04-20 中铁十九局集团轨道交通工程有限公司 Three-arch construction process for connecting tunnel of large cross-section tunnel
CN105507908B (en) * 2016-02-02 2017-08-29 中铁十九局集团轨道交通工程有限公司 A kind of large cross-section tunnel branch-cut bridge Duan Sanlian encircles construction technology

Also Published As

Publication number Publication date
JPH0913872A (en) 1997-01-14

Similar Documents

Publication Publication Date Title
KR100209103B1 (en) Excavator for forming underground continuous wall
JP3824114B2 (en) Whale bone method for large section tunnel
CN110306593A (en) A kind of station construction method
JP3586500B2 (en) Excavation method for large section arched tunnel
JP2020084474A (en) Widening construction method of existing tunnel
US6375390B1 (en) Method for widening road, superhighway or railway tunnels, without interrupting the traffic
CN207047833U (en) A kind of groover for subterranean wall construction
JP2833482B2 (en) Steel lining structure of tunnel
JPH07173835A (en) Excavator for underground continuous wall
JP2979044B2 (en) Large-scale underground structures and their construction methods
JP3931123B2 (en) Non-open-cutting construction method for underground structures
JPH04213695A (en) Segment for shield tunnel
JP3831900B2 (en) Tunnel construction method
JP2001003677A (en) Workstation type tunnel widening device and method
JP2594864B2 (en) Widening method of underground tunnel
JP2004060266A5 (en)
JP3996597B2 (en) Open shield machine and open shield method using it
JP2697762B2 (en) Tunnel structure and construction method
JP4705467B2 (en) Construction method of underground structure
KR102621084B1 (en) Movable excavation temporary shelter and underground structure construction method using the same
JP2656892B2 (en) Underground structure construction method and continuous underground wall construction method
JP2762140B2 (en) Construction method of underground continuous wall based on underground tunnel
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
JP7504841B2 (en) Tunnel box group unit and its construction method
CN211648162U (en) A open shield structure machine system of impulse type for executing and do underground box culvert

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040709

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040720

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040809

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080813

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080813

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090813

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090813

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100813

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100813

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110813

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120813

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130813

Year of fee payment: 9

EXPY Cancellation because of completion of term