JP3555235B2 - Fuel purge method for pressurized fluidized bed boiler - Google Patents

Fuel purge method for pressurized fluidized bed boiler Download PDF

Info

Publication number
JP3555235B2
JP3555235B2 JP08947895A JP8947895A JP3555235B2 JP 3555235 B2 JP3555235 B2 JP 3555235B2 JP 08947895 A JP08947895 A JP 08947895A JP 8947895 A JP8947895 A JP 8947895A JP 3555235 B2 JP3555235 B2 JP 3555235B2
Authority
JP
Japan
Prior art keywords
fuel
pipe
valve
way valve
purge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP08947895A
Other languages
Japanese (ja)
Other versions
JPH08285228A (en
Inventor
邦裕 吉武
Original Assignee
石川島播磨重工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 石川島播磨重工業株式会社 filed Critical 石川島播磨重工業株式会社
Priority to JP08947895A priority Critical patent/JP3555235B2/en
Publication of JPH08285228A publication Critical patent/JPH08285228A/en
Application granted granted Critical
Publication of JP3555235B2 publication Critical patent/JP3555235B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Description

【0001】
【産業上の利用分野】
本発明は、燃料スラリを供給する燃料配管をパージする加圧流動層ボイラの燃料パージ方法に関するものである。
【0002】
【従来の技術】
近年、燃料を高い燃焼効率で燃焼でき、かつコンパクト化、高脱硫率及びプラント熱効率の向上等を図れる加圧流動層ボイラが研究開発されつつある。
【0003】
加圧流動層ボイラは、図3に示すように、火炉1が収容されている圧力容器2に高圧の空気を供給し、その圧力容器2内の燃焼空気を火炉1内に導いて、燃料(石炭)をベッド材と共に流動化させながら燃焼させるものであり、火炉1からの燃焼排ガスをガスタービンに供給すると共に、流動層内の燃焼熱の一部を伝熱管により収熱して蒸気を発生させ、この蒸気を蒸気タービンに供給する。
【0004】
【発明が解決しようとする課題】
ところで、上述の加圧流動層ボイラでは、燃料をスラリ状にして供給することが提案されている。例えば粉砕した石炭(石灰石を含む場合もある)と水とを混合してスラリにし、この石炭水スラリ(CWM)を火炉に供給する。このように燃料をスラリ状にするため、燃料供給停止時に燃料が燃料配管内に残留し、このままの状態であると燃料が配管等に固着して詰まりの原因となる。特に加圧流動層ボイラでは火炉内が高圧であり、この高圧ガスがノズルや配管内に逆流するため、残留スラリが乾燥して固化し易い。
【0005】
そこで、本発明は、このような事情を考慮してなされたものであり、その目的は、燃料の残留による詰まりを抑制できる加圧流動層ボイラの燃料パージ方法を提供することにある。
【0006】
【課題を解決するための手段】
本発明の加圧流動層ボイラの燃料パージ方法は、圧力容器に収容され容器内の高圧空気が導入される火炉に燃料スラリを供給する燃料配管をパージする方法において、前記燃料配管に、前記燃料スラリのスラリタンクに連通する循環管が接続された三方弁を介設し、燃料スラリの供給が停止したとき、三方弁を三方弁の上流側の燃料配管と循環管とが連通するように作動させた後、三方弁の上流側の燃料配管をパージガスでパージし、その後、三方弁を燃料配管が連通するように作動させて、火炉内圧で燃料配管内の燃料を三方弁の上流側に移動させ、移動後、三方弁を三方弁の上流側の燃料配管と循環管とが連通するように作動させてから三方弁の上流側の燃料配管をパージするものである。
【0007】
【作用】
燃料スラリの供給が停止すると、燃料が燃料配管内に残留するが、燃料配管に介設した三方弁が三方弁の上流側の燃料配管と循環管とが連通するように作動され、三方弁の上流側の燃料配管がパージされる。そして、その三方弁は燃料配管が連通するように作動する。これにより、火炉内圧により燃料配管内の燃料が逆流して三方弁より上流側に移動する。移動後、三方弁の上流側の燃料配管がパージされる。これにより、燃料配管内に残留した燃料がパージされるので、燃料の残留による詰まりを抑制することが可能となる。
【0008】
【実施例】
以下、本発明の実施例を添付図面に基づいて詳述する。
【0009】
図3において、1は圧力容器2に収容されている火炉を示し、この火炉1には、スラリ状の燃料例えば石炭水スラリ(CWM)を噴出する燃料ノズル3が設けられている。
【0010】
圧力容器2には、容器2内を高圧にするための空気供給管4が接続され、この空気供給管4から高圧の空気が圧力容器2内の空気分散板5から容器1内に噴射される。この空気により灰や石灰石等からなるベッド材が流動化して流動層が形成され、高温高圧(例えば約 860℃、 9〜10kg/cm)下で燃料(石炭)が燃焼する。この燃焼排ガスは、圧力容器2内のサイクロン6を介して排ガス管7に流入しそしてガスタービン8に供給される。また、燃焼熱の一部は、伝熱管9に収熱され、これにより発生した蒸気が蒸気管10を介して蒸気タービン11に供給される。
【0011】
燃料ノズル3には、図1及び図3に示すように、燃料配管12が接続され、この燃料配管12は燃料スラリタンク13に接続されている。燃料スラリタンク13は、燃料製造装置などで製造された燃料スラリ(例えば平均粒径が8mmまたはそれ以下の石炭(石灰石を含む場合もある)と水とを混合した石炭水スラリ(CWM))が供給・貯蔵されるようになっており、このCWMが燃料配管12を介して燃料ノズル3から火炉1内に噴出される。また、燃料ノズル3には、コンプレッサ14、燃料分散空気弁15、流量調整弁16、流量計17を有する燃料分散空気管18が接続され、燃料分散空気管18からの空気により燃料が分散される。燃料分散空気管18にはバックアップ用の窒素(N)を供給するためのバックアップ弁19を有するN供給管20が接続されている。また、燃料分散空気管18の流量計17の下流側には、高圧(例えば35kg/cm)の空気でノズル3のパージを行うための高圧パージ弁21及びノズルパージ弁22を有するパージ配管23が接続され、この高圧パージ弁21とノズルパージ弁22との間のパージ配管23には燃料分散空気弁15を介した空気等が流入するガス管24が接続されている。
【0012】
燃料配管12には、燃料の流れ方向に、燃料スラリポンプ25、吐出三方弁26、燃料遮断弁27、燃料遮断弁27の前後の配管の圧力及びその圧力差を計測する圧力計28が順次介設されている。吐出三方弁26の残りの口には燃料スラリタンク13に接続されている循環管29が接続され、この吐出三方弁26の開は燃料配管12が連通する状態を示し、閉は三方弁26の上流側の燃料配管12と循環管29とが連通する状態を示す。すなわち、三方弁26が開の状態を示すときは燃料スラリポンプ25からの燃料がノズル3に供給され、閉のときは燃料がスラリタンク13に戻されて循環する。
【0013】
燃料スラリポンプ25と吐出三方弁26との間の燃料配管12には圧力7kg/cmの空気又は前記高圧(35kg/cm)の空気でその燃料配管12をパージするための吐出パージ弁30を有するパージ空気管31が接続されている。循環管29にはその圧力7kg/cmの空気で循環管29内をパージするための循環パージ弁32を有する循環パージ管33が接続されている。
【0014】
吐出三方弁26と燃料遮断弁27との間の燃料配管12には、雑用水等の水を供給するための水濡らし弁34を有する水供給管35、水を燃料スラリタンク13に排出するための水濡らし戻し弁36を有する水排出管37、前記ガス管24に流入した例えば分散空気又は前記パージ配管23に流入した高圧空気で燃料配管12をパージするための配管パージ弁38を有するパージ管39が接続されている。
【0015】
燃料遮断弁27と燃料ノズル3との間の燃料配管12には、前記ガス管24に流入した例えば分散空気で燃料配管12をパージするための逆流防止パージ弁40を有するパージ導管41が接続されている。
【0016】
次に燃料配管12をパージする場合について述べる。
【0017】
起動時は、ガスタービン8を起動させた後、圧力容器2内の圧力が 0.5kg/cm以上になると、逆流防止パージ弁40を開き(尚、燃料分散空気弁15は通常開状態に維持される)、燃料スラリが配管12等を逆流するのを防止する。そして、圧力計28により燃料配管12内の詰まりを判断する。これは、燃料配管12がノズル3を介して火炉1に接続されているためであり、燃料配管12内の圧力が火炉1圧とほぼ同じである場合は詰まり無し、圧力差が大きい場合には詰まり有りとする。詰まり有りの場合は、詰まりを解消するための詰まり解消パージ(後述する)が行われ、これにより詰まりが解消される。詰まりが解消されると、詰まり無しの場合と共に燃料ノズルパージ(後述する)が2回実施され、その後、層内温度が 600℃以上になるとCWMの投入が行われ、通常に運転される。
【0018】
運転中、燃料スラリがトリップされると(ガスタービン運転継続の場合)、図3に示すように、火炉1内が高圧のまま遮断パージマスタが行われる。尚、運転中は、燃料スラリポンプ25が運転されると共に、吐出三方弁26、燃料遮断弁27、燃料分散空気弁15、流量調整弁16及び逆流防止パージ弁40が開であり、それ以外の弁は通常閉である。
【0019】
遮断パージマスタは次のようにして行われる。
【0020】
まず、スラリポンプ25が停止すると、燃料遮断弁27,三方弁26が開から閉になるように作動する。燃料遮断弁27,三方弁26が閉になると、吐出パージ弁30,ノズルパージ弁22が開となる。これにより、例えば高圧(35kg/cm)の空気が三方弁26の上流側の燃料配管12に供給されて、その配管12内の燃料が循環管29を介して燃料スラリタンク13に戻され、三方弁26の上流側の燃料配管12がパージされると共に、燃料ノズル3がパージされる。そして、所定時間(三方弁26の上流側の燃料配管12のパージが終了した)後、吐出パージ弁30が閉じられ、燃料遮断弁27,三方弁26が開となる。これにより、燃料配管12が火炉1と連通して炉1内圧により三方弁26より下流側の燃料が三方弁26の上流側の燃料配管12に移動する。移動後、三方弁26が閉へと作動すると共に配管パージ弁38が開へと作動し、三方弁26が閉じられると吐出パージ弁30が開となる。これにより、配管パージ弁38からのガスで三方弁26の下流側の燃料配管12がパージされると共に、三方弁26の上流側の燃料配管12がパージされる。そして配管パージ弁38、燃料遮断弁27が閉じられると、水濡らし弁34,水濡らし戻し弁36が開となる。これにより、雑用水等の水が吐出三方弁26と燃料遮断弁27との間の燃料配管12に供給されて、水によりその燃料配管12がパージされる。そして、吐出パージ弁30、ノズルパージ弁22、水濡らし弁34が閉となり、その後、水濡らし戻し弁36が閉となって、遮断パージマスタが終了する。
【0021】
すなわち、まず、三方弁26の上流側の燃料配管12内の燃料が燃料タンク13に戻され、次に、火炉1内圧を利用して三方弁26より下流側の燃料が三方弁26の上流側の燃料配管12に移動された後、この燃料がタンク13に戻されてその燃料配管12が空気でパージされると共に、三方弁26の下流側の燃料配管12が空気でパージされてから三方弁26と燃料遮断弁27との間の燃料配管12が水でパージされて、遮断パージマスタが終了する。このように、燃料のパージを三方弁26及び燃料遮断弁27を用いて火炉1内圧が作用しないところで行うので、高圧の火炉1内に燃料をパージする場合に比して配管12等に燃料が残留しにくくより確実に燃料のパージを行える。また、火炉1内の高圧ガスを利用して燃料の移動を行うので、その移動を行うためのガスや配管等を必要としない。さらに、三方弁26と燃料遮断弁27との間の燃料配管12を水でパージしたので、より確実に燃料のパージを行える。よって、燃料配管12内に残留した燃料を火炉1内圧を利用しつつ燃料スラリタンク13に戻すことができ、燃料の残留による詰まりを抑制することができる。
【0022】
遮断パージマスタ終了後、燃料ノズルパージが1回実施されてから層高下げ操作が実施される。層高が 0.2m以下になると燃料ノズルパージが1回実施され、その後ガスタービン8が停止される。
【0023】
燃料ノズルパージは次のようにして行われる。
【0024】
水濡らし戻し弁36が開となると、水濡らし弁34が10秒開かれ、水により吐出三方弁26と燃料遮断弁27との間の燃料配管12がパージされる。水濡らし弁34、水濡らし戻し弁36が閉じられると、配管パージ弁38が開けられ、逆流防止パージ弁40が閉じられた後、燃料遮断弁27が30秒開けられる。これにより配管パージ弁38からの空気により、吐出三方弁26の下流側の燃料配管12がパージされる。燃料遮断弁27、配管パージ弁38が閉じられると、逆流防止パージ弁40が開けられる。そして、水濡らし戻し弁36が開けられてから水濡らし弁34が10秒開かれ、水による吐出三方弁26と燃料遮断弁27との間の燃料配管12のパージが行われ、水濡らし弁34、水濡らし戻し弁36が閉じられて、燃料ノズルパージが終了する。これにより、吐出三方弁26の下流側の燃料配管12がパージされる。このパージは一種のクリーニングであり、これによりその燃料配管12に燃料が残留又は付着しにくくなる。これは、その燃料配管12に燃料が付着しやすいからである。
【0025】
次に、運転中にガスタービン8がトリップされる場合を述べる。
【0026】
ガスタービン8がトリップされると、火炉1の冷却が行われると共に、次に述べるようなGTトリップ遮断パージが行われる。
【0027】
GTトリップ遮断パージ
スラリポンプ25が停止すると、燃料遮断弁27,三方弁26が開から閉になるように作動する。燃料遮断弁27,三方弁26が閉になると、吐出パージ弁30,ノズルパージ弁22が開となる。これにより、例えば高圧(35kg/cm)の空気が三方弁26の上流側の燃料配管12に供給されて、その配管12内の燃料が循環管29を介して燃料スラリタンク13に戻され、三方弁26の上流側の燃料配管12がパージされると共に、燃料ノズル3がパージされる。そして、所定時間(三方弁26の上流側の燃料配管12のパージ終了)後、吐出パージ弁30が閉じられ、燃料遮断弁27,三方弁26が開となる。これにより、燃料配管12が火炉1と連通して炉1内圧により三方弁26より下流側の燃料が三方弁26の上流側の燃料配管12に移動する。移動後、三方弁26が閉じられると、吐出パージ弁30が開となる。これにより、配管パージ弁38からのガスで三方弁26の下流側の燃料配管12がパージされると共に、三方弁26の上流側の燃料配管12がパージされる。そして燃料遮断弁27が閉じられてから、吐出パージ弁30,ノズルパージ弁22が閉じられて、GTトリップ遮断パージマスタが終了する。このように、燃料のパージを三方弁26及び燃料遮断弁27を用いて火炉1内圧が作用しないところで行うので、高圧の火炉1内に燃料をパージする場合に比して配管12等に燃料が残留しにくくより確実に燃料のパージを行える。また、火炉1内の高圧ガスを利用して燃料の移動を行うので、その移動を行うためのガスや配管等を必要としない。よって、燃料配管12内に残留した燃料を火炉1内圧を利用しつつ燃料スラリタンク13に戻すことができ、燃料の残留による詰まりを抑制することができる。
【0028】
そして、GTトリップ遮断パージマスタが終了すると共に、層内温度が 350℃以下になると、ガスタービン8を再起動する(この際逆流防止パージ弁40が開とならないようにする)。ガスタービン再起動後、図5に示すような一連の詰まり解消パージが行われる。
【0029】
詰まり解消パージは、詰まりが発生した場合等に行われるもので、具体的には図2に示すようにして行われる。
【0030】
図2に示すように、まず、スラリノズル詰まりが発生すると、スラリポンプ25が停止された後、前述の遮断パージマスタが行われる。遮断パージマスタが完了すると、スラリポンプ25の循環運転が開始されると共に、高圧パージ弁21が開かれる。ガスタービントリップ時の場合はここから始まる。そしてノズルパージ弁22が開かれてから逆流防止パージ弁40が閉じられる。次に、水張り・リバース、リバース、空気パージが順次行われ、詰まりが解消されるまではこの3つの操作が繰り返される。すなわち、詰まりが解消されるまではこれらの操作が繰り返され、また水張り・リバースのみでも詰まりが解消される(圧力計28により確認される)こともありうる。尚、これら3つの操作のいずれかを繰り返し実施して詰まりを解消するようにしてもよい。詰まりが解消されると、燃料ノズルパージが2回実施されて、詰まりが解消されたことになり、逆流防止パージ弁40が開、ノズルパージ弁22が閉、高圧パージ弁21が閉へと順次作動して、詰まり解消パージが終了する。
【0031】
水張り・リバース
水濡らし戻し弁36が開となると、水濡らし弁34が10秒開けられ、吐出三方弁26と燃料遮断弁27との間の燃料配管12が水によりパージされる。水濡らし弁34、水濡らし戻し弁36が閉じられると、燃料遮断弁27が5秒開けられ、燃料配管12の燃料遮断弁27の前後が連通して、火炉1内のガスが燃料配管12、水濡らし戻し弁36及び水排出管37を介して燃料スラリタンク13に流入し、燃料配管12内がパージされる。これらの操作が繰り返された後、水濡らし戻し弁36が開となると、水濡らし弁34が10秒開かれてから、燃料遮断弁27が5秒開けられる。これにより、吐出三方弁26と燃料遮断弁27との間の燃料配管12が水によりパージされてから、火炉1内のガスにより燃料配管12内がパージされ、水張り・リバースが終了する。
【0032】
リバース
水濡らし戻し弁36が開けられてから燃料遮断弁27が5秒開けられ、燃料配管12の燃料遮断弁27の前後が連通して、火炉1内のガスが燃料配管12、水濡らし戻し弁36及び水排出管37を介して燃料スラリタンク13に流入し、燃料配管12内がパージされる。パージ後、燃料遮断弁27、水濡らし戻し弁36が閉じられ、リバースが終了する。
【0033】
空気パージ
配管パージ弁38が開けられてから燃料遮断弁27が30秒開けられる。これにより、高圧(35kg/cm)の空気が燃料配管12内を火炉1へと流れ、配管12がパージされる。パージ後、燃料遮断弁27、配管パージ弁38が閉じられ、空気パージが終了する。
【0034】
すなわち、水張り・リバース、リバース、空気パージを行うと、まず吐出三方弁26と燃料遮断弁27との間の燃料配管12が水によりパージされ、そして火炉1内のガスが吐出三方弁26の下流側の燃料配管12を逆流してその配管12内がパージされ、次に高圧(35kg/cm)の空気がその燃料配管12内に火炉1に向けて流れて配管12がパージされる。このように、燃料配管12内が水でパージされると共にガスが管12内を行ったり来たりするので、燃料配管12又は燃料ノズル3の詰まりを解消することができる。また、火炉1内の高圧ガスを利用して詰まりの解消を行うので、燃料配管12内を逆流させるためのガスや配管等が不要で装置の簡素化が図れる。尚、吐出三方弁26の下流側だけをパージするのは、停止時に吐出三方弁26の上流側の燃料配管12は水張りされるため詰まりが発生することがほとんどないからである。
【0035】
従って、燃料配管12内に残留した燃料がパージされるので、燃料の残留による詰まりを抑制することができると共に、詰まりが発生しても詰まりを解消することができる。
【0036】
【発明の効果】
以上要するに本発明によれば、燃料の残留による詰まりを抑制できるという優れた効果を奏する。
【図面の簡単な説明】
【図1】本発明の一実施例を示す構成図である。
【図2】本発明の詰まり解消パージを説明するための図である。
【図3】加圧流動層ボイラの一例を示す構成図である。
【符号の説明】
1 火炉
2 圧力容器
12 燃料配管
13 スラリタンク
26 三方弁
29 循環管
[0001]
[Industrial applications]
The present invention relates to a fuel purging method for a pressurized fluidized bed boiler for purging a fuel pipe for supplying a fuel slurry.
[0002]
[Prior art]
2. Description of the Related Art In recent years, a pressurized fluidized-bed boiler capable of burning fuel with high combustion efficiency, achieving compactness, a high desulfurization rate, and improving plant thermal efficiency has been researched and developed.
[0003]
As shown in FIG. 3, the pressurized fluidized-bed boiler supplies high-pressure air to a pressure vessel 2 in which a furnace 1 is accommodated, guides combustion air in the pressure vessel 2 into the furnace 1, and supplies fuel ( Coal) is burned while fluidized together with the bed material. The combustion exhaust gas from the furnace 1 is supplied to the gas turbine, and a part of the combustion heat in the fluidized bed is collected by the heat transfer tube to generate steam. This steam is supplied to a steam turbine.
[0004]
[Problems to be solved by the invention]
By the way, in the pressurized fluidized-bed boiler described above, it has been proposed to supply the fuel in a slurry state. For example, pulverized coal (which may include limestone) and water are mixed into a slurry, and this coal water slurry (CWM) is supplied to a furnace. In order to make the fuel in a slurry state, the fuel remains in the fuel pipe when the fuel supply is stopped, and in this state, the fuel sticks to the pipe or the like and causes clogging. Particularly in a pressurized fluidized-bed boiler, the pressure in the furnace is high, and this high-pressure gas flows back into the nozzles and pipes, so that the residual slurry is easily dried and solidified.
[0005]
The present invention has been made in view of such circumstances, and an object of the present invention is to provide a fuel purging method for a pressurized fluidized-bed boiler capable of suppressing clogging due to residual fuel.
[0006]
[Means for Solving the Problems]
The fuel purging method for a pressurized fluidized-bed boiler according to the present invention is a method for purging a fuel pipe for supplying a fuel slurry to a furnace housed in a pressure vessel and into which high-pressure air in the vessel is introduced. A three-way valve with a circulation pipe connected to the slurry tank of the slurry is interposed, and when the supply of the fuel slurry is stopped, the three-way valve operates so that the fuel pipe upstream of the three-way valve communicates with the circulation pipe. After that, the fuel pipe upstream of the three-way valve is purged with the purge gas, and then the three-way valve is operated so that the fuel pipe communicates, and the fuel in the fuel pipe is moved to the upstream side of the three-way valve by the furnace internal pressure. After the movement, the three-way valve is operated so that the fuel pipe upstream of the three-way valve communicates with the circulation pipe, and then the fuel pipe upstream of the three-way valve is purged.
[0007]
[Action]
When the supply of the fuel slurry is stopped, the fuel remains in the fuel pipe, but the three-way valve interposed in the fuel pipe is operated so that the fuel pipe upstream of the three-way valve communicates with the circulation pipe, and the three-way valve is closed. The upstream fuel line is purged. Then, the three-way valve operates so that the fuel pipe communicates. As a result, the fuel in the fuel pipe flows backward due to the furnace pressure and moves upstream of the three-way valve. After the movement, the fuel pipe upstream of the three-way valve is purged. Thereby, the fuel remaining in the fuel pipe is purged, so that clogging due to the remaining fuel can be suppressed.
[0008]
【Example】
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
[0009]
In FIG. 3, reference numeral 1 denotes a furnace housed in a pressure vessel 2, and the furnace 1 is provided with a fuel nozzle 3 for ejecting a slurry-like fuel, for example, coal water slurry (CWM).
[0010]
An air supply pipe 4 for increasing the pressure inside the vessel 2 is connected to the pressure vessel 2, and high-pressure air is injected from the air supply pipe 4 into the vessel 1 from an air distribution plate 5 in the pressure vessel 2. . The bed material made of ash, limestone or the like is fluidized by this air to form a fluidized bed, and the fuel (coal) burns under high temperature and high pressure (for example, about 860 ° C., 9 to 10 kg / cm 2 ). This combustion exhaust gas flows into the exhaust gas pipe 7 via the cyclone 6 in the pressure vessel 2 and is supplied to the gas turbine 8. A part of the combustion heat is collected by the heat transfer tube 9, and the steam generated by the heat is supplied to the steam turbine 11 via the steam tube 10.
[0011]
As shown in FIGS. 1 and 3, a fuel pipe 12 is connected to the fuel nozzle 3, and the fuel pipe 12 is connected to a fuel slurry tank 13. The fuel slurry tank 13 contains a fuel slurry (for example, a coal water slurry (CWM) obtained by mixing water with coal having an average particle diameter of 8 mm or less (which may include limestone) and water) manufactured by a fuel manufacturing apparatus or the like. The CWM is supplied and stored, and the CWM is ejected from the fuel nozzle 3 into the furnace 1 through the fuel pipe 12. The fuel nozzle 3 is connected to a fuel distribution air pipe 18 having a compressor 14, a fuel distribution air valve 15, a flow control valve 16, and a flow meter 17, and the fuel is dispersed by the air from the fuel distribution air pipe 18. . An N 2 supply pipe 20 having a backup valve 19 for supplying backup nitrogen (N 2 ) is connected to the fuel distribution air pipe 18. A purge pipe 23 having a high-pressure purge valve 21 and a nozzle purge valve 22 for purging the nozzle 3 with high-pressure (for example, 35 kg / cm 2 ) air is provided downstream of the flow meter 17 of the fuel dispersion air pipe 18. A gas pipe 24 into which air or the like flows through the fuel dispersion air valve 15 is connected to a purge pipe 23 connected between the high-pressure purge valve 21 and the nozzle purge valve 22.
[0012]
The fuel pipe 12 is provided with a fuel slurry pump 25, a discharge three-way valve 26, a fuel cutoff valve 27, and a pressure gauge 28 for sequentially measuring the pressure of the pipes before and after the fuel cutoff valve 27 and the pressure difference in the fuel flow direction. Is established. A circulation pipe 29 connected to the fuel slurry tank 13 is connected to the remaining port of the discharge three-way valve 26. Opening of the discharge three-way valve 26 indicates a state in which the fuel pipe 12 is in communication. The state where the fuel pipe 12 on the upstream side communicates with the circulation pipe 29 is shown. That is, when the three-way valve 26 indicates an open state, the fuel from the fuel slurry pump 25 is supplied to the nozzle 3, and when the three-way valve 26 is closed, the fuel returns to the slurry tank 13 and circulates.
[0013]
The fuel pipe 12 between the fuel slurry pump 25 and the discharge three-way valve 26 has a discharge purge valve 30 for purging the fuel pipe 12 with air having a pressure of 7 kg / cm 2 or the high pressure (35 kg / cm 2 ) air. Is connected. The circulation pipe 29 is connected to a circulation purge pipe 33 having a circulation purge valve 32 for purging the inside of the circulation pipe 29 with air at a pressure of 7 kg / cm 2 .
[0014]
A water supply pipe 35 having a water wetting valve 34 for supplying water such as miscellaneous water is provided in the fuel pipe 12 between the discharge three-way valve 26 and the fuel cutoff valve 27, for discharging water to the fuel slurry tank 13. A water discharge pipe 37 having a water wetting return valve 36, and a purge pipe having a pipe purge valve 38 for purging the fuel pipe 12 with, for example, dispersed air flowing into the gas pipe 24 or high-pressure air flowing into the purge pipe 23. 39 are connected.
[0015]
Connected to the fuel pipe 12 between the fuel cutoff valve 27 and the fuel nozzle 3 is a purge conduit 41 having a backflow prevention purge valve 40 for purging the fuel pipe 12 with, for example, dispersed air flowing into the gas pipe 24. ing.
[0016]
Next, a case where the fuel pipe 12 is purged will be described.
[0017]
When the gas turbine 8 is started, when the pressure in the pressure vessel 2 becomes 0.5 kg / cm 2 or more after the gas turbine 8 is started, the backflow prevention purge valve 40 is opened (the fuel dispersion air valve 15 is normally opened). (Maintained) to prevent the fuel slurry from flowing back through the pipe 12 and the like. Then, clogging in the fuel pipe 12 is determined by the pressure gauge 28. This is because the fuel pipe 12 is connected to the furnace 1 via the nozzle 3. When the pressure in the fuel pipe 12 is almost the same as the furnace 1 pressure, there is no clogging, and when the pressure difference is large, There is clogging. If there is a blockage, a blockage clearing purge (to be described later) for clearing the blockage is performed, thereby clearing the blockage. When clogging is eliminated, fuel nozzle purging (described later) is performed twice together with no clogging, and then, when the temperature in the layer reaches 600 ° C. or higher, CWM is charged and normal operation is performed.
[0018]
During operation, when the fuel slurry is tripped (in the case where the gas turbine operation is continued), the shutoff purge master is performed while the pressure in the furnace 1 is high as shown in FIG. During the operation, the fuel slurry pump 25 is operated, and the discharge three-way valve 26, the fuel cutoff valve 27, the fuel dispersion air valve 15, the flow regulating valve 16, and the backflow prevention purge valve 40 are open. The valve is normally closed.
[0019]
The shutoff purge master is performed as follows.
[0020]
First, when the slurry pump 25 stops, the fuel cutoff valve 27 and the three-way valve 26 operate so as to be closed from open. When the fuel cutoff valve 27 and the three-way valve 26 are closed, the discharge purge valve 30 and the nozzle purge valve 22 are opened. Thereby, for example, high-pressure (35 kg / cm 2 ) air is supplied to the fuel pipe 12 on the upstream side of the three-way valve 26, and the fuel in the pipe 12 is returned to the fuel slurry tank 13 via the circulation pipe 29, The fuel pipe 12 upstream of the three-way valve 26 is purged, and the fuel nozzle 3 is purged. Then, after a predetermined time (purging of the fuel pipe 12 on the upstream side of the three-way valve 26 is completed), the discharge purge valve 30 is closed, and the fuel cutoff valve 27 and the three-way valve 26 are opened. Thereby, the fuel pipe 12 communicates with the furnace 1, and the fuel downstream of the three-way valve 26 moves to the fuel pipe 12 upstream of the three-way valve 26 due to the furnace 1 internal pressure. After the movement, the three-way valve 26 operates to close and the pipe purge valve 38 operates to open. When the three-way valve 26 is closed, the discharge purge valve 30 opens. As a result, the gas from the pipe purge valve 38 purges the fuel pipe 12 downstream of the three-way valve 26 and the fuel pipe 12 upstream of the three-way valve 26. When the pipe purge valve 38 and the fuel cutoff valve 27 are closed, the water wetting valve 34 and the water wetting return valve 36 are opened. Thereby, water such as miscellaneous water is supplied to the fuel pipe 12 between the discharge three-way valve 26 and the fuel cutoff valve 27, and the fuel pipe 12 is purged with the water. Then, the discharge purge valve 30, the nozzle purge valve 22, and the water wetting valve 34 are closed, and thereafter, the water wetting return valve 36 is closed, and the shutoff purge master ends.
[0021]
That is, first, the fuel in the fuel pipe 12 on the upstream side of the three-way valve 26 is returned to the fuel tank 13, and then the fuel on the downstream side of the three-way valve 26 is transferred to the upstream side of the three-way valve 26 by using the internal pressure of the furnace 1. The fuel is returned to the tank 13 and the fuel pipe 12 is purged with air, and the fuel pipe 12 downstream of the three-way valve 26 is purged with air before the three-way valve Fuel pipe 12 between 26 and fuel cutoff valve 27 is purged with water, and the shutoff purge master ends. As described above, the fuel is purged by using the three-way valve 26 and the fuel cutoff valve 27 in a place where the internal pressure of the furnace 1 does not act, so that the fuel is supplied to the pipe 12 or the like as compared with the case where the fuel is purged into the high-pressure furnace 1. It is difficult to remain and the fuel can be purged more reliably. In addition, since the fuel is moved by using the high-pressure gas in the furnace 1, no gas, piping, or the like is required for the movement. Further, since the fuel pipe 12 between the three-way valve 26 and the fuel cutoff valve 27 is purged with water, the fuel can be more reliably purged. Therefore, the fuel remaining in the fuel pipe 12 can be returned to the fuel slurry tank 13 while utilizing the internal pressure of the furnace 1, and clogging due to the residual fuel can be suppressed.
[0022]
After the end of the shutoff purge master, the fuel nozzle purge is performed once, and then the bed height lowering operation is performed. When the bed height becomes 0.2 m or less, the fuel nozzle purge is performed once, and then the gas turbine 8 is stopped.
[0023]
The fuel nozzle purge is performed as follows.
[0024]
When the wetting return valve 36 is opened, the wetting valve 34 is opened for 10 seconds, and water purges the fuel pipe 12 between the discharge three-way valve 26 and the fuel cutoff valve 27. When the water wetting valve 34 and the water wetting return valve 36 are closed, the pipe purge valve 38 is opened, the backflow prevention purge valve 40 is closed, and then the fuel cutoff valve 27 is opened for 30 seconds. Thus, the fuel pipe 12 downstream of the discharge three-way valve 26 is purged by the air from the pipe purge valve 38. When the fuel cutoff valve 27 and the pipe purge valve 38 are closed, the backflow prevention purge valve 40 is opened. Then, after the wetting return valve 36 is opened, the wetting valve 34 is opened for 10 seconds, and the fuel pipe 12 between the discharge three-way valve 26 and the fuel cutoff valve 27 is purged with water. Then, the water wetting return valve 36 is closed, and the fuel nozzle purge ends. Thereby, the fuel pipe 12 downstream of the discharge three-way valve 26 is purged. This purging is a type of cleaning, which makes it difficult for the fuel to remain or adhere to the fuel pipe 12. This is because fuel easily adheres to the fuel pipe 12.
[0025]
Next, a case where the gas turbine 8 is tripped during operation will be described.
[0026]
When the gas turbine 8 is tripped, the furnace 1 is cooled and a GT trip cut-off purge described below is performed.
[0027]
When the GT trip cut-off purge slurry pump 25 stops, the fuel cut-off valve 27 and the three-way valve 26 are operated so as to be changed from open to closed. When the fuel cutoff valve 27 and the three-way valve 26 are closed, the discharge purge valve 30 and the nozzle purge valve 22 are opened. Thereby, for example, high-pressure (35 kg / cm 2 ) air is supplied to the fuel pipe 12 on the upstream side of the three-way valve 26, and the fuel in the pipe 12 is returned to the fuel slurry tank 13 via the circulation pipe 29, The fuel pipe 12 upstream of the three-way valve 26 is purged, and the fuel nozzle 3 is purged. After a predetermined time (the purge of the fuel pipe 12 on the upstream side of the three-way valve 26 is completed), the discharge purge valve 30 is closed, and the fuel cutoff valve 27 and the three-way valve 26 are opened. Thereby, the fuel pipe 12 communicates with the furnace 1, and the fuel downstream of the three-way valve 26 moves to the fuel pipe 12 upstream of the three-way valve 26 due to the furnace 1 internal pressure. After the movement, when the three-way valve 26 is closed, the discharge purge valve 30 is opened. As a result, the gas from the pipe purge valve 38 purges the fuel pipe 12 downstream of the three-way valve 26 and the fuel pipe 12 upstream of the three-way valve 26. Then, after the fuel cutoff valve 27 is closed, the discharge purge valve 30 and the nozzle purge valve 22 are closed, and the GT trip cutoff purge master ends. As described above, the fuel is purged by using the three-way valve 26 and the fuel cutoff valve 27 in a place where the internal pressure of the furnace 1 does not act, so that the fuel is supplied to the pipe 12 or the like as compared with the case where the fuel is purged into the high-pressure furnace 1. It is difficult to remain and the fuel can be purged more reliably. In addition, since the fuel is moved by using the high-pressure gas in the furnace 1, no gas, piping, or the like is required for the movement. Therefore, the fuel remaining in the fuel pipe 12 can be returned to the fuel slurry tank 13 while utilizing the internal pressure of the furnace 1, and clogging due to the residual fuel can be suppressed.
[0028]
Then, when the GT trip shut-off purge master ends and the temperature in the formation becomes 350 ° C. or lower, the gas turbine 8 is restarted (at this time, the backflow prevention purge valve 40 is not opened). After restarting the gas turbine, a series of clogging purges as shown in FIG. 5 are performed.
[0029]
The clogging clearing purge is performed when clogging occurs, and is specifically performed as shown in FIG.
[0030]
As shown in FIG. 2, first, when the slurry nozzle is clogged, the above-described shutoff purge master is performed after the slurry pump 25 is stopped. When the shutoff purge master is completed, the circulation operation of the slurry pump 25 is started, and the high-pressure purge valve 21 is opened. In case of gas turbine trip, start here. Then, after the nozzle purge valve 22 is opened, the backflow prevention purge valve 40 is closed. Next, water filling / reverse, reverse, and air purging are sequentially performed, and these three operations are repeated until clogging is eliminated. That is, these operations are repeated until the clogging is eliminated, and the clogging may be eliminated (confirmed by the pressure gauge 28) only with water filling / reverse. Incidentally, any one of these three operations may be repeatedly executed to eliminate the clogging. When the clogging is eliminated, the fuel nozzle purge is performed twice, and the clogging is eliminated, and the backflow prevention purge valve 40 is opened, the nozzle purge valve 22 is closed, and the high-pressure purge valve 21 is sequentially operated to be closed. Then, the clog clearing purge ends.
[0031]
When the water filling / reverse water wetting return valve 36 is opened, the water wetting valve 34 is opened for 10 seconds, and the fuel pipe 12 between the discharge three-way valve 26 and the fuel cutoff valve 27 is purged with water. When the water wetting valve 34 and the water wetting return valve 36 are closed, the fuel cutoff valve 27 is opened for 5 seconds, the front and rear of the fuel cutoff valve 27 of the fuel pipe 12 communicate, and the gas in the furnace 1 is The fuel flows into the fuel slurry tank 13 via the wetting return valve 36 and the water discharge pipe 37, and the inside of the fuel pipe 12 is purged. After these operations are repeated, when the wetting return valve 36 is opened, the wetting valve 34 is opened for 10 seconds, and then the fuel cutoff valve 27 is opened for 5 seconds. Thereby, after the fuel pipe 12 between the discharge three-way valve 26 and the fuel cutoff valve 27 is purged with water, the gas in the furnace 1 is purged inside the fuel pipe 12, and the water filling / reverse is completed.
[0032]
After the reverse water wetting return valve 36 is opened, the fuel cutoff valve 27 is opened for 5 seconds, the front and rear of the fuel cutoff valve 27 of the fuel pipe 12 communicate with each other, and the gas in the furnace 1 is discharged through the fuel pipe 12 and the water wetting return valve. The fuel flows into the fuel slurry tank 13 via the water discharge pipe 37 and the fuel pipe 12, and the inside of the fuel pipe 12 is purged. After the purge, the fuel cutoff valve 27 and the wetting return valve 36 are closed, and the reverse is completed.
[0033]
After the air purge pipe purge valve 38 is opened, the fuel cutoff valve 27 is opened for 30 seconds. Thereby, high-pressure (35 kg / cm 2 ) air flows through the fuel pipe 12 to the furnace 1, and the pipe 12 is purged. After purging, the fuel cutoff valve 27 and the pipe purge valve 38 are closed, and the air purge ends.
[0034]
That is, when water filling / reverse, reverse, and air purging are performed, first, the fuel pipe 12 between the discharge three-way valve 26 and the fuel cutoff valve 27 is purged with water, and the gas in the furnace 1 flows downstream of the discharge three-way valve 26. Then, the inside of the fuel pipe 12 is purged by flowing backward, and then high-pressure (35 kg / cm 2 ) air flows into the fuel pipe 12 toward the furnace 1 to purge the pipe 12. As described above, since the inside of the fuel pipe 12 is purged with water and gas flows back and forth in the pipe 12, clogging of the fuel pipe 12 or the fuel nozzle 3 can be eliminated. Further, since the clogging is eliminated by using the high-pressure gas in the furnace 1, no gas, piping or the like for flowing backward in the fuel pipe 12 is required, and the apparatus can be simplified. The reason why only the downstream side of the discharge three-way valve 26 is purged is that the fuel pipe 12 on the upstream side of the discharge three-way valve 26 is filled with water at the time of stoppage, so that clogging hardly occurs.
[0035]
Therefore, since the fuel remaining in the fuel pipe 12 is purged, clogging due to residual fuel can be suppressed, and even if clogging occurs, clogging can be eliminated.
[0036]
【The invention's effect】
In short, according to the present invention, there is an excellent effect that clogging due to residual fuel can be suppressed.
[Brief description of the drawings]
FIG. 1 is a configuration diagram showing one embodiment of the present invention.
FIG. 2 is a diagram for explaining a clog clearing purge according to the present invention.
FIG. 3 is a configuration diagram illustrating an example of a pressurized fluidized-bed boiler.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Furnace 2 Pressure vessel 12 Fuel pipe 13 Slurry tank 26 Three-way valve 29 Circulation pipe

Claims (1)

圧力容器に収容され容器内の高圧空気が導入される火炉に燃料スラリを供給する燃料配管をパージする方法において、前記燃料配管に、前記燃料スラリのスラリタンクに連通する循環管が接続された三方弁を介設し、燃料スラリの供給が停止したとき、三方弁を三方弁の上流側の燃料配管と循環管とが連通するように作動させた後、三方弁の上流側の燃料配管をパージガスでパージし、その後、三方弁を燃料配管が連通するように作動させて、火炉内圧で燃料配管内の燃料を三方弁の上流側に移動させ、移動後、三方弁を三方弁の上流側の燃料配管と循環管とが連通するように作動させてから三方弁の上流側の燃料配管をパージすることを特徴とする加圧流動層ボイラの燃料パージ方法。A method for purging a fuel pipe for supplying a fuel slurry to a furnace housed in a pressure vessel and into which high-pressure air in the vessel is introduced, wherein a three-way circulating pipe connected to a slurry tank of the fuel slurry is connected to the fuel pipe. A valve is interposed, and when the supply of the fuel slurry is stopped, the three-way valve is operated so that the fuel pipe on the upstream side of the three-way valve communicates with the circulation pipe, and then the fuel pipe on the upstream side of the three-way valve is purged. Then, the three-way valve is operated so that the fuel pipe communicates with the fuel pipe, the fuel in the fuel pipe is moved to the upstream side of the three-way valve by the furnace pressure, and after the movement, the three-way valve is moved to the upstream side of the three-way valve. A fuel purging method for a pressurized fluidized-bed boiler, wherein the fuel pipe is operated so as to communicate with the circulation pipe, and then the fuel pipe upstream of the three-way valve is purged.
JP08947895A 1995-04-14 1995-04-14 Fuel purge method for pressurized fluidized bed boiler Expired - Fee Related JP3555235B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08947895A JP3555235B2 (en) 1995-04-14 1995-04-14 Fuel purge method for pressurized fluidized bed boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08947895A JP3555235B2 (en) 1995-04-14 1995-04-14 Fuel purge method for pressurized fluidized bed boiler

Publications (2)

Publication Number Publication Date
JPH08285228A JPH08285228A (en) 1996-11-01
JP3555235B2 true JP3555235B2 (en) 2004-08-18

Family

ID=13971853

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08947895A Expired - Fee Related JP3555235B2 (en) 1995-04-14 1995-04-14 Fuel purge method for pressurized fluidized bed boiler

Country Status (1)

Country Link
JP (1) JP3555235B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4637658B2 (en) * 2005-06-16 2011-02-23 中国電力株式会社 CWP collection system and CWP collection method
JP4712010B2 (en) * 2007-09-03 2011-06-29 中国電力株式会社 Cleaning method of fuel supply nozzle in pipe
US10288293B2 (en) 2013-11-27 2019-05-14 General Electric Company Fuel nozzle with fluid lock and purge apparatus
US10451282B2 (en) 2013-12-23 2019-10-22 General Electric Company Fuel nozzle structure for air assist injection
CA2933539C (en) 2013-12-23 2022-01-18 General Electric Company Fuel nozzle with flexible support structures

Also Published As

Publication number Publication date
JPH08285228A (en) 1996-11-01

Similar Documents

Publication Publication Date Title
JP4253389B2 (en) Method for reliably removing liquid fuel from a fuel system of a gas turbine and apparatus for carrying out the method
JP2011522990A (en) Method for cleaning a fuel system of a gas turbine and the fuel system
TW487774B (en) Multifunctional water injection manifold and operation method thereof
US9476582B2 (en) System and method for removing slag inside a utility furnace
JP3555235B2 (en) Fuel purge method for pressurized fluidized bed boiler
JP4317628B2 (en) Oil nozzle purge method for gas turbine combustor
JP2001059427A5 (en)
CN105190175A (en) Pressurized fluidized furnace equipment
JP2682681B2 (en) Method for controlling a pressurized fluidized bed combustion power plant in the event of an operation failure in a gas turbine unit and a pressurized fluidized bed combustion power plant having a device for this control
JP2008032388A (en) Method and device for manufacturing/supplying coal-water paste
JP3807273B2 (en) Power plant equipped with heavy oil reformer and operation method thereof
JP3556961B2 (en) High temperature CWM supply device
JP2855874B2 (en) High temperature CWM supply device
JP3389114B2 (en) Fuel slurry supply apparatus, purge method thereof, and fuel slurry supply method
JP2005003266A (en) Stationary type soot blower for coal gasification device
JP3111190B2 (en) Soot-blowing system for removing solid matter from air preheater heat transfer element
JPH0968123A (en) Fuel temperature raising device
JP3807272B2 (en) Reformed fuel-fired gas turbine and its fuel system purge method
JP3823214B2 (en) Method for preventing clogging of fuel supply nozzle during emergency stop of fluidized bed boiler and fuel supply nozzle
KR100234222B1 (en) Device for feeding a pulverized coal of a integrated gasification combined cycle
JPH0642731A (en) Double stage fluidized bed type coal gas furnace
KR20040100183A (en) miying and spray system of activated chemicals coal boiler
JP2009030897A (en) Exhaust gas recirculation boiler
KR20240006883A (en) Urea water nitrogen oxide abatement device
JP3286762B2 (en) Slurry supply conduit and pressurized fluidized bed combustion furnace

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040420

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040503

LAPS Cancellation because of no payment of annual fees