JP3497155B1 - Temporary fixing tool and temporary fixing method for building material support - Google Patents

Temporary fixing tool and temporary fixing method for building material support

Info

Publication number
JP3497155B1
JP3497155B1 JP2002194247A JP2002194247A JP3497155B1 JP 3497155 B1 JP3497155 B1 JP 3497155B1 JP 2002194247 A JP2002194247 A JP 2002194247A JP 2002194247 A JP2002194247 A JP 2002194247A JP 3497155 B1 JP3497155 B1 JP 3497155B1
Authority
JP
Japan
Prior art keywords
building material
fixing
slide lock
lock member
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002194247A
Other languages
Japanese (ja)
Other versions
JP2004036202A (en
Inventor
卓郎 足立
Original Assignee
合資会社千崎三郎商店
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 合資会社千崎三郎商店 filed Critical 合資会社千崎三郎商店
Priority to JP2002194247A priority Critical patent/JP3497155B1/en
Publication of JP2004036202A publication Critical patent/JP2004036202A/en
Application granted granted Critical
Publication of JP3497155B1 publication Critical patent/JP3497155B1/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Fencing (AREA)

Abstract

【要約】 【課題】 基礎ブロックの空洞部に建材支柱を挿入して
モルタルを養生して支柱を固定する際に、建材支柱を安
定に固定することが可能なフェンス支柱等の建材支柱の
仮止め具及びその方法を提供する。 【解決手段】 基礎部の固定用空所内でスライド可能と
されたスライドロック部材と、そのスライドロック部材
を接触させつつそのスライドロック部材のスライド方向
と交差する向きの分力を受けて前記固定用空所の内壁又
は前記建材支柱の基部外面に押し付けられる押圧部材と
を備えるロックユニットを含む。前記スライドロック部
材が非ロック位置からロック位置に移動した状態でその
スライドロック部材と前記押圧部材との相互の押圧作用
に基づき、前記建材支柱が前記固定用空所内で仮止めさ
れる。
Abstract: PROBLEM TO BE SOLVED: To temporarily fix a building material support such as a fence support capable of stably fixing a building material support when a building material support is inserted into a hollow portion of a foundation block to cure a mortar and fix the support. Tools and methods thereof. SOLUTION: A slide lock member slidable in a fixing space of a base portion, and a component force in a direction intersecting a sliding direction of the slide lock member while the slide lock member is in contact with the slide lock member. And a pressing member pressed against the inner wall of the cavity or the outer surface of the base of the building material column. With the slide lock member moved from the unlocked position to the locked position, the building material support is temporarily fixed in the fixing space based on the mutual pressing action of the slide lock member and the pressing member.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、基礎ブロック(基
礎部)にフェンス支柱等の建材支柱を施工する際の支柱
の仮止め具および仮止め方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a temporary fixing tool and a temporary fixing method for a pillar when a building pillar such as a fence pillar is constructed on a foundation block (foundation).

【0002】[0002]

【従来の技術】図7(a)(b)に、従来例の斜視図を
示す。従来、この種のものは例えば図(a)に示される
ように、基礎ブロック101の孔102にモルタルを充
填し、そこにフェンス支柱103を差し込むとともに固
定具104を打ち込んで支柱103の垂直位置と水平位
置を調整してモルタルが固まるまで養生し、その後、再
びモルタルで孔102を塞いで仕上げていた。または、
図7(b)に示されるように、フェンス支柱の垂直位置
を固定するレベル棒105を用いて同様にモルタルにて
施工していた。施工後の状態を図7(c)に示す。
2. Description of the Related Art FIGS. 7A and 7B are perspective views of a conventional example. Conventionally, in this type, for example, as shown in FIG. (A), a hole 102 of a base block 101 is filled with mortar, a fence support 103 is inserted thereinto, and a fixture 104 is driven into the base 102 so that the vertical position of the support 103 is The horizontal position was adjusted to cure the mortar until it solidified, and then the hole 102 was closed again with mortar for finishing. Or
As shown in FIG. 7B, the level bar 105 for fixing the vertical position of the fence support was used to perform the mortar construction in the same manner. The state after construction is shown in FIG.

【0003】[0003]

【発明が解決しようとする課題】しかし、従来例におい
ては、モルタルが固まるまで約1日間養生することが必
要であると共に、フェンス支柱の固定がフェンス支柱の
前後方向(図面左手前から右後方)を固定するのみであ
り、左右方向への移動の自由が許されるため、モルタル
が固まるまでフェンス支柱を真っ直ぐに保持することが
容易ではなかった。
However, in the conventional example, it is necessary to cure the mortar for about one day until it solidifies, and the fence support is fixed in the front-back direction of the fence support (from the front left in the drawing to the rear right). It was not easy to hold the fence support in a straight line until the mortar was solidified, since it was only fixed and the freedom of movement to the left and right was allowed.

【0004】そこで、本発明の課題は基礎ブロックの固
定用空所部にフェンス支柱を挿入してモルタルを養生し
て支柱を固定する際に、フェンス支柱の左右方向の安定
化を図った、より簡単かつ強固に固定が可能なフェンス
支柱等の建材支柱の仮止め具および仮止め方法を提供す
ることにある。
Therefore, an object of the present invention is to stabilize the fence support in the left-right direction when inserting the fence support into the fixing cavity of the foundation block to cure the mortar and fix the support. An object of the present invention is to provide a temporary fixing tool and a temporary fixing method for building support columns such as fence supports that can be easily and firmly fixed.

【0005】[0005]

【課題を解決するための手段および作用・発明の効果】
本発明は、上記の問題を鑑みてなされた、基礎部の固定
用空所内にフェンス支柱等の建材支柱の基部を位置させ
てその固定用空所内にモルタル等の施工材料を充填して
建材支柱を基礎部に固定施工するのに先立ち、その建材
支柱を前記基礎部の固定用空所に仮止めするために、前
記建材支柱の基部と前記基礎部の固定用空所の内壁との
間に挿入される仮止め具であって、前記固定用空所内で
スライド可能とされたスライドロック部材と、そのスラ
イドロック部材を接触させつつそのスライドロック部材
のスライド方向と交差する向きの分力を受けて前記固定
用空所の内壁又は前記建材支柱の基部外面に押し付けら
れる押圧部材とを備えるロックユニットを含む。
[Means and Actions for Solving the Problems / Effects of the Invention]
The present invention has been made in view of the above-mentioned problems, and the base of a building material pillar such as a fence pillar is located in the fixing space of the foundation, and the building material pillar is filled with a construction material such as mortar in the fixing space. Prior to the fixed construction of the building material strut, between the base of the building material strut and the inner wall of the fixing cavity of the foundation part, in order to temporarily fix the building material strut in the fixing space of the foundation portion. A temporary fastener to be inserted, which receives a component force in a direction intersecting with the slide direction of the slide lock member while bringing the slide lock member into contact with the slide lock member, the slide lock member being slidable in the fixing space. And a pressing member that is pressed against the inner wall of the fixing space or the outer surface of the base of the building material column.

【0006】このように構成すれば、前記スライドロッ
ク部材が非ロック位置からロック位置に移動した状態で
そのスライドロック部材と前記押圧部材との相互の押圧
作用に基づき、前記建材支柱が前記固定用空所内で仮止
めされる
According to this structure, when the slide lock member is moved from the unlocked position to the locked position, the building material support post is fixed by the mutual pressing action of the slide lock member and the pressing member. Temporarily fixed in the void

【0007】このように、モルタルを充填する前に、建
材支柱を基礎ブロックの固定用空所内に強固に固定する
ことができれば、建材支柱が垂直方向および水平方向の
双方において安定するまでモルタルの養生を待つ必要も
なく、さらに、確実に建材支柱を真っ直ぐに立設させる
ことが容易となる。
As described above, if the building material columns can be firmly fixed in the fixing space of the foundation block before the mortar is filled, the curing of the mortar can be performed until the building material columns are stable both vertically and horizontally. There is no need to wait, and it becomes easier to ensure that the building material columns are erected straight.

【0008】また、さらに具体的な発明の形態として本
発明は、前記スライドロック部材は、非ロック位置から
ロック位置に移動する側の一端面に、前記スライドロッ
ク部材をスライド移動させるための引っ掛け部を備える
ものとすることができる。さらに、前記スライドロック
部材は、非ロック位置からロック位置に移動する側の一
端面に、前記スライドロック部材をスライドさせるため
のスライド方向にのびる引張り紐を有し、前記スライド
ロック部材が引張り紐に引張られて、前記建材支柱が前
記固定用空所内で仮止めされるようにしてもよい。
As a more specific form of the present invention, in the present invention, the slide lock member is moved from an unlocked position.
On the one end surface on the side that moves to the lock position, slide slide
The hook member may be provided with a hook for slidingly moving the hook member . Furthermore, the slide lock
The member is one of the parts that moves from the unlocked position to the locked position.
To slide the slide lock member on the end face
Has a pull cord that extends in the sliding direction of
When the lock member is pulled by the drawstring,
It may be temporarily fixed in the fixing space .

【0009】また、さらなる別な発明の形態として、建
材支柱の基部外面には前記ロックユニットの一方の押圧
部材が固定されており、他方の押圧部材はそれぞれの一
端部において連結部材にて一体化されてその間にスライ
ドロック部材を配置しており、前記押圧部材を一体化す
る連結部材はスライドロック部材の移動によって外れる
スポット溶接によって固定され、もしくは、他方の押圧
部材に設けられた突起が連結部材に空けられた係止孔に
係合して突起が係止孔に沿って移動するように構成さ
れ、前記建材支柱はロックユニットとともに前記固定用
空所内に挿入され、前記スライドロック部材が非ロック
位置からロック位置に移動する構成としてもよい。
According to still another aspect of the invention, one pressing member of the lock unit is fixed to the outer surface of the base of the building material strut, and the other pressing member is integrated by a connecting member at each one end. The slide lock member is arranged between them to integrate the pressing member.
The connecting member is released by the movement of the slide lock member.
Fixed by spot welding or pressing the other
The projection provided on the member is in the locking hole formed in the connecting member.
It is configured to engage and the protrusion moves along the locking hole.
Then, the building material column may be inserted together with a lock unit into the fixing space, and the slide lock member may be moved from the unlocked position to the locked position.

【0010】このように構成すれば、2つの押圧部材の
間にスライドロック部材を挟むようにしてスライドロッ
ク部材を押圧部材に接触させつつスライドさせることに
よって、スライドロック部材は2つの前記押圧部材を外
側に押し広げるように作用し、ロック位置までスライド
した後には、建材支柱が基礎部であるブロック等の固定
用空所内で強力に仮止めされることとなる。
[0010] With this structure, the slide lock member so as to sandwich the slide lock member between the two pressing members in Rukoto slide while in contact with the pressing member
Therefore, the slide lock member acts to spread the two pressing members outward, and after sliding to the lock position, the building material support is strongly temporarily fixed in a fixing space such as a block that is a foundation. It will be.

【0011】また、フェンス支柱等の建材支柱を固定す
る方法としての本発明は、基礎部の固定用空所内にフェ
ンス支柱等の建材支柱の基部を位置させてその固定用空
所内にモルタル等の施工材料を充填して建材支柱を基礎
部に固定施工するのに先立ち、その建材支柱を前記基礎
部の固定用空所に仮止めする方法であって、前記建材支
柱の基部を前記基礎部の固定用空所に位置させ、その建
材支柱と固定用空所との間に、前記固定用空所内でスラ
イド可能とされたスライドロック部材と、そのスライド
ロック部材を両側から接触させつつそのスライドロック
部材のスライド方向と交差する向きの分力を受けて前記
固定用空所の内壁又は前記建材支柱の基部外面に押し付
けられる押圧部材とを備え、この押圧部材の一方は建材
支柱の外面に固定されており、他方の押部材はそれぞ
れの一端部においてスライドロック部材の移動によって
外れるスポット溶接によって固定する連結部材にて一体
化されており、両押圧部材はその間にスライドロック部
材を配置して、前記建材支柱ロックユニットとともに
前記固定用空所内に挿入し、その前記スライドロック部
材を非ロック位置からロック位置に移動させることによ
りそのスライドロック部材とその両側の前記押圧部材と
の相互の押圧作用に基づき、前記建材支柱を前記固定用
空所内で仮止めすることを特徴とする。
Further, according to the present invention as a method of fixing a building material pillar such as a fence pillar, the base of the building material pillar such as a fence pillar is located in the fixing space of the foundation part, and mortar or the like is placed in the fixing space. Prior to fixing the building material support to the foundation by filling it with a construction material, it is a method of temporarily fixing the building support to the fixing space of the foundation, the base of the building support being the base of the foundation. A slide lock member that is located in a fixed space, and is slidable in the fixed space between the building material support and the fixed space, and the slide lock member while contacting the slide lock member from both sides. A pressing member that is pressed against the inner wall of the fixing cavity or the outer surface of the base of the building material column by receiving a component force in a direction intersecting with the sliding direction of the member, and one of the pressing members is fixed to the outer surface of the building material column. Are, the other the pressing member by the movement of the slide lock member at one ends
The pressing members are integrated by a connecting member that is fixed by spot welding, and a slide lock member is arranged between both pressing members , and the building material support is inserted into the fixing space together with a lock unit, and the slide lock is provided. Characterized in that by moving the member from the unlocked position to the locked position, the building material columns are temporarily fixed in the fixing space based on the mutual pressing action of the slide lock member and the pressing members on both sides thereof. To do.

【0012】また、さらに具体的な発明の形態として、
前記ロックユニットは、前記当接部材とともに、前記建
材支柱の基部外面に簡易性の粘着テープで固定するよう
にしてもよい。
Further, as a more specific form of the invention,
The lock unit may be fixed to the outer surface of the base of the building material strut with a simple adhesive tape together with the contact member .

【0013】このように構成すれば、例えばスライドロ
ック部材を押圧部材と軽く接触するような形態で、これ
らの部材をまとめてロックユニットとして一体化し、建
材支柱の外側面にロックユニットを貼り付けにより簡単
に取り付けることができる。すなわち、このように構成
すれば、その道の職人でなくとも、日曜大工程度に自ら
フェンス支柱等の建材支柱を立てたい場合等に、手軽に
利用することができる。
According to this structure, for example, the slide lock member is lightly contacted with the pressing member, these members are integrated into a lock unit, and the lock unit is attached to the outer side surface of the building support column. Easy to install. That is, with such a configuration, even a craftsman of the road can easily use it when he / she wants to stand a building material support pillar such as a fence support pillar on a Sunday large process degree.

【0014】[0014]

【発明の実施の形態】以下、本発明の実施の形態を図面
に示す実施例を参照しつつ説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The embodiments of the present invention will be described below with reference to the examples shown in the drawings.

【0015】図1は、本発明の建材支柱の仮止め具の使
用状態を説明する図である。以後、ここでの建材部材は
例としてフェンスであるものとして述べる。(a)はフ
ェンス支柱を固定する前の設置状態を示し、(b)で
は、フェンス支柱が固定された状態を示している。両側
面に、直方体形状の当接部材4と第1の押圧部材5を水
平に同位置に設置したフェンス支柱3が、基礎ブロック
1の固定用空所部2内に挿入されている。この時、フェ
ンス支柱3をレベル棒が貫通するためのレベル穴14の
位置にてフェンス支柱3は一定の垂直位置に固定され
る。すなわち、図7(b)に示す従来例と同様な形態で
ある。この状態では、固定されるのは垂直方向の位置の
みであって、水平方向(図1における左右の方向)には
固定されない。
FIG. 1 is a view for explaining a usage state of a temporary fixing tool for a building material strut according to the present invention. Hereinafter, the building material member here will be described as a fence, for example. (A) shows the installation state before fixing the fence support, and (b) shows the state where the fence support is fixed. Fence support pillars 3 in which a rectangular parallelepiped abutting member 4 and a first pressing member 5 are horizontally installed at the same position on both side surfaces are inserted into the fixing cavity 2 of the base block 1. At this time, the fence post 3 is fixed at a certain vertical position at the position of the level hole 14 for the level rod to penetrate the fence post 3. That is, it has the same form as the conventional example shown in FIG. In this state, only the vertical position is fixed, and the horizontal position (the left and right direction in FIG. 1) is not fixed.

【0016】フェンスの片側側面3bに接する第1の押
圧部材5、基礎ブロック1の固定用空所部2の片側内側
面2bに接する第2の押圧部材7およびそれらの押圧部
材を連結する棒状の連結部材6、さらに2つの押圧部材
5,7に挟まれた下方位置から上方に引き上げられるス
ライドロック部材9をまとめてロックユニット20とし
て、その詳細を図2に示す。
A first pressing member 5 in contact with one side surface 3b of the fence, a second pressing member 7 in contact with one side inner surface 2b of the fixing cavity portion 2 of the base block 1, and a rod-like member connecting these pressing members. FIG. 2 shows the details of the connecting member 6 and the slide lock member 9 that is pulled up from the lower position sandwiched by the two pressing members 5 and 7 together as a lock unit 20.

【0017】図2(a)はスライドロック部材9を引き
上げる前、(b)は引張り紐8を上方に引っ張ってスラ
イドロック部材9を引き上げてフェンス支柱を固定して
いく様子を示している。図示のごとく、第1の押圧部材
5および第2の押圧部材7は、共に対称をなすように下
方に向けてその幅が狭くなるようなテーパ形状を有す
る。そして、第1および第2の押圧部材5,7は、その
上端部において直方体の棒状の連結部材6にて一体化さ
れる。この実施例では、第1の押圧部材5を摺動不可能
として、第2の押圧部材7を図面左右方向にわずかに摺
動可能な締結用押圧部材として構成している。第1の押
圧部材5はその上端をねじ10にて連結部材6に固定さ
れて、第2の押圧部材7はその上端にてスポット溶接等
の手法により点付けされる。スライドロック部材9は両
側面が、それぞれ第1の押圧部材5および第2の押圧部
材7のテーパ面に対応したテーパ形状を有し、すなわち
縦断面形状においては等脚台形となる。そして、上方に
のびる引張り紐8を備える。
FIG. 2A shows a state before pulling up the slide lock member 9, and FIG. 2B shows a state in which the pull string 8 is pulled upward to pull up the slide lock member 9 to fix the fence support. As shown in the figure, the first pressing member 5 and the second pressing member 7 have a tapered shape such that the width thereof becomes narrower downward so as to be symmetrical. Then, the first and second pressing members 5 and 7 are integrated by a rectangular parallelepiped rod-shaped connecting member 6 at their upper ends. In this embodiment, the first pressing member 5 is made non-sliding, and the second pressing member 7 is constructed as a fastening pressing member that can slightly slide in the lateral direction of the drawing. The upper end of the first pressing member 5 is fixed to the connecting member 6 with a screw 10, and the second pressing member 7 is spotted at its upper end by a technique such as spot welding. Both sides of the slide lock member 9 have taper shapes corresponding to the taper surfaces of the first pressing member 5 and the second pressing member 7, respectively, that is, they have an isosceles trapezoidal shape in a longitudinal cross section. Then, the pulling string 8 extending upward is provided.

【0018】引張り紐8は、例えば、スライドロック部
材9の上辺に特に図示しないねじや釘等のひっかかりと
なる部材をスライドロック部材9の上辺にねじ込み、ね
じ込まれた釘の頭の部分にビニールテープを巻き付けて
設置することができる。この引張り紐8は、基礎ブロッ
ク1の固定用空所部2内に設置した時に、引張り紐8が
固定用空所部2から十分な長さだけ出るように、すなわ
ち引張る時の持ち手となる十分な長さが確保できるよう
に基礎ブロック1の高さよりある程度長く設けるとよ
い。
The pulling string 8 is made by, for example, screwing a member such as a screw or a nail (not shown) to the upper side of the slide lock member 9 into the upper side of the slide lock member 9, and vinyl tape at the head of the screwed nail. Can be wrapped around and installed. This pulling cord 8 is a handle when pulling the pulling cord 8 out of the fixing void 2 for a sufficient length when installed in the fixing void 2 of the base block 1, that is, when pulling. It is preferable that the base block 1 is provided to be somewhat longer than the height of the base block 1 so that a sufficient length can be secured.

【0019】当接部材4は直方体形状をなし、当接部材
4、第1および第2の押圧部材5、7さらに連結部材6
は共にプラスチックで形成される。当接部材4と第1の
押圧部材5は、共に両面テープ等の粘着テープによって
フェンス支柱3の側面に貼り付け固定されるものであ
る。
The contact member 4 has a rectangular parallelepiped shape, and includes the contact member 4, the first and second pressing members 5 and 7, and the connecting member 6.
Are both made of plastic. Both the abutting member 4 and the first pressing member 5 are attached and fixed to the side surface of the fence post 3 by an adhesive tape such as a double-sided tape.

【0020】さらに、一般的な基礎ブロック1の固定用
空所部2の幅は、当接部材4とロックユニット20を取
り付けたフェンス支柱3の幅より大きく、かつスライド
ロック部材9により仮止めした際には、当接部材4とロ
ックユニット20が固定用空所部2内に密接状態となり
得る幅に形成される。
Further, the width of the fixing space 2 of the general base block 1 is larger than the width of the fence support 3 to which the abutting member 4 and the lock unit 20 are attached, and is temporarily fixed by the slide lock member 9. At this time, the abutting member 4 and the lock unit 20 are formed in a width such that they can be in close contact with each other in the fixing space 2.

【0021】次に、上記構成からなる、フェンス支柱の
固定具の使用方法および動作を説明する。図3は当接部
材4およびロックユニット20をフェンス支柱3に粘着
テープにより固定する様子を示している。当接部材4の
片側側面には図4に示すように両面テープ12が取り付
けられ、特に図示しない剥離紙をはがしてフェンス支柱
3に接着させる。この接着させる垂直位置は図1に示す
ように一般的に基礎ブロック1の上辺から距離L(50
mm程度)下がった位置になるように、予め目印を施して
設置することができる。ロックユニット20のフェンス
支柱3と当接する第1の押圧部材5の当接面について
も、特に図示しないが当接部材4と同様に両面テープが
設けられて、当接部材4が貼り付けられるフェンス支柱
3の側面と逆の側面に当接部材と同じ高さになるように
取り付けることができる。
Next, a method of using and an operation of the fixture for the fence support having the above structure will be described. FIG. 3 shows a state in which the contact member 4 and the lock unit 20 are fixed to the fence support column 3 with an adhesive tape. A double-sided tape 12 is attached to one side surface of the contact member 4 as shown in FIG. 4, and peeling paper (not shown) is peeled off and adhered to the fence post 3. As shown in FIG. 1, the vertical position for adhesion is generally a distance L (50
It can be installed by marking in advance so that it will be in a lowered position. As for the contact surface of the first pressing member 5 that contacts the fence support column 3 of the lock unit 20, a double-sided tape is provided similarly to the contact member 4 (not shown), and the contact member 4 is attached to the fence. It can be attached to the side surface opposite to the side surface of the column 3 so as to have the same height as the contact member.

【0022】このようにして両側面に当接部材4とロッ
クユニット20を取り付けたフェンス支柱3を、続いて
図1(a)に示すように基礎ブロック1の固定用空所部
2内に挿入する。この時、当接部材4と固定用空所部の
内側面2a、また、第2の押圧部材7と固定用空所部の
もう一方の内側面2bとは、必ずしも接している必要は
無く、前にも述べたようにその後の仮止めする作用に奏
して固定用空所部2内に密接状態となる程度の隙間を有
していても構わない。
In this way, the fence pillar 3 having the abutting member 4 and the lock unit 20 attached to both side surfaces is provided, and subsequently, as shown in FIG.
Insert in 2. At this time, the contact member 4 and the inner side surface 2a of the fixing cavity portion, and the second pressing member 7 and the other inner side surface 2b of the fixing cavity portion do not necessarily have to be in contact with each other. As described above, there may be a gap in the fixing cavity portion 2 which is in a close contact state due to the subsequent provisional fixing action.

【0023】こうして、フェンス支柱3を固定用空所部
2内にセッティングした後、スライドロック部材9の上
端に備えられる引張り紐8を上方にむけて引張って(図
面矢印の方向)、スライドロック部材9を第1の押圧部
材5と第2の押圧部材7との間に入り込ませるように引
き上げる。すると、図1(b)に示すように、当接部材
4と固定用空所部の内側面2aとの隙間はなくなって圧
接状態となり、また、スライドロック部材9が第1の押
圧部材5と第2の押圧部材とを外側に押し広げるように
作用するので、第1の押圧部材5とフェンス支柱の側面
3b、および第2の押圧部材と固定用空所部の内側面2
bとの間で強固な締付け力が発生し、フェンス支柱3を
固定用空所部の両内側面2aおよび2bを介して協力に
圧接し固定する。
After setting the fence support 3 in the fixing space 2 in this manner, the pull string 8 provided at the upper end of the slide lock member 9 is pulled upward (in the direction of the arrow in the drawing) to slide the slide lock member. 9 is pulled up so as to be inserted between the first pressing member 5 and the second pressing member 7. Then, as shown in FIG. 1 (b), the gap between the contact member 4 and the inner side surface 2 a of the fixing cavity disappears and the pressure contact state is established, and the slide lock member 9 is connected to the first pressing member 5. Since it acts to spread the second pressing member outwardly, the first pressing member 5 and the side surface 3b of the fence support, and the second pressing member and the inner side surface 2 of the fixing cavity.
A strong tightening force is generated between the fence b and the fence b, and the fence column 3 is fixed by cooperating with the inner side surfaces 2a and 2b of the fixing space by press contact.

【0024】この時、第2の押圧部材7と連結部材6と
は、簡単にスポット溶接等で点付けされているため、ス
ライドロック部材9が引き上がり第1の押圧部材5と第
2の押圧部材7とが左右に広げられていくにつれ、点付
け部分に相当の負荷がかかることによって点付けが切断
される。この作用により、さらに第2の押圧部材7は固
定用空所部の内側面2bへの動きの自由度が増して、よ
り強固な締付け力が得られる。すなわち、レベル棒にて
垂直位置が固定され、そして本仮止め具により水平方向
位置が固定されて、フェンス支柱3は固定用空所部2内
で安定を保って立設されることとなる。
At this time, since the second pressing member 7 and the connecting member 6 are easily spotted by spot welding or the like, the slide lock member 9 is pulled up and the first pressing member 5 and the second pressing member are pushed. As the member 7 and the member 7 are spread to the left and right, a considerable load is applied to the spotting portion, whereby the spotting is cut. This action further increases the degree of freedom of movement of the second pressing member 7 to the inner side surface 2b of the fixing cavity, and a stronger tightening force can be obtained. That is, the vertical position is fixed by the level rod, and the horizontal position is fixed by the temporary fixing tool, so that the fence support column 3 is erected stably in the fixing space 2.

【0025】ここで、フェンス支柱3が傾いていたり、
フェンス支柱3の固定が不十分であったなら、溶接によ
る点付け部分が切断する以前であれば、はめ込んだスラ
イドロック部材9の上部分を上方から押し下げることに
より、簡単にスライドロック部材9の嵌合を解いて図1
(a)の状態に戻すことができる。そして、もう一度引
張り紐8を引っ張って、締付け直すことができる。
Here, the fence pillar 3 is inclined,
If the fixation of the fence support 3 is insufficient, and before the spotted portion by welding is cut, the slide lock member 9 is easily fitted by pushing down the upper portion of the fitted slide lock member 9 from above. Figure 1
The state of (a) can be restored. Then, the pull string 8 can be pulled again and tightened again.

【0026】このようにして、フェンス支柱3が固定用
空所部2内に固定された後は、不要な引張り紐8の一部
を切断して、図5に示すように固定用空所部2内に直接
モルタルを流し込み、固まるまで放置する。図1におい
て、当接部材4にはモルタル充填用の穴13が形成され
ており、この穴13内にもモルタルが入り込み、フェン
ス支柱の一連の固定具はモルタルの中に埋没される。こ
の穴13は、当接部材4を貫通して形成されていて、そ
の穴13が開口する当接部材4の双方の側からモルタル
が穴13内に入り込むようにすることもできるし、穴1
3を一方の側のみに開口する有底穴(行止り穴)とする
こともできる。
After the fence support 3 is fixed in the fixing space 2 in this manner, a part of the unnecessary pulling cord 8 is cut off and, as shown in FIG. Pour the mortar directly into 2 and let it stand until it hardens. In FIG. 1, a hole 13 for mortar filling is formed in the contact member 4, and the mortar also enters the hole 13 so that a series of fixtures of the fence support are buried in the mortar. The hole 13 is formed so as to penetrate through the contact member 4, and the mortar can be introduced into the hole 13 from both sides of the contact member 4 where the hole 13 opens.
It is also possible to use 3 as a bottomed hole (opening hole) which is open only on one side.

【0027】以下、その他の実施例について図面と共に
順次説明する。まず、連結部材の別の実施例を図6に示
す。上記では、直方体の棒状のものであったが、この実
施例は一側面に凹凸を設けて櫛歯のような形状をしたも
のである。この連結部材16は、第1の押圧部材5には
2本のねじ10にて固定され、第2の押圧部材には2箇
所の点付け部(スポット溶接部)11にて点付け固定さ
れる。ねじ10およびスポット溶接を2箇所にすること
により、第1および第2の押圧部材5、7との連結の安
定を図ることができる。
Other embodiments will be sequentially described below with reference to the drawings. First, another embodiment of the connecting member is shown in FIG. In the above, the shape is a rectangular parallelepiped rod, but in this embodiment, one side surface is provided with irregularities and is shaped like a comb tooth. The connecting member 16 is fixed to the first pressing member 5 with two screws 10, and is fixed to the second pressing member at two spotting portions (spot welding portions) 11. . By providing the screw 10 and the spot welding at two positions, the connection with the first and second pressing members 5 and 7 can be stabilized.

【0028】また、その他の連結方法の例を図8に示
す。図8では摺動可能な第2の押圧部材7と連結部材6
との結合部において、連結部材6に空けられた係止孔2
1に第2の押圧部材7に設けられた突起22が係合して
おり、この突起22が係止孔21に沿って移動でき、第
2の押圧部材7の図面横方向への移動を可能にするもの
である。
FIG. 8 shows an example of another connecting method. In FIG. 8, the slidable second pressing member 7 and the connecting member 6
The engaging hole 2 formed in the connecting member 6 at the connecting portion with
1 is engaged with a projection 22 provided on the second pressing member 7, and the projection 22 can be moved along the locking hole 21 and the second pressing member 7 can be moved in the lateral direction of the drawing. It is something to do.

【0029】なお、本実施例ではこれまで第2の押圧部
材7と連結部材6とを点付けによる固定としたが、これ
に限られることなく、例えば第1の部材5と連結部材6
とを点付けにしてもよいし、第1および第2の押圧部材
5,7の双方を点付けによる固定としてもよい。また、
当接部材4を、ロックユニット20と同様に構成して、
左右のスライドロック部材を順次引き上げてフェンス支
柱3の両側面から押圧することもできる。その例を図9
に示す。このように構成すれば、左右のロックユニット
のリフト量L1、L2に応じてフェンス支柱の左右の微調
整が可能になる。
In the present embodiment, the second pressing member 7 and the connecting member 6 have been fixed by dot attachment so far. However, the present invention is not limited to this. For example, the first member 5 and the connecting member 6 may be used.
And may be pointed, or both the first and second pressing members 5 and 7 may be fixed by pointing. Also,
The contact member 4 is configured similarly to the lock unit 20,
It is also possible to sequentially pull up the left and right slide lock members and press them from both side surfaces of the fence post 3. An example is shown in FIG.
Shown in. According to this structure, the left and right fine adjustments of the fence support can be performed according to the lift amounts L1 and L2 of the left and right lock units.

【0030】またさらに、別の実施例を図10(a)か
ら(c)に示す。図(a)に示すように、第1の押圧部
材45とスライドロック部材49との接触面を共に垂直
平面に形成し、第2の押圧部材47とスライドロック部
材49との接触面のみをテーパ形状とした例である。さ
らに、(b)は(a)の構成から第1の押圧部材45を
削除した構成の例を示し、(c)は、これまで述べてき
た実施例において、当接部材4がなく、フェンス支柱3
の片側外側面をブロックの固定用空所部2の内側面に直
接接するように構成した例である。
Still another embodiment is shown in FIGS. 10 (a) to 10 (c). As shown in FIG. 7A, the contact surfaces of the first pressing member 45 and the slide lock member 49 are both formed into vertical planes, and only the contact surface of the second pressing member 47 and the slide lock member 49 is tapered. This is an example of a shape. Further, (b) shows an example of a configuration in which the first pressing member 45 is deleted from the configuration of (a), and (c) shows a fence strut without the abutting member 4 in the embodiments described so far. Three
In this example, the outer surface on one side is directly contacted with the inner surface of the fixing cavity portion 2 of the block.

【0031】さらに、図11には、球形状のスライドロ
ック部材59を、紐60によって引張り上げて、その紐
60の先端を凸部58に巻き付けて締付け固定する例を
示す。このように、スライドロック部材の形状について
も、直方体やテーパを有する形状に限定されることはな
く、種々の形状を取ることが可能である。
Further, FIG. 11 shows an example in which the spherical slide lock member 59 is pulled up by a cord 60, and the tip end of the cord 60 is wound around the convex portion 58 and fixed by tightening. As described above, the shape of the slide lock member is not limited to the rectangular parallelepiped shape or the tapered shape, and various shapes can be adopted.

【0032】また、図12には、スライドロック部材を
引き上げる際の別の構成例を示す。図12に示すよう
に、スライドロック部材9の上部に環状の引っ掛け用係
止部30を形成して、その環の部分に引っ掛け部材31
を引っ掛けて固定し、上方に引っ張り、スライドロック
部材9が固定された後に、引っ掛け部材31を外す構成
とすることもできる。
FIG. 12 shows another example of the structure for pulling up the slide lock member. As shown in FIG. 12, an annular hooking locking portion 30 is formed on the upper portion of the slide lock member 9, and the hooking member 31 is attached to the ring portion.
It is also possible to have a structure in which the hooking member 31 is removed after the slide lock member 9 is fixed by pulling upward by hooking and fixing.

【0033】図13は、ロックユニットを水平状態に設
置した例を示す。(a)はその斜視図、(b)はその平
面図である。(a)に示すようにスライドロック部材9
の一端面から棒状のレバー61により図面矢印の方向に
力を加えると、その作用でスライドロック部材は(b)
に示すように図面上方向にスライドして、支柱3を締付
け固定することができる。
FIG. 13 shows an example in which the lock unit is installed in a horizontal state. (A) is the perspective view, (b) is the top view. As shown in (a), the slide lock member 9
When a force is applied from one end face of the slide lever 61 in the direction of the arrow in the drawing, the action causes the slide lock member to move to (b).
As shown in FIG. 3, the support column 3 can be fixed by sliding it upward in the drawing.

【0034】以上のように、本発明を図示した実施例に
基づき説明したが、この発明の請求項の範囲内におい
て、その他種々の変形例が可能である。
While the present invention has been described above based on the illustrated embodiments, various other modifications are possible within the scope of the claims of the present invention.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の建材支柱の仮止め具の一実施例を説明
する正面図。
FIG. 1 is a front view for explaining an example of a temporary fastener for a building material strut according to the present invention.

【図2】本発明のロックユニットの一実施例の詳細を説
明する正面図。
FIG. 2 is a front view for explaining details of an embodiment of the lock unit of the present invention.

【図3】本発明の建材支柱の仮止め具をフェンス支柱に
取り付ける動作を説明する図。
FIG. 3 is a view for explaining the operation of attaching the provisional fastener of the building material strut of the present invention to the fence strut.

【図4】当接部材の一実施例を示す斜視図。FIG. 4 is a perspective view showing an embodiment of a contact member.

【図5】モルタルを注ぐ際の全体イメージ斜視図。FIG. 5 is a perspective view of the entire image when pouring mortar.

【図6】連結部材の別の実施例を示す正面図。FIG. 6 is a front view showing another embodiment of the connecting member.

【図7】従来例を説明する斜視図。FIG. 7 is a perspective view illustrating a conventional example.

【図8】連結方法の別の実施例を示す図。FIG. 8 is a diagram showing another embodiment of the connecting method.

【図9】フェンス支柱の両側にロックユニットを備える
一実施例を示す図。
FIG. 9 is a diagram showing an embodiment in which lock units are provided on both sides of a fence support.

【図10】本発明の別な実施形態を説明する図。FIG. 10 is a diagram illustrating another embodiment of the present invention.

【図11】さらに本発明の別な実施形態を説明する図。FIG. 11 is a view for explaining another embodiment of the present invention.

【図12】別の実施例におけるスライドロック部材を引
き上げる様子を説明する図。
FIG. 12 is a view for explaining how to pull up the slide lock member in another embodiment.

【図13】本発明の別な一実施例を説明する図。FIG. 13 is a diagram for explaining another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 基礎ブロック 2 固定用空所部 3 フェンス支柱 4 当接部材 5 第1の押圧部材 6 連結部材 7 第2の押圧部材 8 引張り紐 9 スライドロック部材 10 ねじ 11 点付け部 12 両面テープ 13 モルタル用充填穴 14 レベル穴 20 ロックユニット 1 basic block 2 Fixed space 3 fence support 4 Contact member 5 First pressing member 6 connecting members 7 Second pressing member 8 drawstring 9 Slide lock member 10 screws 11 Pointing section 12 double-sided tape 13 Filling holes for mortar 14 level holes 20 lock unit

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E04H 17/22 E04H 12/22 ─────────────────────────────────────────────────── ─── Continuation of the front page (58) Fields surveyed (Int.Cl. 7 , DB name) E04H 17/22 E04H 12/22

Claims (8)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 基礎部の固定用空所内にフェンス支柱等
の建材支柱の基部を位置させてその固定用空所内にモル
タル等の施工材料を充填して建材支柱を基礎部に固定施
工するのに先立ち、その建材支柱を前記基礎部の固定用
空所に仮止めするために、前記建材支柱の基部と前記基
礎部の固定用空所の内壁との間に挿入される仮止め具で
あって、 前記固定用空所内でスライド可能とされたスライドロッ
ク部材と、そのスライドロック部材を接触させつつその
スライドロック部材のスライド方向と交差する向きの分
力を受けて前記固定用空所の内壁及び前記建材支柱の基
部外面に押し付けられる押圧部材とを備えるロックユニ
ットを含み、 前記スライドロック部材は、非ロック位置からロック位
置に移動する側の一端面に、前記スライドロック部材を
スライド移動させるための引っ掛け部を備え、前記スラ
イドロック部材が非ロック位置からロック位置に移動し
た状態でそのスライドロック部材と前記押圧部材との相
互の押圧作用に基づき、前記建材支柱が前記固定用空所
内で仮止めされることを特徴とする建材支柱の仮止め
具。
1. A construction material support is fixed to a foundation by locating a base of a construction support such as a fence support in a fixation space of the foundation and filling a construction material such as mortar into the fixation space. Prior to the above, it is a temporary fastener that is inserted between the base of the building material strut and the inner wall of the fixing cavity of the foundation in order to temporarily secure the building material strut to the fixing cavity of the foundation. And a slide lock member slidable in the fixing cavity, and a component force in a direction intersecting the sliding direction of the slide lock member while contacting the slide lock member, and receiving an internal force of the fixing cavity. And a lock unit provided with a pressing member that is pressed against the outer surface of the base of the building material strut, wherein the slide lock member has the slide lock portion on one end surface on the side that moves from the unlocked position to the locked position. The slide lock member is moved from the non-lock position to the lock position by the mutual pressing action of the slide lock member and the pressing member. Temporary fasteners for building material columns, which are temporarily secured in the space.
【請求項2】 基礎部の固定用空所内にフェンス支柱等
の建材支柱の基部を位置させてその固定用空所内にモル
タル等の施工材料を充填して建材支柱を基礎部に固定施
工するのに先立ち、その建材支柱を前記基礎部の固定用
空所に仮止めするために、前記建材支柱の基部と前記基
礎部の固定用空所の内壁との間に挿入される仮止め具で
あって、 前記固定用空所内でスライド可能とされたスライドロッ
ク部材と、そのスライドロック部材を接触させつつその
スライドロック部材のスライド方向と交差する向きの分
力を受けて前記固定用空所の内壁及び前記建材支柱の基
部外面に押し付けられる押圧部材とを備えるロックユニ
ットを含み、 前記スライドロック部材は、非ロック位置からロック位
置に移動する側の一端面に、前記スライドロック部材を
スライドさせるためのスライド方向にのびる引張り紐を
有し、前記スライドロック部材が引張り紐に引張られて
非ロック位置からロック位置に移動した状態でそのスラ
イドロック部材と前記押圧部材との相互の押圧作用に基
づき、前記建材支柱が前記固定用空所内で仮止めされる
ことを特徴とする建材支柱の仮止め具。
2. A construction material pillar is fixed to the foundation portion by locating a base portion of a building material pillar such as a fence strut in the fixing space of the foundation portion and filling a construction material such as mortar into the fixing space. Prior to the above, it is a temporary fastener that is inserted between the base of the building material strut and the inner wall of the fixing cavity of the foundation in order to temporarily secure the building material strut to the fixing cavity of the foundation. And a slide lock member slidable in the fixing cavity, and a component force in a direction intersecting the sliding direction of the slide lock member while contacting the slide lock member, and receiving an internal force of the fixing cavity. And a lock unit provided with a pressing member that is pressed against the outer surface of the base of the building material strut, wherein the slide lock member has the slide lock portion on one end surface on the side that moves from the unlocked position to the locked position. A slide string extending in the slide direction for sliding the slide lock member, and the slide lock member and the pressing member are pressed against each other in a state where the slide lock member is pulled by the draw string and moved from the unlocked position to the locked position. Based on the action, the building material column is temporarily fixed in the fixing space, and the building material column temporary fixing tool.
【請求項3】 基礎部の固定用空所内にフェンス支柱等
の建材支柱の基部を位置させてその固定用空所内にモル
タル等の施工材料を充填して建材支柱を基礎部に固定施
工するのに先立ち、その建材支柱を前記基礎部の固定用
空所に仮止めするために、前記建材支柱の基部と前記基
礎部の固定用空所の内壁との間に挿入される仮止め具で
あって、 前記固定用空所内でスライド可能とされたスライドロッ
ク部材と、そのスライドロック部材を両側から接触させ
つつそのスライドロック部材のスライド方向と交差する
向きの分力を受けて前記固定用空所の内壁及び前記建材
支柱の基部外面に押し付けられる押圧部材とを備えるロ
ックユニットを含み、 前記建材支柱の基部外面には前記ロックユニットの一方
の押圧部材が固定されており、他方の押圧部材はそれぞ
れの一端部において連結部材にて一体化されてその間に
スライドロック部材を配置しており、 前記建材支柱はロックユニットとともに前記固定用空所
内に挿入され、前記スライドロック部材が非ロック位置
からロック位置に移動した状態でそのスライドロック部
材とその両側の前記押圧部材との相互の押圧作用に基づ
き、前記建材支柱が前記固定用空所内で仮止めされる
共に、 前記スライドロック部材の両側の押圧部材を一体化する
連結部材は、少なくとも一方の押圧部材との間でスライ
ドロック部材の移動によって外れるスポット溶接によっ
て固定されている ことを特徴とする建材支柱の仮止め
具。
3. A construction material pillar is fixed to a foundation portion by locating a base portion of a building material pillar such as a fence strut in a fixing space of the foundation portion and filling a construction material such as mortar into the fixing space. Prior to the above, it is a temporary fastener that is inserted between the base of the building material strut and the inner wall of the fixing cavity of the foundation in order to temporarily secure the building material strut to the fixing cavity of the foundation. A slide lock member slidable in the fixing space, and the fixing space receiving the component force in a direction intersecting the sliding direction of the slide lock member while contacting the slide lock member from both sides. A lock unit having an inner wall and a pressing member that is pressed against an outer surface of the base of the building strut, wherein one pressing member of the lock unit is fixed to the outer surface of the base of the building strut, and the other is pressed. The materials are integrated by a connecting member at each one end, and a slide lock member is arranged between them. The building material column is inserted into the fixing space together with a lock unit, and the slide lock member is in the unlocked position. from, based on the pressing action of the mutual and the slide lock member in a state of being moved to the locked position and the pressing member on both sides thereof, when the building materials post is temporarily fixed by the fixing cavity
Together, the pressing members on both sides of the slide lock member are integrated.
The connecting member may be slid between at least one pressing member.
By spot welding, which is released by the movement of the locking member
Temporary fasteners for building material columns, which are characterized in that they are fixed .
【請求項4】 前記建材支柱の基部の片側にロックユニ
ットを配置し、このロックユニットの反対側の建材支柱
には当接部材を配置し、前記建材支柱は固定用空所の内
壁から離れた位置で固定されることを特徴とする請求項
1ないし請求項3のいずれか1項に記載の建材支柱の仮
止め具。
4. A lock unit is provided on one side of the base of the building material pillar.
Place the cot and the building material struts on the opposite side of this lock unit
A contact member is placed in the
It is fixed at a position away from the wall.
A temporary fastener for a building material pillar according to any one of claims 1 to 3 .
【請求項5】 前記建材支柱を前記固定用空所内で仮止
めするロックユニットは固定用空所の上面よりも下方に
位置しており、前記ロックされたロックユニットの上部
にはモルタルが充填されていることを特徴とする請求項
1ないし請求項4のいずれか1項に記載の建材支柱の仮
止め具。
5. The building material columns are temporarily fixed in the fixing space.
Lock unit to be installed below the upper surface of the fixing space.
Located on top of the locked lock unit
The building material column temporary fixing tool according to any one of claims 1 to 4, wherein the building material column is temporarily filled with mortar .
【請求項6】 基礎部の固定用空所内にフェンス支柱等
の建材支柱の基部を 位置させてその固定用空所内にモル
タル等の施工材料を充填して建材支柱を基礎部に固定施
工するのに先立ち、その建材支柱を前記基礎部の固定用
空所に仮止めする方法であって、 前記建材支柱の基部を前記基礎部の固定用空所に位置さ
せ、 その建材支柱と固定用空所との間に、 前記固定用空所内でスライド可能とされたスライドロッ
ク部材と、そのスライドロック部材を両側から接触させ
つつそのスライドロック部材のスライド方向と交差する
向きの分力を受けて前記固定用空所の内壁又は前記建材
支柱の基部外面に押し付けられる押圧部材とを備え、 この押圧部材の一方は建材支柱の外面に固定されてお
り、他方の押圧部材はそれぞれの一端部においてスライ
ドロック部材の移動によって外れるスポット溶接によっ
て固定する連結部材にて一体化されており、両押圧部材
はその間にスライドロック部材を配置して、前記建材支
柱をロックユニットとともに前記固定用空所内に挿入
し、 その前記スライドロック部材を非ロック位置からロック
位置に移動させることによりそのスライドロック部材と
その両側の前記押圧部材との相互の押圧作用に基づき、
前記建材支柱を前記固定用空所内で仮止めすることを特
徴とする建材支柱の仮止め方法。
6. A fence support or the like in the fixing space of the foundation part.
Position the base of the building material pillar of the
Filling construction material such as tar and fixing the building material support to the foundation.
Prior to construction, the building material supports for fixing the foundation part
A method of temporarily fixing to the void, wherein the base of the building material pillar is located in the void for fixing the foundation.
It was, between the fixing cavity and its building material strut slidably and slides locked in the fixing cavity
The slide lock member and the slide member from both sides.
While intersecting with the slide direction of the slide lock member
The inner wall of the fixing space or the building material by receiving the component force in the direction
And a pressing member that is pressed against the outer surface of the base of the pillar, one of the pressing members being fixed to the outer surface of the building material pillar.
The other pressing member has a slider at one end.
By spot welding, which is released by the movement of the locking member
It is integrated by a connecting member that secures the
Place a slide lock member between them to support the building materials.
Insert the pillar together with the lock unit into the fixing space
And, locking the said slide lock member from the unlocked position
By moving it to the position,
Based on the mutual pressing action with the pressing members on both sides,
It is special to temporarily fix the building material columns in the fixing space.
How to temporarily fix the building material columns to be collected.
【請求項7】 基礎部の固定用空所内にフェンス支柱等
の建材支柱の基部を位置させてその固定用空所内にモル
タル等の施工材料を充填して建材支柱を基礎部に固定施
工するのに先立ち、その建材支柱を前記基礎部の固定用
空所に仮止めする方法であって、 前記建材支柱の基部を前記基礎部の固定用空所に位置さ
せ、 その建材支柱と固定用空所との間に、 前記固定用空所内でスライド可能とされたスライドロッ
ク部材と、そのスライドロック部材を接触させつつその
スライドロック部材のスライド方向と交差する向きの分
力を受けて前記固定用空所の内壁又は前記建材支柱の基
部外面に押し付けられる押圧部材とを備えるロックユニ
ットを挿入し、 前記スライドロック部材の非ロック位置からロック位置
に移動する側の一端面には、このスライドロック部材を
スライドさせるための引っ掛け部を備え、この引っ掛け
部に固定した引っ掛け部材を引張って前記スライドロッ
ク部材を非ロック位置からロック位置に移動させること
によりそのスライドロック部材と前記押圧部材との相互
の押圧作用に基づき、前記建材支柱を前記固定用空所内
で仮止めすることを特徴とする建材支柱の仮止め方法。
7. A construction material pillar is fixed to a foundation portion by locating a base portion of a building material pillar such as a fence strut in a fixing space of the foundation portion and filling a construction material such as mortar into the fixing space. Prior to the method of temporarily fixing the building material columns to the fixing space of the foundation part, the base of the building material columns is located in the fixing space of the foundation part, and the building material columns and the fixing space are fixed. Between the slide lock member slidable in the fixing space and the slide lock member while receiving the component force in a direction intersecting the sliding direction of the slide lock member, Insert a lock unit having a pressing member that is pressed against the inner wall of the place or the outer surface of the base of the building strut, and at the one end surface of the slide lock member that moves from the unlocked position to the locked position, this slide The slide lock member is provided with a hook for sliding the id lock member, and the slide lock member and the pressing member are mutually moved by pulling the hook member fixed to the hook to move the slide lock member from the unlocked position to the lock position. Based on the pressing action of the above, the building material support column is temporarily fixed in the fixing space, and the building material support column is temporarily fixed.
【請求項8】 前記ロックユニットが固定された建材支
柱の反対側と固定用空所の内壁との間に当接部材が配置
され、この当接部材と前記ロックユニットは、前記建材
支柱の基部外面に簡易性の粘着テープで固定されている
ことを特徴とする請求項6又は請求項7に記載の建材支
柱の仮止め方法。
8. A building material support to which the lock unit is fixed
Abutment member is placed between the opposite side of the column and the inner wall of the fixing cavity
The contact member and the lock unit are
The method for temporarily fixing a building strut according to claim 6 or 7, characterized in that it is fixed to the outer surface of the base of the strut with a simple adhesive tape .
JP2002194247A 2002-07-03 2002-07-03 Temporary fixing tool and temporary fixing method for building material support Expired - Fee Related JP3497155B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002194247A JP3497155B1 (en) 2002-07-03 2002-07-03 Temporary fixing tool and temporary fixing method for building material support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002194247A JP3497155B1 (en) 2002-07-03 2002-07-03 Temporary fixing tool and temporary fixing method for building material support

Publications (2)

Publication Number Publication Date
JP2004036202A JP2004036202A (en) 2004-02-05
JP3497155B1 true JP3497155B1 (en) 2004-02-16

Family

ID=31702986

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002194247A Expired - Fee Related JP3497155B1 (en) 2002-07-03 2002-07-03 Temporary fixing tool and temporary fixing method for building material support

Country Status (1)

Country Link
JP (1) JP3497155B1 (en)

Also Published As

Publication number Publication date
JP2004036202A (en) 2004-02-05

Similar Documents

Publication Publication Date Title
CA2669369C (en) Sideform securing system
JP3497155B1 (en) Temporary fixing tool and temporary fixing method for building material support
JP3488870B2 (en) Pillar bracket
JPH05506486A (en) Improved handrail anchor assembly
JPH0544268A (en) Anchor plate
JPH06272219A (en) Support device of buffer stop support
CN218291978U (en) Soil nailing wall structure
JPH0119045Y2 (en)
CN2426136Y (en) Height mark device for floor slab pouring
JP2002146915A (en) Method for assembling connection section and structure
JP2595390Y2 (en) Post mounting aid
JPH0644920U (en) Wall panel pasting equipment
JP3225394B2 (en) Equipment for attaching decorative blocks to concrete products
JPS582837Y2 (en) Building material connection device
JP2008285941A (en) Backing steel member fixing structure
JP3640455B2 (en) Anchor bolt temporary holder
JP3115266B2 (en) Garden balcony deck panel mounting method and mounting structure
JP2952784B2 (en) Formwork structure and installation method
JPH05125816A (en) Jig for leveling of bundle base
JPH0738388Y2 (en) Support pin
JP2642844B2 (en) Spiral stairs and their mounting elements
JP2003247241A (en) Installation method for foundation packing material
CN117888712A (en) Early-dismantling upright rod, early-dismantling system and construction method
JP3003698U (en) Handrail member
JP2549918Y2 (en) Steel bundle base

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081128

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091128

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees