JP3494582B2 - Elevator control panel - Google Patents
Elevator control panelInfo
- Publication number
- JP3494582B2 JP3494582B2 JP00541899A JP541899A JP3494582B2 JP 3494582 B2 JP3494582 B2 JP 3494582B2 JP 00541899 A JP00541899 A JP 00541899A JP 541899 A JP541899 A JP 541899A JP 3494582 B2 JP3494582 B2 JP 3494582B2
- Authority
- JP
- Japan
- Prior art keywords
- control panel
- remodeling
- existing
- elevator
- machine room
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Cage And Drive Apparatuses For Elevators (AREA)
- Elevator Control (AREA)
Description
【発明の詳細な説明】
【0001】
【発明の属する技術分野】本発明は、エレベータの制御
変更や制御追加を行う際に改造用制御盤を新設するのに
好適なエレベータの制御盤に関する。
【0002】
【従来の技術】一般に、エレベータの改造時に、制御変
更や追加を行う場合、信号の検出や動作指令を出力する
ため磁石接触器等を備えた改造用制御盤を新たに設置し
て対応している。このような改造用制御盤は、エレベー
タ機械室の空きスペースに設置され、既設の制御盤とケ
ーブル等で信号接点の送受信を行っている。
【0003】図4は従来の改造用制御盤の設置方法を示
す正面図である。
【0004】従来の改造用制御盤1を機械室に設置する
場合、まず、図4に示すようにエレベータ機械室のコン
クリート床11の一部を除去し、この開口されたスペー
スにプールボックス13を勘合させ、再度、コンクリー
トを流し込んで床面12と同一の高さ寸法とし、次い
で、床下部12aとプールボックス13とをアンカーボ
ルト15により固定するとともに、このプールボックス
13上に改造用制御盤1を結合ボルト14により固定し
ていた。
【0005】
【発明が解決しようとする課題】ところで、前述した従
来の改造用制御盤1の設置方法では、必要な耐震性を確
保するためのプールボックス13を備えるため、コンク
リート床11の除去および再度コンクリートを流し込む
という作業が必要であり、多大な時間や労力を要するも
のとなっていた。
【0006】本発明はこのような従来技術における実情
に鑑みてなされたもので、その目的は、容易に改造用制
御盤を設置することのできるエレベータの制御盤を提供
することにある。
【0007】
【課題を解決するための手段】この目的を達成するため
に本発明は、機械室に既設制御盤および改造用制御盤の
それぞれを設置するエレベータの制御盤において、前記
既設制御盤の側面に前記改造用制御盤の側面を当接させ
て配置するとともに、この改造用制御盤と前記既設制御
盤とを連結部材を介して連結し、前記改造用制御盤の下
部を機械室床にアングルを介して固定した構成にしてあ
る。
【0008】前記のように構成した本発明によれば、改
造用制御盤を設置する場合、機械室にあらかじめ設けら
れる既設制御盤の側面に前記改造用制御盤の側面を当接
させて配置し、前記改造用制御盤と前記既設制御盤とを
連結部材により連結するとともに、前記改造用制御盤の
下部をアングルにより機械室床に固定する。このよう
に、耐震構造となっている既設制御盤に前記改造用制御
盤を当接させて配置することにより、従来のようにコン
クリート床の加工を要するプールボックスを設けること
なく前記改造用制御盤は必要な耐震性を確保でき、した
がって、容易に改造用制御盤を設置することができる。
【0009】
【発明の実施の形態】以下、本発明のエレベータの制御
盤の実施の形態を図に基づいて説明する。
【0010】図1は本発明のエレベータの制御盤の一実
施の形態を示す側面図、図2は図1のA部の要部拡大
図、図3は図1のB部の要部拡大図である。なお、前述
した図4に示すものと同等のものには同一符号が付して
ある。すなわち、1は改造用制御盤、11はコンクリー
ト床である。
【0011】本実施形態のエレベータの制御盤は図1に
示すように、あらかじめ機械室に設置される既設制御盤
2の側面に改造用制御盤1の側面を当接させて配置する
とともに、この改造用制御盤1と既設制御盤2とを連結
する連結部材3と、改造用制御盤1の下部を機械室床、
すなわちコンクリート床11に固定するアングル4とを
設けている。また、図2、3に示すように、前記の連結
部材3およびアングル4は結合ボルト5により改造用制
御盤1あるいは既設制御盤2と接続されるとともに、ア
ングル4はアンカーボルト6によりコンクリート床11
に固定されている。なお、既設制御盤2側に配置される
一方のアングル4は、改造用制御盤1と既設制御盤2と
を連結する連結部材の働きをもなしている。
【0012】この実施形態にあっては、改造用制御盤1
を設置する場合、一方のアングル4の側面を既設制御盤
2の側面に当接させて配置し、結合ボルト5により既設
制御盤2側面と接続するとともに、コンクリート床11
にアンカーボルト6により固定する。また、他方のアン
グル4を既設制御盤2側面に隣接するコンクリート床1
1の所定位置にアンカーボルト6により固定する。次い
で、アングル4の上部に改造用制御盤1を載置し、結合
ボルト5により互いを接続する。この後、連結部材3の
一端を結合ボルト5により改造用制御盤1と接続すると
ともに、連結部材3の他端を結合ボルト5により既設制
御盤2と接続し、作業を完了する。
【0013】このように構成した実施形態では、耐震構
造となっている既設制御盤2に改造用制御盤1を当接さ
せて配置することにより、従来のようにコンクリート床
11の加工を要するプールボックスを設けることなく改
造用制御盤1は必要な耐震性を確保でき、したがって、
容易に改造用制御盤1を設置することができる。
【0014】なお、本実施形態では組立を現地で行う方
法を説明したが、製作工場で可能な加工を行う方法もあ
る。
【0015】
【発明の効果】本発明は以上のように構成したので、従
来のようにコンクリート床の加工を要するプールボック
スを設けることなく改造用制御盤は必要な耐震性を確保
できることから、容易に改造用制御盤を設置することが
でき、これによって、設置作業に要する作業時間および
労力の低減を図ることができるという効果がある。Description: BACKGROUND OF THE INVENTION [0001] 1. Field of the Invention [0002] The present invention relates to an elevator control panel suitable for newly installing a remodeling control panel when changing or adding control of an elevator. 2. Description of the Related Art Generally, when a control is changed or added when an elevator is remodeled, a remodeling control panel provided with a magnet contactor or the like for detecting a signal or outputting an operation command is newly installed. Yes, it is. Such a control panel for remodeling is installed in an empty space in an elevator machine room, and transmits and receives signal contacts to and from an existing control panel using a cable or the like. FIG. 4 is a front view showing a method of installing a conventional control panel for remodeling. When the conventional control panel 1 for remodeling is installed in a machine room, first, as shown in FIG. 4, a part of a concrete floor 11 of an elevator machine room is removed, and a pool box 13 is placed in the opened space. After fitting, concrete is poured again to have the same height as the floor surface 12. Then, the lower floor portion 12 a and the pool box 13 are fixed with the anchor bolts 15, and the remodeling control panel 1 is placed on the pool box 13. Was fixed by the connecting bolt 14. [0005] In the above-mentioned conventional method of installing the control panel 1 for remodeling, since the pool box 13 for securing necessary earthquake resistance is provided, removal of the concrete floor 11 and removal of the concrete floor 11 are performed. The work of pouring the concrete again was necessary, which required a lot of time and labor. The present invention has been made in view of such a situation in the prior art, and an object of the present invention is to provide an elevator control panel in which a retrofit control panel can be easily installed. [0007] In order to achieve this object, the present invention provides an elevator control panel in which an existing control panel and a remodeling control panel are installed in a machine room. Aside from placing the side of the remodeling control panel in contact with the side, the remodeling control panel and the existing control panel are connected via a connecting member, and the lower part of the remodeling control panel is placed on the machine room floor. It is configured to be fixed via an angle . According to the present invention constructed as described above, when the control panel for remodeling is installed, the side face of the control panel for remodeling is arranged in contact with the side face of the existing control panel previously provided in the machine room. The remodeling control panel and the existing control panel are connected by a connecting member, and the lower part of the remodeling control panel is fixed to the machine room floor by an angle. Thus, by arranging the remodeling control panel in contact with the existing control panel having an earthquake-resistant structure, the remodeling control panel can be provided without providing a pool box requiring processing of a concrete floor as in the related art. Can secure the necessary earthquake resistance, and therefore can easily install a control panel for remodeling. An embodiment of an elevator control panel according to the present invention will be described below with reference to the drawings. FIG. 1 is a side view showing an embodiment of an elevator control panel according to the present invention, FIG. 2 is an enlarged view of a main part of a part A of FIG. 1, and FIG. 3 is an enlarged view of a main part of a part B of FIG. It is. The same components as those shown in FIG. 4 are denoted by the same reference numerals. That is, 1 is a control panel for remodeling, and 11 is a concrete floor. As shown in FIG. 1, the elevator control panel of the present embodiment is arranged such that the side of the remodeling control panel 1 is brought into contact with the side of an existing control panel 2 previously installed in a machine room. A connecting member 3 for connecting the control panel 1 for remodeling and the existing control panel 2;
That is, the angle 4 fixed to the concrete floor 11 is provided. As shown in FIGS. 2 and 3, the connecting member 3 and the angle 4 are connected to the remodeling control panel 1 or the existing control panel 2 by connecting bolts 5, and the angle 4 is connected to the concrete floor 11 by anchor bolts 6.
Fixed to. The one angle 4 arranged on the existing control panel 2 also serves as a connecting member for connecting the remodeling control panel 1 and the existing control panel 2. In this embodiment, the control panel 1 for remodeling
Is installed, the side of one of the angles 4 is placed in contact with the side of the existing control panel 2, connected to the side of the existing control panel 2 by the connecting bolt 5, and
With an anchor bolt 6. The other angle 4 is connected to the concrete floor 1 adjacent to the side of the existing control panel 2.
1 is fixed to a predetermined position by an anchor bolt 6. Next, the control panel for remodeling 1 is placed on the upper part of the angle 4 and connected to each other by the connecting bolt 5. Thereafter, one end of the connecting member 3 is connected to the control panel 1 for remodeling by the connecting bolt 5 and the other end of the connecting member 3 is connected to the existing control panel 2 by the connecting bolt 5 to complete the work. In the embodiment configured as described above, the retrofitting control panel 1 is placed in contact with the existing control panel 2 having an earthquake-resistant structure, so that the pool requiring the processing of the concrete floor 11 as in the prior art is provided. The retrofit control panel 1 can secure the required earthquake resistance without providing a box.
The retrofit control panel 1 can be easily installed. In the present embodiment, the method of performing the assembly on site has been described. According to the present invention, the control panel for remodeling can secure necessary earthquake resistance without providing a pool box which requires processing of a concrete floor as in the prior art. The control panel for the remodeling can be installed in the apparatus, and thereby, there is an effect that the working time and labor required for the installation work can be reduced.
【図面の簡単な説明】
【図1】本発明のエレベータの制御盤の一実施の形態を
示す側面図である。
【図2】図1のA部の要部拡大図である。
【図3】図1のB部の要部拡大図である。
【図4】従来の改造用制御盤の設置方法を示す正面図で
ある。
【符号の説明】
1 改造用制御盤
2 既設制御盤
3 結合部材
4 アングル
5 結合ボルト
6 アンカーボルト
11 コンクリート床BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a side view showing an embodiment of an elevator control panel according to the present invention. FIG. 2 is an enlarged view of a main part of a portion A in FIG. 1; FIG. 3 is an enlarged view of a main part of a portion B in FIG. 1; FIG. 4 is a front view showing a method of installing a conventional control panel for remodeling. [Description of Signs] 1 Remodeling control panel 2 Existing control panel 3 Connecting member 4 Angle 5 Connecting bolt 6 Anchor bolt 11 Concrete floor
───────────────────────────────────────────────────── フロントページの続き (72)発明者 田爪 克浩 東京都千代田区神田錦町1丁目6番地 株式会社日立ビルシステム内 (72)発明者 東田 一夫 東京都千代田区神田錦町1丁目6番地 株式会社日立ビルシステム内 (56)参考文献 特開 平10−316326(JP,A) 特開 平10−17223(JP,A) 特開 平9−12235(JP,A) 実開 昭53−47536(JP,U) 実開 昭56−63206(JP,U) (58)調査した分野(Int.Cl.7,DB名) B66B 1/00 - 11/08 ──────────────────────────────────────────────────続 き Continued on the front page (72) Katsuhiro Tazume, Inventor 1-6-6 Kandanishikicho, Chiyoda-ku, Tokyo Inside the Hitachi Building Systems Co., Ltd. (72) Inventor Kazuo Higashida 1-6-6 Kandanishikicho, Chiyoda-ku, Tokyo Co., Ltd. In the Hitachi Building System (56) References JP-A-10-316326 (JP, A) JP-A-10-17223 (JP, A) JP-A-9-12235 (JP, A) JP-A 53-47536 (JP) , U) Actually open 56-63206 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) B66B 1/00-11/08
Claims (1)
のそれぞれを設置するエレベータの制御盤において、 前記既設制御盤の側面に前記改造用制御盤の側面を当接
させて配置するとともに、この改造用制御盤と前記既設
制御盤とを連結部材を介して連結し、前記改造用制御盤
の下部を機械室床にアングルを介して固定したことを特
徴とするエレベータの制御盤。(57) [Claim 1] In an elevator control panel in which an existing control panel and a remodeling control panel are respectively installed in a machine room, a side face of the remodeling control panel is provided on a side face of the existing control panel. Abutting, and connecting the remodeling control panel and the existing control panel via a connecting member, and fixing the lower part of the remodeling control panel to the machine room floor via an angle. Elevator control panel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP00541899A JP3494582B2 (en) | 1999-01-12 | 1999-01-12 | Elevator control panel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP00541899A JP3494582B2 (en) | 1999-01-12 | 1999-01-12 | Elevator control panel |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2000203771A JP2000203771A (en) | 2000-07-25 |
JP3494582B2 true JP3494582B2 (en) | 2004-02-09 |
Family
ID=11610617
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP00541899A Expired - Fee Related JP3494582B2 (en) | 1999-01-12 | 1999-01-12 | Elevator control panel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3494582B2 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4817762B2 (en) * | 2005-08-30 | 2011-11-16 | 東芝エレベータ株式会社 | Elevator control panel system |
JP2012188209A (en) * | 2011-03-09 | 2012-10-04 | Toshiba Elevator Co Ltd | Installation structure of auxiliary console of elevator |
JP5858965B2 (en) * | 2013-09-06 | 2016-02-10 | 東芝エレベータ株式会社 | Control device installation method |
CN110997540B (en) | 2017-08-18 | 2021-12-10 | 三菱电机株式会社 | Elevator renewing method and auxiliary disc |
JP7063425B1 (en) * | 2021-01-19 | 2022-05-09 | 三菱電機株式会社 | Elevator car operation panel and sleeve wall fixing structure |
-
1999
- 1999-01-12 JP JP00541899A patent/JP3494582B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2000203771A (en) | 2000-07-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4291700B2 (en) | Construction method of high-rise building structure with steel frame and reinforced concrete structure | |
JP3494582B2 (en) | Elevator control panel | |
JP3160567B2 (en) | Expansion method of elevating equipment for dwelling unit access and its construction procedure | |
JP3528886B2 (en) | Existing beam reinforcement method | |
JP2020045753A (en) | Pit partition structure and construction method of elevator shaft | |
JP2020041311A (en) | Staircase structure and unit building | |
JPH058305Y2 (en) | ||
CN111535447A (en) | Prefabricated concrete prefabricated house and corner connecting technology | |
JP4511080B2 (en) | Construction method of underground structure | |
JP3597183B2 (en) | Barrier-free construction method of staircase type apartment house by building outer frame | |
CN211037543U (en) | Window frame and have its prefabricated wallboard | |
JP2001227199A (en) | Earth bonding by skeleton of structure | |
JP2728156B2 (en) | Elevator hoist support structure | |
JPH10184032A (en) | Method and apparatus for base isolation of already-constructed building | |
JP2710666B2 (en) | Floor plate fixing structure | |
JP2000073582A (en) | Base isolating construction method for existing building | |
JP3677689B2 (en) | Seismic reinforcement method and structure for existing buildings | |
JPH0317756B2 (en) | ||
JP2001193290A (en) | Seismic isolation method for existing building | |
JP3100102B2 (en) | Ceiling panel, construction method of house and ceiling structure of house | |
JP2024126220A (en) | Precast spandrel wall installation method and precast spandrel wall support structure | |
JPH023499Y2 (en) | ||
KR20230077254A (en) | Construction method of underground structure using large form | |
KR20030047483A (en) | Modified rectangular PC beam which include service duct in the dapped end of beam and method for constructing structure using the same | |
JPH09256457A (en) | Building assembly method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091121 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |