JP3478480B2 - Construction management method in the impermeable sheet method - Google Patents

Construction management method in the impermeable sheet method

Info

Publication number
JP3478480B2
JP3478480B2 JP30992898A JP30992898A JP3478480B2 JP 3478480 B2 JP3478480 B2 JP 3478480B2 JP 30992898 A JP30992898 A JP 30992898A JP 30992898 A JP30992898 A JP 30992898A JP 3478480 B2 JP3478480 B2 JP 3478480B2
Authority
JP
Japan
Prior art keywords
water
sheet
blocking sheet
preceding piece
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP30992898A
Other languages
Japanese (ja)
Other versions
JP2000136529A (en
Inventor
敏博 出口
利久 谷口
修 石田
Original Assignee
不動建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 不動建設株式会社 filed Critical 不動建設株式会社
Priority to JP30992898A priority Critical patent/JP3478480B2/en
Publication of JP2000136529A publication Critical patent/JP2000136529A/en
Application granted granted Critical
Publication of JP3478480B2 publication Critical patent/JP3478480B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、止水等を目的とし
て地中に貫入される遮水シート工法における施工管理方
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction management method in a water-blocking sheet construction method that is penetrated into the ground for the purpose of stopping water.

【0002】[0002]

【従来の技術】この種の遮水シート工法は、例えば、特
開昭64−29518号公報等に示されている如く、合
成樹脂製の遮水シート(所定長さの可撓性遮断板と同
義)が長手方向両側に互いに係合可能な雄部と雌部の一
方をそれぞれ有し、この複数枚を用いて、地中縦方向に
貫入した遮水シートに対し後続の遮水シートを互いの雄
部と雌部を係合しつつ貫入し、幅方向に順に接続配置す
ることにより、地表側から地中鉛直方向に連続止水壁を
形成するものである。適用例としては、産業廃棄物等を
封じ込める廃棄施設用の鉛直止水壁が挙げられる。この
場合は、廃棄施設を新たに構築する際に適用されるばか
りでなく、保守等を目的として既存の廃棄施設に新たな
鉛直止水壁を追加することもある。
2. Description of the Related Art This type of waterproof sheet construction method is disclosed in, for example, Japanese Patent Laid-Open No. 64-29518, which is made of a synthetic resin waterproof sheet (a flexible blocking plate of a predetermined length and Synonym) has one of a male part and a female part that can be engaged with each other on both sides in the lengthwise direction. The male part and the female part are penetrated while engaging with each other, and are sequentially connected and arranged in the width direction to form a continuous water stop wall in the vertical direction from the ground side. An example of application is a vertical stop wall for a waste facility that can contain industrial waste. In this case, not only is it applied when constructing a new disposal facility, but a new vertical stop wall may be added to the existing disposal facility for the purpose of maintenance.

【0003】図6(a)はそのような遮水シート工法に
より連続止水壁を構築する際の遮水シートの貫入状態を
模式的に示している。すなわち、同図において、符号2
0A,20B,20Cは単位長さに形成された遮水シー
トであり、何れも長手方向両側に沿って形成された互い
に係合可能な雄部21と雌部22とを有している。そし
て、遮水シート20Aと遮水シート20Bとの間は、遮
水シート20Aの雄部21に対し遮水シート20Bの雌
部22が上端から下端まで設計通り係合し、両シートの
接続部における遮水性が正常に維持されている。遮水シ
ート20Cは遮水シート20Bに対し接続されるもの
で、貫入途中の状態にある。
FIG. 6 (a) schematically shows the state of penetration of a water blocking sheet when a continuous water blocking wall is constructed by such a water blocking sheet method. That is, in FIG.
Reference numerals 0A, 20B, and 20C denote water-impermeable sheets formed to have unit lengths, and each has a male portion 21 and a female portion 22 that are formed along both sides in the longitudinal direction and are engageable with each other. Then, between the water blocking sheet 20A and the water blocking sheet 20B, the female portion 22 of the water blocking sheet 20B engages with the male portion 21 of the water blocking sheet 20A as designed from the upper end to the lower end, and the connecting portion of both sheets is connected. The water impermeability in is maintained normally. The water blocking sheet 20C is connected to the water blocking sheet 20B and is in a state of being penetrated.

【0004】[0004]

【発明が解決しようとする課題】以上の遮水シート工法
では、施工評価ないしは信頼性が次のような観点から未
だ満足できないものとなっている。すなわち、図6
(b)は遮水シート工法で発生すると考えられる例を模
式的に示したものであり、上記遮水シート20Cは貫入
途中から、雄・雌部21,22の係合を解除した状態で
貫入されている。このような異常事態は、例えば、図6
(a)の状態において、遮水シート20Cの下端付近に
硬質の岩や石の障害物24が存在し、雌部22の下端が
それに当たって局部荷重により形状変形して雄部21か
ら外れるというような希なケースである。後続の遮水シ
ート20Cは、貫入途中で、その下端の係合が一旦外れ
ると、更に貫入される過程で再び係合されず、図6
(b)の如く先行の遮水シート20Bとの間に非接続部
分23を形成し、止水機能を維持できなくなる。
In the above water-impermeable sheet construction method, the construction evaluation or reliability is still unsatisfactory from the following viewpoints. That is, FIG.
(B) schematically shows an example that is considered to occur in the water-impervious sheet construction method. The water-impervious sheet 20C is inserted while the male / female portions 21 and 22 are released from the middle of the penetration. Has been done. Such an abnormal situation is shown in FIG.
In the state of (a), there is a hard rock or stone obstacle 24 near the lower end of the water-impervious sheet 20C, and the lower end of the female portion 22 hits against it and is deformed by the local load to come off from the male portion 21. This is a rare case. The subsequent water-impervious sheet 20C is not engaged again in the process of being penetrated once the engagement of the lower end of the sheet is disengaged during penetration.
As shown in (b), the non-connecting portion 23 is formed between the preceding water blocking sheet 20B and the water blocking function cannot be maintained.

【0005】以上の従来対策としては、雄・雌部21,
22の係合を強度や形状的により解除され難く工夫した
り、本出願人らが先に開発した実公平7−35860号
の如く雄・雌部21,22の強制変形を補強具で阻止す
る等により対処していた。しかしながら、これらの対策
は、何れもが係合強度からの改良に過ぎず、遮水シート
同志の係合状態が正常に維持されるということを必ずし
も保障するものではない。また、現状では、例えば、廃
棄施設用の鉛直止水壁等において施工の信頼性をより客
観的に検証したいという強い要望がある。なお、遮水シ
ートを順次接続しながら地表に敷設する遮水シート工法
では、遮水シートの表裏側での電圧や抵抗計測等により
破損個所や非接続部を検証するシステムが確立されてい
る。これに対し、地中へ貫入する遮水シート工法では、
遮水シートを地中に深く(例えば、数十メートルの単位
で)貫入することに加え、遮水シートの下端側が地中で
連続しているため前記電圧や抵抗計測等により非接続部
等を検証することが難しい。
As the above conventional measures, the male / female portion 21,
The engagement of 22 is devised so that it is hard to be released due to its strength and shape, and the reinforcement prevents the forced deformation of the male / female portions 21 and 22 as in Japanese Utility Model Publication No. 7-35860 developed by the present applicants. And so on. However, each of these measures is merely an improvement from the engagement strength, and does not necessarily guarantee that the engagement state between the water-impermeable sheets is normally maintained. Further, under the present circumstances, for example, there is a strong demand to more objectively verify the reliability of construction in a vertical cutoff wall for a disposal facility. In the impermeable sheet construction method in which impermeable sheets are sequentially connected and laid on the surface of the earth, a system has been established that verifies damaged points and unconnected parts by measuring voltage and resistance on the front and back sides of the impermeable sheet. On the other hand, in the impermeable sheet method that penetrates underground,
In addition to deeply penetrating the impermeable sheet into the ground (for example, in units of several tens of meters), since the lower end side of the impermeable sheet is continuous in the ground, disconnection parts, etc. are measured by the voltage or resistance measurement. It is difficult to verify.

【0006】本発明は以上の背景に鑑みなされたもので
ある。その目的は、地中へ貫入する遮水シート工法にお
いて、遮水シート同志の係合状態が正常か、否かをより
客観的に検証可能にし、しかも検証原理や計測構造的に
簡単な施工管理方法を実現することにある。他の目的は
以下の内容説明の中で明らかにする。
The present invention has been made in view of the above background. The purpose is to make it possible to more objectively verify whether or not the water-impermeable sheets are normally engaged in the water-impermeable sheet construction method that penetrates into the ground. To realize the method. Other purposes will be made clear in the following description.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
本発明は、遮水シートが長手方向両側に雄部と雌部の一
方をそれぞれ有し、地中縦方向に貫入された既設の遮水
シートに対し、後続の遮水シートを互いに隣接する雄部
と雌部を係合しつつ貫入し接続する場合の施工管理方法
であって、前記後続の遮水シートを前記既設の遮水シー
トに係合するに際し、小型の先行ピースを予め既設の遮
水シート側に係合しておき、後続の遮水シートの貫入に
より押されて既設の遮水シートに沿って下降される先行
ピースの移動量を計測することにより、既設の遮水シー
トに対する後続の遮水シートの係合状態が正常か、否か
を判断するようにしたものである。
In order to achieve the above object, the present invention is directed to a water-blocking sheet which has one of a male part and a female part on both sides in the longitudinal direction, and which is an existing shield penetrated in the longitudinal direction of the ground. A water management sheet is a construction management method in the case of penetrating and connecting a subsequent water blocking sheet while engaging adjacent male and female parts, wherein the subsequent water blocking sheet is the existing water blocking sheet. When engaging with, the small preceding piece is previously engaged with the existing water-blocking sheet side, and the preceding piece is pushed down by the penetration of the subsequent water-blocking sheet and lowered along the existing water-blocking sheet. By measuring the amount of movement, it is possible to judge whether or not the engagement state of the subsequent water blocking sheet with respect to the existing water blocking sheet is normal.

【0008】以上の本発明方法において、先行ピース
は、遮水シートの雄部又は雌部に係合可能な形態で、小
型なものである。そして、本発明の検証原理は、先行ピ
ースが後続遮水シートで押し下げられる現象を利用する
ものである。すなわち、先行ピースを既設遮水シート側
に係合した状態から、後続遮水シートをその先行ピース
上から既設遮水シートに係合して貫入することにより、
後続遮水シートが既設遮水シートとの係合状態を維持し
ている限り、前記先行ピースが後続遮水シートの貫入に
より押されて既設遮水シートに沿って下降される。逆
に、後続遮水シートは、既設遮水シートとの係合を貫入
途中で解除されると、更に地中へ貫入されるものの、解
除時点から先行ピースを押し下げることが不可能にな
る。そこで、本発明では、後続遮水シートの貫入圧によ
り下降される先行ピースの移動量を逐次計測して、先行
ピースの下降が後続遮水シートの貫入途中で止まる場合
に後続遮水シートの係合が外れたと判断し、先行ピース
の下降移動量が設計通り(後続遮水シートの設計貫入移
動量と対応している)の場合に後続遮水シートの係合状
態が正常と判断する。
In the above-described method of the present invention, the preceding piece is small in size so that it can be engaged with the male part or the female part of the water shield sheet. The verification principle of the present invention utilizes a phenomenon in which the preceding piece is pushed down by the subsequent water blocking sheet. That is, from the state in which the preceding piece is engaged with the existing water-blocking sheet side, by engaging the subsequent water-blocking sheet with the existing water-blocking sheet from above the preceding piece,
As long as the succeeding water-impervious sheet maintains the engaged state with the existing impermeable sheet, the preceding piece is pushed by the penetration of the succeeding impermeable sheet and lowered along the existing impermeable sheet. On the contrary, if the subsequent water blocking sheet is released from the engagement with the existing water blocking sheet during the penetration, it will be further penetrated into the ground, but it will be impossible to push down the preceding piece from the release point. Therefore, in the present invention, the movement amount of the preceding piece that is lowered by the penetration pressure of the succeeding water-impervious sheet is sequentially measured, and when the descending of the preceding piece stops during the penetration of the succeeding impermeable sheet, the relationship of the succeeding impermeable sheet is increased. If the descending movement amount of the preceding piece is as designed (corresponding to the designed penetrating movement amount of the subsequent impermeable sheet), it is determined that the engagement state of the succeeding impermeable sheet is normal.

【0009】上記先行ピースの移動量や軌跡は、紐部材
を利用したり、信号検出等により計測可能であることか
ら、管理的に簡易であり、しかも原理が客観性に優れて
いる。すなわち、先行ピースの移動量や軌跡は、例え
ば、先行ピースにピアノ線等の紐部材を連結しておき、
紐部材が地表側から引き込まれた長さを計測する等の簡
易な方法で知ることができる。この場合、実施工では、
請求項2の如く巻取ドラムから引き出されて、その引出
し先端を先行ピースに連結した紐部材を用いて、当該紐
部材の送り出し量により計測することが好ましい。この
ような方法は、管理方法の確実性、異常事態に対する迅
速な対策等を可能にし、また、請求項3の如く先行ピー
スが紐部材を巻き上げることにより回収可能なことか
ら、同じ先行ピースが繰り返し利用される点等で優れて
いる。
Since the moving amount and the locus of the preceding piece can be measured by using a cord member or by detecting a signal, it is easy to manage and the principle is excellent in objectivity. That is, the movement amount and the locus of the preceding piece, for example, a string member such as a piano wire is connected to the preceding piece,
It can be known by a simple method such as measuring the length of the string member pulled from the ground side. In this case,
It is preferable to use a cord member which is pulled out from the winding drum and whose leading end is connected to the preceding piece, and is measured by the feed amount of the cord member. Such a method enables the reliability of the management method, prompt measures against an abnormal situation, and the like, and since the preceding piece can be collected by winding the string member, the same preceding piece is repeatedly used. It is excellent in terms of usage.

【0010】[0010]

【発明の実施の形態】以下、本発明の実施形態を添付図
面に基づいて詳細に説明する。この形態例は好適な基本
例であるが、本発明の技術的範囲を制約するものではな
い。なお、図1は本発明に係る遮水シート工法における
施工管理方法の原理を模式的に示し、図2は図1のA−
A線断面を示し、図3は本発明方法で使用される先行ピ
ース例を示し、図4は前記先行ピースの変形例を示し、
図5は施工管理で得られる施工記録(軌跡)例を示して
いる。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below in detail with reference to the accompanying drawings. This form example is a preferable basic example, but does not limit the technical scope of the present invention. In addition, FIG. 1 schematically shows the principle of the construction management method in the waterproof sheet construction method according to the present invention, and FIG. 2 shows A- of FIG.
FIG. 3 shows a section taken along line A, FIG. 3 shows an example of a preceding piece used in the method of the present invention, and FIG. 4 shows a modified example of the preceding piece.
FIG. 5 shows an example of a construction record (trajectory) obtained by construction management.

【0011】先ず、本発明方法が適用される遮水シート
工法自体は従来と同様に行われる。すなわち、施工域に
は、設計必要枚数の遮水シート1A,1B・・・が搬入
されると共に、貫入方式に応じた施工機(例えば、図1
に模式的に示したベースマシン等により起立支持された
支持リーダー5、支持リーダー5に沿って昇降される振
動機等の貫入機や遮水シートの貫入案内用のガイドフレ
ーム等)が搬入される。従来の貫入方式は、施工地盤の
硬さ等に応じて細部的に色々な方式が採用される。代表
例としては、遮水シート1A,1B等が地表側から直に
貫入連行される場合、遮水シート1A,1B等が貫入連
行される際あるいは前工程で地中貫入部の地盤をほぐし
たり、地中貫入部を先行掘削すると共に自硬性のベント
ナイト等で置き換える方式等がある。本発明の施工管理
方法は何れの貫入方式であってもよい。
First, the water-blocking sheet construction method itself to which the method of the present invention is applied is performed in the same manner as the conventional method. That is, the required number of designing water-blocking sheets 1A, 1B, ... Are carried into the construction area, and a construction machine (for example, FIG.
A supporting leader 5 erected and supported by a base machine, etc., a penetrating machine such as a vibrator that is elevated and lowered along the supporting leader 5, and a guide frame for guiding the penetration of the water-impervious sheet) are carried in. . As the conventional penetration method, various methods are used in detail according to the hardness of the construction ground. As a typical example, when the water-impervious sheets 1A, 1B, etc. are directly penetrated from the surface side, when the water-impermeable sheets 1A, 1B, etc. are entrained and carried, or in the previous process, the ground of the underground penetration part is loosened. , There is a method of excavating the underground penetration part in advance and replacing it with self-hardening bentonite. The construction management method of the present invention may be any penetration method.

【0012】また、遮水シート1A,1Bは、比較的硬
質の合成樹脂成形体(例えば、耐薬品性及び耐久性に優
れている高密度ポリエチレンシート)からなり、同形状
で所定の長さに形成されている。シート状の長手方向両
端には、図2の如く凸状雄部2と凹状雌部3の一方がそ
れぞれ一体的に形成されている。雄部2と雌部3は、互
いに係合可能な構造である。そして、地中縦方向に貫入
された既設の遮水シート1Aの雄部2に対し後続の遮水
シート1Bをその雌部3を係合しつつ地中へ貫入連行し
遮水シート1A,1B同士を接続する。この場合、雌部
3の凹状内に紐状のシール材4が配置され、雄部2と雌
部3の係合部はそのシール材4により止水状態となる。
なお、シール材4は、例えば、水膨張性の材質からな
り、雌部3内に設けられた小さな凹状部に挿入配置され
て雄部2との間に生じる隙間を封止するものである。ま
た、遮水シート工法では、例えば、実公平7−3586
0号の補強具が雌部3の下端側に付設されることもあ
る。
The water-blocking sheets 1A and 1B are made of a relatively hard synthetic resin molding (for example, a high-density polyethylene sheet having excellent chemical resistance and durability), and have the same shape and a predetermined length. Has been formed. As shown in FIG. 2, one of the convex male portion 2 and the concave female portion 3 is integrally formed at both ends of the sheet in the longitudinal direction. The male part 2 and the female part 3 have a structure capable of engaging with each other. Then, the male part 2 of the existing water-permeable sheet 1A that has penetrated in the longitudinal direction of the ground is carried into the ground while the female part 3 of the subsequent water-permeable sheet 1B is engaged, and the water-permeable sheet 1A, 1B is carried. Connect each other. In this case, the string-shaped sealing material 4 is arranged in the concave shape of the female portion 3, and the engaging portion between the male portion 2 and the female portion 3 is in a water-stop state by the sealing material 4.
The sealing material 4 is made of, for example, a water-swellable material, is inserted and arranged in a small concave portion provided in the female portion 3, and seals a gap generated between the sealing material 4 and the male portion 2. Further, in the water-blocking sheet construction method, for example, the actual fair 7-3586
The No. 0 reinforcing tool may be attached to the lower end side of the female portion 3.

【0014】そして、本発明の施工管理方法では、例え
ば、図1の如く小型の先行ピース6と、先行ピース6の
下降に随伴されたり、先行ピース6を上昇して回収する
線状の紐部材9と、その紐部材用巻取ドラム10等が用
意される。
In the construction management method of the present invention, for example, a small leading piece 6 as shown in FIG. 1 and a linear string member that accompanies the lowering of the leading piece 6 or raises and collects the leading piece 6. 9 and the winding drum 10 for the string members thereof are prepared.

【0015】ここで、先行ピース6は、図3の如く後続
の遮水シート1Bが既設の遮水シート1Aの雄部2に対
し雌部3を係合しつつ貫入される場合、その雌部3に類
似した形状になっている。この先行ピース6の基部側に
は、紐部材9を通す孔6aが前後に貫通形成されてい
る。このような先行ピース6は、既設遮水シート1Aの
雄部2(又は雌部3)に係合するケースでは雌部3(又
は雄部2)を形成している部分だけで構成したり、それ
に適宜な部分を付設してもよい。材質的には、金属や硬
質樹脂材等であり、図4の先行ピース7の如く樹脂成形
品8aの外側を金属製のカバー体8bにより補強するこ
とが好ましい。なお、同図の符合7aは紐部材9を通す
孔である。孔6aや孔7aは、紐部材9の引出し端9a
を先行ピース6,7に連結するためのものである。した
がって、孔6a,7aに代えて、突起やフック状等の他
の係止部であってもよい。
Here, when the succeeding water-blocking sheet 1B is inserted while the female part 3 is engaged with the male part 2 of the existing water-blocking sheet 1A as shown in FIG. It has a shape similar to 3. On the base side of the preceding piece 6, a hole 6a through which the cord member 9 is inserted is formed in the front and back. Such a preceding piece 6 may be composed of only the portion forming the female portion 3 (or the male portion 2) in the case of engaging with the male portion 2 (or the female portion 3) of the existing water-blocking sheet 1A, You may attach an appropriate part to it. The material is metal, a hard resin material or the like, and it is preferable to reinforce the outside of the resin molded product 8a with a metal cover body 8b like the preceding piece 7 in FIG. Reference numeral 7a in the figure is a hole through which the string member 9 is inserted. The hole 6a and the hole 7a are the pull-out end 9a of the string member 9.
Is connected to the preceding pieces 6 and 7. Therefore, instead of the holes 6a and 7a, other locking portions such as protrusions and hooks may be used.

【0016】紐部材9は、ピアノ線や細目のワイヤ等で
あり、巻取ドラム10に引き出し巻き上げ自在に巻かれ
ている。巻取ドラム10は、トルクモータ11の作動に
より所定の引っ張り力により紐部材9を自動的に引き出
したり、逆に、その引き出し部分に不要な撓みを生じる
ことなく紐部材9を巻き上げ可能になっている。また、
回転ドラム10の回転軸には回転検出器12が連結され
ている。この回転検出器12は、紐部材9の引き出し量
を逐次計測し、その値を演算処理部14に送信する。演
算処理部14は、記録部15や表示部16等を備えてお
り、回転検出部12から受信した紐部材9の送り出し量
について、先行ピース6の現在の地中深さを時間系列的
に処理し、それを例えば記録部15でオシロ表示した
り、表示部16でデジタル表示するものである。なお、
以上の巻取ドラム10、トルクモータ11、回転検出器
12は支持板13上にユニット状態で設けられて、例え
ば、施工機の支持リーダー5や専用の保持部材に取り付
けられる。
The cord member 9 is a piano wire, a fine wire, or the like, and is wound around the winding drum 10 so that it can be pulled out and wound up. The winding drum 10 can automatically pull out the string member 9 by a predetermined pulling force by the operation of the torque motor 11, and conversely, can wind up the string member 9 without causing unnecessary bending in the pulled-out portion. There is. Also,
A rotation detector 12 is connected to the rotary shaft of the rotary drum 10. The rotation detector 12 sequentially measures the pull-out amount of the string member 9 and sends the value to the arithmetic processing unit 14. The arithmetic processing unit 14 includes a recording unit 15, a display unit 16, and the like, and processes the current underground depth of the preceding piece 6 in a time series manner with respect to the feed amount of the string member 9 received from the rotation detection unit 12. Then, for example, it is oscilloscope-displayed on the recording unit 15 or digitally displayed on the display unit 16. In addition,
The winding drum 10, the torque motor 11, and the rotation detector 12 described above are provided in a unit state on the support plate 13, and are attached to, for example, the support leader 5 of the construction machine or a dedicated holding member.

【0017】次に、本発明の施工管理方法について、以
上の機器類を用いた場合の例にて手順等を詳述する。な
お、この施工管理方法は、図1の如く最初の遮水シート
1Aが地中に貫入された状態から、以後の遮水シート1
B等を順に貫入する場合に適用される。すなわち、ここ
では既設遮水シート1Aに対し後続の遮水シート1Bを
貫入する例であるが、遮水シート1Bが貫入された後、
その遮水シート1Bに接続される次の遮水シートでも同
様に行われるものである。
Next, the procedure and the like of the construction management method of the present invention will be described in detail by taking an example of using the above equipment. In addition, this construction management method is, as shown in FIG. 1, a state in which the first waterproof sheet 1A is penetrated into the ground, and thereafter
It is applied when penetrating B etc. in order. That is, here, an example in which the succeeding water-impermeable sheet 1B is inserted into the existing water-impermeable sheet 1A, but after the water-impermeable sheet 1B is penetrated,
The same operation is performed on the next water-blocking sheet connected to the water-blocking sheet 1B.

【0018】この施工管理方法では、遮水シート1Bが
既設遮水シート1Aに沿って貫入される前段階で、作業
者により既設遮水シート1Aの雄部2に先行ピース6が
係合される点が従来操作に追加される。つまり、先行ピ
ース6は、巻取ドラム10に巻かれた紐部材9の引出し
端9aに連結されており、図3の如く紐部材9により吊
り下げられた状態で、既設遮水シート1Aの雄部2の上
側に係合操作される。その後は、従来と同様に行われ
て、後続遮水シート1Bが先行ピース6の上から既設遮
水シート1Aに係合(雄部2に雌部3を係合)して貫入
操作されることになる。そして、先行ピース6は、後続
遮水シート1Bの貫入により、後続遮水シート1Bの下
端で押圧されて、後続遮水シート1Bと共に既設遮水シ
ート1Aに沿って下降される。このとき、先行ピース6
の下降移動量は、回転検出部12での紐部材9の送り出
し量として計測され、演算処理部14により先行ピース
6の現地中深さに換算し、それを時系列的に記憶処理さ
れる。
According to this construction management method, the operator engages the preceding piece 6 with the male portion 2 of the existing water blocking sheet 1A before the water blocking sheet 1B is inserted along the existing water blocking sheet 1A. The point is added to the conventional operation. That is, the preceding piece 6 is connected to the pull-out end 9a of the string member 9 wound around the winding drum 10, and is suspended from the string member 9 as shown in FIG. The engagement operation is performed on the upper side of the portion 2. After that, the subsequent water-impervious sheet 1B is engaged with the existing water-impervious sheet 1A (the male portion 2 is engaged with the female portion 3) from above the preceding piece 6 in the same manner as in the conventional case. become. Then, the preceding piece 6 is pressed by the lower end of the subsequent water-impervious sheet 1B due to the penetration of the subsequent water-impervious sheet 1B, and is lowered along with the subsequent water-impervious sheet 1B along the existing water-impervious sheet 1A. At this time, the preceding piece 6
The amount of downward movement of is measured as the amount of feeding of the string member 9 by the rotation detection unit 12, converted into the in-situ depth of the preceding piece 6 by the calculation processing unit 14, and stored in time series.

【0019】ところで、先行ピース6の下降は、後続遮
水シート1Bが貫入過程において既設遮水シート1Aと
の係合(雄・雌部2,3の係合)を維持し、かつ先行ピ
ース6が既設遮水シート1Aの下端から押し出されるま
で原則として継続される(図1の一点鎖線はその後続遮
水シート1Bの最終貫入状態を示している)。これに対
し、先行ピース6は、後続遮水シート1Bが貫入途中で
既設遮水シート1Aとの係合(雄・雌部2,3の係合)
を障害物等により強制的に解除されると、以後は後続遮
水シート1Bの押圧を受けないので下降しなくなる(図
1の二点鎖線はその後続遮水シート1Bの係合解除から
更に貫入された状態を示している)。これは先行ピース
6が既設遮水シート1Aとの係合を解除した場合も同様
である。以上のケースをまとめると、次の4通りとな
る。 、ケース1は先行ピース6及び後続遮水シート1Bが
共に正常に係合している。 、ケース2は先行ピース6が係合し、後続遮水シート
1Bが係合解除している。 、ケース3は先行ピース6が係合解除し、後続遮水シ
ート1Bが係合している。 、ケース4は先行ピース6及び後続遮水シート1Bが
共に係合解除している。
By the way, the lowering of the preceding piece 6 maintains the engagement of the existing waterproof sheet 1A (engagement of the male and female portions 2 and 3) with the subsequent waterproof sheet 1B in the penetration process, and Is continued in principle until it is pushed out from the lower end of the existing water-impervious sheet 1A (the one-dot chain line in Fig. 1 shows the final penetration state of the subsequent water-impervious sheet 1B). On the other hand, the preceding piece 6 is engaged with the existing impermeable sheet 1A while the succeeding impermeable sheet 1B is being penetrated (engagement of the male / female portions 2 and 3).
If it is forcibly released by an obstacle or the like, it will not descend because it is not pressed by the subsequent water-impervious sheet 1B (the two-dot chain line in FIG. 1 further penetrates from the disengagement of the subsequent water-impermeable sheet 1B). Has been shown). This is the same when the preceding piece 6 is disengaged from the existing water blocking sheet 1A. The above four cases can be summarized as follows. In the case 1, both the preceding piece 6 and the subsequent water blocking sheet 1B are normally engaged. The case 2 has the preceding piece 6 engaged and the subsequent water-blocking sheet 1B disengaged. , The leading piece 6 is disengaged from the case 3, and the subsequent water blocking sheet 1B is engaged with the case 3. The case 4 is disengaged from both the preceding piece 6 and the subsequent water blocking sheet 1B.

【0020】そして、本発明の施工管理方法の判断で
は、前記の場合だけを正常と判定し、前記からを
異常であると判定するものである。これは、前記の場
合、先行ピース6の下降移動量が、例えば、図5中の
(a)の如く地表(GL=0)から設計貫入深度に達す
るまで連続した正常軌跡となって表されることになる。
逆に、前記からの場合には、先行ピース6が後続遮
水シート1Bにより正常に押圧されなくなる結果、その
下降移動量が例えば、図5中の(b)の如く異常発生時
点から全く下降されないか、(c)の如く下降が急激に
減速されるという異常軌跡となって表される。ここで、
図5(a),(b),(c)において、符合H1は先行
ピース6が後続遮水シート1Bに押圧されつつ貫入時の
ピース下降軌跡であり、符合H2は回転ドラム10を強
制的に反転させて紐部材9を巻き上げて先行ピース6を
回収するピース上昇軌跡である。なお、符合S1は後続
遮水シート1Bの貫入時のシート下降軌跡であり、符合
S2は前記した異常発生により後続遮水シート1Bを再
び引き上げるシート上昇軌跡である。このシート上昇操
作は、前記図5(b),(c)のピース下降軌跡H1の
異常を検知した段階で行われることになる。なお、演算
処理部14では、そのピース下降軌跡H1の異常に基づ
いて警報音を発生し、作業者は当該警報音により異常事
態を検知して後続遮水シート1Bの貫入操作を速い段階
で止めて対応できるようになっている。
In the judgment of the construction management method of the present invention, only the above case is judged to be normal and the above steps are judged to be abnormal. In the above case, this is expressed as a continuous normal trajectory until the descending movement amount of the preceding piece 6 reaches the design penetration depth from the ground surface (GL = 0) as shown in (a) of FIG. 5, for example. It will be.
On the contrary, in the case of the above, the preceding piece 6 is not normally pressed by the succeeding water-blocking sheet 1B, and as a result, the descending movement amount is not descended at all from the time of occurrence of an abnormality as shown in (b) of FIG. 5, for example. Or, it is represented as an abnormal locus in which the descent is rapidly decelerated as shown in (c). here,
In FIGS. 5A, 5B, and 5C, reference numeral H1 is a piece descending locus when the preceding piece 6 is being pressed by the succeeding water-impervious sheet 1B and is penetrated, and reference numeral H2 is forcibly the rotating drum 10. It is a piece rising locus for reversing and winding up the string member 9 to collect the preceding piece 6. The reference sign S1 is a sheet descending locus when the succeeding water impervious sheet 1B penetrates, and the sign S2 is a sheet ascending trajectory for pulling up the succeeding impervious sheet 1B again due to the above-described abnormality. This sheet raising operation is performed at the stage when the abnormality of the piece descending locus H1 of FIGS. 5B and 5C is detected. In addition, in the arithmetic processing unit 14, an alarm sound is generated based on the abnormality of the piece descending locus H1, and the worker detects an abnormal situation by the alarm sound and stops the penetration operation of the subsequent water-blocking sheet 1B at an early stage. It is possible to deal with it.

【0021】ところで、従来は、後続遮水シート1Bの
貫入時のシート下降軌跡S1を得ることもあったが、こ
れだけでは既設遮水シート1Aとの間の係合が解除され
たとしても連続軌跡となることから、正常か、否か判断
できない。この点は、本発明方法の如く先行ピース6の
下降移動量や下降軌跡を回転検出部12等により逐次計
測するだけで、容易かつ簡明に検証可能になる。つま
り、施工管理的には、上記した通り先行ピース6の下降
が後続遮水シート1Bの貫入途中で止まる場合((図5
(b),(c)の異常軌跡)にその係合が外れたと判定
し、先行ピース6の下降移動量が設計通りの場合(図5
(a)の正常軌跡)に後続遮水シート1Bの係合状態が
正常と判定できるからである。このような施工管理方法
では、異常事態を貫入過程で検知することから修正操作
も迅速に行えること、使用した各遮水シートの貫入施工
履歴を記録部14で記録保存できること、先行ピース6
が既設遮水シート1Aの雄部2に付着した泥等を落とす
作用もあるため後続遮水シート1B等の係合状態(雌部
3が清掃された雄部2に係合)も理想的なものになるこ
と、等の点で優れたものとなる。
By the way, in the past, the sheet descending locus S1 at the time of penetration of the succeeding water impervious sheet 1B was sometimes obtained, but with this alone, even if the engagement with the existing impermeable sheet 1A is released, the continuous locus is obtained. Therefore, it is impossible to judge whether it is normal or not. This point can be easily and simply verified by simply sequentially measuring the descending movement amount and descending locus of the preceding piece 6 by the rotation detecting unit 12 or the like as in the method of the present invention. That is, in terms of construction management, when the lowering of the preceding piece 6 stops during the penetration of the subsequent water blocking sheet 1B as described above ((FIG.
When it is determined that the engagement is disengaged on the abnormal loci of (b) and (c), and the downward movement amount of the preceding piece 6 is as designed (FIG. 5).
This is because it is possible to determine that the engagement state of the succeeding water-impervious sheet 1B is normal to the (normal trajectory of (a)). In such a construction management method, since an abnormal situation is detected in the penetration process, a correction operation can be performed quickly, and the penetration construction history of each water-impervious sheet used can be recorded and stored in the recording unit 14, and the preceding piece 6
Also has an action of dropping mud and the like adhering to the male portion 2 of the existing water-impervious sheet 1A, so that the subsequent water-impervious sheet 1B or the like is ideally engaged (the female portion 3 is engaged with the cleaned male portion 2). It will be excellent in terms of things.

【0022】なお、本発明方法は、請求項に記載した技
術要素以外についてはこの実施形態に限られることな
く、遮水シートの材質や長さ、施工規模等に応じて適宜
に変更されるものである。また、回転ドラム10,検出
部12,演算処理部14等については、より実施工に合
致したものに適宜改良されることも勿論である。
The method of the present invention is not limited to this embodiment except for the technical elements described in the claims, and may be appropriately changed according to the material and length of the water-blocking sheet, the construction scale, etc. Is. Further, it is needless to say that the rotary drum 10, the detection unit 12, the arithmetic processing unit 14, and the like can be appropriately improved so as to better match the actual work.

【0023】[0023]

【発明の効果】以上説明したように、本発明に係る遮水
シート工法における施工管理方法は次のような利点を有
している。第1に、先行ピースが後続遮水シートに押さ
れて下降される現象を利用することから客観性があり、
先行ピースの移動量や軌跡が紐部材等により容易に計測
可能であることから管理的に簡易で分かり易いものとな
る。加えて、使用した遮水シートについてその貫入施工
履歴を記録保存することも可能なことから、この種の遮
水シート工法の信頼性を向上できる。第2に、先行ピー
スの移動量や軌跡が設計値からズレたときは、後続遮水
シートの貫入操作をその時点で止めて対処可能になるこ
とから、異常事態をより速い段階で検知して、無駄な貫
入操作をなくすことができる。このため、施工効率又は
工期はより的確に維持される。第3に、先行ピースの移
動量や軌跡は、例えば、請求項2の如く巻取ドラムから
引き出されて、その引出し先端を先行ピースに連結した
紐部材を用いて、当該紐部材の送り出し量により計測す
ることも可能である。このため、管理的には、操作が簡
易であり施工効率を悪化することもなく、しかも先行ピ
ースを回収して繰り返し利用することも容易なため合理
的な管理及び施工が行える。
As described above, the construction management method in the water-blocking sheet construction method according to the present invention has the following advantages. Firstly, it is objective because it uses the phenomenon that the preceding piece is pushed down by the succeeding impermeable sheet and descends.
Since the movement amount and the locus of the preceding piece can be easily measured by a string member or the like, it becomes easy and easy to understand in terms of management. In addition, since it is possible to record and store the intrusion construction history of the used waterproof sheet, it is possible to improve the reliability of this type of waterproof sheet construction method. Secondly, when the movement amount or trajectory of the preceding piece deviates from the design value, the penetrating operation of the subsequent water blocking sheet can be stopped at that point, and it becomes possible to deal with it, so an abnormal situation can be detected at a faster stage. It is possible to eliminate useless penetrating operation. Therefore, the construction efficiency or the construction period can be maintained more accurately. Thirdly, the movement amount and the locus of the preceding piece are determined by, for example, using a cord member that is pulled out from the winding drum and has its leading end connected to the preceding piece, according to the feeding amount of the cord member. It is also possible to measure. Therefore, in terms of management, the operation is simple, the construction efficiency is not deteriorated, and the preceding pieces are easily collected and repeatedly used, so that rational management and construction can be performed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明方法の原理を模式的に示す構成図であ
る。
FIG. 1 is a configuration diagram schematically showing the principle of the method of the present invention.

【図2】図1のA−A線断面図である。FIG. 2 is a sectional view taken along the line AA of FIG.

【図3】本発明で使用する先行ピース例を遮水シートと
共に示す図である。
FIG. 3 is a view showing an example of a preceding piece used in the present invention together with a water blocking sheet.

【図4】前記先行ピースの他の例を示す模式断面図であ
る。
FIG. 4 is a schematic cross-sectional view showing another example of the preceding piece.

【図5】本発明施工管理方法をグラフ化した場合の一例
を示す図である。
FIG. 5 is a diagram showing an example of a case where the construction management method of the present invention is graphed.

【図6】従来遮水シート工法の異常事態を説明するため
の模式図である。
FIG. 6 is a schematic diagram for explaining an abnormal situation of a conventional water-blocking sheet construction method.

【符号の説明】[Explanation of symbols]

1Aは既設遮水シート(遮水シート) 1Bは後続遮水シート(遮水シート) 2は雄部 3は雌部 6,7は先行ピース 9は紐部材 10は回転ドラム 1A is an existing impermeable sheet (impermeable sheet) 1B is the subsequent impermeable sheet (impermeable sheet) 2 is male 3 is the female part 6 and 7 are leading pieces 9 is a string member 10 is a rotating drum

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 5/20 102 E02D 19/12 ─────────────────────────────────────────────────── ─── Continuation of the front page (58) Fields surveyed (Int.Cl. 7 , DB name) E02D 5/20 102 E02D 19/12

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 遮水シートが長手方向両側に雄部と雌部
の一方をそれぞれ有し、地中縦方向に貫入された既設の
遮水シートに対し、後続の遮水シートを互いに隣接する
雄部と雌部を係合しつつ貫入し接続する場合の施工管理
方法であって、 前記後続の遮水シートを前記既設の遮水シートに係合す
るに際し、小型の先行ピースを予め既設の遮水シート側
に係合しておき、後続の遮水シートの貫入により押され
て既設の遮水シートに沿って下降される先行ピースの移
動量を計測することにより、既設の遮水シートに対する
後続の遮水シートの係合状態が正常か、否かを判断す
る、ことを特徴とする遮水シート工法における施工管理
方法。
1. A water-impervious sheet has one of a male part and a female part on both sides in the longitudinal direction, and a succeeding impermeable sheet is adjacent to an existing water-impervious sheet penetrating in the longitudinal direction of the ground. It is a construction management method in the case of penetrating and connecting while engaging a male part and a female part, in engaging the subsequent water blocking sheet with the existing water blocking sheet, a small preceding piece is previously installed. By measuring the amount of movement of the preceding piece that has been engaged with the water-blocking sheet side and is pushed down by the penetration of the subsequent water-blocking sheet and lowered along the existing water-blocking sheet, A construction management method in a water-blocking sheet construction method, comprising determining whether or not a subsequent water-blocking sheet is engaged normally.
【請求項2】 前記先行ピースの移動量が、巻取ドラム
から引き出されて、その引出し先端を先行ピースに連結
した紐部材を用いて、当該紐部材の送り出し量により計
測される請求項1に記載の遮水シートの施工管理方法。
2. The moving amount of the preceding piece is measured by the feeding amount of the cord member by using a cord member which is pulled out from a winding drum and whose leading end is connected to the preceding piece. Construction control method for the water-blocking sheet described.
【請求項3】 前記先行ピースが、既設の遮水シートの
下端から押し出された後、前記巻取ドラムを介し紐部材
を巻き上げることにより回収される請求項2に記載の遮
水シートの施工管理方法。
3. The construction management of the water blocking sheet according to claim 2, wherein the preceding piece is recovered by being pushed out from a lower end of an existing water blocking sheet and then wound up with a string member through the winding drum. Method.
JP30992898A 1998-10-30 1998-10-30 Construction management method in the impermeable sheet method Expired - Fee Related JP3478480B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30992898A JP3478480B2 (en) 1998-10-30 1998-10-30 Construction management method in the impermeable sheet method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30992898A JP3478480B2 (en) 1998-10-30 1998-10-30 Construction management method in the impermeable sheet method

Publications (2)

Publication Number Publication Date
JP2000136529A JP2000136529A (en) 2000-05-16
JP3478480B2 true JP3478480B2 (en) 2003-12-15

Family

ID=17999040

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30992898A Expired - Fee Related JP3478480B2 (en) 1998-10-30 1998-10-30 Construction management method in the impermeable sheet method

Country Status (1)

Country Link
JP (1) JP3478480B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4607381B2 (en) * 2001-07-23 2011-01-05 太陽工業株式会社 Vertical impermeable sheet and method for inspecting impermeable wall constructed using the same

Also Published As

Publication number Publication date
JP2000136529A (en) 2000-05-16

Similar Documents

Publication Publication Date Title
US3282057A (en) Underground line and method of installing same
KR100878323B1 (en) Monitoring device of cavity in Tunnel lining concrete
JP5018324B2 (en) Water leakage monitoring system for water shielding material and water shielding wall
JP2010163748A (en) Earth retaining wall load testing method
JP2017078290A (en) Cast-in-place pile construction method
CN216787247U (en) Force measurement display device of ground anchor pile
JP3478480B2 (en) Construction management method in the impermeable sheet method
CN216552110U (en) Water conservancy construction deep basal pit surveys equipment
JPH03152420A (en) Method and apparatus for measuring movement of ground
JP3675164B2 (en) Support ground position detection method and support ground position detection device for ground improvement machine
KR101742785B1 (en) Apparatus for indicating and closing thermal hole, and method for constructing thermal hole
CN217174960U (en) Embedded measuring device for monitoring horizontal displacement at different depths
JP2005257602A (en) Instrument for measuring varying borehole diameter
JP2005226412A (en) Sediment gathering device and ground density measuring method
Chu et al. Prefabricated vertical drains
JPH0347683B2 (en)
JPS61246417A (en) Monitoring/management device for paper drain driving work
JP3139706B2 (en) Drain casting method and device
JP2001329558A (en) Inspection method for foundation pile
CN216766021U (en) Monitoring auxiliary device suitable for vibroflotation gravel pile
JP7337715B2 (en) How to install steel pipes in the ground
CN219674996U (en) Construction engineering supervision foundation ditch measuring device
CN116752584A (en) Device and method for testing internal force of steel pipe nested pile of earth-rock binary stratum
JPH01229907A (en) Sinkage meter
CN118243038A (en) Multi-point displacement meter

Legal Events

Date Code Title Description
S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091003

Year of fee payment: 6

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091003

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091003

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091003

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101003

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101003

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111003

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111003

Year of fee payment: 8

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111003

Year of fee payment: 8

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111003

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121003

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121003

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121003

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131003

Year of fee payment: 10

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees