JP3451050B2 - Construction method for underground structures - Google Patents

Construction method for underground structures

Info

Publication number
JP3451050B2
JP3451050B2 JP2000014832A JP2000014832A JP3451050B2 JP 3451050 B2 JP3451050 B2 JP 3451050B2 JP 2000014832 A JP2000014832 A JP 2000014832A JP 2000014832 A JP2000014832 A JP 2000014832A JP 3451050 B2 JP3451050 B2 JP 3451050B2
Authority
JP
Japan
Prior art keywords
water
underground
drainage
construction
submersible pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000014832A
Other languages
Japanese (ja)
Other versions
JP2001207457A (en
Inventor
和裕 浦田
Original Assignee
和裕 浦田
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 和裕 浦田 filed Critical 和裕 浦田
Priority to JP2000014832A priority Critical patent/JP3451050B2/en
Publication of JP2001207457A publication Critical patent/JP2001207457A/en
Application granted granted Critical
Publication of JP3451050B2 publication Critical patent/JP3451050B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、地下構築物の施工
現場のかま場用排水ボックス用いて行う地下構築物の
施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure, which is carried out by using a drainage box for a kamaba at a construction site for the underground structure.

【0002】[0002]

【従来の技術】周知の通り、地下室等の地下構築物の構
築には、地下水の排水対策が必須となっている。通常の
地下構築物の施工現場、例えば地下室構築の施工現場に
おいては、まず基盤となる地下スラブの構築が行われ
る。この場合にも地盤の掘削作業中にも排水を行うが、
鋼矢板で囲まれた内側の掘削が終了した後は、図5
(a)に示すように、地盤の底地面の鋼矢板61沿いに
排水溝62を設け、これで集められた地下水を排水ポン
プ63で地表に排水している。
2. Description of the Related Art As is well known, groundwater drainage measures are essential for the construction of underground structures such as basements. In an ordinary construction site of an underground construction, for example, a construction site of a basement construction, an underground slab as a base is first constructed. In this case as well, drainage is performed during ground excavation work,
After the excavation inside the steel sheet pile is completed,
As shown in (a), a drainage groove 62 is provided along the steel sheet pile 61 on the bottom ground of the ground, and the groundwater collected by this is drained to the surface by the drainage pump 63.

【0003】地中から排水溝62に流れ込んだ地下水は
誘導水路64を通って要所に設けられたかま場65に集
められ、ここに設置された上記の排水ポンプ63によっ
て排水するようにしている。
Groundwater flowing into the drainage ditch 62 from the ground is collected through a guide water channel 64 to a kamaba 65 provided at a key point, and is drained by the drainage pump 63 installed here. .

【0004】図5(b)に示すように、排水溝62及び
誘導水路64はこの上に地下スラブ60が構築されるた
め、配水管又は側溝に蓋をしたものを連続するように埋
設している。これらの排水溝62及び誘導水路64の随
所には地下水が流入する透孔を設けたものを採用するこ
とにより底地面に流れ込んだり、湧き出した地下水を集
められるようにしている。
As shown in FIG. 5 (b), since the underground slab 60 is constructed on the drainage channel 62 and the guiding channel 64, the drainage channel or the gutter with the lid is continuously buried. There is. The drainage groove 62 and the guiding water channel 64 are provided with through holes through which groundwater flows in, so that the groundwater that flows into the bottom ground or springs out can be collected.

【0005】また、鋼矢板61の内側には、鋼矢板のす
き間から流れ込む地下水を地下スラブや地下壁へ流れ込
まずに、排水溝62に集められるようにしたへちま板6
6を設けている。
Further, inside the steel sheet pile 61, the ground plate 6 is arranged so that the groundwater flowing into the gap of the steel sheet pile can be collected in the drainage ditch 62 without flowing into the underground slab or the underground wall.
6 is provided.

【0006】地下構築物の基盤となる地下スラブ60の
大まかな施工要領は、底地面67の随所にかま場65及
びこのかま場と排水溝62を結ぶ誘導水路64を設け、
かま場の上方には排水ホースの通路を設けるための型枠
68を設けている。底地面67には図示していないが防
水シートを敷き、その上に割栗石層69を敷き、その上
に捨てコンクリート層70を形成し、さらにその上に強
度的にも防水的にも優れた性質を有する耐圧コンクリー
ト層71を形成している。
The rough construction procedure of the underground slab 60, which is the base of the underground structure, is to install a kamaba 65 everywhere on the bottom ground 67 and a guiding water channel 64 connecting the kamaba and the drainage groove 62.
A mold 68 for providing a passage for the drain hose is provided above the kamaba. Although not shown in the drawing, a waterproof sheet is laid on the bottom ground 67, and a split stone layer 69 is laid on it, and a discarded concrete layer 70 is formed on it, which is excellent in strength and waterproofness. A pressure resistant concrete layer 71 having properties is formed.

【0007】地下スラブ60ができ上がったら、次に地
下壁72を設け、最後に型枠68を除去し、かま場65
及びその上にできた空胴部を埋め、耐圧コンクリート層
71に生コンクリートを補充して塞ぎ、最後にその表面
にモルタル層73を形成している。
When the underground slab 60 is completed, an underground wall 72 is provided next, and finally the form 68 is removed, and the kamaba 65
Further, the cavities formed above are filled up, and the pressure-resistant concrete layer 71 is supplemented with fresh concrete to close it, and finally the mortar layer 73 is formed on the surface thereof.

【0008】なお、上記の施工中は絶えず地下水がかま
場65内に流れ込むために、かま場の上にできた空胴部
内にモルタルなどの止水材の充填終了まで排水作業を続
けていなければならない。したがって止水材の充填中に
も排水ポンプ63を運転させなければならず、したがっ
て排水ポンプを除去できないので、このポンプは結局埋
め殺しにしている。
Since groundwater constantly flows into the sickle 65 during the above construction, the drainage work must be continued until the filling of the water blocking material such as mortar into the cavity formed above the sickle. I won't. Therefore, the drainage pump 63 must be operated even during the filling of the water blocking material, and therefore the drainage pump cannot be removed, so that this pump is eventually buried.

【0009】[0009]

【発明が解決しようとする課題】上記従来例におけるか
ま場65は、誘導水路64と常に連通状態となっている
ため、地下スラブの耐圧コンクリート層71の形成後も
なお、かま場65から地下水が逆流して地下スラブ60
の上面へ溢れ出すおそれが生じる。したがって、型枠6
8を除去後も排水ポンプ63を運転していなければなら
ない。
Since the kamaba 65 in the above-mentioned conventional example is always in communication with the guiding water channel 64, groundwater is still discharged from the kamaba 65 even after the pressure resistant concrete layer 71 of the underground slab is formed. Backflow and underground slab 60
May overflow to the upper surface of the. Therefore, the formwork 6
The drainage pump 63 must be operating even after removing 8.

【0010】このため、型枠除去後の空胴部内にモルタ
ルなどの止水材を充填するまでポンプを停止できないの
で、上記したように結局は高価なポンプを埋め殺しにし
ている。ポンプの埋め殺しによる経済的損失を少なくす
るために、性能の低い安価なポンプを採用すれば、施工
中の排水が不十分となり、コンクリートの品質低下を生
じさせるため、安価なポンプを設置することにも限度が
ある。
For this reason, the pump cannot be stopped until the cavities after the mold is removed are filled with a water blocking material such as mortar, so that the expensive pump is eventually buried as described above. If an inexpensive pump with low performance is adopted in order to reduce the economic loss due to the burying of the pump, the drainage during construction will be insufficient and the quality of the concrete will deteriorate, so an inexpensive pump should be installed. There is also a limit.

【0011】また、かま場65の上方に設けられる型枠
68は、地下スラブ60との境界における防水が不十分
であると、かま場から逆流した地下水が打設中の捨てコ
ンクリート層70や耐圧コンクリート層71中へ進入し
て強度の劣る水増しコンクリートにしてしまうおそれが
ある。
Further, if the formwork 68 provided above the kamaba 65 is insufficiently waterproof at the boundary with the underground slab 60, the groundwater that has flowed back from the kamaba will be discarded and the pressure-resistant concrete layer 70 will be used during pouring. There is a risk that it may enter the concrete layer 71 and become inflated concrete having poor strength.

【0012】さらにまた、従来技術においては、かま場
65の空洞部及び型枠68を除去した後の空胴部に充填
する止水材の防水性が完全なものではない場合には、地
下スラブ上面へ地下水が上昇したりする問題もある。
Furthermore, in the prior art, when the waterproofing material for filling the cavity portion of the rotary hook 65 and the cavity after removing the form 68 is not completely waterproof, the underground slab is used. There is also a problem that groundwater rises to the upper surface.

【0013】そこで本発明の目的は、第1に地下スラブ
の構築中における打設中のコンクリート中への地下水の
進入を防止することによりコンクリートの品質低下を防
止すること。第2に高価な排水用水中ポンプの回収を可
能にすること。第3に地下構築物の施工完了後における
かま場から地下スラブ上面への地下水の流失を完全に防
止することにある。
Therefore, firstly, the purpose of the present invention is to prevent the deterioration of the quality of concrete by preventing the ingress of groundwater into the concrete being poured during the construction of the underground slab. Second, to enable the recovery of expensive submersible pumps for drainage. Thirdly, it is to completely prevent the groundwater from spilling from the stove to the upper surface of the underground slab after the construction of the underground structure is completed.

【0014】[0014]

【課題を解決するための手段】上記の目的を達成するた
めに、本発明は以下の手段を採用してある。地下構築物
の施工現場のかま場に以下の要素を備えた排水ボックス
を用いて完全な排水状態の下で地下構築物の施工を可能
としてある。ここで排水ボックスとは、従来技術におけ
るかま場に設けられていた排水桝に代えて、かま場に埋
設することにより地下水の排水を促進する箱体であり、
以下の要素を備えたものである。
In order to achieve the above object, the present invention adopts the following means. It is possible to construct an underground structure under a complete drainage condition by using a drainage box equipped with the following elements in the construction site of the underground structure. Here, the drainage box is a box body that promotes the drainage of groundwater by burying it in the sickle, instead of the drainage basin provided in the sickle in the prior art,
It has the following elements.

【0015】上記の排水ボックスは、水中ポンプを設置
可能な胴部、この胴部の上端部に形成してある筒部に排
水用の水中ポンプを出し入れ可能に設けてある上部開
口、地下水をかま場に誘導するために地下構築物の施工
現場に設けられる誘導水路と接続可能に上記の胴部の周
囲に設けてある複数の導水口、及びこれらの導水口を内
部から開閉可能な止水栓を備えたものである。なお、こ
の排水ボックスは予め工場で製造し、これを施工現場に
搬入して設置するようにしたものである。
The drain box described above is provided with a body portion on which a submersible pump can be installed, an upper opening provided for allowing a submersible pump for drainage to be taken in and out of a tubular portion formed at an upper end portion of the body portion, and ground water. In order to guide to the site, a plurality of water inlets provided around the above-mentioned trunk so that it can be connected to the water canal provided in the construction site of the underground structure, and a water stopper that can open and close these water inlets from the inside Be prepared. In addition, this drainage box is manufactured in advance in a factory, and is carried into a construction site for installation.

【0016】上記の排水ボックスを採用することによ
り、地下構築物の施工現場に設けられるかま場の設置が
容易かつかま場を埋め戻した後の地下水の漏水を完全に
防止することができる。また、水中ポンプを回収可能と
することにより施工コストの引き下げを図ることができ
る。
By adopting the above drainage box, it is possible to easily install the kettle provided at the construction site of the underground construction and to completely prevent leakage of ground water after backfilling the kettle. Further, by making the submersible pump recoverable, it is possible to reduce the construction cost.

【0017】そこで、本発明に係る上記の排水ボックス
を用いた地下構築物の施工方法は、以下の各工程を採用
することにより施工中の排水が完全に行われるようにし
てある。工場で製造された排水ボックスを地下構築物の
施工現場の随所に設けられるかま場に埋設して上記開口
の上方に排水ホースを通すための型枠を設ける第1工程
と、上記の導水口と施工現場の地下水をかま場に誘導す
るために設けられる誘導水路とを接続するとともに、排
水ボックスの胴部内に水中ポンプを設置する第2工程
と、排水ボックス内に導入された地下水を水中ポンプで
排水しながら地下スラブの施工を進める第3工程と、地
下スラブを構築した後に導水口を閉めて排水ボックス内
への地下水の進入を停止させ、排水ボックス内に収納さ
れている水中ポンプを回収し、型枠を除去する第4工程
と、上記の型枠を除去し、排水ボックスの内部に埋め戻
し材を充填し、筒部の上端部の周囲を第1の止水材で取
り囲む第5工程とを含んだものとしてある。
Therefore, the method for constructing an underground structure using the above drainage box according to the present invention is designed so that the drainage during construction can be completely performed by adopting the following steps. The first step of embedding the drainage box manufactured in the factory in the kamaba which is provided everywhere in the construction site of the underground structure and providing the formwork for passing the drainage hose above the opening, and the above-mentioned water guide port and construction The second step of connecting the submersible pump in the body of the drainage box and connecting the guidewater channel provided to guide the groundwater at the site to the stove, and draining the groundwater introduced in the drainage box with the submersible pump. While constructing the underground slab, the third step is to build the underground slab and then close the water inlet to stop the entry of groundwater into the drainage box and collect the submersible pump stored in the drainage box. A fourth step of removing the formwork, a fifth step of removing the formwork, filling the inside of the drainage box with a backfill material, and surrounding the upper end of the tubular portion with a first water blocking material. Including There as.

【0018】上記の施工方法において、第3工程は型枠
で囲まれている上部開口の周囲を第2の止水材で囲む工
程を含んだものとすることにより型枠の周囲からの地下
水の漏水を完全に防止可能としてある。
In the above construction method, the third step includes the step of surrounding the upper opening surrounded by the formwork with the second waterproof material, whereby the groundwater from the periphery of the formwork is included. It is possible to completely prevent water leakage.

【0019】また、上記の施工方法において、第5工程
における第1の止水材としては膨潤性を有するベントナ
イトを採用することにより、かま場からの地下水の漏水
を完全に防止可能としてある。
[0019] In the above construction method, the first water stopping material in the fifth step by employing a bentonite with swelling properties, some water leakage of groundwater from kiln field as fully prevented.

【0020】[0020]

【発明の実施の形態】次に本発明の実施の形態例につい
て図面を参照して説明する。初めに図1,2を参照して
排水ボックスについて説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Next, embodiments of the present invention will be described with reference to the drawings. First, the drainage box will be described with reference to FIGS.

【0021】排水ボックス1は、外観上は直方体の容器
状の胴部2と、この胴部の上部に設けられた直方体状の
筒部3とからなる。胴部2及び筒部3はいずれも鋼板を
溶接により結合して組み立てたいわゆる板金製品からな
り、筒部の内側の胴部の上部は切欠することにより上部
開口4としてある。胴部2内は水中ポンプ5を収納可能
な大きさとしてあり、上記した上部開口4はこのポンプ
を出し入れ可能な大きさとしてある。
The drainage box 1 is composed of a container-shaped body 2 having a rectangular parallelepiped shape in appearance and a rectangular parallelepiped cylinder 3 provided on the upper portion of the body. Both the body 2 and the cylinder 3 are made of so-called sheet metal products assembled by welding steel plates together, and the upper part of the body inside the cylinder is notched to form an upper opening 4. The body 2 has a size capable of accommodating the submersible pump 5, and the above-described upper opening 4 has a size capable of taking in and out the pump.

【0022】また、胴部2の各辺の上部にはそれぞれ円
形の導水口6が設けてある(2か所だけ図示)。導水口
6は後述の誘導水路から地下水を排水ボックス1内に導
水する入口孔であり、それぞれ胴部内で円筒状のスリー
ブ7の基部に取り囲まれている。スリーブ7は鋼管の基
部を胴部2の内側に溶接により固着してあり、先端部に
はおねじ部7aが刻んである。
Further, a circular water inlet 6 is provided on the upper portion of each side of the body portion 2 (only two locations are shown). The water guide port 6 is an inlet hole for introducing ground water into the drainage box 1 from a guide water channel described later, and is surrounded by the base of a cylindrical sleeve 7 in the body. The sleeve 7 has a base of a steel pipe fixed to the inside of the body 2 by welding, and a male screw portion 7a is carved at the tip.

【0023】このスリーブ7の先端には、止水栓8を被
せることにより、導水口6からの地下水の進入を停止可
能としてある。止水栓8は鋼製の袋ナットからなり、開
口側に刻んであるめねじ部8aはスリーブのおねじ部7
aと螺合可能としてある。なお、この導水口6は、施工
現場の実状に応じて個数を定められる。無用な導水口の
設置はコストアップ及び漏水の原因となるので、実状に
対応した導水口数の決定を行うべきである。
The leading end of the sleeve 7 is covered with a water stop plug 8 so that the entry of groundwater from the water inlet 6 can be stopped. The water stop plug 8 is made of a steel cap nut, and the female screw portion 8a engraved on the opening side is the male screw portion 7 of the sleeve.
It can be screwed into a. The number of the water guide ports 6 is determined according to the actual condition of the construction site. Since the installation of unnecessary water inlets causes cost increase and water leakage, it is necessary to determine the number of water inlets corresponding to the actual situation.

【0024】次に図3,4を参照して上記の排水ボック
スを採用した地下構築物の施工方法について地下室の施
工現場を例として説明する。
Next, with reference to FIGS. 3 and 4, a construction method of an underground construction employing the above drainage box will be described by taking a construction site of a basement as an example.

【0025】図3は、上記した排水ボックス1を用いた
地下室の施工の工程状態を示すものである。この図では
地下室の最下階に位置する地下スラブ11の構築を終了
した状態になっているが、以下の説明においては、地盤
の掘下げから地下スラブ及び地下壁の完成までの工程に
ついて地下水の排水を骨子にして順次説明する。
FIG. 3 shows a process state of the construction of the basement using the drainage box 1 described above. In this figure, the construction of the underground slab 11 located at the lowest floor of the basement is completed, but in the following explanation, the process from the excavation of the ground to the completion of the underground slab and the underground wall will be explained. Will be explained in order.

【0026】まず、従来技術と同じく地下構築物の建設
地の周囲に鋼矢板12を打ち込み、その内側を掘削す
る。次に底地面に鋼矢板の内側に沿って地下水の排水溝
13を設け、さらに随所に誘導水路14及びかま場15
となる凹部を設ける。
First, as in the prior art, the steel sheet pile 12 is driven around the construction site of the underground structure and the inside thereof is excavated. Next, a groundwater drainage groove 13 is provided on the bottom ground along the inside of the steel sheet pile, and further, a guide water channel 14 and a kamaba 15 are provided everywhere.
A recess is provided.

【0027】また、鋼矢板12の内側には、地下掘削面
からの漏水を鋼矢板面に沿って下方へ集めるようにする
へちま板16を設けるようにする。へちま板16は下部
が鋼矢板12と排水溝13との間に位置し、上部は後述
の耐圧コンクリート層の上面とほぼ一致する高さになる
ように設ける。
Further, inside the steel sheet pile 12, a hump board 16 is provided to collect water leaking from the underground excavation surface downward along the steel sheet pile surface. The lower part of the chevron plate 16 is located between the steel sheet pile 12 and the drainage groove 13, and the upper part thereof is provided so as to have a height substantially matching the upper surface of a pressure-resistant concrete layer described later.

【0028】かま場15となる凹部には、上記した排水
ボックス1を導水口6が誘導水路14と接続可能な深さ
になるように埋設する。なおこの排水路13及び誘導水
路14には、随所に地下水の進入口が設けてあり、地中
の地下水を集めて、排水ボックス1内へ導入可能として
ある。
The drainage box 1 described above is embedded in the concave portion which will be the kettle 15 so that the water inlet 6 can be connected to the guide water passage 14. It should be noted that the drainage channel 13 and the guiding water channel 14 are provided with entrances for groundwater everywhere so that underground water can be collected and introduced into the drainage box 1.

【0029】次に排水ボックス1の筒部3の周囲にベン
トナイトシートからなる止水部材17を貼付し、さらに
その周囲を取り囲むように型枠18を設ける(第1工
程)。止水部材の存在は、筒部3の外周部と型枠18と
の間からの漏水を防止する役目を果すものである。型枠
18は排水用水中ポンプ5を出し入れ可能にするととも
に、排水ホース9を通す役割を果すものである。型枠1
8の設置は、後述の割栗石層19の敷設後であってもよ
い。止水部材17は排水ボックス1と型枠18との間か
らの漏水を防止する働きをする。型枠18の上端は後述
の耐圧コンクリート層の上面よりも上に位置する高さと
なるように設置する。
Next, a water stop member 17 made of a bentonite sheet is attached around the cylindrical portion 3 of the drainage box 1, and a mold 18 is provided so as to surround the periphery (first step). The presence of the water blocking member serves to prevent water leakage between the outer peripheral portion of the cylindrical portion 3 and the mold 18. The formwork 18 allows the submersible pump 5 for drainage to be taken in and out, and also serves to pass the drainage hose 9. Formwork 1
The setting of 8 may be performed after the laying of the split stone layer 19 described later. The water blocking member 17 functions to prevent water leakage between the drainage box 1 and the form 18. The upper end of the mold 18 is installed so as to be located above the upper surface of the pressure-resistant concrete layer described later.

【0030】次に、排水ボックス1内に水中ポンプ5を
設置し、止水栓8を取り外して導水口6を開けて地下水
この排水ボックス内へ集める。集められた地下水は
ホース9を介して地上へ排水可能な状態とする(第2
工程)。なお、水中ポンプ5はベース5a上に載置した
ストレーナ5bを介して地下水を吸い込み可能となるよ
うに設ける。
[0030] Next, the water pump 5 installed in the drainage box 1, collect open the water introduction port 6, remove the stop cock 8 the underground water to the drainage box. The collected groundwater is drained
The water can be drained to the ground via the water hose 9 (second
Process). The submersible pump 5 is provided so that ground water can be sucked in through a strainer 5b placed on the base 5a.

【0031】次に誘導水路14を含む底地面上に防水シ
ート(図示略)を敷き、その上に中粒の玉石を敷き詰め
てなる割栗石層19を形成する。この割栗石層19の上
面は排水ボックス1の胴部2の上端とほぼ一致する高さ
とする。
Next, a waterproof sheet (not shown) is laid on the bottom surface including the guiding water channel 14, and a crushed stone layer 19 is formed by laying medium-sized boulders on it. The upper surface of the split stone layer 19 has a height that substantially coincides with the upper end of the body portion 2 of the drainage box 1.

【0032】次に排水ボックス1の胴部2の上面と筒部
3の中間位置とを結ぶ型枠18の周囲に、ベントナイト
粉末をほぼ三角形断面状に塗り付けて止水部20を形成
する。この止水部20はモルタルなどで形成してもよ
い。
Next, bentonite powder is applied in a substantially triangular cross-section around the form 18 connecting the upper surface of the body 2 of the drainage box 1 and the intermediate position of the tube 3 to form the water stop 20. The water stop portion 20 may be formed of mortar or the like.

【0033】次に割栗石層19の上面に防水シートを敷
き、その上に排水ボックス1の上端部とほぼ一致する高
さ(約160mm)まで捨てコンクリート層21を形成
する。捨てコンクリート層21が固まったら次にへちま
板16の内側に沿ってL字形断面に形成してなる防水板
22を配置し、さらにその内側に防水シート23を配置
する。防水シート23は、止水板22が設けてある範囲
ではこれに二重に重なり、へちま板16の上方の範囲で
は鋼矢板12と平行になるように設ける。
Next, a waterproof sheet is laid on the upper surface of the split stone layer 19, and a discarded concrete layer 21 is formed on the waterproof sheet up to a height (about 160 mm) which is substantially coincident with the upper end of the drainage box 1. After the discarded concrete layer 21 is solidified, a waterproof plate 22 formed in an L-shaped cross section is arranged along the inner side of the hump plate 16, and a waterproof sheet 23 is further arranged inside thereof. The waterproof sheet 23 is provided so as to be double overlapped with the water blocking plate 22 in the range where the water blocking plate 22 is provided, and to be parallel to the steel sheet pile 12 in the range above the hood plate 16.

【0034】こうして、捨てコンクリート層21の上方
が防水シート23によって覆われた状態としたら、次に
その上に耐圧コンクリート層24を打設する。耐圧コン
クリート層24は、厚さをほぼ300mmとし、型枠1
8の部分を除いて地下の底地面全体に打設する(第3工
程)。
In this way, when the upper part of the discarded concrete layer 21 is covered with the waterproof sheet 23, the pressure resistant concrete layer 24 is then placed thereon. The pressure-resistant concrete layer 24 has a thickness of approximately 300 mm, and
It is cast on the whole of the underground floor except the part 8 (third step).

【0035】ここで鋼矢板12に沿った地下スラブ11
上に地下壁25を構築する。地下壁25は鋼矢板12の
内側に上記の防水シート23を介在させて地下水が打設
中のコンクリート中に流れ込まない状態にして行われ
る。
Here, the underground slab 11 along the steel sheet pile 12
Build the underground wall 25 on top. The underground wall 25 is formed by interposing the waterproof sheet 23 inside the steel sheet pile 12 so that ground water does not flow into the concrete being poured.

【0036】次に水中ポンプ5による排水を行っている
状態で地下スラブ11の上面側から排水ボックス1内に
手を入れて、すべてのスリーブ7にキャップ(止水栓)
8を被せて導水口6を閉め、誘導水路14からの地下水
の進入を停止させる。この後間もなく排水ボックス1内
に残っている地下水はすべて水中ポンプにより排水され
る。次に水中ポンプ5、ストレーナ5b及びホース9を
引き上げて回収するとともに型枠18を除去する(第4
工程)。
Next, while draining water by the submersible pump 5, put a hand into the drainage box 1 from the upper surface side of the underground slab 11 to cap all the sleeves 7 (stop cock).
8 is closed and the water guide port 6 is closed, and the entry of groundwater from the guide water channel 14 is stopped. Shortly after this, all the groundwater remaining in the drainage box 1 is drained by the submersible pump. Next, the submersible pump 5, strainer 5b, and hose 9 are pulled up and collected, and the form 18 is removed (fourth).
Process).

【0037】次に図4に示すように、空になった排水ボ
ックス1内に土砂やがれきなどの埋め戻し材26を充填
して突き固める。この埋め戻し材26の充填量は、筒部
2の上端部近傍までとする。次に筒部3の内部に形成さ
れた空胴部内にベントナイト粉末からなる止水材27を
入れて、筒部3の周囲や上方を取り囲み、排水ボックス
1からの地下水の漏水防止処理を行う(第5工程)。
Next, as shown in FIG. 4, a backfill material 26 such as earth and sand or debris is filled in the empty drainage box 1 and tamped. The filling amount of the backfill material 26 is up to the vicinity of the upper end portion of the tubular portion 2. Next, a water blocking material 27 made of bentonite powder is put in the cavity formed inside the tubular part 3 to surround the perimeter and the upper part of the tubular part 3 to prevent leakage of groundwater from the drain box 1 ( Fifth step).

【0038】次に水中ポンプの上方に取り残された空胴
部に生コンクリートを詰めて固化させることにより充填
コンクリート部28を設ける。なお、耐圧コンクリート
層24、充填コンクリート部28の各上面には、表面モ
ルタル層29を形成するため、排水ボックス1の上方に
取り残された空胴部に充填した充填コンクリート部28
との表面境界は地下スラブ11の表面には表われない。
Next, the filling concrete portion 28 is provided by filling the cavities left above the submersible pump with solid concrete and solidifying it. Since the surface mortar layer 29 is formed on each upper surface of the pressure-resistant concrete layer 24 and the filled concrete portion 28, the filled concrete portion 28 filled in the cavity left above the drainage box 1 is filled.
The surface boundary between and does not appear on the surface of the underground slab 11.

【0039】以上説明した施工法は一例に過ぎず、実際
の施工例は多数存在するが、本発明は、第1に排水ボッ
クス1をかま場15に据え付けることにより排水構造の
設置が容易化すること。第2に型枠を除去した後に止水
栓8を閉めることにより排水ボックスへの地下水の流入
を停止可能であること。第3に型枠除去後に水中ポンプ
を回収可能であること。第4に水中ポンプ回収後のかま
場ボックス1内に埋め戻し材を充填後に、筒部の開口4
の周囲にベントナイトを配置することにより耐圧コンク
リート層のすき間から地下水の漏水を防止可能としてあ
ることに特徴を有するものである。
Although the construction method described above is merely an example and there are many actual construction examples, the present invention makes it easy to install the drainage structure by first installing the drainage box 1 on the stove 15. thing. Secondly, it is possible to stop the inflow of groundwater into the drain box by closing the water stopcock 8 after removing the formwork. Third, the submersible pump can be collected after removing the formwork. Fourthly, after filling the backfill material into the kamaba box 1 after collecting the submersible pump, the opening 4
By arranging bentonite around the ground, it is possible to prevent groundwater from leaking from the gap of the pressure-resistant concrete layer.

【0040】この例では排水ボックスの形状を直方体と
してあるが、形状はこれに拘わるものではなく、材質も
鋼板の他、合成樹脂その他の物質で構成することも可能
である。また、止水栓はキャップ状のものとして説明し
てあるが、これを棒状とし、止水栓におねじを刻み、ス
リーブの開口部側にめねじを刻むようにしたものとして
もよい。
In this example, the shape of the drainage box is a rectangular parallelepiped, but the shape is not limited to this, and the material may be steel plate, synthetic resin or other substance. Further, although the water stopcock is described as a cap-like one, it may be rod-like, and the water stopcock may be engraved with a screw and the female thread is engraved on the opening side of the sleeve.

【0041】また、型枠の設置と割栗石層及び捨てコン
クリート層の形成との工程の前後関係は上記の説明とは
逆になっても本発明の効果に影響を及ぼさない。
Further, the order of the steps of installing the formwork and forming the split stone layer and the discarded concrete layer does not affect the effect of the present invention even if it is contrary to the above description.

【0042】[0042]

【発明の効果】本発明における排水ボックスを採用すれ
ば、地下構築物の施工現場におけるかま場の設置が容易
となり、しかも地下水の漏水のない施工が可能となる。
また、排水ボックスの導水口を開閉自在としてあるの
で、所定の施工時点でこれを閉じることにより排水ボッ
クス内の水を排除状態とすることができる。したがって
導水口を閉じた後に水中ポンプの回収が可能となる。こ
れとともに、ポンプ回収後に埋め戻し材を充填しても、
下から水位が上昇してくることもなくなるので余裕をも
ってかま場の埋め戻し作業をすることができる。
The use of the drainage box according to the present invention makes it easy to install a rotary hook at a construction site of an underground structure, and also enables construction without leakage of groundwater.
Further, since the water guide port of the drainage box is openable and closable, the water in the drainage box can be eliminated by closing it at a predetermined construction point. Therefore, the submersible pump can be recovered after closing the water inlet. Along with this, even if the backfill material is filled after the pump is collected,
Since the water level will not rise from below, it is possible to backfill the kamaba with plenty of time.

【0043】また、施工時に排水ボックスの筒部の周囲
に止水部を形成することにより型枠の周囲からの地下水
の漏水を防止可能となる。
Further, it is possible to prevent the leakage of groundwater from the periphery of the form by forming the water stop around the cylindrical portion of the drainage box during construction.

【0044】さらに、型枠除去後に開口部周辺にベント
ナイト等の止水材を配置すれば、かま場ボックスの内外
からの地下水の上昇を完全に防止することが可能とな
る。
Furthermore, by disposing a water stop material such as bentonite around the opening after removing the formwork, it is possible to completely prevent the rise of groundwater from the inside and outside of the kamaba box.

【0045】なお、本発明を採用して地下構築物の施工
を行えば、防水対策が完全であるため、コンクリート打
設時におけるコンクリート中の水増し現象がなくなるの
で、品質の高いコンクリートからなる地下構築物が得ら
れる。
When the construction of an underground structure is carried out by adopting the present invention, since waterproofing measures are complete, the phenomenon of water filling in the concrete at the time of pouring concrete is eliminated, so that an underground structure made of high-quality concrete can be used. can get.

【図面の簡単な説明】[Brief description of drawings]

【図1】排水ボックスの構成例を示す断面図である。FIG. 1 is a cross-sectional view showing a configuration example of a drainage box.

【図2】排水ボックスの外観の例を示す斜視図である。FIG. 2 is a perspective view showing an example of the appearance of a drainage box.

【図3】排水ボックスを採用した地下構築物の施工例を
示す断面図である。
FIG. 3 is a cross-sectional view showing an example of construction of an underground structure using a drainage box.

【図4】施工終了後の状態を示す断面図である。FIG. 4 is a cross-sectional view showing a state after completion of construction.

【図5】従来例を示すもので、(a)は平面図、(b)
は(a)のB−B線断面図である。
5A and 5B show a conventional example, where FIG. 5A is a plan view and FIG.
FIG. 7A is a sectional view taken along line BB of FIG.

【符号の説明】[Explanation of symbols]

1 排水ボックス 2 胴部 3 筒部 4 上部開口 5 水中ポンプ 6 導水口 8 止水栓 11 地下スラブ 12 鋼矢板 13 排水溝 14 誘導水路 15 かま場 18 型枠 20 止水部 26 埋め戻し材 27 止水材(ベントナイト) 1 drainage box 2 torso 3 tube 4 Upper opening 5 submersible pumps 6 water inlet 8 stopcock 11 underground slabs 12 steel sheet pile 13 drains 14 Induction channel 15 Kamaba 18 formwork 20 Water stop 26 Backfill material 27 Water stop material (bentonite)

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 水中ポンプを収納可能な胴部と、この胴
部の上端部に形成してある筒部と、この筒部に上記水中
ポンプを出し入れ可能に設けてある上部開口と、上記胴
部の周囲に設けてある複数の導水口と、これらの導水口
を内部から開閉可能にする止水栓を備えているかま場用
排水ボックスを地下構築物の施工現場の要所に設けられ
たかま場に埋設し、上記筒部の周囲に型枠を設ける第1
工程と、 上記胴部内に上記水中ポンプを設置し、上記導水口を開
ける第2工程と、 上記排水ボックス内に導入された地下水を上記水中ポン
プで排水しながら地下スラブ構築の施工を進める第3工
程と、 上記地下スラブ構築後に上記導水口を閉め、上記水中ポ
ンプを上記排水ボックス内から回収するとともに上記型
枠を除去する第4工程と、 上記排水ボックス内に埋め戻し材を充填し、この埋め戻
し材の上面及び上記筒部の上端部の周囲を止水材で取り
囲んでなる止水部を形成する第5工程とを含むことを特
徴とする地下構築物の施工方法。
1. A body for accommodating a submersible pump, and this body
Section formed on the upper end of the
The upper opening that allows the pump to be taken in and out, and the
Multiple water inlets around the section and these water inlets
For kettles equipped with a water stopper that can be opened and closed from the inside
A drainage box is buried in a stake area provided at a key point of the construction site of an underground structure, and a formwork is provided around the cylinder section.
Process, installing the submersible pump in the body and opening the water guide, a second process, and proceeding with construction of an underground slab while draining the groundwater introduced into the drainage box with the submersible pump A step, a fourth step of closing the water inlet after the construction of the underground slab, collecting the submersible pump from the drain box and removing the formwork, and filling a backfill material into the drain box, A method of constructing an underground structure, comprising: a fifth step of forming a water blocking portion formed by surrounding a top surface of the backfill material and an upper end portion of the tubular portion with a water blocking material.
【請求項2】 請求項1において、上記第3工程は上記
胴部の上端部かつ上記型枠の周囲を止水材で取り囲む工
程を含んでいることを特徴とする地下構築物の施工方
法。
2. The method for constructing an underground structure according to claim 1, wherein the third step includes a step of surrounding the upper end of the trunk and the periphery of the formwork with a waterproof material.
【請求項3】 請求項1において、上記第5工程に用い
る止水材はベントナイトであることを特徴とする地下構
築物の施工方法。
3. The method for constructing an underground structure according to claim 1, wherein the water blocking material used in the fifth step is bentonite.
JP2000014832A 2000-01-24 2000-01-24 Construction method for underground structures Expired - Fee Related JP3451050B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000014832A JP3451050B2 (en) 2000-01-24 2000-01-24 Construction method for underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000014832A JP3451050B2 (en) 2000-01-24 2000-01-24 Construction method for underground structures

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2003117933A Division JP3756889B2 (en) 2003-04-23 2003-04-23 Kamaba drainage box

Publications (2)

Publication Number Publication Date
JP2001207457A JP2001207457A (en) 2001-08-03
JP3451050B2 true JP3451050B2 (en) 2003-09-29

Family

ID=18542226

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000014832A Expired - Fee Related JP3451050B2 (en) 2000-01-24 2000-01-24 Construction method for underground structures

Country Status (1)

Country Link
JP (1) JP3451050B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104131575A (en) * 2014-04-11 2014-11-05 中国水利水电第十一工程局有限公司 Plugging and drainage method for dam foundation on karst highly developed stratum
CN105275020A (en) * 2014-07-07 2016-01-27 中石化洛阳工程有限公司 Underground pipeline anti-leakage facility
CN110593284A (en) * 2019-09-23 2019-12-20 中交第二航务工程局有限公司 Seepage prevention method for construction of underwater bearing platform in solution hole and solution gap development area

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112779931B (en) * 2021-01-26 2024-07-02 中国五冶集团有限公司 Basement construction joint waterproof device, waterproof structure and waterproof method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104131575A (en) * 2014-04-11 2014-11-05 中国水利水电第十一工程局有限公司 Plugging and drainage method for dam foundation on karst highly developed stratum
CN104131575B (en) * 2014-04-11 2016-11-23 中国水利水电第十一工程局有限公司 A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN105275020A (en) * 2014-07-07 2016-01-27 中石化洛阳工程有限公司 Underground pipeline anti-leakage facility
CN110593284A (en) * 2019-09-23 2019-12-20 中交第二航务工程局有限公司 Seepage prevention method for construction of underwater bearing platform in solution hole and solution gap development area
CN110593284B (en) * 2019-09-23 2021-09-10 中交第二航务工程局有限公司 Seepage prevention method for construction of underwater bearing platform in solution hole and solution gap development area

Also Published As

Publication number Publication date
JP2001207457A (en) 2001-08-03

Similar Documents

Publication Publication Date Title
CN101250879A (en) Method for processing bottom solum trickleing water of deep building pit
CN107326918B (en) Hidden type plugging impervious water collecting well penetrating through raft plates and construction process thereof
JP2006265964A (en) Drainage treatment method
CN110847199A (en) Construction method for drainage of underground water of deep foundation pit
JP3451050B2 (en) Construction method for underground structures
KR100734047B1 (en) Sump system and the setting method
KR200433220Y1 (en) Sump system
JP3756889B2 (en) Kamaba drainage box
KR100422216B1 (en) The method of construction prevening a waterflow of cassion basis for a bridge
JP4011212B2 (en) Construction method of shaft
CN214993997U (en) A structure for deep basal pit elevartor shaft precipitation construction
JP4809728B2 (en) manhole
CN212248623U (en) Plain area water delivery engineering assembled drainage valve well structure
JPS6160948B2 (en)
CN207193994U (en) A kind of concealed type, which passes through raft plate, can block impervious sump
JP2000054420A (en) Method of forming water passing part in underground continuous wall
JP4420536B2 (en) Osmotic box culvert, osmotic pipe rod and construction method thereof
CN111676992B (en) Core tube spring leakage blocking method used under complex geological conditions
CN219045167U (en) Diving underground water drainage system
JP3256002B2 (en) How to build a pit for an underground water tank
JP2634442B2 (en) Underground wall
CN114908808A (en) Leakage stopping device and method for leakage of deep water cofferdam bottom sealing concrete
JP4809741B2 (en) manhole
CN111188329A (en) Underground engineering center part water level monitoring, drainage, pressure relief and anti-floating device and installation and plugging method
JPS6334275B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees