JP3447116B2 - Double-body shield excavator and its simultaneous excavation method. - Google Patents

Double-body shield excavator and its simultaneous excavation method.

Info

Publication number
JP3447116B2
JP3447116B2 JP17386394A JP17386394A JP3447116B2 JP 3447116 B2 JP3447116 B2 JP 3447116B2 JP 17386394 A JP17386394 A JP 17386394A JP 17386394 A JP17386394 A JP 17386394A JP 3447116 B2 JP3447116 B2 JP 3447116B2
Authority
JP
Japan
Prior art keywords
shield
segment
jack
slide
gap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP17386394A
Other languages
Japanese (ja)
Other versions
JPH0842281A (en
Inventor
直 磯部
修 吉野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawasaki Motors Ltd
Original Assignee
Kawasaki Jukogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Jukogyo KK filed Critical Kawasaki Jukogyo KK
Priority to JP17386394A priority Critical patent/JP3447116B2/en
Publication of JPH0842281A publication Critical patent/JPH0842281A/en
Application granted granted Critical
Publication of JP3447116B2 publication Critical patent/JP3447116B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/14Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing calcium sulfate cements

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Structural Engineering (AREA)
  • Organic Chemistry (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この出願に係る発明は、トンネル
等を施工するシールド工法に用いるシールド掘進機とそ
の同時掘進工法に関し、更に詳しくは、カッターディス
クによる掘削する掘進作業を行うとともにセグメント組
立作業を同時に行うことができる複胴型シールド掘進機
とその同時掘進工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The invention of this application relates to a shield machine used in a shield construction method for constructing tunnels and the like, and a simultaneous excavation method therefor. The present invention relates to a double-barreled shield excavator capable of performing simultaneously and a simultaneous excavation method.

【0002】[0002]

【従来の技術と発明が解決しようとする課題】従来よ
り、地山や道路等の地下にトンネルや地下鉄道等を形成
する機械としてシールド掘進機が用いられている。この
シールド掘進機を用いたシールド工法は、例えば、前胴
と後胴とから構成された複胴型シールド掘進機を用い、
前面にカッタービットが設けられたカッターディスクに
より地山を掘削しながら前胴側の掘進用ジャッキ(以
下、スライドジャッキという。)と後胴側の反力受用ジ
ャッキ(以下、シールドジャッキという。)を連通させ
て伸縮させることにより、前胴と後胴とを摺動させて掘
進し、1回分の掘進でセグメント1リング幅分(例えば
1200mm)の掘削を行っている。そして、シールド掘
進作業後、掘進作業を一時停止させた状態で新たなセグ
メントを1リング分組み立て、この組立作業が完了した
時点で、このセグメントに掘進反力を取って新たな掘進
作業を行っている。
2. Description of the Related Art Conventionally, a shield machine has been used as a machine for forming tunnels, subway lines, etc. underground such as rocks and roads. The shield construction method using this shield machine, for example, using a double-barreled shield machine composed of a front body and a rear body,
While excavating the ground with a cutter disk provided with a cutter bit on the front side, the front trunk side jack (hereinafter referred to as the slide jack) and the rear trunk side reaction force receiving jack (hereinafter referred to as the shield jack) are provided. By communicating and expanding and contracting, the front cylinder and the rear cylinder are slid to advance, and the excavation for one segment width of one segment (for example, 1200 mm) is performed by one excavation. Then, after the shield excavation work, a new segment is assembled for one ring while the excavation work is temporarily stopped, and when this assembly work is completed, the excavation reaction force is applied to this segment to perform the new excavation work. There is.

【0003】従って、このシールド工法では、掘進作業
とセグメント組立作業とを別々に行うため、多くの時間
を必要とするシールド工法となっている。
Therefore, this shield method requires a lot of time because the excavation work and the segment assembly work are performed separately.

【0004】一方、近年、都市部やその近郊部における
シールド工事用の用地確保が難しくなり、また、確保し
ても長期使用が困難になっているため、シールド工法に
おける高速掘進が切望されている。そして高速掘進によ
り従来と同様のトンネルを短期間で施工することによ
り、用地使用期間の短縮とともに工期の短縮による工費
等の削減を図ろうとしている。
On the other hand, in recent years, it has become difficult to secure a site for shield work in urban areas and its suburbs, and even if secured, long-term use becomes difficult. . By constructing a tunnel similar to the conventional one in a short period of time by high-speed excavation, the company is trying to reduce the construction period and the construction cost by shortening the construction period.

【0005】この種の従来技術として、特公平3−23
720号公報記載の発明があり、この公報記載の発明
は、セグメント組立と掘進とを同時に施工することによ
り掘進スピードの向上を図ろうとしたシールド掘進機の
運転方法である。この運転方法は、スライドジャッキが
収縮されすべてのシールドジャッキが伸張された初期状
態から、スライドジャッキの伸張で前部のフレームを推
進させて切羽を掘削しながら、複数のシールドジャッキ
のうちの一部を収縮させて既設セグメントとの間に形成
される間隙部にエレクタにより新たなセグメントピース
を組み込んでは該ピースに反力をとり、以下、この動作
を他のシールドジャッキに順次繰り返してセグメントを
リング状に組立てるものであり、組立てた後、スライド
ジャッキとシールドジャッキの押側圧力室を連通させ、
シールドジャッキの引側圧力室に圧力を加えてこれらジ
ャッキを初期状態に戻すものである。
As a conventional technique of this kind, Japanese Patent Publication No. 3-23
There is an invention described in Japanese Patent No. 720, and the invention described in this publication is a method of operating a shield machine, which aims to improve the speed of excavation by simultaneously performing segment assembly and excavation. This operation method starts from the initial state where the slide jacks are contracted and all the shield jacks are extended, and the extension of the slide jacks propels the front frame to excavate the face, while a part of the shield jacks When a new segment piece is installed by an erector in the gap formed by contracting the existing segment with the existing segment, a reaction force is applied to the piece, and then this operation is repeated for other shield jacks in sequence to form a ring-shaped segment. After assembling, make the push jack pressure chambers of the slide jack and shield jack communicate with each other.
The pressure is applied to the pull-side pressure chamber of the shield jack to return these jacks to the initial state.

【0006】しかし、この運転方法では、セグメントの
1リング分を前胴側に設けたスライドジャッキと後胴側
に設けたシールドジャッキとを連通させて1ストローク
で掘進する方法のため、両ジャッキ共に1リング分以上
のストロークを必要とするので、シールド掘進機として
の機長が長くなってしまい、シールド掘進機を地中に搬
入するための大きな立坑が必要となって、広い用地の確
保や立坑形成等に多くの費用が必要となる。
However, in this operating method, since one ring of the segment is made to communicate with the slide jack provided on the front body side and the shield jack provided on the rear body side to dig in one stroke, both jacks are used. Since the stroke for one ring or more is required, the length of the shield machine becomes long, and a large shaft is required to bring the shield machine into the ground, ensuring a large site and forming a shaft. A lot of costs are required for the above.

【0007】また、この従来技術では両ジャッキを連通
させているため蛇行修正等が難しく、更に、中折機構を
設けて曲進掘削を行おうとしても両ジャッキが連通して
いるため難しく、このシールド掘進機の運転方法では曲
進掘削を行うことが困難である。
Further, in this prior art, since both jacks are communicated with each other, it is difficult to correct meandering and the like, and it is difficult to perform curving excavation by providing a center folding mechanism because both jacks are communicated with each other. It is difficult to perform curved excavation by the operation method of the shield machine.

【0008】この出願に係る発明は上記課題に鑑みて、
掘削作業とセグメント組立作業とを同時に行う高速施工
を可能とするとともに、シールド掘進機長のコンパクト
化が可能なシールド掘進機を提供することを一つの目的
とし、そのシールド掘進機による同時掘進工法を提供す
ることと、該同時掘進工法において蛇行修正が容易な同
時掘進工法を提供することを他の目的とする。
In view of the above problems, the invention of this application is
One purpose is to provide a shield machine that enables high-speed construction that performs both excavation work and segment assembly work at the same time, and that can also make the shield machine length compact, and provides a simultaneous excavation method using the shield machine. Another object of the present invention is to provide a simultaneous excavation method in which meandering correction is easy in the simultaneous excavation method.

【0009】[0009]

【課題を解決するための手段】上記目的を達成するため
に、請求項1に係る複胴型シールド掘進機は、前面にカ
ッタディスクを有する前胴と後部にセグメントを組立る
エレクタ装置を有する後胴とを軸方向にスライド自在に
連結した複胴型シールド掘進機において、前記前胴と後
胴との間に前記セグメント幅のほぼ半分のストロークを
有する複数のスライドジャッキを設け、前記後胴にセグ
メント幅と前記スライドジャッキのストロークとセグメ
ント組込隙間とを合わせたストロークとほぼ同じストロ
ークを有する複数のシールドジャッキを設け、該シール
ドジャッキと前記スライドジャッキとを別々に伸縮動作
させる制御装置を設けて駆動したことを特徴とするもの
である。
In order to achieve the above object, a double-barrel shield machine according to claim 1 has a front body having a cutter disk on the front side and a rear body having an erector device for assembling segments on the rear side. In a double-barrel type shield excavator in which a body and a body are slidably connected to each other, a plurality of slide jacks having a stroke of approximately half the segment width are provided between the front body and the rear body, and the rear body is provided with the slide jacks. A plurality of shield jacks having substantially the same stroke as the sum of the segment width, the stroke of the slide jack, and the segment built-in gap are provided, and a control device for separately expanding and contracting the shield jack and the slide jack is provided. It is characterized by being driven.

【0010】請求項2に係る複胴型シールド掘進機の同
時掘進工法は、前胴と後胴とを軸方向にスライド自在に
連結し、該前胴側に複数のスライドジャッキを具備する
とともに後胴側に複数のシールドジャッキを具備した複
胴型シールド掘進機による同時掘進工法において、(a)
シールドジャッキと既設セグメントとの間に所定の間隙
を有する状態から、スライドジャッキにより前胴をセグ
メント幅のほぼ半分以下でセグメント組込隙間以上を第
1掘進させる第1工程、(b) シールドジャッキにより後
胴を前記第1工程と同掘進量だけ前進させるとともにス
ライドジャッキを同掘進量だけ縮める第2工程、(c) シ
ールドジャッキにより後胴とともに前胴を第2掘進させ
てシールドジャッキと既設セグメントとの間にセグメン
ト幅とセグメント組込隙間とを合わせた間隙を形成する
第3工程、(d) スライドジャッキにより前胴を前記第1
工程と第3工程と合わせてセグメント幅となるようにセ
グメント幅のほぼ半分以下でセグメント組込隙間以上を
掘進させるとともに、一部のシールドジャッキを縮めて
その間隙に新たなセグメントを組立る第4工程、(e) ス
ライドジャッキとシールドジャッキとにより後胴を前記
第4工程と同掘進量だけ掘進させるとともに、前記第4
工程以外の一部のシールドジャッキを縮めてその間隙に
新たなセグメントを組立る第5工程、(f) スライドジャ
ッキにより前胴を前記第1工程の第1掘進と同掘進量だ
け掘進させる第6工程、(g) スライドジャッキを停止さ
せてキーセグメントを組立る第7工程、とからなり、前
記 (b)〜(g) の第2工程〜第7工程を順次繰り返して掘
進作業とセグメント組立作業とを同時に行うことを特徴
とするものである。
According to a method for simultaneously excavating a double-barrel type shield machine according to a second aspect, the front body and the rear body are axially slidably connected to each other, and a plurality of slide jacks are provided on the front body side and the rear body In the simultaneous excavation method with a double-barreled shield machine equipped with multiple shield jacks on the trunk side, (a)
From the state that there is a predetermined gap between the shield jack and the existing segment, the first step of making the first excavation of the front body with the slide jack at less than about half of the segment width and above the segment built-in gap, (b) by the shield jack A second step in which the rear body is advanced by the same amount as the first step and the slide jack is contracted by the same amount in the same amount, (c) The shield jack and the front body are secondly advanced by the shield body and the shield jack and the existing segment are formed. A third step of forming a gap in which the segment width and the segment built-in gap are combined, and
Along with the process and the third process, the segment width is excavated at about half or less of the segment width so that the segment width is obtained, and a part of the shield jack is contracted to assemble a new segment in the gap. Step (e) The rear body is dug by the same amount as the fourth step by the slide jack and the shield jack, and
The fifth step of shrinking a part of the shield jack other than the step and assembling a new segment in the gap, (f) The forward trunk is dug by the same amount as the first step of the first step by the slide jack. Process, (g) 7th process of assembling the key segment by stopping the slide jack, and (b) to (g) 2nd to 7th processes are sequentially repeated to perform excavation work and segment assembly work. And is performed at the same time.

【0011】請求項3に係る複胴型シールド掘進機によ
る同時掘進工法は、上記請求項2の同時掘進工法におい
て、第3工程で、複数のシールドジャッキの伸長量を調
節することによりシールド掘進機の方向制御を行うこと
を特徴とするものである。
The simultaneous excavation method using the double-barreled shield excavator according to claim 3 is the simultaneous excavation method according to claim 2, wherein the extension amount of the plurality of shield jacks is adjusted in the third step. It is characterized in that the direction control is performed.

【0012】請求項4に係る複胴型シールド掘進機によ
る同時掘進工法は、上記請求項2の同時掘進工法におい
て、後胴側に中折機構を設け、複数のシールドジャッキ
の伸長量を調節することにより該中折機構によりシール
ド掘進機の方向制御を行いながら曲進施工を行うことを
特徴とするものである。
According to a fourth aspect of the present invention, in the simultaneous excavation method using a double-barrel type shield excavator, in the simultaneous excavation method of the second aspect, a center folding mechanism is provided on the rear trunk side to adjust the extension amounts of a plurality of shield jacks. Thus, the bending operation is performed while the direction of the shield machine is controlled by the center folding mechanism.

【0013】[0013]

【作用】請求項1に係る複胴型シールド掘進機によれ
ば、前胴と後胴との間に設けたスライドジャッキがセグ
メント幅のほぼ半分のストロークを有し、後胴に設けた
シールドジャッキがセグメント幅と前記スライドジャッ
キのストロークとセグメント組込隙間とを合わせたスト
ロークとほぼ同じストロークを有しているため、前面に
カッタディスクを有する前胴と、後部にセグメントを組
立るエレクタ装置を有する後胴とを軸方向にスライド自
在に連結した複胴型シールド掘進機の機長を短くするこ
とができ、しかも、シールドジャッキとスライドジャッ
キとを別々に伸縮動作制御可能に構成したことにより掘
進作業とセグメント組立作業とを同時に行う同時掘進工
法ができる。
According to the double-body shield machine according to the first aspect, the slide jack provided between the front body and the rear body has a stroke of about half the segment width, and the shield jack provided on the rear body. Has substantially the same stroke as the sum of the segment width, the stroke of the slide jack and the segment mounting gap, the front body having a cutter disk on the front side and the erector device for assembling the segments on the rear side. It is possible to shorten the length of the double-barrel type shield excavator in which the rear body is slidably connected in the axial direction, and furthermore, the shield jack and the slide jack can be separately controlled for expansion and contraction. Simultaneous excavation method that performs segment assembly work at the same time is possible.

【0014】請求項2〜4に係る複胴型シールド掘進機
の同時掘進工法によれば、前胴と後胴とを軸方向にスラ
イド自在に連結し、該前胴側に複数のスライドジャッキ
を具備するとともに後胴側に複数のシールドジャッキを
具備した複胴型シールド掘進機により、第1工程で、シ
ールドジャッキと既設セグメントとの間に所定の間隙を
有する状態から、スライドジャッキにより前胴をセグメ
ント幅のほぼ半分以下でセグメント組込隙間以上を第1
掘進させ、第2工程で、シールドジャッキにより後胴を
前記第1工程と同掘進量だけ前進させるとともにスライ
ドジャッキを同掘進量だけ縮め、第3工程で、シールド
ジャッキにより後胴とともに前胴を第2掘進させてシー
ルドジャッキと既設セグメントとの間にセグメント幅と
セグメント組込隙間とを合わせた間隙を形成し、第4工
程で、スライドジャッキにより前胴を前記第1工程と第
3工程と合わせてセグメント幅となるようにセグメント
幅のほぼ半分以下でセグメント組込隙間以上を掘進させ
るとともに、一部のシールドジャッキを縮めてその間隙
に新たなセグメントを組立て、第5工程で、スライドジ
ャッキとシールドジャッキとにより後胴を前記第4工程
と同掘進量だけ掘進させるとともに、前記第4工程以外
の一部のシールドジャッキを縮めてその間隙に新たなセ
グメントを組立て、第6工程で、スライドジャッキによ
り前胴を前記第1工程の第1掘進と同掘進量だけ掘進さ
せるを掘進させ、第7工程で、スライドジャッキを停止
させてキーセグメントを組立てれば、シールド掘進機に
よる掘進作業とセグメント組立作業とを同時に行うこと
が可能となり、前記第2工程〜第7工程を順次繰り返せ
ば同時掘進工法が可能となる。
According to the method for simultaneously excavating the double-barreled shield machine according to claims 2 to 4, the front body and the rear body are axially slidably connected to each other, and a plurality of slide jacks are provided on the front body side. In the first step, a double-jacket type shield excavator equipped with a plurality of shield jacks on the rear torso side is used to move the front torso from the state in which there is a predetermined gap between the shield jack and the existing segment in the first step. The first is the half of the width of the segment or less and the gap above the segment
In the second step, the rear jack is advanced by the shield jack in the second step by the same amount as the first step, and the slide jack is shortened by the same amount in the second step. 2 By excavating, a gap is formed between the shield jack and the existing segment, which is the sum of the segment width and the segment built-in gap. In the fourth step, the front body is combined with the first step and the third step by the slide jack. So that the width of the segment is less than half of the width of the segment so that the space above the segment can be dug in, and some of the shield jacks are shrunk to assemble a new segment in the gap. The rear body is dug by the jack by the same amount as the fourth step, and a part of the shield other than the fourth step is shielded. Shrink the jack and assemble a new segment in the gap, and in the sixth step, use the slide jack to advance the front trunk by the same amount as the first advance in the first step, and in the seventh step, slide the jack. If the key segment is stopped and the key segment is assembled, the excavation work by the shield excavator and the segment assembly work can be performed at the same time, and the simultaneous excavation method can be performed by sequentially repeating the second to seventh steps.

【0015】特に、請求項3に係る同時掘進工法によれ
ば、第3工程で、複数のシールドジャッキの伸長量を調
節することによりシールド掘進機の方向制御を行うこと
ができる。
Particularly, according to the simultaneous excavation method according to the third aspect, the direction of the shield machine can be controlled by adjusting the extension amounts of the plurality of shield jacks in the third step.

【0016】また、特に請求項4に係る同時掘進工法に
よれば、第3工程で、複数のシールドジャッキの伸長量
を調節することにより、後胴側に設けた中折機構でシー
ルド掘進機の方向制御を行いながら曲進施工をすること
ができる。
Further, according to the simultaneous excavation method according to claim 4, in the third step, by adjusting the extension amounts of the plurality of shield jacks, the center folding mechanism provided on the rear trunk side of the shield excavator is used. It is possible to perform bending work while controlling the direction.

【0017】[0017]

【実施例】以下、この出願に係る発明の好ましい実施例
を図面に基づいて説明する。図1は同時掘進工法の初期
状態を示す図面であり、(a) はシールド掘進機の断面
図,(b) はセグメントとシールドジャッキとの間隙を示
す側面図である。なお、以下の実施例ではセグメントC
の幅が1200mmの例を説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT A preferred embodiment of the invention according to this application will be described below with reference to the drawings. FIG. 1 is a drawing showing an initial state of the simultaneous excavation method, (a) is a sectional view of a shield machine, and (b) is a side view showing a gap between a segment and a shield jack. In the following examples, segment C
An example in which the width is 1200 mm will be described.

【0018】図示するように、この出願に係る発明のシ
ールド掘進機は複胴型シールド掘進機Sであり、前面に
カッタディスク1を有する前胴2と、後部にセグメント
Cを組み立てるエレクタ装置3を有する後胴4とを軸方
向にスライド自在に連結しており、前胴2と後胴4との
間にはスライド部5が形成されている。
As shown in the figure, the shield machine of the invention according to this application is a double-barrel type shield machine S comprising a front body 2 having a cutter disk 1 on the front surface and an erector device 3 for assembling a segment C on the rear portion. The rear body 4 which it has is connected slidably in the axial direction, and a slide portion 5 is formed between the front body 2 and the rear body 4.

【0019】このスライド部5は、後胴4の前部に設け
た小径部4aと前胴2の後部との間を摺動自在に接合し
たものであり、前胴2側には周状に設けられた複数のス
ライドジャッキFの基端側が支持され、後胴4側のリン
グ部材6にはスライドジャッキFのピストン先端部Fa
が連結され、このスライドジャッキFを伸縮させること
によってスライド部5で軸方向にスライド自在なように
構成されている。また、後胴4側にはセグメントCによ
り掘進反力を支持するシールドジャッキRが複数設けら
れており、この実施例では14本のシールドジャッキR
が均等角度で周状に設けられ、これらは後胴4に設けら
れた支持フレーム7に保持されている。
The sliding portion 5 is formed by slidably joining a small-diameter portion 4a provided on the front portion of the rear body 4 and a rear portion of the front body 2, and has a circumferential shape on the front body 2 side. The base end sides of the plurality of slide jacks F provided are supported, and the piston tip portion Fa of the slide jacks F is attached to the ring member 6 on the rear body 4 side.
Are connected, and when the slide jack F is expanded and contracted, the slide portion 5 is configured to be slidable in the axial direction. Further, a plurality of shield jacks R supporting the excavation reaction force by the segments C are provided on the rear body 4 side, and in this embodiment, 14 shield jacks R are provided.
Are circumferentially provided at equal angles, and these are held by a support frame 7 provided on the rear body 4.

【0020】これらのスライドジャッキFとシールドジ
ャッキRとは別々に伸縮動作が可能なように図示しない
制御装置により制御されている。また、上記複数のスラ
イドジャッキFの伸縮量もこの制御装置により個々に制
御されている。なお、これらのジャッキの本数はシール
ド径等により最適な本数を選択すればよく、3本以上で
あれば後述するように伸張量を調節して制御できる。
The slide jack F and the shield jack R are controlled by a controller (not shown) so that they can be expanded and contracted separately. The expansion / contraction amount of the plurality of slide jacks F is also individually controlled by this control device. The optimum number of these jacks may be selected depending on the shield diameter and the like, and if the number is 3 or more, the extension amount can be adjusted and controlled as described later.

【0021】上記前胴2に設けられたスライドジャッキ
Fのストロークは、この実施例では後述するように複胴
型シールド掘進機Sを掘進させるため、セグメント幅の
半分である600mmストロークの短いストロークを採用
し、これによって前胴2の長さを短くしてシールド掘進
機全体の機長をコンパクトにした複胴型シールド掘進機
Sが構成されている。このストロークは、セグメント幅
おほぼ半分であれば、後述するように同時掘進工法を可
能とし、しかも機長を短くできる。
The stroke of the slide jack F provided on the front case 2 is a short stroke of 600 mm stroke, which is half of the segment width, in order to advance the double-body type shield excavator S as will be described later in this embodiment. A double-barreled shield machine S is adopted in which the length of the front body 2 is shortened to make the overall length of the shield machine compact. If the stroke is approximately half the segment width, the simultaneous excavation method can be performed and the machine length can be shortened as described later.

【0022】また、シールドジャッキRは、後述するよ
うにセグメントCの組立作業時における複胴型シールド
掘進機Sの掘進反力を支持するため、セグメント幅と上
記スライドジャッキFのストロークと組立上のセグメン
ト組込隙間hとを合わせたストロークが採用されてい
る。この実施例では、セグメント幅1200mmとスライ
ドジャッキFのストローク600mmとセグメント組込隙
間100mmと余裕を見て1950mmのストロークが採用
されている。なお、シールドジャッキRのストロークを
必要以上確保した場合、シールド掘進機長の増加を伴う
ので必要最小限が好ましい。
Further, the shield jack R supports the excavation reaction force of the double-barrel shield excavator S during the assembly work of the segment C, as will be described later, and therefore, the segment width, the stroke of the slide jack F and the assembly. A stroke that matches the segment assembly gap h is adopted. In this embodiment, a segment width of 1200 mm, a stroke of the slide jack F of 600 mm, a segment mounting gap of 100 mm, and a stroke of 1950 mm are used considering a margin. It should be noted that if the stroke of the shield jack R is secured more than necessary, the shield excavator length is increased, so the minimum required is preferable.

【0023】更に、この実施例では、後胴4の中間部に
球面座8aを有する中折機構8が設けられており、この
中折機構8を設けることにより前側後胴4Aと後側後胴
4Bとの間で屈曲可能なように構成されている。なお、
この中折機構8及び上記スライド部5には図示しない土
砂シールが設けられ、泥水等の機内侵入を防止してい
る。
Further, in this embodiment, a center folding mechanism 8 having a spherical seat 8a is provided at an intermediate portion of the rear body 4, and by providing the center folding mechanism 8, the front rear body 4A and the rear rear body 4A. It is configured to be bendable between 4B and 4B. In addition,
The center folding mechanism 8 and the slide portion 5 are provided with earth and sand seals (not shown) to prevent intrusion of muddy water into the machine.

【0024】この図1(a),(b) に示す状態が初期状態で
あり、この状態では図1(b) に示すように既設セグメン
トCO とシールドジャッキRを縮めた時の原点O(以
下、単に原点という。)との間には700mmの間隙Hが
設けられている。
The state shown in FIGS. 1 (a) and 1 (b) is the initial state. In this state, as shown in FIG. 1 (b), the origin O (when the existing segment C O and the shield jack R are contracted is Hereinafter, a gap H of 700 mm is provided between the gap H and the origin.

【0025】以上のように構成された複胴型シールド掘
進機Sによる同時掘進工法を、図2(a),(b) 〜図8(a),
(b) の第1〜第7工程におけるシールド掘進機の断面図
及びセグメントとシールドジャッキとの間隙を示す側面
図と、図9 (a)〜(d) の第4〜第7工程におけるセグメ
ントを組立る状態を示す図面に基づいて以下に説明す
る。なお、上記図1と同一の構成には同一符号を付して
説明は省略する。
2 (a), (b) to FIG. 8 (a), the simultaneous excavation method using the double-barreled shield excavator S configured as described above is described.
Sectional view of the shield machine in the first to seventh steps of (b) and a side view showing the gap between the segment and the shield jack, and segments in the fourth to seventh steps of FIGS. 9 (a) to (d). The following description is based on the drawings showing the assembled state. The same components as those in FIG. 1 are designated by the same reference numerals and the description thereof will be omitted.

【0026】まず、図2(a) に示すように、上述した図
1(a) の状態から前胴2に設けたスライドジャッキFを
伸張させることによりセグメントCの1リング幅である
1200mmの半分以下の掘進量の400mmを第1掘進さ
せる。この第1掘進が第1工程であり、この工程では前
胴2のみが掘進するので、図2(b) に示すように既設セ
グメントCO とシールドジャッキRの原点Oとの間隙H
の700mmは変わらない。
First, as shown in FIG. 2 (a), by extending the slide jack F provided on the front case 2 from the state shown in FIG. 1 (a), one half of 1200 mm which is one ring width of the segment C is extended. The following excavation amount of 400 mm is first excavated. This first excavation is the first step, and since only the front body 2 is excavated in this step, the gap H between the existing segment C O and the origin O of the shield jack R is shown in FIG. 2 (b).
700mm is the same.

【0027】次に、図3(a) に示すように、スライドジ
ャッキFを400mm縮めて後胴4を上記第1工程と同掘
進量の400mm前進させるとともにシールドジャッキR
も400mm伸張させる。つまり、上記第1工程における
前胴2の掘進量と同じ量だけ後胴4を前胴2側へ引き寄
せる。この時、図3(b) に示すように、既設セグメント
O から後胴4が400mm前進するため、シールドジャ
ッキRの原点Oとの間隙Hは1100mmとなる。この工
程が第2工程である。
Next, as shown in FIG. 3 (a), the slide jack F is shrunk by 400 mm to move the rear body 4 forward by 400 mm, which is the same amount as the first step, and the shield jack R.
Also extend 400 mm. That is, the rear body 4 is pulled toward the front body 2 by the same amount as the amount of excavation of the front body 2 in the first step. At this time, as shown in FIG. 3 (b), since the rear body 4 is 400mm forward from the existing segment C O, the gap H between the origin O of the shield jacks R becomes 1100 mm. This step is the second step.

【0028】そして、図4(a) に示すように、シールド
ジャッキRによって、既設セグメントCO とシールドジ
ャッキRの原点Oとの間隙Hが、上記第2工程の掘進量
と合わせて新セグメントCN の1リング幅である120
0mmとセグメント組込隙間hの100mmとの合計である
1300mmとなるように後胴4とともに前胴2を200
mm第2掘進させる。この第2掘進が第3工程となり、上
記第1工程の第1掘進とこの第2掘進とにより、図4
(b) に示すように、既設セグメントCO とシールドジャ
ッキRの原点Oとの間隙Hが1300mmとなって、既設
セグメントCO とシールドジャッキRとの間に1200
mm幅の新セグメントCN を組み立てることができる間隙
Hが確保されることとなる。
Then, as shown in FIG. 4 (a), the shield jack R allows the gap H between the existing segment C O and the origin O of the shield jack R to be adjusted to the new segment C together with the amount of excavation in the second step. One ring width of N is 120
The front body 2 as well as the rear body 4 is set to 200 mm so that a total of 0 mm and 100 mm of the segment assembly gap h is 1300 mm.
mm 2nd dig. This second excavation becomes the third step, and by the first excavation in the first step and this second excavation, the process shown in FIG.
As shown in (b), the gap H between the existing segment C O and the origin O of the shield jack R is 1300 mm, and there is 1200 between the existing segment C O and the shield jack R.
A gap H is secured so that a new segment C N of mm width can be assembled.

【0029】また、この第3工程では複胴型シールド掘
進機Sの掘進のみでセグメントCの組立作業は行わない
ので、周状に設けられた複数のシールドジャッキRの伸
長量を制御装置により調節することにより複胴型シール
ド掘進機Sの方向制御を行うことができるため、この第
3工程において蛇行修正しながら掘進することができ
る。
Further, in this third step, since the segment C is not assembled but only the double-barrel type shield machine S is excavated, the extension amounts of the plurality of circumferentially arranged shield jacks R are adjusted by the controller. By doing so, it is possible to control the direction of the double-barreled shield machine S, and therefore it is possible to dig while correcting the meandering in the third step.

【0030】上記したように、第3工程を終了した時点
で既設セグメントCO とシールドジャッキRの原点Oと
の間隙Hが1300mmとなるため、以下の第4工程から
は複胴型シールド掘進機Sの掘進とともに新セグメント
N の組立作業も同時に行うこととなる。つまり、この
出願に係る発明では、掘進作業とともにこの新セグメン
トCN の組立作業を以下のようにして同時に行うことが
できる。
As described above, since the gap H between the existing segment C O and the origin O of the shield jack R becomes 1300 mm at the time when the third step is completed, the double-barrel type shield excavator from the fourth step below. As S advances, the assembly work of the new segment C N will be performed at the same time. That is, in the invention according to this application, the assembling work of this new segment C N can be performed simultaneously with the excavation work as follows.

【0031】すなわち、図5(a) に示すように、スライ
ドジャッキFにより前胴2をセグメント1リング幅の半
分である600mmを掘進させながら、一部のシールドジ
ャッキRを縮めて、このシールドジャッキRと既設セグ
メントCO の原点Oとの間の間隙Hに新セグメントCN
を組み立てる。この新セグメントCN の組み立ては、こ
の実施例ではリング状のセグメントCを図9(a) に示す
ように、下側の3ピースの新セグメントCN から順次組
み立て作業を行って行く。従って、これら3ピースの新
セグメントCN を組み立てる時は、組み立てる新セグメ
ントCN の位置する箇所のシールドジャッキRのみを縮
めて組み立て、他のシールドジャッキRは掘進反力を支
持することとなる。この時、図5(b) に示すように、新
セグメントCN を組み立てた箇所では、新セグメントC
N とシールドジャッキRの原点Oとの間隙Hがセグメン
ト組込隙間hの100mmのみとなる。この工程が第4工
程である。
That is, as shown in FIG. 5 (a), while the front body 2 is being excavated by the slide jack F by 600 mm which is half the width of the ring of the segment 1, a part of the shield jack R is contracted to In the gap H between R and the origin O of the existing segment C O , the new segment C N
Assemble. To assemble the new segment C N , in this embodiment, the ring-shaped segment C is sequentially assembled from the lower three-piece new segment C N as shown in FIG. 9 (a). Therefore, when assembling the new segment C N of these three pieces are assembled assembled shortened only shield jacks R position to place the new segment C N, the other shield jacks R and thus supporting the excavation reaction force. At this time, as shown in FIG. 5 (b), at the place where the new segment C N is assembled, the new segment C N
The gap H between N and the origin O of the shield jack R is only 100 mm, which is the segment assembly gap h. This step is the fourth step.

【0032】そして、図6(a) に示すように、スライド
ジャッキFを600mm縮めるとともにシールドジャッキ
Rも600mm伸張させて後胴4を上記第4工程と同掘進
量の600mm前進させる。つまり、上記第4工程におけ
る前胴2の掘進量と同じ量だけ後胴4を前胴2側へ引き
寄せる。この時、図6(b) に示すように、新たに組み立
てた新セグメントCN から後胴4が600mm前進するた
め、シールドジャッキRの原点Oとの間隙Hは700mm
となる。また、この掘進作業とともに図9(b)に示すよ
うに、上記第4工程において組み立てた3ピースの新セ
グメントCN の上部に2ピースの新セグメントCN を組
み立てている。この工程が第5工程であり、上記第4工
程からこの第5工程にかけて掘進反力を支持するシール
ドジャッキRの一部は最大ストロークである1900mm
となる。
Then, as shown in FIG. 6 (a), the slide jack F is contracted by 600 mm and the shield jack R is also expanded by 600 mm to move the rear body 4 forward by 600 mm, which is the same amount as the fourth step. That is, the rear body 4 is pulled toward the front body 2 side by the same amount as the amount of the front body 2 excavated in the fourth step. At this time, as shown in FIG. 6 (b), since the rear body 4 is advanced by 600 mm from the newly assembled new segment C N , the gap H from the origin O of the shield jack R is 700 mm.
Becomes Further, along with this excavation work, as shown in FIG. 9B, a two-piece new segment C N is assembled on top of the three-piece new segment C N assembled in the fourth step. This step is the fifth step, and a part of the shield jack R supporting the excavation reaction force from the fourth step to the fifth step has a maximum stroke of 1900 mm.
Becomes

【0033】その後、図7(a) の断面図に示すように、
前胴2に設けたスライドジャッキFにより前胴2をセグ
メントCの1リング幅である1200mmの半分以下の掘
進量の400mmを掘進させる。この掘進が第6工程であ
り、この掘進量は上記第1工程における第1掘進と同じ
量であり、この時には後胴4は移動しないので、図7
(b) に示すようにシールドジャッキRとセグメントCと
の間隙Hは上記第1工程と同じ700mmとなる。
After that, as shown in the sectional view of FIG.
With the slide jack F provided on the front body 2, the front body 2 is advanced by a depth of 400 mm which is less than half of 1200 mm which is one ring width of the segment C. This excavation is the sixth step, and the amount of this excavation is the same as that of the first excavation in the first step. At this time, the rear body 4 does not move.
As shown in (b), the gap H between the shield jack R and the segment C is 700 mm, which is the same as in the first step.

【0034】この第6工程における掘進量は、上記第3
工程における掘進量の200mmと第4工程における掘進
量の600mmとを合わせてセグメントCの幅1200mm
と同じになる掘進量であり、これらの掘進量をスライド
ジャッキFとシールドジャッキRとを別々に制御するこ
とにより、合わせてセグメント幅と同じ掘進量にしてい
る。
The amount of excavation in this sixth step is the same as that in the third step.
The width of segment C is 1200 mm, which is the sum of the excavation amount in the process of 200 mm and the excavation amount of 600 mm in the fourth process.
The slide amount F and the shield jack R are separately controlled so that the total amount of excavation is the same as the segment width.

【0035】そして、図8(a) の断面図に示すようにス
ライドジャッキFを停止させ、図9(d) に示すように、
5ピースの新セグメントCN を組み立てた上部にキーセ
グメントCM を組み立てることにより、リング状の新セ
グメントCN の組み立てが完了する。この時には前胴2
及び後胴4は移動しないので、図8(b) に示すように、
新たに組み立てた新セグメントCN とシールドジャッキ
Rの原点Oとの間隙Hは700mmである。この工程が第
7工程であり、これによりリング状の新セグメントCN
の組立作業が完了する。
Then, the slide jack F is stopped as shown in the sectional view of FIG. 8 (a), and as shown in FIG. 9 (d).
By assembling the key segment C M on top of the assembled 5-piece new segment C N , the assembly of the ring-shaped new segment C N is completed. Front body 2 at this time
Since the rear torso 4 does not move, as shown in FIG. 8 (b),
The gap H between the newly assembled new segment C N and the origin O of the shield jack R is 700 mm. This step is the 7th step, and as a result, a new ring-shaped segment C N
The assembly work of is completed.

【0036】以上が1リングのセグメントCを組み立て
る工程であり、上記第2工程から第7工程までを順次繰
り返して行うことにより、掘進作業を行いながらセグメ
ント組立作業を同時に行う同時掘進が可能となり、複胴
型シールド掘進機Sによる工期を大幅に短縮させること
ができる同時掘進工法が実現できる。
The above is the process of assembling the one-ring segment C. By sequentially repeating the above-mentioned second to seventh processes, it is possible to perform simultaneous excavation in which segment assembling work is performed simultaneously while excavating work. It is possible to realize a simultaneous excavation method capable of significantly shortening the construction period of the double-body shield machine S.

【0037】上記実施例におけるスライドジャッキF及
びシールドジャッキRの掘進量は好ましい一例であり、
これらの掘進量は、例えば以下の表1に示すような値で
あってもよい。
The digging amount of the slide jack F and the shield jack R in the above embodiment is a preferable example,
These digging amounts may be values as shown in Table 1 below, for example.

【0038】[0038]

【表1】 [Table 1]

【0039】この表1に示すように、第2,第3,第5
工程におけるシールドジャッキRの個々の掘進量はセグ
メント幅のほぼ半分以下で、合計の掘進量がセグメント
幅であればよい。
As shown in Table 1, the second, third and fifth
The amount of individual excavation of the shield jack R in the process is approximately half the segment width or less, and the total amount of excavation may be the segment width.

【0040】一方、上述した工程によるシールド工法
は、直線のトンネル等を施工する場合の同時掘進工法で
あり、この出願に係る発明によれば以下のようにして曲
線のトンネル等を施工する曲進施工の同時掘進工法も可
能である。
On the other hand, the shield construction method by the above-mentioned steps is a simultaneous excavation construction method for constructing a straight tunnel or the like, and according to the invention of this application, a curved construction for constructing a curved tunnel or the like is performed as follows. A simultaneous excavation method for construction is also possible.

【0041】すなわち、曲進施工の場合、上述した複胴
型シールド掘進機Sの前部後胴4Aと後部後胴4Bとの
間に設けた中折機構8を用い、図3(a) に示す第2工程
〜図8(a) に示す第7工程における掘進時に複数のスラ
イドジャッキF又はシールドジャッキRの伸長量を制御
装置により調節すれば可能となる。
That is, in the case of the curved construction, the center folding mechanism 8 provided between the front rear body 4A and the rear rear body 4B of the above-mentioned double-barrel type shield machine S is used, and as shown in FIG. This can be achieved by adjusting the extension amounts of the plurality of slide jacks F or shield jacks R during the excavation in the second step to the seventh step shown in FIG. 8A by the control device.

【0042】また、この場合にも、上記直進施工と同様
に、図4(a) に示す第3工程において方向制御を行うこ
とが容易にできるので、複胴型シールド掘進機Sの方向
制御を行いながら曲進施工の同時掘進工法が可能とな
る。
Also in this case, the direction control can be easily performed in the third step shown in FIG. 4 (a) as in the case of the straight-ahead construction. The simultaneous excavation method of bending construction becomes possible while performing.

【0043】この曲線施工を行う場合には、通常、中折
機構8を設ける必要性から機長が長くなるが、この出願
に係る複胴型シールド掘進機Sによれば前胴2側のスラ
イドジャッキストロークを短縮することができるため、
前胴2の長さをコンパクトにすることが可能となって、
複胴型シールド掘進機S全体の機長をコンパクト化でき
る。
When performing this curved construction, the machine length is usually long due to the necessity of providing the center folding mechanism 8. However, according to the double-body shield machine S according to this application, the slide jack on the front body 2 side is provided. Because the stroke can be shortened,
It is possible to make the length of the front body 2 compact,
The overall captain of the double-barrel shield machine S can be made compact.

【0044】[0044]

【発明の効果】この出願に係る発明は、以上説明したよ
うに構成しているので、以下に記載するような効果を奏
する。
Since the invention according to this application is configured as described above, it has the following effects.

【0045】請求項1に係る複胴型シールド掘進機によ
れば、前胴と後胴との間に設けたスライドジャッキのス
トロークを短くして、前胴と後胴とを軸方向にスライド
自在に連結した複胴型シールド掘進機の機長を短くする
ことができるため、小さな立坑でも搬入が可能となって
立坑用地の確保や立坑形成等の費用を削減することがで
きる。しかも、シールドジャッキとスライドジャッキと
を別々に伸縮動作制御可能に構成したことにより同時掘
進工法ができるので、コンパクトなシールド掘進機によ
り工期を短縮して工費等を削減できる同時掘進のシール
ド工法が実現できる。
According to the double-body shield machine of the first aspect, the stroke of the slide jack provided between the front body and the rear body is shortened so that the front body and the rear body can be slid in the axial direction. Since it is possible to shorten the length of the double-barrel type shield machine connected to, it is possible to carry in even a small vertical shaft, and it is possible to reduce costs such as securing a vertical shaft site and forming a vertical shaft. Moreover, since the shield jack and the slide jack can be separately controlled for expansion and contraction, the simultaneous excavation method can be performed, so a compact shield excavator realizes the simultaneous excavation shield method that can shorten the construction period and reduce construction costs. it can.

【0046】請求項2〜4に係る複胴型シールド掘進機
による同時掘進工法によれば、前胴と後胴とを軸方向に
スライド自在に連結し、前胴側に複数のスライドジャッ
キを具備するとともに後胴側に複数のシールドジャッキ
を具備した複胴型シールド掘進機により、掘削作業とと
もにセグメント組立作業を同時に行う同時掘進工法が可
能で、しかも、シールド掘進機の機長を短縮させること
が可能となり、コンパクトなシールド掘進機により工期
を短縮して工費等を削減できる同時掘進のシールド工法
が実現できる。
According to the simultaneous excavation method using the double-barreled shield machine according to claims 2 to 4, the front body and the rear body are axially slidably connected to each other, and a plurality of slide jacks are provided on the front body side. In addition, with the double-barrel type shield machine equipped with multiple shield jacks on the rear trunk side, it is possible to simultaneously excavate and simultaneously perform segment assembly work, and it is possible to shorten the length of the shield machine. Therefore, a compact shield excavator can realize a simultaneous excavation shield method that can shorten the construction period and reduce the construction cost.

【0047】特に、請求項2に係る同時掘進工法によれ
ば、第3工程で、複数のシールドジャッキの伸長量を調
節することによりシールド掘進機の方向制御を行うこと
ができるため、蛇行修正が容易な同時掘進のシールド工
法が可能となり、方向制御のために特別な時間を要する
ことなく作業を続けることができるので正確なトンネル
を短工期で施工して更に工費等の削減を可能とすること
ができる。
Particularly, according to the simultaneous excavation method according to claim 2, in the third step, the shield excavator can be controlled in direction by adjusting the extension amounts of the plurality of shield jacks. A simple simultaneous excavation shield method is possible, and work can be continued without requiring special time for direction control, so it is possible to construct an accurate tunnel in a short construction period and further reduce construction costs. You can

【0048】また、特に請求項3に係る同時掘進工法に
よれば、第3工程で、複数のシールドジャッキの伸長量
を調節することにより、後胴側に設けた中折機構でシー
ルド掘進機の方向制御を行いながら曲進施工をすること
ができるため、工期を大幅に短縮して工費等を削減した
曲進シールド工法が可能となる。
Further, according to the simultaneous excavation method according to claim 3, in the third step, by adjusting the extension amounts of the plurality of shield jacks, the center folding mechanism provided on the rear trunk side of the shield excavator is used. Since the bending work can be performed while controlling the direction, the bending shield construction method that significantly reduces the construction period and reduces the construction cost and the like becomes possible.

【図面の簡単な説明】[Brief description of drawings]

【図1】この出願に係る複胴型シールド掘進機の同時掘
進工法の初期状態を示す図面であり、(a) はシールド掘
進機の断面図,(b) はセグメントとシールドジャッキと
の間隙を示す側面図である。
1 is a drawing showing an initial state of a simultaneous excavation method for a double-barreled shield machine according to this application, (a) is a sectional view of the shield machine, and (b) is a gap between a segment and a shield jack. It is a side view shown.

【図2】この出願に係る複胴型シールド掘進機の同時掘
進工法における第1工程を示す図面であり、(a) はシー
ルド掘進機の断面図,(b) はセグメントとシールドジャ
ッキとの間隙を示す側面図である。
FIG. 2 is a drawing showing a first step in a simultaneous excavation method for a double-barreled shield machine according to this application, (a) is a cross-sectional view of the shield machine, and (b) is a gap between a segment and a shield jack. It is a side view which shows.

【図3】この出願に係る複胴型シールド掘進機の同時掘
進工法における第2工程を示す図面であり、(a) はシー
ルド掘進機の断面図,(b) はセグメントとシールドジャ
ッキとの間隙を示す側面図である。
FIG. 3 is a drawing showing a second step in the simultaneous excavation method for the double-shield shield machine according to this application, (a) is a cross-sectional view of the shield machine, and (b) is a gap between the segment and the shield jack. It is a side view which shows.

【図4】この出願に係る複胴型シールド掘進機の同時掘
進工法における第3工程を示す図面であり、(a) はシー
ルド掘進機の断面図,(b) はセグメントとシールドジャ
ッキとの間隙を示す側面図である。
FIG. 4 is a drawing showing a third step in the simultaneous excavation method for a double-barreled shield machine according to this application, (a) is a sectional view of the shield machine, and (b) is a gap between the segment and the shield jack. It is a side view which shows.

【図5】この出願に係る複胴型シールド掘進機の同時掘
進工法における第4工程を示す図面であり、(a) はシー
ルド掘進機の断面図,(b) はセグメントとシールドジャ
ッキとの間隙を示す側面図である。
FIG. 5 is a drawing showing a fourth step in the simultaneous excavation method for the double-barrel shield machine according to the present application, where (a) is a cross-sectional view of the shield machine and (b) is a gap between the segment and the shield jack. It is a side view which shows.

【図6】この出願に係る複胴型シールド掘進機の同時掘
進工法における第5工程を示す図面であり、(a) はシー
ルド掘進機の断面図,(b) はセグメントとシールドジャ
ッキとの間隙を示す側面図である。
FIG. 6 is a drawing showing a fifth step in the simultaneous excavation method for the double-barrel shield machine according to the present application, where (a) is a cross-sectional view of the shield machine and (b) is a gap between the segment and the shield jack. It is a side view which shows.

【図7】この出願に係る複胴型シールド掘進機の同時掘
進工法における第6工程を示す図面であり、(a) はシー
ルド掘進機の断面図,(b) はセグメントとシールドジャ
ッキとの間隙を示す側面図である。
FIG. 7 is a drawing showing a sixth step in the simultaneous excavation method for a double-barreled shield machine according to this application, where (a) is a sectional view of the shield machine and (b) is a gap between the segment and the shield jack. It is a side view which shows.

【図8】この出願に係る複胴型シールド掘進機の同時掘
進工法における第7工程を示す図面であり、(a) はシー
ルド掘進機の断面図,(b) はセグメントとシールドジャ
ッキとの間隙を示す側面図である。
FIG. 8 is a drawing showing a seventh step in the simultaneous excavation method for a double-barreled shield machine according to this application, where (a) is a sectional view of the shield machine and (b) is a gap between the segment and the shield jack. It is a side view which shows.

【図9】この出願に係る複胴型シールド掘進機の同時掘
進工法における第4工程〜第7工程においてセグメント
を組立る状態を示す図面であり、(a) は第4工程,(b)
は第5工程,(c) は第6工程,(d) は第7工程を示す。
FIG. 9 is a view showing a state in which segments are assembled in the fourth step to the seventh step in the simultaneous excavation method for the double-barreled shield excavator according to this application, (a) is the fourth step, and (b) is a drawing.
Shows the fifth step, (c) shows the sixth step, and (d) shows the seventh step.

【符号の説明】[Explanation of symbols]

1…カッタディスク 2…前胴 3…エレクタ装置 4…後胴 4A…前部後胴 4B…後部後胴 5…スライド部 6…リンク部材 7…支持フレーム 8…中折機構 8a…球面座 O…原点 H…間隙 h…セグメント組込隙間 C…セグメント CO …既設セグメント CN …新セグメント CM …キーセグメント F…スライドジャッキ R…シールドジャッキ S…複胴型シールド掘進機DESCRIPTION OF SYMBOLS 1 ... Cutter disk 2 ... Front body 3 ... Electr device 4 ... Rear body 4A ... Front rear body 4B ... Rear rear body 5 ... Slide part 6 ... Link member 7 ... Support frame 8 ... Center folding mechanism 8a ... Spherical seat O ... origin H ... gap h ... segments embedded clearance C ... segment C O ... existing segment C N ... new segment C M ... key segment F ... slide jack R ... shield jacks S ... Fukudo type shield machine

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平2−153192(JP,A) 特開 平5−306596(JP,A) 実開 平6−49593(JP,U) 特公 平3−23720(JP,B2) (58)調査した分野(Int.Cl.7,DB名) E21D 9/06 E21D 9/06 302 ─────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-2-153192 (JP, A) JP-A-5-306596 (JP, A) Actual Kaihei 6-49593 (JP, U) Japanese Patent Publication 3- 23720 (JP, B2) (58) Fields investigated (Int.Cl. 7 , DB name) E21D 9/06 E21D 9/06 302

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 前面にカッタディスクを有する前胴と後
部にセグメントを組立るエレクタ装置を有する後胴とを
軸方向にスライド自在に連結した複胴型シールド掘進機
において、 前記前胴と後胴との間に前記セグメント幅のほぼ半分の
ストロークを有する複数のスライドジャッキを設け、前
記後胴にセグメント幅と前記スライドジャッキのストロ
ークとセグメント組込隙間とを合わせたストロークとほ
ぼ同じストロークを有する複数のシールドジャッキを設
け、該シールドジャッキと前記スライドジャッキとを別
々に伸縮動作させる制御装置を設けて駆動したことを特
徴とする複胴型シールド掘進機。
1. A double-body shield machine having a front body having a cutter disk on the front surface and a rear body having an erector device for assembling segments at the rear portion slidably connected in the axial direction. A plurality of slide jacks having a stroke approximately half of the segment width, and a plurality of strokes having substantially the same stroke as the sum of the segment width, the stroke of the slide jack and the segment mounting gap in the rear body. 2. A double-body shield machine having a shield jack and a control device for separately expanding and contracting the shield jack and the slide jack.
【請求項2】 前胴と後胴とを軸方向にスライド自在に
連結し、該前胴側に複数のスライドジャッキを具備する
とともに後胴側に複数のシールドジャッキを具備した複
胴型シールド掘進機による同時掘進工法において、(a)
シールドジャッキと既設セグメントとの間に所定の間隙
を有する状態から、スライドジャッキにより前胴をセグ
メント幅のほぼ半分以下でセグメント組込隙間以上を第
1掘進させる第1工程、(b) シールドジャッキにより後
胴を前記第1工程と同掘進量だけ前進させるとともにス
ライドジャッキを同掘進量だけ縮める第2工程、(c) シ
ールドジャッキにより後胴とともに前胴を第2掘進させ
てシールドジャッキと既設セグメントとの間にセグメン
ト幅とセグメント組込隙間とを合わせた間隙を形成する
第3工程、(d) スライドジャッキにより前胴を前記第1
工程と第3工程と合わせてセグメント幅となるようにセ
グメント幅のほぼ半分以下でセグメント組込隙間以上を
掘進させるとともに、一部のシールドジャッキを縮めて
その間隙に新たなセグメントを組立る第4工程、(e) ス
ライドジャッキとシールドジャッキとにより後胴を前記
第4工程と同掘進量だけ掘進させるとともに、前記第4
工程以外の一部のシールドジャッキを縮めてその間隙に
新たなセグメントを組立る第5工程、(f) スライドジャ
ッキにより前胴を前記第1工程の第1掘進と同掘進量だ
け掘進させる第6工程、(g) スライドジャッキを停止さ
せてキーセグメントを組立る第7工程、とからなり、前
記 (b)〜(g) の第2工程〜第7工程を順次繰り返して掘
進作業とセグメント組立作業とを同時に行うことを特徴
とするシールド掘進機の同時掘進工法。
2. A double-body shield excavation in which a front body and a rear body are axially slidably connected to each other, a plurality of slide jacks are provided on the front body side, and a plurality of shield jacks are provided on the rear body side. In the simultaneous excavation method by machine, (a)
From the state that there is a predetermined gap between the shield jack and the existing segment, the first step of making the first excavation of the front body with the slide jack at less than about half of the segment width and above the segment built-in gap, (b) by the shield jack A second step in which the rear body is advanced by the same amount as the first step and the slide jack is contracted by the same amount in the same amount, (c) The shield jack and the front body are secondly advanced by the shield body and the shield jack and the existing segment are formed. A third step of forming a gap in which the segment width and the segment built-in gap are combined, and
Along with the process and the third process, the segment width is excavated at about half or less of the segment width so that the segment width is obtained, and a part of the shield jack is contracted to assemble a new segment in the gap. Step (e) The rear body is dug by the same amount as the fourth step by the slide jack and the shield jack, and
The fifth step of shrinking a part of the shield jack other than the step and assembling a new segment in the gap, (f) The forward trunk is dug by the same amount as the first step of the first step by the slide jack. Process, (g) 7th process of assembling the key segment by stopping the slide jack, and (b) to (g) 2nd to 7th processes are sequentially repeated to perform excavation work and segment assembly work. Simultaneous digging method of shield machine, characterized by performing simultaneously and.
【請求項3】 第3工程で、複数のシールドジャッキの
伸長量を調節することによりシールド掘進機の方向制御
を行うことを特徴とする請求項2記載の複胴型シールド
掘進機の同時掘進工法。
3. The simultaneous excavation method for a double-body shield machine according to claim 2, wherein the direction of the shield machine is controlled by adjusting the extension amounts of the plurality of shield jacks in the third step. .
【請求項4】 後胴側に中折機構を設け、複数のシール
ドジャッキの伸長量を調節することにより該中折機構に
よりシールド掘進機の方向制御を行いながら曲進施工を
行うことを特徴とする請求項2記載の複胴型シールド掘
進機の同時掘進工法。
4. A center folding mechanism is provided on the rear torso side, and bending operation is performed while controlling the direction of the shield machine by adjusting the extension amount of the plurality of shield jacks. The simultaneous excavation method for the double-barreled shield machine according to claim 2.
JP17386394A 1994-07-26 1994-07-26 Double-body shield excavator and its simultaneous excavation method. Expired - Fee Related JP3447116B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17386394A JP3447116B2 (en) 1994-07-26 1994-07-26 Double-body shield excavator and its simultaneous excavation method.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17386394A JP3447116B2 (en) 1994-07-26 1994-07-26 Double-body shield excavator and its simultaneous excavation method.

Publications (2)

Publication Number Publication Date
JPH0842281A JPH0842281A (en) 1996-02-13
JP3447116B2 true JP3447116B2 (en) 2003-09-16

Family

ID=15968540

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17386394A Expired - Fee Related JP3447116B2 (en) 1994-07-26 1994-07-26 Double-body shield excavator and its simultaneous excavation method.

Country Status (1)

Country Link
JP (1) JP3447116B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104879132A (en) * 2015-04-03 2015-09-02 中铁工程装备集团有限公司 Shield tunneling machine suitable for both phi 6000 and phi 6200 pipe pieces and realization method thereof
CN107882569A (en) * 2017-12-20 2018-04-06 江苏格睿特管网工程有限公司 It is a kind of to carry out driving and assembled shield machine and construction simultaneously
CN112727477A (en) * 2021-01-20 2021-04-30 中建三局集团有限公司 Hinged sliding barrel type continuous tunneling shield machine and construction method thereof
CN112796772A (en) * 2021-02-05 2021-05-14 中建三局集团有限公司 Method for transforming conventional shield into tunneling, splicing and synchronous construction shield

Also Published As

Publication number Publication date
JPH0842281A (en) 1996-02-13

Similar Documents

Publication Publication Date Title
JP2657788B2 (en) Tunnel excavator
JP3447116B2 (en) Double-body shield excavator and its simultaneous excavation method.
GB2133439A (en) Method of enlarging a tunnel
JP3104955B2 (en) Simultaneous excavation shield method
JPS6335116Y2 (en)
JP2794639B2 (en) Tunnel excavation method and shield machine used for excavation
JP4360979B2 (en) Simultaneous excavation shield method and shield excavator for simultaneous excavation
JPH08199972A (en) Simultaneously working extensible shield machine and shield driving method by use thereof
JPH0323720B2 (en)
JP3863619B2 (en) Shield machine
JP2794638B2 (en) Tunnel excavation method and shield machine used for excavation
JP4221477B2 (en) How to install a shield machine at the start of propulsion
JP2000145360A (en) Enlargement shield excavator
JPH01203593A (en) Shield excavator
JPH0325195A (en) Segment assembling method and shield machine in multi-connected shield method
JPS58213994A (en) Shield excavator
JP2860368B2 (en) Shield excavator and shield construction method using the same
JPH10121886A (en) Shield machine
JPS6217073B2 (en)
JPS6216312B2 (en)
JPS6217069B2 (en)
JPH08177377A (en) Tunnel boring machine and tunnel excavation method
JPH02266094A (en) Propelling method for shield excavator for shield construction
JPS5912318Y2 (en) Propulsion device with adjustable direction
JPS6217075B2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080704

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090704

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees