JP3445981B2 - Construction method of mud mortar using tremy tube - Google Patents

Construction method of mud mortar using tremy tube

Info

Publication number
JP3445981B2
JP3445981B2 JP2001216772A JP2001216772A JP3445981B2 JP 3445981 B2 JP3445981 B2 JP 3445981B2 JP 2001216772 A JP2001216772 A JP 2001216772A JP 2001216772 A JP2001216772 A JP 2001216772A JP 3445981 B2 JP3445981 B2 JP 3445981B2
Authority
JP
Japan
Prior art keywords
tremie
pipes
tremie pipes
underground hole
rack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001216772A
Other languages
Japanese (ja)
Other versions
JP2003027480A (en
Inventor
友一朗 弘瀬
Original Assignee
大容基功工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 大容基功工業株式会社 filed Critical 大容基功工業株式会社
Priority to JP2001216772A priority Critical patent/JP3445981B2/en
Publication of JP2003027480A publication Critical patent/JP2003027480A/en
Application granted granted Critical
Publication of JP3445981B2 publication Critical patent/JP3445981B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は場所打ち杭や地中連
続壁の構築、更には地盤改良工事等に用いられるトレミ
ー管を使用した泥土モルタルの打設工法に関し、特には
ラック本体の内部に形成された区画部に打設に必要とす
数本のトレミー管が起立した状態に収納された供給
・保管ラックを現場近傍に設置して、打設の進行に応じ
て該トレミー管を供給するとともに揚上するトレミー管
を供給・保管ラックに収納するようにした泥土モルタル
の打設工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for placing mud mortar using a tremie pipe used for construction of cast-in-place piles, continuous underground walls, ground improvement work, etc.
Inside the formed supply and storage rack for several tremie tubes of the double is accommodated in a standing state requiring the pouring to the compartment portions of the rack body installed on site near, depending on the progress of the pouring The present invention relates to a method for placing mud mortar in which a tremie pipe to be fed and lifted is stored in a supply / storage rack.

【0002】[0002]

【従来の技術】従来から各種建築物の基礎工事としての
場所打ち杭とか地中連続壁や地盤改良工事、或いは構築
方法としてリバース工法を採用する場合には、数十〜百
数十メートルの地中孔を掘削してから、該地中孔にトレ
ミー管を挿入して生コンクリートとか泥土モルタル等の
流動化材料を順次打設し、その後に鉄筋又はH型鋼等の
芯材を配設する方法、或いは掘削した地中孔に先に鉄筋
又はH型鋼等の芯材を配設し、その後にトレミー管を挿
入して生コンクリートとか泥土モルタル等の流動化材料
を順次打設して構築する工法が一般に採用されている。
地中孔の掘削法はベノト式工法とかアースドリル工法、
リバース工法等により高濃度泥水とか安定液を使用しな
がら掘削機により掘削を行い、掘削した土砂を泥水とと
もに吸引して地上に排出する方法が一般に行われてい
る。
2. Description of the Related Art Conventionally, when a cast-in-place pile, underground continuous wall or ground improvement work is used as the foundation work of various buildings, or when the reverse construction method is adopted as a construction method, the land of several tens to hundreds of tens meters is used. A method in which a tremy pipe is inserted into the underground hole, a fluidizing material such as ready-mixed concrete or mud mortar is sequentially placed after digging the intermediate hole, and then a core material such as a reinforcing bar or H-shaped steel is arranged. Alternatively, a construction method in which a core material such as a reinforcing bar or H-shaped steel is first placed in an excavated underground hole, and then a tremie pipe is inserted and a fluidizing material such as ready-mixed concrete or mud mortar is sequentially placed and constructed. Is generally adopted.
The excavation method of the underground hole is the Benoto method or the earth drill method,
Generally, a method of excavating with an excavator while using high-concentration mud water or a stable liquid by a reverse construction method and sucking the excavated earth and sand together with the mud and discharging it to the ground is generally used.

【0003】トレミー管とは前記場所打ち杭とか地中連
続壁工事において掘削した地中孔に生コンクリートや泥
土モルタル等の流動化材料を流し込む際に使用する連結
されたパイプを指している。地中孔の深度は地下130
メートルにも達するケースもあるが、一般的には地下7
0メートル程度が普通である。そして掘削した地中孔に
崩壊防止のための泥水又はベントナイト液などの低比重
の土質安定液を入れ、トレミー管を挿入して高比重の生
コンクリートやソイルセメントを該トレミー管の先端部
から流し込む。この時に低比重の土質安定液と高比重の
生コンクリートの混合を防ぐため、トレミー管の先端が
常に打ち込む材料の上場より2メートルか3メートルラ
ップさせて下部にあるようにコントロールする。
The tremie pipe refers to the cast-in-place pile or a connected pipe used when pouring a fluidizing material such as ready-mixed concrete or mud mortar into the underground hole excavated in the underground continuous wall construction. The depth of the underground hole is 130 underground.
In some cases, it can reach up to meters, but generally it is underground 7
0 meters is normal. Then, put mud water or bentonite liquid or other soil stabilization liquid of low specific gravity into the excavated underground hole, insert a tremie pipe, and pour high concrete gravity of raw concrete or soil cement from the tip of the tremie pipe. . At this time, in order to prevent mixing of the soil stabilization liquid with low specific gravity and the green concrete with high specific gravity, the tip of the tremie pipe is controlled so that it is lapped by 2 or 3 meters above the listed material to be cast and always at the bottom.

【0004】トレミー管の長さは予め種々のものが用意
されており、地中孔の深度により6メートル管、5メー
トル管,4メートル管,3メートル管,2メートル管,
1メートル管の中から選択したトレミー管を上下方向に
所定長さとなるように連結して、掘削した地中孔の底部
近傍に達する長さに延ばして使用に供している。これら
のトレミー管は、通常は地面に臨木を敷いて横置きにし
て積載してあり、使用時にはクレーンのフックを利用し
て1本ずつ吊り上げて他のトレミー管と相互に連結し、
地中孔内に挿通させて使用に供している。
Various lengths of tremie pipes are prepared in advance. Depending on the depth of the underground hole, 6m pipes, 5m pipes, 4m pipes, 3m pipes, 2m pipes,
A tremie pipe selected from 1 meter pipes is connected in a vertical direction so as to have a predetermined length, and is extended to a length reaching the vicinity of the bottom of the excavated underground hole for use. These tremie pipes are usually laid horizontally on the ground and placed horizontally, and when used, they are lifted one by one using the hooks of the crane and interconnected with other tremie pipes.
It is used by inserting it into the underground hole.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上記従
来のトレミー管を使用した泥土モルタルの打設工法は、
トレミー管の保管と操作性が良好であるとは言えず、現
場での工事施工時の能率アップをはかることが難しいと
いう課題がある。特に地中連続壁の構築には配筋材とし
てH型鋼を使用しており、各配筋材の間隙が小さいこと
によって泥土モルタルが回り込まないことがあるため、
この配筋材の間に全てトレミー管を挿入して泥土モルタ
ルを打設する必要があり、長さの異なる多数本のトレミ
ー管を常時用意しなければならない。
However, the conventional method for placing mud mortar using the tremie pipe is as follows.
It cannot be said that the storage and operability of the tremie pipe are good, and there is a problem that it is difficult to increase the efficiency during construction work on site. In particular, H-shaped steel is used as a reinforcing material in the construction of the underground continuous wall, and the mud mortar may not go around due to the small gap between the reinforcing materials.
It is necessary to insert a tremie pipe between all the reinforcing bars and pour mud mortar, and many tremie pipes with different lengths must be prepared at all times.

【0006】例えば前記したように地面に臨木を敷き、
各トレミー管を横置きにして積載した場合、使用時にク
レーンのフックを用いて縦方向に1本ずつ吊り上げるた
めの時間を必要とし、しかも施工現場に近接してトレミ
ー管保管用の広い場所を確保することが要求され、この
保管場所が乱雑となって工事進行上の支障になりやすい
という問題が生じる。
[0006] For example, as described above, a tree is laid on the ground,
When loading each tremie pipe horizontally, it takes time to lift one by one vertically using the hook of the crane at the time of use, and secure a wide space for storing the tremie pipe close to the construction site. However, there is a problem in that this storage place becomes messy and tends to hinder the progress of construction.

【0007】更にトレミー管の洗浄時には、横置きのト
レミー管を1本ずつ作業員がクルクル回転させながら中
腰で洗浄しなければならないので、多数本のトレミー管
洗浄作業は重労働になりやすく、洗浄も完璧を期すこと
が困難であるという難点がある。更にトレミー管が丸パ
イプで構成されているため、臨木の上に該トレミー管を
10数本も積み上げると崩落する危険性があり、所謂荷
崩れにより作業員がトレミー管に挟まれて怪我をする事
故が発生しやすくなり、安全性の面での問題がある。こ
のような崩落を防止するには臨木の上にトレミー管を1
列に並べるしかないが、移動時に台付けを掛けて吊り上
げるという操作ができなくなり、操作性が低下するとと
もに保管場所も一層広くなってしまうという課題が生じ
る。
[0007] Further, when cleaning the tremie pipes, the worker has to wash the horizontally placed tremie pipes one by one while rotating the twirl around the waist. The drawback is that it is difficult to achieve perfection. Furthermore, since the tremie pipe is composed of a round pipe, there is a danger that it will collapse if 10 or more tremie pipes are piled up on a tree, so that a worker is caught in the tremie pipe due to a so-called load collapse and an injury is caused. Accidents are more likely to occur and there is a problem in terms of safety. To prevent such a fall, place a tremie tube on the wood.
Although there is no choice but to arrange them in a row, there is a problem in that the operation of hanging the table while hanging it cannot be performed, which reduces the operability and further increases the storage space.

【0008】そこで本発明は上記の問題点を解決して、
地中孔内に泥土モルタルを流し込んで打設する工法にお
けるトレミー管の保管と操作性を高め、打設の進行に応
じて長さの異なるトレミー管を供給するとともに揚上す
るトレミー管を容易に収納可能として、工事施工時の安
全性と能率アップをはかることができる泥土モルタルの
打設工法を提供することを目的とするものである。
Therefore, the present invention solves the above problems,
Improve the storage and operability of the tremie pipe in the method of casting by pouring mud mortar into the underground hole, supplying tremie pipes with different lengths according to the progress of casting and facilitating the lifting tremie pipe It is an object of the present invention to provide a method for placing mud mortar that can be stored and that can improve safety and efficiency during construction work.

【0009】[0009]

【課題を解決するための手段】本発明は上記目的を達成
するために、掘削した地中孔に所定の配筋をした後、該
地中孔内に相互に連結したトレミー管を挿入し、このト
レミー管を介して泥土モルタルを流し込んで打設する工
法において、ラック本体の内部にトレミー管を個別に収
納する区画部が形成されて、各区画部内に長さが異なる
複数本のトレミー管が起立した状態に収納されたトレミ
ー管の供給・保管ラックを現場近傍に配置して、打設の
進行に応じてラック本体に起立した状態に収納された任
意の長さのトレミー管をクレーンのフックを用いて吊り
上げて供給するとともに、揚上するトレミー管を供給・
保管ラックに収納するトレミー管を使用した泥土モルタ
ルの打設工法、及びトレミー管の供給・保管ラックを現
場近傍に配置して、打設の進行に応じてラック本体に起
立した状態に収納された任意の長さのトレミー管をクレ
ーンのフックを用いて吊り上げて、複数本を連結した
後、該連結した複数本を単位として地中孔に供給するト
レミー管を使用した泥土モルタルの打設工法を提供す
る。
In order to achieve the above-mentioned object, the present invention, after arranging a predetermined amount of holes in an excavated underground hole, inserts a mutually connected tremie pipe into the underground hole, In the construction method of pouring mud mortar through this tremie pipe and placing it , the tremie pipes are individually stored inside the rack body.
The compartment to be stored is formed and the length is different in each compartment
A storage / supply rack for tremie pipes with a plurality of tremie pipes stored in an upright position was placed near the site, and stored in the rack body in an upright position as the casting progressed. The tremie pipe of any length is hoisted and supplied using the hook of the crane, and the tremie pipe to be lifted is supplied.
A method of placing mud mortar using tremie pipes stored in a storage rack, and a rack for supplying and storing tremie pipes were placed near the site and stored in a standing state on the rack body as the casting progressed. A method of placing mud mortar using a tremie pipe that feeds a tremie pipe of arbitrary length using a crane hook to connect a plurality of pipes to the underground hole provide.

【0010】更に、トレミー管の供給・保管ラックを現
場近傍に配置して、この供給・保管ラックの作業用デッ
キを利用して、打設の進行に応じてラック本体の内部に
形成された区画部内に起立した状態に収納された任意の
長さのトレミー管をクレーンのフックを用いて吊り上げ
て供給するとともに、地中孔から揚上するトレミー管を
取り外して供給・保管ラックに収納するトレミー管を使
用した泥土モルタルの打設工法、及びトレミー管の供給
・保管ラックを現場近傍に配置して、この供給・保管ラ
ックの作業用デッキを利用して、打設の進行に応じてラ
ック本体の内部に形成された区画部内に起立した状態に
収納された任意の長さのトレミー管をクレーンのフック
を用いて吊り上げて、複数本を連結した後、該連結した
複数本を単位として地中孔に供給するトレミー管を使用
した泥土モルタルの打設工法を提供する。
Further, a supply / storage rack for tremie pipes is arranged near the site, and a working deck of the supply / storage rack is utilized to form a partition formed inside the rack body in accordance with the progress of casting. The tremie pipe of any length stored in the standing state is hoisted and supplied using the hook of the crane, and the tremie pipe lifted from the underground hole is removed and stored in the supply / storage rack. Placing method for mud mortar using the above, and placing the supply / storage rack of tremie pipes near the site, and using the work deck of this supply / storage rack, A tremie pipe of an arbitrary length stored in a standing state inside a partition formed inside is lifted using a hook of a crane, and after connecting a plurality of pipes, the connected plurality is used as a unit. Providing striking 設工 method mud mortar using tremie pipe for supplying the ground hole.

【0011】前記トレミー管の供給・保管ラックは、長
さの異なるトレミー管を個別に収納する区画部が形成さ
れたラック本体と、このラック本体の周囲を取り囲む位
置に架設された作業用デッキとを具備している。該ラッ
ク本体は強度部材で構成され、トレミー管を個別に収納
する区画部の内部に横桁材と底板を配設して、長さの異
なるトレミー管の下端部を該横桁材と底板に支持した状
態として収納してある。また、前記作業用デッキは、ラ
ック本体の周囲を取り囲む位置と、該ラック本体の略中
央部分を横断する位置に架設してある。
The tremie pipe supply / storage rack includes a rack main body having a compartment for individually storing tremie pipes of different lengths, and a work deck installed at a position surrounding the periphery of the rack main body. It is equipped with. The rack body is composed of strength members and stores the tremie tubes individually
A transverse girder member and a bottom plate are disposed inside the partitioning section, and the lower end portions of the tremie pipes having different lengths are stored in a state of being supported by the transverse girder member and the bottom plate. Further, the work deck is installed at a position that surrounds the periphery of the rack body and a position that crosses the substantially central portion of the rack body.

【0012】かかる本発明によれば、掘削した地中孔に
H型鋼や鉄筋等の所定の配筋をした後、現場近傍に配置
したトレミー管の供給・保管ラックの中から打設の進行
に応じて任意の長さのトレミー管をクレーンのフックを
用いて吊り上げて供給し、かつ、地中孔から揚上するト
レミー管を収納することができるので、トレミー管の吊
り上げと収納動作がスムーズに行えるとともに現場が煩
雑になることがなく、施工能率がアップするとともに該
トレミー管の崩落事故を防止して安全性を高めることが
できる。更に、本発明によれば、トレミー管を1本ずつ
吊り上げてセットできると共に、事前に5〜6本のトレ
ミー管を連結して20m位の長さとしたものを準備して
おくことが可能となり、該複数本のトレミー管を連結し
たものを単位として地中孔内に建て込むことが可能とな
る。よって、地中孔内に建て込むトレミー管のセットは
例えば70m程度の地中孔であっても、2〜3回で終わ
ることができ、作業スピードが大きく向上する。また、
従来の横置きにして積載した場合のようにトレミー管保
管用の広い場所を取らず、トレミー管の崩落事故は発生
しないので安全性が高いという作用が得られる。
According to the present invention as described above, after the H-shaped steel, the reinforcing bar, and the like are arranged in the excavated underground hole in a predetermined manner, the tremie pipe supply / storage rack arranged in the vicinity of the site can be used for the progress of the placing. The tremie pipe of any length can be hoisted and supplied using the hook of the crane, and the tremie pipe lifted from the underground hole can be stored, so the tremie pipe can be lifted and stored smoothly. This can be done and the site is not complicated, the construction efficiency is improved, and the fall accident of the tremie pipe can be prevented to enhance the safety. Furthermore, according to the present invention, the tremie tubes can be lifted one by one and set, and it is possible to prepare 5 to 6 tremie tubes connected in advance to have a length of about 20 m, It is possible to build a unit in which a plurality of tremie pipes are connected to each other as a unit. Therefore, the set of tremie pipes to be built in the underground hole can be completed in 2-3 times even if the underground hole is about 70 m in length, and the working speed is greatly improved. Also,
Unlike the conventional case where the tremie tubes are loaded horizontally, a large space for storing the tremie tubes is not taken, and a collapse accident of the tremie tubes does not occur, so that an effect of high safety can be obtained.

【0013】[0013]

【発明の実施の形態】以下図面に基づいて本発明にかか
るトレミー管を使用した泥土モルタルの打設工法の具体
的な実施形態を説明する。従来の地中孔に先に泥土モル
タル等の流動化材料を打設した後に、芯材としてのH型
鋼等を建て込む工法では、建て込み途中において、流動
化材料の固化が始まるために、例えば70メートル程度
の深さの地中孔と構築が不可能であった。そこで、近時
は地中孔に芯材としての鉄筋やH型鋼を先に建て込み、
後からトレミー管を組み立てて、流動化材料を打設する
工法が主流となってきている。特に地中連続壁の構築に
は配筋材としてH型鋼を使用しており、各配筋材の間隙
が小さいことによって泥土モルタルが回り込まないこと
があるため、この配筋材の間に全てトレミー管を挿入し
て泥土モルタルを打設する必要があり、長さの異なる多
数本のトレミー管を常時用意しなければならない。この
工法では大数量のトレミー管を迅速に挿入することが必
要となるため、本発明によって初めて多量のトレミー管
を迅速に所定長さにまで連結して組み立てて、該連結し
た複数本を単位として地中孔に挿入することが可能とな
ったものである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A concrete embodiment of a method for placing mud mortar using a tremie pipe according to the present invention will be described below with reference to the drawings. In the conventional construction method in which the fluidizing material such as mud mortar is first placed in the underground hole, and then the H-shaped steel or the like is built as the core material, solidification of the fluidizing material starts during the building process. It was impossible to construct an underground hole with a depth of about 70 meters. Therefore, recently, the reinforcing rods and H-shaped steel as core materials are built in the underground hole first,
After that, a method of assembling a tremie pipe and placing a fluidizing material has become mainstream. In particular, H-shaped steel is used as a reinforcing bar to construct a continuous underground wall, and since the mud mortar may not get around due to the small gaps between the reinforcing bars, there is no tremie between the reinforcing bars. It is necessary to insert a pipe and pour mud mortar, and many tremie pipes with different lengths must be prepared at all times. Since this method requires rapid insertion of a large number of tremie tubes, the present invention allows for the first time to rapidly assemble a large number of tremie tubes to a predetermined length and assemble them, with the plurality of connected plenum tubes as a unit. It has become possible to insert it into the underground hole.

【0014】図1〜図8は本実施形態による場所打ち杭
工事などの地中孔への芯材建込及び泥土モルタルを打設
する工法を説明する概要図であり、先ず図1(B)に示
すように図外の掘削機を用いて地中孔1の掘削を行って
から、オーガマシンのクレーン2を利用して地中孔1の
上面に芯材ガイドベース3をセットする。同図(A)に
拡大して示したように、芯材ガイドベース3上には芯材
仮受材3aと芯材ガイドアングル3bとが縦横に配設さ
れている。
FIG. 1 to FIG. 8 are schematic views for explaining a method of constructing a core material in an underground hole and placing mud mortar in the cast-in-place pile construction according to the present embodiment. First, FIG. 1 (B) As shown in FIG. 1, after excavating the underground hole 1 by using an excavator (not shown), the core material guide base 3 is set on the upper surface of the underground hole 1 by using the crane 2 of the auger machine. As shown in the enlarged view of FIG. 1A, a core material temporary receiving material 3a and a core material guide angle 3b are vertically and horizontally arranged on the core material guide base 3.

【0015】次に図2(A)(B)に示すように、クレ
ーンのフック2aを用いて各芯材仮受材3a間に形成さ
れた空間部にH形鋼でなる芯材4,4の仮建込を行う。
この時点で各芯材4,4の側面の上端部近傍にネジコン
ナット4aを溶接する。次に図3(A)(B)に示すよ
うに芯材吊上セットであるメイントラバーサ5及び該メ
イントラバーサ5から懸垂された複数本のネジコン用ト
ラバーサ6,6の懸垂具6aの下端部を前記ネジコンナ
ット4aに連結して、図4(A)(B)に示すようにク
レーンのフック2aを用いて芯材4,4を一定の高さま
で吊り上げながら該芯材4,4の側部に幅止めプレート
7を溶接する。
Next, as shown in FIGS. 2 (A) and 2 (B), the core members 4 and 4 made of H-shaped steel are provided in the space formed between the core member temporary receiving members 3a by using the hooks 2a of the crane. The temporary construction of
At this time, the screw connut 4a is welded to the vicinity of the upper end of the side surface of each core material 4, 4. Next, as shown in FIGS. 3 (A) and 3 (B), the lower end portion of the main traverser 5 which is the core material suspension set and the suspending tools 6a of the plurality of screw controller traversers 6 and 6 suspended from the main traverser 5 are attached. While being connected to the screw connut 4a, the hooks 2a of the crane are used to lift the core members 4 and 4 to a certain height as shown in FIGS. Weld the width stop plate 7.

【0016】次に図5(A)(B)に示したように地中
孔1内に芯材4,4の建込を完了し、ネジコン受8を芯
材ガイドベース3に固定する。次に図6(C)に示した
ように本発明で採用したトレミー管の供給・保管ラック
9を現場近傍に配置して、この供給・保管ラック9の作
業用デッキ24上に作業員が立ち、ラック本体20の内
部に形成された区画部21内に起立して収納された任意
の長さのトレミー管10を選択し、クレーンのフックを
用いて該トレミー管10を吊り上げ可能な状態にセット
する。作業用デッキ24はラック本体20の周囲を取り
囲む位置と、該ラック本体20の略中央部分を横断する
位置に架設されているので、作業員によるトレミー管1
0の選択とクレーンのフックへのセット操作は容易であ
る。
Next, as shown in FIGS. 5 (A) and 5 (B), the core materials 4 and 4 are completely installed in the underground hole 1, and the screw contact 8 is fixed to the core guide base 3. Was then shown in Figure 6 (C)
Thus, the supply / storage rack 9 for tremie pipes adopted in the present invention is arranged near the site, and a worker stands on the work deck 24 of the supply / storage rack 9 and is formed inside the rack body 20. The tremie pipe 10 of an arbitrary length stored upright in the compartment 21 is selected, and the tremie pipe 10 is set to be liftable by using the hook of the crane. Since the working deck 24 is installed at a position surrounding the periphery of the rack body 20 and at a position crossing the substantially central portion of the rack body 20, the tremie pipe 1 by the worker is provided.
It is easy to select 0 and set it on the crane hook.

【0017】このとき、トレミー管を1本ずつ吊り上げ
てセットできると共に、事前に5〜6本のトレミー管を
連結して20m位の長さとしたものを準備しておくこと
が可能となり、該複数本のトレミー管を連結したものを
単位として地中孔内に建て込むことが可能となる。よっ
て、地中孔内に建て込むトレミー管のセットは例えば7
0m程度の地中孔であっても、2〜3回で終わることが
でき、作業スピードが大きく向上する。このようにトレ
ミー管の複数本を連結した後、該連結した複数本のトレ
ミー管を単位として地中孔に建て込むことができること
が本発明の特徴である。
At this time, the tremie tubes can be lifted and set one by one, and 5 to 6 tremie tubes can be connected in advance to prepare a tube having a length of about 20 m. It becomes possible to build a book by connecting the tremie pipes as a unit in the underground hole. Therefore, the set of tremie tubes built in the underground hole is, for example, 7
Even an underground hole of about 0 m can be completed in a few times, greatly improving the work speed. It is a feature of the present invention that after connecting a plurality of tremie pipes in this manner, the plurality of connected tremie pipes can be built in the underground hole as a unit.

【0018】そして同図(A)(B)に示すようにクレ
ーンのフック2aの操作によって各芯材4,4間に該ト
レミー管10を建込み、図7(A)(B)に示すように
各トレミー管10に近接して泥土モルタルの分配機11
を配置して、コンクリートミキサー12で製造された泥
土モルタルをシュート12aを用いて各トレミー管10
内に流し込み、各トレミー管10の先端が打ち込む泥土
モルタルの上場より2メートルか3メートルラップさせ
て下部にあるようにコントロールしながら打設を行う。
打設後はトレミー管10を引抜き、一定期間の養生後に
芯材固定枠を撤去して、図8に示すように泥土モルタル
40の打設が完了する。
Then, as shown in FIGS. 7A and 7B, the tremie pipe 10 is installed between the core members 4 and 4 by operating the hook 2a of the crane, and as shown in FIGS. Distributor 11 for mud mortar close to each tremie pipe 10
And the mud mortar produced by the concrete mixer 12 is placed in each tremie tube 10 using the chute 12a.
It is poured into the inside of the tremie pipe 10 and is lapped for 2 to 3 meters from the listing of the mud mortar into which the tip of each tremie pipe 10 is to be placed, and the casting is carried out while controlling so that it is at the bottom.
After the casting, the tremie pipe 10 is pulled out, the core material fixing frame is removed after curing for a certain period, and the casting of the mud mortar 40 is completed as shown in FIG.

【0019】図9は本発明で採用したトレミー管の供給
・保管ラック9を示す平面図、図10は同正面図、図1
1は同右側面図、図12は図10のA−A線に沿う断面
図である。図中の20はラック本体であり、このラック
本体20は鉄材等の強度部材で構成され、該ラック本体
20の内部にはトレミー管を個別に収納するための区画
部21,21が形成されていて、各区画部21,21内
にトレミー管10が起立した状態に収納されている。
FIG. 9 is a plan view showing a supply / storage rack 9 for tremie tubes adopted in the present invention , FIG. 10 is a front view thereof, and FIG.
1 is a right side view of the same, and FIG. 12 is a sectional view taken along the line AA of FIG. Reference numeral 20 in the drawing denotes a rack body, and the rack body 20 is composed of a strength member such as an iron material, and inside the rack body 20, partition portions 21 and 21 for individually storing the tremie tubes are formed. The tremie tube 10 is housed in each of the compartments 21 and 21 in a standing state.

【0020】図10に示したようにラック本体20には
横桁材22,22と底板23が配設されていて、長さの
異なるトレミー管10の下端部が横桁材22,22と底
板23に支持された状態として収納されている。図10
に示した例では、トレミー管10の中で10aは1メー
トル管、10bは2メートル管、10cは3メートル管
となっている。
As shown in FIG. 10, the rack body 20 is provided with cross beam members 22 and 22 and a bottom plate 23, and the lower end portions of the tremie tubes 10 having different lengths are provided with the cross beam members 22 and 22 and the bottom plate. It is stored as being supported by 23. Figure 10
In the example shown in FIG. 3, 10a is a 1-meter tube, 10b is a 2-meter tube, and 10c is a 3-meter tube in the tremie tube 10.

【0021】24はラック本体20の上部に架設された
作業用デッキであり、この作業用デッキ24の平面寸法
はラック本体20の平面寸法よりも大きくなるように構
成されており、支持部材25により作業用デッキ24の
周縁部がラック本体20の側面部に支持されている。2
6は手摺り部である。図9に示すように作業用デッキ2
4は平面視がラック本体20の周囲を取り囲む位置と、
該ラック本体20の略中央部分を横断する位置に架設さ
れている。
Reference numeral 24 denotes a work deck installed above the rack body 20. The work deck 24 has a plane size larger than that of the rack body 20. The peripheral edge of the work deck 24 is supported by the side surface of the rack body 20. Two
6 is a handrail part. Working deck 2 as shown in FIG.
4 is a position that surrounds the periphery of the rack body 20 in plan view,
The rack main body 20 is installed at a position crossing the substantially central portion thereof.

【0022】本発明で用いたトレミー管の供給・保管ラ
ック9は、各トレミー管10a,10b,10cが各区
画部21,21内に起立して収納されているため、従来
の横置きにして積載した場合のようにトレミー管保管用
の広い場所を取らず、作業用デッキ24に乗った作業員
による各トレミー管10の洗浄操作も簡単に行える上、
トレミー管10の崩落事故は発生しないので安全性が高
いという特徴がある。
The tremie tube supply / storage rack 9 used in the present invention is placed in the conventional horizontal position because the tremie tubes 10a, 10b and 10c are stood up and stored in the compartments 21 and 21. Unlike the case of loading, it does not take a large space for storing the tremie tubes, and an operator on the work deck 24 can easily perform the cleaning operation of each tremie tube 10.
Since the tremie pipe 10 does not collapse, it is characterized by high safety.

【0023】[0023]

【発明の効果】以上詳細に説明したように、本発明によ
れば現場近傍に配置したトレミー管の供給・保管ラック
ラック本体から打設の進行に応じて任意の長さのトレ
ミー管を選択して吊り上げ、かつ、地中孔から揚上する
トレミー管をそのまま供給・保管ラック内に収納するこ
とが可能であり、特に作業用デッキを利用して作業員が
ラック本体内に収納されたトレミー管の選択と、吊り上
げ可能な状態にセットする操作及びラック本体内へのト
レミー管の収納操作が容易であり、トレミー管の吊り上
げと収納動作がスムーズに行えて、現場での工事施工時
の能率を高めることができる。
As described above in detail, according to the present invention, a tremie pipe of arbitrary length is selected from the rack body of the supply / storage rack of the tremie pipe arranged near the site according to the progress of the casting. above up to hanging, and it is possible to house the tremie tube elevating from the ground hole directly in the supply and storage in a rack, in particular personnel work using the working deck is accommodated in the rack body It is easy to select a tremie pipe, set it to a state where it can be hoisted, and store the tremie pipe in the rack body.The tremie pipe can be smoothly hoisted and stowed during construction on site. Can improve the efficiency of.

【0024】更に、本発明によれば、ラック本体から
レミー管を1本ずつ吊り上げてセットできると共に、事
前に5〜6本のトレミー管を連結して20m位の長さと
したものを準備しておくことが可能となり、該複数本の
トレミー管を連結したものを単位として地中孔内に建て
込むことが可能となる。よって、地中孔内に建て込むト
レミー管のセットは例えば70m程度の地中孔であって
も、2〜3回で終わることができ、作業スピードが大き
く向上する。よって、トレミー管の複数本を連結した
後、該連結した複数本のトレミー管を単位として地中孔
に建て込むことができる。
Furthermore, according to the present invention, it is possible to set the lifting from the rack body bets <br/> Remy tube one by one, and a length of 20m position by connecting the 5-6 present tremie pipe in advance It is possible to prepare a thing, and it becomes possible to build it up in the underground hole as a unit in which the plurality of tremie pipes are connected. Therefore, the set of tremie pipes to be built in the underground hole can be completed in 2-3 times even if the underground hole is about 70 m in length, and the working speed is greatly improved. Therefore, after connecting a plurality of tremie pipes, the connected tremie pipes can be built in the underground hole as a unit.

【0025】各トレミー管はラック本体内の各区画部内
に起立して収納されているため、各トレミー管の洗浄操
作も簡単に行えて作業員の負担を軽減することができ
る。また、トレミー管を臨木の上に横置きにして積載し
た場合のようにトレミー管保管用の広い場所を取らず、
保管場所が乱雑になることが防止され、更にトレミー管
の崩落事故は発生しないので、作業員の安全性が高めら
れるという大きな効果が得られる。
Since each tremie pipe is stood up and stored in each compartment in the rack body, the washing operation of each tremie pipe can be easily performed and the burden on the operator can be reduced. In addition, it does not take a large space for storing the tremie pipe as in the case where the tremie pipe is placed horizontally on the tree and loaded.
It is possible to prevent the storage place from becoming cluttered and to prevent the collapse of the tremie pipe from occurring, so that it is possible to obtain a great effect that the safety of the worker is enhanced.

【0026】従って本発明によれば、地中孔内に生コン
クリート又は泥土モルタル等を流し込んで打設する工法
におけるトレミー管の操作性を高めるとともに該トレミ
ー管の洗浄作業を容易とし、保管時における崩落事故を
なくして安全性と能率アップをはかったトレミー管を使
用した泥土モルタルの打設工法を提供することができ
る。
Therefore, according to the present invention, the operability of the tremie pipe in the construction method of pouring ready-mixed concrete or mud mortar into the underground hole and placing it is improved, and the cleaning work of the tremie pipe is facilitated and the tremie pipe is easily stored. (EN) It is possible to provide a method for placing mud mortar using a tremie pipe, which has improved safety and efficiency by eliminating collapse accidents.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明を用いた地中孔への芯材建込及び泥土モ
ルタル打設例を示す概要図。
FIG. 1 is a schematic diagram showing an example of core material installation and mud mortar placement in an underground hole according to the present invention.

【図2】本発明を用いた泥土モルタル打設例を示す概要
図。
FIG. 2 is a schematic diagram showing an example of placing mud mortar using the present invention.

【図3】本発明を用いた泥土モルタル打設例を示す概要
図。
FIG. 3 is a schematic diagram showing an example of placing mud mortar using the present invention.

【図4】本発明を用いた泥土モルタル打設例を示す概要
図。
FIG. 4 is a schematic view showing an example of placing mud mortar using the present invention.

【図5】本発明を用いた泥土モルタル打設例を示す概要
図。
FIG. 5 is a schematic view showing an example of placing mud mortar using the present invention.

【図6】本発明を用いた泥土モルタル打設例を示す概要
図。
FIG. 6 is a schematic diagram showing an example of placing mud mortar using the present invention.

【図7】本発明を用いた泥土モルタル打設例を示す概要
図。
FIG. 7 is a schematic diagram showing an example of placing mud mortar using the present invention.

【図8】泥土モルタルの打設完了図。FIG. 8 is a diagram of completion of placing mud mortar.

【図9】本発明で用いたトレミー管の供給・保管ラック
を示す平面図。
FIG. 9 is a plan view showing a supply / storage rack for tremie tubes used in the present invention.

【図10】図9の供給・保管ラックの正面図。FIG. 10 is a front view of the supply / storage rack of FIG.

【図11】図9の供給・保管ラックの右側面図。11 is a right side view of the supply / storage rack of FIG.

【図12】図10のA−A線に沿う断面図。12 is a cross-sectional view taken along the line AA of FIG.

【符号の説明】[Explanation of symbols]

1…地中孔 2…クレーン 2a…フック 3…芯材ガイドベース 3a…芯材仮受材 3b…芯材ガイドアングル 4…芯材 5…メイントラバーサ 6…ネジコン用トラバーサ 7…幅止めプレート 8…ネジコン受 9…(トレミー管の)供給・保管ラック 10,10a,10b,10c…トレミー管 11…分配機 12…コンクリートミキサー 20…ラック本体 21…区画部 22…横桁材 23…底板 24…作業用デッキ 25…支持部材 26…手摺り部 整理番号 P3303 1 ... Underground hole 2 ... crane 2a ... hook 3 ... Core guide base 3a ... Core material temporary receiving material 3b ... Core material guide angle 4 ... Core material 5 ... Main traverser 6 ... screw controller traverser 7 ... Width stop plate 8 ... Screw contact 9 ... Supply / storage rack (of tremie pipe) 10, 10a, 10b, 10c ... Tremy tube 11 ... Distributor 12 ... Concrete mixer 20 ... Rack body 21 ... Compartment 22 ... Cross girder material 23 ... Bottom plate 24 ... Working deck 25 ... Support member 26 ... Handrail part Reference number P3303

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 15/04 E02D 5/20 101 E21B 17/00 - 19/14 ─────────────────────────────────────────────────── ─── Continuation of the front page (58) Fields surveyed (Int.Cl. 7 , DB name) E02D 15/04 E02D 5/20 101 E21B 17/00-19/14

Claims (9)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 掘削した地中孔に所定の配筋をした後、
該地中孔内に相互に連結したトレミー管を挿入し、この
トレミー管を介して泥土モルタルを流し込んで打設する
工法において、ラック本体の内部にトレミー管を個別に収納する区画部
が形成されて、各区画部内に長さが異なる複数本のトレ
ミー管が起立した状態に収納された トレミー管の供給・
保管ラックを現場近傍に配置して、打設の進行に応じて
ラック本体に起立した状態に収納された任意の長さのト
レミー管をクレーンのフックを用いて吊り上げて供給す
ることを特徴とするトレミー管を使用した泥土モルタル
の打設工法。
1. After arranging predetermined holes in the excavated underground hole,
In the construction method in which the mutually connected tremie pipes are inserted into the underground hole, and the mud mortar is poured through the tremie pipes to be placed , a partition part for individually storing the tremie pipes inside the rack body
Is formed, and multiple trays with different lengths are
Supply of tremie pipes stored in the upright state
The storage rack is located near the site, and a tremie pipe of any length stored in the rack body standing upright is lifted and supplied using the hook of the crane as the casting progresses. Placing method for mud mortar using tremie pipe.
【請求項2】 掘削した地中孔に所定の配筋をした後、
該地中孔内に相互に連結したトレミー管を挿入し、この
トレミー管を介して泥土モルタルを流し込んで打設する
工法において、ラック本体の内部にトレミー管を個別に収納する区画部
が形成されて、各区画部内に長さが異なる複数本のトレ
ミー管が起立した状態に収納された トレミー管の供給・
保管ラックを現場近傍に配置して、打設の進行に応じて
ラック本体に起立した状態に収納された任意の長さのト
レミー管をクレーンのフックを用いて吊り上げて供給す
るとともに、揚上するトレミー管を供給・保管ラックに
収納することを特徴とするトレミー管を使用した泥土モ
ルタルの打設工法。
2. After arranging predetermined holes in the excavated underground hole,
In the construction method in which the mutually connected tremie pipes are inserted into the underground hole, and the mud mortar is poured through the tremie pipes to be placed , a partition part for individually storing the tremie pipes inside the rack body
Is formed, and multiple trays with different lengths are
Supply of tremie pipes stored in the upright state
Place the storage rack near the site, and use the crane hook to hoist and feed the tremie pipe of any length stored in the rack body standing upright as the casting progresses. A method of placing mud mortar using tremie pipes, characterized by storing tremie pipes in a supply / storage rack.
【請求項3】 掘削した地中孔に所定の配筋をした後、
該地中孔内に相互に連結したトレミー管を挿入し、この
トレミー管を介して泥土モルタルを流し込んで打設する
工法において、ラック本体の内部にトレミー管を個別に収納する区画部
が形成されて、各区画部内に長さが異なる複数本のトレ
ミー管が起立した状態に収納された トレミー管の供給・
保管ラックを現場近傍に配置して、打設の進行に応じて
ラック本体に起立した状態に収納された任意の長さのト
レミー管をクレーンのフックを用いて吊り上げて、複数
本を連結した後、該連結した複数本を単位として地中孔
に供給することを特徴とするトレミー管を使用した泥土
モルタルの打設工法。
3. After arranging predetermined holes in the excavated underground hole,
In the construction method in which the mutually connected tremie pipes are inserted into the underground hole, and the mud mortar is poured through the tremie pipes to be placed , a partition part for individually storing the tremie pipes inside the rack body
Is formed, and multiple trays with different lengths are
Supply of tremie pipes stored in the upright state
After arranging the storage rack near the site and hoisting the tremie pipe of any length stored upright in the rack body according to the progress of casting using the hook of the crane and connecting multiple A method for placing mud mortar using a tremie pipe, characterized in that the connected plural units are supplied as a unit to an underground hole.
【請求項4】 掘削した地中孔に所定の配筋をした後、
該地中孔内に相互に連結したトレミー管を挿入し、この
トレミー管を介して泥土モルタルを流し込んで打設する
工法において、ラック本体の内部にトレミー管を個別に収納する区画部
が形成されて、各区画部内に長さが異なる複数本のトレ
ミー管が起立した状態に収納された トレミー管の供給・
保管ラックを現場近傍に配置して、この供給・保管ラッ
クの作業用デッキを利用して、打設の進行に応じてラッ
ク本体の内部に形成された区画部内に起立した状態に収
納された任意の長さのトレミー管をクレーンのフックを
用いて吊り上げて供給することを特徴とするトレミー管
を使用した泥土モルタルの打設工法。
4. After arranging predetermined holes in the excavated underground hole,
In the construction method in which the mutually connected tremie pipes are inserted into the underground hole, and the mud mortar is poured through the tremie pipes to be placed , a partition part for individually storing the tremie pipes inside the rack body
Is formed, and multiple trays with different lengths are
Supply of tremie pipes stored in the upright state
Arrange the storage rack near the site, and use the work deck of this supply / storage rack to store it upright in the compartment formed inside the rack body as the casting progresses. The method of placing mud mortar using tremie pipes is characterized in that the tremie pipes of the same length are supplied by hoisting them with the hook of a crane.
【請求項5】 掘削した地中孔に所定の配筋をした後、
該地中孔内に相互に連結したトレミー管を挿入し、この
トレミー管を介して泥土モルタルを流し込んで打設する
工法において、ラック本体の内部にトレミー管を個別に収納する区画部
が形成されて、各区画部内に長さが異なる複数本のトレ
ミー管が起立した状態に収納された トレミー管の供給・
保管ラックを現場近傍に配置して、この供給・保管ラッ
クの作業用デッキを利用して、打設の進行に応じてラッ
ク本体の内部に形成された区画部内に起立した状態に収
納された任意の長さのトレミー管をクレーンのフックを
用いて吊り上げて供給するとともに、地中孔から揚上す
るトレミー管を取り外して供給・保管ラックに収納する
ことを特徴とするトレミー管を使用した泥土モルタルの
打設工法。
5. After arranging predetermined holes in the excavated underground hole,
In the construction method in which the mutually connected tremie pipes are inserted into the underground hole, and the mud mortar is poured through the tremie pipes to be placed , a partition part for individually storing the tremie pipes inside the rack body
Is formed, and multiple trays with different lengths are
Supply of tremie pipes stored in the upright state
Arrange the storage rack near the site, and use the work deck of this supply / storage rack to store it upright in the compartment formed inside the rack body as the casting progresses. A mortar mortar using a tremie pipe characterized in that the tremie pipe of the length is supplied by lifting it using the hook of the crane, and the tremie pipe lifted from the underground hole is removed and stored in the supply / storage rack. Construction method.
【請求項6】 掘削した地中孔に所定の配筋をした後、
該地中孔内に相互に連結したトレミー管を挿入し、この
トレミー管を介して泥土モルタルを流し込んで打設する
工法において、ラック本体の内部にトレミー管を個別に収納する区画部
が形成されて、各区画部内に長さが異なる複数本のトレ
ミー管が起立した状態に収納された トレミー管の供給・
保管ラックを現場近傍に配置して、この供給・保管ラッ
クの作業用デッキを利用して、打設の進行に応じてラッ
ク本体の内部に形成された区画部内に起立した状態に収
納された任意の長さのトレミー管をクレーンのフックを
用いて吊り上げて、複数本を連結した後、該連結した複
数本を単位として地中孔に供給することを特徴とするト
レミー管を使用した泥土モルタルの打設工法。
6. After arranging predetermined holes in the excavated underground hole,
In the construction method in which the mutually connected tremie pipes are inserted into the underground hole, and the mud mortar is poured through the tremie pipes to be placed , a partition part for individually storing the tremie pipes inside the rack body
Is formed, and multiple trays with different lengths are
Supply of tremie pipes stored in the upright state
Arrange the storage rack near the site, and use the work deck of this supply / storage rack to store it upright in the compartment formed inside the rack body as the casting progresses. Of a mortar mortar using a tremie pipe characterized by hoisting a tremie pipe of a length using a hook of a crane, connecting a plurality of the tremie pipes, and then supplying the connected plural pipes as a unit to an underground hole Construction method.
【請求項7】 前記トレミー管の供給・保管ラックは、
長さの異なるトレミー管を個別に収納する区画部が形成
されたラック本体と、このラック本体の周囲を取り囲む
位置に架設された作業用デッキとを具備してなる請求項
4,5又は6に記載のトレミー管を使用した泥土モルタ
ルの打設工法。
7. The rack for supplying and storing the tremie pipe,
7. A rack main body in which partition sections for individually storing tremie pipes having different lengths are formed, and a working deck installed at a position surrounding the periphery of the rack main body. Placing method of mud mortar using the described tremie pipe.
【請求項8】 前記ラック本体は強度部材で構成され、
トレミー管を個別に収納する区画部の内部に横桁材と底
板を配設して、長さの異なるトレミー管の下端部を該横
桁材と底板に支持した状態として収納した請求項7に記
載のトレミー管を使用した泥土モルタルの打設工法。
8. The rack body is composed of a strength member,
The transverse girder material and the bottom plate are arranged inside the compartment for accommodating the tremie pipes individually, and the lower end portions of the tremie pipes having different lengths are accommodated as being supported by the transverse girder material and the bottom plate. Placing method of mud mortar using the described tremie pipe.
【請求項9】 前記作業用デッキは、ラック本体の周囲
を取り囲む位置と、該ラック本体の略中央部分を横断す
る位置に架設した請求項7に記載のトレミー管を使用し
た泥土モルタルの打設工法。
9. The casting of mud mortar using a tremie pipe according to claim 7, wherein the working deck is installed at a position surrounding the periphery of the rack body and at a position crossing a substantially central portion of the rack body. Construction method.
JP2001216772A 2001-07-17 2001-07-17 Construction method of mud mortar using tremy tube Expired - Fee Related JP3445981B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001216772A JP3445981B2 (en) 2001-07-17 2001-07-17 Construction method of mud mortar using tremy tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001216772A JP3445981B2 (en) 2001-07-17 2001-07-17 Construction method of mud mortar using tremy tube

Publications (2)

Publication Number Publication Date
JP2003027480A JP2003027480A (en) 2003-01-29
JP3445981B2 true JP3445981B2 (en) 2003-09-16

Family

ID=19051207

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001216772A Expired - Fee Related JP3445981B2 (en) 2001-07-17 2001-07-17 Construction method of mud mortar using tremy tube

Country Status (1)

Country Link
JP (1) JP3445981B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101216716B1 (en) * 2010-11-03 2012-12-28 주식회사 동아지질 Diaphragm wall and this construction technique

Also Published As

Publication number Publication date
JP2003027480A (en) 2003-01-29

Similar Documents

Publication Publication Date Title
JP2837128B2 (en) Construction method of cast-in-place concrete pile
CN104264682A (en) Anchor traction wall protection pile base layer concrete beam support pouring technology
CN111676893B (en) Temporary wharf structure and construction method thereof
JP3445981B2 (en) Construction method of mud mortar using tremy tube
CN110820723B (en) Construction control method for underground diaphragm wall of deep and large foundation pit support structure of station
JP6645098B2 (en) Removal method of existing pile
JP3445980B2 (en) Supply and storage method and supply and storage rack for tremy tube
CN112281922B (en) Conversion method for cantilever cover plate permanent-faced supporting pile system
CN212742565U (en) Building foundation pit supporting structure
CN111851510B (en) Earth rock foundation pit blasting excavation system and construction method applying same
CN112112167A (en) Height-limited section foundation pit supporting structure and construction method thereof
CN104631878B (en) Aluminum casting machine well construction method
KR100227537B1 (en) Process for hanging concrete large slab forms
CN213015006U (en) Bored concrete pile structure for water conservancy bridge
CN214116593U (en) Combined round wood formwork for pile foundation construction
JP7225049B2 (en) Core material installation method
CN216108512U (en) Synchronous hoisting structure for multiple lengthened sounding pipes of foundation pit reverse construction method cast-in-place pile
CN215759128U (en) Construction device for high-fill foundation cyclone pool
CN213926331U (en) Sump pit supporting template
KR102503780B1 (en) Constructing Method of Pile with Steel Pipe Reinforcement, Pile constructed by such Method, and Retaining Wall having such Piles
CN114875925B (en) Construction method of oversized deep foundation pit of subway tunnel adjacent to sea-filling stratum
JP2583830B2 (en) Construction method of concrete deep foundation pile
CN212673968U (en) Earth rock foundation pit blasting excavation system
CN212956547U (en) Foundation ditch support tower crane basis integral type structure
JP2002038475A (en) Construction method of caisson type pile

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
R150 Certificate of patent or registration of utility model

Ref document number: 3445981

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120627

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120627

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150627

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees