JP3009202U - Suspended support bracket - Google Patents

Suspended support bracket

Info

Publication number
JP3009202U
JP3009202U JP1994012766U JP1276694U JP3009202U JP 3009202 U JP3009202 U JP 3009202U JP 1994012766 U JP1994012766 U JP 1994012766U JP 1276694 U JP1276694 U JP 1276694U JP 3009202 U JP3009202 U JP 3009202U
Authority
JP
Japan
Prior art keywords
hole
diameter hole
construction material
fixing nut
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1994012766U
Other languages
Japanese (ja)
Inventor
慶一 菅谷
Original Assignee
株式会社ブレスト工業研究所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ブレスト工業研究所 filed Critical 株式会社ブレスト工業研究所
Priority to JP1994012766U priority Critical patent/JP3009202U/en
Application granted granted Critical
Publication of JP3009202U publication Critical patent/JP3009202U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

(57)【要約】 【構成】相対峙する上板2と下板3とが側板4を介して
連続形成され、上下板2,3の間に所定の造営材を挟
み、この造営材に圧着する止着ネジ6を上板2に設け
る。下板3に支持孔7を貫通し、この支持孔7に吊りボ
ルトPを着脱自在に装着する。支持孔7は、吊りボルト
Pの端部に固定した固定ナット8を挿入する大径孔7A
と、この固定ナット8が係止する小径孔7Bとを連設す
る。大径孔7Aと小径孔7Bとの境界部分に固定ナット
8を係止する係止突起7Cを設ける。 【効果】造営材に装着した支持金具に、後付けで連結具
を装着して装着作業を簡略化する。
(57) [Summary] [Structure] An upper plate 2 and a lower plate 3 which face each other are continuously formed via a side plate 4, and a predetermined construction material is sandwiched between the upper and lower plates 2 and 3 and pressure-bonded to the construction material. A fastening screw 6 is provided on the upper plate 2. The supporting hole 7 is penetrated through the lower plate 3, and the hanging bolt P is detachably attached to the supporting hole 7. The support hole 7 is a large diameter hole 7A into which a fixing nut 8 fixed to the end of the hanging bolt P is inserted.
And the small diameter hole 7B with which the fixing nut 8 is locked are connected. A locking projection 7C for locking the fixing nut 8 is provided at the boundary between the large diameter hole 7A and the small diameter hole 7B. [Effect] The attachment work can be simplified by attaching a connecting tool to the support fitting attached to the construction material afterwards.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

この考案は、型鋼等の造営材に吊りボルト等を懸吊支持する際に用いる懸吊支 持金具の改良に関する。 The present invention relates to an improvement of a suspension support fitting used when suspending and supporting a suspension bolt or the like on a construction material such as a shape steel.

【0002】[0002]

【従来の技術】[Prior art]

従来、型鋼等の造営材に吊りボルトを支持するには、当出願人が先に提案した 側面略コ字状の支持金具(登録商標パイラック)を使用している。この支持金具 は、支持金具の開口部を造営材に装着し、支持金具上端から締め付ける締め付け ボルトで支持金具を造営材に固定するもので、吊りボルトは、この支持金具の下 部に取り付けた連結具に吊りボルトの上端部を止着ネジでネジ止めするものであ る(実開平1-129408号等参照)。 Conventionally, in order to support a hanging bolt on a construction material such as a shaped steel, a support metal fitting (registered trademark: Pirac) having a substantially U-shaped side surface, which the applicant previously proposed, is used. This support metal fitting attaches the opening of the support metal fitting to the construction material and fixes the support metal fitting to the construction material with a tightening bolt that tightens from the upper end of the support metal fitting. The upper end of the hanging bolt is fastened to the fixture with a fastening screw (see Jitsukaihei 1-129408, etc.).

【0003】[0003]

【考案が解決しようとする課題】[Problems to be solved by the device]

ところが、このような連結具を設けた支持金具には、次の如き課題が残されて いた。すなわち、連結具は、支持金具の下部と造営材との間に装着するものであ るから、造営材に支持金具を装着固定する前に、連結具を支持金具に装着する必 要がある。したがって、支持金具の固定は、この連結具を支持金具の下部に載置 した状態で行われるから、支持金具の固定作業が面倒なものになっていた。 However, the support metal fitting provided with such a connecting tool has the following problems. That is, since the connector is mounted between the lower part of the support metal and the construction material, it is necessary to mount the connector on the support metal before mounting and fixing the support metal on the construction material. Therefore, the fixing of the supporting metal fittings is performed with the connecting tool placed on the lower portion of the supporting metal fittings, which makes the fixing work of the supporting metal fittings troublesome.

【0004】 そこでこの考案は、上述の課題を解消すべく創出されたもので、造営材に装着 した支持金具に、後付けで連結具を装着することができ、装着作業を簡略化する ことが可能な懸吊支持金具の提供を目的とするものである。Therefore, the present invention was created in order to solve the above-mentioned problems, and a connecting tool can be retrofitted to a support metal fitting mounted on a construction material, and the mounting work can be simplified. The purpose of the present invention is to provide a hanging suspension metal fitting.

【0005】[0005]

【課題を解決するための手段】[Means for Solving the Problems]

上述の目的を達成するため、この考案の第1の手段によると、相対峙する上板 2と下板3とが側板4を介して連続形成され、上下板2,3の間に所定の造営材 Qを挟み、この造営材Qに圧着する止着ネジ6を上板2に設け、一方、吊りボル トPを挿通する支持孔7を下板3に貫通し、この支持孔7に着脱自在に装着され て吊りボルトPの端部を連結する懸吊支持金具であって、支持孔7は、吊りボル トPの端部に固定した固定ナット8を挿入する大径孔7Aと、この固定ナット8 が係止する小径孔7Bとを連設したことにある。 In order to achieve the above-mentioned object, according to the first means of the present invention, an upper plate 2 and a lower plate 3 which face each other are continuously formed through a side plate 4, and a predetermined construction is performed between the upper and lower plates 2 and 3. A fastening screw 6 for sandwiching the material Q and crimping to the construction material Q is provided on the upper plate 2, while a supporting hole 7 for inserting the suspension bolt P is penetrated through the lower plate 3 and detachable to the supporting hole 7. Is a suspension support fitting attached to the end of the suspension bolt P, and the support hole 7 includes a large-diameter hole 7A into which a fixing nut 8 fixed to the end of the suspension bolt P is inserted, and the fixing hole 7A. This is because the small diameter hole 7B with which the nut 8 is locked is provided in a row.

【0006】 また、第2の手段の支持孔7は、大径孔7Aと小径孔7Bとの境界部分に固定 ナット8を係止する係止突起7Cを設けたことにある。The support hole 7 of the second means is provided with a locking projection 7C for locking the fixing nut 8 at the boundary between the large diameter hole 7A and the small diameter hole 7B.

【0007】[0007]

【作用】[Action]

この考案の第1の手段によると、金具本体1を造営材Qに装着固定してから、 金具本体1の支持孔7に吊りボルトPを装着する。このとき、吊りボルトPは、 吊りボルトPの端部にネジ止めした固定ナット8を、支持孔7の大径孔7Aの下 方から金具本体1の内側に挿入し、次に、この吊りボルトPを小径孔7Bがわに 移動して固定ナット8をこの小径孔7Bに係止するものである。 According to the first means of this invention, the metal fitting body 1 is mounted and fixed to the construction material Q, and then the hanging bolt P is mounted in the support hole 7 of the metal fitting body 1. At this time, for the suspension bolt P, the fixed nut 8 screwed to the end of the suspension bolt P is inserted into the inside of the metal fitting body 1 from below the large diameter hole 7A of the support hole 7, and then the suspension bolt P is mounted. The small diameter hole 7B is moved to the center of P to lock the fixing nut 8 in the small diameter hole 7B.

【0008】 また、第2の手段は、小径孔7Bに係止した固定ナット8は、吊りボルトP締 め付け時に係止突起7Cに係止するものである。The second means is that the fixed nut 8 locked in the small diameter hole 7B is locked in the locking projection 7C when the suspension bolt P is tightened.

【0009】[0009]

【実施例】【Example】

以下、この考案の実施例を図面に基づいて説明する。 An embodiment of the present invention will be described below with reference to the drawings.

【0010】 この考案懸吊支持金具は、造営材Qに固定する金具本体1と、この金具本体1 に装着する吊りボルトPとから成る。The suspension-supporting metal fitting of the present invention comprises a metal fitting body 1 fixed to the construction material Q and a hanging bolt P attached to the metal fitting body 1.

【0011】 金具本体1は、相対峙する上板2と下板3とが側板4を介して連続形成されて いる。そして、上下板2,3の間に所定の造営材Qを挟着し、この造営材Qに圧 着する止着ネジ6を上板2に設けてある(図1参照)。一方、吊りボルトPを挿 通する支持孔7を下板3に貫通している。そして、この支持孔7に吊りボルトP の端部を着脱自在に連結する(図2参照)。In the metal fitting body 1, an upper plate 2 and a lower plate 3 which face each other are continuously formed via a side plate 4. Then, a predetermined building material Q is sandwiched between the upper and lower plates 2 and 3, and a fastening screw 6 for pressing the building material Q is provided on the upper plate 2 (see FIG. 1). On the other hand, the lower plate 3 has a support hole 7 through which the hanging bolt P is inserted. Then, the end portion of the hanging bolt P 1 is detachably connected to the support hole 7 (see FIG. 2).

【0012】 支持孔7は、吊りボルトPの端部に固定した固定ナット8を挿入する大径孔7 Aと、この固定ナット8が係止する小径孔7Bとを連設してある。更に、大径孔 7Aと小径孔7Bとの境界部分に係止突起7Cを突設している(図3参照)。そ して、吊りボルトPの端部にネジ止めした固定ナット8を、支持孔7の大径孔7 Aの下方から金具本体1の内側に挿入し、次に、この吊りボルトPを小径孔7B がわに移動して固定ナット8をこの係止突起7Cに係止する(図4参照)。The support hole 7 has a large diameter hole 7 A into which a fixed nut 8 fixed to the end of the hanging bolt P is inserted and a small diameter hole 7 B to which the fixed nut 8 is locked. Further, a locking projection 7C is provided at the boundary between the large diameter hole 7A and the small diameter hole 7B (see FIG. 3). Then, the fixing nut 8 screwed to the end of the hanging bolt P is inserted into the metal fitting body 1 from below the large diameter hole 7A of the support hole 7, and then the hanging bolt P is inserted into the small diameter hole. 7B moves to the crocodile and locks the fixing nut 8 to the locking projection 7C (see FIG. 4).

【0013】 吊りボルトPは、吊りボルトPの先端部に一対の固定ナット8をネジ止めして あり、この固定ナット8間に金具本体1の下板3を挟着する。The hanging bolt P has a pair of fixing nuts 8 screwed to the tip of the hanging bolt P, and the lower plate 3 of the metal fitting body 1 is sandwiched between the fixing nuts 8.

【0014】 尚、この種の金具本体1は、板体の両側部が屈曲された断面コ字状の板体で形 成されており、吊りボルトPの上端及び固定ナット8は、この屈曲部分で形成さ れた間隙を利用して装着されるものである(図2参照)。The metal fitting body 1 of this type is formed of a plate body having a U-shaped cross section in which both sides of the plate body are bent, and the upper end of the hanging bolt P and the fixing nut 8 are formed in the bent portion. It is mounted using the gap formed by (see Fig. 2).

【0015】[0015]

【考案の効果】[Effect of device]

この考案は、上述の如く請求項1により、造営材Qに装着した支持金具1に、 後付けで連結具8を装着することができるようになった。 According to the first aspect of the present invention, as described above, the connecting tool 8 can be retrofitted to the supporting metal fitting 1 mounted on the construction material Q.

【0016】 請求項2によると、固定ナット8が係止突起7Cに係止することで、金具本体 1下方からの吊りボルトP操作による装着作業を容易に行なうことができる。According to the second aspect, since the fixing nut 8 is locked to the locking projection 7C, the mounting work can be easily performed by operating the hanging bolt P from below the metal fitting body 1.

【0017】 このように、この考案によると、造営材に装着した支持金具に、後付けで連結 具を装着することができ、装着作業を簡略化することが可能であるなどといった 実用上有益な種々の効果を奏するものである。As described above, according to the present invention, it is possible to attach the connecting tool to the support fittings attached to the construction material afterwards, and it is possible to simplify the attaching work. The effect of.

【図面の簡単な説明】[Brief description of drawings]

【図1】この考案の実施例を示す分解斜視図。FIG. 1 is an exploded perspective view showing an embodiment of the present invention.

【図2】この考案の使用状態を示す一部切欠側面図。FIG. 2 is a partially cutaway side view showing a usage state of the present invention.

【図3】この考案の支持孔を示す斜視図。FIG. 3 is a perspective view showing a support hole of the present invention.

【図4】この考案の支持孔を示す平面図。FIG. 4 is a plan view showing a supporting hole of the present invention.

【符号の説明】[Explanation of symbols]

P 吊りボルト Q 造営材 1 金具本体 2 上板 3 下板 4 側板 5 ネジ孔 6 止着ネジ 7 支持孔 7A 切欠孔 7B 小径孔 7C 係止突起 8 固定ナット P Hanging bolt Q Construction material 1 Metal fitting body 2 Upper plate 3 Lower plate 4 Side plate 5 Screw hole 6 Fastening screw 7 Support hole 7A Notch hole 7B Small diameter hole 7C Locking protrusion 8 Fixing nut

Claims (2)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 相対峙する上板と下板とが側板を介して
連続形成され、上下板の間に所定の造営材を挟み、この
造営材に圧着する止着ネジを上板に設け、一方、吊りボ
ルトを挿通する支持孔を下板に貫通し、この支持孔に着
脱自在に装着されて吊りボルトの端部を連結する懸吊支
持金具であって、支持孔は、吊りボルトの端部に固定し
た固定ナットを挿入する大径孔と、この固定ナットが係
止する小径孔とを連設したことを特徴とする懸吊支持金
具。
1. An upper plate and a lower plate facing each other are continuously formed with side plates interposed therebetween. A predetermined construction material is sandwiched between the upper and lower plates, and a fastening screw for crimping to the construction material is provided on the upper plate, while A suspension-supporting metal fitting that penetrates a lower plate through a supporting hole through which a hanging bolt is inserted, and is detachably attached to the supporting hole to connect the end of the hanging bolt. A suspension supporting metal fitting, characterized in that a large-diameter hole into which a fixed fixing nut is inserted and a small-diameter hole into which this fixing nut is locked are connected.
【請求項2】 支持孔は、大径孔と小径孔との境界部分
に固定ナットを係止する係止突起を設けた請求項1記載
の懸吊支持金具。
2. The suspension support fitting according to claim 1, wherein the support hole is provided with a locking projection for locking the fixing nut at a boundary portion between the large diameter hole and the small diameter hole.
JP1994012766U 1994-09-19 1994-09-19 Suspended support bracket Expired - Lifetime JP3009202U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1994012766U JP3009202U (en) 1994-09-19 1994-09-19 Suspended support bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1994012766U JP3009202U (en) 1994-09-19 1994-09-19 Suspended support bracket

Publications (1)

Publication Number Publication Date
JP3009202U true JP3009202U (en) 1995-04-04

Family

ID=43145003

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1994012766U Expired - Lifetime JP3009202U (en) 1994-09-19 1994-09-19 Suspended support bracket

Country Status (1)

Country Link
JP (1) JP3009202U (en)

Similar Documents

Publication Publication Date Title
JP3009202U (en) Suspended support bracket
JP3009440U (en) Suspended support bracket
JP3077974U (en) Suspension equipment for building aggregate
JP2660811B2 (en) Suspension support bracket
JP3008940U (en) Suspended support bracket
JPS6131521Y2 (en)
JPH0640735Y2 (en) Suspended support bracket
JPH0545212U (en) Right angle stopper
JP2536075Y2 (en) Safety net suspension device for construction
JPH0650572Y2 (en) Auxiliary fitting for hanging bolt support fitting
JP2858301B2 (en) Suspension support bracket
JPH0321144Y2 (en)
JP3031996U (en) Scaffold connecting bracket
JPS6133146Y2 (en)
JPH078891Y2 (en) Bolt mounting structure
JP3008181U (en) Suspended support bracket
JPH0240687Y2 (en)
JPH069217Y2 (en) Building ceramic plate mounting structure
JPH0587145U (en) Pipe clamp mounting device
JPH0615066Y2 (en) Suspended support bracket
JP2544774Y2 (en) Driver's cab hanging with work light bracket
JPS6316084Y2 (en)
JPS5848851Y2 (en) Speaker wall mounting structure
JPH0441704Y2 (en)
JP3917696B2 (en) Supports such as lighting equipment installed on the rooftop of buildings