JP2928952B2 - Joint structure between half precast concrete beam and column and its joining method - Google Patents

Joint structure between half precast concrete beam and column and its joining method

Info

Publication number
JP2928952B2
JP2928952B2 JP32767790A JP32767790A JP2928952B2 JP 2928952 B2 JP2928952 B2 JP 2928952B2 JP 32767790 A JP32767790 A JP 32767790A JP 32767790 A JP32767790 A JP 32767790A JP 2928952 B2 JP2928952 B2 JP 2928952B2
Authority
JP
Japan
Prior art keywords
column
precast concrete
joint
half precast
hooks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP32767790A
Other languages
Japanese (ja)
Other versions
JPH04198533A (en
Inventor
道雄 羽切
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP32767790A priority Critical patent/JP2928952B2/en
Publication of JPH04198533A publication Critical patent/JPH04198533A/en
Application granted granted Critical
Publication of JP2928952B2 publication Critical patent/JP2928952B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、ハーフプレキャストコンクリート(以下ハ
ーフPCaという)梁と柱との接合部の鉄筋の納まりを改
善したハーフPCa梁と柱との接合工法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a method of joining a half PCa beam and a column in which a reinforcing bar at a joint between a half precast concrete (hereinafter referred to as a half PCa) beam and a column is improved. It is about.

〔従来の技術および発明が解決しようとする課題〕[Problems to be solved by conventional technology and invention]

在来工法による鉄筋コンクリート工事は、型枠組立
て、配筋、コンクリート打設、型枠取外し、等すべて現
場作業となるため、人力作業が多い、型枠工事費が嵩
む、工期が長引く、等の欠点があるため、次第に構造体
のPCa化が普及してきた。
Reinforced concrete construction by the conventional construction method involves assembling the formwork, arranging the reinforcement, placing the concrete, removing the formwork, etc., all of which are on-site work, so there are many manpower work, the cost of the formwork construction increases, the construction period is prolonged, etc. Therefore, the use of PCa in the structure has been gradually spread.

そこで梁をPCa化し、これを柱両側に接合する場合、
従来一般に梁、柱接合部でハーフPCa梁の接合小口面を
対向させ、両接合小口面から互いに延出させた下ば筋を
柱の中心を超えて対向側の接合小口面近くで90゜上向き
に折曲げてフックを形成し、この接合部にコンクリート
を打設してフックを埋込み、PCa梁を柱に接合する工法
が行われている。
Therefore, when converting the beam to PCa and joining it to both sides of the column,
Conventionally, the joint edge of the half PCa beam is generally opposed at the joint of the beam and the column, and the lower streaks extending from both the joint edges are extended upward by 90 ° near the joint edge on the opposite side beyond the center of the column In this method, a hook is formed by forming a hook, and concrete is poured into this joint to embed the hook, and the PCa beam is joined to the column.

しかしながらこの工法では、両ハーフPCa梁を同仕様
で製作すると、両ハーフPCa梁の下ば筋が平面的にも立
体的にも同位置にきて互いに干渉するため、両梁の製作
時下ば筋を互いにずらしたものを製作する必要があり、
またこのようにすると両梁のスターラップの大きさも変
り、ハーフPCa梁の製作および現場での対応が面倒にな
る。
However, in this method, if both half PCa beams are manufactured with the same specifications, the lower streaks of both half PCa beams will come to the same position both planarly and three-dimensionally and will interfere with each other. It is necessary to make things with staggered streaks,
In addition, this also changes the size of the stirrups on both beams, making it difficult to manufacture half PCa beams and to respond on site.

また、上記工法の外に、梁、柱接合部で、対向するハ
ーフPCa梁の両小口面から延出させた各下ば筋を柱のほ
ぼ中心上で上向き90゜に折曲げ、これにスパイラル筋を
巻き、この接合部にコンクリートを打設する梁、柱接合
工法が提案されているが、この工法によると、直交する
他方向のハーフPCa梁の鉄筋の納まりが難しくなる。
In addition, besides the above method, at the beam / column joint, each lower streak extending from both small edges of the opposing half-PCa beam is bent upward at approximately 90 ° above the center of the column, and spiral A beam-column connection method has been proposed in which a bar is wound and concrete is poured into this joint. However, according to this method, it is difficult to fit the reinforcing bar of the half-PCa beam in the other direction perpendicular to the beam.

また、ハーフPCa梁を柱頭部で接合せずに通し梁と
し、柱主筋を柱頭部でハーフPCa梁に予め設けたシース
に通す工法も、これに交差する他方向のハーフPCa梁の
接合が難しく、このため柱頭部のハーフPCa梁を十字形
にすると、重量が過大になって運搬、揚重等の取扱いが
困難になる、等の支障がある。
Also, it is difficult to join the half PCa beam in the other direction that crosses the half PCa beam in the other direction crossing the half PCa beam as a through beam without joining at the column capital Therefore, if the half PCa beam at the column capital is formed in a cross shape, the weight becomes excessively large, and handling such as transportation and lifting becomes difficult.

本発明は、上記従来のハーフPCa梁と柱との接合の問
題を解決することを課題としてなされたものであって、
ハーフPCa梁と柱との接合部の鉄筋の納まりがよく、し
かも接合強度が高く、柱も従来の型枠工法は勿論、ハー
フPCa柱工法、フルPCa柱工法のいずれの柱にも実施で
き、かつ梁方向も十字梁、一字梁、丁字梁にも応用可能
なハーフPCa梁と柱との接合構造およびその接合工法を
提供することを目的としている。
The present invention has been made to solve the above-described problem of joining the conventional half PCa beam and column,
The fitting of the rebar at the joint between the half PCa beam and the column is good, and the joint strength is high, and the column can be applied to any column of the half PCa column method or the full PCa column method as well as the conventional formwork method, It is also an object of the present invention to provide a joint structure between a half PCa beam and a column which can be applied to a cross beam, a straight beam, and a T-shaped beam, and a joining method thereof.

〔課題を解決するための手段〕 上記目的を達成するため本発明は、柱に接合する一方
向のハーフプレキャストコンクリート梁は、対向する両
ハーフプレキャストコンクリート梁の各接合小口面から
互いに下ば筋を柱の中心を超えない長さ延出させて下向
き90゜折曲げたフックが形成され、上記ハーフプレキャ
ストコンクリート梁に交差する他方向のハーフプレキャ
ストコンクリート梁は、対向する両ハーフプレキャスト
コンクリート梁の各接合小口面から互いに下ば筋を柱の
中心を超えない長さ延出させて上向き90゜折曲げたフッ
クが形成され、前記一方向のハーフプレキャストコンク
リート梁の対向する各一対の下向き90゜のフック、およ
び交差する他方向のハーフプレキャストコンクリート梁
の対向する各一対の上向き90゜のフックが夫々スリーブ
に挿入され、梁、柱接合部に打設されたコンクリートに
上記スリーブとフックが埋込まれて接合されているハー
フPCa梁と柱との接合構造、および、柱の梁、柱接合部
の一方向両側には、接合小口面から下ば筋を柱の中心を
超えない長さ延出させて下向き90゜折曲げたフックを形
成した一対のハーフプレキャストコンクリート梁を、両
接合小口面を対向させて吊込み、両ハーフプレキャスト
コンクリート梁の接合小口面の各対向する一対のフック
を夫々スリーブに挿入し、上記一方向のハーフプレキャ
ストコンクリート梁に交差する方向には、接合小口面か
ら下ば筋を柱の中心を超えない長さ延出させて上向き90
゜折曲げたフックを形成した一対のハーフプレキャスト
コンクリート梁を両接合小口面を対向させて、前記方向
に交差する方向の梁、柱接合部の両側に吊込み、両ハー
フプレキャストコンクリート梁の接合小口面の各対向す
る一対のフックを夫々前記と別のスリーブに挿入し、
梁、柱接合部にコンクリートを打設し接合することを特
徴とするハーフPCa梁と柱との接合工法を特徴としてい
る。
[Means for Solving the Problems] In order to achieve the above object, the present invention provides a unidirectional half precast concrete beam joined to a column, in which a streak is formed below each joint edge of both opposing half precast concrete beams. A hook that is extended downward not to exceed the center of the column and bent 90 ° downward is formed, and the half precast concrete beam in the other direction crossing the above half precast concrete beam is connected to each of the two opposite half precast concrete beams. Hooks formed by extending the streaks downward from the fore edge to a length not exceeding the center of the column and bending upward by 90 ° are formed, and a pair of downward facing 90 ° hooks of each of the one-way half precast concrete beams are opposed to each other. , And each pair of opposing 90 ° upward hooks of half precast concrete beams intersecting with each other The half PCa beam and column joint structure, in which the sleeves and hooks are embedded and joined in concrete cast into the beam and column joints, and the beam and column joints On both sides in one direction, a pair of half precast concrete beams that form hooks that extend downward from the joint face and extend downward from the center of the column to a length that does not exceed the center of the column and are bent downward 90 °, face both joint faces Then, insert each pair of opposing hooks on the joint face of both half precast concrete beams into the sleeve, and in the direction intersecting the one-way half precast concrete beam, lower the streaks from the joint face. Extend upward not to exceed the center of the pillar
一 対 A pair of half precast concrete beams with bent hooks are hung on both sides of the beam and column joint in the direction intersecting with the two small joints, with the small joints facing each other. Insert each pair of opposite hooks of the surface into a separate sleeve from the above, respectively,
It is characterized by the method of joining half PCa beams and columns, which is characterized by placing concrete and joining the beam and column joints.

〔作用〕[Action]

叙上のごとく、本発明は、柱に接合する一方向および
これに交差する他方向のハーフPCa梁は各下ば筋を、夫
々対向する両ハーフPCa梁の各接合小口面から柱の中心
を超えない長さ対向延出させ、一方向の対向下ば筋は下
向き90゜折曲げ、他方向の対向下ば筋は上向き90゜折曲
げてフックを形成するから、ハーフPCa梁の鉄筋をずら
して製作せずとも、対向する下ば筋同士の干渉がなく、
十字二方向の梁の接合部であっても鉄筋の納まりがよ
く、また、対向する各一対のフックは夫々スリーブに挿
入され、梁、柱接合部に打設するコンクリートに埋込ま
れるから、対向するフック同士の拘束効果が生じ、強力
で確実な接合強度が得られる。
As described above, according to the present invention, the half PCa beam in one direction connecting to the column and the half PCa beam in the other direction intersecting with the column are provided with each lower streak, and the center of the column from each connecting small face of the two opposite half PCa beams. The opposite PC bar in one direction is bent 90 ° downward, and the counter lower bar in the other direction is bent 90 ° upward to form a hook. Even if you do not make it, there is no interference between opposite lower streaks,
Even at the joint of the beam in the two directions of the cross, the reinforcing bar fits well, and each pair of opposing hooks is inserted into the sleeve respectively and embedded in the concrete cast at the beam and column joint, so Thus, the effect of restraining the hooks is obtained, and a strong and reliable joining strength can be obtained.

〔実 施 例〕〔Example〕

以下本発明を図示の一実施例に基いて詳細に説明す
る。
Hereinafter, the present invention will be described in detail based on one embodiment shown in the drawings.

第1図乃至第5図は、本発明工法によって十字二方向
のハーフPCa梁を柱に接合する工程を順次示したもの
で、図を参照して本発明工法を以下説明すると、本発明
工法では、まず下階スラブ上に鉄筋コンクリート柱1を
建込む。この柱1は型枠に現場打ちコンクリートを打設
し、コンクリート硬化後型枠を取外す在来工法の柱で
も、PCa型枠にコンクリートを打設してPCa型枠を残すハ
ーフPCa柱でも、また全工場製作されたフルPCa柱であっ
てもよい。
FIGS. 1 to 5 sequentially show steps of joining a half-PCa half beam in two directions to a column by the method of the present invention. The method of the present invention will be described below with reference to the drawings. First, reinforced concrete columns 1 are built on the lower slab. This pillar 1 can be a conventional construction method in which cast-in-place concrete is cast into a formwork and a concrete form is removed after hardening, or a half PCa column in which concrete is cast into a PCa formwork and a PCa formwork is left. It may be a full PCa pillar manufactured in all factories.

柱1は上階の梁下までの高さで、主筋1aは上階のスラ
ブ面より上方に延出されている。1bはフープで、柱頭部
から上に延出された主筋1aの部には配筋しておかない。
2は柱1の上端面に埋込まれたスリーブ(第6図参照)
で、柱1両側にこの後接合する十字一方向のハーフPCa
梁3,3の横断方向に、ハーフPCa梁3の下ば筋3aと同間隔
で配列され、柱コンクリート打設時、スリーブ2内にコ
ンクリートが入るのを防ぐために、底板を付けてコンク
リート打設が行われている。このスリーブ2は換気ダク
ト等に用いられるスパイラルスリーブを利用することが
できる。
The pillar 1 has a height up to the lower part of the beam on the upper floor, and the main bar 1a extends above the slab surface on the upper floor. Reference numeral 1b denotes a hoop, and no reinforcement is provided at the main bar 1a extending upward from the capital.
Reference numeral 2 denotes a sleeve embedded in the upper end surface of the column 1 (see FIG. 6).
Then, the half PCa in one direction of the cross to be joined to both sides of the pillar 1 after this
Arranged in the transverse direction of the beams 3, 3 at the same interval as the lower streak 3a of the half PCa beam 3, and at the time of placing the pillar concrete, put a bottom plate to prevent concrete from entering the sleeve 2 and cast concrete. Has been done. As the sleeve 2, a spiral sleeve used for a ventilation duct or the like can be used.

柱1建込み後、柱1両側に十字一方向のハーフPCa梁
3,3を吊込む。このハーフPCa梁3は、その下ば筋3aを柱
の中心を超えない長さで梁小口面から延出させて下向き
90゜折曲げたフック3bが形成され、ハーフPCa梁3の吊
込みによって両ハーフPCa梁3,3の対向する各一対のフッ
ク3b,3bが柱頭部の各スリーブ2に挿入される。図中3c
は同梁3の上ば筋、3dはスターラップ、3eは接合小口面
に形成されたコッターである(第1図、第2図)。
After pillar 1 is built, half PCa beam in one direction of cross on both sides of pillar 1
Hang 3,3. This half-PCa beam 3 is extended downward from the beam forehead by extending the lower streak 3a with a length not exceeding the center of the column.
A hook 3b bent by 90 ° is formed, and the pair of opposite hooks 3b, 3b of the two half-PCa beams 3, 3 is inserted into the respective sleeves 2 of the capital by the suspension of the half-PCa beams 3. 3c in the figure
Is an upper streak of the beam 3, 3d is a stirrup, and 3e is a cotter formed on the joint edge (FIGS. 1 and 2).

十字一方向のハーフPCa梁3,3の吊込み後十字他方向の
ハーフPCa梁4,4を吊込む。このハーフPCa梁4は、下ば
筋4aを柱の中心を超えない長さ延出させて上向き90゜折
曲げたフックが形成され、このハーフPCa梁4,4の吊込み
後、両ハーフPCa梁4,4の対向する各一対のフック4bにス
リーブ5(第7図参照)を挿入する。このスリーブ5は
接合部に打設するコンクリートがスリーブ5内によくま
わるように上下貫通したものを用いる。図中4cは同梁4
の上ば筋、4dはスターラップ、4eは接合小口面に形成さ
れたコッターである(第3図、第4図)。
After the half PCa beams 3 in the cross direction are suspended, the half PCa beams 4 in the other cross direction are suspended. The half PCa beam 4 is formed with a hook formed by extending the lower streak 4a by a length that does not exceed the center of the column and bending it upward by 90 °. The sleeve 5 (see FIG. 7) is inserted into each pair of hooks 4b of the beams 4, 4 facing each other. The sleeve 5 is formed by vertically penetrating the concrete to be poured into the joint so that the concrete can be well turned into the sleeve 5. 4c in the figure is the same beam 4
The upper streak, 4d is a stirrup, and 4e is a cotter formed on the fore-edge surface (FIGS. 3 and 4).

十字両方向のハーフPCa梁3,3、4,4の吊込み終了後、
柱頭部から延出されている柱主筋1aにフープ1bを配筋
し、また十字両方向ののハーフPCa梁3,3、4,4の接合小
口面間に各上ば筋3c,3c、4c,4cを横移動させ、接合小口
面間、ハーフPCa梁3,3、4,4上面、およびスラブにコン
クリート6を一体に打設する。このコンクリート6は両
ハーフPCa梁3,3、4,4のコッター3e,4e、およびフック3
b,4bを挿入したスリーブ2,5内にまわり、ハーフPCa梁3,
4と柱1は相互に強固に接合される(第5図)。
After the suspension of the half PCa beams 3,3,4,4 in both directions of the cross,
The hoop 1b is arranged on the column main bar 1a extending from the capital, and the upper struts 3c, 3c, 4c, 4c, 3c, 3c, 4c, between the joint fronts of the half PCa beams 3, 3, 4, 4 in both directions of the cross. 4c is laterally moved, and concrete 6 is cast integrally between the small joint surfaces, the upper surfaces of the half PCa beams 3, 3, 4, 4 and the slab. The concrete 6 consists of cotters 3e, 4e and hooks 3 of both half PCa beams 3, 3, 4, 4.
b, 4b are inserted into the sleeves 2, 5 and half PCa beams 3,
4 and column 1 are firmly joined to each other (FIG. 5).

柱コンクリートとスラブコンクリートとを同時に打設
する工法の場合は、下向き90゜折曲げたフック3bを挿入
するスリーブ2を柱型枠内にサポートすると共に、柱型
枠上端部に十字両方向のハーフPCa梁3,4をサポートし、
柱とスラブにコンクリートを同時に打設する。この場
合、下向き90゜のフック3bを挿入するスリーブ2は底を
付けない。
In the case of the method of casting column concrete and slab concrete at the same time, the sleeve 2 for inserting the hook 3b bent downward by 90 ° is supported in the column formwork, and a half PCa in both directions of the cross is provided on the upper end of the column formwork. Support beams 3 and 4,
Pour concrete into columns and slabs at the same time. In this case, the bottom of the sleeve 2 into which the hook 3b of 90 ° downward is inserted does not have a bottom.

また、スラブは、型枠にコンクリートを打設し、コン
クリート硬化後型枠を取外す在来工法のスラブでも、ハ
ーフPCa床版をそのまま残すハーフPCa床版工法のスラブ
でも、梁に支架したデッキプレートにコンクリートを打
設するデツキプレート工法のスラブのいずれであっても
よい。
In addition, the deck plate supported on the beam can be used for the conventional slab in which concrete is poured into the formwork and the formwork is removed after the concrete is hardened, or in the half-PCa slab where the half-PCa slab remains as it is. Any of the slabs of the deck plate method in which concrete is poured into the slab may be used.

〔発明の効果〕〔The invention's effect〕

以上説明したように本発明は、梁をハーフPCa化した
ことによって施工の合理化が達成されると共に、柱に接
合する一方向およびこれに交差する他方向のハーフPCa
梁の各下ば筋を、夫々対向する両ハーフPCa梁の各接合
小口面から柱の中心を超えない長さ対向延出させ、一方
向の対向下ば筋は下向き90゜折曲げ、他方向の対向下ば
筋は上向き90゜折曲げてフックを形成したから、ハーフ
PCa梁の鉄筋をずらして製作せずとも、対向する下ば筋
同士の干渉がなく、直交二方向の梁の接合部であっても
鉄筋の納まりがよく、現場の施工性が大幅に向上でき、
かつハーフPCa梁製作の生産性も向上される。
As described above, the present invention achieves the rationalization of construction by converting the beam to half PCa, and the half PCa in one direction joining to the column and the other direction crossing the column.
Each lower streak of the beam is extended from each joint face of both half PCa beams facing each other for a length not exceeding the center of the column, and the lower streak in one direction is bent downward 90 °, the other direction Since the opposite lower streak was bent upward 90 ° to form a hook,
Even if the reinforcing bars of the PCa beams are not shifted, there is no interference between the lower bars facing each other, and the reinforcing bars can be fitted well even at the joint of the beams in two orthogonal directions, greatly improving the workability at the site. ,
In addition, the productivity of half PCa beam fabrication is improved.

また、対向する各一対のフックは夫々スリーブに挿入
され、梁、柱接合部に打設するコンクリートに埋込まれ
るから、対向するフック同士の拘束効果が生じ、強力で
確実な接合強度が得られる。
In addition, each pair of opposing hooks is inserted into the sleeve and embedded in concrete cast at the joint between the beam and the column, so that the effect of restraining the opposing hooks is generated, and strong and reliable joining strength is obtained. .

また、接合する梁は、実施例で説明した十字二方向の
梁に限らず、柱両側一方向の梁、柱に丁字方向に接合さ
れる梁にも、前記実施例における一部の梁の接合を省略
することで、本発明を実施することができ、広範な対応
が可能である、等の効果を奏するものである。
In addition, the beams to be joined are not limited to the two-way cross beam described in the embodiment, but also the beam in one direction on both sides of the column and the beam to be joined to the column in the T-shape direction. By omitting the above, the present invention can be implemented and a wide range of responses can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

図面は本発明の一実施例を示し、第1図乃至第5図は、
本発明工法によって柱に十字二方向のハーフPCa梁を接
合していく工程を順次示たもので、第1図は柱両側に一
方向のハーフPCa梁を吊込んだ状態の立断面図、第2図
は同上の一部切欠き平面図、第3図は柱に十字他方向の
ハーフPCa梁を吊込んだ状態の立断面図、第4図は同上
の一部切欠き平面図、第5図は柱に十字二方向のハーフ
PCa梁を接合し、施工を完了した状態の立断面図、第6
図は下向き90゜のフックを挿入したスリーブの立断面
図、第7図は上向き90゜のフックを挿入したスリーブの
立断面図である。 1……柱、2,5……スリーブ、3……十字一方向のハー
フプレキャストコンクリート梁、3a,4a……下ば筋、3b,
4b……フック、4……十字他方向のハーフプレキャスト
コンクリート梁、6……コンクリート。
The drawings illustrate one embodiment of the present invention, and FIGS.
FIG. 1 is a sectional view showing a state in which a half-PCa beam in one direction is suspended on both sides of a pillar, and a step of joining a half-PCa half beam in a two-way cross to a pillar by the method of the present invention. 2 is a partially cutaway plan view of the same as above, FIG. 3 is a vertical sectional view of a half PCa beam with a cross in the other direction suspended on a pillar, and FIG. 4 is a partially cutaway plan view of the same as above. The illustration shows a two-way half cross on a pillar
Sectional view of the state where the PCa beam was joined and the construction was completed.
The figure is an elevational sectional view of a sleeve in which a downward 90 ° hook is inserted, and FIG. 7 is an elevational sectional view of a sleeve in which an upward 90 ° hook is inserted. 1 ... pillar, 2,5 ... sleeve, 3 ... half-precast concrete beam in one direction of cross, 3a, 4a ... bottom rib, 3b,
4b: hook, 4: half precast concrete beam in cross direction, 6: concrete.

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】柱に接合する一方向のハーフプレキャスト
コンクリート梁は、対向する両ハーフプレキャストコン
クリート梁の各接合小口面から互いに下ば筋を柱の中心
を超えない長さ延出させて下向き90゜折曲げたフックが
形成され、上記ハーフプレキャストコンクリート梁に交
差する他方向のハーフプレキャストコンクリート梁は、
対向する両ハーフプレキャストコンクリート梁の各接合
小口面から互いに下ば筋を柱の中心を超えない長さ延出
させて上向き90゜折曲げたフックが形成され、前記一方
向のハーフプレキャストコンクリート梁の対向する各一
対の下向き90゜のフック、および交差する他方向のハー
フプレキャストコンクリート梁の対向する各一対の上向
き90゜のフックが夫々スリーブに挿入され、梁、柱接合
部に打設されたコンクリートに上記スリーブとフックが
埋込まれて接合されていることを特徴とするハーフプレ
キャストコンクリート梁と柱との接合構造。
The unidirectional half precast concrete beam to be joined to the column is formed by extending the streaks downward from each joint face of the opposing half precast concrete beams by a length not exceeding the center of the column.ハ ー フ A bent hook is formed and the half precast concrete beam in the other direction crossing the half precast concrete beam is
Hooks are formed by extending the streak from each joint face of both opposing half precast concrete beams downwardly to a length not exceeding the center of the column and bending upward by 90 °, and forming the hook of the one-way half precast concrete beam. Each pair of facing 90 ° downward hooks and each pair of facing upward 90 ° hooks of the half-precast concrete beam crossing each other are inserted into the sleeve, respectively, and the concrete cast at the beam / column joint. A joint structure between a half-precast concrete beam and a column, wherein the sleeve and the hook are embedded and joined to each other.
【請求項2】柱の梁、柱接合部の一方向両側には、接合
小口面から下ば筋を柱の中心を超えない長さ延出させて
下向き90゜折曲げたフックを形成した一対のハーフプレ
キャストコンクリート梁を、両接合小口面を対向させて
吊込み、両ハーフプレキャストコンクリート梁の接合小
口面の各対向する一対のフックを夫々スリーブに挿入
し、上記一方向のハーフプレキャストコンクリート梁に
交差する方向には、接合小口面から下ば筋を柱の中心を
超えない長さ延出させて上向き90゜折曲げたフックを形
成した一対のハーフプレキャストコンクリート梁を両接
合小口面を対向させて、前記方向に交差する方向の梁、
柱接合部の両側に吊込み、両ハーフプレキャストコンク
リート梁の接合小口面の各対向する一対のフックを夫々
前記と別のスリーブに挿入し、梁、柱接合部にコンクリ
ートを打設し接合することを特徴とするハーフプレキャ
ストコンクリート梁と柱との接合工法。
2. A pair of hooks formed on both sides of a column beam and a column joint in one direction by extending a lower streak from the joint edge to a length not exceeding the center of the column and bending downward by 90 °. The half precast concrete beam is hung with the two small joint faces facing each other, and each pair of opposed hooks of the small joint face of the two half precast concrete beams is inserted into the sleeve, respectively, to the one-way half precast concrete beam. In the intersecting direction, a pair of half precast concrete beams that form a hook that is bent upward by 90 ° by extending the lower streak from the joint front not to exceed the center of the column, with both joint fronts facing each other A beam in a direction intersecting with said direction,
Hanging on both sides of the column joint, insert each pair of opposing hooks on the joint face of both half precast concrete beams into separate sleeves from the above, cast concrete into the beam and column joints and join The method of joining half precast concrete beams and columns characterized by the following.
JP32767790A 1990-11-28 1990-11-28 Joint structure between half precast concrete beam and column and its joining method Expired - Lifetime JP2928952B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32767790A JP2928952B2 (en) 1990-11-28 1990-11-28 Joint structure between half precast concrete beam and column and its joining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32767790A JP2928952B2 (en) 1990-11-28 1990-11-28 Joint structure between half precast concrete beam and column and its joining method

Publications (2)

Publication Number Publication Date
JPH04198533A JPH04198533A (en) 1992-07-17
JP2928952B2 true JP2928952B2 (en) 1999-08-03

Family

ID=18201742

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32767790A Expired - Lifetime JP2928952B2 (en) 1990-11-28 1990-11-28 Joint structure between half precast concrete beam and column and its joining method

Country Status (1)

Country Link
JP (1) JP2928952B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106149875B (en) * 2016-08-24 2019-07-12 中国航天建设集团有限公司 The construction method and mounting process of double-T three-dimensional connecting elements

Also Published As

Publication number Publication date
JPH04198533A (en) 1992-07-17

Similar Documents

Publication Publication Date Title
JP2928952B2 (en) Joint structure between half precast concrete beam and column and its joining method
JPH04161542A (en) Connecting work of column and beam and its structure
JP2671765B2 (en) Prefabricated reinforced concrete structure of reinforced concrete stepped beams
JPS6312987B2 (en)
JPH0334967Y2 (en)
JPS5926001Y2 (en) Precast beam and girder joint structure
JPS6039401Y2 (en) joint reinforcing bars
JPS63533A (en) Slope frame construction work
JP2972955B2 (en) Column and beam joining method and its structure
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
JPH0513846Y2 (en)
JP2978011B2 (en) U-shaped beam formwork and method of constructing beam and beam joint using the same
JPS61169559A (en) Semi-existing concrete panel using assembled reinforcement
JPH044091Y2 (en)
JPH0343282Y2 (en)
JPH0781355B2 (en) Construction method of joist slab using precast concrete girder
JPH0135886Y2 (en)
JPH0449253Y2 (en)
JPH07569Y2 (en) Void slab
JPS6137697Y2 (en)
JPH0528248Y2 (en)
JPS61270462A (en) Construction of reinforced concrete structure
JPH0738390Y2 (en) Formwork for legal form
JPH0791862B2 (en) Concrete column / beam structure and its construction method
JPH0558704U (en) Precast reinforced concrete structure