JP2807869B2 - Construction method of ground anchor in soft ground - Google Patents

Construction method of ground anchor in soft ground

Info

Publication number
JP2807869B2
JP2807869B2 JP35302595A JP35302595A JP2807869B2 JP 2807869 B2 JP2807869 B2 JP 2807869B2 JP 35302595 A JP35302595 A JP 35302595A JP 35302595 A JP35302595 A JP 35302595A JP 2807869 B2 JP2807869 B2 JP 2807869B2
Authority
JP
Japan
Prior art keywords
ground
casing
anchor
injection rod
tip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP35302595A
Other languages
Japanese (ja)
Other versions
JPH09184137A (en
Inventor
徹 宮澤
忠雄 飯島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GURAUNDO SHISUTEMU KK
Taisei Corp
Original Assignee
GURAUNDO SHISUTEMU KK
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GURAUNDO SHISUTEMU KK, Taisei Corp filed Critical GURAUNDO SHISUTEMU KK
Priority to JP35302595A priority Critical patent/JP2807869B2/en
Publication of JPH09184137A publication Critical patent/JPH09184137A/en
Application granted granted Critical
Publication of JP2807869B2 publication Critical patent/JP2807869B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、軟弱地盤において
施工が可能な、グラウンドアンカーの施工方法に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a ground anchor which can be constructed on soft ground.

【0002】[0002]

【従来の技術】従来は、グラウンドアンカーが施工でき
る対象は、アンカーの定着層として使用できる締まった
砂層や砂礫層が存在する地盤の場合に限られている。従
来の技術によるグラウンドアンカーはこのような強固な
層を定着層としてグラウンドアンカーの引き抜き耐力を
確保するものである。
2. Description of the Related Art Conventionally, ground anchors can be constructed only on the ground where there is a tight sand layer or gravel layer that can be used as anchor anchoring layers. The ground anchor according to the prior art uses such a strong layer as a fixing layer to secure the pull-out resistance of the ground anchor.

【0003】[0003]

【本発明が解決しようとする課題】このように従来のグ
ラウンドアンカーでは強固な層の存在が前提であるか
ら、ゆるい砂層や、粘性土層などではアンカーの定着を
行うことができないと考えられていた。
As described above, the conventional ground anchor is premised on the existence of a strong layer. Therefore, it is considered that the anchor cannot be fixed with a loose sand layer or a viscous soil layer. Was.

【0004】本発明は上記したような従来の問題を解決
するためになされたもので、これまでは定着層として利
用できなかった、ゆるい砂層や、粘性土層、などにおい
て施工することができる、軟弱地盤におけるグラウンド
アンカーの施工方法を提供することを目的とする。
The present invention has been made in order to solve the above-mentioned conventional problems, and can be applied to a loose sand layer, a viscous soil layer, etc., which could not be used as a fixing layer. An object of the present invention is to provide a construction method of a ground anchor in soft ground.

【0005】[0005]

【課題を解決するための手段】上記のような目的を達成
するために、本発明の軟弱地盤におけるグラウンドアン
カーの施工方法は、グラウンドアンカー定着長部周囲の
地盤を地盤改良するものであり、地盤改良の工程で、ケ
ーシングを使用し、このケーシングによって周囲の土砂
の崩壊を防止した状態で、ケーシングの回転によって削
孔を行い、削孔が完了したら、ケーシングを、地盤改良
区間だけを引き抜き、その後に、ケーシングの内部に噴
射ロッドを挿入して、噴射ロッドの最深部の先端から、
硬化材を高圧で噴射させながら、噴射ロッドを回転させ
て徐々に引き上げ、地盤改良範囲の硬化後に、アンカー
材を挿入して定着して行う、軟弱地盤におけるグラウン
ドアンカーの施工方法を特徴としたものである。
Means for Solving the Problems In order to achieve the above object, the method of installing a ground anchor in soft ground according to the present invention is to improve the ground around the ground anchor anchoring portion, and to improve the ground. In the improvement process, using a casing, drilling is performed by rotating the casing in a state where the surrounding soil and sand are prevented from collapsing by this casing, and when drilling is completed, the casing is pulled out only the ground improvement section, and then Then, insert the injection rod inside the casing, and from the deepest end of the injection rod,
While injecting the hardening material at high pressure, rotate the injection rod gradually and gradually pull up, after the hardening of the ground improvement area, insert the anchor material and fix it, performing ground anchoring method on soft ground It is.

【0006】さらに本発明の軟弱地盤におけるグラウン
ドアンカーの施工方法は、地盤改良の工程でケーシング
を使用し、このケーシングによって周囲の土砂の崩壊を
防止した状態で、ケーシングの回転によって削孔を行
い、削孔が完了したら、ケーシングの内部に噴射ロッド
を挿入し、ケーシングを多少引き抜き、ケーシングの先
端から噴射ロッド先端が適当な長さだけ露出する状態に
固定し、ケーシングの先端から露出した状態で、噴射ロ
ッドの先端から、硬化材を噴射してケーシングと噴射ロ
ッドを一体で回転させて徐々に引き上げ、地盤改良範囲
の硬化後に、アンカー材を挿入して定着して行う、軟弱
地盤におけるグラウンドアンカーの施工方法を特徴とし
たものである。
Further, in the method of installing a ground anchor in soft ground according to the present invention, a casing is used in a ground improvement process, and drilling is performed by rotating the casing in a state where the surrounding soil and sand are prevented from being collapsed by the casing. When drilling is completed, insert the injection rod into the casing, pull out the casing slightly, fix it so that the tip of the injection rod is exposed from the tip of the casing by an appropriate length, and in the state exposed from the tip of the casing, From the tip of the injection rod, inject the hardening material, rotate the casing and the injection rod together and gradually pull up, after hardening the ground improvement area, insert the anchor material and fix it, the ground anchor in soft ground It features a construction method.

【0007】[0007]

【本発明の実施の態様】以下図面を参照しながら本発明
の軟弱地盤におけるグラウンドアンカーの施工方法の実
施例について説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method for installing a ground anchor in soft ground according to the present invention will be described below with reference to the drawings.

【0008】<イ>施工の順序 本発明の施工方法においては、次の2段階の工程によっ
て施工を行う。 アンカーの施工を予定している範囲の地盤を局部的に
地盤改良する。 改良した地盤へアンカーを施工する。 このように対象が軟弱な地盤であった場合に、アンカー
の打設範囲の地盤を改良して強固なものとし、その後に
アンカーの施工を行うことは、いわば当然の組み合わせ
ということができる。しかし実際には従来の地盤改良方
法をそのまま軟弱地盤におけるグラウンドアンカーの施
工方法へ転用しようとすると、次のような問題が存在す
る。
<A> Order of Construction In the construction method of the present invention, construction is performed by the following two steps. Locally improve the ground in the area where the anchor is to be constructed. Install anchors on the improved ground. In this way, when the target is soft ground, it is a natural combination to improve the ground in the area where the anchor is placed and make the ground strong, and then perform the anchor construction. However, in actuality, if the conventional ground improvement method is used as it is for the ground anchor construction method in soft ground, the following problems exist.

【0009】<ロ>従来の地盤の改良方法。 まず地盤を円筒状に地盤改良する従来の方法について説
明する。これは各種の方法が開発されているが、基本的
には図6に示すように、高圧ポンプdによって圧送した
硬化材aを高圧で噴射し、この硬化材aのもつエネルギ
ーで地山を切削し、同時に硬化材と現地土とを混合撹拌
する方法である。硬化材は細径のロッドbを通して供給
し、ノズルから噴射する。このロッドbを回転させなが
ら上下に移動することによってコイル状、円筒状に撹拌
した地盤改良範囲cを構成してゆくことができる。
<B> Conventional ground improvement method. First, a conventional method for improving the ground into a cylindrical shape will be described. Various methods have been developed, but basically, as shown in FIG. 6, a hardening material a pumped by a high-pressure pump d is jetted at a high pressure, and the ground is cut with the energy of the hardening material a. At the same time, the hardening material and the local soil are mixed and stirred. The hardening material is supplied through a small-diameter rod b and is ejected from a nozzle. By moving the rod b up and down while rotating, the ground improvement area c stirred in a coil shape or a cylindrical shape can be formed.

【0010】<ハ>地盤の局部的な地盤改良の問題点。 噴射ロッドを地中に挿入する場合に、その削孔方向が図
6の例のように垂直方向であれば、削孔方向が曲がる可
能性は少ない。しかし一般にアンカーは斜め方向に施工
する場合が多い。すると図7に示すように、地盤改良を
細い直径の噴射ロッドで行うことから、削孔方向が曲が
ってしまいやすい。図7は地盤改良範囲cが下側に曲が
った状態の例を示している。地盤改良の工程で削孔の方
向が曲がると、円筒状の地盤改良範囲cが設計通りに施
工できないことになる。するとその後に行うアンカーd
の打設線が途中からずれてしまい、重要なアンカー先端
の定着部では地盤改良範囲cから、地盤改良していない
範囲に抜け出してしまう可能性がある。このように円筒
状の地盤改良範囲cが、予定線からずれてしまう原因と
しては次のようなものが考えられる。
<C> Problems of local ground improvement of ground. When the injection rod is inserted into the ground, if the drilling direction is vertical as in the example of FIG. 6, there is little possibility that the drilling direction is bent. However, in general, the anchor is often installed diagonally. Then, as shown in FIG. 7, since the ground improvement is performed with the injection rod having a small diameter, the drilling direction is likely to bend. FIG. 7 shows an example of a state where the ground improvement range c is bent downward. If the direction of the drilling is bent in the ground improvement process, the cylindrical ground improvement range c cannot be constructed as designed. Then anchor d to be performed after that
May be displaced from the middle, and the anchoring portion of the important anchor tip may fall out of the ground improvement range c to a range where the ground has not been improved. The following can be considered as causes of the deviation of the cylindrical ground improvement range c from the planned line.

【0011】 ロッド先端から硬化材を噴射すると、
周囲の地盤は土砂と硬化材の液が混じり合った流動体の
状態となっている。 一方、噴射ロッドは直径の細い、剛性の低いものが使用
される。そのようなロッドは流動体の内部では移動しや
すく、噴射ロッド自身の重量でその先端が下向きに撓も
うとする傾向が発生し、孔の曲りが発生する。 削孔している孔の下側にはスライムがたまる。する
とこのスライムによってロッドの先端が上側に押し上げ
られ、孔の曲りが発生する。 地盤の土質が途中で変化する場合に、噴射によって
軟弱な層は崩れやすく、硬質な側は崩れにくい。そのた
めに、地盤改良範囲は軟弱な層の側に曲がりやすい。 ロッドの剛性が低いから、先端が礫などの局部的に
硬質な物体に当たれば、それを避ける方向に曲りやす
い。
[0011] When the hardening material is injected from the rod tip,
The surrounding ground is in a fluid state in which earth and sand and a liquid of the hardening material are mixed. On the other hand, a jet rod having a small diameter and low rigidity is used. Such a rod is likely to move inside the fluid, causing the tip of the injection rod to tend to flex downward due to the weight of the injection rod itself, resulting in bending of the hole. Slime accumulates below the hole being drilled. Then, the tip of the rod is pushed upward by the slime, and the hole is bent. When the soil quality of the ground changes on the way, the soft layer is easily collapsed by the injection, and the hard side is unlikely to collapse. Therefore, the ground improvement area is likely to bend toward the side of the soft layer. Due to the low rigidity of the rod, if the tip hits a locally hard object such as gravel, it is likely to bend in a direction to avoid it.

【0012】<ニ>本発明の地盤改良方法。 以上のような問題を避け、しかもその後のアンカーの施
工が容易であるように、本発明の地盤改良は次のような
方法で施工する。
<D> The ground improvement method of the present invention. The ground improvement of the present invention is performed by the following method so as to avoid the above problems and to facilitate the subsequent installation of the anchor.

【0013】ケーシングの利用。 まずその後の工程であるグランドアンカーに使用する予
定のケーシング1を、地盤改良にも利用する点が特徴で
ある。
Use of a casing. First, the feature is that the casing 1 to be used for the ground anchor in the subsequent process is also used for ground improvement.

【0014】削孔。(図1) このケーシング1によって周囲の土砂の崩壊を防止した
状態で、ケーシング1の回転によって削孔を行う。ケー
シング1を伴って地盤改良区間の最深部までの削孔する
が、ケーシング1は従来の噴射ロッドと異なり、剛性の
高いものを使用しているので、孔の曲りがほとんど発生
しない。
Drilling. (FIG. 1) In a state where the surrounding soil and soil are prevented from being collapsed by the casing 1, the casing 1 is drilled by rotation. Holes are drilled to the deepest part of the ground improvement section with the casing 1, but unlike the conventional injection rod, the casing 1 is made of a material having high rigidity, so that bending of the hole hardly occurs.

【0015】ケーシング1の引き抜き。(図2) このように保護された状態の削孔が完了したら、ケーシ
ング1も引き抜くが、ケーシング1は全長を引き抜くの
ではなく、地盤改良区間だけを引き抜く。その結果、地
盤改良区間にはケーシング1によって削孔した孔だけが
残り、その孔口側にはケーシング1が位置していること
になる。
[0015] Pulling out of the casing 1. (FIG. 2) When drilling in the protected state is completed, the casing 1 is also pulled out. However, the casing 1 is not pulled out of the entire length, but is pulled out only of the ground improvement section. As a result, only the hole drilled by the casing 1 remains in the ground improvement section, and the casing 1 is located on the hole opening side.

【0016】噴射ロッドの挿入。 その後に、噴射ロッド3を挿入する。噴射ロッド3は地
中に残ったケーシング1と、その先端の地盤改良範囲に
残っている孔をガイドとして、削孔先端まで容易に挿入
することができる。したがって、剛性の低い、直径の小
さい噴射ロッド3であっても、そのロッド自身によって
削孔するのではないから、従来のように孔曲りが発生す
る可能性は全くない。
Insertion of injection rod. After that, the injection rod 3 is inserted. The injection rod 3 can be easily inserted into the drilling tip by using the casing 1 remaining in the ground and the hole remaining in the ground improvement area at the tip as a guide. Therefore, even if the injection rod 3 is low in rigidity and small in diameter, it is not drilled by the rod itself, and there is no possibility that bending of the hole occurs as in the related art.

【0017】硬化材の噴射。(図3) 噴射ロッド3の最深部の先端から、硬化材4を高圧で噴
射させながら、ロッドを回転させて徐々に引き上げる。
その結果、予定の区間に正確な位置の地盤の改良範囲5
を設置することができる。
Injection of hardener. (FIG. 3) While injecting the hardening material 4 at a high pressure from the deepest end of the injection rod 3, the rod is rotated and gradually pulled up.
As a result, the ground improvement area 5 at the correct position in the planned section
Can be installed.

【0018】<ホ>地盤改良方法。(その2) 本発明のアンカー施工前の地盤改良は次に示すような方
法で施工することもできる。
<E> Ground improvement method. (Part 2) The ground improvement before anchor construction of the present invention can also be performed by the following method.

【0019】ケーシング1の利用。 この方法でも、その後の工程であるグランドアンカーに
使用する予定のケーシング1を、地盤改良にも利用する
ことは前記の方法と同様である。
Use of the casing 1. Also in this method, the casing 1 to be used for the ground anchor, which is a subsequent step, is used for ground improvement as in the above-described method.

【0020】削孔。 このケーシング1によって周囲の土砂の崩壊を防止した
状態で、ケーシング1の回転によって削孔を行う。ケー
シング1を伴って地盤改良区間の最深部までの削孔する
が、ケーシング1は従来の噴射ロッド3と異なり、剛性
の高いものを使用しているので、孔の曲りがほとんど発
生しない。
Drilling. In a state where the surrounding earth and sand are prevented from collapsing by the casing 1, the casing 1 is drilled by rotating the casing 1. Holes are drilled to the deepest part of the ground improvement section with the casing 1, but unlike the conventional injection rod 3, the casing 1 is made of a material having high rigidity, so that the hole hardly bends.

【0021】噴射ロッド3の挿入。 次に、ケーシング1の内部に噴射ロッド3を挿入する。
そしてケーシング1を多少引き抜き、ケーシングの先端
から噴射ロッド3先端が適当な長さだけ露出する状態に
固定する。この場合も、剛性の低い、直径の小さい噴射
ロッド3であっても、そのロッド自身によって削孔する
のではないから、従来のように孔曲りが発生する可能性
は全くない。
Insertion of the injection rod 3. Next, the injection rod 3 is inserted into the casing 1.
Then, the casing 1 is slightly pulled out and fixed so that the tip of the injection rod 3 is exposed from the tip of the casing by an appropriate length. Also in this case, even if the injection rod 3 is low in rigidity and small in diameter, it is not drilled by the rod itself, so there is no possibility that the hole is bent unlike the conventional case.

【0022】硬化材4の噴射。 ケーシング1の先端から露出した状態で、噴射ロッド3
の先端から、硬化材4を高圧で噴射する。そしてケーシ
ング1と噴射ロッド3を一体で回転させて徐々に引き上
げる。この方法によっても、その結果、予定の区間の正
確な位置の地盤を改良することができる。
Injection of hardening material 4 With the injection rod 3 exposed from the end of the casing 1,
, The hardening material 4 is injected at a high pressure. Then, the casing 1 and the injection rod 3 are integrally rotated and gradually pulled up. According to this method, as a result, the ground at the exact position of the scheduled section can be improved.

【0023】<ヘ>グラウンドアンカーの施工 以上のいずれの方法によっても、孔の曲りが発生しない
から、正確な位置の地盤が改良されている。しかも地盤
改良範囲5の入り口まではケーシング1が地中に残って
いるから、その方向や位置は地上から容易に判断するこ
とができる。そこで、一定の期間の後、地盤改良範囲5
が所定の設計強度を発現した時点で、地中に残したケー
シング1を利用して地盤改良部分の削孔を行う。(図
4) 削孔後に内部にアンカー引張材6を挿入し、ケーシング
1を引き抜きつつ先端側からグラウトを行って定着する
など、公知の各種の方法を利用してグラウンドアンカー
の施工を行う。(図5)
<F> Construction of Ground Anchor In any of the above-described methods, since the hole does not bend, the ground at an accurate position is improved. Moreover, since the casing 1 remains in the ground up to the entrance of the ground improvement area 5, its direction and position can be easily determined from the ground. Therefore, after a certain period, the ground improvement area 5
When a predetermined design strength is developed, the ground improvement portion is drilled using the casing 1 left in the ground. (FIG. 4) After the drilling, the anchor anchor 6 is inserted into the inside, and the ground anchor is constructed by using various known methods such as fixing by grouting from the front end side while pulling out the casing 1. (Fig. 5)

【0024】[0024]

【本発明の効果】本発明の軟弱地盤におけるグラウンド
アンカーの施工方法は以上説明したようになるから次の
ような効果を得ることができる。 <イ>軟弱地盤において斜め方向に削孔する場合には従
来の方法では孔の曲りが避けられなかった。そのため
に、アンカーの先端の定着部が、せっかく地盤改良した
地盤改良範囲から外れる可能性が存在した。しかし本発
明の方法であれば、後の工程であるアンカーの施工に用
いるケーシング1を、前の工程に使用して正確な範囲の
地盤改良が可能となった。そのためにアンカーは定着部
周囲の地盤が改良されているから、アンカー体の圧縮破
壊耐力を向上させ、アンカー体と周囲の地盤との摩擦抵
抗を増大させて、必要とするアンカー引き抜き耐力を確
保することが可能となった。 <ロ>硬化材4を高圧で噴射しつつ噴射ロッド3を引き
上げてくる場合に、土砂と硬化材4とのヘドロ状の混合
物が地上に吹き出してくる。そのヘドロ状の混合物の処
分には多額の費用が必要であった。しかるに本発明の方
法では、噴射工程の前にいったん削孔が行われており、
その空間が確保されいる。そのために削孔された孔の体
積分だけ地上へ吹き出す土の量、すなわち産業廃棄物の
量を軽減することができる。さらに削孔された孔の体積
分だけ、噴射のエネルギーで土壁を崩すという作業工程
が省略できるから、作業時間を短縮することができる。
[Effects of the present invention] Since the method of installing a ground anchor in soft ground according to the present invention is as described above, the following effects can be obtained. <a> When drilling holes in a soft ground in an oblique direction, bending of the holes cannot be avoided by the conventional method. Therefore, there is a possibility that the anchoring portion at the tip of the anchor may be out of the ground improvement area where the ground has been improved. However, according to the method of the present invention, the ground improvement in an accurate range became possible by using the casing 1 used for anchor installation in the subsequent step in the previous step. For this purpose, the anchor has improved ground around the anchorage, so it improves the compressive fracture strength of the anchor body, increases the frictional resistance between the anchor body and the surrounding ground, and secures the required anchor pull-out strength. It became possible. <B> When the injection rod 3 is pulled up while injecting the hardening material 4 at a high pressure, a sludge-like mixture of earth and sand and the hardening material 4 blows out to the ground. The disposal of the sludge-like mixture was costly. However, in the method of the present invention, drilling is performed once before the injection step,
That space is secured. Therefore, the amount of soil blown to the ground, that is, the amount of industrial waste, can be reduced by the volume of the drilled holes. Further, the operation process of breaking the earth wall with the energy of the injection can be omitted by the volume of the drilled holes, so that the operation time can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】軟弱地盤におけるグラウンドアンカーの施工順
序の説明図
FIG. 1 is an explanatory view of a construction order of ground anchors on soft ground.

【図2】軟弱地盤におけるグラウンドアンカーの施工順
序の説明図
FIG. 2 is an explanatory view of a construction order of ground anchors on soft ground.

【図3】軟弱地盤におけるグラウンドアンカーの施工順
序の説明図
FIG. 3 is an explanatory view of a construction order of ground anchors on soft ground.

【図4】軟弱地盤におけるグラウンドアンカーの施工順
序の説明図
FIG. 4 is an explanatory view of a construction order of ground anchors on soft ground.

【図5】軟弱地盤におけるグラウンドアンカーの施工順
序の説明図
FIG. 5 is an explanatory view of a construction order of ground anchors on soft ground.

【図6】従来の地盤改良方法の説明図FIG. 6 is an explanatory view of a conventional ground improvement method.

【図7】従来のグラウンドアンカーの施工上の問題点の
説明図
FIG. 7 is an explanatory view of a problem on construction of a conventional ground anchor.

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭49−57618(JP,A) 特開 昭62−143747(JP,A) 特開 平9−143975(JP,A) 特開 昭61−113924(JP,A) 特開 平5−214726(JP,A) (58)調査した分野(Int.Cl.6,DB名) E02D 5/80 E02D 3/12 101──────────────────────────────────────────────────続 き Continuation of the front page (56) References JP-A-49-57618 (JP, A) JP-A-62-143747 (JP, A) JP-A-9-143975 (JP, A) JP-A 61-143975 113924 (JP, A) JP-A-5-214726 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E02D 5/80 E02D 3/12 101

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】地盤改良の工程で、ケーシングを使用し、 このケーシングによって周囲の土砂の崩壊を防止した状
態で、ケーシングの回転によって削孔を行い、 削孔が完了したら、ケーシングを、地盤改良区間だけを
引き抜き、 その後に、ケーシングの内部に先端に高圧噴射構造を装
備した噴射ロッドを挿入して、 噴射ロッドの最深部の先端から硬化材を高圧で噴射させ
ながら、ロッドを回転させて徐々に引き上げ、地盤改良
区間に硬化材を注入し、 地盤改良範囲の硬化後に、アンカー材を挿入して定着し
て行う、 軟弱地盤におけるグラウンドアンカーの施工方法
In a ground improvement process, a casing is used, and in a state where the surrounding soil and sand are prevented from collapsing, drilling is performed by rotating the casing. When the drilling is completed, the casing is replaced with a ground improvement. Pull out only the section, then insert the injection rod equipped with a high-pressure injection structure at the tip inside the casing, rotate the rod gradually while spraying the hardening material at high pressure from the deepest end of the injection rod The ground anchor is inserted into the ground improvement section, and after the ground improvement area is hardened, the anchor material is inserted and settled.
【請求項2】地盤改良の工程でケーシングを使用し、 このケーシングによって周囲の土砂の崩壊を防止した状
態で、ケーシングの回転によって削孔を行い、 削孔が完了したら、ケーシングの内部に噴射ロッドを挿
入し、 ケーシングを多少引き抜き、ケーシングの先端から噴射
ロッド先端が適当な長さだけ露出する状態に固定し、 ケーシングの先端から噴射ロッド先端が露出した状態
で、噴射ロッドの先端から、硬化材を噴射してケーシン
グと噴射ロッドを一体で回転させて徐々に引き上げて所
定の区間を注入し、 地盤改良範囲の硬化後に、アンカー材を挿入して定着し
て行う、 軟弱地盤におけるグラウンドアンカーの施工方法
2. A casing is used in a ground improvement process, and drilling is performed by rotating the casing in a state where the surrounding soil and sand are prevented from being collapsed by the casing. When the drilling is completed, the injection rod is inserted into the casing. Then, pull out the casing a little, fix it so that the tip of the injection rod is exposed from the tip of the casing by an appropriate length, and with the tip of the injection rod exposed from the tip of the casing, remove the hardening material from the tip of the injection rod. The ground anchor is installed on soft ground by injecting a predetermined section by rotating the casing and the injection rod together and gradually pulling it up and injecting it into a predetermined section. Method
JP35302595A 1995-12-28 1995-12-28 Construction method of ground anchor in soft ground Expired - Fee Related JP2807869B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35302595A JP2807869B2 (en) 1995-12-28 1995-12-28 Construction method of ground anchor in soft ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35302595A JP2807869B2 (en) 1995-12-28 1995-12-28 Construction method of ground anchor in soft ground

Publications (2)

Publication Number Publication Date
JPH09184137A JPH09184137A (en) 1997-07-15
JP2807869B2 true JP2807869B2 (en) 1998-10-08

Family

ID=18428063

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35302595A Expired - Fee Related JP2807869B2 (en) 1995-12-28 1995-12-28 Construction method of ground anchor in soft ground

Country Status (1)

Country Link
JP (1) JP2807869B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100729661B1 (en) * 2005-09-23 2007-06-18 주식회사 에스에스씨컨설턴트 Construction method for soil improvement anchor system

Also Published As

Publication number Publication date
JPH09184137A (en) 1997-07-15

Similar Documents

Publication Publication Date Title
JPH11510574A (en) Method of putting ground anchor in the ground and anchor used for it
JP2807869B2 (en) Construction method of ground anchor in soft ground
JP2999189B1 (en) Expansion type anchor member
KR101500087B1 (en) Foundation slab reinforcement method for integral behavior with existing building and structure of the same
JP2000220142A (en) Nailing device
JP3608070B2 (en) Construction method of columnar improvements
JPH0617579B2 (en) Soil cement composite pile
KR100523116B1 (en) The steel pipe inserting method making use of the rod for injecting super pressure grout in Jet Grouting Pile
JP2019031836A (en) Repair and reinforcement method of existing structure
JPH0730562B2 (en) Reinforced earth method with tubular reinforcement
JPS5817849B2 (en) Foundation pile construction method
JPH06287943A (en) Foot protection method for tip of foundation pile and cylindrical foundation pile
JPH07305349A (en) Device for preventing tendon from rising together with ground anchor and method for construction
KR100717252B1 (en) Grouting apparatus and Method of construction work using Earth anchor
JPS6046210B2 (en) Horizontal force reinforcement pile construction method and its equipment
JP3415592B2 (en) Pile driving method of pile for pile retaining and screw head used in this method
JP2005105808A (en) Shearing force reinforcing method
KR100404756B1 (en) earth anchor method and a steel wire guide fit with the method
JP2003193465A (en) Bottom widening method for pile and its structure
JP2008280760A (en) Shear reinforcing method and filler injection method
JP2004183444A (en) Slope reinforcing method
JP3102956B2 (en) Expanded bottom anchor method
JPS6012492B2 (en) Root hardening method using ready-made piles
JPH07286327A (en) Application method of ground anchor
JP2789370B2 (en) Piling method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees