Manufacturing and stocking method of unit floor

Info

Publication number
JP2709091B2
JP2709091B2 JP23251688A JP23251688A JP2709091B2 JP 2709091 B2 JP2709091 B2 JP 2709091B2 JP 23251688 A JP23251688 A JP 23251688A JP 23251688 A JP23251688 A JP 23251688A JP 2709091 B2 JP2709091 B2 JP 2709091B2
Authority
JP
Japan
Prior art keywords
unit slab
unit
gantry
slab
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP23251688A
Other languages
Japanese (ja)
Other versions
JPH0280741A (en
Inventor
乙丙 中村
勝久 木内
徳一郎 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP23251688A priority Critical patent/JP2709091B2/en
Publication of JPH0280741A publication Critical patent/JPH0280741A/en
Application granted granted Critical
Publication of JP2709091B2 publication Critical patent/JP2709091B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は高層建物を建設する際における狭隘な敷地に
おけるユニツトフロアの製作、ストツク方法及びその装
置に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Industrial application field) The present invention relates to a method of manufacturing a unit floor in a narrow site when a high-rise building is constructed, a stocking method, and an apparatus therefor.

(従来の技術) 従来鉄骨工事の一環として、デツキプレートと小梁、
ときには大梁まで、更に設備工事、配筋工事まで一体化
したユニツトフロア工法が採用されてきた。
(Conventional technology) As part of conventional steelwork,
In some cases, unit floor construction methods have been adopted, including the construction of girders, equipment construction, and reinforcement work.

この場合、製作ヤードで製作されたユニツトスラブは
ストツクヤードで水平にストツクされ、順次本設位置に
建込まれる。
In this case, the unit slab manufactured in the manufacturing yard is horizontally stocked in the stock yard and is sequentially built at the permanent position.

(発明が解決しようとする課題) しかしながらユニツトフロア工法を採用した場合、ユ
ニツトスラブの製作及び水平ストツク面積に可成りの面
積を要するため、市街地の如く敷地に余裕のない現場で
は十分な製作、及びストツクヤードの確保ができない限
り、ユニツトフロア工法は採用し難いものとなってい
る。
(Problems to be Solved by the Invention) However, when the unit floor method is adopted, a considerable area is required for the production of the unit slab and the horizontal stock area. Unless a stockyard can be secured, the unit floor method is difficult to adopt.

本発明は前記従来技術の有する問題点に鑑みて提案さ
れたもので、その目的とする処は、作業面積を要するユ
ニツトフロア製造工程の流れの中で、ストツクヤードを
立体化し、狭隘な市街地でも積層工法を可能ならしめる
ユニツトフロアの製造、ストツク方法及び装置を提供す
る点にある。
The present invention has been proposed in view of the problems of the prior art described above, and its object is to form a three-dimensional stockyard in the flow of a unit floor manufacturing process that requires a work area, and to stack even in a narrow urban area. An object of the present invention is to provide a unit floor manufacturing and stocking method and apparatus which enable the construction method.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係るユニツトフ
ロアの製造、ストツク方法は、製作ヤードにおいて、架
台端部に荷重支持部材が出没自在に装架されたユニツト
スラブ製作架台を自走台車上載架し、同架台上にユニツ
トスラブを製作し、次いで前記自走台車を前記製作ヤー
ドに隣接するストツクヤードに移動し、同ストツクヤー
ドに設置され、且つ各隅柱に夫々架台支持ブラケツトが
多段式に配設された立体支持架構の直下に位置せしめ、
前記ユニツトスラブに設備配管を取付けたのち、同ユニ
ツトスラブを支持した前記架台を垂直移動せしめ、同架
台端部より荷重支持部材を突出せしめて前記架台支持ブ
ラケツト上に支持せしめ、以下順次前記の工程を繰返し
てユニツトスラブが載架された前記架台を立体的にスト
ツクするように構成されている。
(Means for Solving the Problems) In order to achieve the above object, a method of manufacturing and stocking a unit floor according to the present invention is directed to a unit in which a load support member is mounted at a gantry end at an end of a gantry in a production yard. A slab production platform is mounted on a self-propelled trolley, a unit slab is manufactured on the gantry, and then the self-propelled trolley is moved to a stockyard adjacent to the production yard, and is installed in the stockyard, and each corner pillar has a respective one. The gantry support bracket is located directly below the three-dimensional support frame arranged in multiple stages,
After attaching the equipment pipe to the unit slab, the gantry supporting the unit slab is moved vertically, a load supporting member is protruded from an end of the gantry, and is supported on the gantry supporting bracket. Is repeated so that the gantry on which the unit slab is mounted is three-dimensionally stocked.

前記の方法を効果的に遂行しうるよう、本発明に係る
ユニツトフロアの製造、ストツク装置は、ユニツトスラ
ブの製作ヤード及び同製作ヤードに隣接するユニツトス
ラブのストツクヤード、前記両ヤードに跨って敷設され
たレール上を移動する自走台車、同自走台車上に載架さ
れ、端部に荷重受部材が出没自在に装架されたユニツト
スラブ製作架台、前記ストツクヤードに設置され各隅柱
に夫々多段式に配設された前記荷重受部材の支持ブラケ
ツト、及び前記ユニツトスラブ製作架台の吊上装置を具
えた立体支持架構より構成されている。
In order to effectively carry out the above-mentioned method, the unit floor manufacturing and stocking device according to the present invention is laid across the stock yard of the unit slab and the stock yard of the unit slab adjacent to the manufacturing yard. A self-propelled carriage that moves on a rail that has been moved, a unit slab production platform that is mounted on the self-propelled carriage, and a load receiving member is mounted at the end so that it can move in and out, and a multi-stage is installed on each corner post installed on the stockyard. It comprises a support bracket for the load receiving member arranged in a formula and a three-dimensional support frame provided with a lifting device for the unit slab production stand.

(作用) 本発明は前記したように構成されているので、製作ヤ
ードにおいて走行台車にユニツトスラブ製作架台を載架
し、同架台上にユニツトスラブを製作して前記自走台車
を製作ヤードに隣接するストツクヤードに移動し、同ス
トツクヤードに設置された立体支持架構の直下に位置せ
しめ、前記ユニツトスラブに設備配管を取付ける。
(Operation) Since the present invention is configured as described above, a unit slab production gantry is mounted on a traveling vehicle in a production yard, a unit slab is produced on the gantry, and the self-propelled vehicle is placed adjacent to the production yard. To the stock yard to be installed, and positioned immediately below the three-dimensional support frame installed in the stock yard, and install equipment piping to the unit slab.

次いで前記したように製作が完了したユニツトスラブ
を載架した状態で、前記ユニツトスラブ製作架台を垂直
移動させ、前記立体支持架構の隅柱における所要段の架
台支持ブラケツト上まで移動せしめて前記架台端部より
荷重支持部材を進出させ、同部材を前記ブラケツト上に
載架することによって、ユニツトスラブ製作架台をユニ
ツトスラブとともに前記立体架構に支持せしめる。
Next, with the unit slab, which has been manufactured as described above, mounted thereon, the unit slab manufacturing base is vertically moved, and is moved to the required level of the base support bracket in the corner post of the three-dimensional support frame, and the base end The load supporting member is advanced from the portion, and the member is mounted on the bracket, thereby supporting the unit slab production stand together with the unit slab on the three-dimensional frame.

以下順次前記の工程を繰返すことによって、ユニツト
スラブを載架したユニツトスラブ架台は、前記立体架構
に多段式にストツクされるものであり、建方順序に合わ
せて順次上方のユニツトスラブより所要の本設位置に搬
入される。
By repeating the above steps sequentially, the unit slab base on which the unit slab is mounted is stocked in a multi-stage manner on the three-dimensional frame, and the required books are sequentially read from the upper unit slab in accordance with the construction order. It is carried into the setting position.

(実施例) 以下本発明を図示の実施例について説明する。(Example) Hereinafter, the present invention will be described with reference to an illustrated example.

(A)は製作ヤード、(B)は同製作ヤード(A)に
隣接して設けられたストツクヤードで、前記両ヤードに
跨ってレール(1)が敷設され、同レール(1)上に自
走台車(2)が載置されている。
(A) is a production yard, (B) is a stockyard provided adjacent to the production yard (A), and a rail (1) is laid across the two yards, and runs on the rail (1) by itself. The cart (2) is mounted.

同自走台車(2)は図示せぬ、電動モーターによって
駆動される車輪(3)が装架された走行装置(4)を具
え、同走行装置(4)の上部間にはユニツトスラブ製作
架台(5)を支持するための受梁(6)が横架されてい
る。
The self-propelled carriage (2) includes a traveling device (4) on which wheels (3) driven by an electric motor are mounted, not shown, and a unit slab production stand is provided between upper portions of the traveling device (4). A receiving beam (6) for supporting (5) is suspended.

前記ユニツトスラブ製作架台(5)は前記レール
(1)と平行に延びる左右一双のH形鋼製の側枠材
(7)をH形鋼製横架材(8)で連結して構成され、前
記側枠体材(7)の端部には左右一双の溝型鋼製の荷重
自重部材(9)が出没自在なように可摺動的に嵌装され
ている。
The unit slab production stand (5) is constructed by connecting a pair of left and right H-shaped steel side frame members (7) extending parallel to the rail (1) with an H-shaped steel horizontal member (8), At the end of the side frame member (7), a pair of right and left grooved steel load weight members (9) are slidably fitted so as to be able to come and go.

図中(10)は前記側枠材(7)の上下フランジ外側縁
間に所定間隔に配設された、前記荷重支持部材(9)の
案内用垂直部片、(11)は左右一双の同荷重支持部材
(9)の連結部片、(12)は前記側枠材(7)に配設さ
れた吊上環で吊上げ用ワイヤーロープ(13)が繋着され
るようになっている。
In the drawing, (10) is a vertical piece for guiding the load supporting member (9) disposed at a predetermined interval between outer edges of the upper and lower flanges of the side frame member (7), and (11) is a pair of right and left same. The connecting piece (12) of the load supporting member (9) is configured such that a lifting wire rope (13) is connected thereto by a lifting ring disposed on the side frame member (7).

更に製作ヤード(A)には前記レール(1)と平行に
敷設されたレール(14)上を走行する走行クレーン(1
5)が配設され、同クレーン(15)によってユニツトス
ラブ製作用資材が運搬されるようになっている。
Further, in the production yard (A), a traveling crane (1) traveling on a rail (14) laid in parallel with the rail (1).
5) is arranged, and the crane (15) is used to transport the unit slab working materials.

(16)は製作ヤード(A)に出入するトラツク、(1
7)は同製作ヤード(A)に設けられた小梁のストツク
ヤードである。
(16) is the track entering and leaving the production yard (A), (1)
7) is a stockyard of small beams provided in the production yard (A).

ストツクヤード(B)には立体支持架構(C)が設置
され、同架構(C)の4隅には、相対する一双のH形鋼
製柱材(18)(18′)をラチス材(19)を連結してなる
合成柱が立設され、前後、左右に相対する柱間に横架材
(20)及びブレーシング(21)が連結され、前記柱材
(18)のストツクヤード(B)中心側に指向するフラン
ジ面には、上下方向に亘って所定間隔毎に支持ブラケツ
ト(22)が配設され、また頂部横架材には、前記吊上げ
用ワイヤーロープ(13)の吊上装置(23)が横架されて
いる。
A three-dimensional support frame (C) is installed in the stockyard (B), and a pair of opposed H-shaped steel columns (18) and (18 ') are latticed (19) at the four corners of the frame (C). The pillar (18) is connected with the horizontal member (20) and the bracing (21) between the columns facing the front, rear, right and left, and the stock (B) center side of the pillar (18) is connected. Support brackets (22) are disposed at predetermined intervals in the vertical direction on the flange surface directed to the vertical direction, and the lifting device (23) for the lifting wire rope (13) is provided on the top horizontal member. Is suspended.

而して前記ストツクヤード(A)にユニツトスラブ製
作用資材を搬入し、自走台車(2)に載架されたユニツ
トスラブ製作架台(5)上に鉄骨小梁(a)、デツキプ
レート(b)を組立て、同デツキプレート上にスタツド
ボルト(図示せず)を打ち、鉄筋(図示せず)を配設
し、電気配管を取付けてユニツトスラブ(S)を組立
て、コンクリートを打設し、打設コンクリートがある程
度の強度を発現したのち自走台車(2)をレール(1)
上に沿って移動してストツクヤード(B)における立体
支持架構(C)の直下に位置せしめ、昇降装置(23)に
よって、吊り上げ最下段の架台支持プラケツト上に支持
し、その下部でユニツトスラブ(S)に設備ダクト衛生
配管を取付ける。取り付け後、所定位置まで吊り上げ、
所定の架台支持ブラケツトにて支持する。自走台車
(2)は製作ヤードに移動し、設備ダクト、衛生配管取
付中に次のユニツトスラブ製作を行う。
The unit slab working material is carried into the stockyard (A), and the steel beam (a) and the deck plate (b) are placed on the unit slab manufacturing stand (5) mounted on the self-propelled carriage (2). Is assembled, a stud bolt (not shown) is hit on the deck plate, a reinforcing bar (not shown) is provided, an electric pipe is attached, a unit slab (S) is assembled, concrete is poured, and concrete is poured. After the concrete has developed some strength, the self-propelled trolley (2) is connected to the rail (1).
It moves upward and is positioned directly below the three-dimensional support frame (C) in the stockyard (B), and is supported by a lifting / lowering device (23) on a platform support platform at the lowest lifting stage. Attach the equipment duct sanitary piping to). After installation, lift to a predetermined position,
It is supported by a predetermined gantry support bracket. The self-propelled carriage (2) moves to the production yard, and performs the next unit slab production while installing the equipment duct and sanitary piping.

しかるのち、前記立体支持架構(C)の昇降装置(2
3)によって、吊りワイヤーロープ(13)を吊上げ、前
記ユニツトスラブ製作架台(5)を前記ユニツトスラブ
(S)とともに所定位置まで吊上げると、同架台(5)
の側枠材(7)より荷重支持部材(9)を引出して前記
立体支持架構(C)における柱材(8)より突設された
架台支持ブラケツト(22)上に支持する。
Thereafter, the lifting device (2) of the three-dimensional support frame (C) is used.
3), the hanging wire rope (13) is lifted, and the unit slab production stand (5) is lifted to a predetermined position together with the unit slab (S).
The load support member (9) is pulled out from the side frame member (7) and is supported on a gantry support bracket (22) protruding from the column member (8) in the three-dimensional support frame (C).

以下前記同様の操作を繰返してユニツトスラブ架台
(5)をユニツトスラブ(S)とともに、前記立体支持
架構(C)に多段式にストツクし、順次前記ユニツトス
ラブ(S)をクレーン等によって本設位置に吊込む。
Thereafter, the same operation as above is repeated, and the unit slab stand (5) and the unit slab (S) are stocked in a multi-stage manner on the three-dimensional support frame (C), and the unit slab (S) is sequentially placed in a permanent position by a crane or the like. Hang it on.

(発明の効果) 本発明においては前記したように製作ヤードとストツ
クヤードとを隣接して配置するとともに、両者間に亘っ
て移動する自走台車を設け、製作ヤードにおいて同自走
台車上にユニツトスラブ製作架台を設置するとともに、
同架台上にユニツトスラブを製作したのち、前記自走台
車をストツクヤードに設置された、隅柱に前記架台支持
ブラケツトが多段式に配設された立体支持架構の直下に
位置せしめ、前記ユニツトスラブに設置配管を取付けた
のち、同ユニツトスラブを載架したまま前記架台を垂直
移動せしめ、同架台に出没自在に装架された荷重支持部
材を突出せしめて、前記立体支持架構における架台支持
ブラケツト上に支持せしめ、以下前記同様の工程を繰返
すことによって、前記ストツクヤードにユニツトスラブ
を多段式にストツクするようにしたものである。
(Effect of the Invention) In the present invention, as described above, the production yard and the stockyard are arranged adjacent to each other, and a self-propelled bogie that moves between the two is provided, and the unit slab is mounted on the self-propelled bogie in the production yard. While installing a production stand,
After manufacturing a unit slab on the same gantry, the self-propelled trolley was placed in a stockyard, and the gantry supporting bracket was positioned directly below a three-dimensional support frame in which a plurality of gantry supporting brackets were arranged in a corner post. After the installation piping is attached, the gantry is moved vertically while the unit slab is mounted, and the load supporting member mounted to be able to freely move in and out of the gantry is protruded, so that the gantry is supported on the gantry supporting bracket in the three-dimensional support frame. The unit slab is supported in a multi-stage manner on the stockyard by repeating the same steps as described above.

このように本発明によればストツクヤードを立体化す
ることによって、ストツクヤードの水平ストツク面積を
大幅に節減して多数のユニツトスラブをストツクてきる
ようにし、且つ同ユニツトスラブを建方順序に合わせて
製作できるようにし、市街地等の如き敷地の狭隘な個所
においても、積層工法を効果的に行なうことができる。
As described above, according to the present invention, the stockyard is made three-dimensional, so that the horizontal stock area of the stockyard is greatly reduced, so that a large number of unit slabs can be stocked, and the unit slabs are manufactured according to the construction order. Thus, the laminating method can be effectively performed even in a narrow site such as an urban area.

請求項2の発明は、ユニツトスラブ製作ヤード及びス
トツクヤードを隣接して設け、同両ヤードに跨って敷設
されたレール上を移動する自走台車に、端部より荷重受
部材が出没自在に装架されたユニツトスラブ製作架台を
載架し、前記ストツクヤードには、隅柱に多段式に配設
された前記荷重受部材の支持ブラケツトが設置され、且
つ前記ユニツトスラブ製作架台の吊上装置を具えた立体
支持架構を設置したことによって、前記の方法を効果的
に遂行しうるようにしたものである。
According to a second aspect of the present invention, a unit slab production yard and a stockyard are provided adjacent to each other, and a load receiving member is mounted on a self-propelled vehicle that moves on a rail laid across the two yards so that the load receiving member can come and go from the end. The unit slab production rack is mounted, and the stockyard is provided with a support bracket for the load receiving member arranged in a multi-stage manner in a corner post, and provided with a lifting device for the unit slab production frame. By providing a three-dimensional support frame, the above method can be effectively performed.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明に係るユニツトフロアの製造装置の一実
施例を示す平面図、第2図はその側面図、第3図及び第
4図並に第5図は夫々第1図の矢視III−III図及び矢視
IV−IV図並に矢視V−V図、第6図は自走台車の側面
図、第7図はその側面図、第8図はストツクヤードにお
ける立体支持架構の隅角部を示す平面図、第9図はその
側面図、第10図はユニツトスラブ製作架台における側枠
材の端面を示す正面図である。 (A)……製作ヤード、(B)……ストツクヤード、 (C)……立体支持架構、(1)……レール、 (2)……自走台車、 (5)……ユニツトスラブ製作架台、 (7)……側枠材、(9)……荷重支持部材、 (13)……吊上げ用ワイヤーロープ、 (18)……柱材、(22)……支持ブラケツト、 (23)……吊上げ用ワイヤーロープの吊上装置。
FIG. 1 is a plan view showing an embodiment of a unit floor manufacturing apparatus according to the present invention, FIG. 2 is a side view thereof, and FIGS. 3 and 4 and FIG. III-III diagram and arrow view
FIG. 6 is a side view of the self-propelled vehicle, FIG. 7 is a side view thereof, FIG. 8 is a plan view showing a corner of a three-dimensional support frame in the stockyard, FIG. 9 is a side view thereof, and FIG. 10 is a front view showing an end face of a side frame member in the unit slab production stand. (A) ... production yard, (B) ... stockyard, (C) ... three-dimensional support frame, (1) ... rail, (2) ... self-propelled vehicle, (5) ... unit slab production frame, (7) ... side frame material, (9) ... load supporting member, (13) ... wire rope for lifting, (18) ... pillar material, (22) ... support bracket, (23) ... lifting Wire rope lifting equipment.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 山田 徳一郎 埼玉県川越市古谷上6083―7 川越グリ ーンパークM―2 105 (56)参考文献 特開 昭51−116027(JP,A) 特開 昭61−270437(JP,A) 特開 昭49−88318(JP,A) ──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Tokuichiro Yamada 6083-7 Furuyagami, Kawagoe-shi, Saitama Kawagoe Green Park M-2 105 (56) References JP-A-51-116027 (JP, A) JP-A-61 −270437 (JP, A) JP-A-49-88318 (JP, A)

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】製作ヤードにおいて、架台端部に荷重支持
部材が出没自在に装架されたユニツトスラブ製作架台を
自走台車上に載架し、同架台上にユニツトスラブを製作
し、次いで前記自走台車を前記製作ヤードに隣接するス
トツクヤードに移動し、同ストツクヤードに設置され、
且つ各隅柱に夫々架台支持ブラケツトが多段式に配設さ
れた立体支持架構の直下に位置せしめ、前記ユニツトス
ラブに設備配管を取付けたのち、同ユニツトスラブを支
持した前記架台を垂直移動せしめ、同架台端部より荷重
支持部材を突出せしめて前記架台支持ブラケツト上に支
持せしめ、以下順次前記の工程を繰返してユニツトスラ
ブが載架された前記架台を立体的にストツクすることを
特徴とするユニツトフロアの製造、ストツク方法。
In a production yard, a unit slab production base on which a load supporting member is mounted at the end of the base so as to be freely retractable is mounted on a self-propelled carriage, and a unit slab is manufactured on the base. Move the self-propelled carriage to the stockyard adjacent to the production yard, and set up in the stockyard,
In addition, the gantry supporting brackets are positioned directly below the three-dimensional support frame in which each of the corner pillars is arranged in a multi-stage manner.After the equipment piping is attached to the unit slab, the gantry supporting the unit slab is vertically moved. A load supporting member is protruded from the end of the gantry to be supported on the gantry support bracket, and the above-described steps are sequentially repeated to three-dimensionally stock the gantry on which the unit slab is mounted. Floor manufacturing, stocking method.
【請求項2】ユニツトスラブの製作ヤード及び同製作ヤ
ードに隣接するユニツトスラブのストツクヤード、前記
両ヤードに跨って敷設されたレール上を移動する自走台
車、同自走台車上に載架され、端部に荷重受部材が出没
自在に装架されたユニツトスラブ製作架台、前記ストツ
クヤードに設置され各隅柱に夫々多段式に配設された前
記荷重受部材の支持ブラケツト、及び前記ユニツトスラ
ブ製作架台の吊上装置を具えた立体支持架構よりなるこ
とを特徴とするユニツトフロアの製造、ストツク装置。
2. A unit slab production yard, a stock yard of the unit slab adjacent to the unit slab, a self-propelled truck moving on rails laid across the two yards, and mounted on the self-propelled truck. A unit slab production base having a load receiving member mounted on the end so as to be freely retractable, a support bracket for the load receiving member installed in the stockyard and arranged in each corner column in a multi-stage manner, and the unit slab production base 3. A unit floor manufacturing and stocking device comprising a three-dimensional support frame having a lifting device.
JP23251688A 1988-09-19 1988-09-19 Manufacturing and stocking method of unit floor Expired - Lifetime JP2709091B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23251688A JP2709091B2 (en) 1988-09-19 1988-09-19 Manufacturing and stocking method of unit floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23251688A JP2709091B2 (en) 1988-09-19 1988-09-19 Manufacturing and stocking method of unit floor

Publications (2)

Publication Number Publication Date
JPH0280741A JPH0280741A (en) 1990-03-20
JP2709091B2 true JP2709091B2 (en) 1998-02-04

Family

ID=16940554

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23251688A Expired - Lifetime JP2709091B2 (en) 1988-09-19 1988-09-19 Manufacturing and stocking method of unit floor

Country Status (1)

Country Link
JP (1) JP2709091B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5120610B2 (en) * 2006-10-27 2013-01-16 清水建設株式会社 Unit member pre-assembly device
JP5348519B2 (en) * 2008-04-10 2013-11-20 清水建設株式会社 Unit member lifting device
JP5110587B2 (en) * 2008-06-11 2012-12-26 高砂熱学工業株式会社 Unit floor construction method
JP5613010B2 (en) * 2010-10-26 2014-10-22 鹿島建設株式会社 Floor unit storage equipment and storage method
JP5787652B2 (en) * 2011-07-15 2015-09-30 株式会社日立プラントコンストラクション Electrode dust collector electrode replacement method and lifting electrode loading / unloading stand
JP2013221362A (en) * 2012-04-18 2013-10-28 Ohbayashi Corp Unit floor lifting device
JP6813952B2 (en) * 2016-02-23 2021-01-13 株式会社日立プラントコンストラクション Temporary module assembly system

Also Published As

Publication number Publication date
JPH0280741A (en) 1990-03-20

Similar Documents

Publication Publication Date Title
JP2709091B2 (en) Manufacturing and stocking method of unit floor
JP2539150B2 (en) Bridge erection equipment
JP3032477B2 (en) Moving scaffold for floor slab assembly
JPH05113026A (en) Temporary scaffold structure
JP3750089B2 (en) Construction method of underground structure
JPH0336362B2 (en)
JP3848758B2 (en) Construction method for direct suspension of structures
JP2731907B2 (en) Construction work method on sloping land
JP2832278B2 (en) Building method
JPS63181860A (en) Floor panel building construction method and floor panel
JP2627705B2 (en) Automatic frame assembly method
JPH026906B2 (en)
JP2934567B2 (en) Work gondola for multi-story parking lot construction
JPH10140839A (en) Device for vertically hoisting form material and pipe support
JPS59228570A (en) Construction method of building
JP2530453B2 (en) Ceiling construction method and equipment for large span structures
JPH0416496A (en) Lifting device at building
JPH0445628B2 (en)
JP3240270B2 (en) Scaffold assembling method and scaffolding device
JP2673226B2 (en) Trolley equipment
JP2000045543A (en) Dismantling method of four-strut type vent
JPH07166712A (en) Conveyance system
JPH086453B2 (en) Building frame construction equipment
JPH01198978A (en) Overhead parking area device
JP2003027900A (en) Working truck