JP2670427B2 - Construction method of reinforced concrete columns and reinforcing bar positioning jig used for the implementation - Google Patents

Construction method of reinforced concrete columns and reinforcing bar positioning jig used for the implementation

Info

Publication number
JP2670427B2
JP2670427B2 JP6247425A JP24742594A JP2670427B2 JP 2670427 B2 JP2670427 B2 JP 2670427B2 JP 6247425 A JP6247425 A JP 6247425A JP 24742594 A JP24742594 A JP 24742594A JP 2670427 B2 JP2670427 B2 JP 2670427B2
Authority
JP
Japan
Prior art keywords
formwork
jig
mold
main
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP6247425A
Other languages
Japanese (ja)
Other versions
JPH08109745A (en
Inventor
義久 林
隆雄 藤野
Original Assignee
株式会社松村組
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社松村組 filed Critical 株式会社松村組
Priority to JP6247425A priority Critical patent/JP2670427B2/en
Publication of JPH08109745A publication Critical patent/JPH08109745A/en
Application granted granted Critical
Publication of JP2670427B2 publication Critical patent/JP2670427B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は鉄筋コンクリート柱の構
築方法及びその実施に用いる鉄筋位置決め治具に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a reinforced concrete column and a reinforcing bar positioning jig used for implementing the method.

【0002】[0002]

【従来の技術】鉄筋コンクリート柱は通常、図5に示す
ように、柱を構築する場所Lの所定位置に鉄筋部1を立
設し、次いで鉄筋部1を囲むコンクリート打設用の型枠
2を構築し、そのあと鉄筋部1を型枠2内で型枠1に対
し位置決めし、次いで型枠2内にコンクリートを所定高
さまで打設する。コンクリート養生後、型枠2は取り外
される。
2. Description of the Related Art Generally, as shown in FIG. 5, a reinforced concrete column is constructed by erecting a reinforcing bar portion 1 at a predetermined position L where the column is to be constructed, and then forming a concrete formwork 2 surrounding the reinforcing bar portion 1. After the construction, the reinforcing bar portion 1 is positioned in the formwork 2 with respect to the formwork 1, and then concrete is placed in the formwork 2 to a predetermined height. After curing the concrete, the formwork 2 is removed.

【0003】かかる鉄筋コンクリート柱の代表例は水平
断面が四角形状のものであり、鉄筋部1は図5に示すよ
うに該水平断面の各隅部分に3本ずつ配置される縦方向
主筋11とこれら主筋に連結される補助鉄筋12とを含
んでいる。各3本一組の主筋は平面から見ると主筋中心
を結ぶ線が直角三角形を形成し、該直角頂点にある主筋
が柱の隅角に対応するように配置される。
A typical example of such a reinforced concrete column is one having a quadrangular horizontal cross section, and as shown in FIG. 5, the reinforcing bar portion 1 has three longitudinal main bars 11 arranged at each corner of the horizontal cross section and these. And an auxiliary reinforcing bar 12 connected to the main bar. When viewed from a plane, a line connecting the centers of the main bars of each set of three main bars forms a right-angled triangle, and the main bars at the right-angled vertices are arranged so as to correspond to the corner angles of the columns.

【0004】補助鉄筋12は主筋11に外接するように
四角形リング状等に主筋11に連結され、且つ、主筋1
1相互の間隔を所定のものに設定している。コンクリー
ト型枠2を構築するにあたっては、図5に示すように、
概ね構築した型枠2の一側面2Aに対し、雌ネジを設け
た筒棒211とこれに螺合嵌合する雄ネジ付きロッド2
12とを含む伸縮調節可能の支え棒装置21を設け、該
装置の下端は場所L上の所定位置に固定した支持部22
にて支持するようにするとともに、該支え棒装置21に
並べて、途中にターンバックル231を含むチエーン、
ワイヤ等からなる張設装置23を前記型枠側面2Aと支
持部22とに張設する。また、型枠2の該一側面2Aに
隣合う側面2Bに対しても同様に伸縮調節可能の支え棒
装置21を設けてその下端を場所Lに固定した支持部2
2にて支持するとともに、途中にターンバックル231
を含む張設装置23を該型枠側面2Bと支持部22とに
張設する。そしてこれら支え棒装置21の伸縮調節と張
設装置23による張設作用とにより、型枠2が所定姿勢
に立設固定される。
The auxiliary reinforcing bar 12 is connected to the main reinforcing bar 11 so as to be circumscribed by the main reinforcing bar 11, and is connected to the main reinforcing bar 11.
The mutual interval is set to a predetermined value. In constructing the concrete formwork 2, as shown in FIG.
A cylindrical rod 211 provided with a female screw and a rod 2 having a male screw threadedly fitted to the cylindrical rod 211 provided on one side surface 2A of the generally formed formwork 2
And an adjustable telescopic support rod device 21 including a support portion 22 fixed at a predetermined position on a place L.
A chain including a turnbuckle 231 in the middle thereof,
A tensioning device 23 made of a wire or the like is tensioned between the mold side surface 2A and the support portion 22. Further, the supporting portion 2 is also provided with a supporting rod device 21 which is similarly adjustable in expansion and contraction on the side surface 2B adjacent to the one side surface 2A of the mold 2 and the lower end of which is fixed to the place L.
2 while supporting the turnbuckle 231
A tensioning device 23 including a tensioning device 23 is stretched between the side surface 2B of the mold and the support portion 22. The mold 2 is erected and fixed in a predetermined posture by the expansion and contraction adjustment of the support rod device 21 and the tensioning action of the tensioning device 23.

【0005】コンクリート打設に先立って鉄筋部1を型
枠2内で型枠2に対し位置決めするのは、高く立設され
た鉄筋部1は傾倒して正規位置、正規姿勢の型枠2に対
し正しい位置からずれるからである。この鉄筋部1の位
置決めにあたっては、従来、図6に示す円板形の鉄筋位
置決め部材91や図7に示す板状の位置決め部材92が
採用されてきた。
Before the concrete is poured, the reinforcing bar 1 is positioned in the mold 2 with respect to the mold 2. That is, the reinforcing bar 1 which is erected in a high position is tilted to form the mold 2 in a regular position and in a regular posture. This is because the position deviates from the correct position. Conventionally, a disc-shaped rebar positioning member 91 shown in FIG. 6 and a plate-shaped positioning member 92 shown in FIG. 7 have been used for positioning the rebar 1.

【0006】図6の円板形位置決め部材91はそれに設
けた主筋通し孔911にて主筋11に嵌め通し、周縁を
型枠2の内面に当接させることで主筋11の位置決め、
ひいては鉄筋部全体の位置決めを行うものである。ま
た、図7に示す位置決め部材92は、一枚の板体からな
り、主筋正規位置に対応させて設けた主筋通し孔921
にて主筋11に嵌め通し、型枠2に固定するすることで
主筋11の位置決め、ひいては鉄筋部全体の位置決めを
行うものである。部材92の中央にはコンクリート打設
用の孔922が設けられている。
[0006] The disc-shaped positioning member 91 shown in FIG. 6 is fitted into the main bar 11 through a main bar through hole 911 provided in the disk-shaped positioning member 91, and the peripheral edge thereof is brought into contact with the inner surface of the form 2 to position the main bar 11.
As a result, the entire reinforcing bar is positioned. Further, the positioning member 92 shown in FIG. 7 is composed of a single plate body and is provided with a main bar through hole 921 corresponding to the regular position of the main bar.
The main bar 11 is fitted into the main bar 11 and fixed to the form 2 to position the main bar 11, and thus the entire reinforcing bar. A hole 922 for pouring concrete is provided in the center of the member 92.

【0007】[0007]

【発明が解決しようとする課題】しかしながら、図6に
示す位置決め部材91によると、これを主筋11に嵌め
通したとき、主筋11に対し垂直な姿勢から傾いた姿勢
のまま型枠2内面に当接されやすく、そのため型枠2に
対する主筋11の位置精度を出し難いという問題があ
る。部材91を主筋11に対しできるだけ垂直姿勢をと
るように主筋通し孔911を小さく形成することも考え
られるが、それでは部材91を主筋11に嵌め通す作業
が面倒になる。また、この位置決め部材91のためにコ
ンクリートの円滑、正確な打設作業に支障がでることも
あり得る。
However, according to the positioning member 91 shown in FIG. 6, when the positioning member 91 is fitted into the main bar 11, the inner surface of the mold 2 is contacted with the main member 11 in a posture inclined from a vertical posture. There is a problem that they are easily contacted with each other, and thus it is difficult to obtain the positional accuracy of the main bar 11 with respect to the formwork 2. It is conceivable to make the main through hole 911 small so as to take the member 91 as vertical as possible with respect to the main bar 11, but this makes the work of fitting the member 91 into the main bar 11 cumbersome. Further, the positioning member 91 may hinder smooth and accurate placement work of concrete.

【0008】また、図7に示す位置決め部材92による
と、一体の板体に全ての主筋に対する通し孔921を精
度良く設けてあるので、主筋11への嵌め通し作業が難
しいし、あとで主筋11から抜き取る作業も難しい。ま
た、通常、主筋の位置決め後に取り付けられることがあ
るコンクリート打設高さ標示兼梁支持部材の型枠2内面
への取り付けにあたり、この位置決め部材92が邪魔に
なってそれだけその取り付け作業に手間取るという問題
もある。さらに、コンクリート打設は位置決め部材92
の中央孔922から行わなければならないので、該部材
が邪魔になってその作業がそれだけ困難となる。さら
に、例えば、前記の3本1組の主筋のように複数本一組
の主筋を採用する場合において、構築しようとする柱径
の大小によりその組主筋相互の間隔が変更されるような
ときには、それに見合う異なるサイズの位置決め部材9
2を準備しなければならず、それだけ柱構築が高価につ
く。
Further, according to the positioning member 92 shown in FIG. 7, since the through holes 921 for all the main bars are accurately formed in the integrated plate body, it is difficult to fit the main bars 11 through the holes, and the main bars 11 are later inserted. It is also difficult to extract from. In addition, when mounting the concrete pouring height indicator / beam support member, which is usually mounted after the positioning of the main bar, on the inner surface of the formwork 2, the positioning member 92 becomes an obstacle and the mounting work is time-consuming. There is also. Further, the concrete placing is performed by the positioning member 92.
Must be carried out through the central hole 922 of the above, and the member is an obstacle to the work. Further, for example, in the case where a plurality of sets of main bars are employed as in the above-mentioned set of three main bars, when the interval between the main bars of the pair is changed depending on the diameter of the column to be constructed, Positioning members 9 of different sizes to match it
2 must be prepared, and the pillar construction is expensive accordingly.

【0009】そこで本発明は、鉄筋部のコンクリート打
設用型枠内での位置決めを簡単正確に行うことができ、
また、その位置決めを型枠内面へのコンクリート打設高
さ標示兼梁支持部材の取り付け等の作業に支障のないよ
うに、さらにコンクリート打設作業にも支障のないよう
に行うことができ、それだけ簡単に能率よく鉄筋コンク
リート柱を構築することができる鉄筋コンクリート柱の
構築方法を提供することを課題とする。
Therefore, according to the present invention, the rebar portion can be positioned easily and accurately in the concrete pouring formwork.
In addition, the positioning can be performed so as not to hinder the work such as mounting the concrete pouring height indicator and the beam support member on the inner surface of the formwork, and the concrete pouring work. An object of the present invention is to provide a method for constructing a reinforced concrete column that can easily and efficiently construct a reinforced concrete column.

【0010】また、本発明はかかる方法の実施に用いる
構造簡単にして扱い易く、安価に製作できる、そして柱
外側面からの主筋の深さや、組をなす複数主筋における
主筋同士の間隔が同じである等の一定の条件下では異な
る柱径の柱構築に互いに転用できる鉄筋位置決め治具を
提供することを課題とする。
Further, the present invention has a structure used for carrying out such a method that is simple and easy to handle, can be manufactured at a low cost, and has the same depth of the main reinforcement from the outer surface of the column and the distance between the main reinforcements in a plurality of main reinforcements forming a set. An object of the present invention is to provide a reinforcing bar positioning jig that can be diverted from each other to column constructions having different column diameters under certain conditions such as certain conditions.

【0011】[0011]

【課題を解決するための手段】前記課題を解決する本発
明の鉄筋コンクリート柱の構築方法は、一つは、構築し
ようとする鉄筋コンクリート柱の水平断面における所定
位置に配置されるべき縦方向主筋とそれら主筋に連結さ
れた補助鉄筋とを含む鉄筋部を所定位置に立設する工程
と、前記鉄筋部を囲むコンクリート打設用型枠を構築す
る工程と、前記鉄筋部を前記型枠内に位置決めする工程
と、前記型枠内面にコンクリート打設高さ標示兼梁支持
部材を取り付ける工程と、前記鉄筋部の型枠内位置決め
、且つ、前記型枠内面へのコンクリート打設高さ標示
兼梁支持部材の取り付け後に前記型枠内にコンクリート
を打設する工程とを含み、前記型枠内における前記鉄筋
部の位置決め工程では、鉄筋位置決め治具であって前記
主筋を型枠内の所定位置に位置決めするために当接させ
る主筋当接部及び該主筋当接部を主筋位置決め位置に配
置するように治具全体を型枠上端部に位置決めするため
の型枠係合部とを有する治具を該型枠係合部で型枠所定
位置に係合位置決めして該型枠に取り外し可能に固定
し、該固定した治具の前記主筋当接部にそれに対応する
主筋を型枠内側から当接させて該治具に取り外し可能に
連結固定することを特徴とする鉄筋コンクリート柱の構
築方法(第1の構築方法)であり、もう一つは、 構築し
ようとする鉄筋コンクリート柱の水平断面における隅部
分に配置されるべき縦方向主筋とそれら主筋に連結され
た補助鉄筋とを含む鉄筋部を所定位置に立設する工程
と、前記鉄筋部を囲むコンクリート打設用型枠を構築す
る工程と、前記鉄筋部を前記型枠内に位置決めする工程
と、前記鉄筋部の型枠内位置決め後に前記型枠内にコン
クリートを打設する工程とを含み、前記型枠内における
前記鉄筋部の位置決め工程では、鉄筋位置決め治具であ
って前記主筋を型枠内の所定位置に位置決めするために
当接させる主筋当接部及び該主筋当接部を主筋位置決め
位置に配置するように治具全体を型枠上端隅角部分に位
置決めするための、該型枠上端隅角部分において該型枠
上面からそれに続く一つの外側面にかけての型枠角部分
に係合できる型枠係合部及び該型枠上面からそれに続
き、前記外側面に隣合う外側面にかけての型枠角部分に
係合できる型枠係合部を有している治具をそれら型枠係
合部で前記型枠角部分に係合させて該型枠上端隅角部分
に位置決め するとともに取り外し可能に固定し、該固定
した治具の前記主筋当接部にそれに対応する主筋を型枠
内側から当接させて該治具に取り外し可能に連結固定す
ることを特徴とする鉄筋コンクリート柱の構築方法(第
2の構築方法)であり、さらにもう一つは、 水平断面が
四角形状の鉄筋コンクリート柱の構築方法であり、構築
しようとする該鉄筋コンクリート柱の四角形状水平断面
の各隅部に3本ずつ配置されるべき縦方向主筋と該主筋
に連結された補助鉄筋とを含む鉄筋部を所定位置に立設
する工程と、前記鉄筋部を囲むコンクリート打設用型枠
を構築する工程と、前記鉄筋部を前記型枠内に位置決め
する工程と、前記鉄筋部の型枠内位置決め後に前記型枠
内にコンクリートを打設する工程とを含み、前記型枠内
における前記鉄筋部の位置決め工程では、鉄筋位置決め
治具であって前記主筋を型枠内の所定位置に位置決めす
るために当接させる主筋当接部及び該主筋当接部を主筋
位置決め位置に配置するように治具全体を型枠上端部に
位置決めするための型枠係合部とを有する治具を該型枠
係合部で型枠所定位置に係合位置決めして該型枠に取り
外し可能に固定し、該固定した治具の前記主筋当接部に
それに対応する主筋を型枠内側から当接させて該治具に
取り外し可能に連結固定するようにし、前記治具とし
て、前記3本一組の主筋のそれぞれの組に対して前記型
枠上端隅角部分に固定される治具であって、それぞれ
が、前記主筋当接部を3本一組の主筋のそれぞれが当接
できるように3箇所有しているとともに前記型枠係合部
を前記型枠上面からそれに続く一つの外側面にかけての
型枠角部分及び該型枠上面からそれに続き、前記外側面
に隣合う外側面にかけての型枠角部分にそれぞれ係合で
きるように少なくとも2箇所有しているものを採用する
ことを特徴とする鉄筋コンクリート柱の構築方法(第3
の構築方法)である。 第2及び第3の構築方法において
も、前記コンクリート打設前に前記型枠内面にコンクリ
ート打設高さ標示兼梁支持部材を取り付けることができ
る。
One of the methods for constructing a reinforced concrete column according to the present invention for solving the above-mentioned problems is, in one aspect, a longitudinal main bar to be arranged at a predetermined position in a horizontal cross section of the reinforced concrete column to be constructed and those. A step of standing a reinforcing bar portion including a supplementary reinforcing bar connected to the main bar at a predetermined position, a step of constructing a concrete casting formwork surrounding the reinforcing bar part, and positioning the reinforcing bar part in the formwork Process and concrete placement height marking and beam support on the inner surface of the form
The step of attaching the member , the positioning of the concrete height on the inner surface of the mold after positioning the reinforcing bar in the mold
Placing concrete in the form after the mounting of the double beam support member. In the step of positioning the rebar in the form, the rebar positioning jig may be used to fix the main rebar to a predetermined position in the form. A main frame contact portion to be brought into contact for positioning at a position, and a mold engaging portion for positioning the entire jig at the upper end of the mold so as to arrange the main bar contact portion at the main bar positioning position. The tool is engaged and positioned at a predetermined position of the mold by the mold engaging portion and detachably fixed to the mold, and a main bar corresponding to the main bar contacting portion of the fixed jig is attached from the inside of the mold. Reinforced concrete column structure characterized by being brought into contact with and detachably connected and fixed to the jig
The construction method (first construction method), the other is construction
Corner of horizontal section of reinforced concrete column
Minute longitudinal bars that should be placed for
Process of erection of reinforcing bar including auxiliary reinforcing bar in place
And construct a concrete casting formwork that surrounds the reinforcing bars.
And a step of positioning the reinforcing bar portion in the mold
After positioning the reinforcing bar in the mold,
A step of placing a cleat,
In the step of positioning the reinforcing bar portion, a reinforcing bar positioning jig is used.
In order to position the main bar at a predetermined position in the formwork
Main bar contacting part to be contacted and main bar contacting part
Position the entire jig on the upper corner of the mold so that
The formwork at the top corners of the formwork for positioning
Formwork corners from the top surface to the one outer surface that follows
From the upper surface of the mold and the mold engaging portion that can be engaged with
The corners of the form frame extending to the outer surface adjacent to the outer surface.
A jig having a formwork engaging portion that can be engaged is used as the formworker.
By engaging the corners of the form at the joint, the upper corners of the form
And removably fixed to the
A main bar corresponding to the main bar contacting part of the jig
Contact from inside and removably connect and fix to the jig
Construction method of reinforced concrete column characterized by
2), and the other is that the horizontal section is
It is a method of building a rectangular reinforced concrete column,
Rectangular horizontal section of the reinforced concrete column to be tried
Longitudinal bars and three bars to be placed in each corner of the
Reinforcing bar in place with auxiliary bar connected to
And a concrete pouring formwork surrounding the rebar part
And step of positioning the rebar part in the formwork
And the mold after positioning the reinforcing bar in the mold
In the formwork, including the step of placing concrete inside
In the step of positioning the reinforcing bar portion in
A jig that positions the main bar at a predetermined position in the mold
Main abutment portion to be brought into contact with
Place the entire jig on the top of the formwork so that it is placed in the positioning position.
A jig having a mold engaging portion for positioning is used for the mold.
The engaging part is engaged and positioned at a predetermined position on the formwork, and mounted on the formwork.
Removably fixed to the main bar contact part of the fixed jig
Attach the corresponding main bar from the inside of the mold to the jig.
Removably connected and fixed as the jig
The mold for each set of the main bars of the set of three
A jig that is fixed to the top corner of the frame,
However, each of the main bars of the set comes in contact with the main bar contacting part.
It has three positions so that it can be used and the mold engaging part
From the upper surface of the formwork to the one outer surface that follows.
The corners of the mold and the upper surface of the mold, followed by the outer surface
Engage in the corners of the form frame to the outer surface adjacent to
Use at least two places so that you can
Construction method of reinforced concrete columns characterized by (3rd
Construction method). In the second and third construction methods
Also, before the concrete is placed, the concrete inside
It is possible to attach a beam height
You.

【0012】また、前記課題を解決する本発明の鉄筋位
置決め治具は、かかる本発明方法の実施に用いる治具で
あって、前記鉄筋部の主筋を型枠内の所定位置に位置決
めするために当接させる主筋当接部及び該主筋当接部を
主筋位置決め位置に配置するように治具全体を型枠上端
部に位置決めするための型枠係合部とを有するものであ
る。さらに詳しくは、特に、前記第2及び第3のタイプ
の鉄筋コンクリート柱の構築方法の実施に用いる鉄筋位
置決め治具であって、 第2のタイプの鉄筋コンクリート
柱の構築方法の実施に用いる鉄筋位置決め治具は、前記
鉄筋部の主筋を型枠内の所定位置に位置決めするために
当接させる主筋当接部及び該主筋当接部を主筋位置決め
位置に配置するように治具全体を型枠上端隅角部分に位
置決めするための、該型枠上端隅角部分において該型枠
上面からそれに続く一つの外側面にかけての型枠角部分
に係合できる型枠係合部及び該型枠上面からそれに続
き、前記外側面に隣合う外側面にかけての型枠角部分に
係合できる型枠係合部を有していることを特徴とする鉄
筋位置決め治具であり、 第3のタイプの鉄筋コンクリー
ト柱の構築方法の実施に用いる鉄筋位置決め治具は、前
記鉄筋部の主筋を型枠内の所定位置に位置決めするため
に当接させる主筋当接部及び該主筋当接部を主筋位置決
め位置に配置するように治具全体を型枠上端部に位置決
めするための型枠係合部とを有しており、水平断面が四
角形状のコンクリート柱の各隅部に3本ずつ配置される
べき縦方向主筋の該3本一組の主筋のそれぞれの組に対
応でき、前記主筋当接部を3本一組の主筋のそれぞれが
当接できるように3箇所有しているとともに前記型枠係
合部を前記型枠上面からそれに続く一つの外側面にかけ
ての型枠角部分及び該型枠上面からそれに続き、前記外
側面に隣合う外側面にかけての型枠角部分にそれぞれ係
合できるように少なくとも2箇所有していることを特徴
とする鉄筋位置決め治具である。
Further, a reinforcing bar positioning jig of the present invention for solving the above-mentioned problems is a jig used for carrying out the method of the present invention, and is for positioning the main reinforcing bar of the reinforcing bar portion at a predetermined position in a mold. It has a main bar contacting part to be contacted and a formwork engaging part for positioning the entire jig on the upper end part of the formwork so that the main barn contacting part is located at the main bar positioning position. More particularly, in particular the second and third types
Reinforcement Position Used to Implement the Method of Building Reinforced Concrete Columns
Placement jig, second type of reinforced concrete
The reinforcing bar positioning jig used to carry out the method of constructing the pillar is
In order to position the main bar of the reinforcing bar at a predetermined position in the formwork
Main bar contact portion to be abutted and main bar positioning of the main bar contact portion
Position the entire jig on the upper corner of the mold so that
The formwork at the top corners of the formwork for positioning
Formwork corners from the top surface to the one outer surface that follows
From the upper surface of the mold and the mold engaging portion that can be engaged with
The corners of the form frame extending to the outer surface adjacent to the outer surface.
Iron characterized by having a formwork engaging part that can be engaged
It is a muscle positioning jig and is the third type of reinforcing bar concrete.
The reinforcing bar positioning jig used to implement the
In order to position the main bar of the reinforcing bar at a predetermined position in the formwork
Main bar contacting part to be contacted with the main bar and the main bar contacting part
Position the entire jig on the upper edge of the mold so that
It has a form engaging part for
Three concrete pillars are placed at each corner of a square concrete pillar
Pair each of the three main bars of the longitudinal main bar
Each of the main bars of the set of three main bar abutting parts
It has three places so that it can come into contact, and the formworker
From the top of the mold to the outer surface that follows
From all corners of the mold and the top of the mold,
Engage in the corners of the formwork over the outer surface adjacent to the side
Characterized by having at least two places so that they can be combined
This is a reinforcing bar positioning jig.

【0013】前記本発明方法において、治具の型枠への
取り外し可能の固定は、簡単なものとして、例えば治具
に設けたネジ孔を利用して該治具を型枠にネジ留めする
とか、治具に設けた釘孔を利用して該治具を型枠に釘留
めするとかが考えられる。また、治具への主筋の取り外
し可能の連結にあたっては、簡単なものとして、例え
ば、主筋に対応させて予め治具に立設した突起部材と主
筋とを針金等で連結することが考えられる。
In the method of the present invention, the detachable fixation of the jig to the mold is simplified, for example, by screwing the jig to the mold using a screw hole provided in the jig. It is conceivable that the jig is nailed to a mold using a nail hole provided in the jig. In addition, the detachable connection of the main bar to the jig may be simple, for example, to connect the protruding member and the main bar, which are erected in advance in the jig in correspondence with the main bar, with a wire or the like.

【0014】[0014]

【0015】[0015]

【作用】本発明の鉄筋コンクリート柱の構築方法による
と、鉄筋部が所定位置に立設され、該鉄筋部を囲むコン
クリート打設用型枠が構築される。次いで鉄筋位置決め
治具が鉄筋部の主筋正規位置に対応させて、該治具の型
枠係合部を用いて型枠に位置決めされ、取り外し可能に
固定される。次いで治具に対応する主筋が該治具の主筋
当接部に型枠内側から当接され、該治具に取り外し可能
に連結固定される。このとき本発明の前記第2及び第3
の鉄筋コンクリート柱の構築方法及びその方法の実施に
用いる鉄筋位置決め治具によると、該治具が、その型枠
係合部を用いて、型枠上端隅角部分において該型枠上面
からそれに続く一つの外側面にかけての型枠角部分及び
該型枠上面からそれに続き、前記外側面に隣合う外側面
にかけての型枠角部分にそれぞれ係合され、該型枠上端
隅角部分に位置決めされるとともに取り外し可能に固定
される。次いで治具に対応する主筋が該治具の主筋当接
部に型枠内側から当接され、該治具に取り外し可能に連
結固定される。このとき、前記第3の鉄筋コンクリート
柱の構築方法及びその実施に用いる鉄筋位置決め治具に
よると、該治具が3本一組の主筋のそれぞれの組に対し
て前記型枠上端隅角部に取り外し可能に固定され、各3
本一組の主筋のそれぞれがそれに対応する治具の主筋当
接部に型枠内側から当接され、該治具に取り外し可能に
連結される。 また、前記第1の構築方法では、型枠内へ
のコンクリート打設前に型枠内面にコンクリート打設高
さ標示兼梁支持部材が取り付けられる。前記第2及び第
3の構築方法では、必要に応じ、該コンクリート打設高
さ標示兼梁支持部材が取り付けられる。 次いで、該型枠
内にコンクリートが所定高さまで打設され、コンクリー
ト養生後に治具及び型枠が取り外される。必要に応じ、
同様の手法にて上方へ柱が継ぎ足し延設される。 取り外
した治具及び型枠は、損傷している場合の他は再使用で
きる。
According to the method for constructing a reinforced concrete columns of the [action] The present invention
Then, the reinforcing bar portion is erected at a predetermined position, and a concrete placing formwork surrounding the reinforcing bar portion is constructed. Then, the reinforcing bar positioning jig is positioned on the mold using the mold engaging portion of the jig so as to correspond to the regular position of the main bar of the reinforcing bar and is removably fixed. Next, the main bar corresponding to the jig is brought into contact with the main bar contact portion of the jig from the inside of the mold, and is detachably connected and fixed to the jig. At this time, the second and third aspects of the present invention
Construction method of concrete reinforced concrete columns and implementation of the method
According to the reinforcing bar positioning jig used, the jig is
Using the engaging part, the upper surface of the mold at the upper corners of the mold
To the one outer surface that follows and the corners of the form and
An outer surface that is continuous with the upper surface of the mold and is adjacent to the outer surface.
To the corners of the formwork,
Positioned in the corner and removably secured
Is done. Next, the main bar corresponding to the jig contacts the main bar of the jig
Part from the inside of the mold and is detachably connected to the jig.
It is fixed and fixed. At this time, the third reinforced concrete
For the method of constructing the pillar and the reinforcing bar positioning jig used for its implementation
According to this, the jig is for each set of three main bars
And detachably fixed to the upper corners of the formwork.
Each of the main bars of this set corresponds to the corresponding main bar of the jig.
It comes in contact with the contact part from the inside of the form and can be removed from the jig.
Be linked. In addition, in the first construction method,
Before placing concrete in the concrete
A sign and beam support member is attached. The second and the second
In the construction method of No. 3, if necessary, the concrete pouring height
A sign and beam support member is attached. Then the formwork
Concrete is placed inside the concrete to a specified height,
After the curing, the jig and the mold are removed. As needed,
In the same way, columns will be added and extended upward. Removal
Reused jigs and molds can be reused unless damaged.
Wear.

【0016】[0016]

【0017】[0017]

【0018】[0018]

【実施例】以下、本発明方法実施の1例とその実施に用
いる鉄筋位置決め治具の例について図面を参照して説明
する。図1は鉄筋位置決め治具3の斜視図である。図2
は型枠2への治具3の取り付け状態及び該治具3と主筋
11との位置関係を示す斜視図である。図3は鉄筋部1
を囲むコンクリート打設用型枠2に鉄筋位置決め治具3
を固定し、これら治具3で鉄筋部1を型枠2内で位置決
めし、さらに、型枠2の内面にコンクリート打設高さ標
示兼梁支持部材4を取り付けてコンクリートを打設した
状態の平面図である。図4は図3のX−X線に沿う断面
図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An example of carrying out the method of the present invention and an example of a reinforcing bar positioning jig used for carrying out the method will be described below with reference to the drawings. FIG. 1 is a perspective view of the reinforcing bar positioning jig 3. FIG.
FIG. 3 is a perspective view showing a mounting state of the jig 3 on the mold 2 and a positional relationship between the jig 3 and the main bar 11. Figure 3 shows the rebar part 1
Reinforcing bar positioning jig 3 on concrete pouring form 2 surrounding
And the jigs 3 are used to position the rebar 1 in the formwork 2, and a concrete placement height indicating and beam supporting member 4 is attached to the inner surface of the formwork 2 to cast concrete. It is a top view. FIG. 4 is a sectional view taken along line XX of FIG.

【0019】この実施例における鉄筋コンクリート柱の
構築においても、従来方法同様、図5に示すように、柱
を構築する場所Lの所定位置に鉄筋部1を立設し、次い
で鉄筋部1を囲むコンクリート打設用型枠2を構築す
る。構築しようとする鉄筋コンクリート柱は、ここでは
水平断面四角形のもので、それに埋設される鉄筋部1
は、図5に示すように、断面四角形柱の各隅部分に3本
ずつ配置される縦方向主筋11とこれら主筋を囲むよう
に配置されて該主筋に連結された補助鉄筋12とを含む
ものである。
Also in the construction of the reinforced concrete column in this embodiment, as in the conventional method, as shown in FIG. 5, the reinforcement portion 1 is erected at a predetermined position of the place L where the column is constructed, and then the concrete surrounding the reinforcement portion 1 is reinforced. The casting formwork 2 is constructed. The reinforced concrete column to be constructed here has a rectangular cross section with a horizontal section, and the reinforced concrete section 1
As shown in FIG. 5, includes three longitudinal main bars 11 arranged at each corner of a rectangular column having a cross section and auxiliary reinforcing bars 12 arranged so as to surround these main bars and are connected to the main bars. .

【0020】各3本一組の主筋11は図3から分かるよ
うに、平面から見ると主筋中心を結ぶ線が直角三角形を
形成し、該直角頂点に位置する主筋11が型枠2隅の角
部分(従って柱の隅角部分)に対応している。型枠2の
構築にあたっては、概ね構築した型枠2を図5に示すよ
うに、型枠外側面2A、2Bに対しそれぞれ設けた支え
棒装置21の伸縮調節と張設装置23による張設作用と
により、所定姿勢(ここでは鉛直姿勢)に立設固定す
る。
As can be seen from FIG. 3, each set of three main bars 11 forms a right-angled triangle when viewed from a plane, and the main bars 11 located at the right-angled vertices have corners at the two corners of the formwork. It corresponds to the part (hence the corner of the pillar). When constructing the formwork 2, as shown in FIG. 5, the formwork 2 is constructed so that expansion and contraction adjustment of the supporting rod device 21 provided on the outside faces 2A and 2B of the formwork and a tensioning action by the tensioning device 23 are performed. Thus, it is erected and fixed in a predetermined posture (here, a vertical posture).

【0021】次に鉄筋部1を型枠2内で、正しい姿勢の
型枠2に対し位置決めして鉛直姿勢にする。この鉄筋部
位置決めにあたっては図1から図4に示されている鉄筋
位置決め治具3を用いる。治具3は、水平断面四角形の
コンクリート柱の各隅角部分に3本ずつ配置される縦方
向主筋11の該3本一組の主筋のそれぞれに対し配置さ
れ、型枠2の上端部の各隅角部分に固定される。
Next, the reinforcing bar portion 1 is positioned in the mold 2 with respect to the mold 2 having the correct posture to be in the vertical posture. For positioning the reinforcing bar portion, the reinforcing bar positioning jig 3 shown in FIGS. 1 to 4 is used. The jigs 3 are arranged for each of the set of three main reinforcing bars 11 of the longitudinal main bar 11 arranged at each corner portion of a concrete column having a quadrangular horizontal section, and each of the upper end portions of the formwork 2 is arranged. It is fixed to the corner.

【0022】各治具3は3本一組の主筋11のうち前記
直角三角形の直角頂点に位置する真ん中の主筋11を当
接させるための凹部31、該主筋11の両側に位置する
主筋11を当接させるための二つの凹部32を有してい
る。治具3は金属板を加工して安価に形成されており、
前記の凹部31、32は型枠2の上端面に載置される平
坦部分33のうち型枠上端開口20(図2参照)内へ張
り出す互いに直角をなす直線二縁辺331、332に設
けられている。凹部31は該二縁辺331、332が直
角に交わる部分に平面視四角形状に形成され、凹部32
は各直線縁辺331、332に平面視半円形状に形成さ
れている。
Each jig 3 has a recess 31 for abutting the middle main bar 11 located at the right-angled vertex of the right-angled triangle among the main bars 11 in a set of three, and the main bars 11 located on both sides of the main bar 11. It has two recesses 32 for abutting. The jig 3 is formed by processing a metal plate at low cost,
The recesses 31 and 32 are provided on the two straight edges 331 and 332 of the flat portion 33 placed on the upper end surface of the mold 2 and projecting into the upper end opening 20 (see FIG. 2) of the mold and forming right angles with each other. ing. The recess 31 is formed in a quadrangular shape in a plan view at a portion where the two edges 331 and 332 intersect at a right angle.
Is formed in a semicircular shape in plan view on each of the straight edges 331 and 332.

【0023】治具3の前記平坦部分33のうち、前記一
つの凹部32とは反対側の部分は下方へ屈曲されて型枠
係合部341とされているとともに、もう一つの凹部3
2とは反対側の部分も下方へ屈曲され、型枠係合部34
2とされている。型枠係合部341は前記の張り出し縁
辺331と平行であり、型枠係合部342は前記の張り
出し縁辺332と平行である。
Of the flat portion 33 of the jig 3, the portion opposite to the one concave portion 32 is bent downward to form a mold engaging portion 341, and the other concave portion 3 is formed.
2 is also bent downward, so that the form engaging portion 34
It is 2. The mold frame engaging portion 341 is parallel to the projecting edge 331, and the mold frame engaging portion 342 is parallel to the projecting edge 332.

【0024】この治具3の全体の形状、寸法、主筋当接
凹部31、32、型枠係合部341、342の相互位置
関係等は次のように定められている。すなわち、治具3
の平坦部分33を型枠2の上端隅角部分の上面24に図
2に示すように載置し、型枠係合部341、342を該
上端面とそれに連続する、互いに直交して隣合う二つの
外側面との角部分25にそれぞれ係合させることで治具
3を型枠2に容易に位置決めすることができ、且つ、そ
のように型枠に位置決めしたとき、前記の主筋当接凹部
31、32が、3本一組の主筋11の型枠2内における
正規の位置に丁度対応する位置をとるように定められて
いる。
The overall shape and dimensions of the jig 3 and the mutual positional relationship between the main muscle contact concave portions 31 and 32 and the form engaging portions 341 and 342 are determined as follows. That is, the jig 3
The flat portion 33 is placed on the upper surface 24 of the upper corner portion of the form 2 as shown in FIG. 2, and the form engaging portions 341 and 342 are adjacent to the upper surface and the upper surface at right angles to each other. The jig 3 can be easily positioned on the mold 2 by engaging the corner portions 25 with the two outer surfaces, and when the jig 3 is positioned on the mold as described above, the main bar contact recess 31 and 32 are set so as to take the positions which correspond to the regular positions in the mold 2 of the set of three main bars 11.

【0025】このように位置決めした治具3は、この例
では治具3の平坦部分33及び型枠係合部341、34
2に設けた複数の釘孔35(図1参照)を用いて、型枠
2に釘30で取り外し可能に固定できる。また、治具3
の前記平坦部分33の上面には、各凹部31、32の背
後位置で主筋連結用の突起棒36を立設してある。
In this example, the jig 3 positioned in this way is composed of the flat portion 33 of the jig 3 and the mold engaging portions 341 and 34.
A plurality of nail holes 35 (see FIG. 1) provided in 2 can be used to detachably fix to the formwork 2 with nails 30. Also, the jig 3
On the upper surface of the flat portion 33, a protrusion bar 36 for connecting main bars is provided upright at the position behind each recess 31, 32.

【0026】前述のように鉄筋部1を立設し、それを囲
む型枠2を構築したあとは、かかる治具3を図2〜図4
に示すように、型枠2の各上端隅角部分の上面に治具平
坦部分33で載置するとともに型枠係合部341、34
2を型枠2の外側角部分25に係合させて型枠2に位置
決めし、釘30でそこに固定する。次いで、各治具3の
主筋当接凹部31、32にそれらに対応する主筋11を
型枠内側から嵌め込み当接させて各主筋11を正規位置
に位置決めし、且つ、該主筋と治具上に立設された突起
棒36とに針金37をわたし掛けて主筋11と治具3と
を互いに連結固定する。
After the reinforcing bar 1 is erected and the formwork 2 surrounding the reinforcing bar 1 is constructed as described above, the jig 3 is moved to the position shown in FIGS.
As shown in FIG. 3, the jig flat portion 33 is placed on the upper surface of each upper corner portion of the mold 2 and the mold engaging portions 341, 34 are provided.
2 is engaged with the outer corner portion 25 of the formwork 2 to be positioned on the formwork 2 and fixed there with nails 30. Next, the main bars 11 corresponding to the jigs 3 are fitted into the main bar contact recesses 31 and 32 of the jig 3 from the inside of the form, and the respective main bars 11 are positioned at the proper positions. A wire 37 is hung on the protruding bar 36 which is erected to fix the main bar 11 and the jig 3 to each other.

【0027】次に、この実施例では、型枠2内のコンク
リート打設高さ位置を示す標示部材及び柱構築後の梁支
持部材を兼ねる部材4を図3及び図4に示すように型枠
2内側面にボルトナット41にて取り付ける。該部材4
はここでは断面山形の鋼製部材である。そのあと、型枠
2内に、前記部材4で示される高さまでコンクリートを
打設する。
Next, in this embodiment, as shown in FIGS. 3 and 4, the member 4 which also serves as the marking member indicating the concrete pouring height position in the mold 2 and the beam supporting member after the pillar construction is formed as shown in FIGS. 2 Attach it to the inner surface with bolts and nuts 41. The member 4
Is a steel member having a chevron cross section here. After that, concrete is poured into the formwork 2 up to the height indicated by the member 4.

【0028】コンクリート養生後、各治具3上の突起棒
36と主筋11を連結している針金37を解くととも
に、各治具3を固定している釘30を型枠2から取り去
る。この治具取り外し作業は、針金37を解くことと、
釘30の抜き取りにより容易に行うことができ、しかも
型枠2を再使用できるようにできるだけ傷つけることな
く行うことができる。また、治具3自体の損傷も無い
か、あったとしてもきわめて少なく、取り外した治具3
の再使用も可能である。
After the concrete is cured, the wire 37 connecting the projecting rod 36 on each jig 3 and the main bar 11 is unwound, and the nail 30 fixing each jig 3 is removed from the mold 2. This jig removal work consists of releasing the wire 37,
It can be done easily by pulling out the nails 30 and can be done without damaging the formwork 2 so that it can be reused. In addition, the jig 3 itself is not damaged, or if it is present, it is extremely small.
Can be reused.

【0029】各治具3を取り外したあと型枠2を分解す
る。かくして、所定高さの鉄筋コンクリート柱が構築さ
れる。取り外した治具3、型枠2は再使用できる。鉄筋
コンクリート柱をさらに高く延設するときは、前記と同
様の作業を、既に構築したコンクリート柱から延びる、
また、延ばした鉄筋部を基にして実施すればよい。
After removing the jigs 3, the form 2 is disassembled. Thus, a reinforced concrete column having a predetermined height is constructed. The removed jig 3 and mold 2 can be reused. When extending a reinforced concrete column even higher, the same work as above, extending from the already built concrete column,
Further, it may be carried out based on the extended rebar portion.

【0030】前記治具3は既述のとおり、構造簡単で扱
い易く、型枠2への位置決め、固定、取り外しも容易に
行える。また、該治具3は3本一組の主筋11に対し一
個ずつ設ければ足り、該治具の主筋当接凹部31、32
への主筋11の当接位置決め、そして治具3との連結も
簡単容易に、しかも正確に行える。また、治具3は型枠
上端部の四隅部分に設けられるだけであるから鉄筋部1
の位置決め後におけるコンクリート打設高さ標示兼梁支
持部材4等の型枠2内への取り付けも容易に行えるし、
コンクリート打設も治具3に邪魔されることなく支障無
く行える。これらにより簡単に能率よく鉄筋コンクリー
ト柱が構築される。
As described above, the jig 3 has a simple structure and is easy to handle, and can be easily positioned, fixed and removed from the mold 2. Further, it suffices that one jig 3 is provided for each set of three main bars 11, and the main bar contact recesses 31, 32 of the jig are provided.
Positioning of the main bar 11 in contact with the jig 3 and connection with the jig 3 can be performed easily, easily and accurately. Further, since the jigs 3 are only provided at the four corners of the upper end of the formwork, the reinforcing bar portion 1
It is possible to easily attach the concrete pouring height indicator / beam support member 4 etc. into the mold 2 after positioning
Concrete pouring can also be performed without hindrance by the jig 3 without any trouble. With these, reinforced concrete columns can be constructed easily and efficiently.

【0031】また、構築しようとする柱の径が異なると
きでも、3本一組の主筋11の柱外側面からの深さ、及
び3本一組の主筋11相互の間隔が同じであれば、柱径
にかかわらず同じ治具3を使用でき、それだけ経済的で
あり、安価に柱を構築できる。
Further, even when the diameters of the columns to be constructed are different, if the depth of the set of three main bars 11 from the column outer surface and the interval between the set of three main bars 11 are the same, The same jig 3 can be used regardless of the column diameter, which is economical and the column can be constructed at low cost.

【0032】[0032]

【発明の効果】以上説明したように本発明の鉄筋コンク
リート構築方法によると、鉄筋部のコンクリート打設用
型枠内での位置決めを簡単正確に行うことができ、ま
た、その位置決めを型枠内面へのコンクリート打設高さ
標示兼梁支持部材の取り付け等の作業に支障のないよう
に、さらにコンクリート打設作業にも支障のないように
行うことができ、それだけ簡単に能率よく鉄筋コンクリ
ート柱を構築することができ、また、柱構築後は、その
構築に使用した型枠や鉄筋位置決め治具を、何度も繰り
返し使用して損傷している場合の他は再使用もできる。
As described above, according to the method for constructing reinforced concrete of the present invention, the positioning of the reinforcing bar portion in the concrete placing mold can be performed easily and accurately, and the positioning is performed on the inner surface of the mold. It is possible to construct concrete reinforced concrete pillars easily and efficiently so that it does not hinder the work such as the concrete pouring height marking and installation of beam support members and the concrete pouring work. Further, after the pillar is constructed, the formwork and the reinforcing bar positioning jig used for the construction can be reused except when they are damaged by repeatedly using them repeatedly.

【0033】また、本発明によると、本発明方法の実施
に用いる構造簡単にして扱い易く、安価に製作できる、
そして柱外側面からの主筋の深さや、組をなす複数主筋
における主筋数、主筋同士の間隔が同じである等の一定
の条件下では異なる柱径の柱構築に互いに転用できる鉄
筋位置決め治具を提供することができる。構築しようと
する鉄筋コンクリート柱の水平断面の隅部分に鉄筋部が
配置される場合において、鉄筋位置決め治具として、型
枠上端隅角部分において型枠上面からそれに続く一つの
外側面にかけての型枠角部分及び型枠上面からそれに続
き、前記外側面に隣合う外側面にかけての型枠角部分に
それぞれに係合できる型枠係合部を有しているものを採
用するときは、該治具は構造簡単で型枠へ位置決めし易
く、扱い易いものである。構築しようとするコンクリー
ト柱の水平断面が四角形状であり、前記鉄筋部が該四角
形状断面の各隅部に3本ずつ配置される縦方向主筋と該
主筋に連結された補助鉄筋とを含んでいる場合におい
て、鉄筋位置決め治具として、主筋当接部を3本一組の
主筋のそれぞれが当接できるように3箇所有していると
ともに型枠係合部を型枠上面からそれに続く一つの外側
面にかけての型枠角部分及び型枠上面からそれに続き、
前記外側面に隣合う外側面にかけての型枠角部分にそれ
ぞれに係合できるように少なくとも2箇所有しているも
のを採用するときは、該治具は構造簡単で扱い易いもの
であり、3本一組の主筋に対し一つずつ採用される該治
具により能率よく鉄筋部の位置決めを行える。
Further, according to the present invention, the structure used for carrying out the method of the present invention is simple, easy to handle, and inexpensive to manufacture.
And under certain conditions such as the depth of the main bars from the outer side surface of the column, the number of main bars in multiple main bars forming a set, and the intervals between the main bars, etc. Can be provided. Trying to build
Reinforced concrete column at the corner of horizontal section
When arranging, the mold is used as a reinforcing bar positioning jig.
At the top corner of the frame
The corners of the formwork from the outer side and the top of the formwork
To the outer corner adjacent to the outer side.
The one that has the formwork engaging part that can be engaged with each is adopted.
When used, the jig has a simple structure and can be easily positioned on the mold
It is easy to handle. The horizontal cross section of the concrete column to be constructed has a quadrangular shape, and the reinforcing bar portion includes three longitudinal main bars arranged at each corner of the rectangular cross section and auxiliary reinforcing bars connected to the main bar. In this case, the reinforcing bar positioning jig has three main bar contact portions so that each set of three main bars can come into contact with each other, and the mold frame engaging section is formed from the upper surface of the mold frame to the following one. Continuing from the corners of the form to the outer side and the top of the form,
When a jig having at least two places so as to be able to engage with each of the corner portions of the mold extending to the outer surface adjacent to the outer surface is adopted, the jig has a simple structure and is easy to handle. The jigs that are adopted one by one for the main bars of this set enable efficient positioning of the reinforcing bar.

【図面の簡単な説明】[Brief description of the drawings]

【図1】鉄筋位置決め治具の斜視図である。FIG. 1 is a perspective view of a reinforcing bar positioning jig.

【図2】コンクリート打設用型枠への鉄筋位置決め治具
の取り付け状態及び該治具と主筋との位置関係を示す斜
視図である。
FIG. 2 is a perspective view showing an attachment state of a reinforcing bar positioning jig to a concrete pouring formwork and a positional relationship between the jig and a main bar.

【図3】鉄筋部を囲むコンクリート打設用型枠にコンク
リートを打設した状態の平面図である。
FIG. 3 is a plan view showing a state in which concrete is cast on a concrete casting formwork surrounding a reinforcing bar portion.

【図4】図3のX−X線に沿う断面図である。FIG. 4 is a sectional view taken along line XX of FIG. 3;

【図5】所定位置に立設した鉄筋部及びこれを囲むよう
に構築されたコンクリート打設用型枠の斜視図である。
FIG. 5 is a perspective view of a reinforcing bar portion standing upright at a predetermined position and a concrete pouring formwork constructed so as to surround the reinforcing bar portion.

【図6】型枠内の鉄筋位置決めの従来例を示す平面図で
ある。
FIG. 6 is a plan view showing a conventional example of positioning a reinforcing bar in a formwork.

【図7】鉄筋位置決め部材の他の従来例を示す平面図で
ある。
FIG. 7 is a plan view showing another conventional example of a reinforcing bar positioning member.

【符号の説明】[Explanation of symbols]

L 鉄筋コンクリート柱構築場所 1 鉄筋部 11 主筋 12 補助鉄筋 2 コンクリート打設用型枠 2A 型枠2の外側面 2B 型枠2の外側面2Aに隣合う外側面 21 支え棒装置 22 支持部 23 張設装置 24 型枠2の上端面 25 型枠2の上端面とそれに続く外側面との角部分 3 鉄筋位置決め治具 31、32 主筋当接凹部 33 治具3の平坦部分 341、342 型枠係合部 35 釘孔 30 釘 36 主筋連結用突起棒 37 針金 4 コンクリート打設高さ標示兼梁支持部材 5 コンクリート L Reinforced concrete column construction place 1 Reinforcing bar part 11 Main bar 12 Auxiliary rebar 2 Formwork for concrete placement 2A Outside surface of formwork 2B Outside surface 2B adjacent to outside surface 2A of formwork 21 Support rod device 22 Support part 23 Extension Device 24 Upper end face of formwork 2 25 Corner part between upper end face of formwork 2 and outer side following it 3 Reinforcing bar positioning jig 31, 32 Main bar contact recess 33 33 Flat part of jig 3 341, 342 Formwork engagement Part 35 Nail hole 30 Nail 36 Protrusion bar for connecting main bars 37 Wire 4 Concrete pouring height indicator and beam support member 5 Concrete

Claims (7)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 構築しようとする鉄筋コンクリート柱の
水平断面における所定位置に配置されるべき縦方向主筋
とそれら主筋に連結された補助鉄筋とを含む鉄筋部を所
定位置に立設する工程と、前記鉄筋部を囲むコンクリー
ト打設用型枠を構築する工程と、前記鉄筋部を前記型枠
内に位置決めする工程と、前記型枠内面にコンクリート
打設高さ標示兼梁支持部材を取り付ける工程と、前記鉄
筋部の型枠内位置決め後、且つ、前記型枠内面へのコン
クリート打設高さ標示兼梁支持部材の取り付け後に前記
型枠内にコンクリートを打設する工程とを含み、前記型
枠内における前記鉄筋部の位置決め工程では、鉄筋位置
決め治具であって前記主筋を型枠内の所定位置に位置決
めするために当接させる主筋当接部及び該主筋当接部を
主筋位置決め位置に配置するように治具全体を型枠上端
部に位置決めするための型枠係合部とを有する治具を該
型枠係合部で型枠所定位置に係合位置決めして該型枠に
取り外し可能に固定し、該固定した治具の前記主筋当接
部にそれに対応する主筋を型枠内側から当接させて該治
具に取り外し可能に連結固定することを特徴とする鉄筋
コンクリート柱の構築方法。
1. A step of vertically arranging a reinforcing bar portion including a vertical main bar to be arranged at a predetermined position in a horizontal cross section of a reinforced concrete column to be constructed and an auxiliary reinforcing bar connected to the main bar at a predetermined position, A step of constructing a concrete casting form surrounding the reinforcing part, a step of positioning the reinforcing part in the form, and forming a concrete on the inner surface of the form.
The step of attaching the driving height indicator and beam support member , and the positioning of the reinforcing bars in the formwork , and the connection to the inner surface of the formwork.
A step of placing concrete in the formwork after attaching the cleat placement height marking and beam support member, and in the step of positioning the reinforcing bar portion in the formwork, the reinforcing bar positioning jig and the main bar For contacting the main jig to position the main jig at a predetermined position in the formwork, and a formworker for positioning the entire jig on the upper end of the formwork so that the mainstay contacting part is located at the main-use position. A jig having a mating portion is engaged and positioned at a predetermined position of the mold by the mold engaging portion and is detachably fixed to the mold, which corresponds to the main bar contact portion of the fixed jig. A method for constructing a reinforced concrete column, characterized in that a main bar is brought into contact with the inside of a formwork and detachably connected and fixed to the jig.
【請求項2】 構築しようとする鉄筋コンクリート柱の
水平断面における隅部分に配置されるべき縦方向主筋と
それら主筋に連結された補助鉄筋とを含む鉄筋部を所定
位置に立設する工程と、前記鉄筋部を囲むコンクリート
打設用型枠を構築する工程と、前記鉄筋部を前記型枠内
に位置決めする工程と、前記鉄筋部の型枠内位置決め後
に前記型枠内にコンクリートを打設する工程とを含み、
前記型枠内における前記鉄筋部の位置決め工程では、鉄
筋位置決め治具であって前記主筋を型枠内の所定位置に
位置決めするために当接させる主筋当接部及び該主筋当
接部を主筋位置決め位置に配置するように治具全体を型
枠上端隅角部分に位置決めするための、該型枠上端隅角
部分において該型枠上面からそれに続く一つの外側面に
かけての型枠角部分に係合できる型枠係合部及び該型枠
上面からそれに続き、前記外側面に隣合う外側面にかけ
ての型枠角部分に係合できる型枠係合部を有している治
具をそれら型枠係合部で前記型枠角部分に係合させて該
型枠上端隅角部分に位置決めするとともに取り外し可能
に固定し、該固定した治具の前記主筋当接部にそれに対
応する主筋を型枠内側から当接させて該治具に取り外し
可能 に連結固定することを特徴とする鉄筋コンクリート
柱の構築方法。
2. A reinforced concrete column to be constructed
With the longitudinal main bars that should be placed in the corners of the horizontal section
Predetermined reinforcing bar parts including auxiliary reinforcing bars connected to the main bars
And the concrete that surrounds the reinforcing bars.
The step of constructing the casting form, and the reinforcing bar portion in the form
And the positioning of the rebar within the formwork
And including the step of placing concrete in the form,
In the step of positioning the reinforcing bar portion in the mold,
It is a muscle positioning jig and the main muscle is placed at a predetermined position in the mold.
Main bar contacting part to be contacted for positioning and main bar contact
Mold the entire jig so that the contact part is located at the main bar positioning position.
Top corner of the formwork for positioning at the top corner of the form
From the top surface of the formwork to the one outer surface that follows
Form frame engaging part capable of engaging with the corner part of the form frame
From the top to the outer surface next to the outer surface
All molds have a frame engaging part that can engage with the corners of the frame.
The tool by engaging the corners of the mold with the mold engaging portions.
Can be removed while positioning on the top corner of the formwork
To the main bar contact portion of the fixed jig.
Abut the corresponding main bar from the inside of the form and remove it from the jig.
A method for constructing a reinforced concrete column, characterized by connecting and fixing as much as possible .
【請求項3】 前記コンクリート打設前に前記型枠内面
にコンクリート打設高さ標示兼梁支持部材を取り付ける
請求項2記載の鉄筋コンクリート柱の構築方法。
3. The inner surface of the formwork before the concrete is poured.
Attach concrete pouring height indicator and beam support member to
The method for constructing a reinforced concrete column according to claim 2 .
【請求項4】 水平断面が四角形状の鉄筋コンクリート
柱の構築方法であり、構築しようとする該鉄筋コンクリ
ート柱の四角形状水平断面の各隅部に3本ずつ配置され
るべき縦方向主筋と該主筋に連結された補助鉄筋とを含
む鉄筋部を所定位置に立設する工程と、前記鉄筋部を囲
むコンクリート打設用型枠を構築する工程と、前記鉄筋
部を前記型枠内に位置決めする工程と、前記鉄筋部の型
枠内位置決め後に前記型枠内にコンクリートを打設する
工程とを含み、前記型枠内における前記鉄筋部の位置決
め工程では、鉄筋位置決め治具であって前記主筋を型枠
内の所定位置に位置決めするために当接させる主筋当接
部及び該主筋当接部を主筋位置決め位置に配置するよう
に治具全体を型枠上端部に位置決めするための型枠係合
部とを有する治具を該型枠係合部で型枠所定位置に係合
位置決めして該型枠に取り外し可能に固定し、該固定し
た治具の前記主筋当接部にそれに対応する主筋を型枠内
側から当接させて該治具に取り外し可能に連結固定する
ようにし、前記治具として、前記3本一組の主筋のそれ
ぞれの組に対して前記型枠上端隅角部分に固定される治
具であって、それぞれが、前記主筋当接部を3本一組の
主筋のそれぞれが当接できるように3箇所有していると
ともに前記型枠係合部を前記型枠上面からそれに続く一
つの外側面にかけての型枠角部分及び該型枠上面からそ
れに続き、前記外側面に隣合う外側面にかけての型枠角
部分にそれぞれ係合できるように少なくとも2箇所有し
ているものを採用することを特徴とする鉄筋コンクリー
ト柱の構築方法。
4. Reinforced concrete having a rectangular horizontal cross section
This is a method of constructing a pillar, and
Three pieces are arranged at each corner of the rectangular horizontal section of the pillar.
To include the longitudinal main bar and the auxiliary reinforcing bar connected to the main bar.
The step of standing the reinforcing bar at a predetermined position, and surrounding the reinforcing bar
And a step of constructing a concrete pouring formwork,
Of positioning a part in the mold, and a mold for the reinforcing bar part
Placing concrete in the mold after positioning in the frame
Positioning the rebar within the formwork, including the steps
In the step of forming,
Abutment of the main bar to be contacted to position it in a predetermined position
The main part and the main bar contact part at the main bar positioning position
Form engagement for positioning the entire jig on the upper end of the form
The jig having the part is engaged at the predetermined position of the mold with the mold engaging part.
Position and removably secure to the form,
The main bar corresponding to the main bar contact part of the jig
Abut on the side and removably connect and fix to the jig
Then, as the jig, that of the main bar of the set of 3 pieces
For each set, the jig fixed to the upper corner of the formwork
And a set of three main muscle contact portions
If you have three places so that each of the main bars can contact
In both cases, the mold frame engaging portion is connected to the mold frame from the top surface to the subsequent one.
Corners of the two outer surfaces and the upper surface of the mold.
Then, the formwork angle to the outer surface adjacent to the outer surface
Has at least two points to engage each part
Reinforced concrete concrete characterized by adopting
How to build a pillar.
【請求項5】 前記コンクリート打設前に前記型枠内面
にコンクリート打設高さ標示兼梁支持部材を取り付ける
請求項4記載の鉄筋コンクリート柱の構築方法。
5. The inner surface of the formwork before the concrete is poured.
Attach concrete pouring height indicator and beam support member to
The method for constructing a reinforced concrete column according to claim 4.
【請求項6】 請求項2記載の鉄筋コンクリート柱の構6. The structure of the reinforced concrete column according to claim 2.
築方法の実施に用いる鉄筋位置決め治具であって、前記A reinforcing bar positioning jig used for carrying out the construction method,
鉄筋部の主筋を型枠内の所定位置に位置決めするためにIn order to position the main bar of the reinforcing bar at a predetermined position in the formwork
当接させる主筋当接部及び該主筋当接部を主筋位置決めMain bar contacting part to be contacted and main bar contacting part
位置に配置すPlace るように治具全体を型枠上端隅角部分に位Place the entire jig on the upper corner of the formwork.
置決めするための、該型枠上端隅角部分において該型枠The formwork at the top corners of the formwork for positioning
上面からそれに続く一つの外側面にかけての型枠角部分Formwork corners from the top surface to the one outer surface that follows
に係合できる型枠係合部及び該型枠上面からそれに続From the upper surface of the mold and the mold engaging portion that can be engaged with
き、前記外側面に隣合う外側面にかけての型枠角部分にThe corners of the form frame extending to the outer surface adjacent to the outer surface.
係合できる型枠係合部を有していることを特徴とする鉄Iron characterized by having a formwork engaging part that can be engaged
筋位置決め治具。Muscle positioning jig.
【請求項7】 請求項4記載の鉄筋コンクリート柱の構7. The structure of the reinforced concrete column according to claim 4.
築方法の実施に用いる鉄筋位置決め治具であって、前記A reinforcing bar positioning jig used for carrying out the construction method,
鉄筋部の主筋を型枠内の所定位置に位置決めするためにIn order to position the main bar of the reinforcing bar at a predetermined position in the formwork
当接させる主筋当接部及び該主筋当接部を主筋位置決めMain bar contacting part to be contacted and main bar contacting part
位置に配置するように治具全体を型枠上端部に位置決めPosition the entire jig on the top edge of the mold so that it is placed in position
するための型枠係合部とを有しており、水平断面が四角Has a formwork engaging part for
形状のコンクリート柱の各隅部に3本ずつ配置されるべThree pieces should be placed at each corner of the concrete pillar.
き縦方向主筋の該3本一組の主筋のそれぞれの組に対応Corresponds to each set of the main bar of the three longitudinal main bars
でき、前記主筋当接部を3本一組の主筋のそれぞれが当Yes, the main bar contact parts should be in contact with each of the three main bars.
接できるように3箇所有しているとともに前記型枠係合It has 3 places so that it can come into contact with it
部を前記型枠上面からそれに続く一つの外側面にかけてFrom the top of the mold to the outer surface that follows
の型枠角部分及び該型枠上面からそれに続き、前記外側The corners of the mold and the top of the mold, followed by the outside
面に隣合う外側面にかけての型枠角部分にそれぞれ係合Engage with the corners of the formwork to the outer surface adjacent to the surface
できるように少なくとも2箇所有していることを特徴とCharacterized by having at least two places so that
する鉄筋位置決め治具。Reinforcing bar positioning jig.
JP6247425A 1994-10-13 1994-10-13 Construction method of reinforced concrete columns and reinforcing bar positioning jig used for the implementation Expired - Fee Related JP2670427B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6247425A JP2670427B2 (en) 1994-10-13 1994-10-13 Construction method of reinforced concrete columns and reinforcing bar positioning jig used for the implementation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6247425A JP2670427B2 (en) 1994-10-13 1994-10-13 Construction method of reinforced concrete columns and reinforcing bar positioning jig used for the implementation

Publications (2)

Publication Number Publication Date
JPH08109745A JPH08109745A (en) 1996-04-30
JP2670427B2 true JP2670427B2 (en) 1997-10-29

Family

ID=17163253

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6247425A Expired - Fee Related JP2670427B2 (en) 1994-10-13 1994-10-13 Construction method of reinforced concrete columns and reinforcing bar positioning jig used for the implementation

Country Status (1)

Country Link
JP (1) JP2670427B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963431A (en) * 2015-07-17 2015-10-07 南通德源建设工程科技有限公司 Corner structural column construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1336704B1 (en) 2002-02-15 2013-02-13 NTT Infrastructure Network Corporation Concrete electric pole and method for reinforcing the same
CN103195255B (en) * 2013-03-29 2015-07-15 华北水利水电学院 Construction method for prestressed carbon-fiber reinforced plastic (CFRP) reinforced concrete beam

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0552113U (en) * 1991-12-19 1993-07-09 戸田建設株式会社 Jig for rising rebar

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963431A (en) * 2015-07-17 2015-10-07 南通德源建设工程科技有限公司 Corner structural column construction method

Also Published As

Publication number Publication date
JPH08109745A (en) 1996-04-30

Similar Documents

Publication Publication Date Title
JP2670427B2 (en) Construction method of reinforced concrete columns and reinforcing bar positioning jig used for the implementation
JP3763575B2 (en) Underground beam construction frame and underground beam construction method using the same
JP4111214B2 (en) How to mount the gate block reinforcing bar to the formwork for manufacturing the coupler assembling jig and the reinforcing bar with the coupler
JP3019138U (en) Formwork structure for making cotters on top of girders
JP2002097791A (en) Form support metal
JP2004019303A (en) Anchor bolt fixing device
JPH0459978B2 (en)
JPH0447300Y2 (en)
JP2838922B2 (en) Pillar standing method
JPH048199Y2 (en)
JPH06341167A (en) Working method for concrete structure
JPH0712436Y2 (en) Foundation base muscle positioning jig
JPH0645000Y2 (en) Anchor bolt arrangement ruler
JPS5920489Y2 (en) Anchor bolt mounting structure
JP2611917B2 (en) Pillar formwork equipment
JP3014179U (en) Two column base anchor bolts
JPH0438039Y2 (en)
JP2004027647A (en) Steel structure of house, and its construction method
JPH0132345B2 (en)
JP2528349Y2 (en) Concrete frame fixture
JP3037869U (en) Anchor bolt support plate
JPH0476117A (en) Supporting device for anchor bolt
JP2005320686A (en) Reinforcement assembly body used for housing foundation and construction method of the housing foundation making use of the assembly body
JP2003239299A (en) Anchor bolt mounting device
JPH0633073Y2 (en) Precast concrete beam

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970617

LAPS Cancellation because of no payment of annual fees