JP2655137B2 - Slope construction method - Google Patents
Slope construction methodInfo
- Publication number
- JP2655137B2 JP2655137B2 JP18334795A JP18334795A JP2655137B2 JP 2655137 B2 JP2655137 B2 JP 2655137B2 JP 18334795 A JP18334795 A JP 18334795A JP 18334795 A JP18334795 A JP 18334795A JP 2655137 B2 JP2655137 B2 JP 2655137B2
- Authority
- JP
- Japan
- Prior art keywords
- ground
- formwork
- anchors
- bag
- sheet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、土木工事で用いられる
グラウンドアンカー工法を基礎に、斜面や垂直面等の法
面を強固に保持する法面施工方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a slope construction method for firmly holding a slope such as a slope or a vertical surface based on a ground anchor construction method used in civil engineering works.
【0002】[0002]
【従来の技術】斜面や垂直面等の法面において地盤を安
定に保持するために、従来、多数のグラウンドアンカー
を法面上に所定間隔に設け、さらに各アンカー間に梁を
渡設して、各アンカーを結合する法面施工方法が行なわ
れてきた。この方法により、地盤を一体化した各アンカ
ーで保持して地盤の安定性が高まった。しかし、各アン
カーを結合する梁の打設において、底板のある型枠を各
アンカー間に設けた場合は、完成した梁と地盤表面とが
接触しても、地盤表面の凹凸や石の存在により不均等な
部分接触となり、アンカーの引張による梁の地盤への押
付力が集中荷重でしか伝わらず、梁から地盤への有効な
プレストレスとして作用しなかった。型枠に底板を設け
ず直に地盤に打設した場合には、完成した梁と地盤表面
は完全に密着するが、地盤に梁の重さが加わるのみでプ
レストレスは作用しなかった。このため、アンカー周辺
以外の地盤にはアンカーによるプレストレスが働きにく
く、不安定になって法面崩壊を引き起こす可能性があっ
た。不安定化を防ぐためにはアンカーの設置密度を上げ
なければならないが、間隔を狭めるのにも限界があり、
十分な法面強度を得るのが難しかった。2. Description of the Related Art In order to stably hold the ground on a slope such as a slope or a vertical surface, conventionally, a large number of ground anchors are provided at predetermined intervals on the slope and beams are provided between the anchors. The slope construction method of connecting each anchor has been performed. According to this method, the stability of the ground was improved by holding the ground with each of the integrated anchors. However, when placing a formwork with a bottom plate between the anchors when placing the beams connecting the anchors, even if the completed beam and the ground surface are in contact with each other, due to the unevenness of the ground surface and the presence of stones Non-uniform partial contact occurred, and the pressing force of the beam to the ground due to the tension of the anchor was transmitted only by concentrated load, and did not act as an effective prestress from the beam to the ground. When the formwork was directly driven into the ground without providing a bottom plate, the completed beam and the ground surface were completely adhered to each other, but the prestress did not act because only the weight of the beam was added to the ground. For this reason, the prestress by the anchor is unlikely to work on the ground other than around the anchor, and there is a possibility that the slope may collapse due to instability. In order to prevent instability, it is necessary to increase the installation density of anchors, but there is a limit to narrowing the spacing,
It was difficult to obtain sufficient slope strength.
【0003】[0003]
【発明が解決しようとする課題】本発明が解決しようと
する課題は、上記した問題点を解決し、地盤表面の広い
範囲にプレストレスを均等に発生させ、地盤を強く、安
定に保持する法面施工方法を提供することにある。SUMMARY OF THE INVENTION An object of the present invention is to solve the above-mentioned problems, to uniformly generate prestress over a wide area of the ground surface, and to keep the ground strong and stable. It is to provide a surface construction method.
【0004】[0004]
【課題を解決するための手段】かかる課題を解決した本
発明の構成は、 1) 法面に所定間隔に離して複数のグラウンドアンカ
ーを設け、これらグラウンドアンカーの地上定着部間に
グラウンドアンカー間を連結するコンクリート梁用型枠
を設置すると共に、型枠と地盤の間に梁底面と略同じ広
さの袋を敷いてから、前記型枠にコンクリートを打設し
て各グラウンドアンカーと一体化した梁を形成し、その
型枠を取外した後、前記袋内にモルタル等の硬化する充
填物を圧入して膨張させ、梁と地盤の間の空隙を袋で隙
間なく埋め、圧力をかけた状態で保持して充填物を硬化
させ、袋から下方の地盤にプレストレスが加わるように
した、法面施工方法 2) 法面に所定間隔に離して複数のグラウンドアンカ
ーを設け、これらグラウンドアンカーの地上定着部間に
グラウンドアンカー間を連結するコンクリート梁用型枠
を設置すると共に、型枠と地盤の間に梁底面と略同じ広
さの吸水して膨張し膨張後の形状を維持する性質を備え
たシートを敷いてから、前記型枠にコンクリートを打設
して各グラウンドアンカーと一体化した梁を形成し、そ
の型枠を取外した後、前記シートを吸水させて膨張さ
せ、梁と地盤の間の空隙をシートで隙間なく埋め、完全
に膨張させて圧力が高まった状態に維持して、シートか
ら下方の地盤にプレストレスが加わるようにした、法面
施工方法 3) 前記各グラウンドアンカー間の型枠内に鉄筋を配
し、この鉄筋をグラウンドアンカーの地上定着部と連結
させた後、型枠にコンクリートを打設して各グラウンド
アンカーと一体化した梁を形成した、前記1)に記載の
法面施工方法 4) 前記各グラウンドアンカー間の型枠内に鉄筋を配
し、この鉄筋をグラウンドアンカーの地上定着部と連結
させた後、型枠にコンクリートを打設して各グラウンド
アンカーと一体化した梁を形成した、前記2)に記載の
法面施工方法にある。Means for Solving the Problems The constitution of the present invention which has solved the above problems is as follows: 1) A plurality of ground anchors are provided at predetermined intervals on a slope, and a ground anchor is provided between the ground anchors of these ground anchors. While installing the concrete beam formwork to be connected, laying a bag approximately the same size as the beam bottom between the formwork and the ground, concrete was poured into the formwork and integrated with each ground anchor After forming the beam and removing the formwork, a hardening filler such as mortar is press-fitted into the bag to expand it, and the gap between the beam and the ground is completely filled with the bag and pressure is applied. Slope construction method in which the filler is hardened by holding in a manner and prestress is applied to the ground below the bag. 2) A plurality of ground anchors are provided at predetermined intervals on the slope and A concrete beam formwork that connects the ground anchors between the ground anchorage sections is installed, and between the formwork and the ground, it absorbs water of almost the same size as the beam bottom and expands to maintain the expanded shape. After laying the sheet provided, concrete is poured into the formwork to form a beam integrated with each ground anchor, and after removing the formwork, the sheet is allowed to absorb water and expanded, and the beam and the ground are removed. The slope between the ground anchors is filled with a sheet without gaps and completely expanded to maintain a high pressure so that prestress is applied to the ground below from the sheet. Reinforcing bars were arranged in the formwork between them, and after connecting the reinforcing bars to the ground anchorage of the ground anchor, concrete was poured into the formwork to form beams integrated with each ground anchor. 1) Written in 4) Reinforcing bars are arranged in the formwork between the ground anchors, and the rebars are connected to the ground anchoring portion of the ground anchor, and then concrete is poured into the formwork to form the ground anchors. The slope construction method according to 2), wherein an integrated beam is formed.
【0005】本発明の方法で、梁と地盤表面間に敷いて
用いる硬化する充填物を圧入する袋には、アラミド繊維
など凹凸面に接触して高い圧力を加えられても破れない
強度のある素材の織布袋やゴム袋などが主に用いられ
る。袋に充填する充填物には、モルタルやグラウト、コ
ンクリート等の硬化材が主に用いられる。また、前記同
様に用いる、吸水して膨張し膨張後の形状を維持する性
質をもつシートには、吸水で不可逆的に3〜4倍膨張し
て1.5kgf/cm2位までの圧力に耐えて形状を保つ
ポリアクリル酸ソーダなどの高分子材料とゴムを混ぜて
可撓性を持ったシート状に加工したものが使用される。[0005] In the method of the present invention, the bag for press-fitting the hardening filler used between the beam and the ground surface has a strength that does not break even when high pressure is applied in contact with an uneven surface such as aramid fiber. A woven cloth bag or a rubber bag made of a material is mainly used. Hardening materials such as mortar, grout, concrete and the like are mainly used for filling the bag. Further, the sheet used in the same manner as described above and having the property of expanding by absorbing water and maintaining the shape after expansion, irreversibly expands 3 to 4 times by absorbing water and withstands a pressure up to about 1.5 kgf / cm 2. A material obtained by mixing a rubber and a polymer material such as sodium polyacrylate that maintains its shape and processing it into a flexible sheet shape is used.
【0006】[0006]
【作用】本発明の法面施工方法では、まず、法面に所定
の間隔をおいて、複数のグラウンドアンカーを打設す
る。次に、各グラウンドアンカーの地上定着部間に設置
するコンクリート梁底面と略同じ広さの袋を梁の真下に
あたる地盤表面に敷き、この上に梁用型枠を設置する。
型枠内にコンクリートを打設して硬化させ、梁を形成し
て型枠取外し後、モルタル等の硬化する充填物を梁の下
の袋内に圧入装置を用いて圧入する。充填物で膨張した
袋は梁底面と地盤表面間にできた隙間を埋め、上下面が
両面にそれぞれ密着する。袋内の圧力が所定量に達した
ら、圧力を保持したまま充填物の圧入を止め、袋を密封
する。同時に他の梁にも同様の作業を行い、充填物が硬
化すると、梁下方の地盤にも、梁によって上側を支えら
れた袋からプレストレスを与えることができる。According to the slope construction method of the present invention, a plurality of ground anchors are first placed at predetermined intervals on the slope. Next, a bag of approximately the same size as the bottom of the concrete beam to be installed between the ground anchors of each ground anchor is laid on the ground surface directly below the beam, and a beam formwork is placed thereon.
Concrete is poured into a mold and hardened, a beam is formed, and the mold is removed. After that, a hardening filler such as mortar is press-fitted into a bag below the beam using a press-fitting device. The bag inflated with the filling fills the gap between the bottom of the beam and the surface of the ground, and the upper and lower surfaces adhere to both surfaces. When the pressure in the bag reaches a predetermined amount, press-fitting of the filling is stopped while maintaining the pressure, and the bag is sealed. At the same time, the same operation is performed on the other beams, and when the filling hardens, the ground below the beams can be prestressed from the bag supported on the upper side by the beams.
【0007】梁と地盤表面の間に吸水して膨張し膨張後
の形状を維持する性質をもつシートを設ける施工方法で
は、上記した袋の場合と同様に、法面に所定間隔でグラ
ウンドアンカーを打設する。次に、各グラウンドアンカ
ーの地上定着部間に設置するコンクリート梁底面と略同
じ広さのシートを梁の真下にあたる地盤表面に敷き、こ
の上に梁用型枠を設置する。型枠内にコンクリートを打
設して硬化させ、梁を形成して型枠取外し後、梁の下の
シートに十分な水分を与えると、シートは吸水して膨張
し、梁底面と地盤表面にできた隙間を埋めて、両面にシ
ートの上下面がそれぞれ密着する。吸水によるシートの
膨張が完全に止まれば、梁と地盤表面間に挟まれて圧力
が高まった状態のままシート形状が維持される。こうし
て梁下方の地盤にも、梁によって上側を支えられたシー
トからプレストレスを与えることができる。[0007] In the construction method of providing a sheet having the property of absorbing water and expanding and maintaining the shape after expansion between the beam and the ground surface, ground anchors are provided at predetermined intervals on the slope, as in the case of the bag described above. Cast in. Next, a sheet having substantially the same size as the bottom surface of the concrete beam installed between the ground anchoring portions of the ground anchors is laid on the ground surface directly below the beam, and a beam form is installed thereon. After casting concrete in the formwork and hardening, forming a beam and removing the formwork, give enough moisture to the sheet under the beam, the sheet will absorb water and expand, and it will spread to the bottom of the beam and the ground surface The upper and lower surfaces of the sheet are brought into close contact with both sides, respectively, to fill the gap thus formed. If the expansion of the sheet due to the water absorption is completely stopped, the sheet shape is maintained with the pressure increased between the beam and the ground surface. Thus, prestress can also be applied to the ground below the beam from the sheet whose upper side is supported by the beam.
【0008】各グラウンドアンカーの地上定着部を鉄筋
で連結した上でコンクリートの梁を形成する施工方法で
は、所定間隔の各グラウンドアンカー間にコンクリート
梁底面と略同じ広さの袋またはシートを敷き、この上に
梁用型枠を設置するのに加えて、型枠内に配置した鉄筋
の両端をそれぞれ地上定着部に取り付けて、鉄筋でグラ
ウンドアンカーを連結した形にする。鉄筋を囲む型枠が
できたら、型枠内にコンクリートを打設して硬化させ、
梁を形成する。この後、袋またはシートを膨張させる作
業を行えばよい。In the construction method in which the ground anchoring portions of the ground anchors are connected to each other by a reinforcing bar to form a concrete beam, a bag or sheet having substantially the same size as the bottom of the concrete beam is laid between the ground anchors at predetermined intervals. In addition to installing the beam formwork on this, both ends of the reinforcing bars arranged in the formwork are attached to the ground anchoring sections, respectively, and the ground anchor is connected by the reinforcing bars. Once the formwork surrounding the rebar has been created, cast concrete into the formwork and cure it.
Form a beam. Thereafter, the operation of expanding the bag or sheet may be performed.
【0009】[0009]
【実施例】本発明の実施例1、2を図面に基づいて説明
する。実施例1は各グラウンドアンカー間に鉄筋入りの
梁を設置し梁の下にあらかじめ敷いた袋にモルタルを圧
入して膨張させる施工方法の例、実施例2は実施例1の
袋を吸水して膨張するシートと置き換えた例である。図
1は実施例1のコンクリート梁の打設工程を示す説明
図、図2は実施例1の袋の膨張工程を示す説明図、図3
は実施例1のグラウンドアンカーの要部を示す断面図、
図4は実施例1の袋の膨張状態を示す断面図、図5は実
施例1の梁の型枠設置状態を示す説明図、図6は実施例
1の梁と袋の設置状態を示す説明図、図7は実施例2の
シートの膨張工程を示す説明図である。実施例1の法面
施工方法では、まずグラウンドアンカー1の引張部材3
の一端を、地中にアンカー体2を打設することにより、
法面を構成する地盤17に固定する。同様に、複数の引
張部材3を法面上に約2mピッチに配置して地盤17に
固定していく。これら各引張部材3の地表露出部に、コ
ンクリート梁の鉄筋8の接合用鉄筋5を複数本設けてい
る台座4を各々設置する。この台座4上に定着具7およ
び支圧板6を載せ、定着具7を引張部材3に定着してこ
れらが地上定着部となるグラウンドアンカー1とし、台
座4と地盤17間に所定の緊張力を作用させる。次に、
各グラウンドアンカー1間に渡設する30cm角のコン
クリート梁10の底面と略同じ広さのアラミド繊維製の
袋13を梁10下に対応する位置の地盤17表面に載せ
る。それから鉄筋8の両端を台座4の接合用鉄筋8に溶
接して、各グラウンドアンカー1を鉄筋8で連結するの
と同時に、梁10用型枠9を各グラウンドアンカー1間
に設置する。型枠9内にコンクリート11を打設し硬化
させて梁10を形成した後、型枠9を取外し、モルタル
14を圧入装置12により梁10下の袋13内に圧入す
る。モルタル14の圧入で袋13は膨張して梁10底面
と地盤17表面間にできた隙間を埋め、両面に袋13の
上下面がそれぞれ密着して袋13から均等な圧力が加わ
るようになる。袋13内の圧力が、袋13から地盤17
へ十分なプレストレスを与えられるだけの圧力に達した
ら、この圧力を保持した状態でモルタル14の圧入を止
め、袋13を密封して硬化させる。モルタル14硬化後
は、両端のグラウンドアンカー1に強固に保持された梁
10に上側を支えられた袋13から下面の地盤17に均
等なプレストレスを与えることができ、地盤17が強く
保持される。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments 1 and 2 of the present invention will be described with reference to the drawings. Example 1 is an example of a construction method in which a beam containing a reinforcing bar is installed between ground anchors, and mortar is pressed into a bag previously laid under the beam to expand the mortar, and Example 2 absorbs the bag of Example 1 by absorbing water. This is an example in which the sheet is replaced with an expanding sheet. FIG. 1 is an explanatory diagram showing a concrete beam placing process of the first embodiment, FIG. 2 is an explanatory diagram showing a bag expanding process of the first embodiment, and FIG.
Is a cross-sectional view showing a main part of the ground anchor of Example 1.
FIG. 4 is a cross-sectional view showing an inflated state of the bag according to the first embodiment, FIG. 5 is an explanatory view showing an installed state of the beam formwork of the first embodiment, and FIG. 6 is an explanatory view showing an installed state of the beam and the bag of the first embodiment. FIG. 7 and FIG. 7 are explanatory views showing the sheet expanding process of the second embodiment. In the slope construction method of the first embodiment, first, the tension member 3 of the ground anchor 1 is used.
By placing an anchor body 2 in the ground
It is fixed to the ground 17 constituting the slope. Similarly, the plurality of tension members 3 are arranged on the slope at a pitch of about 2 m and fixed to the ground 17. A pedestal 4 provided with a plurality of reinforcing bars 5 for connecting the reinforcing bars 8 of concrete beams is installed on the exposed surface of each of the tension members 3. The fixing device 7 and the support plate 6 are placed on the pedestal 4, and the fixing device 7 is fixed to the tension member 3 to form a ground anchor 1 serving as a ground fixing portion. Let it work. next,
An aramid fiber bag 13 having substantially the same size as the bottom surface of a 30 cm square concrete beam 10 to be provided between the ground anchors 1 is placed on the surface of the ground 17 at a position corresponding to the position below the beam 10. Then, both ends of the reinforcing bar 8 are welded to the connecting reinforcing bar 8 of the pedestal 4, and the ground anchors 1 are connected by the reinforcing bar 8, and at the same time, the form 9 for the beam 10 is installed between the ground anchors 1. After the concrete 11 is cast into the form 9 and hardened to form the beam 10, the form 9 is removed, and the mortar 14 is pressed into the bag 13 below the beam 10 by the press-fitting device 12. When the mortar 14 is pressed into the bag 13, the bag 13 expands and fills the gap formed between the bottom surface of the beam 10 and the surface of the ground 17. The pressure in the bag 13 increases from the bag 13 to the ground 17.
When a pressure sufficient to give sufficient prestress is reached, press-fitting of the mortar 14 is stopped while maintaining this pressure, and the bag 13 is sealed and cured. After the mortar 14 is hardened, a uniform pre-stress can be applied to the ground 17 on the lower surface from the bag 13 supported on the upper side by the beams 10 firmly held by the ground anchors 1 at both ends, and the ground 17 is strongly held. .
【0010】実施例2の法面施工方法は、実施例1の袋
13を、吸水すると不可逆的に3〜4倍程度膨張し、変
化完了後その形状を保つシート15(例えば、川口エー
ス工業株式会社製ナイスシール(商標)など)に置き換
えたもので、その他の工程は実施例1と同様に行われ
る。グラウンドアンカー1を法面上に複数設けた後、約
2mピッチのグラウンドアンカー1間に渡設する30c
m角のコンクリート梁10の底面と略同じ広さの、袋1
3の代わりとなるシート15を載せる。実施例1と同様
に鉄筋8と型枠9を設け、コンクリート11を打設し硬
化させて梁10を形成してから、型枠9を除去する。こ
の後、シート15が完全に膨張するのに十分な量の水1
6を与えると、シート15は吸水により膨張して梁10
底面と地盤17表面間にできた隙間を埋め、両面にシー
ト15の上下面がそれぞれ密着してシート15から均等
な圧力が加わるようになる。膨張が完了してシート15
の形状が固定化すると、両端のグラウンドアンカー1に
強固に保持された梁10に上側を支えられるシート15
から下面の地盤17に均等なプレストレスを与えること
ができ、地盤17が強く保持される。[0010] In the slope construction method of the second embodiment, the bag 13 of the first embodiment irreversibly expands about 3 to 4 times when absorbing water, and retains its shape after the change is completed. (Ex. Nice Seal (trademark) made by a company). After a plurality of ground anchors 1 are provided on the slope, 30c is provided between the ground anchors 1 having a pitch of about 2 m.
A bag 1 having approximately the same size as the bottom of the m-square concrete beam 10
The sheet 15 that is used in place of the sheet 3 is placed. As in the first embodiment, the reinforcing bar 8 and the formwork 9 are provided, concrete 11 is cast and hardened to form the beam 10, and then the formwork 9 is removed. After this, a sufficient amount of water 1 to fully expand the sheet 15
6, the sheet 15 expands due to water absorption and the beam 10
The gap formed between the bottom surface and the surface of the ground 17 is filled, and the upper and lower surfaces of the sheet 15 are in close contact with both surfaces, so that a uniform pressure is applied from the sheet 15. When the expansion is completed, the sheet 15
Is fixed, the sheet 15 supported on the upper side by the beam 10 firmly held by the ground anchors 1 at both ends.
Thus, an even prestress can be applied to the ground 17 on the lower surface, and the ground 17 is strongly held.
【0011】[0011]
【発明の効果】本発明は上記した構成を採用することに
より、各グラウンドアンカーと、その間に渡設された梁
の下の袋またはシートとで、地盤表面のより多くの部分
に密着して、プレストレスを均等に与えることができ、
地盤を強く安定に保持して法面が不安定になる危険性を
極めて小さくする。According to the present invention, by adopting the above-described structure, each ground anchor and the bag or sheet under the beam provided between the ground anchors are in close contact with a larger portion of the ground surface, Prestress can be given evenly,
Keeping the ground strong and stable minimizes the risk of instability in the slope.
【図1】実施例1のコンクリート梁の打設工程を示す説
明図である。FIG. 1 is an explanatory view showing a concrete beam placing process of Example 1.
【図2】実施例1の袋の膨張工程を示す説明図である。FIG. 2 is an explanatory view showing an inflation step of the bag according to the first embodiment.
【図3】実施例1のグラウンドアンカーの要部を示す断
面図である。FIG. 3 is a cross-sectional view illustrating a main part of the ground anchor according to the first embodiment.
【図4】実施例1の袋の膨張状態を示す断面図である。FIG. 4 is a sectional view showing an inflated state of the bag according to the first embodiment.
【図5】実施例1の梁の型枠設置状態を示す説明図であ
る。FIG. 5 is an explanatory view showing a state in which a beam formwork is installed in the first embodiment.
【図6】実施例1の梁と袋の設置状態を示す説明図であ
る。FIG. 6 is an explanatory diagram showing an installation state of a beam and a bag according to the first embodiment.
【図7】実施例2のシートの膨張工程を示す説明図であ
る。FIG. 7 is an explanatory view showing a sheet expanding process of Example 2.
1 グラウンドアンカー 2 アンカー体 3 引張部材 4 台座 5 接合用鉄筋 6 支圧板 7 定着具 8 鉄筋 9 型枠 10 梁 11 コンクリート 12 圧入装置 13 袋 14 モルタル 15 シート 16 水 17 地盤 DESCRIPTION OF SYMBOLS 1 Ground anchor 2 Anchor body 3 Tensile member 4 Pedestal 5 Reinforcing bar 6 Support plate 7 Fixing tool 8 Reinforcing bar 9 Formwork 10 Beam 11 Concrete 12 Press-in device 13 Bag 14 Mortar 15 Sheet 16 Water 17 Ground
Claims (4)
ドアンカーを設け、これらグラウンドアンカーの地上定
着部間にグラウンドアンカー間を連結するコンクリート
梁用型枠を設置すると共に、型枠と地盤の間に梁底面と
略同じ広さの袋を敷いてから、前記型枠にコンクリート
を打設して各グラウンドアンカーと一体化した梁を形成
し、その型枠を取外した後、前記袋内にモルタル等の硬
化する充填物を圧入して膨張させ、梁と地盤の間の空隙
を袋で隙間なく埋め、圧力をかけた状態で保持して充填
物を硬化させ、袋から下方の地盤にプレストレスが加わ
るようにした、法面施工方法。1. A plurality of ground anchors are provided on a slope at predetermined intervals, and a concrete beam formwork for connecting the ground anchors is installed between the ground anchoring portions of the ground anchors, and the formwork and the ground are fixed. After laying a bag of approximately the same size as the bottom of the beam in between, cast concrete into the form to form a beam integrated with each ground anchor, remove the form, and then in the bag The filling material such as mortar or the like that is to be hardened is press-fitted and expanded, and the gap between the beam and the ground is filled with a bag without any gap. Slope construction method to add stress.
ドアンカーを設け、これらグラウンドアンカーの地上定
着部間にグラウンドアンカー間を連結するコンクリート
梁用型枠を設置すると共に、型枠と地盤の間に梁底面と
略同じ広さの吸水して膨張し膨張後の形状を維持する性
質を備えたシートを敷いてから、前記型枠にコンクリー
トを打設して各グラウンドアンカーと一体化した梁を形
成し、その型枠を取外した後、前記シートを吸水させて
膨張させ、梁と地盤の間の空隙をシートで隙間なく埋
め、完全に膨張させて圧力が高まった状態に維持して、
シートから下方の地盤にプレストレスが加わるようにし
た、法面施工方法。2. A plurality of ground anchors are provided at predetermined intervals on a slope, and a concrete beam formwork for connecting the ground anchors is installed between the ground anchoring portions of the ground anchors. A sheet integrated with each ground anchor by laying a sheet having the property of absorbing water of approximately the same size as the bottom of the beam and expanding to maintain the expanded shape, and then placing concrete in the formwork After removing the formwork, the sheet is expanded by absorbing water, filling the gap between the beam and the ground without a gap, completely expanding and maintaining a state where the pressure is increased,
A slope construction method in which prestress is applied to the ground below the sheet.
鉄筋を配し、この鉄筋をグラウンドアンカーの地上定着
部と連結させた後、型枠にコンクリートを打設して各グ
ラウンドアンカーと一体化した梁を形成した、請求項1
に記載の法面施工方法。3. A reinforcing bar is arranged in a formwork between the ground anchors, and the reinforcing bar is connected to a ground anchoring portion of the ground anchor, and then concrete is poured into the formwork to be integrated with each ground anchor. 2. A shaped beam is formed.
Slope construction method described in.
鉄筋を配し、この鉄筋をグラウンドアンカーの地上定着
部と連結させた後、型枠にコンクリートを打設して各グ
ラウンドアンカーと一体化した梁を形成した、請求項2
に記載の法面施工方法。4. A reinforcing bar is arranged in a formwork between the ground anchors, and the reinforcing bar is connected to a ground anchoring portion of the ground anchor, and then concrete is cast into the formwork to be integrated with each ground anchor. 3. A shaped beam is formed.
Slope construction method described in.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18334795A JP2655137B2 (en) | 1995-06-26 | 1995-06-26 | Slope construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18334795A JP2655137B2 (en) | 1995-06-26 | 1995-06-26 | Slope construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0913383A JPH0913383A (en) | 1997-01-14 |
JP2655137B2 true JP2655137B2 (en) | 1997-09-17 |
Family
ID=16134149
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18334795A Expired - Fee Related JP2655137B2 (en) | 1995-06-26 | 1995-06-26 | Slope construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2655137B2 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100506489B1 (en) * | 2004-11-05 | 2005-08-08 | 주식회사 오륙개발 | A method of construction for stability and afforestation of a sloping surface |
JP4951254B2 (en) * | 2005-03-07 | 2012-06-13 | 株式会社大林組 | Leg frame structure and method for constructing the frame structure |
JP6340659B2 (en) * | 2013-11-27 | 2018-06-13 | 西日本高速道路エンジニアリング四国株式会社 | Anchor pull-out strength prediction method and anchor driving method |
JP6476095B2 (en) * | 2015-09-04 | 2019-02-27 | 公益財団法人鉄道総合技術研究所 | Reinforced soil integrated precast lattice frame method |
CN113944175A (en) * | 2021-10-28 | 2022-01-18 | 山东路达工程设计咨询有限公司 | Modular road bed side slope retaining structure |
-
1995
- 1995-06-26 JP JP18334795A patent/JP2655137B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH0913383A (en) | 1997-01-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US2948995A (en) | Connections between reinforced, precast concrete structures and method of making same | |
JP5373979B2 (en) | Construction Method of Steel Composite Girder Bridge {ConstructionMethod SteelCompositeGirderBridge} | |
US20220380996A1 (en) | Methods for constructing tensionless concrete pier foundations and foundations constructed thereby | |
KR101170922B1 (en) | The rahmen bridge construction technique for which tendon and the connection support stand was used | |
JPH07300820A (en) | Close contact type protective construction method against falling rock and rope/net anchor structure thereof | |
US5197245A (en) | Structural wall reinforcement apparatus and method | |
JP2655137B2 (en) | Slope construction method | |
JP6517122B2 (en) | Superstructure of T-girder bridge | |
JP6517123B2 (en) | T-girder installation method | |
CN112411579B (en) | Assembly type anchor rod frame beam structure containing EPS elastic cushion layer and suitable for expansive soil slope | |
CN206110369U (en) | Prevent connection structure of osmosis membrane and concrete | |
JPH1121816A (en) | Bridge structure | |
JP3450054B2 (en) | Installation method of floor slab on bridge girder and slab cradle | |
KR101170077B1 (en) | Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same | |
KR100403505B1 (en) | The Method of Reinforcing A Steel Girder Beam type Bridge and The Structure thereof | |
JP3055081B2 (en) | How to fix tension material | |
JPH01299963A (en) | Method of re-clamping or repairing and reinforcing or load-reducing deformed existing structure | |
JP3564682B2 (en) | Anchor method and pressing member used for it | |
KR20060110685A (en) | The method for construction of bridge | |
JPH0967823A (en) | Slope stabilizing method and anchor fixing pedestal used therefor | |
JP5785037B2 (en) | Bag-shaped formwork and installation method of solar cell panel using the same | |
JPH10317381A (en) | Structure for protecting face of slope by retaining wall and method for constructing the same | |
JP3275191B2 (en) | Mountain retaining method | |
JP3029908B2 (en) | Construction method of concrete structure | |
JPH0274753A (en) | Concrete mold for construction of mass concrete structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090530 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100530 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100530 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110530 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110530 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120530 Year of fee payment: 15 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130530 Year of fee payment: 16 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140530 Year of fee payment: 17 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |