JP2637245B2 - How to determine switchgear operating procedures for substations - Google Patents
How to determine switchgear operating procedures for substationsInfo
- Publication number
- JP2637245B2 JP2637245B2 JP1227965A JP22796589A JP2637245B2 JP 2637245 B2 JP2637245 B2 JP 2637245B2 JP 1227965 A JP1227965 A JP 1227965A JP 22796589 A JP22796589 A JP 22796589A JP 2637245 B2 JP2637245 B2 JP 2637245B2
- Authority
- JP
- Japan
- Prior art keywords
- procedure
- inference
- main circuit
- rules
- equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Feedback Control In General (AREA)
- Devices For Executing Special Programs (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Description
【発明の詳細な説明】 A.産業上の利用分野 本発明は、発変電所の開閉器操作手順決定方法に関す
る。The present invention relates to a method for determining a switch operation procedure of a substation.
B.発明の概要 本発明は、発変電所の開閉器の操作手順を決定する推
論機構における手順を手順表作成論理情報部よりのプロ
ダクションルールによる前向き推論手法で実現するもの
であって、前記ルールを、主回路ルールと付属設備ルー
ル及び確認事項ルールに分割し、推論を、主回路手順
を作成する推論,付属設備手順を作成する推論、確
認事項手順を作成する推論の順番で行うと共に、の推
論時は生成した手順を評価してによる手順を追加
し、の推論時はとで生成した両手順を評価して
による手順を追加するようにしたものである。B. Summary of the Invention The present invention realizes a procedure in an inference mechanism for determining an operation procedure of a switch of a substation by a forward inference method based on a production rule from a procedure table creation logical information section, and the rule Is divided into the main circuit rule, the auxiliary equipment rule, and the check item rule, and the inference is performed in the order of inference for creating the main circuit procedure, inference for creating the auxiliary equipment procedure, and inference for creating the check item procedure. At the time of inference, a procedure based on the generated procedure is evaluated, and at the time of inference, a procedure based on evaluating both the procedures generated at and is added.
C.従来の技術 発電所,変電所設備の保守点検作業時に変圧器,母
線,送電線などの設備を停止したり、停止状態から使用
したりする。その際、設備回りの開閉器を操作して行
う。この開閉器の操作は、設備の運用規則に従って、設
備ごとに予め決まった手順(シーケンス)で実行され
る。この手順には、主回路の操作の他に、各種安全確認
の手順,他部署への連絡事項手順などを含んでいる。C. Conventional technology During maintenance and inspection work on power plants and substation facilities, facilities such as transformers, buses, and transmission lines are stopped or used from a stopped state. At that time, the switch around the equipment is operated. The operation of the switch is performed according to a predetermined procedure (sequence) for each equipment in accordance with the operation rules of the equipment. This procedure includes, in addition to the operation of the main circuit, various safety confirmation procedures, procedures for contacting other departments, and the like.
D.発明が解決しようとする課題 このため、操作手順が極めて複雑である。また、操作
手順は設備ごとに作成するため、設備の新設,増設など
の変更の際に、新たな開閉器操作手順の作成が必要とな
る。D. Problems to be Solved by the Invention For this reason, the operation procedure is extremely complicated. In addition, since an operation procedure is created for each equipment, it is necessary to create a new switch operation procedure when a new equipment is added or expanded.
本発明は、従来の技術を有するこのような問題点に艦
みてなされたものであり、その目的とするところは、発
変電所の開閉器操作を、設備を停止あるいは使用するた
めの操作指令と予め登録されている情報とから開閉器操
作手順を自動的に作成することにより、発変電所の設備
の新設,増設時には、設備情報の追加変更だけで可能と
なるようにした発変電所の開閉器操作手順決定方法を提
供することにある。The present invention has been made in view of such a problem with the conventional technology, and an object of the present invention is to operate a switch of a power substation with an operation command for stopping or using equipment. Automatically create switch operation procedures from pre-registered information, so that when installing or expanding equipment at a substation, it is possible to open and close the substation only by adding or changing equipment information. It is an object of the present invention to provide a method for determining a device operating procedure.
E.課題を解決するための手段 上記目的を達成するために、本発明における発変電所
の開閉器操作手順決定方法は、開閉器の操作手順を決定
する推論機構における手順を手順表作成理論情報部より
のプロダクションルールによる前向き推論手法で実現す
るものであって、前記ルールを、主回路ルールと付属設
備のルール及び確認事項ルールに分割し、前記推論を、
主回路手順を作成する推論,付属設備手順を作成する推
論、確認事項手順を作成する推論の順番で行うと共に、
付属設備手順の推論時は主回路手順を作成する推論で生
成した手順を評価して付属設備手順を追加し、確認事項
を作成する推論時は主回路手順を作成する推論及び付属
設備手順を作成する推論で生成した両手順を評価して確
認事項手順を追加することを特徴とする。E. Means for Solving the Problems In order to achieve the above object, a method for determining a switch operation procedure of a substation according to the present invention includes a procedure in an inference mechanism for determining a switch operation procedure, a procedure table creation theoretical information. The method is realized by a forward inference method based on a production rule from a department, wherein the rule is divided into a main circuit rule, a rule of an attached facility, and a check item rule, and the inference is performed.
Inference is made in the order of inference for creating the main circuit procedure, inference for creating the auxiliary equipment procedure, and inference for creating the confirmation item procedure.
When inferring auxiliary equipment procedures, create the main circuit procedures.Evaluate the procedures generated in the inference and add the auxiliary equipment procedures. It is characterized in that both procedures generated by the inference to be performed are evaluated and a confirmation item procedure is added.
F.作用 プロダクションルールを、主回路ルール,付属設
備のルール,確認事項のルールの3つに分割している
ので、分かり易く、ルールが書き易い。F. Operation The production rules are divided into three rules: main circuit rules, accessory equipment rules, and confirmation items rules, so that the rules are easy to understand and easy to write.
主回路手順は、主回路ルールにより主回路手順を作成
する推論を行なって作成される。The main circuit procedure is created by performing inference for creating the main circuit procedure according to the main circuit rule.
次に、付属設備手順は上記作成した主回路手順を評価
して付属設備手順ルールにより付属設備手順を作成する
推論を行なって作成される。Next, the accessory facility procedure is created by evaluating the main circuit procedure created above and inferring to create the accessory facility procedure according to the accessory facility procedure rule.
また、確認事項手順は上記作成した主回路手順及び付
属設備手順を評価して確認事項手順を作成する推論を行
って作成する。In addition, the confirmation procedure is created by evaluating the main circuit procedure and the accessory equipment procedure created above and making an inference to create the confirmation procedure.
上記順番で各操作手順を作成するので、操作手順の作
成が容易となり、また、余分なルールを一度に処理する
必要がないので、推論処理スピードが向上する。Since the operation procedures are created in the above order, the creation of the operation procedures becomes easy, and there is no need to process an extra rule at a time, so that the inference processing speed is improved.
G.実施例 本発明の実施例について図面を参照して説明する。G. Embodiment An embodiment of the present invention will be described with reference to the drawings.
第1図において、知識ベース部1は、操作手順を作成
するための情報を格納するもので、発変電所の設備,開
閉器,設備の接続関係などのデータをフレーム構造で表
現する電力設備情報部1aと、手順を作成するための知識
をプロダクションルールで表現する手順表作成論理情報
部1bとよりなり、前向き推論機能とフレーム表現機能を
持つ汎用のエキスパートシステム構築ルーツを使って、
上記電力設備情報部1a及び手順作成論理情報部1bの知識
ベースを有するシステムを構築する。In FIG. 1, a knowledge base unit 1 stores information for creating an operation procedure, and power equipment information that expresses data such as equipment of a substation, switches, and connection relations of equipment in a frame structure. A part 1a and a procedure table creation logic information part 1b that expresses the knowledge for creating the procedure by the production rules, using a general purpose expert system construction roots having a forward reasoning function and a frame expression function,
A system having a knowledge base of the power equipment information section 1a and the procedure creation logic information section 1b is constructed.
推論機構2は操作指令により知識ベース部1よりの情
報を参照して前向き推論を行い、作業エリア3に操作手
順を出力する。The inference mechanism 2 performs forward inference by referring to information from the knowledge base unit 1 according to an operation command, and outputs an operation procedure to the work area 3.
手順表作成論理情報部1bの操作手順を作成するプロダ
クションルールは、第2図に示すように、主回路ルー
ル,付属設備ルール,確認事項のルールの3種類に
分類され、各ルール〜は関連ある複数の個別ルール
をまとめたルールセット11〜13で管理する。As shown in FIG. 2, the production rules for creating the operation procedure of the procedure table creation logic information section 1b are classified into three types: main circuit rules, accessory equipment rules, and check items rules, and each rule is related. A plurality of individual rules are managed by a set of rules 11 to 13.
の主回路ルールは、主回路の開閉器操作の手順を作
成するルールである。Is a rule for creating a procedure for operating the switch of the main circuit.
の付属設備ルールは、発変電所にある設備や系統を
制御する電圧調整装置などの装置,設備,系統を保護す
る保護ルールなどの装置などを操作する手順を作成する
ルールである。Is a rule for creating a procedure for operating equipment such as a voltage regulator for controlling equipment and a system in a substation and a device such as a protection rule for protecting the equipment and the system.
の確認事項手順ルールは、上記の操作にともな
い、電力回路の計測値を確認する手順を操作するルール
である。Is a rule for operating a procedure for confirming the measured value of the power circuit in accordance with the above operation.
なお、主回路ルール、付属の設備ルール、確認事項ル
ールは、それぞれ複数のルールセットで構成することも
できる。複数のルールセットを作成する場合、主回路、
付属設備、確認事項の推論を行う前に、操作指令の内容
から適用するルールセットを決定する処理を追加して行
う。In addition, the main circuit rule, the attached equipment rule, and the check item rule can be configured by a plurality of rule sets, respectively. When creating multiple rule sets, the main circuit,
Before inferring auxiliary equipment and items to be confirmed, processing to determine the rule set to be applied from the contents of the operation command is added.
推論機構2におけるルールによる操作手順の推論の順
番は、第3図で示すように、主回路手順を作成する推
論→付属設備手順を作成する推論→確認事項手順を
作成する推論の順番に実施する。この推論は各段階にお
いて、それぞれルールセット11〜13を抽出して、その中
のルール〜により行う。As shown in FIG. 3, the order of the inference of the operation procedure by the rule in the inference mechanism 2 is performed in the order of the inference for creating the main circuit procedure, the inference for creating the auxiliary equipment procedure, and the inference for creating the check item procedure. . This inference is performed at each stage by extracting the rule sets 11 to 13 and using the rules therein.
第3図について、各手順の作成を説明する。 The creation of each procedure will be described with reference to FIG.
主回路の手順イは、主回路ルールによっての主回
路手順を作成する推論を行って作成する。The procedure a of the main circuit is created by performing inference for creating the main circuit procedure according to the main circuit rule.
付属設備の手順ロは、上記作成した主回路の手順イを
評価対象として付属設備ルールによりの付属設備手
順を作成する推論を行ない、上記主回路手順イに追加す
る形で作成する。The procedure b for the accessory equipment is created by inferring the procedure a of the main circuit created above as an evaluation target and creating an accessory equipment procedure based on the accessory equipment rules, and adding the procedure to the main circuit procedure a.
確認事項の手順ハは、上記作成した主回路の手順イと
付属設備の手順ロを評価対象としての確認事項手順を
作成する推論を行ない、上記回路の手順イ,付属設備の
手順ロに追加する形で作成する。Procedure c for confirmation items is based on the procedure a for the main circuit created above and procedure b for accessory equipment, and makes inferences to create a procedure for confirmation items to be evaluated, and is added to procedure a for the above circuit and procedure b for accessory equipment. Create in shape.
上記推論に順番をつける理由は、の推論で作成され
る付属設備手順はの推論で作成した主回路手順イによ
り決まる手順であり、またの推論で作成される確認事
項手順ハはとの推論で求めた主回路手順イ及び付属
設備手順ロにより決まってくる手順であることによる。The reason for ordering the above inferences is that the auxiliary equipment procedure created in the inference above is the procedure determined by the main circuit procedure a created in the above inference, and the confirmation item procedure created in the inference above is also inferred. This is because the procedure is determined by the obtained main circuit procedure b and attached equipment procedure b.
設備を停止する場合は、まず主回路の開閉器を開くこ
とにより実際の設備停電作業が完了する。それに伴う付
属設備の操作や確認事項の手順は、主回路の操作内容に
より決まって来るものである。When stopping the equipment, first, the switch of the main circuit is opened to complete the actual power outage work. The procedures for the operation of the attached equipment and the items to be confirmed are determined by the operation of the main circuit.
操作手順は、作成する手順の順番に意味がある。の
推論で付属設備手順ロを作成するとき、の推論による
結果の手順イとの相対位置を示すことによる手順を挿入
する。そのためのルールが書きやすくなる。An operation procedure is significant in the order of procedures to be created. When creating the accessory equipment procedure b by the inference, insert the procedure by indicating the relative position to the procedure a of the result of the inference. The rules for that are easier to write.
第4図に「送電線の停止」の手順を作成する場合の具
体例を示す。なお、図中CBは遮断器、LSはラインスイッ
チである。FIG. 4 shows a specific example in the case where the procedure of “stopping the transmission line” is created. In the drawing, CB is a circuit breaker, and LS is a line switch.
H.発明の効果 本発明は、上述のとおり構成されているので、次に記
載する効果を奏する。H. Effects of the Invention Since the present invention is configured as described above, the following effects can be obtained.
(1)プロダクションルールを、主回路ルール,付属設
備ルール,確認事項ルールの用途に分けて作成するので
分り易い。(1) It is easy to understand because the production rules are created separately for the purposes of the main circuit rule, the accessory equipment rule, and the check item rule.
(2)主回路,付属設備,確認事項の順番に手順を作成
することにより、追加手順を既存手順の相対的位置指定
で出力でき、順番に意味がある操作手順を作成し易い。(2) By creating a procedure in the order of the main circuit, the auxiliary equipment, and the items to be confirmed, the additional procedure can be output by specifying the relative position of the existing procedure, and it is easy to create a meaningful operation procedure in the order.
(3)付属設備の手順は、主回路の手順内容により決っ
てくる。また、確認事項の手順は、主回路と付属設備の
手順内容によって決ってくる。従って、ルールのif部で
既存手順を参照するように記述することによりルールが
書き易くなる。(3) The procedure of the attached equipment is determined by the procedure of the main circuit. The procedure of the items to be confirmed depends on the procedure of the main circuit and the attached equipment. Therefore, the rules can be easily written by referring to the existing procedure in the if part of the rules.
(4)既存手順を参照できるので、推論が簡単である。(4) Since the existing procedure can be referred to, the inference is simple.
(5)主回路,付属設備,確認事項の順番に手順を作成
することにより、余分なルールを一度に処理する必要が
なくなり推論処理スピードが向上する。(5) By creating the procedure in the order of the main circuit, the accessory equipment, and the items to be confirmed, it is not necessary to process extra rules at once, and the speed of inference processing is improved.
第1図は本発明の実施例を示すブロック図、第2図は同
実施例における手順表作成論理情報部におけるルールセ
ットの分類説明図、第3図は同実施例における推論の順
番を説明するフローチャート、第4図は同実施例におけ
る推論処理のフローチャートを示す。 1……知識ベース部、1a……電力設備情報部、1b……手
順表作成論理情報部、2……推論機構、3……作業エリ
ア。FIG. 1 is a block diagram showing an embodiment of the present invention, FIG. 2 is a diagram for explaining the classification of rule sets in a procedure table creation logical information section in the embodiment, and FIG. 3 explains the order of inference in the embodiment. FIG. 4 shows a flowchart of the inference processing in the embodiment. 1 ... Knowledge base unit, 1a ... Power equipment information unit, 1b ... Procedure table creation logical information unit, 2 ... Inference mechanism, 3 ... Work area.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 田中 明 東京都品川区大崎2丁目1番17号 株式 会社明電舎内 (56)参考文献 特開 昭62−256128(JP,A) 特開 昭62−128333(JP,A) 電気学会電力技術研究会PE−87− 166(1987年)P.61−70 電気学会論文誌C電子・情報システム 部門誌107巻2号(昭62−2)P.121− 126 ──────────────────────────────────────────────────続 き Continuation of front page (72) Inventor Akira Tanaka 2-1-1-17 Osaki, Shinagawa-ku, Tokyo Inside Meidensha Co., Ltd. (56) References JP-A-62-256128 (JP, A) JP-A-62- 128333 (JP, A) IEEJ Power Technology Research Group PE-87-166 (1987) 61-70 Transactions of the Institute of Electrical Engineers of Japan, C / Electronic Information Systems, Section 107, No. 2 (Showa 62-2) 121− 126
Claims (1)
ける手順を手順表作成論理情報部よりのプロダクション
ルールによる前向き推論手法で実現するものであって、 前記操作手順を、主回路の手順,付属回路の手順,確認
事項の手順に分類すると共に、前記ルールを、手順の種
類に対応する主回路ルールと付属設備のルール及び確認
事項のルールに分割し、 前記推論を、それぞれ主回路ルール,付属設備のルー
ル,確認事項のルールにより主回路手順を作成する推
論,付属設備手順を作成する推論、確認事項手順を作成
する推論の順番で行うと共に、前記付属設備手順の推論
時は前記主回路手順を作成する推論で生成した主回路の
手順を評価対象として付属設備のルールにより付属設備
手順を作成する推論を行い、その手順を前記主回路の手
順に追加し、前記確認事項手順を作成する推論時は前記
主回路手順を作成する推論及び付属設備手順を作成する
推論で生成した主回路の手順及び付属設備の手順を評価
対象として確認事項をルールにより確認事項手順を作成
する推論を行い、その手順を前記主回路の手順及び付属
設備の手順に追加する、 ことを特徴とする発変電所の開閉器操作手順決定方法。A procedure in an inference mechanism for determining an operation procedure of a switch is realized by a forward inference method based on a production rule from a procedure table creation logical information section, wherein the operation procedure is a main circuit procedure. In addition to categorizing the procedures into the procedures for the accessory circuits and the procedures for confirming items, the rules are divided into the main circuit rules corresponding to the types of procedures, the rules for the auxiliary equipment, and the rules for confirming items. The inference for creating the main circuit procedure based on the rules of the accessory equipment and the rules of the check items, the inference for creating the accessory equipment procedure, and the inference for creating the check item procedure are performed in this order. Make inferences to create the auxiliary equipment procedure by using the rules of the auxiliary equipment with the procedure of the main circuit generated by the inference to create the procedure as the evaluation target, and describe the procedure to the main circuit. In addition to the procedures, when making inferences to create the procedure for confirmation, the items to be confirmed shall be evaluated with the procedure of the main circuit and the procedure of auxiliary equipment generated by the inference to create the main circuit procedure and the inference to create the auxiliary equipment procedure. A method for determining a switchgear operation procedure for a substation, comprising: inferring a procedure for confirming items according to a rule; and adding the procedure to the procedure of the main circuit and the procedure of ancillary equipment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1227965A JP2637245B2 (en) | 1989-09-02 | 1989-09-02 | How to determine switchgear operating procedures for substations |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1227965A JP2637245B2 (en) | 1989-09-02 | 1989-09-02 | How to determine switchgear operating procedures for substations |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0393427A JPH0393427A (en) | 1991-04-18 |
JP2637245B2 true JP2637245B2 (en) | 1997-08-06 |
Family
ID=16869034
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1227965A Expired - Fee Related JP2637245B2 (en) | 1989-09-02 | 1989-09-02 | How to determine switchgear operating procedures for substations |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2637245B2 (en) |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62128333A (en) * | 1985-11-30 | 1987-06-10 | Toshiba Corp | Inference system |
JPS62256128A (en) * | 1986-04-30 | 1987-11-07 | Toshiba Corp | Inference system |
-
1989
- 1989-09-02 JP JP1227965A patent/JP2637245B2/en not_active Expired - Fee Related
Non-Patent Citations (2)
Title |
---|
電気学会論文誌C電子・情報システム部門誌107巻2号(昭62−2)P.121−126 |
電気学会電力技術研究会PE−87−166(1987年)P.61−70 |
Also Published As
Publication number | Publication date |
---|---|
JPH0393427A (en) | 1991-04-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Lee et al. | A restoration aid expert system for distribution substations | |
Kimura et al. | Development of an expert system for estimating fault section in control center based on protective system simulation | |
Ghainani et al. | Fuzzy timing Petri net for fault diagnosis in power system | |
JP2637245B2 (en) | How to determine switchgear operating procedures for substations | |
Brand et al. | Systematic design of automation, protection, and control in substations | |
JPS59188317A (en) | Automatic discriminator for power system defect facility | |
JP2666990B2 (en) | Accident recovery system | |
JP3058462B2 (en) | Power supply route inference device for bus inspection | |
JP2647154B2 (en) | Power distribution system simulation test equipment | |
JP3274278B2 (en) | Centralized protection relay | |
JPH03277128A (en) | Deciding method for switch operating sequence in generating substation | |
English et al. | Automating relay coordination | |
JPH01274623A (en) | Loop operation judging system in power system operation | |
JP2727209B2 (en) | Power system operation system | |
JPH0819177A (en) | Preparation system of database for power-system supervisory control system | |
JP2767625B2 (en) | Fuzzy inference apparatus and operation method thereof | |
JP2644243B2 (en) | Shutdown adjustment calculation method for power system equipment | |
JPH0746762A (en) | Operating apparatus for power distribution system | |
CN116088461A (en) | Stability control device testing system and method, storage medium and electronic equipment | |
JPS589532A (en) | Power system control system | |
Ghoshal | Emulation of circuit-breaker control and operation in a typical power system scheme using programmable logic controller | |
JPH01160319A (en) | Electric power system fault judging device | |
JPH03278233A (en) | Expert system | |
JPS63117624A (en) | Electric source system controller | |
JPS58154340A (en) | Computer system for power system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |