JP2538679B2 - Job execution time prediction display method - Google Patents

Job execution time prediction display method

Info

Publication number
JP2538679B2
JP2538679B2 JP1215491A JP21549189A JP2538679B2 JP 2538679 B2 JP2538679 B2 JP 2538679B2 JP 1215491 A JP1215491 A JP 1215491A JP 21549189 A JP21549189 A JP 21549189A JP 2538679 B2 JP2538679 B2 JP 2538679B2
Authority
JP
Japan
Prior art keywords
job
job execution
information
execution
prediction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1215491A
Other languages
Japanese (ja)
Other versions
JPH0378033A (en
Inventor
洋一 石井
康雄 竹内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIPPON DENKI SOFUTOEA KK
NEC Corp
Original Assignee
NIPPON DENKI SOFUTOEA KK
Nippon Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIPPON DENKI SOFUTOEA KK, Nippon Electric Co Ltd filed Critical NIPPON DENKI SOFUTOEA KK
Priority to JP1215491A priority Critical patent/JP2538679B2/en
Publication of JPH0378033A publication Critical patent/JPH0378033A/en
Application granted granted Critical
Publication of JP2538679B2 publication Critical patent/JP2538679B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明はジョブ実行時間予測表示方式に関し、特に情
報処理システムにおけるジョブ実行時間予測表示方式に
関する。
The present invention relates to a job execution time prediction display method, and more particularly to a job execution time prediction display method in an information processing system.

〔従来の技術〕[Conventional technology]

従来、情報処理システムにおいて特定日に実行すべき
ジョブの選択,ジョブの実行順序の決定およびジョブの
実行時間の決定等が行われる場合には、ジョブ毎にその
実行要件の台帳が手書きで作成され、それらの台帳に基
づいて特定日に実行すべきジョブが選択され、ジョブの
実行順序,当該情報処理システムの外部から送付されて
くるジョブの実行に必要なデータの到着時間およびジョ
ブ相互の排他関係等が考慮されてジョブの実行予定表
(特定日に実行すべきものとして選択されたジョブの実
行順序や実行時間を示す予定表)が作成されていた(な
お、このジョブの実行予定表は細部まで明確なものでは
なかった)。
Conventionally, in an information processing system, when a job to be executed on a specific day is selected, a job execution order is determined, a job execution time is determined, etc., an execution requirement ledger is manually created for each job. , Jobs to be executed on a specific day are selected based on those ledgers, job execution order, arrival time of data necessary for execution of jobs sent from outside the information processing system, and mutual exclusion relationship between jobs A job execution schedule (a schedule that shows the execution order and execution time of jobs selected to be executed on a specific day) was created in consideration of the above (the execution schedule of this job is detailed. It wasn't clear).

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

上述した従来のジョブの実行予定表の作成では、人手
による作業が行われているので、当該情報処理システム
においてジョブの実行環境や実行条件が変更された場合
に、その都度関連するジョブの実行予定表中の情報を全
て更新しなければならず、その更新のために多くの労力
が必要になり、更新漏れに起因する支障が生じるおそれ
があるという欠点がある。
The above-described conventional job execution schedule creation requires manual work, so when a job execution environment or execution conditions are changed in the information processing system, the execution schedule of the related job is updated each time. All the information in the table has to be updated, a lot of labor is required for the update, and there is a drawback that trouble due to omission of update may occur.

また、何時にどのジョブが実行されるかということが
細部まで明確になっていないので、当該情報処理システ
ムの外部からの問合せ(ジョブの実行時間等に関する問
合せ)に対して正確な回答ができないという欠点があ
る。
In addition, since it is not clear in detail what job will be executed at what time, it will not be possible to give an accurate answer to inquiries from outside the information processing system (inquiries regarding job execution time, etc.). There are drawbacks.

本発明の目的は、上述の点に鑑み、特定日に実行され
るジョブの実行時間等の自動的な把握,記憶,編集およ
び出力(表示)等を行うことができ、特定日におけるジ
ョブの実行予定を事前に明確にできるジョブ実行時間予
測表示方式を提供することにある。
In view of the above points, an object of the present invention is to automatically grasp, store, edit and output (display) the execution time of a job executed on a specific day, and execute the job on the specific day. It is to provide a job execution time prediction display method that can clarify the schedule in advance.

〔課題を解決するための手段〕[Means for solving the problem]

本発明のジョブ実行時間予測表示方式は、カレンダ情
報およびマシン情報を含むジョブの実行環境ならびにジ
ョブ実行日情報,ジョブ実行時間情報,ジョブ実行順序
情報およびジョブ起動条件情報を含むジョブの実行条件
を指示する指示文を解析する指示文解析手段と、この指
示文解析手段による解析に基づきジョブ実行環境および
ジョブ実行条件に係る情報を有する基本情報をジョブ実
行環境実行条件記憶装置に格納する基本情報格納手段
と、この基本情報格納手段によりジョブ実行環境実行条
件記憶装置に格納された基本情報に基づきジョブの実行
日,実行時間および実行順序を予測するジョブ実行時間
予測手段と、このジョブ実行時間予測手段により予測さ
れた結果である予測情報を前記基本情報格納手段により
ジョブ実行環境実行条件記憶装置に格納された基本情報
とともに編集し出力する予測情報編集出力手段とを有す
る。
The job execution time prediction display method of the present invention indicates a job execution environment including calendar information and machine information, and job execution conditions including job execution date information, job execution time information, job execution sequence information, and job start condition information. And a basic information storage means for storing basic information having information on the job execution environment and job execution conditions in the job execution environment execution condition storage device based on the analysis by the directive statement analysis means. And a job execution time prediction means for predicting the execution date, execution time and execution order of the job based on the basic information stored in the job execution environment execution condition storage device by the basic information storage means, and the job execution time prediction means. The predicted information, which is a predicted result, is stored in the job execution environment execution section by the basic information storage means. Edited with basic information stored in the storage device and a prediction information editing output means for outputting.

〔作用〕[Action]

本発明のジョブ実行時間予測表示方式では、指示文解
析手段がカレンダ情報およびマシン情報を含むジョブの
実行環境ならびにジョブ実行日情報,ジョブ実行時間情
報,ジョブ実行順序情報およびジョブ起動条件情報を含
むジョブの実行条件を指示する指示文を解析し、基本情
報格納手段が指示文解析手段による解析に基づきジョブ
実行環境およびジョブ実行条件に係る情報を有する基本
情報をジョブ実行環境実行条件記憶装置に格納し、ジョ
ブ実行時間予測手段が基本情報格納手段によりジョブ実
行環境実行条件記憶装置に格納された基本情報に基づき
ジョブの実行日,実行時間および実行順序を予測し、予
測情報編集出力手段がジョブ実行時間予測手段により予
測された結果である予測情報を基本情報格納手段により
ジョブ実行環境実行条件記憶装置に格納された基本情報
とともに編集し出力する。
In the job execution time prediction display method of the present invention, the instruction statement analysis unit includes a job execution environment including calendar information and machine information, and a job including job execution date information, job execution time information, job execution sequence information, and job start condition information. The basic information storage means stores basic information having information on the job execution environment and job execution conditions in the job execution environment execution condition storage device based on the analysis by the directive statement analysis means. The job execution time prediction means predicts the execution date, execution time, and execution order of the job based on the basic information stored in the job execution environment execution condition storage device by the basic information storage means, and the predicted information edit output means calculates the job execution time. Execution of the job execution environment by the basic information storage means using the prediction information that is the result predicted by the prediction means Edit and output along with the basic information that has been stored in the matter storage device.

〔実施例〕〔Example〕

次に、本発明について図面を参照して説明する。 Next, the present invention will be described with reference to the drawings.

第1図は、本発明のジョブ実行時間予測表示方式の一
実施例の構成を示すブロック図である。本実施例のジョ
ブ実行時間予測表示方式は、与えられた指示文15の内容
を解析する指示文解析手段11と、基本情報(ジョブの実
行時間等を予測するための資料等となるジョブの実行環
境や実行条件に関する情報)をジョブ実行環境実行条件
記憶装置16に格納する基本情報格納手段12と、ジョブ実
行環境実行条件記憶装置16に格納された基本情報に基づ
いてジョブの実行日,実行時間および実行順序等(特定
日にどのジョブをどういった順序で何時に実行するかと
いうこと等)を予測し予測結果を予測情報として予測情
報記憶装置17に格納するジョブ実行時間予測手段13と、
予測情報記憶装置17に格納された予測情報等に基づいて
各種の帳票(図表を含む)を編集し出力(表示)する予
測情報編集出力手段14と、指示文15と、ジョブ実行環境
実行条件記憶装置16と、予測情報記憶装置17と、表示装
置18とを含んで構成されている。
FIG. 1 is a block diagram showing the configuration of an embodiment of the job execution time prediction display method of the present invention. The job execution time prediction display method according to the present exemplary embodiment includes a command statement analysis unit 11 that analyzes the content of a given command statement 15, and basic information (execution of a job that serves as data for predicting a job execution time and the like). (Basic information storage means 12 for storing information about environment and execution conditions) in the job execution environment execution condition storage device 16, and the execution date and execution time of the job based on the basic information stored in the job execution environment execution condition storage device 16. And a job execution time prediction unit 13 that predicts an execution order and the like (which job is executed in what order and at what time), and stores the prediction result as prediction information in the prediction information storage device 17,
Prediction information edit / output means 14 for editing and outputting (displaying) various forms (including charts) based on the prediction information stored in the prediction information storage device 17, instruction sentence 15, and job execution environment execution condition storage It is configured to include a device 16, a prediction information storage device 17, and a display device 18.

第2図は、ジョブの実行環境および実行条件を指示す
る指示文15の一例を示す図である。
FIG. 2 is a diagram showing an example of an instruction sentence 15 for instructing a job execution environment and execution conditions.

第3図は、ジョブ実行環境実行条件記憶装置16上のジ
ョブ実行環境に係るレコードの一例を示す図である。
FIG. 3 is a diagram showing an example of a record relating to the job execution environment on the job execution environment execution condition storage device 16.

第4図は、ジョブ実行環境実行条件記憶装置16上のジ
ョブ実行条件に係るレコードの一例を示す図である。
FIG. 4 is a diagram showing an example of records relating to job execution conditions in the job execution environment execution condition storage device 16.

第5図は、ジョブの実行時間等の予測を指示する指示
文15の一例を示す図である。
FIG. 5 is a diagram showing an example of an instruction sentence 15 for instructing prediction of job execution time and the like.

第6図は、予測情報記憶装置17上の予測情報のレコー
ドの一例を示す図である。
FIG. 6 is a diagram showing an example of a record of prediction information on the prediction information storage device 17.

第7図は、表示装置18上に出力される帳票(図表)の
一例を示す図である。
FIG. 7 is a diagram showing an example of a form (chart) output on the display device 18.

次に、このように構成された本実施例のジョブ実行時
間予測表示方式の動作について説明する。
Next, the operation of the job execution time prediction display method of this embodiment having the above configuration will be described.

本実施例のジョブ実行時間予測表示方式が適用される
情報処理システムにおいてジョブの実行環境および実行
条件が決定(または変更)した場合には、第2図に示す
ような指示文15が使用されて指示文解析手段11に対して
登録(または更新)の指示が行われる。
When the job execution environment and the execution conditions are determined (or changed) in the information processing system to which the job execution time prediction display method of this embodiment is applied, the instruction statement 15 as shown in FIG. 2 is used. The instruction statement analysis unit 11 is instructed to register (or update).

この指示文15の指示内容としては、少なくとも以下に
示すような項目がある。
The instruction content of the instruction sentence 15 includes at least the following items.

(1) ジョブ実行環境に関する項目 カレンダ情報 休日の曜日の指定,不定期な非稼動日の指定および不
定期な稼動日の指定等 マシン情報 稼動開始時刻と稼動終了時刻とによるマシン稼動時間
の指定および多重度の指定等 (2) ジョブ実行条件に関する項目 ジョブ実行日情報 実行日の指定,非実行日の指定,実行曜日の指定,非
実行曜日の指定および周期の指定等 ジョブ実行時間情報 開始時刻(実行可能時刻)の指定,終了時刻(終了限
度時刻)の指定およびエラップス(実行時間)の指定等 ジョブ実行順序情報 先行ジョブ名の指定および後行ジョブ名の指定等 ジョブ起動条件情報 同時実行不可ジョブ名(排他ジョブ名)の指定および
外部からのデータ到着時刻の指定等 このような指示文15が与えられた指示文解析手段11
は、指示文15の指示内容を解析し、解析結果を基本情報
格納手段12に渡す。
(1) Items related to job execution environment Calendar information Specification of days of the week for holidays, specification of irregular non-working days, specification of irregular working days, etc. Machine information (2) Items related to job execution conditions Job execution date information Job execution date information, non-execution date specification, execution day specification, non-execution day specification, and cycle specification Job execution time information Start time ( Executable time, end time (end limit time), elaps (execution time), etc. Job execution sequence information Preceding job name, succeeding job name, etc. Job start condition information Name (exclusive job name) designation, data arrival time designation from the outside, etc.
Analyzes the instruction content of the instruction sentence 15 and passes the analysis result to the basic information storage means 12.

基本情報格納手段12は、指示文解析手段11による解析
に基づいて、ジョブ実行環境実行条件記憶装置16上に上
述の指示文15により指示された内容に基づく基本情報
(ジョブ実行環境およびジョブ実行条件に係る情報を有
する基本情報)を格納する。
Based on the analysis by the directive statement analysis unit 11, the basic information storage unit 12 stores basic information (job execution environment and job execution conditions) in the job execution environment execution condition storage device 16 based on the contents instructed by the above-mentioned directive statement 15. (Basic information having information relating to) is stored.

基本情報は、第3図および第4図に示すような形式に
よりジョブ実行環境実行条件記憶装置16上で管理され
(ジョブ実行環境実行条件記憶装置16上のジョブ実行環
境に係るレコードはカレンダID(IDentification),
年,休日の曜日,不定期な非稼動日,マシン稼動時間お
よび多重度等を有しており、ジョブ実行環境実行条件記
憶装置16上のジョブ実行条件に係るレコードはジョブ
名,同期,実行可能時刻,終了限度時刻,実行時間,先
行ジョブ名,後行ジョブ名,排他ジョブ名および外部か
らのデータ到着時刻等を有している)、以後必要な時点
で予測情報編集出力手段14によって編集され出力され
る。
The basic information is managed in the job execution environment execution condition storage device 16 in the format as shown in FIGS. 3 and 4 (the record related to the job execution environment in the job execution environment execution condition storage device 16 is the calendar ID ( IDentification),
It has year, holiday days, irregular non-working days, machine operating time, multiplicity, etc., and records related to job execution conditions on the job execution environment execution condition storage device 16 can be job name, synchronization, and execution. The time, end limit time, execution time, preceding job name, succeeding job name, exclusive job name, data arrival time from the outside, etc.) are edited by the prediction information edit output means 14 at a necessary time thereafter. Is output.

利用者が当日以後のジョブの実行日や実行時間等を予
測する場合には、第5図に示すようなジョブの実行時間
等の予測を指示する指示文15により予測したい月または
月日(第5図に示す指示文15では月(予測年月))が指
定された指示(予測指示)が指示文解析手段11に対して
行われる。
When the user predicts the execution date and execution time of the job after the current day, the month or month and day (the first day) to be predicted by the instruction statement 15 for instructing the prediction of the job execution time as shown in FIG. In the instruction sentence 15 shown in FIG. 5, the instruction (prediction instruction) in which the month (prediction date) is designated is given to the instruction sentence analysis means 11.

このような指示文15が与えられた指示文解析手段11
は、指示文15の指示内容を解析し、予測指示であるので
ジョブ実行時間予測手段13に予測対象となる月または月
日を指示する。
The instruction sentence analysis means 11 to which such an instruction sentence 15 is given
Analyzes the instruction content of the instruction sentence 15 and, since it is a prediction instruction, instructs the job execution time prediction means 13 of the month or the month and day to be predicted.

ジョブ実行時間予測手段13は、すでにジョブ実行環境
実行条件記憶装置16上に作成されている基本情報に基づ
いて、以下に示すような手順でジョブの実行時間等の予
測を行う。
The job execution time prediction means 13 predicts the job execution time and the like according to the following procedure based on the basic information already created in the job execution environment execution condition storage device 16.

(1) ジョブ実行環境に係るレコード中のカレンダ情
報(ジョブの実行環境および実行条件を指示する指示文
15における情報名はジョブ実行環境実行条件記憶装置16
上の基本情報中の該当する情報においても使用する)に
基づいて予測対象となる月のカレンダ(稼動日および休
日(非稼動日)の確定したカレンダ)を作成する。
(1) Calendar information in the record related to the job execution environment (instruction statement that indicates the job execution environment and execution conditions
The information name in 15 is the job execution environment execution condition storage device 16
Create a calendar for the month to be predicted (calendar with confirmed working days and holidays (non-working days)) based on the applicable information in the basic information above.

(2) ジョブ実行条件に係るレコード中のジョブ実行
日情報に基づいて、各ジョブの実行の可否を決定する。
(2) Whether or not each job can be executed is determined based on the job execution date information in the record related to the job execution condition.

(3) ジョブ実行条件に係るレコード中のジョブ実行
時間情報およびジョブ実行順序情報に基づいて、各ジョ
ブの実行順序および優先度を決定する。
(3) The execution order and priority of each job are determined based on the job execution time information and the job execution order information in the record related to the job execution condition.

(4) ジョブ実行環境に係るレコード中のマシン情報
およびジョブ実行条件に係るレコード中のジョブ起動条
件情報に基づいて、優先度の高いジョブからの順序で各
ジョブのスケジュール時間を割り付ける。このときに、
指定時間内に各ジョブを割り付けることができない場合
には、その旨を示すエラーメッセージを出力する。
(4) Based on the machine information in the record related to the job execution environment and the job start condition information in the record related to the job execution condition, the schedule time of each job is assigned in the order from the job with the highest priority. At this time,
If each job cannot be assigned within the specified time, an error message indicating that fact is output.

以上のような手順によるジョブ実行時間予測手段13の
予測処理により、予測対象日にどのようなジョブがどの
ような順序で実行されるか、また何時に実行されるかと
いうことが明確にされる。
By the prediction processing of the job execution time prediction means 13 according to the procedure as described above, it is clarified what kind of jobs will be executed in what order in what day, and at what time. .

ジョブ実行時間予測手段13は、上述のような予測の結
果である予測情報を第6図に示すような形式で予測情報
記憶装置17上に格納する(予測情報のレコードは、予測
対象日,曜日,稼動/非稼動フラグ,マシン稼動時間,
多重度,ジョブ名,スケジュール時間,実行時間および
外部からのデータ到着時刻等を有している)。
The job execution time prediction means 13 stores the prediction information, which is the result of the above-described prediction, in the prediction information storage device 17 in the format as shown in FIG. 6 (the prediction information record is the prediction target date, the day of the week). , Active / inactive flag, machine operating time,
It has multiplicity, job name, schedule time, execution time, data arrival time from the outside, etc.).

基本情報格納手段12およびジョブ実行時間予測手段13
からそれぞれの処理(基本情報格納手段12によるジョブ
実行環境実行条件記憶装置16への基本情報の格納および
ジョブ実行時間予測手段13による予測情報記憶装置17へ
の予測情報の格納)が終了している旨が通知された予測
情報編集出力手段14は、ジョブ実行時間予測手段13によ
り予測情報記憶装置17上に格納されている予測情報およ
び基本情報格納手段12によりジョブ実行環境実行条件記
憶装置16上に格納されている基本情報に基づいて、各種
の帳票を表示装置18上に編集して出力する。
Basic information storage means 12 and job execution time prediction means 13
Each processing (the basic information storage means 12 stores the basic information in the job execution environment execution condition storage device 16 and the job execution time prediction means 13 stores the prediction information in the prediction information storage device 17) is completed. The prediction information edit output means 14 notified to that effect is stored on the job execution environment execution condition storage device 16 by the prediction information and basic information storage means 12 stored by the job execution time prediction means 13 on the prediction information storage device 17. Various forms are edited and output on the display device 18 based on the stored basic information.

第7図に示す帳票(図表)は、各種の帳表の一例であ
り、実行時間予測チャート(「JOB1」,「JOB2」,「JO
B3」,「LJOB1」,「LJOB2」および「LJOB3」はジョブ
名を表しており、矢線で示される範囲はスケジュール時
間を表している)を示している(予測情報編集出力手段
14が実行時間予測チャート以外にも各種の帳票を出力で
きることはいうまでもない)。
The form (chart) shown in FIG. 7 is an example of various forms, and the execution time prediction chart (“JOB1”, “JOB2”, “JO
"B3", "LJOB1", "LJOB2" and "LJOB3" represent job names, and the range indicated by the arrow represents the schedule time) (prediction information edit output means)
Needless to say, 14 can output various forms other than the execution time prediction chart).

〔発明の効果〕〔The invention's effect〕

以上説明したように本発明は、指示文解析手段,基本
情報格納手段,ジョブ実行時間予測手段および予測情報
編集出力手段を設けることにより、特定日に実行される
ジョブの実行時間等の自動的な把握,記憶,編集および
出力等を行うことができ、特定日におけるジョブの実行
予定を事前に明確にできるという効果があり、さらに以
下に示すような効果がある。
As described above, according to the present invention, by providing the instruction sentence analysis means, the basic information storage means, the job execution time prediction means, and the prediction information edit output means, it is possible to automatically execute the execution time of a job executed on a specific day. It is possible to grasp, store, edit, output, and the like, and it is possible to clarify the job execution schedule on a specific day in advance, and further, the following effects are obtained.

(1) 人手による煩雑な台帳の更新が不要となる。(1) It is not necessary to manually update the ledger.

(2) 実行すべきジョブが事前に明確になるために、
ジョブが必要とする媒体等の準備が可能となる。
(2) To clarify the job to be executed in advance,
It becomes possible to prepare the media and the like required by the job.

(3) ジョブの実行順序が事前に明確になるために、
ジョブの実行時の起動ミスが減少する。
(3) In order to clarify the job execution order in advance,
Fewer startup mistakes during job execution.

(4) ジョブの実行時間が事前に明確になるために、
ジョブの実行結果の配布予定を明確にできる。
(4) In order to clarify the job execution time in advance,
The distribution schedule of job execution results can be clarified.

(5) ジョブの実行予定が事前に明確になるために、
ジョブの起動漏れがなくなる。
(5) In order to clarify the job execution schedule in advance,
Job start omission is eliminated.

(6) 指定された時間内にジョブが実行できない場合
に、その旨が事前に明確になる。
(6) If the job cannot be executed within the designated time, the fact becomes clear in advance.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明の一実施例の構成を示すブロック図、 第2図はジョブの実行環境および実行条件を指示する第
1図中の指示文の一例を示す図、 第3図は第1図中のジョブ実行環境実行条件記憶装置上
のジョブ実行環境に係るレコードの一例を示す図、 第4図は第1図中のジョブ実行環境実行条件記憶装置上
のジョブ実行条件に係るレコードの一例を示す図、 第5図はジョブの実行時間等の予測を指示する第1図中
の指示文の一例を示す図、 第6図は第1図中の予測情報記憶装置上の予測情報のレ
コードの一例を示す図、 第7図は第1図中の表示装置上に出力される帳票の一例
を示す図である。 図において、 11……指示文解析手段、 12……基本情報格納手段、 13……ジョブ実行時間予測手段、 14……予測情報編集出力手段、 15……指示文、 16……ジョブ実行環境実行条件記憶装置、 17……予測情報記憶装置、 18……表示装置である。
FIG. 1 is a block diagram showing a configuration of an embodiment of the present invention, FIG. 2 is a diagram showing an example of an instruction statement in FIG. 1 for instructing a job execution environment and execution conditions, and FIG. FIG. 4 is a diagram showing an example of a record relating to a job execution environment on the job execution environment execution condition storage device in the figure, and FIG. 4 is an example of a record relating to job execution condition on the job execution environment execution condition storage device shown in FIG. FIG. 5 is a diagram showing an example of an instruction statement in FIG. 1 for instructing prediction of job execution time, etc., and FIG. 6 is a record of prediction information on the prediction information storage device in FIG. FIG. 7 is a diagram showing an example of a form output on the display device shown in FIG. 1. In the figure, 11 ... instruction statement analysis means, 12 ... basic information storage means, 13 ... job execution time prediction means, 14 ... prediction information edit output means, 15 ... instruction text, 16 ... job execution environment execution Condition storage device, 17 ... Prediction information storage device, 18 ... Display device.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】カレンダ情報およびマシン情報を含むジョ
ブの実行環境ならびにジョブ実行日情報,ジョブ実行時
間情報,ジョブ実行順序情報およびジョブ起動条件情報
を含むジョブの実行条件を指示する指示文を解析する指
示文解析手段と、 この指示文解析手段による解析に基づきジョブ実行環境
およびジョブ実行条件に係る情報を有する基本情報をジ
ョブ実行環境実行条件記憶装置に格納する基本情報格納
手段と、 この基本情報格納手段によりジョブ実行環境実行条件記
憶装置に格納された基本情報に基づきジョブの実行日,
実行時間および実行順序を予測するジョブ実行時間予測
手段と、 このジョブ実行時間予測手段により予測された結果であ
る予測情報を前記基本情報格納手段によりジョブ実行環
境実行条件記憶装置に格納された基本情報とともに編集
し出力する予測情報編集出力手段と を有することを特徴とするジョブ実行時間予測表示方
式。
1. A job execution environment including calendar information and machine information, and an instruction statement for instructing a job execution condition including job execution date information, job execution time information, job execution sequence information, and job start condition information is analyzed. And a basic information storage unit for storing basic information having information on the job execution environment and job execution conditions in the job execution environment execution condition storage device based on the analysis by the directive statement analysis unit. The execution date of the job based on the basic information stored in the job execution environment execution condition storage device by means
Job execution time predicting means for predicting execution time and execution order, and basic information stored in the job execution environment execution condition storage device by the basic information storage means, the prediction information being the result predicted by the job execution time predicting means. And a predictive information edit and output means for editing and outputting together with the predictive display method for job execution time.
JP1215491A 1989-08-22 1989-08-22 Job execution time prediction display method Expired - Lifetime JP2538679B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1215491A JP2538679B2 (en) 1989-08-22 1989-08-22 Job execution time prediction display method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1215491A JP2538679B2 (en) 1989-08-22 1989-08-22 Job execution time prediction display method

Publications (2)

Publication Number Publication Date
JPH0378033A JPH0378033A (en) 1991-04-03
JP2538679B2 true JP2538679B2 (en) 1996-09-25

Family

ID=16673265

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1215491A Expired - Lifetime JP2538679B2 (en) 1989-08-22 1989-08-22 Job execution time prediction display method

Country Status (1)

Country Link
JP (1) JP2538679B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2823991B2 (en) * 1992-03-31 1998-11-11 出光興産株式会社 Computer operation automation equipment
JP2519005B2 (en) * 1992-11-02 1996-07-31 日本電気株式会社 Job schedule simulation device
JP2823520B2 (en) * 1993-12-17 1998-11-11 テキサス インスツルメンツ インコーポレイテツド Real-time application task scheduling and processing system
JPH0844574A (en) * 1994-07-29 1996-02-16 Nec Corp Job operation management device
WO2006129285A1 (en) * 2005-06-03 2006-12-07 Nxp B.V. Data processing system and method for scheduling the use of at least one exclusive resource

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6027949A (en) * 1983-07-27 1985-02-13 Hitachi Ltd Automatic job class scheduling system
JPS6396401A (en) * 1986-10-09 1988-04-27 株式会社日立製作所 Power plant starter

Also Published As

Publication number Publication date
JPH0378033A (en) 1991-04-03

Similar Documents

Publication Publication Date Title
US5535388A (en) Apparatus for dynamically collecting and editing management information during a software development process
JP2538679B2 (en) Job execution time prediction display method
US6671855B1 (en) Outline information generating apparatus and computer-readable recording medium recording thereon outline information generating program
JPH11120248A (en) System and method for scheduling production
JP2003108735A (en) Project management system, program and recording medium
JPH0567069A (en) Schedule preparation system
JP3741450B2 (en) Item component element execution method and execution apparatus
JPH11306254A (en) Progress management system for data processing job
JP3541651B2 (en) Job startup date setting device
JPH0683646A (en) Job schedule control system
JPH064166A (en) Expiration date setting device for job
JPH07296056A (en) Schedule managing method and template and schedule for it
JPS6366632A (en) Business form production system
JP2000151883A (en) Information processing unit, its system and its storage medium
JPH02216509A (en) Automatic operation control system for computer system
JP2695803B2 (en) Work information management device
JPH11306253A (en) Progress management system for data processing job
JP2000148274A (en) Routine job implementation assistance system
JP2699572B2 (en) Data definition information quoting method in data definition
JPH02272668A (en) Transaction execution time sequence diagram edition system
JP2002312018A (en) Process control system
JPH0573279A (en) Job execution control system
JPH05108665A (en) Working controller for production equipment
JPH02212925A (en) Used paper prediction output device
JPH08305749A (en) Work planning device

Legal Events

Date Code Title Description
S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070708

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080708

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090708

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100708

Year of fee payment: 14

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100708

Year of fee payment: 14