JP2003108735A - Project management system, program and recording medium - Google Patents

Project management system, program and recording medium

Info

Publication number
JP2003108735A
JP2003108735A JP2001302505A JP2001302505A JP2003108735A JP 2003108735 A JP2003108735 A JP 2003108735A JP 2001302505 A JP2001302505 A JP 2001302505A JP 2001302505 A JP2001302505 A JP 2001302505A JP 2003108735 A JP2003108735 A JP 2003108735A
Authority
JP
Japan
Prior art keywords
project
document
management system
created
project management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001302505A
Other languages
Japanese (ja)
Inventor
Katsumasa Yokogawa
勝正 横川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ricoh Co Ltd
Original Assignee
Ricoh Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ricoh Co Ltd filed Critical Ricoh Co Ltd
Priority to JP2001302505A priority Critical patent/JP2003108735A/en
Publication of JP2003108735A publication Critical patent/JP2003108735A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a project management system for connecting a document prepared by a project with the progress management of the project. SOLUTION: In the project management system provided with a document management data base for managing results prepared at the time of performing the project and a project information management data base for managing the progress state of the project, the empty substance of a result to be prepared in each process of the project is registered in the document management data base, link information to the registered empty substance is registered in the project information management data base in relation with the process, a document group to be prepared in respective processes is standardized, and a person in charge of the project and a reader can grasp which document is prepared during the execution of the project and how is the progress state.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、多人数の要員によ
り構成されたプロジェクトを管理するプロジェクト管理
システム、プログラムおよび記録媒体に関し、詳細に
は、プロジェクトの工程および作成文書の標準化を支援
するとともに、作業の進捗状況を視覚的に表示し、適時
に適切な管理を行うための支援情報を提供するプロジェ
クト管理システム、プロジェクト管理システムの機能を
実行するためのプログラムおよびそのプログラムを記録
したコンピュータ読み取り可能な記録媒体に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a project management system, a program and a recording medium for managing a project composed of a large number of personnel, and more specifically, it supports the standardization of a project process and a created document. A project management system that visually displays the progress of work and provides support information for timely and appropriate management, a program for executing the functions of the project management system, and a computer-readable program recording the program. Recording medium

【0002】[0002]

【従来の技術】一般に、比較的大規模なプロジェクトで
は、まず実行すべき作業内容(一般には、文書が成果物
である)と手順(成果物間の関係)が定義された方法論
が作成され、この方法論にしたがって、複数のプロジェ
クト要員によって共同作業で行なわれる。複数の要員
は、プロジェクトを管理する管理者(プロジェクトマネ
ージャ等)によって、それぞれが実行すべき作業内容が
割り当てられ、また作業の進行等が調整される。
2. Description of the Related Art Generally, in a relatively large-scale project, first, a methodology is created in which work contents (generally documents are deliverables) and procedures (relationships between deliverables) are defined. According to this methodology, it will be carried out jointly by multiple project personnel. A plurality of personnel are assigned work contents to be executed by an administrator (project manager or the like) who manages the project, and the progress of the work is adjusted.

【0003】従来、このようなプロジェクトの管理にお
いては、プロジェクトのスケジュールの管理と、そのプ
ロジェクトの進行に伴い発生する文書を管理する文書の
管理とは別個に管理されているため、ある時点における
スケジュールに関連した文書を検索することが煩雑にな
っている。
Conventionally, in the management of such a project, the management of the project schedule and the management of the document that manages the documents generated as the project progresses are managed separately. Searching for documents related to is complicated.

【0004】特開2000−315228号公報のスケ
ジュール管理システムでは、個人や組織におけるスケジ
ュール管理と文書データとを関連付けて管理することに
より、それぞれ別個に管理することがなくなり関連文書
の検索などが容易に行えるようになっている。
In the schedule management system disclosed in Japanese Unexamined Patent Publication No. 2000-315228, the schedule management in an individual or organization and the document data are managed in association with each other, so that they are not separately managed and the related documents can be easily searched. It can be done.

【0005】また、特開平10−177568号公報の
文書管理システムおよび文書管理用記憶媒体では、プロ
ジェクトのスケジュール管理とプロジェクト内で作成さ
れた文書の管理を効率的に実施し、プロジェクトの進捗
状況、文書の時系列的関係、文書の連鎖関係を明瞭に把
握することができる。
In the document management system and the document management storage medium disclosed in Japanese Patent Laid-Open No. 10-177568, the project schedule management and the documents created in the project are efficiently managed, and the progress status of the project is It is possible to clearly understand the time-series relationship of documents and the chain relationship of documents.

【0006】また、特開平11−282918号公報の
文書管理方法及び装置及びコンピュータ読み取り可能な
記録媒体は、プロジェクトに関する作業者が文書の作成
状況とその内容を互いに参照しながら能率よく文書作成
する。また、プロジェクトの工程と文書とを関連付け
て、文書の作成進行状況を表示している。
Further, the document management method and apparatus and the computer-readable recording medium disclosed in Japanese Patent Laid-Open No. 11-282181 allow a worker associated with a project to efficiently create a document while referring to the document creation status and its contents. Further, the process of the project and the document are associated with each other, and the progress of document creation is displayed.

【0007】[0007]

【発明が解決しようとする課題】複数の会社、事業所、
個人にまたがるプロジェクトを遂行した場合、以下の点
で問題が発生する。 ・プロジェクトの管理する場合、文化・風土の違いによ
って管理の仕方が同一でないため、他社や他事業所およ
び個人の間でのお互いの進捗の管理や進捗状況を把握す
るのが困難である。 ・タスク/ジョブに必要な文書を参照したい場合や配布
したい場合には、現状では、郵便やメール等に頼ってい
る。
[Problems to be Solved by the Invention] Multiple companies, business establishments,
When performing a project that spans individuals, the following problems occur. -When managing projects, it is difficult to manage the progress and grasp the progress of other companies, other business establishments, and individuals because the management methods are not the same due to differences in culture and culture. -Currently, we rely on mail and email to refer to and distribute documents required for tasks / jobs.

【0008】上述の2番目の問題は、インターネット上
のサーバに参照または配布する文書を保管し、文書の保
管、取り出しをするソフトを提供するサービスプロバイ
ダを利用すれば解決する。しかしながら、通常、文書
は、何らかの目的をもった作業による成果物の場合が多
く、プロジェクト/タスク等でまとまった単位で管理さ
れている。また、第3者とプロジェクトを遂行する場
合、閲覧可能な文書と閲覧できない文書とがあるので、
これを解決するためには文書ごとにアクセス権を設定し
ているのが現状である。しかし、不特定多数の第3者と
仕事をする場合には、このような文書ごとにアクセス権
を設定するのは煩雑である。例えば、プロジェクトの進
行状況によっては要員が交代するときがあり、この交代
ごとに該当文書のアクセス権を再設定するのは困難なこ
とである。
The above-mentioned second problem can be solved by using a service provider that stores the document to be referred to or distributed to the server on the Internet and provides the software for storing and retrieving the document. However, in general, a document is often a product of work having some purpose, and is managed in a unit of a project / task or the like. Also, when carrying out a project with a third party, there are documents that can be viewed and documents that cannot be viewed.
In order to solve this, the current situation is to set access rights for each document. However, when working with an unspecified large number of third parties, setting an access right for each such document is complicated. For example, depending on the progress of the project, the personnel may change, and it is difficult to reset the access right of the relevant document for each change.

【0009】このような問題点に対して、上述の特開2
000−315228号公報は、要員や組織に関するス
ケジュールとそれに関連する文書を管理するだけであ
り、多数の要員や多数のタスクからなるプロジェクトに
おける作業工程や作成すべき文書群を標準化したり、そ
れらの文書の機密管理に適したものとはいえない。
With respect to such a problem, the above-mentioned Japanese Patent Laid-Open No. 2
The 000-315228 publication only manages schedules related to personnel and organizations and documents related thereto, standardizes work processes and a group of documents to be created in a project consisting of many personnel and many tasks, and It is not suitable for document confidentiality control.

【0010】また、特開平10−177568号公報
は、作成された文書が審査・承認済みになってからアロ
ーダイアグラムに文書リンクを貼り付けるが、それまで
はその文書の存在や内容を担当者以外の要員から参照す
ることはできない。
Further, in Japanese Patent Laid-Open No. 10-177568, a document link is pasted on an arrow diagram after the created document has been examined and approved, but until then, the existence and contents of the document are not included in the person in charge. Cannot be referred to by personnel.

【0011】また、特開平11−282918号公報
は、プロジェクト進行に伴い、完成前の文書を作成状況
に応じて閲覧させることが目的であり、今までの作成中
または作成完了した文書については分かるが、プロジェ
クトの遂行に伴ってどのような文書が作成される予定で
あるかまでは把握することができない。
Further, Japanese Patent Application Laid-Open No. 11-2821818 aims at making a document before completion be viewed according to the preparation status as the project progresses, and it is possible to know the documents which have been prepared or completed. However, it is not possible to grasp what kind of documents will be created as the project is carried out.

【0012】本発明は、上述した実情を鑑みてなされた
ものであって、次のようなことを目的とするプロジェク
ト管理システム、そのプロジェクト管理システムの機能
を実行するためのプログラムおよびそのプログラムを記
録したコンピュータ読み取り可能な記録媒体を提供す
る。 (1)プロジェクトで作成される文書をプロジェクトの
進捗管理と連動させるとともに、他の要員からの閲覧管
理を容易に行える。 (2)プロジェクトでは、作業工程およびその工程で作
成すべき文書には何があるかを標準化する。また、文書
を作成するときにどの文書を参照して作成するのかが分
かるようにする。 (3)計画に対しての遅延とその進行状況とを視覚化し
て提供することによって進捗管理が容易になる。
The present invention has been made in view of the above-mentioned circumstances, and records a project management system, a program for executing the function of the project management system, and the program for the purpose of the following. A computer-readable recording medium is provided. (1) Documents created in the project can be linked to the progress management of the project and easily viewed and managed by other personnel. (2) In the project, standardize what work process and what documents should be created in that process. Also, when creating a document, identify which document is referred to when creating the document. (3) The progress management becomes easy by visualizing and providing the delay to the plan and its progress.

【0013】[0013]

【課題を解決するための手段】上記の課題を解決するた
めに、本発明の請求項1のプロジェクト管理システム
は、プロジェクトの遂行時に作成される成果物の進捗状
況を管理するプロジェクト管理システムにおいて、プロ
ジェクトの計画時に、プロジェクトの各工程で作成すべ
き成果物の空の実体を初めに登録しておくようにしたこ
とを特徴とする。
In order to solve the above problems, the project management system according to claim 1 of the present invention is a project management system for managing the progress of a product created when a project is executed, The feature is that the empty entity of the artifact to be created in each process of the project is registered first when the project is planned.

【0014】また、本発明の請求項2のプロジェクト管
理システムは、プロジェクトの遂行時に作成される成果
物を管理する文書管理データベースと、プロジェクトの
進捗状況を管理するプロジェクト情報管理データベース
を有するプロジェクト管理システムにおいて、プロジェ
クトの計画時に、プロジェクトの各工程で作成すべき成
果物の空の実体を前記文書管理データベースへ登録し、
この登録した空の実体へのリンク情報を前記プロジェク
ト情報管理データベースへ前記工程と関連付けて登録す
ることを特徴とする。また、本発明の請求項3は、請求
項2に記載のプロジェクト管理システムにおいて、プロ
ジェクトの種類ごとに少なくとも工程およびその工程で
作成すべき成果物をテンプレートとして登録したプロジ
ェクトテンプレートデータベースを有し、このテンプレ
ートを選択することによってプロジェクトの各工程で作
成すべき成果物を登録するようにして、プロジェクトで
作成する成果物を標準化することを特徴とする。また、
本発明の請求項4は、請求項2または3に記載のプロジ
ェクト管理システムにおいて、前記工程で作成される前
記成果物とその成果物を作成する際に参照する参照文書
とをこの工程に関連付けて前記プロジェクト情報管理デ
ータベースへ登録することを特徴とする。また、本発明
の請求項5は、請求項4に記載のプロジェクト管理シス
テムにおいて、前記参照文書は、既存または前工程で作
成される成果物であることを特徴とする。また、本発明
の請求項6は、請求項4または5に記載のプロジェクト
管理システムにおいて、前記プロジェクト情報管理デー
タベースに登録されたリンク情報から、実体である前記
文書管理データベース中の前記成果物または前記参照文
書を参照できるようにしたことを特徴とする。
Further, the project management system according to claim 2 of the present invention is a project management system having a document management database for managing deliverables created when a project is executed and a project information management database for managing the progress of the project. In, at the time of project planning, register an empty entity of the deliverable to be created in each process of the project in the document management database,
It is characterized in that the link information to the registered empty entity is registered in the project information management database in association with the process. According to claim 3 of the present invention, in the project management system according to claim 2, there is a project template database in which at least a process for each type of project and a product to be created in the process are registered as a template. It is characterized by registering the deliverables to be created in each process of the project by selecting a template and standardizing the deliverables created in the project. Also,
According to a fourth aspect of the present invention, in the project management system according to the second or third aspect, the artifact created in the step and a reference document referred to when creating the artifact are associated with the step. It is characterized in that it is registered in the project information management database. A fifth aspect of the present invention is characterized in that, in the project management system according to the fourth aspect, the reference document is an existing product or a product created in a previous step. According to claim 6 of the present invention, in the project management system according to claim 4 or 5, from the link information registered in the project information management database, the deliverable or the product in the document management database which is an entity or the The feature is that the reference document can be referred to.

【0015】また、本発明の請求項7は、請求項2乃至
6のいずれか1に記載のプロジェクト管理システムにお
いて、前記プロジェクト情報管理データベースへプロジ
ェクトの各要員とその役割およびこの役割に応じた文書
へのアクセス権限範囲を登録し、前記要員がこの文書へ
アクセスする際には、その要員の役割に基づいて前記プ
ロジェクト情報管理データベースを調べ、許容された権
限内でその文書の実体へのアクセスを許すようにしたこ
とを特徴とする。
According to a seventh aspect of the present invention, in the project management system according to any one of the second to sixth aspects, the project information management database is provided with the respective personnel of the project, their roles, and documents according to these roles. Access authority to the document, when the personnel access this document, the project information management database is examined based on the personnel's role, and access to the substance of the document is permitted within the permitted authority. It is characterized by having been forgiven.

【0016】また、本発明の請求項8は、請求項2乃至
7のいずれか1に記載のプロジェクト管理システムにお
いて、プロジェクトで作成される前記成果物の進捗状況
を表示する進捗状況表示手段を有し、その進捗状況を表
示する際、前記工程の要員とこの要員が担当する成果物
についての進捗状況を表示して、成果物の作成計画を管
理できるようにしたことを特徴とする。また、本発明の
請求項9は、請求項8に記載のプロジェクト管理システ
ムにおいて、前記進捗状況表示手段は、前記成果物の要
員と作業期間を表示して、その成果物を誰が作成するの
かを管理できるようにしたことを特徴とする。また、本
発明の請求項10は、請求項8または9に記載のプロジ
ェクト管理システムにおいて、前記進捗状況表示手段
は、前記工程ごとに作業期間を表示し、その作業期間内
で作成する成果物の進捗状況を示すアイコンを貼り付け
ることによって、成果物の作成状況が分かるようにした
ことを特徴とする。また、本発明の請求項11は、請求
項10に記載のプロジェクト管理システムにおいて、前
記アイコンは、作成状況および/または作成計画との差
異に応じて識別して表示することを特徴とする。また、
本発明の請求項12は、請求項10または11に記載の
プロジェクト管理システムにおいて、前記アイコンは、
このアイコンが表す成果物または参照文書の実体である
前記文書管理データベース中の文書へリンクしており、
このアイコンから文書の実体を参照できるようにしたこ
とを特徴とする。また、本発明の請求項13のプログラ
ムは、請求項1乃至12のいずれか1に記載のプロジェ
クト管理システムの機能を実行するためのプログラムで
ある。また、本発明の請求項14の記録媒体は、請求項
13に記載のプログラムを記録したコンピュータ読み取
り可能な記録媒体である。
[0016] According to claim 8 of the present invention, in the project management system according to any one of claims 2 to 7, there is provided a progress status display means for displaying a progress status of the deliverable created in the project. However, when displaying the progress status, it is possible to display the progress status of the staff of the process and the deliverables in charge of the staff so that the creation plan of the deliverable can be managed. A ninth aspect of the present invention is the project management system according to the eighth aspect, wherein the progress status display means displays the personnel and the work period of the deliverable to determine who creates the deliverable. The feature is that it can be managed. According to claim 10 of the present invention, in the project management system according to claim 8 or 9, the progress status display means displays a work period for each of the steps, and a product created within the work period. The feature is that the creation status of the deliverable can be understood by pasting an icon indicating the progress status. According to a tenth aspect of the present invention, in the project management system according to the tenth aspect, the icon is displayed by being identified according to a difference between a creation status and / or a creation plan. Also,
Claim 12 of the present invention is the project management system according to claim 10 or 11, wherein the icon is
Linked to the document in the document management database that is the entity of the artifact or reference document represented by this icon,
The feature is that the entity of the document can be referred from this icon. A program according to claim 13 of the present invention is a program for executing the function of the project management system according to any one of claims 1 to 12. A recording medium according to claim 14 of the present invention is a computer-readable recording medium in which the program according to claim 13 is recorded.

【0017】以上のように構成することによって、プロ
ジェクトで作成される文書をプロジェクトの進捗管理と
連動させるので、プロジェクトにおける文書作成の管理
および他の要員からの閲覧管理を容易に行える。また、
プロジェクトを計画したときにそのプロジェクトで作成
すべき文書の計画も作成するので、プロジェクトの計画
段階から文書作成の計画、その進捗状況が一覧できるの
で、プロジェクト管理が容易に行える。その結果、プロ
ジェクトで作成されるべき文書群を標準化することがで
きる。また、文書を作成するのにどの文書を参照すれば
良いかが関連付けられ、その参照文書も簡単に見ること
ができるので、要員の文書作成が確実に且つ容易にな
る。また、計画に対しての遅延とその進行状況とを文書
リンクアイコンの形や色で視覚化して提供するので、プ
ロジェクトの進捗管理が容易になる。
With the above configuration, the document created in the project is linked with the progress management of the project, so that the management of document creation in the project and the browsing management from other personnel can be easily performed. Also,
When a project is planned, a plan of documents to be created in the project is also created, so that the plan of document creation and its progress can be viewed from the project planning stage, so that the project management can be easily performed. As a result, the documents to be created in the project can be standardized. Further, since which document should be referred to when creating a document is associated and the referenced document can be easily viewed, it is possible for the personnel to create the document reliably and easily. Further, the delay in the plan and the progress thereof are visualized and provided in the form and color of the document link icon, so that the progress management of the project becomes easy.

【0018】[0018]

【発明の実施の形態】以下、図面を参照しながら本発明
のプロジェクト管理システム(以下、本システムと呼
ぶ)を説明する。次に、本システムの実施の形態を説明
するときに使用する用語を定義しておく。 ・プロジェクト: 期間と結果が規定されていて、それ
を満たすことを目標とした行動/行為である。 ・タスク: プロジェクトを構成する論理的な作業の単
位を表す。タスクは、分割して小さなタスクにすること
ができる。 ・ジョブ: タスクをさらに分割したものであり、実質
的な作業の最小単位を表す。ジョブは、分割することが
できない。また、1タスクが1ジョブを表すこともあ
る。タスクおよびジョブを工程と呼ぶこともある。 ・プロジェクトリーダ(PL): プロジェクト全体の
タスク/ジョブを管理する管理者である。 ・タスクリーダ: プロジェクトリーダによって割り当
てられたタスク/ジョブを管理する管理者である。 ・(作業)要員: タスク/ジョブを担当する作業者で
ある。 ・参照文書: タスク/ジョブの作業上必要な標準、手
順書、設計文書等であり、前工程のタスク/ジョブから
のアウトプット文書や類似プロジェクトの成果物として
の文書が含まれる。 ・アウトプット文書(成果物): タスク/ジョブの作
業結果として作成される文書であり、プロジェクトの成
果物でもある。上記参照文書を参照してアウトプット文
書を作成することもある。または、類似プロジェクトの
成果物を流用して作成することもある。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A project management system of the present invention (hereinafter referred to as the present system) will be described below with reference to the drawings. Next, terms used in describing the embodiment of the present system will be defined. -Project: An action / action that has a defined period and results and that aims to meet it. -Task: Represents a logical unit of work that constitutes a project. Tasks can be split into smaller tasks. -Job: It is a subdivision of a task and represents the minimum unit of practical work. Jobs cannot be split. Further, one task may represent one job. Tasks and jobs are sometimes called processes. -Project leader (PL): An administrator who manages tasks / jobs for the entire project. -Task leader: An administrator who manages tasks / jobs assigned by the project leader. -(Work) personnel: Workers in charge of tasks / jobs. -Reference documents: Standards, procedure manuals, design documents, etc. necessary for task / job work, including output documents from tasks / jobs in the previous process and documents as deliverables of similar projects. -Output document (deliverable): A document created as a result of the work of a task / job, and also a deliverable of a project. Output documents may be created by referring to the above referenced documents. Alternatively, the products of similar projects may be diverted and created.

【0019】(1)本システムの概略説明 本発明は、プロジェクト管理システムからプロジェクト
で作成される文書(もしくは代用特性とした文書)を保
管・管理する文書管理システムにインタフェース(画
面)を提供することで、文書に時間軸を持たせることを
コンセプトにしている。そのために、プロジェクト開始
時点等で、そのプロジェクトで作成するアウトプット文
書を計画し、書誌データは有するが内容は空のアウトプ
ット文書を文書管理システムに作成する。プロジェクト
管理システムでは、文書管理システムに作成されたアウ
トプット文書への文書リンクと、そのアウトプット文書
を作成するための参照情報やプロジェクト管理情報など
を管理する。
(1) Outline of this system The present invention provides an interface (screen) to a document management system that stores and manages documents (or documents with substitute characteristics) created in a project from the project management system. So, the concept is to have a time axis in the document. Therefore, at the start of the project, an output document created in the project is planned, and an output document that has bibliographic data but empty content is created in the document management system. The project management system manages document links to output documents created in the document management system and reference information and project management information for creating the output documents.

【0020】図1は、本システムの概略を説明するため
の全体構成図である。図1において、本システムは、プ
ロジェクト管理装置100と文書管理装置200とから
なるプロジェクト管理センタ700と、プロジェクトの
管理を行うプロジェクトリーダや実際の作業を行う作業
要員のいる事業所300、サテライトオフィス400や
開発委託会社500の所有するコンピュータとをインタ
ーネットやイントラネット等からなるネットワーク60
0で接続している。これらの事業所300、サテライト
オフィス400や開発委託会社500は、プロジェクト
の規模や要員のいる場所等によって1つ以上存在し、プ
ロジェクト管理センタ700と接続されており、このプ
ロジェクト管理センタ700によってプロジェクトで開
発される文書や進捗状況の管理が行われる。プロジェク
ト管理装置100は、プロジェクトの進捗状況および各
タスク/ジョブで作成される文書とスケジュールとを関
連付けて管理し、文書管理装置200はプロジェクトで
作成される文書および参照する参照文書等を管理する。
FIG. 1 is an overall configuration diagram for explaining the outline of this system. In FIG. 1, the present system includes a project management center 700 including a project management apparatus 100 and a document management apparatus 200, a business office 300 having a project leader who manages a project and a worker who actually performs a work, and a satellite office 400. And a computer owned by the development contracting company 500 and a network 60 including the Internet or an intranet
0 is connected. One or more of these business offices 300, satellite offices 400, and development contracting companies 500 exist depending on the scale of the project, the location of personnel, etc., and are connected to the project management center 700. Documents to be developed and progress are managed. The project management apparatus 100 manages the progress status of the project and the document created by each task / job in association with each other, and the document management apparatus 200 manages the document created by the project and the reference document to be referenced.

【0021】また、プロジェクト管理装置100や文書
管理装置200は、プロジェクト管理センタ700の1
箇所だけに設置するのではなく、事業所300、サテラ
イトオフィス400や開発委託会社500のいずれかま
たはそれぞれに存在してもよい。この場合には、文書管
理装置200で管理される文書は、事業所300、サテ
ライトオフィス400や開発委託会社500で作成され
るものだけであり、参照は、そのアクセス権限のある要
員であれば、他からも参照できるようにする。プロジェ
クト管理装置100も同様に設置されるが、そのプロジ
ェクト全体を統合して進捗管理するプロジェクト管理装
置100も備えなければならない。
The project management apparatus 100 and the document management apparatus 200 are the same as those of the project management center 700.
Instead of being installed only at the location, it may be present at any one of the business office 300, the satellite office 400, and the development contracting company 500, or each of them. In this case, the documents managed by the document management apparatus 200 are only those created by the business office 300, the satellite office 400, and the development contracting company 500, and the reference is made only by the personnel having the access authority. Make it accessible to others. The project management apparatus 100 is also installed in the same manner, but the project management apparatus 100 that integrates the entire project and manages the progress must also be provided.

【0022】また、プロジェクト管理センタ700をA
SP(アプリケーション・サービス・プロバイダ)に設
置した場合には、各装置(100、200)は1箇所に
存在するだけでよいので、プロジェクトを立ち上げるま
でおよびその進捗に際しての煩雑さが減少する。
In addition, the project management center 700
When installed in an SP (application service provider), each device (100, 200) need only be present in one place, and therefore the complexity of starting a project and in its progress is reduced.

【0023】以下、プロジェクト管理センタ700を1
箇所に設置し、事業所300、サテライトオフィス40
0や開発委託会社500からそれぞれ端末によってその
ASPにアクセスするものとして本システムを説明す
る。
In the following, the project management center 700 is set to 1
Installed in various locations, business office 300, satellite office 40
This system will be described assuming that the ASPs are accessed from 0 or the development contracting company 500 by terminals.

【0024】図2は、本システムのプロジェクト管理装
置100の機能構成を説明するブロック図である。図2
において、プロジェクト管理装置100は、少なくとも
プロジェクト定義手段110、プロジェクト情報管理D
B(データベース)120、プロジェクトテンプレート
DB(データベース)130、プロジェクト進捗登録手
段140、プロジェクト進捗状況表示手段150とから
なっている。また、文書管理装置200は文書管理DB
(データベース)210を備えて、このプロジェクト管
理装置100で管理される文書群の内容(実体)を登録
管理する。この文書管理DB210は、プロジェクト情
報管理DB120のタスク/ジョブで参照される参照文
書やアウトプット文書をリンクできるのであれば、デー
タベース管理システム、ファイルサーバまたはWeb上
に格納された情報のいずれであってもよい。
FIG. 2 is a block diagram for explaining the functional configuration of the project management apparatus 100 of this system. Figure 2
In the project management apparatus 100, at least the project definition means 110 and the project information management D
B (database) 120, project template DB (database) 130, project progress registration means 140, and project progress status display means 150. Further, the document management apparatus 200 is a document management DB
A (database) 210 is provided to register and manage the content (entity) of the document group managed by the project management apparatus 100. The document management DB 210 is either a database management system, a file server, or information stored on the Web as long as it can link a reference document or an output document referred to by a task / job of the project information management DB 120. Good.

【0025】(2)プロジェクトの定義(プロジェクト
定義手段110) 先ず、図3で示されるような入力画面で、プロジェクト
の一般的事項(プロジェクト名、プロジェクトリーダ
名、プロジェクトの開始日、終了日、使用テンプレート
等)を入力することによって、プロジェクトを定義す
る。通常、ソフトウェア等の商品開発では、企画、設
計、プログラミング、テスト等の決まった工程があり、
各工程には、参照文書として、参照すべき標準、手順
書、前工程の設計文書がある。各工程で作成されるアウ
トプット文書には、次工程に必要な手順書、設計文書が
発生する。例えば、プロジェクト経験の浅いリーダは、
ソフトウェアの開発の工程、各工程に必要な文書や文書
間の関係等に熟知していない部分がある。こうした問題
は、プロジェクトの遅れを発生させる要因となる。
(2) Project definition (project definition means 110) First, in the input screen as shown in FIG. 3, general items of the project (project name, project leader name, project start date, end date, use) Define the project by entering the template etc.). Usually, in product development such as software, there are fixed processes such as planning, designing, programming, testing,
As a reference document for each process, there are a standard to be referred, a procedure manual, and a design document of a previous process. In the output document created in each process, the procedure manual and design document necessary for the next process are generated. For example, a leader with little experience in projects
Some parts are not familiar with the software development process, the documents required for each process, and the relationships between documents. These problems cause delays in the project.

【0026】このため、例えば、ソフトウェアの開発プ
ロジェクトであれば、「パッケージソフトウェア開
発」、「個別受注ソフトウェア開発」等に対して、タス
ク(大きな工程)、タスクごとに必要な参照文書、アウ
トプット文書、参照する手順書・標準書等が定義されて
いるテンプレートを利用して、経験差によるプロジェク
トの遅延等のリスクを最小限にすることができる。これ
らのテンプレートには、ソフトウェア開発だけでなく建
築や機械の開発、販売戦略等のような種々のプロジェク
トの開発工程とその開発手順やその結果作成される文書
群を定義するためのテンプレートが幾つか用意されてい
る。また、このテンプレートはプロジェクトに応じて新
規にもまたカスタマイズすることもできる。
Therefore, for example, in the case of a software development project, a task (a large process), a reference document required for each task, an output document for “package software development”, “individual order software development”, etc. , By using the template that defines the procedures and standard documents to be referenced, it is possible to minimize the risk of project delay due to experience differences. These templates include several templates for defining not only software development but also the development process of various projects such as architecture and machine development, sales strategy, etc., the development procedure, and the resulting document group. It is prepared. Also, this template can be new or customized for your project.

【0027】プロジェクトの定義時点で、プロジェクト
テンプレートDB130から今回実施するプロジェクト
に類似したテンプレートを選ぶことによって、そのテン
プレートに定義されているタスクおよびそのスケジュー
ルをプロジェクト情報管理DB120に作成される。こ
こで作成される文書は、書誌事項データ(例えば、文書
名、作成者名、部署名、作成日時、完了日時、進行状
況、修正日、配布先、文書ファイルリスト等)だけで実
体が空の文書を文書管理DB210へ登録する。ここで
文書ファイルリストは、文書の内容を格納したファイル
(テキスト、図形、イメージ等を格納している)を示す
ものであり、当初は空とする。また、ここに登録された
文書へのリンク情報を各タスク/ジョブと関連付けてプ
ロジェクト情報管理DB120へ登録する。さらに、展
開された各タスクで作成される文書やその文書を作成す
るときに参照する参照文書は、その実体が登録されてい
る文書管理装置200の文書管理DB210へのリンク
情報を各タスク/ジョブと関連付けてプロジェクト情報
管理DB120へ登録する。
At the time of defining a project, by selecting a template similar to the project to be executed this time from the project template DB 130, the task defined in the template and its schedule are created in the project information management DB 120. The document created here contains only bibliographic data (for example, document name, creator name, department name, creation date, completion date, progress status, modification date, distribution destination, document file list, etc.) The document is registered in the document management DB 210. Here, the document file list indicates a file in which the contents of a document are stored (text, graphics, images, etc. are stored), and is initially empty. Also, the link information to the document registered here is associated with each task / job and registered in the project information management DB 120. Further, the document created by each expanded task and the reference document referred to when creating the document include link information to the document management DB 210 of the document management apparatus 200 in which the entity is registered, for each task / job. It is registered in the project information management DB 120 in association with.

【0028】次に、プロジェクトマネージャは、予め要
員ごとに使用可能なリソース率を定義しておき、それを
使ってこのプロジェクトに参加する要員を定義し(図3
参照)、先にテンプレートで展開された大日程を参照し
て、マイル・ストーン等を勘案してプロジェクト全体の
計画を作成する。この大日程にしたがって、タスクリー
ダがタスクへ展開し、そのタスクに割り当てられた作業
要員がそのタスクをジョブに展開する(図3参照)。
Next, the project manager defines the resource ratio that can be used for each employee in advance, and uses it to define the personnel who participate in this project (see FIG. 3).
Reference), refer to the large schedule developed in the template earlier, and create a plan for the entire project in consideration of milestones, etc. According to this large schedule, the task leader deploys the task, and the worker assigned to the task deploys the task into the job (see FIG. 3).

【0029】先に選択したテンプレートによって、プロ
ジェクトに必要なデフォルトの文書(参照文書およびア
ウトプット文書)が作成されるが、タスク/ジョブの展
開に応じて修正、追加して、必要なアウトプット文書と
それに関連した参照文書とを定義する。それらの文書が
類似プロジェクトからの流用や前工程でのアウトプット
文書のときには、その文書の実体へのリンク情報をプロ
ジェクト情報管理DB120の該当するタスクまたはジ
ョブへ関連付けて登録する。また、新たにアウトプット
文書として作成する場合には、文書管理DB210へ書
誌事項データとその空の実体とを登録し、その登録した
文書へのリンクをプロジェクト情報管理DB120の該
当するタスクまたはジョブへ関連付けて登録する。最
初、テンプレートによって作成されたアウトプット文書
は、図4に示された左のカラムのリストだけであるが、
タスク/ジョブに必要なものを設定し、そのスケジュー
ル(文書作成開始日、終了日)を設定し終わると図4の
ように表示される。
The template selected above creates the default documents (reference document and output document) required for the project, but the necessary output documents can be modified and added depending on the task / job development. And the associated reference documents. When those documents are diverted from similar projects or output documents in the previous process, the link information to the entity of the document is registered in association with the corresponding task or job in the project information management DB 120. In addition, when creating a new output document, the bibliographical matter data and its empty entity are registered in the document management DB 210, and a link to the registered document is linked to the corresponding task or job in the project information management DB 120. Register in association. Initially, the only output document created by the template is the list in the left column shown in Figure 4,
When necessary tasks / jobs are set and the schedule (document creation start date, end date) is set, the screen is displayed as shown in FIG.

【0030】これらの登録されたアウトプット文書は、
図5のようにタスク/ジョブごとにアウトプット文書へ
のリンクを示すアイコンのリストとして表示される。ま
た、登録された参照文書は、図6のようにタスク/ジョ
ブごとに参照文書へのリンクを示すアイコンのリストと
して表示される。これらの図5および図6とを一緒に
し、タスク/ジョブごとの参照文書とアウトプット文書
の関係を図7のように表示することもできる。これらの
参照文書およびアウトプット文書のカラムにある文書ア
イコンをマウスで左クリックすると、文書管理DB21
0へアクセスし、その内容を表示することができる。ま
た、例えば、文書アイコンをマウスで右クリックしてそ
の文書の書誌事項(文書のプロパティ)を図8のように
表示するようにしてもよい。
These registered output documents are
As shown in FIG. 5, it is displayed as a list of icons showing links to output documents for each task / job. Further, the registered reference documents are displayed as a list of icons indicating links to the reference documents for each task / job as shown in FIG. It is also possible to combine these FIGS. 5 and 6 and display the relationship between the reference document and the output document for each task / job as shown in FIG. 7. Left-click the document icon in the column of these reference documents and output documents with the mouse to display the document management DB 21
0 can be accessed and its contents can be displayed. Alternatively, for example, the document icon may be right-clicked with the mouse to display the bibliographic items (document properties) of the document as shown in FIG.

【0031】以上のようにしてタスクリーダや作業要員
が作成したタスク/ジョブをプロジェクトリーダは調整
し、一部修正して決定した全体計画を公開する。したが
って、プロジェクトを計画したときにそのプロジェクト
で作成すべき文書の計画も作成するので、プロジェクト
の計画段階から文書作成の計画、その進捗状況が一覧で
きるようになり、プロジェクト管理が容易に行える。そ
の結果、プロジェクトで作成されるべき文書群を標準化
することができる。
The project leader adjusts the tasks / jobs created by the task leaders and the workers as described above, partially corrects them, and publishes the decided overall plan. Therefore, when a project is planned, a document plan to be created in the project is also created, so that the document creation plan and its progress can be viewed from the project planning stage, and the project management can be easily performed. As a result, the documents to be created in the project can be standardized.

【0032】上述したジョブ/タスクで作成または参照
される文書へのアクセス権限範囲(参照のみ、参照およ
び書き込み可、複写可等)をプロジェクトの各要員の役
割に与えられる権限としてプロジェクト情報管理DB1
20へ格納する。各要員が文書管理DB210に登録さ
れた文書へアクセスする際には、その要員の役割に基づ
いてプロジェクト情報管理DB120を調べ、許容され
た権限内でその文書へアクセスを許すようにする。この
アクセス権が文書内容を管理する文書管理DB210の
各文書に設定されているのではなくプロジェクト管理情
報として設定されているので、作業要員が交代したとき
にも文書管理DB210のアクセス権を変更する必要が
ない。
The project information management DB 1 is used as the authority given to the role of each staff member of the project with the access authority range (reference only, reference and writable, copyable, etc.) to the document created or referred to by the above-mentioned job / task.
Store in 20. When each staff member accesses a document registered in the document management DB 210, the project information management DB 120 is checked based on the role of the staff member, and the access to the document is permitted within the permitted authority. Since this access right is not set for each document of the document management DB 210 that manages the document contents but is set as project management information, the access right of the document management DB 210 is changed even when a worker is replaced. No need.

【0033】(3)プロジェクト進捗(プロジェクト進
捗登録手段140) 作業要員は、後述する担当分のプロジェクト進捗状況を
表示させて、進捗を確認しながら、参照文書の内容を確
認してアウトプット文書を作成する。このときアウトプ
ット文書は、文書管理DB210の参照文書またはプロ
ジェクトテンプレートDB130から該当する手順書/
関連資料の雛形または類似プロジェクトから既存文書を
流用して作成し、文書管理DB210へ登録する。
(3) Project Progress (Project Progress Registering Means 140) The work staff displays the project progress status of the person in charge to be described later, confirms the progress, confirms the contents of the reference document, and outputs the output document. create. At this time, the output document is the reference document of the document management DB 210 or the corresponding procedure manual / from the project template DB 130.
An existing document is diverted from a template of a related material or a similar project, and is created and registered in the document management DB 210.

【0034】作業要員は、担当分の進捗と文書の実績を
プロジェクト情報DB120へ登録する。また、計画外
に作成した文書も、その都度、対応するジョブのアウト
プット文書として登録する。
The work staff registers the progress of the charge and the document achievement in the project information DB 120. Also, a document created unplanned is registered as an output document of the corresponding job each time.

【0035】(4)プロジェクト進捗状況の表示(プロ
ジェクト進捗状況表示手段150) 通常、プロジェクトを作るとき、大規模なシステムの場
合は、システムごと(本発明では、大きなタスクにあた
る)にリーダが設定され、そのタスクの作成・管理が一
任される。しかしながら、システムと要員は、必ずしも
対応関係にあるわけではなく、一人の要員が、複数のシ
ステムにかかわるケースもでてくる。こうした場合、従
来システムではシステム単位でタスクが分割されるた
め、人を中心に捉えたタスク/ジョブを確認しづらい点
があった。
(4) Display of project progress status (project progress status display unit 150) Normally, when a project is created, in the case of a large-scale system, a leader is set for each system (corresponding to a large task in the present invention). , The task creation and management is left to the discretion. However, the system and personnel are not necessarily in a correspondence relationship, and in some cases, one personnel may be involved in multiple systems. In such a case, in the conventional system, tasks are divided on a system-by-system basis, which makes it difficult to confirm tasks / jobs centered on people.

【0036】これを解消するために本発明では、例え
ば、図9に示したようにプロジェクトのタスクごとの進
捗状況と作成すべきアウトプット文書を表示する。図9
において、左のカラムから順に、タスク名、タスクの開
始日時と終了日時、このタスクの作業要員(担当者)名
とその責任区名、アウトプット文書を作成するために参
照する参照文書のアイコンリスト、タスクの進捗度
(%)、このタスクで作成するアウトプット文書のアイ
コンリストである。また、図10に示したようにアウト
プット文書ごとに、だれが・いつ作成するのかを表示す
る。図10において、左のカラムから順に、アウトプッ
ト文書名、このアウトプット文書を作成する作業要員
(担当者)名とその責任区名、このアウトプット文書を
作成するためのタスクまたはジョブの開始日時と終了日
時、それをバーチャート化して視覚化したものである。
これら図9および図10によって、「だれが・いつ・何
をする」ということが分かりやすくなっているため、大
規模システムのタスク間にまたがった人員配置でも管理
しやすくなった。また、文書を作成するのにどの文書を
参照すれば良いかが関連付けられ、その参照文書も簡単
に見ることができるので、要員の文書作成が確実に且つ
容易になる。
In order to solve this, in the present invention, for example, as shown in FIG. 9, the progress status of each task of the project and the output document to be created are displayed. Figure 9
In the left column, in order from the left, the task name, the start date and time and the end date and time of the task, the work staff (person in charge) name of this task and the responsible district name, and the icon list of the reference document to be referenced to create the output document. , Task progress (%), icon list of output documents created by this task. Further, as shown in FIG. 10, for each output document, who and when to create it are displayed. In FIG. 10, in order from the left column, the output document name, the name of the worker (person in charge) who creates this output document and its responsible district name, and the start date and time of the task or job for creating this output document And the end date and time, which is visualized as a bar chart.
9 and 10, it is easy to understand "who, when, what", so that it is easy to manage the staffing across tasks of a large-scale system. Further, since which document should be referred to when creating a document is associated and the referenced document can be easily viewed, it is possible for the personnel to create the document reliably and easily.

【0037】また、タスク/ジョブで作成されるアウト
プット文書の進行状況を図11に示すように表示する。
図11において、一番上の行はこのタスクのタイトルを
示しており、左のカラムから順に、プロジェクト名、参
照文書のアイコンリストを示すカラムのタイトル、この
タスクがどのタスクについてなのかを示すタスク名、ア
ウトプット文書のアイコンリストを示すカラムのタイト
ルである。このタイトルの下の行は、タスク「基礎技術
調査」を分割したタスクおよびジョブごとに参照文書の
アイコンリスト、作業期間とその進捗状況を示すタスク
バー/ジョブバー、およびアウトプット文書のアイコン
リストを示している。この参照文書のアイコンリスト、
タスクバー/ジョブバーおよびアウトプット文書のアイ
コンリストは、左のカラムのタスク/ジョブと対応して
表示される。
Further, the progress status of the output document created by the task / job is displayed as shown in FIG.
In FIG. 11, the top line shows the title of this task. In order from the left column, the project name, the title of the column showing the icon list of the reference document, and the task showing which task this task is about. Name and title of the column showing the icon list of the output document. The line below this title shows the icon list of the reference document, the task bar / job bar showing the work period and its progress, and the icon list of the output document for each task and job obtained by dividing the task "Basic technology survey". There is. This reference document icon list,
The taskbar / jobbar and output document icon lists are displayed corresponding to the tasks / jobs in the left column.

【0038】図中Sで示されたタスク/ジョブ名の前に
ある印は、そのタスク/ジョブの進捗状況を色の変化で
表す。これにより、どのタスク/ジョブが遅れている
か、進んでいるかを確認することができる。また、タス
クとジョブを識別できるように、例えば、タスクを紺
色、ジョブを茶色というように色分けしてタスク/ジョ
ブ名やタスクバー/ジョブバーを表示して、各要員が担
当するタスク/ジョブを確認することができる。
The mark in front of the task / job name shown by S in the figure represents the progress of the task / job by a color change. As a result, it is possible to confirm which task / job is late or is in progress. In order to identify tasks and jobs, for example, tasks are colored in dark blue, jobs are colored in brown, and the task / job name and task bar / job bar are displayed to confirm the task / job that each person is in charge of. be able to.

【0039】さらに、図11において、タスク「基礎技
術発掘まとめ」は3つのジョブ「アイデア展開」、「ア
イデア比較」と「アイデアまとめ」とに分割されている
が、このタスクとしてのスケジュールは図中Wのバーの
くくりで示されており、そのタスクの作業期間はタスク
バーTで示される。ジョブ「アイデア展開」の作業期間
はジョブバーJ1、「アイデア比較」の作業期間はジョ
ブバーJ2、ジョブ「アイデアまとめ」の作業期間はジ
ョブバーJ3で示される。ジョブバーJ1は、アウトプ
ット文書「アイデアシート」とその改訂版「アイデアシ
ート#2」の作成状況を示す。同様にJ2は、アウトプ
ット文書「比較チャート」とその改訂版「比較チャート
#2」の作成状況を示す。J3は、アウトプット文書
「まとめレポート」の作成状況を示す。これらのタスク
バーやジョブバーにはその作業期間に作成されるべきア
ウトプット文書のアイコンが文書の作成終了時期に貼り
付けられている。これらのバーに貼り付けられたアイコ
ンは、アウトプット文書の一覧を示すカラムとも対応し
ている。例えば、図中AのアイコンはBのアイコンと、
CはDと、EはFと対応しているので、バー中のアイコ
ンがどのような文書であるかを確認することができる。
Further, in FIG. 11, the task "basic technology excavation summary" is divided into three jobs "idea development", "idea comparison" and "idea summary". The schedule for this task is shown in the figure. The work period of the task is shown by a task bar T. The work period of the job "idea development" is indicated by a job bar J1, the work period of "idea comparison" is indicated by a job bar J2, and the work period of the job "idea summary" is indicated by a job bar J3. The job bar J1 shows the creation status of the output document "idea sheet" and its revised version "idea sheet # 2". Similarly, J2 indicates the creation status of the output document “comparison chart” and its revised version “comparison chart # 2”. J3 indicates the status of preparation of the output document “Summary Report”. On these task bars and job bars, icons of output documents to be created during the work period are pasted at the time when the creation of the documents is completed. The icons attached to these bars also correspond to the columns showing the list of output documents. For example, the icon A in the figure is the icon B,
Since C corresponds to D and E corresponds to F, it is possible to confirm what kind of document the icon in the bar is.

【0040】このバーや参照文書/アウトプット文書の
カラムにある文書のアイコンは、「未完成(未着手・作
成中)」または「作成完了」等に応じて形・色等を変
え、作成状況が識別できるようになっている。さらに、
そのアイコンは、作成計画で示した完成日と、今日(図
中Nで示された線が今日を示す)の作成状況を比較し
て、計画通り作成されているかどうかによっても、形・
色等を変え識別できるようにした。例えば、図中Aで示
されるアイコンは作成完了を示す「チェック」の入った
アイコンであり、未完成な文書は、図中Cで示されるよ
うな中が空白なアイコンで表示される。また、まだ完了
予定日まで間のある文書のアイコンは白色であり、完了
予定日までに完了した文書は青色であり、完了予定日ま
でに完了していない文書のアイコンは図中EやFで示さ
れるように赤色である。さらに、完了予定日までに完了
していない文書を点滅表示させて目立つようにしてもよ
い。
The icon of the document in this bar or the column of the reference document / output document is changed in shape, color, etc. according to "unfinished (unstarted / under construction)" or "completion of creation", etc. Can be identified. further,
Depending on whether the icon is created according to the plan, the completion date shown in the creation plan is compared with the creation status of today (the line indicated by N in the figure indicates today).
The colors are changed so that they can be identified. For example, the icon shown by A in the drawing is an icon with a "check" indicating that the creation is completed, and the incomplete document is displayed as an icon with a blank inside as shown by C in the drawing. Also, the icon of the document which has the scheduled completion date is white, the document which is completed by the scheduled completion date is blue, and the icon of the document which is not completed by the scheduled completion date is E or F in the figure. It is red as shown. Further, a document that has not been completed by the scheduled completion date may be displayed in a blinking manner so as to be conspicuous.

【0041】以上説明した、タスク/ジョブの表示は、
そのタスク/ジョブの作業要員や関連する要員のみに限
定して表示するようにしてもよい。このようにプロジェ
クトで作成される文書をプロジェクトの進捗管理と連動
させ、計画に対しての遅延とその進行状況とを文書リン
クアイコンの形や色で視覚化して提供するので、プロジ
ェクトの進捗管理が容易になる。
The task / job display described above is
It is also possible to limit the display to only the work staff of the task / job and the related staff. In this way, the documents created in the project are linked with the progress management of the project, and the delay and progress of the plan are visualized and provided in the form and color of the document link icon. It will be easier.

【0042】さらに、本発明は上述した実施形態のみに
限定されたものではなく、上述したプロジェクト管理シ
ステムを構成する各機能をそれぞれプログラム化し、あ
らかじめCD−ROM等の記録媒体に書き込んでおき、
このCD−ROMをCD−ROMドライブのような媒体
駆動装置を搭載したコンピュータに装着して、これらの
プログラムをコンピュータのメモリあるいは記憶装置に
格納し、それを実行することによっても、本発明の目的
が達成されることは言うまでもない。この場合、記録媒
体から読出されたプログラム自体が上述した実施形態の
機能を実現することになり、そのプログラムおよびその
プログラムを記録した記録媒体も本発明を構成すること
になる。
Furthermore, the present invention is not limited to the above-described embodiment, but each function constituting the above-mentioned project management system is programmed and written in advance in a recording medium such as a CD-ROM.
The object of the present invention is also achieved by mounting the CD-ROM on a computer equipped with a medium driving device such as a CD-ROM drive, storing these programs in a memory or a storage device of the computer, and executing the programs. Needless to say, is achieved. In this case, the program itself read from the recording medium realizes the functions of the above-described embodiments, and the program and the recording medium recording the program also constitute the present invention.

【0043】なお、記録媒体としては半導体媒体(例え
ば、ROM、不揮発性メモリカード等)、光媒体(例え
ば、DVD、MO、MD、CD−R等)、磁気媒体(例
えば、磁気テープ、フレキシブルディスク等)のいずれ
であってもよい。
The recording medium is a semiconductor medium (eg, ROM, non-volatile memory card, etc.), optical medium (eg, DVD, MO, MD, CD-R, etc.), magnetic medium (eg, magnetic tape, flexible disk). Etc.).

【0044】また、ロードしたプログラムを実行するこ
とにより上述した実施形態の機能が実現されるだけでな
く、そのプログラムの指示に基づき、オペレーティング
システム等が実際の処理の一部または全部を行い、その
処理によって上述した実施形態の機能が実現される場合
も含まれる。
In addition to executing the functions of the above-described embodiments by executing the loaded program, the operating system or the like performs some or all of the actual processing based on the instructions of the program, and It also includes the case where the functions of the above-described embodiments are realized by the processing.

【0045】さらに、上述したプログラムをサーバコン
ピュータの磁気ディスク等の記憶装置に格納しておき、
インターネットで接続されたユーザのコンピュータから
ダウンロード等の形式で頒布する場合、このサーバコン
ピュータの記憶装置も本発明の記録媒体に含まれる。
Further, the above-mentioned program is stored in a storage device such as a magnetic disk of a server computer,
When distributed in a format such as a download from a user's computer connected to the Internet, the storage device of this server computer is also included in the recording medium of the present invention.

【0046】[0046]

【発明の効果】以上説明したように、本発明によれば、
プロジェクトで作成される文書をプロジェクトの進捗管
理と連動させるので、プロジェクトにおける文書作成の
管理および他の要員からの閲覧管理を容易に行える。ま
た、プロジェクトを計画したときにそのプロジェクトで
作成すべき文書の計画も作成するので、プロジェクトの
計画段階から文書作成の計画、その進捗状況が一覧でき
るので、プロジェクト管理が容易に行える。その結果、
プロジェクトで作成されるべき文書群を標準化すること
ができる。また、文書を作成するのにどの文書を参照す
れば良いかが関連付けられ、その参照文書も簡単に見る
ことができるので、要員の文書作成が確実に且つ容易に
なる。また、計画に対しての遅延とその進行状況とを文
書リンクアイコンの形や色で視覚化して提供するので、
プロジェクトの進捗管理が容易になる。
As described above, according to the present invention,
Since the documents created in the project are linked to the project progress management, it is possible to easily manage the document creation in the project and view management from other personnel. In addition, when a project is planned, a document plan to be created in the project is also created, so that the document creation plan and its progress can be viewed from the project planning stage, so that project management can be performed easily. as a result,
It is possible to standardize the documents to be created in the project. Further, since which document should be referred to when creating a document is associated and the referenced document can be easily viewed, it is possible for the personnel to create the document reliably and easily. In addition, since the delay and progress of the plan are visualized and provided in the shape and color of the document link icon,
The project progress management becomes easy.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本発明のプロジェクト管理システムの概略を
説明するための全体構成図である。
FIG. 1 is an overall configuration diagram for explaining an outline of a project management system of the present invention.

【図2】 プロジェクト管理装置の機能構成を説明する
ブロック図である。
FIG. 2 is a block diagram illustrating a functional configuration of a project management device.

【図3】 プロジェクト定義の入力画面例である。FIG. 3 is an example of a project definition input screen.

【図4】 アウトプット文書リストの表示画面例であ
る。
FIG. 4 is an example of a display screen of an output document list.

【図5】 タスク/ジョブで作成されるアウトプット文
書の表示画面例である。
FIG. 5 is a display screen example of an output document created by a task / job.

【図6】 タスク/ジョブで参照される参照文書の表示
画面例である。
FIG. 6 is an example of a display screen of a reference document referred to by a task / job.

【図7】 タスク/ジョブで参照される参照文書と作成
されるアウトプット文書の表示画面例である。
FIG. 7 is a display screen example of a reference document referred to by a task / job and an output document created.

【図8】 参照文書やアウトプット文書のプロパティの
表示画面例である。
FIG. 8 is a display screen example of properties of a reference document and an output document.

【図9】 タスクごとの進捗状況と作成すべきアウトプ
ット文書の表示画面例である。
FIG. 9 is a display screen example of a progress status for each task and an output document to be created.

【図10】 アウトプット文書ごとの担当者とその作業
期間を示す表示画面例である。
FIG. 10 is an example of a display screen showing a person in charge for each output document and a work period thereof.

【図11】 タスク/ジョブごとの進捗状況とアウトプ
ット文書の進捗状況の表示画面例である。
FIG. 11 is a display screen example of a progress status of each task / job and a progress status of an output document.

【符号の説明】[Explanation of symbols]

100…プロジェクト管理装置、110…プロジェクト
定義手段、120…プロジェクト情報管理DB(データ
ベース)、130…プロジェクトテンプレートDB、1
40…プロジェクト進捗登録手段、150…プロジェク
ト進捗状況表示手段、200…文書管理装置、210…
文書管理DB、300…事業所、400…サテライトオ
フィス、500…開発委託会社、600…ネットワー
ク、700…プロジェクト管理センタ。
100 ... Project management device, 110 ... Project definition means, 120 ... Project information management DB (database), 130 ... Project template DB, 1
40 ... Project progress registration means, 150 ... Project progress status display means, 200 ... Document management device, 210 ...
Document management DB, 300 ... Business office, 400 ... Satellite office, 500 ... Development consignment company, 600 ... Network, 700 ... Project management center.

Claims (14)

【特許請求の範囲】[Claims] 【請求項1】 プロジェクトの遂行時に作成される成果
物の進捗状況を管理するプロジェクト管理システムにお
いて、プロジェクトの計画時に、プロジェクトの各工程
で作成すべき成果物の空の実体を初めに登録しておくよ
うにしたことを特徴とするプロジェクト管理システム。
1. In a project management system for managing the progress status of an artifact created when a project is executed, an empty entity of the artifact to be created in each process of the project is first registered when planning the project. A project management system characterized by being set.
【請求項2】 プロジェクトの遂行時に作成される成果
物を管理する文書管理データベースと、プロジェクトの
進捗状況を管理するプロジェクト情報管理データベース
を有するプロジェクト管理システムにおいて、プロジェ
クトの計画時に、プロジェクトの各工程で作成すべき成
果物の空の実体を前記文書管理データベースへ登録し、
この登録した空の実体へのリンク情報を前記プロジェク
ト情報管理データベースへ前記工程と関連付けて登録す
ることを特徴とするプロジェクト管理システム。
2. A project management system having a document management database that manages deliverables created when a project is executed and a project information management database that manages the progress of the project, at each step of the project at the time of planning the project. Register an empty entity of the artifact to be created in the document management database,
A project management system, wherein the link information to the registered empty entity is registered in the project information management database in association with the process.
【請求項3】 請求項2に記載のプロジェクト管理シス
テムにおいて、プロジェクトの種類ごとに少なくとも工
程およびその工程で作成すべき成果物をテンプレートと
して登録したプロジェクトテンプレートデータベースを
有し、このテンプレートを選択することによってプロジ
ェクトの各工程で作成すべき成果物を登録するようにし
て、プロジェクトで作成する成果物を標準化することを
特徴とするプロジェクト管理システム。
3. The project management system according to claim 2, further comprising a project template database in which at least a process for each type of project and a product to be created in the process are registered as a template, and the template is selected. A project management system characterized by standardizing the deliverables created in the project by registering the deliverables to be created in each process of the project.
【請求項4】 請求項2または3に記載のプロジェクト
管理システムにおいて、前記工程で作成される前記成果
物とその成果物を作成する際に参照する参照文書とをこ
の工程に関連付けて前記プロジェクト情報管理データベ
ースへ登録することを特徴とするプロジェクト管理シス
テム。
4. The project management system according to claim 2 or 3, wherein the deliverable created in the process and a reference document referred to when creating the deliverable are associated with this process. A project management system characterized by being registered in a management database.
【請求項5】 請求項4に記載のプロジェクト管理シス
テムにおいて、前記参照文書は、既存または前工程で作
成される成果物であることを特徴とするプロジェクト管
理システム。
5. The project management system according to claim 4, wherein the reference document is an existing product or a product created in a previous process.
【請求項6】 請求項4または5に記載のプロジェクト
管理システムにおいて、前記プロジェクト情報管理デー
タベースに登録されたリンク情報から、実体である前記
文書管理データベース中の前記成果物または前記参照文
書を参照できるようにしたことを特徴とするプロジェク
ト管理システム。
6. The project management system according to claim 4, wherein the deliverable or the reference document in the document management database, which is the entity, can be referenced from the link information registered in the project information management database. A project management system characterized by the above.
【請求項7】 請求項2乃至6のいずれか1に記載のプ
ロジェクト管理システムにおいて、前記プロジェクト情
報管理データベースへプロジェクトの各要員とその役割
およびこの役割に応じた文書へのアクセス権限範囲を登
録し、前記要員がこの文書へアクセスする際には、その
要員の役割に基づいて前記プロジェクト情報管理データ
ベースを調べ、許容された権限内でその文書の実体への
アクセスを許すようにしたことを特徴とするプロジェク
ト管理システム。
7. The project management system according to any one of claims 2 to 6, wherein each of the project personnel and their roles and the access authority range to the document corresponding to this role are registered in the project information management database. , When the personnel access the document, the project information management database is checked based on the role of the personnel, and access to the entity of the document is permitted within the permitted authority. Project management system to do.
【請求項8】 請求項2乃至7のいずれか1に記載のプ
ロジェクト管理システムにおいて、プロジェクトで作成
される前記成果物の進捗状況を表示する進捗状況表示手
段を有し、その進捗状況を表示する際、前記工程の要員
とこの要員が担当する成果物についての進捗状況を表示
して、成果物の作成計画を管理できるようにしたことを
特徴とするプロジェクト管理システム。
8. The project management system according to claim 2, further comprising a progress status display unit for displaying a progress status of the deliverable created in the project, and displaying the progress status. At this time, the project management system is characterized in that it is possible to display the progress status of the personnel of the process and the deliverables in charge of the personnel so as to manage the creation plan of the deliverables.
【請求項9】 請求項8に記載のプロジェクト管理シス
テムにおいて、前記進捗状況表示手段は、前記成果物の
要員と作業期間を表示して、その成果物を誰が作成する
のかを管理できるようにしたことを特徴とするプロジェ
クト管理システム。
9. The project management system according to claim 8, wherein the progress status display means displays a personnel and a work period of the deliverable and manages who creates the deliverable. A project management system characterized by that.
【請求項10】 請求項8または9に記載のプロジェク
ト管理システムにおいて、前記進捗状況表示手段は、前
記工程ごとに作業期間を表示し、その作業期間内で作成
する成果物の進捗状況を示すアイコンを貼り付けること
によって、成果物の作成状況が分かるようにしたことを
特徴とするプロジェクト管理システム。
10. The project management system according to claim 8 or 9, wherein the progress display means displays a work period for each of the steps, and an icon indicating a progress of a product created within the work period. A project management system characterized by making it possible to know the creation status of deliverables by pasting.
【請求項11】 請求項10に記載のプロジェクト管理
システムにおいて、前記アイコンは、作成状況および/
または作成計画との差異に応じて識別して表示すること
を特徴とするプロジェクト管理システム。
11. The project management system according to claim 10, wherein the icon is a creation status and / or
Or, a project management system characterized by being displayed according to the difference from the creation plan.
【請求項12】 請求項10または11に記載のプロジ
ェクト管理システムにおいて、前記アイコンは、このア
イコンが表す成果物または参照文書の実体である前記文
書管理データベース中の文書へリンクしており、このア
イコンから文書の実体を参照できるようにしたことを特
徴とするプロジェクト管理システム。
12. The project management system according to claim 10 or 11, wherein the icon is linked to a document in the document management database which is an entity of a deliverable or a reference document represented by the icon. A project management system characterized by making it possible to refer to the substance of a document from.
【請求項13】 請求項1乃至12のいずれか1に記載
のプロジェクト管理システムの機能を実行するためのプ
ログラム。
13. A program for executing the function of the project management system according to claim 1.
【請求項14】 請求項13に記載のプログラムを記録
したコンピュータ読み取り可能な記録媒体。
14. A computer-readable recording medium in which the program according to claim 13 is recorded.
JP2001302505A 2001-09-28 2001-09-28 Project management system, program and recording medium Pending JP2003108735A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001302505A JP2003108735A (en) 2001-09-28 2001-09-28 Project management system, program and recording medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001302505A JP2003108735A (en) 2001-09-28 2001-09-28 Project management system, program and recording medium

Publications (1)

Publication Number Publication Date
JP2003108735A true JP2003108735A (en) 2003-04-11

Family

ID=19122736

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001302505A Pending JP2003108735A (en) 2001-09-28 2001-09-28 Project management system, program and recording medium

Country Status (1)

Country Link
JP (1) JP2003108735A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005301496A (en) * 2004-04-08 2005-10-27 Hitachi Ltd Task supporting system
JP2007065778A (en) * 2005-08-29 2007-03-15 Hitachi Software Eng Co Ltd Document management system
JP2007265081A (en) * 2006-03-29 2007-10-11 Fujitsu Ltd Specification preparation support program and specification preparation support device
JP2008139980A (en) * 2006-11-30 2008-06-19 Hitachi Ltd Process management support method, process management support program, and process management support apparatus
JP2012505446A (en) * 2008-10-06 2012-03-01 グリーンブラム アンド バーンスタイン ピー エル シー Invoicing, docketing, document management
JP2012165313A (en) * 2011-02-09 2012-08-30 Sony Corp Editing device, method, and program
CN112766645A (en) * 2020-12-30 2021-05-07 苏州深鉴信息科技有限公司 Supervision and management platform for whole process of information project
CN114971568A (en) * 2022-06-06 2022-08-30 中国银行股份有限公司 Bank project technical scheme management system and working method thereof
EP4246396A1 (en) 2022-03-15 2023-09-20 FUJIFILM Business Innovation Corp. Information processing apparatus, information processing system, program, and information processing method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005301496A (en) * 2004-04-08 2005-10-27 Hitachi Ltd Task supporting system
JP2007065778A (en) * 2005-08-29 2007-03-15 Hitachi Software Eng Co Ltd Document management system
JP4647438B2 (en) * 2005-08-29 2011-03-09 株式会社日立ソリューションズ Document management system
JP2007265081A (en) * 2006-03-29 2007-10-11 Fujitsu Ltd Specification preparation support program and specification preparation support device
JP2008139980A (en) * 2006-11-30 2008-06-19 Hitachi Ltd Process management support method, process management support program, and process management support apparatus
JP2012505446A (en) * 2008-10-06 2012-03-01 グリーンブラム アンド バーンスタイン ピー エル シー Invoicing, docketing, document management
JP2014238854A (en) * 2008-10-06 2014-12-18 グリーンブラム アンド バーンスタイン ピー エル シー Integrated official management system
JP2012165313A (en) * 2011-02-09 2012-08-30 Sony Corp Editing device, method, and program
CN102708905A (en) * 2011-02-09 2012-10-03 索尼公司 Editing device, editing method, and program
CN112766645A (en) * 2020-12-30 2021-05-07 苏州深鉴信息科技有限公司 Supervision and management platform for whole process of information project
EP4246396A1 (en) 2022-03-15 2023-09-20 FUJIFILM Business Innovation Corp. Information processing apparatus, information processing system, program, and information processing method
CN114971568A (en) * 2022-06-06 2022-08-30 中国银行股份有限公司 Bank project technical scheme management system and working method thereof

Similar Documents

Publication Publication Date Title
US5321610A (en) Integrated product for implementing application software and process of developing integrated product for implementing application software
US6865566B2 (en) Approach for re-using business rules
US7600182B2 (en) Electronic data capture and verification
US5737727A (en) Process management system and method
EP0657045B1 (en) Script-based system for testing a multi-user computer system
JP5113119B2 (en) Computer-executable workflow control system
US7613671B2 (en) Approach for re-using business rules
CA2534666C (en) Methodology framework and delivery vehicle
US7836103B2 (en) Exchanging project-related data between software applications
JP2003141320A (en) Project management system, program and recording medium
US20040111284A1 (en) Method and system to perform work units through action and resource entities
Sarin et al. A process model and system for supporting collaborative work
US20090043592A1 (en) Method and system for managing product development processes
US20030182172A1 (en) System and method to build project management processes
Blumöhr et al. Variant configuration with SAP
JPH043247A (en) Enterprise information flow defining method
JP2003108735A (en) Project management system, program and recording medium
JP2003114813A (en) Analysis server, program analysis network system and program analysis method
Assad et al. Project management using a microcomputer
JP5144458B2 (en) Created document navigation system
Singer et al. A single‐source content management system for lean manufacturing
Dart et al. Practical workflow for SAP
Ott Conceptual design and implementation of a graphical workflow-modelling editor in the context of distributed groupware-databases
EP1160715A2 (en) Computerised record keeping and process control
Fletcher et al. Workflow Management with SAP® WebFlow®: A Practical Manual