JP2530053B2 - Building foundation construction method - Google Patents

Building foundation construction method

Info

Publication number
JP2530053B2
JP2530053B2 JP2214850A JP21485090A JP2530053B2 JP 2530053 B2 JP2530053 B2 JP 2530053B2 JP 2214850 A JP2214850 A JP 2214850A JP 21485090 A JP21485090 A JP 21485090A JP 2530053 B2 JP2530053 B2 JP 2530053B2
Authority
JP
Japan
Prior art keywords
foundation
pipe member
connecting beam
pipe
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2214850A
Other languages
Japanese (ja)
Other versions
JPH0497020A (en
Inventor
明 岸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP2214850A priority Critical patent/JP2530053B2/en
Publication of JPH0497020A publication Critical patent/JPH0497020A/en
Application granted granted Critical
Publication of JP2530053B2 publication Critical patent/JP2530053B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、建物のコンクリート基礎を施工する方法に
係り、鉄骨軸組み構造の建物の基礎に利用できるもので
ある。
The present invention relates to a method for constructing a concrete foundation of a building, and can be applied to a building foundation having a steel frame structure.

〔背景技術〕[Background technology]

鉄骨軸組み構造の建物において、柱のコンクリート基
礎との接合部分である柱脚には、埋め込み柱脚と露出柱
脚とがある。埋め込み柱脚は、スタッドボルトを突設し
た基礎柱をコンクリート基礎内に埋め込み、基礎の上面
から突出した基礎柱の上部に建物の柱を接合するもので
ある。露出柱脚は、補強鉄筋を縦横に組み合わせてコン
クリート基礎の骨組みを形成し、コンクリート基礎の上
面からアンカーボルトを突出させ、このアンカーボルト
により建物の柱の下端に設けたベースプレートを固定す
るものである。
In a building with a steel frame structure, there are an embedded column base and an exposed column base in a column base that is a joint portion of a column with a concrete foundation. The embedded column base is to embed a foundation column with a stud bolt projecting into the concrete foundation and join the building column to the upper portion of the foundation column protruding from the upper surface of the foundation. The exposed column base is to form a frame of concrete foundation by combining reinforcing bars vertically and horizontally, projecting anchor bolts from the upper surface of the concrete foundation, and fixing the base plate provided at the lower end of the column of the building by this anchor bolt. .

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

以上の従来方式によると、基礎柱や、アンカーボルト
の配置位置は墨出し作業等を行うことによって決められ
るが、この作業は必ずしも正確に行えず、誤差が生じる
ため、基礎の施工精度は低いものとなっていた。また、
補強鉄筋を縦横に組み合わせてコンクリート基礎の骨組
みを形成するためには、熟練した作業者が必要であり、
かつ、この作業に多くの時間と手間がかかっていた。こ
のため、コンクリート基礎より上に建てられる建物につ
いて工業化を達成しても、従来では、基礎の施工のため
に長い期間がかかっていた。
According to the above conventional method, the placement position of the foundation pillar and the anchor bolt is determined by performing marking work, etc., but this work is not always accurate and errors occur, so the foundation construction accuracy is low It was. Also,
Skilled workers are required to combine the reinforcing bars vertically and horizontally to form the concrete foundation frame.
Moreover, this work took a lot of time and effort. For this reason, even if industrialization was achieved for a building built above a concrete foundation, conventionally it took a long time to construct the foundation.

本発明の目的は、基礎の施工精度を高めることがで
き、また、その施工作業を容易に行えるようになり、施
工期間を短縮できるようにもなる建物の基礎施工方法を
提供するところにある。
It is an object of the present invention to provide a foundation construction method for a building that can improve the construction accuracy of the foundation, facilitate the construction work, and shorten the construction period.

〔課題を解決するための手段〕[Means for solving the problem]

本発明に係る建物の基礎施工方法は、建物の柱を立設
すべきそれぞれの所定の位置に管部材を配置し、これら
の管部材を工場で予め製造されて型枠保持具を備えてい
る連結用梁で連結し、この後、前記型枠保持具に平板状
の基礎成形型枠を取り付けることにより前記管部材およ
び前記連結用梁の周囲をこの基礎成形型枠で囲んでその
内部にコンクリートスラリーを打設する作業と、前記管
部材に前記柱の下部を挿入してこの管部材に充填したグ
ラウト材で前記柱を固定することを特徴とするものであ
る。
The foundation construction method for a building according to the present invention includes pipe members arranged at predetermined positions where columns of the building should be erected, and these pipe members are pre-manufactured in a factory and provided with a mold holder. The pipe member and the connecting beam are connected by a connecting beam, and then a flat plate-shaped basic forming mold is attached to the form holder to enclose the pipe member and the connecting beam with the basic forming mold, and the concrete is formed inside the surrounding frame. It is characterized in that the operation of pouring the slurry and the insertion of the lower portion of the column into the tube member and fixing the column with the grout material filled in the tube member.

以上において、基礎成形型枠の内部にコンクリートス
ラリーを打設する作業と、管部材に柱の下部を挿入して
グラウト材で固定する作業とは、どちらを先に行っても
よい。また、基礎成形型枠は、コンクリートスラリーの
凝固後、取り外してもよいが、そのまま残してもよい。
そのまま残すときには型枠は基礎の表面材として使用さ
れる。
In the above, either the operation of placing the concrete slurry inside the basic forming mold or the operation of inserting the lower portion of the column into the pipe member and fixing it with the grout material may be performed first. The basic forming mold may be removed after the concrete slurry is solidified, or may be left as it is.
When left as it is, the formwork is used as a surface material for the foundation.

〔作用〕[Action]

それぞれの管部材を連結用梁で連結すると、管部材相
互の間隔が定まり、連結用梁は工場で予め製造されて建
設現場に運ばれるものであるため、その長さ寸法は正確
となっており、このため、管部材相互の間隔を所定の正
確な間隔に設定でき、基礎は高精度にでき上る。また、
管部材と連結用梁は骨組みを形成し、管部材相互を連結
用梁で連結すればこの骨組みの組み立て作業が終了し、
この作業を簡単に短時間で行えるため、基礎の施工作業
の容易化、短期間化を達成できる。
When each pipe member is connected with the connecting beam, the interval between the pipe members is determined, and the connecting beam is manufactured in advance at the factory and transported to the construction site, so the length dimension is accurate. Therefore, the interval between the pipe members can be set to a predetermined accurate interval, and the foundation can be completed with high accuracy. Also,
The pipe member and the connecting beam form a skeleton, and if the pipe members are connected with the connecting beam, the assembling work of this skeleton is completed,
Since this work can be performed easily and in a short time, the work for constructing the foundation can be facilitated and shortened.

また、連結用梁が工場で製造されるときにこの連結用
梁には型枠保持具が設けられるため、建物の建設現場に
おいて管部材および連結用梁の周囲を基礎成形用型枠で
囲むときに、この基礎成形用型枠を型枠保持具に取り付
ける作業を行うだけにより、基礎成形用型枠を所定位置
に簡単に配設でき、このため作業の迅速化、容易化を達
成できる。
Also, when the connecting beam is manufactured at the factory, a frame holder is provided on the connecting beam, so when surrounding the pipe member and the connecting beam with the foundation forming formwork at the construction site of the building. In addition, the basic forming mold can be easily arranged at a predetermined position only by attaching the basic forming mold to the mold holder, and thus the work can be speeded up and facilitated.

〔実施例〕〔Example〕

以下に本発明の一実施例を添付図面に基づいて説明す
る。
An embodiment of the present invention will be described below with reference to the accompanying drawings.

第1図は基礎の骨組みを形成する部材を示し、この骨
組みは管部材1と連結用梁2とで形成される。管部材1
は角型鋼管からなり、その上面だけが開口している。連
結用梁2は鉄骨梁であって、上材3と下材4とを斜材5
で接合したものであり、ラチス梁状となっている。
FIG. 1 shows a member forming a basic framework, which is composed of a pipe member 1 and a connecting beam 2. Pipe member 1
Is made of square steel pipe, and only the top surface is open. The connecting beam 2 is a steel beam, and the upper member 3 and the lower member 4 are diagonal members 5.
They are joined together in the shape of a lattice beam.

上材3と下材4にはこれらと直角方向に型枠保持具6
が取付けられ、この型枠保持具6の両端の垂直部6Aには
孔7が形成され、また孔7の裏側にはナット8が固定さ
れている。また、下材4には高さレベル調整ボルト9が
垂直に設けられ、このボルト9は下材4に固定したナッ
ト10に螺合されているため、回転操作すれば、ボルト9
の下材4からの突出量を調整でき、これにより連結用梁
2の高さレベルを調整できるようになっている。
For the upper material 3 and the lower material 4, a mold holder 6 is formed in a direction perpendicular to these.
Are attached, holes 7 are formed in the vertical portions 6A at both ends of the form holder 6, and nuts 8 are fixed to the back side of the holes 7. A height level adjusting bolt 9 is vertically provided on the lower member 4, and the bolt 9 is screwed into a nut 10 fixed to the lower member 4.
The amount of protrusion from the lower member 4 can be adjusted, whereby the height level of the connecting beam 2 can be adjusted.

以上の型枠保持具6及び高さレベル調整ボルト9は連
結用梁2の長手方向にそれぞれ複数設けられている。
A plurality of the above mold holders 6 and height level adjusting bolts 9 are provided in the longitudinal direction of the connecting beam 2.

前記管部材1の4つの側面のうち、連結用梁2が連結
される側面にはブラケット11が取付けられ、このブラケ
ット11は連結用梁2の上材3、下材4と同じ間隔で上下
に2個設けられ、それぞれのブラケット11に孔12が形成
されている。また、連結用梁2の上材3、下材4の端部
には孔13が形成され、これらの孔12,13にボルト14を通
してナット15を締め付けることにより、管部材1と連結
用梁2との連結が行われるようになっている。
Of the four side surfaces of the pipe member 1, a bracket 11 is attached to a side surface to which the connecting beam 2 is connected, and the bracket 11 is vertically arranged at the same intervals as the upper member 3 and the lower member 4 of the connecting beam 2. Two pieces are provided, and holes 12 are formed in each bracket 11. In addition, holes 13 are formed at the ends of the upper member 3 and the lower member 4 of the connecting beam 2, and bolts 14 are passed through these holes 12 and 13 to fasten a nut 15, whereby the pipe member 1 and the connecting beam 2 are connected. It is designed to be linked with.

以上において、連結用梁2は管部材1と共に工場で予
め製造され、そして建設現場に運ばれる。それぞれの連
結用梁2は、これらの連結用梁2で互いに連結される管
部材1の所定の間隔と対応した正確な長さを有するもの
として製造されている。
In the above, the connecting beam 2 is pre-manufactured in the factory together with the pipe member 1 and then transported to the construction site. Each of the connecting beams 2 is manufactured as having an accurate length corresponding to a predetermined distance between the pipe members 1 connected to each other by these connecting beams 2.

次に基礎の施工手順について説明する。 Next, the construction procedure of the foundation will be described.

本実施例に係る基礎は、第3図に示されているよう
に、幅広のフーチング部16と、この上の幅狭の立上部17
とからなり、管部材1と連結用梁2は立上部17の骨組み
を形成するものとなっており、捨てコンクリート18上に
予めフーチング部16が形成されている。
As shown in FIG. 3, the foundation according to this embodiment has a wide footing portion 16 and a narrow rising portion 17 on the footing portion 16.
The pipe member 1 and the connecting beam 2 form a skeleton of the rising portion 17, and the footing portion 16 is previously formed on the discarded concrete 18.

第1図の通り、それぞれの管部材1をフーチング部16
上の所定の位置、すなわち、建物の柱19(第3図、第4
図参照)を立設すべきそれぞれの位置に配置し、これら
の管部材1の間に連結用梁2を配置し、この連結用梁2
で管部材1相互を連結する。この時、前記高さレベル調
整ボルト9により連結用梁2の高さレベルを調整する。
図面では管部材1の上下寸法はフーチング部6まで達す
るものとなっているが、管部材1の上下寸法を短くし、
高さレベル調整ボルト9により連結用梁2を介して管部
材1をフーチング部16から浮かせた状態で支持するよう
にしてもよい。
As shown in FIG. 1, each pipe member 1 is attached to the footing portion 16
Above the predetermined position, namely the pillar 19 of the building (Fig. 3, 4
(Refer to the drawing) are arranged at respective positions to be erected, and the connecting beam 2 is arranged between these pipe members 1.
The pipe members 1 are connected with each other. At this time, the height level of the connecting beam 2 is adjusted by the height level adjusting bolt 9.
Although the vertical dimension of the pipe member 1 reaches the footing portion 6 in the drawing, the vertical dimension of the pipe member 1 is shortened,
The pipe member 1 may be supported by the height level adjusting bolt 9 in a state of being floated from the footing portion 16 via the connecting beam 2.

次いで、第2図の通り、管部材1及び連結用梁2の外
側周囲に基礎成形型枠20を配置する。これらの型枠20の
内面には前記型枠保持具6の垂直部6Aと対応した位置に
リング状突起部20Aが設けられており、この突起部20Aに
型枠20の外側から挿入したボルト21を垂直部6Aの前記孔
7に通し、さらに前記ナット8に螺合する。これにより
型枠20は型枠保持具6に連結されて直立状態を維持する
ようになる。
Next, as shown in FIG. 2, the base forming mold 20 is arranged around the outer periphery of the pipe member 1 and the connecting beam 2. A ring-shaped protrusion 20A is provided on the inner surface of these molds 20 at a position corresponding to the vertical portion 6A of the mold holder 6, and a bolt 21 inserted into the protrusion 20A from the outside of the mold 20. Through the hole 7 of the vertical portion 6A, and further screwed into the nut 8. As a result, the mold 20 is connected to the mold holder 6 and maintains the upright state.

ここで、基礎成形用型枠20は型枠保持具6を介して連
結用梁2と管部材1とで構成される基礎の骨組みに保持
されるため、型枠20は第2図で示されているようにそれ
自身だけでは自立しない平板状のものでよく、このた
め、型枠20の形状、構造は単純で、その製作を容易に行
えるようになっている。
Here, since the foundation molding form 20 is held by the framework of the foundation composed of the connecting beam 2 and the pipe member 1 via the form holder 6, the form 20 is shown in FIG. As described above, it may be a flat plate that does not stand alone by itself, and therefore, the form and structure of the form 20 is simple and its manufacture is easy.

このように管部材1及び連結用梁2の周囲を型枠20で
囲んだ後、その内部にコンクリートスラリーを打設す
る。このスラリーの打設は第2図の二点鎖線22で示す高
さ位置まで行い、これにより管部材1の上面開口部1Aの
露出状態を確保するようにする。
After the pipe member 1 and the connecting beam 2 are surrounded by the form 20 in this way, concrete slurry is poured into the interior thereof. The pouring of this slurry is carried out up to the height position shown by the chain double-dashed line 22 in FIG. 2 to ensure the exposed state of the upper opening 1A of the pipe member 1.

コンクリートスラリーが凝固した後、前記ボルト21を
緩め、そして型枠20を取り外す。これにより、第3図で
示す通り、フーチング部16の上に立上部17が設けられた
コンクリート基礎23が出来上がる。この基礎23の立上部
17の側面には前記リング状突起部20Aによる窪みができ
ているため、この窪みにコンクリートスラリーを詰め、
立上部17の表面を仕上げる。
After the concrete slurry has solidified, the bolts 21 are loosened and the formwork 20 is removed. As a result, as shown in FIG. 3, the concrete foundation 23 in which the rising portion 17 is provided on the footing portion 16 is completed. The rise of this foundation 23
Since a recess is formed by the ring-shaped protrusion 20A on the side surface of 17, the recess is filled with concrete slurry,
Finish the surface of the rising part 17.

次いで、それぞれの管部材1の内部に、第3図の通
り、柱19の下部を前記上面開口部1Aから挿入し、そして
第4図の通り、管部材1の内部にグラウト材24を充填す
る。グラウト材24を充填する前に、管部材1に対して柱
19を前後、左右及び上下方向に位置決めする。この位置
決めは、例えば管部材1の内部に栗石等の詰め物を詰め
たり、管部材1に接続部材を介して柱19を溶接したりす
ることにより行える。
Next, as shown in FIG. 3, the lower part of the column 19 is inserted into the inside of each pipe member 1 through the upper opening 1A, and as shown in FIG. 4, the inside of the pipe member 1 is filled with the grout material 24. . Before filling the grout material 24, the pillar is attached to the pipe member 1.
Position 19 in the front-back, left-right and up-down directions. This positioning can be performed, for example, by filling the inside of the pipe member 1 with a filling material such as crushed stone, or by welding the column 19 to the pipe member 1 via a connecting member.

グラウト材24が凝固すると、管部材1に柱19が固定さ
れることになり、これによりコンクリート基礎23に柱19
の柱脚が接合され、この後、通常の鉄骨軸組み構造の建
物と同様に、柱19間に鉄骨梁を架設する作業等を行う。
When the grout material 24 is solidified, the pillars 19 are fixed to the pipe member 1, so that the pillars 19 are fixed to the concrete foundation 23.
The column pedestals are joined together, and thereafter, the work of constructing the steel beam between the columns 19 is performed as in the case of a building having a normal steel frame structure.

以上説明した本実施例によれば、管部材1相互を連結
する連結用梁2は工場で予め製造され、正確な所定寸法
となっているため、管部材1相互の間隔が正確なものと
なり、これによりそれぞれの管部材1は柱19を立設すべ
き所定の位置に確実に配置されることになり、管部材1
を柱19との接合部材とするコンクリート基礎23は高精度
に仕上がることになる。
According to the present embodiment described above, since the connecting beam 2 for connecting the pipe members 1 to each other is manufactured in advance in the factory and has an accurate predetermined size, the intervals between the pipe members 1 become accurate, As a result, the respective pipe members 1 are securely arranged at the predetermined positions where the columns 19 should be erected, and the pipe members 1
The concrete foundation 23, which is a joint member with the pillar 19, is finished with high precision.

また、管部材1と連結用梁2はコンクリート基礎の立
上部17の骨組みを形成し、管部材1相互を連結用梁2で
連結する作業を行えば、この骨組みの組み立て作業は終
了し、この組み立て作業は特別の熟練を必要とすること
なく行え、かつ、短時間で行えるため、作業の容易化を
実現でき、基礎の施工期間を短縮できる。
Further, the pipe member 1 and the connecting beam 2 form a frame of the rising part 17 of the concrete foundation, and if the pipe members 1 are connected by the connecting beam 2, the assembling work of this frame is completed. Since the assembly work can be performed without requiring special skill and can be performed in a short time, the work can be facilitated and the foundation construction period can be shortened.

さらに本実施例によれば、工場で製造される連結用梁
2には型枠保持具6が設けられるため、管部材1および
連結用梁2の周囲を基礎成形用型枠20で囲むためにこの
型枠20を所定位置に配設するための作業は、型枠保持具
6に型枠20を取り付ける作業によって簡単に行えること
になり、このため、作業の迅速化、容易化を達成でき
る。
Further, according to the present embodiment, since the mold holding tool 6 is provided on the connecting beam 2 manufactured in the factory, in order to surround the periphery of the pipe member 1 and the connecting beam 2 with the basic forming mold 20. The work for arranging the mold 20 at a predetermined position can be easily performed by the work of attaching the mold 20 to the mold holder 6, and thus the work can be speeded up and facilitated.

以上説明した実施例ではコンクリートスラリーの凝固
後に型枠20を取り外すようにしたが、型枠20として例え
ばガラス繊維入りのコンクリート版等を使用することに
より、コンクリートスラリー凝固後も型枠をそのまま残
し、型枠を基礎の表面材として使用するようにしてもよ
い。この場合には、型枠と連結用梁の型枠保持具とを型
枠の内部においてボルト等で連結するようにし、ボルト
の頭部等が型枠外側面に露出しないようにする。
In the embodiment described above, the mold 20 was removed after solidification of the concrete slurry, but by using, for example, a glass fiber-containing concrete plate as the mold 20, leaving the mold as it is after solidifying the concrete slurry, The formwork may be used as a surface material for the foundation. In this case, the formwork and the formwork holder of the connecting beam are connected inside the formwork by bolts or the like so that the heads of the bolts or the like are not exposed to the outside surface of the formwork.

さらに、前記実施例は、管部材1と連結用梁2はコン
クリート基礎23の立上部17の内部に埋設されるものとな
っていたが、これらをフーチング部16まで達するものと
することもでき、また、本発明に係る方法を適用できる
コンクリート基礎はフーチング部16と立上部17とから成
る基礎に限定されず、立上部のみからなる基礎にも本発
明の方法は適用可能である。
Further, in the above-mentioned embodiment, the pipe member 1 and the connecting beam 2 are embedded in the inside of the rising portion 17 of the concrete foundation 23, but it is also possible to extend these to the footing portion 16. Further, the concrete foundation to which the method according to the present invention can be applied is not limited to the foundation including the footing portion 16 and the rising portion 17, and the method according to the present invention can be applied to a foundation including only the rising portion.

また、前記実施例では、基礎成形用型枠20の内部にコ
ンクリートスラリーを打設し、このスラリーの凝固後、
管部材の内部に柱19の下部を挿入してこの柱19をグラウ
ト材24で管部材1に固定するようにしていたが、これら
の作業の順序を逆にしてもよい。
Further, in the above-mentioned embodiment, the concrete slurry is poured into the inside of the basic forming mold 20, and after solidification of this slurry,
Although the lower portion of the column 19 is inserted into the pipe member and the column 19 is fixed to the pipe member 1 with the grout material 24, the order of these operations may be reversed.

〔発明の効果〕〔The invention's effect〕

本発明によれば、工場で予め生産されて正確な長さ寸
法を有する連結用梁で管部材相互を連結するため、基礎
の施工精度が高まり、これにより基礎とこの基礎の上に
立てられる建物との結合強度を大きくでき、また、補強
鉄筋を縦横に配筋する作業を行う必要がなく、管部材と
連結用梁とからなる骨組みを作る作業を簡単に短時間で
行えるため、従来よりも基礎施工作業が容易となり、基
礎の施工期間を短縮できる。
According to the present invention, since the pipe members are connected to each other by the connecting beams that are produced in advance in the factory and have the correct length dimension, the construction accuracy of the foundation is increased, and thereby the foundation and the building that is erected on the foundation are constructed. Since it is possible to increase the strength of the connection with, and it is not necessary to carry out the work of arranging the reinforcing reinforcing bars in the vertical and horizontal directions, and the work of making the skeleton consisting of the pipe members and the connecting beams can be done easily and in a short time, The foundation construction work becomes easy and the foundation construction period can be shortened.

また、本発明によれば、工場で製造される連結用梁に
は型枠保持具が設けられているため、管部材および連結
用梁の周囲を基礎成形用型枠で囲むためにこの型枠を所
定位置に配設する作業は型枠保持具に型枠を取り付ける
作業だけを行えばよく、このため、作業の迅速化、容易
化を達成でき、かつ、型枠は型枠保持具を介して連結用
梁と管部材とで構成される基礎の骨組みに保持されるた
め、この型枠をそれ自身だけでは自立しない平板状のも
のとすることが可能となり、このため、型枠の形状、構
造の単純化、製作の容易化を達成でき、コストの低減を
実現できる。
Further, according to the present invention, since the connecting beam manufactured in the factory is provided with the form holder, this form is used to surround the pipe member and the connecting beam with the basic forming form. The work of arranging the mold at a predetermined position may be performed only by attaching the formwork to the formwork holder, and therefore, the work can be speeded up and facilitated, and the formwork can be installed via the formwork holder. Since it is held by the basic frame composed of the connecting beam and the pipe member, it becomes possible to make this formwork into a flat plate shape that does not stand alone by itself. The structure can be simplified, the manufacturing can be facilitated, and the cost can be reduced.

【図面の簡単な説明】[Brief description of drawings]

第1図は管部材と連結用梁とを分離して示した斜視図、
第2図は基礎成形用型枠を組み立てた後の状態を示す正
断面図、第3図はコンクリートスラリー凝固後に管部材
に柱の下部を挿入する状態を示す斜視図、第4図は管部
材と柱とがグラウト材で結合された状態を示す側断面図
である。 1…管部材、2…連結用梁、6…型枠保持具、9…高さ
レベル調整ボルト、16…フーチング部、17…立上部、18
…捨てコンクリート、19…柱、20…基礎成形型枠、23…
コンクリート基礎、24…グラウト材。
FIG. 1 is a perspective view showing a pipe member and a connecting beam separately.
FIG. 2 is a front sectional view showing a state after the basic forming mold is assembled, FIG. 3 is a perspective view showing a state where a lower portion of a column is inserted into a pipe member after solidification of concrete slurry, and FIG. 4 is a pipe member. It is a sectional side view which shows the state which the column and the pillar were joined by the grout material. DESCRIPTION OF SYMBOLS 1 ... Pipe member, 2 ... Connection beam, 6 ... Form holder, 9 ... Height level adjustment bolt, 16 ... Footing part, 17 ... Upright part, 18
… Discarded concrete, 19… Pillars, 20… Foundation molding form, 23…
Concrete foundation, 24… grout material.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】建物の柱を立設すべきそれぞれの所定の位
置に管部材を配置し、これらの管部材を工場で予め製造
されて型枠保持具を備えている連結用梁で連結し、この
後、前記型枠保持具に平板状の基礎成形用型枠を取り付
けることにより前記管部材および前記連結用梁の周囲を
この基礎成形用型枠で囲んでその内部にコンクリートス
ラリーを打設する作業と、前記管部材に前記柱の下部を
挿入してこの管部材に充填したグラウト材で前記柱を固
定する作業とを行うことを特徴とする建物の基礎施工方
法。
1. A pipe member is arranged at each predetermined position where a pillar of a building is to be erected, and these pipe members are connected by a connecting beam which is manufactured in advance in a factory and is provided with a form holder. After that, by attaching a flat plate-shaped basic forming form to the form holder, the pipe member and the connecting beam are surrounded by the basic forming form, and concrete slurry is placed therein. And a work of inserting the lower part of the column into the pipe member and fixing the column with grout material filled in the pipe member.
JP2214850A 1990-08-13 1990-08-13 Building foundation construction method Expired - Lifetime JP2530053B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2214850A JP2530053B2 (en) 1990-08-13 1990-08-13 Building foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2214850A JP2530053B2 (en) 1990-08-13 1990-08-13 Building foundation construction method

Publications (2)

Publication Number Publication Date
JPH0497020A JPH0497020A (en) 1992-03-30
JP2530053B2 true JP2530053B2 (en) 1996-09-04

Family

ID=16662582

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2214850A Expired - Lifetime JP2530053B2 (en) 1990-08-13 1990-08-13 Building foundation construction method

Country Status (1)

Country Link
JP (1) JP2530053B2 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57129822U (en) * 1981-02-06 1982-08-13
JPH0327072Y2 (en) * 1984-09-12 1991-06-12
JPS61162635A (en) * 1985-01-10 1986-07-23 Asada Kiyoko Column leg securing structure and member thereof and forming method thereof

Also Published As

Publication number Publication date
JPH0497020A (en) 1992-03-30

Similar Documents

Publication Publication Date Title
JP6871495B1 (en) Solid foundation formwork and solid foundation construction method
JP2530053B2 (en) Building foundation construction method
JP2006322154A (en) Foundation construction method of building
JP2537330B2 (en) Precast reinforced concrete columns
JP2004011203A (en) Precast src-column joining section structure
JPH09296565A (en) Precast concrete column, its manufacture, and execution method
JPS61233131A (en) Foundation structure of pole
JPH0523155B2 (en)
JP2504578B2 (en) Steel frame construction method
JPH063879Y2 (en) Basic slab unit
JP2554382B2 (en) Dwelling
JP2552750B2 (en) Basic construction method for housing
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
JP2000120076A (en) Foundation structure of steel framed structure and its execution method
JP3114071B2 (en) Embedded type leg anchoring method for steel columns
JP2574630Y2 (en) Half PC beam structure
JP2677174B2 (en) Column base structure of steel column
JP4319775B2 (en) Seismic reinforcement wall and its manufacturing method
JP2001011868A (en) Column base joint method and blockout device
JPH09256631A (en) Construction method of building reinforced concrete wall
JPH09256383A (en) Erection method of steel framed column
JPH0119005B2 (en)
JPH08246587A (en) Successive concrete placing formwork and wall jointing construction method
JPH0674590B2 (en) Block for building legal framework and method for building legal framework
JP2594654B2 (en) Method for forming PC column and method for joining PC column