JP2527310B2 - Manufacturing method of concrete structure - Google Patents

Manufacturing method of concrete structure

Info

Publication number
JP2527310B2
JP2527310B2 JP61219686A JP21968686A JP2527310B2 JP 2527310 B2 JP2527310 B2 JP 2527310B2 JP 61219686 A JP61219686 A JP 61219686A JP 21968686 A JP21968686 A JP 21968686A JP 2527310 B2 JP2527310 B2 JP 2527310B2
Authority
JP
Japan
Prior art keywords
mound
blocks
water
concrete structure
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP61219686A
Other languages
Japanese (ja)
Other versions
JPS6378924A (en
Inventor
積彦 木林
薫 松浦
Original Assignee
大豊建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 大豊建設株式会社 filed Critical 大豊建設株式会社
Priority to JP61219686A priority Critical patent/JP2527310B2/en
Publication of JPS6378924A publication Critical patent/JPS6378924A/en
Application granted granted Critical
Publication of JP2527310B2 publication Critical patent/JP2527310B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 (発明の属する技術分野) 本発明は、作業台船上でケーソンのごときコンクリー
ト構造物を築造するコンクリート構造物の製作方法に関
する。
Description: TECHNICAL FIELD The present invention relates to a method for producing a concrete structure for constructing a concrete structure such as a caisson on a work table ship.

(従来の技術) 岸壁の近くで、防波堤等として利用されるケーソンの
ごときコンクリート構造物を築造する場合、従来第3図
に示すように、予め水底BWに捨石や砂等でマウンドM″
を造成する。そして、マウンドM″上に床板4と、頂板
6とを有する作業台船Dを着底させる。
(Prior Art) When constructing a concrete structure such as a caisson used as a breakwater near a quay, as shown in FIG. 3, the mound M ″ is previously formed on the water bottom BW with rubble or sand.
To create. Then, the work platform D having the floor plate 4 and the top plate 6 is set on the bottom of the mound M ″.

しかして、前記作業台船Dの頂板6を水面上方に位置
させた状態で、作業台船Dの床板4上でコンクリート構
造物Cを、自力で十分に浮上し得る高さまで築造する。
Then, with the top plate 6 of the work pontoon D positioned above the water surface, the concrete structure C is built on the floor plate 4 of the work pontoon D to a height at which it can sufficiently float by itself.

その後、作業台船Dを水面に浮かべ、その作業台船D
を介してコンクリート構造物Cを所定の位置まで曳航す
る。ついで、作業台船Dを水面下に沈下させ、作業台船
Dの床板4からコンクリート構造物Cを分離させ、コン
クリート構造物Cを単独で水面に浮かべて作業台船Dか
ら取り出す。
Then, float the work pontoon D on the water surface,
The concrete structure C is towed to a predetermined position via. Then, the work pontoon D is sunk below the surface of the water, the concrete structure C is separated from the floor plate 4 of the work pontoon D, and the concrete structure C is independently floated on the water surface and taken out from the work pontoon D.

ついで、コンクリート構造物C内に注水し、そのコン
クリート構造物Cを水底の所定位置に沈下させ、据え付
けるようにしている。
Next, water is poured into the concrete structure C, and the concrete structure C is submerged at a predetermined position on the water bottom and installed.

なお、第3図中、符号Gは岸壁、mはマウンドの法面
を示す。
In addition, in FIG. 3, reference numeral G indicates a quay, and m indicates a slope of the mound.

(発明が解決しようとする課題) ところが、前記従来技術では作業台船着底用のマウン
ドM″を、岸壁Gの製作ヤードに近い水底BWに土や砂等
を盛り固めて築造している。このため、次のような問題
があった。
(Problems to be Solved by the Invention) However, in the above-described conventional technique, the mound M ″ for bottoming the work platform ship is constructed by solidifying soil, sand or the like on the water bottom BW near the manufacturing yard of the quay G. Therefore, there were the following problems.

水中での土砂均しに時間が掛かり、マウンドの築造
に長時間を要する。
It takes time to level the soil in the water, and it takes a long time to build the mound.

マウンドの面積の増減を簡単にはできない。すなわ
ち、マウンドの面積を増加させるには、新たに土砂等を
盛り、土均して固めなければならないし、またマウンド
の面積を縮減するには、余剰部分を掘削して除去しなけ
ればならず、いずれにしても作業が煩雑である。
You cannot easily increase or decrease the area of the mound. That is, in order to increase the area of the mound, it is necessary to newly fill it with earth and sand and level it to solidify it, and to reduce the area of the mound, excavate and remove the surplus portion. In any case, the work is complicated.

海水の流れで土砂が常に侵食を受ける。これを防止
するためには、マウンドM″の法面mや肩部に侵食防止
用のブロック等を設置する必要があり、マウンドの維持
管理が難しい。
Sediment is constantly eroded by the flow of seawater. In order to prevent this, it is necessary to install blocks for erosion prevention on the slope m and shoulders of the mound M ″, which makes maintenance of the mound difficult.

マウンドを撤去する際、水底BWに盛り上げて固めた
土砂等を撤去しなければならず、水中での作業であるた
め容易ではなく、また水の汚濁処理や排土場の管理も容
易ではない。したがって、マウンドの撤去が極めて難し
い。
When removing the mound, it is necessary to remove the soil and sand that is piled up on the water bottom BW and hardened, and it is not easy because it is an underwater operation, and it is not easy to treat water pollution and manage the soil discharge site. Therefore, it is extremely difficult to remove the mound.

水深が深い場所にマウンドを築造する場合には、盛
り上げる土砂等の量が多くなり、裾地も広がるため、マ
ウンドの築造に多くの時間と経費を要する。
When building a mound in deep water, the amount of earth and sand that heaps up increases and the skirts also spread, so it takes a lot of time and money to build the mound.

本発明は、上記の点に鑑み提案されたもので、その目
的とするところは、たとえ水深が深い場所に作業台船用
のマウンドを築造する場合であっても、そのマウンドを
短時間で、しかも少ない施工費用で築造でき、かつマウ
ンドの面積の増減,維持管理および撤去作業とも容易に
行い得るコンクリート構造物の製作方法を提供すること
にある。
The present invention has been proposed in view of the above points, and its purpose is to build a mound for a work pontoon in a place where the water depth is deep, in a short time, and It is an object of the present invention to provide a method for producing a concrete structure which can be constructed at a low construction cost and which can easily perform the increase / decrease in the area of the mound, maintenance and removal work.

(課題を解決するための手段) 前記目的を達成するため、本発明では水底BWに、複数
個のコンクリートブロックまたは土砂をセグメントで固
化したブロックあるいは浮沈ブロック2を所定の間隔を
おいて設置し、前記ブロック2の列上に、鋼材3a,3bを
格子状に組みかつ連結した桁材3を配置し、前記ブロッ
ク2の列に桁材3を固定して、水中にマウンドMを築造
し、前記マウンドM上に、浮沈自在の作業台船Dを載
せ、前記作業台船D上で、コンクリート構造物Cを製作
するようにしている。
(Means for Solving the Problem) In order to achieve the above object, in the present invention, a plurality of concrete blocks or blocks obtained by solidifying earth and sand in segments or floating blocks 2 are installed at predetermined intervals on the water bottom BW, A girder material 3 in which steel materials 3a and 3b are assembled and connected in a grid shape is arranged on the row of the block 2, the girder material 3 is fixed to the row of the block 2, and a mound M is built in water. A floating work platform D is mounted on the mound M, and a concrete structure C is manufactured on the work platform D.

また、前記目的を達成するため、本発明では予め所定
の間隔をおいて配置された所定数のブロック2と、この
単位ブロック2の列の上に格子状に組まれかつブロック
2上に固定された鋼材3a,3bとにより構成された単位桁
材3とを一つのユニットaにまとめ、複数のユニットa
を連結して、前記マウンドMを築造するようにしてい
る。
In order to achieve the above-mentioned object, according to the present invention, a predetermined number of blocks 2 arranged at a predetermined interval in advance, and the unit blocks 2 are assembled in a grid on a row and fixed on the blocks 2. And the unit girder material 3 composed of the steel materials 3a and 3b are combined into one unit a to form a plurality of units a.
Are connected to build the mound M.

さらに、前記目的を達成するため、本発明では水底BW
に、複数本の杭2′を打設し、隣合う杭2′,2′を筋交
い2″により固定し、前記杭2′の列上に、鋼材を格子
状に組んだ桁材3′を載置し、杭2′に連結して、水中
にマウンドM′を築造し、前記マウンドM′上に、浮沈
自在の作業台船Dを載せ、前記作業台船D上で、コンク
リート構造物Cを製作するようにしている。
Furthermore, in order to achieve the above-mentioned object, the water bottom BW
, A plurality of piles 2'is driven, adjacent piles 2 ', 2'are fixed by bracing 2 ", and a girder 3' made up of steel material is assembled on the row of the piles 2 '. It is placed and connected to the stake 2 ′ to build a mound M ′ in water, and a floating work platform D is mounted on the mound M ′, and a concrete structure C is mounted on the work platform D. I am trying to produce.

(発明の実施の形態) 以下、本発明の実施例を図面に基づいて説明する。BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings.

第1図は本発明の第1発明の第1実施例を示すもの
で、同図(イ)は一部を破断して示した平面図、同図
(ロ)は一部縦断側面図である。
FIG. 1 shows a first embodiment of the first aspect of the present invention, in which FIG. 1 (a) is a partially cutaway plan view, and FIG. 1 (b) is a partially longitudinal side view. .

この第1図に示す第1実施例では、水底BW上に砂や捨
石1等を敷き均し、その上に作業台船用のマウンドMを
築造する。
In the first embodiment shown in FIG. 1, sand, rubble stones 1 and the like are spread on the bottom BW of the water, and a mound M for a work pontoon is built on it.

前記マウンドMは、複数個のブロック2と、格子状に
組んだ桁材3とで構築されている。
The mound M is constructed by a plurality of blocks 2 and girder members 3 assembled in a grid pattern.

前記ブロック2には、コンクリートブロック,土砂を
セメントで固化したブロックのいずれを用いてもよい。
また、前記ブロック2としてコンクリート製または/お
よび鋼製で中空のブロックを用い、ポンプ(図示せず)
を介してブロック内部に注排水し、浮沈させることが可
能な、いわゆる浮沈ブロックを用いてもよい。前記複数
個のブロック2を、砂や捨石1等を敷き均した上に、所
定の間隔をおいて設置する。
The block 2 may be either a concrete block or a block obtained by solidifying earth and sand with cement.
Further, a concrete (or / and steel) hollow block is used as the block 2, and a pump (not shown) is used.
It is also possible to use a so-called floating / sinking block, which is capable of being poured and drained into the inside of the block through the to make it float and sink. The plurality of blocks 2 are laid on sand, rubble stones 1 and the like, and placed at predetermined intervals.

前記桁材3は、鋼材3a,3bを格子状に組んで形成され
ている。前記鋼材3a,3bには、例えばH型鋼を用いる。
そして、前記鋼材3aを各ブロック2の上面の中央部に配
置して固定し、前記鋼材3aの列と直交する方向に鋼材3b
を配列しかつ連結する。
The girder material 3 is formed by assembling steel materials 3a and 3b in a grid pattern. For example, H-shaped steel is used for the steel materials 3a and 3b.
Then, the steel material 3a is arranged and fixed at the central portion of the upper surface of each block 2, and the steel material 3b is arranged in a direction orthogonal to the row of the steel material 3a.
Are arranged and connected.

このように、複数本ずつの鋼材3aおよび鋼材3bを格子
状に組みかつ連結した桁材3をブロック2の列上に配置
し、その桁材3をブロック2の列上に固定し、水中にマ
ウンドMを築造する。
In this way, the girder material 3 in which a plurality of steel materials 3a and steel materials 3b are assembled and connected in a grid pattern is arranged on the row of the block 2, and the girder material 3 is fixed on the row of the block 2 and submerged in water. Build Mound M.

また、この第2実施例では例えば縦横2個ずつのブロ
ック2と、この単位ブロック2の列上に固定された単位
桁材3とを一つのユニットaにまとめている。前記単位
桁材3は、鋼材3bと鋼材3aとを格子状に組まれ,単位ブ
ロック2上に配置されかつ固定された部分により構成さ
れている。そして、複数のユニットaを連結し、マウン
ドMを築造するようにしている。
Further, in the second embodiment, for example, two blocks 2 each in the vertical and horizontal directions and the unit girder member 3 fixed on the row of the unit blocks 2 are combined into one unit a. The unit girder member 3 is composed of a steel material 3b and a steel material 3a assembled in a grid pattern, arranged on the unit block 2, and fixed. Then, a plurality of units a are connected to build the mound M.

前述のごとく築造したマウンドM上に作業台船Dを載
せる。この作業台船Dは、床板4と、側部のフロート5
とを有し、浮沈自在に構成されている。
The work platform ship D is placed on the mound M built as described above. This work pontoon D has a floor board 4 and a float 5 on the side.
And is configured to be freely floatable.

前記作業台船D上で、通常の方法によりケーソン等の
コンクリート構造物Cを製作する。
On the work pontoon D, a concrete structure C such as a caisson is manufactured by a usual method.

前記コンクリート構造物Cを、作業台船D上に注水し
た際、自力で浮上し得る高さまで製作する。
The concrete structure C is manufactured to such a height that it can float by itself when water is poured onto the work platform ship D.

コンクリート構造物Cを所定高さまで製作した後、作
業台船Dを水面に浮かべ、所定の位置まで曳航する。そ
の後、作業台船Dを水面下に沈め、コンクリート構造物
Cを作業台船Dから分離,浮上させ、作業台船Dから取
り出す。ついで、コンクリート構造物C内に注水し、コ
ンクリート構造物Cを沈下させ、水底の所定位置に据え
付ける。
After the concrete structure C is manufactured to a predetermined height, the work pontoon D is floated on the water surface and towed to a predetermined position. Then, the work pontoon D is submerged below the water surface, the concrete structure C is separated from the work pontoon D, floated, and taken out from the work pontoon D. Then, water is poured into the concrete structure C to sink the concrete structure C, and the concrete structure C is installed at a predetermined position on the water bottom.

以上のように、この第1実施例では水底BWに複数個の
ブロック2を所定の間隔をおいて設置し、前記ブロック
2の列上に、鋼材3bと鋼材3aとを格子状に組みかつ連結
して構成された桁材3を配置し、ブロック2の列に桁材
3を固定してマウンドMを築造するようにしている。
As described above, in the first embodiment, the plurality of blocks 2 are installed on the water bottom BW at a predetermined interval, and the steel materials 3b and 3a are assembled and connected on the rows of the blocks 2 in a grid pattern. The girder members 3 configured as described above are arranged, and the girder members 3 are fixed to the rows of the blocks 2 to build the mound M.

したがって、この第1実施例では水底BW上に砂や捨石
1等を薄く敷き均すだけで足り、水中で長時間掛けて土
均しする必要がないので、たとえ水深の深い場所にマウ
ンドMを築造する場合であっても、そのマウンドMを短
時間で、かつ少ない施工費用で築造することができる。
Therefore, in the first embodiment, it is sufficient to lay sand or rubble stones 1 thinly on the bottom BW, and it is not necessary to lay it in water for a long time, so even if the mound M is deep in a deep water place. Even in the case of building, the mound M can be built in a short time and at a low construction cost.

また、マウンドMの面積の増減を図る場合には、設置
するブロック2の個数を増減させ、ブロック2の列上に
格子状の桁材3を継ぎ足しまたは取り外すだけでよく、
新たに盛土してマウンドを拡張したり、盛土して築いた
マウンドを削ったりする必要がないので、マウンドMの
面積を容易に増減することができる。
Further, in order to increase or decrease the area of the mound M, it is sufficient to increase or decrease the number of blocks 2 to be installed, and add or remove the grid-shaped girder members 3 on the rows of the blocks 2,
Since it is not necessary to newly fill the mound to expand the mound or to cut the mound built by the embankment, the area of the mound M can be easily increased or decreased.

さらに、マウンドMのブロック2が水で流されること
が殆どなく、かつ水の流れで侵食されることもないの
で、マウンドMの維持管理も容易に行うことができる。
Further, since the block 2 of the mound M is hardly washed with water and is not eroded by the water flow, the mound M can be easily maintained and managed.

しかも、マウンドMを撤去する場合には、ブロック2
の列上から桁材3を外し、ブロック2を引き上げればよ
く、水底BW上に盛り上げ,固めた土砂等を水中で除去す
る必要がないので、撤去作業を容易に行うことができる
ほか、水の汚濁処理を省略することも可能である。
Moreover, when removing Mound M, block 2
It is only necessary to remove the girder material 3 from the top of the row and pull up the block 2, and there is no need to remove the solidified sand and the like that have been piled up on the water bottom BW and solidified in water. It is also possible to omit the pollution treatment.

さらには、第1図(イ)に仮想線で囲んで示すよう
に、所定数のブロック2と、この単位ブロック2の列の
上に格子状に組んで固定された単位桁材3とを一つのユ
ニットaにまとめ、その複数のユニットaを連結してマ
ウンドMを築造することにより、マウンドMをより一層
短時間でかつ少ない施工費用で構築できるし、マウンド
Mの面積の増減や、撤去作業をより一層短時間で行うこ
とができる。
Further, as shown in FIG. 1A by being surrounded by imaginary lines, a predetermined number of blocks 2 and unit beam members 3 fixed in a grid on the rows of the unit blocks 2 are combined. The mound M can be constructed in a shorter time and at a low construction cost by combining the plurality of units a into one unit a and connecting the plurality of units a to each other. Can be performed in an even shorter time.

次に、第2図は本発明の第2発明の実施例を示すもの
で、同図(イ)は一部を破断して示した平面図、同図
(ロ)は一部縦断側面図である。
Next, FIG. 2 shows an embodiment of the second invention of the present invention. FIG. 2 (A) is a partially cutaway plan view, and FIG. 2 (B) is a partially longitudinal side view. is there.

この第2図に示す実施例では、複数本の杭2′と、格
子状に組んだ桁材3′とによりマウンドM′を築造して
いる。
In the embodiment shown in FIG. 2, a mound M'is constructed by a plurality of piles 2'and a girder member 3'assembled in a grid pattern.

前記杭2′には、鋼材による柱状のものを用いる。こ
の杭2′を複数本、それぞれ水底BWに打ち込み、互いに
所定の間隔をおいて立設する。そして、隣合う杭2′,
2′を筋交い2″により固定する。
The pile 2'is made of steel and has a columnar shape. A plurality of these piles 2'are driven into the water bottom BW, respectively, and are erected at predetermined intervals. And adjacent piles 2 ',
Fix 2'with braces 2 ".

ついで、前記杭2′の列上に、桁材3′を載置し、杭
2′に固定する。この桁材3′も鋼材を縦横に組み、格
子状に形成する。
Then, the girder material 3'is placed on the row of the piles 2'and fixed to the piles 2 '. This girder material 3'is also made by assembling steel materials vertically and horizontally to form a lattice.

この実施例の他の構成は、前記第1発明の第1実施例
と同様ある。
The other structure of this embodiment is the same as that of the first embodiment of the first invention.

そして、この実施例では水底BWに複数本の杭2′を打
ち込んでマウンドM′を築造しているので、水底BWに砂
や捨石1等を敷いて均す必要が全くなく、マウンドを築
くための水中での作業をより一層少なくなし得る。ま
た、杭2′を打ち込んで築造しているため、安定性がよ
く、例えば台風等により大波が発生し、水が激しく流れ
るような状態下においても、マウンドM′の設置位置が
ずれない。したがって、マウンドM′をより一層容易に
維持管理することができる。
In this embodiment, since a plurality of piles 2'is driven into the water bottom BW to build the mound M ', there is no need to spread sand or rubble 1 etc. on the water bottom BW to level the mound. Can be done even less underwater. Further, since the piles 2'are struck and constructed, the stability is good, and the installation position of the mound M'will not be displaced even in a state where a large wave is generated due to a typhoon or the like and water flows violently. Therefore, the mound M ′ can be more easily maintained and managed.

この実施例の他の作用については、前記第1発明の実
施例と同様である。
Other functions of this embodiment are similar to those of the first embodiment of the present invention.

(発明の効果) 以上説明したように、本発明の特許請求の範囲第1項
記載の第1発明では、水底BWに複数個のブロック2を所
定の間隔をおいて設置し、前記ブロック2の列上に、鋼
材3aと鋼材3bを格子状に組みかつ連結して構成された桁
材3を配置し、ブロック2の列に桁材3を固定してマウ
ンドMを築造するようにしているので、水底BW上に砂や
捨石1等を薄く敷き均すだけで足り、水中で長時間掛け
て土均しする必要がないので、たとえ水深の深い場所に
マウンドMを築造する場合であっても、そのマウンドM
を短時間で、かつ少ない施工費用で築造するし得る効果
がある。また、本発明によればマウンドMの面積の増減
を図る場合には、設置するブロック2の個数を増減さ
せ、ブロック2の列上に格子状の桁材3を継ぎ足しまた
は取り外すだけでよく、新たに盛土してマウンドを拡張
したり、盛土して築いたマウンドを削ったりする必要が
ないので、マウンドMの面積を容易に増減し得る効果が
ある。さらに、本発明によればマウンドMのブロック2
が水で流されることが殆どなく、かつ水の流れで侵食さ
れることもないので、マウンドMの維持管理も容易に行
い得る効果があり、マウンドMを撤去する場合には、ブ
ロック2の列上から桁材3を外し、ブロック2を引き上
げればよく、水底BW上に盛り上げ,固めた土砂等を水中
で除去する必要がないので、撤去作業を容易に行い得る
効果を有する外、水の汚濁処理を省略し得る効果もあ
る。
(Effect of the invention) As described above, in the first invention described in the first aspect of the present invention, a plurality of blocks 2 are installed on the water bottom BW at predetermined intervals, and Since the girder material 3 constructed by assembling and connecting the steel materials 3a and 3b in a lattice shape is arranged on the row, and the girder material 3 is fixed to the row of the block 2 to build the mound M. , It is enough to lay sand or rubble 1 thinly on the bottom of the water BW, and it is not necessary to lay it in water for a long time, so even if the mound M is built in a deep water place. , That mound M
There is an effect that can be built in a short time and at a low construction cost. Further, according to the present invention, in order to increase or decrease the area of the mound M, it suffices to increase or decrease the number of blocks 2 to be installed and add or remove the grid-shaped girder members 3 on the rows of the blocks 2. Since there is no need to fill the ground to expand the mound or cut the mound built to fill, the area of the mound M can be easily increased or decreased. Furthermore, according to the invention, block 2 of mound M
Is almost never washed away with water, and is not eroded by the flow of water, so there is an effect that the maintenance of the mound M can be easily performed. When removing the mound M, the row of block 2 It suffices to remove the girder material 3 from the top and pull up the block 2, and it is not necessary to remove the solidified sand and the like that has been piled up on the bottom BW of the water and solidified in water, so that the removal work can be easily performed. There is also an effect that the pollution treatment can be omitted.

また、予め所定の間隔をおいて配置された所定数のブ
ロック2と、この単位ブロック2の列の上に格子状に組
まれかつブロック2上に固定された鋼材3a,3bにより構
成された単位桁材3とを一つのユニットaにまとめ、複
数のユニットaを連結して、前記マウンドMを築造する
ようにしているので、マウンドMをより一層短時間でか
つ少ない施工費用で構築し得る効果があり、マウンドM
の面積の増減や、撤去作業をより一層短時間で行い得る
効果もある。
Further, a unit composed of a predetermined number of blocks 2 arranged at a predetermined interval in advance and steel materials 3a, 3b assembled in a grid on the row of the unit blocks 2 and fixed on the block 2. Since the girder member 3 and the girder member 3 are integrated into one unit a and a plurality of units a are connected to construct the mound M, the mound M can be constructed in a shorter time and at a low construction cost. There is a mound M
There is also an effect that the area can be increased or decreased and the removal work can be performed in a shorter time.

さらに、本発明の特許請求の範囲第3項記載の第2発
明では、水底BWに、複数本の杭2′を打設し、隣合う杭
2′,2′を筋交い2″により固定し、前記杭2′の列上
に、鋼材を格子状に組んだ桁材3′を載置し、杭2′に
連結して、水中にマウンドM′を築造するようにしてい
るので、水底BWに砂や捨石等を敷いて均す必要が全くな
く、マウンドを築くための水中での作業をより一層少な
くなし得る効果があり、杭2′を打ち込んで築造してい
るため、安定性がよく、例えば台風等により大波が発生
し、水が激しく流れるような状態下においても、マウン
ドM′の設置位置がずれないので、マウンドM′をより
一層容易に維持管理し得る効果もある。
Further, in the second invention according to the third aspect of the present invention, a plurality of piles 2'is placed on the water bottom BW, and adjacent piles 2 ', 2'are fixed by bracing 2 ", On the row of the piles 2 ', a girder material 3', which is a steel material assembled in a grid pattern, is placed and connected to the piles 2'to build a mound M'in the water. There is no need to lay sand or rubble stones evenly, and there is an effect that the work underwater to build the mound can be further reduced, and because the pile 2'is driven in and built, stability is good, For example, even if a large wave is generated due to a typhoon or the like, and the water flows violently, the installation position of the mound M ′ does not shift, and therefore the mound M ′ can be maintained and managed more easily.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明の第1発明の第1実施例を示すもので、
同図(イ)は一部を破断して示した平面図、同図(ロ)
は一部縦断側面図である。第2図は本発明の第2発明の
実施例を示すもので、同図(イ)は一部を破断して示し
た平面図、同図(ロ)は一部縦断側面図である。第3図
は従来の技術を示す一部縦断側面図である。 BW……水底、M……作業台船用のマウンド、2……マウ
ンドを構成しているブロック、3……同マウンドを構成
している桁材、3a,3b……桁材を構成している鋼材、a
……マウンドを構成しているユニット、D……作業台
船、C……コンクリート構造物、M′……マウンド、
2′……マウンドを構成している杭、2″……隣合う杭
を固定している筋交い、3′……マウンドを構成してい
る桁材。
FIG. 1 shows a first embodiment of the first invention of the present invention.
The same figure (a) is a partially cutaway plan view, and the same figure (b).
FIG. 3 is a partially longitudinal side view. FIG. 2 shows an embodiment of the second invention of the present invention. FIG. 2 (A) is a partially cutaway plan view, and FIG. 2 (B) is a partially longitudinal side view. FIG. 3 is a partially longitudinal side view showing a conventional technique. BW: bottom of the water, M: mound for work platform, 2 ... blocks that make up the mound, 3 ... girders that make up the mound, 3a, 3b ... make up girders Steel, a
…… Units that make up the mound, D …… table carrier, C …… concrete structure, M ′ …… mound,
2 '... Piles that make up the mound, 2 "... Brace that fixes adjacent piles, 3' ... Girder material that makes up the mound.

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】水底BWに、複数個のコンクリートブロック
または土砂をセグメントで固化したブロックあるいは浮
沈ブロック2を所定の間隔をおいて設置し、 前記ブロック2の列上に、鋼材3a,3bを格子状に組みか
つ連結した桁材3を配置し、前記ブロック2の列に桁材
3を固定して、水中にマウンドMを築造し、 前記マウンドM上に、浮沈自在の作業台船Dを載せ、 前記作業台船D上で、コンクリート構造物Cを製作す
る、 ことを特徴とするコンクリート構造物の製作方法。
1. A plurality of concrete blocks or blocks in which earth and sand are solidified by segments or floating / sink blocks 2 are installed at a predetermined interval on a water bottom BW, and steel materials 3a, 3b are arranged on the rows of the blocks 2 in a grid pattern. The girders 3 assembled and connected in a shape are arranged, the girders 3 are fixed to the row of the block 2, the mound M is built in water, and the floating work platform D is mounted on the mound M. A concrete structure C is manufactured on the work pontoon D. A method for manufacturing a concrete structure, comprising:
【請求項2】予め所定の間隔をおいて配置された所定数
のブロック2と、この単位ブロック2の列の上に格子状
に組まれかつブロック2上に固定された鋼材3a,3bとに
より構成された単位桁材3とを一つのユニットaにまと
め、複数のユニットaを連結して、前記マウンドMを築
造することを特徴とする特許請求の範囲第1項記載のコ
ンクリート構造物の製作方法。
2. A predetermined number of blocks 2 arranged at predetermined intervals in advance, and steel members 3a, 3b assembled on the row of the unit blocks 2 in a grid pattern and fixed on the blocks 2. 2. The concrete structure according to claim 1, characterized in that the unit girders 3 thus constructed are combined into one unit a and a plurality of units a are connected to build the mound M. Method.
【請求項3】水底BWに、複数本の杭2′を打設し、隣合
う杭2′,2′を筋交い2″により固定し、 前記杭2′の列上に、鋼材を格子状に組んだ桁材3′を
載置し、杭2′に連結して、水中にマウンドM′を構築
し、 前記マウンドM′上に、浮沈自在の作業台船Dを載せ、 前記作業台船D上で、コンクリート構造物Cを製作す
る、 ことを特徴とするコンクリート構造物の製作方法。
3. A plurality of piles 2 ′ are driven on the water bottom BW, and adjacent piles 2 ′, 2 ′ are fixed by bracing 2 ″, and a steel material is arranged in a grid on the row of the piles 2 ′. The assembled girder material 3'is placed and connected to the pile 2'to construct a mound M'in the water, and a floating work platform D is mounted on the mound M ', and the work platform D A concrete structure C is manufactured as described above.
JP61219686A 1986-09-19 1986-09-19 Manufacturing method of concrete structure Expired - Fee Related JP2527310B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61219686A JP2527310B2 (en) 1986-09-19 1986-09-19 Manufacturing method of concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61219686A JP2527310B2 (en) 1986-09-19 1986-09-19 Manufacturing method of concrete structure

Publications (2)

Publication Number Publication Date
JPS6378924A JPS6378924A (en) 1988-04-09
JP2527310B2 true JP2527310B2 (en) 1996-08-21

Family

ID=16739378

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61219686A Expired - Fee Related JP2527310B2 (en) 1986-09-19 1986-09-19 Manufacturing method of concrete structure

Country Status (1)

Country Link
JP (1) JP2527310B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6888608B2 (en) 1995-09-06 2005-05-03 Kabushiki Kaisha Toshiba Liquid crystal display device

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS574832A (en) * 1980-06-10 1982-01-11 Mitsui Eng & Shipbuild Co Ltd Cargo handling method
JPS58532A (en) * 1981-06-25 1983-01-05 Mitsubishi Heavy Ind Ltd Bottom landing type dredger
JPH064967B2 (en) * 1985-02-04 1994-01-19 大豊建設株式会社 Side wall open / close device for work boats

Also Published As

Publication number Publication date
JPS6378924A (en) 1988-04-09

Similar Documents

Publication Publication Date Title
US5697736A (en) Seawalls and shoreline reinforcement systems
US9644334B2 (en) Methods of and systems for controlling water flow, breaking water waves and reducing surface erosion along rivers, streams, waterways and coastal regions
CA1043581A (en) Quay structure
US5154542A (en) Earth-retaining module, system and method
US4896996A (en) Wave actuated coastal erosion reversal system for shorelines
JPH04504151A (en) Permeable breakwater
KR101053880B1 (en) Improvement structure of free fall hole or beam using geotextile and its construction method
US4998844A (en) Wave actuated coastal erosion reversal system for shorelines
JP2527310B2 (en) Manufacturing method of concrete structure
CN1233903C (en) Construction method for structure of reinforced concrete underwater
CN211815989U (en) Over-current type permeable breakwater structure
CN211447015U (en) H-shaped anti-slide pile plate wall
CN208472649U (en) A kind of Gravity Type Casisson Berth structure setting friction pile in foundation
GB1560703A (en) Marine walls
JP2001172936A (en) Ground face protection structure and construction method therefor
US20200308790A1 (en) Modular marine foundation
JP4927355B2 (en) How to build a sloping bank
JP4496532B2 (en) How to reuse the pier
RU2711973C1 (en) Hydraulic structure on vertical pile base of modular structure
US5118222A (en) Method and apparatus for constructing seawalls and docks
CN113638359B (en) Protection device for preventing coast erosion and construction process thereof
KR102624546B1 (en) Manufacturing and installation method of lightweight foam concrete buoyancy resistance interlocking pattern modular
GB2477163A (en) Flood-resistant building having a floating caisson
KR100228262B1 (en) Method of constructing marine structures
JP2519299B2 (en) Underwater civil engineering structure and its construction method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees