JP2520371B2 - Concrete floor construction method of frame wall construction method - Google Patents

Concrete floor construction method of frame wall construction method

Info

Publication number
JP2520371B2
JP2520371B2 JP5341693A JP34169393A JP2520371B2 JP 2520371 B2 JP2520371 B2 JP 2520371B2 JP 5341693 A JP5341693 A JP 5341693A JP 34169393 A JP34169393 A JP 34169393A JP 2520371 B2 JP2520371 B2 JP 2520371B2
Authority
JP
Japan
Prior art keywords
floor
wall
construction method
reinforcing bar
bar unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP5341693A
Other languages
Japanese (ja)
Other versions
JPH07158159A (en
Inventor
河合  誠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Home Co Ltd
Original Assignee
Mitsui Home Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Home Co Ltd filed Critical Mitsui Home Co Ltd
Priority to JP5341693A priority Critical patent/JP2520371B2/en
Publication of JPH07158159A publication Critical patent/JPH07158159A/en
Application granted granted Critical
Publication of JP2520371B2 publication Critical patent/JP2520371B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、枠組壁工法にて複数階
の一般住宅等を建築する場合において、上階床をコンク
リートで造床してなる枠組壁工法のコンクリート造床施
工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete floor construction method of a frame wall construction method, in which an upper floor is constructed with concrete when a general house or the like having a plurality of floors is constructed by the frame wall construction method.

【0002】[0002]

【従来の技術】従来、枠組壁工法を用いて建築した複数
階の一般住宅等は、断熱気密性の高い壁面構造で構成さ
れるため室内外の音の遮断は良好であったが、遮断され
た音振動が上下方向へ伝達され上下階の音の遮断が好ま
しくなかった。特に近年集合住宅にあっては、上下階の
音の遮断が強く望まれ、また建築基準法の改定により一
層音の遮断基準が高くなることが予想される。このよう
な事情から、近年、上階床を木造施工でなくコンクリー
ト施工によって構築し、上下階の音の遮断性を高めるこ
とが求められている。従来、このような枠組壁工法のコ
ンクリート造床施工方法においては、まず下階壁を建て
起こした後、その上面の床面部にコンクリート打設を行
って上階床を造床し、この上階床の上に上階壁を建て起
こすようにしていた。また3階以上の住宅においては、
このように上階壁を建て起こした後、同様の手順で最上
階床の造床と最上階壁の建て起こしを行なっていた。
2. Description of the Related Art Conventionally, a multi-storey general house constructed using a framed wall construction method has a good insulation of sound inside and outside because it is constructed of a wall structure with high heat insulation and airtightness. Sound vibration was transmitted in the vertical direction, and it was not desirable to block the sound from the upper and lower floors. In particular, in the case of apartment buildings in recent years, it is strongly desired to block sound from the upper and lower floors, and it is expected that the standard for sound blockage will become even higher due to the revision of the Building Standards Law. Under these circumstances, in recent years, it has been required to construct the upper floor by concrete construction instead of wooden construction so as to enhance the sound insulation of the upper and lower floors. Conventionally, in such a concrete floor construction method of the frame wall construction method, first, after erecting the lower floor, concrete placement is performed on the floor surface part of the upper surface to raise the upper floor, and this upper floor I was trying to raise the upper floor on the floor. For houses on the 3rd floor and above,
After erecting the upper floor wall in this way, the uppermost floor and the uppermost floor were constructed by the same procedure.

【0003】[0003]

【発明が解決しようとする課題】しかしながら従来のこ
のような枠組壁工法のコンクリート造床施工方法におい
ては、下階の壁を建て起こした後に建方作業を一旦中止
し、この下階壁の上面部に基礎配筋やコンクリート打設
等のコンクリート施工作業を行って上階床を造床し、そ
の後再び建方作業を開始して上階壁を建て起こしてお
り、建方作業とコンクリート施工作業という異質の作業
を交互に行っていたので、建方作業の効率が非常に悪い
という問題があった。また3階以上の住宅においては、
上階床に打設したコンクリートの乾燥を待って上階壁を
建て起こし、さらに最上階床に打設したコンクリートの
乾燥を待って最上階壁を建て起こしており、コンクリー
トの乾燥期間が再度に渡っていたので、全体の施工期間
が非常に長くなるという問題があった。
However, in the conventional concrete floor construction method of such a framed wall construction method, after the wall of the lower floor is built up, the erection work is temporarily stopped, and the upper surface of the lower floor wall is suspended. Concrete construction work such as foundation bar arrangement and concrete placement is performed on the section to build the upper floor, and then erection work is started again to erected the upper floor wall. Since different types of work were alternately performed, there was a problem that the efficiency of erection work was very poor. For houses on the 3rd floor and above,
Waiting for the concrete placed on the upper floor to dry before erection of the upper floor wall, and waiting for the concrete placed on the uppermost floor to wait for the concrete to dry up, erection of the top floor. Since there were crossings, there was a problem that the entire construction period would be extremely long.

【0004】[0004]

【課題を解決するための手段】このような従来の問題点
を解決するために本発明は、複数階の建屋を枠組壁工法
にて建築する枠組壁工法のコンクリート造床施工方法に
おいて、(a)任意の基礎床面の周囲に下階壁の建て起
こしを枠組壁工法にて行い、(b)上記下階壁の上面の
床面部に床支持部材たる仮設ビームを部屋空間を渡架し
て架設し、(c)上記仮設ビームの取付け後に、下面に
上記仮設ビームを配した上記床面部に台板を張設し、
(d)上記床面部のうち下階壁が配置された壁配置部に
鉄筋ユニットを配設すると共に、この鉄筋ユニットに連
係して複数の支持金具を配設し、(e)上記各支持金具
の上面部に上階壁を建て起こし、この上階壁と下階壁を
上記壁配置部に配設した上記鉄筋ユニットを貫通させて
連結ボルトで緊結し、(f)上記上階壁を建て起こした
後に、この上階壁の上部に屋根体の施工を行ない、
(g)上記屋根体の施工後に、上記鉄筋ユニットで囲ま
れた上記台板上にスラブ鉄筋を配筋して、上記床面部に
コンクリート打設を行なうことを特徴として構成されて
いる。
SUMMARY OF THE INVENTION In order to solve such a conventional problem, the present invention provides a concrete floor construction method of a frame wall construction method in which a building of a plurality of floors is constructed by a frame wall construction method. ) Raising the lower floor wall around the arbitrary foundation floor surface by the frame wall construction method, and (b) laying a temporary beam as a floor support member across the room space on the floor surface on the upper surface of the lower floor wall. And (c) after attaching the temporary beam, a base plate is stretched on the floor surface portion where the temporary beam is arranged on the lower surface,
(D) A reinforcing bar unit is arranged in the wall arrangement portion where the lower floor is arranged in the floor surface section, and a plurality of supporting metal fittings are arranged in association with the reinforcing bar unit, and (e) each supporting metal fitting is arranged. An upper floor wall is erected on the upper surface of the upper floor wall, and the upper floor wall and the lower floor wall are penetrated through the reinforcing bar unit arranged in the wall arrangement portion and tightly connected with a connecting bolt, and (f) the upper floor wall is built. After raising it, we will construct a roof on the upper floor wall,
(G) After the roof is constructed, slab reinforcing bars are arranged on the base plate surrounded by the reinforcing bar units, and concrete is placed on the floor surface.

【0005】さらに本発明は、上記上階壁を建て起こし
た後に、この上階壁の上部に更に最上階壁を上記上階壁
と同様の手順によって建て起こし、この最上階壁の上部
に屋根体の施工を行ない、その後で上記各階の台板上に
上記スラブ鉄筋の配筋を行なうことを特徴として構成さ
れている。
Further, according to the present invention, after the upper floor wall is erected, the uppermost floor wall is further erected on the upper portion of the upper floor wall by the same procedure as the upper floor wall, and the roof is formed on the upper portion of the upper floor wall. The body is constructed, and then the slab reinforcement is arranged on the base plate of each floor.

【0006】さらにまた本発明は、上記各支持金具を上
部材と下部材から構成して分割自在とし、この下部材を
上記壁配置部の上記台板上に固定し、該下部材を内部に
連係させて上記鉄筋ユニットを配設し、その後上記上部
材を上記鉄筋ユニットを抱持するように上記下部材に連
結させ、各支持金具をその上面部を上記鉄筋ユニットの
上面より上方において互いに面一状とし、次いで、上記
上階壁を上記各支持金具の上部材に載置すると共に、こ
の上部材を上階壁に締結して、上階壁の建て起こしを行
なうことを特徴として構成されている。
Still further, according to the present invention, each of the above-mentioned supporting fittings is composed of an upper member and a lower member and is made separable, and the lower member is fixed on the base plate of the wall arrangement portion, and the lower member is internally provided. The reinforcing bar unit is arranged in a linked manner, and then the upper member is connected to the lower member so as to embrace the reinforcing bar unit, and the upper surface portions of the respective support fittings face each other above the upper surface of the reinforcing bar unit. Then, the upper floor wall is placed on the upper member of each of the supporting brackets, and the upper member is fastened to the upper floor wall to raise the upper floor wall. ing.

【0007】しかも本発明は、上記各支持金具を上部材
と下部材から構成して分割自在とすると共に、この支持
金具に高さ調整機構を設け、この下部材を上記壁配置部
の上記台板上に固定し、該下部材を内部に連係させて上
記鉄筋ユニットを配設し、その後上記上部材を上記鉄筋
ユニットを抱持するように上記下部材に連係させると共
に、上記高さ調整機構により上記支持金具の高さを調整
し、各支持金具をその上面部を上記鉄筋ユニットの上面
より上方において互いに面一状とし、次いで、上記上階
壁を上記各支持金具の上部材に載置すると共に、この上
部材を上階壁に締結して、上階壁の建て起こしを行なう
ことを特徴として構成されている。
Further, according to the present invention, each of the above-mentioned support fittings is composed of an upper member and a lower member and is separable, and a height adjusting mechanism is provided on the support fittings, and the lower member is mounted on the base of the wall arrangement portion. The reinforcing member is fixed on a plate, the lower member is linked to the inside, and the reinforcing bar unit is arranged. Then, the upper member is linked to the lower member so as to hold the reinforcing bar unit, and the height adjusting mechanism is also provided. Adjust the height of the above-mentioned supporting metal fittings so that the upper surface portions of the respective supporting metal fittings are flush with each other above the upper surface of the reinforcing bar unit, and then the upper floors are placed on the upper members of the respective supporting metal fittings. In addition, the upper member is fastened to the upper floor wall to raise the upper floor wall.

【0008】しかもまた本発明は、上記各支持金具を上
記壁配置部の上記台板上に固定し、この支持金具を両側
方から挟むように上記鉄筋ユニットを配設すると共に、
この鉄筋ユニットを連結し、各支持金具をその上面部を
上記鉄筋ユニットの上面より上方において互いに面一状
とし、次いで、上記上階壁を上記各支持金具の上部に載
置すると共に、この支持金具を上階壁に締結して、上階
壁の建て起こしを行なうことを特徴として構成されてい
る。
Further, according to the present invention, each of the support fittings is fixed on the base plate of the wall arrangement portion, and the reinforcing bar unit is arranged so as to sandwich the support fittings from both sides.
The reinforcing bar units are connected to each other, and the upper surfaces of the supporting brackets are flush with each other above the upper surface of the reinforcing bar unit, and then the upper floor is placed on the upper parts of the supporting brackets and the supporting members are supported. It is configured by fastening metal fittings to the upper floor wall to raise the upper floor wall.

【0009】また本発明は、上記下階壁の上縁に切欠き
部を形成すると共に、上記仮設ビームをその端部を上記
切欠き部に当接させるように上記下階壁間に架設し、あ
るいは上記下階壁の上端部にビーム受具を載置すると共
に、上記仮設ビームをその端部を上記ビーム受具側面の
突出片に当接させるように上記下階壁間に架設して、上
記仮設ビームの取付けを行なうことを特徴として構成さ
れている。
According to the present invention, a notch is formed at the upper edge of the lower floor, and the temporary beam is installed between the lower walls so that the end of the temporary beam abuts the notch. Alternatively, the beam receiver is placed on the upper end of the lower floor, and the temporary beam is installed between the lower walls so that the end of the temporary beam is brought into contact with the protruding piece on the side surface of the beam receiver. The above-mentioned temporary beam is attached.

【0010】[0010]

【実施例】以下、本発明の枠組壁工法のコンクリート造
床施工方法の一実施例について図面を参照して詳細に説
明する。図1は本実施例の建屋全体の縦断面図、図2は
下階壁への仮設ビーム取付け後の全体斜視図、図3は図
2への台板等取付け後の要部斜視図である。これら各図
において本実施例は、複数階の一般住宅等を枠組壁工法
にて建築するものであって、下階壁2の建て起こし後、
この下階壁2の上面の床面部15に台板6や支持金具1
0等を設け、この支持金具10の上面部に上階壁3を建
て起こし、その後上記床面部15にコンクリート打設を
行なうものである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the concrete floor construction method of the frame wall construction method of the present invention will be described in detail below with reference to the drawings. 1 is a vertical cross-sectional view of the entire building of the present embodiment, FIG. 2 is an overall perspective view after attaching a temporary beam to a lower floor, and FIG. 3 is a perspective view of essential parts after attaching a base plate and the like to FIG. . In each of these drawings, this embodiment is for constructing a general house or the like on a plurality of floors by a framed wall construction method, and after the lower floor 2 is constructed,
The floor plate 15 on the upper surface of the lower floor 2 has a base plate 6 and a support metal 1
0, etc. are provided, the upper floor 3 is built up on the upper surface of the support fitting 10, and then the floor surface 15 is concrete-cast.

【0011】まず本実施例の概要について説明し、その
後各要部の詳細を説明する。任意の基礎床面1の周囲
に、図2に示すように、下階壁2の建て起こしを枠組壁
工法にて行い、上記下階壁2の上面の床面部15に床支
持部材たる仮設ビーム5を部屋空間を渡架して取付け
る。すなわち建屋基礎の上部に基礎床板を張設して構成
した基礎床面1の周囲に、複数のパネル板を枠組壁工法
により枠組して下階壁2を建て起こす。この下階壁2を
建て起こすことによりその上部空間たる床面部15が形
成され、この床面部15に上階床の支持部材たる上記仮
設ビーム5を複数並設する。これら各仮設ビーム5の取
付けは、下階壁2を建て起こして形成した下階の部屋空
間を渡架するように、上記下階壁2の各壁面に架設して
行う。
First, an outline of this embodiment will be described, and then the details of each main part will be described. As shown in FIG. 2, the lower floor 2 is erected around an arbitrary foundation floor 1 by a frame wall construction method, and the floor beam 15 on the upper surface of the lower floor 2 is a temporary beam serving as a floor support member. Install 5 across the room space. That is, a plurality of panel boards are framed by a frame wall construction method around the foundation floor surface 1 formed by stretching the foundation floor board on the upper part of the building foundation, and the lower floor 2 is erected. By erecting the lower floor wall 2, a floor surface portion 15 that is an upper space thereof is formed, and a plurality of temporary beams 5 that are support members for the upper floor are arranged in parallel on the floor surface portion 15. Each of these temporary beams 5 is attached to each wall of the lower floor 2 so as to bridge the room space of the lower floor formed by erecting the lower wall 2.

【0012】上記仮設ビーム5の取付け後に、図3に示
すように、下面に仮設ビーム5を配した上記床面部15
に上記台板6を張設する。上記台板6は方形状の板材
で、これを下階層の略全面を覆うように上記仮設ビーム
5の上面及び上記下階壁2の上面に載置してコンクリー
ト打設用の底型枠とする。また上記台板6の一部を上記
下階壁2の一側面から屋外側に突出状させ、バルコニー
部7を形成する。またこのように張設した上台板6の全
周端部に、横長の方形板たる型枠8を垂直状に取付け
る。
After the temporary beam 5 is attached, as shown in FIG. 3, the floor portion 15 having the temporary beam 5 on the lower surface is arranged.
The base plate 6 is stretched over. The base plate 6 is a rectangular plate material, which is placed on the upper surface of the temporary beam 5 and the upper surface of the lower floor 2 so as to cover substantially the entire surface of the lower floor, and serves as a bottom formwork for concrete pouring. To do. Further, a part of the base plate 6 is projected outward from one side surface of the lower floor wall 2 to form a balcony portion 7. Further, a frame 8 which is a horizontally long rectangular plate is vertically attached to the entire peripheral end portion of the upper base plate 6 thus stretched.

【0013】上記床面部15のうち下階壁2が設置され
た壁配置部16には、図4に示すように、鉄筋ユニット
9を配設すると共に、この鉄筋ユニット9に連係して複
数の支持金具10,10を配設し、これら各支持金具1
0の上面部を上記鉄筋ユニット9の上面より少なくとも
同等以上に設置してなる。上記鉄筋ユニット9は複数の
鉄筋を連係して角筒状の内部空間を形成するようにされ
たもので、これを上記壁配置部16において上記台板6
の上部に載置し、上記した配設をなさしめる。
As shown in FIG. 4, a reinforcing bar unit 9 is arranged in the wall arranging part 16 of the floor surface part 15 on which the lower floor wall 2 is installed, and a plurality of reinforcing bar units 9 are linked to each other. Supporting metal fittings 10 and 10 are provided, and each of these supporting metal fittings 1
The upper surface portion of 0 is installed at least equal to or more than the upper surface of the reinforcing bar unit 9. The rebar unit 9 is configured so that a plurality of rebars are linked to each other to form a rectangular tube-shaped internal space.
Place it on the upper part of the above and complete the above arrangement.

【0014】一方、上記各支持金具10は上部材12及
び下部材11から分割自在に構成されたもので、この下
部材11を上記壁配置部16の上部の上記台板6上に固
定し、該下部材2を内部に連係させて上記鉄筋ユニット
9を配設し、その後の上部材12を上記鉄筋ユニット9
を抱持するように下部材11に連結させる。これら各支
持金具10は、設置した状態において、その上面部が上
記鉄筋ユニット9の上面において互いに面一状となるよ
うにされる。また上記各支持金具10は、図11に示す
ように、高さ調整機構10aを有するものとして構成
し、鉄筋ユニット9への連係後、支持金具10全体の高
さを調整するようにしてもよい。あるいは、図12に示
すように、各支持金具10を一体ものとして形成してこ
れを上記台板6上に固定し、この支持金具10を両側方
から挟むように上記鉄筋ユニット9を配設して、連結し
てもよい。
On the other hand, each of the support fittings 10 is composed of an upper member 12 and a lower member 11 which are separable, and the lower member 11 is fixed on the base plate 6 above the wall arrangement portion 16, The lower member 2 is linked to the inside to dispose the rebar unit 9, and then the upper member 12 is connected to the rebar unit 9.
Is connected to the lower member 11 so as to embrace. In the installed state, the upper surfaces of the respective support fittings 10 are flush with each other on the upper surface of the reinforcing bar unit 9. Further, each of the support fittings 10 may be configured to have a height adjusting mechanism 10a as shown in FIG. 11, and the height of the entire support fitting 10 may be adjusted after being linked to the reinforcing bar unit 9. . Alternatively, as shown in FIG. 12, each support fitting 10 is integrally formed and fixed on the base plate 6, and the reinforcing bar unit 9 is arranged so as to sandwich the support fitting 10 from both sides. And may be connected.

【0015】上記支持金具10の上面部に上階壁3を建
て起こし、図5に示すように、この上階壁3と上記下階
壁2を上記壁配置部16に配設された上記鉄筋ユニット
9を貫通させて連結ボルト13で緊結する。すなわち上
記上階壁3を上記支持金具10に載置し釘等により締結
して建て起こし、この上階壁3と上記下階壁2とを、そ
の長手方向の複数箇所において上記鉄筋ユニット9に貫
通させた連結ボルト13により締結して、上記した緊結
をなさしめる。
An upper floor wall 3 is erected on the upper surface of the support fitting 10 and, as shown in FIG. 5, the upper floor wall 3 and the lower floor wall 2 are provided with the reinforcing bars arranged in the wall arrangement portion 16. The unit 9 is penetrated and tightly connected with the connecting bolt 13. That is, the upper floor wall 3 is placed on the support metal fitting 10 and fastened with nails or the like to be erected, and the upper floor wall 3 and the lower floor wall 2 are attached to the reinforcing bar unit 9 at a plurality of positions in the longitudinal direction. It is fastened with the connecting bolts 13 penetrating therethrough to complete the above-mentioned tight connection.

【0016】上記上階壁3を建て起こした後に、この上
階壁3の上部に屋根体20の施工を行ない、その後に上
記台板6上に上記スラブ鉄筋14の配筋を行なう。また
3階以上の建屋においては、上階壁3を建て起こした後
に、この上階壁3の上部に更に上階壁3を上記上階壁3
と同様の手順によって建て起こして最上階壁とし、この
最上階壁の上部に屋根体20の施工を行ない、その後で
上記各階の台板6上に上記スラブ鉄筋14の配筋を行な
うようにしてもよい。このように各上階の床面部15に
コンクリート4を打設した後、コンクリート4を乾燥さ
せ、下階側より上記仮設ビーム5を取外して、コンクリ
ート造床施工を完了する。
After the upper floor wall 3 is erected, the roof body 20 is installed on the upper floor wall 3, and then the slab reinforcement 14 is laid on the base plate 6. In the case of a building with three or more floors, after the upper floor wall 3 is raised, the upper floor wall 3 is further provided with an upper floor wall 3 above the upper floor wall 3.
The same procedure is used to build up the top floor wall, the roof body 20 is installed on the top floor wall, and then the slab reinforcement 14 is laid on the base plate 6 of each floor. Good. After the concrete 4 has been cast on the floor surface portion 15 of each upper floor in this way, the concrete 4 is dried and the temporary beam 5 is removed from the lower floor side to complete the concrete floor construction.

【0017】上記説明した本実施例の造床施工における
要部詳細について以下説明する。まず上記仮設ビーム5
の取付けについて説明する。この仮設ビーム5は、図6
に示すように、部屋空間と略同一幅とされたトラス状の
ビーム本体5aと該ビーム本体5aの両端部たる載置部
5bから構成されており、この載置部5bを上記下階壁
2の上縁に形成された切欠き部2aに当接させるよう
に、上記下階壁2に架設して上記取付けがなされてい
る。このように取付けられた上記仮設ビーム5は、その
上面を上記下階壁2の上面と略面一とされている。また
この仮設ビーム5は、その両端の載置部5bを長手方向
にスライド自在とされており、この載置部5bのスライ
ド動作によって上記下階壁2から取外し自在とされてい
る。また上記仮設ビーム5は図10に示すように取付け
られてもよい。すなわち上記下階壁2上端部に切欠き部
2aを形成することなくビーム受具17を載置させ、上
記仮設ビーム5をその載置部5bをこのビーム受具17
の側面に形成された突出片に当接させるように上記下階
壁2に架設してもよい。
The details of the main parts in the floor construction of this embodiment described above will be described below. First, the temporary beam 5
The mounting will be described. This temporary beam 5 is shown in FIG.
As shown in FIG. 2, the beam main body 5a has a truss-like shape having substantially the same width as the room space, and the mounting portions 5b that are both ends of the beam main body 5a. The lower floor wall 2 is installed so as to be in contact with the cutout portion 2a formed on the upper edge of the lower floor wall 2. The temporary beam 5 thus mounted has its upper surface substantially flush with the upper surface of the lower floor wall 2. The temporary beams 5 are slidable in the mounting portions 5b at both ends in the longitudinal direction, and can be detached from the lower floor 2 by sliding operation of the mounting portions 5b. Further, the temporary beam 5 may be attached as shown in FIG. That is, the beam receiver 17 is placed on the upper end portion of the lower floor 2 without forming the notch 2a, and the temporary beam 5 is placed on the placing portion 5b.
It may be installed on the lower floor 2 so as to abut on the protruding piece formed on the side surface of the lower floor 2.

【0018】次に上記鉄筋ユニット9と上記各支持金具
10について説明する。上記鉄筋ユニット9は、図8・
9に示すように、上記壁配置部16と略同一の幅及び高
さとされ、この壁配置部16の略全長に渡り配設されて
いる。この鉄筋ユニット9に連係される上記複数の支持
金具10,10は上記したように下部材11と上部材1
2とから分割自在に構成されるもので、上記鉄筋ユニッ
ト9の複数箇所に設置されている。上記支持金具10の
下部材11は、上記下階壁2と略同一幅の長方形の底部
材11aと該底部材11aの上面に略垂直状に取付けら
れた連係部材11bとから構成されている。また連係部
材11bには上面に開放する切欠き部が複数形成されて
いる。
Next, the reinforcing bar unit 9 and the support fittings 10 will be described. The reinforcing bar unit 9 is shown in FIG.
As shown in FIG. 9, the wall arranging portion 16 has substantially the same width and height, and is arranged over substantially the entire length of the wall arranging portion 16. As described above, the plurality of support fittings 10, 10 linked to the reinforcing bar unit 9 include the lower member 11 and the upper member 1.
It is configured so that it can be divided into two parts, and is installed at a plurality of positions of the reinforcing bar unit 9. The lower member 11 of the support fitting 10 is composed of a rectangular bottom member 11a having substantially the same width as the lower floor 2 and a linking member 11b mounted on the upper surface of the bottom member 11a in a substantially vertical shape. Further, the linking member 11b is formed with a plurality of notches that are open to the upper surface.

【0019】この下部材11と連係する上部材12は、
縦断面を上向きコ字状とする壁受部材12aと上記連係
部材11bに対して直交するように上記壁受部材12a
の下面に垂直状に取付けられた複数の連係部材12b,
12bとから構成されている。また各連係部材12bに
は上記連係部材11bに対応する切欠き部が形成されて
おり、これら下部材11と上部材12は互いの切欠き部
を介して連係自在とされている。そして上記上階壁3を
上記支持金具10の上部材12に載置すると共に、この
上部材12を上階壁3に釘を用いて締結して上階壁3の
建て起こしを行なう。
The upper member 12 linked with the lower member 11 is
The wall receiving member 12a having a U-shaped vertical cross section and the wall receiving member 12a so as to be orthogonal to the linking member 11b.
A plurality of link members 12b vertically attached to the lower surface of the
12b and. Further, each linking member 12b is formed with a notch corresponding to the linking member 11b, and the lower member 11 and the upper member 12 can be linked through the notch. Then, the upper floor wall 3 is placed on the upper member 12 of the support fitting 10, and the upper member 12 is fastened to the upper floor wall 3 by using a nail to raise the upper floor wall 3.

【0020】また上記各支持金具10を高さ調整機構1
0aを有するものとして構成した場合について、図11
を用いて説明する。すなわち各支持金具10の下部材1
1は底部材11aの上面略中央に丸棒11cが突出状に
設けられて構成されており、この丸棒11cの上部にね
じ山部を形成されると共に、このねじ山部にナットを締
結固定されている。また上記下部材11と連係する上部
材12は壁受部材12aの下面略中央に短円筒12cが
突出状に設けられて構成されている。これら下部材11
と上部材12とは、上記短円筒12cの内部に上記丸棒
11cを挿通され連係自在されると共に、ナットの締結
位置調整により任意の高さ調整自在とされている。そし
て上記上階壁3を上記支持金具10の上部材12に載置
すると共に、この上部材12を上階壁3に釘を用いて締
結して上階壁3の建て起こしを行なう。
Further, each of the above-mentioned supporting fittings 10 is attached to the height adjusting mechanism 1
FIG. 11 shows a case of being configured as having 0a.
Will be explained. That is, the lower member 1 of each support fitting 10
1, a round bar 11c is provided in a projecting shape substantially at the center of the upper surface of a bottom member 11a. A thread portion is formed on the upper portion of this round bar 11c, and a nut is fastened and fixed to this thread portion. Has been done. Further, the upper member 12 linked to the lower member 11 is configured by providing a short cylinder 12c in a protruding shape at a substantially lower surface of a wall receiving member 12a. These lower members 11
The upper member 12 and the upper member 12 can be freely linked by inserting the round rod 11c into the short cylinder 12c and adjusting the fastening position of the nut. Then, the upper floor wall 3 is placed on the upper member 12 of the support fitting 10, and the upper member 12 is fastened to the upper floor wall 3 by using a nail to raise the upper floor wall 3.

【0021】次に上記各支持金具10を一体とし、上記
配筋ユニット9を分割自在とした場合について、図12
を用いて説明する。この場合には一体として形成した上
記各支持金具10を上記台板6上に固定した後、予め適
宜の長さに分割された上記鉄筋ユニット9を、上記固定
した支持金具10を両側方から挟むように配設して連結
部9aを溶接等により締結する。そして上記上階壁3を
上記支持金具10の上部に載置すると共に、この支持金
具10を上階壁3に釘を用いて締結して上階壁3の建て
起こしを行なう。
Next, FIG. 12 shows a case where the above-mentioned respective support fittings 10 are integrated and the above-mentioned bar arrangement unit 9 can be divided.
Will be explained. In this case, after fixing each supporting metal fitting 10 integrally formed on the base plate 6, the rebar unit 9 divided in advance to an appropriate length is sandwiched by the fixed supporting metal fitting 10 from both sides. Thus, the connecting portion 9a is fastened by welding or the like. Then, the upper floor wall 3 is placed on the upper portion of the support metal fitting 10, and the support metal fitting 10 is fastened to the upper floor wall 3 by using a nail to raise the upper floor wall 3.

【0022】また上階壁3の建て起こしについて説明す
る。上記複数の支持金具10の上面に上階壁3を載置す
ると共に、図9に示すように、この上階壁3と上記下階
壁2とを上記鉄筋ユニット9を貫通した複数の連結ボル
ト13,13にて緊結する。すなわち上記上階壁3を上
記支持金具10の上部材12の壁受部材12a上面に載
置すると共に、この壁受部材12aの側壁を貫通する釘
によって支持金具10と締結する。上記上階壁3を構成
する複数のパネル板は、図5に示すように、方形枠内部
に複数の縦材を並設しその両側面に板材を張設して構成
されるもので、この板材の張設前あるいは片側面に張設
した状態で上記した建て起こしを行ない、上記連係ボル
ト13の締結後に他の板材を張設する。
The raising of the upper floor wall 3 will be described. The upper floor wall 3 is placed on the upper surfaces of the plurality of support fittings 10 and, as shown in FIG. 9, the plurality of connecting bolts that penetrate the upper floor wall 3 and the lower floor wall 2 through the reinforcing bar unit 9. Tighten at 13, 13. That is, the upper floor 3 is placed on the upper surface of the wall receiving member 12a of the upper member 12 of the support fitting 10 and is fastened to the support fitting 10 by a nail penetrating the side wall of the wall receiving member 12a. As shown in FIG. 5, the plurality of panel plates constituting the upper floor wall 3 are formed by arranging a plurality of vertical members in parallel inside the rectangular frame and stretching plate members on both side surfaces thereof. Before the plate material is stretched or in a state where it is stretched on one side surface, the above-described raising and lowering is performed, and after the connection bolt 13 is fastened, another plate material is stretched.

【0023】上記コンクリート4の打設について説明す
る。上記壁配置部16に、図7に示すように、コンクリ
ート4を打設する。このコンクリート打設は屋外側に突
出した上記バルコニー部7の上部やその他各所にコンク
リート4を圧送して行われる。このコンクリート4は上
記壁配置部16と略同一高さに打設され、上記床面部1
5の略全面を覆うようにされている。
The placing of the concrete 4 will be described. Concrete 4 is poured into the wall arranging portion 16 as shown in FIG. 7. This concrete pouring is performed by pumping the concrete 4 to the upper part of the balcony portion 7 protruding to the outside and other places. The concrete 4 is cast at substantially the same height as the wall arrangement portion 16, and the floor surface portion 1
5 covers almost the entire surface.

【0024】[0024]

【発明の効果】上記したように本発明の枠組壁工法のコ
ンクリート造床施工方法は、下階壁を建て起こしてその
上面の床面部に台板を張設し、該台板上に鉄筋ユニット
と支持金具を設置して該支持金具上面部に上階壁を建て
起こした後コンクリート打設を行うようにしたので、下
階壁等の建方作業の後にこれを中断することなく引続き
上階壁等の建方作業を行え、これ等建方作業を終了した
後にコンクリート施工作業を行なうことから建方作業が
非常に効率よく行えるという効果がある。特に上階壁を
建て起こした後に屋根体の施工を行い、その後に鉄筋ユ
ニットで囲まれた台板上にスラブ鉄筋を配筋して、床面
部にコンクリート打設を行なうことから、建方作業を屋
根体まで含めて完全に終了した後でコンクリート打設を
行うことができ、建方作業が非常に効率よく行える。ま
た、屋根体施工がスラブ鉄筋やコンクリート打設前に終
了するので、これらコンクリート打設等を雨天時等にも
行うことができ作業が一層迅速になる。
As described above, in the concrete floor construction method of the frame wall construction method of the present invention, the lower floor is raised and the base plate is stretched on the floor surface portion of the upper floor, and the reinforcing bar unit is mounted on the base plate. After installing the support metal fittings and erected the upper floor wall on the upper surface of the support metal fittings, concrete placement is performed, so that after the erection work on the lower floor wall, etc., this can be continued without interruption. Since erection work such as walls can be performed and concrete construction work is performed after completion of these erection work, there is an effect that the erection work can be performed very efficiently. In particular, after constructing the roof after constructing the upper floor wall, slab reinforcing bars are laid on the base plate surrounded by the reinforcing bar unit, and concrete is placed on the floor surface. The concrete can be placed after the building including the roof is completely finished, and the erection work can be performed very efficiently. Further, since the roof construction is completed before the slab reinforcement and the concrete are laid, these concrete laying can be performed even in rainy weather and the work is further speeded up.

【0025】さらに本発明は、上階壁を建て起こした後
この上部に更に最上階壁を上記上階壁と同様の手順によ
って建て起こして各階の台板上にスラブ鉄筋の配筋を行
なうようにした場合には、各階壁の建て起こし後に各階
床のコンクリート打設をまとめて行なえ、コンクリート
の乾燥期間が再度に渡ることがないので、全体の施行期
間が短縮できるという効果がある。
Further, according to the present invention, after the upper floor wall is erected, the uppermost floor wall is further erected on the upper floor wall by the same procedure as the upper floor wall, and the slab reinforcing bars are arranged on the base plate of each floor. In this case, concrete can be placed on each floor after the floors have been erected, and the drying period of the concrete does not extend again. Therefore, there is an effect that the entire implementation period can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の枠組壁工法のコンクリート造床方法に
よる建屋の縦断面図である。
FIG. 1 is a vertical cross-sectional view of a building according to a concrete floor construction method of a frame wall construction method of the present invention.

【図2】下階壁への仮設ビーム取付け後の全体斜視図で
ある。
FIG. 2 is an overall perspective view after attaching a temporary beam to a lower floor.

【図3】図2への台板等取付け後の要部斜視図である。FIG. 3 is a perspective view of essential parts after the base plate and the like are attached to FIG.

【図4】図3への鉄筋ユニット配置後の要部斜視図であ
る。
FIG. 4 is a perspective view of a main part after the reinforcing bar unit is arranged in FIG.

【図5】図4への上階壁建て起こし時の要部斜視図であ
る。
5 is a perspective view of a main part when the upper floor wall of FIG. 4 is raised.

【図6】上階壁建て起こし終了後の要部縦断面図であ
る。
FIG. 6 is a vertical cross-sectional view of an essential part after the completion of the erecting of the upper floor wall.

【図7】コンクリート打設後の要部縦断面図である。FIG. 7 is a vertical cross-sectional view of a main part after concrete is poured.

【図8】鉄筋ユニット及び支持金具等の分解斜視図であ
る。
FIG. 8 is an exploded perspective view of a reinforcing bar unit, a support fitting, and the like.

【図9】図8の組立て後の斜視図である。9 is a perspective view after assembly of FIG.

【図10】仮設ビーム取付け構造の他の例の要部縦断面
図である。
FIG. 10 is a longitudinal cross-sectional view of a main part of another example of the temporary beam attachment structure.

【図11】支持金具の他の例の分解斜視図である。FIG. 11 is an exploded perspective view of another example of the support fitting.

【図12】支持金具の他の例の要部分解斜視図である。FIG. 12 is an exploded perspective view of a main part of another example of the support fitting.

【符号の説明】[Explanation of symbols]

1 基礎床面 2 下階壁 2a 切欠き部 3 上階壁 4 コンクリート 5 仮設ビーム 5a ビーム本体 6 台板 7 バルコニー部 8 型枠 9 鉄筋ユニット 9a 連結部 10 支持金具 10a 高さ調整機構 11 下部材 11a 底部材 11b 連係部材 11c 丸棒 12 上部材 12a 壁受部材 12b 連係部材 12c 短円筒 13 連結ボルト 14 スラブ鉄筋 15 床面部 16 壁配置部 20 屋根体 1 Foundation floor 2 Lower floor 2a Notch 3 Upper floor 4 Concrete 5 Temporary beam 5a Beam body 6 Base plate 7 Balcony 8 Formwork 9 Rebar unit 9a Connecting part 10 Supporting metal fitting 10a Height adjusting mechanism 11 Lower member 11a Bottom member 11b Coupling member 11c Round bar 12 Upper member 12a Wall receiving member 12b Coupling member 12c Short cylinder 13 Connecting bolt 14 Slab rebar 15 Floor part 16 Wall placement part 20 Roof body

Claims (6)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 複数階の建屋を枠組壁工法にて建築する
ものであって以下の要件を備えたことを特徴とする枠組
壁工法のコンクリート造床施工方法。 (a)任意の基礎床面の周囲に下階壁の建て起こしを枠
組壁工法にて行う。 (b)上記下階壁の上面の床面部に床支持部材たる仮設
ビームを部屋空間を渡架して架設する。 (c)上記仮設ビームの取付け後に、下面に上記仮設ビ
ームを配した上記床面部に台板を張設する。 (d)上記床面部のうち下階壁が配置された壁配置部に
鉄筋ユニットを配設すると共に、この鉄筋ユニットに連
係して複数の支持金具を配設する。 (e)上記各支持金具の上面部に上階壁を建て起こし、
この上階壁と下階壁を上記壁配置部に配設した上記鉄筋
ユニットを貫通させて連結ボルトで緊結する。 (f)上記上階壁を建て起こした後に、この上階壁の上
部に屋根体の施工を行なう。 (g)上記屋根体の施工後に、上記鉄筋ユニットで囲ま
れた上記台板上にスラブ鉄筋を配筋して、上記床面部に
コンクリート打設を行なう。
1. A concrete floor construction method for a frame wall construction method, wherein a multi-story building is constructed by a frame wall construction method and has the following requirements. (A) A lower floor is built around an arbitrary foundation floor by the frame wall construction method. (B) A temporary beam serving as a floor support member is erected across the room space on the floor surface portion on the upper surface of the lower floor. (C) After the temporary beam is attached, a base plate is stretched on the floor portion where the temporary beam is arranged on the lower surface. (D) The reinforcing bar unit is arranged in the wall arrangement portion in which the lower floor is arranged in the floor surface section, and a plurality of support fittings are arranged in association with the reinforcing bar unit. (E) The upper floor is erected on the upper surface of each of the above-mentioned supporting brackets,
The upper floor wall and the lower floor wall are passed through the reinforcing bar unit arranged in the wall arrangement portion and tightly connected with a connecting bolt. (F) After constructing the upper floor, the roof is constructed on the upper wall. (G) After the construction of the roof body, slab reinforcing bars are arranged on the base plate surrounded by the reinforcing bar unit, and concrete is placed on the floor surface.
【請求項2】 上記上階壁を建て起こした後に、この上
階壁の上部に更に最上階壁を上記上階壁と同様の手順に
よって建て起こし、この最上階壁の上部に屋根体の施工
を行ない、その後で上記各階の台板上に上記スラブ鉄筋
の配筋を行なうことを特徴とする請求項1記載の枠組壁
工法のコンクリート造床施工方法。
2. After erection of the upper floor wall, an uppermost floor wall is further erected on the upper portion of the upper floor wall by the same procedure as that of the upper floor wall, and a roof is constructed on the upper portion of the upper floor wall. The concrete floor construction method of the frame wall construction method according to claim 1, characterized in that the slab reinforcement is laid on the base plate of each floor after that.
【請求項3】 上記各支持金具を上部材と下部材から構
成して分割自在とし、この下部材を上記壁配置部の上記
台板上に固定し、該下部材を内部に連係させて上記鉄筋
ユニットを配設し、その後上記上部材を上記鉄筋ユニッ
トを抱持するように上記下部材に連結させ、各支持金具
をその上面部を上記鉄筋ユニットの上面より上方におい
て互いに面一状とし、次いで、上記上階壁を上記各支持
金具の上部材に載置すると共に、この上部材を上階壁に
締結して、上階壁の建て起こしを行なうことを特徴とす
る上記請求項1又は2記載の枠組壁工法のコンクリート
造床施工方法。
3. Each of the support fittings is composed of an upper member and a lower member and is separable, and the lower member is fixed on the base plate of the wall arrangement portion, and the lower members are linked to the inside of the support member. Arranging a reinforcing bar unit, then connecting the upper member to the lower member so as to embrace the reinforcing bar unit, and the upper surface of each supporting metal fitting is flush with each other above the upper surface of the reinforcing bar unit, Next, the upper floor is placed on the upper member of each of the support fittings, and the upper member is fastened to the upper wall to raise and raise the upper floor. The concrete floor construction method of the frame wall construction method described in 2.
【請求項4】 上記各支持金具を上部材と下部材から構
成して分割自在とすると共に、この支持金具に高さ調整
機構を設け、この下部材を上記壁配置部の上記台板上に
固定し、該下部材を内部に連係させて上記鉄筋ユニット
を配設し、その後上記上部材を上記鉄筋ユニットを抱持
するように上記下部材に連係させると共に、上記高さ調
整機構により上記支持金具の高さを調整し、各支持金具
をその上面部を上記鉄筋ユニットの上面より上方におい
て互いに面一状とし、次いで、上記上階壁を上記各支持
金具の上部材に載置すると共に、この上部材を上階壁に
締結して、上階壁の建て起こしを行なうことを特徴とす
る上記請求項1又は2記載の枠組壁工法のコンクリート
造床施工方法。
4. Each of the support fittings is composed of an upper member and a lower member and is separable, and a height adjusting mechanism is provided on the support fittings, and the lower member is placed on the base plate of the wall arrangement portion. It is fixed and the lower member is linked to the inside to dispose the reinforcing bar unit, and then the upper member is linked to the lower member so as to embrace the reinforcing bar unit, and the support is provided by the height adjusting mechanism. Adjusting the height of the metal fittings, the upper surface of each supporting metal fitting is flush with each other above the upper surface of the reinforcing bar unit, and then the upper floor is placed on the upper member of each supporting metal fitting, The concrete floor construction method of the frame wall construction method according to claim 1 or 2, wherein the upper member is fastened to the upper floor wall to raise the upper floor wall.
【請求項5】 上記各支持金具を上記壁配置部の上記台
板上に固定し、この支持金具を両側方から挟むように上
記鉄筋ユニットを配設すると共に、この鉄筋ユニットを
連結し、各支持金具をその上面部を上記鉄筋ユニットの
上面より上方において互いに面一状とし、次いで、上記
上階壁を上記各支持金具の上部に載置すると共に、この
支持金具を上階壁に締結して、上階壁の建て起こしを行
なうことを特徴とする上記請求項1又は2記載の枠組壁
工法のコンクリート造床施工方法。
5. Each of the supporting fittings is fixed on the base plate of the wall disposing portion, the reinforcing bar unit is arranged so as to sandwich the supporting fitting from both sides, and the reinforcing bar units are connected to each other. The upper surfaces of the support fittings are flush with each other above the upper surface of the reinforcing bar unit, and then the upper floors are placed on top of the respective support fittings, and the support fittings are fastened to the upper floor walls. The concrete floor construction method of the framed wall construction method according to claim 1 or 2, wherein the upper floor wall is raised.
【請求項6】 上記下階壁の上縁に切欠き部を形成する
と共に、上記仮設ビームをその端部を上記切欠き部に当
接させるように上記下階壁間に架設し、あるいは上記下
階壁の上端部にビーム受具を載置すると共に、上記仮設
ビームをその端部を上記ビーム受具側面の突出片に当接
させるように上記下階壁間に架設して、上記仮設ビーム
の取付けを行なうことを特徴とする上記請求項1乃至5
記載の枠組壁工法のコンクリート造床施工方法。
6. A notch is formed in the upper edge of the lower floor, and the temporary beam is installed between the lower floors so that the end of the temporary beam abuts the notch, or The beam receiver is placed on the upper end of the lower floor, and the temporary beam is installed between the lower floors so that the end of the temporary beam is brought into contact with the protruding piece on the side surface of the beam receiver, and the temporary beam is installed. 6. The method according to claim 1, wherein the beam is attached.
Concrete floor construction method of the described frame wall construction method.
JP5341693A 1993-12-10 1993-12-10 Concrete floor construction method of frame wall construction method Expired - Fee Related JP2520371B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5341693A JP2520371B2 (en) 1993-12-10 1993-12-10 Concrete floor construction method of frame wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5341693A JP2520371B2 (en) 1993-12-10 1993-12-10 Concrete floor construction method of frame wall construction method

Publications (2)

Publication Number Publication Date
JPH07158159A JPH07158159A (en) 1995-06-20
JP2520371B2 true JP2520371B2 (en) 1996-07-31

Family

ID=18348049

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5341693A Expired - Fee Related JP2520371B2 (en) 1993-12-10 1993-12-10 Concrete floor construction method of frame wall construction method

Country Status (1)

Country Link
JP (1) JP2520371B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3093745A1 (en) * 2019-03-12 2020-09-18 Jean-Luc Chabalier DEVICE FOR FIXING A PREFABRICATED PANEL TO A SLAB

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS52105909U (en) * 1976-02-10 1977-08-12
JPS58204241A (en) * 1982-05-19 1983-11-28 三井建設株式会社 Attachment of pc wall

Also Published As

Publication number Publication date
JPH07158159A (en) 1995-06-20

Similar Documents

Publication Publication Date Title
US4211043A (en) Precast concrete building module form
PL177816B1 (en) Prefabricated panel-type building unit resistant to earthquake, wind and fire, method of making same and structure erected using such units
US20040025463A1 (en) Concrete building construction form unit and manufacturing devicetherefor, and concrete building constructed by using concrete building construction form
GB2243863A (en) Formwork
US7219474B2 (en) Load bearing building panel
KR20210038684A (en) Precast building construction system
PL185435B1 (en) System for erection of shells of buildings in particular one-family houses
JP2520371B2 (en) Concrete floor construction method of frame wall construction method
JP2520372B2 (en) Concrete floor construction of frame wall construction method
JPS6253660B2 (en)
RU2206673C2 (en) Process of erection of monolithic frames
JPH0562178B2 (en)
KR102242175B1 (en) Mold for prefabricated double wall precast concrete
JP3247657B2 (en) Construction method of reinforced concrete building
AU647783B2 (en) Improved building techniques
JP3616304B2 (en) Building wall panel
WO2006050572A1 (en) Modular building construction apparatus and methods
JP2900937B1 (en) Construction method of wall type RC structure
KR950009611B1 (en) Assembling high apartments joining structure
JP3062810B2 (en) Assembling method of plumbing unit in building and plumbing unit
KR200147067Y1 (en) Inside and outside wall setting-up device
KR20030088411A (en) Plural direction deck plate
RU2198988C2 (en) Process of erection of monolithic walls of buildings and structures in permanent forms
AU648918B2 (en) Building construction method
JP2879652B2 (en) Box type building structure and its construction method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090517

Year of fee payment: 13

LAPS Cancellation because of no payment of annual fees