JP2510338B2 - Assembly sequence planning system and assembly sequence planning method - Google Patents

Assembly sequence planning system and assembly sequence planning method

Info

Publication number
JP2510338B2
JP2510338B2 JP2188286A JP18828690A JP2510338B2 JP 2510338 B2 JP2510338 B2 JP 2510338B2 JP 2188286 A JP2188286 A JP 2188286A JP 18828690 A JP18828690 A JP 18828690A JP 2510338 B2 JP2510338 B2 JP 2510338B2
Authority
JP
Japan
Prior art keywords
option
leveling
bay
cant
order
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2188286A
Other languages
Japanese (ja)
Other versions
JPH0475836A (en
Inventor
義明 ▲高▼畠
修 林部
幹夫 福永
恭一 塚村
直純 今井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kubota Corp
Original Assignee
Kubota Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kubota Corp filed Critical Kubota Corp
Priority to JP2188286A priority Critical patent/JP2510338B2/en
Publication of JPH0475836A publication Critical patent/JPH0475836A/en
Application granted granted Critical
Publication of JP2510338B2 publication Critical patent/JP2510338B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Control By Computers (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Automatic Assembly (AREA)
  • Multi-Process Working Machines And Systems (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、各種のオプションが付加される製品群を組
み立てる混流生産方式の組立ラインへの投入型式の順番
を計画する組立順序計画技術、詳しくはその技術を実現
する方法及びシステムに関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to an assembly sequence planning technique for planning the order of the injection types to an assembly line of a mixed-flow production system for assembling a product group to which various options are added. Relates to a method and system for implementing the technology.

〔従来の技術〕[Conventional technology]

上述のような生産方式においては、日々の生産型式別
台数、つまり付加されるオプション別の生産台数は組立
の一定期日前、例えば前日に確定する。一日分の生産型
式をどのような順番で組立ラインに流すかを決定する業
務を組立順序計画というが、この組立順序計画において
最も基本となる考え方が平準化であり、各工程での工数
負荷の変動をできるだけ少なくして工程の安定化を計る
ことが重要である。
In the above-described production method, the daily production model number, that is, the production number of each option to be added is fixed before one regular day of assembly, for example, the day before. The work that determines the order in which the production models for one day are sent to the assembly line is called the assembly sequence plan. The most basic idea in this assembly sequence plan is leveling, and the man-hour load in each process It is important to stabilize the process by minimizing the fluctuation of

この計画作成は、従来より、人手により計画の良否を
判断して試行錯誤しながら負荷の集中を起こす不具合箇
所を手直ししており、計画作成の迅速のためと計画担当
者間の計画精度のばらつきを避けるため、コンピュータ
を用いた自動化を考えられている。
Conventionally, this plan preparation is performed by manually judging the quality of the plan and making trial and error to remedy the defective points that cause the concentration of the load. To avoid this, automation using a computer is being considered.

例えば、組立順序計画の最適な解を求めるためには標
準工数を用いラインバランスを計算するOR的なモデル化
の手法がある。しかしながら、組立順序計画の問題は制
約条件が複雑で、モデルの条件式はすべての順序の組み
合せを計算して最適解を決める以外には解けないもので
あった。組み合せの数は爆発的に増加し高速のコンピュ
ータを用いてもこの計算は現実的な時間内では不可能な
ためこの手法は実用性をもたない。
For example, there is an OR-like modeling method that calculates the line balance using standard man-hours in order to obtain the optimum solution of the assembly sequence plan. However, the problem of the assembly sequence planning has complicated constraints, and the conditional expression of the model can be solved only by calculating the combination of all the sequences and determining the optimum solution. This method is not practical because the number of combinations explosively increases and even if a high-speed computer is used, this calculation is impossible in a realistic time.

このため、数学的な厳密性をもって解を求める代わり
に、ある種のルールのもとに組立順序を作り出し、満足
解を得るようにすることが考えられる。この場合、従来
では製造部門等のスタッフの個人的なノウハウに基づい
て行っていた並び替え処理を、計算機により実用上十分
な速度をもって行わせるためには、従来の並び替えのノ
ウハウを数学的に解析して導出された新しい並び替え手
段の確立が不可欠となる。
For this reason, instead of obtaining a solution with mathematical rigor, it is conceivable to create an assembling order based on a certain kind of rule so as to obtain a satisfactory solution. In this case, in order to perform the sorting process that was conventionally performed based on the personal know-how of the staff of the manufacturing department etc. at a speed practically sufficient for the computer, the conventional sorting know-how is mathematically It is essential to establish a new sorting method derived by analysis.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

本発明の課題は、混流生産方式の組立ラインへの投入
型式の順番を計画する技術において、得られた組立順序
が注目オプションに関して実用上十分な速度と精製をも
って行い得る並び替え処理を実現することである。
An object of the present invention is to realize a rearrangement process in which the obtained assembling order can be performed with a practically sufficient speed and refining with respect to the option of interest in the technique of planning the order of the injection type into the assembly line of the mixed production system. Is.

〔課題を解決するための手段〕[Means for solving the problem]

上記課題を解決するために、本発明による組立順序計
画方法では、複数のオプションから優先度に応じて順次
注目すべきオプションを選択してこの選択されたオプシ
ョンが付加される製品を均等に組立ラインに流すために
組立順序の並び替えを行う並び替えステップと、注目オ
プションに関して並び替えられた組立順序に対してその
平準度を算定する平準度評価ステップと、平準度評価部
で算定された平準度を予め設定されている該当オプショ
ンの基準値と比較して並び替えた順序が満足できるもの
かを判定する比較ステップとから構成されているととも
に、 前記並び替えステップが、注目オプションに関しての
ピークロード中心部と最も広いベイキャントロード中心
部の入れ替えを行って行くことで平準化をすすめていく
ピーク入れ替えステップと、注目オプションのベイキャ
ントロード後方要素と最適な間隔位置の要素との入れ替
えを行っていくことで平準化をすすめていくベイキャン
トロード入れ替えステップ、とを備えている。
In order to solve the above-mentioned problems, in the assembly sequence planning method according to the present invention, an option to be noted is sequentially selected from a plurality of options according to priority, and products to which the selected options are added are evenly assembled on an assembly line. Sorting step for rearranging the assembly order in order to flow to the target, Levelness evaluation step for calculating the level of equality for the assembly order sorted for the option of interest, Levelness calculated by the leveling evaluation section And a comparison step for determining whether or not the rearranged order is satisfied by comparing with a preset reference value of the corresponding option, and the rearrangement step is a peak load center for the attention option. Section and the widest Bay Cantor Road center are replaced to promote leveling. It is equipped with a step, and a bay cant road replacement step that promotes leveling by replacing the element at the rear of the bay cant road, which is an option of interest, with the element at the optimal spacing position.

また、本発明による組立順序計画システムは、複数の
オプションから優先度に応じて順次注目すべきオプショ
ンを選択してこの選択されたオプションが付加される製
品を均等に組立ラインに流すために組立順序の並び替え
を行う並び替え処理部と、前記選択されたオプションに
関して並び替えられた組立順序に対してその平準度を算
定する平準度評価部と、平準度評価部で算定された平準
度を予め設定されている前記選択されたオプションの基
準値と比較して並び替えた順序が満足できるものかを判
定する比較部と、前述した並び換え処理部、平準度評価
部、比較部を制御する制御部とが備えられるとともに、 前記並び替え処理部が、前記選択されたオプションに
関してのピークロード中心部と最も広いベイキャントロ
ード中心部の入れ替えを行って行くことで平準化をすす
めていくピークロード入れ替え手段と、注目オプション
のベイキャントロード後方要素と最適な間隔位置の要素
との入れ替えを行っていくことで平準化をすすめていく
ベイキャントロード入れ替え手段、とから構成されてい
る。
In addition, the assembly sequence planning system according to the present invention sequentially selects, from a plurality of options, an option to be noticed in accordance with the priority and distributes the products to which the selected options are added to the assembly line evenly. A sorting processing unit that sorts the items, a leveling degree evaluation unit that calculates the leveling degree for the assembly order sorted for the selected option, and a leveling degree calculated by the leveling degree evaluation unit in advance. A comparison unit that determines whether the rearranged order is satisfied by comparing with the set reference value of the selected option, and a control that controls the rearrangement processing unit, the levelness evaluation unit, and the comparison unit described above. And a rearrangement processing unit replaces the peak load center with the widest bay cant load center for the selected option. The peak load replacement means that promotes leveling by performing the following, and the bay cant that promotes leveling by exchanging the backward option element of the option of interest and the element at the optimal spacing position. It is composed of a load exchange means.

〔作 用〕[Work]

複数のオプションから優先度に応じて順次注目すべき
オプションを選択してこの選択されたオプションが付加
される製品を均等に組立ラインに流すために組立順序の
並び替えを行う際、最も集中している部分の要素を最も
空いている部分の要素と入れ替えるように並び替えを行
うピークロード入れ替え処理と、最も空いている部分の
後方要素をその最適な間隔位置にある要素と入れ替える
ように並び替えを行うベイキャントロード入れ替え処理
とが、所定のルールに従って選択起動され、注目オプシ
ョンに関する所定の基準を満足するようにその並びを平
準化していく。
Select the most noticeable option from multiple options in order of priority and sort the assembly order to distribute the products to which this selected option is added evenly to the assembly line. The peak load swapping process that sorts the elements in the empty part with the elements in the empty part, and the rearward element in the empty part is replaced with the element at the optimal interval position. The bay cant load replacement processing to be performed is selectively activated according to a predetermined rule, and the arrangement is leveled so as to satisfy a predetermined criterion regarding the option of interest.

〔発明の効果〕〔The invention's effect〕

並び替えにおいて、単に最も集中している部分の要素
を最も空いている部分の要素と入れ替えるピークロード
入れ替え手段だけで並び替えを行うと、ある部分が良く
なると他の部分が悪くなるというような満足できない平
準度で解が振動するような事態がたびたび生じ、満足す
る解が求められなくなるが、この並び替えにベイキャン
トロード入れ替え手段による並び替えを組み合わせるこ
とで前述したような解の振動が抑えられ実用的な速度で
もって満足すべき平準度が得られる。さらに、複数のオ
プションから優先度に応じて順次注目すべきオプション
を選択して並び替えを行う並び替え処理において、ピー
クロード入れ替えやベイキャントロード入れ替えによっ
て行われる並び替えがその平準度を基準値でチェックし
ながら行われることにより、注目すべき複数のオプショ
ンの全てに関する所望の平準化が定量的な精度の保証の
もとで実現する。
Satisfaction that when sorting, only the peak load swapping means that swaps the element of the most concentrated part with the element of the most vacant part becomes better when one part becomes better and the other part becomes worse. Situations in which the solution oscillates with a level that cannot be achieved often occur, and it is not possible to find a satisfactory solution. Satisfactory leveling can be obtained at a practical speed. Furthermore, in the sorting process that sequentially selects and pays attention to the options that should be focused on from multiple options according to their priority, the sorting performed by peak load swapping or bay cant load swapping is based on that level of standardity. By being performed while checking, the desired leveling regarding all of the plurality of options to be noticed is realized while guaranteeing quantitative accuracy.

〔その他の特徴〕[Other features]

ピークロード入れ替え手段とベイキャントロード入れ
替え手段の好ましい組み合せ制御として、本発明による
好適な実施態様において、ベイキャントロードが発生し
ている限り、ベイキャントロード入れ替え手段を用い、
ベイキャントロードがなくなった時点で、1度ピークロ
ード入れ替え手段で平準化を行ったのちに、ベイキャン
トロードが生じておれば再度ベイキャントロード入れ替
え手段を実行することが提案される。このような制御に
より、ピークロード入れ替え手法の高速性を失わずし
て、その平準化レベルの向上が可能となる。
As a preferred combination control of the peak load exchanging means and the bay cant load exchanging means, in a preferred embodiment according to the present invention, as long as the bay cant load occurs, the bay cant load exchanging means is used,
It is proposed to perform the leveling by the peak load exchanging means once when the bay cant load disappears, and then execute the bay cant load exchanging means again if the bay cant load occurs. With such control, the leveling level can be improved without losing the high speed of the peak load replacement method.

〔実施例〕〔Example〕

本発明による組立順序計画システムの全体構成が第1
図に示されている。1日分の組み立てるべき製品の型式
及び各種オプションの有無とそれらの台数をホストコン
ピュータから通信手段や、磁気的又は光学的記憶手段を
介して受け取る入力部1は、それらのデータをI/Oイン
ターフェース2に送る。このインターフェース2は、こ
のデータをシステムの中央処理機構が読み取り可能な形
式に変換する機能を有する。また逆に中央処理機構が導
き出した結果をプリンタやCRTなどの出力部3に送る機
能も有する。
The overall configuration of the assembly sequence planning system according to the present invention is the first
It is shown in the figure. The input unit 1 which receives the model of the product to be assembled for one day and the presence / absence of various options and the number of them from the host computer through the communication means or the magnetic or optical storage means receives the data from the I / O interface. Send to 2. The interface 2 has the function of converting this data into a format readable by the central processing unit of the system. On the contrary, it also has a function of sending the result derived by the central processing unit to the output unit 3 such as a printer or a CRT.

この中央処理機構は、並び換え処理部4、平準度評価
部5、比較部6、基準値変更部7、及びこれらを統括制
御する制御部8から構成されている。並び替え処理部4
は、基本的には、注目されるべきオプションを有する製
品をできるだけ連続させないで均等に組立ラインに流す
ために必要な並び替えのルールに基づいて、組立順序の
並び替えを行なう。平準度評価部5は注目オプションに
関して並び替えられた組立順序に対して後で詳しく説明
されるルールに基づいて平準度を算定するものであり、
注目オプションの集中度を示すピークロード評価値を算
定するピークロード評価部と、注目オプションのバラツ
キ度を示すバラツキ評価値を算定するバラツキ評価部
と、このオプションの最適間隔を求めるとともにこの最
適間隔に基づいて前記ピークロード評価値とバラツキ度
評価値のそれぞれに対する重み係数を決定して、これよ
り注目オプションに関する平準度を算定する平準度算定
部とを備えている。比較部6は平準度評価部で算定され
た平準度を予め設定されている該当オプションの基準値
と比較して並び替えた順序が満足できるものかを判定す
る。さらに、基準値変更部7は、特別なケースに用いら
れるのであるが、各オプションの相互干渉により、並び
替えがどうしてもうまくいかない場合、特定のオプショ
ンの基準値を下げる機能を有する。制御部8は、前述し
た並び換え処理部4、平準度評価部5、比較部6、基準
値変更部7を制御して、このシステムに入力された1日
の生産情報をもとにして、優先度の高いオプションから
順に注目しながら満足すべき組立順序を導く。
The central processing mechanism is composed of a rearrangement processing unit 4, a leveling degree evaluation unit 5, a comparison unit 6, a reference value changing unit 7, and a control unit 8 which controls these in a centralized manner. Sorting processing unit 4
Basically rearranges the assembly order based on the rearrangement rule necessary to make the products having the options to be noticed evenly flow through the assembly line without making them as continuous as possible. The leveling degree evaluation unit 5 calculates the leveling degree based on a rule which will be described in detail later with respect to the assembling order rearranged with respect to the option of interest.
The peak load evaluation part that calculates the peak load evaluation value that indicates the degree of concentration of the option of interest, the variation evaluation part that calculates the variation evaluation value that indicates the degree of dispersion of the option of interest, and the optimal interval for this option Based on this, a weighting coefficient for each of the peak load evaluation value and the variation degree evaluation value is determined, and a leveling degree calculation unit for calculating the leveling degree for the option of interest is provided. The comparing unit 6 compares the leveling degree calculated by the leveling degree evaluation unit with a preset reference value of the corresponding option and determines whether or not the rearranged order is satisfactory. Further, the reference value changing unit 7, which is used in a special case, has a function of lowering the reference value of a specific option when the rearrangement cannot be achieved due to mutual interference between the options. The control unit 8 controls the rearrangement processing unit 4, the leveling degree evaluation unit 5, the comparison unit 6, and the reference value change unit 7 described above, and based on the daily production information input to this system, Derive a satisfying assembly sequence by focusing on the options with the highest priority.

次に、本発明による組立順序計画システムの処理の概
略的な流れを第2図に示すフローチャートを用いて説明
する。
Next, a schematic flow of processing of the assembly sequence planning system according to the present invention will be described with reference to the flowchart shown in FIG.

ステップ10(以下#10と記す)において、入力部1を
介して送り込まれた1日分の組立予定の製品を示すデー
タが本システムのワークエリアにロードされる。#15に
おいて、入力された組立予定の製品に与えられているオ
プション毎に基準値つまり並び替え合格点が設定され
る。#20において、順位を並び替えるための注目すべき
オプションがあるかどうかを判定してYESの場合#25に
進む。#25では、並び替え処理部4によって、注目オプ
ションに関する並び替えを行なう。この並び替えは、例
えば、先に注目した優先度の高いオプションの既に定め
られている順序は替えないといった並び替えの制約条件
下で、後で述べられる手法を用いて行われる。#30にお
いて、#25で並び替えられた順序に対して平準度評価部
5がその平準度を算出する。#35では、算定された平準
度と基準値が比較され、平準度が基準値を上回る場合は
#20にジャンプして次に並び替えるために注目すべきオ
プションがあるかどうかをチェックする。平準度が基準
値以下となった場合、#40へ進む。#40では、現在注目
しているオプションより先に注目された優先度の高い上
位のオプションをもつ製品の並びの固定を解除して、つ
まり上位オプションの制約条件を緩和して、その緩和さ
れたオプションの評価値が対応する基準値を上回る限り
において並び替えが行なわれる。#45と#50では、#30
と#35と同様に平準度が算定され、その平準度を基準値
と比較し、平準度が基準値を上回った場合#20へジャン
プし、平準度が基準値以下となる場合は#60へ進み、基
準点を変更して再度並び替えを行なうかどうかを問い合
わせ、YESの場合#15にジャンプして基準値の設定をや
り直す。NOの場合は、#20にジャンプする。#20におい
てNOの場合、つまり注目すべきオプションがなくなった
場合、#65で最終結果を出力して、終了する。
In step 10 (hereinafter referred to as # 10), the data indicating the product to be assembled for one day, which is sent via the input unit 1, is loaded into the work area of this system. In # 15, a reference value, that is, a rearrangement passing score, is set for each option given to the input product to be assembled. In # 20, it is determined whether or not there is a noticeable option for rearranging the ranking, and if YES, the process proceeds to # 25. In # 25, the rearrangement processing unit 4 rearranges the options of interest. This rearrangement is performed using a method described later, for example, under the rearrangement constraint condition that the previously defined order of the high-priority option that has been focused on is not rearranged. In # 30, the level evaluation unit 5 calculates the level for the order rearranged in # 25. In # 35, the calculated level and the standard value are compared, and if the level is higher than the standard value, it jumps to # 20 to check whether there is a remarkable option to sort next. If the levelness falls below the standard value, proceed to # 40. In # 40, the list of products with higher priority higher priority options that were noticed earlier than the currently focused option was released, that is, the constraint conditions for higher options were relaxed Sorting is performed as long as the evaluation value of the option exceeds the corresponding reference value. # 45 and # 50, # 30
Similar to # 35 and # 35, the level is calculated, and the level is compared with the reference value. If the level exceeds the standard, jump to # 20. If the level is less than the standard, go to # 60. Proceed and inquire whether to change the reference point and rearrange again. If YES, jump to # 15 and set the reference value again. If no, jump to # 20. If NO in # 20, that is, if there are no more options to be noted, the final result is output in # 65, and the process ends.

つぎに並び換え処理における並び換え手法と平準度の
計算方法を説明するが、このために使用される2・3の
語句の定義をまず行う。
Next, the rearrangement method and the leveling degree calculation method in the rearrangement process will be described. First, a few words and phrases used for this purpose will be defined.

オプションを有する製品が均等に分布したときの間隔
状態における間隔台数を“最適間隔”という。つまり、 最適間隔=(総生産台数−オプションを有する台数) /オプションを有する台数 但し、オプションを有する製品の生産台数が0台の
時、その最適間隔は0とし、オプションを有する製品の
生産台数が総数の50%を越えた時、その最適間隔は最適
に分布させても連続する台数を最適間隔とする。最適間
隔が整数にならない場合、その切り上げた値を最適広間
隔、その切り捨てた値を最適狭間隔という。
The number of units in an interval state when products with options are evenly distributed is called an "optimal interval". That is, the optimum interval = (total number of products-number of units with options) / number of units with options However, when the number of units of products with options is 0, the optimal interval is set to 0, and the number of units of products with options is When it exceeds 50% of the total number, even if the optimal interval is optimally distributed, the number of consecutive machines is the optimal interval. When the optimum interval is not an integer, the rounded up value is called the optimum wide interval, and the rounded down value is called the optimum narrow interval.

一日分の製品の組立順序の中で所定のオプションに注
目したとき、連続が存在する場合は最も連続台数の多い
部分を、そして連続が存在しない場合は間隔台数の最も
小さい部分を含むオプションありの部分をそれぞれ“ピ
ークロード”という。このピークロードが複数存在する
場合その部分を“ピークロード集合”という。
When paying attention to a given option in the assembly sequence of products for one day, there is an option that includes the part with the largest number of continuous units when there is a sequence, and the part with the smallest number of units when there is no sequence. Each of the parts is called "peak load". When there are multiple peak loads, the part is called "peak load set".

一日分の製品の組立順序の中で、所定のオプションの
ある間隔が、最適広間隔より大きい場合、その部分を
“ベイキャントロード”といい、その集合を“ベイキャ
ントロード集合”という。
In the assembly sequence of products for one day, when a certain interval of a predetermined option is larger than the optimum wide interval, the part is called "bay cant road set", and the set is called "bay cant road set".

入れ替え処理の手法としては、本発明では、ピークロ
ード入れ替え手法とベイキャントロード入れ替え手法が
用いられており、ピークロード入れ替え手法とは、注目
オプションに関してのピークロード中心部と最も広いベ
イキャントロード中心部の入れ替えを行って行くことで
平準化をすすめていく手法であり、ベイキャントロード
入れ替え手法とは、注目オプションのベイキャントロー
ド後方要素と最適な間隔位置との入れ替えを行っていく
ことで平準化をすすめていく手法である。ここで、ベイ
キャントロード後方要素とは、注目しているオプション
を備えた前方要素と後方要素との間の間隔が前述した最
適広間隔より大きい場合(つまりベイキャントロード)
において、前記後方要素のことである。また、最適な間
隔位置の要素とは、ベイキャントロードにおいて最適広
間隔を形成する注目しているオプションを備えていない
要素のことである。
In the present invention, a peak load replacement method and a bay cant load replacement method are used as a replacement processing method. The peak load replacement method is the peak load center part and the widest bay cant load center part regarding the option of interest. It is a method that promotes leveling by exchanging, and the bay cant road swapping method is a leveling method by swapping the bayant road rear element of the option of interest and the optimal spacing position. Is a method of promoting. Here, a bay cant road rear element is when the distance between the front element and the rear element having the option of interest is larger than the above-mentioned optimum wide distance (that is, bay cant road).
In, the rear element. Further, the element of the optimum spacing position is an element which does not have the option of attention to form the optimum wide spacing in the bay cant road.

十分な高速性をもって平準化のレベルを向上させるた
めには、ベイキャントロードが発生している限り、ベイ
キャントロード入れ替え手法を用い、ベイキャントロー
ドがなくなった時点で、1度ピークロード入れ替え手法
で平準化を行ったのち、ベイキャントロードが生じてお
けば再度ベイキャントロード入れ替えを実行するといっ
たような両方の手法を混合させるやり方が望ましい。
In order to improve the leveling level with sufficient speed, the bay cant load replacement method is used as long as the bay cant road occurs, and the peak load replacement method is used once when the bay cant road disappears. After leveling, it is desirable to mix both methods, such as performing baycant load replacement again if baycant load has occurred.

平準度評価部は、与えられた組立順序に対して次の式
により注目すべきオプションに関する平準度を算定す
る: 平準度=(W*G+(1−W)*H)*100 ここで、Gはバラツキ評価値であり、 Y=<Xの時、(X:実際の間隔の集合、Y:最適間隔の集
合) G=Σ(Y/X)/オプション有りの生産台数 Y>Xの時、 G=Σ(Y/X)/オプション有りの生産台数 Hはピー
クロード評価値であり、 ピークロードが間隔の時、 Hはピークロード間隔台数/最適狭間隔 (値が1を越える場合は全て1とする) ピークロードが連続の時、 H=0 Wはバラツキ度評価値の重みであり、 S=>1の時、(S:最適間隔ないしは最適広間隔) W=1/S S<1の時、 W=1 である。
The levelness evaluation unit calculates the levelness regarding the option to be noted for the given assembly sequence by the following formula: Levelness = (W * G + (1-W) * H) * 100 where G Is a variation evaluation value, and when Y = <X, (X: set of actual intervals, Y: set of optimum intervals) G = Σ (Y / X) / production quantity with option Y> X, G = Σ (Y / X) / Production quantity with option H is the peak load evaluation value. When the peak load is an interval, H is the peak load interval quantity / optimum narrow interval (if the value exceeds 1, all 1 When the peak load is continuous, H = 0 W is the weight of the variation evaluation value, and when S => 1, (S: optimum interval or optimum wide interval) W = 1 / S S <1 When, W = 1.

つぎに、実際の並び換えとその平準度の算定を第3図
(a)から(r)に示された例を用いて説明する。
Next, the actual rearrangement and the calculation of the levelness thereof will be described using the example shown in FIGS. 3 (a) to 3 (r).

各図において横の数列は一つの製品を示しており、そ
の各数、つまり“1"または“0"は各オプションを有する
かどうかを表している。例えば、“0100"で示された製
品は第1オプションが無し、第2オプションが有り、第
2・第3オプションが無しである。図から明らかなよう
に、この例では10個の製品が計画されており、オプショ
ンの数は5である。なお、この組立順序を決定する場
合、これより前の組立順序を考慮しなければならない
が、ここでは前回においてオプションの間隔が3つ空い
ていたと仮定しておく。また各オプションの基準値、つ
まり並び替え合格点は第1オプションから順番に60、5
0、40、30、20点とする。
In each drawing, the horizontal sequence indicates one product, and each number, that is, "1" or "0", indicates whether or not each option is provided. For example, the product indicated by "0100" has no first option, has a second option, and has no second and third options. As is apparent from the figure, 10 products are planned in this example, and the number of options is 5. It should be noted that when this assembly order is determined, the assembly order prior to this must be taken into consideration, but here it is assumed that there were three optional intervals last time. Also, the standard value of each option, that is, the passing score for sorting, is 60, 5 in order from the first option.
0, 40, 30, 20 points.

並び替え処理 第1ステップ・・・第3図(a)から第3図(b) まず第1オプションに注目する。前述したように、前
回の発行分との間隔が3つ空いており、さらに今回のデ
ータにおいてはじめに1つ空いているので合計4間隔と
なる。第1オプションの最適間隔は3となるので、空き
過ぎ部分を積めるベイキャントロード再配置が行われ
る。つまり、第1オプションは上位オプションの制約が
ないので第1段目(最上段の横並び数列で示される製
品)と第2段目(2段目の横並び数列で示される製品)
を入れ替える。ここで、上位オプションとは、複数のオ
プションから優先度に応じて順次注目すべきオプション
を選択して並び替えを行う並び替え処理において、例え
ば、“部品A"というオプションに注目した並び替えにお
いて、既に並び替えのために利用されたより優先度の高
い、つまり“部品A"より高い優先度をもったオプション
である。
Rearrangement process First step ... Figs. 3 (a) to 3 (b) First, attention is paid to the first option. As described above, there are three gaps from the previous issue, and there is one gap at the beginning in this data, so there are a total of four gaps. Since the optimum interval of the first option is 3, the bay cant road rearrangement is carried out so that the over-empty portion is stacked. In other words, since the first option has no restrictions on upper options, the first stage (the product shown in the top row of the side-by-side sequence) and the second stage (the product shown in the second stage of the side-by-side sequence)
Replace. Here, the high-order option is a sort process in which a plurality of options are selected in order according to their priority and sorted, and, for example, in the sort focusing on the option "component A", It is an option with a higher priority that has already been used for sorting, that is, a higher priority than "Part A".

第2ステップ・・・第3図(b)から第3図(c) 第1オプションに関して3段目と8段目の間で間隔が
4となっているので、さらにベイキャントロード再配置
が行われ、7段目と8段目が入れ替えられる。
2nd step ... Fig. 3 (b) to Fig. 3 (c) Since the interval is 4 between the 3rd stage and the 8th stage for the first option, the bay cant road rearrangement is further performed. The 7th and 8th steps are swapped.

第3ステップ・・・第3図(c)から第3図(d) 第1オプションに関して、最適間隔の3以上の間隔部
分がなくなったので、ピークロード再配置が行われる。
まず、一番密度の高い部分が検索されるが、ここでは最
上段と3段目が1間隔なので、最上段が一番密度のひく
い部分に移動される。ここで最上段が移動されることに
なるが、これがなくなると仮定した場合、ここに前回か
ら数えて5間隔が生じることとなる。この中の1つの入
れ替えると良いのであるが、前日のデータはすでに発行
されていて入れ替えはできないのである。このため、8
・9・10段目の3間隔に照準を合わせ、これらが入れ替
えの対象となるが、8段目や9段目と入れ替えても良く
ならないので、10段目が最上段と入れ替えられる。
3rd step ... FIG. 3 (c) to FIG. 3 (d) With respect to the first option, the peak load relocation is performed because there are no more than three optimum intervals.
First, the most dense part is searched, but here the uppermost part and the third part are one interval, so the uppermost part is moved to the least dense part. Here, the uppermost stage is moved, but if this is assumed to disappear, there will be 5 intervals counted from the previous time. It is good to replace one of these, but the data of the previous day has already been issued and cannot be replaced. Therefore, 8
・ Aiming at the 3rd interval of the 9th and 10th stages, these are the targets for replacement, but it is not necessary to replace them with the 8th and 9th stages, so the 10th stage is replaced with the top stage.

第4ステップ・・・第3図(d)から第3図(e) 前回のデータを考慮すると第3番目との間に5間隔が
生じているので、ベイキャントロード再配置が行われ、
最上段と3段目が入れ替えられ、その間隔は3となる。
4th step ... FIG. 3 (d) to FIG. 3 (e) Considering the previous data, since 5 intervals have occurred between the 3rd and the 3rd, bay cant road rearrangement is performed,
The top row and the third row are swapped, and the interval is 3.

第5ステップ・・・第3図(e)から第3図(f) 最上段と7段目の間に5間隔が生じているので、ベイ
キャントロード再配置が行われ、5段目と7段目が入れ
替えられる。
Fifth step ... FIG. 3 (e) to FIG. 3 (f) Since there are 5 intervals between the uppermost stage and the 7th stage, bay cant road rearrangement is performed and the 5th stage and 7th stage. The steps are replaced.

第6ステップ・・・第3図(f)から第3図(g) 5段目と10段目の間に4間隔が生じているので、ベイ
キャントロード再配置が行われ、9段目と10段目が入れ
替えられる。
6th step: Fig. 3 (f) to Fig. 3 (g) Since there are 4 intervals between the 5th and 10th stages, the bay cant road is rearranged and the 9th stage The 10th row is replaced.

以上第1ステップから第6ステップの並び替え処理に
より第1オプションに関する並び替えが完了する。ここ
で、この順序の平準度は前述した式を用いて以下のよう
に算出される。
The rearrangement processing from the first step to the sixth step completes the rearrangement regarding the first option. Here, the levelness of this order is calculated as follows using the above-mentioned formula.

第4図から明らかなように、この段階でオプション1
の間隔に関しては、前日の結果を考慮すると、3間隔が
3つ並んでおり、その間隔の集合は{3、3、3}とな
る。最後の間隔は次の日の順番が決まらないと決定でき
ないので、ここでの平準度を求める対象から外してお
く。生産台数が10でそのうち3台が第1オプション有り
なので最適間隔の集合は{3、2、2}となる。但し、
この集合はその要素の数値を降順で並べるとする。まず
バラツキ評価値は、 G=(3/3+2/3+2/3)/3=0.778 ピークロード評価値は、ピークロード間隔が3なの
で、 H=3/2=1.5 1より大きいからH=1となる。
As you can see from Figure 4, Option 1
Regarding the intervals of, considering the result of the previous day, three intervals are lined up, and the interval set is {3, 3, 3}. The last interval cannot be decided unless the order of the next day is decided, so it is excluded from the target of the levelness here. Since the number of units produced is 10 and 3 of them have the first option, the set of optimal intervals is {3, 2, 2}. However,
This set has numerical values of its elements arranged in descending order. First, the variation evaluation value is G = (3/3 + 2/3 + 2/3) /3=0.778 The peak load evaluation value has a peak load interval of 3, so H = 3/2 = 1.51, so H = 1. .

さらに、バラツキ度評価値の重みWは、最適間隔が3
であるので、 W=1/3=0.333 従って、 平準度=(0.333*0.778+(1−0.333)*1)*100 =93・・・小数点切上げ第1オプションの合格点は60点
であるので、次の第2オプションに関する入れ替え処理
に入るが、ここで先にこの段階での第2オプションの平
準度を第4図を参照して求めると次のようになる。
Further, the weight W of the variation evaluation value has an optimum interval of 3
Therefore, W = 1/3 = 0.333 Therefore, levelness = (0.333 * 0.778 + (1-0.333) * 1) * 100 = 93 ... Rounding up the decimal point The pass point for the first option is 60 points. , The next replacement process for the second option is started. Here, the leveling degree of the second option at this stage is obtained as follows with reference to FIG.

G=(3/3+1/2+1/2)/3=0.667 H=1/2=0.5 W=1/3=0.333 平準度=(0.333*0.667+(1−0.333)*0.5)*100 =56 従って第2オプションの合格点60点を上回っている
が、第2オプションに関してはまだ並び替えを行ってい
ないので、よりよい順序を求めて、ここでは所定の入れ
替えの処理ルーチンを1度行うことにする。
G = (3/3 + 1/2 + 1/2) /3=0.667 H = 1/2 = 0.5 W = 1/3 = 0.333 Levelness = (0.333 * 0.667 + (1-0.333) * 0.5) * 100 = 56 Therefore Although the passing score of the second option is over 60 points, the second option has not been rearranged yet, so a better order is sought, and the predetermined replacement processing routine is performed once here. .

第7ステップ・・・第3図(g)から第3図(h) 2段目と7段目の間に4間隔が生じているので、ベイ
キャントロード再配置が行われ、6段目と7段目が入れ
替えられる。
7th step ... FIG. 3 (g) to FIG. 3 (h) Since there are 4 intervals between the 2nd and 7th steps, the bay cant road is rearranged and the 6th step is performed. The 7th row is replaced.

第8ステップ・・・第3図(h)から第3図(i) 第2オプションに関して、最適間隔3以上の間隔部分
がなくなったので、ピークロード再配置が行われる。最
上段と2段目が連続しているので、この連続を解消す
る。最上段と前回発行分との間及び2段目の下側にも3
間隔が生じているが、ここでは最上段を移動する。7段
目と10段目の間に4間隔が生じているが、7番目と入れ
替えてもまた連続が生じるので、8・9・10番目が入れ
替え対象となるので、その中心である9段目が入れ替え
られることになる。
Eighth step ... FIG. 3 (h) to FIG. 3 (i) With respect to the second option, the peak load rearrangement is carried out because there is no longer the optimum interval 3 or more. Since the top row and the second row are continuous, this continuation is eliminated. 3 between the top row and the last issue, and below the second row
There is a gap, but here we move to the top. There are 4 intervals between the 7th and 10th steps, but even if the 7th step and the 10th step are replaced, continuity occurs again, so the 8th, 9th, and 10th steps are subject to replacement. Will be replaced.

つまり最上段と9段目とが入れ替えられる。第2オプシ
ョンに関しては上位オプションである第1オプションの
制約のため、ここで第7ステップと第8ステップの並び
替え処理により第2オプションに関する並び替えが完了
する。この順序の平準度は上述したように算出すると94
となる。
That is, the top row and the ninth row are interchanged. Since the second option is restricted by the first option, which is a higher-order option, the rearrangement of the second option is completed by the rearrangement processing of the seventh step and the eighth step. The smoothness of this order is 94 when calculated as described above.
Becomes

第2オプションの合格点は50点であるので、次のオプ
ションに関する入れ替え処理に入る。次は第3オプショ
ンに注目する。
Since the passing score for the second option is 50, the replacement process for the next option is started. Next, let's focus on the third option.

第9ステップ・・・第3図(i)から第3図(j) 前回発行分を考慮すると3段目までに5間隔が生じて
いるが第1段目と第2段目が上位オプションをもってい
るため入れ替えることができないので、ここでは最初か
らピークロード再配置が行われる。第3段目と第4段目
が連続となっており、3段より上側の間隔が4段目より
下側の間隔より広いので第3段が移動されることにな
る。第7番目と第10段目との間で4間隔が生じている
が、第7番目を入れ替えると連続となるので第8・9・
10番目が入れ替え対象となり、その中心である第9番が
入れ替えられることになる。つまり第3番目と第9番目
が入れ替えられる。
Step 9: Fig. 3 (i) to Fig. 3 (j) Considering the previous issue, there are 5 intervals up to the 3rd stage, but the 1st stage and the 2nd stage have higher options. Since it cannot be replaced, the peak load relocation is performed from the beginning here. Since the third stage and the fourth stage are continuous and the interval above the third stage is wider than the interval below the fourth stage, the third stage is moved. There are 4 intervals between the 7th and 10th stages, but if the 7th is replaced, it will be continuous, so 8th and 9th.
The 10th will be replaced, and the 9th, which is the center of it, will be replaced. That is, the 3rd and 9th are interchanged.

第10ステップ・・・第3図(j)から第3図(k) 前回発行分を考慮すると4段目までに6間隔が生じて
おり、ベイキャントロード再配置が行われる。しかし第
1番目と第2番は上位オプションを持っているので入れ
替えできないため、第3番と第4番目が入れ替えられ
る。
Step 10: Fig. 3 (j) to Fig. 3 (k) Considering the previously issued amount, 6 intervals have occurred up to the 4th stage, and the bay cant road is rearranged. However, since the 1st and 2nd have upper options and cannot be exchanged, the 3rd and 4th are interchanged.

第11ステップ・・・第3図(k)から第3図(l) 第3オプションに関して、最適間隔3以上の間隔部分
がなくなったので、ピークロード再配置が行われる。第
6番目と第8番目との間だが間隔でかつ第6番目が上位
オプションを持っているので、第8番目を移動すること
にする。第8番目がオプションなしとなると第7番目か
ら第10段目まで4間隔となるが、上位オプションの制約
により第10段目が入れ替えられる。つまり、第8番目と
第10番目が入れ替えられる。
11th step ... FIG. 3 (k) to FIG. 3 (l) With respect to the third option, the peak load rearrangement is performed because there is no space part of the optimum space 3 or more. Since there is an interval between the 6th and the 8th but there is an upper option in the 6th, we will move the 8th. If the 8th option has no options, there will be 4 intervals from the 7th to the 10th tiers, but the 10th tier will be replaced due to the restrictions of the higher options. That is, the 8th and 10th are interchanged.

第3オプションに関しては上位オプションである第1
・2オプションの制約のため、第9ステップから第11ス
テップまでの並び替え処理により第3オプションに関す
る並び替えが完了する。この順序の平準度は92である。
Regarding the third option, the first option, which is a higher option
-Due to the restriction of 2 options, the sorting process from the 9th step to the 11th step completes the sorting for the 3rd option. The level of uniformity of this order is 92.

第2オプションの合格点は40点であるので、次のオプ
ションに関する入れ替え処理に入る。次は第4オプショ
ンに注目する。
Since the passing score for the second option is 40, the replacement process for the next option is started. Next, let's focus on the fourth option.

第12ステップ・・・第3図(l)から第3図(m) 第1段目と第9段目の間に7間隔が生じているが、上
位オプションの制約のためベイキャントロード再配置を
行うことができない。このため、ピークロード再配置が
行われる。第9番目と第10番目が連続しており、第9番
目が上位オプションをもっていることから第9番目が移
動されることになる。第2番目から第8番目までの間隔
において上位オプションの制約にかからない第3番目が
入れ替えの対象として選ばれる。よって第10番目と第3
番目が入れ替えられる。
Step 12 ... Fig. 3 (l) to Fig. 3 (m) There are 7 intervals between the 1st stage and 9th stage, but Bay Canto Road relocation due to the restriction of upper options. Can't do. Therefore, peak load relocation is performed. The 9th and 10th are consecutive, and the 9th has upper options, so the 9th will be moved. In the intervals from the second to the eighth, the third that is not subject to the constraint of the upper option is selected as the replacement target. So 10th and 3rd
The second is swapped.

第4オプションに関しては上位オプションである第1
・2・3オプションの制約のため、このステップの並び
替え処理により第4オプションに関する並び替えが完了
する。この順序の平準度は53となる。
Regarding the 4th option, the 1st which is the higher order option
-Because of the restriction of 2-3 options, the rearrangement processing in this step completes the rearrangement for the fourth option. The level of uniformity of this order is 53.

第4オプションの合格点は30点であるので、次のオプ
ションに関する入れ替え処理に入る。次は第5オプショ
ンに注目する。
Since the passing score for the fourth option is 30, the replacement process for the next option is started. Next, let us focus on the fifth option.

第13ステップ・・・第3図(m)から第3図(n) 前回発行分から第7段目にかけて9間隔が生じている
のでベイキャントロード再配置が行われる。第1段目、
第2番目そして第3番目は上位オプションの制約のため
入れ替えができないため、第4段目と第7段目が入れ替
えられる。
13th step ... FIG. 3 (m) to FIG. 3 (n) Since 9 intervals have occurred from the previous issue to the 7th stage, bay cant road rearrangement is performed. First stage,
Since the second and third items cannot be interchanged due to the restrictions of the upper options, the fourth and seventh columns are interchanged.

第5オプションに関しては上位オプションの制約のた
め、このステップの並び替え処理に加えてさらに並びを
良くする処理ができないが、この順序の平準度は12点で
あり、合格点である20点を下回っている。このため、以
下に示すように上位オプションの制約を緩和して並び替
え処理がおこなわれる。
Regarding the 5th option, due to the restriction of the upper option, it is not possible to further improve the arrangement in addition to the rearrangement processing in this step, but the level of this order is 12 points, which is below the passing point of 20 points. ing. For this reason, the rearrangement processing is performed by relaxing the restrictions of the upper options as shown below.

第14ステップ・・・第3図(n)から第3図(o) 前回発行分から第4段目にかけて6間隔が生じている
ので、制約緩和ベイキャントロード再配置が行われる。
第4番目を最上段と入れ替えて前回発行分との間隔を3
とすれば、第1オプションが連続となり第1オプション
に関する平準度が合格点を割ってしまうので、第4段目
と第2段目が入れ替えられる。この場合は、第2オプシ
ョンの並びは崩れるが、その平準度は合格点である50点
以上となる。
Step 14 ... Fig. 3 (n) to Fig. 3 (o) Since there are 6 intervals from the previous issue to the 4th stage, the constraint relaxation bay cant road relocation is performed.
Replace the 4th with the top row and set the interval from the last issue to 3
In that case, the first option becomes continuous and the levelness regarding the first option falls below the passing score, so that the fourth stage and the second stage are interchanged. In this case, the alignment of the second option will be broken, but the level will be 50 points or more, which is a passing score.

第15ステップ・・・第3図(o)から第3図(p) さらに第9番目が移動されるが、入れ替え対象として
第3番目から第7番目のものを選択するとどの場合も合
格点を満たさないので、上位オプションに関してすべて
の合格点をみたすことになる第8番目を選択し、第9番
目と第8番目が入れ替えられる。その平準度は52とな
る。
Step 15 ... Fig. 3 (o) to Fig. 3 (p) Furthermore, the 9th item is moved, but if you select the 3rd to 7th items to be replaced, the passing score will be given in any case. Since it does not meet, it chooses the 8th, which will meet all passing scores for the top options, and swaps the 9th and 8th. Its levelness is 52.

第5オプションに関する並び替えは処理はこれで完了
し、次のオプションが無いためこれで並び替え処理が最
終的に完了する。
The rearrangement process for the fifth option is now completed, and the rearrangement process is finally completed because there is no next option.

今述べた実施例では、各オプションに注目した並び替
え処理において、ベイキャントロードないしはピークロ
ード再配置が最終まで行われた後平準値を算出している
が、これに代えて、再配置が行われる毎に平準値を算出
し、これが合格点を上回った段階で、すぐ次のオプショ
ンに対する並び替え処理を行うようにすることも可能で
ある。
In the embodiment just described, in the rearrangement process focusing on each option, the level value is calculated after Baycant load or peak load rearrangement has been performed to the end, but instead of this, rearrangement is performed. It is also possible to calculate a standard value every time a request is made and, when it exceeds the passing score, perform the rearrangement process for the next option immediately.

さらに、第3図を用いて説明された例では、生産台数
を10台としていたが、実際の工場においては、その生産
台数は100台から1000台あるいはそれ以上が考えられ
る。この種の生産順序計画システムでは台数が多くなれ
ば累乗的に処理時間が長くなる。これを避けるため、本
発明では、1日分の生産台数をいくつかのブロックに分
割し、各ブロック毎で独立した組立順序を決定し、その
各ブロックをつなぎ合わせることで1日分の組立順序を
決定する。なお、オプションを有する製品を均等にブロ
ックに分割させるにあたって、その製品のオプションを
できるだけ分散させるための簡単で有効な手法として、
第3図に示されているような各製品のオプションの有無
をオプションの優先度の順に表している数列、例えば
“10010"を2進数とみなして、その数値を大きさ順に各
ブロックに振り分けていくことが提案される。又、その
際優先的な納期を持つ製品は最初のブロックに強制的に
割り当てることもできる。
Further, in the example described with reference to FIG. 3, the production number is set to 10, but in an actual factory, the production number may be 100 to 1000 or more. In this type of production order planning system, the processing time increases exponentially as the number of units increases. In order to avoid this, in the present invention, the daily production volume is divided into several blocks, an independent assembly order is determined for each block, and the blocks are connected to each other to construct the assembly order for one day. To decide. In addition, when dividing a product with options evenly into blocks, as a simple and effective method to distribute the options of the product as much as possible,
As shown in Fig. 3, consider the presence or absence of the option of each product in the order of the priority of the option, for example, "10010" as a binary number, and divide the numerical value into each block in order of size. Suggested to go. At that time, the product having the preferential delivery date can be forcibly assigned to the first block.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明に係る組立順序計画システムと組立順序計
画方法の実施例を示し、第1図は全体構成図、第2図は
処理の手順を示すフローチャート、第3図(a)〜
(p)は並び替えの様子を示す説明図、第4図は平準度
計算のための説明図である。 (1)……入力部、(3)……出力部、(4)……並び
換え処理部、(5)……平準度評価部、(51)……ピー
クロード評価部、(52)……バラツキ度評価部、(53)
……平準度算定部、(6)……比較部、(7)……基準
値変更部。
The drawings show an embodiment of an assembly sequence planning system and an assembly sequence planning method according to the present invention. FIG. 1 is an overall configuration diagram, FIG. 2 is a flowchart showing a processing procedure, and FIG.
(P) is an explanatory diagram showing how rearrangement is performed, and FIG. 4 is an explanatory diagram for leveling degree calculation. (1) …… Input section, (3) …… Output section, (4) …… Sorting processing section, (5) …… Levelness evaluation section, (51) …… Peak load evaluation section, (52)… … Variation degree evaluation section, (53)
...... Levelness calculation section, (6) …… Comparison section, (7) …… Reference value change section.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 塚村 恭一 大阪府大阪市浪速区敷津東1丁目2番47 号 株式会社クボタ大阪本社内 (72)発明者 今井 直純 大阪府大阪市浪速区敷津東1丁目2番47 号 株式会社クボタ大阪本社内 (56)参考文献 特開 平1−234142(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Kyoichi Tsukamura, Inventor 1-247 Shikitsu East, Naniwa-ku, Osaka City, Osaka Prefecture Kubota Osaka Head Office (72) Naomi Imai Shiritsu, Naniwa-ku, Osaka City, Osaka Prefecture Higashi 1-24-247 Kubota Osaka Head Office (56) Reference JP-A-1-234142 (JP, A)

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】各種のオプションが付加される製品群を組
み立てる混流生産方式の組立ラインへの投入型式の順番
を計画する組立順序計画システムであって、 複数のオプションから優先度に応じて順次注目すべきオ
プションを選択してこの選択されたオプションが付加さ
れる製品を均等に組立ラインに流すために組立順序の並
び替えを行う並び替え処理部4と、前記選択されたオプ
ションに関して並び替えられた組立順序に対してその平
準度を算定する平準度評価部5と、平準度評価部で算定
された平準度を予め設定されている前記選択されたオプ
ションの基準値と比較して並び替えた順序が満足できる
ものかを判定する比較部6と、前述した並び換え処理部
4、平準度評価部5、比較部6を制御する制御部8とが
備えられるとともに、 前記並び替え処理部4が、前記選択されたオプションに
関してのピークロード中心部と最も広いベイキャントロ
ード中心部の入れ替えを行って行くことで平準化をすす
めていくピークロード入れ替え手段と、注目オプション
のベイキャントロード後方要素と最適な間隔位置の要素
との入れ替えを行っていくことで平準化をすすめていく
ベイキャントロード入れ替え手段、とを備えていること
を特徴とする組立順序計画システム。
1. An assembly sequence planning system for planning the order of models to be put into an assembly line of a mixed-flow production system for assembling a product group to which various options are added, wherein a plurality of options are sequentially focused according to priority. A rearrangement processing unit 4 that rearranges the assembling order so as to evenly distribute the products to which the selected option is added to the assembly line, and the rearrangement is performed with respect to the selected option. A leveling degree evaluation unit 5 for calculating the leveling degree for the assembly sequence, and an order in which the leveling degree calculated by the leveling degree evaluation unit is compared with a preset reference value of the selected option and rearranged. Is provided with the comparison unit 6 for determining whether the above is satisfied, the rearrangement processing unit 4, the leveling degree evaluation unit 5, and the control unit 8 for controlling the comparison unit 6, and The replacement processing unit 4 replaces the peak load center with the widest bay cant load center with respect to the selected option and promotes leveling by promoting the leveling, and the option bay of interest. An assembling order planning system, comprising: bay cant road replacement means for promoting leveling by replacing a rear element of a cant road and an element at an optimal spacing position.
【請求項2】前記制御部8は、ベイキャントロードが発
生している限り、ベイキャントロード入れ替え手段を起
動させ、ベイキャントロードがなくなった時点で、1度
ピークロード入れ替え手段の平準化を行ったのちに、ベ
イキャントロードが生じておれば再度ベイキャントロー
ド入れ替え手段を起動するように並び替え処理部4を制
御することを特徴とする請求項1に記載の組立順序計画
システム。
2. The control unit 8 activates the bay cant load replacement means as long as the bay cant load is generated, and once the bay cant load disappears, the peak load replacement means is leveled once. The assembly sequence planning system according to claim 1, wherein the rearrangement processing unit 4 is controlled so that the bay cant load replacement means is activated again when a bay cant load has occurred.
【請求項3】前記制御部8は、前記選択されたオプショ
ンに注目した並び替え処理の終了後に算定された平準度
が基準値を下回る場合、既に並び替えのために利用され
た優先度の高い上位オプションを有する製品を前記上位
オプションに関する平準度が対応する基準値を上回る限
りにおいて並び替え可能対象として再度並び替え処理を
行うように並び替え処理部4を制御することを特徴とす
る請求項1または2に記載の組立順序計画システム。
3. The control unit 8 has a high priority already used for rearrangement when the level of smoothness calculated after the rearrangement processing focusing on the selected option is below a reference value. The rearrangement processing unit 4 is controlled so that a product having a higher-order option is rearranged as a rearrangeable target as long as the level of flatness regarding the higher-order option exceeds a corresponding reference value. Or the assembly sequence planning system described in 2.
【請求項4】各種のオプションが付加される製品群を組
み立てる混流生産方式の組立ラインへの投入型式の順番
を計画する組立順序計画方法であって、前記方法が、複
数のオプションから優先度に応じて順次注目すべきオプ
ションを選択してこの選択されたオプションが付加され
る製品を均等に組立ラインに流すために組立順序の並び
替えを行なう並び替えステップと、注目オプションに関
して並び替えられた組立順序に対してその平準度を算定
する平準度評価ステップと、平準度評価部で算定された
平準度を予め設定されている該当オプションの基準値と
比較して並び替えた順序が満足できるものかを判定する
比較ステップとから構成されているとともに、 前記並び替えステップが、注目オプションに関してのピ
ークロード中心部と最も広いベイキャントロード中心部
の入れ替えを行って行くことで平準化をすすめていくピ
ークロード入れ替えステップと、注目オプションのベイ
キャントロード後方要素と最適な間隔位置の要素との入
れ替えを行っていくことで平準化をすすめていくベイキ
ャントロード入れ替えステップ、 とを備えている組立順序計画方法。
4. An assembling sequence planning method for planning the order of types to be put into an assembly line of a mixed production system for assembling a product group to which various options are added, wherein the method changes the priority from a plurality of options. According to the selection step, the step of rearranging the assembling order so that the products to which the selected option is added are evenly distributed to the assembly line, Whether the leveling step that calculates the leveling level for the sequence and the leveling level calculated by the leveling evaluation unit are compared with the preset standard value of the corresponding option and the rearranged order is satisfactory And a sorting step for determining the By replacing the center of Bay Canto Road, we will promote the leveling by promoting the leveling, and by replacing the Bay Canto Road rear element of the optional option and the element of the optimal spacing position. An assembling sequence planning method comprising: a bay cant road replacement step for promoting leveling.
JP2188286A 1990-07-16 1990-07-16 Assembly sequence planning system and assembly sequence planning method Expired - Lifetime JP2510338B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2188286A JP2510338B2 (en) 1990-07-16 1990-07-16 Assembly sequence planning system and assembly sequence planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2188286A JP2510338B2 (en) 1990-07-16 1990-07-16 Assembly sequence planning system and assembly sequence planning method

Publications (2)

Publication Number Publication Date
JPH0475836A JPH0475836A (en) 1992-03-10
JP2510338B2 true JP2510338B2 (en) 1996-06-26

Family

ID=16220977

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2188286A Expired - Lifetime JP2510338B2 (en) 1990-07-16 1990-07-16 Assembly sequence planning system and assembly sequence planning method

Country Status (1)

Country Link
JP (1) JP2510338B2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2596050B2 (en) * 1988-03-11 1997-04-02 トヨタ自動車株式会社 Production planning method for mixed production line

Also Published As

Publication number Publication date
JPH0475836A (en) 1992-03-10

Similar Documents

Publication Publication Date Title
AU692929B2 (en) Priority queue filtering system and method of operation
CN109636011B (en) Multi-shift planning and scheduling method based on improved variable neighborhood genetic algorithm
KR100286442B1 (en) Production process control device and production process control method
JP5134601B2 (en) Production schedule creation device
JP4754894B2 (en) Production plan creation method, production plan creation device, and program
JP2510338B2 (en) Assembly sequence planning system and assembly sequence planning method
JP2510337B2 (en) Assembly sequence planning system and assembly sequence planning method
KR20100134057A (en) Course creation system and course creation method
JP2002149223A (en) Production management support system
JP2013171481A (en) Process plan creation system
JP3391261B2 (en) Production planning method and device
Jain A simulation-based scheduling and management information system for a machine shop
CN116451936A (en) Scheduling method, system and storage medium based on genetic algorithm
Zgurovsky et al. Algorithms and software of the four-level model of planning and decision making
JP3119195B2 (en) Production planning device, method, and recording medium recording program for executing the same
JP6096648B2 (en) Production plan creation method, production plan creation program, and production plan creation device
KR101770303B1 (en) Meta heuristic based production planning method considering allocation rate conformance
CN110163402A (en) Determine the method and device of keeper unit in order
JP6477309B2 (en) Steelmaking production schedule creation device, steelmaking production schedule creation method, operation method, and steelmaking product manufacturing method
JP2006155011A (en) Production schedule planning device, and production schedule planning method
JP2005216074A (en) Production plan preparation system, production plan preparation method and program
JP2510313B2 (en) Assembly sequence planning expert system
JP2001076082A (en) System and method for optimizing distribution flow
JPH11245142A (en) Method and device for making production plan
JPH0512303A (en) Production control method for iron and steel industry

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees