JP2023174958A - Creation method of integrating estimate for facility construction and creation supporting device of integrating estimate for facility construction - Google Patents

Creation method of integrating estimate for facility construction and creation supporting device of integrating estimate for facility construction Download PDF

Info

Publication number
JP2023174958A
JP2023174958A JP2023181546A JP2023181546A JP2023174958A JP 2023174958 A JP2023174958 A JP 2023174958A JP 2023181546 A JP2023181546 A JP 2023181546A JP 2023181546 A JP2023181546 A JP 2023181546A JP 2023174958 A JP2023174958 A JP 2023174958A
Authority
JP
Japan
Prior art keywords
data
estimate
cost
terminal
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2023181546A
Other languages
Japanese (ja)
Other versions
JP7466133B2 (en
Inventor
一 庄司
Hajime Shoji
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Firstskill Co Ltd
Original Assignee
Firstskill Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Firstskill Co Ltd filed Critical Firstskill Co Ltd
Priority to JP2023181546A priority Critical patent/JP7466133B2/en
Publication of JP2023174958A publication Critical patent/JP2023174958A/en
Application granted granted Critical
Publication of JP7466133B2 publication Critical patent/JP7466133B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

To provide a creation method of an integration estimate for a facility construction capable of creating the integrating estimate by organizing various data requesting to and submitted by an integrating business office, an agency and the like when a person in charge of facility construction integrates and estimates required equipment, materials and the like for various facilities.SOLUTION: An estimation supporting system is that a person in charge of facility construction responsible for various facility constructions requested by a constructor creates an integration estimate of its facility construction content. The estimation supporting system receives integrated quantity document data in a general-purpose file format from a person-in-charge-of-integration side terminal 20 of a person in charge of integration who requests the integration of various equipment and materials for the facility construction contents and creates them as integrated data in a person-in-charge-of-facility construction side terminal 10. The system receives estimation data in a general-purpose file format from a person-in charge-of-estimation side terminal 30 of a person in charge of estimation who requests to estimate the various equipment, materials and the like based on the integration data and creates the integration estimate by organizing it using these general-purpose file formats. The permission/rejection of a work, the progress of the works such as a work in progress and the work completion for the integration and estimation respectively are sequentially notified and displayed on the person-in-charge-of-facility construction side terminal 10.SELECTED DRAWING: Figure 1

Description

本発明は、主として各種の建築工事において、建築物に付随する各種設備、例えば天井灯等の照明設備、エアコン等の空調設備、水回り等の衛生設備等を施工する設備工事担当業者において、建築物本体の施工者からの依頼で設備工事を担当するときの設備内容の積算に基づく費用の見積を容易に算出し、施工者に提示できるようにした設備工事の積算見積書の作成方法及び設備工事の積算見積書作成支援装置に関する。 The present invention is primarily intended for use by equipment construction contractors who install various types of equipment associated with buildings, such as lighting equipment such as ceiling lights, air conditioning equipment such as air conditioners, and sanitary equipment such as plumbing, etc., in various types of construction work. A method and equipment for creating cost estimates for facility work that allows for easy calculation of cost estimates based on the cost estimate of equipment contents when in charge of facility work at the request of a constructor of the object itself and to present the cost estimate to the constructor. This invention relates to a construction cost estimate creation support device.

従来から、各種建築物の施工に際し、施工を請け負う例えばゼネコンでは躯体本体を担当し、建築物に関連する照明設備、空調設備、衛生設備等はそれぞれの専門業者であるそれぞれの設備工事担当業者である設備工事会社等に請け負わせている。請け負わせるに際し、設備工事会社から提示される工事費用の見積書を検討し、適当と判断される設備工事会社を選定し、発注している。 Traditionally, when constructing various types of buildings, for example, the general contractor who undertakes the construction is in charge of the main structure, and the lighting equipment, air conditioning equipment, sanitary equipment, etc. related to the building are handled by the respective specialist equipment construction companies. The work is outsourced to a certain facility construction company. When contracting out work, we examine construction cost estimates provided by equipment construction companies, select the equipment construction company we deem appropriate, and place orders.

ここで、設備工事会社において見積書を作成するには、建築物の内容・仕様が説明されている図面、要綱書その他を参照し、必要とする各種設備の選定、すなわち機器資材等の数量、仕様、メーカー名、型番その他を積算し、その単価を確認し、総費用を算出して作成している。ただ、近時は建築物の大型化、諸設備の多様化その他によって設備工事会社で建築物それぞれに相当する適切な設備を選定積算し、見積を算出するには各種の積算資料、単価表その他を参照する必要があり、極めて面倒である。 Here, in order to prepare a quotation at a facility construction company, we refer to drawings, outline documents, etc. that explain the contents and specifications of the building, and select the various types of equipment required, that is, the quantity of equipment materials, etc. It is created by adding up specifications, manufacturer name, model number, etc., checking the unit price, and calculating the total cost. However, in recent years, as buildings have become larger and equipment has become more diverse, equipment construction companies have to select and estimate the appropriate equipment for each building, and use various cost estimation materials, unit price lists, etc. to calculate estimates. , which is extremely troublesome.

そのため、設備工事会社では、諸設備の選定積算を専門の積算事務所に依頼し、積算事務所から提供された積算数量調書(いわゆる拾いデータ)に基づき、今度はその費用の見積を、機器資材等を納入する複数の代理店・メーカー等に依頼している。次いで設備工事会社では、代理店等に算出させた見積データを比較対照し、最適な見積価格を提示した代理店等の見積データを採用して、設備工事会社として作成した積算見積書を施工者に提出している。 Therefore, equipment construction companies request a specialized cost estimation office to estimate the selection of various equipment, and based on the estimation quantity record (so-called picked-up data) provided by the estimation office, they then estimate the cost of equipment, materials, etc. We have asked multiple agencies, manufacturers, etc. to deliver such products. Next, the facility construction company compares and contrasts the estimate data calculated by the agency, etc., adopts the estimate data of the agency, etc. that has presented the optimal estimated price, and sends the cost estimate prepared by the facility construction company to the contractor. has been submitted to.

このような設備工事会社から積算依頼された積算事務所にて作成した拾いデータは、積算事務所において独自に採用している積算プログラムによって作成されて提供されている。また、設備工事会社から見積もり依頼された代理店等で作成した見積データは、代理店等において独自に採用している見積プログラムによって同様に作成されて提供されている。そして、設備工事会社においては、積算事務所から提供された拾いデータ、代理店から提供された見積データを自社のコンピュータに入力し、設備工事会社としての積算見積書を作成している。 The collected data created by a cost estimation office that receives a cost estimation request from such an equipment construction company is created and provided by a cost estimation program that is independently adopted by the cost estimation office. Furthermore, the estimate data created by an agency or the like that receives a quotation request from an equipment construction company is similarly created and provided by an estimate program that the agency or the like employs independently. The equipment construction company inputs the collected data provided by the cost estimate office and the estimate data provided by the agency into its own computer, and creates a cost estimate for the equipment construction company.

こうした現状においては、積算事務所の拾いデータ、代理店等の見積データはそれぞれで独自に作成されているから、これらのデータが提供される設備工事会社でもそれらのデータを再度入力し、設備工事会社として独自に整理し、検討している。この設備工事会社における各種データの再入力は、入力ミスが生じやすく、その検証も必要となるから極めて面倒である。 In this current situation, data collected by quantity surveying offices and estimate data provided by agencies, etc. are created independently by each company, so the equipment construction companies that provide these data also have to re-enter the data and perform equipment construction work. The company is organizing and considering the matter on its own. This re-input of various data by the equipment construction company is extremely troublesome because input errors are likely to occur and verification thereof is also required.

そのため、従来から、例えば特許文献1に示される建築積算システムおよびプログラム、特許文献2に示される積算書作成装置及びプログラム、特許文献3に示される設備工事の積算見積装置等が提案されている。特許文献1のシステム・プログラムは、CADデータとして作成された設計図上で指定された入力操作による座標データを利用して、積算に必要な部材数量を算出し、見積書、原価計算書等の建築関連帳票を自動作成するとする。特許文献2の作成装置・プログラムは、設計書ファイルから抽出したテキストデータ、位置情報によって作成した抽出データファイルにおけるテキストデータを、発注者識別情報で特定された積算書テンプレートファイルに埋め込むことで積算書ファイルを作成し、次いで積算基準データベース、単価データベースを参照して算出した見積額を積算書ファイルに書き込むとする。特許文献3の積算見積装置は、CADなどの設計図作成手段によって各設備工事の工事項目毎に材料、数量のデータをメモリーにストアしておき、拾い出し手段によって各機器材料の数量を拾い出して集計手段によって集計表を作成し、別に作成した集計比較表から機器材料を選択、決定し、機器材料毎の合計価格を演算し、見積表を作成するとする。 Therefore, conventionally, for example, a construction cost estimation system and program shown in Patent Document 1, a cost estimate preparation device and program shown in Patent Document 2, a cost estimation device for equipment work shown in Patent Document 3, etc. have been proposed. The system program in Patent Document 1 uses coordinate data specified by input operations on a design drawing created as CAD data to calculate the number of parts required for cost estimation, and prepares estimates, cost statements, etc. Suppose you want to automatically create construction-related documents. The creation device/program of Patent Document 2 creates a cost estimate by embedding text data extracted from a design document file and text data in an extracted data file created based on location information into a cost estimate template file specified by customer identification information. It is assumed that a file is created, and then the estimated amount calculated by referring to the cost estimation standard database and unit price database is written into the cost estimate file. The cost estimation device of Patent Document 3 stores data on materials and quantities for each construction item of each facility work in a memory using a design drawing creation means such as CAD, and picks up the quantity of each equipment material using a pick-up means. It is assumed that a totalization table is created by the totalization means, equipment materials are selected and determined from a separately created total comparison table, the total price of each equipment material is calculated, and an estimate table is created.

特許第6293104号公報Patent No. 6293104 特開2008-299541号公報JP2008-299541A 特開2002-230082号公報Japanese Patent Application Publication No. 2002-230082

ところがこれらの従来の積算、見積作成方法では、特許文献1及び2では設備工事に必要な積算データを作成することであり、積算に基づいての見積算出までは行われない。特許文献3では積算後に見積処理が行われるとしても、一連のプログラムによって実行されるから、例えば積算、見積等を異なる作業者が別個に行う場合には、同一のプログラム等を使用する必要がある。そうすると、積算、見積等の処理をそれぞれの担当者・会社が別個のプログラムを使用して行っている場合には、それらを総合的に纏めるのは困難であり、それぞれを専門業者が各別に行っている現状では実際的ではない。 However, in these conventional cost estimation and estimate creation methods, Patent Documents 1 and 2 only create cost estimation data necessary for facility construction, but do not calculate estimates based on the cost estimation. In Patent Document 3, even if the estimation process is performed after estimation, it is executed by a series of programs, so for example, if different workers perform estimation, estimation, etc. separately, it is necessary to use the same program, etc. . If this is the case, if each person or company uses a separate program to process cost estimates and estimates, it will be difficult to compile them comprehensively. It is not practical in the current situation.

そこで本発明は叙上のような従来存した諸事情に鑑み創出されたもので、建築物における各種の設備工事を施工者から依頼されて、その積算と見積とを設備工事担当者が提示するに際し、例えば専門の積算事務所等に必要とする機器資材等を拾い出す積算を依頼指示し、またその積算データに基づく機器資材等の見積を複数の代理店・メーカー等に依頼指示し、これらからの積算データ、見積書データに基づき所定の積算見積書を作成するとき、積算事務所からの積算データ、また代理店・メーカー等からの見積書データを設備工事担当者において再入力することなく、これらの諸データを利用して容易に作成でき、また見積価格の比較検討によって適正な見積価格として施工者に提示できるようにした設備工事の積算見積書の作成方法及び設備工事の積算見積書作成支援装置を提供することにある。 Therefore, the present invention was created in view of the existing circumstances as described above, and when a builder requests various types of equipment work for a building, the person in charge of equipment work presents cost estimates and estimates. In this case, for example, we request and instruct a specialized cost estimation office etc. to carry out an estimate of the necessary equipment materials, etc., and also request and instruct multiple agents/manufacturers etc. to estimate the equipment materials etc. based on the estimate data. When creating a predetermined cost estimate based on the cost estimate data and quotation data from the cost estimate office, the facility construction staff does not have to re-enter the cost estimate data from the cost estimate office or the quotation data from agents, manufacturers, etc. , a method for creating a cost estimate for facility work that can be easily created using these various data, and a cost estimate for facility work that can be presented to the constructor as an appropriate estimated price by comparing estimated prices. The purpose is to provide a creation support device.

上述した課題を解決するため、本発明にあっては、工事施工者側から依頼された各種設備工事を担当する設備工事担当者がその設備工事内容の積算見積書を作成する見積支援システムであって、設備工事内容の各種機器資材等を積算依頼した積算担当者からの積算数量調書データを汎用データ形式で受領して設備工事担当者における積算データとして作成し、この積算データを基にして各種機器資材等を見積依頼した見積担当者からの見積書データを汎用データ形式で受領し、これらの汎用データ形式によって整理し積算見積書を作成するようにしたことを特徴とする。
見積担当者は複数とし、複数の見積担当者から受領した各見積書データ中の各種機器資材等の諸データを積算データ中の各種機器資材等の諸データとの項目等の突合処理、紐付け処理後に、各種機器資材等の諸データを羅列表示し、比較対照できるようにして構成することができる。
設備工事担当者から積算依頼した積算担当者における積算作業進捗状況、見積依頼した見積担当者における見積作業進捗状況それぞれが、依頼中・受託の諾否・作業中・作業終了・報告それぞれの段階毎の状況が設備工事担当者に更新通知され、把握できるようにして構成することができる。
設備工事担当者は設備工事内容に対応した機器資材等の積算を積算担当者に依頼し、積算担当者による積算データに対応した費用見積を見積担当者に依頼し、見積担当者からの見積書データに基づき積算見積書を作成する見積支援システムであって、設備工事担当者と積算担当者との相互間で、設備工事担当者側端末10においては、設備工事担当者から積算担当者に設備工事内容の物件資料を通知し,機器資材等の拾出しを依頼する積算依頼手段12、積算担当者からの積算数量調書データを受領する積算数量調書受領手段14を備え、積算担当者側端末20においては、設備工事担当者からの物件資料を受領する物件資料受領手段21、作成した積算数量調書を汎用データ形式で送信する積算数量調書送付手段22を備え、設備工事担当者と見積担当者との相互間で、設備工事担当者側端末10は、設備工事担当者から積算データに基づく機器資材等の費用見積を依頼する見積依頼手段16、見積担当者からの見積書データを受領する見積書受領手段18を備え、見積担当者側端末30は、積算データを受領する積算データ受領手段31、作成した見積書データを汎用データ形式で送信する見積書送付手段32を備えて成ることを特徴とする。
設備工事内容の物件資料は、設備工事担当者側端末10で登録物件としてクラウド2上にアップロードされて積算担当者の積算依頼受託と共に積算担当者側端末20によってダウンロード可能にされ、積算担当者作成による積算数量調書データは、クラウド2上にアップロードされて設備工事担当者側端末10によってダウンロード可能にされ、設備工事担当者確認の積算データは、クラウド2上にアップロードされて見積担当者の見積依頼受託と共に見積担当者側端末30によってダウンロード可能にされ、見積担当者による見積書データは、クラウド2上にアップロードされて設備工事担当者側端末10によってダウンロード可能にされるようにしてあり、設備工事担当者側端末10、積算担当者側端末20、見積担当者側端末30それぞれがアップロード手段、ダウンロード手段を備えて成ることで構成することができる。
設備工事担当者側端末10には、複数の見積担当者それぞれからの見積書データを比較対照する見積比較手段19を備え、また、この見積比較手段19では、見積書データは積算データと対照可能とする一覧表示できるようにして構成することができる。
設備工事担当者側端末10には、積算担当者への積算依頼による積算担当者からの受託有無の通知、見積担当者への見積依頼による見積担当者からの受託有無の通知を確認処理する諾否確認手段13,17を備えて構成することができる。
設備工事担当者側端末10には、積算担当者における積算依頼受託の有無、積算作業中、積算終了による積算数量調書の送付通知の積算作業の進捗状況、及び見積担当者における見積依頼受託の有無、見積作業中、見積終了による見積書の送信通知の見積作業の進捗状況を表示する進捗状況確認手段15を備えて構成することができる。
積算担当者側端末20には、積算依頼の受託と共に、設備工事担当者が予めアップロードしてある設備工事内容の物件資料をダウンロードする物件資料受領手段21を備えて構成することができる。
見積担当者側端末30には、見積依頼の受託と共に、設備工事担当者が予めアップロードしてある積算データをダウンロードする積算データ受領手段31を備えて構成することができる。
そして、本発明にあっての設備工事の積算見積書の作成方法の第1は、
各種設備工事において、その設備工事内容の積算見積書を作成する設備工事の積算見積書の作成方法であって、
設備工事担当者側に設置される設備工事者側端末と、積算担当者側に設置される積算担当者側端末と、見積担当者側に設置される見積担当者側端末とがクラウドを介して相互に送受信可能に繋がっており、
設備工事者側端末によって設備工事内容の物件資料が登録物件としてクラウド上にアップロードされ、
アップロードされた物件資料がクラウド上から積算担当者側端末によってダウンロードされ、
積算担当者側端末によって設備工事内容の各種機器資材が積算されて、CSVデータ、エクセル(登録商標)データの汎用データ形式で作成された積算数量調書データがクラウド上にアップロードされ、
アップロードされた積算数量調書データが設備工事担当者側端末によってダウンロードされ、
設備工事担当者側端末によってダウンロードされた積算数量調書データによる積算処理後に前記各種機器資材の積算データとして作成され、この作成された積算データは設備工事担当者側端末によってクラウド上にアップロードされ、
アップロードされた積算データは複数の見積担当者側端末それぞれによってダウンロードされ、
見積担当者側端末によってダウンロードされた積算データを基にして前記の各種機器機材が見積もられて前記の汎用データ形式で作成された見積書データが見積担当者側端末によってクラウド上にアップロードされ、
クラウド上にアップロードされた複数の見積書データは設備工事担当者側端末によってダウンロードされ、
複数の見積書データがダウンロードされた設備工事担当者側端末では、複数の見積書データの各種機器資材の諸データを前記積算データ中の各種機器資材の諸データとの項目の突合処理、紐付け処理後に、各種機器資材の諸データを羅列表示し、比較対照され、
比較対照後に採用される見積額による積算見積書が作成される、
ことを特徴とする。
また、設備工事の積算見積書の作成方法の第2は、
工事施工者側から依頼された各種設備工事を担当する設備工事担当者がその設備工事内容の積算見積書を作成する設備工事の積算見積書の作成方法であって、設備工事内容の各種機器資材をCSVデータ、エクセル(登録商標)データの汎用データ形式で作成された積算数量調書データを基にして積算データとして作成され、この積算データを基にして各種機器資材の見積書データを前記の汎用データ形式によって整理し積算見積書が作成されるようにして成り、
設備工事担当者側に設置される設備工事担当者側端末と、積算担当者側に設置される積算担当者側端末と、見積担当者側に設置される見積担当者側端末とがクラウドを介して相互に送受信可能に繋がっており、
設備工事担当者側端末によって物件登録された物件資料が物件資料アップロード手段によってクラウド上にアップロードされるステップと、
設備工事担当者側端末による積算受託承認済の積算担当者側端末によって物件資料がクラウド上からダウンロードされるステップと、
積算担当者側端末によって、前記の汎用データ形式として整理された前記各種機器資材の積算数量調書データがクラウド上にアップロードされるステップと、
設備工事担当者側端末によって、クラウド上からダウンロードされた積算数量調書データによる積算処理後に各種機器資材の積算データが作成されるステップと、
設備工事担当者側端末における見積依頼手段によって、見積依頼内容を複数の見積担当者側端末に通知表示させるステップと、
設備工事担当者側端末と見積担当者側端末との相互間で、見積依頼の諾否状況が更新表示されるステップと、
見積担当者側端末における積算データ受領手段によって前記積算データが見積担当者側端末にクラウド上からダウンロードされるステップと、
見積担当者側端末における見積書送付手段によってクラウド上に前記各種機器資材の見積書データが前記の汎用データ形式としてアップロードされるステップと、
設備工事担当者側端末において見積書受領手段によってクラウド上からダウンロードされて複数の見積書データそれぞれが保存されるステップと、
設備工事担当者側端末に表示される見積比較画面において、複数の見積書データ中の各種機器資材の諸データを積算データ中の各種機器資材の諸データとの項目の突合処理、紐付け処理後に、各種機器資材の諸データを羅列表示し、見積比較手段によって比較対照できるようにされたステップと、
設備工事担当者側端末において、積算データ、見積書データの比較対照後に採用された見積額でCSVデータによって積算見積書が作成されるステップ、
を備えたことを特徴とする。
そして、本発明にあっての設備工事の積算見積書作成支援装置は、
設備工事担当者側に設置される設備工事担当者側端末と、積算担当者側に設置される積算担当者側端末と、見積担当者側に設置される見積担当者側端末とがクラウドを介して相互に送受信可能に繋がっており、
設備工事担当者側端末は、設備工事内容の物件資料をクラウド上にアップロードし,積算担当者側端末に各種機器資材の拾出しを依頼送信する積算依頼手段、積算担当者側端末からクラウド上にアップロードされたCSVデータ、エクセル(登録商標)データの汎用データ形式の前記各種機器資材の積算数量調書データをクラウド上からダウンロードして受領する積算数量調書受領手段、積算担当者側端末から得た積算数量調書データによる積算処理後に作成された前記各種機器資材の積算データをクラウド上にアップロードして、この積算データに基づく各種機器資材の費用見積を複数の見積担当者側端末に依頼送信する見積依頼手段、見積担当者側端末から前記の汎用データ形式でクラウド上にアップロードされた前記各種機器資材の複数の見積書データをクラウド上からダウンロードして受領する見積書受領手段、複数の見積書データを比較対照する見積比較手段を備えていて、この見積比較手段では、見積書データは積算データと対照可能とする一覧表示でき、比較対照後に採用された見積額でCSVデータによって積算見積書が作成できるようにしてあり、
積算担当者側端末は、設備工事担当側端末からの物件資料をクラウド上からダウンロードして受領する物件資料受領手段、作成した前記各種機器資材の積算数量調書データを前記の汎用データ形式でクラウド上にアップロードすることで送信する積算数量調書送付手段を備え、
見積担当者側端末は、前記積算データをクラウド上からダウンロードすることで受領する積算データ受領手段、作成した前記各種機器資材の見積書データを前記の汎用データ形式でクラウド上にアップロードすることで設備工事担当者側端末に送信する見積書送付手段を備えて、
成ることを特徴とする。
In order to solve the above-mentioned problems, the present invention provides an estimate support system in which a facility construction person in charge of various facility works requested by a construction contractor prepares an estimate for the details of the facility work. Then, the person in charge of equipment construction receives the cost estimation record data in a general data format from the person in charge of cost estimation who requested the cost estimation of various equipment materials, etc. for equipment work, creates it as cost estimation data for the person in charge of equipment construction, and uses this data as the basis for various cost estimation data. The present invention is characterized in that estimate data is received in a general-purpose data format from an estimator who has requested an estimate for equipment materials, etc., and the estimate data is organized in the general-purpose data format to create an estimated estimate.
There will be multiple estimators, and various data such as various equipment materials in each estimate data received from multiple estimators will be compared and linked with various data such as various equipment materials in cost estimate data. After processing, various data such as various equipment and materials can be displayed in a list and configured so that they can be compared and contrasted.
The progress of the cost estimate by the person in charge of the cost estimate who requested the estimate from the person in charge of equipment construction, and the progress of the estimate work by the person in charge of the estimate who requested the estimate, are shown for each stage: requesting, acceptance/rejection of contract, work in progress, work completed, and reporting. It is possible to configure the system so that the status is updated and notified to the person in charge of equipment construction so that it can be understood.
The person in charge of equipment construction requests the person in charge of cost estimation to estimate equipment materials, etc. corresponding to the details of the facility work, requests the person in charge of cost estimation to provide a cost estimate corresponding to the cost estimation data provided by the person in charge of cost estimation, and receives a written estimate from the person in charge of estimate. This is an estimate support system that creates a cost estimate based on data, in which a person in charge of equipment work and a person in charge of cost estimation communicate with each other on the terminal 10 on the side of the person in charge of equipment work. Estimation requesting means 12 for notifying property materials of construction contents and requesting pick-up of equipment materials, etc., and cost estimation quantity record receiving means 14 for receiving quantity quantity record data from the quantity estimater, and a terminal 20 on the side of the quantity estimater. The system is equipped with a property information receiving means 21 for receiving property data from a person in charge of facility construction, and a cost estimate quantity report sending means 22 for transmitting the created cost estimate quantity record in a general-purpose data format. , a terminal 10 on the side of the person in charge of equipment construction, an estimate requesting means 16 for requesting a cost estimate for equipment materials, etc. based on cost estimate data from the person in charge of equipment construction, and an estimate requesting means 16 for receiving estimate data from the person in charge of estimating. The estimator side terminal 30 includes a receiving means 18, an estimate data receiving means 31 for receiving estimate data, and an estimate sending means 32 for transmitting the prepared estimate data in a general-purpose data format. do.
The property data of equipment construction details is uploaded to the cloud 2 as a registered property on the terminal 10 of the person in charge of equipment construction, and is made available for download by the person in charge of cost estimation at the same time as the cost estimate request is accepted by the person in charge of cost estimation, and is created by the person in charge of cost estimation. Estimated quantity record data is uploaded to the cloud 2 and made available for download by the facility construction person's terminal 10, and cost estimation data confirmed by the facility construction person is uploaded to the cloud 2 and sent to the estimator's request for quotation. The data of the estimate by the estimator is uploaded to the cloud 2 and made downloadable by the terminal 10 of the equipment construction worker. The person in charge terminal 10, the person in charge of cost estimation terminal 20, and the person in charge of estimating the terminal 30 may each include an uploading means and a downloading means.
The equipment construction person's terminal 10 is equipped with an estimate comparison means 19 for comparing and contrasting estimate data from a plurality of estimators, and this estimate comparison means 19 allows the estimate data to be compared with cost estimation data. It can be configured so that it can be displayed as a list.
The facility construction person's terminal 10 displays notifications of whether or not a contract has been accepted from the cost estimate person based on an estimate request, and whether or not to confirm and process notifications from the estimator that have received a request for quotation based on a request for quotation. It can be configured to include confirmation means 13 and 17.
The terminal 10 on the equipment construction staff side displays information such as whether or not the person in charge of estimating has accepted an estimate request, the progress of the estimate work such as the notification of sending an estimate quantity record when the estimate is in progress, and whether the estimate request has been accepted by the person in charge of estimating. The present invention may include a progress confirmation means 15 for displaying the progress status of the estimation work during the estimation work and the notification of transmission of the estimate upon completion of the estimation.
The terminal 20 on the side of the person in charge of cost estimation can be configured to include property data receiving means 21 for receiving the cost estimation request and downloading property data on the details of equipment work that has been uploaded in advance by the person in charge of equipment work.
The estimator side terminal 30 can be configured to include an estimate data receiving means 31 that receives an estimate request and downloads estimate data that has been uploaded in advance by the facility construction person.
The first method of creating a cost estimate for facility work according to the present invention is as follows:
A method for preparing cost estimates for equipment work for preparing cost estimates for the contents of equipment work in various types of equipment work, the method comprising:
The equipment installer's terminal installed on the equipment construction worker's side, the cost estimate worker's terminal installed on the estimator's side, and the estimator's terminal installed on the estimator's side are connected via the cloud. They are connected to each other so that they can send and receive data,
The equipment construction worker's terminal uploads the property data of the equipment work to the cloud as a registered property.
Uploaded property materials are downloaded from the cloud by the cost estimate specialist's terminal,
The cost estimate staff's terminal calculates the cost of various equipment and materials for equipment construction, and the cost estimate quantity record data created in general-purpose data formats such as CSV data and Excel (registered trademark) data is uploaded to the cloud.
The uploaded cumulative quantity record data is downloaded by the facility construction worker's terminal,
After the cost estimation process is performed using the cost estimate quantity record data downloaded by the terminal on the equipment construction person's side, it is created as cost estimation data for the various equipment materials, and this created cost estimate data is uploaded to the cloud by the terminal on the equipment construction person's side.
The uploaded cost estimation data is downloaded by each of the multiple estimator side terminals,
The various equipment and equipment are estimated based on the cost estimation data downloaded by the estimator's terminal, and the estimate data created in the general data format is uploaded to the cloud by the estimator's terminal.
Multiple estimate data uploaded to the cloud are downloaded by the facility construction worker's terminal,
On the equipment construction worker's side terminal where multiple pieces of estimate data have been downloaded, item comparison processing and linkage are performed between various data on various equipment materials in the multiple estimate data and various data on various equipment materials in the cost estimate data. After processing, various data on various equipment materials are listed and compared and contrasted.
A cost estimate is created based on the estimated amount adopted after comparison.
It is characterized by
In addition, the second method for creating cost estimates for equipment construction is:
A method of preparing cost estimate for facility work in which a person in charge of various facility works requested by the construction contractor prepares a cost estimate for the content of the facility work. is created as cost estimate data based on cost estimate quantity record data created in general-purpose data formats such as CSV data and Excel (registered trademark) data, and based on this cost estimate data, quotation data for various equipment and materials is converted into the above-mentioned general-purpose data format. The data is organized according to the format and a cost estimate is created.
The facility construction worker's terminal installed at the equipment construction worker's side, the cost estimation worker's terminal installed at the cost estimation worker's side, and the estimator's terminal installed at the estimator's side are connected via the cloud. are connected to each other so that they can send and receive data,
a step in which the property data registered by the equipment construction worker's side terminal is uploaded to the cloud by the property data uploading means;
a step in which property materials are downloaded from the cloud by a terminal on the equipment construction person's side that has been approved for the cost estimation contract;
a step in which the cost estimate quantity record data of the various equipment materials organized in the general-purpose data format is uploaded to the cloud by a terminal on the side of the cost estimate person;
A step in which cost estimation data for various equipment materials is created after cost estimation processing using cost estimate quantity record data downloaded from the cloud by a terminal on the side of the facility construction worker;
a step of notifying and displaying the contents of the quotation request on a plurality of estimator side terminals by the quotation requesting means on the equipment construction person side terminal;
a step in which the approval/disapproval status of the quotation request is updated and displayed between the equipment construction person's side terminal and the estimating person's side terminal;
downloading the cost estimate data to the estimator's side terminal from the cloud by the cost estimate data receiving means on the estimator's side terminal;
uploading the estimate data for the various equipment and materials onto the cloud in the general-purpose data format by the estimate sending means on the estimator's terminal;
a step in which a plurality of pieces of estimate data are each downloaded from the cloud by an estimate receiving means on a facility construction worker's side terminal, and each of the plurality of estimate data is saved;
On the quotation comparison screen displayed on the equipment construction worker's terminal, the data for various equipment materials in multiple quotation data is compared and linked with the data for various equipment materials in the cost estimation data. , a step of displaying various data of various equipment materials in a list and making it possible to compare and contrast using an estimate comparison means;
A step in which a cost estimate is created using CSV data using the estimated amount adopted after comparing and contrasting the cost estimate data and the quotation data on the facility construction worker's side terminal;
It is characterized by having the following.
The equipment construction cost estimate creation support device according to the present invention includes:
The facility construction worker's terminal installed at the equipment construction worker's side, the cost estimation worker's terminal installed at the cost estimation worker's side, and the estimator's terminal installed at the estimator's side are connected via the cloud. are connected to each other so that they can send and receive data,
The facility construction worker's terminal uploads the property data of the facility construction work onto the cloud, and sends a request to the cost estimation specialist's terminal to pick up various equipment materials. A cost estimate quantity record receiving means for downloading and receiving the quantity record data of the various equipment and materials in the general data format of uploaded CSV data and Excel (registered trademark) data from the cloud, and a cost estimate obtained from the terminal on the side of the person in charge of quantity estimation. A request for quotation that uploads the cost estimate data of the various equipment materials created after the cost estimation process using the bill of quantities data to the cloud, and sends a request to multiple estimators' side terminals for cost estimates for the various equipment materials based on this cost estimate data. means, an estimate receiving means for downloading and receiving from the cloud a plurality of estimate data for the various equipment and materials uploaded from the estimator's terminal in the general-purpose data format to the cloud; Equipped with an estimate comparison means for comparison, this estimate comparison means can display a list of estimate data that can be compared with cost estimate data, and can create a cost estimate using CSV data with the estimated amount adopted after comparison. It is as follows,
The cost estimation person's side terminal has a property information receiving means that downloads and receives property materials from the equipment construction staff terminal from the cloud, and downloads the created cost estimate quantity report data for the various equipment materials onto the cloud in the general-purpose data format. Equipped with a means to send cumulative quantity records by uploading them to
The estimator's side terminal receives the cost estimation data by downloading the cost estimation data from the cloud, and uploads the created quotation data for the various equipment and materials to the cloud in the general-purpose data format. Equipped with a means to send an estimate to the construction worker's terminal,
It is characterized by becoming.

以上のように構成された本発明に係る設備工事の積算見積書の作成方法及び設備工事の積算見積書作成支援装置にあって、施工者からの各種設備工事に関する機器資材等の費用見積を依頼された設備工事担当者において、その機器資材等の積算を専門の積算事務所の如き積算担当者に依頼し、また費用見積を代理店・メーカーの如き見積担当者に依頼するとき、それらとの資料、諸データその他の収受を円滑にし、また積算作業、見積作業の進捗状況を設備工事担当者において逐次に把握させる。
積算数量調書及び見積書による諸データは、汎用データ形式として設備工事担当者において入手させ、設備工事担当者側端末10によるこれらの諸データの再入力を不要にさせると共に、諸データの確認、検討、更には複数の見積書における機器資材等に対する見積額その他の比較対照を容易にさせる。
積算担当者においては、設備工事担当者からの積算依頼に対しての受託と共に、物件資料受領手段21によって工事内容の物件資料を受領でき、積算作業の進捗状況は設備工事担当者において進捗状況確認手段15によって把握でき、積算数量調書送付手段22は設備工事担当者に積算数量調書データを受領可能にさせる。
見積担当者においては、設備工事担当者からの見積依頼に対しての受託と共に、積算データ受領手段31によって積算すべき機器資材等の諸データを受領でき、見積作業の進捗状況は設備工事担当者において進捗状況確認手段15によって把握でき、見積書送付手段32は設備工事担当者に見積書データを受領可能にさせる。
複数の見積担当者からの見積書は、設備工事担当者において見積比較手段19において互いの見積額を比較対照させ、積算担当者による積算データとの各項目をも対照確認させ、提示された見積額のうちの適正なものを採用して、施工者に提出する積算見積書を作成させる。
In the method for creating a cost estimate for equipment work and the support device for creating a cost estimate for equipment work according to the present invention configured as described above, it is possible to request cost estimates for equipment materials, etc. related to various types of equipment work from a constructor. When a person in charge of equipment construction work requests an estimate for equipment materials, etc. from a specialist estimator, such as an estimate firm, or an estimator, such as an agent or manufacturer, for a cost estimate, it is necessary to communicate with them. Facilitates the collection of materials, data, and other materials, and allows equipment construction personnel to keep track of the progress of cost estimation work and estimation work.
Various data from the cost estimate quantity record and the estimate are obtained by the person in charge of equipment construction in a general-purpose data format, making it unnecessary to re-enter these data on the terminal 10 on the side of the person in charge of equipment construction, and making it possible to confirm and study the various data. Furthermore, it facilitates comparison and comparison of estimated amounts for equipment materials, etc. in multiple estimates.
The person in charge of cost estimation can accept the request for cost estimation from the person in charge of equipment construction, and also receive the property materials of the construction details through the property information receiving means 21, and the progress of the cost estimation work can be checked by the person in charge of equipment construction. The data can be grasped by means 15, and the cumulative quantity record sending means 22 enables the person in charge of equipment construction to receive the cumulative quantity record data.
The person in charge of estimating can accept requests for quotation from the person in charge of equipment construction, as well as receive various data such as equipment materials to be estimated through the estimation data receiving means 31, and the progress of the estimation work can be reported to the person in charge of equipment construction. The progress confirmation means 15 can grasp the progress status, and the estimate sending means 32 allows the person in charge of equipment construction to receive the estimate data.
When receiving estimates from multiple estimators, the person in charge of equipment construction compares and contrasts the estimated amounts with each other using the estimate comparison means 19, and also compares and confirms each item with the cost estimate data provided by the estimator, and then compares and contrasts each item with the cost estimate data provided by the estimator. Select the appropriate amount and have the contractor prepare a cost estimate to submit to the contractor.

本発明は以上説明したように構成されているため、例えば建築物における各種の設備工事に必要な機器資材等を積算し、見積もるとき、例えば専門の積算事務所等に機器資材等を拾い出す積算を依頼指示して得た積算データ、またその積算データに基づく機器資材等の見積を複数の代理店・メーカー等に依頼指示して得た見積書データに基づき所定の積算見積書を作成するとき、積算データ、見積書データ等を設備工事担当者において再入力することなく、これらの諸データを利用して容易に作成でき、また見積価格の比較検討によって適正な見積価格として施工者に提示することができる。 Since the present invention is configured as described above, for example, when estimating and estimating equipment materials necessary for various facility works in a building, e.g. When creating a predetermined cost estimate based on the cost estimate data obtained by requesting and instructing multiple agencies, manufacturers, etc. to request and instruct estimates for equipment materials, etc. based on the cost estimate data. , cost estimation data, estimate data, etc. can be easily created using these data without having to be re-entered by the person in charge of equipment construction, and the appropriate estimated price can be presented to the constructor by comparing estimated prices. be able to.

尚、上記の課題を解決するための手段、発明の効果の項それぞれにおいて付記した符号は、図面中に記載した構成各部を示す部分との参照を容易にするために付した。本発明は、これらの記載、図面中の符号等によって示された構造・形状等に限定されない。 It should be noted that the reference numerals added in each of the sections ``Means for Solving the Problems'' and ``Effects of the Invention'' are added to facilitate reference to the parts indicating each component described in the drawings. The present invention is not limited to the structure, shape, etc. shown by these descriptions or the symbols in the drawings.

本発明を実施するための一形態を示す概要図である。FIG. 1 is a schematic diagram showing one embodiment of the present invention. 同じく設備工事担当者と積算担当者との間における積算作業を説明する積算フロー図である。It is a cost estimation flowchart explaining the cost estimation work between the person in charge of equipment construction and the person in charge of cost estimation. 同じく設備工事担当者と見積担当者との間における見積作業を説明する見積フロー図である。It is also an estimation flow diagram illustrating estimation work between a person in charge of equipment construction and a person in charge of estimating. 同じく設備工事担当者側端末における工事物件作業画面例図であり、物件一覧画面が表示されている。It is also an example of a construction object work screen on the equipment construction person's side terminal, and a property list screen is displayed. 同じく設備工事担当者側端末における代理店一覧画面例である。This is also an example of an agency list screen on the equipment construction worker's terminal. 同じく設備工事担当者側端末における商材代理店メーカー選択画面例図である。It is also an example diagram of a product agent manufacturer selection screen on the equipment construction worker's side terminal. 同じく設備工事担当者側端末における物件詳細画面例図である。Similarly, it is a diagram showing an example of a property details screen on a terminal on the side of a person in charge of equipment construction. 同じく設備工事担当者側端末における資料アップロード画面例図である。It is also a diagram showing an example of a document upload screen on a terminal on the side of a person in charge of equipment construction. 同じく設備工事担当者側端末における物件担当者を設定する受信メール設定画面例図である。FIG. 7 is a diagram illustrating an example of a received email setting screen for setting a person in charge of a property on a terminal on the side of a person in charge of equipment construction. 同じく設備工事担当者側端末における仕訳選択画面例図である。Similarly, it is a diagram showing an example of a journal entry selection screen on the terminal on the side of the person in charge of equipment construction. 同じく設備工事担当者側端末における資料送付&見積依頼画面例図である。It is also an example of a screen for sending materials and requesting an estimate on a terminal on the side of the person in charge of equipment construction. 同じく設備工事担当者側端末における見積依頼画面例図である。It is also an example of an estimate request screen on the equipment construction person's side terminal. 同じく設備工事担当者側端末における仕訳分類一覧画面例図である。It is also an example of a journal entry classification list screen on the facility construction worker side terminal. 同じく設備工事担当者側端末における依頼先選択画面例図である。It is also an example diagram of a request destination selection screen on the facility construction worker side terminal. 同じく設備工事担当者側端末における依頼状況画面例図である。It is also a diagram showing an example of a request status screen on a terminal on the side of the person in charge of equipment construction. 同じく設備工事担当者側端末における積算依頼画面例図である。It is also an example diagram of an estimate request screen on the terminal on the side of the person in charge of equipment construction. 同じく積算担当者側端末における積算物件作業画面例図である。It is also an example of a cost estimation property work screen on the terminal on the side of the cost estimation person. 同じく積算担当者側端末における積算作業ステータス画面例図である。FIG. 7 is a diagram showing an example of the cost estimation work status screen on the terminal on the side of the person in charge of cost estimation. 同じく積算担当者側端末における材料入力画面例図である。Similarly, it is a diagram showing an example of a material input screen on the terminal on the side of the person in charge of cost estimation. 同じく積算担当者側端末における比較表画面例図である。It is also a diagram showing an example of a comparison table screen on the terminal on the side of the person in charge of cost estimation. 同じく設備工事担当者側端末における依頼先選択画面において数量送付後の商材取扱代理店一覧表中の履歴欄のプラグ表示例図である。It is also a diagram showing an example of the display of a plug in the history column in the list of agents handling the product after the quantity has been sent on the request destination selection screen on the terminal on the side of the person in charge of equipment construction. 同じく見積担当者側端末における見積物件作業画面例図である。It is also an example of an estimate property work screen on the estimator side terminal. 同じく見積担当者側端末における見積作業ステータス画面例図である。FIG. 4 is a diagram illustrating an example of an estimate work status screen on the estimator's terminal. 同じく見積担当者側端末における見積作業画面例図である。FIG. 4 is a diagram illustrating an example of an estimation work screen on the estimator's terminal. 同じく設備工事担当者側端末における工事見積作業画面例図である。FIG. 7 is a diagram illustrating an example of a construction estimate work screen on a terminal on the side of a person in charge of equipment construction. 同じく設備工事担当者側端末における比較代理店一覧表が表示されている見積比較画面例図である。FIG. 7 is an example of an estimate comparison screen on which a comparison agency list is displayed on the equipment construction worker's terminal. 同じく設備工事担当者側端末における項目突合画面例図である。It is also an example of an item matching screen on the facility construction worker's side terminal. 同じく設備工事担当者側端末における見積比較表例図である。It is also an example diagram of an estimate comparison table on a terminal on the side of the person in charge of equipment construction. 同じく設備工事担当者側端末における見積比較画面において、見積比較表及び未割当データ一覧表が合わせて表示されて、紐付け作業を実施するときの画面例図である。FIG. 10 is a diagram showing an example of a screen when an estimate comparison table and an unallocated data list are displayed together on the estimate comparison screen on the equipment construction worker's side terminal to perform linking work. 同じく設備工事担当者側端末におけるグレードリスト表示画面例図である。FIG. 6 is a diagram illustrating an example of a grade list display screen on the facility construction worker side terminal. 同じく設備工事担当者側端末におけるグレードリスト金額入力画面例図である。It is also an example diagram of a grade list amount input screen on the terminal on the side of the person in charge of equipment construction. 同じく設備工事担当者側端末における項目突合処理、グレード入力処理後における更新見積比較表画面例図である。It is a screen example of the updated estimate comparison table after the item matching process and the grade input process on the equipment construction worker side terminal. 同じく設備工事担当者側端末における見積を採用した際のチドリ選択結果表示画面例図である。Similarly, it is a diagram showing an example of a plover selection result display screen when an estimate is adopted on the terminal on the side of the person in charge of equipment construction. 同じく設備工事担当者側端末における項目名採用画面例図である。It is also a diagram showing an example of an item name adoption screen on a terminal on the side of a person in charge of equipment construction. 同じく設備工事担当者側端末における資料ダウンロード画面例図である。It is also a diagram showing an example of a document download screen on a terminal on the side of a person in charge of equipment construction.

(概要)
以下、図面を参照して本発明を実施するための一形態を説明すると、図において示される符号1は本発明に係る見積支援システムであり、この見積支援システムは、設備工事担当者(設備工事会社という)において設置される設備工事担当者側端末10、積算担当者(積算事務所という)において設置される積算担当者側端末20、代理店・メーカー等の見積担当者(代理店等という)において設置される見積担当者側端末30との間で連携して使用される。
(overview)
Hereinafter, one embodiment of the present invention will be described with reference to the drawings. Reference numeral 1 shown in the drawings is an estimate support system according to the present invention. A terminal 10 on the side of a person in charge of equipment construction installed at a company (referred to as a company), a terminal 20 on the side of a person in charge of cost estimation installed at a person in charge of cost estimation (referred to as a cost estimation office), a terminal 20 on the side of an estimater installed at a person in charge of estimating at an agency, manufacturer, etc. (referred to as an agency, etc.) It is used in conjunction with the estimator side terminal 30 installed in the estimator.

ビル、工場、マンションその他の各種建築物の施主、施工業者、例えばいわゆるゼネコンが施工するに際し、その建築物に伴う例えば天井灯等の照明設備、エアコン等の空調設備、水回り等の衛生設備等を、これらを施工する設備工事会社に発注するとき、それらの設備の施工に要する各種機器、資材その他を積算し、その費用見積が施工者に提示される。依頼された設備工事会社では、それぞれの各種の設備内容に詳しい専門の積算事務所に、その建築物に必要とされる機器、資材その他の検討、選定、数量等の拾い出しを依頼するのであり、積算数量調書(拾いデータ)として積算事務所から提出させる。次いで、設備工事会社では、積算数量調書における拾いデータによる機器資材等の資材内容及び数量等による費用見積を、複数の代理店等に依頼指示し、これらの代理店等から提示された見積額を比較対照し、機器資材等毎あるいは代理店等毎によって提示された見積額から採用した適正な見積額を基にして、設備工事会社において積算見積書が作成されて、施工者に提示される。 When a building, factory, condominium, or other building owner or contractor, such as a so-called general contractor, constructs a building, lighting equipment such as ceiling lights, air conditioning equipment such as an air conditioner, sanitary equipment such as plumbing, etc. When an order is placed with a facility construction company to construct these facilities, the various equipment, materials, and other items required to construct those facilities are estimated and a cost estimate is presented to the constructor. The requested equipment construction company requests a specialized quantity surveying firm that is familiar with each type of equipment to examine, select, and determine the quantities of equipment, materials, and other equipment required for the building. , to be submitted by the cost estimation office as an estimate quantity report (pickup data). Next, the equipment construction company requests and instructs multiple agencies, etc. to estimate the cost based on the contents and quantities of equipment materials, etc. based on the data collected in the cost estimate quantity report, and then calculates the estimated amount presented by these agencies, etc. A cost estimate is prepared by the facility construction company based on a comparison and contrast, and an appropriate estimate adopted from the estimates presented by each equipment, material, etc. or each agency, etc., and presented to the builder.

なお、設備工事会社において、設備工事の内容に応じ、電気設備関係、空調設備関係、衛生設備関係その他のそれぞれを個別に、あるいは全体を担当させることもあり、これらは施工者、設備工事会社間で任意に定められる。本明細書においては、特に説明しない限り、いずれの場合にも設備内容の機器資材等によって区別される必要はないから、全設備の積算見積に適用可能である。 Depending on the content of the equipment work, the equipment construction company may be in charge of electrical equipment, air conditioning equipment, sanitary equipment, etc., individually or in total. arbitrarily determined. In this specification, unless otherwise specified, in any case there is no need to distinguish between the equipment and materials of the equipment content, so it can be applied to the cumulative estimate of all equipment.

設備工事会社、積算事務所、代理店等は、設備工事会社が用意するクラウド2上の作業エリアを介して、例えば電子メールによって各種の資料データが相互間で送受信される。図1に示すように、設備工事担当者側端末10、積算担当者側端末20、及び見積担当者側端末30がクラウド2を介して繋がっている。そして、それぞれにおけるパソコン、タブレット等の電子機器端末に対する入力操作で、所定の各種データの発注、入手、提示その他が例えばクラウド2に対するアップロード、クラウド2からのダウンロードによってできるようになっていて、閉鎖環境にある作業エリアには所定のID、パスワードによってアクセスできる。なお、本発明においては、このクラウド2を介して設備工事担当者側端末10、積算担当者側端末20、見積担当者側端末30それぞれの間で通知連絡がなされるも、クラウド2を介さずに電子メール等を介して直接に通知連絡、送受信することも可能である。 Equipment construction companies, quantity surveying offices, agents, and the like exchange various material data with each other by e-mail, for example, via a work area on the cloud 2 prepared by the equipment construction company. As shown in FIG. 1, a terminal 10 on the equipment construction staff side, a terminal 20 on the estimating staff side, and a terminal 30 on the estimating staff side are connected via the cloud 2. Input operations on electronic device terminals such as personal computers and tablets at each site allow ordering, obtaining, presenting, and other various types of predetermined data by, for example, uploading to and downloading from the cloud 2, in a closed environment. The work area can be accessed using a predetermined ID and password. In addition, in the present invention, although notifications and communications are made between the equipment construction person's terminal 10, the cost estimation person's terminal 20, and the estimator's side terminal 30 via the cloud 2, the communication is not made via the cloud 2. It is also possible to directly contact, send and receive notifications via e-mail etc.

また、設備工事会社から積算事務所への積算依頼は、図2に示す積算フロー図にあるように、設備工事会社の設備工事担当者側端末10と積算事務所の積算担当者側端末20との間での通知、連絡等によって積算作業が進捗される。設備工事会社から代理店等への見積依頼は、図3に示す見積フロー図にあるように、設備工事会社の設備工事担当者側端末10と代理店等の見積担当者側端末30との間での通知、連絡等によって見積作業が進捗される。 In addition, as shown in the cost estimation flow diagram shown in Figure 2, an estimate request from an equipment construction company to an estimate office is sent to a terminal 10 on the side of the person in charge of equipment construction at the equipment construction company and a terminal 20 on the side of the person in charge of estimate at the cost estimate office. The cost estimation work progresses through notifications and communications between the parties. A request for quotation from an equipment construction company to an agency, etc. is made between a terminal 10 on the equipment construction company's equipment construction staff side and a terminal 30 on the estimator's side of the agency, etc., as shown in the quotation flow diagram shown in Figure 3. The estimate work progresses through notifications and communications.

積算作業によって得られる積算数量調書の機器資材等の各拾いデータは積算データとして、見積作業によって得られる複数の見積書の機器資材等に対する見積金額のデータは見積データとして設備工事担当者側端末10において受領され、これらの確認、所定の加工によって積算見積書として纏められる(図1参照)、 Each piece of data on equipment materials, etc. in the cost estimate quantity record obtained through the cost estimation work is stored as cost estimation data, and data on estimated amounts for equipment materials, etc. in multiple quotations obtained through the estimation work is stored as quotation data on the facility construction worker's side terminal 10. The cost estimate is received through confirmation and predetermined processing (see Figure 1).

(設備工事担当者側端末)
先ず、設備工事担当者側端末10では、上記作業エリアへのアクセスが許可されたときに、図4に示すように、設備工事会社用に用意されている設備工事担当者側端末10において工事物件作業画面100が、物件一覧画面110と共に表示される。
(Terminal on equipment construction staff side)
First, when access to the above-mentioned work area is permitted, the facility construction worker side terminal 10 displays the construction object on the facility construction worker side terminal 10 prepared for the facility construction company, as shown in FIG. A work screen 100 is displayed together with a property list screen 110.

この工事物件作業画面100では、その作業選択域101に「物件一覧」、「物件登録」、「利用者メンテナンス」、「代理店取扱商材設定」等のメニューが表示されている。工事物件作業画面100中に区画表示した作業指示域102に、後述するように登録された工事物件毎に登録内容を確認表示できるように指示するボタンが配置されている。例えば詳細内容を表示させる「詳」、積算内容を表示させる「積」、見積内容を表示させる「見」、複数の見積内容を対比させている「比」、積算あるいは見積を依頼発注した際の記録を表示させる「出」、積算見積を提示した物件を表示させる「完」等の各ボタンが配置されている。 In this construction property work screen 100, menus such as "Property List", "Property Registration", "User Maintenance", and "Agent Materials Settings" are displayed in the work selection area 101. In a work instruction area 102 displayed in sections on the construction object work screen 100, buttons are arranged to instruct the user to confirm and display the registered contents for each registered construction object, as will be described later. For example, ``Details'' displays detailed contents, ``Sumi'' displays cost estimate contents, ``See'' displays quotation contents, ``Ratio'' compares multiple quotation contents, and when requesting or ordering cost estimate or quotation. Various buttons are arranged, such as ``Exit'' to display records, and ``Complete'' to display properties for which cost estimates have been presented.

また、工事物件作業画面100には、登録された物件の全部あるいはその一部である作業中の案件、完了した物件を絞り込んで一覧表示させる物件絞込表示域103が設けられている。この物件絞込表示域103では、プルダウンメニューで表示される「全て」、「作業中」、「完了」のいずれかの選択設定によって、絞込条件に対応した物件が抽出されて一覧表示できるようにしてある。 Further, the construction property work screen 100 is provided with a property narrowing display area 103 that narrows down and displays a list of ongoing projects and completed projects that are all or part of the registered properties. In this property narrowing display area 103, properties corresponding to the narrowing conditions are extracted and displayed in a list by selecting one of "All", "Working", and "Completed" displayed in the pull-down menu. It is set as.

(代理店取扱商材の設定)
工事物件に関連する機器資材それぞれにつき、代理店等にそれらの見積を依頼するとき、代理店等によっては取り扱う機器資材(商材ともいう)が種々に異なっている。そのため、必要として予定する商材の代理店等を予め整理し、データベースとして設備工事担当者側端末10に事前に登録しておくのであり、工事物件作業画面100における前記作業選択域101中から「代理店取扱商材設定」をクリック選択する。
(Setting of products handled by agents)
When requesting an estimate from an agent for each piece of equipment and materials related to a construction property, the equipment and materials (also referred to as merchandise) that the agent handles vary depending on the agent. For this reason, agents for the necessary and planned materials are organized in advance and registered as a database in the equipment construction person's terminal 10. From the work selection area 101 on the construction work screen 100, Click to select “Agent handling product settings”.

この選択によって、図5に示すように、代理店一覧画面120が表示され、「表示名」、「会社名」、「担当者名」、「取扱商材」の各欄が代理店表示行毎に設けられていて、取扱商材欄に表示されている「設定」ボタンのクリックによって、図6に示すように、商材代理店メーカー選択画面121が表示される。この商材代理店メーカー選択画面121には、商材表122が一覧表示されており、「削除」、「編集」、「コード」、「商材名称」、「取扱」の各欄が商材行毎に設けられており、代理店等が取り扱う商材行の取扱欄中にチェックマークを入力すればよい。 As a result of this selection, the agency list screen 120 is displayed as shown in FIG. By clicking on the "Settings" button provided in the ``Settings'' button displayed in the handling products field, a product agency manufacturer selection screen 121 is displayed as shown in FIG. This product agency manufacturer selection screen 121 displays a list of product tables 122, and each column of "Delete", "Edit", "Code", "Product name", and "Handling" is A check mark is provided for each line, and a check mark can be entered in the handling column of the product line handled by the agent, etc.

なお、この商材代理店メーカー選択画面121中に表示されていない、新規の商材は上部に区画表示されている仕訳追加域123において、商材のコードをコード欄に、商材名称を名称欄にそれぞれ入力し、仕訳追加ボタン124のクリックによって商材表122の下部等に追加表示されるようになっている。また、商材を削除する場合には削除欄中に表示される削除ボタンの、あるいは商材内容を編集する場合には編集欄中に表示される「編集」ボタンのクリックによって行えるようにしてあり、これらの入力作業後では、更新ボタン125のクリックによって保存される。 For new products that are not displayed on the product agency manufacturer selection screen 121, enter the code of the product in the code field and the name of the product in the journal addition area 123 displayed in the upper section. By inputting the information in each column and clicking the journal addition button 124, the information is added and displayed at the bottom of the product list 122, etc. Additionally, if you want to delete a product, you can click the delete button displayed in the deletion field, or if you want to edit the content of the product, you can click the "edit" button displayed in the edit field. , After these input operations, the data is saved by clicking the update button 125.

(物件登録)
そして、設備工事会社においては、施工者から設備工事が依頼されたとき、その建築物等に係る工事内容を物件登録する(ステップ1/S1)。物件登録には、設備工事担当者側端末10における前記工事物件作業画面100中の作業選択域101に表示の「物件登録」を選択すると、登録物件の詳細が表示される物件詳細画面130が表示され、物件内容の概要となる各項目を入力するようになっている。
(Property registration)
When a facility construction company receives a request for facility construction from a builder, it registers the details of the construction work related to the building, etc. (step 1/S1). To register a property, select "Property Registration" displayed in the work selection area 101 of the construction property work screen 100 on the equipment construction person's terminal 10, and a property details screen 130 will be displayed that displays details of the registered property. and enter each item that provides an overview of the property details.

この物件詳細画面130は、図7に示すように、施工業者名である会社名である「会社名」、「担当部署」、「担当者名」、「工事番号」、「工事件名(積事・代理店通知)」、機器資材等によって異なる期限が設定される場合の複数の提出納期である「積事宛提出納期A材」、「積事宛提出納期B材」、「作成日時」、「提出金額」等の必要項目欄に所定事項が入力されて、登録される。これらは積算見積すべき設備工事毎に作成され、施工者から提供された工事内容の詳細である例えば図面、要綱書等の物件資料は、設備工事担当者側端末10において別にファイルされている。なお、この登録された物件の詳細は、図4における作業指示域102における「詳」ボタンのクリックによって、表示される物件詳細画面130によって確認できるようになっている。 As shown in FIG. 7, this property details screen 130 includes "company name," which is the company name that is the construction contractor's name, "department in charge," "name of person in charge," "construction number," and "construction case name (project name)."・Agent Notification)", multiple submission deadlines when different deadlines are set for equipment materials, etc., "Material A submission deadline to the distributor", "Material B submission deadline to the distributor", "Creation date and time", Predetermined items are entered in the necessary item fields such as "submitted amount" and registered. These are created for each piece of equipment work to be estimated, and property materials such as drawings and outline documents, which are details of the work provided by the builder, are filed separately on the equipment work person's terminal 10. Note that the details of the registered property can be confirmed on the property details screen 130 that is displayed by clicking the "Details" button in the work instruction area 102 in FIG.

物件詳細画面130において登録された物件毎に入力された所定事項は、前記物件一覧画面110における物件一覧表111として、その入力された必要とする所定事項が各欄に表示された物件行毎に整理して表示される(図4参照)。この物件一覧表111においては、その登録物件毎の設備工事会社内における各作業の進捗状況がその進捗状況に応じて逐次表示されるようにしたステータス欄112が設けられており、設備工事担当者側端末10において、それらの進捗状況が表示確認できるようにしている。例えば、「未作業」、「見積」、「完了」その他が登録物件毎に進捗状況に応じて通知表示される。 The predetermined items entered for each registered property on the property details screen 130 are used as the property list table 111 on the property list screen 110, and the input required predetermined items are displayed for each property line displayed in each column. They are organized and displayed (see Figure 4). In this property list 111, a status column 112 is provided in which the progress status of each work within the equipment construction company for each registered property is displayed sequentially according to the progress status. On the side terminal 10, the progress status can be displayed and confirmed. For example, notifications such as "unfinished work", "estimate", "completed", etc. are displayed according to the progress status of each registered property.

(物件資料のアップロード)
設備工事担当者側端末10では、この物件一覧表111において、施工者から提供された図面・要綱書等の登録物件毎の物件資料を選択して物件資料アップロード手段11によってクラウド2上にアップロードできる(ステップ2/S2)。作業指示域102の「詳」ボタンのクリックによって表示される前記物件詳細画面130中に配置されている添付資料のアップロードを指示するアップロード指示ボタン131の「こちら」をクリックすることで、図8に示すように、表示される資料アップロード画面140上の操作によってアップロードできるようにしている。アップロード操作によって、クラウド2上の作業エリアにおける登録物件毎に区分された領域に保存されることでアップロードが完了する。
(Upload of property materials)
On the facility construction worker side terminal 10, property data for each registered property such as drawings and outline documents provided by the builder can be selected from the property list 111 and uploaded to the cloud 2 by the property data upload means 11. (Step 2/S2). By clicking "Click here" of the upload instruction button 131 that instructs to upload attached documents placed in the property details screen 130 displayed by clicking the "Details" button in the work instruction area 102, the screen shown in FIG. As shown, uploading can be performed by operating the displayed material upload screen 140. By the upload operation, the upload is completed by being saved in an area divided for each registered property in the work area on the cloud 2.

この資料アップロード画面140には、設備工事担当者側端末10に保存されている物件資料を選択する「アップロードファイル選択」、設備工事会社における担当者を設定する「受信メール設定」のボタンが配置されている作業指示域141が設けられ、アップロードした物件資料を表示するファイル表142が表示されている。ファイル表142には、ファイル行毎に「ファイル名」、「ファイルサイズ」、「アップロード日時」、「送付先選択」、「送信履歴」を表示する各欄が設けられ、またファイルを削除するよう、チェックマークが入力される削除用ボタンが用意されている。 This material upload screen 140 includes buttons for "upload file selection" for selecting property materials stored in the facility construction worker's terminal 10 and "receiving email settings" for setting the person in charge at the facility construction company. A work instruction area 141 is provided, and a file table 142 displaying uploaded property materials is displayed. The file table 142 has columns for displaying "file name", "file size", "upload date and time", "destination selection", and "transmission history" for each file line, and also for displaying "file name", "file size", "upload date and time", "destination selection", and "transmission history". , a delete button is provided where a check mark is entered.

(設備工事会社における登録物件毎の担当者の設定)
物件資料のアップロード後、設備工事担当者側端末10において、「受信メール設定」ボタンのクリックによって、設備工事会社ではその登録物件を担当して、積算事務所、代理店等との連絡、例えば受託、完了メール等を受信する係としての内部の物件担当者(主担当、副担当、資材手配担当者等)を設定できるように、図9に示される受信メール設定作業画面145が用意されている。
(Setting of person in charge for each registered property at equipment construction company)
After uploading the property information, by clicking the "Receive email settings" button on the terminal 10 on the side of the equipment construction worker, the equipment construction company will be in charge of the registered property and will be able to communicate with the quantity surveying office, agency, etc., for example. A reception email setting work screen 145 shown in FIG. 9 is prepared so that an internal person in charge of the property (main person in charge, deputy person in charge, person in charge of material arrangement, etc.) can be set as the person in charge of receiving completion emails, etc. .

すなわち、この受信メール設定作業画面145では、「選択」、「会社名」、「ユーザー名」、「メールアドレス」等の各欄が設けられている受信担当者表146が表示されており、積算担当者側端末20や見積担当者側端末30からの受託・完了メール等を受信する物件担当者を設定できる。この設定は、選択欄中にチェックマークを入力し、更新ボタンのクリックでダイヤログ表示される確認画面で更新確認すればよいものである。 That is, on this received mail setting work screen 145, a receiving person table 146 is displayed, which has columns such as "selection", "company name", "user name", "email address", etc. A person in charge of the property can be set to receive consignment/completion emails, etc. from the person in charge terminal 20 or the estimator side terminal 30. To make this setting, simply enter a check mark in the selection field and confirm the update on the confirmation screen that appears in a dialog when you click the update button.

このようにして、設備工事担当者側端末10において、登録物件毎の各種情報の登録が完了したことの確認によって、用意されている「更新」ボタンをクリックすることで、登録物件の現状、進捗状況が逐次に更新されて保存される。 In this way, by confirming that the registration of various information for each registered property has been completed on the equipment construction staff terminal 10, by clicking the "Update" button provided, the current status and progress of the registered property can be updated. The status is updated and saved sequentially.

(積算事務所、代理店等のデータベース)
一方、以上のような物件登録とは別に、積算事務所それぞれにおける諸情報、代理店等それぞれにおける担当者名、そのメールアドレスを含む各種情報が積算事務所データ、代理店等データとして、設備工事担当者側端末10におけるそれぞれのデータベースに登録保存されている。設備工事担当者側端末10においてこれらにアクセスすることでそれぞれのデータが表示されると共に、メールアドレスに基づき電子メールで通知できるようにしてある。
(Database of cost estimation offices, agents, etc.)
On the other hand, apart from the property registration as described above, various information including various information at each quantity surveying office, the name of the person in charge at each agency, etc., and their email address is collected as quantity surveying office data, agency data, etc. It is registered and saved in each database in the person-in-charge side terminal 10. By accessing these on the terminal 10 on the side of the person in charge of equipment construction, each data is displayed, and notification can be sent by e-mail based on the e-mail address.

(積算依頼時の代理店等への事前通知)
設備工事会社が積算事務所に積算を依頼するに際し、積算後に見積を依頼する予定がある、通常は複数の代理店等には、設備工事担当者側端末10によって、必要な選択した物件資料を予め送付しておくのであり、代理店等においては事前に検討できるようにしている(ステップ3/S3)。
(Advance notification to agency, etc. when requesting cost estimate)
When a facility construction company requests an estimate from a cost estimation office, it usually sends the necessary selected property materials to multiple agencies, etc., from which it plans to request estimates after the cost estimate, using the terminal 10 on the facility construction person's side. The information is sent in advance so that the agency or the like can consider it in advance (Step 3/S3).

この事前送付処理は、設備工事担当者側端末10において、図8に示される資料アップロード画面140のファイル表142における送付先選択欄に配置されている選択ボタンのクリックによって表示される、見積依頼確認メッセージの確認によって処理される。見積依頼確認があると、図10に示すように、仕訳選択画面150が表示され、この仕訳選択画面150には、商材である品名が行形式で表示された仕訳分類表151が用意されている。この仕訳分類表151に設けられた商材品名毎の「選択」、「仕訳分類」の各欄において、選択欄中にチェックマークを入力し、次へボタン152をクリックすることで、図11に示すように、それらの商材を取り扱っていて依頼できる代理店等のみが一覧表示されている資料送付&見積依頼画面160が表示される。 This pre-sending process is performed by confirming the quotation request, which is displayed by clicking the selection button located in the destination selection field in the file table 142 of the material upload screen 140 shown in FIG. Processed by message confirmation. When the quotation request is confirmed, a journal selection screen 150 is displayed as shown in FIG. 10, and this journal selection screen 150 includes a journal classification table 151 in which product names, which are commercial materials, are displayed in row format. There is. In the "selection" and "journal classification" columns for each product name provided in this journal classification table 151, enter a check mark in the selection field and click the next button 152 to display the screen shown in FIG. As shown, a material sending and quotation request screen 160 is displayed that lists only the agencies that handle these products and can be requested.

この資料送付&見積依頼画面160では、作業指示域161に「資料送付&見積依頼画面」、「全選択」、「アップロード一覧に戻る」等のボタンが配置されており、共通事項反映域162には、「共通見積期限日」、「共通見積期限時間」、「共通コメント」等の項目と共にそれらの各事項を任意入力する入力部を配置してある。また、送付先、見積を依頼できる代理店等の代理店一覧表163が表示されており、「選択」、「履歴」、「依頼先」、「見積期限日」、「見積期限時間」、「コメント」、「取扱商材」、「送信履歴」、「ダウンロード日時」の各欄が、依頼先欄に表示された代理店等毎に行表示されている。 In this material sending & quotation request screen 160, buttons such as "material sending & quotation request screen", "select all", and "return to upload list" are arranged in the work instruction area 161, and in the common matter reflection area 162. In addition to items such as "common quotation deadline date," "common quotation deadline time," and "common comment," there is an input section for optionally inputting each of these items. In addition, an agency list 163 such as shipping destinations and agencies from which quotations can be requested is displayed, including "selection", "history", "request destination", "estimate deadline date", "estimate deadline time", " The columns ``Comment'', ``Products handled'', ``Transmission history'', and ``Download date and time'' are displayed in rows for each agency etc. displayed in the request destination column.

資料送付&見積依頼画面160において、共通事項反映域162における各項目の入力部に入力した内容等は、共通事項反映ボタン164のクリックによって代理店一覧表163における「見積期限日」、「見積期限時間」、「コメント」の各欄に反映入力され、必要に応じて代理店等毎に変更入力することも可能である。反映・変更入力後、依頼すべき代理店等の選択欄中にチェックマークを入力し、作業指示域161中の「資料送付&見積依頼画面」ボタンをクリックすることで、これの確認画面で再確認することで送付処理が行われる。送付処理が終了すると、代理店一覧表163の送信履歴欄に送信日時が自動入力されると共に、代理店等の見積担当者側端末30から受託通知があり、それを承認すると履歴欄に「受託承認済み」が表示されるようになっている。 On the document sending & quotation request screen 160, the contents entered in the input section of each item in the common matter reflection area 162 can be changed to "Quotation deadline date" and "Quotation deadline date" in the agency list 163 by clicking the common matter reflection button 164. The information is reflected in the "Time" and "Comment" columns, and can be changed and entered for each agency, etc., if necessary. After inputting the reflection/changes, enter a check mark in the selection field of the agency, etc. to request, and click the "Send materials & quotation request screen" button in the work instruction area 161 to re-enter the confirmation screen. Upon confirmation, the sending process will be performed. When the sending process is completed, the sending date and time will be automatically entered in the sending history column of the agency list 163, and a acceptance notification will be sent from the estimator's terminal 30 at the agency. "Approved" will now be displayed.

なお、代理店等によっては、資料送付のみを行うこともあり、図8において示された前記資料アップロード画面140において、送付先選択欄中の「選択」ボタンのクリックによって表示される確認画面中で、資料送付と共に見積依頼をするか、資料送付のみとするかが選択できるようにしてある。 Note that some agencies may only send materials, and in the confirmation screen displayed by clicking the "Select" button in the destination selection field on the material upload screen 140 shown in FIG. , you can choose whether to request a quote along with sending the materials, or just send the materials.

また、代理店等に送付する資料に関連する追加資料、変更資料等がある場合、設備工事担当者側端末10によって、それらをアップロードファイル選択によって指示し、送付すべき代理店等、またコメント等をコピーすることで、追加送付でき、その送信日時は代理店一覧表163の送信履歴を表示する履歴欄に自動的に反映入力されるようにしてある。 In addition, if there are additional materials, changed materials, etc. related to the materials to be sent to agencies, etc., they can be instructed by uploading file selection on the terminal 10 on the equipment construction staff side, and the agency, etc. to be sent, comments, etc. By copying , additional sending can be made, and the sending date and time is automatically reflected and entered in the history column displaying the sending history of the agency list 163.

(代理店等への仕訳分類毎の個別依頼)
また、工事物件に関する資料送付、その見積依頼を複数の代理店等に対して一括して行う場合に限らず、特定の代理店等に対して個別に依頼することもできる。この個別依頼は、設備工事担当者側端末10において、図4に示される工事物件作業画面100における作業指示域102の「見」ボタンのクリックによって、図12に示すように、表示される見積依頼画面170によって処理操作される。
(Individual requests for each journal classification to agencies, etc.)
In addition, it is not limited to sending materials related to construction objects and requesting estimates to multiple agencies all at once, but it is also possible to make individual requests to specific agencies, etc. This individual request is a request for quotation that is displayed as shown in FIG. 12 by clicking the "View" button in the work instruction area 102 on the construction object work screen 100 shown in FIG. Processing operations are performed using the screen 170.

この見積依頼画面170は、「見積依頼」、「工事項目取込」のボタンが配置されている作業指示域171が区画表示されており、工事項目表172、見積依頼中一覧表173が表示されている。「見積依頼」ボタンのクリックによって、図13に示すように、仕訳分類一覧画面180が表示される。この仕訳分類一覧画面180には、仕訳分類一覧表181が設けられており、図10に示された仕訳分類表151に基づく仕訳分類に従い商材等の「仕訳分類」、「代理店選択」、「依頼済」、「依頼済代理店名」、「送付」、「図面送付代理店名」等の各欄が設けられている。依頼する仕訳分類の商材に該当する代理店選択欄中に表示されている「設定」ボタンをクリックすると、図14に示すように、依頼先選択画面190が表示される。 In this quotation request screen 170, a work instruction area 171 in which buttons for "request quotation" and "import construction items" are arranged is displayed as a section, and a construction item table 172 and a list of quotation requests 173 are displayed. ing. By clicking the "Request Estimate" button, a journal classification list screen 180 is displayed as shown in FIG. 13. This journal classification list screen 180 is provided with a journal classification list 181, in which "journal classification", "agency selection", etc. of merchandise, etc. are performed according to the journal classification based on the journal classification table 151 shown in FIG. Columns such as "Requested", "Requested Agency Name", "Sending", and "Drawing Sending Agency Name" are provided. When the user clicks the "setting" button displayed in the agency selection column corresponding to the requested journal classification product, a request destination selection screen 190 is displayed as shown in FIG. 14.

この依頼先選択画面190には、「見積依頼」、「一時保存」、「一時保存反映」、「取扱代理店表示」、「全代理店表示」、「閉じる」の各ボタンが配置されている作業指示域191が区画表示されており、「取扱代理店表示」ボタンのクリックによって、仕訳分類に従ってそれらの商材を取り扱う代理店等の商材取扱代理店一覧表192が表示されるようになっている。この商材取扱代理店一覧表192には、「仕訳分類」、「選択」、「履歴」、「依頼先」、「見積期限日」、「見積期限時間」、「代理店希望日時」、「コメント」、「代理店コメント」等の各欄が、仕訳分類の商材行それぞれで表示されるように設けられている。 This request destination selection screen 190 has buttons such as "Request for quotation", "Temporary save", "Temporary save reflection", "Display handling agencies", "Display all agencies", and "Close" buttons. The work instruction area 191 is divided and displayed, and by clicking the "Display handling agency" button, a list 192 of product handling agencies such as agencies that handle those products according to the journal classification is displayed. ing. This product handling agency list 192 includes "journal classification", "selection", "history", "request destination", "estimate deadline date", "estimate deadline time", "desired agency date and time", " Columns such as "Comment" and "Agent Comment" are provided so as to be displayed for each product line of the journal classification.

この商材取扱代理店一覧表192において、依頼をする代理店等の選択欄中にチェックマークを入力すると共に、見積期限日欄、見積期限時間欄、コメント欄にそれらの所定事項・内容を入力して、作業指示域191の「見積依頼」ボタンをクリックする。そうすると、見積依頼した代理店等に見積依頼したことが電子メールによって通知される。なお、代理店等によっては取り扱っていない商材があるところ、取扱商材以外であっても依頼することの確認のダイヤログ画面が用意されており、また「一時保存」ボタン、「一時保存反映」ボタン等によって、作業中処理の一時保存、その解除による作業続行ができるようにしてある。 In this product handling agent list 192, enter a check mark in the selection column of the agency you are making a request to, and enter the specified items and contents in the quotation deadline date column, quotation deadline time column, and comment column. Then, click the "Request for quotation" button in the work instruction area 191. Then, you will be notified by e-mail that you have requested a quote from the agency, etc. that requested the quote. Please note that some agencies, etc. do not handle some products, so a dialog screen is prepared to confirm that you are making a request even if the product is not handled by the agency. ” button, etc., it is possible to temporarily save the process being worked on, and to continue the work by canceling it.

図13に示される仕訳分類一覧画面180において配置されている依頼状況ボタン182をクリックすると、図15に示すように、依頼状況画面1010が表示され、「CSV出力」、「戻る」の各ボタンが配置されている作業指示域1011が区画表示されていると共に、依頼状況一覧表1012が設けられている。依頼状況一覧表1012には、「工事番号」、「件名」、「仕訳分類」、「履歴」、「依頼先」、「見積期限日時」、「代理店希望日時」、「コメント」、「代理店コメント」等の各欄が仕訳分類の商材それぞれで表示されるようになっている。なお、「CSV出力」ボタンのクリックによって、これらの依頼状況をCSV形式によって一覧表示することも可能にしてある。 When you click the request status button 182 located on the journal classification list screen 180 shown in FIG. 13, a request status screen 1010 is displayed as shown in FIG. 15, and the "CSV output" and "back" buttons are displayed. The arranged work instruction area 1011 is displayed in sections, and a request status list 1012 is provided. The request status list 1012 includes "construction number", "subject", "journal classification", "history", "request party", "estimate deadline date and time", "preferred agency date and time", "comments", and "agent Each column such as ``Store Comment'' is displayed for each item in the journal classification. It is also possible to display a list of these request statuses in CSV format by clicking the "CSV output" button.

以上に説明したように、設備工事会社においては、設備工事担当者側端末10を使用して、工事物件の積算依頼に関連して、見積を依頼する予定がある代理店等に事前に物件資料を送付しておくのであり、その事前送付に際し、工事に必要とする商材に対応して、これらを取り扱う代理店等が選択される。この事前の送付は、代理店等データベースによって一覧表示されている代理店等の中から、設備工事会社が選択した代理店等のみに送付され、設備工事担当者側端末10では、その送付資料、送付先が記録され、通知された代理店等では見積担当者側端末30によって物件資料をダウンロードでき、その受領は設備工事担当者側端末10に通知表示される。 As explained above, equipment construction companies use the terminal 10 on the side of the equipment construction staff to send property information in advance to agencies, etc. from which they plan to request an estimate, in connection with requests for estimates for construction properties. When sending the materials in advance, the agency that handles them is selected depending on the materials needed for the construction work. This advance sending is sent only to the agency, etc. selected by the equipment construction company from among the agencies, etc. listed in the agency database, and the equipment construction person's terminal 10 displays the materials to be sent, The delivery destination is recorded, and the notified agency or the like can download the property materials using the estimator's terminal 30, and a notification of receipt thereof is displayed on the equipment construction worker's terminal 10.

(積算事務所への積算依頼)
積算依頼は、図4に示される工事物件作業画面100に表示されている物件一覧画面110において、積算依頼すべき物件のリストと共に表示される作業指示域102における「積」ボタンのクリックによって、図16に示すように、表示された積算依頼画面1020の各項目中の選択、入力によって行われる(積算ステップ1/AS1)。この積算依頼画面1020では、積算依頼ボタン1021、コメント入力部1022が配置されており、積算事務所データベース中の積算事務所が一覧表示される積算事務所一覧表1023が表示されている。この積算事務所一覧表1023には、「選択」、「会社名」、「状況」の各欄が積算事務所表示行毎に設けられている。さらに、積算依頼した積算事務所が表示される積算依頼中一覧表1024が積算事務所一覧表1023の下部に表示されており、「取消」、「会社名」、「状況」、「更新」の各欄が設けられている。
(Request for cost estimation to cost estimation office)
A cost estimation request can be made by clicking the "Built" button in the work instruction area 102 displayed together with the list of properties for which cost estimation is to be requested on the property list screen 110 displayed on the construction property work screen 100 shown in FIG. As shown in 16, this is done by selecting and inputting each item on the displayed integration request screen 1020 (integration step 1/AS1). On this cost estimation request screen 1020, a cost estimation request button 1021 and a comment input section 1022 are arranged, and a cost estimation office list 1023 is displayed in which a list of cost estimation offices in the cost estimation office database is displayed. In this cost estimation office list 1023, columns of "selection", "company name", and "situation" are provided for each cost estimation office display line. Furthermore, a list 1024 of requesting cost estimation offices that displays cost estimation offices that have requested cost estimation is displayed at the bottom of the list of cost estimation offices 1023, and the options for "cancellation", "company name", "status", and "update" are displayed. Each column is provided.

そして、依頼すべき積算事務所の選択欄にチェックマークを入力し、積算依頼ボタン1021をクリックすると、積算依頼中一覧表1024の会社名欄に該当の積算事務所名が表示され、状況欄には依頼中のフラグが更新表示されると共に、その積算事務所には積算依頼手段12によって電子メール等で通知される。また、状況欄中では、その積算事務所からの諾否の通知内容を表示する待機した状態となる。 Then, if you enter a check mark in the selection column of the cost estimation office to request and click the cost estimation request button 1021, the name of the corresponding cost estimation office will be displayed in the company name column of the list of requesting cost estimation 1024, and the name of the corresponding cost estimation office will be displayed in the status column. The requesting flag is updated and displayed, and the cost estimation office is notified by e-mail or the like by the cost estimation requesting means 12. In addition, the status column is in a standby state where the content of the notification of acceptance or rejection from the cost estimate office is displayed.

なお、積算事務所への積算依頼は、1箇所である場合に限らず、複数箇所とすることも可能であり、設備工事担当者側端末10において、複数の積算事務所が表示される積算事務所一覧表1023の中から例えばチェックマークの付記によって選択する。通知後は、それらからの諾否通知を待機している状況が同様に表示される。また、場合によっては特定の積算事務所への積算依頼が確定している場合には、このような積算依頼の諾否の送受信を省略することもある。 Note that the request for cost estimation to a cost estimation office is not limited to one location, but can also be made to multiple locations. A selection is made from the location list 1023, for example, by adding a check mark. After notification, the status of waiting for notifications of acceptance or rejection from them will be displayed in the same way. Furthermore, in some cases, if the request for cost estimation to a specific cost estimation office has been confirmed, the transmission and reception of approval or rejection of the request for cost estimation may be omitted.

(積算事務所における積算依頼の諾否処理)
積算が依頼された積算事務所において、図17に示すように、積算事務所用に用意されている積算担当者側端末20に、積算物件作業画面200が積算物件一覧画面210と共に表示される。積算物件作業画面200には、積算物件作業画面200中に区画表示した作業指示域201に、積算依頼された工事物件毎に積算依頼内容を確認表示できるように指示するボタンが配置されている。例えば積算依頼された工事物件の詳細を表示させる「詳」、積算内訳内容データを選択して取込作業を行う「入」、積算内容の内訳を表示させる「内」、変更前の積算データと変更後の積算データとにおいて、それらの積算の項目番号毎に、変更の有無・内容、数量増減等の差異を一覧表示させる「比」、設備工事会社がアップロードした図面・資料等をダウンロードするための「出」等の各ボタンが配置されている。
(Processing of acceptance or rejection of cost estimation request at cost estimation office)
At the cost estimation office where the cost estimation is requested, as shown in FIG. 17, the cost estimation property work screen 200 is displayed together with the cost estimation property list screen 210 on the cost estimation person's side terminal 20 prepared for the cost estimation office. On the cost estimation property work screen 200, a button is arranged in a work instruction area 201 which is divided and displayed in the cost estimation property work screen 200 to instruct the user to confirm and display the content of the cost estimation request for each construction property for which a cost estimation has been requested. For example, "Details" displays the details of the construction property for which the cost estimate has been requested, "Enter" selects and imports the cost estimate breakdown data, "In" displays the breakdown of the cost estimate contents, and "In" displays the cost estimate data before the change. "Ratio" to display a list of differences such as presence/absence/content of changes, increase/decrease in quantity, etc. for each item number of the cost estimation data after the change, and to download drawings/materials etc. uploaded by equipment construction companies. Each button such as ``out'' is arranged.

また、積算物件一覧画面210には、積算物件一覧表211が表示されており、「作業状況」、「会社名」、「工事番号」、「工事件名」、「提出納期A材」、「提出納期B材」、「変更内容」、「作成日」の各欄が設備工事担当者側端末10における物件一覧画面110と同様に設けられており、積算物件毎にそれらの内容が行表示されるようになっている。 In addition, the cost estimation property list screen 210 displays a cost estimation property list 211, which includes "work status", "company name", "construction number", "construction case name", "submission delivery date A material", "submission Columns such as "Delivery date B material", "Change details", and "Creation date" are provided in the same way as the property list screen 110 on the equipment construction person terminal 10, and their contents are displayed in a line for each cost-intensive property. It looks like this.

前記したように、設備工事会社から積算事務所に積算依頼があると、積算担当者側端末20において、積算物件一覧画面210の積算物件一覧表211における作業状況欄に依頼中のフラグが更新表示される。 As mentioned above, when an equipment construction company makes an estimate request to an estimate office, the requesting flag is updated and displayed in the work status column of the estimate property list 211 on the estimate property list screen 210 on the estimate person's terminal 20. be done.

そこで、積算事務所では、積算担当者側端末20によって、積算依頼の諾否を通知する(積算ステップ2/AS2)。通知に際し、積算物件作業画面200中の作業指示域201における「詳」ボタンのクリックで、図18に示すように、表示される積算作業ステータス画面220において、積算依頼状況が表示される作業状況表示域221、諾否・作業進捗状況等を通知する状況通知域222、設備工事会社への任意の通知文等を入力するコメント入力部223が設けられている。また、この積算作業ステータス画面220には、積算事務所から設備工事会社に送付する積算データその他の資料をクラウド2上にアップロード指示する資料アップロードボタン225も配置されている。 Therefore, at the cost estimation office, the terminal 20 on the side of the person in charge of cost estimation notifies the person of acceptance or rejection of the cost estimation request (cost estimation step 2/AS2). At the time of notification, by clicking the "Details" button in the work instruction area 201 of the cost estimation property work screen 200, the work status display in which the cost estimation request status is displayed on the cost estimation work status screen 220 that is displayed, as shown in FIG. 18. A status notification area 222 for notifying acceptance/rejection, work progress status, etc., and a comment input area 223 for inputting an arbitrary notification message to the equipment construction company are provided. The cost estimation work status screen 220 also includes a material upload button 225 for instructing to upload cost estimation data and other materials to be sent from the cost estimation office to the equipment construction company onto the cloud 2.

そして、作業状況表示域221に「依頼中」であることが表示されている状態で、積算作業を受託する場合には、状況通知域222に例えばプルダウンで表示される「受託」を、辞退する場合には「辞退」のいずれかを選択し、「更新」ボタンをクリックする。受託の場合には、作業状況表示域221に「受託」と更新表示されると共に、この諾否の通知内容は、設備工事担当者側端末10にメール等で通知され、設備工事会社からの承認を待機した承認待ち状態であることが、この積算作業ステータス画面220の作業状況表示域221に更新表示される。 If the work status display area 221 shows "Requesting" and you accept the estimate work, you can decline the "Consignment" that is displayed in the status notification area 222, for example, as a pull-down. If so, select either "Decline" and click the "Update" button. In the case of consignment, "Consignment" is updated and displayed in the work status display area 221, and the content of the notification of approval or rejection is notified by e-mail etc. to the terminal 10 on the side of the equipment construction person, and approval from the equipment construction company is sent. The status of the waiting approval status is updated and displayed in the work status display area 221 of the cumulative work status screen 220.

積算事務所の積算担当者側端末20からの通知は、設備工事会社における設備工事担当者側端末10における諾否確認手段13によって図16に示される前記積算依頼画面1020中の積算依頼中一覧表1024の状況欄に「受託」と表示され、更新欄において表示される「承認」を確認、クリックすることで状況欄では「受託承認済み」と更新表示されるようになっている。設備工事担当者側端末10からの受託承認済みが通知された積算事務所では、積算担当者側端末20によって物件内容の詳細を確認し(積算ステップ4/AS4)、積算担当者側端末20における積算物件一覧画面210中の積算物件一覧表211における作業状況欄に受託承認済みと更新表示される。 The notification from the terminal 20 on the side of the person in charge of cost estimate at the cost estimate office is sent to the request confirmation list 1024 in the cost estimate request screen 1020 shown in FIG. "Consignment" will be displayed in the status column, and by checking and clicking "Approval" displayed in the update column, the status column will be updated to "Consignment approved". At the cost estimation office, which has been notified that the contract has been approved from the equipment construction worker terminal 10, the details of the property are confirmed using the cost estimation worker terminal 20 (cost estimation step 4/AS4). The work status column in the cost-intensive property list 211 on the cost-priced property list screen 210 is updated to indicate that the contract has been approved.

なお、積算依頼された積算事務所において積算作業が受託されずに辞退した場合には、設備工事担当者側端末10において、前記積算依頼中一覧表1024の状況欄に「辞退」と更新表示され、その場合には他の積算事務所の積算担当者側端末20に同様な操作手順によって通知依頼される(積算ステップ3/AS3)。 In addition, if the cost estimation office to which the cost estimation request was made does not accept the cost estimation work and declines, the status column of the cost estimation requesting list 1024 is updated and displayed as "Declined" on the terminal 10 on the side of the person in charge of equipment construction. In that case, a notification request is made to the terminal 20 on the side of the cost estimation staff at another cost estimation office using the same operating procedure (cost estimation step 3/AS3).

(積算事務所における物件資料のダウンロード)
そして、積算物件作業画面200中の作業指示域201における「出」ボタンのクリックによって、設備工事会社がアップロードした図面、要綱書等データである物件資料が物件資料受領手段21によって、ダウンロード可能となっている(積算ステップ5/AS5)。このとき、積算物件一覧表211における作業状況欄には、ダウンロード可能なように受託承認済みのフラグが表示されている。
(Downloading property materials at the cost estimation office)
Then, by clicking the "Out" button in the work instruction area 201 of the cost estimate property work screen 200, the property data such as drawings, outlines, etc. uploaded by the equipment construction company can be downloaded by the property data receiving means 21. (accumulation step 5/AS5). At this time, in the work status column of the cost-intensive property list 211, a flag indicating that the contract has been approved is displayed so that the work can be downloaded.

また、積算担当者側端末20において、図18に示される前記積算作業ステータス画面220における作業状況表示域221では、設備工事会社からの依頼中であることが表示される「依頼中」、受託を承認したときに表示される「受託承認済み」、積算作業中であることが表示される「作業中」その他の積算依頼の進捗状況がそれらに応じて更新表示されるようになっている。また、状況通知域222では、設備工事会社との逐次の連絡に対応して積算作業の受託、その開始、完了等が逐次プルダウン表示されるようにしてあり、作業状況に対応してそれらを選択し、更新することで設備工事担当者側端末10に通知表示されるようになっている。 Furthermore, in the work status display area 221 of the cost estimation work status screen 220 shown in FIG. The progress status of the cost estimate request is updated accordingly, such as "Approved," which is displayed when the request is approved, and "Work in progress," which is displayed when the cost estimate is in progress. In addition, in the status notification area 222, in response to successive communications with equipment construction companies, information such as estimate work entrustment, start, completion, etc. is sequentially displayed in a pull-down manner, and these can be selected according to the work status. By updating, a notification is displayed on the terminal 10 on the side of the person in charge of equipment construction.

(積算作業)
その後、積算事務所では必要な機器資材等を拾い出す積算作業を開始する。例えば積算事務所が採用している諸種の積算プログラムが搭載されている積算事務所内のパソコンその他の端末機器によって積算が行われ、機器資材等の品名、型番、数量、メーカー名その他を一覧表示した諸データとしてまとめた積算数量調書(いわゆる拾いデータ)を作成する(積算ステップ6/AS6)。
(cost estimation work)
After that, the cost estimation office will begin the cost estimation work to pick up the necessary equipment and materials. For example, cost estimation is performed using a computer or other terminal device in the cost estimation office that is equipped with various cost estimation programs adopted by the cost estimation office, and a list of equipment materials, etc., such as product name, model number, quantity, manufacturer name, etc. is displayed. A cumulative quantity record (so-called picked-up data) that is summarized as various data is created (cost estimation step 6/AS6).

積算事務所における積算作業に際し、拾出ルールが一定の表示形式とすることが予め定められており、例えば文字入力、照会記号(設計段階で付与されていて、積算、見積のいずれの段階でも参照可能にしている)、型番及び特注品、メーカー名の略称方法、照会記号が姿図等に記載がない場合の表現方法その他がルール化されている。尚、設備工事会社の設備工事担当者側端末10において各種資材毎にこれらをデータベース化してある場合、各種資材毎に付与されている資材コードを共通して使用することも可能である。 When carrying out cost estimation work at a cost estimation office, it is predetermined in advance that the pick-up rules should be in a certain display format, such as character input, reference symbols (given at the design stage and referenced at both the cost estimation and estimation stages). ), model numbers, custom-made products, how to abbreviate manufacturer names, how to express reference symbols when they are not shown in the figure, etc. have been set as rules. In addition, if these are made into a database for each type of material in the terminal 10 on the side of the person in charge of equipment construction at the equipment construction company, it is also possible to commonly use the material code assigned to each type of material.

(積算数量調書における内訳確認)
拾い出されて作成される積算数量調書による積算データは、積算担当者側端末20において、作業中であれば、図17に示される積算物件一覧表211における作業状況欄に「作業中」としてフラグ表示されているところ、そのアップロードは、作業指示域201中の「入」ボタンのクリックによって作動される積算数量調書送付手段22によってクラウド2上へのアップロート作業が開始される。作業開始に際し、ダイヤログ表示される内訳データ取込画面において、積算データを作成する積算プログラムそれぞれのファイル種別を指定し、表示されている積算データのファイル名から選択した後、「登録」ボタンのクリックによって取り込まれた汎用データ形式となる例えばCSVデータ、エクセル(登録商標)データ等として拾いデータをアップロードする。
(Confirmation of details in cost estimate quantity record)
If the cost estimation data based on the estimated quantity record that is picked up and created is being worked on, it will be flagged as "work in progress" in the work status column of the cost estimation property list 211 shown in FIG. As shown, the upload work to the cloud 2 is started by the cumulative quantity report sending means 22 which is activated by clicking the "Enter" button in the work instruction area 201. When starting work, on the breakdown data import screen that appears in the dialog, specify the file type for each cost estimation program that creates cost data, select from the displayed file names of cost data, and then click the "Register" button. The selected data is uploaded in a general-purpose data format, such as CSV data or Excel (registered trademark) data, which is imported by clicking.

アップロードされたCSVデータによる積算数量調書における内訳内容は、積算担当者側端末20に、図17に示されている積算物件作業画面200における作業指示域201中の「内」ボタンのクリックによって、図19に示すように、表示される材料入力画面230によって確認される(積算ステップ7/AS7)。この材料入力画面230には、照会記号によってチェックする「照会記号チェック表示」、機器仕様によってチェックする「機器仕様チェック」等の各ボタンが用意されたチェック指示域231が区画表示され、更に確認済みを表示するチェックマークを入力する機器仕様確認欄232が設けられている。この材料入力画面230中に表示される材料入力表233には、「項目番号」、「項目名称」、「系統名」、「品名」、「照会記号」、「摘要……」等の各欄が設けられている。 The breakdown contents in the cost estimate quantity record based on the uploaded CSV data can be displayed on the cost estimate person's terminal 20 by clicking the "inside" button in the work instruction area 201 on the cost price work screen 200 shown in FIG. As shown in 19, this is confirmed on the displayed material input screen 230 (accumulation step 7/AS7). This material input screen 230 displays a check instruction area 231 with buttons such as "Inquiry symbol check display" to check by query symbol, "Equipment specification check" to check by equipment specification, etc. An equipment specification confirmation field 232 is provided for entering a check mark to display. The material input table 233 displayed on the material input screen 230 includes columns such as "Item number", "Item name", "Strain name", "Product name", "Inquiry symbol", "Summary...", etc. is provided.

この材料入力画面230においては、積算担当者側端末20によって、クラウド2上にアップロードされた積算数量調書における積算データの内訳内容を確認でき、アップロードした物件毎の拾いデータを一覧表示した状態において、チェック指示域231中の「照会記号チェック表示」ボタンのクリックによって、それらの重複、更には品名・仕様が存在しない場合、エラー対象の資材が拾われている工事項目名称その他が表示される。同じく「機器仕様チェック」ボタンのクリックによって、機器仕様入力のルールに対応していない記述その他が表示される。いずれもその対応を修正することで、再取り込みが行われるようになっている。 On this material input screen 230, you can check the breakdown of the cost estimation data in the cost estimate quantity record uploaded to the cloud 2 using the terminal 20 on the side of the person in charge of cost estimation. By clicking the "Display inquiry symbol check" button in the check instruction area 231, if there are duplicates or product names and specifications do not exist, the name of the construction item for which the material in error is being picked up, etc. will be displayed. Similarly, by clicking the "Device Specification Check" button, descriptions and other information that do not comply with the rules for inputting device specifications are displayed. In either case, re-importing can be done by correcting the response.

また、図17に示される前記積算物件作業画面200における作業指示域201の「比」ボタンのクリックによって図20に示すように、比較表画面240が表示される。この比較表画面240では、「全明細表示」、「CSV出力」、「内訳データ」の各ボタンが配置されている作業指示域241が区画表示されており、また変更履歴内容が表示される変更履歴表示部242が設けられている。 Further, by clicking the "ratio" button in the work instruction area 201 on the cost-intensive property work screen 200 shown in FIG. 17, a comparison table screen 240 is displayed as shown in FIG. 20. In this comparison table screen 240, a work instruction area 241 in which buttons for "display all details", "output CSV", and "breakdown data" are arranged is displayed as a section, and a change history is displayed. A history display section 242 is provided.

そして、積算データが修正その他によって変更されることに伴い、その変更前の積算データと変更後の積算データとを対比して一覧表示する比較表243が設けられている。この比較表243では、変更後積算データ表示部244が例えば左側に、変更前積算データ表示部245が例えば右側に対比されて、例えば積算項目番号毎に行表示されるように並列配置されていると共に、変更表示部域内容の有無・内容、数量増減等を表示する変更内容表示部246を例えば左側端部に、例えば積算項目番号毎の行表示と同様に行表示するようにして配置して成る。変更後積算データ表示部244、変更前積算データ表示部245では、「項目番号」、「項目名称」等の積算内容を表示する各欄が同様に配列されて設けられている。 Then, as the integrated data is changed by correction or the like, a comparison table 243 is provided that compares and displays a list of the integrated data before the change and the integrated data after the change. In this comparison table 243, the post-change cumulative data display section 244 is on the left side, and the pre-change cumulative data display section 245 is on the right side, and they are arranged in parallel so that, for example, a row is displayed for each cumulative item number. At the same time, a change display area 246 for displaying the presence/absence and content of change display area contents, increase/decrease in quantity, etc. is arranged, for example, at the left end in a line display similar to the line display for each cumulative item number. Become. In the post-change cumulative data display section 244 and the pre-change cumulative data display section 245, columns for displaying cumulative contents such as "item number" and "item name" are arranged in the same manner.

また、変更内容表示部246では、「変更内容」、「数量増減」の各欄が設けられており、変更後積算データと変更前積算データとの各欄における表示内容を対比して、変更内容欄では、表示文字列の相違の有無によって変更内容が具体的に表示される。また、数量増減欄では、変更後積算データと変更前積算データとの数量数値の差量を自動計算して、その増減数が表示される。なお、変更後積算データと変更前積算データとの間で、いずれかが存在しない場合には、例えば「右に記載なし」、「左に記載なし」のメッセージが変更内容欄に表示されるようになっている。 In addition, the change content display section 246 is provided with columns for "change content" and "quantity increase/decrease", and the content displayed in each column of the integrated data after change and the integrated data before change is compared, and the changed content is displayed. In the column, the content of the change is specifically displayed depending on whether there is a difference in the displayed character strings. In addition, in the quantity increase/decrease column, the difference in quantity between the post-change integrated data and the pre-change integrated data is automatically calculated, and the increase/decrease is displayed. If either of the post-change cost data and pre-change cost data does not exist, a message such as "No entry on the right" or "No entry on the left" will be displayed in the change details column. It has become.

また、内訳確認と共に、前記積算物件作業画面200において、作業指示域201中の「詳」ボタンのクリックによって表示される前記積算作業ステータス画面220の状況通知域222においてプルダウン表示される「完了」を指定した完了の確認、その「更新」ボタンのクリックによって、汎用データ形式として整理された拾い関連資料である積算数量調書データがクラウド2上にアップロードされる(積算ステップ8/AS8)。 In addition to confirming the details, click the "Complete" pull-down menu in the status notification area 222 of the cost estimate work status screen 220 that is displayed by clicking the "Details" button in the work instruction area 201 on the cost estimate property work screen 200. By confirming the specified completion and clicking the "Update" button, the cumulative quantity record data, which are collection-related materials organized in a general-purpose data format, is uploaded to the cloud 2 (cost estimation step 8/AS8).

(積算事務所から設備工事会社への諸事連絡)
積算担当者側端末20において、前記積算作業ステータス画面220では、積算事務所における各種資料をクラウド2上にアップロードできるようにする前記資料アップロードボタン225が配置されている(図18参照)。この資料アップロードボタン225のクリック操作によって、ダイヤログ表示されるアップロードファイル選択画面に表示される、例えば積算担当者側端末20に格納ファイルされている各種のファイル資料を選択確認し、積算担当者側端末20から設備工事担当者側端末10に対して例えば諸種のファイルをアップロードすることができる。例えば、積算依頼された物件資料である図面、要綱書等に対する質疑事項その他を内容とするファイルを作成したとき、それらを選択してアップロードでき、アップロードされたファイルは設備工事担当者側端末10において確認される。
(Communication of various matters from the quantity surveying office to the equipment construction company)
On the cost estimation work status screen 220 of the cost estimation person's side terminal 20, the material upload button 225 that allows various materials in the cost estimation office to be uploaded onto the cloud 2 is arranged (see FIG. 18). By clicking the material upload button 225, the user selects and confirms various file materials stored in the terminal 20 on the cost estimation person's side, which is displayed on the upload file selection screen displayed in a dialog. For example, various types of files can be uploaded from the terminal 20 to the equipment construction worker side terminal 10. For example, when creating a file containing questions and answers regarding drawings, outline documents, etc. that are property materials for which cost estimation has been requested, you can select and upload them, and the uploaded file can be stored on the equipment construction person's terminal 10. It is confirmed.

(積算事務所における物件資料の変更)
また、積算事務所において積算作業中の調査・確認等に基づいて追加された変更図、追加資料があれば、積算担当者側端末20によって同様にしてクラウド2上にアップロードし、設備工事担当者側端末10に通知表示させるようにすることも可能である。すなわち、資料アップロードボタン225における同様な操作によって、送付するファイルを選択確認し、アップロード操作を行う。
(Changes in property documents at the quantity surveying office)
In addition, if there are any changed drawings or additional materials added based on investigations and confirmations during the cost estimation work at the cost estimation office, they can be uploaded to the cloud 2 using the terminal 20 on the cost estimation staff's side, and then sent to the equipment construction staff. It is also possible to have the side terminal 10 display the notification. That is, by performing a similar operation on the material upload button 225, the user selects and confirms the file to be sent, and performs the upload operation.

(積算事務所から設備工事会社への積算数量調書データのアップロード)
積算担当者側端末20において、図17に示された積算物件作業画面200の作業指示域201に用意されている各ボタンのクリックによって表示された作業手順に従って行われる。積算作業ステータス画面220における状況通知域222にプルダウン表示される「完了」を指定して「更新」ボタンのクリックによってクラウド2上にアップロードされ、積算数量調書送付手段22を介して積算事務所の作業完了が設備工事担当者側端末10に電子メール等によって通知される(積算ステップ9/AS9)。通知されることで、設備工事担当者側端末10における積算数量調書受領手段14によって、アップロードされた積算数量調書データは設備工事担当者側端末10にダウンロード可能となる。このときの積算担当者側端末20においては、例えば照会記号等に誤りがある場合にはその修正を慫慂するメッセージが表示され、その確認を可能にしている。
(Upload of cost estimate quantity record data from quantity surveying office to equipment construction company)
On the cost estimation person's side terminal 20, the work is performed according to the work procedure displayed by clicking each button provided in the work instruction area 201 of the cost estimation property work screen 200 shown in FIG. By specifying “Complete” that is displayed as a pull-down in the status notification area 222 on the cost estimation work status screen 220 and clicking the “Update” button, the work will be uploaded to the cloud 2 and sent to the cost estimation office via the cost estimation quantity report sending means 22. Completion is notified to the terminal 10 on the side of the person in charge of equipment construction by e-mail or the like (accumulation step 9/AS9). By being notified, the uploaded cumulative quantity record data can be downloaded to the equipment construction person terminal 10 by the cumulative quantity record receiving means 14 in the equipment construction person terminal 10 . At this time, on the cost estimation staff terminal 20, if there is an error in the inquiry symbol, for example, a message encouraging correction is displayed to enable confirmation.

(設備工事会社における積算数量調書データの確認)
積算担当者側端末20によってクラウド2上に積算数量調書データがアップロードされたことが通知された設備工事会社では、設備工事担当者側端末10において、図4に示される前記工事物件作業画面100における作業指示域102中の「積」ボタンのクリックによって、図16に示された積算依頼画面1020中に表示されている積算依頼中一覧表1024において、その状況欄に「完了」がフラグ表示され、この「完了」ボタンのクリックによって拾い内容である積算数量調書データを確認できるようにしてある(積算ステップ10/AS10)。そして、この確認の終了によって、積算数量調書データによる積算処理が完了する(積算ステップ11/AS11)
(Confirmation of cost estimate quantity record data at equipment construction company)
At the equipment construction company, which has been notified by the cost estimation person's terminal 20 that the cost estimate quantity record data has been uploaded to the cloud 2, the equipment construction company, which has been notified by the cost estimation person's terminal 20, displays the information on the construction object work screen 100 shown in FIG. 4 on the equipment person's terminal 10. By clicking the "Product" button in the work instruction area 102, "Complete" is flagged in the status column of the estimation requesting list 1024 displayed in the estimation request screen 1020 shown in FIG. By clicking this "Complete" button, it is possible to confirm the cumulative quantity record data, which is the contents of the collection (accumulation step 10/AS10). Then, upon completion of this confirmation, the cost estimation process using the cumulative quantity record data is completed (cost estimation step 11/AS11)

なお、積算事務所に対し、積算数量調書の見直し、その他を設備工事会社から依頼指示すべく再度のアップロードを依頼する場合には、この積算依頼中一覧表1024の更新欄に表示される「戻す」ボタンのクリックによって、その戻すことを確認し、更新処理する。そうすると、積算担当者側端末20には積算数量調書データの作成の見直し依頼があったことが表示されると共に、積算依頼中一覧表1024の状況欄には積算作業中であることの「作業中」のフラグに更新表示される。 In addition, when requesting the cost estimation office to re-upload the cost estimate quantity record or other requests from the facility construction company, please click the "Return" button displayed in the update column of the list of request for cost estimate 1024. ” button to confirm the change back and process the update. Then, the terminal 20 on the cost estimation person's side displays that there has been a request to review the creation of the cost estimation quantity record data, and the status column of the list 1024 of the cost estimation requests indicates that the cost estimation work is in progress. ” flag will be updated.

以上に説明した積算処理に関し、設備工事会社から積算事務所に積算を依頼するに際し、設備工事担当者側端末10、積算担当者側端末20相互間でクラウド2を介して諸データがアップロードされ、またダウンロードされる。このときの積算事務所における積算作業の進捗状況として設備工事会社からの依頼、依頼に対する諾否、開始、作業中、完了その他の状況は、設備工事担当者側端末10における進捗状況確認手段15によって、積算担当者側端末20によって作業されている状況は、例えば物件一覧画面110におけるステータス欄112、積算依頼画面1020に表示される積算依頼中一覧表1024の状況欄等に状況表示のフラグとして逐次更新表示される。 Regarding the cost estimation process explained above, when an equipment construction company requests a cost estimation office to perform a cost estimation, various data are uploaded between the equipment construction person's terminal 10 and the cost estimation person's terminal 20 via the cloud 2. It will be downloaded again. At this time, the progress status of the cost estimation work at the cost estimation office, such as the request from the facility construction company, acceptance or rejection of the request, start, work in progress, completion, and other statuses, is checked by the progress confirmation means 15 on the terminal 10 on the side of the facility construction worker. The status of the work being performed by the cost estimation person's terminal 20 is sequentially updated as a status display flag in, for example, the status column 112 on the property list screen 110, the status column of the cost estimation requesting list 1024 displayed on the cost estimation request screen 1020, etc. Is displayed.

なお、積算依頼作業処理に限らず、後述する見積依頼作業処理においても、設備工事会社から代理店等に対する見積依頼、見積依頼に対する諾否、開始、作業中、完了その他の状況は、同様に設備工事担当者側端末10における進捗状況確認手段15によって見積担当者側端末30との相互間通知と共に所定画面において逐次更新表示される。 Note that not only the estimate request process, but also the estimate request process described later, the request for quotation from the equipment construction company to the agency, acceptance or rejection of the quotation request, start, work in progress, completion, and other statuses are the same as those for the equipment work. The progress confirmation means 15 in the terminal 10 on the person in charge of estimating updates and displays the information on a predetermined screen together with mutual notification with the terminal 30 on the estimating person's side.

(積算数量データの代理店等への送付)
設備工事担当者側端末10における工事物件作業画面100の作業指示域102に配置の「見」ボタンのクリックによって図12に示される見積依頼画面170における工事項目表172中の選択欄に配置の選択ボタンのクリックによって、あるいは図13に示される仕訳分類一覧画面180中の代理店選択欄に配置の「設定」ボタンのクリックによって、図14に示される依頼先選択画面190の操作で行われる。
(Sending cumulative quantity data to agents, etc.)
By clicking the "View" button placed in the work instruction area 102 of the construction object work screen 100 on the equipment construction person's terminal 10, the selection of placement is made in the selection field in the work item table 172 on the quotation request screen 170 shown in FIG. 12. This is done by operating the client selection screen 190 shown in FIG. 14 by clicking a button, or by clicking the "setting" button placed in the agency selection column in the journal entry classification list screen 180 shown in FIG. 13.

すなわち、図21に示すように、前記依頼先選択画面190における数量送付ボタン193のクリックによって、その送付確認メッセージ画面がダイヤログ表示され、そのメッセージの確認をすることで所定の代理店等への積算数量データが送付され、商材取扱代理店一覧表192における履歴欄に「受託(数量送付済)」のフラグが更新表示されるようになっている。 That is, as shown in FIG. 21, by clicking the quantity sending button 193 on the request destination selection screen 190, a sending confirmation message screen is displayed as a dialog, and by confirming the message, you can send a message to a specified agency, etc. The accumulated quantity data is sent, and the flag "Consigned (quantity sent)" is updated and displayed in the history column of the product handling agent list 192.

(代理店等への見積依頼)
設備工事会社において、見積を担当する代理店・メーカーの代理店等に見積を依頼するとき、前記したように設備工事担当者側端末10において物件登録に伴い代理店等に対してその物件資料を事前に送付していることでもあり、積算担当者側端末20から送付された積算数量調書の積算データの内容を確認、確定した資料と共に、代理店等に対し、それに基づく見積が依頼され、見積担当者側端末30に表示される。見積依頼は、前記したように、設備工事担当者側端末10に、図4に示される前記工事物件作業画面100における作業指示域102中の「見」ボタンのクリックによって表示される各画面に従い行われる。
(Request for quotation from agents, etc.)
When an equipment construction company requests an estimate from an agent in charge of estimation, a manufacturer's agent, etc., the property information is sent to the agent, etc. on the terminal 10 on the equipment construction person's side to register the property, as described above. The content of the cost estimation data in the cost estimate quantity report sent from the terminal 20 on the cost estimation staff side is confirmed, and along with the finalized materials, the agency etc. is requested to provide a quotation based on the confirmed data. It is displayed on the terminal 30 on the person in charge's side. As described above, a request for quotation is made on the equipment construction person's terminal 10 according to each screen displayed by clicking the "view" button in the work instruction area 102 on the construction object work screen 100 shown in FIG. be exposed.

見積依頼作業は、見積を依頼すべき工事内容と、その依頼先とを適宜に組み合わせるよう選択するのであり、設備工事担当者側端末10における見積依頼手段16によって見積担当者側端末30に通知表示される(見積ステップ1/ES1)。なお、依頼すべき見積内容、依頼先の選択に際しては、通常は複数の見積依頼先が選択され、また依頼先によって見積依頼内容、例えば工事項目として項目番号、項目名称、仕分分類、数量、単位等も異なるので、それぞれに対応した選択によって組み合わせられる。 In the quotation request work, the content of the work for which the quotation should be requested and the request destination are selected in an appropriate combination, and a notification is displayed on the quotation staff terminal 30 by the quotation request means 16 on the equipment construction staff terminal 10. (Estimate step 1/ES1). In addition, when selecting the quotation content to be requested and the requesting party, usually multiple quotation requesting parties are selected, and depending on the requesting party, the quotation request contents, for example, item number, item name, classification classification, quantity, unit for construction items. etc. are also different, so they can be combined by making selections that correspond to each.

(代理店等における物件資料の受領)
見積が依頼された代理店等においては、図22に示すように、代理店等用に用意されている見積担当者側端末30における見積物件作業画面300が、見積物件一覧画面310と共に表示される。見積物件作業画面300には、その作業選択域301に「物件一覧」、「物件受領メール設定」等のメニューが表示されている。また、見積物件作業画面300中に区画表示した作業指示域302に、見積依頼された工事物件毎に見積依頼内容を確認表示できるように指示するボタンが配置されている。例えば見積依頼された工事物件の詳細を表示させる「詳」、見積内容を表示させる「見」、提出した見積書を表示させる「出」等の各ボタンが配置されている。
(Receipt of property materials at an agency, etc.)
As shown in FIG. 22, at the agency or the like where the estimate has been requested, an estimate property work screen 300 on the estimator side terminal 30 prepared for the agency, etc. is displayed together with an estimate property list screen 310. . On the estimated property work screen 300, menus such as "property list" and "property receipt email settings" are displayed in the work selection area 301. Further, a button is arranged in a work instruction area 302 sectioned and displayed in the estimated object work screen 300 to instruct the user to check and display the contents of the estimate request for each construction object for which an estimate has been requested. For example, buttons such as "Details" to display the details of the construction property for which an estimate has been requested, "View" to display the contents of the estimate, and "Submit" to display the submitted estimate are arranged.

また、見積物件一覧画面310には、見積物件一覧表311が表示されており、「作業状況」、「会社名」、「工事番号」、「工事件名」、「提出納期A材」、「提出納期B材」、「作業仕訳分類」の各欄が設けられており、見積物件毎にそれらの内容が行表示されるようになっている。 In addition, the estimated property list screen 310 displays an estimated property list 311, which includes "work status", "company name", "construction number", "construction project name", "submitted delivery date A material", "submitted Columns such as "Delivery date B material" and "Work journal classification" are provided, and their contents are displayed in rows for each estimated item.

見積依頼があった代理店等では、見積担当者側端末30において、作業選択域301の物件受領メール設定のクリックによって、設備工事会社からの通知を受ける代理店担当者を選択する。図示を省略したが、この選択は、例えば代理店における通知受領担当者が表示されている一覧表において、チェックマークを入力することで行われ、物件依頼の際にはこの担当者のみに電子メール等によって通知されるようにしている。 The agency or the like that has received the quotation request selects the agency representative who will receive the notification from the equipment construction company by clicking on the property receipt email setting in the work selection area 301 on the estimator side terminal 30. Although not shown, this selection is made by entering a check mark in a list displaying the person in charge of receiving notifications at an agency, for example, and when making a property request, an e-mail is sent to only this person. etc., to be notified.

そして、設備工事担当者側端末10において、資料アップロード後では、図22に示すように、見積担当者側端末30における見積物件作業画面300に表示されている見積物件一覧画面310において、見積物件一覧表311中で、アップロードされた見積依頼物件の表示行の作業状況欄に「依頼中」のフラグが更新表示される。そこで、作業指示域302中の「出」ボタンのクリックによって表示される資料ダウンロード画面から所定の資料をダウンロードできるようにしている。なお、この資料ダウンロード画面において、上記のように、代理店等における物件担当メール設定によって、物件毎に代理店等における担当者を選定できるようにしている。 After uploading the materials on the equipment construction person's terminal 10, as shown in FIG. In the table 311, the "requesting" flag is updated and displayed in the work status column of the display line of the uploaded quotation requested property. Therefore, a predetermined document can be downloaded from the document download screen displayed by clicking the "Exit" button in the work instruction area 302. In addition, on this material download screen, as mentioned above, the person in charge at the agency, etc. can be selected for each property by setting the e-mail for the person in charge of the property at the agency, etc.

(代理店等における見積依頼の諾否処理)
設備工事担当者側端末10からの見積依頼が通知されると、見積担当者側端末30では、図22に示すように、見積物件作業画面300に表示された見積物件一覧表311において、見積依頼された物件の作業状況欄中に「依頼中」のフラグが更新表示される。ここで、作業指示域302の「詳」ボタンのクリックによって、図23に示すように、表示される見積作業ステータス画面320によって、代理店等の見積作業の進捗による設備工事担当者側端末10においての確認、その連絡内容等が更新表示されるようにしてある。
(Processing of acceptance or rejection of quotation requests at agencies, etc.)
When a request for quotation is notified from the terminal 10 on the equipment construction staff side, the terminal 30 on the estimator side displays the request for quotation in the quotation property list 311 displayed on the quotation property work screen 300, as shown in FIG. The "Requesting" flag will be updated and displayed in the work status column of the requested property. Here, by clicking the "Details" button in the work instruction area 302, the estimated work status screen 320 that is displayed as shown in FIG. confirmation and the contents of the communication are updated and displayed.

この見積作業ステータス画面320には、設備工事会社との連絡状況が表示される作業状況表示域321、代理店等においての諾否・作業進捗状況等の表示がプルダウン式に表示されることでこれらを選択更新して通知するようにしてある状況通知域322、見積提出希望日入力部323、設備工事会社への任意の通知文等を入力するコメント入力部324が設けられている。また、この見積作業ステータス画面320には、見積担当者側端末30から設備工事担当者側端末10に送付される見積データその他の資料をクラウド2上にアップロード指示する資料アップロードボタン325、代理店等における見積作業の開始を設備工事担当者側端末10に通知表示する作業開始ボタン326も配置されている。 This estimate work status screen 320 includes a work status display area 321 where the communication status with the equipment construction company is displayed, and information such as acceptance/rejection at the agency, work progress status, etc. is displayed in a pull-down manner. A status notification area 322 for selectively updating and notification, a desired estimate submission date input area 323, and a comment input area 324 for inputting an arbitrary notification message to the equipment construction company are provided. The estimate work status screen 320 also includes a material upload button 325 for instructing to upload the estimate data and other materials sent from the estimator's terminal 30 to the facility construction worker's terminal 10 onto the cloud 2, and an agent, etc. A work start button 326 is also arranged to notify and display the start of the estimation work on the equipment construction person side terminal 10.

図22に示される見積物件作業画面300において、作業指示域302の「出」ボタンのクリックによって、設備工事担当者側端末10によってアップロードした図面等をダウンロードできる。こうして見積依頼物件の詳細が確認、検討されたのち、見積作業ステータス画面320において、作業状況表示域321では依頼中であることが更新表示され、状況通知域322の表示によって諾否を選択通知する。受託する場合にはこの状況通知域322において、例えばプルダウン表示される「受託」を、辞退する場合には「辞退」のいずれかを選択し、コメント入力部324に所定のコメントを入力し、「更新」ボタンをクリックする(見積ステップ2/ES2)。選択内容は、設備工事担当者側端末10にメール等で通知表示され、設備工事会社からの承認待ち状態であることがこの見積作業ステータス画面320の作業状況表示域321に更新表示される。 On the estimated property work screen 300 shown in FIG. 22, by clicking the "Exit" button in the work instruction area 302, drawings etc. uploaded by the equipment construction person's terminal 10 can be downloaded. After the details of the property requested for quotation are confirmed and examined in this way, on the quotation work status screen 320, the status of the request is updated in the work status display area 321, and the status notification area 322 is displayed to selectively notify whether or not to accept the request. To accept the contract, select "Consignment" from the pull-down menu in the status notification area 322, and to decline the contract, select "Decline," enter a predetermined comment in the comment input field 324, and select "Decline." Click the "Update" button (Estimate Step 2/ES2). The contents of the selection are displayed as a notification via e-mail or the like on the terminal 10 on the side of the person in charge of equipment construction, and the status of waiting for approval from the equipment construction company is updated and displayed in the work status display area 321 of the estimate work status screen 320.

代理店等からの見積担当者側端末30による諾否の通知は、設備工事担当者側端末10における諾否確認手段17によって、設備工事担当者側端末10における図12に示されている見積依頼画面170において表示されている見積依頼中一覧表173中の状況欄におけるフラグ表示と、図23に示されている見積作業ステータス画面320において表示されている作業状況表示域321における表示内容とによって、諾否の連絡状況が設備工事担当者側端末10と見積担当者側端末30との相互間で更新表示されるようになっている。代理店等から受託の連絡があると、見積依頼中一覧表173中の状況欄に「受託」のフラグが表示され、更新欄中に表示される「承認」ボタンのクリックによって、状況欄では「受託承認済み」のフラグに更新され、その一方、見積担当者側端末30における見積作業ステータス画面320の作業状況表示域321では「受託承認済み」と更新表示される(見積ステップ3/ES3)。また、場合によっては特定の代理店等への見積依頼が確定している場合には、このような見積依頼の諾否の送受信を省略することもある。 The notification of acceptance or rejection from the estimator's terminal 30 from an agency or the like is sent to the quotation request screen 170 shown in FIG. Acceptance or rejection is determined by the flag display in the status column of the request for quotation list 173 displayed in , and the display content in the work status display area 321 displayed in the quotation work status screen 320 shown in FIG. The communication status is updated and displayed between the facility construction person's terminal 10 and the estimating person's terminal 30. When you receive a contract request from an agency, etc., the "Consignment" flag will be displayed in the status column of the quotation request list 173, and by clicking the "Approve" button displayed in the update column, the status column will change to "Consignment". On the other hand, in the work status display area 321 of the estimate work status screen 320 on the estimator's terminal 30, the flag is updated to "Consignment approved" (estimate step 3/ES3). Furthermore, in some cases, if a request for quotation to a specific agency or the like has been finalized, the transmission and reception of acceptance or rejection of the quotation request may be omitted.

なお、見積依頼した代理店等において、受託せずに辞退の連絡があった場合には、設備工事担当者側端末10において、見積依頼中一覧表173中の状況欄に「辞退」のフラグが表示される。必要があれば、他の代理店等宛に見積依頼処理が実行される。 In addition, if the agency, etc. to which you requested a quotation informs you that it has declined without accepting the contract, a "declined" flag will be displayed in the status column of the quotation requesting list 173 on the equipment construction person's terminal 10. Is displayed. If necessary, quotation request processing is executed to other agencies, etc.

代理店等においての見積作業の開始は、見積担当者側端末30において、図23に示される見積作業ステータス画面320の状況通知域322中の表示から「開始」を選択、更新すると、設備工事担当者側端末10における図14に示される依頼先選択画面190中に表示されている商材取扱代理店一覧表192の履歴欄に「作業中」のフラグが更新表示される。また代理店希望日時欄には代理店等が希望する見積書の提出日時が、代理店コメント欄には代理店からの通知文が表示されるようになっている。 To start estimate work at an agency, etc., select and update "Start" from the status notification area 322 of the estimate work status screen 320 shown in FIG. 23 on the estimator side terminal 30, and then The "Work in progress" flag is updated and displayed in the history column of the product handling agent list 192 displayed on the client selection screen 190 shown in FIG. 14 on the client terminal 10. In addition, the agency's desired date and time field displays the date and time that the agency, etc. desires to submit the quotation, and the agency comment field displays a notification from the agency.

そして、見積担当者側端末30における積算データ受領手段31によって、設備工事会社が確認している積算数量調書による積算データ等がダウンロード可能となる。図22に示される前記見積物件作業画面300における作業指示域302中の「見」ボタンのクリックによって、図24に示すように、表示される見積作業画面330によって積算事務所のファイルをダウンロードする。すなわち、この見積作業画面330においては、「ファイル出力(積算事務所)」、「見積ファイル取込」、「見積資料アップロード」、「見積履歴」、「積算比較」、「見積比較」、「提出掛率設定」の各ボタンが配置されている作業指示域331が区画表示されており、「ファイル出力(積算事務所)」ボタンをクリックすることで積算事務所の拾い数量表をダウンロードできるようになっている。 Then, the cost estimate data receiving means 31 on the estimator's side terminal 30 makes it possible to download the cost estimate data based on the cost estimate quantity record confirmed by the equipment construction company. By clicking the "View" button in the work instruction area 302 on the estimated property work screen 300 shown in FIG. 22, the file of the cost estimation office is downloaded on the displayed estimation work screen 330, as shown in FIG. That is, on this estimate work screen 330, "File output (quantity estimate office)", "Estimation file import", "Estimation material upload", "Estimate history", "Estimate comparison", "Estimate comparison", "Submit" The work instruction area 331 in which each button for ``Setting Multiplying Rate'' is arranged is displayed as a section, and by clicking the ``File Output (Quantity Quantity Office)'' button, you can download the table of quantities picked up by the Quantity Surveying Office. It has become.

(見積作業)
その後、代理店等では積算データに記載されている機器資材等、更には必要あれば図面、仕様書等の原資料を参照してそれぞれについての品名、数量等に従って見積作業を開始する(見積ステップ6/ES6)。見積作業は、例えば代理店等が採用している諸種の見積プログラムが搭載されている代理店等内のパソコンその他の端末機器によって見積が行われ、積算データ中で一覧表示された機器資材等の品名、型番、数量、メーカー名その他に対応した見積金額が入力された見積書が作成される(見積ステップ7/ES7)。
(Estimate work)
After that, the agency, etc. refers to the equipment and materials listed in the cost estimate data, and if necessary, the source materials such as drawings and specifications, and starts estimating according to the product name, quantity, etc. for each item (estimate step 6/ES6). Estimates are performed using personal computers or other terminal devices installed at agencies, etc., which are equipped with various estimation programs used by agencies, etc., and estimates are made using computers and other terminal equipment installed at agencies, etc., which are equipped with various estimation programs used by agencies. An estimate is created in which the estimated amount corresponding to the product name, model number, quantity, manufacturer name, etc. is entered (estimate step 7/ES7).

この代理店等にて作成された見積書における諸データは、見積担当者側端末30において、汎用データ形式である例えばエクセル(登録商標)形式あるいはCSV形式として取り込まれ、またPDF形式でも取り込み可能としてある。そして、前記見積作業画面330の作業指示域331中の「見積ファイル取込」ボタンのクリックでダイヤログ表示されるファイル選択画面によってプルダウン表示されるファイル種別から所定の書式を選択することで登録される。 Various data in the estimate prepared by the agency etc. are imported into the estimator's terminal 30 in a general-purpose data format such as Excel (registered trademark) format or CSV format, and can also be imported in PDF format. be. Then, by clicking the "Import quotation file" button in the work instruction area 331 of the quotation work screen 330, a dialog is displayed on the file selection screen, and by selecting a predetermined format from the file types displayed as a pull-down, the file is registered. Ru.

この見積ファイル取込処理によって、見積作業画面330において、図24に示すように、取り込み結果が取込見積表332として表示される。この取込見積表332では、代理店見積データから取り込んだ工事項目名称の「工事項目名称」、同様に「照会記号」、「品番」、「品名」「数量」、「単価」、数量×単価の「金額」、掛率区分の「グレード」、コメントである「備考…」の各欄が設けられており、機器資材等毎にそれぞれのデータが行表示される。一覧表示される機器資材等及び項目名称その他の表示は、見積担当者側端末30の画面において、他の画面と同様にスクロール操作で順次に表示されるようにしてある。 Through this estimate file import process, the import results are displayed as an import estimate table 332 on the estimate work screen 330, as shown in FIG. This imported quotation table 332 includes the "construction item name" of the construction item name imported from the agency quotation data, as well as the "inquiry symbol", "product number", "product name", "quantity", "unit price", and quantity x unit price. There are columns for ``amount'', ``grade'' for multiplication rate classification, and ``remarks...'' for comments, and each data is displayed in a row for each equipment material, etc. The list of equipment materials, item names, and other displays are sequentially displayed on the screen of the estimator's terminal 30 by scrolling similarly to other screens.

(代理店等からの設備工事会社への見積書データのアップロード)
図22に示されるように、前記見積物件作業画面300において見積物件一覧表311で一覧表示されている見積物件毎に、見積作業中である場合に作業状況欄において「作業中」とフラグ表示されている。この「作業中」と表示されている見積物件につき見積作業が終了した場合、この見積物件に相当する作業指示域302中の「詳」ボタンのクリックによって、図23に示されている見積作業ステータス画面320が表示され、この見積作業ステータス画面320に配置されている資料アップロードボタン325を確認クリックする。すると、ダイヤログ表示されるファイル一覧画面の一覧表示された中からアップロードする見積書のファイル名を選択確認し、状況通知域322によってプルダウン表示された「完了」を更新することで、見積担当者側端末30における見積書送付手段32によってクラウド2上への見積資料等のアップロード作業が完了するようになっている(見積ステップ8/ES8)。
(Upload of quotation data from agency etc. to facility construction company)
As shown in FIG. 22, for each estimated property listed in the estimated property list 311 on the estimated property work screen 300, if the estimation work is in progress, a flag is displayed as "in progress" in the work status column. ing. When the estimation work is completed for the estimated property displayed as "in progress", the estimated work status shown in FIG. 23 can be changed by clicking the "Details" button in the work instruction area 302 corresponding to this estimated property. A screen 320 is displayed, and the user confirms and clicks on the material upload button 325 arranged on this estimate work status screen 320. Then, the person in charge of estimating can select and confirm the file name of the estimate to be uploaded from the list displayed on the file list screen displayed in the dialog, and update the pull-down display of “Complete” in the status notification area 322. The uploading work of estimate materials and the like onto the cloud 2 is completed by the estimate sending means 32 in the side terminal 30 (estimate step 8/ES8).

この見積作業完了による見積書のアップロードは、見積担当者側端末30において、前記見積作業ステータス画面320の作業状況表示域321においても完了したことの状況が「完了」として表示され、見積作業の完了は設備工事担当者側端末10に通知表示される。通知された設備工事会社では、この完了通知は設備工事担当者側端末10において、図4に示される前記工事物件作業画面100における作業指示域102の「見」ボタンのクリックによって、図12に示されている見積依頼画面170に表示されている見積依頼中一覧表173の状況欄にも「完了」としてフラグ表示される(見積ステップ9/ES9)。 When the quotation is uploaded due to completion of the quotation work, the completion status is also displayed as "Completed" in the work status display area 321 of the quotation work status screen 320 on the estimator side terminal 30, and the quotation work is completed. is displayed as a notification on the equipment construction worker side terminal 10. At the equipment construction company that received the notification, this completion notification is sent to the equipment construction person's terminal 10 by clicking the "view" button in the work instruction area 102 on the construction object work screen 100 shown in FIG. 4, as shown in FIG. 12. A flag as "completed" is also displayed in the status column of the quotation request list 173 displayed on the quotation request screen 170 (estimate step 9/ES9).

(設備工事会社における見積内容の確認)
設備工事担当者側端末10において表示される物件一覧表111において、見積が完了したと通知された工事物件では、上記のように、見積依頼中一覧表173の状況欄にフラグ表示される「完了」ボタンのクリックによって、見積書受領手段18によって見積内容である見積書データを確認できるようにしてある(見積ステップ10/ES10)。
(Confirmation of quotation details from equipment construction company)
In the property list 111 displayed on the equipment construction person's terminal 10, for the construction property for which the estimate has been notified, the "completed" flag is displayed in the status column of the quotation requesting list 173, as described above. '' button, the estimate data that is the contents of the estimate can be confirmed by the estimate receiving means 18 (estimate step 10/ES10).

なお、積算データに基づく設備工事費用の見積は、通常は複数の代理店等に依頼されるから、複数の代理店等からはそれぞれの見積担当者側端末30によって見積書データが各別にアップロードされ、設備工事会社では、図25に示すように、設備工事担当者側端末10に表示される工事見積作業画面1030において、それらの各別の数種類の見積書データを比較対照できるように見直し整理し、それらの突合処理、関連する機器資材等の紐付け処理が行われる。これらの処理作業中の設備工事担当者側端末10における画面上では、対応データの存否、項目毎の入力上の齟齬その他がある場合、例えば背景色の変更表示その他によって注意が喚起されるようにしている。 Note that estimates of equipment construction costs based on cost estimation data are normally requested from multiple agencies, so the estimate data is uploaded separately from multiple agencies using the estimator's terminal 30. As shown in FIG. 25, the equipment construction company reviews and organizes several types of estimate data for each type on the construction estimate work screen 1030 displayed on the terminal 10 on the equipment construction person's side so that they can be compared and contrasted. , a matching process between them, and a process of linking related equipment materials, etc. are performed. On the screen of the equipment construction worker's terminal 10 during these processing operations, if there is any corresponding data, discrepancies in input for each item, etc., attention is called by changing the background color, etc. ing.

また、代理店等においての見積作業に際し、代理店等それぞれでは同一の機器資材等に対してその構成部材を一括して計上している場合、あるいはその構成部材を例えば本体部分・付属部分に分離して計上している場合があり、これに対応して、これらを統一的に整理、表示するようにされている。設備工事担当者側端末10の工事見積作業画面1030には、図25に示すように、機器資材区分表示表1031が表示され、この機器資材区分表示表1031において、例えば機器資材毎に「区分」、「工事項目名称」、「照会記号」、「品番」、「品名」、「数量」その他の各欄が設けられており、必要な修正作業の実施後で確定する更新ボタン1032も配置されている。そして、区分欄には、例えば本体部分の表示には「本」を、付属部分の表示には「付」が機器資材等の資材データ行毎に付記的に表示され、本体部分と付属部分とに分離されているときには、機器資材等の本体部分に従って付属部分が次行に表示されるようにしている。こうした照会修正後に更新ボタン1032のクリックによってそれぞれの代理店等毎の見積書データとして保存される(ステップ10/S10)。 In addition, when an agency, etc. performs estimation work, each agency may account for the component parts of the same equipment materials, etc. all at once, or separate the component parts into, for example, the main body part and attached parts. In response to this, these items are organized and displayed in a unified manner. As shown in FIG. 25, an equipment material classification display table 1031 is displayed on the construction estimate work screen 1030 of the equipment construction person's terminal 10. In this equipment material classification display table 1031, for example, "classification" is displayed for each equipment material. , "Construction item name", "Inquiry symbol", "Product number", "Product name", "Quantity" and other columns are provided, and an update button 1032 to confirm after performing necessary correction work is also provided. There is. Then, in the classification field, for example, "book" is displayed for the main body part, and "attached" is displayed for the attached part, as an additional note for each row of material data such as equipment materials. When the equipment is separated into two parts, the attached parts are displayed on the next line according to the main part of the equipment and materials. After such inquiries and corrections are made, by clicking the update button 1032, the data is saved as quotation data for each agency, etc. (Step 10/S10).

機器資材区分表示表1031において、項目の一覧表示見積書データの同一項目内に、照会記号・品番・品名・単位・単価・グレード・備考を同じとする行の存在がある場合の確認メッセージが、また同一の照会記号の重複連続がある場合の処理中断メッセージがそれぞれ表示され、確認・修正等の所定の作業処理が行われるようにしている。 In the equipment material classification display table 1031, if there are rows with the same reference code, product number, product name, unit, unit price, grade, and notes in the same item in the item list display quotation data, a confirmation message will be displayed. In addition, a processing interruption message is displayed when the same inquiry symbol continues to be repeated, and predetermined work processing such as confirmation and correction is performed.

なお、代理店等に修正、見直し等の依頼その他で再度のアップロードを設備工事会社が依頼する場合には、設備工事担当者側端末10において、図12に示される前記見積依頼画面170に表示されている見積依頼中一覧表173の更新欄に一旦は表示された「承認」フラグが変更されて「戻す」のフラグが表示される。この「戻す」ボタンのクリックによって戻すことを確認し、更新処理することで状況欄には「作業中」のフラグが更新表示される。この再度の見直し依頼は、該当する代理店等に通知され、見直した見積書データが再度アップロードされ、その承認によって代理店等の見積担当者側端末30に通知表示されることで代理店等への見積依頼、受領の処理が完了する。 In addition, when the equipment construction company requests re-uploading for corrections, reviews, etc. to the agency, etc., the information is displayed on the quotation request screen 170 shown in FIG. 12 on the equipment construction person's terminal 10. The "approval" flag that was once displayed in the update column of the quotation requesting list 173 is changed and a "return" flag is displayed. By clicking this "Return" button, you confirm that you want to restore the data, and by performing the update process, the "Working" flag is updated and displayed in the status column. This re-review request is notified to the relevant agency, etc., the revised quotation data is uploaded again, and upon approval, a notification is displayed on the terminal 30 of the person in charge of estimating at the agency, etc. The request for quotation and receipt processing is completed.

(代理店等の見積書データの見積項目の突合)
設備工事会社において施工者に提示する積算見積書では、適正な価格を反映したものとなるように、複数の代理店等から通知された見積書データそれぞれから機器資材等に対応した見積額を取捨選択することで作成する。作成するに際し、各代理店等からの見積書データでは項目その他において各代理店等相互間において異なっていることが多く、単に羅列して比較処理することは困難である。そのため、代理店等から通知された見積書データを一覧的に比較対照するに先立ち、設備工事担当者側端末10において、積算項目に対応した見積項目の存否を確認することによって工事項目を割り当てる作業として突合処理を行う(ステップ11/S11)。
(Comparison of quotation items in quotation data from agencies, etc.)
In order to ensure that the cost estimate presented to the contractor by an equipment construction company reflects an appropriate price, the estimated amount corresponding to equipment materials, etc. is discarded from each estimate data notified from multiple agencies, etc. Create by selecting. When creating quotation data from agencies, etc., items and other factors often differ between agencies, making it difficult to simply list them and compare them. Therefore, before comparing and contrasting the estimate data notified from agencies etc. in a list, work items are assigned by checking on the equipment construction worker side terminal 10 whether or not there is an estimate item corresponding to the estimate item. A matching process is performed as follows (Step 11/S11).

突合処理を行うには、代理店等から提示された見積書データが一覧表示されている中から、突合処理が行われていない代理店等による見積書データについて行われる。ここで、設備工事担当者側端末10における物件一覧画面110において表示されている物件一覧表111では、そのステータス欄には見積書データが通知されている「見積」のフラグが表示されているところ(図4参照)、見積比較手段19によって、工事物件作業画面100の作業指示域102中の「比」ボタンをクリックすることで、図26に示すように、見積比較画面1040が表示される。 In order to perform the comparison process, the quotation data presented by the agencies, etc. is displayed in a list, and the comparison process is performed on the quotation data from the agencies, etc. that have not been subjected to the comparison process. Here, in the property list 111 displayed on the property list screen 110 on the equipment construction person's terminal 10, the status column displays the "Estimate" flag indicating that the estimate data has been notified. (See FIG. 4) By clicking the "ratio" button in the work instruction area 102 of the construction object work screen 100 by the estimate comparison means 19, an estimate comparison screen 1040 is displayed as shown in FIG.

この見積比較画面1040では、見積書データが通知されている代理店等が羅列表示されている比較代理店一覧表1041が用意されている。この比較代理店一覧表1041では、見積比較の表示操作が表示される「操作」、仕訳分類が表示される「仕訳分類」、見積書データを提示した代理店等が表示される「代理店メーカー」、突合処理の有無を表示する「項目突合」、見積の定価の合計を表示する「定価合計」、グレード入力の有無を表示する「グレード入力」、掛け率を表示する「掛率」、代理店等による提示金額を表示する「提出金額」、見積採用の採否を表示する「採用/未採用」、後述する品名等の選択に際しチェックマークを入力する「品名等選択」、資材データ等の修正等の制限可否を表示する「排他制御」、後述する割当作業中における更新後の作業内容を一時的に前作業状態に戻す「前回設定戻し」の各欄が設けられている。また、この見積比較画面1040では、CSVデータを指示するCSVボタン1042、品名等選択処理ボタン1043が配置されている。 On this estimate comparison screen 1040, a comparison agency list 1041 is prepared in which agencies etc. to which estimate data has been notified are listed. In this comparison agency list 1041, "Operation" displays the display operation for quotation comparison, "Journal classification" displays the journal classification, and "Agency manufacturer" displays the agency that presented the quotation data. ", "Item Match" to display the presence or absence of reconciliation processing, "List Price Total" to display the total of the list price of the estimate, "Grade Input" to display the presence or absence of grade input, "Multiplication Rate" to display the multiplication rate, proxy "Submitted amount" to display the amount offered by the store, etc., "Accepted/Not adopted" to display the acceptance or rejection of the quotation, "Select product name, etc." to enter a check mark when selecting the product name, etc. described later, and correction of material data, etc. There are columns for ``exclusive control'' that displays whether or not restrictions are possible, such as ``exclusive control,'' and ``return previous settings'' that temporarily return updated work contents during assigned work, which will be described later, to the previous work state. Further, on this estimate comparison screen 1040, a CSV button 1042 for specifying CSV data, and a product name selection process button 1043 are arranged.

そして、この比較代理店一覧表1041において、項目突合欄に突合が行われていない代理店等の見積書データであれば「未実施」のフラグが表示されているので、この「未実施」ボタンのクリックによって、図27に示される項目突合画面1050が表示される。 In this comparative agency list 1041, if the quotation data of an agency, etc. that has not been matched is displayed in the item matching column, a "not done" flag is displayed, so click the "not done" button. By clicking , an item matching screen 1050 shown in FIG. 27 is displayed.

この項目突合画面1050において表示されている突合項目引当表1051によって積算事務所の積算データの項目名称と、代理店等の見積書データから取り込んだ項目を引き当てるのであり、突合項目引当表1051には、積算データにおける工事項目番号の「項目番号」、工事項目名称の「項目名称」、見積書データに記載している工事項目名称の「エリア選択」等の各欄が設けられている。積算データで使用されている項目名称(例えば照明器具設備工事)と、見積書データで使用されている工事項目を表示する名称(例えば[一般照明])とが対応していなくとも、積算データと見積書データとの表現における文字の一致率と、過去の事例における過去物件で紐付けた項目突合の履歴との組合せ等によって自動判定することで、それらが同一行に一覧的に表示されるようにしている。もし、その項目名称に対応する工事項目がない場合には警告メッセージが表示される。 The matching item reservation table 1051 displayed on this item matching screen 1050 is used to allocate the item names of the cost estimation data of the cost estimation office and the items imported from the estimate data of the agency, etc. , "Item number" for the construction item number in the estimate data, "Item name" for the construction item name, and "Area selection" for the construction item name described in the estimate data. Even if the item name used in the cost estimate data (for example, lighting equipment equipment work) and the name used to display the construction item used in the estimate data (for example, [General Lighting]) do not correspond, the name of the item used in the cost estimate data Automatic judgment is made based on a combination of the character match rate in the expression with the estimate data and the history of item matching linked with past properties in past cases, so that they are displayed in a list on the same line. I have to. If there is no construction item corresponding to that item name, a warning message will be displayed.

こうして、名称が異なっていても積算データの項目名称に対応する見積書データの項目に関する名称が表示されることで積算データに対応する見積書データが存在することが確認でき、項目突合画面1050に配置されている実行ボタン1052がクリックされる。なお、エリア選択欄における見積項目名は手動入力も可能であり、一致していれば自動割り当てができるようにしている。チェック後、見積書データに積算データの項目情報を追加し、積算データと照会記号を比較し紐付けたデータが保存される。 In this way, even if the names are different, by displaying the name of the item of the estimate data that corresponds to the item name of the cost estimate data, it can be confirmed that quotation data corresponding to the cost estimate data exists, and the item matching screen 1050 is displayed. The arranged execution button 1052 is clicked. Note that the estimate item names in the area selection field can also be entered manually, and if they match, automatic assignment is possible. After checking, the item information of the cost data is added to the estimate data, the cost data is compared with the reference symbol, and the linked data is saved.

(設備工事会社における紐付け処理)
設備工事担当者側端末10の操作による突合作業が実施されても、積算データにおける積算項目に対応した見積書データの見積項目が関連付けられなかった代理店等による見積書データがある場合、積算項目それぞれに対応して関連付ける紐付け処理が行われる(ステップ12/S12)。
(Linking process at equipment construction company)
Even if the comparison work is performed by operating the equipment construction worker's terminal 10, if there is quotation data from an agency etc. that does not correspond to the quotation item in the quotation data that corresponds to the quotation item in the quotation data, the quotation item A linking process for associating each one is performed (step 12/S12).

図26に示される前記見積比較画面1040に表示されている比較代理店一覧表1041の操作欄に表示されている「比較表表示」ボタンのクリックによって、見積比較画面1040の下部に、図28に示すように、代理店等別の見積比較表1044が表示される。また、この見積比較表1044と共に、見積比較に伴う各作業を指示させるようにした「CSV」、「代理店メーカー選択」、「採用データ更新」、「未割当データ表示」、「割当データ更新」の各ボタンが配置されている見積対照作業指示域1045も区画表示されている。 By clicking the "Display Comparison Table" button displayed in the operation column of the comparison agency list 1041 displayed on the quotation comparison screen 1040 shown in FIG. As shown, an estimate comparison table 1044 by agency, etc. is displayed. In addition to this quotation comparison table 1044, "CSV", "Agent Manufacturer Selection", "Recruitment Data Update", "Unallocated Data Display", and "Allocation Data Update" are provided to instruct each task associated with quotation comparison. An estimate comparison work instruction area 1045 in which each button is arranged is also displayed in sections.

さらに、図29に示すように、見積比較表1044の下部には、見積対照作業指示域1045の「未割当データ表示」ボタンのクリックによって、更に未割当データ一覧表1046も同一画面上に表示されるようになっており、見積比較表1044と、未割当データ一覧表1046との間には、データ反映指示域1047が区画表示されている。このデータ反映指示域1047では、未割当データ中から見積比較表1044に反映させる処理を行う「反映」、一旦は反映させたが解除させる処理を行う「解除」、新規に追加させる処理を行う「新規」の各ボタンが配置されていて、反映・解除方向を示す矢印表示と合わせて表示されている。 Furthermore, as shown in FIG. 29, at the bottom of the estimate comparison table 1044, by clicking the "Display unallocated data" button in the estimate comparison work instruction area 1045, an unallocated data list 1046 is also displayed on the same screen. A data reflection instruction area 1047 is partitioned between the estimate comparison table 1044 and the unallocated data list 1046. In this data reflection instruction area 1047, "Reflect" is used to reflect the unallocated data in the quotation comparison table 1044, "Cancellation" is used to cancel the previously reflected data, and "Cancellation" is used to add new data. "New" buttons are arranged, along with arrows indicating the direction of reflection/cancellation.

見積比較表1044は、見積を採用する場合のチェックマークを入力する「採用」、見積を提出した代理店等を表示する「代理店メーカー」、機器資材等の品名を表示する「品名」、その仕様を表示する「仕様」、照会記号の「照会記号」、新設か支給品かの区別を表示する「支給区分」、「数量」、「単位」、「単価」、「定価合計」、「グレード」、「備考」その他の各欄が設けられている。これらの各欄の表示内容は、代理店等からアップロードされ、ダウンロードされた汎用データ形式による資材見積データ行を確認整理して得られた諸データを基にしている。 The quotation comparison table 1044 includes "Adopt" to enter a check mark if the quotation is accepted, "Agent Manufacturer" to display the agency that submitted the quotation, "Product Name" to display the product name of equipment materials, etc. "Specifications" to display the specifications, "Inquiry symbol" for the reference symbol, "Supply classification" to display whether it is a new installation or a supplied product, "Quantity", "Unit", "Unit price", "Total list price", "Grade" ”, “Notes” and other columns are provided. The display contents of each of these columns are based on various data obtained by checking and organizing material estimate data lines in a general-purpose data format that have been uploaded and downloaded from an agency or the like.

未割当データ一覧表1046では、この未割当データ一覧表1046における見積データを見積比較表1044に反映させることのチェックマークを入力する「選択」、「区分」、「品名」、「仕様」、「照会記号」、「数量」、「元数量」、「単位」、「単価」、「金額」、「グレード」、「備考……」その他の欄が設けられている。 In the unallocated data list 1046, select "Select", "Category", "Product name", "Specification", and "Enter a check mark to reflect the quotation data in the unassigned data list 1046 in the quotation comparison table 1044". Other columns are provided such as "Inquiry code", "Quantity", "Original quantity", "Unit", "Unit price", "Amount", "Grade", "Remarks...".

また、見積比較表1044では、見積額を提示した機器資材等の品名毎に、見積を提示した代理店等が例えば行方向に沿って順次に羅列表示されており、代理店等が品名それぞれに対して提示した見積額を比較対照できるようにしている。なお、羅列方法は、列方向に沿って順次に表示されてもよく、これらの表示方法は任意に選択できる。列方向に沿って表示する場合には、所定数のカラム群毎に纏めて特定の代理店等であることで表示され、そのカラム群中で材料名、数量その他の必要な諸データがカラム群中の各欄に表示されるようになっている。 In addition, in the quotation comparison table 1044, the agencies, etc. that have submitted quotations are listed sequentially along the row direction, for example, for each product name of equipment materials, etc., for which the quotation price has been presented, and the agencies, etc. are displayed for each product name. This allows you to compare and contrast the estimated amounts presented to you. Note that the list may be displayed sequentially along the column direction, and these display methods can be selected arbitrarily. When displaying along the column direction, a specific agency, etc. is displayed together in a predetermined number of column groups, and material names, quantities, and other necessary data are displayed in column groups. It is displayed in each column inside.

この見積比較表1044において、数量欄中に数量が「0」であることの品名材料等が存在する場合、その代理店等の見積書データと関連付けられていないことを示し、この行を選択してのクリックあるいは前記見積対照作業指示域1045における「未割当データ表示」ボタンのクリックによって、上述したように、未割当データの一覧が表示されるようになっている。 In this quotation comparison table 1044, if there is a product name, material, etc. whose quantity is "0" in the quantity column, it indicates that it is not associated with the quotation data of the agency, etc., and this row is selected. or the "Display Unallocated Data" button in the estimate comparison work instruction area 1045, as described above, a list of unallocated data is displayed.

そして、未割当データ一覧表1046中の割り当てたい品名材料の資材データ行の選択欄中にチェックマークを入力することで選択し、データ反映指示域1047中の「反映」ボタンのクリックによって見積比較表1044の該当行に反映入力され、未割当データ一覧表1046中から削除される。なお、「解除」ボタンがクリックされると該当行の表示を原状に復帰させて元の状態に戻るのであり、いずれにしても関連付けの紐付けが行われたデータが使用可能になる。 Then, select it by entering a check mark in the selection field of the material data row of the product name and material you want to allocate in the unallocated data list 1046, and click the "Reflect" button in the data reflection instruction area 1047 to display the quotation comparison table. The data is reflected in the corresponding row 1044 and deleted from the unallocated data list 1046. Note that when the "Cancel" button is clicked, the display of the corresponding row is restored to its original state, and in any case, the data with which the association has been linked becomes usable.

積算、見積もられた機器資材等に関し、未割当データ一覧表1046における数量と、見積比較表1044における数量とが一致しない場合には、必要とする数量が割り当てられるようにしている。例えば、積算事務所による積算データによる積算数量に対し、代理店等による見積データによる見積数量が上回る場合、確認メッセージ画面がダイヤログ表示される。図示を省略したが、この表示されたダイヤログ画面において、積算数量分のみを割り当て、残り数量を未割り当てとして残す場合には「積算数量分を割当て」、積算数量を超過して全ての数量を割り当てる場合には「代理店全数量を割当て」、確認メッセージが表示されるも自由に割り当てる場合には「任意数量割当て」の各表示ボタンが用意されていて、これらのいずれかのボタンを選択クリックする。 When the quantity in the unallocated data list 1046 and the quantity in the estimate comparison table 1044 do not match with respect to the estimated and estimated equipment materials, etc., the required quantity is allocated. For example, if the estimated quantity based on estimate data from an agency or the like exceeds the estimated quantity based on the estimate data from the cost estimation office, a confirmation message screen will be displayed as a dialog. Although not shown in the diagram, in this displayed dialog screen, if you want to allocate only the cumulative quantity and leave the remaining quantity unallocated, select "Allocate cumulative quantity" or select "Allocate cumulative quantity" to allocate all quantities beyond the cumulative quantity. There are two display buttons: ``Allocate all agency quantities'' if you want to allocate, and ``Allocate any quantity'' if you want to allocate freely even though a confirmation message is displayed.Click to select one of these buttons. do.

見積比較表1044では、割り当てた数量分が入力表示されると共に、未割当データ一覧表1046では割当数量分が減算されて表示され、未割当数量が残らない場合には未割当データの該当行が削除され、未割当数量が残る場合には減算された残量が表示されるようにしてある。なお、未割当データ一覧表1046では、割り当てた数量を表示する「数量」、割り当て前の数量を表示する「元数量」の欄が設けられていて、代理店等の見積書データの元数量と割当数量とが対比可能なようにしている。 In the estimate comparison table 1044, the allocated quantity is entered and displayed, and in the unallocated data list 1046, the allocated quantity is subtracted and displayed. If there is no unallocated quantity remaining, the corresponding row of unallocated data is If the amount is deleted and an unallocated amount remains, the subtracted remaining amount is displayed. Note that the unallocated data list 1046 has columns for "Quantity" that displays the assigned quantity and "Original Quantity" that displays the quantity before assignment. This allows for comparison with the allocated quantity.

積算事務所による積算データになく、代理店等の見積書データにある品名等の各種データは「新規」として見積比較表1044の一覧に追加される。この追加に際し、例えば見積比較表1044の最下行箇所に追加されると共に、追加後は未割当データ一覧表1046から削除され、これらを処理した更新後では、例えば照会記号によるソートによって関連した機器資材等のデータとして表示確認可能になるようにしてある。 Various data such as product names that are not included in the estimate data from the estimate office but are included in the estimate data of the agency, etc. are added to the list of estimate comparison table 1044 as "new". At the time of this addition, for example, it is added to the bottom row of the estimate comparison table 1044, and after the addition, it is deleted from the unallocated data list 1046, and after processing these, for example, the related equipment materials are sorted by reference symbol. It is possible to display and confirm the data such as.

この新規追加処理に関連し、機器資材等によっては本体部分、付属部分がある場合、その区分表示が付属部分である「付」となっている材料・部材等を同様に「新規」として追加可能にしてある。このような付属部分を新規として追加処理するのは、積算データでは機器資材等が一部材として表示されていても、見積書データでは同一機器資材でありながら、本体部分、付属部分として別表示されていることがあるからであり、これらの取り扱いの相違に対応できるようにしている。 In relation to this new addition process, if there is a main body part or an attached part depending on the equipment material, etc., the materials/parts etc. whose classification display is "attached", which is the attached part, can be added as "new" in the same way. It is set as. Adding and processing such attached parts as new is because even if equipment materials, etc. are displayed as one component in the cost estimate data, they are displayed separately as the main body part and the attached part, even though they are the same equipment material in the estimate data. This is because there may be cases where there are differences in handling, and we are trying to accommodate these differences in handling.

なお、このような未割当データの割当処理は、機器資材等の本体部分のデータが1行で表示されているところ、その本体部分の選択を複数で指定した場合、1行のみしか選択できないことの確認メッセージ画面がダイヤログ表示される。また、重複して選択し、指定した場合、既に割り当てられていることの確認メッセージが同様に表示される。 In addition, in the process of allocating unallocated data like this, when the data of the main body part such as equipment materials is displayed in one line, if multiple selections of the main body part are specified, only one line can be selected. A confirmation message screen will be displayed. Also, if you select and specify duplicates, a confirmation message that they have already been assigned will be displayed in the same way.

こうした紐付け作業中に、例えば見積書データにおいて区分内容を修正した場合、紐付けした機器資材等が解除されることになり、これを回避できるように図26に示される前記見積比較画面1040に表示されている比較代理店一覧表1041において、その資材データ行に設けられている「前回設定戻し」欄中に表示される「実行」ボタンのクリックによって作業内容を戻すことができるようにしている。作業を戻したことによる見積比較表1044、未割当データ一覧表1046において必要な箇所を修正した後、「更新」ボタンをクリックする。すると、比較代理店一覧表1041における項目突合欄中の「実施済」ボタンのクリックによって、再度、項目突合処理を行い、この項目突合処理によって紐付けした内容が解除され、見積比較表1044において数量欄中に「0」が表示され、前回設定戻しの「実行」ボタンのクリックによって作業途中の状態に戻る。 If, for example, the classification contents are modified in the quotation data during such linking work, the linked equipment materials, etc. will be canceled, and to avoid this, the quote comparison screen 1040 shown in FIG. In the comparison agency list 1041 that is displayed, the work details can be restored by clicking the "Execute" button displayed in the "Return previous settings" column provided in the material data row. . After correcting the necessary parts in the estimate comparison table 1044 and the unallocated data list 1046 due to the returned work, the user clicks on the "Update" button. Then, by clicking the "Completed" button in the item matching field in the comparison agency list 1041, the item matching process is performed again, and the linked content is canceled by this item matching process, and the quantity is changed in the estimate comparison table 1044. ``0'' is displayed in the field, and by clicking the ``Execute'' button to restore the previous settings, the process returns to the state in progress.

そして、前記見積比較画面1040における見積対照作業指示域1045に表示される「割当データ更新」ボタンのクリックによって(図28参照)、それぞれの作業が終了した段階の状態が反映されたデータで更新され、この更新が比較代理店一覧表1041の積上合計欄中に反映表示されるようになっている(図26参照)。 Then, by clicking the "Update Allocation Data" button displayed in the estimate comparison work instruction area 1045 on the estimate comparison screen 1040 (see FIG. 28), the data is updated with data that reflects the state at the stage when each task is completed. , this update is reflected and displayed in the accumulated total column of the comparison agency list 1041 (see FIG. 26).

(設備工事会社におけるグレードリストの作成)
設備工事会社において実際の見積を作成するには、代理店等から納入されるそれぞれの機器資材等が定価に従って納入されることは極めて少なく、実売価格に基づくのがほとんどである。また、その実売価格は定価に対する掛率(グレード)によって通常は算出されているから、設備工事担当者側端末10における見積価格の算定にはこのグレードを考慮したものとなる。
(Creation of grade list at equipment construction company)
When preparing an actual estimate at an equipment construction company, it is extremely rare for each equipment and material delivered from an agent etc. to be delivered according to the list price, and in most cases it is based on the actual selling price. Further, since the actual selling price is usually calculated by a multiplier (grade) on the list price, this grade is taken into consideration when calculating the estimated price at the terminal 10 on the equipment construction staff side.

図26に示される前記見積比較画面1040において表示されている比較代理店一覧表1041におけるグレード入力欄中で表示されている「未入力」ボタンのクリックによって、図30に示すように、グレード別によるグループ設定用のグレードリスト表示画面1060が表示される(ステップ13/S13)。このグレードリスト表示画面1060では、「見積比較に戻る」、「次へ」の各ボタンが配置されている作業指示域1061、算出後の「定価合計」、「採用合計」、「差額」等が表示される採用見積金額表示域1062が区画表示されている。また、このグレードリスト表示画面1060にはグループ別表示表1063が表示されており、このグループ別表示表1063には、同一の掛率になるグレードのグループ設定を行うように表示する「グループ設定」、各グレードが表示される「項目グレード」、各グレードの定価合計額が表示される「定価合計金額」、代理店等の見積金額による各グレードの採用金額が表示される「採用合計金額」、定価合計額から採用合計額が減算されて表示される「差額」の各欄が設けられている。 By clicking the "Not entered" button displayed in the grade input field in the comparison agency list 1041 displayed on the quotation comparison screen 1040 shown in FIG. A grade list display screen 1060 for group setting is displayed (step 13/S13). This grade list display screen 1060 includes a work instruction area 1061 in which buttons such as "Return to estimate comparison" and "Next" are arranged, as well as "Total list price", "Total recruitment", "Difference amount", etc. after calculation. The displayed employment estimate amount display area 1062 is displayed in sections. In addition, a group display table 1063 is displayed on the grade list display screen 1060, and the group display table 1063 includes "group settings" that are displayed to set groups of grades with the same multiplication rate. , "Item grade" where each grade is displayed, "Total list price" where the total list price of each grade is displayed, "Total amount adopted" where the adoption price of each grade based on the estimated price of the agent etc. is displayed. Each column is provided with a "difference amount" in which the total adopted amount is subtracted from the total list price and displayed.

そして、グループが設定された後に作業指示域1061の「次へ」ボタンのクリックによって、図31に示すように、提出金額入力のための提出金額入力用のグレードリスト金額入力画面1070が表示される。このグレードリスト金額入力画面1070では、「見積比較に戻る」、「前へ」、「更新」の各ボタンが配置されている作業指示域1071が区画表示されており、また「定価合計」、「提出合計」、「採用合計」、「採用提出合計」がそれぞれ表示されている提出見積金額表示域1072が区画表示されている。また、このグレードリスト金額入力画面1070には、グループ別提出金額表1073が表示されており、このグループ別提出金額表1073には、「グループ設定」、グループ設定してある場合にグレードが集約して表示される「項目グレード」、グループ設定してある場合に定価合計金額が表示される「定価合計金額」、提出合計金額を定価合計金額で除算して%で表示される「掛率」、代理店等の見積金額による各グレードの採用合計金額が表示される「採用合計金額」、採用合計金額に掛率を乗じて算出表示される「採用提出合計金額」の各欄が設けられている。 Then, by clicking the "Next" button in the work instruction area 1061 after the group is set, a grade list amount input screen 1070 for inputting the submission amount is displayed, as shown in FIG. . In this grade list amount input screen 1070, a work instruction area 1071 in which buttons "Return to estimate comparison", "Previous", and "Update" are arranged is displayed as sections, and "List price total", " A submission estimate amount display area 1072 in which "Submission Total", "Recruitment Total", and "Recruitment Submission Total" are respectively displayed is displayed in sections. In addition, this grade list amount input screen 1070 displays a table of submitted amounts by group 1073, and in this table of submitted amounts by group 1073, there is a “group setting” and if groups are set, grades are aggregated. "Item grade" that is displayed as a group, "Total list price" that displays the total list price if a group is set, "Multiplication rate" that divides the total submitted amount by the total list price and displays as a percentage, There are two columns: ``Total Recruitment Amount,'' which displays the total recruitment amount for each grade based on the estimated amount by the agency, and ``Total Recruitment Submission Amount,'' which is calculated and displayed by multiplying the total recruitment amount by a multiplier. .

提出合計金額が入力され、グレードリスト金額入力画面1070における作業指示域1071の「更新」ボタンのクリックによってグレードリスト情報が保存され、図26に示される前記見積比較画面1040が再び表示される。この見積比較画面1040における比較代理店一覧表1041のグレード入力欄では「入力済」が、提出掛率欄、提出金額欄、採用提出合計欄それぞれにはグレードリスト金額入力画面1070で入力した所定の金額の数値が更新表示され、見積比較、その採否が検討されるようになっている(ステップ14/S14)。 The total submission amount is input, and by clicking the "Update" button in the work instruction area 1071 on the grade list amount input screen 1070, the grade list information is saved and the estimate comparison screen 1040 shown in FIG. 26 is displayed again. In the grade input field of the comparison agency list 1041 on this estimate comparison screen 1040, "input completed" is displayed, but in each of the submission rate field, submission amount field, and employment submission total field, the predetermined value input on the grade list amount input screen 1070 is displayed. The numerical value of the amount is updated and displayed, and the estimates are compared and acceptance/rejection is considered (Step 14/S14).

(設備工事会社における見積比較の確認)
設備工事担当者側端末10における図4に示される前記工事物件作業画面100において、作業指示域102中の「比」ボタンのクリックによって、図26に示される前記見積比較画面1040に移行される。この見積比較画面1040においては、突合処理、グレード入力処理が終了し、それらが更新されて整理されており、代理店等それぞれにおける行データ内には、項目突合欄では「実施済」として、グレード入力欄では「入力済」としてそれぞれ更新表示されている。次いで操作欄中の「比較表表示」ボタンのクリックによって、この見積比較画面1040の下部に、図32に示すように、更新表示状態の代理店等別の更新見積比較表1048が表示されるようにしてある。
(Confirmation of estimate comparison among equipment construction companies)
On the construction object work screen 100 shown in FIG. 4 on the equipment construction worker side terminal 10, by clicking the "ratio" button in the work instruction area 102, the screen is transferred to the estimate comparison screen 1040 shown in FIG. In this quotation comparison screen 1040, the matching process and grade input process have been completed, they have been updated and organized, and in the line data for each agency etc., the item matching column shows the grade as "completed". In the input field, each entry is updated and displayed as "input completed". Next, by clicking the "Display Comparison Table" button in the operation column, an updated quotation comparison table 1048 for each agency, etc. in an updated display state is displayed at the bottom of this quotation comparison screen 1040, as shown in FIG. It is set as.

この更新後の更新見積比較表1048においては、上述したように見積した品名毎に、この品名を積算した積算事務所及び見積もった代理店等を順次に羅列表示してあり、スクロール操作によって各欄の表示内容が確認できるようにしてある。この更新見積比較表1048において、さらに詳しく説明すると、「CSV」、「代理店メーカー選択」、「採用データ更新」、「未割当データ表示」等の各ボタンが配置されている前記見積対照作業指示域1045が設けられている。そして、一覧表示として、見積を採用するときのチェックマークを入力する「採用」、品名毎に積算事務所名を上段に、この品名を見積もった代理店等名を下段に順次に表示される「代理店メーカー」、積算事務所・代理店等による機器資材等の名称が表示される「品名」、その品名による仕様が表示される「仕様」、設計時に記載され、積算事務所・代理店等でも参照するよう表示される「照会記号」、その品名のものが新設されるのか、支給されるのか、あるいは撤去されるのかが表示される「支給区分」、図面に記載の型番(ない場合には「不明」と表示される)のメーカーが表示される「取込メーカー」、同じく型番(特注品の場合は例えばYYYと表示される)が表示される「取込型番」、代理店等の型番・仕様が表示される「型番」、代理店等が見積もった数量が表示される「数量」(なお、積算データと見積書データとで異なる場合は例えば赤字表記される)、積算事務所・代理店等による単位が表示される「単位」、代理店等が見積もった単価が表示される「単価」、数量に単価を乗じたことで表示される「定価合計」、代理店等の掛率グレードが表示される「グレード」、代理店等によるコメント等が表示される「備考」、積算事務所の拾い出し作業時での系統名が表示される「拾い系統」等の各欄が設けられている。 In the updated quotation comparison table 1048, as mentioned above, for each product name that was estimated, the cost estimation office that estimated the product name, the agency that provided the estimate, etc. are listed in order, and each column can be changed by scrolling. The display contents can be checked. In this updated quotation comparison table 1048, to explain in more detail, the quotation comparison work instructions are arranged with buttons such as "CSV", "Select agency manufacturer", "Update recruitment data", "Display unallocated data", etc. A region 1045 is provided. Then, as a list display, enter the check mark when accepting the quotation, "Adopt", the name of the cost estimation office for each product name will be displayed in the upper row, and the name of the agency etc. that estimated this product name will be displayed in the lower row. "Product name" which displays the name of the equipment and materials provided by the quantity surveyor's office, agency, etc., "Specifications" which displays the specifications for that product name, and which is stated at the time of design and is provided by the quantity surveyor's office, agency, etc. However, the "inquiry symbol" that is displayed for reference, the "supply classification" that displays whether the product name is newly installed, supplied, or removed, and the model number written on the drawing (if not available) "Intake Manufacturer" which displays the manufacturer (displayed as "Unknown"), "Intake Model Number" which also displays the model number (for example, YYY is displayed in the case of a custom-made product), and the agency etc. "Model number" where the model number and specifications are displayed, "Quantity" where the quantity estimated by the agent etc. is displayed (if the cost estimate data and the estimate data are different, it will be written in red, for example), the quantity estimate office, etc. "Unit" displays the unit provided by the agency, etc., "Unit price" displays the unit price estimated by the agency, etc., "Total list price" displays by multiplying the quantity by the unit price, and the multiplication rate of the agency, etc. There are various columns such as "Grade" where the grade is displayed, "Remarks" where comments etc. from the agent etc. are displayed, and "Pickup system" where the system name at the time of picking up at the cost estimation office is displayed. ing.

この更新処理された更新見積比較表1048によって、見積もられた機器資材等による品名毎に、あるいは代理店等毎に採否を検討する。なお、品名毎に代理店等に関係なく個別に採用する場合の、いわゆるチドリ採用の場合には代理店等による見積データにおけるグレード設定が実施されている必要があり、これが実施されていないと実行できないようにしてある。 Based on this updated estimate comparison table 1048, acceptance or rejection is considered for each product name of estimated equipment materials, etc., or for each agency, etc. In addition, in the case of so-called Chidori adoption, where each product name is adopted individually regardless of the agency, etc., it is necessary to set the grade in the quotation data by the agency, etc., and if this is not done, it will not be executed. I've made it impossible to do so.

更新見積比較表1048の見積対照作業指示域1045に配置されている「代理店メーカー選択」ボタンのクリックによって、図示を省略したが、採用すべき代理店メーカー選択画面がダイヤログ表示される。そして、この代理店メーカー選択画面中にリストアップされた複数の代理店等の中から選択することで、更新見積比較表1048において、この選択された代理店等が表示されているデータ行の採用欄中に一括してチェックマークが付記される。品名によっては別の代理店等の見積を採用する場合には、その採用欄中にチェックマークを記入し、保存する場合には見積対照作業指示域1045中の「採用データ更新」ボタンをクリックする。 By clicking on the "Select Agency Manufacturer" button located in the quotation comparison work instruction area 1045 of the updated quotation comparison table 1048, a dialogue box for selecting the agency manufacturer to be adopted is displayed (not shown). Then, by selecting from among the multiple agencies etc. listed on this agency manufacturer selection screen, the data row in which this selected agency etc. is displayed is selected in the updated quotation comparison table 1048. A check mark will be added all at once in the column. If you want to adopt a quotation from another agency depending on the product name, enter a check mark in the quotation column, and if you want to save it, click the "Update recruitment data" button in the quotation comparison work instruction area 1045. .

この採用データ更新後の前記見積比較画面1040において、図33に示すように、前記比較代理店一覧表1041の代理店メーカー欄中に、採用された代理店等の名称が「材料選択データ」と更新表示され、チドリ選択した際の積上合計金額が積上合計欄に表示される。 In the quotation comparison screen 1040 after this recruitment data has been updated, as shown in FIG. The display will be updated and the total accumulated amount when Chidori is selected will be displayed in the accumulated total column.

採用代理店等が確定した際には、図26に示される見積比較画面1040中の比較代理店一覧表1041における採用/不採用欄より「採用」を選択すると、その確認メッセージ画面がダイヤログ表示され、それを確認することで採用/不採用欄中に「採用中」と表示される。このとき、見積を採用した代理店等の見積データ中に例えば単価表示が0円である等の項目内容に不備等があると警告メッセージが表示されるようにしてある。 When the hiring agency etc. has been decided, select "Recruitment" from the recruitment/rejection column in the comparison agency list 1041 in the quotation comparison screen 1040 shown in FIG. 26, and a confirmation message screen will be displayed as a dialog. After confirming this, “Currently Hiring” will be displayed in the Hiring/Rejection column. At this time, a warning message is displayed if there is a deficiency in the item content, such as a unit price display of 0 yen, in the quotation data of the agency or the like that adopted the quotation.

(設備工事会社における品名等選択の設定)
そして、同じく図26に示される前記比較代理店一覧表1041において、品名等選択欄中にチェックマークを入力し、見積比較画面1040中に配置されている品名等選択処理ボタン1043のクリックによって、例えば設備工事担当者側端末10に搭載されている積算システムに取り込む品名、数量等を編集できる(ステップ15/S15)。なお、この編集中では、他のユーザー(他ID)による、例えば品名等選択処理で編集を不可としてロックするよう、排他制御欄中に例えば「設備工事会社 使用中」等のメッセージが表示されるようにしてある。
(Settings for selecting product names, etc. at equipment construction companies)
Then, in the comparison agency list 1041 also shown in FIG. 26, enter a check mark in the product name selection field, and click the product name selection processing button 1043 arranged in the estimate comparison screen 1040, for example. It is possible to edit the product name, quantity, etc. to be imported into the cost estimation system installed in the facility construction worker's terminal 10 (step 15/S15). During this editing, a message such as "In use by equipment construction company" will be displayed in the exclusive control field to prevent other users (other IDs) from editing, for example, by selecting the product name. It's like this.

品名等選択処理ボタン1043のクリックによって、図34に示すように、項目名採用画面1080が表示される。この項目名採用画面1080において、見積比較処理作業に戻すことを指示する「比較に戻る」、項目名の採用更新を指示する「更新」の各ボタンが配置されている作業指示域1081が区画表示されている。また、項目名採用一覧表1082が表示されており、この項目名採用一覧表1082には、積算システムに取り込むようCSVに出力される情報を表示する「[取込]品名」、代理店等の見積書データの情報による品名が表示される「[見]品名」、積算事務所の積算データの情報による品名を表示させる「[積]品名」等の各欄が設けられている。[見]品名欄中の情報表示はデフォルトで例えば赤文字で表示され、修正した場合には例えば青文字で表示され、その修正等を保存する場合には「更新」ボタンがクリックされる。 By clicking the product name etc. selection process button 1043, an item name adoption screen 1080 is displayed as shown in FIG. In this item name recruitment screen 1080, a work instruction area 1081 in which the buttons "Return to comparison" for instructing to return to the estimate comparison processing work and "Update" for instructing to update the recruitment of item names are arranged is displayed as a section. has been done. In addition, an item name adoption list 1082 is displayed, and this item name adoption list 1082 includes “[Imported] product name” that displays information output to CSV to be imported into the cost estimation system, and information about agents, etc. There are columns such as ``[See] product name'' where the product name based on the information on the estimate data is displayed, and ``[product] product name'' where the product name based on the information on the cost estimate data of the cost estimation office is displayed. [See] By default, the information in the product name field is displayed in red text, for example, and if it is modified, it is displayed in blue text, for example, and the "Update" button is clicked to save the modification.

(積算事務所・代理店等から提供された積算・見積データと設備工事会社における設備工事会社用の積算システム取込用CSV出力)
設備工事会社では、積算作業を依頼した積算事務所からの積算データ、これに基づく見積作業を依頼した代理店等からの見積書データ等を整理し、突合、紐付け、見積比較によって採用した見積額によって積算見積を施工者等に提示する。この提示される積算見積に先立ち、積算データ、見積書データから得た例えばCSVデータによって、設備工事会社独自の積算システムを使用して積算見積が作成される(ステップ16/S16)。
(CSV output for importing cost estimation/estimate data provided by cost estimation offices, agencies, etc. and the cost estimation system for equipment construction companies)
Equipment construction companies organize the cost estimation data from the cost estimation office that requested the cost estimation work, the estimate data from the agency that requested the estimation work based on this data, and then compare, link, and compare the estimates to obtain the adopted estimate. A cost estimate will be presented to the constructor etc. based on the amount. Prior to the presented cost estimate, a cost estimate is created using, for example, CSV data obtained from the cost estimate data and estimate data using a cost estimate system unique to the equipment construction company (step 16/S16).

設備工事担当者側端末10における図4に示される前記工事物件作業画面100に表示される物件一覧表111において、ステータス欄112では比較が終了していることを示す「比較」フラグが更新表示されており、工事物件作業画面100における作業指示域102中の「出」ボタンのクリックによって、図35に示すように、資料ダウンロード画面1090が表示される。この資料ダウンロード画面1090では、表示された積算担当者表1091には、今回の物件において積算を依頼した「積算担当名」、その積算事務所がアップロードした資料をダウンロードさせる「出」ボタンを配置してある「資料」の各欄が設けられている。 In the property list 111 displayed on the construction property work screen 100 shown in FIG. 4 on the equipment construction worker side terminal 10, the "comparison" flag indicating that the comparison has been completed is updated and displayed in the status column 112. By clicking the "Exit" button in the work instruction area 102 on the construction object work screen 100, a material download screen 1090 is displayed as shown in FIG. In this material download screen 1090, the displayed cost estimation staff table 1091 includes the "name of the cost estimation person" who requested the cost estimation for this property, and an "out" button to download the materials uploaded by the cost estimation office. There are columns for each ``Materials''.

同様に見積を依頼した代理店等が表示されるよう区画された見積担当者表1092には、「見積担当名」、代理店等が見積もった項目番号が表示される「見積項目番号」、そのアップロードしたそれらの見積資料毎に出力指示させる「出」ボタンを配置した「資料」の各欄が設けられている。 Similarly, the estimator table 1092, which is partitioned to display the agents, etc. who requested the estimate, includes the "estimator name", the "estimate item number" which displays the item number estimated by the agent, etc. Each column of ``Materials'' is provided with an ``Output'' button for instructing the output of each of the uploaded estimate materials.

また、積算担当者が拾い完了時に設備工事担当者側端末10における積算システムへ取り込むための、単価未入力状態の積算事務所CSVデータを出力指示させる「出」ボタンを配置してある積算事務所CSVデータ出力指示域1093が区画表示されている。 In addition, the cost estimation office is equipped with an "output" button that instructs the cost estimation office to output the cost estimation office CSV data with no unit price input, so that it can be imported into the cost estimation system on the terminal 10 on the equipment construction staff side when the cost estimation staff completes picking up. A CSV data output instruction area 1093 is displayed in sections.

さらに、代理店等が見積完了し、積算システムに取り込むための、単価入力状態の代理店等CSVデータを出力させる「出力」ボタンが配置されているCSVデータ出力指示域1094が区画表示されている。この代理店等CSVデータでは、機器資材等の項目に対応した仕訳分類に従った積算・見積項目名称が表示される「仕訳分類」、それ等を選択して出力させるようにチェックマークが入力される「選択」の各欄が設けられている仕訳分類表1095から選択されるようになっている。なお、選択後の出力に際し、二重取込防止機能が設定されており、例えば選択欄にチェックマークが付されている仕訳分類として過去にCSVデータとして出力していない項目であり、チェックマークが付されていない品名欄等は過去に出力済であることを記憶しているため、デフォルトでチェックマークが外れている状態を示すようにしている。 Furthermore, a CSV data output instruction area 1094 is displayed as an area in which an "output" button is arranged to output CSV data of the agency, etc. in the unit price input state after the agency, etc. completes the estimate and imports it into the cost estimation system. . In this agency CSV data, "journal classification" displays the cost estimation/estimate item names according to the journal classification corresponding to items such as equipment materials, etc., and a check mark is entered to select and output them. The selection is made from the journal entry classification table 1095, which has columns for "selection". Please note that when outputting after selection, a double import prevention function is set, and for example, items that have not been output as CSV data in the past as journal classifications with a check mark in the selection column, Since it is remembered that the product name columns and the like that are not marked have been output in the past, they are shown as unchecked by default.

(設備工事会社における物件完了、解除方法)
設備工事担当者側端末10における、図4に示される前記物件一覧画面110において、作業指示域102中の「完」ボタンのクリックによって対象とする工事物件全体の諸データがロックされ、編集不可の状態となり、ステータス欄112では「完」のフラグが更新表示されることになる。この編集不可の状態にあるときでは、作業中欄の「完」は「解」に更新表示されていて、「解」ボタンのクリックによって編集可能になるようにしている。
(Property completion and cancellation method at equipment construction company)
On the property list screen 110 shown in FIG. 4 on the equipment construction worker side terminal 10, clicking the "Complete" button in the work instruction area 102 locks the various data of the entire target construction property and makes it impossible to edit. status, and the "Complete" flag is updated and displayed in the status column 112. In this non-editable state, "Complete" in the work in progress column is updated to "Solution", and editing becomes possible by clicking the "Solution" button.

これらによって、設備工事担当者側端末10においては、積算担当者側端末20からの積算データ、見積担当者側端末30からの見積書データに基づき、例えば搭載している積算システムによって施工者等に提示する積算見積書を作成できる(ステップ17/S17)。 As a result, the facility construction worker terminal 10 can send information to the construction worker, etc., using the installed cost estimation system, based on the cost estimation data from the cost estimation worker terminal 20 and the estimate data from the estimating worker terminal 30. A cost estimate to be presented can be created (step 17/S17).

本発明は、以上のように建築物の施工に際し、その設備工事に伴う各種機器資材等に関しての積算、見積を作成する好適なものとしてあるが、建築物の施工に限らず、例えば土木工事その他の実施等の各種工事の施工に関連して行われる各種設備品の積算、見積に利用できる。 As described above, the present invention is suitable for creating cost estimates and estimates for various equipment and materials associated with facility construction when constructing a building, but is not limited to construction of a building, for example, for civil engineering work, etc. It can be used for estimating and estimating various types of equipment related to the construction of various types of construction work, such as construction work.

1…見積支援システム
10…設備工事担当者側端末
11…物件資料アップロード手段
12…積算依頼手段
13…諾否確認手段
14…積算数量調書受領手段
15…進捗状況確認手段
16…見積依頼手段
17…諾否確認手段
18…見積書受領手段
19…見積比較手段
20…積算担当者側端末
21…物件資料受領手段
22…積算数量調書送付手段
30…見積担当者側端末
31…積算データ受領手段
32…見積書送付手段
100…工事物件作業画面
101…作業選択域
102…作業指示域
103…物件絞込表示域
110…物件一覧画面
111…物件一覧表
112…ステータス欄
120…代理店一覧画面
121…商材代理店メーカー選択画面
122…商材表
123…仕訳追加域
124…仕訳追加ボタン
125…更新ボタン
130…物件詳細画面
131…アップロード指示ボタン
140…資料アップロード画面
141…作業指示域
142…ファイル表
145…受信メール設定作業画面
146…受信担当者表
150…仕訳選択画面
151…仕訳分類表
152…次へボタン
160…資料送付&見積依頼画面
161…作業指示域
162…共通事項反映域
163…代理店一覧表
164…共通事項反映ボタン
170…見積依頼画面
171…作業指示域
172…工事項目表
173…見積依頼中一覧表
180…仕訳分類一覧画面
181…仕訳分類一覧表
182…依頼状況ボタン
190…依頼先選択画面
191…作業指示域
192…商材取扱代理店一覧表
193…数量送付ボタン
1010…依頼状況画面
1011…作業指示域
1012…依頼状況一覧表
1020…積算依頼画面
1021…積算依頼ボタン
1022…コメント入力部
1023…積算事務所一覧表
1024…積算依頼中一覧表
1030…工事見積作業画面
1031…機器資材区分表示表
1032…更新ボタン
1040…見積比較画面
1041…比較代理店一覧表
1042…CSVボタン
1043…品名等選択処理ボタン
1044…見積比較表
1045…見積対照作業指示域
1046…未割当データ一覧表
1047…データ反映指示域
1048…更新見積比較表
1050…項目突合画面
1051…突合項目引当表
1052…実行ボタン
1060…グレードリスト表示画面
1061…作業指示域
1062…採用見積金額表示域
1063…グループ別表示表
1070…グレードリスト金額入力画面
1071…作業指示域
1072…提出見積金額表示域
1073…グループ別提出金額表
1080…項目名採用画面
1081…作業指示域
1082…項目名採用一覧表
1090…資料ダウンロード画面
1091…積算担当者表
1092…見積担当者表
1093…積算事務所CSVデータ出力指示域
1094…CSVデータ出力指示域
1095…仕訳分類表
200…積算物件作業画面
201…作業指示域
210…積算物件一覧画面
211…積算物件一覧表
220…積算作業ステータス画面
221…作業状況表示域
222…状況通知域
223…コメント入力部
225…資料アップロードボタン
230…材料入力画面
231…チェック指示域
232…機器仕様確認欄
233…材料入力表
240…比較表画面
241…作業指示域
242…変更履歴表示部
243…比較表
244…変更後積算データ表示部
245…変更前積算データ表示部
246…変更内容表示部
300…見積物件作業画面
301…作業選択域
302…作業指示域
310…見積物件一覧画面
311…見積物件一覧表
320…見積作業ステータス画面
321…作業状況表示域
322…状況通知域
323…見積提出希望日入力部
324…コメント入力部
325…資料アップロードボタン
326…作業開始ボタン
330…見積作業画面
331…作業指示域
332…取込見積表
1...Estimation support system 10...Equipment work person side terminal 11...Property data uploading means 12...Estimation requesting means 13...Acceptance/refusal confirmation means 14...Estimated quantity record receiving means 15...Progress confirmation means 16...Estimate requesting means 17...Acceptance/refusal Confirmation means 18...Estimation receiving means 19...Estimate comparison means 20...Estimator side terminal 21...Property data receiving means 22...Estimation quantity record sending means 30...Estimator side terminal 31...Estimation data receiving means 32...Estimate Sending means 100...Construction property work screen 101...Work selection area 102...Work instruction area 103...Property narrowing display area 110...Property list screen 111...Property list 112...Status field 120...Agent list screen 121...Product agent Store manufacturer selection screen 122...Product list 123...Journal addition area 124...Journal addition button 125...Update button 130...Property details screen 131...Upload instruction button 140...Material upload screen 141...Work instruction area 142...File table 145...Receive Email setting work screen 146...recipient person table 150...journal selection screen 151...journal classification table 152...next button 160...material sending & quotation request screen 161...work instruction area 162...common item reflection area 163...agency list 164...Common items reflection button 170...Quotation request screen 171...Work instruction area 172...Construction item table 173...Quotation request list 180...Journal classification list screen 181...Journal classification list 182...Request status button 190...Request destination selection Screen 191... Work instruction area 192... List of agents handling materials 193... Quantity sending button 1010... Request status screen 1011... Work instruction area 1012... Request status list 1020... Estimate request screen 1021... Estimate request button 1022... Comment input Part 1023...Estimation office list 1024...Estimation requesting list 1030...Construction estimate work screen 1031...Equipment and material classification display table 1032...Update button 1040...Estimate comparison screen 1041...Comparison agency list 1042...CSV button 1043... Product name etc. selection processing button 1044...Estimate comparison table 1045...Estimate comparison work instruction area 1046...Unallocated data list 1047...Data reflection instruction area 1048...Update estimate comparison table 1050...Item matching screen 1051...Matched item reservation table 1052...Execute Button 1060...Grade list display screen 1061...Work instruction area 1062...Estimated recruitment amount display area 1063...Display table by group 1070...Grade list amount input screen 1071...Work instruction area 1072...Estimated submission amount display area 1073...Amount to be submitted by group Table 1080...Item name recruitment screen 1081...Work instruction area 1082...Item name recruitment list 1090...Document download screen 1091...Estimating person table 1092...Estimating person table 1093...Estimating office CSV data output instruction area 1094...CSV data Output instruction area 1095... Journal classification table 200... Estimated property work screen 201... Work instruction area 210... Estimated property list screen 211... Estimated property list 220... Estimated work status screen 221... Work status display area 222... Status notification area 223... Comment input section 225...Material upload button 230...Material input screen 231...Check instruction area 232...Equipment specification confirmation column 233...Material input table 240...Comparison table screen 241...Work instruction area 242...Change history display section 243...Comparison table 244 ...Estimated data display section after change 245...Estimated data display section 246 before change...Change content display section 300...Estimated property work screen 301...Work selection area 302...Work instruction area 310...Estimated property list screen 311...Estimated property list 320 ... Estimation work status screen 321 ... Work status display area 322 ... Status notification area 323 ... Desired estimate submission date input section 324 ... Comment input section 325 ... Document upload button 326 ... Work start button 330 ... Estimate work screen 331 ... Work instruction area 332 …Intake estimate table

Claims (3)

各種設備工事において、その設備工事内容の積算見積書を作成する設備工事の積算見積書の作成方法であって、
設備工事担当者側に設置される設備工事者側端末と、積算担当者側に設置される積算担当者側端末と、見積担当者側に設置される見積担当者側端末とがクラウドを介して相互に送受信可能に繋がっており、
設備工事者側端末によって設備工事内容の物件資料が登録物件としてクラウド上にアップロードされ、
アップロードされた物件資料がクラウド上から積算担当者側端末によってダウンロードされ、
積算担当者側端末によって設備工事内容の各種機器資材が積算されて、CSVデータ、エクセル(登録商標)データの汎用データ形式で作成された積算数量調書データがクラウド上にアップロードされ、
アップロードされた積算数量調書データが設備工事担当者側端末によってダウンロードされ、
設備工事担当者側端末によってダウンロードされた積算数量調書データによる積算処理後に前記各種機器資材の積算データとして作成され、この作成された積算データは設備工事担当者側端末によってクラウド上にアップロードされ、
アップロードされた積算データは複数の見積担当者側端末それぞれによってダウンロードされ、
見積担当者側端末によってダウンロードされた積算データを基にして前記の各種機器機材が見積もられて前記の汎用データ形式で作成された見積書データが見積担当者側端末によってクラウド上にアップロードされ、
クラウド上にアップロードされた複数の見積書データは設備工事担当者側端末によってダウンロードされ、
複数の見積書データがダウンロードされた設備工事担当者側端末では、複数の見積書データの各種機器資材の諸データを前記積算データ中の各種機器資材の諸データとの項目の突合処理、紐付け処理後に、各種機器資材の諸データを羅列表示し、比較対照され、
比較対照後に採用される見積額による積算見積書が作成される、
ことを特徴とする設備工事の積算見積書の作成方法。
A method for preparing cost estimates for equipment work for preparing cost estimates for the contents of equipment work in various types of equipment work, the method comprising:
The equipment installer's terminal installed on the equipment construction worker's side, the cost estimate worker's terminal installed on the estimator's side, and the estimator's terminal installed on the estimator's side are connected via the cloud. They are connected to each other so that they can send and receive data,
The equipment construction worker's terminal uploads the property data of the equipment work to the cloud as a registered property.
Uploaded property materials are downloaded from the cloud by the cost estimate specialist's terminal,
The cost estimate staff's terminal calculates the cost of various equipment and materials for equipment construction, and the cost estimate quantity record data created in general-purpose data formats such as CSV data and Excel (registered trademark) data is uploaded to the cloud.
The uploaded cumulative quantity record data is downloaded by the facility construction worker's terminal,
After the cost estimation process is performed using the cost estimate quantity record data downloaded by the terminal on the equipment construction person's side, it is created as cost estimation data for the various equipment materials, and this created cost estimate data is uploaded to the cloud by the terminal on the equipment construction person's side.
The uploaded cost estimation data is downloaded by each of the multiple estimator side terminals,
The various equipment and equipment are estimated based on the cost estimation data downloaded by the estimator's terminal, and the estimate data created in the general data format is uploaded to the cloud by the estimator's terminal.
Multiple estimate data uploaded to the cloud are downloaded by the facility construction worker's terminal,
On the equipment construction worker's side terminal where multiple pieces of estimate data have been downloaded, item comparison processing and linkage are performed between various data on various equipment materials in the multiple estimate data and various data on various equipment materials in the cost estimation data. After processing, various data on various equipment materials are listed and compared and contrasted.
A cost estimate is created based on the estimated amount adopted after comparison.
A method for preparing a cost estimate for equipment construction, characterized by:
工事施工者側から依頼された各種設備工事を担当する設備工事担当者がその設備工事内容の積算見積書を作成する設備工事の積算見積書の作成方法であって、設備工事内容の各種機器資材をCSVデータ、エクセル(登録商標)データの汎用データ形式で作成された積算数量調書データを基にして積算データとして作成され、この積算データを基にして各種機器資材の見積書データを前記の汎用データ形式によって整理し積算見積書が作成されるようにして成り、
設備工事担当者側に設置される設備工事担当者側端末と、積算担当者側に設置される積算担当者側端末と、見積担当者側に設置される見積担当者側端末とがクラウドを介して相互に送受信可能に繋がっており、
設備工事担当者側端末によって物件登録された物件資料が物件資料アップロード手段によってクラウド上にアップロードされるステップと、
設備工事担当者側端末による積算受託承認済の積算担当者側端末によって物件資料がクラウド上からダウンロードされるステップと、
積算担当者側端末によって、前記の汎用データ形式として整理された前記各種機器資材の積算数量調書データがクラウド上にアップロードされるステップと、
設備工事担当者側端末によって、クラウド上からダウンロードされた積算数量調書データによる積算処理後に各種機器資材の積算データが作成されるステップと、
設備工事担当者側端末における見積依頼手段によって、見積依頼内容を複数の見積担当者側端末に通知表示させるステップと、
設備工事担当者側端末と見積担当者側端末との相互間で、見積依頼の諾否状況が更新表示されるステップと、
見積担当者側端末における積算データ受領手段によって前記積算データが見積担当者側端末にクラウド上からダウンロードされるステップと、
見積担当者側端末における見積書送付手段によってクラウド上に前記各種機器資材の見積書データが前記の汎用データ形式としてアップロードされるステップと、
設備工事担当者側端末において見積書受領手段によってクラウド上からダウンロードされて複数の見積書データそれぞれが保存されるステップと、
設備工事担当者側端末に表示される見積比較画面において、複数の見積書データ中の各種機器資材の諸データを積算データ中の各種機器資材の諸データとの項目の突合処理、紐付け処理後に、各種機器資材の諸データを羅列表示し、見積比較手段によって比較対照できるようにされたステップと、
設備工事担当者側端末において、積算データ、見積書データの比較対照後に採用された見積額でCSVデータによって積算見積書が作成されるステップ、
を備えたことを特徴とする設備工事の積算見積書の作成方法。
A method of preparing cost estimate for facility work in which a person in charge of various facility works requested by the construction contractor prepares a cost estimate for the content of the facility work. is created as cost estimate data based on cost estimate quantity record data created in general-purpose data formats such as CSV data and Excel (registered trademark) data, and based on this cost estimate data, quotation data for various equipment and materials is converted into the above-mentioned general-purpose data format. The data is organized according to the format and a cost estimate is created.
The facility construction worker's terminal installed at the equipment construction worker's side, the cost estimation worker's terminal installed at the cost estimation worker's side, and the estimator's terminal installed at the estimator's side are connected via the cloud. are connected to each other so that they can send and receive data,
a step in which the property data registered by the equipment construction worker's side terminal is uploaded to the cloud by the property data uploading means;
a step in which property materials are downloaded from the cloud by a terminal on the equipment construction person's side that has been approved for the cost estimation contract;
a step in which the cost estimate quantity record data of the various equipment materials organized in the general-purpose data format is uploaded to the cloud by a terminal on the side of the cost estimate person;
A step in which cost estimation data for various equipment materials is created after cost estimation processing using cost estimate quantity record data downloaded from the cloud by a terminal on the side of the facility construction worker;
a step of notifying and displaying the contents of the quotation request on a plurality of estimator side terminals by the quotation requesting means on the equipment construction person side terminal;
a step in which the approval/disapproval status of the quotation request is updated and displayed between the equipment construction person's side terminal and the estimating person's side terminal;
downloading the cost estimate data to the estimator's side terminal from the cloud by the cost estimate data receiving means on the estimator's side terminal;
uploading the estimate data for the various equipment and materials onto the cloud in the general-purpose data format by the estimate sending means on the estimator's terminal;
a step in which a plurality of pieces of estimate data are each downloaded from the cloud by an estimate receiving means on a facility construction worker's side terminal, and each of the plurality of estimate data is saved;
On the quotation comparison screen displayed on the equipment construction worker's terminal, the data for various equipment materials in multiple quotation data is compared and linked with the data for various equipment materials in the cost estimation data. , a step of displaying various data of various equipment materials in a list and making it possible to compare and contrast using an estimate comparison means;
A step in which a cost estimate is created using CSV data using the estimated amount adopted after comparing and contrasting the cost estimate data and the quotation data on the facility construction worker's side terminal;
A method for preparing a cost estimate for equipment construction, characterized by comprising:
設備工事担当者側に設置される設備工事担当者側端末と、積算担当者側に設置される積算担当者側端末と、見積担当者側に設置される見積担当者側端末とがクラウドを介して相互に送受信可能に繋がっており、
設備工事担当者側端末は、設備工事内容の物件資料をクラウド上にアップロードし,積算担当者側端末に各種機器資材の拾出しを依頼送信する積算依頼手段、積算担当者側端末からクラウド上にアップロードされたCSVデータ、エクセル(登録商標)データの汎用データ形式の前記各種機器資材の積算数量調書データをクラウド上からダウンロードして受領する積算数量調書受領手段、積算担当者側端末から得た積算数量調書データによる積算処理後に作成された前記各種機器資材の積算データをクラウド上にアップロードして、この積算データに基づく各種機器資材の費用見積を複数の見積担当者側端末に依頼送信する見積依頼手段、見積担当者側端末から前記の汎用データ形式でクラウド上にアップロードされた前記各種機器資材の複数の見積書データをクラウド上からダウンロードして受領する見積書受領手段、複数の見積書データを比較対照する見積比較手段を備えていて、この見積比較手段では、見積書データは積算データと対照可能とする一覧表示でき、比較対照後に採用された見積額でCSVデータによって積算見積書が作成できるようにしてあり、
積算担当者側端末は、設備工事担当側端末からの物件資料をクラウド上からダウンロードして受領する物件資料受領手段、作成した前記各種機器資材の積算数量調書データを前記の汎用データ形式でクラウド上にアップロードすることで送信する積算数量調書送付手段を備え、
見積担当者側端末は、前記積算データをクラウド上からダウンロードすることで受領する積算データ受領手段、作成した前記各種機器資材の見積書データを前記の汎用データ形式でクラウド上にアップロードすることで設備工事担当者側端末に送信する見積書送付手段を備えて、
成ることを特徴とする設備工事の積算見積書作成支援装置。
The facility construction worker's terminal installed at the equipment construction worker's side, the cost estimation worker's terminal installed at the cost estimation worker's side, and the estimator's terminal installed at the estimator's side are connected via the cloud. are connected to each other so that they can send and receive data,
The facility construction worker's terminal uploads the property data of the facility construction work onto the cloud, and sends a request to the cost estimation specialist's terminal to pick up various equipment materials. A cost estimate quantity record receiving means for downloading and receiving the quantity record data of the various equipment and materials in the general data format of uploaded CSV data and Excel (registered trademark) data from the cloud, and a cost estimate obtained from the terminal on the side of the person in charge of quantity estimation. A request for quotation that uploads the cost estimate data of the various equipment materials created after the cost estimation process using the bill of quantities data to the cloud, and sends a request to multiple estimators' side terminals for cost estimates for the various equipment materials based on this cost estimate data. means, an estimate receiving means for downloading and receiving from the cloud a plurality of estimate data for the various equipment and materials uploaded from the estimator's terminal in the general-purpose data format to the cloud; Equipped with an estimate comparison means for comparison, this estimate comparison means can display a list of estimate data that can be compared with cost estimate data, and can create a cost estimate using CSV data with the estimated amount adopted after comparison. It is as follows,
The cost estimation person's side terminal has a property information receiving means that downloads and receives property materials from the equipment construction staff terminal from the cloud, and downloads the created cost estimate quantity report data for the various equipment materials onto the cloud in the general-purpose data format. Equipped with a means to send cumulative quantity records by uploading them to
The estimator's side terminal receives the cost estimation data by downloading the cost estimation data from the cloud, and uploads the created quotation data for the various equipment and materials to the cloud in the general-purpose data format. Equipped with a means to send an estimate to the construction worker's terminal,
1. A support device for creating cost estimates for equipment construction, which is characterized by:
JP2023181546A 2020-10-29 2023-10-23 Method for preparing cost estimate for facility construction and support device for preparing cost estimate for facility construction Active JP7466133B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2023181546A JP7466133B2 (en) 2020-10-29 2023-10-23 Method for preparing cost estimate for facility construction and support device for preparing cost estimate for facility construction

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2020181067A JP2022071930A (en) 2020-10-29 2020-10-29 Estimation support system of facilities construction work
JP2023181546A JP7466133B2 (en) 2020-10-29 2023-10-23 Method for preparing cost estimate for facility construction and support device for preparing cost estimate for facility construction

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2020181067A Division JP2022071930A (en) 2020-10-29 2020-10-29 Estimation support system of facilities construction work

Publications (2)

Publication Number Publication Date
JP2023174958A true JP2023174958A (en) 2023-12-08
JP7466133B2 JP7466133B2 (en) 2024-04-12

Family

ID=81605208

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2020181067A Pending JP2022071930A (en) 2020-10-29 2020-10-29 Estimation support system of facilities construction work
JP2023181546A Active JP7466133B2 (en) 2020-10-29 2023-10-23 Method for preparing cost estimate for facility construction and support device for preparing cost estimate for facility construction

Family Applications Before (1)

Application Number Title Priority Date Filing Date
JP2020181067A Pending JP2022071930A (en) 2020-10-29 2020-10-29 Estimation support system of facilities construction work

Country Status (1)

Country Link
JP (2) JP2022071930A (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6224364A (en) * 1985-07-24 1987-02-02 Yamamoto Sohei General-purpose control system
JP2000048071A (en) * 1998-05-28 2000-02-18 Shiimaa:Kk Integral estimate system for building and interior construction
JP2002334234A (en) * 2001-05-09 2002-11-22 Shinshowa Corp Wage integrating and estimating system/wage integrating and estimating method for building/interior decoration construction, computer program therefor and recording medium
JP2003006272A (en) 2001-06-22 2003-01-10 Misumi Corp Construction design support system, and architect support terminal device, construction design support server, construction contractor support terminal device and construction design support method, which are usable on the system
JP2003114990A (en) * 2001-10-05 2003-04-18 Universal Home Inc Franchise data processing system for house or the like

Also Published As

Publication number Publication date
JP7466133B2 (en) 2024-04-12
JP2022071930A (en) 2022-05-17

Similar Documents

Publication Publication Date Title
AU2015101964A4 (en) Construction management system
US7409392B2 (en) System and method for managing construction projects
US20060212323A1 (en) Production management system
US7099726B2 (en) Production planning system
US20100257012A1 (en) Lead management system
US7039481B2 (en) Production planning system
US20130231981A1 (en) Construction trade building information management system, software and method
JP2002169996A (en) Server device, scheduling control device, production/ physical distribution management system, terminal device, production/physical distribution management method, and computer-readable recording medium with production/physical distribution management program recorded thereon, program for making computer function as scheduling control device, and computer-readable recording medium with the same program recorded thereon
JP2004021364A (en) Management intention decision support system
US20030097288A1 (en) Inspection schedule management support system and inspection schedule management support method
JP6691283B2 (en) Control system
JP3695312B2 (en) Management / maintenance part providing method and system
US20200126145A1 (en) System and method for management of web order placement
JP2005101928A (en) Edi data assignment system, edi system, and program
JP2007041799A (en) Project management support system
JP2023174958A (en) Creation method of integrating estimate for facility construction and creation supporting device of integrating estimate for facility construction
KR101878261B1 (en) Apparatus and the method for managing rental or lease
JPH09319795A (en) Work control system in product processing work
JP2002288493A (en) Electronic procuring system, electronic procuring support device and electronic procuring method
JP7193190B1 (en) Manufacturing consignment support system, manufacturing consignment support program, manufacturing consignment support method
JP2002203031A (en) Cleaning service management system
JP5199795B2 (en) Forecast management system and program
JP2012173759A (en) Component information management system and method
KR20190084739A (en) Apparatus and method for synthetically managing resource for cost accounting
JPH0896045A (en) Sales program support system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20231023

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20231025

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240206

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240208

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240227

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240322

R150 Certificate of patent or registration of utility model

Ref document number: 7466133

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150