JP2022171395A - Start and end scheduled date calculation device, start and end scheduled date calculation method, and start and end scheduled date calculation program - Google Patents
Start and end scheduled date calculation device, start and end scheduled date calculation method, and start and end scheduled date calculation program Download PDFInfo
- Publication number
- JP2022171395A JP2022171395A JP2021078006A JP2021078006A JP2022171395A JP 2022171395 A JP2022171395 A JP 2022171395A JP 2021078006 A JP2021078006 A JP 2021078006A JP 2021078006 A JP2021078006 A JP 2021078006A JP 2022171395 A JP2022171395 A JP 2022171395A
- Authority
- JP
- Japan
- Prior art keywords
- date
- project
- scheduled
- days
- identification data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
本発明は、開始・終了予定日算出装置、開始・終了予定日算出方法および開始・終了予定日算出プログラムに関する。 The present invention relates to a start/end date calculation device, a start/end date calculation method, and a start/end date calculation program.
特許文献1には、営業段階から住宅の受注、施工、完成引き渡し、アフターケアまでの多様な工程と膨大な作業項目について、その作業項目の担当者(実施責任者)に対して、最適なタイミングで個別に作業指示を出すことができるとともに、作業項目単位でのきめ細かな進捗管理が行える進捗管理システムが開示されている(特許文献1の0007段落参照)。
In
上記特許文献1に記載のように、プロジェクト(例えば、工事の案件)を構成する工程のスケジュールを正確に管理することは重要である。
As described in
しかしながら、従来においては、例えばある工事における工程を組む際には、各工程についての作業の開始予定日および終了予定日をオペレータが手動で設定しなければならず、大変な時間と労力を要し、入力ミスの問題もあった。また、工事の遅延等により、既にスケジュールが組まれた工程について日程の変更が生じ、作業の開始予定日および終了予定日のリスケジュールを行う際にも、同様の問題があった。 However, in the past, for example, when setting up the processes for a certain construction work, the operator had to manually set the scheduled start date and scheduled end date of the work for each process, which required a great deal of time and labor. , there was also a problem of input errors. Also, due to delays in construction, etc., the schedule of the already scheduled process is changed, and the same problem arises when rescheduling the scheduled start date and scheduled end date of the work.
本発明は、上記問題点に鑑みてなされたものであって、プロジェクトを構成する各工程についての作業の開始予定日および終了予定日を自動算出することができる開始・終了予定日算出装置、開始・終了予定日算出方法および開始・終了予定日算出プログラムを提供することを目的とする。 SUMMARY OF THE INVENTION The present invention has been made in view of the above problems. - The purpose is to provide a method for calculating a scheduled end date and a program for calculating a scheduled start/end date.
上述した課題を解決し、目的を達成するために、本発明に係る開始・終了予定日算出装置においては、制御部および記憶部を備え、プロジェクトを構成する工程についての作業の開始予定日および終了予定日を算出することができる開始・終了予定日算出装置であって、前記記憶部には、前記プロジェクトを識別するためのプロジェクト識別データと、前記プロジェクトに関する情報と、を含むプロジェクト基本情報データと、前記工程の組み方に関するパターンと、当該パターンに対応する条件と、を対応付けて含む工程パターンマスタと、が格納されており、前記パターンは、前記工程を識別するための工程識別データ、前記工程毎に設定された算出元工程識別データ、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数によって構成され、前記制御部は、前記プロジェクト基本情報データから、オペレータによって指定されたプロジェクト識別データと紐づく前記プロジェクトに関する情報を取得する第一取得手段と、前記工程パターンマスタから、前記第一取得手段で取得した前記プロジェクトに関する情報に合致する前記条件に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数を取得する第二取得手段と、前記第二取得手段で取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、当該ある工程については、前記指定された開始予定日および前記第二取得手段で取得した前記ある工程についての前記作業日数を用いて、前記終了予定日を算出し、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、前記第二取得手段で取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数を用いて、前記開始予定日および前記終了予定日を算出する日付算出手段と、を備えること、を特徴とする。 In order to solve the above-described problems and achieve the object, a scheduled start/end date calculation apparatus according to the present invention includes a control unit and a storage unit, and calculates the scheduled start date and end date of work for the steps constituting a project. A scheduled start/end date calculation device capable of calculating a scheduled date, wherein the storage unit stores project basic information data including project identification data for identifying the project and information about the project. , a process pattern master including a pattern related to the combination of the processes and a condition corresponding to the pattern in association with each other, and the pattern includes process identification data for identifying the process; Calculation source process identification data set for each process, interval days set for each process, and work days set for each process, and the control unit is specified by the operator from the project basic information data a first acquiring means for acquiring information about the project linked to the project identification data obtained from the process pattern master; and forming a pattern corresponding to the condition matching the information about the project acquired by the first acquiring means from the process pattern master. A second acquisition means for acquiring the process identification data, the calculation source process identification data, the interval days and the work days, and a process specified by the process identification data acquired by the second acquisition means When the scheduled start date of the work is specified by the operator, for the certain process, using the specified scheduled start date and the work days for the certain process acquired by the second acquisition means, calculating the scheduled end date, and identifying the calculation source process acquired by the second acquisition means for the process from the process next to the certain process to the last process among the specified processes date calculation means for calculating the scheduled start date and the scheduled end date using the data, the interval days and the work days.
また、本発明に係る開始・終了予定日算出装置においては、前記日付算出手段は、前記ある工程については、前記指定された開始予定日に、前記第二取得手段で取得した前記ある工程についての前記作業日数から1を減じた日数を加算した日付を前記終了予定日として算出すること、を特徴とする。 Further, in the scheduled start/end date calculation device according to the present invention, the date calculation means calculates the date of the certain process acquired by the second acquisition means on the specified scheduled start date for the certain process. The date obtained by adding the number of days obtained by subtracting 1 from the number of working days is calculated as the scheduled end date.
また、本発明に係る開始・終了予定日算出装置においては、前記日付算出手段は、前記次の工程については、前記第二取得手段で取得した前記次の工程についての前記算出元工程識別データで特定される工程についての前記終了予定日に、前記第二取得手段で取得した前記次の工程についての前記インターバル日数に1を加えた日数を加算した日付を前記開始予定日として算出し、当該算出した開始予定日に、前記第二取得手段で取得した前記次の工程についての前記作業日数から1を減じた日数を加算した日付を前記終了予定日として算出する処理を実行し、前記次の工程の更に次の工程から前記最後の工程までについては、前記処理と同様の処理を繰り返すことにより、前記開始予定日および前記終了予定日を算出すること、を特徴とする。 Further, in the scheduled start/end date calculation device according to the present invention, the date calculation means uses the calculation source process identification data for the next process acquired by the second acquisition means for the next process. calculating the scheduled start date by adding the number of days obtained by adding 1 to the number of interval days for the next step acquired by the second acquiring means to the scheduled end date of the identified step, and calculating the scheduled start date; calculating the scheduled end date by adding the number of days obtained by subtracting 1 from the number of working days for the next step acquired by the second acquisition means to the scheduled start date obtained, and calculating the scheduled end date of the next step; From the next step to the last step, the scheduled start date and the scheduled end date are calculated by repeating the same processing as the above processing.
また、本発明に係る開始・終了予定日算出装置においては、前記プロジェクトに関する情報が、前記プロジェクトの種類および前記プロジェクトの金額に関する情報であり、前記条件が、前記プロジェクトの種類および前記プロジェクトの金額に関する条件であること、を特徴とする。 Further, in the scheduled start/end date calculation device according to the present invention, the information on the project is information on the type of the project and the amount of the project, and the conditions are information on the type of the project and the amount of the project. being a condition.
また、本発明に係る開始・終了予定日算出装置においては、前記プロジェクトが、工事の案件であること、を特徴とする。 Further, in the scheduled start/end date calculation device according to the present invention, the project is a construction project.
また、本発明に係る開始・終了予定日算出方法においては、制御部および記憶部を備える情報処理装置で実行される、プロジェクトを構成する工程についての作業の開始予定日および終了予定日を算出することができる開始・終了予定日算出方法であって、前記記憶部には、前記プロジェクトを識別するためのプロジェクト識別データと、前記プロジェクトに関する情報と、を含むプロジェクト基本情報データと、前記工程の組み方に関するパターンと、当該パターンに対応する条件と、を対応付けて含む工程パターンマスタと、が格納されており、前記パターンは、前記工程を識別するための工程識別データ、前記工程毎に設定された算出元工程識別データ、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数によって構成され、前記制御部で実行される、前記プロジェクト基本情報データから、オペレータによって指定されたプロジェクト識別データと紐づく前記プロジェクトに関する情報を取得する第一取得ステップと、前記工程パターンマスタから、前記第一取得ステップで取得した前記プロジェクトに関する情報に合致する前記条件に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数を取得する第二取得ステップと、前記第二取得ステップで取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、当該ある工程については、前記指定された開始予定日および前記第二取得ステップで取得した前記ある工程についての前記作業日数を用いて、前記終了予定日を算出し、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、前記第二取得ステップで取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数を用いて、前記開始予定日および前記終了予定日を算出する日付算出ステップと、を含むこと、を特徴とする。 Further, in the method for calculating scheduled start/end dates according to the present invention, the scheduled start date and scheduled end date of work for the steps constituting a project, which are executed by an information processing apparatus having a control unit and a storage unit, are calculated. In the storage unit, project basic information data including project identification data for identifying the project and information about the project, and the process combination method and a process pattern master including a pattern associated with the pattern and a condition corresponding to the pattern, and the pattern includes process identification data for identifying the process and set for each process. A project specified by an operator from the project basic information data, which is composed of calculation source process identification data, interval days set for each process, and work days set for each process, and is executed by the control unit a first acquisition step of acquiring information about the project linked to the identification data; and the step of configuring a pattern corresponding to the condition that matches the information about the project acquired in the first acquisition step from the process pattern master. A second acquisition step of acquiring identification data, the calculation source process identification data, the interval days and the work days; and a process specified by the process identification data acquired in the second acquisition step. When the scheduled start date of the work is specified by the operator, for the certain process, the specified scheduled start date and the work days for the certain process acquired in the second acquisition step are used to determine the end date. Calculate the scheduled date, and for the process next to the certain process among the specified processes to the last process among the specified processes, the calculation source process identification data acquired in the second acquisition step; and a date calculation step of calculating the scheduled start date and the scheduled end date using the interval days and the work days.
また、本発明に係る開始・終了予定日算出プログラムにおいては、制御部および記憶部を備える情報処理装置に実行させるための、プロジェクトを構成する工程についての作業の開始予定日および終了予定日を算出することができる開始・終了予定日算出プログラムであって、前記記憶部には、前記プロジェクトを識別するためのプロジェクト識別データと、前記プロジェクトに関する情報と、を含むプロジェクト基本情報データと、前記工程の組み方に関するパターンと、当該パターンに対応する条件と、を対応付けて含む工程パターンマスタと、が格納されており、前記パターンは、前記工程を識別するための工程識別データ、前記工程毎に設定された算出元工程識別データ、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数によって構成され、前記制御部に実行させるための、前記プロジェクト基本情報データから、オペレータによって指定されたプロジェクト識別データと紐づく前記プロジェクトに関する情報を取得する第一取得ステップと、前記工程パターンマスタから、前記第一取得ステップで取得した前記プロジェクトに関する情報に合致する前記条件に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数を取得する第二取得ステップと、前記第二取得ステップで取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、当該ある工程については、前記指定された開始予定日および前記第二取得ステップで取得した前記ある工程についての前記作業日数を用いて、前記終了予定日を算出し、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、前記第二取得ステップで取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数を用いて、前記開始予定日および前記終了予定日を算出する日付算出ステップと、を含むこと、を特徴とする。 Further, in the scheduled start/end date calculation program according to the present invention, the scheduled start date and scheduled end date of the work for the steps constituting the project to be executed by the information processing apparatus having the control unit and the storage unit are calculated. In the storage unit, project basic information data including project identification data for identifying the project and information about the project; A process pattern master containing a combination pattern and a condition corresponding to the pattern is stored, and the pattern includes process identification data for identifying the process and set for each process. Calculation source process identification data, interval days set for each process, and work days set for each process, and specified by the operator from the project basic information data for causing the control unit to execute a first acquisition step of acquiring information on the project linked to the project identification data obtained; and forming a pattern corresponding to the condition that matches the information on the project acquired in the first acquisition step from the process pattern master. a second acquisition step of acquiring the process identification data, the calculation source process identification data, the interval days, and the work days; and a process specified by the process identification data acquired in the second acquisition step. When the scheduled start date of the work is specified by the operator, for the certain process, using the specified scheduled start date and the work days for the certain process acquired in the second acquisition step, calculating the scheduled end date, and identifying the calculation source process acquired in the second acquiring step for the process next to the certain process among the specified processes to the last process among the specified processes; and a date calculation step of calculating the scheduled start date and the scheduled end date using the data, the interval days and the work days.
本発明によれば、プロジェクトを構成する各工程についての作業の開始予定日および終了予定日を自動算出することができるという効果を奏する。 Advantageous Effects of Invention According to the present invention, it is possible to automatically calculate the scheduled start date and scheduled end date of work for each process that constitutes a project.
以下に、本発明に係る開始・終了予定日算出装置、開始・終了予定日算出方法および開始・終了予定日算出プログラムの実施形態を、図面に基づいて詳細に説明する。なお、本実施形態により本発明が限定されるものではない。 Hereinafter, embodiments of the scheduled start/end date calculation device, the scheduled start/end date calculation method, and the scheduled start/end date calculation program according to the present invention will be described in detail based on the drawings. It should be noted that the present invention is not limited by this embodiment.
[1.概要]
デベロッパー工事の工程は、大きくいくつかのパターンに分類することができるが、大抵スケジュール通りに進まない。天候の影響や人員のアサイン変更により、工途中の段階で何度もスケジュールの見直しを行う。そのたびに、各工程の開始予定日および終了予定日の再設定を行っているが、時間がかかりミスも発生し大きく時間を消費するという問題があった。また、各工程を進める上で、a工程が完了していないとb工程に進めないという場合もあるため、工程を進める段取りの間違えでプロジェクトの進捗を遅らせないようにするためには、各工程を細かく管理することが必要であった。なお、各工程の管理は、通常、工程管理課が各工程の進捗を把握し工事依頼できる業者がいないか等の判断をすることにより行っており、これにより、プロジェクトの最適化を図っている。
[1. Overview]
The process of developer construction can be roughly classified into several patterns, but most of them do not proceed according to schedule. Due to the influence of weather and changes in personnel assignments, the schedule will be reviewed many times during the construction stage. Each time, the scheduled start date and scheduled end date of each process are set again, but there is a problem that it takes time and mistakes occur, which consumes a lot of time. Also, when proceeding with each process, there may be cases where you cannot proceed to process b unless process a is completed. had to be carefully managed. In addition, the management of each process is usually carried out by the process control section grasping the progress of each process and making judgments such as whether there is a contractor who can request construction work.This is how we are trying to optimize the project. .
そこで、本実施形態においては、例えば、工程パターン単位で、工程毎の予定日数を設定しておくことにより、工程パターン単位で、工程毎の開始予定日および終了予定日を算出(再算出含む)できるようにした。具体的には、システムで登録した工事の種類に応じて工程パターンが自動決定された後、担当者が最初の工程の開始予定日を入力すれば、すべての工程について、開始予定日および終了予定日が自動セットされる。また、本実施形態においては、例えば、工程の途中でスケジュール遅延等が発生した場合には、担当者が対象工程の開始予定日を変更することで、後続の工程について、開始予定日および終了予定日が自動的に再算出されて変更される。言い換えると、終了予定日が変更された工程の変更後の終了予定日を基に、自身を起点とする次工程の開始日予定日および終了予定日の洗替が自動的に順次行われ、新たなスケジュール立案が実施される。 Therefore, in the present embodiment, for example, by setting the scheduled number of days for each process for each process pattern, the scheduled start date and scheduled end date for each process are calculated (including recalculation) for each process pattern. made it possible. Specifically, after the process pattern is automatically determined according to the type of construction registered in the system, if the person in charge enters the scheduled start date of the first process, the scheduled start date and scheduled end date will be displayed for all processes. The date is set automatically. In addition, in this embodiment, for example, if a schedule delay or the like occurs in the middle of a process, the person in charge changes the scheduled start date of the target process so that the scheduled start date and scheduled end date for subsequent processes are changed. The date is automatically recalculated and changed. In other words, based on the changed scheduled end date of the process whose scheduled end date has been changed, the scheduled start date and scheduled end date of the next process starting from itself are automatically replaced sequentially, and the new scheduled end date is automatically changed. scheduling is carried out.
このように、工事の種類や条件により、工程パターンが自動で決定されて工程毎の開始予定日および終了予定日が自動算出されることにより、工程管理の際の入力ミスを減らすことができる。また、従来においては、スケジュール遅延が発生する度に、担当者が、後続の工程についての開始予定日および終了予定日を手動で再設定していたが、本実施形態によれば、変更が生じた工程について開始予定日を変更すれば、後続の工程についての開始予定日および終了予定日が自動的に再算出されて変更されるため、時間短縮やミス削減等をすることができる。以下、具体的な構成および動作について説明する。 In this manner, the process pattern is automatically determined according to the type and conditions of construction, and the scheduled start date and scheduled end date for each process are automatically calculated, thereby reducing input errors during process management. Conventionally, every time a schedule delay occurs, the person in charge manually resets the scheduled start date and scheduled end date for the subsequent process. If the scheduled start date of the first process is changed, the scheduled start date and scheduled end date of the succeeding process are automatically recalculated and changed, so that time can be shortened and errors can be reduced. Specific configurations and operations will be described below.
[2.構成]
本実施形態に係る開始・終了予定日算出装置100の構成の一例について、図1を参照して説明する。図1は、開始・終了予定日算出装置100の構成の一例を示すブロック図である。
[2. Constitution]
An example of the configuration of the scheduled start/end
開始・終了予定日算出装置100は、市販のデスクトップ型パーソナルコンピュータである。なお、開始・終了予定日算出装置100は、デスクトップ型パーソナルコンピュータのような据置型情報処理装置に限らず、市販されているノート型パーソナルコンピュータ、PDA(Personal Digital Assistants)、スマートフォン、タブレット型パーソナルコンピュータなどの携帯型情報処理装置であってもよい。
The scheduled start/end
開始・終了予定日算出装置100は、制御部102と通信インターフェース部104と記憶部106と入出力インターフェース部108と、を備えている。開始・終了予定日算出装置100が備えている各部は、任意の通信路を介して通信可能に接続されている。
The scheduled start/end
通信インターフェース部104は、ルータ等の通信装置および専用線等の有線または無線の通信回線を介して、開始・終了予定日算出装置100をネットワーク300に通信可能に接続する。通信インターフェース部104は、他の装置と通信回線を介してデータを通信する機能を有する。ここで、ネットワーク300は、開始・終了予定日算出装置100とサーバ200とを相互に通信可能に接続する機能を有し、例えばインターネットやLAN(Local Area Network)等である。なお、後述する各種マスタ等のデータは、例えばサーバ200に格納されてもよい。
The
入出力インターフェース部108には、入力装置112および出力装置114が接続されている。出力装置114には、モニタ(家庭用テレビを含む)の他、スピーカやプリンタを用いることができる。入力装置112には、キーボード、マウス、及びマイクの他、マウスと協働してポインティングデバイス機能を実現するモニタを用いることができる。なお、以下では、出力装置114をモニタ114とし、入力装置112をキーボード112またはマウス112として記載する場合がある。
An input device 112 and an output device 114 are connected to the input/
記憶部106には、各種のデータベース、テーブルおよびファイルなどが格納される。記憶部106には、OS(Operating System)と協働してCPU(Central Processing Unit)に命令を与えて各種処理を行うためのコンピュータプログラムが記録される。記憶部106として、例えば、RAM(Random Access Memory)・ROM(Read Only Memory)等のメモリ装置、ハードディスクのような固定ディスク装置、フレキシブルディスク、および光ディスク等を用いることができる。
The
記憶部106は、例えば、プロジェクト基本情報データ106aと、プロジェクト種類一覧データ106bと、工程マスタ106cと、工程パターンマスタ106dと、工程進捗データ106eと、を備えている。
The
本実施形態にかかる開始・終了予定日算出装置100によれば、プロジェクトを構成する工程についての作業の開始予定日および終了予定日を算出することができる。前記プロジェクトは、例えば、工事の案件である。
According to the scheduled start/end
プロジェクト基本情報データ106aは、前記プロジェクトに関する基本情報を管理するためのマスタである。プロジェクト基本情報データ106aは、図7に示すように、例えば、前記プロジェクトを識別するためのプロジェクト識別データ(工事番号および工事名)と、前記プロジェクトに関する情報と、を含む。前記プロジェクトに関する情報は、図7に示すように、例えば、前記プロジェクトの種類に関する情報(工事種類)、前記プロジェクトの金額に関する情報(請負金額)、前記プロジェクトの開始日(着工日)および前記プロジェクトの完了予定日(完成予定日)等である。
The project
プロジェクト種類一覧データ106bは、図7に示すように、例えば、前記プロジェクトの種類に関する情報(工事種類)等を含む。図7のプロジェクト種類一覧データ106bは、6種類の工事種類を含むが、オペレータは、工事種類を適宜追加することが可能である。
As shown in FIG. 7, the project
工程マスタ106cは、図7に示すように、例えば、前記工程を識別するための工程識別データ(工程)等を含む。
The
工程パターンマスタ106dは、本発明の特徴であり、前記開始予定日および前記終了予定日を算出するために必要な情報を設定するためのマスタである。工程パターンマスタ106dは、図8に示すように、例えば、前記工程の組み方に関するパターンを識別するためのパターン識別データ(パターンコードおよびパターン名)と、当該パターンに対応する条件(パターン条件)と、当該パターンを構成する情報と、を対応付けて含む。前記条件(パターン条件)は、図8に示すように、例えば、前記プロジェクトの種類に関する条件(工事種類)および前記プロジェクトの金額に関する条件(請負金額)等である。
The
前記パターンを構成する情報とは、図8に示すように、例えば、前記工程を識別するための工程識別データ(工程および工程名)、前記工程毎に設定された算出元工程識別データ(算出元工程)、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数(開始終了日数)等である。 The information constituting the pattern includes, for example, process identification data (process and process name) for identifying the process, calculation source process identification data (calculation source process), interval days set for each process, and work days (start and end days) set for each process.
詳細は以下の[4.処理の具体例]で述べるが、工程パターンマスタ106d中の前記前記パターン条件、前記算出元工程および前記開始終了日数は、以下のようにして使用される。前記パターン条件については、プロジェクト基本情報データ106a中の請負工事契約の情報が、登録された前記パターン条件を満たしている場合、当該パターン条件に対応する前記パターンが取得される。前記算出元工程については、対象工程にとっての前記算出元工程の前記終了予定日に、前記インターバル日数に1を加えた日数を加算することにより、前記対象工程の開始予定日が算出される。前記開始終了日数については、前記対象工程の前記開始予定日に、前記開始終了日数から1を減じた日数を加算することにより、前記対象工程の前記終了予定日が算出される。
Details are described in [4. Specific example of processing], the pattern condition, the calculation source process, and the start/end days in the
工程進捗データ106eは、後述する工程進捗入力画面に入力された内容をデータとして出力したものである。工程進捗データ106eは、図10および図12に示すように、例えば、前記プロジェクト識別データ(工事番号)と、前記パターン識別データ(パターンコード)と、前記工程識別データ(工程および工程名)と、前記開始予定日と、前記終了予定日と、作業の実際の開始日(実開始日)と、作業の実際の終了日(実終了日)と、等を含む。
The
制御部102は、開始・終了予定日算出装置100を統括的に制御するCPU等である。制御部102は、OS等の制御プログラム・各種の処理手順等を規定したプログラム・所要データなどを格納するための内部メモリを有し、格納されているこれらのプログラムに基づいて種々の情報処理を実行する。
The control unit 102 is a CPU or the like that comprehensively controls the scheduled start/end
制御部102は、機能概念的に、例えば、(1)前記プロジェクト基本情報データから、オペレータによって指定されたプロジェクト識別データと紐づく前記プロジェクトに関する情報を取得する第一取得手段としての第一取得部102aと、(2)前記工程パターンマスタから、前記第一取得手段で取得した前記プロジェクトに関する情報に合致する前記条件に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数を取得する第二取得手段としての第二取得部102bと、(3)前記第二取得手段で取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、当該ある工程については、前記指定された開始予定日および前記第二取得手段で取得した前記ある工程についての前記作業日数を用いて、前記終了予定日を算出し、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、前記第二取得手段で取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数を用いて、前記開始予定日および前記終了予定日を算出する日付算出手段としての日付算出部102cと、を備えている。 The control unit 102 functionally conceptually includes, for example, (1) a first acquisition unit as a first acquisition unit that acquires information about the project linked to the project identification data specified by the operator from the project basic information data; 102a, (2) from the process pattern master, the process identification data, the calculation source process identification data, and the interval that form a pattern corresponding to the conditions that match the information on the project acquired by the first acquisition means; a second acquisition unit 102b as second acquisition means for acquiring the number of days and the number of work days; When the scheduled start date is specified by the operator, the scheduled end date for the certain process is calculated using the specified scheduled start date and the number of working days for the certain process acquired by the second acquiring means. is calculated, and from the step following the certain step to the last step among the specified steps, the calculation source step identification data acquired by the second acquisition means, the interval and a date calculation unit 102c as date calculation means for calculating the scheduled start date and the scheduled end date using the number of days and the number of work days.
第一取得部102aは、前記プロジェクト識別データ(工事番号)と前記プロジェクトに関する情報(工事種類および請負金額)とを含むプロジェクト基本情報データ106a(図7参照)から、オペレータによって指定されたプロジェクト識別データ(工事番号)と紐づく前記プロジェクトに関する情報(工事種類および請負金額)を取得する。
The first acquisition unit 102a acquires the project identification data specified by the operator from the project
第二取得部102bは、前記工程を識別するための工程識別データ、前記工程毎に設定された算出元工程識別データ、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数(開始終了日数)で構成される前記パターンと、当該パターンに対応する条件(パターン条件)と、を対応付けて含む工程パターンマスタ106d(図8参照)から、第一取得部102aで取得した前記プロジェクトに関する情報(工事種類および請負金額)に合致する前記条件(パターン条件)に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数(開始終了日数)を取得する。
The second acquisition unit 102b obtains process identification data for identifying the process, calculation source process identification data set for each process, interval days set for each process, and work days set for each process. The pattern obtained by the first obtaining unit 102a from the
日付算出部102cは、第二取得部102bで取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、以下の(1)および(2)の算出を行う。開始予定日が指定される当該ある工程は、初工程であってもよいし(新規登録の場合)、初工程より後の任意の工程であってもよい(リスケジュールの場合)。 The date calculation unit 102c performs the following (1) and (2) is calculated. The certain process for which the scheduled start date is specified may be the first process (in the case of new registration) or any process after the first process (in the case of rescheduling).
(1)日付算出部102cは、前記ある工程については、前記指定された開始予定日および第二取得部102bで取得した前記ある工程についての前記作業日数(開始終了日数)を用いて、前記終了予定日を算出する。具体的には、日付算出部102cは、前記ある工程については、前記指定された開始予定日に、第二取得部102bで取得した前記ある工程についての前記作業日数(開始終了日数)から1を減じた日数を加算した日付を前記終了予定日として算出する。 (1) The date calculation unit 102c, for the certain process, uses the specified scheduled start date and the working days (start and end days) for the certain process acquired by the second acquisition unit 102b to calculate the end date. Calculate the due date. Specifically, for the certain process, the date calculation unit 102c subtracts 1 from the work days (start and end days) for the certain process acquired by the second acquisition unit 102b on the specified scheduled start date. The date obtained by adding the subtracted number of days is calculated as the scheduled end date.
(2)日付算出部102cは、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、第二取得部102bで取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数(開始終了日数)を用いて、前記開始予定日および前記終了予定日を算出する。具体的には、日付算出部102cは、前記次の工程については、第二取得部102bで取得した前記次の工程についての前記算出元工程識別データで特定される工程についての前記終了予定日に、第二取得部102bで取得した前記次の工程についての前記インターバル日数に1を加えた日数を加算した日付を前記開始予定日として算出し、当該算出した開始予定日に、第二取得部102bで取得した前記次の工程についての前記作業日数(開始終了日数)から1を減じた日数を加算した日付を前記終了予定日として算出する処理を実行し、更に、前記次の工程の更に次の工程から前記最後の工程までについては、前記処理と同様の処理を繰り返すことにより、前記開始予定日および前記終了予定日を算出する。 (2) The date calculation unit 102c obtains the calculation source process acquired by the second acquisition unit 102b from the process next to the certain process to the last process among the specified processes. The scheduled start date and the scheduled end date are calculated using the identification data, the interval days, and the work days (start/end days). Specifically, for the next step, the date calculation unit 102c calculates the scheduled end date for the step specified by the calculation source step identification data for the next step acquired by the second acquisition unit 102b. , a date obtained by adding 1 to the interval days for the next step acquired by the second acquisition unit 102b is calculated as the scheduled start date, and the calculated scheduled start date is set to the second acquisition unit 102b for the next step obtained by subtracting 1 from the number of working days (starting and ending days) obtained in , and calculating the date as the scheduled end date; From the process to the last process, the scheduled start date and the scheduled end date are calculated by repeating the same processing as the above processing.
[3.処理の概要]
本項目では、本実施形態に係る処理の概要を説明する。具体的には、工程管理のイメージを、工事を計画する場合、工事が完了した場合およびリスケジュールの場合に分けて説明する。なお、本項目で用いる図2~図6においては、オペレータ(例えば、工程管理課の担当者)により画面から手動入力される日付をドット状のハッチングで示しており、これに対して、自動算出される日付を斜線状のハッチングで示している。
[3. Overview of processing]
In this section, an outline of processing according to this embodiment will be described. Specifically, the image of process management will be explained separately for the case of planning construction, the case of completion of construction, and the case of rescheduling. In FIGS. 2 to 6 used in this section, the date manually input from the screen by the operator (for example, the person in charge of the process control section) is indicated by dotted hatching. Dates to be completed are indicated by diagonal hatching.
[3-1.工事を計画する場合の工程管理のイメージ]
本項目では、工事を計画する場合の工程管理のイメージについて、図2および図3を参照して説明する。工程管理課の担当者は、プロジェクトのスケジュールを立てて、工事を依頼する業者の選定を行う。この際、並行で進めることができる工程については、並行で予定を立てて各業者に依頼する。
[3-1. Image of process control when planning construction]
In this section, an image of process control when planning construction work will be described with reference to FIGS. 2 and 3. FIG. The person in charge of the process control section makes a schedule for the project and selects contractors to request the construction work. At this time, for processes that can be carried out in parallel, a schedule is made in parallel and a request is made to each supplier.
図2の例では、工程管理課は、業者A~Cに対して工事を依頼している。図2に示すように、工事依頼の際には、工程管理課の担当者が算出元工程の予定日を入力すれば、後続の工程の予定日が自動算出される。図3には、工事を計画する場合に入力される予定日および自動算出される予定日を業者毎にまとめた表を示している。 In the example of FIG. 2, the process control section requests contractors A to C to perform construction work. As shown in FIG. 2, when a construction request is made, if the person in charge of the process control section inputs the scheduled date of the calculation source process, the scheduled date of the succeeding process is automatically calculated. FIG. 3 shows a table summarizing the scheduled dates that are input when planning a construction work and the scheduled dates that are automatically calculated for each contractor.
[3-2.工事が完了した場合の工程管理のイメージ]
本項目では、工事が完了した場合の工程管理のイメージについて、図4を参照して説明する。図4に示すように、工事が完了すると、工程管理課の担当者は、現場監督等から工事完了の連絡を受ける。工事完了の実績日は、当該連絡の後に、工程管理課の担当者により画面から入力されるか、または、他システムから連携される。
[3-2. Image of process management when construction is completed]
In this section, an image of process control when construction is completed will be described with reference to FIG. As shown in FIG. 4, when the construction work is completed, the person in charge of the process control section receives notification of construction completion from the site supervisor or the like. After the communication, the construction completion date is input from the screen by the person in charge of the process control section, or is linked from another system.
[3-3.リスケジュールする場合の工程管理のイメージ]
本項目では、リスケジュールする場合の工程管理のイメージについて、図5および図6を参照して説明する。図5の例では、業者Aに依頼した〇〇工事および業者Cに依頼した××工事は完了したが、業者Bに依頼した△△工事が遅延した場合を想定している。この場合、工程管理課の担当者は、△△工事のリスケジュールを行う。リスケジュールを行う場合、図5に示すように、工程管理課の担当者が算出元工程の予定日(2020/2/1)を入力すれば、後続の工程の予定日(2020/2/7)が自動算出される。図6には、業者Bに依頼した工事をリスケジュールする場合に入力される予定日および自動算出される予定日をまとめた表を示している。
[3-3. Image of process control when rescheduling]
In this section, an image of process control for rescheduling will be described with reference to FIGS. 5 and 6. FIG. In the example of FIG. 5, it is assumed that the XX construction commissioned to contractor A and the XX construction commissioned to contractor C were completed, but the △△ construction commissioned to contractor B was delayed. In this case, the person in charge of the process control section reschedules the △△ construction. When rescheduling, as shown in Figure 5, if the person in charge of the process control section enters the scheduled date (2020/2/1) of the calculation source process, the scheduled date of the subsequent process (2020/2/7) ) is automatically calculated. FIG. 6 shows a table summarizing the scheduled dates to be input and the automatically calculated scheduled dates when rescheduling the work commissioned by the contractor B. As shown in FIG.
[4.処理の具体例]
本項目では、本実施形態に係る処理の具体例を説明する。本項目では、新規セット(新規登録)の場合における予定日算出を[4-1]で説明し、リスケジュールの場合における予定日算出を[4-2]で説明する。
[4. Specific example of processing]
In this section, a specific example of processing according to this embodiment will be described. In this item, the calculation of the scheduled date in the case of a new set (new registration) will be described in [4-1], and the calculation of the scheduled date in the case of rescheduling will be described in [4-2].
なお、本項目では、プロジェクト基本情報データ106aは図7に示す内容で、工程パターンマスタ106dは図8に示す内容で予め登録されているという前提で説明を進める。
In this item, the description will proceed on the premise that the project
[4-1.新規セット(新規登録)の場合における予定日算出]
本項目では、新規セット(新規登録)の場合における各工程についての開始予定日および終了予定日の自動算出について、図7~図10を参照して説明する。
[4-1. Scheduled date calculation for new set (new registration)]
In this section, the automatic calculation of the scheduled start date and scheduled end date for each process in the case of a new set (new registration) will be described with reference to FIGS. 7 to 10. FIG.
新規セット(新規登録)の場合における処理の詳細は次段落から説明するが、概要は本段落で説明するとおりである。すなわち、工程進捗入力より、工事工程のスケジュールが登録されると、プロジェクト基本情報データ106aおよび工程パターンマスタ106dの情報を参照して、工程情報が初期セットされる。そして、当該初期セットされた工程に対して計算元の開始予定日が入力されることで、工程パターンマスタ106dに設定された内容に従い、各工程についての開始予定日および終了予定日が自動算出される。
The details of the processing in the case of a new set (new registration) will be explained from the next paragraph, but the outline is as explained in this paragraph. That is, when the construction process schedule is registered from the process progress input, process information is initially set by referring to the information in the project
(1)第一取得処理
最初に、図9に示すように、工程進捗入力画面において、工程管理課の担当者により、工事番号として「0001」が指定されると、第一取得部102aは、図7のプロジェクト基本情報データ106aから、当該指定された工事番号「0001」と紐づく情報として、工事種類「分譲工事_開発あり_解体あり」、請負金額「22,000,000円」、着工日「2021/3」および完成予定日「2021/7」を取得する。
(1) First Acquisition Processing First, as shown in FIG. 9, when the person in charge of the process control section specifies "0001" as the construction number on the process progress input screen, the first acquisition unit 102a From the project
(2)第二取得処理
続けて、図8の工程パターンマスタ106dを参照すると、第一取得部102aで取得した工事種類「分譲工事_開発あり_解体あり」および請負金額「22,000,000円」に合致するパターン条件は、パターンコードA01についてのパターン条件「請負金額<50,000,000円、工事種類=分譲工事_開発あり_解体あり」である。このため、第二取得部102bは、パターンコードA01についてのパターン条件に対応する情報として、図8に点線枠で囲んで示す情報(工程、工程名、算出元工程、インターバル日数および開始終了日数)を取得する。
(2) Second Acquisition Processing Subsequently, referring to the
(3)日付算出処理
最後に、日付算出部102cは、図9の工程進捗入力画面において工程管理課の担当者により工程「001:仕入契約日」について入力された開始予定日「2020/01/01」および第二取得部102bで取得した情報に基づいて、第二取得部102bで取得した各工程についての日付を、以下のようにして算出する。
(3) Date Calculation Processing Finally, the date calculation unit 102c calculates the scheduled start date "2020/01" entered for the process "001: purchase contract date" by the person in charge of the process control section on the process progress input screen in FIG. /01” and the information acquired by the second acquisition unit 102b, the date of each step acquired by the second acquisition unit 102b is calculated as follows.
まず、日付算出部102cは、工程「001:仕入契約日」については、前記入力された開始予定日「2020/01/01」に、第二取得部102bで取得した工程「001:仕入契約日」についての開始終了日数5から1を減じた日数である4日を加算することにより、終了予定日「2020/01/05」を算出する。 First, the date calculation unit 102c adds the input scheduled start date “2020/01/01” to the process “001: purchase contract date” acquired by the second acquisition unit 102b. By adding 4 days, which is the number of days obtained by subtracting 1 from the starting and ending days of 5 for the "contract date", the scheduled end date "2020/01/05" is calculated.
次に、図8の工程パターンマスタ106dを参照すると、工程「002:決済予定」についての算出元工程は「001:仕入契約日」であるため、日付算出部102cは、工程「001:仕入契約日」の終了予定日「2020/01/05」を起点として、以下の計算を行う。すなわち、日付算出部102cは、工程「002:決済予定」については、工程「001:仕入契約日」の終了予定日「2020/01/05」に、第二取得部102bで取得した工程「002:決済予定」についてのインターバル日数2日に1日を加えた日数である3日を加算することにより、開始予定日「2020/01/08」を算出する。また、日付算出部102cは、当該算出した開始予定日「2020/01/08」に、第二取得部102bで取得した工程「002:決済予定」についての開始終了日数10から1を減じた日数である9日を加算することにより、終了予定日「2020/01/17」を算出する。
Next, referring to the
更に、日付算出部102cは、工程「003:プラン着手依頼」から工程「126:販売売上」までについても、前段落で説明した処理と同様の処理を繰り返すことにより、開始予定日および終了予定日を算出する。 Further, the date calculation unit 102c calculates the scheduled start date and scheduled end date by repeating the same processing as the processing described in the previous paragraph for the steps “003: Request to start plan” to “126: Sales”. Calculate
以上のようにして、第二取得部102bで取得した各工程のうち日付が入力された工程「001:仕入契約日」についての終了予定日、ならびに、これ以降の工程についての開始予定日および終了予定日が自動算出される。当該自動算出された日付は、図9の工程進捗入力画面に表示される。図9の工程進捗入力画面において、ドット状のハッチングで示す日付2020/01/01は、工程管理課の担当者により入力された日付であり、斜線状のハッチングで示す日付は、日付算出部102cにより自動算出された日付である。 As described above, among the processes acquired by the second acquiring unit 102b, the scheduled end date of the process "001: purchase contract date" for which the date is entered, and the scheduled start date and The scheduled end date is automatically calculated. The automatically calculated date is displayed on the process progress input screen of FIG. In the process progress input screen of FIG. 9, the date 2020/01/01 indicated by dotted hatching is the date entered by the person in charge of the process control section, and the date indicated by diagonal hatching is the date calculation unit 102c. This date is automatically calculated by
日付算出部102cは、図9の工程進捗入力画面に表示された内容を含む工程進捗データ106eを、図10に示すように出力してもよい。
The date calculation unit 102c may output the
[4-2.リスケジュールの場合における予定日算出]
本項目では、リスケジュールの場合における各工程についての開始予定日および終了予定日の自動算出について、図7、図8、図11および図12を参照して説明する。
[4-2. Scheduled date calculation in case of rescheduling]
In this section, the automatic calculation of the scheduled start date and scheduled end date for each process in the case of rescheduling will be described with reference to FIGS. 7, 8, 11 and 12. FIG.
リスケジュールの場合における処理の詳細は次段落から説明するが、概要は本段落で説明するとおりである。すなわち、工程進捗入力より、工事工程のリスケジュールは行われる。工程「003:プラン着手依頼」まで工事が完成している状態で、工程「004:設計着手依頼」以降の工程のスケジュール変更が必要になったとすると、工程「004:設計着手依頼」の開始予定日が工程管理課の担当者によりメンテナンス(変更)されることで、工程パターンマスタ106dに設定された内容に従い、後続の工程についての開始予定日および終了予定日が自動算出されて変更される。
The details of the processing in the case of rescheduling will be explained from the next paragraph, but the outline is as explained in this paragraph. That is, the construction process is rescheduled based on the process progress input. If the construction is completed up to the process "003: Request to start planning" and it becomes necessary to change the schedule of the process after "004: Request to start design", the schedule for the start of "004: Request to start design" When the date is maintained (changed) by the person in charge of the process control section, the scheduled start date and scheduled end date for the subsequent process are automatically calculated and changed according to the details set in the
本項目[4-2]においては、[4-1]で説明した処理により、工程進捗入力画面が図9に示す内容が予め表示されており、かつ、工程「003:プラン着手依頼」まで工事が完成して実開始日および実終了日が登録済であるという状態で、工程管理課の担当者により、工程「004:設計着手依頼」についての開始予定日が「2020/03/09」から「2020/03/14」に変更される場面を想定して説明をする。 In this item [4-2], the process progress input screen is displayed in advance with the contents shown in FIG. has been completed and the actual start date and actual end date have been registered, the person in charge of the process control section will set the scheduled start date for the process "004: Design start request" from "2020/03/09" I will explain assuming the scene to be changed to "2020/03/14".
日付算出部102cは、工程「004:設計着手依頼」についての当該変更された後の開始予定日「2020/03/14」および第二取得部102bで取得した情報に基づいて、第二取得部102bで取得した各工程のうち工程「004:設計着手依頼」以降の工程についての日付を、以下のようにして算出する。 The date calculation unit 102c calculates the second acquisition unit The dates of the processes after the process "004: design start request" among the processes acquired in 102b are calculated as follows.
まず、日付算出部102cは、工程「004:設計着手依頼」については、前記変更後の開始予定日「2020/03/14」に、第二取得部102bで取得した工程「004:設計着手依頼」についての開始終了日数3から1を減じた日数である2日を加算することにより、終了予定日「2020/03/16」を算出する。 First, for the process "004: Design start request", the date calculation unit 102c adds the process "004: Design start request" acquired by the second acquisition unit 102b to the scheduled start date "2020/03/14" after the change. ”, the scheduled end date “2020/03/16” is calculated by adding 2 days, which is the number of days obtained by subtracting 1 from the start and end days of 3.
次に、図8の工程パターンマスタ106dを参照すると、工程「005:境界確定」についての算出元工程は「004:設計着手依頼」であるため、日付算出部102cは、工程「004:設計着手依頼」の終了予定日「2020/03/16」を起点として、以下の計算を行う。すなわち、日付算出部102cは、工程「005:境界確定」については、工程「004:設計着手依頼」の終了予定日「2020/03/16」に、第二取得部102bで取得した工程「005:境界確定」についてのインターバル日数2日に1日を加えた日数である3日を加算することにより、開始予定日「2020/03/19」を算出する。また、日付算出部102cは、当該算出した開始予定日「2020/03/19」に、第二取得部102bで取得した工程「005:境界確定」についての開始終了日数5から1を減じた日数である4日を加算することにより、終了予定日「2020/03/23」を算出する。
Next, referring to the
更に、日付算出部102cは、工程「005:境界確定」から工程「126:販売売上」までについても、前段落で説明した処理と同様の処理を繰り返すことにより、開始予定日および終了予定日を算出する。 Further, the date calculation unit 102c calculates the scheduled start date and the scheduled end date by repeating the same processing as the processing described in the previous paragraph for the steps “005: Determine boundary” to “126: Sales”. calculate.
以上のようにして、第二取得部102bで取得した各工程のうち日付が変更された工程「004:設計着手依頼」についての終了予定日、ならびに、これ以降の工程についての開始予定日および終了予定日が自動算出される。当該自動算出された日付は、図11の工程進捗入力画面に表示される。図11の工程進捗入力画面において、ドット状のハッチングで示す日付2020/03/14は、工程管理課の担当者による変更後の日付であり、斜線状のハッチングで示す日付は、日付算出部102cにより自動算出された変更後の日付である。 As described above, among the processes acquired by the second acquisition unit 102b, the scheduled end date of the process "004: Design start request" whose date has been changed, and the scheduled start date and end of the subsequent processes The due date is automatically calculated. The automatically calculated date is displayed on the process progress input screen of FIG. In the process progress input screen of FIG. 11, the date 2020/03/14 indicated by dotted hatching is the date after the change by the person in charge of the process control section, and the date indicated by diagonal hatching is the date calculation unit 102c. This is the date after the change automatically calculated by
日付算出部102cは、図11の工程進捗入力画面に表示された内容を含む工程進捗データ106eを、図12に示すように出力してもよい。
The date calculation unit 102c may output the
[5.本実施形態のまとめ]
このように、本実施形態に係る開始・終了予定日算出装置100によれば、プロジェクトを構成する各工程の新規登録の場合およびリスケジュールの両方の場合において、各工程についての作業の開始予定日および終了予定日を自動算出することができる。これにより、例えば、各工程についての作業の開始予定日および終了予定日の入力または変更の作業に要する時間および労力を削減し、また、ミスもなくすことができる。
[5. Summary of this embodiment]
As described above, according to the scheduled start/end
[6.国連が主導する持続可能な開発目標(SDGs)への貢献]
本実施形態により、業務効率化や企業の適切な経営判断を推進することに寄与することができるので、SDGsの目標8及び9に貢献することが可能となる。
[6. Contribution to the Sustainable Development Goals (SDGs) led by the United Nations]
Since this embodiment can contribute to improving operational efficiency and promoting appropriate management decisions of companies, it is possible to contribute to Goals 8 and 9 of the SDGs.
また、本実施形態により、廃棄ロス削減や、ペーパレス・電子化を推進することに寄与することができるので、SDGsの目標12、13及び15に貢献することが可能となる。 In addition, the present embodiment can contribute to the reduction of disposal loss and the promotion of paperless and computerization.
また、本実施形態により、統制、ガバナンス強化に寄与することができるので、SDGsの目標16に貢献することが可能となる。 In addition, since this embodiment can contribute to strengthening control and governance, it is possible to contribute to Goal 16 of the SDGs.
[7.他の実施形態]
本発明は、上述した実施形態以外にも、特許請求の範囲に記載した技術的思想の範囲内において種々の異なる実施形態にて実施されてよいものである。
[7. Other embodiments]
The present invention may be implemented in various different embodiments other than the embodiments described above within the scope of the technical idea described in the claims.
例えば、実施形態において説明した各処理のうち、自動的に行われるものとして説明した処理の全部または一部を手動的に行うこともでき、あるいは、手動的に行われるものとして説明した処理の全部または一部を公知の方法で自動的に行うこともできる。 For example, among the processes described in the embodiments, all or part of the processes described as being automatically performed can be manually performed, or all of the processes described as being manually performed Alternatively, some can be done automatically by known methods.
また、本明細書中や図面中で示した処理手順、制御手順、具体的名称、各処理の登録データや検索条件等のパラメータを含む情報、画面例、データベース構成については、特記する場合を除いて任意に変更することができる。 In addition, unless otherwise specified, the processing procedures, control procedures, specific names, information including parameters such as registration data and search conditions for each process, screen examples, and database configurations shown in this specification and drawings can be changed arbitrarily.
また、開始・終了予定日算出装置100に関して、図示の各構成要素は機能概念的なものであり、必ずしも物理的に図示の如く構成されていることを要しない。
Further, regarding the scheduled start/end
例えば、開始・終了予定日算出装置100が備える処理機能、特に制御部にて行われる各処理機能については、その全部または任意の一部を、CPUおよび当該CPUにて解釈実行されるプログラムにて実現してもよく、また、ワイヤードロジックによるハードウェアとして実現してもよい。尚、プログラムは、本実施形態で説明した処理を情報処理装置に実行させるためのプログラム化された命令を含む一時的でないコンピュータ読み取り可能な記録媒体に記録されており、必要に応じて開始・終了予定日算出装置100に機械的に読み取られる。すなわち、ROMまたはHDD(Hard Disk Drive)などの記憶部などには、OSと協働してCPUに命令を与え、各種処理を行うためのコンピュータプログラムが記録されている。このコンピュータプログラムは、RAMにロードされることによって実行され、CPUと協働して制御部を構成する。
For example, all or any part of the processing functions provided by the scheduled start/end
また、このコンピュータプログラムは、開始・終了予定日算出装置100に対して任意のネットワークを介して接続されたアプリケーションプログラムサーバに記憶されていてもよく、必要に応じてその全部または一部をダウンロードすることも可能である。
In addition, this computer program may be stored in an application program server connected to the scheduled start/end
また、本実施形態で説明した処理を実行するためのプログラムを、一時的でないコンピュータ読み取り可能な記録媒体に格納してもよく、また、プログラム製品として構成することもできる。ここで、この「記録媒体」とは、メモリーカード、USB(Universal Serial Bus)メモリ、SD(Secure Digital)カード、フレキシブルディスク、光磁気ディスク、ROM、EPROM(Erasable Programmable Read Only Memory)、EEPROM(登録商標)(Electrically Erasable and Programmable Read Only Memory)、CD-ROM(Compact Disk Read Only Memory)、MO(Magneto-Optical disk)、DVD(Digital Versatile Disk)、および、Blu-ray(登録商標) Disc等の任意の「可搬用の物理媒体」を含むものとする。 Also, the program for executing the processing described in this embodiment may be stored in a non-temporary computer-readable recording medium, or may be configured as a program product. Here, the term "recording medium" refers to memory cards, USB (Universal Serial Bus) memories, SD (Secure Digital) cards, flexible disks, magneto-optical disks, ROMs, EPROMs (Erasable Programmable Read Only Memory), EEPROMs (registered (trademark) (Electrically Erasable and Programmable Read Only Memory), CD-ROM (Compact Disk Read Only Memory), MO (Magneto-Optical disk), DVD (Digital Versatile Disk), and Disc (registered trademark) such as Blu- shall include any "portable physical medium".
また、「プログラム」とは、任意の言語または記述方法にて記述されたデータ処理方法であり、ソースコードまたはバイナリコード等の形式を問わない。なお、「プログラム」は必ずしも単一的に構成されるものに限られず、複数のモジュールやライブラリとして分散構成されるものや、OSに代表される別個のプログラムと協働してその機能を達成するものをも含む。なお、実施形態に示した各装置において記録媒体を読み取るための具体的な構成および読み取り手順ならびに読み取り後のインストール手順等については、周知の構成や手順を用いることができる。 A "program" is a data processing method written in any language or writing method, regardless of the format such as source code or binary code. In addition, the "program" is not necessarily limited to a single configuration, but is distributed as multiple modules or libraries, or cooperates with a separate program represented by the OS to achieve its function. Including things. It should be noted that well-known configurations and procedures can be used for the specific configuration and reading procedure for reading the recording medium in each device shown in the embodiments, the installation procedure after reading, and the like.
記憶部に格納される各種のデータベース等は、RAM、ROM等のメモリ装置、ハードディスク等の固定ディスク装置、フレキシブルディスク、および、光ディスク等のストレージ手段であり、各種処理やウェブサイト提供に用いる各種のプログラム、テーブル、データベース、および、ウェブページ用ファイル等を格納する。 The various databases stored in the storage unit are storage means such as memory devices such as RAM and ROM, fixed disk devices such as hard disks, flexible disks, and optical disks. It stores programs, tables, databases, files for web pages, and so on.
また、開始・終了予定日算出装置100は、既知のパーソナルコンピュータまたはワークステーション等の情報処理装置として構成してもよく、また、任意の周辺装置が接続された当該情報処理装置として構成してもよい。また、開始・終了予定日算出装置100は、当該装置に本実施形態で説明した処理を実現させるソフトウェア(プログラムまたはデータ等を含む)を実装することにより実現してもよい。
Further, the scheduled start/end
更に、装置の分散・統合の具体的形態は図示するものに限られず、その全部または一部を、各種の付加等に応じてまたは機能負荷に応じて、任意の単位で機能的または物理的に分散・統合して構成することができる。すなわち、上述した実施形態を任意に組み合わせて実施してもよく、実施形態を選択的に実施してもよい。 Furthermore, the specific forms of distribution and integration of devices are not limited to those shown in the figures, and all or part of them can be functionally or physically arranged in arbitrary units according to various additions or functional loads. It can be distributed and integrated. In other words, the embodiments described above may be arbitrarily combined and implemented, or the embodiments may be implemented selectively.
本発明は、例えば、工事業界および不動産業界等において有用である。 The present invention is useful, for example, in the construction industry, the real estate industry, and the like.
100 開始・終了予定日算出装置
102 制御部
102a 第一取得部
102b 第二取得部
102c 日付算出部
104 通信インターフェース部
106 記憶部
106a プロジェクト基本情報データ
106b プロジェクト種類一覧データ
106c 工程マスタ
106d 工程パターンマスタ
106e 工程進捗データ
108 入出力インターフェース部
112 入力装置
114 出力装置
200 サーバ
300 ネットワーク
100 Scheduled Start/End Date Calculation Device 102 Control Unit
102a first acquisition unit
102b second acquisition unit
102c
106a Project basic information data
106b Project type list data
106c Process master
106d process pattern master
106e
Claims (7)
前記記憶部には、
前記プロジェクトを識別するためのプロジェクト識別データと、前記プロジェクトに関する情報と、を含むプロジェクト基本情報データと、
前記工程の組み方に関するパターンと、当該パターンに対応する条件と、を対応付けて含む工程パターンマスタと、
が格納されており、
前記パターンは、前記工程を識別するための工程識別データ、前記工程毎に設定された算出元工程識別データ、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数によって構成され、
前記制御部は、
前記プロジェクト基本情報データから、オペレータによって指定されたプロジェクト識別データと紐づく前記プロジェクトに関する情報を取得する第一取得手段と、
前記工程パターンマスタから、前記第一取得手段で取得した前記プロジェクトに関する情報に合致する前記条件に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数を取得する第二取得手段と、
前記第二取得手段で取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、当該ある工程については、前記指定された開始予定日および前記第二取得手段で取得した前記ある工程についての前記作業日数を用いて、前記終了予定日を算出し、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、前記第二取得手段で取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数を用いて、前記開始予定日および前記終了予定日を算出する日付算出手段と、
を備えること、
を特徴とする開始・終了予定日算出装置。 A scheduled start/end date calculation device, comprising a control unit and a storage unit, and capable of calculating the scheduled start date and scheduled end date of work for a process constituting a project,
The storage unit contains
project basic information data including project identification data for identifying the project and information about the project;
a process pattern master that includes, in association with, a pattern relating to how to set the processes and a condition corresponding to the pattern;
is stored and
The pattern includes process identification data for identifying the process, calculation source process identification data set for each process, interval days set for each process, and work days set for each process. ,
The control unit
a first acquiring means for acquiring information about the project linked to the project identification data specified by the operator from the project basic information data;
From the process pattern master, the process identification data, the calculation source process identification data, the interval days, and the work days, which constitute a pattern corresponding to the conditions that match the information about the project acquired by the first acquisition means, are obtained. a second acquisition means for acquiring;
When the operator specifies a scheduled work start date for a certain process among the processes specified by the process identification data acquired by the second acquiring means, the specified scheduled start date for the certain process calculating the scheduled end date using the date and the working days for the certain process acquired by the second acquisition means, and calculating the specified process from the process next to the certain process among the specified processes date calculation means for calculating the scheduled start date and the scheduled end date by using the calculation source process identification data, the interval days, and the work days acquired by the second acquisition means for up to the last process When,
to provide
A scheduled start/end date calculation device characterized by:
前記ある工程については、前記指定された開始予定日に、前記第二取得手段で取得した前記ある工程についての前記作業日数から1を減じた日数を加算した日付を前記終了予定日として算出すること、
を特徴とする請求項1に記載の開始・終了予定日算出装置。 The date calculation means is
For the certain process, calculating the scheduled end date by adding the number of days obtained by subtracting 1 from the number of working days for the certain process acquired by the second acquisition means to the specified scheduled start date. ,
The scheduled start/end date calculation device according to claim 1, characterized by:
前記次の工程については、前記第二取得手段で取得した前記次の工程についての前記算出元工程識別データで特定される工程についての前記終了予定日に、前記第二取得手段で取得した前記次の工程についての前記インターバル日数に1を加えた日数を加算した日付を前記開始予定日として算出し、当該算出した開始予定日に、前記第二取得手段で取得した前記次の工程についての前記作業日数から1を減じた日数を加算した日付を前記終了予定日として算出する処理を実行し、
前記次の工程の更に次の工程から前記最後の工程までについては、前記処理と同様の処理を繰り返すことにより、前記開始予定日および前記終了予定日を算出すること、
を特徴とする請求項1または2に記載の開始・終了予定日算出装置。 The date calculation means is
With respect to the next step, the next step obtained by the second obtaining means on the scheduled end date of the step specified by the calculation source step identification data for the next step obtained by the second obtaining means calculating the date obtained by adding the number of days obtained by adding 1 to the number of interval days for the step as the scheduled start date, and on the calculated scheduled start date, the work for the next step acquired by the second acquisition means Execute a process of calculating the date obtained by adding the number of days obtained by subtracting 1 from the number of days as the scheduled end date,
calculating the scheduled start date and the scheduled end date by repeating the same processing as the above processing from the next step of the next step to the last step;
3. The scheduled start/end date calculation device according to claim 1 or 2, characterized by:
前記条件が、前記プロジェクトの種類および前記プロジェクトの金額に関する条件であること、
を特徴とする請求項1から3のいずれか一つに記載の開始・終了予定日算出装置。 the information about the project is information about the type of the project and the amount of the project;
said conditions relate to the type of said project and the amount of said project;
The scheduled start/end date calculation device according to any one of claims 1 to 3, characterized by:
を特徴とする請求項1から4のいずれか一つに記載の開始・終了予定日算出装置。 The project is a construction project;
The scheduled start/end date calculation device according to any one of claims 1 to 4, characterized by:
前記記憶部には、
前記プロジェクトを識別するためのプロジェクト識別データと、前記プロジェクトに関する情報と、を含むプロジェクト基本情報データと、
前記工程の組み方に関するパターンと、当該パターンに対応する条件と、を対応付けて含む工程パターンマスタと、
が格納されており、
前記パターンは、前記工程を識別するための工程識別データ、前記工程毎に設定された算出元工程識別データ、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数によって構成され、
前記制御部で実行される、
前記プロジェクト基本情報データから、オペレータによって指定されたプロジェクト識別データと紐づく前記プロジェクトに関する情報を取得する第一取得ステップと、
前記工程パターンマスタから、前記第一取得ステップで取得した前記プロジェクトに関する情報に合致する前記条件に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数を取得する第二取得ステップと、
前記第二取得ステップで取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、当該ある工程については、前記指定された開始予定日および前記第二取得ステップで取得した前記ある工程についての前記作業日数を用いて、前記終了予定日を算出し、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、前記第二取得ステップで取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数を用いて、前記開始予定日および前記終了予定日を算出する日付算出ステップと、
を含むこと、
を特徴とする開始・終了予定日算出方法。 A scheduled start/end date calculation method capable of calculating the scheduled start date and scheduled end date of work for a process constituting a project, which is executed by an information processing device having a control unit and a storage unit,
The storage unit contains
project basic information data including project identification data for identifying the project and information about the project;
a process pattern master that includes, in association with, a pattern relating to how to set the processes and a condition corresponding to the pattern;
is stored and
The pattern includes process identification data for identifying the process, calculation source process identification data set for each process, interval days set for each process, and work days set for each process. ,
executed by the control unit;
a first acquisition step of acquiring information about the project associated with the project identification data specified by the operator from the project basic information data;
From the process pattern master, the process identification data, the calculation source process identification data, the number of interval days, and the number of work days that constitute a pattern corresponding to the conditions that match the information about the project acquired in the first acquisition step. a second obtaining step of obtaining;
When the operator designates a scheduled work start date for a certain process among the processes identified by the process identification data acquired in the second acquisition step, the specified scheduled start date for the certain process is Calculate the scheduled end date using the date and the working days for the certain process acquired in the second acquiring step, and calculate the specified process from the process next to the certain process among the specified processes For up to the last process, the date calculation step of calculating the scheduled start date and the scheduled end date using the calculation source process identification data, the interval days, and the work days acquired in the second acquisition step When,
including
A start/end date calculation method characterized by:
前記記憶部には、
前記プロジェクトを識別するためのプロジェクト識別データと、前記プロジェクトに関する情報と、を含むプロジェクト基本情報データと、
前記工程の組み方に関するパターンと、当該パターンに対応する条件と、を対応付けて含む工程パターンマスタと、
が格納されており、
前記パターンは、前記工程を識別するための工程識別データ、前記工程毎に設定された算出元工程識別データ、前記工程毎に設定されたインターバル日数および前記工程毎に設定された作業日数によって構成され、
前記制御部に実行させるための、
前記プロジェクト基本情報データから、オペレータによって指定されたプロジェクト識別データと紐づく前記プロジェクトに関する情報を取得する第一取得ステップと、
前記工程パターンマスタから、前記第一取得ステップで取得した前記プロジェクトに関する情報に合致する前記条件に対応するパターンを構成する前記工程識別データ、前記算出元工程識別データ、前記インターバル日数および前記作業日数を取得する第二取得ステップと、
前記第二取得ステップで取得した前記工程識別データで特定される工程のうちのある工程についての作業の開始予定日が前記オペレータによって指定されると、当該ある工程については、前記指定された開始予定日および前記第二取得ステップで取得した前記ある工程についての前記作業日数を用いて、前記終了予定日を算出し、前記特定される工程のうち前記ある工程の次の工程から前記特定される工程のうち最後の工程までについては、前記第二取得ステップで取得した前記算出元工程識別データ、前記インターバル日数および前記作業日数を用いて、前記開始予定日および前記終了予定日を算出する日付算出ステップと、
を含むこと、
を特徴とする開始・終了予定日算出プログラム。 A scheduled start/end date calculation program capable of calculating the scheduled start date and scheduled end date of work for a process constituting a project, to be executed by an information processing apparatus having a control unit and a storage unit,
The storage unit contains
project basic information data including project identification data for identifying the project and information about the project;
a process pattern master that includes, in association with, a pattern relating to how to set the processes and a condition corresponding to the pattern;
is stored and
The pattern includes process identification data for identifying the process, calculation source process identification data set for each process, interval days set for each process, and work days set for each process. ,
for causing the control unit to execute
a first acquisition step of acquiring information about the project associated with the project identification data specified by the operator from the project basic information data;
From the process pattern master, the process identification data, the calculation source process identification data, the number of interval days, and the number of work days that constitute a pattern corresponding to the conditions that match the information about the project acquired in the first acquisition step. a second obtaining step of obtaining;
When the operator designates a scheduled work start date for a certain process among the processes identified by the process identification data acquired in the second acquisition step, the specified scheduled start date for the certain process is Calculate the scheduled end date using the date and the working days for the certain process acquired in the second acquiring step, and calculate the specified process from the process next to the certain process among the specified processes For up to the last process, the date calculation step of calculating the scheduled start date and the scheduled end date using the calculation source process identification data, the interval days, and the work days acquired in the second acquisition step When,
including
A start/end date calculation program characterized by
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2021078006A JP2022171395A (en) | 2021-04-30 | 2021-04-30 | Start and end scheduled date calculation device, start and end scheduled date calculation method, and start and end scheduled date calculation program |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2021078006A JP2022171395A (en) | 2021-04-30 | 2021-04-30 | Start and end scheduled date calculation device, start and end scheduled date calculation method, and start and end scheduled date calculation program |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2022171395A true JP2022171395A (en) | 2022-11-11 |
Family
ID=83946264
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2021078006A Pending JP2022171395A (en) | 2021-04-30 | 2021-04-30 | Start and end scheduled date calculation device, start and end scheduled date calculation method, and start and end scheduled date calculation program |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2022171395A (en) |
-
2021
- 2021-04-30 JP JP2021078006A patent/JP2022171395A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2021119512A (en) | Project accounting management device, project accounting management method, and project accounting management program | |
JP7020802B2 (en) | Common cost apportioning device, common cost apportioning method and common cost apportioning program | |
JP2019139388A (en) | Work in process automatic transfer device and work in process automatic transfer method and work in process automatic transfer program | |
JP7197989B2 (en) | Progress rate calculation device, progress rate calculation method, and progress rate calculation program | |
JP7223889B2 (en) | Common cost apportionment device, common cost apportionment method and common cost apportionment program | |
JP2018073192A (en) | Amount calculation apparatus, amount calculation method and amount calculation program | |
JP2022171395A (en) | Start and end scheduled date calculation device, start and end scheduled date calculation method, and start and end scheduled date calculation program | |
JP7252813B2 (en) | Product transfer instruction device, product transfer instruction method, and product transfer instruction program | |
JP7074458B2 (en) | Workflow management device, workflow management method and workflow management program | |
JP7104520B2 (en) | Withholding tax-related business support equipment, withholding tax-related business support methods, and withholding tax-related business support programs | |
JP2021149405A (en) | Management device associating prepayment with transfer, management method associating prepayment with transfer and management program associating prepayment with transfer | |
JP7394716B2 (en) | Inspection schedule data generation device, inspection schedule data generation method, and inspection schedule data generation program | |
JP2021093070A (en) | Device, method, and program for calculating estimated progress rate | |
JP2020166614A (en) | Deposit transfer device, deposit transfer method, and deposit transfer program | |
JP7291088B2 (en) | Slip Closing Support Device, Slip Closing Support Method, and Slip Closing Support Program | |
JP7261332B2 (en) | Automatic work-in-process transfer device, automatic work-in-process transfer method, and automatic work-in-process transfer program | |
JP7406464B2 (en) | Inspection date data generation device, inspection date data generation method, and inspection date data generation program | |
JP2018109869A (en) | Amount calculation apparatus, amount calculation method and amount calculation program | |
JP6853705B2 (en) | Usage content management device, usage content management method, and usage content management program | |
JP7190825B2 (en) | Contract-related information management device, contract-related information management method, and contract-related information management program | |
JP2023075787A (en) | Component supply management device, component supply management program, and component supply management method | |
JP2018112988A (en) | Journaling preparation device, journaling preparation method, and journaling preparation program | |
JP2023027994A (en) | Manufacturing instruction data generation device, manufacturing instruction data generation method, and manufacturing instruction data generation program | |
JP2022117005A (en) | Budget data generation apparatus, budget data generation method, and budget data generation program | |
JP2021140737A (en) | Information processing device, information processing method and information processing program |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20231019 |