JP2022090740A - Conveyance mechanism and construction method - Google Patents

Conveyance mechanism and construction method Download PDF

Info

Publication number
JP2022090740A
JP2022090740A JP2020203223A JP2020203223A JP2022090740A JP 2022090740 A JP2022090740 A JP 2022090740A JP 2020203223 A JP2020203223 A JP 2020203223A JP 2020203223 A JP2020203223 A JP 2020203223A JP 2022090740 A JP2022090740 A JP 2022090740A
Authority
JP
Japan
Prior art keywords
girder
transport mechanism
transport
structural pillar
transport device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2020203223A
Other languages
Japanese (ja)
Inventor
康貴 今中
Yasutaka Imanaka
道洋 柿崎
Michihiro Kakizaki
孝義 沼崎
Takayoshi Numazaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2020203223A priority Critical patent/JP2022090740A/en
Publication of JP2022090740A publication Critical patent/JP2022090740A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

To provide a conveying device capable of conveying a material even when there is no support structure above.SOLUTION: To provide a conveyance mechanism comprising a track part supported by a structural column and a conveyance device for conveying a material by traveling the track section.SELECTED DRAWING: Figure 1

Description

本発明は搬送機構及び施工方法に関する。 The present invention relates to a transport mechanism and a construction method.

従来技術として、床版下面に固定されたレールを走行する電動ホイストが、搬送装置として開示されている(特許文献1)。 As a prior art, an electric hoist traveling on a rail fixed to the lower surface of a deck slab is disclosed as a transport device (Patent Document 1).

特開平5-8991号公報Japanese Unexamined Patent Publication No. 5-8991

上記従来技術では、上方にレールを支持させるための構造がない工区で作業を行う場合、搬送装置を設置することができない。このため、人力など他の搬送方法を用いる必要があり、工事の効率化を図ることができない。 In the above-mentioned conventional technique, when the work is performed in the construction area where there is no structure for supporting the rail above, the transport device cannot be installed. Therefore, it is necessary to use other transportation methods such as human power, and it is not possible to improve the efficiency of construction.

上記課題に鑑み、本発明は、上方に支持構造が無い場合においても、資材の搬送を可能にする搬送装置を提供することにある。 In view of the above problems, the present invention is to provide a transport device capable of transporting materials even when there is no support structure above.

上記課題を解決するため、本発明は一態様として、構真柱に支持される軌道部と、前記軌道部を走行して資材を搬送する搬送装置と、を備える搬送機構を提供する。 In order to solve the above problems, the present invention provides, as one aspect, a transport mechanism including a track portion supported by a structural pillar and a transport device that travels on the track portion to transport materials.

本発明によれば、上方に支持構造が無い場合においても、資材の搬送を可能にする搬送装置を提供することができる。 According to the present invention, it is possible to provide a transport device that enables transport of materials even when there is no support structure above.

実施形態に係る搬送機構及び構造物を示すX軸方向に沿った断面図である。It is sectional drawing along the X-axis direction which shows the transport mechanism and structure which concerns on embodiment. 実施形態に係る搬送機構及び構造物の配置図である。It is a layout drawing of a transport mechanism and a structure which concerns on embodiment. 実施形態に係る搬送機構の側面図である。It is a side view of the transport mechanism which concerns on embodiment. 実施形態に係る搬送機構の上面図である。It is a top view of the transport mechanism which concerns on embodiment. 実施形態に係る搬送機構の、図2V-V線に沿った断面図である。FIG. 2 is a cross-sectional view of the transport mechanism according to the embodiment along the line VV. 図5の一部拡大図である。It is a partially enlarged view of FIG. 実施形態に係る搬送機構におけるホイスト近傍の拡大図であり(a)X軸方向視による側面図、及び(b)Y軸方向視による側面図を示す。It is an enlarged view of the vicinity of the hoist in the transport mechanism which concerns on embodiment, and shows (a) the side view by the X-axis direction view, and (b) the side view by the Y-axis direction view. 実施形態に係る搬送機構の、図2V-V線に沿った断面図であり、上床版施工後の状態を示す。FIG. 2 is a cross-sectional view of the transport mechanism according to the embodiment along the line VVV, showing a state after construction of the upper floor slab. 変形例に係る搬送機構の断面図である。It is sectional drawing of the transport mechanism which concerns on a modification. 変形例に係る搬送装置の側面図である。It is a side view of the transfer device which concerns on a modification.

図1~図8を参照して、本発明の実施形態に係る搬送機構1について、以下に説明する。搬送機構1は、杭基礎を有する既存構造物9の下方に形成された空間S内部に設置され、主に、構造物8を施工するための資材搬入に用いられる。 The transport mechanism 1 according to the embodiment of the present invention will be described below with reference to FIGS. 1 to 8. The transport mechanism 1 is installed inside the space S formed below the existing structure 9 having a pile foundation, and is mainly used for carrying in materials for constructing the structure 8.

図中の機構、部材、装置等の方向は、互いに直交する水平なX軸及びY軸を用いて、図1に示すように定義する。機構や装置等に対して取り外し可能な部品、部材等については、機構や装置等に組付けられた状態において、方向を定義する。 The directions of the mechanisms, members, devices, etc. in the figure are defined as shown in FIG. 1 using horizontal X-axis and Y-axis orthogonal to each other. For parts, members, etc. that can be removed from the mechanism, device, etc., the direction is defined in the state of being assembled to the mechanism, device, etc.

構造物8は、杭91を備える既存構造物9の下方において、場所打ち杭である杭81、及び、上下に延びる構真柱82を有する。構真柱82は、杭81に支持された柱であり、その上部は、杭81上部から上方に延びる。構造物8は、逆打ち工法によって施工される構造物であり、構真柱82の施工後に、構真柱82上端部に支持、固定される上床版83(図8)が施工される。なお、構造物8の構造及び施工等の詳細については後述する。 The structure 8 has a pile 81 which is a cast-in-place pile and a structural pillar 82 extending vertically below the existing structure 9 provided with the pile 91. The structural Shinbashira 82 is a pillar supported by the pile 81, and the upper portion thereof extends upward from the upper portion of the pile 81. The structure 8 is a structure constructed by a reverse striking method, and after the construction of the structural pillar 82, an upper floor slab 83 (FIG. 8) supported and fixed to the upper end of the structural pillar 82 is constructed. The details of the structure and construction of the structure 8 will be described later.

搬送機構1は、主として上床版83の施工に必要な資材を搬送するための機構であり、構真柱82の上方に設置される。搬送機構1は、図1及び図2に示すように、構真柱82に支持される軌道部10と、軌道部10に移動可能に支持される搬送装置20とを備える。 The transport mechanism 1 is a mechanism for transporting materials necessary for the construction of the upper floor slab 83, and is installed above the structural pillar 82. As shown in FIGS. 1 and 2, the transport mechanism 1 includes a track portion 10 supported by the structural pillar 82 and a transport device 20 movably supported by the track portion 10.

軌道部10は、図3及び図4に示すように、支持部11、ガーダ12、及びレール13を備える。 As shown in FIGS. 3 and 4, the track portion 10 includes a support portion 11, a girder 12, and a rail 13.

支持部11は、複数の鋼材を互いに接合して組み立てられた、ガーダ12を支持する束材である。支持部11の下部は、構真柱82の上端部に固定され、上端部はガーダ12を固定する。構真柱82及びガーダ12に対する固定方法は、ボルト接合または溶接接合など、任意の方法が採用され得る。また、実施形態において、支持部11は複数の山形鋼によって構成されるが、山形鋼以外の部材を用いてもよい。 The support portion 11 is a bundle material that supports the girder 12 and is assembled by joining a plurality of steel materials to each other. The lower portion of the support portion 11 is fixed to the upper end portion of the structural pillar 82, and the upper end portion fixes the girder 12. As the fixing method to the structural pillar 82 and the girder 12, any method such as bolt joining or welding joining may be adopted. Further, in the embodiment, the support portion 11 is composed of a plurality of angle steels, but members other than the angle steels may be used.

ガーダ12は、X軸方向に延びた、レール13を支持する部材である。ガーダ12は、支持部11を介して構真柱82によって支持され、複数の構真柱82の上方に架設される。ガーダ12の下部は、支持部11の上端部に固定される。ガーダ12は、縦桁12A、横桁12B、及び台座12Cを有する。 The girder 12 is a member that extends in the X-axis direction and supports the rail 13. The girder 12 is supported by the structural pillar 82 via the support portion 11 and is erected above the plurality of structural pillars 82. The lower portion of the girder 12 is fixed to the upper end portion of the support portion 11. The girder 12 has a vertical girder 12A, a horizontal girder 12B, and a pedestal 12C.

縦桁12A及び横桁12Bは、それぞれX軸方向及びY軸方向に延びる鋼材であり、互いに接合される。縦桁12Aは、X軸方向に延びるように2本平行に並べられ、支持部11の上部に固定される。横桁12Bは、X軸方向に略等間隔となるように複数本並べられ、いずれも縦桁12Aの下部に固定される。縦桁12A及び横桁12Bの接合方法は、ボルト接合または溶接接合など、任意の方法が採用され得る。 The vertical girder 12A and the horizontal girder 12B are steel materials extending in the X-axis direction and the Y-axis direction, respectively, and are joined to each other. Two vertical girders 12A are arranged in parallel so as to extend in the X-axis direction, and are fixed to the upper part of the support portion 11. A plurality of horizontal girders 12B are arranged at substantially equal intervals in the X-axis direction, and all of them are fixed to the lower part of the vertical girder 12A. As the joining method of the vertical girder 12A and the horizontal girder 12B, any method such as bolt joining or welding joining can be adopted.

台座12Cは、横桁12Bの上部に2本平行に敷設される。詳細には、2本の台座12Cは、横桁12BのY軸方向端部に、それぞれ固定される。台座12Cは、いずれもX軸方向に延びるH形鋼であり、フランジが略水平となるように設置される。台座12Cは、それぞれの上部において、レール13を支持する。 Two pedestals 12C are laid in parallel on the upper part of the cross girder 12B. Specifically, the two pedestals 12C are fixed to the Y-axis direction ends of the cross girder 12B, respectively. The pedestals 12C are all H-shaped steels extending in the X-axis direction, and are installed so that the flanges are substantially horizontal. The pedestal 12C supports the rail 13 at the top of each.

レール13は、X軸方向に延びるように、台座12Cの上面に2本平行に敷設される。レール13は、搬送装置20を走行可能に支持し、搬送装置20の走行をX軸方向に案内する機能を有する。本実施形態におけるレール13にはレール鋼が用いられるが、H形鋼、I形鋼などが用いられてもよい。 Two rails 13 are laid in parallel on the upper surface of the pedestal 12C so as to extend in the X-axis direction. The rail 13 has a function of supporting the transport device 20 so as to be travelable and guiding the travel of the transport device 20 in the X-axis direction. Although rail steel is used for the rail 13 in this embodiment, H-shaped steel, I-shaped steel, or the like may be used.

搬送装置20は、図3~図7に示すように、台車21、吊桁22、及びホイスト23を備える。 As shown in FIGS. 3 to 7, the transport device 20 includes a carriage 21, a suspension girder 22, and a hoist 23.

台車21は、型鋼を略直方体形状に組んで構成された本体部211と、ローラ212と、ローラ212を駆動する2つのモータ213と、ロック機構216とを備える(図3~図6)。 The bogie 21 includes a main body portion 211 formed by assembling a shaped steel into a substantially rectangular parallelepiped shape, a roller 212, two motors 213 for driving the roller 212, and a lock mechanism 216 (FIGS. 3 to 6).

ローラ212は、本体部211下部の複数個所に設置され、それぞれが、本体部211によって回転可能に支持される(図3)。ローラ212は、フランジを有しており、レール13の上部に配置される。ローラ212は、レール13上を転動可能である。 The rollers 212 are installed at a plurality of locations below the main body 211, and each is rotatably supported by the main body 211 (FIG. 3). The roller 212 has a flange and is arranged on the upper part of the rail 13. The roller 212 can roll on the rail 13.

モータ213は、図3及び図4に示すように、本体部211の下部に固定される。モータ213は、不図示の減速機構を介して駆動力をローラ212に伝達し、回転駆動することができる。これにより、台車21は、レール13上を走行することができる。 As shown in FIGS. 3 and 4, the motor 213 is fixed to the lower part of the main body portion 211. The motor 213 can transmit the driving force to the roller 212 via a deceleration mechanism (not shown) and drive the motor 213 in rotation. As a result, the bogie 21 can travel on the rail 13.

ロック機構216は、本体部211の下部から下方に延びる部材であり、その下端部は台座12Cのフランジ間に位置する(図6)。ロック機構216は、本体部211のY軸方向両端部に設けられる。本体部211が傾いた場合、ロック機構216の下端部は台座12Cのフランジと当接する。これにより台車21の転倒が防止される。 The lock mechanism 216 is a member extending downward from the lower part of the main body portion 211, and the lower end portion thereof is located between the flanges of the pedestal 12C (FIG. 6). The lock mechanism 216 is provided at both ends of the main body 211 in the Y-axis direction. When the main body portion 211 is tilted, the lower end portion of the lock mechanism 216 comes into contact with the flange of the pedestal 12C. This prevents the dolly 21 from tipping over.

吊桁22は、2本の支持材221、桁材222、上部ローラ223、下部ローラ224、及び2つのモータ225を備える(図3~図7)。吊桁22は、本発明における腕部に相当する。 The suspension girder 22 includes two support members 221, a girder member 222, an upper roller 223, a lower roller 224, and two motors 225 (FIGS. 3 to 7). The hanging girder 22 corresponds to the arm portion in the present invention.

支持材221は、いずれもY軸方向に延びるH形鋼であり、フランジが略水平となるように、本体部211の上部に固定される。支持材221の下部フランジは、桁材222を支持する。 The support members 221 are all H-shaped steels extending in the Y-axis direction, and are fixed to the upper part of the main body portion 211 so that the flanges are substantially horizontal. The lower flange of the support member 221 supports the girder member 222.

桁材222は、X軸方向及びY軸方向に延びる複数のH形鋼を井桁状に組み、互いに接合することによって形成された部材である。図4に示すように、桁材222は、上面視で略矩形状に形成される。 The girder member 222 is a member formed by assembling a plurality of H-shaped steels extending in the X-axis direction and the Y-axis direction in a grid shape and joining them together. As shown in FIG. 4, the girder member 222 is formed in a substantially rectangular shape when viewed from above.

上部ローラ223及び下部ローラ224は、桁材222の上部、かつY軸方向における両端部及び中央部の3か所において設置され、各々が桁材222によって回転可能に支持される(図6、図7)。上部ローラ223及び下部ローラ224は、支持材221の下部フランジを上下に狭持する。 The upper roller 223 and the lower roller 224 are installed at three locations above the girder member 222 and at both ends and the central portion in the Y-axis direction, and each is rotatably supported by the girder member 222 (FIG. 6, FIG. 7). The upper roller 223 and the lower roller 224 hold the lower flange of the support member 221 up and down.

モータ225は、上部ローラ223の近傍、かつ桁材222の上部に設置される(図7(b))。モータ225は、上部ローラ223と減速機構を介して接続しており、上部ローラ223を回転駆動することができる。モータ225が上部ローラ223を回転駆動すると、上部ローラ223は支持材221に対して回転しながら移動し、これに追従して下部ローラ224も支持材221に対して転動する。これにより、桁材222は、支持材221に対してY軸方向に移動できる。すなわち、吊桁22は、図4~図6、及び図8に白抜き矢印で示すように、Y軸方向に伸縮することができる。 The motor 225 is installed in the vicinity of the upper roller 223 and above the girder member 222 (FIG. 7 (b)). The motor 225 is connected to the upper roller 223 via a reduction mechanism, and the upper roller 223 can be rotationally driven. When the motor 225 rotationally drives the upper roller 223, the upper roller 223 moves while rotating with respect to the support member 221, and the lower roller 224 also rolls with respect to the support member 221 following this. As a result, the girder member 222 can move in the Y-axis direction with respect to the support member 221. That is, the hanging girder 22 can be expanded and contracted in the Y-axis direction as shown by the white arrows in FIGS. 4 to 6 and 8.

ホイスト23は、桁材222のX軸方向略中央部に配置される(図7(b))。ホイスト23は、桁材222に対してY軸方向に移動可能に支持されており、図7に示すように、ワイヤ231、フック232、モータ233、モータ234、及びローラ235を備える。 The hoist 23 is arranged at a substantially central portion in the X-axis direction of the girder member 222 (FIG. 7 (b)). The hoist 23 is movably supported in the Y-axis direction with respect to the girder member 222, and includes a wire 231, a hook 232, a motor 233, a motor 234, and a roller 235 as shown in FIG. 7.

ホイスト23は、モータ233を用いてワイヤ231の巻き上げ及び巻き下げを行い、ワイヤ231に吊下げられたフック232を上下に移動させることができる。フック232には、直接、またはワイヤロープなどを介して、資材を吊下げて保持することができる。フック232は、本発明における保持部に相当する。 The hoist 23 can wind up and down the wire 231 by using the motor 233, and can move the hook 232 suspended from the wire 231 up and down. The material can be hung and held on the hook 232 either directly or via a wire rope or the like. The hook 232 corresponds to the holding portion in the present invention.

モータ234は、ローラ235の近傍に設置される(図7)。モータ234はローラ235と減速機構を介して接続しており、ローラ235を回転駆動することができる。ローラ235は、桁材222を構成するH形鋼の下部フランジ上に配置される(図7(b))。ホイスト23は、モータ234を用いてローラ235を回転駆動することにより、桁材222の両端部間を、Y軸方向に走行することができる。 The motor 234 is installed in the vicinity of the roller 235 (FIG. 7). The motor 234 is connected to the roller 235 via a reduction mechanism, and the roller 235 can be rotationally driven. The roller 235 is arranged on the lower flange of the H-shaped steel constituting the girder member 222 (FIG. 7 (b)). The hoist 23 can travel between both ends of the girder member 222 in the Y-axis direction by rotationally driving the roller 235 using the motor 234.

<工程>
上記搬送機構1を使用例として、既存構造物9の下方において構造物8を施工する際の工程について以下に説明する。
<Process>
Using the transport mechanism 1 as an example of use, a process for constructing the structure 8 below the existing structure 9 will be described below.

(構真柱の設置)
施工者は、最初の工程として、場所打ち杭である杭81の施工を行う。まず既存構造物9付近の地表面に開口部Aを設けるとともに、既存構造物9の下方を掘削する。これにより、既存構造物9の下方に、構造物8の施工を行うための空間Sと、地表面Gが形成される(図1)。
(Installation of Shinbashira)
As the first step, the builder constructs the pile 81, which is a cast-in-place pile. First, an opening A is provided on the ground surface near the existing structure 9, and the lower part of the existing structure 9 is excavated. As a result, a space S for constructing the structure 8 and a ground surface G are formed below the existing structure 9 (FIG. 1).

次に施工者は、杭81及び構真柱82を施工する。なお、杭81の構造及び施工方法は、設計条件等に応じて適宜選択されるものである。例えば、杭81を鉄筋コンクリート造としてもよいし、鋼管コンクリート造としてもよい。また、杭81を鋼管柱とし、これを上方に延長して構真柱82とする構造とすることも可能である。構真柱82の構造についても適宜選択されるものであり、例として、鉄骨柱、鋼管柱、H形鋼の柱、断面十字型にH型鋼を組んだ鋼製柱等が挙げられる。一例として、杭81が鉄筋コンクリート造の場所打ち杭である場合は、地表面Gを掘削し、掘削孔内への配筋及び構真柱82の建込みと、コンクリート打設とを行う。 Next, the builder constructs the pile 81 and the structural pillar 82. The structure and construction method of the pile 81 are appropriately selected according to the design conditions and the like. For example, the pile 81 may be made of reinforced concrete or steel pipe concrete. It is also possible to use the pile 81 as a steel pipe column and extend it upward to form a structural pillar 82. The structure of the structural column 82 is also appropriately selected, and examples thereof include steel columns, steel tube columns, columns of H-shaped steel, and steel columns in which H-shaped steel is assembled in a cross-shaped cross section. As an example, when the pile 81 is a cast-in-place pile made of reinforced concrete, the ground surface G is excavated, reinforcement is arranged in the excavation hole, the structural pillar 82 is built, and concrete is placed.

施工の結果、図1に示すように、構真柱82の下部は杭81に固定され、構真柱82の上部は地表面Gから上方に突出した状態となる。 As a result of the construction, as shown in FIG. 1, the lower portion of the structural pillar 82 is fixed to the pile 81, and the upper portion of the structural pillar 82 protrudes upward from the ground surface G.

(搬送機構の設置)
次の工程として施工者は、以下の手順で搬送機構1を設置する。
(Installation of transport mechanism)
As the next step, the builder installs the transport mechanism 1 according to the following procedure.

施工者は、ガーダ12を構真柱82上方に架設する。ガーダ12は、既存構造物9の下方において、既存構造物9の杭91の間を通り、さらに開口部Aの下方を通過するように設置される(図2)。搬送機構1は、既存構造物9の大きさや工区の形状に応じて複数個所に設置することが可能である。なお本実施形態においては、図2のように、搬送機構1は2か所に設置される。 The builder erected the girder 12 above the Shinbashira 82. The girder 12 is installed below the existing structure 9 so as to pass between the piles 91 of the existing structure 9 and further below the opening A (FIG. 2). The transport mechanism 1 can be installed at a plurality of locations according to the size of the existing structure 9 and the shape of the work area. In this embodiment, as shown in FIG. 2, the transport mechanism 1 is installed at two places.

ガーダ12を架設する工程において施工者は、まず構真柱82の頂部に支持部11を組立て、固定する(図3、図4)。次に複数の支持部11の頂部に2本の縦桁12Aを架設、固定し、次いで横桁12B及び縦桁12Aを互いに井桁状に組み、接合させる。このようにして、図3及び図4に示すように、ガーダ12が構真柱82の上方に架設される。 In the process of erection of the girder 12, the builder first assembles and fixes the support portion 11 on the top of the structural pillar 82 (FIGS. 3 and 4). Next, two vertical girders 12A are erected and fixed on the tops of the plurality of support portions 11, and then the horizontal girders 12B and the vertical girders 12A are assembled and joined to each other in a grid shape. In this way, as shown in FIGS. 3 and 4, the girder 12 is erected above the structural pillar 82.

なお、ガーダ12の架設は、上記のように支持部11の上方で順次組み立てることによって行われてもよいし、予め組立てられたガーダ12を支持部11の上部に据付けることによって行われてもよい。横桁12B及び縦桁12Aを用いることにより、台車21を軽量で制作でき、現場での設置作業性、経済性を向上させることができる。 The girder 12 may be erected by sequentially assembling the girder 12 above the support portion 11 as described above, or by installing the pre-assembled girder 12 on the upper part of the support portion 11. good. By using the horizontal girder 12B and the vertical girder 12A, the dolly 21 can be produced in a lightweight manner, and the installation workability and economy at the site can be improved.

次に施工者は、ガーダ12の上部にレール13を敷設して軌道部10の組立てを完了する。レール13の敷設後、施工者は、搬送装置20をレール13上に設置する。搬送装置20の設置は、組立て後の搬送装置20をレール13上に設置する方法によって実行されてもよい。また、レール13上において台車21、吊桁22、及びホイスト23を順次組み立てる方法によって搬送装置20の設置が実行されてもよい。 Next, the builder lays the rail 13 on the upper part of the girder 12 and completes the assembly of the track portion 10. After laying the rail 13, the builder installs the transport device 20 on the rail 13. The installation of the transport device 20 may be performed by a method of installing the transport device 20 after assembly on the rail 13. Further, the transport device 20 may be installed by the method of sequentially assembling the carriage 21, the suspension girder 22, and the hoist 23 on the rail 13.

(上床版の施工)
次に施工者は、上床版83を構築する。上床版83の構築に必要な資材は、搬送装置20によって搬入される。詳細には、施工者は、開口部Aから空間Sへ支保工71、型枠72(図5及び図6)や、鉄筋などの資材を搬入し、その後、搬送機構1を使ってこれらの資材を適切な箇所へ搬送する。資材の空間Sへの荷卸しは、例えば、図1及び図2に示すようにクレーンCRを用いて行われる。
(Construction of upper floor slab)
Next, the builder constructs the upper floor slab 83. The materials necessary for constructing the upper floor slab 83 are carried in by the transport device 20. Specifically, the builder carries materials such as support 71, formwork 72 (FIGS. 5 and 6) and reinforcing bars from the opening A to the space S, and then uses the transport mechanism 1 to carry these materials. To the appropriate place. The unloading of the material to the space S is performed using, for example, a crane CR as shown in FIGS. 1 and 2.

資材の搬送時においては、図5などに示すように、搬送装置20の吊桁22及びホイスト23をY軸方向に伸縮、移動させ、さらにホイスト23でワイヤ231の巻上げ及び巻下げを行うことにより、資材の荷揚及び荷卸しが行われる。吊桁22が伸縮し、さらにホイスト23が桁材222に対して移動するため、資材の荷揚及び荷卸しが可能な範囲を拡張することができる。また、搬送時には吊桁22を縮め、杭91との干渉を防止できる(図5右側)。荷揚時及び荷卸し時において、ロック機構216によって搬送装置20の転倒が防止される。そのため搬送装置20は、ロック機構のない搬送装置に比較して、高い楊重性能を有する。 When transporting materials, as shown in FIG. 5, the suspension girder 22 and the hoist 23 of the transport device 20 are expanded and contracted and moved in the Y-axis direction, and the hoist 23 winds and unwinds the wire 231. , Materials are unloaded and unloaded. Since the hanging girder 22 expands and contracts and the hoist 23 moves with respect to the girder member 222, the range in which the material can be unloaded and unloaded can be expanded. In addition, the hanging girder 22 can be shrunk during transportation to prevent interference with the pile 91 (right side of FIG. 5). The lock mechanism 216 prevents the transport device 20 from tipping over during unloading and unloading. Therefore, the transport device 20 has a high load performance as compared with a transport device without a lock mechanism.

搬送装置20は、レール13上を走行し、資材を搬送する。搬送機構1が上床版83の施工範囲よりも上方に設置されているため、配筋作業や型枠組立などの作業に干渉することなく、資材の搬送が実行される。軌道部10が開口部Aの下方を通過するように設置されるため(図1、図2)、開口部Aから搬入された資材を、搬送装置20によって容易に荷揚げし、搬送することが可能である。 The transport device 20 travels on the rail 13 and transports materials. Since the transport mechanism 1 is installed above the construction range of the upper floor slab 83, the material can be transported without interfering with the work such as bar arrangement work and formwork assembly. Since the track portion 10 is installed so as to pass below the opening A (FIGS. 1 and 2), the material carried in from the opening A can be easily unloaded and transported by the transport device 20. Is.

本実施形態では搬送機構1が2か所に設置されているため、施工者は、搬送機構1の設置個所を中心に、施工領域を2つの工区R1、R2に分割し、工区R1、R2で並行して施工を行うことができる(図2)。そのため、工事を効率よく進捗させることができる。 In the present embodiment, since the transport mechanism 1 is installed at two places, the builder divides the construction area into two work zones R1 and R2 centering on the place where the transport mechanism 1 is installed, and in the work zones R1 and R2. Construction can be done in parallel (Fig. 2). Therefore, the construction can be efficiently progressed.

施工者は、図3及び図4に示すように支保工71と型枠72の組立て、及び配筋を実施する。その後、コンクリートの打設と養生を行い、上床版83を構築する(図8)。なお、コンクリート打設時に、搬送装置20によってバケットが搬送されてもよい。 As shown in FIGS. 3 and 4, the builder carries out the assembly of the support work 71 and the formwork 72, and the reinforcement arrangement. After that, concrete is placed and cured to construct the upper floor slab 83 (Fig. 8). The bucket may be conveyed by the conveying device 20 at the time of placing concrete.

上床版83の施工後、搬送装置20は解体され、開口部Aから搬出される。一方で上床版83下方の地盤が掘削され、新たな床版の構築を含む、上床版83の下方における構造物8の施工が継続される。 After the construction of the upper floor slab 83, the transport device 20 is disassembled and carried out from the opening A. On the other hand, the ground below the upper deck 83 will be excavated, and the construction of the structure 8 under the upper deck 83 will be continued, including the construction of a new deck.

<変形例>
実施形態においては、ガーダ12の上部に敷設された2本のレール13を搬送装置20の軌道としていた。しかし本発明はこのような構成に限定されない。図9に示すように、軌道としてモノレール13Aを用いて、支持部11Aに支持させる構成としてもよい。レール13に十分な耐力がある場合、構真柱82に対してレール13を直接載置する構成としてもよい。
<Modification example>
In the embodiment, the two rails 13 laid on the upper part of the girder 12 are used as the tracks of the transport device 20. However, the present invention is not limited to such a configuration. As shown in FIG. 9, the monorail 13A may be used as the track and may be supported by the support portion 11A. If the rail 13 has a sufficient yield strength, the rail 13 may be directly mounted on the structural pillar 82.

実施形態では、搬送装置20として伸縮可能な吊桁22を有する組立式クレーンを用いていたが、ジブクレーンなど(図10)、他の形式のクレーンを用いることも可能である。また、吊桁22やジブの無い、すなわち腕部を持たない構成とし、台車21に資材を直接載置して搬送する構成としてもよい。 In the embodiment, an assembly-type crane having a telescopic suspension girder 22 is used as the transport device 20, but other types of cranes such as a jib crane (FIG. 10) can also be used. Further, the structure may be such that there is no hanging girder 22 or jib, that is, the structure does not have an arm portion, and the material is directly placed and transported on the trolley 21.

実施形態では、構真柱82は上端部において上床版83を支持していた。構真柱82の構成はこのような構造に限定されない。一般的な逆打ち工法において採用される工法及び構造と同様、既存構造物9と干渉しない領域では、上床版83よりも上方に延びて柱として機能し、床版を支持、固定することができる(図1右側)。 In the embodiment, the structural pillar 82 supported the upper floor slab 83 at the upper end portion. The structure of the structure Shinbashira 82 is not limited to such a structure. Similar to the construction method and structure adopted in the general reverse striking method, in the region that does not interfere with the existing structure 9, it extends upward from the upper floor slab 83 and functions as a pillar, and can support and fix the floor slab. (Fig. 1, right side).

上床版83は、鉄骨造、鉄筋鉄骨コンクリート造等、鉄筋コンクリート造以外の構造としてもよい。上床版83と構真柱82の取り合いの構造についても、鉄筋コンクリートや、鉄骨のブラケットなど、設計条件に応じて適宜選択されるものである。 The upper floor slab 83 may have a structure other than the reinforced concrete structure, such as a steel frame structure or a reinforced steel frame concrete structure. The structure of the connection between the upper floor slab 83 and the structural pillar 82 is also appropriately selected according to the design conditions such as reinforced concrete and steel frame brackets.

<効果>
上記実施形態では、搬送機構1は、構真柱82に支持される軌道部10と、軌道部10を走行して資材を搬送する搬送装置20と、を備える。
<Effect>
In the above embodiment, the transport mechanism 1 includes a track portion 10 supported by the structural pillar 82, and a transport device 20 that travels on the track portion 10 to transport materials.

上記構成では、搬送装置20を用いて効率よく資材を搬送し、工事を進めることができる。搬送機構1が無い場合、人力など他の搬送方法を用いる工事の効率化を図ることができない。一方、上記構成では、構真柱82に軌道部10が支持されるため、上方に軌道部10を支持する構造が無い場合であっても搬送経路を確保でき、工事を効率よく進捗させることが可能である。 In the above configuration, the material can be efficiently transported by using the transport device 20, and the construction work can proceed. Without the transport mechanism 1, it is not possible to improve the efficiency of construction using other transport methods such as human power. On the other hand, in the above configuration, since the track portion 10 is supported by the structural pillar 82, a transport path can be secured even when there is no structure for supporting the track portion 10 above, and the construction can be efficiently progressed. It is possible.

上記実施形態では、軌道部10の少なくとも一部は、構真柱82とは異なる既存構造物9の下方に位置する。また、軌道部10は、既存構造物9の杭91の間に位置する。 In the above embodiment, at least a part of the track portion 10 is located below the existing structure 9 different from the structural pillar 82. Further, the track portion 10 is located between the piles 91 of the existing structure 9.

上記構成では、既存構造物9との干渉を避け、既存構造物9の下方において資材を効率よく搬送することが可能である。搬送機構1が無い場合、資材の搬入口である開口部Aから最も遠い箇所から型枠工事等を進めていく必要があるのに対し、搬送機構1を用いれば軌道部10に沿って任意の箇所に資材を搬入し、施工を行うことができる。工区R1、R2それぞれの工区内において、開口部Aからの距離にかかわらず同時に工事を進めることも可能であり、施工効率を向上させ、工期の短縮を図ることができる。このように資材の搬入口が限定されるような場合であっても、施工の効率化を図ることができる。 With the above configuration, it is possible to avoid interference with the existing structure 9 and efficiently transport the material below the existing structure 9. If there is no transport mechanism 1, it is necessary to proceed with formwork work from the farthest point from the opening A, which is the material entrance, whereas if the transport mechanism 1 is used, it is arbitrary along the track portion 10. Materials can be brought into the location and construction can be performed. It is possible to proceed with the construction at the same time regardless of the distance from the opening A in each of the construction zones R1 and R2, and it is possible to improve the construction efficiency and shorten the construction period. Even when the material entrance is limited in this way, it is possible to improve the efficiency of construction.

上記実施形態では、軌道部10が構真柱82の上方に位置する。詳細には、構真柱82は、その上端部において上床版83を支持し、軌道部10は、構真柱82及び上床版83の上方に位置する。 In the above embodiment, the track portion 10 is located above the structural pillar 82. Specifically, the structural pillar 82 supports the upper floor slab 83 at its upper end, and the track portion 10 is located above the structural pillar 82 and the upper floor slab 83.

上記構成では、構真柱82上端部までの構造物の工事と干渉しない。そのため、上床版83など、構造物8の施工を効率よく進捗させることができる。 In the above configuration, it does not interfere with the construction of the structure up to the upper end of the structural pillar 82. Therefore, the construction of the structure 8 such as the upper floor slab 83 can be efficiently progressed.

上記実施形態では、軌道部10は、搬送装置20が走行するレール13と、互いに接合された縦桁12A及び横桁12Bによって構成されたガーダ12とを有する。 In the above embodiment, the track portion 10 has a rail 13 on which the transport device 20 travels, and a girder 12 composed of vertical girders 12A and horizontal girders 12B joined to each other.

上記構成では、縦桁12A、横桁12Bを用いて簡易な構成で軽量のガーダ12を組み立てることができる。そのため、搬送機構1を容易に設置することができる。現場での設置作業性、経済性が向上する。 In the above configuration, the lightweight girder 12 can be assembled with a simple configuration using the vertical girder 12A and the horizontal girder 12B. Therefore, the transport mechanism 1 can be easily installed. Installation workability and economy at the site are improved.

上記実施形態では、搬送装置20は、伸縮可能な吊桁22と、吊桁22に支持されるワイヤ231と、ワイヤ231に吊下られた、資材を保持可能な保持部であるフック232と、を有する。 In the above embodiment, the transport device 20 includes a stretchable suspension girder 22, a wire 231 supported by the suspension girder 22, and a hook 232 suspended from the wire 231 which is a holding portion capable of holding materials. Have.

上記構成では、簡易な機構によって搬送装置20を構成し、資材を保持、搬送可能な装置とすることができる。吊桁22が伸縮可能であるため、搬送装置20が荷揚及び荷卸し可能な範囲が拡張可能である。 In the above configuration, the transport device 20 can be configured by a simple mechanism to be a device capable of holding and transporting materials. Since the suspension girder 22 can be expanded and contracted, the range in which the transport device 20 can be unloaded and unloaded can be expanded.

上記実施形態に示す施工方法は、構真柱82を構築する工程と、搬送機構1を設置する工程と、搬送装置20を用いて資材を搬送する工程と、搬送した資材を用いて構真柱82の上端部に支持される上床版83を構築する工程とを含む。 The construction method shown in the above embodiment includes a step of constructing a structural pillar 82, a step of installing a transport mechanism 1, a step of transporting materials using a transport device 20, and a structural pillar using the transported materials. It includes a step of constructing an upper floor slab 83 supported by the upper end portion of 82.

上記施工方法では、搬送装置20を用いて効率よく資材を搬送し、工事を進めることができる。構真柱82に軌道部10が支持されるため、上方に軌道部10を支持する構造が無い場合であっても搬送経路を確保でき、工事を効率よく進捗させることが可能である。 In the above construction method, the material can be efficiently transported by using the transport device 20, and the construction can proceed. Since the track portion 10 is supported by the structural pillar 82, it is possible to secure a transport path even when there is no structure for supporting the track portion 10 above, and it is possible to efficiently proceed with the construction.

1 搬送機構
10 軌道部
20 搬送装置
8 構造物
81 杭
82 構真柱
83 上床版
9 既存構造物
91 杭
1 Transport mechanism 10 Track section 20 Transport device 8 Structure 81 Pile 82 Structure Shinbashira 83 Upper floor slab 9 Existing structure 91 Pile

Claims (7)

構真柱によって支持される軌道部と、
前記軌道部を走行して資材を搬送する搬送装置と、を備える搬送機構。
The track part supported by the Shinbashira and
A transport mechanism including a transport device that travels on the track portion to transport materials.
前記軌道部の少なくとも一部は、前記構真柱とは異なる既存構造物の下方に位置する、請求項1に記載の搬送機構。 The transport mechanism according to claim 1, wherein at least a part of the track portion is located below an existing structure different from the structural pillar. 前記軌道部は、前記構真柱の上方に位置する、請求項1または2に記載の搬送機構。 The transport mechanism according to claim 1 or 2, wherein the track portion is located above the structural pillar. 前記構真柱は、その上端部において床版を支持し、
前記軌道部は、前記構真柱及び前記床版の上方に位置する、請求項3に記載の搬送機構。
The structural pillar supports the deck at its upper end and
The transport mechanism according to claim 3, wherein the track portion is located above the structural pillar and the deck.
前記軌道部は、
前記搬送装置が走行するレールと、
互いに接合された縦桁及び横桁によって構成された、前記レールが敷設されるガーダと、を有する、請求項1から4のいずれか1項に記載の搬送機構。
The track portion is
The rail on which the transport device travels and
The transport mechanism according to any one of claims 1 to 4, further comprising a girder on which the rail is laid, which is composed of vertical girders and horizontal girders joined to each other.
前記搬送装置は、
伸縮可能な腕部と、
前記腕部に支持されるワイヤと、
前記ワイヤに吊下られた、資材を保持可能な保持部と、を有する、請求項1から5のいずれか1項に記載の搬送機構。
The transport device is
Stretchable arms and
The wire supported by the arm and
The transport mechanism according to any one of claims 1 to 5, further comprising a holding portion suspended from the wire and capable of holding a material.
前記構真柱を構築する工程と、
請求項1から6のいずれか1項に記載の搬送機構を設置する工程と、
前記搬送装置を用いて資材を搬送する工程と、
搬送された前記資材を用いて前記構真柱の上端部に支持される床版を構築する工程と、を含む施工方法。
The process of constructing the above-mentioned Shinbashira and
The step of installing the transport mechanism according to any one of claims 1 to 6 and
The process of transporting materials using the transport device and
A construction method including a step of constructing a deck supported on the upper end of the structural pillar using the transported materials.
JP2020203223A 2020-12-08 2020-12-08 Conveyance mechanism and construction method Pending JP2022090740A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020203223A JP2022090740A (en) 2020-12-08 2020-12-08 Conveyance mechanism and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020203223A JP2022090740A (en) 2020-12-08 2020-12-08 Conveyance mechanism and construction method

Publications (1)

Publication Number Publication Date
JP2022090740A true JP2022090740A (en) 2022-06-20

Family

ID=82060731

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020203223A Pending JP2022090740A (en) 2020-12-08 2020-12-08 Conveyance mechanism and construction method

Country Status (1)

Country Link
JP (1) JP2022090740A (en)

Similar Documents

Publication Publication Date Title
JP4504910B2 (en) Dolly and method of erection of temporary pier using it
JP5051591B2 (en) Precast PC plate erection device for floor slab and its erection method
JP2009002053A (en) Bridge girder erection apparatus and bridge girder erection method
JP2012036596A (en) Heavy load erection machine and erection method of heavy load
JP6952572B2 (en) Overhang erection work vehicle and construction method
JP2020002778A (en) Bridge pier construction method
JP2008162749A (en) Jib crane
CN108396749B (en) Installation system and installation method of steel support in foundation pit
JP7202424B2 (en) Lifting device and construction method of concrete structure using the lifting device
JP2008248664A (en) Hoisting method of curtain wall
JP2009091816A (en) Method and device for constructing bridge
JP2019157441A (en) Demolition system and demolition method for existing structure
JP5793062B2 (en) Tunnel construction apparatus and tunnel construction method
JP2022090740A (en) Conveyance mechanism and construction method
JP4489872B2 (en) Bridge erection method and apparatus
JP5027015B2 (en) Cable conveyor
JP2019173435A (en) Floor system replacement method and floor system replacement device
JP2005307684A (en) Laying apparatus of precast concrete floor board
JP2001055733A (en) Construction method for underground wall and underground wall structure thereof
JP2019173365A (en) Method of constructing linear structure
JP2021031878A (en) Construction system and construction method of elevated structure
JP2020133213A (en) Floor slab lifting device
JP2007138496A (en) Beam construction method
JP2020122359A (en) Floor slab erection system, additional floor slab installation method, and floor slab removing method
JP2768281B2 (en) Bridge construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20231117