JP2021143547A - Pile head treatment method - Google Patents

Pile head treatment method Download PDF

Info

Publication number
JP2021143547A
JP2021143547A JP2020044003A JP2020044003A JP2021143547A JP 2021143547 A JP2021143547 A JP 2021143547A JP 2020044003 A JP2020044003 A JP 2020044003A JP 2020044003 A JP2020044003 A JP 2020044003A JP 2021143547 A JP2021143547 A JP 2021143547A
Authority
JP
Japan
Prior art keywords
pile
pipe
concrete
treatment method
freezing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2020044003A
Other languages
Japanese (ja)
Inventor
達朗 石丸
Tatsuro Ishimaru
達朗 石丸
輝士 山崎
Teruji Yamazaki
輝士 山崎
信也 鈴木
Shinya Suzuki
信也 鈴木
康浩 井戸
Yasuhiro Ido
康浩 井戸
明彦 松岡
Akihiko Matsuoka
明彦 松岡
和幸 植木
Kazuyuki Ueki
和幸 植木
浩 小椋
Hiroshi Ogura
浩 小椋
聡 江口
Satoshi Eguchi
聡 江口
和希 高橋
Kazuki Takahashi
和希 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seiken Co Ltd
Toda Corp
Original Assignee
Seiken Co Ltd
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seiken Co Ltd, Toda Corp filed Critical Seiken Co Ltd
Priority to JP2020044003A priority Critical patent/JP2021143547A/en
Publication of JP2021143547A publication Critical patent/JP2021143547A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

To provide a pile head treatment method for dismantling an extra-banking concrete of an on-site construction pile, which does not require the work of scraping the side surface of the on-site construction pile and prevents the generation of noise and vibration.SOLUTION: In a pile head treatment method, a refrigeration pipe 13 embedded in concrete in advance is frozen and expanded to generate a crack, and an extra banking concrete part 12 of an on-site construction pile 11 is removed using the cracked part as a boundary. The refrigeration pipe is fixed to a pile bar 14 or a fixing hoop 15 of the on-site construction pile via a fixing reinforcing bar 16, and raises a refrigerant pipe 17 for injecting low temperature liquefied gas into the refrigeration pipe above the extra banking concrete part.SELECTED DRAWING: Figure 1

Description

本発明は、現場造成杭の余盛コンクリート部分を解体処理するための杭頭処理工法に関するものである。 The present invention relates to a pile head treatment method for dismantling a surplus concrete portion of a pile created on site.

従来、この種の杭頭処理工法としては、特許第6475553号公報に開示された杭頭処理工法と凍結破砕管の発明が知られている。 Conventionally, as this type of pile head treatment method, the invention of the pile head treatment method and the frost weathering pipe disclosed in Japanese Patent No. 6475553 is known.

この杭頭処理工法は、図11(A)(B)(C)に示すように、現場造成杭1の余盛コンクリート部分2を、コンクリート中に埋設させた膨張性破砕材3でひび割れを発生させて、そのひび割れ部分を境に撤去して杭頭処理する工法であって、膨張性破砕材3は、予め水を封入して冷却部を内包した冷凍管(凍結破砕管)4であり、この冷凍管4をコンクリート中に埋設させた後に、冷却部に液体窒素を注入して水を凍結させて冷凍管4を凍結膨張させ、ひび割れを発生させる工法である(特許文献1参照)。 In this pile head treatment method, as shown in FIGS. 11A, 11B, and 11C, cracks are generated in the expansive crushing material 3 in which the surplus concrete portion 2 of the on-site pile 1 is buried in the concrete. The expansion crushing material 3 is a freezing pipe (freezing crushing pipe) 4 in which water is previously sealed and a cooling portion is included, which is a construction method in which the cracked portion is removed at the boundary to perform pile head treatment. This is a method of burying the freezing pipe 4 in concrete and then injecting liquid nitrogen into a cooling unit to freeze water to freeze and expand the freezing pipe 4 to generate cracks (see Patent Document 1).

このような構成の杭頭処理工法によれば、杭頭処理を低騒音及び低振動で施工できるだけでなく、ひび割れが容易に発生して余盛コンクリートの解体施工性が向上することとなる。 According to the pile head treatment method having such a configuration, not only the pile head treatment can be performed with low noise and low vibration, but also cracks are easily generated and the dismantling workability of the surplus concrete is improved.

特許第6475553号公報Japanese Patent No. 6475553

(イ)この従来例の杭頭処理工法においては、冷凍管4の冷却部に液体窒素を注入するに先立ち、冷却部の注入口を探し出すために現場造成杭1の側面を斫り出す必要があり、その結果、騒音や振動が発生するという問題点を有している。 (B) In this conventional pile head treatment method, prior to injecting liquid nitrogen into the cooling portion of the refrigerating pipe 4, it is necessary to scrape the side surface of the on-site pile 1 in order to find the injection port of the cooling portion. As a result, there is a problem that noise and vibration are generated.

それに加えて、(ロ)従来は、杭主筋5に対して余盛コンクリート部分2との縁切り材として発泡ポリエチレン製の養生材を被せて取り付けているが、その結果、余盛コンクリートガラにプラスチックゴミが混入することとなり、産業廃棄物を処理する上で問題点を有している。 In addition to that, (b) Conventionally, the pile main bar 5 is covered with a curing material made of foamed polyethylene as an edge cutting material with the surplus concrete portion 2, but as a result, plastic waste is attached to the surplus concrete waste. Will be mixed in, and there is a problem in treating industrial waste.

(ハ)従来は、杭主筋5に対して補強支持鉄筋6を介して番線等で、ひび割れを発生させようとする計画線の位置で略水平に冷凍管4を取り付け固定しているが、この場合、余盛コンクリート部分2を引き抜いた後に、冷凍管4が杭本体1aに残置することがあるという問題点を有している。 (C) Conventionally, the refrigerating pipe 4 is attached and fixed substantially horizontally at the position of the planned line where cracks are to be generated at the number line or the like via the reinforcing support reinforcing bar 6 with respect to the pile main reinforcing bar 5. In this case, there is a problem that the refrigerating pipe 4 may be left in the pile body 1a after the surplus concrete portion 2 is pulled out.

(ニ)従来は、図11(A)(B)に示すように、複数本、例えば6本の冷凍管4を取り付け固定しているが、この場合、現場造成杭1が概ね1200φ以下の小径杭の場合は、複数本の冷凍管4の存在によってコンクリート打設用のトレミー管が空間8内を通り難く、その結果、コンクリートの打設が困難であるという問題点を有している。 (D) Conventionally, as shown in FIGS. 11A and 11B, a plurality of, for example, 6 refrigerating pipes 4 are attached and fixed, but in this case, the on-site construction pile 1 has a small diameter of about 1200φ or less. In the case of piles, there is a problem that the presence of a plurality of refrigerating pipes 4 makes it difficult for the tremie pipe for placing concrete to pass through the space 8, and as a result, it is difficult to place concrete.

(ホ)従来は、現場造成杭1が場所打ち鋼管コンクリート杭であって、杭頭に主筋が延びていないタイプのものが存在する。この場合、冷凍管4を鉄筋籠7の杭主筋5に取り付けることができないという問題点を有している。 (E) Conventionally, there is a type in which the on-site construction pile 1 is a cast-in-place steel pipe concrete pile and the main bar does not extend to the pile head. In this case, there is a problem that the freezing pipe 4 cannot be attached to the pile main bar 5 of the reinforcing bar cage 7.

従って、従来例における杭頭処理工法においては、(い)冷凍管4の冷却部の注入口を探し出すために現場造成杭1の側面を斫り出す作業を無くして騒音や振動の発生を防止することに必須の解決課題を有している。
さらには、(ろ)余盛コンクリートガラにプラスチックゴミが混入する事態を防止することと、(は)余盛コンクリート部分2を引き抜いた後に冷凍管4が杭本体1aに残置する事態を無くすことと、(に)現場造成杭1が小径杭であってもコンクリートの打設を円滑に行うこと、(ほ)現場造成杭1が場所打ち鋼管コンクリート杭で杭頭に主筋が延びていない場合であっても冷凍管4を取り付け固定することとに解決しなければならない課題を有している。
Therefore, in the pile head treatment method in the conventional example, (a) the work of scraping the side surface of the on-site pile 1 in order to find the injection port of the cooling part of the freezing pipe 4 is eliminated to prevent the generation of noise and vibration. In particular, it has an essential solution.
Furthermore, it is possible to prevent the situation where plastic dust is mixed into the (b) surplus concrete waste, and to eliminate the situation where the refrigerating pipe 4 is left in the pile body 1a after the (ha) surplus concrete portion 2 is pulled out. , (Ni) Even if the on-site construction pile 1 is a small-diameter pile, concrete can be placed smoothly. However, there is a problem that must be solved by attaching and fixing the refrigerating pipe 4.

前記従来例の課題を解決するための本発明の要旨は、現場造成杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、前記冷凍管は、前記現場造成杭の杭主筋又は固定用フープに対して固定用鉄筋を介して固定し、前記冷凍管に低温液化ガスを注入するための冷媒管を前記余盛コンクリート部分の上部に立ち上げてあることである。 The gist of the present invention for solving the above-mentioned problems of the conventional example is that the surplus concrete portion of the on-site construction pile is frozen and expanded by freezing and expanding a refrigerating pipe embedded in the concrete in advance to generate cracks, and the cracked portion is defined as a boundary. The refrigerating pipe is fixed to the pile main bar or the fixing hoop of the on-site construction pile via the fixing reinforcing bar, and the low-temperature liquefied gas is injected into the refrigerating pipe. A refrigerant pipe for this purpose is set up above the surplus concrete portion.

また、前記冷凍管は、前記固定用鉄筋の一端部を前記余盛コンクリート部分の前記杭主筋又は前記固定用フープに固定してあること、;
前記現場造成杭の直径が1200mm以下の小径杭の場合は、1本の前記冷凍管を前記杭主筋又は前記固定用フープに対して前記固定用鉄筋を介して固定してあること、;
を含むものである。
Further, in the freezing pipe, one end of the fixing reinforcing bar is fixed to the pile main bar or the fixing hoop of the surplus concrete portion;
In the case of a small-diameter pile having a diameter of 1200 mm or less, one of the refrigerating pipes is fixed to the pile main bar or the fixing hoop via the fixing reinforcing bar.
Is included.

前記従来例の課題を解決するための本発明の要旨は、現場造成杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、前記冷凍管は、前記現場造成杭の杭主筋又は固定用フープに対して固定用鉄筋を介して固定し、前記杭主筋には、前記余盛コンクリート部分との縁切り材としてシースを取り付けてあることである。 The gist of the present invention for solving the above-mentioned problems of the conventional example is that the surplus concrete portion of the on-site pile is frozen and expanded by freezing and expanding a refrigerating pipe embedded in the concrete in advance to generate cracks, and the cracked portion is defined as a boundary. The refrigerating pipe is fixed to the pile main bar or the fixing hoop of the on-site construction pile via a fixing reinforcing bar, and the pile main bar is attached to the surplus concrete. A sheath is attached as an edge cutting material with the part.

前記従来例の課題を解決するための本発明の要旨は、現場造成杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、前記冷凍管は、前記現場造成杭の内側で、かつ杭主筋と固定用フープとからなる鉄筋かごの外側の設置位置に設置してあることである。 The gist of the present invention for solving the above-mentioned problems of the conventional example is that the surplus concrete portion of the on-site pile is frozen and expanded by freezing and expanding a refrigerating pipe embedded in the concrete in advance to generate cracks, and the cracked portion is defined as a boundary. The refrigerating pipe is installed at the installation position inside the on-site construction pile and outside the reinforcing bar cage composed of the pile main bar and the fixing hoop. ..

前記従来例の課題を解決するための本発明の要旨は、鋼管コンクリート杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、前記冷凍管は、前記鋼管コンクリート杭の内側に仮設鉄筋を固定し、該仮設鉄筋に対して前記固定用鉄筋を介して固定してあることである。 The gist of the present invention for solving the above-mentioned problems of the conventional example is that the surplus concrete portion of the steel pipe concrete pile is frozen and expanded by freezing and expanding a refrigerating pipe previously embedded in the concrete to generate cracks, and the cracked portion is defined as a boundary. The refrigerating pipe is a pile head treatment method for removing the pile head, in which a temporary reinforcing bar is fixed inside the steel pipe concrete pile and fixed to the temporary reinforcing bar via the fixing reinforcing bar. ..

本発明の請求項1に係る杭頭処理工法によれば、冷凍管に液体窒素(低温液化ガス)を注入するための冷媒管を余盛コンクリート部分の上部に立ち上げたことによって、従来例のように冷凍管の冷却部の注入口を探し出す斫り出し作業が必要なく、その結果、斫り出し作業に伴う騒音や振動が発生しない。また、速やかに液体窒素の注入作業を開始することができる。
さらには、液体窒素が冷凍管内に長く滞留することで、凍結効果が長く持続することとなり、その結果、使用する液体窒素量が概略20%程度減少するという種々の優れた効果を奏する。
According to the pile head treatment method according to claim 1 of the present invention, a refrigerant pipe for injecting liquid nitrogen (low temperature liquefied gas) into the refrigerating pipe is set up on the upper part of the surplus concrete portion, which is a conventional example. As described above, it is not necessary to perform the squeezing work to find the injection port of the cooling part of the refrigerating pipe, and as a result, the noise and vibration associated with the squeezing work are not generated. In addition, the liquid nitrogen injection work can be started promptly.
Further, since the liquid nitrogen stays in the freezing pipe for a long time, the freezing effect is maintained for a long time, and as a result, the amount of liquid nitrogen used is reduced by about 20%, which is an excellent effect.

冷凍管は、固定用鉄筋の一端部を余盛コンクリート部分の杭主筋又は固定用フープに固定してあることによって、余盛コンクリート部分を引き抜いた後に、従来例のように冷凍管が杭本体に残置することが無く、その結果、冷凍管を斫り取る余分な作業が発生しないという優れた効果を奏する。 In the freezing pipe, one end of the fixing reinforcing bar is fixed to the pile main bar of the surplus concrete part or the fixing hoop, so that after the surplus concrete part is pulled out, the freezing pipe is attached to the pile body as in the conventional example. It has an excellent effect that it is not left behind, and as a result, no extra work is required to scrape the freezing tube.

現場造成杭の直径が概ね1200mm以下の小径杭の場合は、1本の冷凍管を杭主筋又は固定用フープに対して固定用鉄筋を介して固定してあることによって、冷凍管が1本なので空間が広くなり、その空間にトレミー管を通してコンクリートの打設が可能である。また、冷凍管の凍結膨張によるひび割れは問題なく発生するという優れた効果を奏する。 In the case of small-diameter piles with a diameter of approximately 1200 mm or less, one refrigerating pipe is fixed to the pile main bar or fixing hoop via fixing reinforcing bars, so that there is only one refrigerating pipe. The space becomes wider, and concrete can be placed in the space through a tremie pipe. In addition, it has an excellent effect that cracks due to freezing expansion of the freezing tube occur without any problem.

本発明の請求項4に係る杭頭処理工法によれば、杭主筋には、余盛コンクリート部分との縁切り材としてシースを取り付けてあることによって、余盛コンクリートガラにプラスチックゴミが混入しない。
さらには、余盛コンクリート部分の引き抜き時に揚重機に掛かる負荷が低減する。
また、杭主筋に対する養生材は、シースだけでなく紙ボイドやVP管等の硬質で薄物でも良く、この場合は、コンクリート打設時の主筋間距離を適切に確保でき、コンクリートの側方流動に影響を及ぼさないという種々の優れた効果を奏する。
According to the pile head treatment method according to claim 4 of the present invention, the pile main bar is provided with a sheath as an edge cutting material with the excess concrete portion, so that plastic dust does not mix in the excess concrete waste.
Furthermore, the load applied to the lifting machine when the surplus concrete portion is pulled out is reduced.
Further, the curing material for the pile main bar may be not only a sheath but also a hard and thin material such as a paper void or a VP pipe. It has various excellent effects that it does not affect.

本発明の請求項6に係る杭頭処理工法によれば、冷凍管は、前記鋼管コンクリート杭の内側に仮設鉄筋を溶接固定し、仮設鉄筋に対して固定用鉄筋を介して固定してあることによって、現場造成杭が場所打ち鋼管コンクリート杭で杭頭に主筋が延びていない場合であっても冷凍管を仮設鉄筋に取り付け固定することができるという優れた効果を奏する。 According to the pile head treatment method according to claim 6 of the present invention, the refrigerating pipe has a temporary reinforcing bar welded and fixed to the inside of the steel pipe concrete pile, and is fixed to the temporary reinforcing bar via a fixing reinforcing bar. As a result, even when the on-site construction pile is a cast-in-place steel pipe concrete pile and the main bar does not extend to the pile head, the refrigerating pipe can be attached and fixed to the temporary reinforcing bar, which is an excellent effect.

本発明に係る杭頭処理工法における現場造成杭の平面図である。It is a top view of the pile made in the field in the pile head processing method which concerns on this invention. 本発明に係る杭頭処理工法における現場造成杭の側面図である。It is a side view of the pile made in the field in the pile head processing method which concerns on this invention. 杭径長さ合計と窒素ボンベ使用本数との関係を示す図である。It is a figure which shows the relationship between the total pile diameter length and the number of nitrogen cylinders used. 余盛コンクリート部分の引き抜き荷重倍率÷鉄筋の表面積の図である。It is a figure of the pull-out load ratio of the surplus concrete part ÷ the surface area of the reinforcing bar. 作業所毎、縁切り材の種類毎の杭主筋の接触表面積と余盛コンクリート部分との引き抜き荷重倍率との関係を示す図である。It is a figure which shows the relationship between the contact surface area of a pile main bar and the pull-out load ratio with the surplus concrete part for each work place, and for each type of edge cutting material. 本発明に係る杭頭処理工法における小径杭の平面図である。It is a top view of the small diameter pile in the pile head processing method which concerns on this invention. 本発明に係る杭頭処理工法における小径杭の側面図である。It is a side view of the small-diameter pile in the pile head processing method which concerns on this invention. 本発明に係る杭頭処理工法における鋼管コンクリート杭の平面図である。It is a top view of the steel pipe concrete pile in the pile head processing method which concerns on this invention. 本発明に係る杭頭処理工法における鋼管コンクリート杭の側面図である。It is a side view of the steel pipe concrete pile in the pile head processing method which concerns on this invention. 杭頭処理工法の施工手順を示すブロック図である。It is a block diagram which shows the construction procedure of a pile head processing method. (A)従来例に係る杭頭処理工法における現場造成杭の平面図である。(B)同現場造成杭の側面図である。(C)側面図におけるX−X線に沿った断面図である。(A) It is a top view of the pile created in the field in the pile head processing method which concerns on a conventional example. (B) It is a side view of the pile made at the same site. (C) is a cross-sectional view taken along line XX in the side view.

次に、本発明の実施の形態について図面を参照しながら説明する。本発明は、図1及び図2に示すように、現場造成杭11の余盛コンクリート部分12を、予めコンクリート中に埋設させた冷凍管13を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法である。
冷凍管13は、ひび割れを発生させようとする計画線の位置で略水平に取り付け固定するのであり、現場造成杭11の杭主筋14又は固定用フープ15に対して固定用鉄筋16を介して固定する。
なお、冷凍管13は、図1及び図2に示すように、現場造成杭11の内側で、かつ杭主筋14と固定用フープ15とからなる鉄筋かごの外側の設置位置25に設置しもよい。
Next, an embodiment of the present invention will be described with reference to the drawings. In the present invention, as shown in FIGS. 1 and 2, the surplus concrete portion 12 of the on-site pile 11 is freeze-expanded by freezing and expanding the freezing pipe 13 previously embedded in the concrete to generate cracks, and the cracked portion is formed. It is a pile head treatment method that removes at the boundary.
The refrigerating pipe 13 is mounted and fixed substantially horizontally at the position of the planned line where cracks are to be generated, and is fixed to the pile main bar 14 or the fixing hoop 15 of the site-developed pile 11 via the fixing reinforcing bar 16. do.
As shown in FIGS. 1 and 2, the freezing pipe 13 may be installed at the installation position 25 inside the on-site construction pile 11 and outside the reinforcing bar cage composed of the pile main bar 14 and the fixing hoop 15. ..

本発明は、図1及び図2に示すように、冷凍管13に液体窒素(低温液化ガス)を注入するための冷媒管17を余盛コンクリート部分12の上部に立ち上げたものであり、冷媒管17の注入口17aを余盛コンクリート部分12の上部に位置させている。また、冷媒管17の基部17bは、図2に示すように、冷凍管13に接続しており、その内部に液体窒素が充填できるようになっている。 In the present invention, as shown in FIGS. 1 and 2, a refrigerant pipe 17 for injecting liquid nitrogen (low temperature liquefied gas) into the refrigerating pipe 13 is raised above the surplus concrete portion 12, and the refrigerant is used. The injection port 17a of the pipe 17 is located above the surplus concrete portion 12. Further, as shown in FIG. 2, the base portion 17b of the refrigerant pipe 17 is connected to the freezing pipe 13 so that the inside thereof can be filled with liquid nitrogen.

このように、冷媒管17を余盛コンクリート部分12の上部に立ち上げたことによって、従来例のように冷凍管の冷却部の注入口を探し出す斫り出し作業が必要なく、斫り出し作業に伴う騒音や振動が発生しない。また、速やかに液体窒素の注入作業を開始することができる。 By raising the refrigerant pipe 17 above the surplus concrete portion 12 in this way, it is not necessary to perform the squeezing work for finding the injection port of the cooling portion of the freezing pipe as in the conventional example, and the squeezing work can be performed. No noise or vibration is generated. In addition, the liquid nitrogen injection work can be started promptly.

さらには、液体窒素が冷凍管13内に長く滞留することで、凍結効果が長く持続することとなり、その結果、使用する液体窒素量が概略20%程度減少する効果がある。 Further, since the liquid nitrogen stays in the freezing pipe 13 for a long time, the freezing effect is maintained for a long time, and as a result, the amount of liquid nitrogen used is reduced by about 20%.

図3は、杭径長さ合計と窒素ボンベ使用本数との関係を示す図であり、縦軸は窒素ボンベ使用本数を示し、横軸は杭径長さ合計(m)を示している。図中の▲印は三角配置の場合であり、■印は並行配置の場合であり、●印は本願発明の上部供給の場合であり、窒素ボンベ使用本数が約77%減少することが示される。 FIG. 3 is a diagram showing the relationship between the total pile diameter length and the number of nitrogen cylinders used. The vertical axis shows the number of nitrogen cylinders used, and the horizontal axis shows the total pile diameter length (m). The ▲ mark in the figure is for the triangular arrangement, the ■ mark is for the parallel arrangement, and the ● mark is for the upper supply of the present invention, indicating that the number of nitrogen cylinders used is reduced by about 77%. ..

杭主筋14には、図2に示すように、余盛コンクリート部分12との縁切り材としてシース18を取り付けている。具体的には、杭主筋14の周囲に図示しないハツリカバーを取り付け、その上にシース18を取り付けて、その上部及び下部で番線等を用いて固定している。
このように、杭主筋14の周囲にシース18を取り付けてあることによって、余盛コンクリート部分12を引き抜いた後の余盛コンクリートガラにプラスチックゴミが混入しない。さらには、余盛コンクリート部分12の引き抜き時に揚重機に掛かる負荷が低減することとなる。
また、杭主筋14に対する養生材は、シースだけでなく紙ボイドやVP管等の硬質で薄物でも良く、この場合は、コンクリート打設時の主筋間距離を適切に確保でき、コンクリートの側方流動に影響を及ぼさない。
As shown in FIG. 2, a sheath 18 is attached to the pile main bar 14 as an edge cutting material with the surplus concrete portion 12. Specifically, a chipping cover (not shown) is attached around the pile main bar 14, a sheath 18 is attached on the cover, and the sheath 18 is attached to the upper and lower portions thereof by using a number wire or the like.
By attaching the sheath 18 around the pile main bar 14 in this way, plastic dust is not mixed into the surplus concrete glass after the surplus concrete portion 12 is pulled out. Further, the load applied to the lifting machine when the surplus concrete portion 12 is pulled out is reduced.
Further, the curing material for the pile main bar 14 may be not only a sheath but also a hard and thin material such as a paper void or a VP pipe. Does not affect.

図4は、作業所A、作業所B、作業所Cの3箇所の作業所での杭頭引き抜き試験結果の比較グラフであり、作業所Aは杭主筋14の養生材にハツリカバー、ボイド、VP管(塩ビ管)を用い、作業所Bはシース、ハツリカバーを用い、作業所Cはハツリカバーを用いている。
縦軸は余盛コンクリート部分の引き抜き荷重倍率÷鉄筋の表面積を示し、縦軸の値が小さいほど少ない抵抗で引き抜きが出来ることを示している。また、グラフ中の■印は平均値を示している。
FIG. 4 is a comparison graph of the pile head pull-out test results at the three work places of the work place A, the work place B, and the work place C. A VP pipe (PVC pipe) is used, the work place B uses a sheath and a chip cover, and the work place C uses a chip cover.
The vertical axis shows the pull-out load ratio of the surplus concrete part ÷ the surface area of the reinforcing bar, and the smaller the value on the vertical axis, the smaller the resistance required for pulling out. In addition, the ■ mark in the graph indicates the average value.

図5は、図4の試験結果を別のグラフに表したものであり、縦軸は余盛コンクリート部分の引抜荷重倍率を示し、横軸は鉄筋付着面積(mm ×10 )を示している。
グラフの縦軸の値が小さいほど少ない抵抗で引き抜きが出来ることを示しており、実線Aが作業所Bのシースを用いた場合で、実線Bが南砂のハツリカバーを用いた場合であり、即ちシースを用いた場合の方が少ない抵抗で引き抜きが出来ることを示している。
Figure 5 is a representation of the test results of FIG. 4 in a different graph, the ordinate indicates the pulling load ratio of excess weld concrete portions, the horizontal axis represents the rebar adhesion area (mm 2 × 10 6) There is.
The smaller the value on the vertical axis of the graph, the smaller the resistance required for drawing. The solid line A is the case where the sheath of the work place B is used, and the solid line B is the case where the chipping cover of the south sand is used. It is shown that pulling out can be performed with less resistance when using a sheath.

図1及び図2に示すように、冷凍管13に接続する固定用鉄筋16の一端部16aを余盛コンクリート部分12中の杭主筋14又は固定用フープ15まで延出してこれに固定している。
冷凍管13は、一例として約500〜1000mm程度の長さであり、その一端側と他端側とにそれぞれ固定用鉄筋16が連結している。固定用鉄筋16は、上方に立ち上がって、途中に折曲げ部16bを有し、一端部16aが余盛コンクリート部分12の杭主筋14又は固定用フープ15に固定される。
As shown in FIGS. 1 and 2, one end portion 16a of the fixing reinforcing bar 16 connected to the freezing pipe 13 extends to the pile main reinforcing bar 14 or the fixing hoop 15 in the surplus concrete portion 12 and is fixed thereto. ..
The freezing pipe 13 has a length of about 500 to 1000 mm as an example, and fixing reinforcing bars 16 are connected to one end side and the other end side, respectively. The fixing reinforcing bar 16 stands up and has a bent portion 16b in the middle, and one end portion 16a is fixed to the pile main reinforcing bar 14 or the fixing hoop 15 of the surplus concrete portion 12.

このように、固定用鉄筋16の一端部16aを余盛コンクリート部分12中の杭主筋14又は固定用フープ15に固定してあることによって、余盛コンクリート部分12を引き抜いたときに、冷凍管13が余盛コンクリート部分12に取り付くこととなる。つまり、従来例のように冷凍管が杭本体に残置することがないので、冷凍管を斫り取る等の余分な作業が発生しない。 By fixing the one end portion 16a of the fixing reinforcing bar 16 to the pile main bar 14 or the fixing hoop 15 in the surplus concrete portion 12 in this way, when the surplus concrete portion 12 is pulled out, the freezing pipe 13 Will be attached to the surplus concrete portion 12. That is, since the freezing pipe is not left on the pile body as in the conventional example, extra work such as scraping the freezing pipe does not occur.

図6及び図7に示すように、現場造成杭11の直径が1200mm以下の小径杭の場合は、1本の冷凍管13を杭主筋14又は固定用フープ15に対して固定用鉄筋16を介して固定する。
この場合、冷凍管13が1本なので空間19が広くなり、その空間19に図示しないトレミー管を通してコンクリートの打設が可能である。また、冷凍管13の凍結膨張によるひび割れは問題なく発生する。
As shown in FIGS. 6 and 7, in the case of a small-diameter pile having a diameter of 1200 mm or less, one refrigerating pipe 13 is connected to the pile main bar 14 or the fixing hoop 15 via the fixing reinforcing bar 16. And fix it.
In this case, since there is only one freezing pipe 13, the space 19 becomes wide, and concrete can be placed in the space 19 through a tremie pipe (not shown). Further, cracks due to freezing expansion of the freezing tube 13 occur without any problem.

図8及び図9に示すように、本発明は、鋼管コンクリート杭20の余盛コンクリート部分12を、予めコンクリート中に埋設させた冷凍管13を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法である。
冷凍管13は、鋼管コンクリート杭20の内側に仮設鉄筋21を溶接固定し、仮設鉄筋21に対して固定用鉄筋16を介して固定する。
As shown in FIGS. 8 and 9, in the present invention, the surplus concrete portion 12 of the steel pipe concrete pile 20 is frozen and expanded by freezing and expanding the refrigerating pipe 13 previously embedded in the concrete to generate cracks, and the cracked portion is formed. It is a pile head treatment method that removes at the boundary.
In the freezing pipe 13, the temporary reinforcing bar 21 is welded and fixed to the inside of the steel pipe concrete pile 20, and fixed to the temporary reinforcing bar 21 via the fixing reinforcing bar 16.

鋼管コンクリート杭20の杭頭処理工法についての作業手順の一部を説明する。まず、仮設鉄筋21を鋼管コンクリート杭20の内側に溶接固定して、シース22を仮設鉄筋21に被せ、固定用フープ23を取り付け、冷凍管13を取り付け、固定用フープ24を取り付け、冷凍管13に液体窒素を注入するための冷媒管17を立ち上げる。 A part of the work procedure about the pile head treatment method of the steel pipe concrete pile 20 will be described. First, the temporary reinforcing bar 21 is welded and fixed to the inside of the steel pipe concrete pile 20, the sheath 22 is put on the temporary reinforcing bar 21, the fixing hoop 23 is attached, the refrigerating pipe 13 is attached, the fixing hoop 24 is attached, and the refrigerating pipe 13 is attached. A refrigerant pipe 17 for injecting liquid nitrogen into the concrete pipe 17 is set up.

このように、鋼管コンクリート杭20の内側に仮設鉄筋21を溶接固定してあることによって、現場造成杭が場所打ち鋼管コンクリート杭20で杭頭に主筋が延びていない場合であっても冷凍管13を仮設鉄筋21に取り付け固定することができる。 By welding and fixing the temporary reinforcing bars 21 to the inside of the steel pipe concrete pile 20 in this way, the refrigerating pipe 13 is used even when the cast-in-place steel pipe concrete pile 20 does not extend the main reinforcing bar to the pile head. Can be attached and fixed to the temporary reinforcing bar 21.

次に、杭頭処理工法についての施工手順について説明する。まず、図10の杭頭処理工法の施工手順を示すブロック図に示す通り、液体窒素搬入を行う。施工内容は、根切り作業により杭頭部が露出した段階で液体窒素の搬入を行う。 Next, the construction procedure for the pile head treatment method will be described. First, as shown in the block diagram showing the construction procedure of the pile head treatment method of FIG. 10, liquid nitrogen is carried in. As for the construction contents, liquid nitrogen will be carried in when the pile head is exposed by the root cutting work.

そして、冷媒管17の注入口17aの確認を行う。施工内容は、冷媒管17の注入口17a確認し、万一、余盛コンクリート部分12に埋没している場合は斫り出す。
余盛コンクリート部分12の撤去時のラインをきれいにするために、杭頭レベルでカッターを入れることが好ましい。
杭頭鋼管巻きの場合は、成形斫りの段階で行うので、この段階での作業は不要である。
Then, the injection port 17a of the refrigerant pipe 17 is confirmed. As for the construction contents, the injection port 17a of the refrigerant pipe 17 is confirmed, and if it is buried in the surplus concrete portion 12, it is scraped out.
It is preferable to insert a cutter at the pile head level in order to clean the line when the excess concrete portion 12 is removed.
In the case of pile head steel pipe winding, the work is not required at this stage because it is performed at the stage of forming and chipping.

さらに、杭頭の余盛コンクリート部分12の処理を行う。施工内容は、液体窒素容器と冷凍管を配管接続し、完了後に液体窒素を供給し、杭頭の余盛コンクリート部分12に水平クラックが発生するのを確認する。 Further, the surplus concrete portion 12 of the pile head is processed. As for the construction contents, the liquid nitrogen container and the refrigerating pipe are connected by pipes, liquid nitrogen is supplied after completion, and it is confirmed that horizontal cracks occur in the surplus concrete portion 12 of the pile head.

そして、余盛コンクリート部分12の撤去を行う。施工内容は、凍結杭頭処理完了後に余盛コンクリート部分12を揚重、撤去する。揚重計画によっては、余盛コンクリート部分12の撤去前に分割する。 Then, the surplus concrete portion 12 is removed. As for the construction contents, the surplus concrete portion 12 is lifted and removed after the frozen pile head treatment is completed. Depending on the lifting plan, the surplus concrete portion 12 is divided before removal.

1 現場造成杭
1a 杭本体
2 余盛コンクリート部分
3 膨張性破砕材
4 冷凍管
5 杭主筋
6 補強支持鉄筋
7 鉄筋籠
8 空間
11 現場造成杭
12 余盛コンクリート部分
13 冷凍管
14 杭主筋
15 固定用フープ
16 固定用鉄筋
16a一端部
16b折曲げ部
17 冷媒管
17a注入口
17b基部
18 シース(養生材:鋼製シース、紙ボイド、VP管等)
19 空間
20 鋼管コンクリート杭
21 仮設鉄筋
22 シース(養生材:鋼製シース、紙ボイド、VP管等)
23、24 固定用フープ
25 設置位置
1 On-site construction pile 1a Pile body 2 Overlay concrete part 3 Expandable crushing material 4 Refrigeration pipe 5 Pile main reinforcement 6 Reinforcing support reinforcement 7 Reinforcing bar cage 8 Space 11 On-site construction pile 12 Overlay concrete part 13 Refrigeration pipe 14 Pile main reinforcement 15 For fixing Hoop 16 Reinforcing bar for fixing 16a One end 16b Bent part 17 Refrigerator pipe 17a Injection port 17b Base 18 Sheath (curing material: steel sheath, paper void, VP pipe, etc.)
19 Space 20 Steel pipe Concrete pile 21 Temporary reinforcing bar 22 Sheath (curing material: steel sheath, paper void, VP pipe, etc.)
23, 24 Hoop for fixing 25 Installation position

Claims (6)

現場造成杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、
前記冷凍管は、前記現場造成杭の杭主筋又は固定用フープに対して固定用鉄筋を介して固定し、
前記冷凍管に低温液化ガスを注入するための冷媒管を前記余盛コンクリート部分の上部に立ち上げてあること
を特徴とする杭頭処理工法。
This is a pile head treatment method in which the surplus concrete part of the on-site pile is frozen and expanded by freezing and expanding a refrigeration pipe buried in the concrete in advance to generate cracks, and the cracked part is removed as a boundary.
The freezing pipe is fixed to the pile main bar or the fixing hoop of the on-site construction pile via the fixing reinforcing bar.
A pile head treatment method characterized in that a refrigerant pipe for injecting a low-temperature liquefied gas into the freezing pipe is set up above the surplus concrete portion.
前記冷凍管は、前記固定用鉄筋の一端部を前記余盛コンクリート部分の前記杭主筋又は前記固定用フープに固定してあること
を特徴とする請求項1に記載の杭頭処理工法。
The pile head treatment method according to claim 1, wherein the freezing pipe has one end of the fixing reinforcing bar fixed to the pile main bar of the surplus concrete portion or the fixing hoop.
前記現場造成杭の直径が1200mm以下の小径杭の場合は、1本の前記冷凍管を前記杭主筋又は前記固定用フープに対して前記固定用鉄筋を介して固定してあること
を特徴とする請求項1に記載の杭頭処理工法。
In the case of a small-diameter pile having a diameter of 1200 mm or less, one of the refrigerating pipes is fixed to the pile main bar or the fixing hoop via the fixing reinforcing bar. The pile head treatment method according to claim 1.
現場造成杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、
前記冷凍管は、前記現場造成杭の杭主筋又は固定用フープに対して固定用鉄筋を介して固定し、
前記杭主筋には、前記余盛コンクリート部分との縁切り材としてシースを取り付けてあること
を特徴とする杭頭処理工法。
This is a pile head treatment method in which the surplus concrete part of the on-site pile is frozen and expanded by freezing and expanding a refrigeration pipe buried in the concrete in advance to generate cracks, and the cracked part is removed as a boundary.
The freezing pipe is fixed to the pile main bar or the fixing hoop of the on-site construction pile via the fixing reinforcing bar.
A pile head treatment method characterized in that a sheath is attached to the pile main bar as an edge cutting material with the surplus concrete portion.
現場造成杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、
前記冷凍管は、前記現場造成杭の内側で、かつ杭主筋と固定用フープとからなる鉄筋かごの外側の設置位置に設置してあること
を特徴とする杭頭処理工法。
This is a pile head treatment method in which the surplus concrete part of the on-site pile is frozen and expanded by freezing and expanding a refrigeration pipe buried in the concrete in advance to generate cracks, and the cracked part is removed as a boundary.
A pile head treatment method characterized in that the freezing pipe is installed at an installation position inside the on-site construction pile and outside a reinforcing bar cage composed of a pile main bar and a fixing hoop.
鋼管コンクリート杭の余盛コンクリート部分を、予めコンクリート中に埋設させた冷凍管を凍結膨張させてひび割れを発生させ、そのひび割れ部分を境にして撤去する杭頭処理工法であって、
前記冷凍管は、前記鋼管コンクリート杭の内側に仮設鉄筋を固定し、該仮設鉄筋に対して前記固定用鉄筋を介して固定してあること
を特徴とする杭頭処理工法。
This is a pile head treatment method in which the surplus concrete part of a steel pipe concrete pile is frozen and expanded by freezing and expanding a refrigerated pipe buried in the concrete in advance to generate cracks, and the cracked part is removed as a boundary.
The freezing pipe is a pile head treatment method characterized in that a temporary reinforcing bar is fixed inside the steel pipe concrete pile and fixed to the temporary reinforcing bar via the fixing reinforcing bar.
JP2020044003A 2020-03-13 2020-03-13 Pile head treatment method Pending JP2021143547A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020044003A JP2021143547A (en) 2020-03-13 2020-03-13 Pile head treatment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020044003A JP2021143547A (en) 2020-03-13 2020-03-13 Pile head treatment method

Publications (1)

Publication Number Publication Date
JP2021143547A true JP2021143547A (en) 2021-09-24

Family

ID=77766078

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020044003A Pending JP2021143547A (en) 2020-03-13 2020-03-13 Pile head treatment method

Country Status (1)

Country Link
JP (1) JP2021143547A (en)

Similar Documents

Publication Publication Date Title
CN107059903B (en) Bottom plate plugging dewatering well construction method is worn in foundation pit
CN105927234A (en) Construction method for reinforcing and excavating horizontal tunnel by multi-vertical-shaft freezing method
JP2017122354A (en) Construction method of freezing pipe
JP2021143547A (en) Pile head treatment method
JP2019108766A (en) Maintenance method of frozen soil and construction method of frozen soil
JP2011169057A (en) Method of constructing vertical shaft
CN106812131A (en) A kind of permanent sheet pile underground structure and its construction method
CN206513380U (en) A kind of tunnel double-lining vault with rubber seal reserves Grouting Pipe
JP2020037808A (en) Method of constructing vertical shaft
CN206157860U (en) Drainage pipeline
RU2157872C2 (en) Mechanical design of cooled fill footing of structures and method for temperature control of permafrost soils
JPH03257298A (en) Construction method of large-depth large-scale underground space by ground freezing method and ground freezing pipe therefor
JP2007154635A (en) Tunnel repairing method no. 2
JP2003055958A (en) Water sealing structure of joint for steel pipe pile, and construction method thereof
RU2720893C1 (en) Development method of repair trench for replacement of defect section of pipeline
KR100217845B1 (en) Construction process of underground structure
JPS5953994B2 (en) Underground tank construction method
RU2552253C1 (en) Method of arrangement of foundation slab on piles for low-temperature product tank
JP4214033B2 (en) Construction method of shaft
JP3926804B2 (en) Bottom water stop method in open caisson method.
JP2006112065A (en) Element pipe, bulkhead, and construction method for bulkhead
JP6475553B2 (en) Pile head processing method and frozen crushing pipe
JP2016027226A (en) Underground continuous wall water-stop structure and method
JP6751001B2 (en) Construction method of thermal resistance material for PC ground tank
JP2009068203A (en) Earth retaining wall composed of horizontal sheathing with soldier beam, and cut-off structure, construction method and cut-off method for the earth retaining wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230126

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230926

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230929

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231122

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20240109