JP2019127737A - Junction structure of highest floor and junction method of joint part of highest floor - Google Patents

Junction structure of highest floor and junction method of joint part of highest floor Download PDF

Info

Publication number
JP2019127737A
JP2019127737A JP2018009632A JP2018009632A JP2019127737A JP 2019127737 A JP2019127737 A JP 2019127737A JP 2018009632 A JP2018009632 A JP 2018009632A JP 2018009632 A JP2018009632 A JP 2018009632A JP 2019127737 A JP2019127737 A JP 2019127737A
Authority
JP
Japan
Prior art keywords
column
concrete
fixing
steel
flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2018009632A
Other languages
Japanese (ja)
Other versions
JP7200478B2 (en
Inventor
彩夏 鈴木
Ayaka Suzuki
彩夏 鈴木
安彦 増田
Yasuhiko Masuda
安彦 増田
拓也 穴吹
Takuya Anabuki
拓也 穴吹
一晃 水越
Kazuaki Mizukoshi
一晃 水越
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2018009632A priority Critical patent/JP7200478B2/en
Publication of JP2019127737A publication Critical patent/JP2019127737A/en
Priority to JP2022102776A priority patent/JP7384241B2/en
Application granted granted Critical
Publication of JP7200478B2 publication Critical patent/JP7200478B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

To provide a junction structure of a highest floor and a junction method of a joint part of the highest floor capable of improving workability.SOLUTION: A junction structure 10 of a highest floor is provided with a steel concrete column 20 configured to embed steel bars in concrete 25 and a steel beam 30. The steel beam 30 is configured by intersecting two H-shaped steels 31, 35 perpendicular to each other. The H-shaped steels 31, 35 are provided with webs 32, 37, upper flanges 33, 38, and lower flanges 34, 39. A cover plates 17 is welded on the H-shaped steels 31, 35 to surround the column 20 at a joint part. Each of steel bars of the column 20 is composed of a main girder 21, fixation metal members 22 attached on an upper end surface of the main girder 21, and hoop reinforcements 23 positioned below the steel beam 30. The steel bars are arranged in a way that the upper surfaces of the fixation members 22 making upper end surface of the steel bars are placed between the upper flanges 33, 38 and the lower flanges 34, 39.SELECTED DRAWING: Figure 1

Description

本発明は、鉄筋コンクリート造の柱と鉄骨造の梁とを備えた最上階の接合構造及び最上階の仕口部の接合方法に関する。   The present invention relates to a joint structure of a top floor provided with a reinforced concrete column and a steel frame beam and a joint method of a junction of the top floor.

鉄筋コンクリート造の柱(RC柱)と、鉄骨の梁(S梁)とを用いた混合構造を用いることがある。この構造では、圧縮に強い鉄筋コンクリートを柱に使用し、曲げとせん断に強く軽量な鉄骨を梁に使用する。この構造は、倉庫やショッピングセンター等、ロングスパン構造物に適する。   A mixed structure using a reinforced concrete column (RC column) and a steel beam (S beam) may be used. In this structure, a reinforced concrete with high compression resistance is used for the columns, and a lightweight steel frame with high strength for bending and shear is used for the beams. This structure is suitable for long span structures such as warehouses and shopping centers.

このような混合構造は、最上階においても行なわれる。柱主筋の定着方法として、機械式定着金物を用いた定着工法を採用した場合、通常、最上階においては、柱に埋設される鉄筋の上端部を、鉄骨梁の上面よりも上に突出させた外定着形式が採用される(例えば、非特許文献1参照。)。この非特許文献1には、RC柱とS梁とを用いた混合構造において、柱の主筋の定着長さ(設計的に必要な定着長さ)が記載されている。この非特許文献1では、設計的に必要な定着長さとして、鉄筋の直径dの21倍以上、かつ、下記の(1)式の必要定着長さlab以上とされている。
lab=α・S・σ・d/(10f) (mm) …(1)
Such a mixed structure is also performed on the top floor. When a fixing method using a mechanical fixing metal is adopted as a fixing method of the column main bars, the upper end of the reinforcing bar embedded in the column is usually protruded above the upper surface of the steel frame beam on the uppermost floor The external fixing type is adopted (see, for example, Non-Patent Document 1). This Non-Patent Document 1 describes the fixing length (fixing length necessary for design) of a main bar of a column in a mixed structure using RC columns and S beams. In the non-patent document 1, as a design to fix the required length, or 21 times the diameter d b of the reinforcing bars, and are with the following equation (1) requires fixing length l ab more.
l ab = α · S · σ t · d b / (10f b) (mm) ... (1)

ここで、αは、柱梁接合部コアの拘束度合いの影響係数であり、ふさぎ板形式の場合「1.0」である。Sは修正係数で「0.7」である。σは、仕口面での柱主筋の引張応力で、原則として、短期引張許容応力度(N/mm)である。dは、柱主筋直径(mm)である。fは、付着割裂の基準となる強度(付着割裂基準強度)で、f=(F/40)+0.9(N/mm)である。この式において、Fは、コンクリートの設計基準強度(N/mm)である。 Here, α is an influence coefficient of the degree of restraint of the beam-to-column joint core, and is “1.0” in the case of the blind plate type. S is a correction coefficient "0.7". σ t is a tensile stress of a column main bar at a connection surface, and in principle, is a short-term allowable tensile stress (N / mm 2 ). d b is the column main bar diameter (mm). f b is the strength that serves as a reference for adhesion splitting (adhesion splitting reference strength), and f b = (F c /40)+0.9 (N / mm 2 ). In this formula, F c is the design standard strength (N / mm 2 ) of concrete.

図6は、従来の外定着形式の接合構造50を示している。この接合構造50では、鉄筋コンクリート造の柱60と、鉄骨梁70とを備える。鉄骨梁70は、2つのH形鋼71,75を交差して構成される。柱60は、垂直方向に延在する主筋61と、フープ筋63と、これらを埋設するコンクリート65とを備える。主筋61の上端部は、鉄骨梁70の上面よりも上に突出する。そして、この上端部には、定着金物62が設けられている。更に、定着金物62と鉄骨梁70との間には、定着部拘束筋64が配置されており、仕口部の柱60を囲むようにふさぎ板57が配置されている。この構成によって、定着金物62の位置において、主筋61に生じる引張力、コンクリート圧縮ストラットの圧縮力、定着部拘束筋64に生じる引張力の釣り合いにより、抵抗機構を形成する。   FIG. 6 shows a conventional external fixing type joining structure 50. The joint structure 50 includes a reinforced concrete column 60 and a steel frame beam 70. The steel frame beam 70 is configured by intersecting two H-shaped steels 71 and 75. The column 60 includes a vertically extending main bar 61, a hoop bar 63, and concrete 65 in which these are embedded. The upper end portion of the main reinforcement bar 61 projects above the upper surface of the steel frame beam 70. A fixing metal 62 is provided at the upper end. Further, between the anchor metal 62 and the steel frame beam 70, an anchor portion restraint muscle 64 is disposed, and a closing plate 57 is disposed so as to surround the column 60 of the connection portion. With this configuration, the resistance mechanism is formed at the position of the anchor metal 62 by balancing the tensile force generated in the main bar 61, the compressive force of the concrete compression strut, and the tensile force generated in the anchor portion restraint bar 64.

例えば、柱60の主筋61の直径dを22(mm)、柱主筋の引張応力σを516(N/mm)とする。そして、コンクリート強度及び付着割裂基準強度を表1に示す値にした3つの接合構造50(Tc1、Tc2,Tc3)について、非特許文献1における必要定着長さlabを算出すると、表1に示す値になる。 For example, the diameter d b of the main bar 61 of the column 60 is 22 (mm), and the tensile stress σ t of the column main bar is 516 (N / mm 2 ). The concrete strength and Bond Splitting reference intensity three junction structures to the values shown in Table 1 50 (Tc1, Tc2, Tc3 ) for, when calculating the necessary fixing length l ab in Non-Patent Document 1, are shown in Table 1 It becomes a value.

また、外定着形式の接合構造50において、定着部拘束筋64に異形鉄筋D13を用いて、定着部拘束筋64が2段設けられている場合、鉄骨梁70から定着金物62の内面までの定着拘束筋高さは、最小で28(mm)になる。ここで、各接合構造50(Tc1、Tc2,Tc3)の梁せいD0が、「450」、「400」、「350」(mm)の場合、外定着形式から算出される鉄筋の長さは、梁せいD0と定着拘束筋高さとの和であるため、「478」、「428」、「378」(mm)になる。   Further, in the outer fixing type joint structure 50, when the fixing portion restraining bar 64 is provided in two stages using the deformed reinforcing bar D13, the fixing from the steel beam 70 to the inner surface of the fixing hardware 62 is performed. The height of the restraint muscle is 28 (mm) at the minimum. Here, when the beam height D0 of each joint structure 50 (Tc1, Tc2, Tc3) is “450”, “400”, “350” (mm), the length of the rebar calculated from the external fixing form is Since it is the sum of the beam height D0 and the anchorage restraint muscle height, it becomes “478”, “428”, “378” (mm).

従来では、設計的に必要な定着長さ(鉄筋の直径dの21倍以上、かつ、(1)式の必要定着長さlab以上)と、外定着形式から算出される定着長さとのうち、長いほうを定着長さL0として用いる。各接合構造50(Tc1、Tc2,Tc3)においては、必要定着長さlabが外定着形式から算出される長さより長いため、必要定着長さlabを定着長さL0として用いる。 Conventionally, designed to fix the required length (more than 21 times the diameter d b of the reinforcing bars, and, (1) require fixing or length l ab of expression) and, with the fixing length is calculated from the outer fixing format The longer one is used as the fixing length L0. In each junction structure 50 (Tc1, Tc2, Tc3) , necessary fixing length l ab is longer than the length which is calculated from the outer fixing format, using the necessary fixing length l ab as the fixing length L0.

更に、上述した外定着形式の接合構造50の場合、定着部拘束筋64を配置するために、鉄骨梁70よりも上に突出する定着金物62を配置する。この定着金物62は、柱60を構成する部材のため、コンクリートに埋設させる必要がある。このコンクリートも柱60を構成するため、このコンクリートには、柱60のコンクリート強度のコンクリートが用いられる。従って、柱60に用いるコンクリート65の強度と、床等のスラブ55に用いるコンクリートの強度とが異なる場合には、低強度のコンクリートが高強度コンクリートの打設領域に流入しないようにして、仕口部の上のコンクリート65aと、その他の領域のスラブ55とを打ち分ける。   Furthermore, in the case of the above-described external fixing type joint structure 50, the fixing hardware 62 protruding above the steel beam 70 is disposed in order to dispose the fixing portion restraining bars 64. The anchor metal 62 needs to be embedded in concrete because it is a member constituting the pillar 60. Since this concrete also constitutes the column 60, concrete of the concrete strength of the column 60 is used for this concrete. Therefore, when the strength of the concrete 65 used for the column 60 and the strength of the concrete used for the slab 55 such as a floor are different, the low strength concrete is prevented from flowing into the high strength concrete casting area, and the connection is made. The concrete 65a on the part and the slab 55 in the other area are separated.

このコンクリートを打ち分けるための構造も検討されている(例えば、特許文献1参照。)。特許文献1においては、RC柱とS梁との仕口部に、鉄骨梁の梁せいと同じ高さ寸法に形成されるふさぎ板を設ける。鉄骨梁及びふさぎ板の上端部には、断面形状がL字型の鋼材を接合する。   A structure for striking the concrete is also being studied (see, for example, Patent Document 1). In patent document 1, the connection board part of RC column and S beam is provided with the blind board formed in the same height dimension as the beam of a steel frame beam. At the upper end of the steel frame beam and the closing plate, a steel material having an L-shaped cross section is joined.

特開2013−2140号公報JP, 2013-2140, A

一般社団法人建築構造技術支援機構 著、「SABTEC機械式定着工法 RCS混合構造設計指針(2017年)」、第1版、2017年10月11日、p29、p39、p40Building Construction Technology Support Organization, "SABTEC Mechanical Fixation Method RCS Mixed Structure Design Guideline (2017)", 1st edition, October 11, 2017, p29, p39, p40

最上階において仕口部の上のコンクリート65aと、その他の領域のスラブ55とを打ち分ける場合、柱60の上部を囲むようにラス型枠54を設け、仕口部の上のコンクリート65aとスラブ55とを別々に打設するので、施工に手間が掛かる。また、完成後、コンクリートを打ち分けた部分で色が異なる場合もあった。更に、スラブ55のスラブ高さに柱60の主筋61、定着金物62、定着部拘束筋64が突出するため、これらを避けてスラブ55の配筋を行なう必要があり、手間が掛かっていた。ここで、スラブ55のスラブ筋をラス型枠54に貫通させる場合には、更に手間が掛かっていた。   When the concrete 65a above the joint portion and the slab 55 in other regions are separated on the top floor, a lath mold 54 is provided so as to surround the upper part of the column 60, and the concrete 65a and slab above the joint portion are provided. Since 55 is separately installed, it takes time for construction. In addition, after completion, there was also a case where the color was different in the part which beats the concrete. Furthermore, since the main reinforcement 61 of the column 60, the fixing hardware 62, and the fixing portion restraining reinforcement 64 protrude at the slab height of the slab 55, it is necessary to arrange the slab 55 while avoiding these, which takes time. Here, in the case where the slab line of the slab 55 is to be penetrated by the glass form 54, it takes more time.

また、建物によっては、柱60に埋設される鉄筋の定着長さが、鉄骨梁70の梁せいD0より小さいこともある。この場合においても、外定着形式の構造では、鉄骨梁70の上に鉄筋を突出させる必要があり、鉄筋を長くする必要があった。   Further, depending on the building, the fixing length of the reinforcing bar embedded in the column 60 may be smaller than the beam length D0 of the steel frame beam 70. Also in this case, in the structure of the external fixation type, it is necessary to project the rebar over the steel frame beam 70, and it is necessary to lengthen the rebar.

上記課題を解決するための最上階の接合構造は、鉄筋コンクリート造の柱と、上側フランジ及び下側フランジを有した鉄骨梁とを備えた最上階の接合構造であって、前記上側フランジ及び前記下側フランジに接触させた前記柱を囲むふさぎ板を設け、前記柱の主筋の上端部には定着金物が取り付けられており、前記主筋の上端面又は前記定着金物の上端面の高さ方向の位置を、前記上側フランジと前記下側フランジとの間に設けた。   The joint structure on the uppermost floor for solving the above-mentioned problem is a joint structure on the uppermost floor comprising a reinforced concrete column and a steel beam having an upper flange and a lower flange, wherein the upper flange and the lower floor A cover plate surrounding the column in contact with the side flange is provided, and a fixing metal is attached to the upper end portion of the main bar of the column, and the height direction position of the upper end surface of the main bar or the upper end surface of the fixing metal Was provided between the upper flange and the lower flange.

更に、上記課題を解決するための最上階の仕口部の接合方法は、鉄筋コンクリート造の柱と、上側フランジ及び下側フランジを有した鉄骨梁とを備え、前記柱の主筋の上端部には定着金物が取り付けられた最上階の仕口部の接合方法であって、前記主筋の上端面又は前記定着金物の上端面の高さ方向の位置を、前記上側フランジと前記下側フランジとの間に設けた状態で、前記上側フランジ及び前記下側フランジに接触するふさぎ板を配置し、前記ふさぎ板内にコンクリートを打設し、前記上側フランジ及び前記柱の上に、スラブコンクリートを打設する。   Further, the method for joining the joints on the uppermost floor for solving the above-mentioned problem includes a reinforced concrete column and a steel beam having an upper flange and a lower flange, and the upper end of the main bar of the column A method of joining a joint portion of a top floor to which a fixing hardware is attached, wherein the position in the height direction of the upper end surface of the main reinforcement or the upper end surface of the fixing metal is between the upper flange and the lower flange. In this state, a cover plate that contacts the upper flange and the lower flange is disposed, concrete is placed in the cover plate, and slab concrete is placed on the upper flange and the column. .

本発明によれば、最上階の接合構造の施工性を向上させることができる。   According to the present invention, the workability of the joint structure on the top floor can be improved.

実施形態における最上階の接合構造を示す図であり、(a)は上面図、(b)は正面断面図。It is a figure which shows the joining structure of the top floor in embodiment, (a) is a top view, (b) is front sectional drawing. 実施形態における最上階の接合構造の斜視図。The perspective view of the junction structure of the uppermost floor in embodiment. 実施形態における実験を説明する説明図であって、(a)は実験に用いた接合構造の全体を説明する図、(b)は各試験体の諸元値を説明する図。It is explanatory drawing explaining the experiment in embodiment, Comprising: (a) is a figure explaining the whole joining structure used for experiment, (b) is a figure explaining the specification value of each test body. 実施形態における実験結果における柱せん断力の変化の説明図であり、(a)は試験体T1、(b)は試験体T2、(c)は試験体T3の場合を示す。It is explanatory drawing of the change of the column shear force in the experimental result in embodiment, (a) is test body T1, (b) shows test body T2, (c) shows the case of test body T3. 変更例における最上階の接合構造を示す図であり、(a)は第1変更例の正面図、(b)は(a)の要部斜視図、(c)は第2変更例の正面図、(d)は(c)の要部斜視図。It is a figure which shows the bonded structure of the top floor in a modification, (a) is a front view of a 1st modification, (b) is a principal part perspective view of (a), (c) is a front view of a 2nd modification (D) is a principal part perspective view of (c). 従来技術における最上階の接合構造を示す正面断面図。Front sectional drawing which shows the joining structure of the top floor in a prior art.

以下、図1〜図4を用いて、最上階の接合構造及び最上階の仕口部の接合方法を具体化した一実施形態を説明する。
図1(a)は、本実施形態の最上階の接合構造10の上面図、図1(b)は、接合構造10の正面断面図、図2は、接合構造10の斜視図である。図面を見やすくするために、図1(a)及び図2では、上部のスラブ15を省略し、図1(b)では、柱20のコンクリート25及びスラブ15の断面ハッチングを省略している。
Hereinafter, one embodiment which materialized the joining structure of the top floor and the junction method of the top floor junction part is explained using Drawings 1-4.
1A is a top view of the bonding structure 10 on the uppermost floor of the present embodiment, FIG. 1B is a front sectional view of the bonding structure 10, and FIG. 2 is a perspective view of the bonding structure 10. In order to make the drawing easy to see, the upper slab 15 is omitted in FIGS. 1A and 2 and the cross-sectional hatching of the concrete 25 of the pillar 20 and the slab 15 is omitted in FIG. 1B.

図1及び図2に示すように、接合構造10は、鉄筋コンクリート造の柱20に、鉄骨梁30が取り付けられた仕口部の構造である。具体的には、この接合構造10では、柱20の柱頭部(上端部)に、鉄骨梁30の一部が埋め込まれることにより、鉄骨梁30が取り付けられて構成される。   As shown in FIG. 1 and FIG. 2, the joint structure 10 is a structure of a connecting portion in which a steel frame beam 30 is attached to a reinforced concrete column 20. Specifically, in the joint structure 10, a part of the steel frame beam 30 is embedded in the column top (upper end) of the column 20, whereby the steel frame beam 30 is attached and configured.

図1(b)に示すように、柱20及び鉄骨梁30の上には、スラブ15が形成される。このスラブ15は、鉄筋コンクリートで構成される。
図1及び図2に示すように、鉄骨梁30は、2本のH形鋼31,35を、十字形状に、直角に交差して構成される。H形鋼31,35は、ウェブ32,37と、上側フランジ33,38と、下側フランジ34,39とを備える。上側フランジ33,38及び下側フランジ34,39は、それぞれウェブ32,37で接続される。
更に、H形鋼31,35には、ふさぎ板17が溶接されている。このふさぎ板17は、仕口部における柱20を囲むように配置される。
As shown in FIG. 1 (b), a slab 15 is formed on the column 20 and the steel frame beam 30. The slab 15 is made of reinforced concrete.
As shown in FIG. 1 and FIG. 2, the steel frame beam 30 is configured by intersecting two H-shaped steels 31 and 35 at right angles in a cross shape. The H-section steels 31, 35 comprise webs 32, 37, upper flanges 33, 38 and lower flanges 34, 39. The upper flanges 33, 38 and the lower flanges 34, 39 are connected by webs 32, 37 respectively.
Furthermore, a closing plate 17 is welded to the H-shaped steels 31 and 35. The cover plate 17 is disposed so as to surround the column 20 in the connection portion.

柱20のコンクリート25には、垂直方向に延在された複数の主筋21が埋設されている。鉄骨梁30よりも下方の主筋21には、主筋21を囲むようにフープ筋23が取り付けられている。   In the concrete 25 of the column 20, a plurality of vertically extending main bars 21 are embedded. A hoop muscle 23 is attached to the main muscle 21 below the steel frame 30 so as to surround the main muscle 21.

各主筋21の上端部には、定着金物22が取り付けられる。この定着金物22は、鉄筋を挿し込むための略円筒形状の下部と、これに一体化された円板形状の上部とを有する。ここで、定着金物22の上端面が、柱20に埋設される鉄筋の上端面となる。   A fixing hardware 22 is attached to the upper end portion of each main bar 21. The anchor metal 22 has a substantially cylindrical lower portion for inserting a reinforcing bar, and a disk-shaped upper portion integrated with the lower portion. Here, the upper end surface of the anchor metal 22 is the upper end surface of the reinforcing bar embedded in the column 20.

定着金物22の上端面の高さ方向の位置は、鉄骨梁30の上側フランジ33,38と下側フランジ34,39との間に設けられる。具体的には、定着金物22の上端面は、上側フランジ33,38の下面よりも下に位置し、下側フランジ34,39の上面よりも上に位置する。ここで、鉄骨梁30の下側フランジ34,39の底面から鉄筋の上端面までの定着長さL1は、力学的に必要な定着長さとする。   The position in the height direction of the upper end surface of the anchor metal 22 is provided between the upper flanges 33 and 38 and the lower flanges 34 and 39 of the steel frame beam 30. Specifically, the upper end surface of the anchor metal 22 is located below the lower surface of the upper flanges 33, 38 and above the upper surface of the lower flanges 34, 39. Here, the fixing length L1 from the bottom surface of the lower flanges 34 and 39 of the steel frame beam 30 to the upper end surface of the reinforcing bar is set as the fixing length necessary mechanically.

<力学的に必要な定着長さ>
力学的に必要な定着長さとは、柱20の主筋21が降伏する前に、柱20のせん断力が低下することを防ぐために必要な長さである。この必要な定着長さは、主筋21の直径、コンクリート25の強度、定着金物22の円板部の大きさ等によって特定される。
<Fixing length required mechanically>
The mechanically necessary fixing length is a length necessary to prevent the shearing force of the column 20 from being lowered before the main bar 21 of the column 20 yields. The necessary fixing length is specified by the diameter of the main bar 21, the strength of the concrete 25, the size of the disc portion of the fixing metal 22, and the like.

従来では、力学的に必要な定着長さは、非特許文献1の(1)式に記載の設計的に必要な定着長さと同じとして、設計的に必要な定着長さを用いて算出していた。しかしながら、(1)式で算出した長さよりも短くても、柱20のせん断力が低下することなく、柱20の主筋21が降伏する長さであれば、必要な定着長さとして用いることができる。   Conventionally, the fixing length required mechanically is calculated using the fixing length necessary for design, assuming that it is the same as the fixing length required for design described in equation (1) of Non-Patent Document 1 The However, even if the length is shorter than the length calculated by the equation (1), the shear strength of the column 20 is not reduced, and if the main bar 21 of the column 20 yields, it can be used as a necessary fixing length it can.

そこで、具体的な必要な定着長さについて、柱20にせん断力を与えて実験を行なった。ここでは、鉄筋の定着長さL1や柱20のコンクリート25の強度を変更した試験体を用いた。   Then, the shear force was given to the column 20 about a concrete required fixing length, and it experimented. Here, a test body is used in which the fixing length L1 of the reinforcing bar and the strength of the concrete 25 of the column 20 are changed.

図3(a)には、実験に用いた接合構造10を示している。この接合構造10の鉄骨梁30は、全長Lb1が3450(mm)である。鉄骨梁30の両端は回転端で支持する。柱せん断力は、柱20の下端部に加える。この柱20の下端部から、鉄骨梁30のウェブの中央の水平面までの高さH1は、1200(mm)とした。   FIG. 3A shows the bonding structure 10 used in the experiment. The steel frame beam 30 of the joint structure 10 has a total length Lb1 of 3450 (mm). Both ends of the steel beam 30 are supported by rotation ends. The column shear force is applied to the lower end of the column 20. The height H1 from the lower end of the column 20 to the horizontal plane at the center of the web of the steel frame beam 30 was 1200 (mm).

図3(b)には、各試験体T1,T2,T3の諸元値を示している。試験体T1,T2,T3において、定着長さL1以外の諸元値は、従来技術の各接合構造50(Tc1、Tc2,Tc3)に対応している。試験体T1,T2,T3の梁せいD1は、それぞれ「450」、「400」、「350」(mm)である。試験体T1,T2,T3のコンクリート(目標)強度は、それぞれ「27」、「36」、「45」(N/mm)である。各試験体T1,T2,T3に用いた主筋21の直径dは、いずれも同じく22(mm)である。ここで、各試験体T1,T2,T3の定着長さL1を、それぞれ「396」、「352」、「308」(mm)と、主筋21の直径dの18倍、16倍、14倍とした。 FIG. 3 (b) shows specification values of each of the test specimens T1, T2 and T3. In the test specimens T1, T2, and T3, the specification values other than the fixing length L1 correspond to the respective joining structures 50 (Tc1, Tc2, and Tc3) of the prior art. Beam heights D1 of the test bodies T1, T2, and T3 are “450”, “400”, and “350” (mm), respectively. The concrete (target) strengths of the test bodies T1, T2 and T3 are “27”, “36” and “45” (N / mm 2 ), respectively. The diameter d b of the main reinforcement 21 used for each of the test bodies T1, T2 and T3 is 22 mm in the same manner. Here, the fixing length L1 of each of the test bodies T1, T2 and T3 is “396”, “352”, “308” (mm) and 18 times, 16 times, 14 times the diameter d b of the main muscle 21 respectively. And

図4(a)〜(c)には、実験による各試験体T1,T2,T3の層間変形角(%)と柱せん断力(kN)との関係グラフを示している。図4における白抜き四角形が、柱20の主筋21が降伏した点を表す。柱20における鉄筋の定着力が十分でない場合、主筋21が降伏する前に抜け出してしまい、柱20のせん断力の低下を生じると考えられる。しかし、図4(a)〜(c)に示すように、いずれの試験体T1,T2,T3においても、主筋21が降伏するまでせん断力は低下しなかった。従って、実験で用いた各試験体T1,T2,T3の定着長さL1は、力学的に必要な定着長さとして用いることができる。よって、柱20に埋設した鉄筋の上端面を、鉄骨梁30の上側フランジ33,38よりも下にしても、従来と同等の性能を得ることは可能と考えられる。   FIGS. 4 (a) to 4 (c) show relationship graphs between the interlayer deformation angle (%) and the column shear force (kN) of each of the test specimens T1, T2 and T3 by experiments. An open square in FIG. 4 represents a point at which the main bar 21 of the column 20 has yielded. When the fixing strength of the reinforcing bars in the column 20 is not sufficient, it is considered that the main bars 21 come out before yielding, and the shearing force of the columns 20 is reduced. However, as shown in FIGS. 4A to 4C, in any of the test bodies T1, T2, and T3, the shear force did not decrease until the main bar 21 yields. Therefore, the fixing length L1 of each of the test specimens T1, T2 and T3 used in the experiment can be used as the mechanically required fixing length. Therefore, even if the upper end surface of the reinforcing bar embedded in the column 20 is below the upper flanges 33 and 38 of the steel beam 30, it is considered possible to obtain the same performance as the conventional one.

<接合方法>
次に、図1及び図2を用いて、上述した接合構造10の接合方法について説明する。この場合においても、最上階の下層までは、従来と同様に構成する。
<Joining method>
Next, a method of bonding the above-described bonding structure 10 will be described using FIGS. 1 and 2. Also in this case, the lower layer of the top floor is configured in the same manner as in the prior art.

そして、下層階から立ち上げた複数の主筋21にフープ筋23を取り付け、主筋21上端に定着金物22を取り付けて、先組み鉄筋を準備する。そして、この先組み鉄筋を、柱20を構築する空間内に設置する。   Then, hoop reinforcements 23 are attached to the plurality of main reinforcements 21 raised from the lower floor, and the fixing hardware 22 is attached to the upper ends of the main reinforcement 21 to prepare a pre-assembled reinforcement. Then, this pre-assembled reinforcing bar is placed in the space where the pillar 20 is to be constructed.

そして、柱20を構築する予定の空間であって鉄骨梁30より下方の部分を囲むように、コンクリート用の型枠を配置する。そして、仕口部の部分には、ふさぎ板17を取り付けた鉄骨梁30を配置する。そして、ふさぎ板17を仕口部のコンクリートの型枠として用いて、鉄骨梁30の下方の柱20のコンクリートと、ふさぎ板17の内部のコンクリートとを、一緒に打設する。この場合、先組み鉄筋の上端面は、コンクリート内に埋設される。なお、鉄骨梁30の下方の柱20のコンクリートを打設した後、ふさぎ板17の内部のコンクリートを打設してもよい。   Then, a concrete formwork is arranged so as to surround a portion below the steel beam 30 in a space where the pillar 20 is to be constructed. And the steel frame beam 30 which attached the closing board 17 is arrange | positioned in the part of a connection part. Then, using the closing plate 17 as a concrete form of the connection, the concrete of the column 20 below the steel frame beam 30 and the concrete inside the closing plate 17 are cast together. In this case, the upper end surface of the pre-assembled reinforcing bar is embedded in concrete. In addition, after placing the concrete of the pillar 20 below the steel beam 30, the concrete inside the cover plate 17 may be placed.

その後、スラブ15を構築する。具体的には、柱20及び鉄骨梁30の上に、デッキプレートを配置する。そして、このデッキプレートの上に、スラブ筋を配筋して、コンクリートを打設する。   Thereafter, the slab 15 is constructed. Specifically, a deck plate is disposed on the columns 20 and the steel frame beams 30. And a slab line is arranged on this deck plate, and concrete is poured.

本実施形態によれば、以下のような効果を得ることができる。
(1)本実施形態の接合構造10では、鉄筋コンクリート造の柱20を構成する定着金物22(鉄筋)の上端面を、鉄骨梁30の上側フランジ33,38より下方で、下側フランジ34,39より上となるように、鉄筋(主筋21及び定着金物22)を配置する。これにより、柱20の上方のコンクリートを、この周囲の他の領域のスラブのコンクリートと同時期に打設することができる。従って、スラブの配筋の納まりを簡略化でき、施工性及び美観を向上させることができる。また、コンクリートを打ち分けないため、従来、鉄骨梁70の上に配置していたラス型枠54をなくすことができ、施工性を更に向上させることができる。
According to the present embodiment, the following effects can be obtained.
(1) In the joint structure 10 of the present embodiment, the upper end surface of the anchor metal 22 (rebar) constituting the reinforced concrete column 20 is lower than the upper flanges 33 and 38 of the steel frame beam 30 and the lower flanges 34 and 39 Reinforcing bars (main bars 21 and anchors 22) are arranged to be higher. Thereby, the concrete above the pillars 20 can be cast at the same time as the concrete of the slab in the other area around this. Therefore, the placement of the reinforcements of the slab can be simplified, and the workability and the appearance can be improved. In addition, since the concrete is not divided, the lath mold 54 that has been conventionally disposed on the steel beam 70 can be eliminated, and the workability can be further improved.

(2)本実施形態の接合構造10では、柱20に埋設する鉄筋の定着長さL1を、力学的に必要な定着長さ(柱20のせん断力が低下することなく、柱20の主筋21が降伏する長さ)に設定する。柱20に埋設する鉄筋の定着力が十分でない場合には、柱20の主筋21が降伏する前に主筋21がコンクリート25より抜け出す。このため、主筋21が降伏する前に、柱20のせん断力の低下が生じる。しかしながら、非特許文献1に記載の設計的に必要な定着長さよりも短くても、十分な定着力を得ることができ、主筋21が降伏するまで、せん断力の低下を抑制できる。   (2) In the joint structure 10 of the present embodiment, the fixing length L1 of the reinforcing bar embedded in the column 20 is the fixing length that is mechanically required (the shear strength of the column 20 does not decrease, and the main bars 21 of the column 20 Set the length) to yield. If the anchoring strength of the reinforcing bars embedded in the pillars 20 is not sufficient, the main bars 21 slip out of the concrete 25 before the main bars 21 of the pillars 20 yield. For this reason, a reduction in shear force of the column 20 occurs before the main bar 21 yields. However, even if it is shorter than the fixing length necessary for design described in Non-Patent Document 1, sufficient fixing power can be obtained, and a reduction in shear force can be suppressed until the main bar 21 yields.

(3)本実施形態の接合構造10では、鉄骨梁30のH形鋼31,35には、ふさぎ板17が溶接されている。このため、ふさぎ板17が、従来の外定着形式における定着部拘束筋64の役割を代替し、抵抗機構を形成することができる。   (3) In the joint structure 10 of the present embodiment, the blocking plate 17 is welded to the H-shaped steels 31 and 35 of the steel frame beam 30. For this reason, the closing plate 17 can substitute for the role of the fixing portion restraint muscle 64 in the conventional external fixing type, and form a resistance mechanism.

本実施形態は、以下のように変更して実施することができる。本実施形態及び以下の変更例は、技術的に矛盾しない範囲で互いに組み合わせて実施することができる。
・上記実施形態の接合構造10においては、主筋21の上端部に定着金物22を設けた。これに加えて、柱20のコンクリート25において主筋21の付着を向上させるダボ部材を更に設けてもよい。このダボ部材とは、仕口部のコンクリート25が、仕口部の鉄骨梁30から抜け出さないように、コンクリート25と鉄骨梁30との連結を補強する部材である。
The present embodiment can be modified as follows. The present embodiment and the following modifications can be implemented in combination with one another as long as there is no technical contradiction.
In the bonded structure 10 of the above embodiment, the fixing metal 22 is provided at the upper end portion of the main bar 21. In addition to this, a dowel member may be further provided to improve adhesion of the main reinforcement 21 in the concrete 25 of the pillar 20. The dowel member is a member that reinforces the connection between the concrete 25 and the steel frame beam 30 so that the concrete 25 at the joint portion does not slip out of the steel frame beam 30 at the connection part.

具体的には、ダボ部材として、柱20のコンクリート25内において割裂面Lw1よりウェブ37側に一部を配置させた部材を用いてもよい。ここで、割裂面Lw1とは、上側フランジ38の外端部と下側フランジ39の外端部とを結ぶ垂直面である。   Specifically, as the dowel member, a member in which a portion is disposed closer to the web 37 than the split surface Lw1 in the concrete 25 of the column 20 may be used. Here, the split surface Lw1 is a vertical surface connecting the outer end of the upper flange 38 and the outer end of the lower flange 39.

例えば、図5(a)及び図5(b)に示すように、鉄骨梁30のH形鋼35のウェブ37にスタッド41を溶接して設ける。
また、定着金物42の円板形状の上部の一部が、割裂面Lw1よりもウェブ37側に位置させるように、定着金物42の上部を大きくしてもよい。
For example, as shown in FIGS. 5 (a) and 5 (b), a stud 41 is provided by welding to the web 37 of the H-shaped steel 35 of the steel frame beam 30.
Further, the upper part of the fixing metal 42 may be enlarged so that a part of the disk-shaped upper part of the fixing metal 42 is positioned closer to the web 37 than the split surface Lw1.

更に、図5(c)及び図5(d)に示すように、主筋21を貫通させた係止板43を設けてもよい。この係止板43は、割裂面Lw1よりウェブ37側に位置するような大きさにする。   Furthermore, as shown in FIG. 5 (c) and FIG. 5 (d), a locking plate 43 in which the main reinforcement 21 is penetrated may be provided. The locking plate 43 is sized so as to be closer to the web 37 than the split surface Lw1.

また、小型フープ筋44を、主筋21を囲むように配置する。この場合、小型フープ筋44の一部が割裂面Lw1よりもウェブ37側に延在するように、小型フープ筋44を配置する。この小型フープ筋44の代わりに、主筋21を囲むスパイラル形状のフープ筋を設けてもよい。   Further, the small hoop muscle 44 is disposed so as to surround the main muscle 21. In this case, the small hoops 44 are arranged such that a part of the small hoops 44 extends closer to the web 37 than the split surface Lw1. Instead of the small hoops 44, spiral hoops may be provided to surround the main bars 21.

また、H形鋼35のウェブ37に、L字形状部材45を溶接する。このL字形状部材45の一部が、割裂面Lw1より主筋21側に位置するように、L字形状部材45を配置する。   Further, the L-shaped member 45 is welded to the web 37 of the H-shaped steel 35. The L-shaped member 45 is disposed such that a portion of the L-shaped member 45 is positioned closer to the main reinforcement 21 than the split surface Lw1.

更に、図5(a)及び図5(b)に示すように、ダボ部材として、ふさぎ板17に、スタッド46を溶接して設けてもよい。
また、ふさぎ板17のコンクリート25側の面に、突条部47を設けてもよい。突条部47の代わりに、ふさぎ板自体を縞鋼板に変更したり、シアキーとなる丸鋼を溶接したりしてもよい。
更に、ダボ部材として、H形鋼35の下側フランジ39及びふさぎ板17に渡る板形状部材48を設けてもよい。
Further, as shown in FIGS. 5A and 5B, a stud 46 may be welded to the cover plate 17 as a dowel member.
In addition, a protrusion 47 may be provided on the surface of the closing plate 17 on the concrete 25 side. Instead of the projecting portion 47, the closing plate itself may be changed to a striped steel plate, or a round steel serving as a shear key may be welded.
Furthermore, as the dowel member, a plate-shaped member 48 may be provided so as to extend over the lower flange 39 of the H-shaped steel 35 and the covering plate 17.

また、図5(c)及び図5(d)に示すように、ダボ部材として、アンカー鉄筋又はスタッドを溶接した鋼板49を、上側フランジ38とふさぎ板17に渡すように取り付けてもよい。
以上のようなダボ部材を設けることにより、コンクリート25からの主筋21の抜け出しを抑制することができる。
Further, as shown in FIGS. 5C and 5D, a steel plate 49 welded with anchor bars or studs may be attached to the upper flange 38 and the cover plate 17 as a dowel member.
By providing the above-described dowel member, it is possible to suppress the detachment of the main reinforcement 21 from the concrete 25.

・上記実施形態の接合構造10は、鉄骨梁30を構成するH形鋼31,35が直角に交差する部分について用いた。接合構造10は、最上階における接合構造であれば、鉄骨梁30が十字形状に交差した部分に限られない。例えば、T字形状やL字形状に交差した部分(仕口部)の接合構造でもよい。   -The junction structure 10 of the said embodiment was used about the part which the H-section steels 31 and 35 which comprise the steel beam 30 cross | intersect at right angle. The joint structure 10 is not limited to a portion where the steel beam 30 intersects in a cross shape as long as it is a joint structure on the top floor. For example, it may be a joint structure of a portion (connection portion) intersecting with a T-shape or an L-shape.

・上記実施形態において、主筋21の上端部に取り付けた定着金物22は、鉄筋を差し込むための略円筒形状の下部と円板形状の上部とを有する。主筋21に取り付けられる定着金物22は、この形状に限定されない。例えば、定着金物22の形状のように段付き筒形状を有し、この筒形状に主筋21が貫通する定着金物を用いることも可能である。また、異形鉄筋の端部に摩擦圧接したねじに、ねじ込み締め付けにより取り付ける円形定着板を用いることも可能である。これらの定着金物を用いる場合、RC柱のコンクリートに埋設する必要のある鉄筋部分(主筋21、又は定着金物22)の上端面(定着金物の上端面、又は定着金物を貫通した主筋21の上端面)の高さ方向の位置を、上側フランジ33,38と、下側フランジ34,39との間に配置すればよい。   In the embodiment described above, the fixing hardware 22 attached to the upper end portion of the main reinforcement 21 has a substantially cylindrical lower portion for inserting the reinforcing bar and a disk-shaped upper portion. The anchor hardware 22 attached to the main reinforcement 21 is not limited to this shape. For example, it is also possible to use a fixing metal having a stepped cylindrical shape like the shape of the fixing metal 22 and in which the main reinforcement 21 penetrates. In addition, it is also possible to use a circular fixing plate that is attached by screwing to a screw friction-welded to the end of the deformed rebar. When using these fixing hardware, the upper end surface (the upper end surface of the fixing hardware, or the upper end surface of the main reinforcement 21 penetrating the fixing hardware) of the reinforcing bar portion (main reinforcing bar 21 or fixing hardware 22) that must be embedded in the concrete of the RC pillar ) May be disposed between the upper flanges 33 and 38 and the lower flanges 34 and 39.

・上記実施形態の接合構造10では、柱20に埋設する鉄筋の定着長さL1を、力学的に必要な定着長さ(柱20のせん断力が低下することなく、柱20の主筋21が降伏する長さ)に設定する。この力学的に必要な定着長さは、図3(b)に示す試験体T1,T2,T3の具体例では、同図に示した定着長さL1以上でよい。ここで、定着長さL1を更に短くしたい場合は、各試験体T1,T2,T3で用いたコンクリート強度を高くしたり、定着金物22の定着板(上部)の支圧面積を大きくしたりする。これにより、定着金物の上端面、又は定着金物を貫通した主筋21の上端面の高さは、鉄骨梁30の下側フランジ34,39に近づく。   In the joint structure 10 of the above embodiment, the fixing length L1 of the reinforcing bar embedded in the column 20 is the mechanically required fixing length (the main bars 21 of the columns 20 yield without the shear force of the columns 20 decreasing). To the desired length). In the specific example of the test bodies T1, T2, and T3 shown in FIG. 3B, this mechanically necessary fixing length may be equal to or longer than the fixing length L1 shown in FIG. Here, when it is desired to further shorten the fixing length L1, the concrete strength used in each of the test pieces T1, T2 and T3 is increased or the bearing pressure area of the fixing plate (upper part) of the fixing metal 22 is increased. . As a result, the height of the upper end surface of the anchor metal or the upper end surface of the main reinforcement 21 penetrating the anchor metal approaches the lower flanges 34 and 39 of the steel frame beam 30.

H1…高さ、L0,L1…定着長さ、T1,T2,T3…試験体、Lb1…全長、Lw1…割裂面、10,50…接合構造、15,55…スラブ、17…ふさぎ板、20,60…柱、21,61…主筋、22,42,62…定着金物、23,63…フープ筋、25,65,65a…コンクリート、30,70…鉄骨梁、31,35,71,75…H形鋼、32,37…ウェブ、33,38…上側フランジ、34,39…下側フランジ、41,46…スタッド、突条部、43…係止板,44…小型フープ筋、45…L字形状部材、47…突条部、48…板形状部材、49…鋼板、54…ラス型枠、64…定着部拘束筋。   H1, height, L0, L1 ... fixing length, T1, T2, T3 ... test body, Lb1 ... full length, Lw1 ... split surface, 10,50 ... joining structure, 15,55 ... slab, 17 ... sleeve plate, 20 , 60 ... pillars 21, 21 ... main bars 22, 22, 62 ... anchorage metal, 23, 63 ... hoop bars, 25, 65, 65 a ... concrete, 30, 70 ... steel beam, 31, 35, 71, 75 ... H-shaped steel, 32, 37 ... web, 33, 38 ... upper flange, 34, 39 ... lower flange, 41, 46 ... stud, projecting part, 43 ... locking plate, 44 ... small hoop bar, 45 ... L Shaped members, 47: ridges, 48: plate-shaped members, 49: steel plates, 54: ras form, 64: fixing portion restraint bars.

Claims (2)

鉄筋コンクリート造の柱と、上側フランジ及び下側フランジを有した鉄骨梁とを備えた最上階の接合構造であって、
前記上側フランジ及び前記下側フランジに接触させた前記柱を囲むふさぎ板を設け、
前記柱の主筋の上端部には定着金物が取り付けられており、
前記主筋の上端面又は前記定着金物の上端面の高さ方向の位置を、前記上側フランジと前記下側フランジとの間に設けたことを特徴とする最上階の接合構造。
A joint structure of the top floor comprising a reinforced concrete column and a steel frame beam having an upper flange and a lower flange,
Providing a cover plate surrounding the column in contact with the upper flange and the lower flange;
Anchors are attached to the upper ends of the main bars of the columns,
A joint structure on the uppermost floor, wherein a position in the height direction of the upper end surface of the main bar or the upper end surface of the fixing hardware is provided between the upper flange and the lower flange.
鉄筋コンクリート造の柱と、上側フランジ及び下側フランジを有した鉄骨梁とを備え、前記柱の主筋の上端部には定着金物が取り付けられた最上階の仕口部の接合方法であって、
前記主筋の上端面又は前記定着金物の上端面の高さ方向の位置を、前記上側フランジと前記下側フランジとの間に設けた状態で、前記上側フランジ及び前記下側フランジに接触するふさぎ板を配置し、前記ふさぎ板内にコンクリートを打設し、
前記上側フランジ及び前記柱の上に、スラブコンクリートを打設することを特徴とする最上階の仕口部の接合方法。
A method of joining a joint portion of a top floor having a reinforced concrete column and a steel frame beam having an upper flange and a lower flange, the upper end portion of the main bar of the column being provided with an anchorage material,
A cover plate in contact with the upper flange and the lower flange in a state where the position in the height direction of the upper end surface of the main bar or the upper end surface of the anchor metal is provided between the upper flange and the lower flange. Place and cast concrete in the blind board,
A method of joining a top floor connection section, comprising placing slab concrete on the upper flange and the column.
JP2018009632A 2018-01-24 2018-01-24 Joint structure of the top floor and joint method of the joint part of the top floor Active JP7200478B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2018009632A JP7200478B2 (en) 2018-01-24 2018-01-24 Joint structure of the top floor and joint method of the joint part of the top floor
JP2022102776A JP7384241B2 (en) 2018-01-24 2022-06-27 Top floor joint structure and top floor joint joint method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018009632A JP7200478B2 (en) 2018-01-24 2018-01-24 Joint structure of the top floor and joint method of the joint part of the top floor

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2022102776A Division JP7384241B2 (en) 2018-01-24 2022-06-27 Top floor joint structure and top floor joint joint method

Publications (2)

Publication Number Publication Date
JP2019127737A true JP2019127737A (en) 2019-08-01
JP7200478B2 JP7200478B2 (en) 2023-01-10

Family

ID=67472011

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2018009632A Active JP7200478B2 (en) 2018-01-24 2018-01-24 Joint structure of the top floor and joint method of the joint part of the top floor
JP2022102776A Active JP7384241B2 (en) 2018-01-24 2022-06-27 Top floor joint structure and top floor joint joint method

Family Applications After (1)

Application Number Title Priority Date Filing Date
JP2022102776A Active JP7384241B2 (en) 2018-01-24 2022-06-27 Top floor joint structure and top floor joint joint method

Country Status (1)

Country Link
JP (2) JP7200478B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115370000A (en) * 2022-08-05 2022-11-22 中交一公局集团有限公司 Multiple shear force key pile board rigid connection structure

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7200478B2 (en) 2018-01-24 2023-01-10 株式会社大林組 Joint structure of the top floor and joint method of the joint part of the top floor

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06185117A (en) * 1992-12-18 1994-07-05 Fujita Corp Joining structure of reinforced concrete column with steel beam
JP2006194002A (en) * 2005-01-14 2006-07-27 East Japan Railway Co Joint structure of steel framed beam and reinforced concrete column and composite structure using the same
JP2014173330A (en) * 2013-03-08 2014-09-22 Shimizu Corp Junction structure of highest floor

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7200478B2 (en) 2018-01-24 2023-01-10 株式会社大林組 Joint structure of the top floor and joint method of the joint part of the top floor

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06185117A (en) * 1992-12-18 1994-07-05 Fujita Corp Joining structure of reinforced concrete column with steel beam
JP2006194002A (en) * 2005-01-14 2006-07-27 East Japan Railway Co Joint structure of steel framed beam and reinforced concrete column and composite structure using the same
JP2014173330A (en) * 2013-03-08 2014-09-22 Shimizu Corp Junction structure of highest floor

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
水越一晃ほか: "梁貫通型柱RC梁S架構のT形接合部における機械式定着", 大林組技術研究所報, vol. No.83 2019, JPN6022048943, 2019, JP, pages 1 - 6, ISSN: 0004924997 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115370000A (en) * 2022-08-05 2022-11-22 中交一公局集团有限公司 Multiple shear force key pile board rigid connection structure

Also Published As

Publication number Publication date
JP2022123147A (en) 2022-08-23
JP7200478B2 (en) 2023-01-10
JP7384241B2 (en) 2023-11-21

Similar Documents

Publication Publication Date Title
JP7384241B2 (en) Top floor joint structure and top floor joint joint method
JP2012522913A (en) Truss type shear reinforcement with double anchorage function on both top and bottom
JP6815183B2 (en) Complex building
JP6096367B1 (en) Steel pipe pile and steel column joint structure
KR20210003315A (en) Column form system using deckplate form
KR101750177B1 (en) Punching shear stiffening member of cutting bridge type and method for constructing footing using of the same
JP6447777B2 (en) Column beam connection structure and steel reinforced concrete column
JP6573111B2 (en) Beam-column joint structure
JP6567368B2 (en) Reinforcement structure and reinforcement method for existing columns
JPH10331437A (en) Earthquake resistant reinforcing construction for existing beam and column
JP2005139650A (en) Shearing reinforcing structure, reinforcing structure, anchoring structure and joining structure using reinforcement having dished head part
JP2017082548A (en) Concrete foundation joint member and pile structure
JP5344702B2 (en) Column and slab joint structure
JP6052460B2 (en) Seismic reinforcement structure and construction method
JP2006194036A (en) Fixation structure of steel stud to reinforced concrete beam
JP2754377B2 (en) Building structure
JP2007154565A (en) Joint structure and construction method of column and beam-less slab
JP7137978B2 (en) Plate-shaped member for pillar
JPH0932311A (en) Reinforcement structure of existing building
KR102429445B1 (en) Shear Reinforcement Integrated with Vertical Rebars that can be Constructed with a Crane and its Installation Method
JP6807157B2 (en) Joint member and joint structure
JP4184538B2 (en) Column base semi-fixed joint structure, building and building design method
JP2536361B2 (en) Column-beam joint structure of RC structure
JP2020204257A (en) Composite building
JP3430326B2 (en) Column and beam joint structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201202

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211013

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211019

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20211217

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20220329

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220627

C60 Trial request (containing other claim documents, opposition documents)

Free format text: JAPANESE INTERMEDIATE CODE: C60

Effective date: 20220627

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20220704

C21 Notice of transfer of a case for reconsideration by examiners before appeal proceedings

Free format text: JAPANESE INTERMEDIATE CODE: C21

Effective date: 20220705

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220816

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20221005

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20221122

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20221205

R150 Certificate of patent or registration of utility model

Ref document number: 7200478

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150