JP2019109945A - Support system, support method, and program - Google Patents

Support system, support method, and program Download PDF

Info

Publication number
JP2019109945A
JP2019109945A JP2019075137A JP2019075137A JP2019109945A JP 2019109945 A JP2019109945 A JP 2019109945A JP 2019075137 A JP2019075137 A JP 2019075137A JP 2019075137 A JP2019075137 A JP 2019075137A JP 2019109945 A JP2019109945 A JP 2019109945A
Authority
JP
Japan
Prior art keywords
period
rebuilding
building
year
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2019075137A
Other languages
Japanese (ja)
Other versions
JP2019109945A5 (en
Inventor
直樹 倉形
Naoki Kurakata
直樹 倉形
尚志 青木
Hisashi Aoki
尚志 青木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NTT Facilities Inc
Original Assignee
NTT Facilities Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NTT Facilities Inc filed Critical NTT Facilities Inc
Priority to JP2019075137A priority Critical patent/JP2019109945A/en
Publication of JP2019109945A publication Critical patent/JP2019109945A/en
Publication of JP2019109945A5 publication Critical patent/JP2019109945A5/ja
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

To present a period suitable for carrying out rebuilding for a building to be considered.SOLUTION: A support system, in which a predetermined consideration period predefined as a period in which a building to be considered is considered is divided into a plurality of unit periods and a rebuilding scenario assuming that rebuilding of the building to be considered will be carried out in any of the unit periods within the consideration period is defined, includes: a cost calculation unit which calculates a cumulative amount of cost, within the consideration period, including cost required for maintaining and rebuilding the building to be considered under the rebuilding scenario in correspondence with a unit period in which the rebuilding of the building is assumed to be carried out in the rebuilding scenario; and a recommended period calculation unit which, based on the cumulative amount of the cost calculated for each unit period within the consideration period, defines a threshold value from a value obtained from a different between a maximum value of the cumulative amount and a minimum value of the cumulative amount and calculates, through determination based on the threshold value, the candidate period in which the rebuilding is carried out.SELECTED DRAWING: Figure 2

Description

本発明は、既存の建物の建替に適した期間を提示する支援システム、支援方法、及びプログラムに関する。   The present invention relates to a support system, support method, and program for presenting a period suitable for rebuilding an existing building.

建物の劣化状況の調査を行うと、内装や設備等に多くの不具合が見つかり、多額の修繕や更新コストが必要であることが判明する場合がある。その場合、修繕や更新コストを負担して建物を継続使用すべきか、新たに建替えるべきかについて、建物所有者等は決断を迫られることになる。
現状のファシリティマネジメントの考え方では、既存の建物を延命させる場合のライフサイクルコスト(LCC)と、建替えを行う場合のライフサイクルコストとを比較することにより、延命又は建替えの優劣を判定する。このため、現状のファシリティマネジメントの考え方では、建物の建替えを何時行うと効率的であるかの判定ができなかった。
When investigating the deterioration of a building, many problems may be found in interiors and facilities, etc., and it may be found that a large amount of repair and renewal costs are required. In that case, the owner of the building is forced to make a decision on whether the building should be used continuously or rebuilt with the cost of repair and renewal.
According to the current concept of facility management, the superiority or inferiority of life extension or rebuilding is determined by comparing the life cycle cost (LCC) when extending an existing building with the life cycle cost when rebuilding. For this reason, it was not possible to determine when it is efficient to rebuild a building according to the current concept of facility management.

なお、関連する資産運用管理支援システムがある(特許文献1を参照)。この特許文献1に記載の資産運用管理支援システムは、橋梁等の複数の構造物について、維持管理に伴う補修・改修対策や更新対策を、各構造物にとって最適な時期に、かつ、短期、中期および長期予算を満たすように実行するための計画作成を支援する。   There is a related asset operation management support system (see Patent Document 1). The asset operation management support system described in Patent Document 1 is for a plurality of structures such as bridges at a time when the maintenance / repair measures and update measures associated with maintenance management are optimal for each structure, in the short and medium terms. And support planning to execute to meet the long-term budget.

特開2006−323741号公報Unexamined-Japanese-Patent No. 2006-323741

上記特許文献1に記載の建築物評価システムでは、各橋梁について、健全度の許容レベルと回復レベルとを指標にした複数のシナリオを選定する。そして、特許文献1の建築物評価システムは、橋梁の劣化予測式に基づいて健全度の将来予測を行い、上記複数のシナリオ毎にLCCの累積額の算出処理を実行し、このLCCが最小になるシナリオを選択する。この選択されたシナリオは、予算計画に基づいて実施時期が変更されることがあり、また、他のシナリオに変更されることがある。
しかしながら、特許文献1の建築物評価システムでは、ビル等の建物について、所定の検討期間内においてコスト的に有利である建替えの期間を提示する方法については開示されていない。
In the building evaluation system described in Patent Document 1, for each bridge, a plurality of scenarios are selected in which the acceptable level of the soundness level and the recovery level are used as indicators. Then, the building evaluation system of Patent Document 1 predicts the soundness in the future based on the deterioration prediction formula of the bridge, executes the calculation processing of the LCC accumulated amount for each of the plurality of scenarios, and minimizes this LCC. Select the scenario The selected scenario may be changed in implementation timing based on the budget plan, and may be changed to another scenario.
However, the building evaluation system of Patent Document 1 does not disclose a method for presenting a rebuilding period that is cost-effective within a predetermined examination period for a building or other building.

本発明は、斯かる実情に鑑みなされたものであり、本発明の目的は、検討対象となる1又は複数の建物について、所定の検討期間内において建替えを実施するのに適した期間を提示できる、支援システム、支援方法、及びプログラムを提供することにある。   The present invention has been made in view of such circumstances, and an object of the present invention is to present a period suitable for carrying out rebuilding within a predetermined examination period for one or more buildings to be examined. It is possible to provide a support system, a support method, and a program that can.

本発明は、上記課題を解決するためになされたものであり、本発明の支援システムは、検討対象の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて算出する費用算定部と、前記検討期間内の前記単位期間ごとに前記算出された費用の累計額に基づいて、当該累計額の最大値と当該累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定する推奨期間算定部と、を備えることを特徴とする。   The present invention has been made to solve the above problems, and in the support system of the present invention, a predetermined examination period predetermined as a period for examining a building to be examined is divided into a plurality of unit periods, A rebuilding scenario is defined on the assumption that rebuilding of the building under consideration is performed in any of the unit periods within the review period, and maintenance and rebuilding of the building under consideration under the rebuilding scenario are defined. Cost calculation unit for calculating the cumulative amount expected to be incurred within the examination period of the cost including the cost to the unit period assumed to carry out the rebuilding of the building in the rebuilding scenario, and within the examination period A threshold is determined from a value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount based on the accumulated amount of expenses calculated for each unit period of More, characterized in that it and a preferred lifetime calculating unit for calculating the duration of the candidate to implement the rebuilding.

また、本発明の支援システムは、検討対象の複数の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記建物毎に前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建物毎の前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建物毎の前記建替シナリオにおいて前記建物の建て替えを実施すると仮定した単位期間に対応させて前記建物毎に算出する費用算定部と、前記検討期間内の前記単位期間ごとに前記算出された費用の前記建物毎の累計額に基づいて、当該建物毎の累計額の最大値と当該建物毎の累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建物毎に建替えを実施する候補の期間を算定する推奨期間算定部と、を備えることを特徴とする。   Further, in the support system of the present invention, a predetermined examination period predetermined as a period for examining a plurality of buildings to be examined is divided into a plurality of unit periods, and any of the units within the examination period is divided into each building. A rebuilding scenario is defined that assumes rebuilding of the building under consideration during the period, and includes the cost of maintaining and rebuilding the building under consideration under the rebuilding scenario for each building A cost calculation unit for calculating the accumulated amount expected within the examination period of expenses in association with the unit period assumed to carry out the rebuilding of the building in the rebuilding scenario for each building; A value determined from the difference between the maximum value of the accumulated amount for each building and the minimum value of the accumulated amount for each building based on the accumulated amount for each building of the expenses calculated for each unit period in the period Defining a Luo threshold, according to the judgment based on the threshold value, characterized in that and a preferred lifetime calculating unit for calculating the duration of the candidate to carry out reconstruction for each of the building.

また、上記支援システムにおいて、前記推奨期間算定部は、当該累計額の最大値と当該累計額の最小値との差額から求めた値を前記最小値に加えて閾値にして、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定することを特徴とする。   Further, in the support system, the recommended period calculation unit adds a value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount to the minimum value as a threshold, and performs determination based on the threshold Calculating a candidate period to carry out the rebuilding.

また、上記支援システムにおいて、前記推奨期間算定部は、当該累計額の最大値と当該累計額の最小値との差額から求めた値を前記最小値に加えて閾値にして、前記閾値に基づく判定の結果から得られた前記単位期間を、前記建替えを実施する候補の期間として算定することを特徴とする。   Further, in the support system, the recommended period calculation unit adds a value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount to the minimum value as a threshold, and performs determination based on the threshold Calculating the unit period obtained from the result of the step as a candidate period to carry out the rebuilding.

また、本発明の支援システムは、検討対象の複数の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記建物毎に前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建物毎の前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建物毎の前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて前記建物毎に算出する費用算定部と、前記検討期間内の前記単位期間ごとに前記算出された費用の前記建物毎の累計額に基づいて、当該建物毎の累計額の最大値と当該建物毎の累計額の最小値との差額から値を求め、前記複数の建物の前記差額から求めた値から代表値を定め、前記定めた代表値を基準にした判定により、前記建物毎に建替えを実施する候補の期間を算定する推奨期間算定部と、を備えることを特徴とする。   Further, in the support system of the present invention, a predetermined examination period predetermined as a period for examining a plurality of buildings to be examined is divided into a plurality of unit periods, and any of the units within the examination period is divided into each building. A rebuilding scenario is defined that assumes rebuilding of the building under consideration during the period, and includes the cost of maintaining and rebuilding the building under consideration under the rebuilding scenario for each building A cost calculation unit for calculating the accumulated amount expected within the examination period of the cost for each building corresponding to the unit period assumed to carry out the rebuilding of the building in the rebuilding scenario for each building; A value is calculated from the difference between the maximum value of the accumulated amount for each building and the minimum value of the accumulated amount for each building based on the accumulated amount for each building of the expenses calculated for each unit period within the examination period Ask for A recommended period calculation unit which determines a representative value from values calculated from the differences of the plurality of buildings, and calculates a period of a candidate for rebuilding for each of the buildings by determination based on the determined representative values; And the like.

また、本発明の支援方法は、検討対象の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて算出するステップと、前記検討期間内の前記単位期間ごとに前記算出された費用の累計額に基づいて、当該累計額の最大値と当該累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定するステップと、を含む処理をコンピュータに実施させることを特徴とする。   Further, in the supporting method of the present invention, a predetermined examination period predetermined as a period for examining a building to be examined is divided into a plurality of unit periods, and the building to be considered in any of the unit periods within the examination period A rebuilding scenario is defined under the assumption that rebuilding is to be carried out, and the cumulative total of expenses expected for the maintenance and rebuilding of the building under consideration under the rebuilding scenario within the review period of the expenses within the review period. Calculating the amount corresponding to the unit period assumed to carry out the rebuilding of the building in the rebuilding scenario, and based on the accumulated amount of the expenses calculated for each unit period within the examination period A step of determining a threshold from a value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount, and calculating the period of the candidate for performing the rebuilding by the determination based on the threshold Characterized in that to practice the, the processing including the computer.

また、本発明のプログラムは、検討対象の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて算出するステップと、前記検討期間内の前記単位期間ごとに前記算出された費用の累計額に基づいて、当該累計額の最大値と当該累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定するステップと、を支援システムのコンピュータに実施させるためのプログラムである。   Further, in the program of the present invention, a predetermined examination period predetermined as a period for examining a building to be examined is divided into a plurality of unit periods, and the building of the examination object in any of the unit periods within the examination period. A rebuilding scenario is defined which assumes that a rebuilding is to be carried out, and the cumulative amount of expenses expected to be incurred within the review period of the expenses including the costs for maintaining and rebuilding the building under the rebuilding scenario. Calculating according to the unit period assumed to carry out the rebuilding of the building in the rebuilding scenario, and based on the accumulated amount of the expenses calculated for each unit period within the examination period, A threshold is determined from the value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount, and the period based on the threshold value is calculated to calculate the period of the candidate for the rebuilding Is a program for implementation and up, to the computer support system.

本発明によれば、検討対象となる1又は複数の建物について、所定の検討期間内において建替えを実施するのに適した期間を提示できる。   According to the present invention, it is possible to present a period suitable for implementing rebuilding within a predetermined examination period for one or more buildings to be examined.

本発明の第1実施形態に係わる支援システムの動作の概要を示す説明図である。It is explanatory drawing which shows the outline | summary of operation | movement of the assistance system concerning 1st Embodiment of this invention. 支援システム100の構成例を示すブロック図である。FIG. 2 is a block diagram showing a configuration example of a support system 100. 第1実施形態の支援システム100における処理の流れを示すフローチャートである。It is a flow chart which shows a flow of processing in support system 100 of a 1st embodiment. 検討期間の例を示す説明図である。It is explanatory drawing which shows the example of examination period. 既存の建物の維持コストの例を示す説明図である。It is explanatory drawing which shows the example of the maintenance cost of the existing building. 建替え後の建物の維持コストの例を示す説明図である。It is an explanatory view showing an example of maintenance cost of a building after rebuilding. 30年の検討期間において10年目に建替えを実施する建替シナリオの例を示す説明図である。It is explanatory drawing which shows the example of the rebuilding scenario which implements rebuilding in a 10th year in the examination period of 30 years. 建替シナリオ毎の累計額T(y)の第1の例を示す説明図である。It is explanatory drawing which shows the 1st example of the sum total T (y) for every rebuilding scenario. 建替シナリオ毎の累計額T(y)の第2の例を示す説明図である。It is explanatory drawing which shows the 2nd example of the sum total T (y) for every rebuilding scenario. 候補期間の第1の算定例を示す説明図である。It is an explanatory view showing the 1st example of calculation of a candidate period. 候補期間の第2の算定例を示す説明図である。It is an explanatory view showing the 2nd example of calculation of a candidate period. 第2実施形態における候補期間の算定例を示す説明図である。It is explanatory drawing which shows the example of calculation of the candidate period in 2nd Embodiment. 複数の建物のそれぞれの候補期間の例を示す説明図である。It is an explanatory view showing an example of a candidate period of each of a plurality of buildings. 第2実施形態の支援システム100における処理の流れを示すフローチャートである。It is a flow chart which shows a flow of processing in support system 100 of a 2nd embodiment. 第3実施形態における候補期間の算定例を示す説明図である。It is explanatory drawing which shows the example of calculation of the candidate period in 3rd Embodiment. 建物10−3自身の累計額T(y)の差額Δを用いた候補期間の算定例を示す説明図である。It is explanatory drawing which shows the example of calculation of the candidate period using difference (DELTA) of total sum T (y) of building 10-3 self. 建物10−1の累計額T(y)の差額Δmaxを用いる場合と建物10−3自身の累計額T(y)の差額Δを用いる場合との候補期間の算定結果の違いを示す説明図である。It is an explanatory view showing the difference of the calculation result of the candidate period in the case of using the difference Δmax of the accumulated sum T (y) of the building 10-1 and the case of using the difference Δ of the accumulated sum T (y) of the building 10-3 itself. is there. 第3実施形態の支援システム100における処理の流れを示すフローチャートである。It is a flow chart which shows a flow of processing in support system 100 of a 3rd embodiment. ファシリティ機能、性能、品質のレベル向上に掛るコスト情報の設定例を示す説明図である。It is explanatory drawing which shows the example of a setting of the cost information concerning a facility function, performance, and the level improvement of quality.

以下、本発明の実施の形態を、添付図面を参照して説明する。   Hereinafter, embodiments of the present invention will be described with reference to the attached drawings.

[第1実施形態]
(概要)
図1は、本発明の第1実施形態に係わる支援システム100の動作の概要を示す説明図である。建替えの検討対象となる建物10は、例えば、オフィスビル等である。支援システム100は、検討対象の建物10について、所定の検討期間(例えば、現在から)30年間の検討期間を設定する。そして、支援システム100は、初年度に建替えを実施すると仮定した場合の建替シナリオから、30年目(現在から30年後)の最終年度に建替えを実施すると仮定した場合の建替シナリオまでの、それぞれの建替シナリオを作成する。つまり、支援システム100は、建物10について、建替えを実施する時期(以下、「建替時期」とも記載)を変化させた場合の複数の建替シナリオを作成する。
なお、以下の説明において、検討期間内の「初年度から数えてy年後」を、「y年目」と記載することがある。
First Embodiment
(Overview)
FIG. 1 is an explanatory view showing an outline of the operation of the support system 100 according to the first embodiment of the present invention. The building 10 to be considered for rebuilding is, for example, an office building or the like. The support system 100 sets a predetermined examination period (for example, from the present) of 30 years for the examination target building 10. Then, from the rebuilding scenario on the assumption that the rebuilding is carried out in the first year, the rebuilding scenario on the assumption that the rebuilding is carried out in the final year of the 30th year (after 30 years from now). Create each rebuilding scenario up to That is, the support system 100 creates, for the building 10, a plurality of rebuilding scenarios in the case of changing the time of rebuilding (hereinafter, also described as “rebuild time”).
In the following description, “y year after the first year” in the examination period may be described as “y year”.

支援システム100において、費用算定部120は、建替時期が異なる建替シナリオ毎に、建物10の維持コスト(維持費用)と、建替えに掛る建替コスト(建替費用)とを含むコスト(費用)の累計額T(y)を算出する。
推奨期間算定部130は、検討対象の建物10について、累計額T(y)が最も少ないTminの年度(例えば、8年目)を、建替えを実施するのに最も適した「推奨年度」として算定する。また、推奨期間算定部130は、累計額T(y)の最大値Tmaxと最小値との差額Δに基づいて、累計額T(y)が比較的少ない年度(例えば、6年目、7年目、9年目、10年目)を、建替えを実施するのに適した候補となる年度(以下、「候補年度」とも記載)を算出する。
そして、推奨期間算定部130は、推奨年度と候補年度とを含む期間を、建替えを実施するのに適した候補となる期間(以下、「候補期間」とも記載)として算定する。支援システム100は、推奨年度と候補年度とを含む候補期間201を提示する。
これにより、支援システム100は、検討対象となる建物10について、所定の検討期間内において建替えを実施するのに適した候補となる期間を提示できる。
In the support system 100, the cost calculation unit 120 includes the cost including the maintenance cost (maintenance cost) of the building 10 and the rebuilding cost for rebuilding (rebuilding cost) for each rebuilding scenario in which the rebuilding time differs. Calculate the accumulated amount T (y) of expenses).
The recommended period calculation unit 130 sets the year Tmin (for example, the eighth year) with the smallest accumulated amount T (y) as the “recommended year” most suitable for rebuilding for the building 10 to be considered. Calculate In addition, based on the difference Δ between the maximum value Tmax and the minimum value of the accumulated amount T (y), the recommended period calculating unit 130 determines the year in which the accumulated amount T (y) is relatively small (for example, the sixth and seventh years). Calculate the year (hereinafter also referred to as “candidate year”) that is a candidate suitable for rebuilding in the second, ninth, and tenth years.
Then, the recommended period calculating unit 130 calculates a period including the recommended year and the candidate year as a period (hereinafter, also referred to as a “candidate period”) that is a candidate suitable for performing rebuilding. The support system 100 presents a candidate period 201 including a recommended year and a candidate year.
Thus, the support system 100 can present, for the building 10 to be considered, a period that is a candidate suitable for implementing rebuilding within a predetermined examination period.

なお、図1に示す例では、1つの建物10の候補期間201を算定する例を示しているが、これに限定されない。後述する第2実施形態及び第3実施形態で示すように、支援システム100は、複数の建物のそれぞれについての候補期間を算定して提示することができる。   In addition, although the example shown in FIG. 1 shows the example which calculates the candidate period 201 of one building 10, it is not limited to this. As shown in the second and third embodiments described later, the support system 100 can calculate and present candidate periods for each of a plurality of buildings.

(支援システム100の構成例)
次に、支援システム100の構成例について説明する。
図2は、支援システム100の構成例を示すブロック図である。この図2に示すように、支援システム100は、制御部101と、入出力インタフェース102と、建替シナリオ生成部110と、記憶部150と、を備える。また、この支援システム100には、入出力端末装置161が接続される。この入出力端末装置161は、液晶表示ディスプレイ等の表示部162と、マウスやキーボード等の入力装置163とを備えている。
(Example of configuration of support system 100)
Next, a configuration example of the support system 100 will be described.
FIG. 2 is a block diagram showing a configuration example of the support system 100. As shown in FIG. As shown in FIG. 2, the support system 100 includes a control unit 101, an input / output interface 102, a rebuild scenario generation unit 110, and a storage unit 150. Further, an input / output terminal device 161 is connected to the support system 100. The input / output terminal device 161 includes a display unit 162 such as a liquid crystal display, and an input device 163 such as a mouse or a keyboard.

制御部101は、支援システム100内の各部を制御し、支援システム100の全体を統括して制御することにより、支援システム100に必要とされる処理機能を実現する。入出力インタフェース102は、支援システム100に接続される入出力端末装置161とのインタフェースとなる処理部である。
入力装置163は、例えば、建物10の建替シナリオ毎の累計額T(y)を算出する際に必要となるデータの入力に使用される。支援システム100は、入力装置163から入力されたデータを、入出力インタフェース102を介して取得して記憶部150に記憶する。また、支援システム100は、推奨期間算定部130により算定された候補期間201の情報を、入出力インタフェース102を介して入出力端末装置161に出力して、表示部162に表示させる。
The control unit 101 controls each unit in the support system 100 to control the entire support system 100 to realize processing functions required for the support system 100. The input / output interface 102 is a processing unit serving as an interface with the input / output terminal device 161 connected to the support system 100.
The input device 163 is used, for example, to input data required to calculate the accumulated amount T (y) for each rebuilding scenario of the building 10. The support system 100 acquires data input from the input device 163 via the input / output interface 102 and stores the data in the storage unit 150. Further, the support system 100 outputs the information of the candidate period 201 calculated by the recommended period calculating unit 130 to the input / output terminal device 161 via the input / output interface 102 and causes the display unit 162 to display the information.

建替シナリオ生成部110は、費用算定部120と、推奨期間算定部130と、作図部140と、を含んでいる。
建替シナリオ生成部110は、予め設定された検討期間(例えば、30年)の初年度から最終年度までの間において、建替えを実施する年度を変化させた複数の建替シナリオを作成する。つまり、建替シナリオ生成部110は、建替時期の異なる複数の建替シナリオを作成する。
費用算定部120は、建替時期の異なる建替シナリオ毎に、検討期間内における建物10の維持コストと建替コストとのコストの累計額T(y)を算出する。この建替シナリオ毎の累計額T(y)の算出方法の詳細については、後述する。
The rebuilding scenario generating unit 110 includes an expense calculating unit 120, a recommended period calculating unit 130, and a drawing unit 140.
The rebuilding scenario generation unit 110 creates a plurality of rebuilding scenarios in which the year of rebuilding is changed between the first year of the examination period (for example, 30 years) set in advance and the final year. That is, the rebuilding scenario generation unit 110 creates a plurality of rebuilding scenarios having different rebuilding times.
The expense calculating unit 120 calculates the accumulated amount T (y) of the maintenance cost of the building 10 and the rebuilding cost in the examination period for each rebuilding scenario having a different rebuilding time. The details of the method of calculating the accumulated amount T (y) for each rebuilding scenario will be described later.

推奨期間算定部130は、検討対象の建物10について、累計額T(y)が最も少ないTminの年度を、建替えを実施するのに最も適した「推奨年度」として算定する。また、推奨期間算定部130は、累計額T(y)が比較的少ない年度を、建替えを実施するのに適した候補年度として算定する。この候補年度を算定する場合、推奨期間算定部130は、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)に基づいて候補年度を算定する。また、推奨期間算定部130は、推奨年度と候補年度とを含む期間を、候補期間として算定する。この候補年度及び候補期間の算定方法の詳細については、後述する。
作図部140は、推奨年度、候補年度、及び候補期間等を表示する図表を生成する。支援システム100は、この図表を表示部162に表示する。例えば、作図部140は、建替シナリオ毎のコストの累計額T(y)を、建替時期に対応させて、累計額T(y)を年度別に比較することが可能な図表を生成するとともに、推奨年度、候補年度、及び候補期間を示す情報を含む図表を生成する。
The recommendation period calculation unit 130 calculates, for the building 10 to be considered, a year of Tmin having the smallest accumulated amount T (y) as a “recommended year” most suitable for rebuilding. In addition, the recommended period calculation unit 130 calculates a year with a relatively small accumulated amount T (y) as a candidate year suitable for implementing rebuilding. When calculating this candidate year, the recommended period calculation unit 130 calculates the candidate year based on the difference Δ (= Tmax−Tmin) between the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y). Further, the recommended period calculating unit 130 calculates a period including the recommended year and the candidate year as a candidate period. Details of the method of calculating the candidate year and candidate period will be described later.
The drawing unit 140 generates a chart that displays the recommended year, the candidate year, the candidate period, and the like. The support system 100 displays this chart on the display unit 162. For example, the drawing unit 140 generates a chart that allows the accumulated amount T (y) to be compared year by year, corresponding to the rebuilding time, with the accumulated amount T (y) of costs for each rebuilding scenario. Generate a chart that includes information indicating the recommended year, the candidate year, and the candidate period.

また、記憶部150には、建物属性情報151、劣化診断情報152、耐震診断情報153、長期修繕計画情報154、建物の建替えに掛かるコスト情報155、既存の建物の維持に掛かるコスト情報156、建替え後の建物の維持に掛かるコスト情報157、及びファシリティ機能、性能、品質のレベル向上に掛るコスト情報158等が記憶されている。
なお、上記の建物属性情報151からコスト情報158までの各情報は、入出力端末装置161の入力装置163から予め入力される情報である。支援システム100は、入力装置163から入力された建物属性情報151からコスト情報158までの各情報を、記憶部150に記憶する。
In addition, the storage unit 150 includes building attribute information 151, deterioration diagnosis information 152, earthquake resistance diagnosis information 153, long-term repair plan information 154, cost information 155 for rebuilding a building, cost information 156 for maintenance of an existing building, The cost information 157 for maintaining the building after rebuilding, and the cost information 158 for improving the facility function, performance, and quality level are stored.
The pieces of information from the building attribute information 151 to the cost information 158 are information input in advance from the input device 163 of the input / output terminal device 161. The support system 100 stores each piece of information from the building attribute information 151 to the cost information 158 input from the input device 163 in the storage unit 150.

上記の建物属性情報151は、建物10の現況情報、例えば、土地面積、延床面積、建築後の経過年数、建物の耐用年数、及び土地や建物の所有権の情報等である。
劣化診断情報152は、建物10について定期的に行われる劣化診断(例えば、現地調査等)の診断結果の情報である。この劣化診断情報152には、例えば、耐久性診断、外壁等劣化診断、設備劣化診断、配管劣化診断などの建物劣化診断の情報が含まれる。
耐震診断情報153は、建物10についての耐震性能の診断結果の情報である。この耐震診断は、建物10について定期的に行われる劣化診断と合わせて行うことができる。
The above-mentioned building attribute information 151 is current information of the building 10, for example, land area, total floor area, age after construction, useful life of the building, and information of land and building ownership.
The deterioration diagnosis information 152 is information on the diagnosis result of the deterioration diagnosis (for example, on-site survey etc.) periodically performed on the building 10. The deterioration diagnosis information 152 includes, for example, information on building deterioration diagnosis such as durability diagnosis, deterioration diagnosis such as outer wall, equipment deterioration diagnosis, pipe deterioration diagnosis and the like.
The seismic resistance diagnostic information 153 is information on the diagnostic result of the seismic performance of the building 10. This earthquake proofing diagnosis can be performed together with the deterioration diagnosis regularly performed on the building 10.

長期修繕計画情報154は、建物の劣化診断情報152と、耐震診断情報153とに基づいて設定される建物10の整備計画の情報である。なお、この長期修繕計画情報154は、劣化診断情報152と、耐震診断情報153とに基づいて、建物10の将来の劣化状態を予測して設定することができる。
建物の建替えに掛かるコスト情報155は、建物10の撤去、設計、新築に掛るコストの情報である。
既存の建物の維持に掛るコスト情報156は、上記の長期修繕計画情報154に基づいて、建物10の修繕・改修を行う際に必要となるコストの情報である。
建替え後の建物の維持に掛るコスト情報157は、建物10の建替え後に新たに建てた建物の維持コストの情報である。この建替え後の建物の維持に掛るコスト情報157の例については、後述する。
前段までに説明した各コスト情報は、ファシリティ機能、性能、品質を維持することを前提にして、建物10の修繕・改修並びに建替えを実施する際に掛るコストの情報であった。一方、建物10の修繕・改修並びに建替えを実施する際に、ファシリティ機能、性能、品質を部分的に向上させる場合がある。そこで、ファシリティ機能、性能、品質のレベルを部分的に向上させる場合についても、ファシリティ機能、性能、品質のレベルをコスト化することにより、統合して検討することができる。ファシリティ機能、性能、品質のレベル向上に掛るコスト情報158は、建物10のファシリティ機能、性能、品質のレベルを向上させる場合に、この向上の程度を金額に変換した情報である。このファシリティ機能、性能、品質のレベル向上に掛るコスト情報158の詳細については、後述する。
The long-term repair plan information 154 is information of a maintenance plan of the building 10 set based on the building deterioration diagnosis information 152 and the earthquake resistance diagnosis information 153. In addition, this long-term repair plan information 154 can predict and set the future deterioration state of the building 10 based on the deterioration diagnosis information 152 and the earthquake resistance diagnosis information 153.
The cost information 155 for rebuilding the building is information on the cost for removing, designing, and newly building the building 10.
The cost information 156 for maintenance of the existing building is information on the cost required when repairing or repairing the building 10 based on the long-term repair plan information 154 described above.
The cost information 157 on maintenance of the building after rebuilding is information on the maintenance cost of a newly built building after rebuilding the building 10. An example of the cost information 157 taken to maintain the post-reconstruction building will be described later.
Each cost information explained to the front | former stage was information of the cost which takes when performing repair, repair, and rebuilding of the building 10 on the assumption that a facility function, performance, and quality are maintained. On the other hand, when carrying out repair, repair and rebuilding of the building 10, there are cases where the facility function, performance and quality are partially improved. Therefore, even in the case of partially improving the facility function, performance and quality level, it can be integrated and considered by costing the facility function, performance and quality level. The cost information 158 for improving the level of the facility function, the performance, and the quality is information obtained by converting the degree of the improvement into the amount of money when improving the level of the facility function, the performance, and the quality of the building 10. Details of the cost information 158 for improving the facility function, performance, and quality levels will be described later.

図3は、第1実施形態の支援システム100における処理の流れを示す説明図である。以下、図3を参照して、本実施形態の支援システム100における処理の流れについて説明する。
この支援システム100において、検討対象の建物10についての処理が開始される(ステップS10)。
検討対象の建物10についての処理が開始されると、建替シナリオ生成部110は、検討対象の建物10についての検討期間を設定する。この検討期間は、建物10の機能を維持する期間として設定される。例えば、検討期間は、現在から将来に向けての30年間として年単位で設定される(ステップS20)。
FIG. 3 is an explanatory view showing a flow of processing in the support system 100 of the first embodiment. Hereinafter, the flow of processing in the support system 100 of the present embodiment will be described with reference to FIG.
In the support system 100, processing for the building 10 to be studied is started (step S10).
When the process for the building 10 to be considered is started, the rebuilding scenario generation unit 110 sets a study period for the building 10 to be considered. The examination period is set as a period for maintaining the function of the building 10. For example, the examination period is set on a yearly basis as 30 years from the present to the future (step S20).

続いて、建替シナリオ生成部110は、30年間の検討期間において、初年度に建替えを実施すると仮定した場合の建替シナリオから、30年目の最終年度に建替えを実施すると仮定した場合の建替シナリオまでの、それぞれの建替シナリオを作成する。つまり、建替シナリオ生成部110は、建物10について、建替えを実施する時期を変化させた場合の複数の建替シナリオを作成する(ステップS30)。
続いて、費用算定部120は、建替時期が異なる建替シナリオ毎に、建物10の維持コスト(維持費用)と、建替えに掛る建替コスト(建替費用)とを含むコスト(費用)の累計額T(y)を算出する(ステップS40)。
Subsequently, the rebuilding scenario generation unit 110 assumes that rebuilding is to be performed in the final year of the 30th year based on the rebuilding scenario in the case of performing rebuilding in the first year in the 30-year examination period. Create each rebuilding scenario up to the rebuilding scenario of. That is, the rebuilding scenario generation unit 110 creates a plurality of rebuilding scenarios in the case where the time to rebuild is changed for the building 10 (step S30).
Subsequently, the cost calculation unit 120 calculates the cost (cost) including the maintenance cost (maintenance cost) of the building 10 and the rebuilding cost (rebuilding cost) for the rebuilding for each rebuilding scenario having a different rebuilding time. The accumulated amount T (y) of the image is calculated (step S40).

続いて、推奨期間算定部130は、累計額T(y)が最小値Tminになる年度を、建替えを実施するのに最も適した「推奨年度」として算定する(ステップS50)。
続いて、推奨期間算定部130は、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)を算出する(ステップS60)。
続いて、推奨期間算定部130は、差額Δ(=Tmax−Tmin)から、
閾値「Tmin+(Tmax−Tmin)×p」、を算出する。
ここで、pは、例えば、「p=0.2」等の1以下の正の値である(ステップS70)。
続いて、推奨期間算定部130は、閾値「Tmin+(Tmax−Tmin)×p」に基づいて、累計額T(y)が閾値よりも少ない年度を候補年度として算定する(ステップS80)。
続いて、推奨期間算定部130は、推奨年度と候補年度とを含む期間を、候補期間として算定する(ステップS90)。
Subsequently, the recommended period calculating unit 130 calculates a year in which the accumulated amount T (y) is the minimum value Tmin as a “recommended year” most suitable for implementing rebuilding (step S50).
Subsequently, the recommended period calculation unit 130 calculates the difference Δ (= Tmax−Tmin) between the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y) (step S60).
Then, from the difference Δ (= Tmax−Tmin), the recommended period calculation unit 130 calculates
The threshold “Tmin + (Tmax−Tmin) × p” is calculated.
Here, p is, for example, a positive value of 1 or less such as “p = 0.2” (step S70).
Subsequently, the recommended period calculation unit 130 calculates a year whose accumulated amount T (y) is smaller than the threshold as a candidate year based on the threshold “Tmin + (Tmax−Tmin) × p” (step S80).
Subsequently, the recommended period calculating unit 130 calculates a period including the recommended year and the candidate year as a candidate period (step S90).

続いて、作図部140は、候補期間等を提示する図表を生成する。支援システム100は、この図表を表示部162に表示する(ステップS100)。
上記ステップS100において図表を表示部162に表示した後に、支援システム100は、処理を終了する(ステップS110)。
これにより、支援システム100は、検討対象となる建物10について、所定の検討期間内において建替えを実施するのに適した期間を提示できる。
Subsequently, the drawing unit 140 generates a chart presenting candidate periods and the like. The support system 100 displays this chart on the display unit 162 (step S100).
After displaying the chart on the display unit 162 in step S100, the support system 100 ends the process (step S110).
Thereby, the support system 100 can present a period suitable for implementing rebuilding within a predetermined examination period for the building 10 to be examined.

(検討期間の例)
支援システム100において、検討期間は、事業等に供するための「建物10の目的機能を維持する期間」として設定される。この検討期間nは、「現在」から「現在+n」までの期間として定義される。例えば、検討期間nは、30年である。
図4は、検討期間の例を示す説明図である。この図4では、横方向に、時間の経過を年単位で示し、縦方向に、検討対象となる建物Aの例と、検討対象となる建物Bの例と、検討対象とならない建物Cの例と、を並べて示している。
(Example of examination period)
In the support system 100, the examination period is set as a “period in which the objective function of the building 10 is maintained” to be provided to a business or the like. The examination period n is defined as a period from "present" to "present + n". For example, the examination period n is 30 years.
FIG. 4 is an explanatory view showing an example of the examination period. In FIG. 4, the passage of time is shown by year in the horizontal direction, and an example of the building A to be considered, an example of the building B to be considered, and an example of the building C not to be considered in the vertical direction. And are shown side by side.

図4に示す例は、検討対象とする建物10を、検討期間n内に築40年を超える建物と、現在の時点で築40年を超えている建物とする例である。このため、建替時期の検討対象となる建物は、検討期間n内に築40年を超える建物Aと、現在の時点で築40年を超えている建物Bとなる。
一方、建物Cは、検討期間nの後に築40年を迎えるため、検討対象外とする。つまり、現在の時点で新築されたばかりの新しい建物Cについては、建替時期の検討対象から除外するのが合理的であるからである。
The example shown in FIG. 4 is an example in which the building 10 to be considered is a building over 40 years old within the examination period n and a building over 40 years old at present. For this reason, the buildings to be examined for the rebuilding time are a building A over 40 years old within the examination period n and a building B over 40 years old now.
On the other hand, since Building C reaches 40 years after the examination period n, it is not considered. In other words, it is reasonable to exclude the new building C, which has just been newly built at the present time, from the consideration of the rebuilding time.

(建替シナリオのコストの累計額Tの算定方法)
次に、費用算定部120により行われる建替シナリオのコストの累計額Tの算出方法について説明する。
費用算定部120は、現在から検討期間nの間に発生する修繕・改修・建替に要するコストの累計額Tを算出する。この累計額Tの算出において、既存の建物10のk年目における維持コスト(修繕・改修コスト)をM1、建物の建替後のj年目における維持コストをM2、建替コストをA(y)と定義する。
そして、検討期間n内のy年目に建替えると仮定し、現在(k=1)から建替前年度(k=y−1) までに発生する維持コストの累計額を、
(How to calculate the accumulated cost T of the rebuilding scenario)
Next, a method of calculating the total cost T of the rebuilding scenario performed by the expense calculating unit 120 will be described.
The cost calculation unit 120 calculates a cumulative amount T of costs required for repair, repair, and rebuilding that occur between the current and the review period n. In the calculation of the accumulated amount T, the maintenance cost (repair and repair cost) of the existing building 10 in the k-th year is M1 k , the maintenance cost in the j-year after the building rebuilding is M2 j , and the rebuilding cost is A Define as (y).
Then, assuming that the y-year in the examination period n is to be rebuilt, the accumulated maintenance cost incurred from the present (k = 1) to the last year of rebuilt (k = y-1) is

Figure 2019109945
Figure 2019109945

とする。
また、建替えに要するコストA(y)は、建替年度(1年間と仮定)に発生するものとする。
また、建替後の建物において建替の翌年度(j=1)から検討期間の最終年度(j=n−y)までに発生する維持コストの累計額を、
I assume.
In addition, the cost A (y) required for rebuilding is assumed to occur in the rebuilding year (assuming one year).
In addition, in the building after rebuilding, the accumulated sum of maintenance costs incurred from the year after rebuilding (j = 1) to the final year of reviewing period (j = n-y),

Figure 2019109945
Figure 2019109945

とする。
そして、費用算定部120は、下記式(3)により、建替シナリオ毎のコストの累計額T(y)を算出する。
I assume.
Then, the expense calculation unit 120 calculates the accumulated amount T (y) of the cost for each rebuilding scenario by the following equation (3).

Figure 2019109945
Figure 2019109945

ここで、「n:検討期間(年)」、「M1:k年目の既存の建物の維持コスト」、「y:建替時期」、「M2:建替後のj年目の建物の維持コスト」、である。
また、「T(y):y年目に建替えを実施する建替シナリオにおけるコストの累計額」、「A(y):y年目に建替えを実施する建替シナリオにおける建替(撤去、設計、新築)に必要なコスト」、である。
Here, “n: examination period (year)”, “M1 k : maintenance cost of existing buildings in k years”, “y: rebuilding period”, “M2 j : buildings in j years after rebuilding” The maintenance cost of
In addition, "T (y): Cumulative cost of rebuilding scenario to rebuild in y year", "A (y): rebuilding in rebuild scenario to rebuild in y year (removal) , Cost of design, new construction).

例えば、図5は、既存の建物の維持コストの例を示す説明図である。この図5に示す例は、ケーススタディとして築46年の既存の建物を対象とし、対象建物の劣化診断を行い、既存建物の維持コストの累計額ΣM1を算出する例である。
費用算定部120は、記憶部150に記憶された長期修繕計画情報154に基づいて、「ΣM1:現在からk年目までに発生する既存建物の維持コストの累計額」を算出する。
図5において、横軸は、現在から30年目までの検討期間を年単位のkで示し、縦軸は、維持コストの累計額ΣM1を「千円/m」の単位で示している。そして、図5では、30年間の検討期間の各年度kに対応させて、維持コストの累計額ΣM1をヒストグラムで示している。
For example, FIG. 5 is an explanatory view showing an example of the maintenance cost of the existing building. The example shown in FIG. 5 is an example in which a 46-year-old existing building is targeted as a case study, the deterioration diagnosis of the target building is performed, and the accumulated amount 維持 M1 k of maintenance costs of the existing building is calculated.
Based on the long-term repair plan information 154 stored in the storage unit 150, the cost calculation unit 120 calculates “ΣM1 k : cumulative amount of maintenance costs of existing buildings generated from the present to the k-th year”.
In FIG. 5, the horizontal axis indicates the examination period from the present to the 30th year by k on a yearly basis, and the vertical axis indicates the accumulated maintenance cost amount MM1 k in the unit of “1,000 yen / m 2 ” . And in FIG. 5, it is made to respond | correspond to each year k of the examination period of 30 years, and the sum total ΣM1 k of maintenance cost is shown by the histogram.

この図5に示すように、ヒストグラムの網掛けされた部分で示す「各年毎に発生する維持コストM1」が、毎年発生する。この「各年毎に発生する維持コストM1は、ヒストグラムの網掛けされていない部分で示す「前年度までの累計額ΣM1k−1」に加算されて、当該年度における新たな「累計額ΣM1」になる。このように、各年毎に発生する維持コストM1が累積されることにより、既存の建物10の維持コストの累計額ΣM1が年々増加する。そして、維持コストの累計額ΣM1は、検討期間の30年目の最終年度において、最大になる。 As shown in FIG. 5, "maintenance costs M1 k generated each year" shown by the shaded portions of the histogram occur each year. This “maintenance cost M1 k generated each year is added to the“ total amount MM1 k−1 to the previous year ”shown by the unshaded part of the histogram, and the new“ total amount It becomes k . As described above, by accumulating the maintenance costs M1 k generated each year, the accumulated amount ΣM1 k of the maintenance costs of the existing building 10 is increased year by year. And, the accumulated amount of maintenance costs ΣM1 k is the largest in the final year of the 30th year of the examination period.

また、図6は、建替え後の建物の維持コストの例を示す説明図である。この図6に示す建替え後の建物の維持コストは、文献(「平成17年版 建築物のライフサイクルコスト」、一般財団法人建築保全センター)の概算システムで定められる事務所3000型case2の値を用いている。この概算システムで定められる維持コストは、新築から65年目までとなっており、この値が検討期間の最大値となる。なお、図6では、修繕のグレードとして上記文献の概算システムで定められる事務所3000型case2の値を用いているが、事務所3000型にはcase2の他に、グレードの要求レベルを比較的高く設定することを条件にするのに適したcase1と、グレードの要求レベルを比較的低く設定することを条件にするのに適したcase3がある。修繕のグレードに適したcaseを選択することにより、目的に応じたコストを算出できる。また、上述した建替コストA(y)は、上記概算システムで定められる値の中から建物用途および規模に合わせた値を用いている。   Moreover, FIG. 6 is explanatory drawing which shows the example of the maintenance cost of the building after rebuilding. The maintenance cost of the building after rebuilding shown in FIG. 6 is the value of the office 3000 type case 2 defined by the rough system of the document (“Life Cycle Cost of Building in 2005, Building Conservation Center General Foundation”) It is used. The maintenance cost defined by this rough estimate system is from the new construction until the 65th year, and this value is the maximum value of the examination period. In addition, in FIG. 6, although the value of office 3000 type case 2 defined by the rough estimation system of the above-mentioned document is used as a grade of repair, in addition to case 2 for office 3000 type, the required level of grade is relatively high. There are Case 1 suitable for setting conditions, and Case 3 suitable for setting conditions for setting the grade requirement level relatively low. By selecting the case that is appropriate for the repair grade, it is possible to calculate the cost according to the purpose. Moreover, the rebuilding cost A (y) mentioned above uses the value according to the building use and a scale out of the value defined by the said rough estimate system.

図6において、横軸は、建替え後の初年度から30年の期間を年単位のjで示し、縦軸は、維持コストの累計額ΣM2を「千円/m」の単位で示している。そして、図6では、建替え後の30年間の期間の各年度jに対応させて、維持コストの累計額ΣM2をヒストグラムで示している。 In FIG. 6, the horizontal axis indicates the period from the first year after rebuilding to 30 years by j on a yearly basis, and the vertical axis indicates the cumulative maintenance cost amount MM2 j in the unit of “1,000 yen / m 2 ”. ing. And in FIG. 6, it is made to respond | correspond to each year j of the period of 30 years after rebuilding, and the sum total (SIGMA) M2 j of maintenance cost is shown by the histogram.

この図6に示すように、ヒストグラムの網掛けされた部分で示す「各年毎に発生する維持コストM2」が、毎年発生する。この「各年毎に発生する維持コストM2」は、ヒストグラムの網掛けされていない部分で示す「前年度までの累計額ΣM2j−1」に加算されて、当該年度における新たな「累計額ΣM2」になる。このように、各年毎に発生する維持コストM2が累積されることにより、建替後の建物10の維持コストの累計額ΣM2が年々増加する。そして、維持コストの累計額ΣM2は、建替後の30年目において、最大になる。 As shown in FIG. 6, "maintenance costs M2 j generated each year" shown by shaded portions of the histogram occur each year. The "maintenance costs M2 j generated every year" are summed in the "cumulative ΣM2 j-1 of the previous years," as indicated by the portion not hatched histogram, a new "cumulative during the year It becomes ΣM2 j ". As described above, by accumulating the maintenance costs M2 j generated each year, the accumulated amount MM2 j of the maintenance costs of the building 10 after the rebuilding is increased year by year. Then, the accumulated amount of maintenance costs ΣM2 j is the largest in the 30th year after the rebuilding.

次に、上記築46年の建物についての建替シナリオの事例について説明する。
図7は、30年の検討期間において10年目に建替えを実施する建替シナリオの例を示す説明図である。この図7において、1年目から9年目までは、図5の「既存の建物の維持コスト」の1年目から9年目までの累計額ΣM1を示している。
また、10年目は、1年目から9年目までの維持コストの累計額ΣM1(k=1〜9)と、建物の建替コストA(10)と、を加算した金額、
ΣM1(k=1〜9)+A(10)、
を示している。上記式における変数kは、検討期間の開始年度から建替え実施までの経過年数を示す。
Next, an example of the rebuilding scenario for the 46-year-old building will be described.
FIG. 7 is an explanatory view showing an example of a rebuilding scenario in which rebuilding is performed in the tenth year in a 30-year study period. In FIG. 7, the first year to the ninth year indicates the accumulated value MM1 k from the first year to the ninth year of the “maintenance cost of the existing building” in FIG. 5.
In the 10th year, the sum of the maintenance costs from the first year to the 9th year Σ M1 k (k = 1 to 9) and the rebuilding cost A (10) of the building,
Σ M 1 k (k = 1 to 9) + A (10),
Is shown. The variable k in the above equation indicates the number of years elapsed from the start year of the examination period to the implementation of the rebuilding.

また、11年目から30年目までは、10年目におけるコストの累計額「ΣM1(k=1〜9)+A(10)」に、図6の「建替え後の建物の維持に掛るコストの累計額ΣM2(j=1〜20)」を加算した値を示している。変数jは、建替え後の初年度から経過した期間を年単位で示す。換言すれば、変数jは、建替え実施年度からの経過年数を示す。例えば、10年目に建替えを実施して、変数jの値が5である年は、検討期間の開始から15年経過した年になる。
そして、検討期間の30年目における累計額T(10)は、
ΣM1(k=1〜9)+A(10)+ΣM2(j=1〜20)、
となる。
そして、図7の例では、累計額T(10)が約「500千円/m」になっており、この金額が、10年目の建替シナリオにおけるコストの累計額T(10)となる。
In addition, from the 11th year to the 30th year, the accumulated amount of costs “維持 M1 k (k = 1 to 9) + A (10)” in the 10th year depends on the maintenance of the building after rebuilding in FIG. It shows a value obtained by adding the accumulated amount of costs MM2 j (j = 1 to 20). The variable j represents the period elapsed from the first year after rebuilding on a yearly basis. In other words, the variable j indicates the number of years since the rebuilding implementation year. For example, rebuilding is performed in the tenth year, and the year in which the value of the variable j is 5 is 15 years after the start of the examination period.
And the accumulated amount T (10) in the 30th year of the examination period is
Σ M 1 k (k = 1 to 9) + A (10) + M M 2 j (j = 1 to 20),
It becomes.
And in the example of FIG. 7, the accumulated amount T (10) is about "500 thousand yen / m 2 ", and this amount is the accumulated amount T (10) of the cost in the 10-year rebuilding scenario. Become.

以上、10年目に建替えを実施する建替シナリオの例について説明したが、建替時期yは、1年目から30年目まで変化する。この建替時期yの変化に伴い、「既存の建物の維持に掛るコストM1」の発生期間と、「建替え後の建物の維持に掛るコストM2」の発生期間とが、それぞれ変動する。このため、建替シナリオ毎の累計額T(y)が変動することになる。 As mentioned above, although the example of the rebuilding scenario which implements rebuilding in the 10th year was demonstrated, rebuilding time y changes from the 1st year to the 30th year. With the change of the rebuilding time y, the occurrence period of "the cost M1 k for maintaining the existing building" and the occurrence period of the "cost M2 j for the maintenance of the building after the replacement" fluctuate respectively . For this reason, the accumulated amount T (y) for each rebuilding scenario changes.

次に、一定の整備が行われている建物10について、建替時期yを1年目から30年目まで変化させた場合の建替シナリオ毎の累計額T(y)の変動の例を示す。
図8は、建替シナリオ毎の累計額T(y)の第1の例を示す説明図である。
図8において、グラフの横軸は、1年目から30年目までの建替時期(y年後)を示し、縦軸は、累計額Tを「千円/m」の単位で示している。そして、図8で示す例では、建替えをy年目に行うと仮定した場合の建替シナリオ毎の累計額T(y)を、建替えを行うそれぞれ年度に対応させてヒストグラムにより示している。なお、図8に示す例では、建替コストA(y)として固定値を用いているが、建替コストA(y)を建替えを行う年度yに対応して変化させるようにしてもよい。
Next, with respect to the building 10 in which a certain level of maintenance is performed, an example of the fluctuation of the total sum T (y) for each rebuilding scenario when changing the rebuilding time y from the first year to the 30th year is shown. .
FIG. 8 is an explanatory view showing a first example of the accumulated amount T (y) for each rebuilding scenario.
In FIG. 8, the horizontal axis of the graph indicates the rebuilding period (after y) from the first year to the 30th year, and the vertical axis indicates the accumulated amount T in the unit of “1,000 yen / m 2 ”. There is. And, in the example shown in FIG. 8, the cumulative sum T (y) for each rebuilding scenario assuming that rebuilding is performed in the y-th year is shown by a histogram corresponding to each fiscal year to be rebuilt. . Although the fixed value is used as the rebuilding cost A (y) in the example shown in FIG. 8, the rebuilding cost A (y) may be changed according to the year y in which the rebuilding is performed. .

図8に示す第1の例では、1年目、7年目、11年目に建替えるシナリオの累計額T(y)が最小になり、1年目、7年目、11年目に建替えを実施するとコストを抑制できるという結果を示している。また、17年目後以降、緩やかに累計額T(y)が増加していくことが読み取れる。このため、図8に示す第1の例では、建替えを行うのであれば16年以内に行うと効果的であることが分かる。このことから一定の整備が行われている施設については、現時点では施設寿命の延命化を図ることが有効であるが、中期的に建替えを視野に入れた建物整備計画を立案するべきという結果が示されている。
このようにして、支援システム100は、無駄を省いた建物整備計画の立案を支援する。また、支援システム100は、建物10についての最適な建替時期を提示するので、建物10の長期整備計画を立案する際の精度が向上する。
In the first example shown in FIG. 8, the cumulative sum T (y) of the scenarios to be rebuilt in the first, seventh, and eleventh years is the smallest, and the first, seventh, and eleventh years are constructed. It shows the result that the cost can be reduced by implementing replacement. In addition, it can be seen that the cumulative sum T (y) gradually increases after the 17th year. For this reason, in the first example shown in FIG. 8, it can be seen that it is effective to carry out the replacement within 16 years if rebuilding is performed. From this, it is effective at present to extend the service life of facilities for which maintenance has been carried out, but as a result, it is necessary to draw up a building maintenance plan with a view to rebuilding in the medium term It is shown.
In this manner, the support system 100 supports the creation of a building maintenance plan that has eliminated waste. In addition, since the support system 100 presents the optimal rebuilding time for the building 10, the accuracy in creating a long-term maintenance plan for the building 10 is improved.

(候補期間の算定)
ところで、図8に示す第1の例の場合、支援システム100は、建物の建替えを行うのに最も適した年度は、1年目と、7年目と、11年目とであり、また、16年目以前に建替えを実施するのであれば、コストを抑制できるという結果を提示している。つまり、図8の例の場合、建物の建替えを行うのに適した年度は、30年間の検討期間中の比較的広い範囲に分散している。このため、建物10の建替えを実施する年度は、建物整備計画や予算計画等に応じて、柔軟に選択することができる。
(Calculation of candidate period)
By the way, in the case of the first example shown in FIG. 8, in the support system 100, the years most suitable for rebuilding a building are the first year, the seventh year, and the eleventh year, and If the rebuilding is carried out before the 16th year, the results show that the cost can be reduced. That is, in the case of the example of FIG. 8, the year suitable for rebuilding a building is dispersed in a relatively wide range during the 30-year examination period. Therefore, in the year in which the building 10 is to be rebuilt, it can be selected flexibly according to the building maintenance plan, the budget plan, and the like.

しかしながら、建物の建替えを行うのに適した年度は、狭い範囲の期間に限定される場合がある。例えば、図9は、建替シナリオ毎の累計額T(y)の第2の例を示す説明図である。この図9に示す例は、建替えを実施するに最も適した年度(推奨年度)が8年目の例である。
この図9に示す例の場合、建物の建替えは、累計額T(y)が最小になる8年目に実施されること望まれるが、予算計画の都合等により実施できない場合もある。このため、支援システム100の推奨期間算定部130は、建替えを実施するのに適する候補の期間(候補期間)を算定して提示する。
However, the year suitable for rebuilding a building may be limited to a narrow period. For example, FIG. 9 is an explanatory view showing a second example of the accumulated amount T (y) for each rebuilding scenario. The example shown in FIG. 9 is an example in which the year most suitable for carrying out the rebuilding (recommended year) is the eighth year.
In the case of the example shown in FIG. 9, although rebuilding of a building is desired to be implemented in the eighth year when the cumulative sum T (y) is minimized, it may not be possible due to reasons such as budget planning. Therefore, the recommended period calculation unit 130 of the support system 100 calculates and presents candidate periods (candidate periods) suitable for implementing rebuilding.

図10は、候補期間の第1の算定例を示す説明図である。
この図10に示す例において、支援システム100は、建物10の建て替え実施の推奨年度として、累計額T(y)が最小値Tminとなる8年目を算定する。また、支援システム100は、建替えを実施するのに適する候補期間を算定する。
この候補期間の算定は、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax1−Tmin1)に基づいて、下記の式(4)に基づいて行われる。
FIG. 10 is an explanatory diagram of a first calculation example of the candidate period.
In the example illustrated in FIG. 10, the support system 100 calculates, as a recommended year for rebuilding the building 10, the eighth year in which the accumulated value T (y) is the minimum value Tmin. Further, the support system 100 calculates a candidate period suitable for implementing a rebuild.
The calculation of the candidate period is performed based on the following equation (4) based on the difference Δ (= Tmax1−Tmin1) between the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y).

T(y)−Tmin<(Tmax−Tmin)×p ・・・(4)、
ここで、「T(y):y年目に建替えを実施する建替シナリオにおけるコストの累計額」、「Tmin:累計額T(y)の最少値」、「Tmax:累計額T(y)の最大値」、「p:定数(「p=0.2」等の1以下の正の値)」、である。
つまり、「Tmin+(Tmax−Tmin)×p」が、候補期間を算定する閾値になる。支援システム100の推奨期間算定部130は、累計額T(y)が閾値よりも小さい年度を候補年度と算定する。また、支援システム100は、候補年度と推奨年度とを含む期間を候補期間として算定する。
T (y) −Tmin <(Tmax−Tmin) × p (4),
Here, “T (y): accumulated cost in the rebuilding scenario to be rebuilt in the y-th year”, “Tmin: minimum value of the accumulated sum T (y)”, “Tmax: accumulated sum T (y) Maximum value of), "p: a constant (a positive value of 1 or less such as" p = 0.2 ")".
That is, “Tmin + (Tmax−Tmin) × p” is a threshold for calculating the candidate period. The recommended period calculation unit 130 of the support system 100 calculates a year whose accumulated amount T (y) is smaller than a threshold as a candidate year. Further, the support system 100 calculates a period including the candidate year and the recommended year as a candidate period.

図10に示す例では、斜線で網掛けして示す「8年目の建替シナリオの累計額T(8)」が最小になり、この8年目が建替えを行う推奨年度になる。そして、点々模様で網掛けして示す「6年目、7年目、9年目、10年目の累計額T(y)」が式(4)の関係を満たし、この「6年目、7年目、9年目、10年目」が候補年度となる。そして、推奨期間算定部130は、推奨年度(8年目)と、候補年度(6年目、7年目、9年目、10年目)とを含む期間を、建替えを実施するのに適した推奨する候補期間201として算定する。   In the example shown in FIG. 10, the “cumulative sum T (8) of rebuilding scenarios for the eighth year” shown by hatching is minimized, and the eighth year is the recommended year for rebuilding. And "the accumulated sum T (y) of the sixth year, the seventh year, the ninth year, the tenth year" shown by shading with dotted patterns satisfies the relation of the formula (4), and this "the sixth year, The seventh, ninth, and tenth years are the candidate years. Then, the recommended period calculation unit 130 carries out rebuilding of a period including the recommended year (eighth year) and the candidate year (sixth, seventh, ninth, tenth year). Calculate as a suitable recommended candidate period 201.

そして、支援システム100は、例えば、建替シナリオ毎の累計額T(y)のヒストグラムを表示部162に表示する。このヒストグラムを表示する際に、支援システム100は、推奨年度の累計額T(y)の部分と、候補年度の累計額T(y)の部分と、その他の年度の累計額T(y)の部分と、を区別できるよう表示する。例えば、支援システム100は、推奨年度(8年目)の累計額T(y)の部分を濃青色で表示し、候補年度(6年目、7年目、9年目、10年目)の累計額T(y)の部分を薄い青色で表示する。また、支援システム100は、例えば、推奨年度と候補年度とを除くその他の年度における累計額T(y)の部分を黄色(或いは灰色)で表示する。また、候補年度(6年目、7年目、9年目、10年目)の累計額T(y)の部分は、累計額T(y)が小さいほど色を濃くする等、累計額T(y)の大きさに応じて色の濃淡を変えて表示してもよい。
これにより、支援システム100は、所定の検討期間内において建替えを実施するのに適した候補期間を分かり易く提示できる。
Then, the support system 100 displays, for example, a histogram of the accumulated amount T (y) for each rebuilding scenario on the display unit 162. When displaying this histogram, the support system 100 includes a portion of the accumulated amount T (y) of the recommended year, a portion of the accumulated amount T (y) of the candidate year, and an accumulated amount T (y) of the other years. Display to distinguish the part. For example, the support system 100 displays the portion of the total sum T (y) of the recommended year (eighth year) in dark blue, and for the candidate year (sixth, seventh, ninth, tenth year). The portion of the accumulated amount T (y) is displayed in light blue. In addition, the support system 100 displays, for example, the portion of the accumulated amount T (y) in the other years excluding the recommended year and the candidate year in yellow (or gray). In addition, the portion of the accumulated amount T (y) of the candidate year (sixth, seventh, ninth, tenth year) is such that the smaller the accumulated amount T (y), the darker the color, etc. Depending on the size of (y), the color shade may be changed and displayed.
Thereby, support system 100 can present a candidate period suitable for carrying out rebuilding within a predetermined examination period in an easy-to-understand manner.

また、例えば、支援システム100は、候補期間201を表示する場合、推奨年度(8年目)を示す数字「8」と、候補年度(6年目、7年目、9年目、10年目)を示す数字「6、7、9、10」とを、青色の数字で表示するとともに、他の年度の数字を黒色で表示する。また、例えば、支援システム100は、候補期間201の数字「6、7、8、9、10」を方形の枠線により囲んで表示し、推奨年度の数字「8」を赤丸で囲んで表示する。
なお、推奨年度の累計額T(y)と、候補年度の累計額T(y)、その他の年度の累計額T(y)を区別して表示する方法は、ヒストグラムを色分けして表示する他に種々の方法により表示することができる。候補期間201の表示方法についても同様である。
また、推奨年度と、候補年度と、候補期間とは、必ずしもヒストグラムの形式で表示する必要はなく、例えば、後述する図13に示すように、検討期間nに対応させて年度で表示するようにしてもよい。
Further, for example, when the support system 100 displays the candidate period 201, the numeral “8” indicating the recommended year (eighth year) and the candidate year (sixth, seventh year, ninth year, tenth year) The numbers “6, 7, 9, 10” indicating) are displayed in blue and the numbers of other fiscal years are displayed in black. Also, for example, the support system 100 displays the numbers “6, 7, 8, 9, 10” of the candidate period 201 by enclosing them with a rectangular frame, and displays the number “8” of the recommended year by encircling a red circle. .
In addition, the method to distinguish and display the accumulated sum T (y) of the recommended year, the accumulated sum T (y) of the candidate year, and the accumulated sum T (y) of the other years is displayed by color-coding the histogram. It can be displayed by various methods. The same applies to the display method of the candidate period 201.
In addition, the recommended year, the candidate year, and the candidate period do not necessarily have to be displayed in the form of a histogram, and for example, as shown in FIG. May be

また、図10に示す例は、30年の検討期間内において、1つの候補期間201のみが算定された例であるが、複数の候補期間が算定される場合もある。
例えば、図11は、候補期間の第2の算定例を示す説明図である。この図11に示す例は、候補期間201と候補期間202との2つの候補期間が算定された例である。このように、候補期間は、2以上に分かれて算定されることがある。
Further, although the example shown in FIG. 10 is an example in which only one candidate period 201 is calculated within the 30-year examination period, there may be cases where a plurality of candidate periods are calculated.
For example, FIG. 11 is an explanatory view of a second calculation example of the candidate period. The example shown in FIG. 11 is an example in which two candidate periods of the candidate period 201 and the candidate period 202 are calculated. Thus, the candidate period may be calculated separately in two or more.

これにより、支援システム100は、検討対象となる建物10について、所定の検討期間n内において建替えを実施するのに適した期間を候補期間201として提示できる。このため、建物10の所有者は、施設整備計画や予算計画の都合等により、建物10の建替えを実施するのに最も適した推奨年度に実施することができない場合においても、建替えを実施するのに適した候補期間201を確認して、建替えを実施する時期を柔軟に選択することができる。   As a result, the support system 100 can present, as the candidate period 201, a period suitable for performing rebuilding within the predetermined examination period n for the building 10 to be examined. For this reason, the owner of the building 10 carries out the rebuilding even when it can not be implemented in the recommended year most suitable for implementing the rebuilding of the building 10 due to the facility maintenance plan and the budget plan. It is possible to flexibly select the time to carry out the rebuilding by confirming the candidate period 201 which is suitable for performing.

[第2実施形態]
第1実施形態では、1つの建物について、検討期間nにおいて建替えを実施するのに適した候補期間を算定する例について説明したが、本発明の第2実施形態では、複数の建物について、候補期間を算定する例について説明する。
なお、第2実施形態の支援システムの構成は、図2に示す第1実施形態の支援システム100と基本的に同じ構成である。但し、第2実施形態の支援システム100は、費用算定部120が複数の建物のそれぞれについて建替シナリオ毎の累計額T(y)の算出を行う点が異なる。また、第2実施形態の支援システム100は、推奨期間算定部130が複数の建物のそれぞれについて建替えを実施するのに適した候補期間の算定を行う点が異なる。
Second Embodiment
In the first embodiment, an example of calculating a candidate period suitable for performing rebuilding in the examination period n for one building has been described, but in the second embodiment of the present invention, candidates for a plurality of buildings are considered. An example of calculating a period will be described.
The configuration of the support system of the second embodiment is basically the same as that of the support system 100 of the first embodiment shown in FIG. However, the support system 100 of the second embodiment is different in that the cost calculation unit 120 calculates the total sum T (y) for each of the plurality of buildings for each rebuilding scenario. Further, the support system 100 of the second embodiment is different in that the recommended period calculation unit 130 calculates a candidate period suitable for implementing rebuilding for each of a plurality of buildings.

このように、複数の建物についての候補期間を算定する理由は、各建物について累計額T(y)が最も少ない年度を最適な推奨年度として算定すると、推奨年度が重なることが有るためである。これに対処するため、第2実施形態の支援システム100では、複数の建物のそれぞれに対して、建替えに適する候補期間を算定する。   Thus, the reason why the candidate periods for a plurality of buildings are calculated is that when the year having the smallest accumulated amount T (y) for each building is calculated as the optimum recommended year, the recommended years may overlap. In order to cope with this, in the support system 100 of the second embodiment, candidate periods suitable for rebuilding are calculated for each of a plurality of buildings.

図12は、第2実施形態における候補期間の算定例を示す説明図である。この図12において、図12(A)は、建物10−1に対する候補期間の算定例を示し、図12(B)は、建物10−2における候補期間の算定例を示している。
なお、図12では、2つの建物10−1と建物10−2とを例にして、それぞれの候補期間を算定する例を示しているが、3つ以上の複数の建物である建物10−1から建物10−N(Nは3以上の整数)のそれぞれに対して、候補期間を算定する場合がある。
FIG. 12 is an explanatory view showing an example of calculation of candidate periods in the second embodiment. In FIG. 12, FIG. 12 (A) shows an example of calculation of a candidate period for the building 10-1, and FIG. 12 (B) shows an example of calculation of a candidate period in the building 10-2.
In addition, although the example which calculates each candidate period is shown in FIG. 12 by making the two buildings 10-1 and the building 10-2 into an example, the buildings 10-1 which are three or more multiple buildings are shown. The candidate period may be calculated for each of the buildings 10-N (N is an integer of 3 or more).

図12(A)に示す建物10−1において、建替シナリオ毎の累計額T(y)は、検討期間の開始年から8年目(y=8)に建替えを行う建替シナリオの場合に、最小値Tmin1になる。また、累計額T(y)は、30年目(y=30)に建替えを行う建替シナリオの場合に、最大値Tmax1になる。そして、建物10−1における建替シナリオ毎の累計額T(y)の差額Δは、「Δ=Tmax1−Tmin1」になる。
そして、図12(A)に示す建物10−1についての候補の年(候補期間)の算定は、下記の式(5)に基づいて行われる。
In the building 10-1 shown in FIG. 12A, the total sum T (y) for each rebuilding scenario is a rebuilding scenario in which rebuilding is performed in the eighth year (y = 8) from the start year of the examination period. To the minimum value Tmin1. Further, the cumulative sum T (y) is the maximum value Tmax1 in the case of a rebuilding scenario in which rebuilding is performed in the 30th year (y = 30). Then, the difference Δ between the accumulated amounts T (y) for each rebuilding scenario in the building 10-1 is “Δ = Tmax1−Tmin1”.
And calculation of the year (candidate period) of a candidate about building 10-1 shown in Drawing 12 (A) is performed based on a following formula (5).

T(y)−Tmin1<(Tmax1−Tmin1)×p ・・・(5)、
ここで、pは、例えば、「p=0.2」等の1以下の正の値である。
T (y) −Tmin1 <(Tmax1−Tmin1) × p (5),
Here, p is, for example, a positive value of 1 or less such as “p = 0.2”.

そして、上記式(5)により、建物10−1の候補期間211は、6年目から10年目までとなる。また、最も累計額T(y)が少ない8年目が推奨年度になる。   And candidate period 211 of building 10-1 will be from the sixth year to the tenth year according to the above-mentioned formula (5). In addition, the eighth year, in which the accumulated amount T (y) is the smallest, is the recommended year.

そして、図12(B)に示す建物10−2において、建替シナリオ毎の累計額T(y)は、検討期間の開始年から10年目(y=10)に建替えを行う建替シナリオの場合に、最小値Tmin2になる。また、累計額T(y)は、30年目(y=30)に建替えを行う建替シナリオの場合に、最大値Tmax2になる。そして、建物10−2における累計額T(y)の差額Δは、「Δ=Tmax2−Tmin2」になる。   And in building 10-2 shown in FIG. 12 (B), the total amount T (y) for each rebuilding scenario is a rebuilding scenario in which rebuilding is performed in the tenth year (y = 10) from the start year of the examination period. In this case, the minimum value Tmin2 is obtained. The cumulative sum T (y) is the maximum value Tmax2 in the case of a rebuilding scenario in which rebuilding is performed in the 30th year (y = 30). And difference delta of total sum T (y) in building 10-2 serves as "delta = Tmax2-Tmin2."

そして、図12(B)に示す建物10−2についての候補の年(候補期間)の算定は、下記の式(6)に基づいて行われる。   And calculation of the year (candidate period) of a candidate about building 10-2 shown in Drawing 12 (B) is performed based on a following formula (6).

T(y)−Tmin2<(Tmax2−Tmin2)×p ・・・(6)、
ここで、pは、例えば、「p=0.2」等の1以下の正の値である。
T (y) -Tmin2 <(Tmax2-Tmin2) * p (6),
Here, p is, for example, a positive value of 1 or less such as “p = 0.2”.

そして、上記式(6)により、建物10−2の候補期間212は、7年目から13年目までとなる。また、最も累計額T(y)が少ない10年目が推奨年度になる。   And candidate period 212 of building 10-2 will be from the seventh year to the 13th year by the above-mentioned formula (6). In addition, the 10th year with the smallest accumulated amount T (y) is the recommended year.

そして、図13は、複数の建物のそれぞれの候補期間の例を示す説明図である。なお、この図13では、建物10−Nにおける候補期間213を、仮に「11年目から16年目」であるものとして示している。
この図13に示すように、建物10−1の候補期間211は、6年目から10年目となる。また、最も累計額T(y)が少ない8年目が推奨年度になる。
また、建物10−2の候補期間212は、7年目から13年目となる。また、最も累計額T(y)が少ない10年目が推奨年度になる。
また、建物10−Nの候補期間213は、11年目から16年目となる。また、最も累計額T(y)が少ない14年目が推奨年度になる。
And FIG. 13 is explanatory drawing which shows the example of the candidate period of each of several buildings. In FIG. 13, the candidate period 213 in the building 10 -N is temporarily assumed to be “the 11th year to the 16th year”.
As shown in FIG. 13, the candidate period 211 of the building 10-1 is from the sixth year to the tenth year. In addition, the eighth year, in which the accumulated amount T (y) is the smallest, is the recommended year.
In addition, the candidate period 212 of the building 10-2 is the seventh to the thirteenth years. In addition, the 10th year with the smallest accumulated amount T (y) is the recommended year.
Also, the candidate period 213 of the building 10-N is from the 11th year to the 16th year. In addition, the 14th year with the smallest accumulated amount T (y) is the recommended year.

例えば、支援システム100は、この図13に示す候補期間の情報を表示部162に表示する。これにより、支援システム100は、建物10−1、建物10−2、・・・、建物10−Nのそれぞれについて、建替えを実施するのに適した候補期間を分かり易く提示することができる。このため、支援システム100は、建物10−1から建物10−Nの複数の建物の建替えを含む施設整備計画の立案を支援することができる。   For example, the support system 100 displays the information of the candidate period shown in FIG. 13 on the display unit 162. As a result, the support system 100 can easily present candidate periods suitable for rebuilding for each of the buildings 10-1, 10-2, ..., and 10-N. Therefore, the support system 100 can support the planning of a facility maintenance plan including rebuilding of a plurality of buildings from the building 10-1 to the building 10-N.

また、図14は、第2実施形態の支援システム100における処理の流れを示すフローチャートである。以下、図14を参照して、第2実施形態の支援システム100における処理の流れについて説明する。
本第2実施形態の支援システム100において、検討対象の建物10−1から建物10−Nについての処理が開始される(ステップS200)。
続いて、建替シナリオ生成部110は、建物10−1から建物10−Nの複数の建物に共通する検討期間を設定する。この検討期間は、建物10−1から建物10−Nについての機能を維持する期間として設定される。例えば、検討期間は、現在から将来に向けての30年間として年単位で設定される(ステップS210)。
Moreover, FIG. 14 is a flowchart which shows the flow of the process in the assistance system 100 of 2nd Embodiment. The flow of processing in the support system 100 of the second embodiment will be described below with reference to FIG.
In the support system 100 according to the second embodiment, the process for the building 10-1 to be considered and the building 10-N is started (step S200).
Subsequently, the rebuilding scenario generation unit 110 sets a study period common to a plurality of buildings from the building 10-1 to the building 10-N. The examination period is set as a period for maintaining the functions of the buildings 10-1 to 10-N. For example, the examination period is set on a yearly basis as 30 years from the present to the future (step S210).

続いて、建替シナリオ生成部110は、30年間の検討期間において、建物10−1から建物10−Nのそれぞれに対して、建替時期を変化させた場合の建替シナリオを作成する。つまり、建替シナリオ生成部110は、建物10−1から建物10−Nのそれぞれ対して、初年度に建替えを実施する建替シナリオから、30年目の最終年度に建替えを実施する建替シナリオまでの、それぞれの建替シナリオを作成する(ステップS220)。
続いて、費用算定部120は、建物10−1から建物10−Nのそれぞれにおいて、建替時期が異なる建替シナリオ毎に、建物10の維持コストと、建替えに掛る建替コストとを含むコスト(費用)の累計額T(y)を算出する(ステップS230)。
Subsequently, the rebuilding scenario generation unit 110 creates a rebuilding scenario when the rebuilding time is changed for each of the building 10-1 to the building 10-N in the 30-year examination period. That is, the rebuilding scenario generation unit 110 rebuilds in the final year of the 30th year from the rebuilding scenario in which rebuilding is performed in the first year for each of the buildings 10-1 to 10-N. Each rebuilding scenario up to the replacement scenario is created (step S220).
Subsequently, the cost calculation unit 120 includes the maintenance cost of the building 10 and the rebuilding cost for rebuilding for each of the rebuilding scenarios having different rebuilding times in each of the building 10-1 to the building 10-N. A cumulative amount T (y) of costs (expenses) is calculated (step S230).

続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、累計額T(y)が最も少ない最小値Tminになる年度を、建替えを実施するのに最も適した推奨年度として算定する(ステップS240)。
続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)を算出する(ステップS250)。
Subsequently, the recommended period calculation unit 130 is most suitable for rebuilding the year in which the accumulated amount T (y) is the smallest minimum value Tmin in each of the buildings 10-1 to 10-N. Calculate as a recommended year (step S240).
Subsequently, the recommended period calculation unit 130 calculates the difference Δ (= Tmax−Tmin) between the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y) in each of the buildings 10-1 to 10-N. (Step S250).

続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、それぞれの累計額T(y)の最小値Tminと差額Δ(=Tmax−Tmin)とから、
閾値「Tmin+(Tmax−Tmin)×p」、を算出する。
ここで、pは、例えば、「p=0.2」等の1以下の正の値である(ステップS260)。
続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、それぞれの閾値「Tmin+(Tmax−Tmin)×p」に基づいて、累計額T(y)が閾値よりも小さい年度を候補年度として算定する(ステップS270)。
続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、推奨年度と候補年度とを含む期間を、候補期間として算定する(ステップS280)。
Subsequently, in each of the buildings 10-1 to 10-N, the recommended period calculation unit 130 calculates the minimum value Tmin of the total sum T (y) and the difference Δ (= Tmax−Tmin).
The threshold “Tmin + (Tmax−Tmin) × p” is calculated.
Here, p is, for example, a positive value of 1 or less such as “p = 0.2” (step S260).
Subsequently, in each of the buildings 10-1 to 10-N, the recommended period calculation unit 130 determines that the total sum T (y) is greater than the threshold based on the respective threshold “Tmin + (Tmax−Tmin) × p”. A small year is calculated as a candidate year (step S270).
Subsequently, the recommended period calculation unit 130 calculates a period including the recommended year and the candidate year as a candidate period in each of the buildings 10-1 to 10-N (step S280).

続いて、作図部140は、建物10−1から建物10−Nのそれぞれにおける候補期間等を表示する図表を生成する。支援システム100は、この図表を表示部162に表示する(ステップS290)。
上記ステップS290において図表を表示部162に表示した後に、支援システム100は、処理を終了する(ステップS300)。
これにより、支援システム100は、建物10−1から建物10−Nの複数の建物のそれぞれについて、所定の検討期間内において建替えを実施するのに適した期間を分かり易く提示できる。
Subsequently, the drawing unit 140 generates a chart that displays candidate periods and the like in each of the buildings 10-1 to 10-N. The support system 100 displays this chart on the display unit 162 (step S290).
After displaying the chart on the display unit 162 in step S290, the support system 100 ends the process (step S300).
Thus, the support system 100 can present a period suitable for implementing rebuilding within a predetermined examination period for each of the buildings 10-1 to 10-N.

[第3実施形態]
第2実施形態の支援システム100では、建物10−1から建物10−Nの複数の建物のそれぞれにおいて、累計額T(y)の最大値Tmaxと最小値Tminとに基づいて閾値「Tmin+(Tmax−Tmin)×p」を定め、この閾値に基づいて建物毎に候補期間を算定している。しかしながら、各建物における累計額T(y)と累計額T(y)の最大値Tmaxと累計額T(y)の最小値Tminとについて、建物10−1から建物10−Nの建物毎に比較すると、対応する値であっても建物毎に大きく異なる場合がある。
この場合、建物の建替えの実施年度を推奨年度と異なる年度に実施する場合に、複数の建物の中でコスト的に大きな影響を与える建物は、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)が大きな建物である。一方、最大値Tmaxと最小値Tminとの差額Δが小さな建物は、建替えの実施年度を推奨年度と異なる年度に実施することにしてもコストに与える影響が小さい。
第3実施形態の支援システムでは、累計額T(y)の差額Δ(=Tmax−Tmin)が、検討対象の複数の建物の中で最大の値になった建物を基準にして、他の建物の候補期間を算定する例について説明する。
Third Embodiment
In the support system 100 according to the second embodiment, the threshold value “Tmin + (Tmax) is calculated based on the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y) in each of the buildings 10-1 to 10-N. -Tmin) x p "is defined, and the candidate period is calculated for each building based on this threshold value. However, for each building, the building 10-1 to the building 10-N are compared for the cumulative sum T (y) and the maximum value Tmax of the cumulative sum T (y) and the minimum value Tmin of the cumulative sum T (y) in each building. Then, even the corresponding values may differ greatly from one building to another.
In this case, when implementing the rebuilding year of the building in a year different from the recommended year, the buildings having a large cost impact among the multiple buildings are the maximum value Tmax and the minimum value of the cumulative sum T (y). The difference Δ (= Tmax−Tmin) with the value Tmin is a large building. On the other hand, a building having a small difference Δ between the maximum value Tmax and the minimum value Tmin has little influence on the cost even if the year of implementation of the rebuilding is different from the year of recommendation.
In the support system of the third embodiment, another building is used based on the building in which the difference Δ (= Tmax−Tmin) of the accumulated amount T (y) is the largest among the plurality of buildings to be considered. An example of calculating the candidate period of

なお、第3実施形態の支援システムの構成は、図2に示す第1実施形態の支援システム100と基本的に同じ構成である。但し、第3実施形態の支援システム100では、費用算定部120が建物10−1から建物10−Nの複数の建物のそれぞれについて建替シナリオ毎の累計額T(y)の算出を行う点が異なる。また、推奨期間算定部130が、建物10−1から建物10−Nの複数の建物のそれぞれについて候補期間の算定を行う場合に、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)が最も大きな建物を基準として算定する点が異なる。   The configuration of the support system of the third embodiment is basically the same as that of the support system 100 of the first embodiment shown in FIG. However, in the support system 100 of the third embodiment, the cost calculation unit 120 calculates the total sum T (y) for each rebuilding scenario for each of a plurality of buildings from the building 10-1 to the building 10-N. It is different. In addition, when the recommended period calculation unit 130 calculates candidate periods for each of a plurality of buildings from the building 10-1 to the building 10-N, the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y) The difference is that the difference Δ (= Tmax−Tmin) is calculated on the basis of the largest building.

図15は、第3実施形態における候補期間の算定例を示す説明図である。この図15において、図15(A)は、例えば、6階建て等の比較的大きな建物10−1の例であり、図16(B)は、3階建て等の比較的小さい建物10−3の例である。
そして、図15(A)において、建物10−1の建替シナリオ毎の累計額T(y)の最大値がTmax1であり、最小値がTmin1であり、差額Δは、「Tmax1−Tmin1」になる。
一方、図15(B)において、建物10−3の建替シナリオ毎の累計額T(y)の最大値がTmax3であり、最小値がTmin3であり、差額Δは、「Tmax3−Tmin3」になる。
そして、建物10−1における累計額T(y)の差額Δ(=Tmax1−Tmin1)が、建物10−3における累計額T(y)の差額Δ(=Tmax3−Tmin3)よりも大きく、建物10−1の差額Δが、この例における最大の差額Δmaxになる。
なお、図15では、2つの建物10−1と建物10−2との候補期間を算定する例を示しているが、3つ以上の複数の建物である建物10−1から建物10−N(Nは3以上の整数)のそれぞれに対して、候補期間を算定する場合がある。
FIG. 15 is an explanatory view showing an example of calculation of candidate periods in the third embodiment. In FIG. 15, FIG. 15 (A) is an example of a relatively large building 10-1 such as six floors, for example, and FIG. 16 (B) is a relatively small building 10-3 such as three floors. An example of
Then, in FIG. 15A, the maximum value of the accumulated sum T (y) for each rebuilding scenario of the building 10-1 is Tmax1, the minimum value is Tmin1, and the difference Δ is “Tmax1−Tmin1”. Become.
On the other hand, in FIG. 15B, the maximum value of the total sum T (y) for each rebuilding scenario of the building 10-3 is Tmax3, the minimum value is Tmin3, and the difference Δ is “Tmax3-Tmin3”. Become.
Then, the difference Δ (= Tmax1-Tmin1) of the accumulated sum T (y) in the building 10-1 is larger than the difference Δ (= Tmax3-Tmin3) of the accumulated sum T (y) in the building 10-3. The difference Δ of -1 is the maximum difference Δmax in this example.
In addition, although the example which calculates the candidate period of the two buildings 10-1 and the building 10-2 is shown in FIG. 15, the building 10-1 to the buildings 10-N which are three or more multiple buildings are shown. A candidate period may be calculated for each of N is an integer of 3 or more.

図15に示す例において、推奨期間算定部130は、建物10−1の累計額T(y)の差額Δmax(=Tmax1−Tmin1)に基づいて、「Δmax×p」を代表値に定める。ここで、pは、例えば、「p=0.2」等の1以下の正の値である。
つまり、Δmax×pは、「Δmax×p=(Tmax1−Tmin1)×p」である。
そして、図15(A)に示す建物10−1の候補期間を算定する場合、推奨期間算定部130は、建物10−1自身から算出した代表値「Δmax×p」に基づいて、閾値「Tmin1+Δmax×p」を定める。
推奨期間算定部130は、建物10−1について、累計額T(y)が閾値「Tmin1+Δmax×p」よりも小さい年度を候補期間221として算定する。この図15(A)に示す例では、建物10−1の建替えの候補期間221は、6年目から10年目までの5年間になる。
In the example illustrated in FIG. 15, the recommended period calculation unit 130 sets “Δmax × p” as a representative value based on the difference Δmax (= Tmax1−Tmin1) of the accumulated amount T (y) of the building 10-1. Here, p is, for example, a positive value of 1 or less such as “p = 0.2”.
That is, Δmax × p is “Δmax × p = (Tmax1−Tmin1) × p”.
And when calculating the candidate period of the building 10-1 shown to FIG. 15 (A), the recommendation period calculation part 130 is based on the representative value "(DELTA) max xp" calculated from building 10-1 itself, and threshold value "Tmin1 + (DELTA) max Define xp.
The recommended period calculation unit 130 calculates, for the building 10-1, a year in which the accumulated amount T (y) is smaller than the threshold value “Tmin1 + Δmax × p” as the candidate period 221. In the example illustrated in FIG. 15A, the candidate period 221 for rebuilding the building 10-1 is five years from the sixth year to the tenth year.

一方、図15(B)に示す建物10−3の場合、推奨期間算定部130は、建物10−1の候補期間の算定に用いた代表値「Δmax×p」を用いる。
そして、推奨期間算定部130は、建物10−3について、累計額T(y)が閾値「Tmin3+Δmax×p」よりも小さい年度を候補期間222として算定する。この図15(B)に示す例では、建物10−3の建替えの候補期間222は、2年目から16年目までの15年間になる。
On the other hand, in the case of the building 10-3 illustrated in FIG. 15B, the recommended period calculating unit 130 uses the representative value “Δmax × p” used for calculating the candidate period of the building 10-1.
Then, for the building 10-3, the recommended period calculation unit 130 calculates a year in which the cumulative sum T (y) is smaller than the threshold “Tmin3 + Δmax × p” as the candidate period 222. In the example shown in FIG. 15B, the candidate period 222 for rebuilding the building 10-3 is 15 years from the second year to the sixteenth year.

なお、図16は、建物10−3自身の累計額T(y)の差額Δを用いた候補期間の算定例を示す説明図である。この図16に示す例は、建物10−3の候補期間を算定する際に、建物10−3自身の累計額T(y)の差額Δ(=Tmax3−Tmin3)から算出した閾値「Tmin3+(Tmax3−Tmin3)×p」を用いて、候補期間223を算定した例である。
この図16に示す例では、建物10−3の建替の候補期間223は、7年目から13年目までの7年間となる。
In addition, FIG. 16 is explanatory drawing which shows the example of calculation of the candidate period using difference (DELTA) of total sum T (y) of building 10-3 self. In the example shown in FIG. 16, when calculating the candidate period of the building 10-3, the threshold “Tmin3 + (Tmax3) calculated from the difference Δ (= Tmax3−Tmin3) of the accumulated sum T (y) of the building 10-3 itself This is an example in which the candidate period 223 is calculated using −Tmin3) × p ”.
In the example illustrated in FIG. 16, the candidate period 223 for rebuilding the building 10-3 is seven years from the seventh year to the thirteenth year.

そして、図17は、建物10−1の累計額T(y)の差額Δmaxを用いる場合と建物10−3自身の累計額T(y)の差額Δを用いる場合との候補期間の算定結果の違いを示す説明図である。
図17(A)に示すように、建物10−1の累計額T(y)の差額Δmax(=Tmax1−Tmin1)から算出される代表値「Δmax×p」を用いて、建物10−3の候補期間222を算定する場合、候補期間222は、2年目から16年目の15年間になる。
一方、建物10−3自身の累計額T(y)の差額Δ(=Tmax3−Tmin3)から算出される数値「(Tmax3−Tmin3)×p」を用いる場合、候補期間223は、7年目から13年目の7年間になる。
And FIG. 17 shows calculation results of candidate periods when using the difference Δmax of the accumulated sum T (y) of the building 10-1 and when using the difference Δ of the accumulated sum T (y) of the building 10-3 itself. It is an explanatory view showing a difference.
As shown in FIG. 17A, using the representative value “Δmax × p” calculated from the difference Δmax (= Tmax1−Tmin1) of the accumulated sum T (y) of the building 10-1, the building 10-3 is obtained. When calculating the candidate period 222, the candidate period 222 is 15 years from the second year to the 16th year.
On the other hand, when using the numerical value “(Tmax3-Tmin3) × p” calculated from the difference Δ (= Tmax3-Tmin3) of the accumulated sum T (y) of the building 10-3 itself, the candidate period 223 starts from the seventh year. It will be seven years of the thirteenth year.

このように、第3実施形態の支援システム100は、建物10−1の累計額T(y)の差額Δmaxから得られる代表値「Δmax×p」を用いて、建物10−3の候補期間を算出する。これにより、支援システム100は、建物10−3の候補期間を広い範囲の期間に設定することができる。3つ以上の建物10−1から建物10−Nがある場合についても同様である。
なお、建物10−1から建物10−Nの複数の建物がある場合、建物10−1から建物10−Nの建物毎の累計額T(y)の差額Δ(Tmax−Tmin)が異なるため、場合によっては、ある建物の累計額T(y)の差額Δが、代表値「Δmax×p」以下になることもある。このような場合であれば、当該建物の建替えはいつ実施してもよいことになる。
As described above, the support system 100 according to the third embodiment uses the representative value “Δmax × p” obtained from the difference Δmax of the sum T (y) of the buildings 10-1 to select the candidate period of the building 10-3. calculate. Thus, the support system 100 can set the candidate period of the building 10-3 to a wide range of periods. The same applies to the case where there are three or more buildings 10-1 to 10-N.
In the case where there are a plurality of buildings 10-1 to 10-N, the difference Δ (Tmax-Tmin) of the accumulated sum T (y) for each of the buildings 10-1 to 10-N is different, In some cases, the difference Δ of the accumulated sum T (y) of a certain building may be equal to or less than the representative value “Δmax × p”. In such a case, rebuilding of the building may be carried out at any time.

また、図18は、第3実施形態の支援システム100における処理の流れを示すフローチャートである。この図18に示すフローチャートにおいて、ステップS210からステップS240まで処理と、ステップS280からステップS300までの処理とは、図14に示す第2実施形態のフローチャートと同じである。このため、同じ処理内容のステップには同じステップ番号を付して重複する説明は省略する。   FIG. 18 is a flowchart showing the flow of processing in the support system 100 of the third embodiment. In the flowchart shown in FIG. 18, the process from step S210 to step S240 and the process from step S280 to step S300 are the same as the flowchart of the second embodiment shown in FIG. For this reason, the same step number is attached | subjected to the step of the same processing content, and the overlapping description is abbreviate | omitted.

ステップS240において、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、累計額T(y)が最も少ない最小値Tminになる年度を、建替えを実施するのに最も適した推奨年度として算定する(ステップS240)。
続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)を算出する。そして、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおける累計額T(y)の差額Δから、最も大きな差額Δを判定し、この最も大きな差額Δを「差額Δmax」として算定する(ステップS250A)。
In step S240, the recommended period calculation unit 130 is most suitable for rebuilding the year in which the accumulated value T (y) is the smallest minimum value Tmin in each of the buildings 10-1 to 10-N. It is calculated as a recommended year (step S240).
Subsequently, the recommended period calculation unit 130 calculates the difference Δ (= Tmax−Tmin) between the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y) in each of the buildings 10-1 to 10-N. . Then, the recommended period calculation unit 130 determines the largest difference Δ from the difference Δ between the accumulated amounts T (y) in each of the buildings 10-1 to 10-N, and determines the largest difference Δ as the “difference Δmax”. (Step S250A).

続いて、推奨期間算定部130は、最も大きな差額Δmaxから、代表値「Δmax×p」を算出する(ステップS255A)。
続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、それぞれの建物自身の累計額T(y)の最小値Tminと、上記の代表値「Δmax×p」とから、閾値「Tmin+Δmax×p」、を算出する(ステップS260A)。
Subsequently, the recommended period calculation unit 130 calculates a representative value “Δmax × p” from the largest difference Δmax (step S255A).
Subsequently, in each of the buildings 10-1 to 10-N, the recommended period calculation unit 130 calculates the minimum value Tmin of the accumulated sum T (y) of each building itself and the above representative value ".DELTA.max.times.p" From this, the threshold “Tmin + Δmax × p” is calculated (step S260A).

続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、それぞれの閾値「Tmin+Δmax×p」に基づいて、累計額T(y)が閾値よりも小さい年度を候補年度として算定する(ステップS270A)。
続いて、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、推奨年度と候補年度とを含む期間を、候補期間として算定する(ステップS280)。
Subsequently, in each of the buildings 10-1 to 10-N, the recommended period calculation unit 130 selects a year in which the accumulated sum T (y) is smaller than the threshold based on the respective threshold values "Tmin + Δmax × p". (Step S270A).
Subsequently, the recommended period calculation unit 130 calculates a period including the recommended year and the candidate year as a candidate period in each of the buildings 10-1 to 10-N (step S280).

続いて、作図部140は、建物10−1から建物10−Nのそれぞれにおける候補期間等を表示する図表を生成する。支援システム100は、この図表を表示部162に表示する(ステップS290)。
上記ステップS290において図表を表示部162に表示した後に、支援システム100は、処理を終了する(ステップS300)。
これにより、支援システム100は、累計額T(y)の差額Δが小さな建物の建替えの候補期間を算定する場合、当該建物自身の累計額T(y)の差額Δに基づいて候補期間を算定する場合と比較して、より広い範囲の候補期間を算定することができる。
Subsequently, the drawing unit 140 generates a chart that displays candidate periods and the like in each of the buildings 10-1 to 10-N. The support system 100 displays this chart on the display unit 162 (step S290).
After displaying the chart on the display unit 162 in step S290, the support system 100 ends the process (step S300).
Thereby, when the support system 100 calculates a candidate period for rebuilding a building having a small difference Δ of the accumulated sum T (y), the candidate period is set based on the difference Δ of the accumulated sum T (y) of the building itself. A wider range of candidate periods can be calculated compared to when calculating.

(ファシリティ機能、性能、品質のレベル向上の例)
なお、上述の支援システム100の例では、建物10の維持コストと建替コストとに基づいて、建替シナリオ毎の累計額T(y)を算出する例について説明したが、これに限定されない。例えば、費用算定部120は、建物のファシリティ機能、性能、品質のレベルを向上させる場合、この向上の程度を金額に変換して、建替シナリオ毎のコストの累計額T(y)の内数にして算出してもよい。
(Example of level improvement of facility function, performance, quality)
In addition, although the example of the above-mentioned support system 100 demonstrated the example which calculates the sum total T (y) for every rebuilding scenario based on the maintenance cost and rebuilding cost of the building 10, it is not limited to this. For example, when the cost calculation unit 120 improves the level of the facility function, performance, and quality of the building, the degree of this improvement is converted into a monetary amount, and the number of accumulated costs T (y) for each rebuilding scenario It may be calculated.

図19は、ファシリティ機能、性能、品質のレベル向上に掛るコスト情報の設定例を示す説明図である。例えば、支援システム100は、この図19に示す表300を表示部162に表示する。支援システム100は、この表300上の各項目について、修繕・改修により実施するか、建物の建替え時に実施するか、或いは、実施しないかを選択できるように表示する。   FIG. 19 is an explanatory diagram of an example of setting of cost information for improving the level of the facility function, the performance, and the quality. For example, the support system 100 displays the table 300 illustrated in FIG. 19 on the display unit 162. The support system 100 displays that each item on the table 300 can be selected to be implemented by repair / renovation, to be implemented at the time of rebuilding a building, or not to be implemented.

また、支援システム100は、建替えにより実施しようとする項目について、当該項目を実施する際に必要となる建替コストの増加分の金額の情報を、この表300の該当する位置に入力装置163により入力できるように表示する。或いは、支援システム100は、修繕・改修により実施しようとする項目について、当該項目を実施する際に必要となる維持コストの増加分の金額の情報と、実施時期の情報とを、この表300の該当する位置に入力できるように表示する。
そして、例えば、支援システム100は、ある項目についてのコストの増加分の金額が入力された場合に、当該項目が実施される項目であると判定し、増加分の金額が入力されなかった項目については、当該項目が実施されない項目であると判定する。
この図19の表300に入力された金額の情報と、実施時期の情報とは、記憶部150に、「ファシリティ機能、性能、品質に掛るコスト情報158」として記憶される。
Further, with regard to the item to be implemented by rebuilding, the support system 100 inputs information on the amount of increase in the rebuilding cost, which is necessary when implementing the item, to the corresponding position of the table 300 as the input device 163. Display to be able to input by. Alternatively, with regard to the item to be implemented by repair / repair, the support system 100 may obtain information on the amount of increase in maintenance cost required to implement the item and information on the implementation time of the table 300. Display to be able to input at the corresponding position.
Then, for example, when the amount of increase in cost for a certain item is input, the support system 100 determines that the item is an item to be implemented, and the item for which the amount of increase is not input is input. It is determined that the item is not implemented.
The information on the amount of money input in the table 300 of FIG. 19 and the information on the implementation time are stored in the storage unit 150 as “cost information 158 on facility function, performance, and quality”.

図19において、項目1−1の「省エネ機器(LED照明等)の導入」は、例えば、蛍光灯照明をLED照明に変更する際に必要となるコストの情報である。
項目1−2の「リフレッシュルームの設置」は、オフィスワーカの福利厚生のための休憩ルームを新たに設置する際に必要となる設備や什器に掛るコストの情報である。
項目1−3の「収納スペースの増加」は、例えば、1部屋毎に、或いは、複数の部屋毎に収納スペースを増加させる際に必要となるコストの情報である。
In FIG. 19, “introduction of energy saving device (LED illumination etc.)” in item 1-1 is, for example, information on the cost required when changing the fluorescent lamp illumination to the LED illumination.
Item 1-2 “Refreshing Room Installation” is information on the cost of equipment and fixtures required when newly installing a break room for the welfare of an office worker.
Item 1-3 “increase in storage space” is, for example, cost information required to increase the storage space for each room or for each of a plurality of rooms.

また、項目2−1の「電気設備容量の増加」は、例えば、電力会社からの受電電力を増加する際に必要となる受電設備の変更や配電線の変更に掛るコストの情報である。項目2−2の「照明の個別制御の導入」は、照明装置を個別にON/OFFさせる(或いは、調光制御をさせる)際に必要となるコストの情報である。また、項目2−3の「冷暖房設備の個別制御の導入」は、例えば、1部屋毎に、別々に温湿度制御を行う際に必要になるコストの情報である。
なお、上記各項目の内容及び個数は、固定的なものではなく、検討対象となる建物10の態様や建物所有者の経営方針等に応じて柔軟に設定されるものである。
The item 2-1 “increase in electric facility capacity” is, for example, information on the cost of changing the power receiving facility or changing the distribution line, which is required when increasing the received power from the power company. Item 2-2 “Introduction of individual control of illumination” is information on the cost required when individually turning on / off the illumination device (or performing dimming control). In addition, “introduction of individual control of heating and cooling equipment” in item 2-3 is, for example, information on the cost required when performing temperature and humidity control separately for each room.
The contents and the number of the above items are not fixed, and can be set flexibly according to the form of the building 10 to be considered, the management policy of the building owner, and the like.

この図19に示す例では、項目1−1の「省エネ機器(LED照明等)の導入」は、修繕・改修により実施されることが選択され、この「省エネ機器(LED照明等)の導入」に必要となる金額312と、その実施時期313とが表300の該当する位置に入力されている。
また、項目1−2の「リフレッシュルームの設置」は、修繕・改修により実施されることが選択され、この「リフレッシュルームの設置」に必要となる金額314と、その実施時期315とが表300の該当する位置に入力されている。
なお、項目1−3の「収納スペースの増加」は、実施されないため、金額等の情報が入力されていない。
In the example shown in FIG. 19, item 1-1 “Introduction of energy saving equipment (LED lighting etc.)” is selected to be implemented by repair or repair, and this “introduction of energy saving equipment (LED lighting etc)” The necessary amount of money 312 and its implementation time 313 are entered at the corresponding positions in the table 300.
In addition, item 1-2 “Refreshing Room Installation” is selected to be implemented by repair and repair, and the amount 314 required for this “Refreshing Room Installation” and its implementation time 315 are shown in Table 300. Is entered at the corresponding position of.
In addition, since "the increase of a storage space" of the item 1-3 is not implemented, the information of moneys etc. is not input.

そして、項目1−1の「省エネ機器(LED照明等)の導入」に必要となる金額312は、その実施時期313に対応する年度の維持コストの内数として加算される。同様にして、項目1−2の「リフレッシュルームの設置」に必要となる金額314は、その実施時期315に対応する年度の維持コストの内数として加算される。   And amount of money 312 required for "introduction of an energy saving apparatus (LED lighting etc.)" of item 1-1 is added as a number of maintenance costs of the year corresponding to the implementation time 313. Similarly, the amount of money 314 required for “setting up the refresh room” in item 1-2 is added as the number of maintenance costs for the year corresponding to the implementation time 315 thereof.

また、項目2−1の「電気設備容量の増加」と、項目2−2の「照明の個別制御の導入」と、項目2−3の「冷暖房の個別制御の導入」とは、修繕・改修により行うことが選択され、それらを実施する際に必要となる金額と、実施時期とのそれぞれが、表300の該当する位置に入力されている。
そして、項目2−1の「電気設備容量の増加」と、項目2−2の「照明の個別制御の導入」と、項目2−3の「冷暖房の個別制御の導入」とを実施する際に必要となるそれぞれの金額は、それぞれの実施時期に対応する年度の維持コストの内数として加算される。
In addition, item 2-1 "increase of electric equipment capacity", item 2-2 "introduction of individual control of lighting" and item 2-3 "introduction of individual control of heating and cooling" are repair and repair. Is selected, and the amount of money required to perform them and the implementation time are respectively input to the corresponding positions in the table 300.
And when carrying out "increase of electric equipment capacity" of an item 2-1, "introduction of individual control of lighting" of an item 2-2, and "introduction of individual control of an air conditioning and heating" of an item 2-3. Each required amount of money is added as the number of maintenance costs for the year corresponding to each implementation time.

これにより、費用算定部120は、建替シナリオ毎の累計額T(y)を算出する際に、ファシリティ機能、性能、品質のレベルを向上させるために必要な維持コストの増加分と、建替コストの増加分とを含めて累計額T(y)を算出することができる。
このため、支援システム100は、建替シナリオ毎の累計額T(y)を算出する際に、ファシリティ機能、性能、品質のレベル向上に掛るコストを累計額T(y)に盛り込み、コスト化して一元的に評価することができる。
また、建替シナリオ毎の累計額T(y)を算出する際に、ファシリティ機能、性能、品質のレベル向上に掛るコストを累計額T(y)に盛り込むことにより、長期整備計画を立案する際の選択肢を増やすことができる。
Thereby, the cost calculation unit 120 calculates the accumulated cost T (y) for each rebuilding scenario, and increases the maintenance cost required to improve the facility function, performance, and level of quality, and rebuilding. The accumulated amount T (y) can be calculated including the increase in cost.
Therefore, when calculating the cumulative amount T (y) for each rebuilding scenario, the support system 100 incorporates the cost for improving the facility function, performance, and the quality level in the cumulative amount T (y), and converts the cost into cost. It can be evaluated centrally.
In addition, when calculating the accumulated sum T (y) for each rebuilding scenario, when the long-term maintenance plan is formulated by including the cost for improving the facility function, performance, and quality level in the accumulated sum T (y). The choice of can be increased.

なお、支援システム100は、ファシリティ機能、性能、品質のレベル向上の程度をコスト化して評価するだけでなく、建替えに関する他の要素もコスト化して評価することもできる。例えば、支援システム100は、施設仮設費用、施設の統廃合等の要素をコスト化して評価することもできる。また、例えば、支援システム100は、建物10を建替える場合に、自社単独で建替える場合や、他社と共同で建替える場合等について、それぞれの場合における建替費用の要素や経営的な要素をコスト化して評価することもできる。   The support system 100 can not only cost and evaluate the facility function, performance, and the level of quality improvement, but can also cost and evaluate other factors related to rebuilding. For example, the support system 100 can also cost and evaluate factors such as temporary facility costs and consolidation of facilities. In addition, for example, when rebuilding the building 10, the support system 100 includes an element and a managerial factor of the rebuilding cost in each case when rebuilding by itself or rebuilding jointly with other companies. It is also possible to evaluate costs.

以上、本発明の実施形態について説明したが、図2に示す支援システム100は、内部にコンピュータシステムを有している。そして、上述した処理に関する一連の処理の過程は、プログラムの形式でコンピュータ読み取り可能な記憶媒体に記憶されており、このプログラムをコンピュータが読み出して実行することによって、上記処理が行われる。ここで、コンピュータ読み取り可能な記憶媒体とは、磁気ディスク、光磁気ディスク、CD−ROM、DVD−ROM、半導体メモリ等をいう。また、このコンピュータプログラムを通信回線によってコンピュータに配信し、この配信を受けたコンピュータが当該プログラムを実行するようにしても良い。また、ここでいう「コンピュータシステム」とは、OS等も含むものとする。   As mentioned above, although embodiment of this invention was described, the assistance system 100 shown in FIG. 2 has a computer system inside. Then, the process of the series of processes related to the process described above is stored in a computer readable storage medium in the form of a program, and the above process is performed by the computer reading and executing this program. Here, the computer readable storage medium refers to a magnetic disk, a magneto-optical disk, a CD-ROM, a DVD-ROM, a semiconductor memory, and the like. Alternatively, the computer program may be distributed to a computer through a communication line, and the computer that has received the distribution may execute the program. The term "computer system" as used herein also includes an OS and the like.

つまり、支援システム100内の制御部101、入出力インタフェース102、建替シナリオ生成部110における各処理の全部又は一部の処理は、CPU等の中央演算処理装置がROMやRAM等の主記憶装置に上記プログラムを読み出して、情報の加工、演算処理を実行することにより、実現されるものである。勿論、図2に示す支援システム100を構成する各処理部は専用のハードウェアにより実現されるものであってもよい。   That is, the central processing unit such as CPU is a main storage device such as ROM or RAM for all or a part of each processing in control unit 101, input / output interface 102, and rebuild scenario generation unit 110 in support system 100. This is realized by reading out the above-mentioned program and processing information and executing arithmetic processing. Of course, each processing unit constituting the support system 100 shown in FIG. 2 may be realized by dedicated hardware.

以上説明したように、上記実施形態の支援システム100においては、検討対象の建物10について検討する期間として予め定めた所定の検討期間nが年単位(複数の単位期間)に分割され、検討期間n内の何れかの年度(単位期間)に検討対象の建物10の建替えを実施すると仮定する建替シナリオが定義されている。
そして、費用算定部120は、建替シナリオのもとで検討対象の建物10の維持および建替えに掛る費用を含むコスト(費用)の検討期間n内に見込まれる累計額T(y)を、建替シナリオにおいて建物10の建替えを実施すると仮定した年度(単位期間)に対応させて算出する。
推奨期間算定部130は、検討期間n内の年度(単位期間)ごとに算出されたコストの累計額T(y)に基づいて、当該累計額T(y)の最大値Tmaxと当該累計額T(y)の最小値Tminとの差額Δ(=Tmax−Tmin)から求めた値から閾値「Tmin+(Tmax−Tmin)×p」を定め、この閾値に基づく判定により、建替えを実施する候補の期間を算定する。
As described above, in the support system 100 according to the above-described embodiment, the predetermined examination period n predetermined as the period for examining the building 10 to be examined is divided into year units (a plurality of unit periods). A rebuilding scenario is defined on the assumption that rebuilding of the building 10 to be considered is performed in any of the years (unit period) of the year.
Then, the cost calculation unit 120 estimates the accumulated amount T (y) within the examination period n of the cost (expense) including the cost for maintaining and rebuilding the building 10 to be examined under the rebuilding scenario, Calculated according to the year (unit period) assumed to carry out rebuilding of the building 10 in the rebuilding scenario.
The recommended period calculation unit 130 calculates the maximum value Tmax of the accumulated amount T (y) and the accumulated amount T based on the accumulated amount T (y) of costs calculated for each year (unit period) within the examination period n. The threshold value "Tmin + (Tmax-Tmin) x p" is determined from the value obtained from the difference Δ (= Tmax-Tmin) with the minimum value Tmin of (y), and based on this threshold value Calculate the period.

このような構成の支援システム100であれば、支援システム100は、建物10について検討期間nの初年度に建替えを行うと仮定した場合から最終年度に建替えを行うと仮定した場合までの複数の建替シナリオを作成する。つまり、支援システム100は、建物10に対して建替を実施する年度が異なる複数の建替シナリオを作成する。
費用算定部120は、建替を実施する年度が異なる複数の建替シナリオ毎に、建物10の維持に掛るコスト(費用)と建替えに掛るコスト(費用)との累計額T(y)を算出する。
推奨期間算定部130は、建替シナリオ毎に算定されたコストの累計額T(y)に基づいて、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)から求めた値から閾値「Tmin+(Tmax−Tmin)×p」を定め、累計額T(y)が閾値よりも小さい年度を候補期間として算定する。
これにより、支援システム100は、検討対象となる建物10について、所定の検討期間内において建替えを実施するのに適した期間を提示できる。
In the case of the support system 100 having such a configuration, there are a plurality of support systems 100 in the case where it is assumed that the building 10 is to be rebuilt in the first year of the examination period n to the case in which the rebuilding is performed in the last year. Create a rebuilding scenario for That is, the support system 100 creates a plurality of rebuilding scenarios in which the year in which rebuilding is performed on the building 10 is different.
The cost calculation unit 120 calculates the accumulated amount T (y) of the cost (cost) for maintaining the building 10 and the cost (cost) for rebuilding for each of a plurality of rebuilding scenarios in which the year of rebuilding is different. calculate.
The recommended period calculation unit 130 calculates the difference Δ (= Tmax−Tmin) between the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y) based on the accumulated amount T (y) of costs calculated for each rebuilding scenario. The threshold “Tmin + (Tmax−Tmin) × p” is determined from the value obtained from the above, and the year in which the accumulated amount T (y) is smaller than the threshold is calculated as a candidate period.
Thereby, the support system 100 can present a period suitable for implementing rebuilding within a predetermined examination period for the building 10 to be examined.

また、上記実施形態の支援システム100においては、検討対象の建物10−1から建物10−N(Nは正の整数)について検討する期間として予め定めた所定の検討期間nが年単位(複数の単位期間)に分割され、建物10−1から建物10−Nの建物毎に検討期間n内の何れかの年度(単位期間)に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されている。
そして、費用算定部120は、建物10−1から建物10−Nの建物毎の建替シナリオのもとで検討対象の建物の維持および建替えに掛る費用を含む費用の検討期間n内に見込まれる累計額T(y)を、建物10−1から建物10−Nの建物毎の建替シナリオにおいて建物の建替えを実施すると仮定した年度(単位期間)に対応させて建物10−1から建物10−Nの建物毎に算出する。
推奨期間算定部130は、検討期間n内の年度(単位期間)ごとに算出されたコスト(費用)の建物毎の累計額T(y)に基づいて、当該建物毎の累計額T(y)の最大値Tmaxと当該建物毎の累計額T(y)の最小値Tminとの差額Δ(=Tmax−Tmin)から求めた値から閾値「Tmin+(Tmax−Tmin)×p」を定め、閾値に基づく判定により、建物10−1から建物10−Nの建物毎に建替えを実施する候補の期間を算定する。
Further, in the support system 100 according to the above-described embodiment, a predetermined examination period n predetermined as the period for examining the buildings 10-1 to 10-N (N is a positive integer) to be examined is divided by year (a plurality of It is divided into unit period) and it is assumed that rebuilding scenario of rebuilding target building of examination object is carried out in any year (unit period) in examination period n for every building of building 10-1 to building 10-N It is defined.
Then, the cost calculation unit 120 estimates the cost within the examination period n of the cost including the cost for maintaining and rebuilding the building under consideration under the rebuilding scenario for each of the buildings 10-1 to 10-N. The accumulated sum T (y) corresponds to the year (unit period) on which it is assumed that the building rebuilding is performed in the building 10-1 to 10-N building rebuilding scenario, and the building 10-1 to the building Calculated for each 10-N building.
The recommended period calculation unit 130 calculates the accumulated amount T (y) for each building based on the accumulated amount T (y) for each building of the cost (expense) calculated for each year (unit period) within the examination period n. The threshold "Tmin + (Tmax-Tmin) x p" is determined from the value obtained from the difference Δ (= Tmax-Tmin) between the maximum value Tmax of and the minimum value Tmin of the total sum T (y) for each building. By the determination based on, the period of the candidate of implementing rebuilding for every building of building 10-1 to building 10-N is calculated.

このような構成の支援システム100であれば、建替シナリオ生成部110は、建物10−1から建物10−Nのそれぞれに対して、検討期間nの初年度に建替えを行うと仮定した場合から最終年度に建替えを行うと仮定した場合までの複数の建替シナリオを作成する。つまり、支援システム100は、建物10−1から建物10−Nのそれぞれに対して、複数の建替シナリオを作成する。
そして、費用算定部120は、建物10−1から建物10−Nのそれぞれに対して、建替を実施する年度が異なる複数の建替シナリオ毎に、建物の維持に掛るコスト(費用)と建替えに掛るコスト(費用)との累計額T(y)を算出する。
推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、累計額T(y)の最大値Tmaxと最小値Tminとの差額Δ(=Tmax−Tmin)を算出する。そして、推奨期間算定部130は、建物10−1から建物10−Nのそれぞれにおいて、差額Δから求めた値から閾値「Tmin+(Tmax−Tmin)×p」を算出し、累計額T(y)が閾値よりも小さい年度を、建替えを実施する候補の期間として算定する。
これにより、支援システム100は、建物10−1から建物10−Nのそれぞれについて、所定の検討期間内において建替えを実施するのに適した期間を提示できる。
In the case of the support system 100 having such a configuration, it is assumed that the rebuilding scenario generation unit 110 rebuilds each of the buildings 10-1 to 10-N in the first year of the examination period n. Create multiple rebuilding scenarios from when to assuming that rebuilding will be performed in the final year. That is, the support system 100 creates a plurality of rebuilding scenarios for each of the buildings 10-1 to 10-N.
Then, the cost calculation unit 120 calculates the cost (cost) for maintenance of the building for each of a plurality of rebuilding scenarios in which the year of rebuilding is different for each of the buildings 10-1 to 10-N. Calculate the accumulated amount T (y) with the cost to be replaced (expense).
The recommended period calculation unit 130 calculates the difference Δ (= Tmax−Tmin) between the maximum value Tmax and the minimum value Tmin of the accumulated amount T (y) in each of the buildings 10-1 to 10-N. Then, in each of the buildings 10-1 to 10-N, the recommended period calculation unit 130 calculates the threshold "Tmin + (Tmax-Tmin) × p" from the value obtained from the difference Δ, and the total sum T (y) Calculate the year when is smaller than the threshold as the candidate period to carry out the rebuilding.
Thereby, the support system 100 can present a period suitable for implementing rebuilding within a predetermined examination period for each of the buildings 10-1 to 10-N.

また、上記実施形態において、推奨期間算定部130は、当該累計額T(y)の最大値Tmaxと当該累計額T(y)の最小値Tminとの差額Δ(=Tmax−Tmin)から求めた値「(Tmax−Tmin)×p」を最小値Tminに加えて閾値「Tmin+(Tmax−Tmin)×p」にして、閾値に基づく判定により、建替えを実施する候補の期間を算定する。
これにより、支援システム100は、累計額T(y)の差額Δ(=Tmax−Tmin)と、最小値Tminと、に基づいて、建替えを実施する候補の期間を算定することができる。
Further, in the above embodiment, the recommended period calculation unit 130 calculates the difference Δ (= Tmax−Tmin) between the maximum value Tmax of the accumulated amount T (y) and the minimum value Tmin of the accumulated amount T (y). The value “(Tmax−Tmin) × p” is added to the minimum value Tmin to make the threshold “Tmin + (Tmax−Tmin) × p”, and the period based on the threshold is calculated to calculate the candidate period to be rebuilt.
Thus, the support system 100 can calculate the period of the candidate to be rebuilt based on the difference Δ (= Tmax−Tmin) of the accumulated amount T (y) and the minimum value Tmin.

また、上記実施形態において、推奨期間算定部130は、当該累計額T(y)の最大値Tmaxと当該累計額T(y)の最小値Tminとの差額Δ(=Tmax−Tmin)から求めた値「(Tmax−Tmin)×p」を最小値Tminに加えて閾値「Tmin+(Tmax−Tmin)×p」にして、閾値に基づく判定の結果から得られた年度(単位期間)を、建替えを実施する候補の期間として算定する。
これにより、支援システム100は、累計額T(y)の差額Δ(=Tmax−Tmin)と、最小値Tminと、に基づいて、建替えを実施する候補の年度(単位期間)を算定し、この候補の年度を含む期間を、建替えを実施する候補の期間とすることができる。
Further, in the above embodiment, the recommended period calculation unit 130 calculates the difference Δ (= Tmax−Tmin) between the maximum value Tmax of the accumulated amount T (y) and the minimum value Tmin of the accumulated amount T (y). By adding the value “(Tmax−Tmin) × p” to the minimum value Tmin to make the threshold “Tmin + (Tmax−Tmin) × p”, the year (unit period) obtained from the result of the determination based on the threshold is rebuilt Calculated as a candidate period for implementing
Thus, the support system 100 calculates the year (unit period) of the candidate to be rebuilt on the basis of the difference Δ (= Tmax−Tmin) of the accumulated amount T (y) and the minimum value Tmin, The period including the candidate year can be set as the candidate period to carry out the rebuilding.

また、上記実施形態の支援システム100においては、検討対象の建物10−1から建物10−N(Nは正の整数)について検討する期間として予め定めた所定の検討期間nが年単位(複数の単位期間)に分割され、建物10−1から建物10−Nの建物毎に検討期間n内の何れかの年度(単位期間)に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されている。
そして、費用算定部120は、建物10−1から建物10−Nの建物毎の建替シナリオのもとで検討対象の建物の維持および建替えに掛る費用を含む費用の検討期間n内に見込まれる累計額T(y)を、建物10−1から建物10−Nの建物毎の建替シナリオにおいて建物の建替えを実施すると仮定した年度(単位期間)に対応させて建物10−1から建物10−Nの建物毎に算出する。
推奨期間算定部130は、検討期間n内の年度(単位期間)ごとに算出されたコスト(費用)の建物毎の累計額T(y)に基づいて、当該建物毎の累計額T(y)の最大値Tmaxと当該建物毎の累計額T(y)の最小値Tminとの差額Δ(=Tmax−Tmin)から値を求め、複数の建物の差額Δから求めた値から代表値を定め、この定めた代表値を基準にした判定により、建物10−1から建物10−Nの建物毎に建替えを実施する候補の期間を算定する。
Further, in the support system 100 according to the above-described embodiment, a predetermined examination period n predetermined as the period for examining the buildings 10-1 to 10-N (N is a positive integer) to be examined is divided by year (a plurality of It is divided into unit period) and it is assumed that rebuilding scenario of rebuilding target building of examination object is carried out in any year (unit period) in examination period n for every building of building 10-1 to building 10-N It is defined.
Then, the cost calculation unit 120 estimates the cost within the examination period n of the cost including the cost for maintaining and rebuilding the building under consideration under the rebuilding scenario for each of the buildings 10-1 to 10-N. The accumulated sum T (y) corresponds to the year (unit period) on which it is assumed that the building rebuilding is performed in the building 10-1 to 10-N building rebuilding scenario, and the building 10-1 to the building Calculated for each 10-N building.
The recommended period calculation unit 130 calculates the accumulated amount T (y) for each building based on the accumulated amount T (y) for each building of the cost (expense) calculated for each year (unit period) within the examination period n. Determine the value from the difference Δ (= Tmax-Tmin) between the maximum value Tmax of and the minimum value Tmin of the accumulated value T (y) for each building, and determine a representative value from the value obtained from the difference Δ between multiple buildings Based on the determination based on the determined representative value, a period of a candidate for rebuilding for each of the buildings 10-1 to 10-N is calculated.

このような構成の支援システム100であれば、推奨期間算定部130は、複数の建物10−1から建物10−Nのそれぞれにおける建替シナリオ毎の累計額T(y)の差額Δ(=Tmax−Tmin)から最大値を判定し、この最大値を「Δmax」とする。そして、推奨期間算定部130は、この差額Δmaxから代表値「Δmax×p」を算出し、この代表値「Δmax×p」を基準にした判定により、建物10−1から建物10−Nの建物毎に建替えを実施する候補の期間を算定する。
これにより、支援システム100は、累計額T(y)の差額Δが小さな建物の建替えを実施する候補の期間を算定する場合、累計額T(y)の差額Δが大きな建物を基準にして、建替えを実施する候補の期間を算定することができる。このため、支援システム100は、累計額T(y)の差額Δが小さな建物の建替えの候補の期間を算定する場合、当該建物自身の累計額T(y)の差額Δに基づいて算定する場合と比較して、より広い範囲の候補の期間を算定することができる。
In the case of the support system 100 having such a configuration, the recommended period calculation unit 130 calculates the difference Δ (= Tmax) of the accumulated sum T (y) for each rebuilding scenario in each of the plurality of buildings 10-1 to 10-N. The maximum value is determined from −Tmin), and this maximum value is taken as “Δmax”. Then, the recommended period calculation unit 130 calculates a representative value “Δmax × p” from the difference Δmax, and based on the representative value “Δmax × p”, the buildings 10-1 to 10-N are determined. Calculate the candidate period to carry out the rebuilding every time.
Thereby, when the support system 100 calculates the period of the candidate to carry out the rebuilding of the building where the difference Δ of the accumulated amount T (y) is small, the difference Δ of the accumulated amount T (y) is based on the large building. , It is possible to calculate the period of the candidate to carry out rebuilding. For this reason, when calculating the period of a candidate for rebuilding a building with a small difference Δ of the accumulated sum T (y), the support system 100 calculates it based on the difference Δ of the accumulated sum T (y) of the building itself. A wider range of candidate periods can be calculated compared to the case.

以上、本発明の実施の形態について説明したが、本発明の支援システム100は、上述の図示例にのみ限定されるものではなく、本発明の要旨を逸脱しない範囲内において種々変更を加え得ることは勿論である。
例えば、上記支援システム100では、検討期間nを年単位で設定し、建替シナリオの累計額T(y)の算出や候補期間の算定等を年単位で行う例を示したが、これに限定されない。例えば、検討期間nの設定や、建替シナリオの累計額T(y)の算出や、候補期間の算定等は、月単位、半年単位、或いは、複数年単位で行うようにしてもよい。
As mentioned above, although embodiment of this invention was described, the support system 100 of this invention is not limited only to the above-mentioned illustrated example, A various change can be added in the range which does not deviate from the summary of this invention. Of course.
For example, in the support system 100 described above, the examination period n is set on a yearly basis, and the calculation of the accumulated sum T (y) of the rebuilding scenario, the calculation of the candidate period, etc. I will not. For example, the setting of the examination period n, the calculation of the accumulated amount T (y) of the rebuilding scenario, the calculation of the candidate period, and the like may be performed on a monthly basis, a half year basis, or a multiple year basis.

なお、上記支援システム100では、検討期間nとして定めた期間を通して、予め定めた共通の条件のもとで検討と判定とを行うものとして説明したが、検討期間nとして定めた期間内を複数の期間に分割して、分割された期間毎に判定の条件を変えるようにしてもよい。例えば、中期計画の対象期間と中期計画終了後の期間とに分割する場合が挙げられる。この場合、中期計画の対象期間では、計画実行に当たり建替え候補期間と建替えに関係する事項を具体化させた条件で判定し、中期計画終了後の期間では、建替え候補期間として選択する範囲に幅を持たせて選択できるように条件を設定する。より具体的な例を挙げるとすれば、中期計画の対象期間として設定した5年間は、建替え候補期間を具体的な年度で示し、中期計画終了後の期間では、5年を単位とする期間の何れに、建替え候補期間が含まれるかを選定できるように設定する。なお、上記の例も一例である。   In the support system 100 described above, the examination and the judgment are performed under the common conditions determined in advance through the period determined as the examination period n. However, a plurality of periods determined as the examination period n are described. The conditions of determination may be changed for each divided period by dividing into periods. For example, it may be divided into a target period of the mid-term plan and a period after the mid-term plan ends. In this case, in the target period of the medium-term plan, it is judged on the condition that the matters related to the rebuilding period and the rebuilding period are embodied in the plan execution, and in the period after the end of the mid-term plan, the range selected as the rebuilding candidate period Set the condition so that it can be selected by giving width to. As a more specific example, the five years set as the target period of the mid-term plan show the rebuilding candidate period as a specific year, and the period after the end of the mid-term plan is a period of five years It is set to be able to select which of the rebuilding candidate periods is included in which. The above example is also an example.

10,10−1,10−2,10−3,10−N・・・建物、
100・・・支援システム、110・・・建替シナリオ生成部、
120・・・費用算定部、130・・・推奨期間算定部、140・・・作図部、
150・・・記憶部、161・・・入出力端末装置、162・・・表示部
10, 10-1, 10-2, 10-3, 10-N ... building,
100 ··· Support system, 110 ··· Reconstruction scenario generation unit,
120: cost calculation unit 130: recommended period calculation unit 140: drawing unit
150: storage unit 161: input / output terminal device 162: display unit

Claims (7)

検討対象の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて算出する費用算定部と、
前記検討期間内の前記単位期間ごとに前記算出された費用の累計額に基づいて、当該累計額の最大値と当該累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定する推奨期間算定部と、
を備えることを特徴とする支援システム。
It is assumed that a predetermined examination period predetermined as a period for examining a building to be examined is divided into a plurality of unit periods, and rebuilding of the building to be considered is performed in any of the unit periods within the examination period. Replacement scenario is defined, and the cumulative amount of expenses, including the cost for maintaining and rebuilding the building under consideration under the rebuilding scenario, within the reviewing period is considered in the rebuilding scenario. An expense calculation unit that calculates the unit period corresponding to the unit period assumed to carry out the rebuilding of the building;
A threshold is determined from a value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount based on the accumulated amount of expenses calculated for each unit period within the examination period, and A recommended period calculation unit for calculating a period of a candidate to carry out the rebuilding based on the determination based on
A support system comprising:
検討対象の複数の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記建物毎に前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建物毎の前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建物毎の前記建替シナリオにおいて前記建物の建て替えを実施すると仮定した単位期間に対応させて前記建物毎に算出する費用算定部と、
前記検討期間内の前記単位期間ごとに前記算出された費用の前記建物毎の累計額に基づいて、当該建物毎の累計額の最大値と当該建物毎の累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建物毎に建替えを実施する候補の期間を算定する推奨期間算定部と、
を備えることを特徴とする支援システム。
A predetermined examination period predetermined as a period for examining a plurality of buildings to be examined is divided into a plurality of unit periods, and rebuilding of the buildings to be examined in any of the unit periods within the examination period is performed for each building. It is defined that a rebuilding scenario is assumed to be carried out, and it is expected within the reviewing period of the cost including the cost of maintaining and rebuilding the building under consideration under the rebuilding scenario for each building. A cost calculation unit which calculates a cumulative amount for each building in correspondence with a unit period assumed to carry out the rebuilding of the building in the rebuilding scenario for each building;
Calculated from the difference between the maximum value of the accumulated amount for each building and the minimum value of the accumulated amount for each building based on the accumulated amount of the expenses calculated for the building for each unit period within the examination period A recommended period calculation unit which determines a threshold value from the calculated value and calculates a period of a candidate for rebuilding for each of the buildings by determination based on the threshold value;
A support system comprising:
前記推奨期間算定部は、
当該累計額の最大値と当該累計額の最小値との差額から求めた値を前記最小値に加えて閾値にして、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定する
ことを特徴とする請求項1又は請求項2に記載の支援システム。
The recommendation period calculation unit
A value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount is added to the minimum value to be a threshold, and the period based on the threshold is calculated to calculate the period of the candidate to be rebuilt The support system according to claim 1 or 2, characterized in that.
前記推奨期間算定部は、
当該累計額の最大値と当該累計額の最小値との差額から求めた値を前記最小値に加えて閾値にして、前記閾値に基づく判定の結果から得られた前記単位期間を、前記建替えを実施する候補の期間として算定する
ことを特徴とする請求項1から請求項3の何れか1項に記載の支援システム。
The recommendation period calculation unit
The value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount is added to the minimum value as a threshold, and the unit period obtained from the result of the determination based on the threshold is rebuilt The support system according to any one of claims 1 to 3, wherein the support system is calculated as a candidate period to carry out.
検討対象の複数の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記建物毎に前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建物毎の前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建物毎の前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて前記建物毎に算出する費用算定部と、
前記検討期間内の前記単位期間ごとに前記算出された費用の前記建物毎の累計額に基づいて、当該建物毎の累計額の最大値と当該建物毎の累計額の最小値との差額から値を求め、前記複数の建物の前記差額から求めた値から代表値を定め、前記定めた代表値を基準にした判定により、前記建物毎に建替えを実施する候補の期間を算定する推奨期間算定部と、
を備えることを特徴とする支援システム。
A predetermined examination period predetermined as a period for examining a plurality of buildings to be examined is divided into a plurality of unit periods, and rebuilding of the buildings to be examined in any of the unit periods within the examination period is performed for each building. It is defined that a rebuilding scenario is assumed to be carried out, and it is expected within the reviewing period of the cost including the cost of maintaining and rebuilding the building under consideration under the rebuilding scenario for each building. A cost calculation unit which calculates a cumulative amount for each building in correspondence with a unit period assumed to carry out rebuilding of the building in the rebuilding scenario for each building;
From the difference between the maximum value of the accumulated amount for each building and the minimum value of the accumulated amount for each building based on the accumulated amount for each building of the expenses calculated for each unit period within the examination period To determine the representative value from the value obtained from the difference between the plurality of buildings, and by determining based on the determined representative value, calculating the recommended period for calculating the candidate period for rebuilding for each building Department,
A support system comprising:
検討対象の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて算出するステップと、
前記検討期間内の前記単位期間ごとに前記算出された費用の累計額に基づいて、当該累計額の最大値と当該累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定するステップと、
を含む処理をコンピュータに実施させることを特徴とする支援方法。
It is assumed that a predetermined examination period predetermined as a period for examining a building to be examined is divided into a plurality of unit periods, and rebuilding of the building to be considered is performed in any of the unit periods within the examination period. Replacement scenario is defined, and the cumulative amount of expenses, including the cost for maintaining and rebuilding the building under consideration under the rebuilding scenario, within the reviewing period is considered in the rebuilding scenario. Calculating corresponding to the unit period assumed to carry out rebuilding of the building;
A threshold is determined from a value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount based on the accumulated amount of expenses calculated for each unit period within the examination period, and Calculating a period of a candidate to carry out the rebuilding according to the determination based on
A computer-implemented method comprising:
検討対象の建物について検討する期間として予め定めた所定の検討期間が複数の単位期間に分割され、前記検討期間内の何れかの前記単位期間に検討対象の建物の建替えを実施すると仮定する建替シナリオが定義されており、前記建替シナリオのもとで前記検討対象の建物の維持および建替えに掛る費用を含む費用の前記検討期間内に見込まれる累計額を、前記建替シナリオにおいて前記建物の建替えを実施すると仮定した単位期間に対応させて算出するステップと、
前記検討期間内の前記単位期間ごとに前記算出された費用の累計額に基づいて、当該累計額の最大値と当該累計額の最小値との差額から求めた値から閾値を定め、前記閾値に基づく判定により、前記建替えを実施する候補の期間を算定するステップと、
を支援システムのコンピュータに実施させるためのプログラム。
It is assumed that a predetermined examination period predetermined as a period for examining a building to be examined is divided into a plurality of unit periods, and rebuilding of the building to be considered is performed in any of the unit periods within the examination period. Replacement scenario is defined, and the cumulative amount of expenses, including the cost for maintaining and rebuilding the building under consideration under the rebuilding scenario, within the reviewing period is considered in the rebuilding scenario. Calculating corresponding to the unit period assumed to carry out rebuilding of the building;
A threshold is determined from a value obtained from the difference between the maximum value of the accumulated amount and the minimum value of the accumulated amount based on the accumulated amount of expenses calculated for each unit period within the examination period, and Calculating a period of a candidate to carry out the rebuilding according to the determination based on
A program for causing a computer of a support system to execute.
JP2019075137A 2019-04-10 2019-04-10 Support system, support method, and program Pending JP2019109945A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019075137A JP2019109945A (en) 2019-04-10 2019-04-10 Support system, support method, and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019075137A JP2019109945A (en) 2019-04-10 2019-04-10 Support system, support method, and program

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2015114129A Division JP6514043B2 (en) 2015-06-04 2015-06-04 SUPPORT SYSTEM, SUPPORT METHOD, AND PROGRAM

Publications (2)

Publication Number Publication Date
JP2019109945A true JP2019109945A (en) 2019-07-04
JP2019109945A5 JP2019109945A5 (en) 2019-08-15

Family

ID=67179972

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019075137A Pending JP2019109945A (en) 2019-04-10 2019-04-10 Support system, support method, and program

Country Status (1)

Country Link
JP (1) JP2019109945A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021119450A (en) * 2020-03-19 2021-08-12 東京瓦斯株式会社 Pipe maintenance system, information processing device, and program

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0922432A (en) * 1995-07-07 1997-01-21 Hitachi Ltd Facility maintenance management method and system
JP2003108646A (en) * 2001-09-28 2003-04-11 Takenaka Komuten Co Ltd Reconstructing investment judging system
JP2003345883A (en) * 2002-05-28 2003-12-05 Yamatake Corp Building managing apparatus and program
US20080270202A1 (en) * 2007-04-27 2008-10-30 Nokia Siemens Networks Gmbh & Co Methods of life cycle optimization for solutions including tooling
JP2013015922A (en) * 2011-06-30 2013-01-24 Daikin Ind Ltd Equipment controlling device
JP2013054410A (en) * 2011-08-31 2013-03-21 Rakuten Inc Advertisement system, control method of advertisement system, advertisement control device, control method of advertisement control device, program, and information storage medium
JP6514043B2 (en) * 2015-06-04 2019-05-15 株式会社Nttファシリティーズ SUPPORT SYSTEM, SUPPORT METHOD, AND PROGRAM

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0922432A (en) * 1995-07-07 1997-01-21 Hitachi Ltd Facility maintenance management method and system
JP2003108646A (en) * 2001-09-28 2003-04-11 Takenaka Komuten Co Ltd Reconstructing investment judging system
JP2003345883A (en) * 2002-05-28 2003-12-05 Yamatake Corp Building managing apparatus and program
US20080270202A1 (en) * 2007-04-27 2008-10-30 Nokia Siemens Networks Gmbh & Co Methods of life cycle optimization for solutions including tooling
JP2013015922A (en) * 2011-06-30 2013-01-24 Daikin Ind Ltd Equipment controlling device
JP2013054410A (en) * 2011-08-31 2013-03-21 Rakuten Inc Advertisement system, control method of advertisement system, advertisement control device, control method of advertisement control device, program, and information storage medium
JP6514043B2 (en) * 2015-06-04 2019-05-15 株式会社Nttファシリティーズ SUPPORT SYSTEM, SUPPORT METHOD, AND PROGRAM

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021119450A (en) * 2020-03-19 2021-08-12 東京瓦斯株式会社 Pipe maintenance system, information processing device, and program

Similar Documents

Publication Publication Date Title
Kuai et al. An application of system dynamics for evaluating planning alternatives to guide a green industrial transformation in a resource-based city
Tagliabue et al. Probabilistic behavioural modeling in building performance simulation—The Brescia eLUX lab
Nagpal et al. A framework for using calibrated campus-wide building energy models for continuous planning and greenhouse gas emissions reduction tracking
Becchio et al. The cost-optimal methodology for the energy retrofit of an ex-industrial building located in Northern Italy
US20120221371A1 (en) System, method and computer program for asset management optimization
JP2004086896A (en) Method and system for constructing adaptive prediction model
KR101553476B1 (en) Apparatus for measuring likelihood ratio of building and method thereof
US20110313808A1 (en) Built Environment Management System and Method
Tang et al. System dynamics modeling for construction material flows of urban residential building: A case study of Beijing, China
Chen et al. AI-Assisted approach for building energy and carbon footprint modeling
Zhuang et al. A risk-based robust optimal chiller sequencing control strategy for energy-efficient operation considering measurement uncertainties
JP6514043B2 (en) SUPPORT SYSTEM, SUPPORT METHOD, AND PROGRAM
JP6959975B2 (en) How to determine computer system and resource allocation
Srinivasan et al. Sustainability assessment frameworks, evaluation tools and metrics for buildings and its environment—A review
Liu et al. Energy and carbon performance of urban buildings using metamodeling variable importance techniques
JP2019109945A (en) Support system, support method, and program
Mao et al. Towards fast energy performance evaluation: A pilot study for office buildings
KR20190128282A (en) Method of decision making based on modeling portfolio of public building
Brenière et al. Optimization of preventive replacements dates and covariate inspections for repairable systems in varying environments
KR20210047507A (en) Apparatus for managing building energy collectively and method thereof
CN111105050A (en) Method, device and equipment for generating fan maintenance plan and storage medium
Schwartz An integrated thermal simulation & generative design decision support framework for the refurbishment or replacement of buildings: a life cycle performance optimisation approach
JP2003281248A (en) Comprehensive building asset diagnostic system
KR20130062382A (en) Method and system of facility condition index of quantity for building management priority calculation
Ismail et al. Integrating CMMS, expert systems and BIM for IBS building maintenance

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190410

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190604

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200519

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20201201