JP2019065518A - Construction machine - Google Patents
Construction machine Download PDFInfo
- Publication number
- JP2019065518A JP2019065518A JP2017190342A JP2017190342A JP2019065518A JP 2019065518 A JP2019065518 A JP 2019065518A JP 2017190342 A JP2017190342 A JP 2017190342A JP 2017190342 A JP2017190342 A JP 2017190342A JP 2019065518 A JP2019065518 A JP 2019065518A
- Authority
- JP
- Japan
- Prior art keywords
- counterweight
- shackle
- construction machine
- ring
- suspension
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Component Parts Of Construction Machinery (AREA)
Abstract
Description
本発明は建設機械に係り、特に建設機械をクレーンなどで吊上げるための吊り環を備える技術に関する。 BACKGROUND OF THE INVENTION Field of the Invention The present invention relates to a construction machine, and more particularly to a technology provided with a suspension ring for lifting a construction machine by a crane or the like.
例えば、比較的小型の油圧ショベルはそのフロントアタッチメントに掘削バケットのみならず、リッパ、ブレーカ及び圧砕機などの装着が可能である。それゆえ、この種の油圧ショベルは単に掘削作業のみならず、建物や岩石の破砕作業などにも適用可能であることから、その作業用途は広範囲に亘り、しかも、その作業現場が自走により到達できない所である場合も多い。 For example, a relatively small hydraulic excavator can be equipped with not only a digging bucket but also a ripper, a breaker and a crusher at its front attachment. Therefore, since this type of hydraulic excavator is applicable not only to digging work but also to crushing work of buildings and rocks, the work application is extensive and the work site is reached by self-propelled There are many cases where you can not do it.
そのため、油圧ショベルはクレーンなどでワイヤロープにより吊上げられ、そして、その作業現場に運ばれることになるが、このためには油圧ショベルにワイヤロープを掛止するための吊環を装備しておく必要がある(特許文献1)。 Therefore, the hydraulic shovel is lifted by a wire rope by a crane etc., and is transported to the work site, but for this purpose, it is necessary to equip the hydraulic shovel with a ring for retaining the wire rope. (Patent Document 1).
ところで、油圧ショベルに装備された吊環にワイヤロープを掛止する作業は、一般的に該ワイヤロープの一端に設けられたシャックルを吊環に取付けることが行われている。
また、特許文献1に開示されている技術によると、吊環が開閉フードのカバー部により隠されており、油圧ショベルを吊上げる作業を行うとき、カバーを機体前方向に開放して吊環にシャックルを取付けることになる。
By the way, the operation of hooking the wire rope to the suspension ring equipped on the hydraulic shovel is generally performed by attaching a shackle provided at one end of the wire rope to the suspension ring.
Further, according to the technology disclosed in Patent Document 1, when the lifting ring is hidden by the cover portion of the opening and closing hood and the hydraulic shovel is lifted, the cover is opened in the front direction of the machine to shackle the lifting ring. It will be installed.
しかしながら、カバーを機体前方向に開放して吊上げ作業を行うことは、該吊上げ作業後にワイヤが撓んでカバー側に倒れることでカバーを破損させる虞がある。また、例えばカバーがワイヤと接触しないような位置に開放するようにしたとしても、吊上げ作業後にワイヤが撓むときにシャックルが横転して機体の意匠面等を傷つける虞がある。特に、近年では環境対策等のために排気ガス中に含まれるNOxを低減させるSCR触媒等を搭載することによりエンジンが大型化する傾向にあるため、吊環を設ける位置は、カバーに覆われる部分に設けることが難しく、カウンタウエイト等の意匠面上に設けられることとなる。 However, when the cover is opened in the forward direction of the machine and the lifting operation is performed, the wire may be bent after the lifting operation so that the cover may be damaged by falling on the cover side. Also, even if the cover is opened to a position where it does not contact the wire, for example, when the wire bends after the lifting operation, there is a possibility that the shackle will overturn and damage the design surface or the like of the airframe. In particular, in recent years, the engine tends to be upsized by mounting an SCR catalyst or the like for reducing NOx contained in exhaust gas for environmental measures etc. Therefore, the location where the ring is provided is the portion covered by the cover It is difficult to provide, and it will be provided on a design surface such as a counterweight.
そのため、上記したような吊上げ作業後にワイヤが撓むことでシャックルが横転し、カウンタウエイトの意匠面を傷つける虞がある。
本発明はこのような課題に鑑みてなされたものであり、その目的とするところは、吊上げ作業後におけるワイヤの撓みや該撓みによってシャックルが倒れ、ワイヤ及びシャックルが機体を傷つけ、更にはエンジンを損傷させることを防止することができる建設機械を提供することにある。
Therefore, when the wire bends after the lifting operation as described above, the shackle may roll and damage the design surface of the counterweight.
The present invention has been made in view of such problems, and the object of the present invention is to bend the wire after the lifting work and the shackle to fall due to the bending, and the wire and shackle damage the airframe, and further the engine. An object of the present invention is to provide a construction machine that can be prevented from being damaged.
上記の目的を達成するため、本発明の建設機械は、機体と、前記機体にエンジン及びエンジンの後方にカウンタウエイトが搭載されている建設機械において、前記カウンタウエイトの上部に複数配設され、上方に向かって延びる吊環を備え、前記吊環には、前記機体の前後方向に開口してなる吊穴が設けられていることを特徴とする。 In order to achieve the above object, a construction machine according to the present invention includes an airframe and a construction machine having an engine and a counterweight mounted on the rear side of the airframe. The suspension ring is provided with a suspension hole which is opened in the front-rear direction of the machine body.
これにより、前後方向に開口する吊穴が設けられた吊環をカウンタウエイトの上部に複数配設することで、建設機械の吊上げ作業の用に例えばワイヤの一端に設けられたシャックルが吊穴を貫通するように装着され、該吊上げ作業後、即ち建設機械が接地してワイヤが撓むとき、シャックルは、吊穴の開口方向を軸にして回動する。故に、吊穴の開口方向が前後方向であるため、シャックルは、重力によって左右方向に回動して倒れることとなり、換言すればカウンタウエイトより前方にシャックル及びワイヤが倒れ込みエンジンを損傷させることを防止することが可能とされる。 Thus, by arranging a plurality of suspension rings provided with suspension holes that open in the front-rear direction on the upper part of the counterweight, a shackle provided at one end of the wire for lifting work of the construction machine penetrates the suspension holes, for example. After the lifting operation, i.e., when the construction machine is grounded and the wire is bent, the shackle pivots about the opening direction of the hanging hole. Therefore, because the opening direction of the hanging hole is the front and back direction, the shackle will turn to the left and right direction by gravity and fall down, in other words it prevents the shackle and the wire from falling forward than the counterweight and damaging the engine. It is possible to do.
その他の態様として、前記吊環の左右に設けられ、前記吊穴より上方に延びるガイド部を有するのが好ましい。
これにより、吊環の左右、即ち吊上げ作業後にシャックルが吊穴の開口方向を軸にして回動する方向に、吊穴より上方に延びるガイド部を有しているので、シャックルは、吊上げ作業後に吊穴の開口方向を軸にして回動して吊穴より上方に延びるガイド部に当たって支持される。即ち、シャックルがガイド部より下方に倒れることを防止して該シャックルが意匠面であるカウンタウエイトに当たり傷つけることを防止することが可能とされる。
As another mode, it is preferable to have a guide part which is provided on the left and right of the hanging ring and extends upward from the hanging hole.
As a result, the shackle is suspended after the lifting operation because it has guide portions extending upward from the suspending hole in the direction in which the shackle pivots around the opening direction of the lifting hole after the lifting operation. It is pivoted about the opening direction of the hole and supported by a guide portion extending upward from the hanging hole. That is, it is possible to prevent the shackle from falling below the guide portion and to prevent the shackle from hitting against the counterweight which is a design surface and damaging it.
その他の態様として、前記ガイド部の上端は、上方に延びるにつれて前記吊環から離間する方向に屈曲して形成されているのが好ましい。
これにより、ガイド部の上端が吊環から離間する方向に屈曲することで、シャックルを吊穴に取付ける際にガイド部が該取り付け作業の邪魔にならないようにすることが可能とされる。
In another aspect, it is preferable that the upper end of the guide portion is bent in a direction away from the ring as it extends upward.
Thus, by bending the upper end of the guide portion in the direction of separating from the suspension ring, it is possible to prevent the guide portion from interfering with the attaching operation when the shackle is attached to the hanging hole.
その他の態様として、前記吊環は、前記機体の左右方向に延びる平板形状であり、前記ガイド部は、前記機体の前後方向に延びる左右一対の平板形状であり、前記吊環及び前記ガイド部は、結合または一体に形成されているのが好ましい。
これにより、左右方向に延びる平板形状である吊環に前後方向に延びる左右一対の平板形状であるガイド部が溶接されることで、吊環の前後方向に加わる力をガイド部によって補強することが可能とされる。
In another aspect, the suspension ring is a flat plate extending in the left-right direction of the machine body, the guide portion is a pair of left and right flat plate shapes extending in the front-rear direction of the machine body, and the suspension ring and the guide portion are coupled Alternatively, they are preferably integrally formed.
As a result, by welding a pair of left and right flat plate shapes extending in the front and rear direction to the ring extending in the left and right direction, the force applied in the front and rear direction of the ring can be reinforced by the guide portion Be done.
その他の態様として、前記カウンタウエイトに設けられ、後方に向かって突出する突出部を更に有し、前記吊環は、前記突出部に設けられているのが好ましい。
これにより、カウンタウエイトに設けられた突出部が後方に向かって突出しており、該突出部に吊環を設けることで、カウンタウエイトの重心がより後方となり、カウンタウエイトの効果である機体後側に加わる重力方向への力を増加させることが可能とされる。
As another aspect, it is preferable that the counterweight further includes a protruding portion that protrudes rearward, and the ring is provided to the protruding portion.
As a result, the protrusion provided on the counterweight protrudes rearward, and by providing a ring on the protrusion, the center of gravity of the counterweight becomes more rearward, and the effect of the counterweight is added to the rear side of the machine body It is possible to increase the force in the direction of gravity.
本発明の建設機械によれば、前後方向に開口する吊穴が設けられた吊環をカウンタウエイトの上部に複数配設したので、建設機械の吊上げ作業の用に例えばワイヤの一端に設けられたシャックルが吊穴を貫通するように装着され、該吊上げ作業後、即ち建設機械が接地してワイヤが撓むとき、シャックルは、吊穴の開口方向を軸にして回動する。故に、吊穴の開口方向が前後方向であるため、シャックルは、重力によって左右方向に回動して倒れることとなり、換言すればカウンタウエイトより前方にシャックル及びワイヤが倒れ込みエンジンを損傷させることを防止することができる。 According to the construction machine of the present invention, since a plurality of the rings provided with the hanging holes opened in the front and rear direction are disposed on the upper part of the counterweight, for example, a shackle provided at one end of the wire for lifting work of the construction machine Is mounted so as to penetrate the suspension hole, and after the lifting operation, ie, when the construction machine is grounded and the wire is bent, the shackle pivots about the opening direction of the suspension hole. Therefore, because the opening direction of the hanging hole is the front and back direction, the shackle will turn to the left and right direction by gravity and fall down, in other words it prevents the shackle and the wire from falling forward than the counterweight and damaging the engine. can do.
これにより、吊上げ作業後におけるワイヤの撓みやシャックルの横転によってワイヤ及びシャックルが機体を傷つけ、更にはエンジンを損傷させることを防止することができる。 As a result, it is possible to prevent the wire and the shackle from damaging the airframe and further damaging the engine due to the bending of the wire and the rollover of the shackle after the lifting operation.
以下、図面に基づき本発明の一実施形態について説明する。
図1を参照すると、建設機械としての油圧ショベル(建設機械)1を後方から視た斜視図が示されている。油圧ショベル1は、下部走行体3及び上部旋回体(機体)5によって構成される。
下部走行体3は、油圧ショベル1が走行可能となるように上部旋回体5を支持する所謂クローラ型の走行装置である。
Hereinafter, an embodiment of the present invention will be described based on the drawings.
Referring to FIG. 1, a perspective view of a hydraulic excavator (construction machine) 1 as a construction machine as viewed from the rear is shown. The hydraulic shovel 1 is configured by a lower traveling body 3 and an upper revolving superstructure (body) 5.
The lower traveling body 3 is a so-called crawler-type traveling device that supports the
上部旋回体5は、フロントアタッチメント7、操縦室9、エンジン10、カウンタウエイト11が設けられ、下部走行体3に回動可能となるように支持される機体である。フロントアタッチメント7は、上部旋回体5の前後方向前側の中央部に設けられた図示しない基部から上部旋回体5の前方に延びている。また、フロントアタッチメント7は、基部から順にブーム13、アーム15、バケット17が配設されて構成される。即ち、フロントアタッチメント7は、第1ジョイント19にてブーム13とアーム15とが回動可能に接続され、第2ジョイント21にてアーム15とバケット17とが回動可能に接続されており、基点、第1ジョイント19、第2ジョイント21にてそれぞれブーム13、アーム15、バケット17を回動させることで掘削作業等を行うことが可能に構成される。また、ブーム13の前後方向中央の左右には、それぞれブーム吊部14、14が設けられており、後述する油圧ショベル1の吊上げ作業時にワイヤ40の一端が掛止される。なお、バケット17は第2ジョイント21にて脱着して取り替え可能となっており、リッパ、ブレーカ及び圧砕機などに取り替えることが可能である。
The
操縦室9は、上部旋回体5の前後方向前側の左右方向左側に設けられる。この操縦室9は、下部走行体3を駆動させることによる油圧ショベル1の走行やフロントアタッチメント7の操作等、油圧ショベル1の操作をオペレータが搭乗して行う操縦室である。
エンジン10は、上部旋回体5の前後方向後部、即ち上部旋回体5及びフロントアタッチメント7の後方に設けられている。このエンジン10は、下部走行体3の駆動、上部旋回体5の旋回、及びフロントアタッチメント7の作動を行うための駆動源である。
The
The
カウンタウエイト11は、上部旋回体5の前後方向最後部、即ちエンジン10の後方に設けられる。また、カウンタウエイト11は、例えば金属製の製缶体に鉄鉱石やポンチカス等を充填し、セメントで固めて形成される。このようなカウンタウエイト11は、フロントアタッチメント7が重量物をバケット17ですくい上げるときのように上部旋回体5の前後方向前方に重心が移動することを考慮して上部旋回体5の後方に重心を設けることで上部旋回体5の重心が前方に偏り油圧ショベル1が転倒することを防止すべく設けられたものである。
The
また、カウンタウエイト11の上下方向上部には、前後方向後方に膨らむように突出して構成される突出部22、22が左右方向に2つ並んで設けられている。これにより、カウンタウエイト11の重心が油圧ショベル1の後方寄りになる。即ち、フロントアタッチメント7を使用して作業する際、フロントアタッチメント7に加わる重力方向への力によって油圧ショベル1の前部に重力方向の力が発生する。この力に対して反対方向の力が突出部22によって発生するので、油圧ショベル1が重力方向に倒れることをより良好に防止することができる。
Further, at the upper part in the vertical direction of the
図2を参照すると、吊部23及びカウンタウエイト11の斜視図が示されている。
吊部23は、吊環30及びガイド部32によって構成されており、カウンタウエイト11に設けられた突出部22、22それぞれに配設されている。吊環30は、上下方向上側に吊穴34が前後方向に開口して設けられた、左右方向に延びる平板部材である。
Referring to FIG. 2, a perspective view of the hanging
The hanging
ガイド部32は、吊環30の左右に溶接して設けられた、前後方向に延びる矩形平板部材である。また、ガイド部32は、上下方向上側が上方に延びるにつれて吊環30から離間するように屈曲した形状である。また更に、ガイド部32の上端は、吊穴34より上方に延びている。
The
図3を参照すると、図2中の矢視Aから吊部23及びカウンタウエイト11を視た図が示されている。
吊部23は、カウンタウエイト11に埋め込まれて配設される。詳しくは、吊部23は、上下方向下部にピン36が設けられており、カウンタウエイト11から吊部23が上方に抜けないようカウンタウエイト11にピン36によって固定される。
Referring to FIG. 3, a view of the hanging
The hanging
図4を参照すると、油圧ショベル1の吊上げ作業時の側面図が示されている。
吊上げ作業時、油圧ショベル1は、前部がブーム13に設けられたブーム吊部14、14に、後部がカウンタウエイト11に設けられた吊部23、23の吊環30、30にそれぞれワイヤ40が掛止されて吊上げられる。詳しくは、ワイヤ40の一端に設けられたシャックル42がブーム吊部14、14及び吊環30、30のそれぞれに掛止されており、ワイヤ40の他端を重力方向上方に吊上げることで油圧ショベル1を吊上げることができる。
Referring to FIG. 4, a side view of the hydraulic shovel 1 during the lifting operation is shown.
At the time of lifting work, the hydraulic shovel 1 has the
図5を参照すると、油圧ショベル1の吊上げ作業後における吊部23及びシャックル42の状態が斜視図によって示されている。シャックル42は、吊上げ作業後、即ち油圧ショベル1が地面に着地すると重力によって吊穴34の周縁の下部に当たるまで降下し、該吊穴34の下部に設置した部分を基点に左右方向に吊穴34の開口方向を軸にして回動する。このとき、シャックル42は、ガイド部32によって支持される。更に、ワイヤ40は、該シャックル42が左右方向に吊穴34の開口方向を軸にして回動するので、油圧ショベル1の前側に撓むことなく油圧ショベル1の左右方向に撓む。シャックル42もまた同様に油圧ショベル1の前側に倒れることなく油圧ショベル1の左右方向に倒れる。
Referring to FIG. 5, the state of the hanging
即ち、吊部23は、油圧ショベル1に設けられたエンジン10に向かってシャックル42が倒れることや、ワイヤ40が撓んで該エンジン10を破損させることを抑制することができる。故に、シャックル42がガイド部32によって支持されることで、カウンタウエイト11の意匠面を傷つけないように支持することができる。
That is, the hanging
以上説明したように、本発明に係る建設機械では、エンジン10及びエンジン10の後方にカウンタウエイト11が搭載された油圧ショベル1において、カウンタウエイト11の上部に2つ左右に並んで配設され、上方に向かって延びる吊環30と、吊環30の上端に設けられ、前後方向に開口してなる吊穴34とを備えて構成している。
As described above, in the construction machine according to the present invention, the
従って、前後方向に開口する吊穴34が設けられた吊環30をカウンタウエイト11の上部に2つ左右に並んで配設するようにしたので、シャックル42は、油圧ショベル1の吊上げ作業の用にワイヤ40の一端に設けられたシャックル42が吊穴34を貫通するように装着され、該吊上げ作業後、即ち油圧ショベル1が接地してワイヤ40が撓むとき、吊穴34の開口方向を軸にして回動する。故に、吊穴34の開口方向が前後方向であるため、シャックル42は、重力によって左右方向に回動して倒れることとなり、換言すればカウンタウエイト11より前方にシャックル42及びワイヤ40が倒れ込みエンジン10を損傷させることを防止することができる。
Therefore, since the hanging
特に、ガイド部32の上端は、上方に延びるにつれて吊環30から離間する方向に屈曲しているので、シャックル42を吊穴34に取付ける際にガイド部32が該取り付け作業の邪魔にならないようにすることができる。
そして、吊環30は、左右方向に延びる平板形状であり、ガイド部32は、前後方向に延びる左右一対の平板形状であり、吊環30及びガイド部32は、溶接により結合されて形成されるので、吊環30の前後方向に加わる力をガイド部32によって補強することができる。
In particular, the upper end of the
The
以上で本発明に係る建設機械の説明を終えるが、本発明は上記実施形態に限られるものではなく、発明の主旨を逸脱しない範囲で変更可能である。
例えば、本実施形態では、建設機械として油圧ショベル1を用いて説明しているが、油圧ショベル以外の建設機械でもよく、油圧ショベルのみに限らない。
This completes the description of the construction machine according to the present invention, but the present invention is not limited to the above embodiment, and can be changed without departing from the scope of the invention.
For example, in this embodiment, although explained using hydraulic excavator 1 as a construction machine, construction machines other than a hydraulic shovel may be used, and it is not restricted only to a hydraulic shovel.
また、本実施形態では、ガイド部32が吊環30の左右に溶接して設けられるようにしているが、溶接でなくてもよく、H型の断面を有して延びる柱状の部材を加工して形成することで一体型にしてもよい。詳しくは、該部材のH型の断面の真ん中の棒に該当する部分を削り出し及び開口させて吊環30とし、H型の断面の残りの棒に該当する部分を折り曲げてガイド部32となるようにしてもよい(図6)。
Moreover, in the present embodiment, the
1 油圧ショベル(建設機械)
5 上部旋回体(機体)
10 エンジン
11 カウンタウエイト
22 突出部
23 吊部
30 吊環
32 ガイド部
34 吊穴
40 ワイヤ
42 シャックル
1 Hydraulic excavator (construction machine)
5 Upper revolving unit (airframe)
DESCRIPTION OF
Claims (5)
前記機体にエンジン及びエンジンの後方にカウンタウエイトが搭載されている建設機械において、
前記カウンタウエイトの上部に複数配設され、上方に向かって延びる吊環を備え、
前記吊環には、前記機体の前後方向に開口してなる吊穴が設けられている、
ことを特徴とする建設機械。 The aircraft,
In a construction machine having an engine and a counterweight mounted behind the engine on the airframe,
A plurality of ring rings disposed above the counterweight and extending upward,
The hanging ring is provided with a hanging hole opened in the front-rear direction of the machine body,
Construction machinery characterized by.
前記ガイド部は、前記機体の前後方向に延びる左右一対の平板形状であり、
前記吊環及び前記ガイド部は、結合または一体に形成されていることを特徴とする、請求項2または3に記載の建設機械。 The suspension ring has a flat plate shape extending in the left-right direction of the airframe,
The guide portion has a pair of left and right flat plate shapes extending in the front-rear direction of the airframe,
The construction machine according to claim 2 or 3, wherein the suspension ring and the guide portion are formed integrally or integrally.
前記吊環は、前記突出部に設けられていることを特徴とする、請求項1に記載の建設機械。 The counterweight is further provided with a protrusion that protrudes rearward.
The construction machine according to claim 1, wherein the hanging ring is provided at the projecting portion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017190342A JP2019065518A (en) | 2017-09-29 | 2017-09-29 | Construction machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017190342A JP2019065518A (en) | 2017-09-29 | 2017-09-29 | Construction machine |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2019065518A true JP2019065518A (en) | 2019-04-25 |
Family
ID=66339217
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2017190342A Pending JP2019065518A (en) | 2017-09-29 | 2017-09-29 | Construction machine |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2019065518A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2023286309A1 (en) * | 2021-07-16 | 2023-01-19 | 日本国土開発株式会社 | Construction machine |
-
2017
- 2017-09-29 JP JP2017190342A patent/JP2019065518A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2023286309A1 (en) * | 2021-07-16 | 2023-01-19 | 日本国土開発株式会社 | Construction machine |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5173976B2 (en) | Construction equipment front guard mounting device | |
JP2013087455A (en) | Work machine | |
US9982412B1 (en) | Dragline bucket assembly | |
JP2006233641A (en) | Earth removal device of construction machine | |
CN101426980A (en) | Boom for excavation machine | |
JP2019065518A (en) | Construction machine | |
CN110171777B (en) | Crawler crane for reconstruction of excavator and connector for crawler crane | |
JP2007023607A (en) | Bucket device of excavator | |
KR102001256B1 (en) | Clamshell bucket | |
WO2013027328A1 (en) | Work machine | |
EP3812515B1 (en) | Rotary working vehicle | |
JP7067223B2 (en) | Work machine equipped with a hanging tool at the connection part of the attachment | |
JP5699027B2 (en) | Excavator | |
JP6648081B2 (en) | Hydraulic excavator | |
JP4781416B2 (en) | Construction machinery | |
JP3659393B2 (en) | Civil work machine work attachment | |
JP2019173478A (en) | Construction machine | |
JP2014141805A (en) | Wide grab bucket for thin layer | |
JP5430606B2 (en) | Double-armed work machine | |
JP7496292B2 (en) | Construction Machinery | |
JP2018111983A (en) | Construction machine | |
JP2011106118A (en) | Working apparatus for construction machine | |
JP2007162404A (en) | Hydraulic shovel | |
JP2003147797A (en) | Work tool connecting device of construction machine | |
JP6689535B2 (en) | Drag line |