JP2019056227A - Method of placing steel sheet piles - Google Patents

Method of placing steel sheet piles Download PDF

Info

Publication number
JP2019056227A
JP2019056227A JP2017180601A JP2017180601A JP2019056227A JP 2019056227 A JP2019056227 A JP 2019056227A JP 2017180601 A JP2017180601 A JP 2017180601A JP 2017180601 A JP2017180601 A JP 2017180601A JP 2019056227 A JP2019056227 A JP 2019056227A
Authority
JP
Japan
Prior art keywords
sheet pile
steel sheet
placing
guide
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017180601A
Other languages
Japanese (ja)
Other versions
JP6288362B1 (en
Inventor
祐人 田中
Sachito Tanaka
祐人 田中
山崎 直樹
Naoki Yamazaki
直樹 山崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
JFE Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Engineering Corp filed Critical JFE Engineering Corp
Priority to JP2017180601A priority Critical patent/JP6288362B1/en
Application granted granted Critical
Publication of JP6288362B1 publication Critical patent/JP6288362B1/en
Publication of JP2019056227A publication Critical patent/JP2019056227A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

To provide a method of placing steel sheet piles with improved placement accuracy and construction efficiency.SOLUTION: A method of placing steel sheet piles in which a plurality of steel sheet piles 20 are connected to each other at joint portions and the steel sheet piles are placed in a single row, comprises a pre-placement step of placing the steel sheet piles 20 in the two end areas in advance, a guide sheet pile arrangement step in which a plurality of guide sheet piles are arranged in a row, connected to each other at the joint portion of the guide sheet piles in a central area located between the two end areas, the joint portions of guide sheet piles arranged at both ends of the plurality of guide sheet piles arranged in a row are respectively connected to and arranged at the joint portions of the steel sheet pile 20 at the end on the side of the steel sheet pile 20, which is placed in advance of the two end areas, toward the center portion of one row, and a replacement and placing step of sequentially replacing and placing the plurality of guide sheet piles arranged in the guide sheet pile arrangement step into a permanent steel sheet pile 20 whose cross section in the width direction is substantially the same as the guide sheet pile.SELECTED DRAWING: Figure 1

Description

本発明は、鋼矢板の打設方法に関し、詳細には、本設の鋼矢板ではないガイド矢板を用いることにより打設精度と施工効率を向上させた鋼矢板の打設方法に関する。   TECHNICAL FIELD The present invention relates to a steel sheet pile placing method, and more particularly, to a steel sheet pile placing method in which placement accuracy and construction efficiency are improved by using a guide sheet pile that is not a steel pile sheet.

アーク矢板ジャケット工法は、図24に示されるように、ジャケット式桟橋300と土留め壁100を一体化した岸壁の構築工法であるが、土留め壁100を、直線形鋼矢板102を円弧(アーク)状に打設してなる鋼矢板セル式土留めのアーク矢板104と、サドルプレート106によって構成している(例えば、非特許文献1参照)。アーク矢板104とサドルプレート106で構成される土留め壁100の施工においては、アーク矢板104を確実に閉合することが必要であり、そのためには、個々の直線形鋼矢板102を高い精度で打設することが必要である(例えば、非特許文献2参照)。   As shown in FIG. 24, the arc sheet pile jacket construction method is a construction method of a quay where the jacket type pier 300 and the retaining wall 100 are integrated. ) Steel sheet pile cell type earth retaining arc sheet pile 104 and saddle plate 106 (see Non-Patent Document 1, for example). In the construction of the retaining wall 100 composed of the arc sheet pile 104 and the saddle plate 106, it is necessary to securely close the arc sheet pile 104. For this purpose, the individual straight steel sheet piles 102 are hit with high accuracy. It is necessary to install (for example, refer nonpatent literature 2).

また、非特許文献2においては、「左右から最終根入れまで打ち下げて、残りの中央部の数枚を交互に屏風打設して打ち下げる方法」(具体的には、両端のサドルプレートから左右4枚ずつ中央に向けて打設した後、中央部で残り5枚の矢板を建て込み、両端の矢板から順に少しずつ打ち下げる作業を繰り返し、所定の深度まで打ち込む屏風打ちを行う方法。)を採用することで、アーク矢板104を円滑に閉合できた旨が報告されている。   Further, in Non-Patent Document 2, “a method of lowering from the left and right to the final insertion, and placing several remaining sheets in the center portion alternately and driving down” (specifically, from the saddle plates at both ends) (4) After placing 4 sheets left and right toward the center, build up the remaining 5 sheet piles at the center, repeat the work of gradually lowering from the sheet piles at both ends, and drive to a predetermined depth. It has been reported that the arc sheet pile 104 can be closed smoothly by adopting.

しかしながら、アーク矢板ジャケット工法において、アーク矢板をより高い打設精度で打設するとともに、より高い施工効率を実現することがさらに求められている。   However, in the arc sheet pile jacket method, it is further required to place the arc sheet pile with higher placement accuracy and to realize higher construction efficiency.

また、アーク矢板ジャケット工法に限らず、鋼矢板を打設する工事全般において、鋼矢板の打設精度と施工効率を向上させることが望まれている。   Further, not only the arc sheet pile jacket method but also the overall construction of placing steel sheet piles is desired to improve the steel sheet pile placing accuracy and construction efficiency.

高橋久雄、外5名、「アーク矢板ジャケット工法におけるアーク矢板打設の試験施工」、平成28年度土木学会全国大会 第71回年次学術講演会 講演概要集、平成28年9月、VI-628、p.1255 - 1266Hisao Takahashi and five others, “Test construction of arc sheet pile placement in the arc sheet pile jacket method”, Annual Conference of the 71st Annual Conference of Japan Society of Civil Engineers, September 2016, VI-628 , P.1255-1266 高橋久雄、外5名、「アーク矢板ジャケット工法におけるアーク矢板土留めの本施工」、平成28年度土木学会全国大会 第71回年次学術講演会 講演概要集、平成28年9月、VI-627、p. 1253 - 1254Hisao Takahashi and five others, “Main construction of arc sheet pile earth retaining in the arc sheet pile jacket method”, Annual Conference of the 71st Annual Conference of Japan Society of Civil Engineers, September 2016, VI-627 , P. 1253-1254

本発明は、かかる状況に鑑みてなされたものであり、打設精度と施工効率を向上させた鋼矢板の打設方法を提供することを課題とする。   This invention is made | formed in view of this condition, and makes it a subject to provide the placement method of the steel sheet pile which improved the placement precision and construction efficiency.

本発明は、以下の鋼矢板の打設方法により、前記課題を解決したものである。   The present invention solves the above problems by the following steel sheet pile driving method.

即ち、本発明に係る鋼矢板の打設方法は、幅方向の両方の端部に継手部を備えた鋼矢板を、前記継手部でお互いに連結させて一列状に複数打設する鋼矢板の打設方法であって、一列状に複数打設する鋼矢板のうち、それらの両端部に位置する鋼矢板をそれぞれ含むとともに、それらの両端部から前記一列状の中央部に向かってそれぞれ所定の枚数の鋼矢板を含む2つの端部領域の鋼矢板を先行して打設する先行打設工程と、前記先行打設工程で先行して打設された前記鋼矢板の長さよりも長さが短く、かつ、幅方向の両方の端部に継手部を備えたガイド矢板を、前記2つの端部領域の間に位置する中央部領域に、前記ガイド矢板の前記継手部でお互いに連結させて一列状に複数配置するとともに、一列状に複数配置する前記ガイド矢板のうち両端部に配置する前記ガイド矢板の前記継手部を、前記2つの端部領域に先行して打設された前記鋼矢板のうち前記一列状の中央部に向かう側の端部の鋼矢板の前記継手部にそれぞれ連結させて配置するガイド矢板配置工程と、前記ガイド矢板配置工程で配置した前記複数のガイド矢板を、幅方向断面が前記ガイド矢板と略同一である本設の鋼矢板に順次置き換えて打設する置き換え打設工程と、を有することを特徴とする鋼矢板の打設方法である。   That is, the steel sheet pile driving method according to the present invention is a steel sheet pile in which a plurality of steel sheet piles provided with joint portions at both ends in the width direction are connected to each other at the joint portions to form a plurality of steel sheet piles. Among the steel sheet piles to be placed in a row, each of the steel sheet piles is located at both ends of each of the sheet piles, and each of the predetermined distances from the both ends toward the center of the row A preceding placement step of placing steel sheet piles in two end regions including a number of steel sheet piles in advance, and a length longer than the length of the steel sheet pile placed in advance in the preceding placement step A guide sheet pile that is short and has joint portions at both ends in the width direction is connected to each other at the joint portion of the guide sheet pile in a central region located between the two end regions. Among the guide sheet piles that are arranged in a row and arranged in a row The joint of the guide sheet pile arranged at the end portion is the steel sheet pile at the end portion on the side facing the central portion of the row of steel sheet piles placed in advance of the two end regions. The guide sheet pile arrangement step that is connected to the joint portion and arranged, and the plurality of guide sheet piles arranged in the guide sheet pile arrangement step are sequentially replaced with main steel sheet piles whose cross sections in the width direction are substantially the same as the guide sheet piles. A steel sheet pile placing method comprising: a replacement placing step for placing the steel sheet pile.

ここで、鋼矢板の「幅方向」とは、鋼矢板として地盤に打設された状態において地盤面から立ち上がる方向と直交する方向で、かつ、当該鋼矢板の面内方向(当該鋼矢板が形成する壁面内の方向)のことである。   Here, the “width direction” of the steel sheet pile is a direction orthogonal to the direction rising from the ground surface in the state of being placed on the ground as a steel sheet pile, and the in-plane direction of the steel sheet pile (formed by the steel sheet pile) Direction in the wall surface).

また、ガイド矢板の「幅方向」とは、ガイド矢板として地盤に配置された状態において地盤面から立ち上がる方向と直交する方向で、かつ、当該ガイド矢板の面内方向(当該ガイド矢板が形成する壁面内の方向)のことである。   Further, the “width direction” of the guide sheet pile is a direction orthogonal to the direction rising from the ground surface in a state where the guide sheet pile is arranged on the ground, and the in-plane direction of the guide sheet pile (the wall surface formed by the guide sheet pile) (Inside direction).

また、鋼矢板の幅方向断面とは、鋼矢板として地盤に打設された状態において、当該鋼矢板が地盤面から立ち上がる方向と直交する平面で当該鋼矢板を切断して得られる断面のことであり、ガイド矢板の幅方向断面とは、ガイド矢板として地盤に配置された状態において、当該ガイド矢板が地盤面から立ち上がる方向と直交する平面で当該ガイド矢板を切断して得られる断面のことである。   In addition, the cross section in the width direction of the steel sheet pile is a cross section obtained by cutting the steel sheet pile in a plane perpendicular to the direction in which the steel sheet pile rises from the ground surface in a state where the steel sheet pile is placed on the ground. Yes, the cross-section in the width direction of the guide sheet pile is a cross section obtained by cutting the guide sheet pile in a plane perpendicular to the direction in which the guide sheet pile rises from the ground surface in the state where the guide sheet pile is arranged on the ground. .

また、ガイド矢板と該ガイド矢板と置き換える本設の鋼矢板の幅方向断面が略同一であるとは、作製時等の誤差以外は同一ということであり、実質的に同一の幅方向断面とみなせるということである。   Also, the fact that the width direction cross section of the guide sheet pile and the steel sheet pile of the present construction that replaces the guide sheet pile is substantially the same means that it is the same except for errors during production, etc., and can be regarded as substantially the same width direction cross section. That's what it means.

前記一列状に複数打設する鋼矢板の幅方向断面は、略同一であってもよい。   The cross sections in the width direction of the steel sheet piles that are placed in a row may be substantially the same.

ここで、鋼矢板の幅方向断面が略同一であるとは、作製時等の誤差以外は同一ということであり、実質的に同一の幅方向断面とみなせるということである。   Here, that the cross sections in the width direction of the steel sheet piles are substantially the same means that they are the same except for errors during production and the like, and can be regarded as substantially the same cross section in the width direction.

前記置き換え打設工程においては、前記ガイド矢板配置工程で配置した前記複数のガイド矢板のうちの一部のガイド矢板であってお互いに隣り合っていないガイド矢板を選んで前記本設の鋼矢板に置き換えて打設する工程が含まれていてもよい。   In the replacement placing step, the guide sheet piles that are part of the plurality of guide sheet piles arranged in the guide sheet pile arrangement step and that are not adjacent to each other are selected to the main steel sheet piles. A step of replacing and placing may be included.

前記置き換え打設工程においては、前記ガイド矢板配置工程で配置した前記複数のガイド矢板のうちの一部のガイド矢板であって1つ飛ばしに配置されたガイド矢板を選んで前記本設の鋼矢板に置き換えて打設する工程が含まれていてもよい。   In the replacement driving step, the main steel sheet pile is selected by selecting one guide sheet pile among the plurality of guide sheet piles arranged in the guide sheet pile arrangement step. A step of placing and placing may be included.

前記置き換え打設工程においては、前記ガイド矢板配置工程で配置した前記複数のガイド矢板のうちの一部のガイド矢板であって2つ飛ばしに配置されたガイド矢板を選んで前記本設の鋼矢板に置き換えて打設する工程が含まれていてもよい。   In the replacement driving step, the main steel sheet pile is selected by selecting a guide sheet pile that is a part of the plurality of guide sheet piles arranged in the guide sheet pile arrangement step. A step of placing and placing may be included.

前記一列状に複数打設する鋼矢板の両端部の位置は、予め決められていてもよい。   The position of the both ends of the steel sheet pile to be placed in a row may be determined in advance.

前記鋼矢板の幅方向断面は、略直線形状であってもよい。   The cross section in the width direction of the steel sheet pile may be substantially linear.

ここで、鋼矢板の幅方向断面が略直線形状であるとは、継手部等の細部の形状を除けば、全体として直線形状であると判断できるということである。   Here, that the cross section in the width direction of the steel sheet pile has a substantially linear shape means that it can be determined as a whole linear shape except for the shape of details such as the joint portion.

前記一列状に複数打設する鋼矢板のうちの少なくとも一部の鋼矢板は、曲線状に列を形成していてもよい。   At least some of the steel sheet piles that are placed in a single row may form a curved line.

前記鋼矢板の前記継手部の遊びが8mm以上12mm以下であってもよい。   The play of the joint portion of the steel sheet pile may be 8 mm or more and 12 mm or less.

ここで、「前記鋼矢板の前記継手部の遊び」とは、連結される2つの前記鋼矢板の幅方向の嵌合余裕代のことであり、具体的には、前記継手部でお互いに連結された2つの前記鋼矢板に、幅方向に引張力を加えた場合と幅方向に圧縮力を加えた場合における、前記連結された2つの前記鋼矢板の幅方向の長さの差のことである。   Here, “the play of the joint portion of the steel sheet pile” is a margin of fitting margin in the width direction of the two steel sheet piles to be connected. Specifically, the joint portions are connected to each other at the joint portion. The difference in length in the width direction between the two connected steel sheet piles when the tensile force is applied in the width direction and the compressive force is applied in the width direction. is there.

前記ガイド矢板が前記ガイド矢板配置工程で地盤に配置された状態において、前記ガイド矢板の上端の高さ位置は、当該ガイド矢板に対して作業を行う作業者の足場面よりも1m以上2m以下だけ高い位置であることが好ましい。   In the state where the guide sheet pile is arranged on the ground in the guide sheet pile arrangement step, the height position of the upper end of the guide sheet pile is only 1 m or more and 2 m or less than the foot scene of the operator who performs work on the guide sheet pile. A high position is preferable.

本発明に係る鋼矢板の打設方法によれば、打設精度と施工効率を向上させることができる。   According to the steel sheet pile driving method according to the present invention, the driving accuracy and construction efficiency can be improved.

本発明の第1実施形態および第2実施形態に係る鋼矢板の打設方法を用いて打設を行う直線形鋼矢板20の打設位置および配置状況を模式的に示す平面図The top view which shows typically the placement position and arrangement | positioning condition of the linear steel sheet pile 20 which performs placing using the steel sheet pile placing method which concerns on 1st Embodiment and 2nd Embodiment of this invention. 直線形鋼矢板20の幅方向断面を示す拡大断面図The expanded sectional view which shows the width direction cross section of the linear steel sheet pile 20 直線形鋼矢板20についての弱軸回りの方向および強軸回りの方向を模式的に示した図The figure which showed typically the direction of the weak axis about the linear steel sheet pile 20, and the direction of the strong axis 図2および図5のIV−IV線断面図であり、取り付け治具32の部位を拡大して示す拡大側断面図It is the IV-IV sectional view taken on the line of FIG. 2 and FIG. 5, and the expanded side sectional view which expands and shows the site | part of the attachment jig 32 図2および図4のV−V線断面図であり、取り付け治具32の部位を拡大して示す拡大正断面図FIG. 5 is a cross-sectional view taken along the line V-V in FIGS. 2 and 4, and is an enlarged front cross-sectional view showing an enlarged portion of the mounting jig 32. 4つの直線形鋼矢板20が、継手部20Aを介してお互いに連結している状況を示す幅方向断面図Cross-sectional view in the width direction showing a state in which the four straight steel sheet piles 20 are connected to each other via the joint portion 20A. 本発明の第1実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placement method of the steel sheet pile concerning 1st Embodiment of this invention. 本発明の第1実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placement method of the steel sheet pile concerning 1st Embodiment of this invention. 本発明の第1実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placement method of the steel sheet pile concerning 1st Embodiment of this invention. 本発明の第1実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placement method of the steel sheet pile concerning 1st Embodiment of this invention. 本発明の第1実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placement method of the steel sheet pile concerning 1st Embodiment of this invention. 本発明の第1実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placement method of the steel sheet pile concerning 1st Embodiment of this invention. 4つのガイド矢板24が、継手部24Aを介してお互いに連結している状況を示す幅方向断面図Cross-sectional view in the width direction showing a state in which the four guide sheet piles 24 are connected to each other via the joint portion 24A. 非特許文献2で報告されている工事における中央部領域(打設位置5〜9)への本設の直線形鋼矢板20の建て込み状況を模式的に示す図The figure which shows typically the erection situation of the linear steel sheet pile 20 of the permanent installation to the center part area | region (setting position 5-9) in the construction currently reported by the nonpatent literature 2. 非特許文献2で報告されている工事において、中央部領域(打設位置5〜9)に建て込んだ本設の直線形鋼矢板20を干渉が生じない範囲内で少しずつ(300mmずつ)打ち下げる作業を行っている状況を模式的に示す図In the construction reported in Non-Patent Document 2, hammering the straight steel sheet piles 20 installed in the central area (placement positions 5 to 9) little by little (300 mm) within a range where interference does not occur. The figure which shows the situation where the work which lowers is done typically 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. 本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階のうちの1つの段階を模式的に示す図The figure which shows typically one stage of each characteristic stage of the placing method of the steel sheet pile concerning 2nd Embodiment of this invention. アーク矢板ジャケット工法について模式的に示す斜視図Perspective view schematically showing arc sheet pile jacket method

以下、図面を参照しつつ、本発明の第1実施形態および第2実施形態に係る鋼矢板の打設方法について詳細に説明する。   Hereinafter, a steel sheet pile placing method according to the first and second embodiments of the present invention will be described in detail with reference to the drawings.

(1)本発明の第1実施形態および第2実施形態に係る鋼矢板の打設方法における共通事項
図1は、本発明の第1実施形態および第2実施形態に係る鋼矢板の打設方法を用いて打設を行う直線形鋼矢板20の打設位置および配置状況を模式的に示す平面図である。図2は、直線形鋼矢板20の幅方向断面を示す拡大断面図である。図1において補助H鋼30の上方に付した数字は、直線形鋼矢板20を打設する各打設位置を示している。
(1) Common items in the steel sheet pile placing method according to the first embodiment and the second embodiment of the present invention FIG. 1 shows a steel sheet pile placing method according to the first embodiment and the second embodiment of the present invention. It is a top view which shows typically the placement position and arrangement | positioning condition of the linear steel sheet pile 20 which performs placement using. FIG. 2 is an enlarged cross-sectional view showing a cross-section in the width direction of the linear steel sheet pile 20. In FIG. 1, the numbers given above the auxiliary H steel 30 indicate the respective placement positions at which the linear steel sheet pile 20 is to be placed.

以下では、直線形鋼矢板20の打設を、隣り合うサドルプレート23の間の打設位置1〜13において行って、アーク矢板22の構築を行う場合を取り上げて、本発明の第1実施形態および第2実施形態に係る鋼矢板の打設方法を説明する。アーク矢板22は、隣り合うサドルプレート23の間の打設位置1〜13に直線形鋼矢板20を打設することによって構築される。サドルプレート23は、打設位置1〜13に直線形鋼矢板20を打設する前に所定の位置に打設されている。したがって、打設位置1〜13に打設する直線形鋼矢板20の両端部の位置(打設位置1、13に打設する直線形鋼矢板20のサドルプレート23と嵌合する継手部20Aの位置)は、打設位置1〜13に直線形鋼矢板20を打設する前に予め決められている。   Hereinafter, the case where the arc sheet pile 22 is constructed by placing the straight steel sheet pile 20 at the placement positions 1 to 13 between the adjacent saddle plates 23 will be described. A method for placing a steel sheet pile according to the second embodiment will be described. The arc sheet pile 22 is constructed by placing linear steel sheet piles 20 at placement positions 1 to 13 between adjacent saddle plates 23. The saddle plate 23 is driven at a predetermined position before the linear steel sheet pile 20 is driven at the driving positions 1 to 13. Therefore, the positions of both ends of the linear steel sheet pile 20 to be placed at the placement positions 1 to 13 (of the joint portion 20A to be fitted with the saddle plate 23 of the linear steel sheet pile 20 to be placed at the placement positions 1 and 13). The position) is determined in advance before placing the linear steel sheet pile 20 at the placement positions 1 to 13.

直線形鋼矢板20は、図2に示すように、幅方向の両方の端部に継手部20Aを備えている。また、打設位置1〜13に打設される直線形鋼矢板20は、図2に示すように、その背面(埋立側の面)には、補助H鋼30が、取り付け治具32を介してそれぞれ取り付けられている。取り付け治具32は直線形鋼矢板20の背面(埋立側の面)に溶接で取り付けられている。直線形鋼矢板20の形状は、幅W=500mm、長さL=22m、厚さt=9.5mmであり、弱軸回りの曲げ剛性が小さく、そのため、直線形鋼矢板20は、打設時に弱軸回りに変形するおそれがある。図3は、直線形鋼矢板20についての弱軸回りの方向および強軸回りの方向を模式的に示した図である。弱軸回りの変形を防止するため、直線形鋼矢板20の曲げ剛性を補う補助H鋼30を介して鉛直方向下向きの力を直線形鋼矢板20に加えて打設するようにしている。ただし、地盤条件によっては、補助H鋼30を用いなくても直線形鋼矢板20を適切に打設できる場合もある。このような場合は、補助H鋼30を用いることは不要である。また、地盤条件によっては、補助H鋼30を用いるだけでなく、さらに、ウォータージェットを併用した方が適切な場合がある。このような場合にはウォータージェットを併用してもよい。   As shown in FIG. 2, the linear steel sheet pile 20 includes joint portions 20 </ b> A at both ends in the width direction. Further, as shown in FIG. 2, the linear steel sheet pile 20 to be placed at the placement positions 1 to 13 is provided with an auxiliary H steel 30 on the back surface (surface on the landfill side) via an attachment jig 32. Are attached to each. The attachment jig 32 is attached to the back surface (surface on the landfill side) of the linear steel sheet pile 20 by welding. The shape of the linear steel sheet pile 20 is W = 500 mm, length L = 22 m, and thickness t = 9.5 mm, and the bending rigidity around the weak axis is small. There is a risk of deformation around the weak axis. FIG. 3 is a diagram schematically showing the direction around the weak axis and the direction around the strong axis for the linear steel sheet pile 20. In order to prevent deformation around the weak axis, a vertical downward force is applied to the linear steel sheet pile 20 through the auxiliary H steel 30 that supplements the bending rigidity of the linear steel sheet pile 20. However, depending on the ground conditions, the straight steel sheet pile 20 may be appropriately driven without using the auxiliary H steel 30. In such a case, it is not necessary to use the auxiliary H steel 30. Further, depending on the ground conditions, it may be appropriate not only to use the auxiliary H steel 30 but also to use a water jet together. In such a case, a water jet may be used in combination.

図4は、図2および図5のIV−IV線断面図であり、取り付け治具32の部位を拡大して示す拡大側断面図である。図5は、図2および図4のV−V線断面図であり、取り付け治具32の部位を拡大して示す拡大正断面図である。   4 is a cross-sectional view taken along the line IV-IV in FIGS. 2 and 5, and is an enlarged side cross-sectional view showing a portion of the attachment jig 32 in an enlarged manner. FIG. 5 is a cross-sectional view taken along the line VV in FIGS. 2 and 4 and is an enlarged front cross-sectional view showing an enlarged portion of the attachment jig 32.

図4、図5に示すように、補助H鋼30のフランジ30Aには、取り付け治具32と係合する切り欠き30A1が設けられている。切り欠き30A1の上辺部が取り付け治具32と係合して、鉛直方向下向きの力が、補助H鋼30から取り付け治具32を介して直線形鋼矢板20に伝達できるようになっている。一方、補助H鋼30を上方に引き抜く際には、取り付け治具32は切り欠き30A1と係合しないので、直線形鋼矢板20の打設完了後に補助H鋼30を上方に引き抜いて撤去できるようになっている。なお、図4、図5において、符号30Bは、補助H鋼30のウェブを示している。   As shown in FIGS. 4 and 5, the flange 30 </ b> A of the auxiliary H steel 30 is provided with a notch 30 </ b> A <b> 1 that engages with the attachment jig 32. The upper side portion of the notch 30A1 is engaged with the attachment jig 32, so that a downward force in the vertical direction can be transmitted from the auxiliary H steel 30 to the linear steel sheet pile 20 via the attachment jig 32. On the other hand, when the auxiliary H steel 30 is pulled upward, the mounting jig 32 does not engage with the notch 30A1, so that the auxiliary H steel 30 can be pulled upward and removed after the linear steel sheet pile 20 is placed. It has become. 4 and 5, reference numeral 30 </ b> B indicates a web of the auxiliary H steel 30.

図4、図5に示す取り付け治具32は、直線形鋼矢板20の長手方向の異なる複数の中間部(上端と下端以外の部位であり、例えば、直線形鋼矢板20の全長の3分の1の地点および3分の2の地点)に設けられている。直線形鋼矢板20の上端と下端に設けられている取り付け治具(図示せず)は、取り付け治具32と形状が異なる。直線形鋼矢板20の上端に設けられている取り付け治具は、上向きの力を補助H鋼30から直線形鋼矢板20に伝達できるようになっており、かつ、直線形鋼矢板20からの取り外しも容易に行えるようになっている。直線形鋼矢板20の下端に設けられている取り付け治具は、下向きの力のみを直線形鋼矢板20に伝達できるようになっている。   The attachment jig 32 shown in FIGS. 4 and 5 is a plurality of intermediate parts (parts other than the upper end and the lower end of the linear steel sheet pile 20 that are different in the longitudinal direction. 1 point and 2/3 point). Mounting jigs (not shown) provided at the upper and lower ends of the linear steel sheet pile 20 are different in shape from the mounting jig 32. The attachment jig provided at the upper end of the linear steel sheet pile 20 can transmit an upward force from the auxiliary H steel 30 to the linear steel sheet pile 20 and is detached from the linear steel sheet pile 20. Can be easily done. The mounting jig provided at the lower end of the linear steel sheet pile 20 can transmit only a downward force to the linear steel sheet pile 20.

図6は、4つの直線形鋼矢板20が、継手部20Aを介してお互いに連結している状況を示す幅方向断面図である。図6に示すように、直線形鋼矢板20同士は一列状に連結しており、土圧等の外力に対してフープテンション(嵌合している矢板列の面内周方向引張力)で抵抗することができるようになっている。したがって、直線形鋼矢板20の継手部20Aの遊びは、8mm以上12mm以下と小さく設定されている。ここで、直線形鋼矢板20の継手部20Aの遊びとは、連結される2つの直線形鋼矢板20の幅方向の嵌合余裕代のことであり、具体的には、継手部20Aでお互いに連結された2つの直線形鋼矢板20に、幅方向に引張力を加えた場合と幅方向に圧縮力を加えた場合における、連結された2つの直線形鋼矢板20の幅方向の長さの差のことである。   FIG. 6 is a cross-sectional view in the width direction showing a state in which the four straight steel sheet piles 20 are connected to each other via the joint portion 20A. As shown in FIG. 6, the linear steel sheet piles 20 are connected in a row, and resist against external force such as earth pressure by hoop tension (in-plane circumferential tensile force of the fitted sheet pile row). Can be done. Therefore, the play of the joint part 20A of the linear steel sheet pile 20 is set as small as 8 mm or more and 12 mm or less. Here, the play of the joint part 20A of the linear steel sheet pile 20 is a margin of fitting margin in the width direction of the two linear steel sheet piles 20 to be connected. The width of the two linear steel sheet piles 20 connected in the width direction when a tensile force is applied in the width direction and a compressive force is applied in the width direction to the two linear steel sheet piles 20 connected to each other Is the difference between

なお、図6においては、補助H鋼30等の記載は省略している。   In addition, in FIG. 6, description of the auxiliary H steel 30 grade | etc., Is abbreviate | omitted.

(2)本発明の第1実施形態に係る鋼矢板の打設方法の手順
図7〜図12は本発明の第1実施形態に係る鋼矢板の打設方法の特徴的な各段階を模式的に示す図である。図7〜図12において、各直線形鋼矢板20または各ガイド矢板24の上方に記載した数字は、直線形鋼矢板20を打設する各打設位置(図1参照)を示している。本第1実施形態に係る鋼矢板の打設方法を実施する地点の海底面の深さは、海面から6.5mである。また、本第1実施形態に係る鋼矢板の打設方法を実施するに当たり、海面から1〜1.5mの高さ位置に、作業者が作業する足場面の高さが位置するように、足場を構築している。なお、図7〜図12においては、補助H鋼30等の記載は省略しており、また、以降に記載する図14〜図23についても同様である。
(2) Procedure of the steel sheet pile placing method according to the first embodiment of the present invention FIGS. 7 to 12 schematically show the characteristic steps of the steel sheet pile placing method according to the first embodiment of the present invention. FIG. 7-12, the number described above each linear steel sheet pile 20 or each guide sheet pile 24 has shown each placement position (refer FIG. 1) which places the linear steel sheet pile 20. FIG. The depth of the sea bottom at the point where the steel sheet pile driving method according to the first embodiment is carried out is 6.5 m from the sea surface. In addition, in carrying out the steel sheet pile driving method according to the first embodiment, the scaffold is positioned so that the height of the foot scene on which the worker works is located at a height of 1 to 1.5 m from the sea surface. Is building. In addition, in FIGS. 7-12, description of the auxiliary | assistant H steel 30 grade | etc., Is abbreviate | omitted, and it is the same also about FIGS. 14-23 described later.

図7は、先行打設工程を実施した後の状態を模式的に示す図である。   FIG. 7 is a diagram schematically showing a state after the preceding placing step.

先行打設工程では、打設位置1〜13のうち、両端部に位置する打設位置1、13をそれぞれ含むとともに、打設位置1、13から一列状に並んだ打設位置1〜13の中央部に向かってそれぞれ4つの打設位置を含む2つの端部領域(打設位置1〜4の端部領域と打設位置10〜13の端部領域)について本設の直線形鋼矢板20を先行して打設する。   In the preceding placement process, the placement positions 1 to 13 located at both ends of the placement positions 1 to 13 are included, and the placement positions 1 to 13 arranged in a line from the placement positions 1 and 13 are included. The linear steel sheet pile 20 of this installation about two edge area | regions (the edge area | region of the casting positions 1-4 and the edge area of the casting positions 10-13) each including four placement positions toward a center part. Is placed in advance.

詳細には、この先行打設工程では、打設位置1〜4の端部領域について、打設位置1、2、3、4の順に片押しで、直線形鋼矢板20を所定の深さまで地盤80に打設するととともに、打設位置10〜13の端部領域について、打設位置13、12、11、10の順に片押しで、直線形鋼矢板20を所定の深さまで地盤80に打設する。両端部に位置する打設位置1、13に打設する直線形鋼矢板20は、継手部20Aをサドルプレート23に嵌合させて打設を行う。   Specifically, in the preceding placement process, the straight steel sheet pile 20 is grounded to a predetermined depth by pushing the placement areas 1, 2, 3, and 4 in the order of the end regions of the placement positions 1 to 4. 80, and at the end regions of the casting positions 10 to 13, the straight steel sheet pile 20 is driven to the ground 80 to a predetermined depth by one-pressing in the order of the casting positions 13, 12, 11, and 10. To do. The straight steel sheet piles 20 to be placed at the placement positions 1 and 13 located at both ends are placed by fitting the joint portion 20A to the saddle plate 23.

先行打設工程で本設の直線形鋼矢板20を所定の深さまで地盤80に打設する際には、例えば、バイブロハンマを用いて打設を行うことができる。   When the permanent straight steel sheet pile 20 is driven to the ground 80 to a predetermined depth in the preceding driving process, the driving can be performed using, for example, a vibro hammer.

この先行打設工程が終了した段階(図7に示す状態)では、2つの端部領域(打設位置1〜4および10〜13)については直線形鋼矢板20の打設が完了しているが、中央部領域(打設位置5〜9)については何も実施されていない状態である。   At the stage where the preceding placing process is completed (the state shown in FIG. 7), the placement of the linear steel sheet pile 20 is completed for the two end regions (placement positions 1 to 4 and 10 to 13). However, nothing is implemented for the central region (placement positions 5 to 9).

図8は、ガイド矢板配置工程を実施した後の状態を模式的に示す図である。   FIG. 8 is a diagram schematically illustrating a state after the guide sheet pile arrangement process is performed.

ガイド矢板配置工程では、先行打設工程の終了後(図7に示す状態の後)、中央部領域(打設位置5〜9)に、ガイド矢板24を継手部24Aでお互いに連結させて一列状に複数(5つ)配置するとともに、一列状に複数(5つ)配置するガイド矢板24のうち両端部(打設位置5、9)に配置するガイド矢板24の継手部24Aを、先行打設工程で2つの端部領域(打設位置1〜4および10〜13)に先行して打設された直線形鋼矢板20のうち一列状の中央部に向かう側の端部の直線形鋼矢板20(打設位置4、10に打設された直線形鋼矢板20)の継手部20Aにそれぞれ連結させて配置する。ガイド矢板24を所定の位置に配置する際には、例えば、クレーンに連結された吊下げ治具を用いて行うことができるが、本設の直線形鋼矢板20を打設する際に用いるバイブロハンマのチャック装置を振動させずに用いてもよい。   In the guide sheet pile arranging step, after the preceding placing step (after the state shown in FIG. 7), the guide sheet piles 24 are connected to each other by the joint portion 24A in the central region (placed positions 5 to 9). The joint portion 24A of the guide sheet pile 24 arranged at both ends (placement positions 5 and 9) of the guide sheet pile 24 arranged in a row (five) is arranged in advance. Of the straight steel sheet piles 20 placed in advance of the two end regions (placement positions 1 to 4 and 10 to 13) in the installation step, the linear steel at the end on the side toward the central portion in a line. The sheet piles 20 (the straight steel sheet piles 20 placed at the placement positions 4 and 10) are respectively connected to the joint portions 20A. When the guide sheet pile 24 is arranged at a predetermined position, for example, it can be performed using a hanging jig connected to a crane. The chuck device may be used without vibrating.

ガイド矢板24の幅方向断面の形状は、直線形鋼矢板20の幅方向断面の形状と同一であり、ガイド矢板24の幅方向の両方の端部には、幅方向断面の形状が直線形鋼矢板20の継手部20Aと同一である継手部24Aが設けられている。ガイド矢板24は、その長さが直線形鋼矢板20の長さよりも短くなっている。具体的には、本第1実施形態で用いるガイド矢板24の長さは、海底から海面上2.5mに達する長さであり、9mである。なお、前述したように、本第1実施形態に係る鋼矢板の打設方法を実施する地点の海底面の深さは、海面から6.5mである。   The shape of the cross section in the width direction of the guide sheet pile 24 is the same as the shape of the cross section in the width direction of the linear steel sheet pile 20, and the shape of the cross section in the width direction is linear steel at both ends in the width direction of the guide sheet pile 24. A joint portion 24A that is the same as the joint portion 20A of the sheet pile 20 is provided. The length of the guide sheet pile 24 is shorter than the length of the linear steel sheet pile 20. Specifically, the length of the guide sheet pile 24 used in the first embodiment is a length that reaches 2.5 m above the sea surface from the sea bottom, and is 9 m. As described above, the depth of the sea bottom at the point where the steel sheet pile placing method according to the first embodiment is performed is 6.5 m from the sea surface.

図13は、4つのガイド矢板24が、継手部24Aを介してお互いに連結している状況を示す幅方向断面図である。前述したように、ガイド矢板24の幅方向断面の形状は、直線形鋼矢板20の幅方向断面の形状と同一であるので、連結した4つのガイド矢板24についての幅方向断面図(図13)における輪郭線は、連結した4つの直線形鋼矢板20についての幅方向断面図(図6)における輪郭線と同一である。   FIG. 13 is a cross-sectional view in the width direction showing a state where the four guide sheet piles 24 are connected to each other via the joint portion 24A. As described above, since the shape of the cross section in the width direction of the guide sheet pile 24 is the same as the shape of the cross section in the width direction of the linear steel sheet pile 20, the cross section in the width direction of the four guide sheet piles 24 connected (FIG. 13). The contour line is the same as the contour line in the cross-sectional view in the width direction of the four linear steel sheet piles 20 connected (FIG. 6).

ガイド矢板24は、本設の直線形鋼矢板20の打設位置を事前に正確に把握するために用いる部材であり、地盤80上に配置するだけで地盤80に打設しないので、その配置位置の調整を容易に行うことができる。また、ガイド矢板24は、海底面上に配置するだけで地盤80に打設しないので、補助H鋼30も不要である。また、本設の直線形鋼矢板20の長さは22mであるのに対し、ガイド矢板24の長さは9mと短いので、この点からもガイド矢板24は配置位置の調整を容易に行うことができる。   The guide sheet pile 24 is a member used for accurately grasping in advance the placement position of the linear steel sheet pile 20 of the actual installation, and is disposed on the ground 80 and not placed on the ground 80. Can be easily adjusted. Further, since the guide sheet pile 24 is merely placed on the sea bottom and is not placed on the ground 80, the auxiliary H steel 30 is also unnecessary. In addition, the length of the straight steel sheet pile 20 is 22 m, whereas the length of the guide sheet pile 24 is as short as 9 m. From this point, the guide sheet pile 24 can easily adjust the arrangement position. Can do.

したがって、位置を微調整しながらガイド矢板24を中央部領域(打設位置5〜9)に配置して、先行打設工程で打設位置1〜4および10〜13に打設した8つの本設の直線形鋼矢板20と連結して閉合させることを、確実かつ容易に行うことができる。   Accordingly, the guide sheet pile 24 is arranged in the central region (placement positions 5 to 9) while finely adjusting the position, and the eight books placed in the placement positions 1 to 4 and 10 to 13 in the preceding placement process. It is possible to reliably and easily perform the connection and closing with the provided linear steel sheet pile 20.

また、前述したように、作業者が作業する足場面の高さ位置は、海面から1〜1.5mの高さ位置であるので、中央部領域(打設位置5〜9)に配置した長さ9mのガイド矢板24の上端の高さ位置は、作業者が作業する足場面の高さ位置よりも1〜1.5m上方の高さ位置である。したがって、すでに配置したガイド矢板24の隣の位置に別のガイド矢板24を配置する際、隣り合うガイド矢板24の継手部24A同士を嵌合させる作業を作業者が行いやすくなっている。   In addition, as described above, the height position of the foot scene on which the operator works is a height position of 1 to 1.5 m from the sea surface, so the length arranged in the central region (placed position 5 to 9). The height position of the upper end of the 9-meter guide sheet pile 24 is a height position 1 to 1.5 m higher than the height position of the foot scene on which the worker works. Therefore, when another guide sheet pile 24 is arranged at a position adjacent to the already arranged guide sheet pile 24, the operator can easily perform the operation of fitting the joint portions 24A of the adjacent guide sheet piles 24 together.

図9〜図12は、置き換え打設工程を実施している各段階の状態を模式的に示す図である。   9-12 is a figure which shows typically the state of each step which is implementing the replacement placement process.

置き換え打設工程では、ガイド矢板配置工程の終了後(図8に示す状態の後)、中央部領域(打設位置5〜9)に配置したガイド矢板24を本設の直線形鋼矢板20に順次置き換えて打設する。ガイド矢板配置工程で、ガイド矢板24が中央部領域(打設位置5〜9)に適切に配置されて、先行打設工程で打設位置1〜4および10〜13に打設した8つの本設の直線形鋼矢板20と適切に連結して閉合しているので、そのガイド矢板24と順次置き換えて本設の直線形鋼矢板20を打設すれば、打設位置5〜9の本設の直線形鋼矢板20も必然的に適切な位置に打設されて打設精度が向上し、先行打設工程で打設位置1〜4および10〜13に打設した8つの本設の直線形鋼矢板20と適切に連結して閉合して、アーク矢板22を確実に形成することができる。   In the replacement driving process, after the guide sheet pile arrangement process is completed (after the state shown in FIG. 8), the guide sheet pile 24 arranged in the central region (placement position 5 to 9) is used as the linear steel sheet pile 20 of the actual installation. Sequentially replace and cast. In the guide sheet pile arrangement process, the guide sheet pile 24 is appropriately arranged in the central region (placement positions 5 to 9), and eight books are placed in the placement positions 1 to 4 and 10 to 13 in the preceding placement process. Since it is appropriately connected and closed with the installed linear steel sheet pile 20, if the installed linear steel sheet pile 20 is sequentially replaced with the guide sheet pile 24, the installed positions 5 to 9 are installed. The straight steel sheet piles 20 are inevitably placed at appropriate positions to improve the placement accuracy, and the eight straight lines placed at the placement positions 1 to 4 and 10 to 13 in the preceding placement process. The arc sheet pile 22 can be reliably formed by appropriately connecting and closing with the shaped steel sheet pile 20.

置き換え打設工程では、ガイド矢板配置工程の終了後(図8に示す状態の後)、まず図9に示すように、1つ飛ばしの位置である打設位置5、7、9に配置したガイド矢板24を本設の直線形鋼矢板20に置き換える。   In the replacement driving process, after the guide sheet pile arrangement process is completed (after the state shown in FIG. 8), first, as shown in FIG. 9, the guides are arranged at the driving positions 5, 7, and 9 which are positions to be skipped. The sheet pile 24 is replaced with a regular straight steel sheet pile 20.

次に、図10に示すように、1つ飛ばしの位置である打設位置5、7、9に配置した本設の直線形鋼矢板20を地盤80に所定の深さまで順次打設する。   Next, as shown in FIG. 10, the permanent straight steel sheet piles 20 arranged at the placement positions 5, 7, and 9, which are one skipping position, are sequentially placed on the ground 80 to a predetermined depth.

次に、図11に示すように、1つ飛ばしの位置である残りの打設位置6、8に配置したガイド矢板24を本設の直線形鋼矢板20に置き換える。   Next, as shown in FIG. 11, the guide sheet piles 24 arranged at the remaining placement positions 6 and 8, which are one skipped position, are replaced with the straight linear steel sheet piles 20.

次に、図12に示すように、1つ飛ばしの位置である打設位置6、8に配置した本設の直線形鋼矢板20を地盤80に所定の深さまで順次打設する。   Next, as shown in FIG. 12, the permanent straight steel sheet piles 20 arranged at the placement positions 6 and 8, which are one skipping position, are sequentially placed on the ground 80 to a predetermined depth.

置き換え打設工程で本設の直線形鋼矢板20を所定の深さまで地盤80に打設する際も、先行打設工程と同様に、例えば、バイブロハンマを用いて打設を行うことができる。   Even when the permanent straight steel sheet pile 20 is driven to the ground 80 to a predetermined depth in the replacement driving process, the driving can be performed using, for example, a vibro hammer as in the preceding driving process.

本第1実施形態に係る鋼矢板の打設方法の置き換え打設工程で、1つ飛ばしの打設位置について、順次、本設の直線形鋼矢板20の打設を行っていくので、バイブロハンマ等の打設機具類と打設が完了していない本設の直線形鋼矢板20との干渉が生じないようにすることができ、本設の直線形鋼矢板20を一気に所定の深さまで打設することができる。   In the replacement placing process of the steel sheet pile placing method according to the first embodiment, the straight steel sheet pile 20 of the present construction is sequentially placed at the place where one skip is placed. Can be prevented from interfering with the existing straight steel sheet pile 20 that has not been driven, and the installed straight steel sheet pile 20 can be driven to a predetermined depth all at once. can do.

打設位置5〜9のそれぞれについて、いちどきにガイド矢板24から直線形鋼矢板20に置き換えると、置き換えた直線形鋼矢板20の打設を行う際に、打設が完了していない隣の直線形鋼矢板20と打設機具類に干渉が生じてしまい、置き換えた直線形鋼矢板20を一気に所定の深さまで打設することができなくなる場合がある。このような場合には、打設位置5〜9のそれぞれの直線形鋼矢板20を、順次、干渉が生じない範囲内で少しずつ打設していく必要がある。   For each of the placement positions 5 to 9, when the guide sheet pile 24 is replaced with the straight steel sheet pile 20 at a time, when the replaced linear steel sheet pile 20 is placed, the adjacent straight form where the placement is not completed. There is a case where interference occurs between the steel sheet pile 20 and the driving equipment, and the replaced linear steel sheet pile 20 cannot be driven to a predetermined depth at a stretch. In such a case, it is necessary to sequentially place the respective linear steel sheet piles 20 at the placement positions 5 to 9 within a range where interference does not occur.

非特許文献2で報告されている工事では、ガイド矢板24は用いておらず、図14に模式的に示すように、長さ22mの本設の直線形鋼矢板20を、打設位置5〜9において海底面に深さ8mだけ仮に打設して建て込んだが、打設位置5〜9の海底面は、海面からの深さが6.5mであり、建て込む際には、海面から7.5mの高さ位置である仮下げ天端で本設の直線形鋼矢板20の継手部20Aを相互に嵌合させる必要があった。この作業は高所作業であり、打設位置5〜9に本設の直線形鋼矢板20を建て込むだけでも困難を伴った。一方、打設位置5〜9に建て込んだ直線形鋼矢板20を打設する際には、打設が完了していない隣の直線形鋼矢板20と打設機具類に干渉が生じてしまうため、図15に模式的に示すように、両端の直線形鋼矢板20(打設位置5、9の直線形鋼矢板20)から順に干渉が生じない範囲内で少しずつ(300mmずつ)打ち下げる作業を繰り返し、所定の深度まで打ち込むことを実現しており、施工効率は良好であるとは言えない。   In the construction reported in Non-Patent Document 2, the guide sheet pile 24 is not used. As shown schematically in FIG. Although the depth of 8m was tentatively cast on the bottom of the sea at 9 and the depth of the seabed at the placement positions 5 to 9 is 6.5m from the sea surface. It was necessary to fit the joint part 20A of the linear steel sheet pile 20 of the permanent installation with each other at the temporarily lowered top end which is a height of 0.5 m. This work was a high place work, and it was difficult to install the straight steel sheet pile 20 at the placement positions 5-9. On the other hand, when the straight steel sheet pile 20 built in the placement positions 5 to 9 is placed, interference occurs between the adjacent straight steel sheet pile 20 where the placement is not completed and the placement equipment. Therefore, as schematically shown in FIG. 15, the steel sheets are lowered little by little (by 300 mm) within a range in which no interference occurs in order from the straight steel sheet piles 20 at the both ends (the straight steel sheet piles 20 at the placement positions 5 and 9) The work is repeated and driven to a predetermined depth, and it cannot be said that the construction efficiency is good.

これに対し、本第1実施形態に係る鋼矢板の打設方法の置き換え打設工程では、前述したように、1つ飛ばしの打設位置について、順次、本設の直線形鋼矢板20の打設を行っていくので、バイブロハンマ等の打設機具類と打設が完了していない本設の直線形鋼矢板20との干渉が生じないようにすることができ、打設位置5〜9の本設の直線形鋼矢板20を一気に所定の深さまで打設することができる。   On the other hand, in the replacement placing step of the steel sheet pile placing method according to the first embodiment, as described above, the placement of the straight steel sheet pile 20 of the present construction is sequentially performed at one placement position. Therefore, it is possible to prevent interference between the driving equipment such as a vibro hammer and the straight steel sheet pile 20 that has not been set up. The straight steel sheet pile 20 of this installation can be driven to a predetermined depth at a stretch.

1つ飛ばしの打設位置について、順次、打設位置5〜9の本設の直線形鋼矢板20の打設を行っていく場合でも、直線形鋼矢板20を一気に所定の深さまで打設すると、打設が完了していない本設の直線形鋼矢板20と打設機具類に干渉が生じてしまう場合には、2つ飛ばしの打設位置について、順次、本設の直線形鋼矢板20の置き換えと打設を行っていくようにしてもよい。これについては、第2実施形態として次に説明する。   Even in the case of sequentially placing the straight steel sheet piles 20 at the placement positions 5 to 9 for one skipping position, if the straight steel sheet piles 20 are driven to a predetermined depth all at once. In the case where interference occurs between the conventional straight steel sheet pile 20 that has not been driven and the driving equipment, the continuous linear steel sheet pile 20 is sequentially placed at the two skipping positions. You may make it perform replacement and placement. This will be described next as a second embodiment.

(3)本発明の第2実施形態に係る鋼矢板の打設方法の手順
本発明の第2実施形態に係る鋼矢板の打設方法は、置き換え打設工程で、2つ飛ばしの打設位置について、順次、本設の直線形鋼矢板20の置き換えと打設を行っていく点が、本発明の第1実施形態に係る鋼矢板の打設方法と異なり、それ以外の点については本発明の第1実施形態に係る鋼矢板の打設方法と同様であり、用いる直線形鋼矢板20およびガイド矢板24も同一である。本発明の第1実施形態に係る鋼矢板の打設方法と同様の内容については、説明を省略するか、あるいは簡略化して説明する。
(3) Procedure of steel sheet pile driving method according to the second embodiment of the present invention The steel sheet pile driving method according to the second embodiment of the present invention is a replacement driving step in which two skipping positions are set. Is different from the steel sheet pile driving method according to the first embodiment of the present invention in that the replacement of the linear steel sheet pile 20 and the driving of the steel sheet pile 20 are sequentially performed. The steel sheet pile driving method according to the first embodiment is the same, and the linear steel sheet pile 20 and the guide sheet pile 24 used are the same. About the content similar to the placement method of the steel sheet pile concerning 1st Embodiment of this invention, description is abbreviate | omitted or simplified and demonstrated.

図16〜図23は本発明の第2実施形態に係る鋼矢板の打設方法の特徴的な各段階を模式的に示す図である。   FIGS. 16-23 is a figure which shows typically each characteristic step of the placement method of the steel sheet pile concerning 2nd Embodiment of this invention.

図16は、先行打設工程を実施した後の状態を模式的に示す図であり、第1実施形態に係る鋼矢板の打設方法の説明に用いた図7と同一であり、本第2実施形態に係る鋼矢板の打設方法における先行打設工程の内容は第1実施形態に係る鋼矢板の打設方法と同様であるので、説明は省略する。   FIG. 16 is a diagram schematically showing a state after performing the preceding placing process, which is the same as FIG. 7 used for explaining the placing method of the steel sheet pile according to the first embodiment. Since the content of the prior placing process in the steel sheet pile placing method according to the embodiment is the same as the steel sheet pile placing method according to the first embodiment, the description thereof is omitted.

図17は、ガイド矢板配置工程を実施した後の状態を模式的に示す図であり、第1実施形態に係る鋼矢板の打設方法の説明に用いた図8と同一であり、本第2実施形態に係る鋼矢板の打設方法におけるガイド矢板配置工程の内容は第1実施形態に係る鋼矢板の打設方法と同様であるので、説明は省略する。   FIG. 17 is a diagram schematically showing a state after the guide sheet pile arrangement step is performed, which is the same as FIG. 8 used for explaining the steel sheet pile placing method according to the first embodiment. Since the content of the guide sheet pile arrangement process in the steel sheet pile placing method according to the embodiment is the same as that of the steel sheet pile placing method according to the first embodiment, the description thereof is omitted.

図18〜図23は、置き換え打設工程を実施している各段階の状態を模式的に示す図である。   18-23 is a figure which shows typically the state of each step which is implementing the replacement placement process.

置き換え打設工程では、ガイド矢板配置工程の終了後(図17に示す状態の後)、中央部領域(打設位置5〜9)に配置したガイド矢板24を本設の直線形鋼矢板20に順次置き換えて打設する。ガイド矢板配置工程で、ガイド矢板24が中央部領域(打設位置5〜9)に適切に配置されて、先行打設工程で打設位置1〜4および10〜13に打設した8つの本設の直線形鋼矢板20と適切に連結して閉合しているので、そのガイド矢板24と順次置き換えて本設の直線形鋼矢板20を打設すれば、打設位置5〜9の本設の直線形鋼矢板20も必然的に適切な位置に打設されて打設精度が向上し、先行打設工程で打設位置1〜4および10〜13に打設した8つの本設の直線形鋼矢板20と適切に連結して閉合して、アーク矢板22を確実に形成することができる。   In the replacement driving process, after the guide sheet pile arrangement process is completed (after the state shown in FIG. 17), the guide sheet pile 24 arranged in the central region (placement positions 5 to 9) is used as the straight steel sheet pile 20 of the actual installation. Sequentially replace and cast. In the guide sheet pile arrangement process, the guide sheet pile 24 is appropriately arranged in the central region (placement positions 5 to 9), and eight books are placed in the placement positions 1 to 4 and 10 to 13 in the preceding placement process. Since it is appropriately connected and closed with the installed linear steel sheet pile 20, if the installed linear steel sheet pile 20 is sequentially replaced with the guide sheet pile 24, the installed positions 5 to 9 are installed. The straight steel sheet piles 20 are inevitably placed at appropriate positions to improve the placement accuracy, and the eight straight lines placed at the placement positions 1 to 4 and 10 to 13 in the preceding placement process. The arc sheet pile 22 can be reliably formed by appropriately connecting and closing with the shaped steel sheet pile 20.

置き換え打設工程では、ガイド矢板配置工程の終了後(図17に示す状態の後)、まず図18に示すように、2つ飛ばしの位置である打設位置5、8に配置したガイド矢板24を本設の直線形鋼矢板20に置き換える。   In the replacement driving process, after the guide sheet pile arrangement process is completed (after the state shown in FIG. 17), first, as shown in FIG. 18, the guide sheet piles 24 arranged at the driving positions 5 and 8 which are two skipping positions. Is replaced with the straight steel sheet pile 20 of the actual installation.

次に、図19に示すように、2つ飛ばしの位置である打設位置5、8に配置した本設の直線形鋼矢板20を地盤80に所定の深さまで順次打設する。   Next, as shown in FIG. 19, permanent linear steel sheet piles 20 arranged at the placement positions 5 and 8, which are two skipping positions, are sequentially placed on the ground 80 to a predetermined depth.

次に、図20に示すように、2つ飛ばしの位置である打設位置6、9に配置したガイド矢板24を本設の直線形鋼矢板20に置き換える。   Next, as shown in FIG. 20, the guide sheet piles 24 arranged at the placement positions 6 and 9, which are two skipping positions, are replaced with the regular straight steel sheet piles 20.

次に、図21に示すように、2つ飛ばしの位置である打設位置6、9に配置した本設の直線形鋼矢板20を地盤80に所定の深さまで打設する。   Next, as shown in FIG. 21, the permanent straight steel sheet piles 20 arranged at the placement positions 6 and 9 which are two skipping positions are placed on the ground 80 to a predetermined depth.

次に、図22に示すように、残った打設位置7に配置したガイド矢板24を本設の直線形鋼矢板20に置き換える。   Next, as shown in FIG. 22, the guide sheet pile 24 arranged at the remaining placement position 7 is replaced with a regular straight steel sheet pile 20.

次に、図23に示すように、残った打設位置7に配置した本設の直線形鋼矢板20を地盤80に所定の深さまで打設する。   Next, as shown in FIG. 23, the permanent straight steel sheet pile 20 arranged at the remaining placement position 7 is driven to the ground 80 to a predetermined depth.

置き換え打設工程で本設の直線形鋼矢板20を所定の深さまで地盤80に打設する際も、先行打設工程と同様に、例えば、バイブロハンマを用いて打設を行うことができる。   Even when the permanent straight steel sheet pile 20 is driven to the ground 80 to a predetermined depth in the replacement driving process, the driving can be performed using, for example, a vibro hammer as in the preceding driving process.

本第2実施形態に係る鋼矢板の打設方法の置き換え打設工程では、2つ飛ばしの打設位置について、順次、本設の直線形鋼矢板20の打設を行っていくので、バイブロハンマ等の打設機具類と打設が完了していない本設の直線形鋼矢板20との干渉が生じないようにすることができ、本設の直線形鋼矢板20を一気に所定の深さまで打設することができる。   In the replacement placing process of the steel sheet pile placing method according to the second embodiment, the straight steel sheet pile 20 is placed in sequence for the two skipped placement positions. Can be prevented from interfering with the existing straight steel sheet pile 20 that has not been driven, and the installed straight steel sheet pile 20 can be driven to a predetermined depth all at once. can do.

(4)ガイド矢板の効果
前述したように、ガイド矢板24は、本設の直線形鋼矢板20の打設位置を事前に正確に把握するために用いる部材であり、海底面上に配置するだけで地盤80に打設しないので、その配置位置の調整を容易に行うことができる。また、本設の直線形鋼矢板20の長さは22mであるのに対し、ガイド矢板24の長さは9mと短いので、この点からもガイド矢板24は配置位置の調整を容易に行うことができる。
(4) Effect of Guide Sheet Pile As described above, the guide sheet pile 24 is a member used for accurately grasping the placement position of the linear steel sheet pile 20 in advance, and is only disposed on the sea bottom. Therefore, the placement position can be easily adjusted since the ground 80 is not driven. In addition, the length of the straight steel sheet pile 20 is 22 m, whereas the length of the guide sheet pile 24 is as short as 9 m. From this point, the guide sheet pile 24 can easily adjust the arrangement position. Can do.

したがって、位置を微調整しながらガイド矢板24を中央部領域(打設位置5〜9)に配置して、先行打設工程で打設位置1〜4および10〜13に打設した8つの本設の直線形鋼矢板20と連結して閉合させることを、確実かつ容易に行うことができる。このため、ガイド矢板24と置き換えて本設の直線形鋼矢板20を打設することにより打設精度が向上し、本設の直線形鋼矢板20の位置を打設後に調整する手戻りを少なくすることができ、施工効率が大幅に向上する。   Accordingly, the guide sheet pile 24 is arranged in the central region (placement positions 5 to 9) while finely adjusting the position, and the eight books placed in the placement positions 1 to 4 and 10 to 13 in the preceding placement process. It is possible to reliably and easily perform the connection and closing with the provided linear steel sheet pile 20. For this reason, the placement accuracy is improved by replacing the guide sheet pile 24 with the permanent linear steel sheet pile 20, and the rework for adjusting the position of the permanent linear sheet pile 20 after placement is reduced. Construction efficiency can be greatly improved.

また、前述したように、作業者が作業する足場面の高さ位置は、海面から1〜1.5mの高さ位置であるので、中央部領域(打設位置5〜9)に配置した長さ9mのガイド矢板24の上端の高さ位置は、作業者が作業する足場面の高さ位置よりも1〜1.5m上方の高さ位置である。したがって、すでに配置したガイド矢板24の隣の位置に別のガイド矢板24を配置する際、隣り合うガイド矢板24の継手部24A同士を嵌合させる作業を作業者が行いやすくなっている。   In addition, as described above, the height position of the foot scene on which the operator works is a height position of 1 to 1.5 m from the sea surface, so the length arranged in the central region (placed position 5 to 9). The height position of the upper end of the 9-meter guide sheet pile 24 is a height position 1 to 1.5 m higher than the height position of the foot scene on which the worker works. Therefore, when another guide sheet pile 24 is arranged at a position adjacent to the already arranged guide sheet pile 24, the operator can easily perform the operation of fitting the joint portions 24A of the adjacent guide sheet piles 24 together.

また、本発明の第1実施形態および第2実施形態に係る鋼矢板の打設方法における置き換え打設工程の図9〜図12および図18〜図23から明らかなように、打設位置5〜9においてガイド矢板24から置き換えた本設の直線形鋼矢板20は、両側をガイド矢板24または直線形鋼矢板20のいずれかによって保持された状態で打設される。このため、適切な位置を保持させたまま、置き換えた本設の直線形鋼矢板20の打設を行うことができる。このため、隣接する本設の直線形鋼矢板20との摩擦も減るので、共下がり量を減らすこともでき、この点でも施工効率が向上する。   Moreover, as is clear from FIGS. 9 to 12 and FIGS. 18 to 23 of the replacement placing process in the steel sheet pile placing method according to the first and second embodiments of the present invention, 9, the straight steel sheet pile 20 which is replaced with the guide sheet pile 24 is driven in a state where both sides are held by either the guide sheet pile 24 or the straight steel sheet pile 20. For this reason, it is possible to place the replaced linear steel sheet pile 20 while maintaining an appropriate position. For this reason, since the friction with the adjacent linear steel sheet pile 20 of an installation is also reduced, the amount of co-falling can also be reduced and a construction efficiency improves also in this point.

また、前述したように、アーク矢板22を形成する直線形鋼矢板20は、土圧等の外力に対してフープテンション(嵌合している矢板列の面内周方向引張力)で抵抗することができるようになっているため、直線形鋼矢板20の継手部20Aの遊びは、8mm以上12mm以下と小さく設定されている。しかしながら、ガイド矢板24を用いることにより、適切な打設位置を予め設定することができるので、直線形鋼矢板20の継手部20Aの遊びが前記したように小さくても、問題は生じにくい。   Further, as described above, the linear steel sheet pile 20 that forms the arc sheet pile 22 resists external force such as earth pressure by hoop tension (in-plane circumferential tensile force of the sheet pile row fitted). Therefore, the play of the joint part 20A of the linear steel sheet pile 20 is set to be as small as 8 mm or more and 12 mm or less. However, since an appropriate driving position can be set in advance by using the guide sheet pile 24, even if the play of the joint portion 20A of the linear steel sheet pile 20 is small as described above, a problem hardly occurs.

また、本発明に係る鋼矢板の打設方法で用いるガイド矢板の効果が特に重要になる場合は、複数打設する鋼矢板の両端部の位置が予め決められている場合である。このような場合に鋼矢板の打設位置にずれが生じると、所定の枚数の鋼矢板を閉合するように打設することが困難になることがある。したがって、複数打設する鋼矢板の両端部の位置が予め決められている場合には、本設の鋼矢板の打設位置が閉合できる打設位置となるように予めガイド矢板を用いて定めておくという効果が特に重要になる。   In addition, when the effect of the guide sheet pile used in the steel sheet pile placing method according to the present invention is particularly important, the positions of both ends of the steel sheet piles to be placed are determined in advance. In such a case, if a deviation occurs in the placement position of the steel sheet pile, it may be difficult to place a predetermined number of steel sheet piles to be closed. Therefore, when the positions of the both ends of the steel sheet piles to be placed in advance are determined in advance, the guide sheet piles are determined in advance so that the placement positions of the steel sheet piles of the main construction can be closed. The effect of keeping is particularly important.

なお、本発明に係る鋼矢板の打設方法で用いるガイド矢板は、アーク状に複数の鋼矢板を打設する場合だけでなく、直線状に複数の鋼矢板を打設する場合にも用いることができ、本発明に係る鋼矢板の打設方法は、複数の鋼矢板を曲線状に打設する場合でも、直線状に打設する場合でも用いることができる。   The guide sheet pile used in the steel sheet pile driving method according to the present invention is used not only when a plurality of steel sheet piles are driven in an arc shape, but also when a plurality of steel sheet piles are driven linearly. Therefore, the steel sheet pile driving method according to the present invention can be used even when a plurality of steel sheet piles are driven in a curved shape or in a straight shape.

1〜13…打設位置
20、102…直線形鋼矢板
20A、24A…継手部
22、104…アーク矢板
23、106…サドルプレート
24…ガイド矢板
30…補助H鋼
30A…フランジ
30A1…切り欠き
30B…ウェブ
32…取り付け治具
80…地盤
100…土留め壁
200、300…ジャケット式桟橋
DESCRIPTION OF SYMBOLS 1-13 ... Placing position 20, 102 ... Linear steel sheet pile 20A, 24A ... Joint part 22, 104 ... Arc sheet pile 23, 106 ... Saddle plate 24 ... Guide sheet pile 30 ... Auxiliary H steel 30A ... Flange 30A1 ... Notch 30B ... Web 32 ... Mounting jig 80 ... Ground 100 ... Earth retaining wall 200, 300 ... Jacket type jetty

即ち、本発明に係る鋼矢板の打設方法は、幅方向の両方の端部に継手部を備えた鋼矢板を、前記継手部でお互いに連結させて一列状に複数打設する鋼矢板の打設方法であって、一列状に複数打設する鋼矢板のうち、それらの両端部に位置する鋼矢板をそれぞれ含むとともに、それらの両端部から前記一列状の中央部に向かってそれぞれ所定の枚数の鋼矢板を含む2つの端部領域の鋼矢板を他の領域より先行して打設する先行打設工程と、前記先行打設工程で先行して打設された前記鋼矢板の長さよりも長さが短く、かつ、幅方向の両方の端部に継手部を備えたガイド矢板を、前記2つの端部領域の間に位置する中央部領域に、前記ガイド矢板の前記継手部でお互いに連結させて地盤上に一列状に複数配置するとともに、一列状に複数配置する前記ガイド矢板のうち両端部に配置する前記ガイド矢板の前記継手部を、前記2つの端部領域に先行して打設された前記鋼矢板のうち前記一列状の中央部に向かう側の端部の鋼矢板の前記継手部にそれぞれ連結させて配置するガイド矢板配置工程と、前記ガイド矢板配置工程で配置した前記複数のガイド矢板を、幅方向断面が前記ガイド矢板と略同一である本設の鋼矢板に順次置き換えて打設する置き換え打設工程と、を有し、前記先行打設工程では前記ガイド矢板は用いずに前記鋼矢板を打設し、前記ガイド矢板配置工程で配置した前記ガイド矢板は地盤上に配置するだけで打設はしないことを特徴とする鋼矢板の打設方法である。 That is, the steel sheet pile driving method according to the present invention is a steel sheet pile in which a plurality of steel sheet piles provided with joint portions at both ends in the width direction are connected to each other at the joint portions to form a plurality of steel sheet piles. Among the steel sheet piles to be placed in a row, each of the steel sheet piles is located at both ends of each of the sheet piles, and each of the predetermined distances from the both ends toward the center of the row From the prior placing step of placing the steel sheet piles in the two end regions including the number of steel sheet piles ahead of other regions, and the length of the steel sheet pile placed in advance in the preceding placement step The guide sheet pile having a short length and joint portions at both ends in the width direction is mutually connected at the joint portion of the guide sheet pile to the central region located between the two end regions. with a plurality disposed in a row ligated onto the ground, a plurality arranged in a line shape The ends of the guide sheet piles arranged at both ends of the guide sheet piles on the side toward the central portion of the row of steel sheet piles that are driven in advance of the two end regions. The guide sheet pile arrangement step of connecting and arranging the joint portions of the steel sheet piles, and the plurality of guide sheet piles arranged in the guide sheet pile arrangement step, the width direction cross section is substantially the same as the guide sheet pile possess a replacement striking setting step of pouring sequentially replaced with steel sheet piles, and the higher the preceding hitting設工in the guide sheet pile is pouring the steel sheet pile without using the guide said guide arranged in the sheet pile arrangement step It is a steel sheet pile placing method characterized in that the sheet pile is merely placed on the ground and is not placed .

前記ガイド矢板が前記ガイド矢板配置工程で地盤に配置された状態において、前記ガイド矢板の上端の高さ位置は、当該ガイド矢板に対して作業を行う作業者の足場面よりも1m以上2m以下だけ高い位置であることが好ましい。 In a state in which the guide sheet pile is placed on the ground with the guide sheet pile arrangement step, the height position of the upper end of the guide sheet piles, 1m or 2m or less than the operator's foot scene to work with respect to the guide sheet pile It is preferable that the position is as high as possible.

Claims (10)

幅方向の両方の端部に継手部を備えた鋼矢板を、前記継手部でお互いに連結させて一列状に複数打設する鋼矢板の打設方法であって、
一列状に複数打設する鋼矢板のうち、それらの両端部に位置する鋼矢板をそれぞれ含むとともに、それらの両端部から前記一列状の中央部に向かってそれぞれ所定の枚数の鋼矢板を含む2つの端部領域の鋼矢板を先行して打設する先行打設工程と、
前記先行打設工程で先行して打設された前記鋼矢板の長さよりも長さが短く、かつ、幅方向の両方の端部に継手部を備えたガイド矢板を、前記2つの端部領域の間に位置する中央部領域に、前記ガイド矢板の前記継手部でお互いに連結させて一列状に複数配置するとともに、一列状に複数配置する前記ガイド矢板のうち両端部に配置する前記ガイド矢板の前記継手部を、前記2つの端部領域に先行して打設された前記鋼矢板のうち前記一列状の中央部に向かう側の端部の鋼矢板の前記継手部にそれぞれ連結させて配置するガイド矢板配置工程と、
前記ガイド矢板配置工程で配置した前記複数のガイド矢板を、幅方向断面が前記ガイド矢板と略同一である本設の鋼矢板に順次置き換えて打設する置き換え打設工程と、
を有することを特徴とする鋼矢板の打設方法。
Steel sheet piles having joint portions at both ends in the width direction are connected to each other at the joint portions, and a steel sheet pile placing method for placing a plurality of steel sheet piles in a row,
Among steel sheet piles to be placed in a row, each includes steel sheet piles positioned at both ends thereof, and includes a predetermined number of steel sheet piles from both ends toward the central portion in the row. A prior placing step of placing steel sheet piles in one end region in advance;
A guide sheet pile having a length shorter than the length of the steel sheet pile previously placed in the preceding placing step and provided with joint portions at both ends in the width direction, the two end regions. The guide sheet piles arranged at both ends of the guide sheet piles arranged in a row and connected to each other at the joint portion of the guide sheet piles in a central region located between the guide sheet piles. The joint portions of the steel sheet piles placed prior to the two end regions are respectively connected to the joint portions of the steel sheet piles at the end portion toward the central portion of the row. A guide sheet pile arrangement process to perform,
The replacement placing step of sequentially placing and placing the plurality of guide sheet piles arranged in the guide sheet pile arrangement step with a steel sheet pile of a main structure whose width direction cross section is substantially the same as the guide sheet pile,
A method for placing a steel sheet pile, comprising:
前記一列状に複数打設する鋼矢板の幅方向断面は、略同一であることを特徴とする請求項1に記載の鋼矢板の打設方法。   2. The steel sheet pile driving method according to claim 1, wherein a plurality of the steel sheet piles arranged in a single row have substantially the same cross-section in the width direction. 前記置き換え打設工程においては、前記ガイド矢板配置工程で配置した前記複数のガイド矢板のうちの一部のガイド矢板であってお互いに隣り合っていないガイド矢板を選んで前記本設の鋼矢板に置き換えて打設する工程が含まれていることを特徴とする請求項1または2に記載の鋼矢板の打設方法。   In the replacement placing step, a guide sheet pile that is a part of the plurality of guide sheet piles arranged in the guide sheet pile arrangement step and that is not adjacent to each other is selected to the main steel sheet pile. The method for placing a steel sheet pile according to claim 1 or 2, further comprising a step of placing by replacing. 前記置き換え打設工程においては、前記ガイド矢板配置工程で配置した前記複数のガイド矢板のうちの一部のガイド矢板であって1つ飛ばしに配置されたガイド矢板を選んで前記本設の鋼矢板に置き換えて打設する工程が含まれていることを特徴とする請求項3に記載の鋼矢板の打設方法。   In the replacement driving step, the main steel sheet pile is selected by selecting one guide sheet pile among the plurality of guide sheet piles arranged in the guide sheet pile arrangement step. The method for placing a steel sheet pile according to claim 3, wherein a step of placing the steel sheet pile is included. 前記置き換え打設工程においては、前記ガイド矢板配置工程で配置した前記複数のガイド矢板のうちの一部のガイド矢板であって2つ飛ばしに配置されたガイド矢板を選んで前記本設の鋼矢板に置き換えて打設する工程が含まれていることを特徴とする請求項3に記載の鋼矢板の打設方法。   In the replacement driving step, the main steel sheet pile is selected by selecting a guide sheet pile that is a part of the plurality of guide sheet piles arranged in the guide sheet pile arrangement step. The method for placing a steel sheet pile according to claim 3, wherein a step of placing the steel sheet pile is included. 前記一列状に複数打設する鋼矢板の両端部の位置は、予め決められていることを特徴とする請求項1〜5のいずれかに記載の鋼矢板の打設方法。   The steel sheet pile placing method according to any one of claims 1 to 5, wherein the positions of both ends of the steel sheet piles to be placed in a row are determined in advance. 前記鋼矢板の幅方向断面は、略直線形状であることを特徴とする請求項1〜6のいずれかに記載の鋼矢板の打設方法。   The steel sheet pile placing method according to any one of claims 1 to 6, wherein a cross section in the width direction of the steel sheet pile has a substantially linear shape. 前記一列状に複数打設する鋼矢板のうちの少なくとも一部の鋼矢板は、曲線状に列を形成していることを特徴とする請求項1〜7のいずれかに記載の鋼矢板の打設方法。   The steel sheet piles according to any one of claims 1 to 7, wherein at least some of the steel sheet piles to be placed in a single row form a curved line. Installation method. 前記鋼矢板の前記継手部の遊びが8mm以上12mm以下であることを特徴とする請求項1〜8のいずれかに記載の鋼矢板の打設方法。   The play of the steel sheet pile according to any one of claims 1 to 8, wherein a play of the joint portion of the steel sheet pile is 8 mm or more and 12 mm or less. 前記ガイド矢板が前記ガイド矢板配置工程で地盤に配置された状態において、前記ガイド矢板の上端の高さ位置は、当該ガイド矢板に対して作業を行う作業者の足場面よりも1m以上2m以下だけ高い位置であることを特徴とする請求項1〜9のいずれかに記載の鋼矢板の打設方法。   In the state where the guide sheet pile is arranged on the ground in the guide sheet pile arrangement step, the height position of the upper end of the guide sheet pile is only 1 m or more and 2 m or less than the foot scene of the operator who performs work on the guide sheet pile. The steel sheet pile placing method according to any one of claims 1 to 9, wherein the steel sheet pile is at a high position.
JP2017180601A 2017-09-20 2017-09-20 Steel sheet pile placing method Active JP6288362B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017180601A JP6288362B1 (en) 2017-09-20 2017-09-20 Steel sheet pile placing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017180601A JP6288362B1 (en) 2017-09-20 2017-09-20 Steel sheet pile placing method

Publications (2)

Publication Number Publication Date
JP6288362B1 JP6288362B1 (en) 2018-03-07
JP2019056227A true JP2019056227A (en) 2019-04-11

Family

ID=61557927

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017180601A Active JP6288362B1 (en) 2017-09-20 2017-09-20 Steel sheet pile placing method

Country Status (1)

Country Link
JP (1) JP6288362B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115679956A (en) * 2022-11-04 2023-02-03 广东佰业泰建设工程有限公司 Construction method of stirring pile for sand-rich stratum

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5186209A (en) * 1975-01-27 1976-07-28 Shimizu Construction Co Ltd KOYAITANOCHI KOMISOCHI
JPS5728928Y2 (en) * 1978-01-27 1982-06-24
JPH0480418A (en) * 1990-07-23 1992-03-13 Kobe Steel Ltd Method of driving steel pipe sheet pile
JPH07197464A (en) * 1993-12-28 1995-08-01 Ishikawajima Constr Mach Co Driving method of submerged steel pipe pile
JP2002227190A (en) * 2001-02-02 2002-08-14 East Japan Railway Co Surface layer casing pipe for cast-in-place concrete pile and method of executing surface layer casing pipe for cast-in-place concrete pile
JP2005171596A (en) * 2003-12-10 2005-06-30 Jfe Steel Kk Cylindrical casing driving construction method, ruler for driving and gripping tool
CN1869340A (en) * 2005-05-23 2006-11-29 上海市第七建筑有限公司 Combined box type steel sheet pile construction method of dock wall
JP2012207371A (en) * 2011-03-29 2012-10-25 Penta Ocean Construction Co Ltd Method for installing steel sheet pile
JP6206528B2 (en) * 2016-03-18 2017-10-04 Jfeスチール株式会社 Steel sheet pile closing structure and its construction method

Also Published As

Publication number Publication date
JP6288362B1 (en) 2018-03-07

Similar Documents

Publication Publication Date Title
JP5347898B2 (en) Strengthening structure and method of existing sheet pile quay
US11732432B2 (en) Method of constructing underwater concrete block structure
JP4998646B2 (en) Connection structure of steel pipe sheet pile and steel sheet pile and its construction method
JP4597921B2 (en) How to build a pier
JP2007297826A (en) Method for reinforcing bridge pier with steel plate
JP6288362B1 (en) Steel sheet pile placing method
JP2020041341A (en) Pier structure construction method and pier structure
JP5825644B2 (en) Pier construction method
JPWO2015050207A1 (en) Continuous wall casting method and continuous wall casting jig
JP6138192B2 (en) Steel pipe pile construction method
JP4429784B2 (en) How to install underwater structures
JP7102228B2 (en) How to build concrete sheet pile members, earth retaining walls and earth retaining walls
JP2009209577A (en) Marine structure and construction method for marine structure
JP2016003444A (en) Parting member and pile head treatment method for on-site constructed pile
DE202012012250U1 (en) Mounting device for the installation of fasteners
JP2012207371A (en) Method for installing steel sheet pile
JP5513229B2 (en) Offshore construction method
JP5331724B2 (en) Construction method of temporary pier and temporary pier
JP2009185582A (en) Unit and method for mounting pile head reinforcement
JP7341035B2 (en) work equipment
JP2019052466A (en) Construction method of concrete structure and positioning jig used therefor
JP2008106542A (en) Method for holding deformed steel sheet pile or steel driven member, and holding tool therefor
JP6832467B1 (en) Template for foundation piles, foundation pile installation method
CN202881953U (en) Correction fixation improvement device of top-down constructed steel column
JP2019127748A (en) Construction method for structure

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20171219

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180109

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180122

R150 Certificate of patent or registration of utility model

Ref document number: 6288362

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350