JP2018204328A - Steel pipe column member for filing concrete and construction method of concrete filled steel pipe member - Google Patents

Steel pipe column member for filing concrete and construction method of concrete filled steel pipe member Download PDF

Info

Publication number
JP2018204328A
JP2018204328A JP2017111604A JP2017111604A JP2018204328A JP 2018204328 A JP2018204328 A JP 2018204328A JP 2017111604 A JP2017111604 A JP 2017111604A JP 2017111604 A JP2017111604 A JP 2017111604A JP 2018204328 A JP2018204328 A JP 2018204328A
Authority
JP
Japan
Prior art keywords
steel pipe
concrete
column
pipe column
wind
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017111604A
Other languages
Japanese (ja)
Other versions
JP6917786B2 (en
Inventor
洋二 大久保
Yoji Okubo
洋二 大久保
一郎 折登
Ichiro Orito
一郎 折登
和浩 奥山
Kazuhiro Okuyama
和浩 奥山
大喜 庄子
Daiki Shoji
大喜 庄子
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2017111604A priority Critical patent/JP6917786B2/en
Publication of JP2018204328A publication Critical patent/JP2018204328A/en
Application granted granted Critical
Publication of JP6917786B2 publication Critical patent/JP6917786B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

To provide a construction method of a concrete filled steel pipe member which keeps a concrete temperature equal to or more than a control predetermined temperature during and five days after filling concrete without arrangement of large-scale thermal insulation even when constructing the concrete filled steel pipe member in a cold season.SOLUTION: A steel pipe member 21 for filling concrete is a steel pipe member 21 provided with a column-beam joint portion 24 to which a steel beam 31 is connected, in which concrete 22 is filled, wherein an air duct 30 covering a steel pipe member 21 is arranged at a lower portion of the column-beam joint portion 24.SELECTED DRAWING: Figure 2

Description

本発明は、コンクリート充填用の鋼管柱材、及び、コンクリート充填鋼管柱の構築方法に関する。   The present invention relates to a steel pipe column material for filling concrete and a method for constructing a concrete filled steel tube column.

建築構造物を構成する躯体に、コンクリート充填鋼管柱(いわゆるCFT柱)を用いることがある。コンクリート充填鋼管柱は、上下方向に延びる筒状の鋼管柱材と、鋼管柱材の内部に充填されたコンクリートと、を備える。このようなコンクリート充填鋼管柱は、鋼管柱材を所定の位置に建方した後、鋼管柱材の内部にコンクリートを打設充填する。打設したコンクリートが硬化し、所定の強度を発現することで、コンクリート充填鋼管柱の施工が完了する。
ところで、冬期や寒冷地でコンクリート充填鋼管柱の施工を行う場合、外気温が低いと、鋼管柱材の内部に打設したコンクリートの温度が低くなり、コンクリートに所定の強度が発現しない場合がある。そこで、例えば、鋼管柱に充填するコンクリートの養生について、「打込み中及び打込み後5日間は、コンクリートの温度が2℃を下回らない」ようにすることが求められている(平成14年国土交通省告示第464号第5項第1号)。
このため、鋼管柱材の内部にコンクリートを打設した後、コンクリートの養生を行う際に、外部から加温する提案が複数なされている。
A concrete-filled steel pipe column (a so-called CFT column) may be used for the frame constituting the building structure. The concrete-filled steel pipe column includes a cylindrical steel pipe column material extending in the vertical direction, and concrete filled in the steel pipe column material. In such a concrete-filled steel pipe column, after the steel pipe column material is erected in a predetermined position, concrete is cast and filled inside the steel pipe column material. Construction of the concrete-filled steel pipe column is completed when the placed concrete hardens and develops a predetermined strength.
By the way, when performing concrete-filled steel pipe columns in winter or cold regions, if the outside air temperature is low, the temperature of the concrete placed inside the steel pipe column material will be low, and the concrete may not exhibit the prescribed strength . Therefore, for example, regarding the curing of concrete to be filled in steel pipe columns, it is required that “the temperature of the concrete does not fall below 2 ° C. during and after the placement for 5 days” (2002 Ministry of Land, Infrastructure, Transport and Tourism) Notification No. 464, paragraph 5, item 1).
For this reason, a plurality of proposals have been made to heat from the outside when concrete is cured after placing the concrete inside the steel pipe column.

例えば特許文献1には、気室を有したバルーンによって、柱状のコンクリート構造物の表面に密着させ、気室内に加熱した空気を送り込む構成のコンクリート養生装置が開示されている。この構成において、バルーンは、柱状のコンクリート構造物の上部と、その側面を包囲するよう形成されている。
特許文献1に開示されたようなコンクリート養生装置では、バルーンは、柱状のコンクリート構造物の上部までを覆う。鋼管柱材に、鉄骨梁を接合するための柱梁接合部(仕口部)が一体に設けられている場合、柱梁接合部は、鋼管柱から側方に突出している。このため、バルーンを、鋼管の側面と上面に加えて、柱梁接合部を覆うように形成すると、バルーンが複雑で大がかりなものとなる。その結果、バルーンの設置にも手間がかかり、工期の長期化に繋がってしまう。また、バルーンを鋼管柱材の建方前に取り付けると、鋼管柱材の建て込み作業中に、特に鋼管柱材から突出した柱梁接合部の部分で、周囲との干渉等によってバルーンの気室が損傷してしまう場合がある。気室が損傷すると、加熱した空気を気室に送り込んだときに、空気が漏れてしまう。このため、バルーンは、施工現場で鋼管柱材を建方した後に取り付けなければならず、これも工期の長期化に繋がる。
For example, Patent Document 1 discloses a concrete curing device configured to send heated air into the air chamber, which is brought into close contact with the surface of the columnar concrete structure with a balloon having an air chamber. In this configuration, the balloon is formed so as to surround the upper portion of the columnar concrete structure and the side surface thereof.
In the concrete curing device as disclosed in Patent Document 1, the balloon covers up to the upper part of the columnar concrete structure. In the case where a steel beam column is integrally provided with a beam-column joint (joint portion) for joining a steel beam, the beam-column joint protrudes laterally from the steel tube column. For this reason, if the balloon is formed so as to cover the column beam joint portion in addition to the side surface and the upper surface of the steel pipe, the balloon becomes complicated and large. As a result, it takes time to install the balloon, which leads to a longer construction period. In addition, if the balloon is attached before the construction of the steel pipe column material, during the construction work of the steel pipe column material, the balloon air chamber is caused by interference with the surroundings, especially at the part of the column beam joint protruding from the steel pipe column material. May be damaged. If the air chamber is damaged, the air leaks when heated air is sent into the air chamber. For this reason, the balloon must be attached after constructing the steel pipe column material at the construction site, which also leads to a prolonged construction period.

また、特許文献2には、コンクリート構造物の両外側と上端側とを養生マットで覆い、養生マットに形成された送風路を通して温風を供給する構成の養生装置が開示されている。
特許文献2に開示されたような養生装置においても、養生マットでコンクリート構造物の上部までを覆うため、鉄骨梁を接合するための柱梁接合部が一体に設けられている鋼管柱材を養生マットで覆うには、養生マットが複雑で大がかりなものとなる。また、養生マットは、通気性シートと非通気性シートとを有する2重構造であり、養生マットを、工場で装着しておくと、運搬中に養生マットが損傷し、温風を供給したときに、送風路から温風が漏れてしまう場合がある。
Further, Patent Document 2 discloses a curing device configured to cover both the outer side and the upper end side of a concrete structure with a curing mat and supply warm air through an air passage formed in the curing mat.
Also in the curing device as disclosed in Patent Document 2, the steel pipe column material in which column beam joints for joining steel beams are integrally provided to cover the upper part of the concrete structure with the curing mat is cured. To cover with a mat, the curing mat becomes complicated and large. The curing mat has a double structure having a breathable sheet and a non-breathable sheet. If the curing mat is installed in a factory, the curing mat is damaged during transportation and hot air is supplied. In addition, warm air may leak from the air passage.

また、特許文献3には、鋼管柱材の内部に打設したコンクリートを養生する際に、鋼管柱材の周囲を発熱シートで被覆し、発熱シートに温水を循環させる構成の寒中施工装置が開示されている。
特許文献3に開示されたような寒中施工装置においては、発熱シートは、温水を循環させるため、少なくとも2重構造とする必要がある。このため、発熱シートを、工場で鋼管柱材に装着しておくと、特に、柱梁接合部が突出して設けられた鋼管柱材の場合、鋼管柱材の建て込み作業中に発熱シートが柱梁接合部に干渉して損傷し、温水を巡回させたときに、温水が漏れてしまう場合がある。
Patent Document 3 discloses a cold construction apparatus configured to cover the periphery of a steel pipe pillar with a heat generating sheet and circulate hot water through the heat generating sheet when curing the concrete placed inside the steel pipe pillar. Has been.
In a cold construction apparatus as disclosed in Patent Document 3, the heat generating sheet needs to have at least a double structure in order to circulate hot water. For this reason, when the exothermic sheet is attached to the steel pipe column material at the factory, especially in the case of the steel pipe column material provided with the column beam joint protruding, the exothermic sheet is columned during the construction work of the steel pipe column material. When hot water is circulated and damaged by interfering with the beam joint, the hot water may leak.

特開2007−231563号公報JP 2007-231563 A 特開平9−221913号公報JP-A-9-221913 特開2001−132230号公報JP 2001-132230 A

本発明が解決しようとする課題は、寒冷期にコンクリート充填鋼管柱を寒中施工する場合であっても、大掛りな断熱養生を行うことなく、コンクリート充填中および充填後5日間のコンクリート温度を管理設定温度以上に確保することができるコンクリート充填用の鋼管柱材、及び、コンクリート充填鋼管柱の構築方法を提供することである。   The problem to be solved by the present invention is to control the concrete temperature during concrete filling and for 5 days after filling without performing large-scale heat insulation curing even when concrete filled steel pipe columns are constructed in the cold season. It is to provide a steel tube pillar material for concrete filling that can be secured at a set temperature or higher, and a method for constructing a concrete filled steel tube pillar.

本発明者らは、寒冷期に充填鋼管コンクリート柱を構築する方法として、鋼管柱内に充填するコンクリートを直接加熱するのではなく、鋼管柱の柱本体を風管で包み込んだ状態で、風管内に温風を送風することで、コンクリート充填中および充填後5日間のコンクリート温度を管理設定温度(2℃)以上に確保することができる点に着眼して、本発明に至った。また、本発明方法の効果については、建築中の充填鋼管コンクリート柱において、外気温とコンクリート温度を計測し、確認を行った。
本発明は、上記課題を解決するため、以下の手段を採用する。
すなわち、本発明のコンクリート充填用の鋼管柱材は、柱梁接合部を有するコンクリートが充填される鋼管柱材であって、前記柱梁接合部の下方に、前記鋼管柱材を覆う風管が縮めて設置されていることを特徴とする。なお、柱梁接合部には、鋼製梁と接合するために梁接合部材が取り付けられており、鋼管柱材の本体から梁接合部材が突出している。
このような構成によれば、鋼管柱材が建て込まれる前段階にて、鋼管柱材に風管が設置されていることで、鋼管柱材にコンクリートを充填した後には、この風管によって外気が鋼管柱材に直接触れるのを抑えて保温を図りながら、コンクリートの養生を行うことができる。また、風管を、鋼管柱材の柱梁接合部の下方に縮めて設置することで、風管で柱梁接合部を覆うことがない。したがって、風管が設置された鋼管柱材の建て込み作業、梁接合作業中に、風管が損傷してしまうのを抑えることができる。
As a method for constructing a filled steel tube concrete column in the cold season, the present inventors do not directly heat the concrete filled in the steel tube column, but in a state where the column body of the steel tube column is wrapped with the wind tube, The present invention was achieved by focusing on the point that the concrete temperature during the filling of the concrete and the concrete temperature for 5 days after the filling can be maintained at the control set temperature (2 ° C.) or higher by blowing the warm air. Moreover, about the effect of this invention method, the external temperature and concrete temperature were measured and confirmed in the filling steel pipe concrete pillar under construction.
The present invention employs the following means in order to solve the above problems.
That is, the steel pipe column material for filling concrete of the present invention is a steel tube column material filled with concrete having a column beam joint, and a wind pipe covering the steel tube column material is provided below the column beam joint. It is characterized by being installed in a reduced size. In addition, in order to join with a steel beam, a beam joining member is attached to the column beam joining portion, and the beam joining member protrudes from the main body of the steel pipe column material.
According to such a configuration, the wind pipe is installed in the steel pipe column material at the stage before the steel pipe column material is built. It is possible to cure the concrete while keeping the steel pipe pillar material from touching directly. In addition, the wind pipe is installed below the column beam joint portion of the steel pipe column material, so that the column beam joint portion is not covered with the wind pipe. Therefore, it is possible to prevent the wind pipe from being damaged during the erection work and the beam joining work of the steel pipe column material in which the wind pipe is installed.

本発明のコンクリート充填鋼管柱の構築方法は、コンクリート充填鋼管柱の構築方法であって、風管を備えた鋼管柱材を建て込む工程と、前記鋼管柱材の一部を前記風管で覆った後、当該鋼管柱材にコンクリートを充填する工程と、を含むことを特徴とする。
このような構成によれば、鋼管柱材に充填したコンクリートを養生する際には、鋼管柱材の一部を覆う風管によって、外気が鋼管柱材に直接触れるのを抑えて保温がなされる。
A method for constructing a concrete-filled steel pipe column according to the present invention is a method for constructing a concrete-filled steel pipe column, the step of building a steel pipe column material provided with a wind pipe, and covering a part of the steel pipe column material with the wind pipe. And then filling the steel pipe column with concrete.
According to such a configuration, when curing the concrete filled in the steel pipe column material, the wind pipe covering a part of the steel pipe column material suppresses the outside air from directly touching the steel pipe column material, thereby keeping the heat. .

本発明の一態様においては、本発明のコンクリート充填鋼管柱の構築方法は、前記鋼管柱材に前記コンクリートを充填する工程では、前記コンクリートの打設前及びまたは打設後に、前記風管に連結された温風発生装置から温風を送風する。
このような構成によれば、温風発生装置から温風を風管に送り込むことで、鋼管柱材に充填されたコンクリートを加熱し、より良い温度条件でコンクリートを養生することができる。
In one aspect of the present invention, the method for constructing a concrete-filled steel pipe column according to the present invention is connected to the wind pipe before and / or after placing the concrete in the step of filling the steel pipe column material with the concrete. Hot air is blown from the generated hot air generator.
According to such a configuration, by sending warm air from the warm air generator to the wind pipe, the concrete filled in the steel pipe column material can be heated and the concrete can be cured under better temperature conditions.

本発明によれば、寒冷期にコンクリート充填鋼管柱を寒中施工する場合であっても、大掛りな断熱養生を行うことなく、コンクリート充填中および充填後5日間のコンクリート温度を管理設定温度以上に確保することが可能となる。   According to the present invention, even when a concrete-filled steel pipe column is constructed in the cold season, the concrete temperature during concrete filling and for 5 days after filling is equal to or higher than the control set temperature without performing large-scale heat insulation curing. It can be secured.

本実施形態における、構築すべき建築構造物の躯体の一部の構成を示す正面図である。It is a front view which shows the structure of a part of the housing of the building structure which should be constructed in this embodiment. 図1の躯体の柱を構成する鋼管柱材を示す斜視図である。It is a perspective view which shows the steel pipe pillar material which comprises the pillar of the housing of FIG. 本実施形態におけるコンクリート充填鋼管柱の構築方法の流れを示すフローチャートである。It is a flowchart which shows the flow of the construction method of the concrete filling steel pipe pillar in this embodiment. 風管を備えた鋼管柱材を所定の位置に建て込む状態を示す図である。It is a figure which shows the state which builds the steel pipe pillar material provided with the wind pipe in the predetermined position. 所定の位置に建て込んだ鋼管柱材に、鋼製梁を接合した状態を示す図である。It is a figure which shows the state which joined the steel beam to the steel pipe pillar material built in the predetermined position. 鋼管柱材に備えた風管を下方に伸ばし、鋼管柱材を予熱している状態を示す図である。It is a figure which shows the state which extended the wind pipe with which the steel pipe column material was equipped below, and preheated the steel pipe column material. コンクリートの打設後、鋼管柱材を加熱している状態を示す図である。It is a figure which shows the state which is heating the steel pipe column material after placement of concrete. コンクリートの打設が完了した後、温風供給を継続しているときの、鋼管柱材の外部の温度の計測結果を示すグラフである。It is a graph which shows the measurement result of the temperature outside the steel pipe pillar material when the hot air supply is continued after the concrete placement is completed. コンクリートの打設が完了した後、温風供給を継続しているときの、鋼管柱材内のコンクリートの温度の計測結果を示すグラフである。It is a graph which shows the measurement result of the temperature of the concrete in a steel pipe pillar material when hot air supply is continued after completion of concrete placement. 温風供給を停止した後の、鋼管柱材の外部の温度の計測結果を示すグラフである。It is a graph which shows the measurement result of the temperature outside the steel pipe pillar material after stopping hot air supply.

本発明は、鋼管柱材を建て込む前段階において、柱梁接合部の下方側に、鋼管柱材を覆う風管が縮めて設置されているコンクリート充填用の鋼管柱材(図2、図4、図5)と、鋼管柱材を構成する柱本体を風管で覆った状態で、鋼管柱内へのコンクリートの打設前及び/または打設後に、風管内に温風を送風することを特徴とするコンクリート充填鋼管柱の構築方法である(図6、図7)。
以下、添付図面を参照して、本発明によるコンクリート充填用の鋼管柱材、及び、コンクリート充填鋼管柱の構築方法を実施するための形態について、図面に基づいて説明する。
本実施形態における、構築すべき建築構造物の躯体の一部の構成を図1に示す。図1の躯体の柱を構成する鋼管柱材を示す斜視図を図2に示す。
図1に示されるように、構築すべき建築構造物の躯体1は、鉛直方向に延びる柱2と、建築構造物の各階において、互いに隣接する柱2に架設された梁3と、を備えている。
The present invention provides a steel tube column material for concrete filling (FIGS. 2 and 4) in which a wind tube covering the steel tube column material is installed on the lower side of the column beam joint portion before the steel tube column material is built. 5) and with the wind pipe covering the column main body constituting the steel pipe column material, before the concrete is placed in the steel pipe column and / or after the placement, warm air is blown into the wind pipe. It is a construction method of a concrete-filled steel pipe column that is characterized (FIGS. 6 and 7).
Hereinafter, with reference to an accompanying drawing, the form for carrying out the construction method of the steel pipe pillar material for concrete filling by this invention and the concrete filling steel pipe pillar is explained based on a drawing.
FIG. 1 shows a partial configuration of a building structure to be constructed in the present embodiment. The perspective view which shows the steel pipe pillar material which comprises the pillar of the housing of FIG. 1 is shown in FIG.
As shown in FIG. 1, a building structure 1 to be constructed includes a column 2 extending in the vertical direction, and beams 3 installed on columns 2 adjacent to each other on each floor of the building structure. Yes.

柱2は、上下方向に連続する筒状の鋼管柱材21と、鋼管柱材21内に充填されたコンクリート22と、を有するコンクリート充填鋼管柱20によって形成されている。図2に示されるように、鋼管柱材21は、上下方向に、例えば複数階層にわたる長さを有している。鋼管柱材21には、上下方向に間隔をあけて、柱梁接合部24が形成されている。柱梁接合部24は、鋼管柱材21の外周面から各梁3に向けて水平方向に突出する梁接合部材25を有している。各梁接合部材25は、後述する鋼製梁31と同一断面形状を有し、上部フランジ25aと、下部フランジ25bと、上部フランジ25aと下部フランジ25bとを接続するウェブ25cと、を一体に有している。また、鋼管柱材21の外周面には、梁接合部材25の上部フランジ25a、下部フランジ25bと同じ高さに、鋼管柱材21の周方向に連続し、水平方向外方に向かって突出するリブ26が形成されている。
この実施形態において、1本の鋼管柱材21には、上下2個所に柱梁接合部24が形成されている。これにより、鋼管柱材21は、上下2個所の柱梁接合部24を除いた部分、すなわち、鋼管柱材21の上部、中間部、下部に、それぞれ筒状部21pが形成されている。
図1に示されるように、梁3は、上部フランジ31aと、下部フランジ31bと、上部フランジ31aと下部フランジ31bとを接続するウェブ31cとを一体に有した鋼製梁31を有している。鋼製梁31の両端部は、ジョイントプレート32およびボルト33により、各梁接合部材25に接合されている。また、各階の梁3上には、デッキプレート27等が敷設され、各階の床を形成する。
The column 2 is formed by a concrete-filled steel tube column 20 having a tubular steel tube column material 21 continuous in the vertical direction and a concrete 22 filled in the steel tube column material 21. As shown in FIG. 2, the steel pipe column member 21 has a length extending in a vertical direction, for example, over a plurality of layers. In the steel pipe column 21, column beam joints 24 are formed at intervals in the vertical direction. The column beam joint portion 24 has a beam joint member 25 that protrudes in the horizontal direction from the outer peripheral surface of the steel pipe column member 21 toward each beam 3. Each beam joining member 25 has the same cross-sectional shape as a steel beam 31 described later, and integrally includes an upper flange 25a, a lower flange 25b, and a web 25c that connects the upper flange 25a and the lower flange 25b. doing. Further, on the outer peripheral surface of the steel pipe column member 21, it is continuous with the circumferential direction of the steel pipe column member 21 at the same height as the upper flange 25a and the lower flange 25b of the beam joining member 25 and protrudes outward in the horizontal direction. Ribs 26 are formed.
In this embodiment, one steel pipe column member 21 has column beam joints 24 formed at two upper and lower portions. Thereby, as for the steel pipe column material 21, the cylindrical parts 21p are each formed in the part except the column beam junction part 24 of two upper and lower places, ie, the upper part of the steel pipe column material 21, an intermediate part, and the lower part.
As shown in FIG. 1, the beam 3 has a steel beam 31 integrally having an upper flange 31a, a lower flange 31b, and a web 31c that connects the upper flange 31a and the lower flange 31b. . Both ends of the steel beam 31 are joined to each beam joining member 25 by a joint plate 32 and a bolt 33. In addition, deck plates 27 and the like are laid on the beams 3 on each floor to form a floor on each floor.

次に、上記したような柱2を構成するコンクリート充填鋼管柱20の構築方法について説明する。
本実施形態におけるコンクリート充填鋼管柱の構築方法の流れを示すフローチャートを図3に示す。風管を備えた鋼管柱材を所定の位置に建て込む状態を図4に示す。また、所定の位置に建て込んだ鋼管柱材に、鋼製梁を接合した状態を図5に示す。
鋼管柱材21は、予め、工場で製造する。図2に示されるように、鋼管柱材21を施工現場に搬入後に、施工現場仮置場において、鋼管柱材21に伸縮可能な風管30を縮めた状態で取り付けておく。風管30は、鋼管柱材21の筒状部21pの外径よりも大きな内径を有した筒状で、柔軟性を有した材料、例えばビニール系材料から形成される。風管30は、上下2個所に設けられた柱梁接合部24の下方にそれぞれ設けられている。各風管30は、上端部30tが鋼管柱材21に設けられた各階の柱梁接合部24の梁接合部材25の下部フランジ25bに、クランプ金具36によって係止されている。クランプ金具36は、風管30の上端部30tにおいて、周方向に間隔をあけた複数個所に配置されている。これにより、風管30の上端部30tは、その全周が鋼管柱材21に密着しているわけではなく、クランプ金具36で柱梁接合部24に固定された部位以外は、鋼管柱材21との間に隙間を有し、上方に向かって開放されている。また、各風管30は、鋼管柱材21の筒状部21pの下端部までを覆うことができる長さを有している。
このような風管30を備えた鋼管柱材21を、工場から施工現場にトラック等で搬入した後に、風管30を上方に縮めてまとめるようにして、ゴムバンド34等で鋼管柱材21の筒状部21pに仮固定しておく。このように、風管30を施工現場仮置場で鋼管柱材21に取り付けておくことで、鋼管柱建て込み後に風管30を取り付ける必要が無い。また、風管30を柱梁接合部24の下側に取り付けることで、建て込み作業中等に風管30が、鋼管柱材21から側方に突出した柱梁接合部24に干渉するのを抑える。さらに、風管30を筒状部21pの上方に縮めてまとめておくことで、鋼管柱建て込み中等に風管30が他の物品と干渉して破損することを抑える。
Next, the construction method of the concrete filling steel pipe column 20 which comprises the above pillars 2 is demonstrated.
The flowchart which shows the flow of the construction method of the concrete filling steel pipe pillar in this embodiment is shown in FIG. FIG. 4 shows a state in which a steel pipe column member provided with a wind pipe is built in a predetermined position. Moreover, the state which joined the steel beam to the steel pipe pillar material built in the predetermined position is shown in FIG.
The steel pipe column 21 is manufactured in advance at a factory. As shown in FIG. 2, after the steel pipe column 21 is carried into the construction site, the retractable wind tube 30 is attached to the steel pipe column 21 at the construction site temporary storage site. The wind pipe 30 has a cylindrical shape having an inner diameter larger than the outer diameter of the cylindrical portion 21p of the steel pipe column 21 and is made of a flexible material, for example, a vinyl material. The wind pipes 30 are respectively provided below the beam-column joints 24 provided at two upper and lower portions. Each wind pipe 30 is locked by a clamp fitting 36 to a lower flange 25b of a beam joining member 25 of a beam-to-column joint 24 of each floor provided at the upper end 30t of the steel pipe column 21. The clamp fittings 36 are arranged at a plurality of locations spaced apart in the circumferential direction on the upper end 30 t of the wind tube 30. As a result, the upper end 30t of the wind pipe 30 is not in close contact with the steel pipe column 21 and the steel pipe column 21 except for the portion fixed to the column beam joint 24 by the clamp fitting 36. There is a gap between them and is open upward. Each wind pipe 30 has a length that can cover up to the lower end of the tubular portion 21p of the steel pipe column 21.
After the steel pipe pillar 21 provided with such a wind pipe 30 is carried from the factory to the construction site by a truck or the like, the wind pipe 30 is shrunk upward, and the steel pipe pillar 21 is formed by the rubber band 34 or the like. Temporarily fixed to the cylindrical portion 21p. Thus, it is not necessary to attach the wind pipe 30 after the steel pipe column is installed by attaching the wind pipe 30 to the steel pipe column material 21 at the temporary construction site. Further, by attaching the wind tube 30 to the lower side of the beam-column joint portion 24, the wind tube 30 is prevented from interfering with the beam-column joint portion 24 projecting laterally from the steel tube column material 21 during the erection operation or the like. . Furthermore, the wind tube 30 is contracted above the cylindrical portion 21p and collected, so that the wind tube 30 is prevented from being damaged due to interference with other articles during the construction of the steel tube column.

図3、図4に示されるように、風管30を仮固定した後には、風管30が装着された鋼管柱材21を、クレーン等の揚重手段のワイヤーWによって吊下し、コンクリート充填鋼管柱20を構築すべき所定の位置に建て込む(工程S1)。建て込んだ鋼管柱材21は、既に構築が完了した下階の鋼管柱材21に、溶接等により接合する。
図5に示されるように、鋼管柱材21を建て込んだ後には、鋼管柱材21に設けられた各階の柱梁接合部24の各梁接合部材25に、鋼製梁31を接合する。さらに、各階の梁3上に、デッキプレート27を敷設する。
As shown in FIGS. 3 and 4, after temporarily fixing the wind pipe 30, the steel pipe column 21 to which the wind pipe 30 is attached is suspended by a wire W of a lifting means such as a crane, and filled with concrete. The steel pipe column 20 is built at a predetermined position to be constructed (step S1). The built-in steel pipe pillar material 21 is joined to the steel pipe pillar material 21 on the lower floor that has already been constructed by welding or the like.
As shown in FIG. 5, after the steel pipe column member 21 is installed, the steel beam 31 is joined to each beam joining member 25 of the column beam joining portion 24 of each floor provided in the steel tube pillar material 21. Further, a deck plate 27 is laid on the beam 3 on each floor.

鋼管柱材に備えた風管を下方に伸ばし、鋼管柱材を予熱する状態を図6に示す。
この後、鋼管柱材21内にコンクリート22を打設充填にするに先立ち、鋼管柱材21を予熱する。このため、図6に示されるように、鋼管柱材21の外側では、各風管30のゴムバンド34を切断し、風管30の下端部30bの仮固定を解除する。このとき、ゴムバンド34の切断に高枝ばさみ等を用いることで、足場を用いることなく、各階のデッキプレート27上からゴムバンド34の切断作業を行うことができる。次いで、各風管30の下端部30bを下方に引き下ろし、風管30を伸ばし、風管30によって鋼管柱材21における各柱梁接合部24の下側の筒状部21pを覆う(工程S2)。
さらに、鋼管柱材21の各柱梁接合部24の下方の各階において、デッキプレート27上に温風発生装置40A,40Bを設置し、筒状のダクト41A、41Bを介して風管30の下端部30bに接続する。
また、鋼管柱材21の上側の柱梁接合部24の上方において、ジェットヒーター型のオイルファーネス等の温風発生装置40Cをデッキプレート27上に設置する。温風発生装置40Cには、筒状のダクト41Cを接続し、ダクト41Cの先端部を、鋼管柱材21の上端部21tから鋼管柱材21内に挿入する。このとき、鋼管柱材21の上端部21tを覆うように、ビニールシート等からなる囲い45を設ける。
FIG. 6 shows a state in which the wind pipe provided for the steel pipe column material is extended downward to preheat the steel pipe column material.
Thereafter, the steel pipe column material 21 is preheated prior to placing and filling the concrete 22 into the steel tube column material 21. For this reason, as shown in FIG. 6, the rubber band 34 of each wind tube 30 is cut outside the steel tube column 21 and the temporary fixing of the lower end portion 30 b of the wind tube 30 is released. At this time, by using high branch scissors or the like for cutting the rubber band 34, the rubber band 34 can be cut from the deck plate 27 on each floor without using a scaffold. Next, the lower end portion 30b of each wind tube 30 is pulled down, the wind tube 30 is extended, and the tubular portion 21p on the lower side of each column beam joint portion 24 in the steel tube column 21 is covered with the wind tube 30 (step S2). .
Furthermore, in each floor below each beam-column joint portion 24 of the steel pipe column member 21, hot air generators 40A and 40B are installed on the deck plate 27, and the lower ends of the wind pipes 30 are provided via the cylindrical ducts 41A and 41B. Connect to the unit 30b.
Further, a hot air generator 40C such as a jet heater type oil furnace is installed on the deck plate 27 above the column beam joint 24 on the upper side of the steel pipe column 21. A tubular duct 41 </ b> C is connected to the hot air generator 40 </ b> C, and the tip of the duct 41 </ b> C is inserted into the steel tube column 21 from the upper end 21 t of the steel tube column 21. At this time, the enclosure 45 which consists of a vinyl sheet etc. is provided so that the upper end part 21t of the steel pipe pillar material 21 may be covered.

次いで、温風発生装置40A〜40Cで、温風を発生させる。温風発生装置40A、40Bで発生させた温風は、ダクト41A,41Bを介して、各風管30の内側に送り込む(工程S3)。すると、風管30と鋼管柱材21の外周面との間に、暖かい空気層が形成され、これによって、鋼管柱材21の筒状部21pが外側から予熱される。さらに、風管30に送り込まれた温風は、風管30の上端部30tにおける鋼管柱材21との隙間から上方に向かって噴き出す。噴き出した温風により、風管30によって覆われていない鋼管柱材21の柱梁接合部24が予熱される。
温風発生装置40Cで発生させた温風は、ダクト41Cを介して鋼管柱材21の内側に送り込まれ、鋼管柱材21を内側から予熱する。
Next, warm air is generated by the warm air generators 40A to 40C. The warm air generated by the warm air generators 40A and 40B is sent to the inside of each wind tube 30 via the ducts 41A and 41B (step S3). Then, a warm air layer is formed between the wind pipe 30 and the outer peripheral surface of the steel pipe column member 21, and thereby the tubular portion 21p of the steel pipe column member 21 is preheated from the outside. Furthermore, the warm air sent into the wind tube 30 is ejected upward from the gap between the upper end portion 30t of the wind tube 30 and the steel tube column 21. The column beam joint 24 of the steel pipe column 21 that is not covered by the wind tube 30 is preheated by the hot air that is blown out.
The hot air generated by the hot air generator 40C is sent to the inside of the steel pipe column 21 through the duct 41C, and preheats the steel pipe column 21 from the inside.

コンクリートの打設後、鋼管柱材を加熱している状態を図7に示す。
所定時間の予熱を行った後、トレミー管(図示無し)を介して、鋼管柱材21の上端部21tから、鋼管柱材21内に、コンクリート22を打設する(工程S4)。このときには、図7に示されるように、予熱のために鋼管柱材21の上端部21tに挿入していたダクト41Cの先端部を上方に引き抜き、温風発生装置40Cのダクト41Cから囲い45内に温風を噴き出すようにする。
コンクリート22を鋼管柱材21に打設している間、及び鋼管柱材21への打設完了後は、所定期間、例えば5日間、温風発生装置40A,40Bによる風管30内への温風供給、及び、温風発生装置40Cによる囲い45内への温風供給を継続する。
各柱梁接合部24の下側に配置された風管30においては、温風発生装置40A、40Bから温風を送り込むことで、鋼管柱材21の筒状部21pが加熱される。さらに、風管30の上端部30tから上方に噴き出す温風により、鋼管柱材21の柱梁接合部24が加熱される。また、囲い45内においては、温風発生装置40Cから温風を送り込むことで、鋼管柱材21の上端部21tが加熱される。このようにして鋼管柱材21の全体が、温風によって加熱され、コンクリート22の硬化反応が促進される。
FIG. 7 shows a state in which the steel pipe column material is heated after the concrete is placed.
After preheating for a predetermined time, concrete 22 is placed in the steel pipe column 21 from the upper end 21t of the steel pipe column 21 via a tremy pipe (not shown) (step S4). At this time, as shown in FIG. 7, the front end portion of the duct 41C that has been inserted into the upper end portion 21t of the steel pipe column 21 for preheating is pulled upward, and the inside of the enclosure 45 from the duct 41C of the hot air generator 40C. To blow out warm air.
While the concrete 22 is being placed on the steel pipe column 21 and after the completion of the placement on the steel pipe column 21, the temperature in the wind pipe 30 by the hot air generators 40A and 40B is maintained for a predetermined period, for example, 5 days. The supply of hot air and the supply of hot air into the enclosure 45 by the hot air generator 40C are continued.
In the wind pipe 30 arrange | positioned under each column beam junction part 24, the cylindrical part 21p of the steel pipe column material 21 is heated by sending warm air from warm air generator 40A, 40B. Furthermore, the column beam joint portion 24 of the steel pipe column member 21 is heated by the warm air blown upward from the upper end portion 30 t of the wind tube 30. Moreover, in the enclosure 45, the upper end part 21t of the steel pipe column material 21 is heated by sending warm air from the warm air generator 40C. In this way, the entire steel pipe column 21 is heated by the hot air, and the hardening reaction of the concrete 22 is promoted.

鋼管柱材21内へのコンクリート22の打設が完了した後は、予め定めた所定期間、例えば5日間が経過するまで、温風発生装置40A,40B,40Cから風管30および囲い45内への温風供給を継続しながら、コンクリート22を養生する(工程S5)。
ここで、上記のようにして、コンクリート22の打設が完了した後、温風供給を継続しているときの、鋼管柱材21の外部の温度の計測結果を図8に示す。また、コンクリート22の打設が完了した後、温風供給を継続しているときの、鋼管柱材21内のコンクリート22の温度の計測結果を図9に示す。
図8に示されるように、風管30、及び囲い45内に温風を供給することにより、気温が氷点下であるときにも、風管30の上端部30tからの温風の噴出し部P1(図7参照)と、風管30の上端部30tよりも上方の柱梁接合部24の上端部(上階のデッキプレート27の直下部分)P2(図7参照)の温度は、概ね10℃以上を維持している。また、図9に示されるように、風管30、及び囲い45内に温風を供給することにより、気温が氷点下であるときにも、鋼管柱材21内のコンクリート22の温度は、10℃以上を維持している。
After the concrete 22 is placed in the steel pipe column 21, the hot air generators 40 </ b> A, 40 </ b> B, 40 </ b> C enter the wind pipe 30 and the enclosure 45 until a predetermined period, for example, 5 days elapses. The concrete 22 is cured while continuing the supply of hot air (step S5).
Here, the measurement result of the temperature outside the steel pipe column 21 when the hot air supply is continued after the concrete 22 is placed as described above is shown in FIG. Moreover, the measurement result of the temperature of the concrete 22 in the steel pipe column 21 when the hot air supply is continued after the concrete 22 is placed is shown in FIG.
As shown in FIG. 8, by supplying warm air into the wind tube 30 and the enclosure 45, even when the air temperature is below freezing point, the warm air ejection portion P1 from the upper end 30t of the wind tube 30 (Refer to FIG. 7) and the temperature of the upper end portion of the column beam joint 24 above the upper end portion 30t of the wind pipe 30 (a portion directly below the deck plate 27 on the upper floor) P2 (see FIG. 7) is approximately 10 ° C. The above is maintained. Further, as shown in FIG. 9, by supplying warm air into the wind pipe 30 and the enclosure 45, the temperature of the concrete 22 in the steel pipe column 21 is 10 ° C. even when the air temperature is below freezing point. The above is maintained.

鋼管柱材21内へのコンクリート22の打設が完了してから、予め定めた所定期間、例えば5日間が経過したら、温風発生装置40A,40B,40Cから風管30および囲い45内への温風供給を停止する。そして、風管30および囲い45を撤去する(工程S6)。ここで、風管30は、ビニール系材料から形成されているので、カッター等で切り裂くことで、容易に撤去することができる。
上記のようにして、温風供給を停止した後の、鋼管柱材21の外部の温度の計測結果を図10に示す。
この図10に示されるように、温風発生装置40A,40B,40Cから風管30および囲い45内への温風供給を停止した後は、2日程度が経過した時点(図10中、符号Tで図示)で、鋼管柱材21の外部の温度が管理設定温度である2℃以下に低下した。しかし、温風供給を停止してから1日程度は、鋼管柱材21の外部の温度が管理設定温度の2℃以上を維持していることから、外気温等の条件によっては、温風供給を継続する期間を、コンクリート22の充填後5日よりも短くすることも可能である。
After the concrete 22 has been placed in the steel pipe column 21, when a predetermined period, for example, five days has elapsed, the hot air generators 40 </ b> A, 40 </ b> B, 40 </ b> C enter the wind pipe 30 and the enclosure 45. Stop supplying hot air. And the wind pipe 30 and the enclosure 45 are removed (process S6). Here, since the wind tube 30 is formed of a vinyl-based material, it can be easily removed by cutting with a cutter or the like.
The measurement result of the temperature outside the steel pipe column 21 after the hot air supply is stopped as described above is shown in FIG.
As shown in FIG. 10, after the hot air supply from the hot air generators 40A, 40B, and 40C to the wind tube 30 and the enclosure 45 is stopped, about two days have passed (reference numeral in FIG. 10). At T), the temperature outside the steel pipe column 21 decreased to 2 ° C. or lower, which is the management set temperature. However, for about one day after the supply of hot air is stopped, the temperature outside the steel pipe column 21 is maintained at the control set temperature of 2 ° C. or higher. It is also possible to make the period of continuing to be shorter than 5 days after filling the concrete 22.

上述したようなコンクリート充填用の鋼管柱材21によれば、鋼製梁31が接合される柱梁接合部24を備えてコンクリート22が充填される鋼管柱材21であって、柱梁接合部24の下方には、鋼管柱材21を覆う風管30が設置されている。
このような構成によれば、鋼管柱材21が建て込まれる前段階にて、風管30が設置されていることで、鋼管柱材21にコンクリート22を充填した後には、この風管30によって、外気が鋼管柱材21の筒状部21pに直接触れるのを抑えて保温を図りながら、コンクリート22の養生を行うことができる。また、風管30を、鋼管柱材21の柱梁接合部24の下方に縮めて固定することで、風管30で柱梁接合部24を覆うことがない。したがって、風管30が設置された鋼管柱材21の建て込み作業、梁接合作業中に、風管30が損傷してしまうのを抑えることができる。また、風管30を施工現場仮置場で鋼管柱材21に取り付けておくことで、鋼管柱建て込み後に風管30を取り付ける必要が無く、工期の長期化を抑えることができる。
According to the steel pipe column material 21 for filling concrete as described above, the steel tube column material 21 is provided with the column beam joint portion 24 to which the steel beam 31 is joined and is filled with the concrete 22. A wind pipe 30 covering the steel pipe column 21 is installed below 24.
According to such a configuration, the wind tube 30 is installed in the stage before the steel pipe column member 21 is built, and after the steel tube column member 21 is filled with the concrete 22, The concrete 22 can be cured while keeping the heat by keeping the outside air from directly touching the tubular portion 21p of the steel pipe column 21. In addition, the wind tube 30 is not covered with the wind tube 30 by shrinking and fixing the wind tube 30 below the column beam joint portion 24 of the steel pipe column member 21. Therefore, it is possible to prevent the wind pipe 30 from being damaged during the erection work and the beam joining work of the steel pipe column member 21 in which the wind pipe 30 is installed. In addition, by attaching the wind pipe 30 to the steel pipe pillar material 21 at the temporary construction site, it is not necessary to attach the wind pipe 30 after the steel pipe pillar has been built, and the lengthening of the construction period can be suppressed.

また、上述したようなコンクリート充填鋼管柱20の構築方法によれば、風管30を備えた鋼管柱材21を建て込む工程と、鋼管柱材21の一部を風管30で覆った後、当該鋼管柱材21にコンクリート22を充填する工程と、を含む。
このような構成によれば、鋼管柱材21に充填したコンクリート22を養生する際には、鋼管柱材21の一部を覆う風管30によって、外気が鋼管柱材21の筒状部21pに直接触れるのを抑えて保温がなされる。
Moreover, according to the construction method of the concrete-filled steel pipe column 20 as described above, after the step of building the steel pipe column material 21 provided with the wind pipe 30 and covering a part of the steel pipe column material 21 with the wind pipe 30, Filling the steel pipe column 21 with concrete 22.
According to such a configuration, when curing the concrete 22 filled in the steel pipe column 21, the outside air is transferred to the tubular portion 21 p of the steel pipe column 21 by the wind pipe 30 that covers a part of the steel pipe column 21. Insulation is suppressed by touching directly.

さらに、鋼管柱材21にコンクリート22を充填する工程では、コンクリート22の打設前及びまたは打設後に、風管30に連結された温風発生装置40A,40Bから温風を送風する。
このような構成によれば、温風発生装置40A,40Bから温風を風管30に送り込むことで、鋼管柱材21に充填されたコンクリート22を加熱し、より良い温度条件でコンクリート22を養生することができる。
このようにして、寒冷期にコンクリート充填鋼管柱20を寒中施工する場合であっても、大掛りな断熱養生を行うことなく、コンクリート22充填中および充填後5日間のコンクリート22の温度を管理設定温度以上に確保することが可能となる。
Further, in the step of filling the steel pipe column material 21 with the concrete 22, hot air is blown from the hot air generators 40 </ b> A and 40 </ b> B connected to the wind pipe 30 before and / or after the concrete 22 is placed.
According to such a configuration, the hot air is sent from the hot air generators 40A and 40B to the wind pipe 30, thereby heating the concrete 22 filled in the steel pipe column 21 and curing the concrete 22 under better temperature conditions. can do.
In this way, even when the concrete-filled steel pipe column 20 is constructed in the cold season, the temperature of the concrete 22 during the filling of the concrete 22 and for 5 days after filling is managed and set without performing a large-scale heat insulation curing. It becomes possible to ensure more than the temperature.

また、各風管30は、上端部30tが柱梁接合部24の梁接合部材25の下部フランジ25bに、クランプ金具36によって、周方向に間隔をあけた複数個所で固定されている。
これにより、風管30の上端部30tは、その全周が鋼管柱材21に密着しているわけではなく、クランプ金具36で柱梁接合部24に固定された部位以外は、鋼管柱材21との間に隙間を有し、上方に向かって開放されている。したがって、風管30に温風が送り込まれると、風管30の上端部30tにおける鋼管柱材21との隙間から上方に向かって温風が噴き出し、風管30によって覆われていない鋼管柱材21の柱梁接合部24の部分を加熱することができる。これによって、風管30を、鋼管柱材21に対し、柱梁接合部24を除いた一部のみに設けても、鋼管柱材21の全体を加熱することができる。したがって、コンクリート22の打設に先立って、デッキプレート27を敷設しても、鋼管柱材21の加熱を行うことができる。さらに、デッキプレート27をコンクリート22の打設に先立って敷設することで、足場等を組むことなく、各階のデッキプレート27上で各種の作業が行うことができ、作業の効率化を図ることもできる。
また、鋼管柱材21を施工現場仮置場に搬入した際に、風管30を取付けるときには、風管30を上方に縮めてまとめるようにして、ゴムバンド34等で鋼管柱材21の筒状部21pに仮固定するようにした。これにより、風管30が、鋼管柱材21から側方に突出した柱梁接合部24周辺での梁接合作業中に、破損するのを抑えることができる。
In addition, each wind tube 30 is fixed at a plurality of locations at intervals in the circumferential direction by clamp fittings 36 at the upper end 30t to the lower flange 25b of the beam connecting member 25 of the column beam connecting portion 24.
As a result, the upper end 30t of the wind pipe 30 is not in close contact with the steel pipe column 21 and the steel pipe column 21 except for the portion fixed to the column beam joint 24 by the clamp fitting 36. There is a gap between them and is open upward. Therefore, when warm air is sent into the wind tube 30, the warm air is blown upward from the gap between the upper end portion 30 t of the wind tube 30 and the steel tube column 21, and the steel tube column 21 that is not covered by the wind tube 30. The part of the column beam joint 24 can be heated. Thereby, even if the wind pipe 30 is provided only in a part excluding the column beam joint portion 24 with respect to the steel pipe column member 21, the entire steel pipe column member 21 can be heated. Therefore, even if the deck plate 27 is laid before the concrete 22 is placed, the steel pipe column 21 can be heated. Furthermore, by laying the deck plate 27 prior to the placement of the concrete 22, various operations can be performed on the deck plate 27 on each floor without assembling a scaffold, and the work efficiency can be improved. it can.
In addition, when the steel pipe column 21 is carried into the construction site temporary storage place, when the wind pipe 30 is attached, the wind pipe 30 is shrunk upward and bundled so that the tubular portion of the steel pipe pillar 21 is covered with a rubber band 34 or the like. Temporarily fixed to 21p. Thereby, it can suppress that the wind pipe 30 breaks during the beam joining operation | work in the column beam joint part 24 periphery which protruded from the steel pipe column material 21 to the side.

(実施形態の変形例)
なお、本発明のコンクリート充填用の鋼管柱材、及び、コンクリート充填鋼管柱の構築方法は、図面を参照して説明した上述の実施形態に限定されるものではなく、その技術的範囲において様々な変形例が考えられる。
例えば、上記実施形態では、風管30の上端部30tの固定にクランプ金具36を用いたが、その具体的な構成については、いかなるものを用いてもよい。
また、上記実施形態では、風管30を、柱梁接合部24の下端部に位置する下部フランジ25bに固定するようにしたが、風管30の仮固定位置は、柱梁接合部24の下方であれば、例えば、筒状部21pの上下方向中間位置等としてもよい。
また、上記実施形態では、温風発生装置40A〜40Cで、温風を供給しているが、温風の供給は、常時連続的に行うことは必須ではなく、外気温等に応じ、適宜間欠的に行うようにしても良い。
また、上記実施形態では、鋼管柱材を施工現場仮置場に搬入した後、鋼管柱材の柱梁接合部の下方側に風管を取り付けて、その風管が設置された鋼管柱材を建て込んだが、工場にて、鋼管柱材に縮めた風管を取り付け、その風管が設置された鋼管柱材を、トラック等で施工現場に搬入しても良い。
これ以外にも、本発明の主旨を逸脱しない限り、上記実施の形態で挙げた構成を取捨選択したり、他の構成に適宜変更したりすることが可能である。
(Modification of the embodiment)
In addition, the construction method of the steel pipe pillar material for concrete filling of this invention and a concrete filling steel pipe pillar is not limited to the above-mentioned embodiment described with reference to drawings, Various in the technical scope. Variations are possible.
For example, in the above embodiment, the clamp fitting 36 is used to fix the upper end 30t of the wind tube 30, but any specific configuration may be used.
In the above embodiment, the wind tube 30 is fixed to the lower flange 25b located at the lower end of the beam-column joint 24. However, the temporarily fixed position of the wind tube 30 is below the beam-column joint 24. If so, for example, the intermediate position in the vertical direction of the cylindrical portion 21p may be used.
Moreover, in the said embodiment, although warm air is supplied with the warm air generators 40A-40C, it is not essential to supply warm air continuously, and it is intermittent as appropriate according to the outside air temperature or the like. You may make it carry out.
Moreover, in the said embodiment, after carrying a steel pipe pillar material in a construction site temporary storage place, a wind pipe is attached to the lower side of the column beam joint part of a steel pipe pillar material, and the steel pipe pillar material in which the wind pipe was installed is built. However, at the factory, a shortened wind pipe may be attached to the steel pipe pillar material, and the steel pipe pillar material on which the wind pipe is installed may be carried into the construction site by a truck or the like.
In addition to this, the configuration described in the above embodiment can be selected or changed to another configuration as appropriate without departing from the gist of the present invention.

21 鋼管柱材 30 風管
22 コンクリート 31 鋼製梁
24 柱梁接合部 40A、40B 温風発生装置
21 Steel pipe column material 30 Wind pipe 22 Concrete 31 Steel beam 24 Column beam joint 40A, 40B Hot air generator

Claims (3)

柱梁接合部を有するコンクリートが充填される鋼管柱材であって、
前記柱梁接合部の下方に、前記鋼管柱材を覆う風管が縮めて設置されていることを特徴とするコンクリート充填用の鋼管柱材。
A steel pipe column material filled with concrete having a beam-column joint,
A steel pipe column material for filling concrete, characterized in that a wind pipe covering the steel pipe column material is installed below the column beam joint.
コンクリート充填鋼管柱の構築方法であって、
風管を備えた鋼管柱材を建て込む工程と、
前記鋼管柱材の一部を前記風管で覆った後、当該鋼管柱材にコンクリートを充填する工程と、を含むことを特徴とするコンクリート充填鋼管柱の構築方法。
A method for constructing a concrete-filled steel pipe column,
Building a steel pipe column with a wind pipe,
A method of constructing a concrete-filled steel pipe column, comprising: covering a part of the steel pipe column material with the wind pipe, and then filling the steel pipe column material with concrete.
前記鋼管柱材に前記コンクリートを充填する工程では、前記コンクリートの打設前及びまたは打設後に、前記風管に連結された温風発生装置から温風を送風することを特徴とする請求項2に記載のコンクリート充填鋼管柱の構築方法。
3. The step of filling the steel pipe column with the concrete includes blowing hot air from a hot air generator connected to the wind pipe before and / or after placing the concrete. A method for constructing a concrete-filled steel pipe column as described in 1.
JP2017111604A 2017-06-06 2017-06-06 Steel pipe column material for concrete filling and construction method of concrete-filled steel pipe column Active JP6917786B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017111604A JP6917786B2 (en) 2017-06-06 2017-06-06 Steel pipe column material for concrete filling and construction method of concrete-filled steel pipe column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017111604A JP6917786B2 (en) 2017-06-06 2017-06-06 Steel pipe column material for concrete filling and construction method of concrete-filled steel pipe column

Publications (2)

Publication Number Publication Date
JP2018204328A true JP2018204328A (en) 2018-12-27
JP6917786B2 JP6917786B2 (en) 2021-08-11

Family

ID=64956715

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017111604A Active JP6917786B2 (en) 2017-06-06 2017-06-06 Steel pipe column material for concrete filling and construction method of concrete-filled steel pipe column

Country Status (1)

Country Link
JP (1) JP6917786B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139975A (en) * 2020-02-24 2020-05-12 浙江东南网架股份有限公司 Light steel pipe concrete structure filled with inflation pressure bar and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58153652U (en) * 1982-04-06 1983-10-14 株式会社長谷川工務店 Heat-retaining shelter made of cast-on-site concrete floor
JPH0586646A (en) * 1991-09-30 1993-04-06 Maeda Corp Construction of steel pipe column with beam connected thereto
JPH09221913A (en) * 1996-02-15 1997-08-26 Kunii Kensetsu Kk Curing method of concrete and curing equipment and curing mat used therefor
JPH10227125A (en) * 1997-02-18 1998-08-25 Hitachi Home Tec Ltd Concrete curing device for house foundation
JP2001132230A (en) * 1999-11-09 2001-05-15 Shimizu Corp Method and device for constructing infilled steel-pipe concrete pole in cold weather
KR100750589B1 (en) * 2006-08-14 2007-08-21 동방엔지니어링 주식회사 Structure for steam curing of precast member
EP1967669A1 (en) * 2007-03-09 2008-09-10 Carlo Cuttitta Formwork member, formwork, pouring and curing plant and related method for making building elements
JP2011207028A (en) * 2010-03-30 2011-10-20 Fujita Corp Wet-curing method of concrete structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58153652U (en) * 1982-04-06 1983-10-14 株式会社長谷川工務店 Heat-retaining shelter made of cast-on-site concrete floor
JPH0586646A (en) * 1991-09-30 1993-04-06 Maeda Corp Construction of steel pipe column with beam connected thereto
JPH09221913A (en) * 1996-02-15 1997-08-26 Kunii Kensetsu Kk Curing method of concrete and curing equipment and curing mat used therefor
JPH10227125A (en) * 1997-02-18 1998-08-25 Hitachi Home Tec Ltd Concrete curing device for house foundation
JP2001132230A (en) * 1999-11-09 2001-05-15 Shimizu Corp Method and device for constructing infilled steel-pipe concrete pole in cold weather
KR100750589B1 (en) * 2006-08-14 2007-08-21 동방엔지니어링 주식회사 Structure for steam curing of precast member
EP1967669A1 (en) * 2007-03-09 2008-09-10 Carlo Cuttitta Formwork member, formwork, pouring and curing plant and related method for making building elements
JP2011207028A (en) * 2010-03-30 2011-10-20 Fujita Corp Wet-curing method of concrete structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139975A (en) * 2020-02-24 2020-05-12 浙江东南网架股份有限公司 Light steel pipe concrete structure filled with inflation pressure bar and construction method thereof

Also Published As

Publication number Publication date
JP6917786B2 (en) 2021-08-11

Similar Documents

Publication Publication Date Title
JP4928429B2 (en) Tunnel arch concrete reinforcement self-supporting method
JP5732262B2 (en) Construction method of cylindrical tank
JP2011153446A (en) Method for assembling arch reinforcement and arch reinforcement structure
JP2018204328A (en) Steel pipe column member for filing concrete and construction method of concrete filled steel pipe member
KR101570474B1 (en) Structure of pipe bridge and Constructing method of pipe bridge
JP6708524B2 (en) Removal method and cooling device
JP4824596B2 (en) Wet curing equipment for lining concrete
JP2013139828A (en) Refrigerant piping unit and refrigerant piping installation method
JP2010013803A (en) Concrete curing system
JP2008144510A (en) Construction method for multiple circular arc tunnel
KR101856672B1 (en) Method for Reparing the Pipe using a Protect Guard and Thermostat in Work Zone
KR101457110B1 (en) Method for connecting double insulation pipe and method and apparatus for manufacturing connection pipe with roller rotation plate
JP2015048621A (en) Low temperature storage tank and construction method thereof
JP2010261270A (en) Composite structure and method for constructing composite structure building
KR101739841B1 (en) Consecutive cable shrinkable tube welding apparatus for cable bridge
KR20140087306A (en) Pillar heat truss
JP2006233509A (en) Joining structure of column and beam and disassembling method of its structure
JP2009013592A (en) Frame assembling method and frame of building
JP2019113174A (en) Heating device for pipe reclamation member
JP2017128907A (en) Jig for installation and covering from weather of lining plate and method for installation of lining plate using the jig
JP2017227023A (en) Freezing method
JP2002070488A (en) Method and device for installing anti-corrosive sheet
JP7496948B1 (en) Pipe rehabilitation method
KR100567925B1 (en) Heating panel of bridge for winter work
JP6078178B1 (en) Supporting device for lining pipe in pipe and construction method of supporting work

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200421

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210226

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210302

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210329

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210629

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210720

R150 Certificate of patent or registration of utility model

Ref document number: 6917786

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150