JP2018198019A - Building Construction Management Support System, Building Construction Management Support Method, and Building Construction Management Support Program - Google Patents

Building Construction Management Support System, Building Construction Management Support Method, and Building Construction Management Support Program Download PDF

Info

Publication number
JP2018198019A
JP2018198019A JP2017103157A JP2017103157A JP2018198019A JP 2018198019 A JP2018198019 A JP 2018198019A JP 2017103157 A JP2017103157 A JP 2017103157A JP 2017103157 A JP2017103157 A JP 2017103157A JP 2018198019 A JP2018198019 A JP 2018198019A
Authority
JP
Japan
Prior art keywords
construction
date
completion
members
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017103157A
Other languages
Japanese (ja)
Other versions
JP6876523B2 (en
Inventor
大輔 長沼
Daisuke Naganuma
大輔 長沼
利昭 友近
Toshiaki Tomochika
利昭 友近
▲高▼志 秋葉
Takashi Akiba
▲高▼志 秋葉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2017103157A priority Critical patent/JP6876523B2/en
Publication of JP2018198019A publication Critical patent/JP2018198019A/en
Application granted granted Critical
Publication of JP6876523B2 publication Critical patent/JP6876523B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

To provide a construction management support system for a building capable of easily grasping a progress situation of building construction.SOLUTION: A construction management support system 1 comprises: means 11 for extracting a member in completed construction that extracts a member that is in completed construction at a reference day among respective members, as a construction completed member; means 12 for extracting a member in well-oiled construction that extracts a member that is in well-oiled construction at the reference day among respective member, as a construction well-oiled member; means 13 for extracting a member in moved-up construction that extracts a member that is in plan moved-up construction at the reference day among the respective members, as a construction moved-up member 33; means 14 for extracting a member in delayed construction that extracts a member that is in delayed construction at the reference day among the respective members, as a construction delayed member; and display means 16 that displays the construction completed member, the construction well-oiled member, the construction moved-up member, and the construction delayed member on a three-dimensional virtual space so as to be three-dimensionally and visually distinguishable from each other.SELECTED DRAWING: Figure 1

Description

本発明は、建物の施工管理を支援する建物の施工管理支援システム、建物の施工管理支援方法、および建物の施工管理支援プログラムに関する。   The present invention relates to a building construction management support system that supports building construction management, a building construction management support method, and a building construction management support program.

従来より、三次元の仮想空間上に建物のデジタルモデルを作成し、この建物を構成する部材に名称、形状、仕様などの属性情報を紐付けることで、建物の設計や施工を支援する、BIM(Building Information Modeling)が知られている。
特許文献1では、ベース図面とこのベース図面に割り当てる割り当て図面とのそれぞれについて、通り芯の検索範囲を設定してその範囲内について通り芯を検索するステップS1〜S8と、ベース図面および割り当て図面の縮尺や縦横比を考慮して、ベース図面および割り当て図面の通り芯同士が一致するように、座標軸の位置調整を行なうステップS9と、を備える施工情報管理方法が示されている。
Conventionally, BIM supports building design and construction by creating a digital model of a building in a three-dimensional virtual space and associating attribute information such as name, shape, and specifications with the members that make up the building. (Building Information Modeling) is known.
In Patent Document 1, for each of the base drawing and the assigned drawing assigned to the base drawing, steps S1 to S8 for setting a search range for the core and searching for the core within the range, Considering the scale and aspect ratio, there is shown a construction information management method including step S9 for adjusting the position of the coordinate axes so that the cores coincide with each other as in the base drawing and the assigned drawing.

特開2015−118535号公報JP2015-118535A

しかしながら、特許文献1では、建物を構成する部材に建物の工程や施工費についての情報が紐付けられておらず、建物構築の進捗状況を把握することが困難であった。   However, in Patent Document 1, it is difficult to grasp the progress of building construction because information about building processes and construction costs is not linked to members constituting the building.

本発明は、建物構築の進捗状況を容易に把握できる、建物の施工管理支援システム、建物の施工管理支援方法、および建物の施工管理支援プログラムを提供することを目的とする。   An object of the present invention is to provide a building construction management support system, a building construction management support method, and a building construction management support program that can easily grasp the progress of building construction.

請求項1に記載の建物の施工管理支援システムは、建物の施工管理を支援する建物の施工管理支援システム(例えば、後述の建物の施工管理支援システム1)であって、前記建物(例えば、後述の建物30)を構成する各部材について、位置、形状、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日を設定するとともに、施工管理の基準となる基準日として設定する設定手段(例えば、後述の設定手段10)と、前記各部材のうち前記基準日において施工が完了しているものを、施工完了部材(例えば、後述の施工完了部材31)として抽出する施工完了部材抽出手段(例えば、後述の施工完了部材抽出手段11)と、前記各部材のうち前記基準日において予定通りに順調に施工中であるものを、施工順調部材(例えば、後述の施工順調部材32)として抽出する施工順調部材抽出手段(例えば、後述の施工順調部材抽出手段12)と、前記各部材のうち前記基準日において予定を繰り上げて施工中であるものを、施工繰上部材(例えば、後述の施工繰上部材33)として抽出する施工繰上部材抽出手段(例えば、後述の施工繰上部材抽出手段13)と、前記各部材のうち前記基準日において施工が遅延しているものを、施工遅延部材(例えば、後述の施工遅延部材34)として抽出する施工遅延部材抽出手段(例えば、後述の施工遅延部材抽出手段14)と、前記施工完了部材、前記施工順調部材、施工繰上部材、および前記施工遅延部材を、三次元の仮想空間上に立体的かつ視覚的に互いに識別可能に表示する表示手段(例えば、後述の表示手段16)と、を備えることを特徴とする。   The building construction management support system according to claim 1 is a building construction management support system (for example, a building construction management support system 1 to be described later) that supports the building management. Set the position, shape, scheduled construction start date, scheduled construction completion date, actual construction start date, and actual construction completion date for each member constituting the building 30), and the standard date for construction management And setting means (for example, setting means 10 to be described later) and the members that have been installed on the reference date among the members are extracted as construction completion members (for example, a construction completion member 31 to be described later). Construction completion member extraction means (for example, construction completion member extraction means 11 to be described later) and a member that is being constructed smoothly as scheduled on the reference date among the members. For example, a construction smooth member extraction means (for example, a construction smooth member extraction means 12 described later) to be extracted as a construction smooth member 32 described later, and a member that is being constructed by raising the schedule on the reference date among the members. Construction advancement member extraction means (for example, construction advancement member extraction means 13 to be described later) to be extracted as a construction advancement member (for example, construction advancement member 33 to be described later), and construction is delayed on the reference date among the members. A construction delay member extracting means (for example, a construction delay member extracting means 14 described later) for extracting what is present as a construction delay member (for example, a construction delay member 34 described later), the construction completion member, the construction smooth member, and a construction Display means for displaying the lifting member and the construction delay member in a three-dimensional virtual space in a three-dimensional and visually distinguishable manner (for example, display means described later) 6), characterized in that it comprises a.

ここで、建物を構成する各部材の名称、位置、形状の情報については、例えば、設定手段により、三次元の仮想空間上において建物を立体的に設計できるBIM(Building Information Modeling)ソフトウエアから取り込んで設定してもよい。
また、建物を構成する各部材の施工費、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日などの情報については、例えば、設定手段により、建物の工程管理を支援するソフトウエアから取り込んで設定してもよい。
また、表示手段として、例えば、BIM(Building Information Modeling)ソフトウエアを用いて、三次元の仮想空間上に部材の位置や形状を立体的に表示してもよい。
Here, the name, position, and shape information of each member constituting the building is imported from, for example, BIM (Building Information Modeling) software that can design the building three-dimensionally in a three-dimensional virtual space by the setting means. It may be set with.
In addition, for information such as the construction cost, scheduled construction start date, scheduled construction completion date, actual construction start date, and actual construction completion date of each component constituting the building, for example, the building process management by the setting means It may be set by taking in software that supports the above.
Further, as the display means, for example, the position and shape of the member may be displayed three-dimensionally in a three-dimensional virtual space using BIM (Building Information Modeling) software.

この発明によれば、基準日を設定することで、この基準日において施工が完了している施工完了部材、基準日において予定通りに順調に施工中である施工順調部材、基準日において予定を繰り上げて施工中である施工繰上部材、および、基準日において施工が遅延している施工遅延部材が、三次元の仮想空間上に立体的かつ視覚的互いに識別可能に表示される。よって、建物構築の進捗状況を視覚的に容易に把握でき、施工管理が容易となる。   According to this invention, by setting a reference date, a construction completion member that has been completed on this reference date, a construction smooth member that is under construction smoothly on schedule on the reference date, and a schedule that is advanced on the reference date The construction advancement member under construction and the construction delay member whose construction is delayed on the reference date are displayed in a three-dimensional virtual space so as to be distinguishable in three dimensions. Therefore, the progress of building construction can be easily grasped visually, and construction management becomes easy.

請求項2に記載の建物の施工管理支援システムは、前記施工完了部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工完了日以後のものを抽出して、施工完了部材とし、前記施工順調部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日以後で前記施工完了予定日よりも前のものを抽出して、施工順調部材とし、前記施工繰上部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日よりも前のものを抽出して、施工繰上部材とし、前記施工遅延部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工開始日よりも前でかつ前記施工開始予定日以後のものを抽出して、施工遅延部材とするとともに、前記各部材のうち、前記基準日が前記実際の施工完了日よりも前でかつ前記施工完了予定日以後のものを抽出して、施工遅延部材とすることを特徴とする。   The construction management support system for a building according to claim 2, wherein the construction completion member extraction unit extracts a member having the reference date after the actual construction completion date from among the members as a construction completion member. The construction-successful member extraction means is configured such that, among the members, the reference date is after the actual construction start date and before the actual construction completion date and after the scheduled construction start date. Before the actual construction completion date, the construction advancement member extraction means extracts the material before the actual construction start date after the actual construction start date. And the thing before the said construction start scheduled date is extracted, it is set as a construction advance member, and the said construction delay member extraction means is the said reference date before the said actual construction start date among each said member. And after the scheduled start date of construction To extract a construction delay member, and among those members, extract the reference date before the actual construction completion date and after the scheduled construction completion date, It is characterized by doing.

請求項3に記載の建物の施工管理支援システムは、前記設定手段は、前記各部材について、当該部材を構築するのに必要な施工費を設定し、前記施工完了部材の施工費の総額を、出来高として算出する出来高算出手段(例えば、後述の出来高算出手段15)をさらに備え、前記表示手段は、当該出来高を表示することを特徴とする。   The construction management support system for a building according to claim 3, wherein the setting means sets, for each member, a construction cost necessary for constructing the member, and the total construction cost of the construction completion member, It is further characterized by a volume calculation means (for example, volume calculation means 15 described later) for calculating the volume, and the display means displays the volume.

この発明によれば、施工完了部材の施工費の総額を出来高として算出して表示したので、建物構築の進捗状況を視覚的だけではなく、金額面でも容易に把握できる。   According to the present invention, since the total construction cost of the construction completion member is calculated and displayed, the progress of building construction can be easily grasped not only visually but also in terms of money.

請求項4に記載の建物の施工管理支援方法は、建物の施工管理を支援する建物の施工管理支援方法であって、前記建物を構成する各部材について、位置、形状、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日を設定する第1の手順(例えば、後述のステップS1)と、施工管理の基準となる基準日を設定する第2の手順(例えば、後述のステップS2)と、前記各部材のうち前記基準日において施工が完了しているものを施工完了部材として抽出するとともに、前記各部材のうち前記基準日において予定通りに順調に施工中であるものを施工順調部材として抽出し、前記各部材のうち前記基準日において予定を繰り上げて施工中であるものを、施工繰上部材として抽出し、前記各部材のうち前記基準日において施工が遅延しているものを施工遅延部材として抽出する第3の手順(例えば、後述のステップS3)と、前記施工完了部材、前記施工順調部材、前記施工繰上部材、および前記施工遅延部材を、三次元の仮想空間上に立体的かつ視覚的に互いに識別可能に表示する第4の手順(例えば、後述のステップS4)と、を備えることを特徴とする。   The building construction management support method according to claim 4 is a building construction management support method for supporting building construction management, and for each member constituting the building, a position, a shape, a scheduled construction start date, a construction A first procedure for setting a scheduled completion date, an actual construction start date, and an actual construction completion date (for example, step S1 to be described later), and a second procedure for setting a reference date to be a basis for construction management (for example, Step S2) to be described later and, among the members, those that have been completed on the reference date are extracted as work completion members, and the members are being smoothly constructed as planned on the reference date. A certain thing is extracted as a construction-smooth member, and among those members, those scheduled to be advanced on the reference date and being under construction are extracted as construction-promoting members. A third procedure for extracting a construction delay member as a construction delay member (for example, step S3 described later), the construction completion member, the construction smooth member, the construction advance member, and the construction delay member, And a fourth procedure (for example, step S4 to be described later) for displaying the images in a three-dimensional virtual space in a three-dimensional and visually distinguishable manner.

この発明によれば、請求項1と同様の効果がある。   According to the present invention, there is an effect similar to that of the first aspect.

請求項5に記載の建物の施工管理支援方法は、前記第3の手順では、前記各部材のうち、前記基準日が前記実際の施工完了日以後のものを抽出して、施工完了部材とし、前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日以後で前記施工完了予定日よりも前のものを抽出して、施工順調部材とし、前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日よりも前のものを抽出して、施工繰上部材とし、前記各部材のうち、前記基準日が前記実際の施工開始日よりも前でかつ前記施工開始予定日以後のものを抽出して、施工遅延部材とするとともに、前記各部材のうち、前記基準日が前記実際の施工完了日よりも前でかつ前記施工完了予定日以後のものを抽出して、施工遅延部材とすることを特徴とする。   The building construction management support method according to claim 5, in the third procedure, out of each member, the reference date is extracted after the actual construction completion date to obtain a construction completion member, Of the members, the reference date is extracted after the actual construction start date and before the actual construction completion date and after the construction start scheduled date and before the construction completion scheduled date. And, as a construction smooth member, out of each member, the reference date is after the actual construction start date and before the actual construction completion date and before the scheduled construction start date, As a construction advancement member, among those members, the reference date is earlier than the actual construction start date and after the scheduled construction start date, and is used as a construction delay member. Of which, the base date is from the actual construction completion date Before a and extracts those of the construction completion date after, characterized by the construction delay member.

請求項6に記載の建物の施工管理支援方法は、前記第1の手順では、前記各部材について、当該部材を構築するのに必要な施工費を設定し、前記第3の手順では、前記施工完了部材の施工費の総額を出来高として算出し、前記第4の手順では、当該出来高を表示することを特徴とする。   In the construction management support method for a building according to claim 6, in the first procedure, for each member, a construction cost necessary for constructing the member is set, and in the third procedure, the construction work is performed. The total construction cost of the completed member is calculated as a volume, and the volume is displayed in the fourth procedure.

この発明によれば、請求項3と同様の効果がある。   According to the present invention, there is an effect similar to that of the third aspect.

請求項7に記載の建物の施工管理支援プログラムは、建物の施工管理を支援する建物の施工管理支援プログラムであって、コンピュータに、上述の建物の施工管理支援方法を実行させることを特徴とする。   The building construction management support program according to claim 7 is a building construction management support program that supports building construction management, and causes a computer to execute the above-described building construction management support method. .

本発明によれば、建物構築の進捗状況を容易に把握できる。   According to the present invention, the progress of building construction can be easily grasped.

本発明の一実施形態に係る建物の施工管理支援システムの構成を示すブロック図である。It is a block diagram which shows the structure of the construction management support system of the building which concerns on one Embodiment of this invention. 前記実施形態に係る建物の施工管理支援システムが適用される建物の各部材について、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日の時系列のパターン(その1)である。For each member of the building to which the construction management support system for a building according to the embodiment is applied, a construction start date, a construction completion scheduled date, an actual construction start date, and a time series pattern of the actual construction completion date (that 1). 前記実施形態に係る建物の各部材について、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日の時系列のパターン(その2)である。It is the time series pattern (the 2) about a construction start scheduled date, a construction completion scheduled date, an actual construction start date, and an actual construction completion date about each member of the building concerning the embodiment. 前記実施形態に係る建物の施工管理支援システムの表示装置であるモニタ画面の一例である。It is an example of the monitor screen which is a display apparatus of the construction management support system of the building which concerns on the said embodiment. 前記実施形態に係る建物の施工管理支援システムの表示装置であるモニタ画面の別の例である。It is another example of the monitor screen which is a display apparatus of the construction management support system of the building which concerns on the said embodiment. 前記実施形態に係る建物の施工管理支援システムにより建物の施工管理の支援を行う手順のフローチャートである。It is a flowchart of the procedure of performing the support of building construction management by the building construction management support system according to the embodiment.

以下、本発明の一実施形態について、図面を参照しながら説明する。
図1は、本発明の一実施形態に係る建物の施工管理支援システム1の構成を示すブロック図である。
建物の施工管理支援システム1は、建物の施工管理作業を支援するものである。この建物の施工管理支援システム1は、入力装置2、表示装置3、演算処理装置4、および記憶装置5を備える。
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a block diagram showing the configuration of a building construction management support system 1 according to an embodiment of the present invention.
The building construction management support system 1 supports building construction management work. The building construction management support system 1 includes an input device 2, a display device 3, an arithmetic processing device 4, and a storage device 5.

入力装置2は、演算処理装置4に情報を入力する装置であり、キーボードやマウスのほか、タッチパネルなどがある。
表示装置3は、入力装置2で入力された情報や演算処理装置4から出力された情報を表示する装置であり、例えばモニタである。
The input device 2 is a device for inputting information to the arithmetic processing device 4 and includes a touch panel in addition to a keyboard and a mouse.
The display device 3 is a device that displays information input from the input device 2 or information output from the arithmetic processing device 4, and is, for example, a monitor.

記憶装置5は、種々の情報を記憶する装置であり、例えばハードディスクである。
演算処理装置4は、コンピュータであり、記憶装置5に記憶されたプログラムを読み出して、動作制御を行うOS(Operating System)上に展開して実行するものである。
The storage device 5 is a device that stores various information, and is, for example, a hard disk.
The arithmetic processing unit 4 is a computer that reads out a program stored in the storage unit 5 and develops and executes it on an OS (Operating System) that performs operation control.

演算処理装置4は、設定手段10、施工完了部材抽出手段11、施工順調部材抽出手段12、施工繰上部材抽出手段13、施工遅延部材抽出手段14、出来高算出手段15、および表示手段16を備える。   The arithmetic processing unit 4 includes a setting unit 10, a construction completion member extraction unit 11, a construction smooth member extraction unit 12, a construction advancement member extraction unit 13, a construction delay member extraction unit 14, a volume calculation unit 15, and a display unit 16.

設定手段10は、建物を構成する各部材について、名称、位置、形状、当該部材を構築するのに必要な施工費、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日を設定し、記憶装置5に記憶させる。
また、設定手段10は、入力装置2により特定の日にちが入力されると、この日にちを施工管理の基準となる基準日として設定して、記憶装置5に記憶させる。
The setting means 10 includes, for each member constituting the building, a name, a position, a shape, a construction cost necessary for constructing the member, a construction start date, a construction completion date, an actual construction start date, and an actual construction start date. A construction completion date is set and stored in the storage device 5.
Further, when a specific date is input by the input device 2, the setting means 10 sets this date as a reference date that is a reference for construction management and stores it in the storage device 5.

施工完了部材抽出手段11は、各部材のうち基準日において施工が完了しているものを、施工完了部材として抽出する。具体的には、施工完了部材抽出手段11は、各部材のうち、基準日が実際の施工完了日以後のものを抽出して、施工完了部材とする。   The construction completion member extraction means 11 extracts a member for which construction has been completed on the reference date among the members as a construction completion member. Specifically, the construction completion member extraction means 11 extracts a member whose reference date is after the actual construction completion date from among the members, and sets it as a construction completion member.

例えば、各部材について、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日を時系列に並べると、図2および図3に示すように、パターンA、パターンB、パターンC、パターンD、パターンE、パターンFの6通りがある。
図2および図3のパターンA〜Fに示すように、基準日が実際の施工完了日以後となる場合、当該部材は施工完了部材となる。
For example, for each member, when the scheduled construction start date, the scheduled construction completion date, the actual construction start date, and the actual construction completion date are arranged in time series, as shown in FIG. 2 and FIG. , Pattern C, pattern D, pattern E, and pattern F.
As shown in patterns A to F in FIGS. 2 and 3, when the reference date is after the actual construction completion date, the member is a construction completion member.

施工順調部材抽出手段12は、各部材のうち基準日において、予定通りに順調に施工中であるものを、施工順調部材として抽出する。   The construction smooth member extraction means 12 extracts, as a construction smooth member, a member that is being constructed smoothly as planned on the reference date among the members.

具体的には、施工順調部材抽出手段12は、各部材のうち、基準日が実際の施工開始日以後で実際の施工完了日よりも前で、かつ、施工開始予定日以後で施工完了予定日よりも前のものを抽出して、施工順調部材とする。これは、基準日において施工中であり、かつ、予定された施工期間中であれば、施工が順調であると判定するものである。
例えば、図2および図3のパターンA、C、D、Fに示すように、基準日が実際の施工開始日以後で実際の施工完了日よりも前でかつ施工開始予定日以後で施工完了予定日よりも前となる場合、当該部材は施工順調部材となる。
Specifically, the construction smooth member extraction means 12 is the construction completion date after the actual construction completion date and after the actual construction completion date after the actual construction start date among the members. The thing before is extracted and made into a construction smooth member. In this case, if the construction is underway on the reference date and the scheduled construction period, the construction is judged to be smooth.
For example, as shown in patterns A, C, D, and F in FIGS. 2 and 3, the construction date is scheduled to be completed after the actual construction start date and before the actual construction completion date and after the scheduled construction start date. When it is before the day, the member becomes a construction smooth member.

施工繰上部材抽出手段13は、各部材のうち基準日において、予定を繰り上げて施工中であるものを、施工繰上部材として抽出する。   The construction advancement member extraction means 13 extracts, as a construction advancement member, a member that is scheduled to be advanced on the reference date among the members.

具体的には、施工繰上部材抽出手段13は、各部材のうち、基準日が実際の施工開始日以後で実際の施工完了日よりも前で、かつ、施工開始予定日よりも前のものを抽出して、施工繰上部材とする。これは、基準日において施工中であり、かつ、予定された施工期間よりも前であれば、予定を繰り上げて早期に施工していると判定するものである。
例えば、図2および図3のパターンD〜Fに示すように、基準日が実際の施工開始日以後で実際の施工完了日よりも前でかつ施工開始予定日よりも前となる場合、当該部材は施工繰上部材となる。
Specifically, the construction advancement member extracting means 13 is one in which the reference date is after the actual construction start date and before the actual construction completion date and before the scheduled construction start date. Extract it and use it as a construction lifting member. If it is under construction on the reference date and before the scheduled construction period, it is determined that the construction is carried out early by moving up the schedule.
For example, as shown in patterns D to F in FIGS. 2 and 3, when the reference date is after the actual construction start date and before the actual construction completion date and before the scheduled construction start date, the member Becomes a construction lifting member.

施工遅延部材抽出手段14は、各部材のうち基準日において施工が遅延しているものを、施工遅延部材として抽出する。   The construction delay member extracting means 14 extracts a member whose construction is delayed on the reference date among the members as a construction delay member.

具体的には、施工遅延部材抽出手段14は、各部材のうち、基準日が実際の施工開始日よりも前でかつ施工開始予定日以後のものを抽出して、施工遅延部材とする。これは、基準日において、施工開始予定日が経過しているにもかかわらず、実際の施工が開始されておらず、未着手であるため、遅延していると判定するものである。
例えば、図2のパターンA〜Cに示すように、基準日が実際の施工開始日よりも前でかつ施工開始予定日以後となる場合、当該部材は施工遅延部材となる。
Specifically, the construction delay member extracting unit 14 extracts a member having a reference date before the actual construction start date and after the scheduled construction start date, as a construction delay member. This is to determine that the construction date is delayed because the actual construction has not started and the construction has not yet started on the reference date, even though the scheduled construction start date has passed.
For example, as shown in patterns A to C in FIG. 2, when the reference date is before the actual construction start date and after the scheduled construction start date, the member is a construction delay member.

また、施工遅延部材抽出手段14は、各部材のうち、基準日が実際の施工完了日よりも前でかつ施工完了予定日以後のものを抽出して、施工遅延部材とする。これは、基準日において、施工完了予定日が経過しているにもかかわらず、実際の施工が完了していないため、遅延していると判断するものである。
例えば、図2および図3のパターンA、B、Fに示すように、基準日が実際の施工完了日よりも前でかつ施工完了予定日以後となる場合、当該部材は施工遅延部材となる。
Further, the construction delay member extracting means 14 extracts a member having a reference date before the actual construction completion date and after the construction completion scheduled date, as a construction delay member. This is because the actual construction is not completed although the scheduled construction completion date has passed on the reference date, and it is determined that the schedule is delayed.
For example, as shown in patterns A, B, and F in FIGS. 2 and 3, when the reference date is before the actual construction completion date and after the construction completion scheduled date, the member is a construction delay member.

出来高算出手段15は、施工完了部材の施工費の合計額を出来高として算出する。
表示手段16は、施工完了部材、施工順調部材、施工繰上部材、および施工遅延部材を、表示装置3に表示するとともに(図4および図5参照)、出来高も表示するものである。具体的には、表示手段16は、施工完了部材、施工順調部材、施工繰上部材、および施工遅延部材を、三次元の仮想空間上に立体的かつ視覚的に互いに識別可能に表示する。
The volume calculation means 15 calculates the total amount of the construction cost of the construction completion member as the volume.
The display means 16 displays the construction completion member, the construction smooth member, the construction advance member, and the construction delay member on the display device 3 (see FIGS. 4 and 5) and also displays the output. Specifically, the display means 16 displays the construction completion member, the construction smooth member, the construction advancement member, and the construction delay member in a three-dimensional virtual space so as to be distinguishable from each other three-dimensionally and visually.

例えば、図4は、表示装置3であるモニタの画面20の一例である。
この画面20の右側には、3階建ての建物30が三次元の仮想空間上に立体的に表示されている。具体的には、建物30の1階床、1階柱、2階梁、2階床、2階柱、および3階梁は、施工完了部材31であり、実線で表示されている。また、建物30の3階床は、施工順調部材32であり、実線で表示されて斜線でハッチングされている。また、建物30の3階柱は、施工遅延部材34であり、破線で表示されている。
For example, FIG. 4 is an example of a monitor screen 20 that is the display device 3.
On the right side of the screen 20, a three-story building 30 is three-dimensionally displayed in a three-dimensional virtual space. Specifically, the first floor, the first-floor pillar, the second-floor beam, the second-floor floor, the second-floor pillar, and the third-floor beam of the building 30 are the construction completion members 31 and are indicated by solid lines. Further, the third floor of the building 30 is a construction smooth member 32, which is indicated by a solid line and hatched by a diagonal line. Further, the third floor pillar of the building 30 is a construction delay member 34 and is indicated by a broken line.

また、画面20の左上には、基準日(2016年7月23日)が表示されている。
また、画面20の左上には、施工遅延部材34である3階柱が未着手であること、施工順調部材32である3階床が順調に施工中であること、施工完了部材31である3階梁が施工完了であることが示されている。
また、画面20の左上には、基準日における出来高も表示されている。
A reference date (July 23, 2016) is displayed on the upper left of the screen 20.
Further, in the upper left of the screen 20, the third-floor pillar as the construction delay member 34 is not started, the third-floor floor as the construction smooth member 32 is under construction, and the construction completion member 31 is 3 The floor beam is shown to be complete.
In the upper left of the screen 20, the volume on the reference date is also displayed.

また、画面20の左下には、3階柱、3階床、3階梁について、それぞれ、施工開始予定日、施工完了予定日、実際の施工開始日、実際の施工完了日、施工費が示されている。
この画面20を見るだけで、基準日において、3階柱の構築が遅延していることが理解可能となっている。
The lower left of the screen 20 shows the scheduled start date, scheduled completion date, actual start date, actual completion date, and construction cost for the 3rd floor pillar, 3rd floor, and 3rd floor beam, respectively. Has been.
By just looking at this screen 20, it can be understood that the construction of the third floor pillar is delayed on the reference date.

また、例えば、図5は、表示装置3であるモニタの画面20の別の例である。
この画面20の右側には、3階建ての建物30が三次元の仮想空間上に立体的に表示されている。具体的には、建物30の1階床、1階柱、2階梁、2階床、2階柱、および3階梁は、施工完了部材31であり、実線で表示されている。また、建物30の3階床は、施工順調部材32であり、実線で表示されて斜線でハッチングされている。また、建物30の3階柱は、施工繰上部材33であり、実線で表示されてドットでハッチングされている。
Further, for example, FIG. 5 is another example of the screen 20 of the monitor that is the display device 3.
On the right side of the screen 20, a three-story building 30 is three-dimensionally displayed in a three-dimensional virtual space. Specifically, the first floor, the first-floor pillar, the second-floor beam, the second-floor floor, the second-floor pillar, and the third-floor beam of the building 30 are the construction completion members 31 and are indicated by solid lines. Further, the third floor of the building 30 is a construction smooth member 32, which is indicated by a solid line and hatched by a diagonal line. Moreover, the 3rd-floor pillar of the building 30 is the construction lifting member 33, which is displayed with a solid line and hatched with dots.

また、画面20の左上には、基準日(2016年7月23日)が表示されている。
また、画面20の左上には、施工遅延部材34である3階柱が繰り上げて施工中であること、施工順調部材32である3階床が順調に施工中であること、施工完了部材31である3階梁が施工完了であることが示されている。
また、画面20の左上には、基準日における出来高も表示されている。
A reference date (July 23, 2016) is displayed on the upper left of the screen 20.
In addition, in the upper left of the screen 20, the third-floor pillar as the construction delay member 34 is moved up and under construction, the third floor as the construction smooth member 32 is under construction, and the construction completion member 31 A 3rd floor beam is shown to be complete.
In the upper left of the screen 20, the volume on the reference date is also displayed.

また、画面20の左下には、3階柱、3階床、3階梁について、それぞれ、施工開始予定日、施工完了予定日、実際の施工開始日、実際の施工完了日、施工費が示されている。
この画面20を見るだけで、基準日において、3階柱の構築が繰り上げて施工していることが理解可能となっている。
The lower left of the screen 20 shows the scheduled start date, scheduled completion date, actual start date, actual completion date, and construction cost for the 3rd floor pillar, 3rd floor, and 3rd floor beam, respectively. Has been.
By just looking at this screen 20, it is possible to understand that the construction of the third-floor pillar has been advanced and constructed on the reference date.

以上の建物の施工管理支援システム1により建物の施工管理の支援を行う手順について、図6のフローチャートを参照しながら説明する。   The procedure for supporting the construction management of the building by the above construction management support system 1 will be described with reference to the flowchart of FIG.

まず、ステップS1では、設定手段10により、建物を構成する各部材について、名称、位置、形状、施工費、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日を設定して、記憶装置5に記憶させる。   First, in step S1, the setting means 10 uses the name, position, shape, construction cost, scheduled construction start date, scheduled construction completion date, actual construction start date, and actual construction completion date for each member constituting the building. Is stored in the storage device 5.

ステップS2では、設定手段10により、施工管理の基準となる基準日を設定する。
ステップS3では、施工完了部材抽出手段11により、基準日において施工が完了している施工完了部材を抽出する。また、施工順調部材抽出手段12により、基準日において順調に施工中である施工順調部材を抽出する。また、施工繰上部材抽出手段13により、基準日において予定を繰り上げて早期に施工中である施工繰上部材を抽出する。また、施工遅延部材抽出手段14により、基準日において施工が遅延している施工遅延部材を抽出する。また、出来高算出手段15により出来高を算出する。
In step S <b> 2, the setting unit 10 sets a reference date as a reference for construction management.
In step S <b> 3, the construction completion member extraction unit 11 extracts construction completion members that have been completed on the reference date. In addition, the construction-successful member extraction unit 12 extracts construction-successful members that are being constructed smoothly on the reference date. Further, the construction advancement member extracting means 13 extracts the construction advancement member that is under construction at an early stage by raising the schedule on the reference date. Moreover, the construction delay member extraction means 14 extracts the construction delay member whose construction is delayed on the reference date. Further, the volume calculation means 15 calculates the volume.

ステップS4では、表示手段16により、施工完了部材、施工順調部材、施工繰上部材、および施工遅延部材を、三次元の仮想空間上に立体的かつ視覚的に互いに識別可能に表示する。また、表示手段16により、出来高を表示する。   In step S4, the display means 16 displays the construction completion member, the construction smooth member, the construction advancement member, and the construction delay member in a three-dimensional virtual space so that they can be distinguished from each other three-dimensionally and visually. Further, the output is displayed by the display means 16.

本実施形態によれば、以下のような効果がある。
(1)基準日を設定することで、この基準日において施工が完了している施工完了部材31、基準日において順調に施工している施工順調部材32、基準日において繰り上げて施工している施工繰上部材33、および、基準日において施工が遅延している施工遅延部材34が、モニタの画面20に視覚的互いに識別可能に表示される。よって、建物30の構築の進捗状況を視覚的に容易に把握でき、施工管理が容易となる。
According to this embodiment, there are the following effects.
(1) By setting the reference date, the construction completion member 31 that has been completed on this reference date, the construction smooth member 32 that is performing smoothly on the reference date, and the construction that has been advanced on the reference date The lifting member 33 and the construction delay member 34 whose construction is delayed on the reference date are displayed on the monitor screen 20 so as to be visually distinguishable from each other. Therefore, the progress of construction of the building 30 can be easily grasped visually, and the construction management becomes easy.

(2)施工完了部材の施工費の総額である出来高を算出して、モニタの画面20にこの出来高を表示したので、建物30の構築の進捗状況を視覚的だけではなく、金額面でも容易に把握できる。   (2) Since the volume, which is the total construction cost of the construction completion member, is calculated and displayed on the monitor screen 20, the progress of the construction of the building 30 can be easily confirmed not only visually but also in monetary terms. I can grasp.

なお、本発明は前記実施形態に限定されるものではなく、本発明の目的を達成できる範囲での変形、改良等は本発明に含まれるものである。
例えば、本実施形態では、施工完了部材、施工順調部材、および施工遅延部材を、実線や破線で表示したり、ハッチングとして斜線やドットを用いることで、視覚的に互いに識別可能に表示したが、これに限らず、各部材を、表示色を異ならせたり半透明で表示したりすることで、視覚的に互いに識別可能に表示してもよい。
It should be noted that the present invention is not limited to the above-described embodiment, and modifications, improvements, etc. within a scope that can achieve the object of the present invention are included in the present invention.
For example, in the present embodiment, the construction completion member, the construction smooth member, and the construction delay member are displayed by solid lines or broken lines, or by using diagonal lines or dots as hatching, they are displayed visually distinguishable from each other. However, the present invention is not limited to this, and each member may be displayed so as to be visually distinguishable from each other by changing the display color or displaying it in a translucent manner.

1…建物の施工管理支援システム 2…入力装置 3…表示装置
4…演算処理装置 5…記憶装置
10…設定手段 11…施工完了部材抽出手段 12…施工順調部材抽出手段
13…施工繰上部材抽出手段 14…施工遅延部材抽出手段 15…出来高算出手段
16…表示手段 20…モニタの画面
30…建物 31…施工完了部材 32…施工順調部材
33…施工繰上部材 34…施工遅延部材
DESCRIPTION OF SYMBOLS 1 ... Building construction management support system 2 ... Input device 3 ... Display device 4 ... Arithmetic processing device 5 ... Memory | storage device 10 ... Setting means 11 ... Construction completion member extraction means 12 ... Construction smooth member extraction means 13 ... Construction advancement member extraction means DESCRIPTION OF SYMBOLS 14 ... Construction delay member extraction means 15 ... Volume calculation means 16 ... Display means 20 ... Monitor screen 30 ... Building 31 ... Construction completion member 32 ... Construction smooth member 33 ... Construction advance member 34 ... Construction delay member

Claims (7)

建物の施工管理を支援する建物の施工管理支援システムであって、
前記建物を構成する各部材について、位置、形状、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日を設定するとともに、施工管理の基準となる基準日として設定する設定手段と、
前記各部材のうち前記基準日において施工が完了しているものを、施工完了部材として抽出する施工完了部材抽出手段と、
前記各部材のうち前記基準日において予定通りに順調に施工中であるものを、施工順調部材として抽出する施工順調部材抽出手段と、
前記各部材のうち前記基準日において予定を繰り上げて施工中であるものを、施工繰上部材として抽出する施工繰上部材抽出手段と、
前記各部材のうち前記基準日において施工が遅延しているものを、施工遅延部材として抽出する施工遅延部材抽出手段と、
前記施工完了部材、前記施工順調部材、施工繰上部材、および前記施工遅延部材を、三次元の仮想空間上に立体的かつ視覚的に互いに識別可能に表示する表示手段と、を備えることを特徴とする建物の施工管理支援システム。
A building construction management support system that supports building construction management,
For each member constituting the building, the position, shape, scheduled construction start date, scheduled construction completion date, actual construction start date, and actual construction completion date are set, and set as a reference date for construction management. Setting means to
Construction completion member extracting means for extracting, as a construction completion member, construction completed on the reference date among the members,
A construction smooth member extracting means for extracting, as a construction smooth member, one that is being constructed smoothly as scheduled on the reference date among the members,
A construction advancement member extracting means for extracting, as a construction advancement member, a construction being advanced by raising the schedule on the reference date among the members,
Construction delay member extraction means for extracting, as the construction delay member, the construction delayed on the reference date among the members,
A display means for displaying the construction completion member, the construction smoothing member, the construction advancement member, and the construction delay member in a three-dimensional virtual space in a three-dimensional and visually distinguishable manner. Construction management support system for building.
前記施工完了部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工完了日以後のものを抽出して、施工完了部材とし、
前記施工順調部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日以後で前記施工完了予定日よりも前のものを抽出して、施工順調部材とし、
前記施工繰上部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日よりも前のものを抽出して、施工繰上部材とし、
前記施工遅延部材抽出手段は、前記各部材のうち、前記基準日が前記実際の施工開始日よりも前でかつ前記施工開始予定日以後のものを抽出して、施工遅延部材とするとともに、前記各部材のうち、前記基準日が前記実際の施工完了日よりも前でかつ前記施工完了予定日以後のものを抽出して、施工遅延部材とすることを特徴とする請求項1に記載の建物の施工管理支援システム。
The construction completion member extraction means extracts, from among the members, the reference date that is after the actual construction completion date as a construction completion member,
The construction-successful member extraction means includes a reference date that is after the actual construction start date and before the actual construction completion date and after the construction start scheduled date and after the construction completion scheduled date. Extract the previous one as a construction smooth member,
The construction advancement member extracting means extracts, among the members, those whose reference date is after the actual construction start date and before the actual construction completion date and before the scheduled construction start date. As a construction advancement member,
The construction delay member extracting means extracts, among the members, the reference date before the actual construction start date and after the scheduled construction start date, as a construction delay member, 2. The building according to claim 1, wherein among the members, the reference date is before the actual construction completion date and after the construction completion scheduled date, and is used as a construction delay member. Construction management support system.
前記設定手段は、前記各部材について、当該部材を構築するのに必要な施工費を設定し、
前記施工完了部材の施工費の総額を、出来高として算出する出来高算出手段をさらに備え、
前記表示手段は、当該出来高を表示することを特徴とする請求項1または2に記載の建物の施工管理支援システム。
The setting means sets, for each member, a construction cost necessary for constructing the member,
Further comprising a volume calculation means for calculating the total cost of the construction completion member as a volume,
The building construction management support system according to claim 1, wherein the display unit displays the volume.
建物の施工管理を支援する建物の施工管理支援方法であって、
前記建物を構成する各部材について、位置、形状、施工開始予定日、施工完了予定日、実際の施工開始日、および実際の施工完了日を設定する第1の手順と、
施工管理の基準となる基準日を設定する第2の手順と、
前記各部材のうち前記基準日において施工が完了しているものを施工完了部材として抽出するとともに、前記各部材のうち前記基準日において予定通りに順調に施工中であるものを施工順調部材として抽出し、前記各部材のうち前記基準日において予定を繰り上げて施工中であるものを施工繰上部材として抽出し、前記各部材のうち前記基準日において施工が遅延しているものを施工遅延部材として抽出する第3の手順と、
前記施工完了部材、前記施工順調部材、前記施工繰上部材、および前記施工遅延部材を、三次元の仮想空間上に立体的かつ視覚的に互いに識別可能に表示する第4の手順と、を備えることを特徴とする建物の施工管理支援方法。
A building construction management support method for supporting building construction management,
For each member constituting the building, a first procedure for setting the position, shape, scheduled construction start date, scheduled construction completion date, actual construction start date, and actual construction completion date;
A second procedure for setting a reference date as a reference for construction management;
Among the above members, those that have been completed on the reference date are extracted as construction completion members, and those members that are under construction smoothly on schedule on the reference date are extracted as construction smooth members. Then, among those members, those that are under construction on the reference date are extracted as construction advance members, and those members whose construction is delayed on the reference date are extracted as construction delay members. A third procedure to
A fourth procedure for displaying the construction completion member, the construction smooth member, the construction lifting member, and the construction delay member in a three-dimensional virtual space in a three-dimensional and visually distinguishable manner. A construction management support method for buildings.
前記第3の手順では、前記各部材のうち、前記基準日が前記実際の施工完了日以後のものを抽出して、施工完了部材とし、
前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日以後で前記施工完了予定日よりも前のものを抽出して、施工順調部材とし、
前記各部材のうち、前記基準日が前記実際の施工開始日以後で前記実際の施工完了日よりも前でかつ前記施工開始予定日よりも前のものを抽出して、施工繰上部材とし、
前記各部材のうち、前記基準日が前記実際の施工開始日よりも前でかつ前記施工開始予定日以後のものを抽出して、施工遅延部材とするとともに、前記各部材のうち、前記基準日が前記実際の施工完了日よりも前でかつ前記施工完了予定日以後のものを抽出して、施工遅延部材とすることを特徴とする請求項4に記載の建物の施工管理支援方法。
In the third procedure, among the members, the reference date is extracted after the actual construction completion date, and is used as a construction completion member.
Of the members, the reference date is extracted after the actual construction start date and before the actual construction completion date and after the construction start scheduled date and before the construction completion scheduled date. , As a construction smooth member,
Among the members, the reference date is extracted after the actual construction start date and before the actual construction completion date and before the scheduled construction start date, and is used as a construction advancement member,
Among the members, the reference date is earlier than the actual construction start date and after the scheduled construction start date, and is used as a construction delay member. Among the members, the reference date 5. The construction management support method for a building according to claim 4, wherein a construction delay member is obtained by extracting a thing before the actual construction completion date and after the construction completion scheduled date.
前記第1の手順では、前記各部材について、当該部材を構築するのに必要な施工費を設定し、
前記第3の手順では、前記施工完了部材の施工費の総額を出来高として算出し、
前記第4の手順では、当該出来高を表示することを特徴とする請求項4または5に記載の建物の施工管理支援方法。
In the first procedure, for each member, set a construction cost necessary to construct the member,
In the third procedure, the total amount of construction cost of the construction completion member is calculated as the volume,
6. The building construction management support method according to claim 4 or 5, wherein in the fourth procedure, the volume is displayed.
建物の施工管理を支援する建物の施工管理支援プログラムであって、
コンピュータに、
請求項4から6のいずれかに記載の建物の施工管理支援方法を実行させることを特徴とする建物の施工管理支援プログラム。
A building construction management support program that supports building construction management,
On the computer,
A building construction management support program for executing the building construction management support method according to claim 4.
JP2017103157A 2017-05-24 2017-05-24 Building construction management support system, building construction management support method, and building construction management support program Active JP6876523B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017103157A JP6876523B2 (en) 2017-05-24 2017-05-24 Building construction management support system, building construction management support method, and building construction management support program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017103157A JP6876523B2 (en) 2017-05-24 2017-05-24 Building construction management support system, building construction management support method, and building construction management support program

Publications (2)

Publication Number Publication Date
JP2018198019A true JP2018198019A (en) 2018-12-13
JP6876523B2 JP6876523B2 (en) 2021-05-26

Family

ID=64663718

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017103157A Active JP6876523B2 (en) 2017-05-24 2017-05-24 Building construction management support system, building construction management support method, and building construction management support program

Country Status (1)

Country Link
JP (1) JP6876523B2 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0926995A (en) * 1995-07-11 1997-01-28 Takenaka Komuten Co Ltd Architectural drawing preparing device with completed amount control function
JP2001262829A (en) * 2000-03-16 2001-09-26 Hitachi Ltd Construction process control system
US20030050871A1 (en) * 2001-02-05 2003-03-13 Quickpen International Corp. System and method for tracking and managing construction projects
JP2005050098A (en) * 2003-07-28 2005-02-24 Takenaka Komuten Co Ltd Construction process visualization method
US20060074608A1 (en) * 2004-10-01 2006-04-06 Freeman Clay System and method for designing building structures with associated estimates and schedules
JP2014211710A (en) * 2013-04-17 2014-11-13 株式会社Lixil Estimation support device, information processor and estimation support method
JP2015088141A (en) * 2013-11-01 2015-05-07 日立Geニュークリア・エナジー株式会社 Process planning assistance apparatus and process planning assistance method
JP2016211260A (en) * 2015-05-11 2016-12-15 東芝エレベータ株式会社 BIM system, method and program

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0926995A (en) * 1995-07-11 1997-01-28 Takenaka Komuten Co Ltd Architectural drawing preparing device with completed amount control function
JP2001262829A (en) * 2000-03-16 2001-09-26 Hitachi Ltd Construction process control system
US20030050871A1 (en) * 2001-02-05 2003-03-13 Quickpen International Corp. System and method for tracking and managing construction projects
JP2005050098A (en) * 2003-07-28 2005-02-24 Takenaka Komuten Co Ltd Construction process visualization method
US20060074608A1 (en) * 2004-10-01 2006-04-06 Freeman Clay System and method for designing building structures with associated estimates and schedules
JP2014211710A (en) * 2013-04-17 2014-11-13 株式会社Lixil Estimation support device, information processor and estimation support method
JP2015088141A (en) * 2013-11-01 2015-05-07 日立Geニュークリア・エナジー株式会社 Process planning assistance apparatus and process planning assistance method
JP2016211260A (en) * 2015-05-11 2016-12-15 東芝エレベータ株式会社 BIM system, method and program

Also Published As

Publication number Publication date
JP6876523B2 (en) 2021-05-26

Similar Documents

Publication Publication Date Title
JP2010108321A (en) Construction progress visualization system
CN102682150B (en) Design navigation scene
JP5342507B2 (en) Carry-in planning support system
JP2005050098A (en) Construction process visualization method
JP5785864B2 (en) Manufacturing line simulation apparatus, data input support apparatus, and data input support method
US20150277434A1 (en) Production plan creation support method and production plan creation support apparatus
Pitake et al. Visualization of construction progress by 4D modeling application
JP6209909B2 (en) Concrete strike design drawing support device, concrete strike design drawing support method and program
JP2016509285A5 (en)
Su et al. A graphical planning method for workspace-aware, four-dimensional modeling to assist effective construction planning.
JP2018198019A (en) Building Construction Management Support System, Building Construction Management Support Method, and Building Construction Management Support Program
Ayer et al. Development of ecoCampus: a prototype system for sustainable building design education.
US20220374802A1 (en) Automated analysis of objects for construction planning
JP6040538B2 (en) Server device and information management system
Sampaio et al. Construction planning supported in 4D interactive virtual models
Mellado et al. Computational design and construction of notch-free reciprocal frame structures
JP5414601B2 (en) Construction plan creation device and program
CN108510234B (en) Work area visualization device and work area visualization method
JP2006079472A (en) Automatic three-dimensional model construction system
CN107704709A (en) Building and Decoration Design integrated system, design method, electronic equipment and computer program product
Al Dafaay Visualizing the constructability of a steel structure using building information modeling and game simulation
JP6576788B2 (en) Plant construction plan support device
KR20140045102A (en) Three-dimensional modeling system using parametric data
JP2006039617A (en) Method and device for supporting process design task
JP5180791B2 (en) Test procedure evaluation system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200304

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201214

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210121

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210222

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210413

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210426

R150 Certificate of patent or registration of utility model

Ref document number: 6876523

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150